2017 05 15 - Bses - Prm 04

  • Uploaded by: Anoop Dikshit
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 2017 05 15 - Bses - Prm 04 as PDF for free.

More details

  • Words: 6,658
  • Pages: 54
Loading documents preview...
V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur

Monthly Project Review Meeting GIS BRPL-66/11 kV Substation at Mithapur 62OP-90942

POC

Project Execution:

Status 2017-05-15 EM TS SAM / EM TS P IN

Business Segment Manager: Burkhard Ortmann Business Subsegm. Manager: N Vaidyanathan Business Responsible: Amresh Kakkar Compliance Officer BU: Compliance Officer Region:

Saksena, Nishi

Coach: Franz Gerner Process Manager Local: Process Promoter Region: V Sajeev Project Manager: Sharma, Ritesh Commercial Project Manager: Vibha Chhabra World Project Controller: Pless, Daniel QMiP: Indu Shekhar EHSMIP: Vashista, Shruti 2016 © Siemens AG 2015 PRM

Unrestricted

EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur Agenda

1. Project Overview 2. Project Picture 3. Contract Structure 4. LoP last meeting 5. Status Summary 6. Financials 7. Highlights - Lowlights 8. EWIS@EM TS 9. EHS Status 10. Schedule 10.1 Key Dates 10.2 Critical Path - 3-month-window 10.3 Work progress 11. Resources 12. CCN Approval

page 2/54

PRM

13. Risk Assessment 14. Opportunities' 15. Claims Status / PMTC+ 16. NCR+ Status 17. Profit Bridge 18. Collection Plan 19. Cash 20. Procurement Status 21. Engineering status 22. Organizational Topics

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 1. Project Overview

Source: PMTC+

Project Key Information End Customer: BSES Rajdhani Power Ltd. Customer: BSES Rajdhani Power Ltd. Regional Unit: India Type of Business: Business on own account (BOA) Project Category: C Scope: Supply, Civil & ETC for 66/11KV GIS Substation at Mithapur Project Volume: 211' 160 INR Key Dates: LoI date : 29/04/2016 End Date : 31/08/2017 Warranty: Warranty for Everything except GIS : 18 months from commissioning or 24 months from last supply GIS : 36 months from commissioning or 40 months from last supply

Country: India

LD's: LD Clause: Liquidated damages a sum equivalent to 0.5 % of the contract value for each week or part there of delay until the actual date up to a

Type: GIS Substation

maximum deduction of 5% of unexecuted work

Main Data: 66/11KV GIS

Liability: Defect Liability for Everything except GIS: 18 months from commissioning or 24 months from last supply GIS: 36 months from commissioning or 40 months from last supply Accounting method: POC

page 3/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 1. Project Overview Owner

BSES Rajdhani Power Limited

Project Details

66/11 kV GIS Substation at Mithapur

Location

Mithapur, Delhi

Funding

BRPL Funding

Consultant

NA

PM CPM

Ritesh Kr Sharma Vibha Chhabra

Start/Completio n date

Start Date: 29th April’16 Completion Date: 31st Aug’ 17

Duration

16 months

Order Value

231,457,837.00 INR

page 4/54

PRM

Source: PMTC+

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

SAFETY HUT

page 5/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

NATIONAL SAFETY WEEK CELEBRATION AND GIFT DISTRIBUTION

page 6/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

SIDE IN PROGRESS 66 kV (8DN85) GIS 11kV ERECTION COLUMN CASTING ABOVE 1 ST LVL SLAB IN PROGRESS

page 7/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

11kV SIDE BRICK WORK ABOVE 1ST LVL SLAB IN PROGRESS ERECTION & TESTING COMPLETED FOR 11 kV HV TESTING FOR 66 kV GIS COMPLETED ON 12 04 17 SWITCHGEAR

page 8/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

GIS SIDE BEAM AT+5.65m PROGRESS 66 kV INDOOR & OUTDOOR HT CABLE TERMINATION IN GIS IN SIDE GIS SIDE COLUMNPROGRESS ABOVE CORBEL BEAM IN PROGRESS STAGING FOR GIS PORTION SLAB CASTING COMPLETED TILL 5.65M LVL

page 9/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

GIS SIDE 66 kV GIS ROOM – EOT CRANE BEAM AT+5.65m IN PROGRESS

Page 10/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

GIS SIDE BEAM AT+5.65m IN PROGRESS

GIS SIDE COLUMN ABOVE CORBEL BEAM IN ETC FOR ACDB COMPLETED PROGRESS RELAY & RTU TESTING IN PROGRESS page 11/54

PRM

BATTERY CHARGER CUM DCDB

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

GIS SIDE BEAM AT+5.65m IN PROGRESS GIS CUM CUM CONTROL CONTROL ROOM ROOM BUILDING BUILDING GRIT FRONT VIEW GIS WASH COMPLETED GIS SIDE COLUMNCORBEL ABOVE CORBEL BEAM INBEAM PROGRESS IN PROGRESS

page 12/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

66 kV POWER TRANSFORMER TESTING IN PROGRESS

Page 13/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

2 NOS. CAPACITOR BANK ITC IN PROGRESS

page 14/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Project Picture

Source: PMTC+

BRICK WORK FOR FIREWALL IN PROGRESS

WATER TANK IN PROGRESS

page 15/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur Source: manual

3. Contract Structure PO No (Split contracts )

SUPPLY: NB/D01/23080276 dtd 09.06.2016, CIVIL: SER/DSC/23556735 dtd 21.06.2016, ETC: SER/DSE/23556737 dtd 21.06.2016

Payment terms

10% against ABG 20% against drg. approval/ mobilization 60% against inspection/prorata 10% against testing & comm.

