07_hse, Quality & Risk Management

  • Uploaded by: JJ Welding
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 07_hse, Quality & Risk Management as PDF for free.

More details

  • Words: 6,569
  • Pages: 81
Loading documents preview...
Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 7. HSE, Quality and Risk Management

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

Management of Medium-Size / Revamping Projects: course content I.

Introduction

II.

Preliminary Studies

III. Basic Engineering (or FEED) IV. EPC Contracting V.

Organization and Engineering

VI. Procurement VII. HSE, Quality and Risk Management VIII. Project Control (cost/schedule) X.

Completion / Commissioning / Start-up / Closure

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2013 - IFP Training

IX. Construction and Fabrication Management

1

HSE Management

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

2

Scope and Objectives 

Scope: • “HSE design”: impact of the permanent change created by the Project • “HSE construction”: risks during the field work stage of the Project



HSE Design objectives • • • •



Identify HSE hazards created by the change Evaluate their criticality and the need for mitigation measures Document, obtain approvals, and design the Project accordingly Verify before Start-Up that the HSE measures are effective

HSE Construction objectives

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Ensure personnel Safety (incl. Owner and contractors) during Execution • Ensure the absence of Environmental incident during Construction will be discussed in more detail in the Construction chapter

3

HSE Management HSE Design

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

4

Objectives



Build safe facilities, through their life-time, by: • • • •



Identifying and evaluating all HSE hazards of the Project Eliminating them, or making their effects acceptable for Owner Permitting effective control of the remaining hazards Complying with applicable local regulations and Owner standards

Main areas of application: • Safety and Health (Owner, Contractors, surrounding communities) • Protection of Natural Environment (air, water, soil, waste) • Preservation of Owner image in case of a major accident © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

5

Main terms & definitions



Hazard • Existing potential of a product, a process, or a practice to cause damage to people or to environment



Risk • Potential accident created by the existence of a hazard • RISK value = Probability x Consequences [Severity or Gravity]

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

6

Steps and tools PREVENT Decrease probability of release

CONTROL Avoid accidental ignition of release

MITIGATE Mitigation of consequences

Provide for escape, evacuation, rescue

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

HAZAN (consequence) analysis, QRA, Safety Distances

Layout & Zoning Ventilation Insulation Electrical isolation ESD upon Gas detection Dispersion Drainage

Consequence analysis Escalation analysis Risk assessment

Escape, Evacuation, and Rescue study

Layout Fire detection ESD & EDP Bunding & Drainage Blast proofing Active Fire protection Passive fire protection

Layout Protection of evacuation routes & means Alert Emergency room

© 2013 - IFP Training

EVACUATE

HAZID, HAZOP Safe design, Frequency analysis

Process control Process isolation Overpressure protection Material selection

7

HSE Studies during project lifecycle

PRE PROJECT STUDIES

PROJECT SOR

EPC STAGE

BASIC or FEED

P&ID REVIEW

S.O.R CHANGE

START UP

DEROGATION REQUESTS

SAFETY DOSSIER

HSE CASE / REPORT

HAZOP 2

HAZOP 3

PTR 1

PTR 2

PTR 3

POST STARTUP AUDIT PTR 4

PTR 5

6 months after S/U

© 2013 - IFP Training

HAZOP 1

Feedback

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

COMMISSIONNING

HAZID HAZAN

HAZID HAZAN

TECHNICAL SPECIFICATIONS

PRODUCTION

8

HSE steps at Preliminary stage



Environmental design Management steps: • EBS (Environmental Baseline Survey): analysis of the initial status of the site (reference status for further controls comparisons) • EIA (Environmental Impact Assessment): detailed description of the impacts of the projected activities on the site and mitigation measures for reducing these impacts to a level as low as possible



HSE Risk Assessment tools: HAZID (HAZard IDentification) PRA / QRA (Preliminary/Quantiative Risk Assessment) HAZOP (HAZard and OPerability study) DREAM: analysis of Operational Releases (water, air) Various computerized atmospheric dispersion models Various 3-D Oil Spill Contingency and Response models

