04_contracting For Epc Phase

  • Uploaded by: JJ Welding
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 04_contracting For Epc Phase as PDF for free.

More details

  • Words: 4,031
  • Pages: 45
Loading documents preview...
Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 4. Contracting for EPC phase

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

Management of Medium-Size / Revamping Projects: course content I.

Introduction

II.

Preliminary Studies

III. Basic Engineering (or FEED) IV. EPC Contracting V.

Organization and Engineering

VI. Procurement VII. HSE, Quality and Risk Management IX. Construction and Fabrication Management X.

Completion / Commissioning / Start-up / Closure

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

VIII. Project Control (cost/schedule)

2

Contracting Objectives / Strategy

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

3

Objectives



Once the FEED is complete and the project approved: • Confirm the expected contract scope − Engineering Services − Equipment supplies − Fabrication, Construction, Installation

• Confirm Engineering contract type (Lump Sum or Reimbursable) • Select the Engineering Contractor(s) • Select LLI suppliers and place early orders if any 

Process should comply with Owner requirements

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Tendering policy, standard contractual terms, legal reviews • Authority approval levels, exception/waiver rules • Project cost/schedule constraints

4

Owner level



What does that mean for Owner ? • • • •



Owner has to take into account: • • • •

His own contracting rules and Project Management standards His internal resources available (or not) The overall project size: Revamping projects may not need splitting Availability, qualification, experience and management of contractors

Contract Strategy is critical for project cost and schedule performance

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



How many contracts ? How to separate the Project into sub-projects ? Where to place interfaces ? how to minimize them? What type of contracts to be used ?

5

Contracting Objectives / Strategy



Contract: agreement between two or more parties, by which they commit themselves to fulfil pre-defined obligations



EPC contract for a Medium-Size / Revamping project: • Typical agreement between Owner and one Engineering Contractor • Typical Scope: Engineering, Procurement, Construction, till handover



EPC Contract: the tool by which, under certain conditions: • Contractor agrees to carry out the execution of the approved project • Owner agrees to compensate Contractor, according to contract terms

There are many subtle differences between a contract and a PO



Pay attention to: placing an order for a contract is fundamentally different to place an order for materials or equipments ... see next page

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



6

Contracting Objectives / Strategy

CONTRACT In general will include several engineering … fabrication, construction

PURCHASE ORDER disciplines: For an equipment or materials issued from “standard” fabrication

May be performed at several sites including the final Fabrication will take place at supplier’s and /or subproject site supplier’s premises The contract documents are based on Company’s The purchase order is based on supplier’s definition as detailed requirement agreed by buyer The result of the work will be checked at the Owner The result of the supply will be agreed at delivery (with Site a warranty period) Overall responsibility of the Work, liability could be Responsibility limited to the supply and the compliance very large. i.e 100% with the specification.

May endorse several orders from the Company

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

May be used for “packages”, several equipment for a specific process

© 2011 - IFP Training

Payment can be by unit rates, time rates, progress, Payment through milestones is the normal procedure milestones

7

New LPG tank + compressor LPG Rundown storage & loading Battery limits

LPG Loading & circulation pump

Boil off gas compressor LPG Storage tank © 2011 - IFP Training

How many contracts would you go for? What scope? Which type? RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

8

Interfaces Examples of Interfaces Management,… Interconnecting Piping, Electricals, Controls…

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

9

A few key questions Are there any preferred Vendors for specific equipment ? Why ?



Do you have any black-listed suppliers ? How should Contractors manage this ?



How is Cost important vs Schedule ? Is there a schedule window ?



What qualified resources does Owner have now ? And in the future ?



What can be the impact of the project construction on Facility performance ?



What is the level of knowledge of the plant by each Contractor ?



Have Contractors good relationship with local authorities ? Is it important ?



Which Contractors do you really trust ? Why ?

