Loading documents preview...
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 1 of 28 REV NO: R0
DESIGN QUALIFICATION DOCUMENT OF AIR HANDLING UNIT (AHU-09)
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 2 of 28 REV NO: R0
TABLE OF CONTENTS SL.NO
DESCRIPTION
PAGE NO
1.0
PURPOSE
4
2.0
SCOPE
4
3.0
RESPONSIBILITY
5
4.0
FACILITY DESCRIPTION
5
5.0
STANDARDS & GUIDELINES
6
6.0
BASIS OF DESIGN PARAMETERS
7
6.1
AREAS COVERED, ROOM AREA, HEIGHT & ROOM VOLUME
7
6.2
OUTISDE CONDITIONS
7
6.3
DESIGNED INSIDE CONDITIONS
7
6.4
OCCUPANCY, EQUIPMENT LOAD, AREA CLASSIFICATION, DESIGN AIR
8
CHANGES, ROOM AIR QUANTITY, TOTAL AIR QUANTITY & TOTAL COOLING LOAD REQUIREMENTS.
6.5
ROOM DIFFERENTIAL PRESSURE GRADIENT
8
6.6
TEMPERATURE & HUMIDITY CONTROL
8
7.0
HVAC SYSTEM DESCRIPTION & TECHNICAL SPECIFICATIONS
9
7.1
HIGH SIDE SYSTEM
9
7.1.1
CHILLED WATER GENERATION SYSTEM
9
7.1.2
CHILLED WATER DISTRIBUTION
9
LOW SIDE SYSTEM
10
EQUIPMENTS – I. AIR HANDLING UNIT
10
II. DEHUMIDIFIER
11
III. PRE COOLING COIL
12
7.2 7.2.1
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 3 of 28 REV NO: R0
TABLE OF CONTENTS CONTINUED... 7.2.2
TERMINAL HEAP MODULES WITH PERFORATED GRILLS
13
7.2.3
TERMINAL MINIPLEAT HEPA FILTERS
13
7.2.4
RETURN RISERS GRILLS WITH FILTERS
13
7.2.5
AIR DISTRIBUTION
14
7.2.6
DUCTING
14
7.2.7
DUCT WORK DETAILS
14
7.2.8
DUCT INSULATION
15
7.2.9
VOLUME CONTROL DAMPERS & FIRE DAMPERS
15
7.2.10
MAGNEHELIC GAUGES
16
7.2.11
TEMPERATURE, RH & DIFFERENTIAL PRESSURE INDICATORS
17
7.2.12
CHILLED WATER PIPING & VALVE FITTINGS
17
7.2.13
CHILLED WATER DRAIN U TRAP
20
7.2.14
CHILLED WATER INSULATION
21
7.2.15
PRESSURE GAUGES
21
7.2.16
TEMPERATURE GAUGES
21
8.0
SAFETY CONSIDERATION
21
9.0
PERFORMANCE TESTING
22
10.0
ATTACHMENTS
23
11.0
ABBREVIATIONS
24
12.0
SUMMARY REPORT
25
13.0
CONCLUSION
26
14.0
AHU DESIGN QUALIFICATION APPROVAL SHEET
27
DESIGN QUALIFICATION
1.0
SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 4 of 28 REV NO: R0
PURPOSE: To Document & demonstrate that the AHU-09 is designed as per the approved specifications to meet the respective area requirements and other regulatory guideline requirements. To design and document the HVAC system of AHU-09 for manufacturing facility at . The complete facility is to be designed as per regulatory requirement, comply with the following cGMP critical parameters as prescribed in the URS: 1. Environmental conditions - Air Cleanliness Classification levels and Microbiological Levels 2. Non-Unidirectional air flow (Grade C & Grade D Area) 3. Temperature. 4. Relative humidity. 5. Differential pressure to provide assurance against contamination from lower grade environments.
2.0
SCOPE: Design, engineering, testing, validation and documentation of Low Side HVAC System comprising of the following main equipments: 1.
AHUs
2.
Supply air Terminal Filters
3.
Return air risers
4.
Instrumentation and Controls including Room side –Digital Indicators to maintain – room pressure differentials, Temperature & Relative Humidity.
5.
Volume Control Dampers & Fire Dampers
6.
GI Ducting, Duct thermal Insulation
7.
CHW MS Piping and Insulation
8.
Distribution of Chilled Water System comprising of piping valves, fittings.
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
3.0
RESPONSIBILITY:
3.1
VEPL
PAGE NO. 5 of 28 REV NO: R0
3.1.1 Design, Engineering & provide the complete technical details of the HVAC system 3.1.2 Documentation preparation. 3.1.3 To control work specification of sub contractor. 3.1.4 To control specification of all components. 3.1.5 Safety features & alarms. 3.1.6 Pre-installation requirements. 3.1.7 To ensure unauthorized or unrecorded design modification does not take place. 3.1.8 To confirm safe delivery of equipment to site. 3.1.9 Demonstration of design to comply with the requirement. 3.1.10 Project Manager / Project Engineer of VEPL are responsible for verifying the design specifications and Execution of the project. 3.2
HPPL.
