02 Preliminary Studies

  • Uploaded by: JJ Welding
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 02 Preliminary Studies as PDF for free.

More details

  • Words: 4,780
  • Pages: 58
Loading documents preview...
Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 2. Preliminary Studies

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Foreword The management of projects is not an exact science. The elements of the process are not complex. However : • The management of projects is based on multiple human contacts. Inside and outside the project, conflicts and contradictions may arise

• There are many interfaces to manage. The most delicate technology issues are often dealt by people coming from different cultures • Management of Projects keeps changing… but basic principles remain, and must be rigorously applied for projects to be successful © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Management of Medium-Size / Revamping Projects: course content I.

Introduction

II.

Preliminary Studies

III. Basic Engineering (or FEED) IV. EPC Contracting

V.

EPC Organisation, Engineering Management

VI. Procurement Management VII. HSE, Quality and Risk Management IX. Construction and Fabrication Management X.

Completion / Commissioning / Startup / Closure

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

VIII. Project Control (cost/schedule)

Module 2 Contents 1. Scope and Objectives

04 - 07

2. Technical studies

08 - 19

3. Project Team Organization

20 - 22

4. Deliverables

23 - 26

5. Preliminary Project Planning

27 - 49

ATTACHMENTS (slides 50 to 66)

II. Progress control

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

I. Economic justification

Scope and Objectives



Scope: • • • •



Confirmation of technical feasibility Project justification (economic and HSE) Technical schemes or concepts Execution Plan principles

Objectives: • • • •

Select the overall technical solution Evaluate Project cost and schedule Appraise uncertainty and risks Prepare approval dossier to move to next step (Basic Engineering) © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Scope and Objectives Key elements

Technical studies

Risk reduction

Phases definition Appraisal Development Schemes & concept Budget and Schedule Execution Principles

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Dossier for Project Decision to move to FEED

Scope and Objectives Key elements

1. Select the “best” technical scheme for the Project (based on technical, cost, risks & economical criteria) in coordination with, and input from, Company concerned parties 2. Evaluate Project risks, starting with HSE, and manage them 3. Study how the project will be performed (Project Plan) with recommendations for next Project stages 4. Document the technical studies, Project Risks, Project Definition (“SOW”: Scope Of Work) and Project planning 5. Obtain Owner and Project Stakeholders Approvals © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Technical studies Disciplines 

Process basis • Base Case Process study for facilities to be built • Plant performance tests (revamping/debottleneck) • Utilities additional requirements, available resources



Physical configuration • Plot Plan & Lay-out studies (particularly for Revamping) • Structural & foundations outlines for revamping



Project philosophy

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• List of possible alternates to evaluate • Electrical & Controls impacts, philosophy • Modularisation concept if applicable

Technical studies First reviews 

Project Reviews • • • • • •



Conceptual design review Value Engineering / Cold Eye Review Safety review Constructability review Coordination review Economical and procurement reviews

HSE & Risk Reviews

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Depending on Project size/impact: HAZID, HAZOP, QRA, other • Preparation of Project Risks register • First draft of Environmental Impact Statement

Technical studies First reviews 

Workshop or series of meetings with Project Team participants • Should include site Operations and Technology people • Engineering Contractor participation may be useful



Discuss project basis, expectations, execution constraints • Focus on consistency with site infrastructure and operations − Reliability performance, shutdown constraints and schedule − Available space, utilities and infrastructure resources − Competence and professionalism of Owner and Operator

• Consider resources aspects (quantity/quality) for future operation 

Brainstorm on possible alternates

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Selecting a limited number of realistic cases • Preferring existing know-how to innovation • Define further analysis to be performed

Technical studies Sample Review checklist

Infrastructure Execution Environment

Process 1.

Capacity (flow rate)

1.

Layout & constraints

2.

Technology selection

2.

Electrical Distribution & Power Management System

3.

Treatment of feed

3.

Control Systems

4.

Fractionation

4.

Buildings

5.

Power Generation & Heat Integration

5.

Construction & constructability

6.