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • •

9

HAZID (Hazard Identification)



Method to identify hazards, mainly those outside the Project: • • • •

Use of Guide word and prompters list “Helicopter” view required, zoom in as necessary Hazards from the project affecting the neighbouring environment Hazards from outside (natural, weather, other industries…)



Done normally once, at the Preliminary stage



Key attitude: openness, rigorousness, thoroughness



Needs a multidisciplinary team knowing the scope

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Multiple technical expertise of the team • People having experience of executing projects • A leader, but no censor, and some imagination

10

HAZID (Hazard Identification)



HAZID categories and key-word examples: • • • • •

Fire Explosion Toxicity Dropped objects Collision

Plant, sources of heat, risky zones Sources of ignition, release duration Vent, chemicals Crane, equipments, scaffolds Truck, vessels, engines



Helps FEED and selection (or elimination) of alternates



More about HAZID: see Attachment I © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

11

Preliminary/Quantitative Risk Assessment



Semi-quantitative method referring to predefined scenario



The scenario have been defined using another method • HAZID or other type of check-list • What-If review



The analysis aims at selecting a limited number of major scenario on which a more detailed risk assessment (QRA) will be made

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

12

PRA/QRA elements



Probability of occurrence, such as: • 1 per year, 1 per 1 000 years, 1 per 10 000 years, 1 per 100 000 years



Type and gravity of lethal consequences, such as: • • • • • •



Risk of death for 5 hours spent to go mountaineering each week-end Risk of death in the industrial activities at high risks (mines) Risk of death by road accident Risk of death in an accident at work in an industrial activity at low risk Risk of death in a fire or an explosion due to a gas leak at home Risk of death by lightning

Assessment tools:

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• PRA: matrix ranking (see next page, or Owner-specific matrix) • QRA: quantitative evaluation, based on statistical records and models

13

Risk-ranking matrix Probability of event

Owner matrix categories may be much more precisely defined

10-1 Likely

Unacceptable

10-2 Unlikely 10-3

Tolerable if ALARP

Very unlikely 10-4

Extremely unlikely

Acceptable

10-5

10-6 Moderate

Serious

Major

Catastrophic

Gravity of consequences RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

Disastrous

© 2013 - IFP Training

Remote

14

HAZard and OPerability Study



Objectives: • Identify reaction of plant during abnormal process conditions (Malfunction or mis-operation) that could cause a hazard • Check if design adequate to prevent hazard occurring • Record all corrective actions, and remaining hazard (accepted)



Multidisciplinary team with : • A trained leader having planned the work • Project engineers knowing in detail its content • Operations knowledgeable people

Needs an accurate version of all P&IDs (so a tool for FEED)



Lengthy (may take several weeks) but very effective

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



15

Project Technical Reviews



Interdisciplinary independent team (with Owner) reviews of the main HSE documents or studies prepared by the project team: HAZID, Consequence Analysis Flare, vent radiation and dispersion Safety Concept, SOR Hazardous area classification Fire, Gas and low temperature detection Pressure Protection and Relief Emergency Shutdown and Emergency Depressurisation Active and Passive Fire Protection Lay out Escape Evacuation and Rescue

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • • • • • •

17

Safety Concept



Main Purposes: • State Owner requirements for the protection of assets & personnel • Indicate safety requirements for implementation in plant design • Identify derogations to reference standards (Owner corporate) • Hand out to Operations a complete document on safety design of the unit • Keep a reference document for subsequent: − Internal, external or even regulatory auditing − Updates during Engineering − Change Management © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

18

Safety dossier



Objectives • Assemble all safety-related documents for permanent reference • Give to the operator a clear and traceable view of safety design • Safety basis for possible future modifications of the unit



Typical contents Safety Concept (updates & revisions included) HAZOP # 1, 2, 3 reports, including approved corrective actions Minutes of Technical Reviews # 1, 2, 3, 4 Waivers to Corporate standards, with supporting documents List of approved safety-related documents and studies Evidence that all HSE actions decided have been completed