3.2.1 Project Engineer is responsible for checking of the qualification documents 3.2.2 Formulation/Analytical services is responsible for review of the qualification documents 3.2.3 Technical services is responsible for review & approval of the qualification documents 3.2.4 QA is responsible for review and authorization of reports/qualification documents.
4.0
FACILITY DESCRIPTION
4.1
The HVAC system shall be designed to provide Air-conditioning and Ventilation for the following areas.
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 6 of 28 REV NO: R0
GRANULATION
MATERIAL OUT
MATERIAL IN
STAFF ENTRY
HVAC System AHU-09 is positioned in the Services Area, to cater conditioned and Filtered Air to GRANULATION, MATERIAL IN, MATERIAL OUT & STAFF ENTRY located in first Floor. Consideration is made to group rooms to form different zones to eliminate the possibility of cross contamination between different classes of clean zones. Each AHU shall cater to specified areas and the same is explained in the AHU zoning drawing (VEPL-HPPL-AHUZONEAHU-09).
Non-walk able ceiling shall be provided above the classified process areas. All the cutouts done for fixing HEPA filters shall be opened from clean room side for maintenance purpose. All the AHU’s has been placed in 2nd floor service area in the specific planned locations to keep minimum distance from usage area. Filtered and treated air from AHU-09 is fed to the air conditioning space of that particular zone by means of GI ducting. For all the classified areas, the supply air is provided from ceiling mounted HEPA filters, the return air shall be picked up from return air risers/space between two panels and collected in return air ducting and shall be taken back to the AHU-09. Supply air ducting shall be insulated with 13mm thickness and as well as return air ducting shall be insulated with 9mm & 13mm thickness (9mm Insulation for the ducts above ceiling, 13mm insulation for the ducts exposed to environmental conditions) insulation & shall be laminated with Aluminum foil for the exposed ducts in service area. The AHU Service area located at 2nd floor level. The Fresh Air for AHU-09 shall be taken from ambient. 5.0
STANDARDS & GUIDELINES a)
Centrifugal fans
IS 4894-1987 (Reaffirmed 1991)
b)
Propeller type A/C Ventilation Fans
IS 2312-1967 (Reaffirmed 1991)
c)
Horizontal Centrifugal Pumps for clear, cold & fresh water
IS 1520-1980
d)
Mild steel tubes, tubular & other wrought steel fittings
IS 1239-1990 Part I & II
e)
Galvanized Sheet Steel
IS 277-1992
f)
Metal Air Ducts fabrication and construction
SMACNA
DESIGN QUALIFICATION
g)
SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
Dimension of 3 phase foot mounted induction motors
PAGE NO. 7 of 28 REV NO: R0 IS 1231-1974
6.0
BASIS OF DESIGN PARAMETERS:
6.1
AREAS COVERED, ROOM AREA, HEIGHT & ROOM VOLUME: Room Name
6.2
Room Area in Ft2
False Ceiling Height Ft
Room Volume in Ft3
GRANULATION
273.44
8.69
2377
MATERIAL IN
50.32
7.87
396
MATERIAL OUT
56.51
7.87
445
STAFF ENTRY
43.86
7.87
345
OUT SIDE CONDITIONS
Season
6.3
Dry Bulb
Temperature Wet Bulb
Dew Point
Relative Humidity
Summer
96°F
78°F
71°F
45%
Monsoon
82°F
78°F
76°F
82%
Winter
58°F
54°F
51°F
78%
DESIGNED IN SIDE CONDITIONS:
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
Room Name
PAGE NO. 8 of 28 REV NO: R0
Temperature
R.H. %
22±20 c
NMT 45
GRANULATION MATERIAL IN MATERIAL OUT STAFF ENTRY
6.4
OCCUPANCY, EQUIPMENT LOAD, AREA CLASSIFICATION, DESIGN AIR CHANGES, ROOM AIR QUANTITY, TOTAL AIR QUANTITY & TOTAL COOLING LOAD REQUIREMENTS:
Room Name
Occupancy
Equip. Load
Number
KW
1
20
GRANULATION MATERIAL IN
6.5
Class
100K
MATERIAL OUT STAFF ENTRY
Area Classification
1
Design ACPH Number
Room Selected Total Cooling wise Air AHU Load Qty Capacity CFM TR CFM
30
3093
30
198
30
222
30
173
10TR
5050
DIFFERENTIAL ROOM PRESSURE GRADIENT: Sr. No.