Utilities, catalysts, chemicals

6.

Modularisation

7.

Effluents, flare

7.

Civil Works

8.

Water Treatment & Disposal

8.

Air Emissions

9.

Product storage

9.

Effluent Water Treatment & Disposal

10. Environmental Impact Assessment

11. Interconnecting with pipe networks

11. Interfaces 12. Authority Approval, permits and authorizations 13. Local Content 14. Project Execution Strategy

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

10. Offsite storage, transfer, loading

Technical studies Sample Review checklist (Power Plant) Process units energy requirements • Type of energy required, steam vs power selection • Turbine overhaul frequency, duration, backup supply • Load flexibility, steam shedding / power shedding constraints



Energy Cost Effectiveness: • Most energy-effective cycle (open, combined, cogeneration) • Heat integration limits, energy value assumptions • CO2 penalties and other environmental taxes • Regulatory reporting requirements, metering



Technology questions: • Best gas turbine type with regard to equipment reliability/cost • Environmental protection parameters (low NOx, flue gas temp) • Equipment metallurgy (resistance, cost, corrosion)

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Technical studies Comparison of alternates 

Alternates comparison: key aspects • • • • • • • •

HSE advantages & drawbacks Technical advantages & drawbacks Compatibility with existing facilities, future expansions Operability, maintenability, future flexibility Economic justification (cost difference vs benefits) Compatibility with expected budgets (CAPEX/OPEX) Project risks (proven process vs technical innovation) Execution risks (schedule, cost, field construction)

The sooner alternates and considered/evaluated, the better



Alternates considered too late cost more than they save

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Technical studies Capex commitments Investment 100%

50%

Construction Basic or FEED engineering

Major commitment generated by early technical decisions Conceptual Preliminary studies studies

On-site operations

(Pre-FEED) Actual commitments towards suppliers

0%

Time

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

PRODUCTION START-UP

Technical studies Capex commitments

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Technical studies Value engineering / Cold eye review 

How can we select the best project design ?



If project “deserves” it (medium-size, or complex), perform: • « Value Engineering » Review: − − − −

once the base concept is established includes the Project Team members and Site representatives added value in having an external Consultant as Chairman the team questions each functionality using a formal procedure

• « Cold Eye Review »: − similar process to the Value Engineering Review − includes « Peer » representatives not being project team members

There are always several possible answers to a technical problem



Be prepared to accept constructive critique and modify your view

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Technical studies Value engineering / Cold eye review process

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Technical studies Sample Cold eye review report Description of proposals issued in March, 2012

Leader

Target date

1

Evaluate one-stage reactor at high pressure, instead of HP+LP (simpler and lower CAPEX, but energy cost increase)

Technology

June, 2012

2

Once-through water cooling for compressor (vs air cooler)

Engineering

April, 2012

3

Conceptual cost / reliability benefits of spare compressor

Production

May, 2012

4

Standardization of exchangers (vs « optimized design » for each)

Engineering

April, 2012

5

Pump standardization: same pump casing for various impellers

Engineering

May, 2012

6

Full automation of demin water resins regeneration system, including PLC, ROV and manpower impact

Production

May, 2012

7

Pre-investment on oil tank size for future capacity debottleneck

Marketing

June, 2012

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Project Team organization Highlights 

Owner may perform or partly contract preliminary studies, depending on: • His knowledge of related processes • His technical resources available • The feasibility studies required • The use of proprietary processes or technology (licensors)



Risks are more important in existing facilities (Debottlenecking, Revamping)



Owner experience and site knowledge is very useful at early stages



Various organizations, more or less strong, can be built (see next pages)



Even when preliminary studies are contracted out, Owner remains the leader



The Owner Project Team has to manage, coordinate and take decisions © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Project Team organization Multidisciplinary team coordination HSE & Sustainable Development

Economics

Construction

Operations

Procurement

Coordination

Engineering

Infrastructures Design & Layout

Commissioning

Completion & Start-up

Cost Estimate/Schedule

RC - 21677_b_A_ppt_01 EP PR GES - 08169_A_A--Preliminary Rev.1 - 18/07/2013 studies to pre-FEED