Liquidation Damages

0.5 % of the contract value for each week up to a maximum deduction of 5% of unexecuted work

ToC

Completion Certificate effective immediately after Commissioning

Defect Liability:

•18 months from commissioning or 24 months from last supply •GIS 36 months from commissioning or 40 months from last supply

Payment Process:

POC

page 16/54

PRM

Siemens In- House Supply: 66 kV GIS–7 Bays 11 KV – 22 Bay Switchgear. CRP Panels and Substation Automation System Bought out equipments: 1. Transformer Accessories – 2 Sets 2. Station Transformer-1 No. 3. Battery & battery charger-1 No. each 4. ACDB- 1 No. 5. Capacitor Bank-2 Nos. 6. Surge arrestor-7 Sets 7. Earthing-1 Lot 8. Illumination system-1 Lot 9. Fire detection system – 1 Lot 10. LT Power & Control Cable-1 Lot 11. 3.5 Ton EOT Crane- 1 No. 12. DSLP – 1 Lot 13. Cable tray & Accessories – 1 Lot Civil Works: Civil works for GIS cum control room Building, Transformer foundations, Cable trench, Roads, Capacitor bank, Gravel spreading as applicable. ETC Works: Erection Testing Commissioning for the above supply and free issue items such as 25MVA transformers, 11 kV NCT, HT Cables, Zebra conductor.

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 3. Contract Structure

Source: PMTC+

Plan Cost Split

OV Split Civil

ETC

Supply BO 17%

Supply IH

Civil

Supply BO

Civil 24%

ETC

Supply IH Supply BO OTH Suppl y BO 10%

ETC 7%

Supply IH 53% Package Civil ETC Supply IH Supply BO

Value (INR) 55,092,600 15,322,394 121,554,535 39,488,339

TOTAL

231,457,869

page 17/54

PRM

Package Civil ETC Supply IH Supply BO OTHERS

%

24% 7% 53% 17%

TOTAL

Unrestricted

OTHERS

ERS Civil 18% 22% ETC 5.5% Supp ly IH 44.5 %

% Value (INR) 41,000,000 22% 10,536,527 5.5% 83,380,102 44.5% 18,043,202 10% 34,202,739 18%

187,162,569

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 4. LoP last meeting

Item

Date of Issue Review Type

Observations

Source: PMTC+

Action Items

Financi al Due Impact Responsible Date (INR Million)

Status Remarks

A) Engineering -99% completed - O&M manual and as built is pending B) Procurement - 94% completed. Major Items i) CRP and SAS ii) Capacitor Bank under inspection and pending delivery at site. 1

27-Mar- Project C) Civil works - 52% in progress. - expected 17 Status completion by May'17 i) Security room - pending ii) Cables trench - 150 mtrs iii) Fire wall - In progress iv) Outdoor Equipment foundation (12) - In progress v) Cable trench, drain road etc are pending vi) GIS Building - Finishing work underway

A) Closely monitor the civil progress at site. B) Civil BoQ reconciliation to be performed. Also, Cost to come to be evaluated for balance scope of work and necessary adjustment to be recorded accordingly.

 

Ritesh Sharma

30Apr17

Done

 

C) Cost to come related to Civil & ETC to be assessed.

D) Team is ahead of project schedule and customer is supporting the effort.

page 18/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 5. Status Summary Project Nam e SAP Num ber

GIS BRPL-66/11 kV Substation at Mithapur 62OP-90942 BSES Rajdhani Pow er Ltd. BSES Rajdhani Pow er Ltd. India Business on ow n account (BOA)

Custom er End Custom er Regional Unit Type of Business Portfolio System Main Data LOA-ID Finance current Month TINR LOA 211,160 As S o ld P M 80 211,160 OEC P M 100 211,160 16-12 211,160 17-01 211,160 17-02 211,160 17-03 211,160 17-04 211,160 17-05 211,160 Target Change Orders Order Costs Date PM, Engineering Products - EM TS TI Products - EM TR Products - EM HP Other Equipment Transportation Installation Civil Works Platform Surcharges and Inclusions Risk (incl. LD) Warranty C o s t to a ggre ga te d pro je c ts

Total n/a Imminent Losses fx effects not PoC

PMTC+ V2.26

actual

TINR

TINR

31,901 38,382 126,764 147,603 161,616 211,160 0 TINR LOA As Sold PM80 TINR 15-12 25,669 0 0 62,845 38,578 3,089 10,537 41,000 0 2,053 890 940 0 185,602 0 0 0 0

TINR 16-07 25,669 0 0 62,845 38,578 3,089 10,537 41,000 0 2,053 890 940 0 185,602 0 0 0 0

INCO-Term s

FOR

Cost of Sales (CS) current expected actual TINR TINR 185,602 185,602 185,602 185,612 187,162 187,162 187,162 187,162 187,162 187,162 Target Costs of Capital OEC PM100 EAC* TINR 16-03 25,669 0 0 62,845 38,578 3,089 10,537 41,000 0 2,053 890 940 0 185,602 0 0 0 0

