03 Basic Engineering

  • Uploaded by: JJ Welding
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 03 Basic Engineering as PDF for free.

More details

  • Words: 3,872
  • Pages: 42
Loading documents preview...
Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 3. Basic Engineering

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

FEED Scope and Objectives 

Scope • Complementary studies, analysis, engineering and design • Technical optimization of project contents • Finalize Safety/Health/Environmental Analysis



Objectives • Confirm technical scheme selection (including Licensing) • Develop technical specifications for supplier bidding purposes

• Confirm Budget and Schedule • Finalize Project Execution Plan • Compile dossier for:

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

− Final Investment Decision by Owner − EPC Contractor Call for Tender − Regulatory approval, when applicable

4

Typical FEED start checklist Are the following items complete? Preliminary Study (or pre-FEED) report



Basis of Design



Statement of Requirements (SOR)



For Revamped areas: • Valid documentation on existing facilities • Accurate description of existing processes and utilities • Up-to-date layout, plot plan, undergroung routing



Preliminary Safety Analysis (HAZID, HAZOP) built in the design basis



Environment Base Line Study, preliminary Environment Impact Assessment



Owner design standards and rules



Owner approved FEED Budget & Schedule

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



6

Specific objectives 

TECHNICAL • Study in depth the technical solutions of the pre-project for each discipline • Issue AFD (Approved For Design) drawings (layouts, PID's…) and specifications • Prepare technical dossiers for LLI (Long Lead Items) and EPC contract bidding • Issue CAPEX cost estimate with the adequate accuracy level (10%)



CONTRACTS • Prepare the contractual part of the call for tenders for LLI and EPC • Issue tenders evaluation procedures for LLI and EPC, and launch calls



ORGANIZATION • Finalize Project Execution Plan including:

• Define communication and project control systems • Finalize Owner organization and project schedule RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

− Contracting strategy − Quality Assurance plan − HSE Risk Mitigation plan

7

Technical package



The FEED package should be sufficient to start Detail Engineering: • In-depth studies to support the Safety Analysis (as per corporate method) • Environmental Impact Assessment consistent with local requirements • Specific studies/deliverables to obtain approval from local authorities • Review and integration of Licensor’s Basic Engineering Packages



Adequate reviews of the FEED package should be performed

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Independent review/audit of the most delicate calculations • Systematic workshop with Owner/Stakeholders to validate FEED quality • Communication with the site Safety Committee, if appropriate • Technical package reviewed and approved by the Owner

8

FEED Organization/Management

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

13

PMC role 

Reminder: the Leader of the FEED is the Owner



Owner may manage and control the Project with its own resources



If so, a Project Management Consultant will usually provide support: • • • • •



Additional Management resources Technical skills for verification of Contractor studies Assistance for developing the execution strategy (PEP) Contracting strategy, tender selection process/criteria Internal communication

Later, the PMC may remain in the Project Team (part-time)

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Auditing • Ad-hoc technical advice • Controls of equipment (quality, delivery schedule) and field works

14

Management Usual Project Management techniques are used, (in particular for Engineering & Project Control); the following higher level management concerns apply: Coordination and communication between Owner & FEED Contractor; participation of Operations personnel at right times



Resource planning and qualification (full-time & part-time personnel, experts…)



Coordination of Licensors (Special Processes) and Consultants for Special Packages



Project Contractor/Owner Reviews with experts from Contractor /Owner/Partners



FEED Project Control (cost, schedule & progress, changes management, …): similar as described for the Concept studies, but the FEED Contractor may use his regular Engineering Project Controls tools (e.g. Progress system, PRIMAVERA for scheduling).



Risks & uncertainties identification; track latent defects; do not « fix » too early.