Research & Development

© 2011 - IFP Training

New Technology

Process Design

Engineering

Operations

21

Project Team organization Example of Integrated Team Owner

Contractor (on-site)

Rotating specialists

Site Manager

Production

Maintenance

Contractor (off-site)

Project Manager

Computer resources

Drafting offices

Legal experts

(piping, E/I, civil)

etc. Process

Purchasing

Support Sces

Construction supervision

RPCI RC - PR - PR GES GES - 08169_A_A - 01338_A_A - Rev.1 - Rev.-018/07/2013 - 14/11/2011

© 2011 - IFP Training

QA/QC

Equipment suppliers Field subcontractors

22

Deliverables Preliminary studies (typical) 

Basis of design (and basic design data) specification, Scope Of Work



Preliminary Study Technical Report, including documents: • • • • •

Process material balances Main utility requirements Process description, PFD, preliminary P&ID List of main equipment Preliminary plot plan

Project Review Reports



List of alternates considered, evaluation and proposed decision



Design philosophy (modularization, standardization, process controls)



Operating philosophy (principles, staffing, start-up)



Permanent buildings: type, approximate size, function

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Deliverables Preliminary studies (specific to Revamping projects) 

Process description: • Marked-up PFD / P&ID (installation & dismantling) • Increase in utility requirements, by main utility (steam, power, N2) • Known capacity limits, plant test results



List of tie-ins and tie-in strategy



Position of new equipment on existing Plot Plans: • • • •



Main pressure vessels Pipe racks, underground networks Storage tanks, modification of product loading facilities Safety facilities (fire fighting, gas detection)

Electrical and Process Control changes: • Electrical substation and cable path drawings • Controls Architecture Diagram

Existing buildings mark-up for modification

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Deliverables Scope Of Work (SOW) 

Summarizes the Technical Plan for the Project facilities defined in the preliminary study; it formalizes the “Scope Of Work”



Ensure that approvers (Designer, Project Manager, Operator) have understood and agreed the fundamental project choices



Subsequent purposes: during project life • It will allow Owner to check that the Project actually designed remains in line with the approved initial requirements • It will serve as a basis to evaluate and record main scope changes proposed and agreed during the Project execution • It will be used, after closure, to verify that the Project has actually reached its business objectives, and if not, eventually improve it © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Deliverables Scope Of Work (SOW) 

The document will cover technical description: • Process Units, heating & cooling media • Power Generation & Utilities Units • Offsite units, storage, transfer, loading, unloading • Interconnections with existing facilities • Upgrading / revamping requirements



Key elements of the project scope will be addressed: • Feedstocks, Technology/Process, Capacity of each process unit • Utilities (air, water, chemicals, …)

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Storage, key equipment size & type, sparing philosophy, phasing

Preliminary Project Plan 

Justification (economic and/or HSE)



Preliminary project schedule



Conceptual CAPEX estimate



Project Execution Plan



Risks analysis & management © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Preliminary Project Planning Economic justification Invest or not in a Project? What is the preferred solution among alternatives? 

The justification is the first thing to validate before starting to work



Value of the Project is best reflected by the Net Present Value (NPV)



NPV is the Sum of Discounted Cash Flows generated by the Project



NPV will depend on: • Technical options • Economic Assumptions • Tax situation © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Preliminary Project Planning Economic justification 

CAPEX estimate • Total Erected Cost of the project

Internal Rate of Return (I.R.R) is the main economical item or way used to decide a downstream investment

OPEX estimate • Raw materials cost • Fuel and Utilities cost • Operation cost, Maintenance cost



Revenues estimate • Estimated products prices



Above elements are used to determine Project NPV and profitability



They are also used to compare alternates profitability (« Delta NPV » can be calculated, integrating only CAPEX & OPEX differences between alternates)

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Preliminary Project Planning Justification