*w /o Commitment

page 19/54

C 322143 India

TINR 17-04 27,220 0 0 62,845 38,578 3,089 10,537 41,000 0 2,053 901 940 0 187,163 0 0 0 0

PoC * actual

Gross Margin

current (Rcur - CScur) TINR TINR TINR 25,558 12.1% 25,558 12.1% 25,558 12.1% 28,041 15.0% 25,548 12.1% 34,020 18.0% 23,998 11.4% 112,358 60.0% 23,998 11.4% 130,828 70.0% 23,998 11.4% 143,236 77.0% 23,998 11.4% 23,998 11.4% 0 TINR Target Gross Margin CS act. Obligo /C o m m itm . CS exp. PoC * TINR TINR TINR % 17-04 17-04 17-05 17-04 17,801 1,244 27,220 65.4% 0 0 0 0 0 0 62,845 0 62,845 100.0% 32,805 792 38,578 85.0% 1,152 1,141 3,089 37.3% 5,693 2,776 10,537 54.0% 22,683 11,695 41,000 55.3% 0 0 0 258 0 2,053 12.6% 0 0 900 0 0 940 0 0 0 0.0% 143,236 17,649 187,162 76.5% -0 57 0 0 0 0 0 0 0 0 0 0

Currency Exchange Rate

PRM

OEC Date Softw are Tools Accounting m ethod NCM Project

2016-03-16 SAP, PMTC, Plato & MS Office POC

Key Roles

No

Business Responsible Compliance Officer BU Compliance Officer Region Coach Process Manager Local Process Promoter Region Project Manager

Business Segment Manager Burkhard Ortmann Business Subsegment Manager

Scope of Supply Supply, Civil & ETC for 66/11KV GIS Substation at Mithapur

GIS Substation 66/11KV GIS 322143 Revenue (R) expected

Source: PMTC+ Project Category WUPID Destination

71.000

actual (Ract - CSact) TINR

3,860 4,362 14,406 16,775 18,380

12.1% 11.4% 11.4% 11.4% 11.4%

0 TINR Work progr. Changes % 17-05 65.4% 0.0% 0.0% 100.0% 85.0% 37.3% 54.0% 55.3% 0.0%

76.5% 0.0% 0.0% 0.0% 0.0%

Currency

16-12 17-01 17-02 17-03 17-04 17-05 Com m ents

Milestones PM080 PM100 PM150 PM200 PM300 PM400 PM550 PM600 PM650 PM670

INR

Unrestricted

Profit current TINR 19,224 19,224 19,224 19,214 17,663 17,663 17,663 17,663 17,663 Risks

Profit LOA 9.10%

Commercial Project Manager

World Project Controller QMiP EHSMIP

9.1% 9.1% 9.1% 9.1% 8.4% 8.4% 8.4% 8.4% 8.4%

OpportunitiesChange Orders

(Risk Cont.) Impact after Measure TINR TINR -1,840 -1,840 -1,840 -1,840 -1,840 -1,840

Revenue current TINR 0 0 0 0 0 0

0 0 0 0 0 0

Cost Improvement current TINR 0 0 0 0 0 0 expected

planned 15.06.2016 Start of project 05.07.2016 QG_Order receipt clarified 22.07.2016 Approval and freeze basic design 03.07.2016 Approval of detailed planning 17.02.2017 Dispatch approval 18.04.2017 Material & resources at site Construction / installation completed 15.08.2017 QG_Release for customer acceptance31.08.2017 31.08.2017 Customer acceptance 30.10.2020 QG_Project closure

NCC current TINR 0 0 0 0 0 0

N Vaidyanathan Amresh Kakkar Saksena, Nishi Franz Gerner V Sajeev Sharma, Ritesh Kumar Vibha Chhabra Pless, Daniel Indu Shekhar Vashista, Shruti

Claim

Claim

IN D1-3 Net Value TINR 0 0 0 0 0 0

OUT D1-3 Net Value TINR 0 0 0 0 0 0

expected

actual

15.06.2016 05.07.2016 22.07.2016 27.07.2016 17.03.2017 25.05.2017 15.06.2017 30.06.2017 30.06.2017 30.06.2020

01.07.2016 03.10.2016 13.07.2016 07.10.2016 23.02.2017 28.04.2017

2017-05-15 12:45:15 © Siemens AG 2015 EM TS PO

Report from

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Financials (1/2)