Room Designation
Standard DP Range In mm wc 0.5-1.5 mm
From (High Pressure)
To (Low Pressure)
1
CORRIDOR-4
MATERIAL IN
2
CORRIDOR-4
MATERIAL OUT
0.5-1.5 mm
3
CORRIDOR-4
STAFF ENTRY
0.5-1.5 mm
4
STAFF ENTRY
GRANULATION
0.5- 1.5 mm
DESIGN QUALIFICATION
6.6
SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 9 of 28 REV NO: R0
TEMPERATURE AND HUMIDITY CONTROL: Temperature Control: Temperature Control is achieved by Cooling. Sensible & latent heat is removed from the Air Stream by the Chilled Water Cooling Coil in the AHU. Relative Humidity: Relative Humidity is achieved by providing Dehumidifier connected to AHU-09, part of humidified air coming from return air duct passing through dehumidifier, get dehumidified and dehumidified air will pass through AHU and respective rooms. Reduction of moisture content in air stream take place through chilled water cooling coil and dehumidifier, the conditioned air is delivered to the respective clean rooms through the insulated ducting system.
7.0
HVAC SYSTEM DESCRIPTION WITH TECHNICAL SPECIFICATION
7.1
HIGH SIDE SYSTEM All AC space in first floor shall be air conditioned by providing chilled water from a central chilling plant which generates chilling water at NMT (+) 7 °C temperature. The further network of the chilling line distribution shall be done at respective user points within proposed facility.
7.1.1
CHILLED WATER GENERATION SYSTEM Existing Chiller shall be used for this facility.
7.1.2
CHILLED WATER DISTRIBUTION To maintain the room temperature and RH, chilled Water is required to be supplied in all AHUs. Chilled Water from AHU returns back through pumps, strainers and butterfly valve to the chiller at a temperature 12°C and get cooled by rejecting its sensible heat to the refrigerant circulating in chillers and come out at the conditioned state of temperature at (+) 7 °C. This chilled water then circulated to AHU’s as per the load requirements. Circulation of Chilled Water from chiller to AHU’s is done through MS ‘C’ class IS–1239 piping. Chilled Water from chiller enters in to the AHU through butterfly valve/Ball Valve and Y strainer where dust / dirt particles are removed. This chilled water circulates through cooling coil of AHU made up of copper and gets hot by taking latent and sensible heat of the Return Air and Fresh Air entering in the AHU. This chilled water then enters to three ways mixing valve installed at the out let of AHU. The function of three way mixing valve is to regulate the flow of chilled water according to the temperature required inside the process
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 10 of 28 REV NO: R0
floor by means of actuator installed at the stem of valve and actuated by return air temperature sensor installed at return Air duct, which senses temperature of return Air. If the temperature inside process room goes above required design temperature it energize the motor inside the actuator that pulls the rod and open the orifice of the valve making direction of flow in such a way that chilled water circulates from AHU coils occurring more heat absorption and temperature reduction. Now if the temperature lowers down below required conditioned limits due to continuous heat absorption return air sensor sense and de energize the motor inside actuator which again push the rod and disc and closing the circuit of cooling coil, restricts the flow of chilled water from cooling coil and making the flow from bypass line which is connected between inlet and out let manifolds of the AHU. This chilled water then enters in to balancing valve that regulates pressure differential in the outlet line. Balancing valve consist of threaded stem, disc, one port before disc and another after disc. The purpose of balancing Valve is to regulate the chilled water flow rate across chilled water piping as per designed water flow rate with respect to cooling load requirement, ensuring adequate water flow across the pipe line. This chilled water then returns back to the chiller for further chilling process. This circulation of chilled water repeated through closed loop pipe network.
7.2
LOW SIDE SYSTEM In low side system, Air Handling Units, ventilation/exhaust units, piping, valves, Duct works, grilles/diffusers, HEPA filters, return air risers, insulation, instrumentation etc. shall be provided.
7.2.1
EQUIPMENTS AIR HANDLING UNIT TYPE The Air Handling Unit shall be double skin construction comprising of various sections such as mixing box, filter sections with filters, coil section with chilled water, supply air dampers, return air dampers, fresh air dampers, exhaust air dampers, blower section with imported blowers, pre filter, fine filter plenum, purge Pre filter plenum, discharge plenum with openings etc. as applicable. AHU HOUSING / CASING
Parameters
Specifications
Capacity
5050 CFM@160 mm of wc Static Pressure.
Over all Dimension
5239 L X 1450 W X 1150H in mm.
BLOWER Parameters
Specifications
Type / Model
BDB355T DRAUGHT FAN
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
M.O.C
PAGE NO. 11 of 28 REV NO: R0
Blower is made of G.I sheet
Capacity
5050 CFM
Static Pressure
160 mm WG Static Pressure
Speed
2874 RPM
MOTOR Parameters
Specifications
Rating/Pole
7.5 KW / 2 Pole
Speed in RPM
2916 RPM
COOLING COIL Parameter
Specification
Type
Chilled Water Cooling Coil
Coil Header Size
1.5” NB Copper Tube with M S End Connection
Coil Size and Face Area
1.1m x 0.92m & 10.89 Sqft.
