Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 8. Project Control

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

Management of Medium-Size / Revamping Projects: course content I.

Introduction

II.

Preliminary Studies

III. Basic Engineering (or FEED) IV. EPC Contracting V.

Organization and Engineering

VI. Procurement VII. HSE, Quality and Risk Management VIII. Project Control (cost/schedule)

X.

Completion / Commissioning / Start-up / Closure

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

IX. Construction and Fabrication Management

2

Module 7 Contents 1. Project control

04 - 06

2. Scheduling and progress control

07 - 26

3. Cost estimating and control

27 - 55

ATTACHMENTS (slides 56 to 82) I. WBS and Schedule examples

III. Cost Reporting details/examples

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

II. More about Progress Control

3

Project Control Scope / Objectives 

Scope: • Engineering, Procurement and Construction stages of the project (including main Contractor, Subcontractors and Suppliers) • Mainly Cost and Schedule (for HSE and Quality: see previous chapter)



Schedule Control objectives: • Establish an optimized project schedule, accepted by all contributors • Determine constraints and critical path • Define method to measure progress, and apply it throughout execution



Cost Control objectives: • According to Owner cost structure, produce an optimized Cost Estimate • Make sure the budget is kept under control − Defining roles and responsibilities at all levels

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

− Using appropriate tools

4

Project Control Process

« FEEDBACK » PROCESSES PROJECT SCHEDULE SYSTEM (e.g CPM) PROJECT WORK BREAK DOWN (WBS) STRUCTURE: Activities Split

(Monthly) SCHEDULE STATUS LINE

Schedule Status

Trend Analysis PROJECT PROGRESS CONTROL SYSTEM (Activities weights USD, mhrs)

(Monthly) Planned CONTROL PROGRESS Progress ACTION CALCULATION

Actual Progress

Progress Analysis Progress Forecast

(Monthly) Initial CONTROL COST ACTION Budget CALCULATION Cost Analysis Cost Forecast

Expenses & Committments

© 2011 - IFP Training

PROJECT COST CONTROL SYSTEM (USD)

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

Baseline CONTROL Schedule ACTION

5

Project Control Communication / Reporting  

Frequent communication / reporting is critical for performance It enables the Project Manager to obtain • A clear picture of the Project progress vs budget and schedule • A timely identification of adverse trends / threats



It allows the Project Team: • To react and take immediate corrective actions, • If necessary, to design strategic recovery plans • To communicate with Owner and avoid last-minute surprises



Cost and Schedule can be both critical (but it depends on contract type)

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• To Owner (more often, Schedule) • To Engineering Contractor (more often, Cost)

6

Scheduling and progress control 



Contractor Scheduling • Same content as above



Progress Control • Progress measurement • Recovery Plan • Schedule re-baselining

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

Owner Scheduling • Work Breakdown Structure • Scheduling, Schedule levels • Critical path • Schedule revisions • Scheduling tool

7

Owner Scheduling Work Breakdown Structure 

The objective of the WBS is to provide an organised structure covering the whole content of the project and to include, at different levels of detail, the information necessary to monitor, control and correctly report all project activities



The project WBS takes consideration of: • Project configuration (size, geographical and technical nature) • Project management considerations (split of responsibilities, contracting strategy / packages, reporting requirements)



It is generally organized (for an EPC schedule), by: • A geographical divisions: Work Packages / Areas / units

See examples in Attachment I RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Work subdivisions (engineering disciplines, construction trades...)

8

Owner Scheduling Purpose 

Owner may have to prepare a Schedule for various reasons, e.g.: • A consolidated Project schedule (Project split into several EPC packages) • Preliminary Project schedule at pre-Project stage (Owner leader)

• Commercial reasons (e.g. external customer commitments) • Schedule with contingency, vs. the one discussed with EPC Contractor 

Level-0 Owner schedule will generally be presented as a Bart Chart



More detailed levels will also be developed, using PERT/CPM



Schedule presentation will be consistent with Owner WBS © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

9

Owner Scheduling Bart Chart example for 4 packages year

J F M A M J J A S O N D J F MA M J

JACKET & FLARE

4

Basic Engineering CFT - EPCI Detail Engineering Procurement Construction Installation

TOPSIDES Basic Engineering CFT - EPCI Detail Engineering Procurement Construction & Transportation Installation Hook up & commissionning

PIPELINES & CABLES

DRILLING & COMPLETION PRODUCTION

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

4 5 8 1 4 4 8 10 11

3 3 9

27

© 2011 - IFP Training

Engineering CFT Procurement & transport Installation

J AS O N D J F M A M J J A S O

10

Owner Scheduling Schedule types

Scheduling: a fundamental task of Project Management 

In Revamp projects, Schedule and Cost can be closely interrelated



Bar Chart: common way to prepare the first-pass schedule • Easy to prepare, to read (condensed format, 1 line per activity) • More difficult to see critical path and to evaluate impact of changes



