09_construction & Fabrication Management.pptx

  • Uploaded by: JJ Welding
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 09_construction & Fabrication Management.pptx as PDF for free.

More details

  • Words: 3,957
  • Pages: 52
Loading documents preview...
Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 9. Construction and Fabrication Management

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

Management of Medium-Size / Revamping Projects: course content I.

Introduction

II.

Preliminary Studies

III. Basic Engineering (or FEED)

IV. EPC Contracting V.

Organization and Engineering

VI. Procurement VII. HSE, Quality and Risk Management IX. Construction and Fabrication Management X.

Completion / Commissioning / Start-up / Closure

RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013

© 2013 - IFP Training

VIII. Project Control (cost/schedule)

1

Construction Contracting Issues

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

2

Scope and objectives



Scope • Prefabrication of equipment and transportation to project site • Site preparation including civil works • Erection of main equipment, installation and connection



Objectives

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Assure prefabrication of equipment and transportation to the site • Confirm and implement the site construction strategy and organization • Ensure timely mobilization and control of field subcontractors • Achieve the construction challenges (Safety, Quality, Schedule, Cost) • Adequate communication with Owner, to prepare smooth handover

3

Construction challenges for Medium-Size and Revamp Projects 

Availability of construction manpower: a medium-size project may still require up to 2000 workers at peak (typical in Middle East), with more than 30 different nationalities



Remote locations (South and North America, Australia, Deserts, Africa) with limited infrastructure and serious access difficulties



Local requirements often call for maximum use of local construction workforce (capability and productivity concerns)



Construction schedule pressure due to market pressure, weather issues, and shutdown durations for revamping projects © 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

4

Fabrication contractors



Generally Fabrication / Integration Contractors are Yards / Shipyards



Fabrication cost (key issue) is continuously changing the landscape



Effective fabrication workshop are located sometime in Oil & Gas production areas • • • •

America: Mexico Gulf, Brazil, Venezuela Middle East: Arabic Gulf, Caspian Sea, Northern Russia Far East:, Korea, Singapore, Indonesia, Malaysia, Southern Thailand Europe: Northern England, Norway, Spain

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

… but this is sometimes very far from Project construction sites

5

Construction contractors



Construction Contractors are either locally established Companies or Companies operating in some areas, or relatively worldwide



In many countries, local companies are generally specialized by trades (Civil works, Structural Steel, Mechanical, E/I)



General Contractors exist in many locations



Direct Hiring for construction by EPC Contractor is a possibility



Experienced Construction personnel should be selected for

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Construction field supervision (extensive training may be required) • Revamping works during plant operation and shut-down

6

Unit-rate contracts



“Price schedule” or “unit rates” contracts: • extensively used for onshore Lump Sum projects to meet Project Schedule • Direct cost: unit price for each item of a detailed price schedule • Plus lump sum for indirect costs • The subcontractor guarantees a progress rate and completion dates



Flexibility advantage as:

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Quantities cannot be known exactly until detail engineering is completed • The subcontractor can progress as long as work front is available, even if there are some delays for some activities of the construction schedule

7

Unit-rate contracts



The contract structure is prepared with a Master Subcontracting Package (MSP) and specifics are added for each contract type; e.g., typically: • Site preparation • Piling, Civil works, U/G piping, roads, Buildings (independent or together) • Structures fabrication • Piping pre-fabrication • Mechanical erection (equipment, piping, structures)

• Electrical works • Insulation, Painting (independent or together) RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Instrumentation works…

8

Transportation

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

9

Transportation



Minimize transportation cost / erection cost



Balance large lifting requirement cost versus advantage of direct delivery / erection onto foundations



Delivery of abnormal loads (heavy, large): • On-land Transportation studies to site foundation • Rigging study for erection

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

10

Heavy lifts & Transport on barge

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

320 tons Coke Drums

11

Heavy lifts - Rigging study

© 2013 - IFP Training

840 tons column RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

12

Modular approach



Modularization may save considerable time and/or cost for: • Projects in areas where construction manpower is limited and/or expensive



And for: • Revamping projects with modules which will be installed during shut-downs, instead of erecting corresponding facilities



Modularization may include all kinds of facilities:

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• PAU: Process Assembled Units • PAR: Process Assembled Racks • Main constraints are due to transportation limits Discuss: what is the difference between modules and skids?

13

Modularized sulfur recovery unit

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

14

Module construction

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

15

Module transportation



Road transportation on low-bed trailers possible for smaller modules



Sea transport of modules requires



A MOF facility at or near site to berth barges or vessels for unloading: • RO/RO (Roll On – Roll Off) using SPMTs (Self Propelled Modular Transporters) • LO-LO (Lift On – Lift Off) using Heavy Lift Vessel cranes • Shore cranes



And a suitable hauling road from MOF to site.

