Loading documents preview...
BRIDGE FOUNDATION DESIGN Siva Theivendrampillai Sivakumar Principal Engineer (Geotechnical)
Geotechnical Branch
Overview Brief Discussion on: • Foundation Type • Foundation Design • Pile Load Testing • Approach Embankment to Bridge
2
TMR-Specifications • • • •
Cast-in-Place Piles – MRTS63 and 63A Driven PSC Piles – MRTS65 Driven Steel Piles –MRTS66 Dynamic Testing of piles—MRTS68
• Project Specific- Geotechnical Design Standard – Minimum Requirements 3
Basic Foundation Types • Shallow Foundations ¾ Bearing
strata at shallow depths
• Deep Foundation (Piles) ¾ Deeper
bearing strata
Driven Piles Cast-in-Place Piles
4
Basic Foundation Types
SHALLOW FOUNDATIONS
5
6
When can we use Shallow Foundations? When Surface strata are: • Strong ( Adequate bearing capacity and no settlement issues). • Not vulnerable to Scour • Non-expansive • Low ground water level
7
Shallow Foundation Design – Things to Consider
• Concentric / Eccentric Loading • Overturning moment • Sliding • Global Stability ( esp. footing on / adjacent to slope)
8
Basic Foundation Types
DEEP FOUNDATIONS - PILES
9
When do we need piles? • When surface strata are ¾ ¾ ¾ ¾
Weak Compressible Erodable Expansive
• To resist flood, earth pressures ¾ ¾ ¾
Lateral loads Uplift loads Overturning loads 10
Pile Use: Transfer load through surface strata which may be weak, compressible, expansive etc.
11
Pile Use: For resisting lateral loading
12
Pile Use: For resisting uplift
13
Pile Use: Support against scour or lateral loading due to excavation
14
Pile Use – Further example of lateral support for deep excavation induced lateral loading
15
Deep Foundations - Pile Types • Driven piles ¾ ¾
Displacement piles Soil is ‘displaced’ within the adjoining soil mass (displaced volume ≈ pile volume)
• Cast-in-place piles or Bored piles ¾
Non-Displacement piles
¾
Soil is removed
¾
The excavation may or may not be supported 16
Driven Piles - Types and basic requirement in design • Types ¾
¾ ¾ ¾
Octagonal Prestressed Concrete (PSC) Reinforced Concrete (RC) Steel “H Pile” Timber Piles
• Limitations on maximum length 17
DRIVEN PILES
PSC Piles in use at Wetheron Creek Bridgesite 18
Pile Driving Frame
19
SITE INVESTIGATION FOR DRIVEN PILES
1. Soil strength and stiffness 2. Soil chemical analysis ⇒ corrosion/aggressiveness 3. Possible obstructions to installation 4. Potential for damage to adjoining structure due to “ground heave” 5. Vibrations
20
Driven Piles • Will refuse in SPT N>50 material • Loads: e.g.,550mm PSC working 1500kN • Settlement: ~ 10 mm • Vulnerable to: ¾
Lateral movement / Negative skin friction
¾
Excess vertical settlement
• Drive after construction of approach embankments 21
Example of Negative Skin friction
22
Bored or Cast-in-place Piles • Types ¾ ¾ ¾ ¾
Short bored piers Cylinders on rock Cylinders socketed into rock** Belled sockets Bedrock
• Bored piles ¾
Could be up to 4 x cost of driven pile 23
Bored Piles - Construction • Bored piles are cast in place cylindrical piles • Excavated by
Augers
Buckets
Large drill bit (for hard rock)
Chisel grab and casing oscillator for bouldery ground, etc.