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • •

20

HSE Management HSE Construction

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

21

HSE Construction 

Identification of particular risks linked to Construction • Planning and scheduling of Construction activities • Risks related to SIMultaneous OPerationS (SIMOPS)



Development of Safety Management System and HSE Plan • Construction Key Performance Indicators (KPI), including − Target level, monitoring process and responsibility − Management review frequency, followup actions

• Key HSE procedures, training, field audit planning • HSE resource planning: field supervision, budgets, safety equipment 

HSE input in Subcontractor selection process

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• HSE policy, goals, organization, job task analysis • Past HSE performance, improvement actions underway • Field controls, incident investigation skill

22

HSE Construction



Technology-related risks • Flammable / toxic / explosives substances • Complex mechanical equipment • Process conditions (units in operation)



People-related risks Application of life-critical procedures Simultaneous operations, congestion Human behavior aspects, sensitization Communication between teams

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • •

23

Reporting 

HSE Reporting frequency, contents and responsibility should be defined



Main purposes: • Inform Authorities, Owner and Contractor Management • Maintain/develop HSE awareness within Project subcontractors



team

/

Typical contents of a monthly HSE construction report: KPI monitoring (month, average, year-to-date, since Project start) Safety Recordable accidents and potentially serious near-misses Field audits performed and common observations Significant spills and air pollution releases from the Project works Waste and soil pollution concerns, if any Main improvement actions decided and/or actually implemented

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • •

24

Field observations

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

25

Quality Management

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

26

Definition

Expressed needs

Customer Satisfaction

Implicit needs

QUALITY SYSTEM

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

Open behavior

© 2013 - IFP Training

Conformance to scope

27

Scope and objectives



Scope: for each EPC stage: • Quality Management System • Controls (conformance) and communication (behavior)



Objectives:

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Provide assurance to Owner that the technical scope will be achieved • Clearly define scope change process, consequences, and Owner role • Provide adequate documentation to Owner and 3rd-parties • Assure timely handling of non-conformances (Contractor, Subcontractors) • Comply with agreed certifications (ISO-9001, 10006, 14001, etc.)

28

Management System



The word “Management System” is difficult to define



The best way to explain it is to list its main components • • • • • •

Culture, policy, permanent goals Organization, roles and responsibilities of each position Processes (Work/Production and Support) Resources available (human, technical, financial) Controls Communication and information flow

Owner and EPC Contractor Management Systems should be consistent



Application to Suppliers and Subcontractors needs to be clarified

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



29

Common Standards

Quality

Internal Control

Safety

IT & Communication

Environment

Policy Charters

Health Security

Management and Organisation

Social Reponsibility Sustainable Development Ethic & Integrity

General and Transverse

Projects: ISO-10006

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Entity specific Working documents

30

Continuous Improvement P.D.C.A.: the Deming wheel

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

31

Quality Management

Project Organization

Surveillance Philosophy

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

Document Management

Project Objectives Project Management

Project QMS

Interface Management

Risk Management Change Management

© 2013 - IFP Training

Key topics

Purpose

Project Quality Management System

32

Project Quality Plan Project Organization



PQP reflects an established Quality Management principle

Project Objectives Project Management

Project QMS

• Common understanding of what Quality on project means • A standardized implementation of the management principles • A better assurance to get what is expected 

Project Quality Plan

− Project Execution Plan − HSE Management Plan − Risk Management Plan RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

and

© 2013 - IFP Training

• Objectives and Commitments are expressed in writing • Project QMS is presented (organization, content implementation) • Project control principles are defined • Procedures and associated resources to be applied • Consistency with source documents

33

Project Quality Plan Project Organization



Typical contents: 1. 2.

3. 4.

5. 6.