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Sea Transportation Vessels and SPMTs Transporters are in limited in numbers and should be hired well in advance (pre-commit before project sanction)

16

Module transportation + lifting

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

19

Site Construction Execution

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

20

Subcontractor selection process



Objective: select construction contractors who will ensure cost/schedule effective fabrication and construction



Surveys of potential contractors / pre-qualification criteria: • Motivated by the Project • Qualified for the works to be performed / similar successful experience • Qualified manpower resources available in the projected time window



Preparation of a list of acceptable Subcontractors



Competitive bidding (formal tendering procedure) leading to:

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Acceptance of contract conditions • Good understanding of the scope • Most competitive rates

21

Strategic highlights



Construction / fabrication activities split by work packages, according to WBS: • By Process Units • Then, by discipline



Splitting allows to group several packages after analyzing bid responses



Splitting or not splitting is a trade-off between: • Securing enough contractor resources to provide reliable execution • Limiting the number of interfaces and of different contractors

Too many interfaces will make the project difficult to manage by Owner



Medium-size revamp projects, if too small, may not be split

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



22

Construction challenges for Revamping Projects 

Construction must overcome general challenges, as discussed before: • • • •



Availability of construction resources, particularly manpower Remote or semi-remote locations Local Content requirements Schedule pressure from Project schedules shortening

But, revamping projects include works in live facilities (“pre-shutdown” works) and during facilities shutdowns (S/Ds); to be executed with specific methods:

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

1. To protect safety of Site Operations & Project Construction personnel and integrity of the facilities with stringent work procedures: Site HSE Management System, PTW (Permit To Work) with detail Method Statements 2. To minimize facilities shutdown time due to project execution: prefabrication, modularization; use of planned « usual » S/D and of « given » S/D; controlled pre-shutdown cold works and « hot work » in live facilities 3. To tightly control execution time during S/Ds: use of a detailed planning & control system (“Job Cards”); to mobilize dedicated S/D construction teams (Project, Plant)

23

Skids: special concerns



Skids are often small (“EPC”) units; concerns for alignment with other facilities design, procurement & construction include: • Design capability of Vendor e.g. for instrumentation, electrical design to be carefully checked and controlled • Equipment standardization: consider free issue of components (instrumentation, minor piping parts, pump seals) • Process Control integration (PLCs: Programmable Controllers…): standardization, design, FATs, SATs

Logic

• Acceptance of “Vendors standards” in particular for utilities skids such as N2 production, instrument air, cooling systems © 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

24

Execution Plan Highlights Occupational Health & Safety Plan, Security Plan



Organization, Management plan, Subcontractor administration



Accommodation, site offices, Accesses & Traffic, various Logistics



Construction methods, heavy lifts, prefabrication



Materials Management



Change Management



Field Engineering and Supervision, Schedule and Quality Control



Anticipation of Commissioning and Handover

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



25

Key Construction Management procedures



Interfaces Management



Roles and responsibilities between Subcontractors, and with Owner



Decision Process (changes, financial matters, safety issues)



Project quality documentation circulation, approval and follow-up



Communication presentations)



Deviation Requests authorities



Non-conformance procedure, near-misses, incident investigation



Change Order Procedure, Owner and Contractor rights, traceability

to

meetings,

construction

reporting, standards,

staff

approval

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

(periodic

28

Specific safety risks for projects in existing facilities

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

29

Construction HSE Prevention Plan components Subcontractors Commitment



Professional Competence (qualification and training of workers)



Safety Communication, Safety Information, Safety Meetings



Work Preparation and Organization, Risk Evaluation, Job Safety Analysis



Accidents / Near Miss Incidents Investigation and Reporting



Report and immediate correction of Unsafe Conditions and Behaviours



Field and System Audits, Continuous Improvement System



Permit To Work system for work in existing facilities



Safety awareness at site and at facilities used to work at site

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

Selection

Criteria,

Subcontractor

Management

© 2013 - IFP Training



30

Work permit types



Cold work permit



Hot work permit category 1 (involves positive source of ignition) • Naked flame, electric welding, grinding, hot air gun, electrical induction pre-heating / stress relieving



Hot work permit category 2 (involves potential source of ignition) • Dry grit shot blasting, cutting, chipping or wire brushing using air / hydraulic tools, use of electrical drills, use of equipment with portable diesel engines, use of non-certified electrical equipment, opening or working in live electrical junction boxes, use of radioactive sources, use of powered vehicles / cranes...