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



10

EPC Contract scopes and types

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

11

Possible scopes 

Separate contracts • Not too common in Revamping projects (too many interfaces) • Owner keeps better control of activities, but needs resources



Combined contracts • EP: Engineering, Procurement (transportation may be included or not), and usually construction & commissioning assistance • EPC: Engineering, Procurement, Construction/Installation (Operations taking care of Commissioning/Startup). Common for Revamp projects • EPCC: E.P.C. + Commissioning • EPCCS: E.P.C. + Commissioning and Startup (very seldom for Revamps, but possible for Medium-Size grassroots projects, with Owner-loaned team)

Although Procurement is always included in the scope, the EPC contractor may have limited decision authority (sometimes none…)

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



12

Possible scopes SEPARATE CONTRACTS

Pre-FEED, FEED, EPCI

Pre-FEED, FEED, EPCC

TURN-KEY

PRE-FEED

PRE-FEED

PRE-FEED

PRE-FEED

BASIC or FEED

BASIC or FEED DESIGN

BASIC or FEED DESIGN PROCUREMENT SERVICES FOR LONG LEAD ITEMS

BASIC or FEED DESIGN

PROCUREMENT

PROCUREMENT SERVICES FOR

LONG LEAD ITEMS

LONG LEAD ITEMS

DETAIL ENGINEERING

DETAIL ENGINEERING

DETAIL ENGINEERING PROCUREMENT

PROCUREMENT

PROCUREMENT

ASSIGNMENT

DETAIL ENGINEERING

PROCUREMENT

LONG LEAD ITEMS SUPPLY OTHER EQUIPMENT

SUPPLY

LONG LEAD ITEMS

ASSIGNED L.L. ITEMS

BULK MATERIALS

CONSTRUCTION

SUPPLY

OTHER EQUIPMENT

OTHER EQUIPMENT

OTHER EQUIPMENT

BULK MATERIALS CONSTRUCTION INSTALLATION

BULK MATERIALS

BULK MATERIALS

CONSTRUCTION

CONSTRUCTION

COMMISSIONING

COMMISSIONING

COMMISSIONING AND START UP

OPERATING TESTS

OPERATING TESTS

OPERATING TESTS

OPERATING TESTS

PERFORMANCE TESTS

PERFORMANCE TESTS

PERFORMANCE TESTS

PERFORMANCE TESTS

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

COMMISSIONING

13

Most common types



Lump Sum • Pros: clear definition of work, final price fixed, Contractor responsibility • Cons: long tendering period before contract award, rigidity, schedule • Common for Grassroots (even medium-size), difficult for Revamps



Reimbursable • Pros: quick contract award, global project schedule shortened, flexibility • Cons: final price not firm, large Owner supervision team • Owner may be assisted by a PMC (Project Management Consultant)



Payment on behalf:

similar to Reimbursable

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Orders and Subcontracts placed by Contractor and paid by Owner • Pros: quick contract award, global project schedule shortened, flexibility • Cons: Owner directly exposed to Sub-Contractors and Vendors

14

Variants



Lump Sum Turn Key: includes S/U (infrequent for revamp)



Reimbursable + Incentives: improves Contractor motivation • Target Price + bonus/malus • Incentive based on performance indices

• Schedule incentive • Cost + Fixed Fee (common for Umbrella contracts)

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

15

Risk for owner Remaining risks for the Owner: Owner prepares the Plant base description (wrong description  extra costs)



Owner is responsible of the Plant performance once the project is started



Plant incidents during project construction are typically not compensated



Owner has to manage early interface risks (FEED, early contracts, LLI)



An endorsement process is organised and put in place to reduce above risks



Owner has limited flexibility to make late scope changes (even if justified)



Schedule overruns may not be easy to recover and compensate



Too few Contractors able to perform the scope restrict Owner options

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



16

Risk for owner

Mechanical completion

Construction and pre-commissioning

Punch lists

Commissioning

Ready for Commissioning (mechanical completion)

Ready for start-up

Start-up and performance tests

warranty period 18 months or 24 m

Provisional acceptance

Final acceptance

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

17

Direct EPC Contracting option Idea Contracting Proceed to Concept or CFT

Concept and/ or Direct CFT

Approval and Contract Award

Detailed Engineering

Procurement (Simple Projects) Proceed to Basic

(Fabrication),Construction,

Basic (or FEED) Engineering

Commissioning, Start-Up, Perf.Tests Mechanical Completion Provisional Acceptance

Direct preparation of Project definition & requirements for CFT FID after potential Contractors Tenders evaluation & selection Depends on Contractors willingness to quote on this basis May allow alternate designs comparison(e.g debottlenecking)