Project Management

Project QMS

Project characteristics (Field description, scope of work, stakeholders) Project strategy (Quality policy, objectives, KPI, Performance reviews) Project Management (Organization, Authorities, Interfaces control, Team co-ordination, Reporting, Communication) Project Quality Management System (Risk-based Quality, Control of documents and records, Continuous Improvement process) Project resources management (Cost control, Schedule control, Human Resources management, Material resources management) Project operational processes (Detail Engineering, Procurement and subcontracting, Construction, Commissioning) Verification and acceptances (Monitoring, equipment verification/certification, non-conformances, Internal Quality audits)

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

7.

Project Objectives

34

Quality Management Project Organization



Key issues • • • • •



Project Objectives Project Management

Project QMS

Fulfil the initial requirements (SOR, FDP…) Have a defined and clear Project Team organization Have a complete and approved documentation process Coordinate the Project Risk Management activities Assure regulatory compliance and timely approval

Key Controls Project Reviews and Audits, as planned, with Owner involvement Assure the correct implementation of Owner standards Quality Control Plans for each Supplier and Subcontractor Document verification by adequate specialists Effective and timely implementation of corrective actions

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • •

35

Interfaces Surveillance Management



It’s important to implement a system that allows

Risk Management

Project QMS

Change Management

Interface Management Document Management

• To keep track of interface issues • To give ownership of interface issues to the relevant function 

Interfaces with Owner are critical for Revamping projects • Ignoring Operations and/or HSE interfaces may lead to: − HSE exposures during Construction − Difficulties at the Completion/Acceptance stage

• Ignoring Technology interfaces may lead to: − Late (but mandatory) scope changes − Blockage at the Completion/Acceptance stage

• Ignoring Maintenance interfaces may lead to:

Refer to Interfaces Management (section 5) Project shall retain the control over interfaces RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

− Lost cost-reduction Construction opportunities − Difficulties, reworks, claims at or after Startup

36

Documentation Surveillance Management

Refer to Documentation Management (section 5) 

Change Management

Interface Management Document Management

Consider documentary requirements throughout the unit lifetime: • • • • •



Risk Management

Project QMS

Pre-FEED and FEED EPC Contract execution, til completion Start-up and early operations Routine operations, maintenance, ageing Dismantling of facilities

Documentation Management System should be easy to use for:

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Interface management (mainly during execution) • Change Management (mainly after execution)

37

Change Management Surveillance Management



Types of changes:

Risk Management

Project QMS

Change Management

Interface Management Document Management

• Changes to SOR • Contractual changes • Technical modification requests 

Even minor-looking changes may have a major impact • Always open “change dossier” • Always perform a Risk Analysis (HSE, Cost, Schedule)



The Change Management System should allow to: • • • •

Keep track of all changes, irrespective of type Assure Project Team timely information Review and approve (or reject) all changes Reflect consequences to Project Design and Construction

Ignoring or underestimating a change can lead to disaster RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Refer to Changes Management section under Project Control section

38

Risk Management

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

39

Risk Management



In the execution of a Project: • HSE Design & Construction risks are not the only risks • Some other risks may have a much bigger financial impact − Schedule delay (if Turnaround-related, or if major savings) − Non-conformances compromising the Business objective − Cost overrun above the allowable budget

• Projects in existing facilities have specific risks − Safety issues due to SIMOPS − Presence of chemicals in the work environment − Reliability impacts on running units

PROJECT RISKS ARE NOT PROPORTIONAL TO PROJECT SIZE © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

40

Categories at Owner level

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

41

Process Project Start

Yes

RISKS REVIEW WORKSHOP with P.MT Managers & LDEs.

PROJECT REVIEWS

CONTRACT REVIEWS

Yes

RISKS REGISTER is updated (initially from Concept /FEED or prepared)

No

Significant Project impact?

RISKS EVALUATION & MITIGATION PLAN for risks that require a response Each risk is followed by a « Risk Owner »

PCM in charge of administrating the Risks Register Reviews on monthly basis at least, with risks Owners, PMT & LDEs inputs

New risks or Risks modification?

Yes

Project Mgt Meetings Insp. Reports, Site reports, Project Changes, etc. RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

No

42

Consequence rating



“Severity” or “Consequence rating” generally evaluated with respects to importance of potential impacts on: • • • • •

Health & Safety System / Environment Production / Oil-in Cost Schedule

Impact generally rated with a 1(low side) to 5 (high side) rating



Highest value assigned to the five areas: Risk “Severity Rating” or “Consequence Rating”.