Source: PMTC+

Accounting method POC

SAP

Figures in TINR * MIKA import date: 2017-05-10

PMTC+

LoA

As Sold PM80

OEC*

Change

EAC*

Actual*

Current

Expected

2015-12-16

2016-07-01

2016-03-16

OEC to EAC

17-04

17-04

16-12

17-01

17-02

17-03

17-04

17-05

211' 160

211' 160

211' 160

211' 160

161' 616

211' 160

211' 160

211' 160

211' 160

211' 160

211' 160

211' 160

211' 160

211' 160

211' 160

211' 160

185' 612

187' 162

187' 162

187' 162

187' 162

186' 006

187' 162

187' 162

187' 162

187' 162

Target

17-05

Date of project management review Revenue

0

expected Cost of sales

185' 602

185' 602

185' 602

+ 1' 561

187' 163

143' 236

expected Gross margin in % of revenue

in % of revenue Profit in % of revenue

187' 162 187' 162

25' 558

25' 558

25' 558

- 1' 561

23' 997

18' 380

25' 548

23' 998

23' 998

23' 998

23' 998

23' 998

23' 998

12.1%

12.1%

12.1%

- 0.7%

11.4%

11.4%

12.1%

11.4%

11.4%

11.4%

11.4%

11.4%

11.4%

6' 335

6' 335

6' 335

0

6' 335

4' 848

6' 335

6' 335

6' 335

6' 335

6' 335

6' 335

6' 335

3.0%

3.0%

3.0%

0%

3.0%

3.0%

3.0%

3.0%

3.0%

3.0%

3.0%

3.0%

3.0%

19' 224

19' 224

19' 224

- 1' 561

17' 663

13' 532

19' 214

17' 663

17' 663

17' 663

17' 663

17' 663

17' 663

9.1%

9.1%

9.1%

- 0.7%

8.4%

8.4%

9.1%

8.4%

8.4%

8.4%

8.4%

8.4%

8.4%

2

Functional costs

211' 160

Costs of capital

' 000

5

1

5

4

.4

5

5

5

2

3

9

9

7

.7

9

5

5

2

3

9

9

7

.7

9

5

5

2

3

9

9

7

.7

9

5

5

2

3

9

9

7

.7

9

5

5

' 000

' 000

' 000

' 000

' 000

' 000

Risks (CCN+Clo s eOutCCN)

-' 010

-' 010

-' 010

-' 010

-' 010

-' 010

-' 010

NCC (CC N+C lo s eOutCCN)

' 000

' 000

' 000

' 000

' 000

' 000

' 000

Improvement (CCN+Clo s eOutCCN)

' 000

' 000

' 000

' 000

' 000

' 000

' 000

Change orders Revenue (CCN+Clo seOutCCN)

' 000

' 000

' 000

' 000

' 000

' 000

' 000

Claim Out (CCN+Clo s eOutCCN)

' 000

' 000

' 000

' 000

' 000

' 000

' 000

Risks

-1' 840

-1' 840

-1' 840

-1' 840

-1' 840

-1' 840

Opportunities

' 000

' 000

' 000

' 000

' 000

' 000

Claims incoming

' 000

' 000

' 000

' 000

' 000

' 000

Claims outgoing

' 000

' 000

' 000

' 000

' 000

' 000

page 20/54

PRM

Unrestricted

' 000

0.0%

' 000

© Siemens AG 2015 EM TS PO

' 000

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 2. Financials (2/2) LoA

Cost of sales by category PM, Engineering

Source: PMTC+

As Sold PM80

OEC*

Change

EAC*

Actual*

Obligo*

Expected

POC

Work

2016-03-16

OEC to EAC

17-04

17-04

17-04

17-05

17-04

Progress

25' 669

25' 669

25' 669

+ 1' 551

27' 220

17' 801

1' 244

27' 220

Products - EM TS TI

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

0.0%

Products - EM TR

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

0.0%

Products - EM HP

62' 845

62' 845

62' 845

0

62' 845

62' 845

' 000

62' 845

100.0%

100.0%

Other Equipment

38' 578

38' 578

38' 578

0

38' 578

32' 805

' 792

38' 578

85.0%

85.0%

Transportation

65.4%

65.4%

3' 089

3' 089

3' 089

0

3' 089

1' 152

1' 141

3' 089

37.3%

37.3%

Installation

10' 537

10' 537

10' 537

0

10' 537

5' 693

2' 776

10' 537

54.0%

54.0%

Civil Works

41' 000

41' 000

41' 000

0

41' 000

22' 683

11' 695

41' 000

55.3%

55.3%

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

Platform Surcharges and Inclusions

0.0%

2' 053

2' 053

2' 053

0

2' 053

' 258

' 000

2' 053

12.6%

Risk (incl. LD)

' 890

' 890

' 890

+ ' 011

' 901

' 000

' 000

' 900

0.0%

Warranty

' 940

' 940

' 940

0

' 940

' 000

' 000

' 940

0.0%

185' 602

185' 602

185' 602

+ 1' 561

187' 163

143' 236

17' 649

187' 162

76.5%

Cost to aggregated projects

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

#DIV/0!

n/a

' 000

' 000

' 000

0

' 000

' 000

' 057

' 000

0.0%

Imminent Losses

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

0.0%

fx effects

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

0.0%

not PoC

' 000

' 000

' 000

0

' 000

' 000

' 000

' 000

0.0%

Total

page 21/54

PRM

Unrestricted

76.5%

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 7. Highlights - Lowlights (1/3)

Source: PMTC+

Last month Actual month Total Project Status

Green

Green

Highlights

The Project is inlined with Schedule.

Lowlights

NA

Highlights

Customer is supportive and is eager to finish the contract as soon as possible.

Lowlights

Since the customer is doing GIS project for the 1st time, they are not very technically sound. Our engineering team is extending all technical supports to customer for Engineering approvals.

Last month Actual month Customer

Green

page 22/54

Green

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 7. Highlights - Lowlights (2/3)

Source: PMTC+

Last month Actual month Financials

Yellow

Yellow

Highlights

Payment of Civil RA 04 partly received.

Lowlights

Customer is not good in making payments to contractors as per customer past record. We have taken a very aggressive approach for our payments as per T&C of PO.

Highlights

The project is adequately resourced .