PERT (Project Evaluation and Review Technique) ... then PDM • Determination of Critical Path • Sequencing logics is built into the schedule

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Then, bar charts can be produced from the network

11

Owner Scheduling Schedule levels 

Level 0 – Project Master Schedule: • Executive summary schedule used for reporting at Management level • Frozen at Project Sanction = Initial Baseline Schedule • Shows target dates, key milestones and main phases



Level 1 – Integrated Project Control Schedule: • Time-scale logic diagram • Decision steps, contracts sequence, work package summary activities, LLIs • Major milestones and overall project critical path



Level 2 and 3 – Contractor and sub-contractor Schedules

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Cover all the activities/tasks of the Contracts • All milestones necessary to control contractors’ physical progress • Procurement of main equipment and fabrication, construction, installation, commissioning, with the critical path

12

Owner Scheduling Links between activities and critical path 

Network is built with activities predecessors and followers &, linked by End-Start, Start-Start, or End-End link Critical Path Critical Path Critical Path Critical Path

Float Float



Critical path: path of activities with no float

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Provides shortest project duration • Goes through a series of activities from Project Start to Project Completion (e.g. studies and technical evaluation, delivery of some equipment, fabrication, site installation, hook-up, drilling)

13

Owner Scheduling Example: Gantt bar chart

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

14

Owner Scheduling Schedule revisions 



Baseline Schedule revisions performed on Project Manager decision in case of significant changes or delays Detailed assessment, based on Level 2 schedule, of all remaining activities (internal / contractors), duration & sequences including: • Actual physical progress and achieved milestones • Manhours progress and actual vs estimated productivity • Upcoming Change Orders (requested or potential) impacts on schedules • Performance of simulation schedules and “what-if” scenario as well as detailed schedules risks analysis performed by/with the Risks Assessment Manager.

Contractors may also need to revise their Baseline Schedules which may cause a revision of Company schedule

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



15

Owner Scheduling Common softwares 

Scheduling: common softwares for Medium & Small Projects: • MS-Project for small EPC projects, preliminary studies, FEED • Primavera for EPC phase (and FEED if necessary)



For presentation purposes: • Level 0 (on Excel, with information extracted from Primavera Level 1) • Level 1 or 2 only for specific critical activities



Progress reports : often prepared with Excel

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

16

Contractor Scheduling Differences 

Scheduling by EPC Contractor: more detailed than Owner • A detailed WBS/OBS is prepared to define areas and work phases for the project schedule & progress reporting • Scheduling hierarchy generally includes 4 main Levels for the concerned EPC contract, plus many sub-level schedules



Contractor responsibility on schedule compliance • Depends on the contract type (and therefore on Owner priorities) • May have financial consequences for him (or not)



Owner control on Contractor progress has to be applied © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

17

Contractor Scheduling EPC schedule hierarchy 

Level 0 schedule: Project Master Schedule: milestones dates and main work phases



Level 1: Overall Project Schedule with, for major WBS areas: • Engineering by discipline (major engg milestones: PIDs, Plot Plan, MTOs, Reviews...), • Procurement with LLIs and major equipment purchasing / delivery, • Construction by trade, pre-com/com, milestones dates (MC, RFC, RFSU…) • Critical path



Level 2 schedule: Areas Schedule: CPM network; all activities according to WBS / OBS • All engineering activities by discipline and deliverables category, • Procurement activities for all equipment & bulks requisitions, • Construction by trade or construction packages, pre-com / com,

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Detail critical path from CPM

18

Contractor Scheduling EPC schedule hierarchy 

Level 3: Detailed Schedules • Engineering deliverables (usually with engineering progress measurement system) • Procurement schedule (may be with procurement progress measurement system) • Site Level 3 CPM construction schedule, with Level 3 construction contractor subcontract schedules, in line with Level 2 schedule; used for progress reporting • Site CPM pre-commissioning / commissioning schedule detailed by Areas / Units / Systems / Tasks and used for progress reporting • For Revamped areas: Shut-down schedules by Job Cards

A 3 months look-ahead schedule may be used for reporting

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

19

Contractor Scheduling Key elements to consider 

Contractual milestones for achievements of the whole project or intermediary.