No of Rows
8 Rows
Temp at inlet
(+) 7 + 1 °C
Temp at outlet
(+) 12 + 1 °C
CONDENSATE DRAIN DESCRIPTION: Condensate coming from cooling coil shall be collected in duly insulated SS drain pan and taken out of the AHU thru a Class ‘A’ GI piping to the nearest drain trap at service floor. A ‘U’ trap is provided in the drain circuit AHU to prevent air in/out from AHU thru drainpipe. A minimum of 1:100 slopes is maintained to ensure gravity flow of drain water. PRE FILTER :( G4) Parameters Filter Type MOC Frame / MOC Media Filter Size / Qty
Specifications Pocket Filter Aluminum / Synthetic Fiber 595Lx 595Wx400H mm / 2 No, 595Lx287Wx400H mm /2 No
FINE FILTER :( F8) Parameters
Specifications
Filter Type
Bag Filter
MOC Frame / MOC Media
Aluminum / Synthetic Fiber 595Lx 595Wx400H mm / 2 No, 595Lx287Wx400H mm /2 No
Filter Size / Qty
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 12 of 28 REV NO: R0
II. DE-HUMIDIFIER SPECIFICATIONS: Parameters
Specifications
DH MODULE
CCR – 100
CAPACITY
600 CFM
APPROX. DIMENSIONS
1470x1020x1130 MM
FRAME
CRCA POWDER COATED
PROCESS AIR FLOW
600 CFM
PROCESS MOTOR MAKE
SIEMENS
PROCESS MOTOR RATING/CURRENT
0.5 HP / 1.12 Amps.
PROCESS MOTOR SPEED
1400 RPM
PROCESS FILTER
470x280x75 MM – 10 MICRONS
REACTIVATION AIR FLOW
200 CFM
REACT. MOTOR MAKE
SIEMENS
REACT. MOTOR RATING/CURRENT
180 WATTS / 0.8 Amps.
REACT. MOTOR SPEED
2550 rpm
REACT. FILTER
260x250x75 MM – 10 MICRONS
DESICCANT ROTOR
470 DIA x 200 MM
HUMIDITY & TEMP. SENSOR
GALLTEC, GERMANY
PLC & HMI
MISTSUBISHI
LIMIT SWITCH
TECHNIC MAKE
PRESSURE SWITCH RANGE
(1 – 10 M BAR)
THERMOSTAT MAKE
ELCON 50 – 300 ◦ C
ELECTRICAL HEATERS
1.2KW x 12 Nos.
III. PRE - COOLING COIL TECHNICAL SPECIFICATIONS Parameters
Specifications
FRESH AIR CAPACITY
184 CFM
DIMENSIONS
600x600x550MM
MOC CASING
ALUMINUN PROFILES WITH 2MM THK
OUTER SKIN
0.63 MM PRE COATED & PRE PLASTIC
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 13 of 28 REV NO: R0
INNE SKN
0.63 MM PLAIN GI
INSULATION
PUFF WITH 23±2MM THK
PRE-COOLING COIL SIZE
10” x 10” x 8 ROW
COIL TUBE MOC/DIA
COOPER / 3/8” DIA
FIN MATERIAL
ALUMINUN 0.15MM THK
FILTER MAKE / TYPE / MEDIA/SIZE
AAF/ FLANGED / HDPE+NONOWEN+AL.MESH /305x305x75
EU CLASSIFATION / EFFICIENCY
EU 4 / 90% DOWN TO 10 MICRON
PRESSURE DROP
4-5 MM OF WC
FINAL PRESSURE DROP
12MM OF WC
DRAIN PAN MOC /THK/INSULATION
SS 304 / 1MM/12MM TORCELIN
DRAIN PIPE
SS 304 / DIA 25 MM
DAMPER MOC
GI POWDER COATING
DAMPER SIZE
9” x 9”
(REFER ATTACHED DE-HUMIDIFIER G.A DRAWING, PRE-COOLING COIL G.A DRAWING WITH TECHNICAL SPECIFICATIONS SHEET ATTCHED WITH THIS DOCUMENT.)