Enclosed space entry permit



Excavation permit



Radiography permit



Electrical isolation permit

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



31

Construction schedule drivers



Availability of up-to-date Engineering documents



Equipment and bulk timely delivery



Consistent progress by trades, consistent with planned progress



Workfront availability



Recovery measures in case of schedule slippage



Completion by systems, as soon as works complete © 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

32

Construction schedule: taking advantage of shutdowns



Existing facilities are subject to maintenance S/D from time to time, to be considered when planning a project which requires stoppage of units or other facilities



Planned Shut-Downs (shown in the Plant; several years sliding operation calendar):



Unplanned Shut-Downs occur from time to time due to unexpected reasons within the existing facilities concerned by the project or upstream an provide possibility to perform “opportunity tie-ins”.

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Major Plant turn-around S/D for general inspection, repairs… (Typ. every 3 years; typ. duration several weeks) • Major unit turnaround S/D (if several trains or spared units or unit by-pass possible) • S/D for major overhaul of large unique equipment • Other intermediate shut-downs (e.g.: “hot path” inspection of GTs: typical every 8,000 oper. hrs; typ. duration 2 days) • S/D due to planned shut-downs of upstream facilities providing feedstock to the Plant (outage) • S/D for execution of other projects under way

33

Works during shutdown phase



Civil: foundations replacements and reinforcements (should be avoided due to duration)



Mechanical: equipment replacement (exchangers, vessels…); column trays and/or other internals replacement; rotating equipment modifications (pumps, compressors, GTS…); chemicals replacement (e.g. mole sieves); heaters modifications…



Piping completion: dismantling, remaining erection, remaining tie-ins, hydrotests, insulation, painting



Instrumentation completion: dismantling, remaining installation & connections; loop checks



Electricals completion: dismantling, remaining connections

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Dummy assembly of piping, structure, equipment internals, column trays… to avoid erection problems as far as possible; marking of items to be removed

34

Job cards 

“Job Cards” sheets: a method to define and control revamping works (in particular S/D) by detail itemization of work & required resources, material & time



Work is defined by reference to Commissioning sub-systems; PIDs, GA drawings tie-ins list per discipline (showing work definition for ea. S/D)



Equipment card: new or modified equipment



Piping card: a piping network with limits defined by tie-ins, equipment nozzles or sub-systems limits (a commissioning sub-system includes 1 or several JC)



Job Cards identify applicable technical documents (PID, installation and dismantling dwgs, list of included isos & tie-ins), & include: Detail work description; sketches showing system dismantling, installation, tie-ins Safety requirements with required personnel Construction personnel & man-hours Construction equipment (scaffolding, crane, tools… with sketches for erection) Required material and Bill Of Materials by isometric Required QC

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • •

35

Job cards



The Job Card detail work split allows, ahead of Shutdown, to: • • • • •



Estimate man-hours by Card and globally required Plan/schedule Shutdown by Card, with manpower histograms Assign construction teams by geographical areas Use similar system for construction & commissioning Prepare materials by Card (piping spools are identified by their Card number, erection materials are bagged & tagged per Card)

During the Shutdown

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Progress report by Card and globally, daily • Quality control and punch list by Card • Better evaluation of completion progress

36

Typical Construction Schedule

Site Preparation Civil Works, Roads, Railways

Mechanical Completion

Structural Steel U/G Piping Installation Equipment Erection A/G Piping Erection

Generally on the critical path

U/G Electrical Cables

A/G Electrical Installation Electrical Tracing Instrumentation Painting - Insulation Precommissioning RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Fire Proofing

37

Typical conditions for good piping erection



% of Isometrics Issued AFC*



% of Pipe Spools Available



% of Equipment Nozzles Available



Pipe Supports and Pipe Racks Available



Piping Material Supplied to Prefabrication Workshop



Construction Equipment Available



Construction Resources Mobilized

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

*AFC = Approved For Construction

38

Material management system 

Major EPC Contractors have implemented an integrated Material Management System which incorporates all data on commodities requisitioned, bill of bulks materials and their procurement status.



Purchasing, expediting, inspection, shipping, receiving and site storage and handling information is loaded in the system, successively by engineering, procurement (expediting) and construction.



The system allows individual tracking of bulks items from MTOs to the site



At Site it allows to:

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• Continuously update the material warehouse inventory upon material receipts • Issue OS&D reports • Know the status of material deliveries and check or forecast availability of material for pre-fabrication or erection in order to plan the fabrication / construction or expedite lacking items (this can also be done at Home Office).

39

Monitoring of construction



Progress Measurement • Weekly Progress follow up by Work Quantities / Man-hours



Productivity Analysis



Man-hours Expenditure • Weekly man-hours follow up per trade



Trending and Forecasting • Compare Yields Man-hours per Work Quantities • Look for Trends • Permanently update the forecasted finishing date © 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

40

Monitoring of construction Construction progress control allows to calculate a planned progress when implementing the system, and to calculate the physical progress and the forecast progress.