Ensure FEED quality as basis for the EPC phase



Well understood Owner decision process and Level of decision Approval



Contract based on reimbursable expenses as the scope, in some cases, may not be sufficiently fixed at the start (e.g.: revamping; projects with novel aspects…)

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



17

Constructability review Lay-out Constructability Concepts Construction and Commissioning Inputs into the Engineering



Accesses for: • Contractor personnel (from inside/outside offices, control room) • Equipment / modules delivery • Temporary storage of equipment, parts, bulk • In-situ lifting or rolling • Equipment dismantling (important for revamping)



Conflicts created by simultaneous operations (“SIMOPs”)



Pre-fabrication plans



Module fabrication / delivery / integration plan for offshore facilities

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



20

3D models help to check construction feasibility

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

21

3D models help to check construction feasibility

© 2011 - IFP Training

• An up-to-date 3D model is a useful tool for revamping studies but • As-built drawings must always remain the contractual reference (the model may not be updated with last construction status) RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

22

Procedures



Appropriate and well-known procedures: a key Management tool



General Project Management procedures • • • • •

List of Project Procedures, Glossary of terms and acronyms Guidelines for the Preparation of Project Procedures Coordination Procedure (with Owner, Partners, Licensors) Document Management and Control Preparation of Call For Tenders for − EPC contract − Equipment Supplies − Field work subcontracts

For small projects, all of them may be summarized in a single “FEED coordination procedure” applicable as part of an umbrella contract

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



23

Procedures 

Engineering • Equipment, Instrument, Electrical & Piping Lines Numbering • PFD, P&ID preparation, Drawings numbering and formatting • Preparation of Project Specifications



HSEQ • HSE and Quality Management Plan • Safety review procedure and applicable tools (HAZID, HAZOP, HAZAN…) • Constructability review procedure



Project control • Cost Estimating, Cost Reporting and Control • Elaboration, communication, revision of Schedule • Progress measurement, reporting and control • Management of change requests

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

For a Small Project FEED, the Procedures may be simplified to: • Management of Engineering • Project Control (HSE, schedule, quality) • Cost Estimating, Reporting and Control

24

FEED Deliverables 

Statement of Requirements + Execution Plan til S/U (revised)



Process basis, data sheets, flow diagrams, heat&matl balances



Job specifications and standard drawings for each discipline • • • •



Vessels (columns, drums, storage tanks) Thermal equipment (furnaces, boilers, exchangers) Piping networks, key instrumentation, control loops Buildings, infrastructure (site study, jetty, roads…)

Procurement basis (refined) • Call For Tender documents, Quality Plans, evaluation criteria • List of acceptable suppliers, short-list, Long Lead Items orders

Health/Safety/Environmental risk analysis (revised)



Final Cost estimate and EPC schedule, controls structure Detailed lists of Deliverables: see Attachment III

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



26

Specific considerations for Revamping projects



Drawings should include Installation & Dismantling documents



Indication “ New “, “ Modified “, or “ Dismantled “ should appear



Drawings for Modified or Dismantled should refer to existing ones



Systematic field verification of existing documents, even if controlled • • • • • •

Concrete structures, buildings, internal roads Steel structures, racks, underground networks (careful) Piping configuration (isometric drawings may have to be re-created) Electrical cabinets drawings, cable paths, available power in SS DCS loops, synoptics, lists of I/O, process computer interface, alarms Sizing of Fire Fighting and Waste Water Treatment facilities

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Detailed lists of Deliverables: see Attachment III

27

Definitive Project Planning The following elements, already previously defined, will be revised, detailed, re-approved, and frozen: 

Project Execution strategy



Project Schedule



Project CAPEX estimate © 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

28

Project Execution strategy

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

29

Influencing factors The following location factors may impact the Project Execution Strategy  Remoteness and availability of site existing infrastructure (roads, railways, bridges, prefab areas)  Transportation logistics (may require special transportation means, sometimes in harsh climatic conditions and in limited climatic windows)  Local availability of Construction Contractors and Equipment (if insufficient, may require workforce from abroad, prefabrication at shop, modularisation)  Local context may impose the use of local contractors, with insufficient qualification, leading to stronger QC and field supervision requirements  Impact of local environment on project scope/risk should be closely examined • Political climate and foreseable changes, security, visa procedures • Regulatory requirements (US standards, European-type, other, none…) • Social situation, role and authority of Trade Unions, of local communities • Religious prevailing rules and off-work periods (e.g “Ramadan”)

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Customs clearance requirements, taxes, currencies, financing/bank concerns

30

Owner permanent objectives 

Sustainable development • HSE performance (no personnel/process/environmental accidents) • Risk management (quality of equipment/works, for long-term reliability) • Preserve good relationship with local environment