Last month Actual month Resources

Green

page 23/54

Green

PRM

Lowlights

NA

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 7. Highlights - Lowlights (3/3)

Source: PMTC+

Last month Actual month Eng. / Technics

Green

Green

Highlights

Engineering approvals have been completed. All the major approvals have been received namely: Key SLD, OGA, GIS, 11 kV switcgear, CRP, Scada, earthing, GIS cum control room building civil drawings, cable trenches

Lowlights

NA

Highlights

The Project is inlined with Schedule. Actual Project progress is 93%

Lowlights

Customer has expressed their concern of commissioning the substation by 30th April 17. We are working our level best to meet customer satisfaction

Last month Actual month Schedule

Green

page 24/54

Green

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 8. EWIS@EM TS

6446 F323GIS AF79 BRPL66/11 2FC7 kV Substat EEC3 ion at 62OP Mithap D6B2 ur (IN) 131B 9094 322 62OP3E04 2 143 90942 C

page 25/54

EM TS SA 200 M IN

PRM

Source: PMTC+

EM TS Regi 565 2,97 2,97 2,9 12.1 India on IN 5 4 360 12.10% 4 74 360 0%

Unrestricted

0.50%

0

370

50

150

150

0

20

370

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 9. EHS Status Project Name: GIS BRPL-66/11 kV Substation at Mithapur   Site Mobilisation: 2017-04-18  

Source: PMTC+

Project-ID: 62OP-90942

Reporting period: 2017-05

  Project Portfolio: GIS Substation

 

  Project Manager: Sharma, Ritesh Kumar Country: India

 

   

*EHS Performance Dashboard in PMTC+ does not replace the mandatory Siemens Health and Safety reporting of your local entity outside ARE 7441             Lagging Indicator Project Month Leading Indicator Project n   Project AFR     n         Fatalities       Site Safety Walks by PM 23 n       Lost Time Incident LTI       JHA´s / Tool Box Talks 212           Restricted Work Cases 0 0   Induction Training Sessions 18     Medical Treatments 0 0   EHS specific Training Sessions 22           First Aid Treatments 11 1   Drug Screen 0 Monthly LTI   Near Misses 11 2   Alcohol Tests 0           Sigificant Events 0 0   Issued Permits to Work 310 Hazardous Situations / Safety     Incidents environment / equipment 0 0   273 Observations           Manhours without LTI 63,368 8,856   Stop work order 1           Total Manhours 63,368     EHS Audit by BU EHS 1           Lost Time Days 0 0       Project LTI   Personal on Site                     Severity Rate 0.00     Concerns / Corrective: Planned actions this Period     AFR per 100k mhrs       Project (SM:18 PM:5) Month(SM:3 PM:1)                                 Summary of safety Recognitions, Significant events, Incidents, Accidents, Near Misses, etc             Project Manhours without LTI               First aid treatment: During walking on site near transformer area victim   hit with bunch of steel and he fell down and got a cut injury on his left 63,368               hand         Near miss: During walking on staircase in evening time due to less       Highlights this Period illumination a scaffolding bracing hit victim's helmet and he fall down Project Fatalities   but not injured               During walking on out side cable trench Mr. prahallad fell down due to       the trench (300mm )is in opening condition no injury                           Induction Training           18                

page 26/54

PRM

 

Unrestricted

  Month 4 52 0 3 0 0 27 33 0 0    

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Key Dates - Contractual

Source: PMTC+

LOA

PAC

29/04/16

31/08/17

Contractual LOA

29/04/16 Actual

page 27/54

66 kV GIS Clean Room

Site Mobilization Start

03/15/17

19/07/16

PRM

Unrestricted

PAC

31/08/17

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Key Dates - Contractual

page 28/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Critical Path – Expediting Schedule

page 29/54

PRM

Unrestricted

Source: Manual

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

Source: PMTC+

EXPEDITING SCHEDULE

CONTRACTUAL SCHEDULE

page 30/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

Page 31/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

page 32/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

page 33/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

page 34/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

page 35/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 10. Schedule – Status as on May 5th ‘17

page 36/54

PRM

Unrestricted

Source: PMTC+

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 11. Resources

page 37/54

PRM

Source: PMTC+

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 12. CCN Approval

Source: PMTC+

No CCN pending for approval as on date

page 38/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 12. Risk Assessment OPEN RISKS (Status 0-4) Item Subject

6

Warranty RIsk

Source: PMTC+

BEFORE MEASURE Costs Probability Costs Measure Impact Potential [TINR] [TINR] '940

100.00%

'940

Back to Back warranties taken from the supplier.

AFTER MEASURE Probability Costs Revenue Potential [TINR] [TINR]

Costs of measure [TINR]

Costs Impact [TINR]

Result

'000

'940

100.00%

'940

'000

-'940

'000

1'640

25.00%

'410

'000

'000

'527

25.00%

'132

'000

'506

25.00%

'000 '000 '000

4'077 '000 4'077   3'137 '000 '940 4'077 '000

Action owner

Action expected date

Creation date

Last modified date

Ritesh Kumar Sharma

6/30/2020

26.10.2016

12.12.2016

-'410

Ritesh Kumar Sharma

6/30/2017

09.09.2016

26.10.2016

'000

-'132

Ritesh Kumar Sharma

6/30/2017

09.09.2016

26.10.2016

'126

'000

-'126

Ritesh Kumar Sharma

6/30/2017

09.09.2016

26.10.2016

45.14%   45.14%

1'840 '000 1'840

'000 '000 '000

28.70%

'900 '000 '940 1'840 '000

'000 '000 '000 '000 '000

-1'840 '000 -1'840   -'900 '000 -'940 -1'840 '000

[TINR]

We have prepared detailed building layouts for GIS taking into account the specification, electrical, civil as well as equipment manufacturer's requirement. With the detailed engineering, the risk associated with the change in size of the building has been mitigated. 2

Risk in Civil Activities

1'640

25.00%

'410

We, however foresee that 25% of the quantities might have an effect on account of any change in layout/ routing vis-a-vis the estimation and for which risk contingency of 30% has been considered. This also includes the risk contigency requirement from Head Quarters (Email Dated 12.04.2014) .