7.2.2 TERMINAL HEPA FILTERMODULES WITH PERFORATED GRILLS: Parameter
Specification
M.O.C HOUSING/GRILLS
Extruded Aluminum / SS 304
Room No/Name
Housing Size/Qty, Grill Size/Qty
GRANULATION
610Lx610Wx175Hmm/06 No’s, 680Lx680W mm/06 No’s
MATERIAL IN
610Lx610Wx175H mm/01 No’s, 680Lx680W mm/01 No’s
MATERIAL OUT
610Lx 610Wx 175H mm / 01 No’s, 680Lx680W mm/01 No’s
AIR LOCK
610Lx 610Wx 175H mm / 01 No’s, 680Lx680W mm/01 No’s
7.2.3 TERMINAL MINIPLEAT HEPA FILTERS: Parameter
Specification
MOC – Filter Frame / Media
Aluminum Anodized / Micro Glass Fiber Media
Type
Hooded type Mini pleat HEPA Filter in TM RSC module
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 14 of 28 REV NO: R0
Location Room No / Room Name
At Room Ceiling Size/Quantity
GRANULATION
580Lx580Wx124H mm / 06 No’s
MATERIAL IN
580Lx580Wx124H mm / 01 No’s
MATERIAL OUT
580Lx580Wx124H mm / 01 No’s
AIR LOCK
580Lx580Wx124H mm / 01 No’s
7.2.4 RETURN RISERS GRILLS WITH FILTERS: Parameter
Specification
MOC – Filter Frame / Media
Aluminum Anodized / Micro Glass Fiber Media
Type
Hooded type Mini pleat HEPA Filter in TM RSC module
Location Room No / Room Name
At Room Ceiling Size/Quantity
GRANULATION
780Wx380H mm/06 No’s, 745Wx345H mm/06 No’s,
MATERIAL IN
630Wx380H mm/01 No’s, 595Wx345H mm/01 No’s
MATERIAL OUT
630Wx380H mm/01 No’s, 595Wx345H mm/01 No’s
AIR LOCK
630Wx380H mm/01 No’s, 595Wx345H mm/01 No’s
7.2.5 AIR DISTRIBUTION Each Air Handling Unit shall consist of Return air damper, pre filter, and supply air fan with V-belt drive motor, cooling coil, fine filter, drain tray, supply air damper, return air damper, limit switch and other ancillaries. Return air- humidified air is being sucked in to the mixing chamber of AHU, where it is mixed with Fresh air. Fresh air is meant for makeup and to maintain indoor air quality. Mixed air is filtered thru pre filter (EU-4) and passed thru cooling coil, BDB355T DRAUGHT FAN blower is to be used for supplying air. Make up air changes for each room is considered according to the Room Data Sheet and AHU wise Airflow Schematic Drawing. In the HVAC system AHU (Air Handling Unit), dehumidified and filtered air supplied to maintaining required environment condition in the various area thru GSS ducting. Air distribution is enabled by Factory Fabricated GSS supply and return air ducts. The supply air duct joints are sealed with silicon sealant. Flange joints are provided with min 5mm thick Neoprene gasket Treated conditioned air is supplied in the room through HEPA filter / Diffuser installed at terminal in the Non-Walk able Ceiling. Airflow through each HEPA Filters/Diffusers is controlled by volume control damper. This circulation of airflow repeated continuously.
DESIGN QUALIFICATION
7.2.6
SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
REV NO: R0
DUCTING: Parameter
Specification
Fabrication
G.I. Sheet metal Ducting – Prefabricated ducts 24G (0.6MM), 22G (0.8MM), 20G (1.0MM) SMACNA standards
Duct Sizing Design
Duct Sizing Design done based on Air Velocity Method.
Duct size
As per duct layout attached.
Duct Leak Test Pressure Application
Through Smoke test at site
MOC
Joint Sealing: Flange joints Leak Testing
7.2.7
PAGE NO. 15 of 28
For distribution of conditioned air from air handling unit to The designated areas. Rubbers gasket & RTV sealant. Air supply with blower is to be blown in the duct & leak testing to be done by the duct smoke testing
DUCT WORK DETAILS I.
STANDARDS:
Unless otherwise specified here, the construction, erection, testing and performance of the ducting system shall conform to the SMACNA-1995 standards (“HVAC Duct Construction Standards – Metal and Flexible – Second Edition – 1995”-SMACNA). II.
CONSTRUCTION DETAILS:
All ductwork including straight sections, tapers, elbows, branches, shoe pieces, collars, terminal boxes and other transformation pieces must be factory-fabricated. Equivalency will require fabrication by utilizing the following machines and processes to provide the requisite quality of ducts and speed of supply: Coil lines to ensure location of longitudinal seams at corners/folded edges only to obtain the required duct rigidity and low leakage characteristics. No longitudinal seams permitted along any face side of the duct. All ducts, transformation pieces and fittings to be made on CNC profile cutters for required accuracy of dimensions, location and dimensions of notches at the folding lines. All edges to be machine treated using lock formers, flanges and roller for turning up edges. The fabricated duct dimensions should be as per approved drawings and all connecting sections are dimensionally matched to avoid any gaps. Ducts shall be straight and smooth on the inside. Longitudinal seams shall be airtight and at corners only, which shall be either Pittsburgh as per SMACNA practice, to ensure air tightness. Changes in dimensions and shape of ducts shall be gradual (between 1:4 and 1:7). Turning vanes or air splitters shall be installed in all bends and duct collars designed to permit the air to make the turn without appreciable turbulence.