Technical objectives • Delivery in accordance with the FEED or BASIC package • Unit business performance requirements achieved • Satisfactory performance during the whole expected project lifetime

Project cost and schedule • Project completed on schedule and within approved budget • Adequate definition and management of contingencies • Adequate cost control methods

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



33

Contracting strategy 

The Contracting strategy elaborated by Owner (*), considering: • Project desired or required schedule, and phasing • Project resource requirements versus expected availability, particularly for: − − − −



EPC Contractors Fabrication Transportation & Installation Construction

Execution Strategy: for overall project optimization (Quality, Cost, Schedule), the scope may be split into manageable Work Packages Each package may have a different contract type Medium-size projects: single Work package can be considered Revamping projects: single Work package highly advisable (interfaces) Owner keeps overall coordination of interfaces between packages

(*) with FEED Contractor support RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• • • •

34

Contracting strategy 





RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Strategy confirmed after market surveys and pre-qualification requests for: • EPC contractors • Fabrication contractors and Construction contractors • Transportation & Installation contractors • Early Contracts such as site preparation Simplified Contractor bids may be acceptable for medium-size projects, if: • Pre-commitments are necessary for engineering studies • Early procurement is justified and approved by Owner (LLI) The choice of contracting strategy is crucial for EPC phase: • Project organization: identification of Company personnel in charge of each main contract management • Budget and scheduling: structured according to the split of contracts The contracting strategy has a major impact on project cost and schedule

35

Final Project Execution Plan 

Updated from Preliminary stage (based on additional information) • Executive Summary, Project Summary description • HSE aspects and Risk analysis (more complex tools)

• Execution concerns and contraint, and plan to resolve them • Regulatory authorization file (from HSE analysis) • Final Contracting strategy, EPC contract type proposed 

New elements elaborated during FEED (related to the EPC stage) • Organisation/roles/responsibilities of Owner and EPC Contractor • Detailed execution Schedule, unit shutdown and startup plan • Quality Assurance / Quality Control / Inspection plan • Selection criteria for suppliers and subcontractors

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Involvement of Owner Operations personnel, training, startup

36

Project EPC schedule 

Project EPC Schedule includes: • Schedule (at least 2 levels of accuracy) • Identification of the Critical Path • S-curves and histograms (from detailed level) allowing progress control • Estimated man.hours for each activity/task − Detail Engineering, global and by disciplines − Field Construction, global and by trade



Schedule Risk analysis (probabilistic method) describes: • The highlights of the method used, and the assumptions

• The most likely range of project execution duration • The probability of the project going beyond this duration



Schedule may not be that critical for all medium-size projects (value ?)

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Proposed actions and controls to reduce this probability

38

Project CAPEX estimate    

CAPEX estimate is required to support the Project Approval by Owner CAPEX estimate should be prepared according to Owner WBS/OBS For smooth approval, CAPEX accuracy should be around +/- 10% to 15% CAPEX remains an estimate, based on quantitative information: • Manhours and rates for design services • Equipment list and budget • MTO/BOQ Quantities x Unit Costs for bulk material • Construction cost rates x construction mhrs

  

Contingency, Risks and Profit factor is added on top of the cost estimate Probabilistic tools can help quantifying the risk of cost overrun CAPEX estimate memorandum summarizes: • underlying assumptions (consistent with PEP) • uncertainties, risks and proposed action to mitigate the risks

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• estimating methodology, sources of data, tools used

39

Project CAPEX estimate Methods (Engineering, Equipment)

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

40

Basic engineering or FEED Key points to keep in mind      

   

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



Applicable standards clearly identified, deviations approved by Owner Long Lead Items and Licensor packages should be identified FEED consistent with local regulatory requirements (studies conducted) Availability and qualification of local workforce to be seriously addressed Project schedule includes assumptions, critical path, schedule risk analysis CAPEX estimate with 15% accuracy required for project final approval CAPEX estimate should be based on quantitative info, not only ratios Engineering contracts to perform FEED are typically of reimbursable type Most often, final Project Approval is taken right after FEED completion Revamping projects have higher risk of cost/schedule overrun Revamping: involving Owner Operations / Technology personnel is critical

41

ATTACHMENTS I.

FEED contract types

II.