Detailed manpower & machinery/tool estimation is to be done before finalising erection contract in order to mitigate possible additional cost. 3

Risk in Erection Activities

'527

25.00%

'132

However, we have considered a risk with a probablity of 25% towards possible additional cost during execution.

Estimation of Control Cables, Erection Hardware, etc. has been done after preparation of electrical layouts and from inputs from ongoing projects. 4

Risk on Lot items

Subtotal TOP5 Subtotal REST Total identified Therein with: General risk contingency RC for default and delay RC for warranty RC Total No risk contingency

'506

25.00%

'126

4'077 '000 4'077   3'137 '000 '940 4'077 '000

45.14%   45.14%

1'840 '000 1'840   '900 '000 '940 1'840 '000

28.70% 100.00% 45.14%  

We, however foresee that approx 10% of the quantities might have an effect on account of any change in layout/ routing vis-a-vis the estimation and for which risk contingency of 25% has been considered.

   

'000 '000 '000 '000 '000

100.00% 45.14%  

 

 

 

 

see detailed report in PMTC+

page 39/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 14. Opportunities

Source: PMTC+

No Opportunities as on date

see detailed report in PMTC+

page 40/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 15. Claims Status

Source: PMTC+

No Claims as on date

see detailed report in PMTC+

page 41/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 16. NCR+ Status

No NCR as on date

page 42/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 17. Profit Bridge

Source: PMTC+

25'558

-1'550

-'011

23'997

in INR OEC

NCC

page 43/54

CI

Claims

PRM

Change Order Risks Change 6 Productive - Statutory risk Hours + Freight risk

Unrestricted

Change 7

Change 8

Change 9

Others

MIKA

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 18. Collection Plan

Source: PMTC+

Receivable Summary

Description

Billing and Collection Plan

Amount

Cumulative Invoicing till Apr'17( incl adv of 13 Mil)

178'9

Cumulative Collections upto Apr'17

102'2

Cumulative excess or Month Billing Collection plan shortfall

Remarks

Excess cost at 30th Apr 2017

0'0

17-May

8'3

4'8

67'2

 

Opening Balance of Debtors as on 1st Apr 17

63'7

Add: Invoicing during the month Apr'17

17-Jun

13'8

62'2

18'8

 

15'6

17-Jul

23'0

8'3

33'5

 

17-Aug

0'0

12'4

21'1

 

17-Sep

0'0

0'0

21'1

 

2017-18

0'0

21'1

0'0

10% retention

 

211'1

211'1

 

 

Less: Collections during the month Apr'17

3'0

Balance as 30.04.2017

76'3

wherein( As on Mar17)

 

Retention

18'2

Tax certificates

0'2

Not Due

72'0

Overdue

0'0

Page44/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 17. Cash

70,000 60,000 50,000 40,000 30,000 20,000 10,000 0 -10,000 -20,000 -30,000

Source: (PLATO)

Cash Balance - GIS BRPL-66/11 kV Substation at Mithapur

16-Q3

16-Q4

17-Q1

17-Q2

17-Q3

17-Q4

18-Q1

18-Q2

18-Q3

18-Q4

19-Q1

19-Q2

19-Q3

19-Q4

20-Q1

20-Q2

20-Q3

20-Q4

21-Q1

OEC

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

prev. month

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

-336

56,782

52,156

-25,022

-11,400

2,899

23,999

23,999

23,999

23,999

23,999

23,999

23,999

23,999

23,999

23,999

23,999

23,999

23,999

present month 250,000

120,000

Quarterly cash slices - GIS BRPL-66/11 kV Substation at Mithapur

100,000

Cash In cum

200,000

80,000

150,000

60,000 100,000

40,000

50,000

Cash In

16-Q3

16-Q4

17-Q1

17-Q2

17-Q3

17-Q4

18-Q1

18-Q2

18-Q3

18-Q4

19-Q1

19-Q2

19-Q3

19-Q4

20-Q1

20-Q2

20-Q3

20-Q4

21-Q1

0

64,172

3,125

32,945

69,159

20,661

21,100

0

0

0

0

0

0

0

0

0

0

0

0

336

7,054

7,751

110,123 55,537

6,362

0

0

0

0

0

0

0

0

0

0

0

0

0

Cash in cum

0

64,172

67,297 100,242 169,401 190,062 211,162 211,162 211,162 211,162 211,162 211,162 211,162 211,162 211,162 211,162 211,162 211,162 211,162

Cash in cum (OEC)

0

0

Cash out

page 45/54

PRM

0

0

0

0

0

0

0

0

Unrestricted

0

0

0

0

0

0

0

0

0

0

© Siemens AG 2015 EM TS PO

Cash in/Cash out

0

20,000

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 20. Procurement Status SL No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Item Description 66 kV GIS CRP Scada 11 kV switchgear Power transformer accessories 66 KV Bus post Insulator 11KV, 7.2 (3.6 +3.6) MVAR, Capacitor Bank with Motorized 66KV surge arrestor Station Aux. Transformer, 11/0.433KV, 400KVA Battery for 220 V DC Battery charger for 220 V dc (float & float cum boost) Exhaust and Ventilation for complete S/Stn building. Maintenance tools & tackles including testing instruments Fire detection and alarm system ACDB Outdoor lighting including street lighting with Poles High Mast Lighting 16M high Indoor Lighting system Crane & its arrangement in GIS Room LT Power & Control Cables 11/66 KV cable termination kits & glands Cable trays Grounding and earthing DS Lightning protection by spikes

page 46/54

PRM

Unrestricted

Qty

UNIT

7 7 1 26 1 1 2 21 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1

bays nos nos nos lot lot set Nos. no. no. no. lot lot lot no. lot Nos. lot No. lot lot lot lot lot