24
Bored Pile Excavation- Augering
25
Bored Pile Excavation - Bucket Cleaning Bucket
Drilling Rig Excavation Bucket
26
Bored Piles – Cylinders Socketed into rock
Rock Sockets
Rock Sockets • • • • •
High compression loads Greater resistance to lateral movement Socket length 2 to 5 x diameter Diameter from 900mm to 1800mm High strength rock ¾ Point
Load (Is50 > 1 MPa) ¾ Rock anchors preferred to resist large uplift loads 28
Rock Sockets • May need casing in overburden soils and XW rock (SPT N<50) • Sealing/control of groundwater important • Capacity to take heavy loads dependent on extremely clean socket bases – inspection important (WH&S) • More expensive - so fewer, larger piles may be more economical 29
Loads on Bridge Foundations Structural Engineer to advise, consists of but not limited to •
Vertical Compressive (Dead + imposed) loads
¾ Imposed Loads ¾ + ½ Dead Load – highway bridges ¾ + 2/3 Dead Load – railway bridges • Vertical Uplift ¾
flood loads in transverse direction 30
Loads on Bridge Foundations • Horizontal Loads ¾
braking force of vehicle in longitudinal direction
¾
flood loads in transverse direction
¾
Earthquake
• Horizontal Loads create Bending Moments 31
Selection of Foundation Type What influences the decision for driven or bored piles? The following factors will influence the choice of foundation type: 9 Loads 9 Environment 9 Logistics
and
9 Geology
32
Selection of Foundation Type: Loads • Structural Loads ¾
Heavy compressive loads from large spans
• Hydraulic Issues ¾
Lateral and uplift loads from flood loading
¾
Scour in loose sands and silts
33
Selection of Foundation Type: Environment
• Vibration ¾ ¾ ¾
proximity to people vulnerable structures damage to services
• Aggressiveness due to groundwater • Obstructions ¾
overhead power lines / headroom
34
Selection of Foundation Type: Logistics • Transporting fresh concrete in western Queensland ¾
Distance and temperature
• Availability/Transporting PSC piles ¾
Max length around 25 – 27m
• Quality of access roads • Accessibility at foundation locations ¾
Crane pads, piling rig pads 35
Selection of Foundation Type: Geology • Depth to competent strata • Obstructions to pile driving ¾
Coffee rock (Indurated Sand)
• Steeply dipping bearing strata ¾
Basalt flows
• Interbedded rock types with different properties 36
Selection of Foundation Type: Geology • Compressible deposits • Defects with soft infills • High head of groundwater ¾
Sealing issues
¾
Hole stability
¾
Concreting
• Rock excavatability 37
Coffee Rock (Indurated Sand)
38
Steeply Dipping Bearing Strata
39
Pile Design - Approaches PILE DESIGN THEORY
Engineering Geology Soil Mechanics Rock Mechanics Structural Mechanics
EMPIRICISM
To account for various methods of pile installation
EXPERIENCE
Regional (geology + local construction practices)
FIELD LOADING TESTS Static Dynamic
Design Stage
Construction Stage
40
PILES - design The following aspects should be considered in design: 1. Load carrying capacity (Geotechnical Engineer) - strength and stiffness ⇒ “serviceability” 2. Pile material strength (Structural Engineer) 3. Pile material durability (Structural Engineer)
41
Pile Design - Geotechnical The following DESIGN ELEMENTS should be accounted for in design:
• Foundations: ¾ ¾ ¾ ¾
Load capacity Settlements Lateral Fixity Uplift resistance
• Scour Issues ¾
Land/water structures
• Approaches ¾ ¾
Stability Settlements
• Interaction ¾ ¾
Abutments Widening/ duplication 42
Pile Capacity • Q
= Pile Capacity
Q
• Qend = End Resistance • Qshaft = Shaft Resistance • Q
Qshaft
= Qend + Qshaft Qend 43
End versus Shaft Bearing Piles • Pile in Clay
• Pile in Sand
Qshaft
Qend = 5-10% Qshaft