LLI (Long Lead Items), when applicable: items on the project critical path



Global project size and engineering, procurement and construction resources requirements versus their availability for the concerned project / site (progress rates) will translate into required manhours at peak and feasible progress rate



For Revamping projects: Planned shut-downs calendar times and durations



Standard « statistic » progress curves with % completion vs. project duration in % are available to provide a reference progress for each activity: • Engineering by discipline (process, equipment, civil, piping, E/I/A) • Procurement (main equipment, bulk material)

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Construction (For each trade: Civil, U/G piping, Piping pre-fabrication, equipment erection, piping erection, instrumentation, painting, insulation)

20

Contractor Scheduling Typical critical path 

Typical critical path for an E/P onshore project usually includes: • • • • •

Long Lead Items (including erection and installation) Process PIDs (approved by Owner for design) Main equipment purchases (including inspection/transportation) Piping isometrics, pre-fabrication and installation Control loop checks at the end of construction

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

21

Contractor Scheduling Schedule of Revamp projects Revamping Project Schedule is strongly influenced by:  Production objectives vs time: new production milestones after revamp  « Usual shut-downs » planned time and duration (need to minimize production outage time, including upstream and/or downstream facilities)  Work authorised during pre-shutdown phases in live facilities: if too limited, amount of work during S/D and construction may become: • More/very expensive • Higher HSE/Reliability risk • Even unrealistic  delays and/or major Quality concerns 

Consider using available Owner supervision & commissioning staff

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Carefully review schedule constraints with Owner during FEED, to avoid subsequent trouble and change orders

22

Progress control Purpose 

Compare actual progress vs schedule. Several ways: • • • • •

Milestones Overall physical progress Physical progress of the Critical Path Expected completion date vs plan Manhours progress vs detailed schedule



Analyze trends to decide if corrective actions are necessary



Depending on contract type, Owner validation may be required © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

23

Progress control Progress reporting 

Periodic Progress Reports: a key Project Management tool



Address progress, but also all key events, problem areas and higher level problem areas (« areas of concern »)



Prepared: • • • •

Daily at site (construction / pre-com / com). Weekly for Head Office activities and for construction Monthly Issued before periodic Owner / Main Contractor review meetings

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

24

Progress control Progress reporting COMPANY PROJECT MANAGEMENT TEAM Prepares Daily report (constr) Weekly report Monthly reprt Feedback Incident Close-out

MONTHLY MEETING WEEKLY MEETING

CONTRACTOR PROJECT MANAGEMENT TEAM

CONTRACTORS MONTHLY MEETING WEEKLY MEETING DAILY MEETING (Constr.)

SUB CONTRACTORS

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

Prepares Daily report (constr) Weekly report Monthly report Alerts Feedback Incident Close-out

Reviews, Responds, Consolidates Oper. Centers & Site Reports Alerts Feedback Incident Close-out

MONTHLY MEETING

Monitors, Monthly

CONTRACTOR MANAGEMENT Monitors, Recommends Monthly Incident Close-out

© 2011 - IFP Training

Prepares Daily report (constr) Weekly report Monthly reprt Alerts Feedback Incident Close-out

JV STEERING COMMITTEE

25

Progress control Progress reporting Typical CONTENT



Major events, highlights



Executive Summary



HSE statistics, near misses register



HSE performance





Engineering

Progress S curves, tabulations: planned, actual, forecast for Project, Work Packages, global E, Disciplines, P, global C, C by areas/ units, C by trades



Procurement



Milestones status



Subcontracting



COI/COR register



Construction



Invoices register



Pre-com / Com



Cash flow actual & predictions



Project Controls



Procurement materials status reports



Quality



NCR register



Areas of Concern



Documents register



Level 1 Project Schedule with progress status; Trend analysis; recovery plan



Manpower histograms planned & actual

problem

areas,

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

achievements,

26

Progress control Progress measurement 

Split project activities according to structure close to the WBS



Define weights to each line, using adequate units (€, manhours…)



For each Work package, aggregate these tasks by Levels : • • • • •



1: Work-Package or sub-project 2: Categories: home office services, procurement, construction… 3: Sub-categories: engineering discipline, requisition, construction trade 4: Tasks: engineering deliverables, equipment, construction items 5: Elementary steps: drawings, fabrication, construction works

During execution: • Measure progress achieved for each elementary step • Then, aggregate to the different Levels and compute overall progress

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

See examples/illustrations in Attachment II

27

Progress control Progress curves

TYPICAL PROGRESS CURVES 100%

100% 99% 97% 95% 92% 90% 87% 84%85% 82% 79% 76% 73% 70% 67%

90%

80% 70%

61% 56% 51%

60% 50%

46%

40%

40% 35% 30%

30% 20% 10% 0% 0% 1%

0% 1

2

3

4

2%

5

6% 3% 4%

6

7

8

7%

9%

25% 20% 17% 14% 11%

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

Engineering

Procurement

Fabrication

Construction

Commissioning

Total

© 2011 - IFP Training

Months

28

Progress control Progress curves

Engineering « S » progress curves are prepared from Level 3 schedule (typically during the first 3 months of the contract)



More detailed “S” curves are prepared during Execution: • Detailed construction / fabrication curve • Field erection curve • Installation / commissioning curve



First « S » progress curves and histograms can be prepared from Level 2 schedule and manhours estimates; they allow to check that construction scheme is realistic for construction contractors



Until the Project EPC schedule is issued, a 3-month look-ahead schedule is prepared to anticipate short-term schedule and resource concerns

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



29

Progress control Typical causes for EPC contractors delays 

Insufficient manpower resources (quantity and/or quality)



Supplier or Subcontractors (careful on sub-sub-contracting !)