Companies & Contractors establish their own Project Risks Management Processes to identify & control the Project risks. The next slides describe the process principles.

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



44

Consequence rating

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

45

Probability rating

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Manageability: Ability of Project Management Team to Manage the Risk For some risks, Probability rating may be assessed by calculations

46

Prioritization (or Criticality rating)

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

47

Examples of mitigation plans Avoid the risk: stop the project activity affected by the risk (modify the design, change plan or practice…)



Accept the risk: manage the risk if assessment leads to acceptability criteria. Consider contingency planning.



Transfer the risk: through transfer of responsibility (insurance, other contractor being more able to manage the risk)



Reduce the risk probability: implement a specific inspection plan…modify an engineering, purchasing, contracting or transportation plan



Reduce the risk severity: sparing, contingency plan, scope split between more contractors…

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



48

HSE Quality and Risk Management Key points to keep in mind Risk may be related to any of the project key objectives



Both probability of occurrence and gravity should be evaluated



High risk score (probability x gravity) leads to preventive action



Standard checklists (e.g. HAZID) help to identify possible risks



HAZOP is the most common HSE Risk Analysis tool at FEED stage



Semi-quantitative risk scoring needs expertise and modelling tools



Mitigation can act either on probability or on consequences, or both



Quantitative Risk Analysis helps defining the required contingencies



Triggers help predicting that the probability of risk is increasing



Action plans, once approved, should be closely monitored



When the project progresses, Risk Analysis should be updated

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



49

Attachments I.

More about HAZID

II. More about HAZOP III. Quality Surveillance

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

50

Attachment I More about HAZID The HAZID method

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

51

HAZID (HAZard IDentification)



Brainstorming using a standard list of keywords and experience of participants



Purpose: concentrate team attention on : − − − −

Impact of surroundings and environment on the Project Impact of the Project on the surroundings Interference between the main design elements General purpose dangers

HAZID mainly considers non-process exposures



HAZID looks at the whole project life-time from start-up to dismantling



HAZID looks at combined / simultaneous operations

HAZID PROJECT management RC - PR–GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



52

Workflow 1. Identify causes related to the various keywords 2. Evaluate potential consequences 3. Verify effectiveness of preventive and protective measures 4. Recommend actions if measures are insufficient

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

53

Workflow



Each keyword is discussed within a team of experienced people



Conclusions: summary table showing the following categories • • • • • •



Danger Causes Consequences Risk gravity level Risk reduction existing measures Proposed action plan

RC - PR–GES - 08173_A_A - Rev. 1 - 18/07/2013 HAZID PROJECT management

© 2013 - IFP Training

Action plan formally reviewed and accepted by responsible Manager

54

Example



Danger: seismic



Causes: selected location in a seismic area



Impacts: structural damage, rupture of chlorine pipe



Risk gravity level: 1 (major)



Risk reduction existing measures: • Design according to latest seismic regulatory standards • Minimization of chlorine liquid inventory

Proposed additional action plan: • Double check calculation with independent third-party expert • Isolation of liquid chlorine inventory with water curtain

RC - PR–GES - 08173_A_A - Rev. 1 - 18/07/2013 HAZID PROJECT management

© 2013 - IFP Training



55

HAZID Keywords

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

56

HAZID Keyword Categories



Section 1: exposures external to the Project • • • • •



Impact of the Project on the Environment Impact of the Project on People Impact of Human behaviour on the Project Impact of the Environment on the Project Exposures related to infrastructure

Section 2: exposures internal to the Project • Impact of the Process risk on the Project • Impact of the risk created by Utilities on the Project • Other types of risks within the Project

Section 3: exposures of the Project for people

RC - PR–GES - 08173_A_A - Rev. 1 - 18/07/2013 HAZID PROJECT management

© 2013 - IFP Training



57

Section 1 (external hazards)