ORDERING STATUS Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed

TARGET /ACTUAL DELIVERY 05-Mar-17 05-Apr-17 05-Apr-17 20-Feb-17  21-Mar-17 21-Feb-17 05-Apr-17 18-Jan-17 23-Mar-17 15-Dec-17 7-Jan-17 9-Feb-17 27-Feb-17 1-Feb-17 18-Jan-17 14-Feb-17 30-Mar-17 14-Feb-17 28-Dec-16 14-Mar-17 4-Apr-17 24-Feb-17 16-Feb-17 16-Feb-17

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 21. Engineering Status - Electrical Status

Date as per L2

Completion

Single Line Diagram of 66/11kV

Approved

20.08.2016

Completed,02.09.2016

Electrical Overall General Arrangement Drawing

Approved

13.07.2016

Completed,11.08.2016

GIS & Control Room Building Plan & Section

Approved 

13.07.2016

Completed. 13.07.2016

Single line Diagram – LT Aux system

Approved

20.07.2016

Completed. 20.07.2016

20/25MVA Power Transformer Outdoor Yard details

Submitted

23.09.2016

Completed. 25.10.2016

Direct stroke lightning protection

Approved

12.09.2016

Completed. 02.09.2016

Earthing

Approved

02.09.2016

Completed. 15.09.2016

Illumination (Indoor)

Approved

24.08.2016

Completed. 22.09.2016

Illumination (Outdoor)

Approved

30.09.2016

Completed. 22.11.2016

HT power cable schedule

Approved

15.08.2016

Completed. 11.08.2016

LT power & control cable schedule

Information category

07.10.2016

Completed. 08.02.2017

Cable routing & trench layout (indoor)

Approved

03.08.2016

Completed. 26.09.2016

Cable routing & trench layout (outdoor)

Approved

03.08.2016

Completed. 02.09.2016

Erection key Diagram

Approved

19.10.2016

Completed. 02.11.2016

66 kV GIS

Approved

19.08.2016

Completed. 14.09.2016

11 kV switchgear

Approved

05.08.2016

Completed. 30.09.2016

3.5 T EOT Crane

Approved

20.10.2016

Completed. 06.10.2016

60 kV lightning arrestor

Approved

03.10.2016

Completed. 23.09.2016

66 kV BPI

Approved

03.10.2016

Completed. 02.09.2016

page 47/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 21. Engineering Status - Electrical Status

Date as per L2

Completion

7.2MVAr Capacitor Bank

Approved

11.10.2016

Completed. 03.01.2017

Control & Relay Panel

Approved

04.10.2016

Completed. 24.12.2016

SCADA Panel

Approved

04.10.2016

Completed. 24.12.2016

11/0.415kV, 400kVA LT Aux Transformer

Approved

13.10.2016

Completed. 19.12.2016

ACDB

Approved

11.10.2016

Completed. 07.11.2016

Hardware & Accessories

Approved

17.01.2017

Completed. 03.02.2017

Battery charger cum DCDB

Approved

10.10.2016

Completed. 05.10.2016

150 AH, Ni- Cd battery

Approved

20.10.2016

Completed. 04.10.2016

16M High Lighting Mast

Approved

30.12.2016

Completed. 06.10.2016

Lighting fixtures – data sheet

Approved

30.12.2016

Completed. 09.01.2017

11 kV termination kits

Approved

03.11.2016

Completed. 22.11.2016

66 kV termination kits

Approved

03.11.2016

Completed. 02.11.2016

Fire fighting

Approved

18.10.2016

Completed. 22.11.2016

Exhaust & Ventilation system

Approved

18.10.2016

Completed. 09.01.2017

LT power & control cables GTP

Approved

20.12.2016

Completed. 28.12.2016

page 48/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 21. Engineering Status - Civil Status

Date as per L2

Completion

GIS Cum Control Room Building Architectural Drawing

Approved

30.06.2016

Completed.08.09.2016

Details of Doors & Windows

Approved

30.06.2016

Completed.08.09.2016

Design and analysis

Approved

19.08.2016

Completed.08.09.2016

Design of Internal Cable Trench

Approved

29.09.2016

Completed. 03.10.2016

Design of Steel Corbel & Insert plate

Approved

29.09.2016

Completed. 03.10.2016

GA and RC Detail of Foundation

Approved

19.08.2016

Completed.08.09.2016

GA & RC Details of Plinth Beam

Approved

15.09.2016

Completed.21.09.2016

GA & RC Details of Corbel

Approved

29.09.2016

Completed.03.10.2016

G.A. & RCC Details of Staircase

Approved

05.09.2016

Completed.28.09.2016

GA & RCC Details of First Floor

Approved

26.09.2016

Completed.07.10.2016

GA & RCC Details of Roof & Mumty

Approved

05.10.2016

Completed.04.11.2016

GA & RCC Details of Internal Cable Trench

Approved

22.09.2016

Completed.06.10.2016

Details of Sanitary & water supply

Approved

19.10.2016

Completed.13.02.2017

Design of Steel Corbel & Crane Runway Girder

Approved

13.10.2016

Completed.03.10.2016

Structural Details of Steel Corbel & Crane Runway girder

Approved

27.10.2016

Completed. 03.10.2016

Approved

02.09.2016

Completed.21.09.2016

Security Room building Architectural Drawing

page 49/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 21. Engineering Status - Civil Status