Guarantee Period

© 2011 - IFP Training

• • • •

Final Acceptance RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

18

Long Lead Items management



Long Lead Items / Critical Equipment should be limited to: • Equipment that cannot be delivered on time at site if selected and purchased at EPC Contract time (possible examples: LNG Tanks, large rotating equipment, MCHE, extra heavy vessels, pipelines materials…) • Equipment requesting rapid specific design finalization to fit the requirement of the project (possible examples: air coolers for air cooled modularized LNG Plant) • Equipment that Owner desires to select before EPC Contract Award for “standardisation” purpose (example: control systems)

For an EPC contract, all tasks regarding the procurement and the initial steps of the LLI supply remain under the responsibility of the Owner



The endorsement by EPC Contractor of the LLI supply has to be implemented as early as possible during the tendering phase



If applicable, Licensor packages may be considered as LLI (EPC Contractors are very reluctant to accept the Licensors guarantees)

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



19

EPC Contract bidding process

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

20

EPC Contract bidding process

CONTRACT STRATEGY PLAN

Contracts Scope / Split

COORDINATION MEETING

Identification of suitable Tenderers Tenderers

Selection

Award type / Schedule

PRE QUALIFICATION TENDER ISSUE PERIOD BIDDERS LIST

Unpriced / Priced Evaluation Exact Terms & Conditions + Scope

Tenderers complete CFT, clarification notices issued

TENDER EVALUATION

PREPARE CALL FOR TENDER (CFT)

Ranking & Selection

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

APPROVAL

© 2011 - IFP Training

Contract Initialling

RECOMMENDATION TO AWARD

21

Call for Tender documents INSTRUCTIONS TO TENDERERS (Introduction & Instructions)

ITT

AGREEMENT & ANNEXES (Terms & Conditions)

AGR.

EXHIBITS & Attachments (Scope & Requirements) FEED dossier

Company Items

Particular Conditions

J

Subcontractors& Vendors

G

Coordination Procedure

K

Contractors Organisation

H

Quality

L

HSE

Scope

E

B

Schedule of Prices

F

C

Work Time Schedule

D

Performance Guarantees

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

I

A

22

Typical tendering procedure (medium-size project) Five Main Steps 3 months

4 months

3 months

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

??

Prequalification of potential Tenderers Preparation of the call for tenders (by Company)  Conditions for tender preparation & issue  Contract conditions (clauses, prices, etc.)  Scope of work and specifications Tenders preparation (by Tenderer)  Price preparation (critical path) Technical and unpriced commercial  Priced Commercial Tenders analysis (by Company)  Receipt and formal opening  Comparison  Clarification meetings  Additional submissions  Evaluation and recommendation Decision

23

Prequalification of Contractors



Verification that Contractors have sufficient • Experience • Organization and resources • Financial solidity

Process managed by knowledgeable Owner team, not a single person



Qualification questionnaires are launched, received and analyzed



Contractor facility surveys are performed for each good-looking one



Finding enough contractors to assure competition may be a problem



Tenderers with complementary skills may form a Joint Venture



Prequalification may be performed through public advertisement

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



24

“Call for tender” procedure



Objectives • Ensure a fair and equitable treatment of all tenderers • Select the best contractor after an open competition • Assure the best acceptable conditions for Owner



At the end of the selection process: • The successful tenderer should have full knowledge of the dossier • He shall not later be able not plead ignorance and dispute contract validity

A satisfactory tendering process has expected benefits for both



Clarifications will always be required during the process



Be ethical (any Owner has his own ethics rules)

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



25

Opening the bids Two philosophies exist for Tenders opening

Same opening date for technical and commercial tenders Technical and contractual

Updated tenders

Analysis, clarifications, confirmations

Recommendation

Commercial

Two different opening dates for Technical commercial tenders

Commercial Short list

Updated tenders

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

Analysis, clarifications, technical confirmations

Lowest bid selected

© 2011 - IFP Training

Technical and contractual

26

Tender period Tender Period: A reasonable tendering period shall to be allowed taking into account the project schedule, and the amount of work of tenderers are required to perform to complete the CFT.



Any request for extension of the tendering period shall be subject to approval. If such extensions are granted, all tenderers shall be informed by means of a Tender bulletin.



Tendering costs incurred by tenderers in connection with the bidding process shall normally be borne by the tenderers and this principle made clear in the CFT documents. However, the project may consider compensating unsuccessful Tenderers for the cost of tendering in certain circumstances (e.g. in the case of major EPC Contracts).