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 16 of 28 REV NO: R0
The deflection of transverse joints should be within specified limit for rectangular duct deflection as given in SMACNA. Reinforcement of ducts shall be achieved by either cross breaking or straight beading depending on length of ducts. 7.2.8
DUCT INSULATION Parameter
Specification Nitrile Rubber / closed cell polyethylene elastomeric foam insulation with aluminum foil.
MOC Thickness of supply duct
13MM
Thickness of return duct
9MM/13MM
Thermal conductivity
0.029 to 0.035 W/m K at 230 C
Density
25 to 30 Kg/m3
Moisture absorption
Non hydroscopic
Temperature Range
-40°C to +115°C
Fire Performance/rating
Class 0 or Class 1
7.2.9 VOLUME CONTROL DAMPERS & FIRE DAMPERS: I. VOLUME CONTROL DAMPERS The dampers shall be zero leakage airfoil having thick extruded Aluminium frame sections and blades minimum 1.2 mm thick extruded aluminium airfoil. The bearing having heavy duty moulded nylon/bronze. The linkage shall be plated steel blade brackets, brass rollers and galvanised steel rods. Neoprene Rubbers Seals at tips of blades shall be provided. Stops shall be aluminium at head and sill. The motorised dampers shall be provided with motors and electrical wiring as required. Every damper shall have an indicating device clearly showing the damper position at all times.
Parameter Body Louvers Bush Size / Qty Type
Specification 16 G Aluminum sheet 16 G Aluminum sheet ALUMINUM 300 Hx300 L mm –9 No. Opposed blade
II. FIRE DAMPERS Return air duct in air handling units in main duct shall be provided with approved fire dampers of at least 90 minutes fire rating. Fire damper blades shall be one piece folded high strength galvanised steel construction. In normal position, these blades shall be gathered and stacked at
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 17 of 28 REV NO: R0
the frame head providing maximum air passage and preventing passing air current from creating noise chatter. The blades shall be held in position through fusible links. The thrust of the suddenly released tension shall instantly drive the blades down and keep it down without the use of springs, weights or other devices subject to failure. Fire damper sleeves and access doors shall be provided within the ducts in accordance with the manufacturer’s recommendations. Parameters
Specifications
Body
18 G GI sheet
Louvers
18 G GI sheet
Fire Rating
90 Minutes
Size/Qty (for return)
550L x 550W mm– 1 No
Type
Opposed blade
7.2.10 MAGNEHELIC GAUGES: Parameters
Specifications
Location
Air Handling Unit
Range
0-50 MM WC
Quantity
2 Nos.
Housing
Die cast aluminum case and bezel with acrylic cover
Accuracy
(+/-)2% of F.S
Dial size
4"
Process connection
1/8" NPT Female
7.2.11 TEMPERATURE, RELATIVE HUMIDITY & DIFFERENTIAL PRESSURE, INDICATORS
DIFFERENTIAL PRESSURE INDICATOR Parameters
Specifications
Location
IN AIR CONDITIONED AREA
Range
0 to 10mm WC
Quantity
1 Nos.
Power
24 Volts D.C Typical
Accuracy
±0.5% of F.S
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
Communication
PAGE NO. 18 of 28 REV NO: R0
Isolated RS485 Modbus RTU Protocol
DIFFERENTIAL PRESSURE, TEMPERATURE & RH INDICATOR Parameters
Specifications
Location
IN AIR CONDITIONED AREA
Range for Differential Pressure
0 to 10mm WC
Range for Temperature
0 to +50 OC
Range for RH
0.0 to 100.0 %RH
Quantity
3 Nos.
Power
24 Volts D.C Typical (250 Ma)
Accuracy for Differential Pressure
±0.5% of F.S
Accuracy for Temperature
±0.5 OC of F.S
Accuracy for RH
±1.8% for 10 to 95 %RH For Relative Humidity indicator
Communication
Isolated RS485 RTU Modbus Protocol
7.2.12 M.S. PIPING – CHILLED WATER: I MATERIAL OF CONSTRUCTION All chilled brine and hot water piping shall be MS C class as per IS 1239. II FABRICATION DETAILS The proper additional precautions shall be taken for vibration isolation of piping, passing through sensitive areas. Piping shall be properly supported or suspended from stands, clamps, hanger’s etc. as required. Each support will be isolated from supported pipe or fittings by anti-vibration springs or non-deteriorating and durable lines of rubber or neoprene.