On Medium-Size projects, there may be other more important factors: • Pay-Back Time (when short-term profits are critical) • Profitability Index (when financial resource is a constraint)



HSE justification (semi-quantitative) is also very important • Matrix used to evaluate project HSE justification • Project should allow to move from high-risk to lower • Matrix can also be used to evaluate project changes

Economic and HSE justifications may be combined



If justification borderline, this may be the key to obtain approval

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Preliminary Project Planning EHS Justification LEVEL

Safety

Envirt

I

No significant personnel injury

No impact on environment

Never heard of any occurrence in the world

Has already occurrred in Petrochemicals

Occurred once in company, but not here

Several times per year in the company

Occurs often of permanently in our plant

Low Risk

II

Minor injury, no long-term impact

Slight impact, hard to perceive

III

Major injury with longterm impact

Significant impact, local perception

IV

Fatality

Major impact on area, national perception

Medium Risk

V

Several fatalities

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Massive impact, worldwide perception

© 2011 - IFP Training

High Risk

Preliminary project schedule 



At Conceptual Stage, a Project Schedule will be prepared using a simple software such as Microsoft Project to show the Project Phases to Completion: • Basic or FEED • Contracting for EPC • Time for Approvals by Company • Foreseen Long Lead Items (LLI) • EPC phase • Planned shutdown duration (if known) for revamping projects Plant shut-down times & durations is a key issue. • A first approach of required Plant S/Ds & their duration will be made. A preliminary S/D schedule (PERT Chart) will preferably be prepared to identify the critical path.

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• A critical activity such as column retraying, compressor replacement, furnace revamp… may set the shut-down duration while other activities can be performed in parallel.

Conceptual CAPEX estimate Highlights  

CAPEX estimate accuracy desired at this stage: +/- 30 % Accuracy may be hard to reach on Medium-Size projects, depending on: • • • •



Project complexity and location Onshore with offshore extension projects Concerned facilities More difficult for projects with modifications to existing facilities

The CAPEX estimating method will depend on: • Cost database completeness and adequacy at that specific location, recent local experience from Engineering Contractor, prices volatility • Facilities involved by the project (onshore, new or revamped units, utilities, interconnections with brown field) • Experience of the company, quality of the available data



At this stage, assumptions/uncertainties/risks are critical to document See AACE methodology and Nelson Farrar indexes.

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Conceptual CAPEX estimate Structure

By courtesy of Exxon and Shell Main Equipment Bulk Fabrication/Construction(onshore/offshore) Transportation Temporary Facilities Construction camps Engineering Services Management & Supervision Surveys

Insurance Commissioning

Direct Costs

+ Indirect Costs

+ General Expenses

+ Associated Expenses

+ Contingencies

= Facilities Cost Estimate

Fabrication / Construction cost are the highest costs and the most difficult to estimate, in particular for works in revamped process units and brown field; they are very site dependent (productivity) RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Direct Costs + Indirect Costs = Technical Costs

Conceptual CAPEX estimate Methodology

© 2011 - IFP Training

EP - 21252_a_A_ppt_03 RC PR GES - 08169_A_A- -2_Preliminary Rev.1 - 18/07/2013 studies

37

Conceptual CAPEX estimate Methodology

Estimating methods are global or by factorisation as long as project details such as P&IDs are not prepared; the estimating methodology will combine available cost data base and toolbox tools



Estimate cost data breakdowns, unit costs etc. from similar recent project units at the location, or a similar (in terms of cost) location with corrections, escalation, and other foreseen different project conditions. Often the estimators will use units information from several projects.



Estimate must includes complexity and local coefficients.



Estimate have to include spare parts (2 years operation), material takeoff extra and surplus.

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Conceptual CAPEX estimate Methodology 

Many « factors » are used for « factored estimates », mainly: • Correction using a scaling factor vs. unit or equipment capacity: P1 / Po = (C1 / Co)0.65 • For sized equipment, a “factored” estimate from equipment cost: P installed= K x P equipment

• K: 1.5 to 6, depending on equipment type & construction location. • For revamped areas another K1 factor is to be applied on top. The use of this method will depend on Owner (or assisting Contractor) practice (data base for applicable factors for equipment at the facilities).