Process Licensors packages

III. Detailed FEED Deliverables lists © 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

42

ATTACHMENT I FEED contract types

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

43

FEED contract types (pros & cons)

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

44

ATTACHMENT II Process Licensors packages

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

45

Process licensors packages (1/2) 

Process Licensors provide specific Process Packages (usually referred to as « Basic Engineering Package » in particular technology areas, examples: • Distillation: EXXON, SHELL, FLUOR, PHILIPS, FOSTER, LUMMUS ... • Acid Gas Treatment and S removal: IFP, LURGI, KTI, MERICHEM, PROSERNAT, SGSI, UOP… • Sulphur Plants: JACOBS, PRITCHARD, LURGI, KTI, UOP…



In addition, technology is provided together with certain equipment, e.g. Molecular Sieves • Heavy Oil Upgrading; heavy cuts (Delayed Coker, Visbreaker): CHEVRON, FWC, LUMMUS… (x) All Licensors names are in alphabetical order, current readiness to license to be checked. • Typically BEP (Basic Engineering Package) include:

− Recommended Plot Plan (option)

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

− HMBs; PFDs: Major Equipment or Equipment Lists and Specifications; Process Descriptions; Cause & Effect matrices; Information for special equipment; Operations & Start-Up manuals (option) or instructions

46

Process licensors packages (2/2) 



 

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

It is often required / necessary to compare different processing schemes including a number of licensed units. Licensors usually provide proposals for this purpose. BEP packages preparation for a new unit or modified unit may take 2/3 months; If possible, BEPs should be prepared or at least launched before FEED to gain Project time. Licensors BEPs preparation is otherwise a critical element of the FEED schedule BEPs will be reviewed by FEED Contractor / Company in Design Reviews Final Process Licensor selection is normally through a formal Tendering procedure with scope including: • Supply of License, Proprietary Items if any (« Licensing Agreement ») • Supply of engineering and assistance services (« Engineering Agreement » that includes BEP and review (some FEED & EPC deliverables) and supervision services (as-built construction inspection and start-up & tests assistance)

47

ATTACHMENT III Detailed FEED Deliverables lists

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

48

FEED Main deliverables catalogue (technical)  







© 2011 - IFP Training

GENERAL • BEDD (Basic Engineering Design Data) • Value Engineering Review report • Technical scope for EPC CFT PROCESS • Process Optimisation studies report • Process Flow Diagrams (PFDs) “ID” • Process Descriptions. “NDL” • Process Equipment Lists. “NDL” • Main Equipment Process data Sheets (EDS) “NDL” • P&I Diagrams (PIDs) / Line Lists (Process) “ID” • PIDs Diagrams (Main Utilities) “ID” • Preliminary Relief Valves Discharge Summary. “NDL” • Safety Control System Process Description. “NDL” • Catalysts and Chemicals Specification. “NDL” • Preliminary Utility Balance; Chemicals lists. “NDL”

THERMAL • Heat Exchangers TEMA data sheet “NDL” • Data sheets for Air Coolers (preliminary) “NDL” EQUIPMENT & TANKS • Job Specifications • Design & construction standards. • Specifications for equipment “NDL” • Specifications for Packages “NDL” • Main/ critical Vessels & Heat Exchangers drawings “NDL” • For LLIs: Requisitions, Mechanical specifications, ITPs, Bid comparisons & recommendations • Tanks list “NDL” • LNG & LPG Tanks Specifications “NDL” CORROSION / PIPING • Job Specifications. • Design & construction standards. • Material Selection Diagrams (MSD) and Corrosion study “NDL”

Notes for Revamped areas: “ID”: “Installation” & “Dismantling” documents; “NDL”: new/modified/deleted items RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

49

FEED main deliverables catalogue (technical) 

SAFETY & ENVIRONMENT • Job Specifications.



PLANT LAY-OUT

• Fire Demand Calculation Notes.