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



27

Tender evaluation Tender Evaluation Procedure: the responses to the CFT shall be assessed technically and commercially against previously established criteria by a team of representatives of the technical, contractual and commercial functions, co-ordinated by the Owner or PMC.



It may be appropriate to include Partner/Shareholder personnel within the Tender Evaluation Team.



Organisation and criteria of the Tender evaluation must be recorded and approved in a contract specific Tender Evaluation Procedure which shall contain details on the evaluation.



Project should give careful consideration to opening only the technical packages first. This will allow a technical evaluation to be performed to decide whether or not Tenders are technically acceptable.

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



28

Clarification meetings



Objective for Owner is to review and clarify with each Tenderer: • The Contract “execution plan” submitted, including the work schedule • The qualifications and alternatives submitted by the Tenderer • His reaction to the qualifications or suggestions made by other Tenderers • His position re. endorsement of the FEED and of the Long Lead Items



The clarification meetings will allow:

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Owner to appreciate the understanding and motivation of Tenderers • Tenderers to improve their understanding of the Owner’s position • Owner to improve the dossier quality by taking into account comments

29

Final selection Opening of final tenders and selection of the Contractor 

After having checked that each tenderer has accepted (through his initialling) the Contract conditions, the Owner opens the commercial proposals.



The selection is made in principle on the lowest price basis.



If it is not the case, the Owner is usually requested to document his decision (detailed scored evaluations).



Accept at the last minute an uncontrolled price reduction from one contractor outside the normal procedure would be:

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Unfair to other Tenderers • Counter-productive for future projects • Risky (Contractor will try to recover during the Contract execution)

30

Design competition strategy (applicable to some mediumsize Projects) An EPC Contract can be negotiated on LSTK basis after a Design Competition (paid FEED and offer based on a limited Project Definition).



Allows to bring innovation and competition of designs



Basis of Design and minimum SOR requirements, Project objectives, areas open to new or novel « Design », evaluation criteria should be specified by Cy



FEED scope should be defined to avoid « short » FEED, although the FEED content may be lighter than required to be the basis for a later LSTK bidding



Areas of innovation should be followed-up by Company team in order that they fall under Company expectations



Company teams are needed at each Competitor’s office to follow the process



Equal treatment should be applied to both Competitors for fair competition



Company should ensure that key participants to the design competition can participate for each Bid (e.g. Process Licensors, Critical Equipment suppliers…)

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



31

Project EPC contracting Key points to keep in mind 

Good Project execution relies on “solid” contract, based on: • • • • •

Clear scope of work (clear for both) Confidence in each party performance capability Good definition and management of interfaces Review and Agreement, for each party, of all contracting aspects Openness to change, but risk management



Placing the EPC contract is a major Owner responsibility



Some EPC contracts need less Owner management resources than others, but any EPC contract has to be managed



A good contract is based on a win-win situation © 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

32

ATTACHMENTS I.

Examples of Medium-Size projects

II.

Detailed tendering elements

III. EPC contract structure/contents © 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

33

ATTACHMENT I Examples of Medium-Size projects

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

34

EPC LSTK: Gas plant accro project Santa Barbara 2nd Train extension EPCC LSTK PROJECT (Compl. 1994): GRASS ROOTS PLANT (Compl. 1994) 2x400 MMSCFD Trains; 2nd Train to be completed rapidly

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Discuss Contracting Plan & contract type for Train 2 (Duplicate Train)

35

Small project example

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

38

ATTACHMENT II Detailed tendering elements STEPS

EVALUATION TABLE © 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

42

Tendering detailed steps When an ITT includes a FEED, and if the construction execution plan is based on unit-rates contracts (x) per trade, the proposal critical path usually goes thru: Preparation of MTOs and BOQs for construction contracts



Issue of inquiry package to the potential construction contractors (unit rates contractors & others)



Preparation of bids by construction contractors



Receipt and review of these bids, Preparation of comparative construction estimates, finalization of construction estimate



Estimate of related « contingencies » (MTO allowances, provision for changes...)