Spacing of pipe supports shall not be more than that specified below: Nominal Pipe Size (mm)
Spacing (m)
12 and 15
1.25
20 and 25
2.00
32, 40, 50 and 65
2.50
80, 100 and 125
2.50
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 19 of 28 REV NO: R0
Spacing of pipe supports shall not be more than that specified below: 150 and above
3.00
Extra support shall be provided at the bends and heavy fittings like valves to avoid undue stresses on the pipes. Pipe hangers shall be fixed on walls and ceiling by means of metallic or expansion fasteners. Vertical risers shall be parallel to walls and column lines and shall be straight and plump. Risers passing from floor to floor shall be supported at each floor by clamp or collars attached to pipe with a 12 mm thick rubber pad. Risers shall also have suitable elbow or concrete pipe support at the lowest point. Pipe sleeves of 50 mm or larger diameter shall be provided wherever pipes pass through walls and the annular space filled with felt and finished with retaining rings. Insulated piping shall be supported in such a manner as not to put undue pressure on the insulation. All pipes using screwed fittings shall be accurately cut to the required sizes and threaded in accordance with IS: 554 and burrs removed before laying. Open ends of the piping shall be blocked to avoid entrance of foreign matter. Wherever reducers are to be made in horizontal runs, eccentric reducers shall be used. If the piping is to drain freely in other locations, concentric reducers may be used. Flanged inspection pieces 1.5 meters long, with bolted flanges on both ends, shall be provided not more than 30 meter centres, to facilitate future cleaning of all welded pipes. All buried pipes shall be cleaned and coated with zinc chromate primer and bitumen paint, then wrapped with three layers of fibreglass felt, each layer laid in bitumen. In General pressure tests shall be applied to piping only before connection of equipment and appliances. In no case shall piping, equipment or appliances be subjected to pressures exceeding their test ratings. Tests shall be completed and approved before any insulation is applied. After tests have been completed, the system shall be drained and cleaned of all dust and foreign matter all strainers, valves and fittings shall be cleaned of all dirt, filings and debris. HYDROSTATIC PRESSURE TEST – CHILLED WATER PIPING All water piping shall be tested and proven tight under hydro statistic pressure of 1.5 times of design pressure in Kg/cm². Unless stated otherwise in the specifications the prescribed pressure shall be maintained for four hours. The section sets out the general requirements for design, standards of workmanship, supply, at site, installation of pipes, pipe fittings and valves application, testing and balancing of all galvanised and steel water piping system for air-conditioning application. All piping inclusive of fittings and valves shall follow the applicable Indian Standards. III VALVES & FITTINGS a) BALL VALVES Parameter
Specification
Application
Flow Isolation
Size
Ø40 MM
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 20 of 28 REV NO: R0
Quantity
5 Nos.
Ball
OTTONE CW617N UNI EN 12165
b) BALANCING VALVES Parameter
Specification
Make
Advance valves
MOC
Cast Gun metal (IS 318 Gr. LTB2)
Application
Flow control
Size / Quantity
Ø40 MM / 1 No.
Hand Wheel
Nylon Gr. 66
Bonnet
IS 319 Brass
Stem
IS 319 Brass
End Connection Type
BSP Screwed End
c) Y- STRAINERS Parameter
Specification
Body/Cover
Cast Iron
Connecting Studs/Nuts
A-307,Grade B
Filter Screen
Stainless Steel Perforated Screen of 2-3mm Perforation X 24G
Flanges
Drilled As Per BS-10, ANSI,ASA Standards
Drain Plug
Stainless Steel -410
Size / Qty
Ø40 MM / 1 No
Application
Removal of solids/suspended particles in the main stream
d) DRAIN VALVES Parameter M.O.C Size & Quantity Application
Specification Brass Ø25 MM & 1 No. Removal of water condensate from drain line
e) AIR VENT VALVES Parameter
Specification
Body
OTTONE/BRASS CW 617 N
Float
Polyethylene Resin
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 21 of 28 REV NO: R0
Ring
NBR
Maximum Working Temperature
110°C
Maximum Working Pressure
10 bar
Threads
ISO228
Application
Removal of air in main stream
Size / Quantity
Ø20 MM / 1 No.
f) 3 WAY MODULATING MIXING VALVES WITH ACTUATOR Parameter
Specification
MOC
Brass
Operating voltage at power supply of AC 230V
AC 24V +/-20%
Operating Frequency
50Hz
Degree of protection of actuator
IP 54
Size
Ø32 MM
Quantity
1 No.
Application
Flow control for temperature modulation
7.2.13 CHILLED WATER PIPING - DRAIN U TRAP Parameter Pipe size Pipe MOC
Specification Ø40 MM
Quantity
1 Nos.
MS A Class Piping
7.2.14 CHILLED WATER PIPING INSULATION Parameter
Specification
M.O.C
Pipes are insulated with k-flex and aluminum outer layer.