Natural Hazards (extreme weather, lightning, seismic events)



Natural Environment (air releases, water releases, soil pollution, emergency upsets, waste management)



Human Environment (economic, adjacent industry, adjacent population, transport corridors, land use, vibrations, visual impacts)



Human Constraints (security, social unrest, strikes)



Infrastructure (emergency access, mutual assistance, evacuation) © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

58

Section 2 (internal hazards) Product (flammability, toxicity, environmental, inter-compatibility)



Process (reaction, leaks, pressure, vacuum, temperature, H/L level)



Maintenance (philosophy, preventive, start-up, shutdown)



Utilities (firewater, foam, drains, blanketing, air, water, power)



Other in Facility (flooding/spill, structural, rotating equipment, pressure vessels, site traffic, loading station, equipment supply



Health Hazards (workplace, product exposure)



Safety Hazards (day-to-day work)

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



59

HAZID (Hazard Identification) 

Example of HAZID Worksheet (CARINA-ARIES OFFSHORE HAZID #1) • Priority Categories: 1. 2. 3.

Mandatory (Immediate action) Recommended (Short Term action) To be developed (Long Term action)

SYSTEM / NODE

UNIT / LOCATION

GUIDE WORD

CAUSE

12

SUBSEA ITEMS

SUBSEA PIPELINES

EXISTING HIDRA SUBSEA PIPELINES

Construction activities / pipes laying / barge anchoring

Potential damage or rupture of Hidra existing pipelines.

No specific protection to subsea existing pipelines. Physical & electronic surveys to be performed on site to locate and mark existing pipelines.

Anchor pattern to be submitted to TA marine Dept for approval. Operating procedures to be issued by contractor and validated by project. Work permits to be used when works are carried near live installations. (distances to be defined by TA) Specific HAZID to be carried out with TA operations (Mc Dermott).

2

13

TOP SIDES

ONSHORE PIPELINES ARRIVAL

PROXIMITY TO TRANSPORT CORRIDOR

Crossing of onshore pipes

Potential pipes damages or rupture and gas release.

Survey and marking of existing pipes carried out.

On site checking of pipes markings. Insure safe clearance between existing and new pipes. Shut down and depressurisation of existing pipes while drilling new pipe tunnel. Specific HAZID to be carried out with TA operations (Mc Dermott).

2

14

TOP SIDES

ONSHORE PIPELINES ARRIVAL

PROXIMITY TO HOTEL FACILITIES

Crossing of onshore pipes

Potential pipes damages or rupture and gas release close to hotel facilities.

Safe distance required between new pipes and hotel as per onshore preproject.

Landfall and pipes route to be agreed by TA as per safety concept requirement with offshore and onshore project teams. Specific HAZID to be carried out with TA along with the onshore project during basic phase prior to EPC award.

1

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

POTENTIAL DEVELOPMENT & CONSEQUENCES

SAFEGUARDS / CONTROLS IN PLACE

ACTIONS / CONTROLS TO BE INCORPORATED

PRIORITY

© 2013 - IFP Training

N⁰

60

ATTACHMENT II More about HAZOP Hazard & Operability Studies

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

61

Introduction: HAZOP Study



HAZard & OPerability Study method was developed by ICI in the 1960s and its use and development are encouraged by Chemical Industries Association (CIA).



Most common use is for new facilities, however it is often applied to existing facilities and modifications.



Primary purpose is to identify and evaluate hazards within a planned process or operation.

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

62

Essential features



HAZOP Study is a structured analysis of a system, process or operation carried out by a multi-disciplinary team.



Whilst being systematic and rigorous, it also aims to be open and creative.



This is achieved through the use of a set of guide words in combination with system parameters to seek meaningful deviations from the design intention.



It is good practice to develop a clear design intent linked to the P&IDs being used, to be referred to during the search for deviations. © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

63

Essential features A meaningful deviation means one that is physically possible, such as No Flow / More Pressure / More Temperature ...



Deviations such as No Temperature have no sensible meaning and are not considered.