Strikes, disturbances related to local environment



Underestimates (manhours, bulk quantities)



Equipment Quality unacceptable non-conformances



Late information, comments or reviews from Owner This list is incomplete. Other ideas ?... © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

30

Cost Estimating and Control • Cost estimating • Cost reporting and control • Change Management © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

31

Cost Estimating and control Scope and objectives  

Scope: Project CAPEX (OPEX is not in the scope) Objectives: • Estimate the project CAPEX and propose the overall budget • Make sure that this budget is acceptable to all contributors − Sufficient to assure Project HSE/Quality performance − Generating acceptable profit for each stakeholder » Owner » EPC contractor » Suppliers and Subcontractors

− Consistent with the cost and schedule constraints − Allowing adequate risk management

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Organize the Cost Reporting/Control process (involving Owner) • Define the Change Management process (involving Owner)

32

Cost Estimating Budget 

Any Project has a controlled and approved Budget



The Budget may be adjusted (Revised Budget) during the Project Life:

• Budget transfer from other projects • Scope deletions or additions, approved by Owner 

Structurally, the budget is expected to increase as Project develops



At the end of the Project: • Cost analysis will establish the “Final cost” − After Mechanical Completion and Handover − Once claims are settled and invoices paid

• Comparison with Revised Budget allows to draw feedback lessons RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• The final Cost Control report is issued

33

Cost estimating Methodology

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

34

Cost estimating Structure

Main Equipment Bulk Fabrication/Construction(onshore/offshore) Transportation Temporary Facilities Construction camps Engineering Services Management & Supervision Surveys Insurance Commissioning

Direct Costs

+ Indirect Costs

+ General Expenses

+ Associated Expenses

+ Contingencies

Direct Costs + Indirect Costs = Technical Costs

Facilities Cost Estimate

Fabrication / Construction cost are the highest costs and the most difficult to estimate, in particular for works in revamped process units and brown field; they are very site dependent (productivity) RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

=

35

Cost estimating Preliminary Estimate: a Challenge 

CAPEX estimate usual desired accuracy is +/- 30% for « new » or « expanded » parts of projects in existing facilities, which may be relatively easy if the Plant is recent and cost data base available or difficult depending on: • Project complexity and location • Onshore or Offshore projects • Concerned facilities • Modifications to facilities (Expansion, Debottleneck, Upgrade, Revamp)



The CAPEX estimating method will depend on: • Cost data base (Owner and/or Contractor) for works at that location • Nature of facilities (onshore or offshore, subsea or surface, new or revamped process units, interconnecting with work in brown field…),

The CAPEX estimate should be prepared with a memorandum underlying assumptions, estimating methodology, uncertainties and risks

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



36

Cost estimating Preliminary Estimate: a Challenge 

Estimating methods are global as project details such as P&IDs are not prepared; the estimating methodology will combine available cost data base and estimating tool box.



Estimators use cost data breakdowns, unit costs, etc. from similar recent project units at the location, or at similar (in terms of cost) location, with corrections for location (importance of construction cost), escalation, and other foreseen different project conditions. (Often the estimators will use units information from several projects).



Many « factors » are used for so called « factored estimates »: • Scaling factor: P1 / Po = (C1 / Co)0.65 • Factored estimate from equipment cost: P installed= K x P equipment K may range from 2 to 6 depending on equipment type For revamped areas an other K1 factor is to be applied on top • A cost factor can be used for transportation (onshore projects)

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Global factor on top of Direct Costs: Total cost = K x Project Direct Cost

37

Cost estimating Preliminary Estimate: a Challenge



Cost information is gathered from all possible sources at the time, e.g:

• Major / special equipment or packages (glycol treatment, water treatment, utilities and power packages, etc.): prices from Vendors « budget » quotes. • Interconnecting preliminary quantities estimated by engineering from preliminary MTOs & unit costs used from previous project at the facilities, for bulks cost & for construction cost; quotations from Vendors for large pipe / pipelines • Engineering, construction supervision manhours may be estimated by ratios.

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Contingencies or CRP (Contingency, Risks and Profit) factor, added on top of estimate

38

Cost estimating CAPEX estimate during FEED 

CAPEX estimate prepared according WBS/OBS; desired accuracy +/- 15%



Estimate is Quantities x Unit Costs



Construction cost is all-in construction mhrs rates x construction mhrs



Construction cost: the most important cost item, the most difficult to estimate



CRP (Contingency, Risks and Profit factor) is added on top of the cost estimate



CAPEX estimate prepared with a memorandum underlying assumptions, estimating methodology, uncertainties and risks.