• A global factor can be used on top of Direct Costs for Projects at the facilities: Project total cost = K x Project Direct Cost © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Conceptual CAPEX estimate Methodology



Cost information is gathered from all possible sources at the time, e.g.: • Major equipment prices and special equipment or packages, towers, reactors, heat exchangers, water treatment, utilities and power equipments, etc.) from « budget » quotes from Vendors.

• Budget quotations from specialized parties (consultants, contractors..) for infrastructure works (buildings, roads, …) or for other specific packages (atmospheric tank storage, LPG storages, chemicals).

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Conceptual CAPEX estimate Methodology 

Cost information is gathered from all possible sources at the time, e.g.: • Interconnecting preliminary quantities estimated by engineering from preliminary MTOs & unit costs used from previous project at the facilities for bulks procurement cost & for construction cost; quotations from vendors for large pipe / piperacks • For modules and skids fabrication, construction mhrs by ratios (volume or weight if estimated) and mhr cost from zones used (particularly if Company (site) has particular relationships established with given zones). • For specific equipments like air and water treatment: budget quotes from specialized contractors or vendors. • Engineering, construction supervision manhours may be estimated by ratios.

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Contingencies or Profit&Loss factor, if estimate by a Contractor, added on top of the cost estimate

Project Execution Plan (PEP) Highlights 

Purpose: define project objectives and strategy to reach them



Key aspects: • Organisation • Execution strategy • HSE, risks/uncertainties



Preliminary version prepared at this stage, then communicated and revised during Basic Engineering, then normally frozen



Discussed with all Project Stakeholders, needs formal approval by Owner Management at the right level © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Project Execution Plan (PEP) Detailed content Executive Summary, Project Summary description



Summary of Preliminary Study report; main items to solve later



HSE aspects and risk analysis



Organisation/roles (Owner, Project Team, Operations) during execution



Authority Approvals & Regulatory administrative steps required



Global Project schedule, constraints related to shutdown and other Projects



Plan for Basic Engineering (or FEED if applicable)



Key aspects of Detail Engineering, Procurement, Fabrication, Construction, S/U



Proposed Contracting strategy



Key concerns and constraints, with proposed action plan to resolve them

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Project Execution Plan (PEP) Contracting strategy ... page 1 Preliminary Project Contracting Strategy is prepared, focusing on: 

Project execution quality, cost, schedule and phasing



Project resources requirements analysis versus expected availability for the project and in the country, and resulting contracting plan / constraints in particular for: • Engineering Contractors • Transportation & Installation • Construction • Local content resources • Pre-qualification required from large and critical equipment Vendors © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Project Execution Plan (PEP) Contracting strategy ... page 2

Preliminary Project Contracting Strategy is prepared, focusing on: 

Local Content requirements



Contract(s) type for Basic or FEED, if required



Preliminary strategy for contract(s) for EPC phase is prepared considering work packages suited to project specifics and prequalification, discussions (as the case) with Vendors & Contractors.

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Project Execution Plan (PEP) Risk analysis 

At this stage, a first risk analysis is performed



The method used is simple (check-list based, HAZID)



More detailed methods will be used later, but are not yet applicable, mainly by lack of appropriate information



First draft of Project Risk Register prepared listing identified risks and planned mitigation measures



Revamping/Debottleneck of existing facilities

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Importance to check data on the field (don’t trust controlled documents) • Validate raw materials and products properties (use lab data) • Precautions to preserve Safety and Reliability: consider impact on Project Execution (cost, schedule, even sometimes alternates feasibility)

Project Execution Plan (PEP) Risk categories

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Preliminary studies Key points to keep in mind 

Evaluate the economic potential added value of the project



Building early a multidisciplinary team is critical to success



Technical alternates should be listed and evaluated at that stage



Economic evaluation should include CAPEX and OPEX



SHE justification may help project approval by Owner



A preliminary Execution Plan should be prepared at that stage



Revamping projects need good knowledge of actual plant



Safety and Reliability constraints should be clearly addressed © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

ATTACHMENTS I. Economic Justification

II. Progress Control

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

ATTACHMENT I Economic Justification

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Economic Justification (Operating Period = N years)

Revenues Capex

Opex Taxes Cash Flow = Cash Inflow – Cash Outflow Operating period Present years Investment

One must “bring” all cash flows from the future to the present time, i.e., discount all the project’s cash flows. RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

It is not valid to compare funds received or spent at different periods.