The team concentrates on those deviations that could lead to potential safety or environmental hazards, operational or quality problems.



Where causes of deviations are found, the team evaluates the potential consequences using experience and judgment.



If the existing safeguards are deemed inadequate, the team recommends an action for change or calls for further investigation of the problem.

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



64

Essential features



The physical boundaries for the study must be clearly defined as part of the specification / ToR for the study.



Study nodes or stages should also be defined by the study leader in order that the study progresses in a systematic manner, with the plant to be studied ‘sectioned’ into meaningful nodes.



Each node requires a design intent …



The range of operational modes should also be defined in the ToR – normal operations, start-up, shut-down, emergency conditions … © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

65

Data / Documents required



As a minimum, the following should be available: • • • • • • • •

P&IDs PFDs, UFDs Material and energy balances Operating conditions Operating and control philosophy / methods Equipment and instrument specifications Relief settings Alarm and trip setting

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

66

Limitations



Difficulties can be created through inadequate terms of reference or poor definition of the study scope.



It is not infallible … expertise and experience within the team is crucial to the quality and completeness of the study.



The accuracy and extent of information available to the team and the manner of the study all influence its success.



The study is not to become a re-design meeting. Analysis of an identified problem may require further study outside of the meeting. © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

67

Hazard & Operability Studies 

The main operating parameters considered are: • • • • • •



Human Factors Vibration / Cavitation Separation Maintain / Preservation Sequence Wrong Materials

The main GUIDE WORDS, together with their meanings, that are used: NO or NOT: MORE: LESS: AS WELL AS: PART OF: REVERSE: OTHER THAN: WHERE ELSE:

none of the design intent achieved a quantitative increase in a parameter a quantitative decrease in a parameter additional activity occurs only some of the design intention occurs the opposite of the design or operational intention another activity takes place can flow or transfer come from or go to

Modes of Operation considered: Start Up / Shutdown / Normal Operation

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • • • • 

Pressure Temperature Flow Level Control Loss of Utilities

68

Hazard & Operability Studies



The fault conditions listed below can lead to overpressure; they shall therefore be taken in account during the HAZOP study:

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Blocked outlet / blow by / inadvertent inlet valve opening from a high pressure source / check valve malfunction • Loss of cooling / loss of power / loss of cooling agent / mechanical fan failure, etc. • Fire / excessive heat input / unsteady process • Utility failure and or loss of control (air, instrument, power...) • Uncontrolled repressurization • Heat exchanger tube failure / transient pressure surges / quick closing valves • Slugging

69

Attachment III Quality Surveillance Project Quality Surveillance

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

70

Definitions (1/3) 

Quality Assurance • Quality Assurance is the CONTRACTOR management process of systematic planning, implementing and evidencing organizational provisions, which, if properly applied, will reasonably assure OWNER that the quality of the final product will be achieved in line with the Contract requirements.



Quality Control • Quality Control is the CONTRACTOR operational process of inspecting and testing individual components or assembled units or packages to check the conformity to Contract requirements (+required documentation).

Quality Surveillance • Quality Surveillance is the OWNER process of monitoring at second level that the Quality Assurance / Control is properly implemented by CONTRACTOR.

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



71

Definitions (2/3)



First party: means that verifications are performed by the EPC Contractor upon itself, or upon his Suppliers / Subcontractors



Second party: means that verifications are conducted by Owner (or associated stakeholders having an interest in the organization), or by others on their behalf (like independent auditors)



Third party: means that verifications are conducted by external, independent auditing organizations, such as those delivering regulatory authorizations, registrations or ISO certifications © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

72

Definitions (3/3)



Certification: means a formal procedure by which an accredited or authorized person or agency assesses and verifies (and attests in writing by issuing a certificate) the attributes, characteristics, quality, qualification, or status of individuals or organizations, goods or services, procedures or processes, or events or situations, in accordance with established requirements or standards.