Estimating methodology principles are presented on next slides © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

39

Cost estimating CAPEX estimate during FEED

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

40

Cost estimating CAPEX estimate during FEED

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

41

Cost Control process Owner perspective 

Owner cost control process and involvement in tracking cost components depends on the type of EPC contract



If a contract is on Reimbursable basis, Owner will have access to all cost elements and is responsible for the complete Project cost



If a contract is on a Lump Sum basis, Owner will have access only to the cost items specified in the contract



Owner will have access to the cost estimate to support change orders, approve them, and include them to Cost Control process © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

42

Cost Reporting and Control Forecast 

Purpose : determine the Forecast to Complete



Cost Forecast is updated on a regular basis (typically, monthly)



Cost Forecast may anticipate on non-finalized commitments



Cost Forecast requires a good knowledge of technical matters



Cost Forecast may introduce some budget transfer



Cost Forecast includes proper management of Contingencies • Advisable not to consume them during the early stages • The Project Manager has ultimate authority

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• Corporate rules (Owner and/or Contractor) may exist

43

Cost Reporting and Control Organisation principles

Cost control organisation includes mainly: Cost Control Manager, assisted by Cost Controllers depending on Project size, responsible for global project cost control and reporting to operationally to the Project Control Manager and functionnaly to the Contractor Management (in case of a JV, will report to JV Project Manager on one hand and, on the other hand, to Partner Management within its own organisation, issues being then adressed if necessary by the JV Steering Committee)



Site Cost Control Manager responsible for cost control at the site and reporting operationnally to the Site Manager but functionally to the Cost Control Manager



Cost Estimators to estimate project cost changes and reporting to the Project Control Manager

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



45

Cost Reporting and Control Cost Controller duties (1/2) Mainly coordinates with: Engineering and scheduling / progress control organisations to control engineering manhours cost expenditure, planned mobilisation and trends from productivity and personnel mhrs rates, and to control bulks quantities trends considering MTOs vs their engineering documents basis



Procurement to control Vendors offers versus budget (advise budget target before negotiations, check and approve CBTs and Vendor price), and track P.Os change trends



Fabrication / construction contracts management to control cost and trends versus budget (before transfer of construction contracts administration the site)



Site cost control to control site costs and trends



Project Management for allocation and use of technical cost contingencies or global project risks provisions Prepares costs expenses reports, forecast and monthly cost reports; also prepares change orders

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



46

Cost Reporting and Control Cost Controller duties (2/2) Mainly Coordinates with: Fabrication / Construction / Pre-com / com Management to control site supervision cost (mobilised cost, planned mobilisation, daily rates costs...)



Site Contracts Administrator(s) / quantities surveyors and Scheduling / Progress Control Manager to control current construction cost, establish forecasts from anticipated quantities variations, productivity, and additional work orders



Site procurement for local purchases



Site Administration Manager for site running costs control (accommodation / camps, TCF...)



Prepares back-charges to Vendors and Construction Contractors as applicable, insurance claims in case of damages during transport or at site



Prepares site costs expenses reports, forecast and monthly cost reports; also prepares change orders

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



47

Cost Reporting and Control Periodic actions 





RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Day-to-day: • Review work progress and consistency with contract terms • Inform Management of any non-budgeted items • Review all invoices received and consistency with contract terms Typically on a monthly basis: • Calculate the escalation formulae and price revisions, if any • Manage the various provisions • Review the estimate to complete and the final forecast Less frequently (quarterly, annually, or ad hoc): • Formal reporting to EPC Management, Owner and Partners • Regulatory reporting if applicable (e.g. tax) • Propose budget revisions

48

Cost Reporting and Control Keys of effective cost control 

Timely and serious estimate of Engineering Manhours



Bulk Quantities estimate based on complete detail engineering



Check of Suppliers and Fabrication/Construction contracts: • Estimates based on up-to-date verified info • Actual costs timely compared to estimate, and challenged • Rigorous Procurement procedures, no by-pass

Schedule changes: careful about cost consequences



Rigourous Change Management



Accurate and timely Reporting / Forecasting to Management



Timely followup of cost control actions decided by the team

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



49

Management of change Process

Management of Change Covers all changes to contract Engineering Deviation Requests • Cover deviations to contractual reference standards or already Approved Design Specifications • Written Procedure • Deviation Requests Register • Clear Owner approval authority

Change Order Procedure • Covers Additions, Modifications and Deletions to Project scope, with impact on Project cost, schedule, process performance • Procedure includes: − Change Process − Change Orders Log − Approvals

• Change Requests Register © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

50

Management of change Deviation requests/engineering queries 

Clarify or ask a deviation to a contractual document, for the purpose of developing the detail engineering and procurement requisitions