Economic Justification

Net Present Value (N.P.V) Internal Rate of Return (I.R.R)

Pay-Out Time (P.O.T) / Exposure © 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Economic Justification Net Present Value

Net Present Value of a Cash Flow Profile

Year Discounting at a rate i Cash Flows After-Tax

0 1

(1+i)

CF0

CF1



1

C



N (1+i)N



CFN

(1+i)n



CFn

CF0 CF1/(1+i) … CFn/(1+i)n … CFN/(1+i)N Discounted Cash Flows Net Present Value = Sum of Discounted Cash Flows N

CFn NPV   n n  0 (1  i )

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

i = Discount Rate = Average Cost of Capital

Economic Justification Net Present Value



If NPV > 0, the project revenues are sufficient to: • • • •

pay all costs incurred by the project reimburse the capital invested remunerate it at rate equal to the discount rate in addition, create a profit for the company

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

NPV > 0 measures the value created by the project

Economic Justification Internal Rate of Return

Rate at which the project remunerates the capital invested

NPV

IRR Discount Rate

Average Cost of Capital

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

If Internal Rate of Return > company Discount Rate, then project NPV >0

Economic Justification Pay-Out Time / Exposure Time needed for the project cash-flow to reimburse the capital invested

M$

POT

0

EXPOSURE

1

2

3

4

Cash Flows

5

6

7

8

10

11

12

Acc. Cash Flows © 2011 - IFP Training

Starting date to be defined: • either 1st year of investment • or start of unit operation

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

9

Economic Justification Pay-Out Time / Exposure

Accumulated net cash Flows flows Cumul des Cash

Flows Nets Net Cash cash flows - Discount rate 8%

Discount rate 8%

M$

300

400

200

200

100

0

0

-200

-100

-400

-200

-600

-300

M$

-800

0

1

2

3

4

5

6

7

8

9 10 11 12 Année years

0

1

2

3

4

5

6

7

8

9 10 11 12 Année years

What is the Pay-Out Time?

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

What is the Financial exposure?

58

ATTACHMENT II Progress control

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Progress control 



A Concept study may require 2 to 6 months and few hundreds up to 10,000 Engineering manhours. Usual « Project Control » techniques will be used, with simple tools, to:

• Prepare the study budget (mobilisation bar charts on Excel to estimate mhrs + estimates from different participants for their scope) • Prepare the study schedule with planned progress curves (Excel or Milestone Project), overall, management and disciplines

• Follow & control the study progress

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

− « Broken line » progress on the schedule − Hourly progress: ratio of expended mhrs to planned mhrs − Physical progress by assigning mhrs weights to the different disciplines / deliverables-activities / milestones for deliverables-activities − Forecast for completion

Progress control



A Concept study may require 2 to 6 months and few hundreds up to 10,000 Engineering manhours. • Follow & control the study cost − Costs are basically all-in mhrs cost x mhrs number − Expended cost, planned cost, forecast cost to be established on monthly basis

• Prepare a monthly progress report indicating key events, progress, costs, areas of concern etc. and including above control elements (a short weekly progress, or bi-weekly progress are advised, in particular for subcontracted studies)

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Progress control Progress control using BS 6079

Reference BS 6079

© 2011 - IFP Training

RC - PR GES - 08169_A_A - Rev.1 - 18/07/2013

Related Documents

02 Preliminary Studies
March 2021 0
02
March 2021 0
02
February 2021 4

More Documents from "Carlos Anillo"