The construction work is divided into unitary works, all measured in the same unit (e.g. construction man-hours, using available estimated manhours and ratios).



These works are then aggregated into work item, category, construction trade, worksite



Achieved physical progress: work achieved / work planned. Checking of achieved items allows to calculate corresponding “earned man-hours”. Physical progress = earned man-hours / planned man-hours



“Productivity”: earned man hours / spent man hours



Reports are prepared weekly and monthly.

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



41

Temporary Construction Facilities



Adequate temporary facilities are essential: Owner/Contractor/Subcontractor offices with modern telecomm First Aid / Medical Aid Facilities Housing facilities for subcontractors, cafeteria, showers, toilets Construction Contractors Warehouse / Consumables Store Main Laydown Area Concrete Batching Plant (if on site) Piping site prefabrication area (in safe location) Dress-up area, Air coolers assembly area Plant & Vehicles maintenance facilities Painting & blasting workshop Hot insulation & cold insulation shops Access roads & gates

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

• • • • • • • • • • • •

42

Construction quality control Detailed Quality Control Plans are prepared to check construction quality for all areas of construction by inspection and tests, as construction progresses and works are completed



Quality is controlled by the Quality Control teams (Construction Contractor, Main contractor, Company) which include:



Piping & mechanical inspectors



Civil works inspectors



Welding inspectors



E&I inspectors…



Non-conformance reports are prepared when works are not in conformity with specifications, drawings or construction specifications



Site Quality Control may also be controlled by an Independent Third Party, for instance for welding inspection

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



43

Reporting of non-conformances

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

44

Construction / Operation Interfaces



End of Construction • • • • •

Pressure Tests Static Mechanical Tests Precommissioning Mechanical Completion Handover to Commissioning Team

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

Operation • • • • • • • •

Operators Training Commissioning Start-up Nominal production Performance Tests Provisional Acceptance Mechanical Warranty Final Acceptance

Commissioning Manager

© 2013 - IFP Training

Construction Manager



45

Precommissioning 

Precommissioning is the last phase of Construction (to be maximized): • Piping hydrotests

• Test Electrical Installation and Energize • Test Instrument Control Loops Continuity Tests • Align Rotating Equipment • Punch Lists − Prepared by both Construction and Operation Teams − Categorize Punch-List Items

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

A = Items to be completed before Mechanical Completion B = Items to be completed before Start-Up C = Items which can be completed post Start-Up D = Nice to have items, but not part of the scope, Items to be assessed later on their own merit by Operation

© 2013 - IFP Training

» » » »

46

Construction and Fabrication Management Key points to keep in mind 

Always consider Safety and Health issues as first priority, and let it know



Set-up and maintain Trust between all field players



Clearly define roles and responsibilities (many players at the same time)



Assure effective and timely corrective actions



Maintain effective documentation system (issue and sharing)



Ensure effective implementation by each players of their own system for: • Safety and Health awareness • Quality control

Provide logistic site support for personnel (temporary facilities)



Assure clear Contract terms at the working level, no ambiguities



Give enough authority to the field organization (empowerment)



Keep close control on schedule – it will have a cost impact

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



47

Attachments I. Specific construction II. Pre-shutdown works © 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

48

Attachment I Specific Construction

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

49

Execution Plan Highlights



Maximal weight acceptable for lifting, acceptable alternates



Coordination with local fabrication shop, load out procedures



Transportation procedures



Site installation and hook-up procedures, tie-ins



Equipment construction main procedures



Safety procedures © 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

50

Typical work during turnaround

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training

Exxon, Shell, BP, by courtesy

51

Turnaround work Exxon, Shell, BP, by courtesy

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

52

Refinery construction work Exxon, Shell, BP, by courtesy

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

53

Attachment II Pre-shutdown works

© 2013 - IFP Training

RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

54

Works during pre-shutdown phase 









RC - PR GES - 08175_A_A - Rev. 1 - 18/07/2013

© 2013 - IFP Training



Civil works: new buildings, foundations, structures; cables trenches (excavation may need to be done by hand; should be minimized: cable trays preferred) Mechanical: erection of new equipment on new foundations & structures; pre-dressing when possible; painting & insulation where possible Piping: all pre-fabrication; spool installation & erection on new equipment and on pipe racks, up to tie-ins; including supports; possibility of shop hydrotest with field welds 100% Gamma rayed Instrumentation: new cable trays, cable pulling (instrument cables trench closure), junction boxes, installation of instruments for new equipment / piping; connections of cables to new instruments Electricals: cable pulling (electrical trench closure), connections to new motors; new lighting & earthling Tie-ins which can be performed pre-shutdown: lines which may be individually shut-down, FW lines, hot taps; tie-ins during “given” S/Ds

55

Related Documents


More Documents from "Saj1985"