End Bearing Pile
Qshaft
Qend
Qshaft
Qend 44
Ultimate load
Low load
fs = τ max fs = τ max
fs << τ max
Base resistance, fb, mobilized
for the full length
45
Driven Pile Capacity
Design of Piles Traditional Approach Ultimate Geotechnical Capacity = Ult. Skin Friction + Ult. End Resistance Allowable Geotechnical Capacity = Ult. Skin Friction/1.5 + Ult. End Resistance/3.0 OR
Allowable Geotechnical Capacity = Ultimate Geotechnical Capacity/2.5 The allowable geotechnical capacity should be compared with design load (unfactored) from the structure. 47
Design of Piles Limit State Design (e.g AS2159) Rug (Ultimate Geotechnical Capacity) = Ult. Skin Friction + Ult. End Resistance Rg* (Design Geotechnical Capacity) = Ф x Rug Rg* >= N* or S*
(Design Action Effect or Ultimate Design Load)
Rg* should be compared with ultimate design load (not driving capacity or structural capacity) 48
Load and Settlement- (idealized) (600 mm, 10 m long bored pile in stiff clay)
PILE DESIGN – WIDELY ACCEPTED BEHAVIOUR Increasing unit base or shaft resistance Pile NONDISPLACEMENT Drilled shafts Micropiles in soils
CFA (Auger cast)
PARTIAL DISPLACEMENT H-Piles Open-ended pipe piles (in some soils)
FULL DISPLACEMENT Precast concrete Closed-ended pipe piles Open-ended pipe piles (in some soils) Franki
Spectrum of soil displacement caused by pile installation and Its relationship to bearing capacity.
2nd Session • Pile Load Testing • Site Investigation – Need to get it right • Design Elements – Stability and Settlement at Bridge Approaches • Selection of Design Parameters • Design Charts – for estimating shaft resistance and settlement of piles
51
Pile Load Test • Why Pile Load Test ¾
Derivation of design parameter
¾
Verification of design load or pile carrying capacity
• MRTS63 Requires that at least 10% of piles at a site to be tested • Common methods of pile load test ¾
Static Load Test (Kentledge or Reaction Piles)
¾
Dynamic Test (PDA with CAPWAP) 52
Static Load Test Kentledge
Reaction Piles
53
Kentledge Set up for Static Pile Load Test
54
Static Load Test – Further example of Kentledge
55
Dynamic Load Test – Pile Driving Analyser (PDA) • The PDA system consists of ¾
Two strain transducers (to measure strain/force)
¾
Two accelerometers (to measure velocity)
Attached to opposite sides of the pile (near the top of the pile).
• The measured force and velocity at the pile top provide necessary information to estimate soil resistance and its distribution. 56
PDA – Set Up
57
Typical arrangement of PDA - Schematic
58
Force & velocity wave traces recorded during initial driving and restriking
59
Load-settlement Behaviour
Test Pile: Predicted versus Measured Performance
Site Investigation - Need to get it right
• What can go wrong? • How can we manage undue contractual claims as well as save construction time • Limited investigation can be disastrous as this could lead to undue claims • Example – Six Mile Creek, Central Qld
62
Six Mile Creek, Central Qld
63
Six Mile Creek – Footing Plan Area
64
Six Mile Creek: Additional Investigation-DCP
65
Six Mile Creek - Footing Excavation
66
Six Mile Creek: Footing re-design
67
Design Element – Stability and Settlement at Bridge Approaches
• Stability • Settlement
68
Different Origins that could Lead to Formation of Bump at the Approaches to a Bridge
69
Abutment Stability and Settlement • Compression of Natural Soil Due to Embankment Load • What are compressible Soils? ¾ Soft
clays (SPT N = HW to 6 or Su <25kPa)
• Where can we find soft clays (compressible soils)? ¾ Old
River Channels ¾ Paleo-channels (very dangerous) 70
Paleo-channels • GUP, near Schultz canal • From old topography maps and airphotos