Usually due to: • Conflicting requirements in different documents • Proposal of an engineering improvement • Required materials not consistent with local availability 

Ask a deviation to already approved requisition documents

Usually due to: Proposal of a supply improvement Availability of raw materials different from requirements Vendors fabrication or test standards different from requirements Standard packages or skids

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

• • • •

51

Management of change Change order procedure

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

A “Change Order” is not an anomaly • When cost variations are not due to Contractor and potentially give rise to a Change Order: Contractor notifies Company and prepares a Change Order Request (COR) with an estimate and formal request to be usually submitted within 2 weeks maximum to Company. • Company may also need to change the scope, or to exert Options provided under the contract, or for any reason to ask Contractor to change its work thru a Change Order Instruction (COI). Company then notifies Contractor with an estimate to be usually submitted within 2 weeks maximum to Company. • Change Orders are monitored by the Project Cost Management team and recorded as soon as they are identified on a Change Order Register. • Change Orders estimates are evaluated by the Contractor (using contract unit costs as available), and checked by Company Cost Management team. • Change Orders need to be formalized and agreed by all Parties and will therefore be transferred to Project budgets (Company and Contractor) only after Approval by Company.

52

Management of change Cost trends caused by Owner

Project definition unclear or incomplete



Scope changes during execution



Delayed access to construction areas



Missing elements or information



Wrong assumptions on market costs



Unclear interfaces between contractors



Conflicts with EPC Contractor, or Suppliers, or Subcontractors



Insufficient quality of Project Management Team



Delays in achieving Owner tasks

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



53

Management of change Cost trends caused by Environment 

Unplanned inflation rate or exchange rate changes



Weather catastrophy (cyclones, flooding, earthquakes)



Political trouble (strikes, wars, unplanned regulatory changes)



Delays to obtain working visas



Unexpectedly low productivity due to bad weather



Unforeseen difficulties (soils or sea bed conditions)

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

54

Management of change Cost trends caused by EPC Contractor 

Initial Price too low



Insufficient qualification of Project Management Team



Inability to forecast on time



Sub-contractors lack of performance



Estimating errors (incomplete/incorrect technical info)



Insufficient provisions or contingency



Missing cost elements



Wrong assumptions on supplier/subcontractor markets © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

55

Project control Key points to keep in mind 

Owner has a critical role in controlling EPC Contractor performance



This role depends on the contract type but is always to be assured



Scheduling: • May be quite critical on Revamping projects (shutdown windows) • Smaller projects need simpler tools • Critical path should be clearly identified and optimized



Cost estimating: • Up-to-date cost databases are a key to effective estimating • Accuracy of Cost Control estimate should be around 10% • Estimate used for approval (FEED stage) should be based on quantities

Cost and Schedule control: • Monitoring methods should be clearly defined in the EPC contract • For Revamping projects, may be closely inter-related

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



56

ATTACHMENTS I.

WBS and Schedule examples

II.

More about progress control

III. Cost reporting details/examples

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

57

ATTACHMENT I WBS and Schedule examples

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

58

ATTACHMENT II More about Progress Control

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

65

Principle split

OVERALL PROJECT

WORK PACKAGE 1

WORK PACKAGE 2

MANUFACTURING DELIVERY

CONSTRUCTION AND PRECOMMISSIONING

HOME OFFICE SERVICES

MANUFACTURING DELIVERY

CONSTRUCTION AND PRECOMMISSIONING

15%

35%

50%

15%

35%

50%

% according to USD values RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

HOME OFFICE SERVICES

66

Principle split – Weights sample onshore

© 2011 - IFP Training

% according to mhrs for services and USD for procurement RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

67

Progress measurement: Weighting sample offshore FPSO

28,6% TOPSIDES Engineering Procurement Construction Integration Towing FPSO & Flotel Tie-in precomm and Comm HULL & L Q

10,6% 34,2% 16,8% 3,3% 2,1% 1,8% 31,2%

SPS

14,3% Engineering Procurement Manufacturing Systems Testing Transport

4,0% 22,1% 67,3% 3,3% 3,3%

UFR

24,5% 4,5% 36,2% 14,5% 27,8% 17,0%

DRILLING

32,7% Drilling Rig Rig Contract Services

42,8% 57,2%

TOTAL RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Engineering Procurement Construction Offshore Installation OLT

100,0% 68

Recovery plan example: loss of mobilisation at year end and drifting

RECOVERY PLAN: INCREASE MOBILISATION TO INCREASE PROGRESS ACTUAL PROGRESS ON TIME UNTIL END DEC. BUT DRIFTING

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

71

Project Schedule sample: Gas Plant 2 Trains extension and upgrade – S/Ds Planning