Date as per L2

Completion

Design and analysis of Security Room Building with UG Water Tank

Approved

13.09.2016

Completed, 13.01. 2017

GA & RC Details of Fdn & Column of Security Room cum UG Water Tank

Approved

16.09.2016

Completed, 13.01. 2017

GA & RC Details of Plinth Beam, Roof Beam & Slab of Security Room & UG Water Tank

Approved

16.09.2016

Completed, 13.01. 2017

Detail of Septic Tank & Soak Pit

Approved

02.12.2016

Completed, 13.02. 2017

Detail of Switchyard Fencing

Approved

18.11.2016

Completed, 10.01. 2017

Design of Supporting Structure for LA & BPI

Approved

06.10.2016

Completed, 11.01. 2017

General Details of Supporting Structure for LA & BPI

Approved

13.10.2016

Completed, 11.01. 2017

Fabrication Details of Supporting Structure for LA & BPI

Approved

Design of Foundation for 66 kV Equipment Structure

Approved

22.10.2016

Completed, 11.01. 2017

GA & R. C. detail of Fdn for 66 kV equipment support structure

Approved

22.10.2016

Completed, 11.01. 2017

Design of Lighting Mast Foundation

Approved

18.10.2016

Completed, 25.10. 2016

G.A. & RCC Details of Lighting Mast Foundation

Approved

18.10.2016

Completed, 25.10. 2016

Design of 20/25 MVA 66/11 kV Power X-mer foundation

Approved

04.10.2016

Completed, 09.12. 2016

Miscellaneous

page 50/54

PRM

Unrestricted

Completed, 11.01. 2017

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 21. Engineering Status - Civil Status

Date as per L2

Completion

GA and RC Plan of 20/25 MVA 66/11 kV Power X-mer Foundation

Approved

13.10.2016

Completed, 06.01. 2017

Design of Firewall for 20/25 MVA 66/11 kV Power X-mer

Approved

22.09.2016

Completed, 21.12. 2016

GA and RC Plan of Firewall for 20/25 MVA 66/11 kV Power X-mer

Approved

03.10.2016

Completed, 21.12. 2016

Design of 250 KVA LT X-mer Foundation

Approved

27.09.2016

Completed, 24.01. 2017

GA and RC Plan of 250 KVA 11/0.4 kV LT X-mer Foundation

Approved

27.09.2016

Completed, 24.01. 2017

Design of Burnt Oil Tank

Approved

04.10.2016

Completed, 23.12. 2016

GA and RC details of Burnt Oil Tank

Approved

18.10.2016

Completed, 17.01. 2017

Design of 7.2 MVAr Capacitor Bank Foundation

Approved

13.09.2016

Completed, 21.02. 2017

GA and RC details of 7.2 MVAr Capacitor Bank Foundation

Approved

13.09.2016

Completed, 21.02. 2017

Details of fencing for Capacitor Bank

Approved

18.11.2016

Completed, 21.02. 2017

page 51/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 22. Construction Progress – Civil Works

Civil Works

Qty

Status

Completion/Target construction date

1 Lot

Completed

03.08.2016

Foundation

29 Nos

Completed

29.09.2016

Column upto Plinth level

29 Nos

Completed

20.10.2016

Plinth Beam

160 mts

Completed

06.12.2016

Column up to 1st lvl

29 Nos

Completed

06.12.2016

140 Sqmt

Completed

28.11.2016

Column upto Corbel level GIS Hall and Corbel Beam

8 nos

Completed

11.12.2016

Column upto GIS Roof level

21 nos

Completed

15.12.2016

320 Sqm

Completed

30.12.2016

Completion of Building Structural works

1 Lot

Completed

14.01.2017

Clean room condition of GIS Hall & 11kV Switchgear

 1 Lot

 Completed

15.03.2017

Site Establishment GIS cum Control Room Building  

1st lvl roof bean & slab

2nd lvl slab casting

page 52/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 22. Construction Progress – Civil Works Civil Works

Qty

Status

Completion date

Security room building

1 No.

In Progress

30.05.2017

Transfomer foundation

2 Nos.

Completed

27.01.2017

150 mtr.

In Progress

25.05.2017

200 sqmtr.

Not Started

15.06.2017

153 mtr.

Not Started

15.06.2017

1 No.

In progress

20.05.2017

14 Nos.

Completed

05.04.2017

External cable trench Internal road Drain Firewall Equipment (LA, BPI, station transformer, cap. bank) foundation

page 53/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

V 17

PRM - GIS BRPL-66/11 kV Substation at Mithapur 18. Organizational Topics

Source: PMTC+

Further Organizational Topics can be found in Onlinehelp

page 54/54

PRM

Unrestricted

© Siemens AG 2015 EM TS PO

Related Documents

04-05-08
February 2021 1
05 15 Clio Biografias
February 2021 0
Aerojournal_021_2011-04-05
February 2021 0
Homework 17-05-2017
January 2021 0
Moneylife - 15 Sept. 2017
January 2021 1

More Documents from "Alok Kumar Singh"