• Site Plan

• Fire Fighting and Fire Protection Drawings and Diagrams (principles). (ID)

• Overall Plot Plan. • Unit Plot Plans (Process, Utilities, Offsites) (ID)

• Main Equipment Specifications. (NDL)

• Flare radiation study

• Hazards Register

• Interconnecting drawings (option) (ID)

• Consequence Analysis (HAZAN) and/or QRA (x)

• Modules drawings (option) (ID)

• HAZOP review report

• Special areas lay-out studies (option)

• HAZID review report

• Preliminary MTOs for estimate (ID)

• Safety Concept or Safety Case (update)

• Preliminary BOQs for construction contracts (ID)

• Emission studies

• Battery Limits drawings • Piping Classes (NDL)

• Noise study • EBS(x)

• EIA(x) • HSE Plan for EPC phase

(x): may be performed by specialized Consultant Notes for Revamped areas: “ID”: “Installation” & “Dismantling” documents; “NDL”: new/modified/deleted items RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Tie-ins list (option)

• Hazardous Area Classification Drawings. (ID)

51

Example of layout principles

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

52

QRA output: Addition of new facilities in an existing site; generated Total Risk Contour

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

53

Addition of new facilities in an existing site; generated VCE Overpressure exceeded with a frequency of 10-4/year

© 2011 - IFP Training

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

54

FEED main deliverables catalogue (technical) 

Civil / buildings

Infrastructure • Sea Water intake / outfall / pumping station study (x) (NDL) • Reclamation over sea study (x) (option)

(x): may be performed by specialized Consultant

© 2011 - IFP Training

 • Job Specifications • Design and construction Standards • Preliminary Drawings for main piperacks and structures (ID) • Modularisation study (option) • Preliminary Drawings for modules (option) (ID) • Drainage study • U/G networks drawings (ID) • Foundations preliminary drawings (revamping) • Buildings architectural dwgs; finishing schedules (ID) • HVAC systems specs, diagrams (ID) • Geotechnical study (x) • Bathymetry survey (x), Topography survey (x), Soils survey (x) • Preliminary MTOs, BOQs for estimate (option) (ID)

Notes for Revamped areas: “ID”: “Installation” & “Dismantling” documents; “NDL”: new/modified/deleted items RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

55

FEED main deliverables catalogue (technical) 

Electrical • Job Specifications • Preliminary users list (NDL), elec balance • Preliminary calculation Notes (Load Summary, etc.) • Single Line Diagrams. (ID) • Preliminary Substations Drawings. (ID) • Design Standards and Typical Diagrams

Controls & instrumentation • Job Specifications • Design Standards and Typical Diagrams • Control Systems Architecture Drawing (ID) • DCS/ESD/F&G Systems Specifications. (NDL) • Preliminary Control Room and Instrument Technical Rooms Drawings. (ID) • Interfaces definition drawings (ID) • Preliminary MTOs, BOQs for estimate (option) (ID)

© 2011 - IFP Training

• Main Equipment Specifications. (NDL) • Preliminary MTOs, BOQs for estimate (option) (ID)



Notes for Revamped areas: “ID”: “Installation” & “Dismantling” documents; “NDL”: new/modified/deleted items RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

56

FEED main deliverables (project planning) 

Construction/Fabrication/ T&I • Constructability review report • Construction requirements

• Accommodation requirements • TCF requirements • Construction Accommodation specs and drawings (option)

• Construction / Fabrication / T&I Execution & contracting Plans • Construction raw materials availability study (option)

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

Commissioning • Main operating principles (production, utilities, export, control system, metering) • Laboratory requirements

and

QC

• Staffing (Main chart), Logistic Logistic base

organization means and

• Commissioning plan

and Start-up

© 2011 - IFP Training

• Construction Contractors / Fabrication Contractors prequalification / availability study (option)



57

FEED main deliverables catalogue (project planning)



Quality plan (requirements for EPC phase (for EPC CFT) Project controls • WBS / OBS • Level II EPC Schedule and schedule memorandum



Procurement and contracts • Tendering Procedures • CFT for EPC Contracts • CFT for LLIs

• CFT for Early Contracts • Tenders Evaluation Reports

• Project Controls requirements for EPC phase (for EPC CFT) (Scheduling, Progress Control, Reporting)

• Procurement requirements for EPC phase (for EPC CFT) (Purchasing, Inspection, Expediting, Traffic) • Approved Vendors list

RC - PR GES - 08170_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• CAPEX Estimate (generally +/- 15%)

58

Related Documents


More Documents from "rohitbharti2290"