Four S/Ds at actual EPC time start

One major S/D initially

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

72

Progress curves: Schedule Baseline Revisions

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

73

JC preparation progress curve

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

Preparation of JCs may take several months: procedure for preparation, progress control to be implemented

74

Fabrication scheduling

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

75

Scheduling transportation to site Transportation to site of the main components is not very difficult by itself, but the coordination of this activity can be a real challenge



The speed of the spread(s) transporting the main components is directly calculated from the distance and the marine spread speed + some provisions for bad weather, adverse wind, …



The capacity of the transportation barge or vessel must be assessed carefully: transporting 2000 tons, 5000 tons or even 30000 tons is a case by case study

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training



76

Scheduling offshore installation Initial scheduling of offshore installation requires: 

Detailed analysis of the scope: number and main characteristics of all modules / decks / jackets / pipelines / floating storage…



Evaluation of the marine construction equipment required: • • • • •

Derrick barge – crane capacity Pipe Laying Barge – stinger – max pipe size – type of welding Offshore tie-in means: ROV… Trenching, shore approach equipment Drilling rigs type…

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

The schedule will be reviewed after contractors selection

77

Scheduling offshore installation

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

78

Scheduling hook-up



Hook-up time is highly dependant upon the yard fabrication and its level of completion



It is fundamental to reduce as much as possible the hook-up work: hook-up is very costly and always critical



No hook-up without accommodation



No hook-up without a good logistic and supporting equipment © 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

79

ATTACHMENT III Cost Reporting details/examples

© 2011 - IFP Training

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

80

Company Cost Report Format Principles

Project Level* (1) (2) Approve Scope Description d Change Budget

(3) Budget Transfer

(4) Current Budget (1+2+3)

(5) Commit

(6) (7) Estimate Forecast To (5+6) Complete

(8) Variance (+/-) (4-7)

(9) (10) Expend. Approved Incurred Invoices

AFE X Y Z

100 50 90

0 0 0

0 10 - 10

100 60 80

90 60 80

12 0 -5

102 60 75

2 0 -5

70 60 73

65 60 65

Sub-total

240

0

0

240

230

7

237

-3

203

190

24

0

0

24

0

22

22

-2

0

0

264

0

0

264

230

29

259

-5

203

190

Provisions Contingen cy Total

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2011 - IFP Training

* Level 0 = Project 1 = Phase 2 = Major Work Split 3 = Commitment 4 = Work Package

82

Cost monitoring example TOTAL E&P XXXX DATE: OCT 2003

PROJECT: ANGELA PAPYRUS LEVEL 0 (1)

CODE TOTAL E&P XXXX DATE: OCT 2004

DESCRIPTION

APPROVED BUDGET

(2)

200

(4)

BUDGET TRANSFER

(5)

CURRENT BUDGET (1+2+3)

(6)

COMMITMENT

(7)

ESTIMATE to COMPLETE

PROJECT: ANGELA PAPYRUS 0 0 13350 13350 0 LEVEL 1 WELLHEAD PF & CONNECTION 0 0 54550 51550 3000

Initial Studies 13350 Wellhead Connect. 54550 (1) (2) 300 Production Pltf 137320 400 Quarter Pltf 37070 APPROVED SCOPE CODE DESCRIPTION 500 FPSO 42430 CHANGE TOTAL E&P XXXX600 Buoy & SealinesBUDGET 12900 DATE: 2004 210OCT Gen. Mngt700 & Serv 2200 0 Management 5600 100

(3)

SCOPE CHANGE

ALL IN k US$

0

(3)

(4)

-10000

0 BUDGET 0 TRANSFER

127320

CURRENT -500 36570

(5)

118380

(6)

0

0

22005600

2200 0 4523

(9)

13350 127320 36570 FORECAST 45130 (5+6) 12900

(10)

Expenditure ALL IN k US$ Incurred

Approved Invoices

0

54550

(7)

8940

34500 ESTIMATE 2070to 2700BUDGET 45130 COMMITMENT 43170 1960 COMPLETE (1+2+3) 0 PROJECT: 0 12900 0 12900 ANGELA PAPYRUS 0

(8)

Variance FORECAST (+/ -) (7(5+6) 4)

0

(8)

0

30

26

(9)

(10)