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
Maximum & Minimum Surface Temperature
PAGE NO. 22 of 28 REV NO: R0
-40°C to +85°C
Fire
Euroclass B-s3, d0
Thermal Conductivity at +20° C
≤ 0.035 W/(m-K)
7.2.15 CHW PIPING PRESSURE GAUGES: Parameter Specification BAUMER Make MOC-Case ANSI 304 SS Range/Connection Size
0 to 10 Kg/Cm2 / 3/8 ” BSP
Size
4’(100 mm) dial type
Accuracy
+/- 1.0% of F.S
Quantity
2 Nos. (1 No. Each in Supply & Return header of CHW Manifold)
7.2.16 CHW PIPING TEMPERATURE GAUGES: Temperature gauge BAUMER MAKE MOC-Case
ANSI 304 SS
Range
0-50 Deg0C
Size
4’(100 mm) dial type
Accuracy
Class 1 as per EN-13190 : 1999
Quantity
2 Nos. (1 No. Each in Supply & Return header of CHW Manifold)
8.0 SAFETY CONSIDERATION: For Personnel Protection, there are following provisions.
9.0
8.1 open.
There are limit switches in the AHUs to make the system off when access doors are
8.2
All the electrical equipment grounded properly to prevent electrical shocks.
PERFORMANCE TESTING Performance of system shall be demonstrated at rest conditions. Non-viable counts shall be as per ISO standards 14644-Clean Room & Associated Controlled Environment. Viable counts shall be as per EU GMP & US FDA guidelines.
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 23 of 28 REV NO: R0
Latest edition shall be followed for testing and acceptance of the system. Following tests (minimum) shall be performed during system qualification.
ROOM TEMPERATURE Room temperature shall be controlled and monitored in the individual as per the room book data. It shall be monitored in the system.
RELATIVE HUMIDITY Relative humidity shall be controlled in the individual as per the room book data. It shall be monitored in the system.
DIFFERENTIAL PRESSURE
Differential pressure shall be controlled in the individual as per the room book data. It shall be monitored in the system. ACPH Room ACPH shall be calculated based on the individual filter CFM achieved. ACPH of individual room shall be as per the room book data.
FILTER INTEGRITY TEST Individual filter shall be checked as per the ISO 14644-3.
AIRBORNE PARTICULATE TESTING (NON-VIABLE PARTICLE COUNT) Sr. No.
ISO Classification
0.5µ/m3
5µ/m3
2.
ISO 5
3,520
29
3.
ISO 6
3,5200
293
4.
ISO 7
352,000
2,930
5.
ISO 8
3,520,000
29,300
At Rest
RECOVERY TEST Area required conditions shall be achieved within 15-20 minutes.
AIRFLOW VISUALIZATION TEST Airflow Visualization of non unidirectional clean rooms shall be performed through digital Videography of Airflow direction of individual clean rooms
10.0 ATTACHMENTS
G.A. DRAWING FOR AHU
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 24 of 28 REV NO: R0
HVAC ROOM DATA SHEET
AIR FLOW SCHEMATIC DIAGRAM
DUCT LAYOUT & AHU LOCATION LAY OUT
PIPING MANIFOLD DIAGRAM (CHILLED WATER) WITH DRAIN PIPING
TEMPERATURE, ROOM PRESSURE & AREA CLASSIFICATION ZONING
G.A DRAWING FOR DE-HUMIDIFIER
G.A DRAWING FOR PRE-COOLING COIL
TECHNICAL CALCULATION SHEET FOR DEHUMIDIFIER
11.0
ABBREVIATION
Abbreviation
Description
Abbreviation
Description
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 25 of 28 REV NO: R0
AHU
Air Handling Unit
MM WG
Millimeter Water gauge
CHW
Chilled Water
NA
Not Applicable
MM WC
Millimeter Water Column
HPPL
HIGHER PHARMATECH PVT. LTD.
cGMP
Current Good manufacturing practices
VEPL
Vindair Engineers Pvt. Ltd.
DQ
Design Qualification
Pa
Pascal
DP
Differential Pressure
QA
Quality Assurance
DWG.
Drawing.
RH
Relative Humidity
TR
Tonnage Refrigeration
URS
User Requirement Specification
CS
Carbon Steel
S.A
Supply air
GI
Galvanized Iron
R.A
Return air
VCD
Volume Control Damper
PTFE
Poly Tetra Fluoro Ethylene
HEPA
High Efficiency Particulate Air filter
MS
Mild Steel
MOC
Material Of Construction
FS
Full Scale
DESIGN QUALIFICATION
12.0
SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 26 of 28 REV NO: R0
SUMMARY REPORT:
………………………………………………………………………………………………………………................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... .......................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................................................... ....................................................................................
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 27 of 28 REV NO: R0
13.0 CONCLUSION: -
Concluded By: For VEPL
For HPPL
Name:
Name:
Sign:
Sign:
Date:
Date:
DESIGN QUALIFICATION SYSTEM NAME
AIR HANDLING UNIT
SYSTEM NUMBER
AHU-09
DOCUMENT NO
VEPL/HPPL/DQ/S09
PAGE NO. 28 of 28 REV NO: R0
14.0 AHU DESIGN QUALIFICATION APPROVAL SHEET VEPL Name
Designation
Signature
Date
Designation
Signature
Date
HPPL Name