Analysis Of Steel Moment Connections

  • Uploaded by: Dhana Durai
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Analysis Of Steel Moment Connections as PDF for free.

More details

  • Words: 782
  • Pages: 30
Loading documents preview...
Analysis of moment connections

Basic principles of connection design • Provide as direct a load path as possible • Avoid complex stress conditions • Weld in the shop, bolt on site

Welded connections

Moment connection of an I-Beam

• Bending moment is carried mainly by the flanges • Therefore connect flanges for moment transfer

M

Moment connection of an I-Beam

• Welded connection C=T • Fillet welds • Full penetration welds • Compression transfer d can also be accomplished through direct bearing

Resultant tension force T = M/d

M

Shear connection of an I-Beam • Shear is carried mainly by the web • Therefore connect the web for shear transfer

V

Shear connection of an I-Beam • Fillet welds in shear are commonly used • Connect entire web and adjust weld size to suit shear load

V

Moment connection of a plate Stress in weld σ = M (d/2) / I = M (d/2) / (ad3/12) [kN/m2] q =σa = M (d/2) / (d3/12) = M (d/2) / I’ [kN/m] Where I’ = I/a

M d

Then choose a weld size a that will carry q q = σ.a where a = weld size

Moment connection of a plate Can also use simplified approach: • Break moment into a force couple • Choose a suitable weld size • Then calculate the required length of the weld to carry the tension force T

C=T

Resultant tension force T = M/d

M d

q = T/l where l = weld length

Welded shear plate V V Centroid of weld group

e

M = V.e

Simplified approach • Break eccentric load up into a vertical force along the vertical weld and a pair (couple) of horizontal forces along the horizontal welds • Then choose lengths of welds to carry the calculated forces

V.e’/d V d

V

V.e’/d e’

“Stress” calculations

V

V

+ M = V.e

M = V.e

“Stress” calculations for vertical force V qV

V

Divide shear equally amongst all the weld lines q = V / (total length of weld) Choose a weld size that can carry the “stress” q Note q is actually a force per length [kN/m]

“Stress” calculations for Moment M = V.e xB

xA

Treat the weld group as a crosssection subjected to a torsional moment

A qAx qAy qAM

yA

qAx = M yA / I’p qAy = M xA / I’p

M = V.e qBy

qBM qBx

yB

B

I’p2 = I’x2 + I’y2 where I’ = I/a

qAM = (qAx2 + qAy2)0.5 Similarly for point B Then select weld size for max. q

“Stress” calculations for combined V and M A

qAx

qAy V

qAV qA M = V.e

B

Combine the weld “stress” components from the vertical force and the torsional moment

qA = [qAx2 + (qAV + qAy)2]0.5 Similarly for point B or any other point that might be critical Then select weld size for the maximum value of q

Example of a complex connection

Column tree for Times Square 4, NYC

Bolted connections

Moment splice in a column

Moment splice of an I-Beam • Bolted connection C=T • Divide tension and compression resultant equally between bolts

M d

Resultant tension force T = M/d

Shear connection in bridge diaphragm girder (Alex Fraser Bridge)

Shear connection of an I-Beam • Bolted connections to transfer shear are commonly used • Connect entire web to avoid stress concentrations and shear lag

V

End plate Coped flanges to fit in between column flanges

Shear connection via end plate

Moment connection with and end or base plate

Moment connection with fully welded end plate Tmax

Ti = Tmax (hi / hmax) Ti

M = Σ Ti hi

hmax hi

C = Σ Ti

M

Pre-tensioned moment connection

Pre-tensioned Moment Connection Apply both tension and compression forces to pretensioned bolts. Compression force can be seen as a release of the tension force.

Ti

+ TM

M

=

M

Bolted shear plate e

P P

Centroid of bolt group

M = Pe

Vertical load VP

P

Divide the force by n, the number of bolts VP = P / n

VP

Moment xi

Treat the bolt group as a cross-section subjected to a torsional moment

bolt i

FxM ri

FyM

FMi

M

bolt area A

yi

Ip = Σi A ri2 = Σi A (xi2 + yi2) and with I’P = IP/A FxM = M yi / I’p FyM = M xi / I’p FMi = (FxM2 + FyM2)0.5 Then select a bolt size for the maximum force FM

Combined vertical force and moment FxM FyM

P

Fmax

VP

M = Pe

Fmax = [FxM2 + (FyM + VP)2]0.5 Then select a bolt size for the maximum force Fmax

Related Documents


More Documents from "Sanjay Rao"