Input to Project estimate



Finalisation of construction execution plan; Management Price reviews



Preparation of commercial proposal with corresponding required price break-downs and unit prices



Dispatching of the proposal (generally in sealed envelopes hand delivered at Owner designated office) (x) Unit-rates contracts are contracts with a unit price for « direct cost » of each item shown in Bill Of Quantities and a lump sum price for « indirect costs ». The lump sum price does not change as long as the contract estimated price (based on the estimated quantities) remains within +- x %

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



43

Tendering detailed steps When the CFT is structured per common international practice for major projects, other main tasks include: FEED review / endorsement; CFT review



Preparation of clarification requests (follow format and watch dead line)



H.O manhours estimates



Bulks MTOs and estimate of MTO allowances



Preparation of requisitions and inquiries to Vendors, technical & commercial evaluation



Proposal Executive Summary

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



44

Tendering detailed steps 

Technical Offer preparation with, in general: • FEED endorsement report • Project Execution Plan (Engineering, Procurement, Construction, Commissioning, Project Controls, Materials Controls, Systems etc.), EPCC Schedule • Technical qualifications • Proposal Forms • A mandatory principle is to strictly answer Owner requirements and required proposal formats in the ITT



Commercial Offer preparation with, in general: • Prices and Price breakdowns • Unit prices and rates • Payment Conditions

• Commercial qualifications  

CFT Agreement review and Legal qualifications And, if required, financing proposal

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Bid Bond

45

Example of tender evaluation table No

CATEGORY

Weight (A)

1.0 1.1 1.2 1.3 1.4 1.5 1.6

MANAGEMENT PROJECT MANAGEMENT CONTRACTUAL COMMERCIAL COMPLIANCE SUB-CONTRACTING QUALITY ASSURANCE & QUALITY CONTROL HEALTH, SAFETY & ENVIRONMENTAL PROCEDURES SCHEDULE COMPLIANCE CAPABILITIES AND PLANS DETAIL ENGINEERING PROCUREMENT FABRICATION, CONSTRUCTION & TESTING TRANSPORTATION, HOOK-UP, INSTALLATION & SURVEY PRE-COMMISSIONING & COMMISSIONING

3.0 3.1a 3.1b 3.2 3.3 3.4 3.5 3.6 3.7 3.8

PROJECT EXECUTION PLAN FOR DETAIL DESIGN RISERS – FLEXIBLE RISER SYSTEM RISERS – ORGANISED RISER SYSTEM FLOWLINES (PIPE-IN-PIPE or BUNDLE) SPOOLS & JUMPERS UMBILICALS OIL LOADING TERMINAL SPM BUOY OIL LOADING TERMINAL OIL OFFLOADING LINES FPSO MOORING SYSTEM INSTALLATION ANCHORS

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

CONTRACTOR B Un-weighted Score Weighted Score (B) (A * B)

Sub Total:

3.0% 2.0% 2.0% 2.0% 2.0% 2.0% 13%

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Sub Total:

4.0% 3.0% 8.0% 6.0% 6.0% 27%

0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00

Sub Total:

8.0% 8.0% 8.0% 8.0% 8.0% 7.0% 7.0% 6.0% 60%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

OVERALL TOTAL:

100%

0.00

0.00

0.00

0.00

See Note

© 2011 - IFP Training

2.0 2.1 2.2 2.3 2.4 2.5

CONTRACTOR A Un-weighted Score Weighted Score (B) (A * B)

46

Example of tender evaluation table Example of tender evaluation table Scoring Criteria (1/2 point possible)

1 : unsatisfactory 2 : satisfactory

Safety

Quality

Specialists

Contracts Responsible

Average score

Weight coefficient

Weighted score

3 : good 2

Procurement quality management

3

Capability adapted to scope

3

Job conformance to tender

3

Conformance to contract terms

2

Conformance to schedule

3

Quality control performance

2

Safety control performance

3

Quality of studies & technical documents

1

Management administration of project

3

Adaptability to changes

1

Subcontractors selection quality

3

Relations with client

1

Social climate

1

Bank confidence

2

Comments : compulsory if score under 2

Total

33

© 2011 - IFP Training

Engineering quality

Evaluation /33 RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

47

ATTACHMENT III EPC contract structure / contents

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

48

Work scope typical contents

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

49

Work scope typical contents

© 2011 - IFP Training

RC - PR GES - 08171_A_A - Rev.1 - 18/07/2013

50

Related Documents


More Documents from "softmailer1253"