12760

10000

Variance0 6383 Expenditure (+/ -) 0 18823 Incurred (7-4) 0 ALL IN k US$45

5073 Approved 16450 Invoices 42

5600 0

56002200

0 0

350 15

150

300 8940 0 400 100

5400 127320 14000 3350 1500

0 00 0 0

0 14000 12760 0 240

800 3650 10200300

0 0 0 0

LEVEL 1 Production Platform Engineering 4400 323 0 4723 200 4723 0 0 0 Sub-Total 0 (3) 295420 34470 295420 38056 31606 (1) 8500 303220 (2)645 (4) 9145 (5) 260950 (6) (7) 9145 (8) 0 0 (9) (10) 0 230 Mal & Eqpt supply 0-7800 9045 100 0 240 Onshore fab 22500 1682 0 24182 23582 600 24182 0 0 0 CURRENT Variance 800 Provisions (rate) 2100 0 -10 2090 0 2090 2090 0 10 10 APPROVED SCOPE BUDGET0 ESTIMATE to FORECAST Expenditures Approved 250 Transportation 3550 0 3550 3450 100 3550 0 0 0 900 Contingency 12430 0 0 12430 0 12430 12430 0 0 0 CODE DESCRIPTION BUDGET COMMITMENT (+/ -) 260 Offshore Works 16500 0 -500 16000 15800 200 16000 0 0 0 BUDGET CHANGE TRANSFER COMPLETE (5+6) Incurred Invoices TOTAL E&P XXXX (1+2+3) (7-4) ALL IN k US$ PROJECT: ANGELA PAPYRUS 270 Hook-up Wks 6200 0 0 6200 6000 200 6200 0 0 0 DATE: OCT 2004 280 Long Commissioning sup 3200 317750 0 0 -1800 1400 1000 400 0 1400 0 0 310 lead Items 28630 -4200 -7810 1 24430 24430 24430 **** TOTAL 0 309940 260950 48990 309940 0 00 38066 4800 316162400 LEVEL Quarter Platform 290 Gen. Spare parts 950 0 0 -350 0 600 550 50 600 00 0 240 0240 320 Mngt & Serv 2640 2640 2400 240 2640 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 330 Engineering 4680 0 -700 3980 3600 380 3980 0 720 360 CURRENT Variance 340 Mal & Eqpt supply 45840 0 -5100 40740 40300 40740 0 Expenditure4500Approved4500 APPROVED SCOPE BUDGET ESTIMATE440 to FORECAST CODE DESCRIPTION BUDGET COMMITMENT (+/ -) 350 16480 16480 16150 330 16480 0 BUDGET CHANGE TRANSFER COMPLETE (5+6)68000 Incurred3502500 Invoices 2500 2*** Onshore TOTAL fab 68000 2650 0 -2650 0 68000 66150 1850 0 (1+2+3) (7-4)ALL0IN k US$ TOTAL E&P XXXX 360 Transportation 4500 0 0 4500 4500 0 4500 0 0 0 PROJECT: ANGELA PAPYRUS DATE: OCT 2004 Long Works lead Items 2560 2560 2560 2560 00 2560 1250 370 410 Offshore 18000 0 0 00 18000 14500 35000 18000 0 0 LEVEL 18500 FPSO & BUOY Gen. Mngt 1200 1200 1200 1200 00 240 240 380 420 Hook-up Wks & Serv 8500 0 0 00 6200 23000 8500 0 0 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Engineering sup 2150 2150 2050 100 2150 00 410 410 380 430 Commissioning 4850 0 0 00 4850 3800 1050 4850 0 0 CURRENT Malparts & Eqpt supply 12720 -250 12470 11890 12470 00 2600 2600 390 440 Spare 3200 0 0 0 3200 2500 ESTIMATE 580 700 FORECAST 3200 Variance 0 0 APPROVED SCOPE BUDGET to Expenditure Approved CODE BUDGET COMMITMENT (+/ -) 450 Onshore DESCRIPTION fab 6140 0 0 6140 5725 415 6140 0 573 573 BUDGET CHANGE TRANSFER COMPLETE (5+6) Incurred Invoices (1+2+3) (7-4) 460 Transportation 2200 0 0 2200 2125 75 2200 0 0 0 220

Offshore Works 3*** 470 TOTAL 510 Purchase Hull 480520 Hook-up Wks& Serv Gen. Mngt

Onshore fab 560 Towing 4*** 570 TOTAL Offshore Works 580 Hook-up Wks 580 Commissioning sup 590 Spare parts 550

5***

TOTAL

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

0 00 00

0 -10000 1500 -250 0

5400 127320 14000 3350 1500

5100 118380 14000 2950 1400

800 3650 300 10200

00 00

00 00

800 3650 300 10200

600 3500 300 9900

200 150 300 0

6500

0

0

6500

5900

600

6500

0

1800 37070 2500

0 00

0 -500 0

1800 36570 2500

1800 34500 2200

0 2070 300

1800 36570 2500

0

2280

0

1200

3480

3100

380

3480

0

0

0

1100

0

0

1100

970

130

1100

0

0

0

400

0

0

400

400

400

0

0

0

42430

0

2700

45130

43170

0

1960

45130

0 0

0

240

0 10000 0

14000

410

0

410

0

3600

0

1800

0

573 0 6383 0

18823

0 0 5073 0

© 2011 - IFP Training

480530 Commissioning Engineering sup 490540 Spare parts Mal & Eqpt supply

5400 137320 12500 3600 1500

16450

83