Abutment Stability and Settlement
•
Paleochannels
Old buried channels from previous creek routes
Deposits of softer younger alluvium
Can be difficult to identify
Create a sudden change in ground conditions 72
Paleo-channels – Long Section
10 – 15m soft clay
Abutment Stability and Settlement • Risks associated with soft clays ¾Embankment stability and settlement ¾Structures (damage, bumps) ¾Pavements Deterioration - unevenness ¾Retaining wall foundations ¾Construction delays ¾Construction access 74
Abutment Stability: Soft Clay Issue Slip Failure - Schematic
75
Abutment Stability and Settlement: Soft Clay Issue
76
Abutment Stability and Settlement: Soft Clay Issue, Bump at Bridge Approach
Vertical Settlement 77
Abutment Stability and Settlement: Soft Clay Issue, Differential Settlement
78
Abutment Stability and Settlement: Typical Examples on Projects in South East Queensland
• Gateway Arterial @ Bald Hills Creek • East – West Arterial @ Pound Drain • Ipswich Motorway – BR340 @ Dinmore
79
Gateway Arterial – Bald Hills Creek, Stability
Gateway Arterial - Bald Hills Creek • 3m high embankment • 100m failure during construction • Boreholes 150m apart
Bald Hills Creek - Mitigation Strategy • Stability failure reinstated with timber piled raft • Abrupt differential settlement between embankment sections
Embankment on piles didn’t settle
Embankment on natural did (4-5mm /month)
82
Bald Hills Creek, Settlement
≈ 150 mm predicted in 1986 by consultant ≈ 800 mm by Jul 98
East – West Arterial @ Pound Drain
East – West Arterial @ Pound Drain • Damaged by lateral loading on piles from the approach embankment • Differential settlement also ¾Loads on abutment piled foundations ¾Interaction effects on adjacent structures ¾Functionality of drainage structures ¾Problems at relieving slab and pavement 85
Ipswich Motorway - Bridge BR340, Stability •
Number of Spans = 3
•
Span Length = 13m, 18m & 13m
•
Bridge Spillthrough Embankment 9m high with batter Slopes 1(H):1(V)
•
Number of Piles at Abutments = 3 Spaced at 6.5m c/c
•
Number of Piles at Piers = 5 Spaced at 3.3m c/c
86
Ipswich Motorway - 2009 Approach embankment failed. Cracks in embankment plus Pier piles displaced.
87
Risks Associated with Soft Clays – Managing Stability and Settlement
• How can we manage stability and settlement
88
Overview of Management Strategies
Light-weight Fill
Stone Columns
Embankment on Piles
Vacuum Preload
Partial Replacement
Stage Construction
Reinforced Embankment
Total Replacement
Temporary Surcharge Counter Berms
Height reduction.
89
Vertical Drains
SELECTION OF DESIGN PARAMETERS • SOILS • ROCKS
90
Soils CLAY
SAND
Soft
Stiff
CPT
SPT
UU
SPT: Standard Penetrometer CPT: Cone Penetrometer CPTu: Piezocone UU: Triaxial VS: Vane Shear Test
CPT
CPTu
UU
VS
Oedometer Consolidation 91
Selection of Design Parameters : CPT
CPT Sands / Stiff Clays
fs Shaft resistance
qc End bearing resistance
92
Selection of Design Parameters : CPTu CPTu
Soft Clays
qc Su (Undrained Strength for stability)
u Cv (Rate of settlement)
Fs/qc/u Drainage lenses 93
Selection of Design Parameters : Su Undrained Strength
Soft clay
Stability
Stiff Clay Shaft Resistance End Bearing 94
Selection of Design Parameters: Rock XW/HW
Visual
SPT
MW/SW
Point Load
Visual
USC
Point Load
Pressure -meter
95
Selection of Design Parameters: Rock Tests Point Load (Is)50
UCS
Pressuremeter
HW/MW/ SW/Fr Shaft Resistance End Bearing
CNS
MW/SW/Fr
Settlement of Sockets
Shaft Resistance 96
Design Charts (after Poulos) • Design charts for the estimation of shaft resistance and settlement of piles ¾Driven Piles ¾Bored Piles
97
Shaft Resistance
98
Settlement
(Poulos 1989)
Settlement
(Poulos 1989)