Classification: means a document issued by a shipping classification organization confirming the class under which a vessel is registered. © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

73

Quality Surveillance



2 key Quality Plan surveillance principles • Quality audits, and guidance on Quality issues • Quality Control assessment at manufacturing sites



Consideration with regards to Certified Contractors • Any ISO-certified contractor has some advantages compared to the non-ISO-certified ones (quality understanding, methodology). • But Quality is also an attitude and it is not granted for ever • Even ISO-certified contractors have to be controlled (but controls can be lighter, less frequent, and more oriented towards critical elements)

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Surveillance preparation is a precedent to accountability  You get what you inspect

74

Attachment III Quality Surveillance Surveillance Philosophy

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

75

Quality Surveillance



Quality audits • Follow a formalized process (see ISO-19011)  Audit questionnaire to be prepared and used • Audit adapted (content, duration, auditors) to each Project • Feedback from previous Projects taken into account



No complacency when gaps are identified

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Audit results showing a lot of Major deficiencies in the contractors Quality management systems may result in their ISO certification being challenged or suspended

76

Quality Surveillance



Why implement a Surveillance plan?



Because Contractors and Operators have different perspectives • • • •



Control/Surveillance cannot be improvised once things are on-going Allow to prepare the contracts and follow-up mechanisms Allow to anticipate volume and resources to cover inspection Allow to supplement Contractor, and to take-over in case of failure

Surveillance plan issuance: When? • During basic engineering phase / before EPC contract award • Once equipment lists are available © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

77

Quality Surveillance philosophy



Quality Control Plan (QCP) • QCP is the document describing the Contractor operational processes of control: reviewing, verification, qualification (in case of special processes), inspection, testing activities at each stage



Surveillance plan • By convention, surveillance is limited to the activities which allow to get the insurance that Control activities (inspection) are satisfactorily performed by Contractor • Surveillance plan is based on Quality Control Plan • Owner involvement to be contractually defined and agreed © 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

78

Quality Surveillance Plan



Basis of definition  Criticality rating exercise • Criticality rating exercise perform by contractors. • Parallel exercise performed by the project team. • Contractor and Operator do not have the same vision.



Surveillance plan objectives • To allow the project team members to react quickly. • To complement surveillance definition planned by contractor. • To substitute to inadequate contractor surveillance.



To exercise surveillance in all contexts.

Accountability requires surveillance RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Design & Construction phase. • Yards, manufacturers, vendors, sub-contractors.

79

Quality Surveillance Plan 

Inspection & Test Plan (ITP) • Consolidated document listing all the quality assurance and quality control activities, and of there satisfactory performance. • Each ITP topic co-signed by entities involved, at completion of the related activity. • ITP is co-signed at end of the realization & satisfactory performance of all activities.

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

80

Attachment III Quality Surveillance Project Quality Surveillance

© 2013 - IFP Training

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

81

Quality Surveillance Plan - Definition



Step 1: Criticality rating exercise • Based on a formal methodology, with established criterias. • Basically for each equipment / PO. • Ensures traceability and is effective.



Step 2: Identifying the resources • Project internal (discipline specialists). • Corporate specialists – experts. • Frame contract with inspection Services Company.



Step 3: Set up the execution mechanisms

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• To make information available to the right people. • To collect (and act upon) the inspection results.

82

Quality Surveillance Plan - Outputs 

Quality records - Typical content

RC - PR GES - 08173_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Approved Quality Plans & Inspection & Test (Surveillance) plans • Material certificates (mil, calibration, …) • Qualification of processes records (WPS, NDT, heat treat, painting, Weld repair, …) • QC procedures and records (visual inspections, NDT, check-lists, …) • Survey reports (vibration, alignment, weight, …) • All Traceability records (marking, mark-up, …) • All NCR's and waivers (accepted and rejected) • Third party certificates & reports (design appraisals, verifications, classifications, certifications, fire test, cranes, …) • Contractual certificates (RFC, RFSU, transportation, hand-over, load-out, acceptance, …) and associated punch lists • Overall pre-commissioning and Commissioning dossiers if not furthermore filed.

83

Related Documents


More Documents from "indra2053"