DAILY ACTIVITY REPORT (MECHANICAL- CPP) SL NO.

1

PACKAGE

CHP

EQUIPMENT CENTRE

ACTIVITY AT SITE

PRIMARY CRUSHER/COAL SHED

Monorail beam erection work in progress &rafter bracing erection in progress

TRANSFER HOUSE 1

Sheeting work started&final welding in progress

TRANSFER TOWER 2

No activity

CONVEYOR 1A & 1B

Gallery-5 welding completed & idler frame erection work in progress

CONVEYOR 2A &2B

Trussel TR-3 chequered plate for flooring erection in progress & floor beams final welding in progress.

DATE-17.08.1

2

BOILER & ESP

CONVEYOR 3A &3B

No activity

CONVEYOR 4A & 4B

No activity

CONVEYOR 5A & 5B

No activity

SECONDARY CRUSHER HOUSE

One no.Primary screen received from Hari Machines

BOILER -I STRUCTURAL

Completed

PRESSURE PART

Completed

ROTATING EQUIPMENTS

Completed

HOT AIR PATH

Completed

COLD AIR PATH

Completed

FLUE GAS PATH

Sand filling for RDO in progress.Ducting support for drag chain feeder welding work in progress.

FUEL PATH

Completed

INSULATION

SA FAN delivery side duct insulation In progress. Insulation work of MDC in progress

ESP

Placing of insert plates &checking completed ready for casting.

BOILER -II

STRUCTURAL

Bunker welding in progress. Erection of ID fan monorail structure in progress.Erection of bed material &lime stone outlet chute in progress.

PRESSURE PART

DM water filling for internal hydro.Erection of piping support for drain line & feed water line in progress.

ROTATING EQUIPMENTS

id fan foundation modification in progress & foundation work for PA & SA FAN in progress.

HOT AIR DUCTING

No activity

COLD AIR DUCTING

Erection of secondary air ducting work started with 80T Crane placed outside the foundation area under pressure from RFTL.

3

LP PIPING

FLUE GAS DUCTING

ID FAN ducting erection &welding work in progress. Erection of economiser casing started.Connecting duct from boiler to economiser work in progress.

FUEL PATH

burner ducting completed & MDC welding in progress.

INSULATION

No activity

ESP

Emitting electrode erection in progress & hopper erection in progress.

RAW WATER PUMP HOUSE

Side sheeting work completed.

CLARIFIER WATER PUMP HOUSE

No activity

CW AND ACW PUMP HOUSE

Erection of remaining 4 nos of columns completed.

UTILITY WATER PUMP HOUSE

No activity as monitoring basin work yet to start.

COMPRESSOR HOUSE

Pipe headers of all conveying compressors erection completed.Erection of instrument air pipe line in progress.

FIRE FIGHTING SYSTEM LDO SYSTEM

No activity

PIPE RACK

Fabrication of racks between clarified water pump house &main rack, in progress. Doubling with welding on pipe rack in progress.

250 mmcooling water makeup pipeline erection in progress ,400mm ACW pipe FABRICATION &ERECTION OF PIPING painting wrapping in progress & fabrication of 300NB Bend completed.

4

5

COOLING TOWER

TG BUILDING

FANS ,GEAR BOXES PROPELLER SHAFT & STRUCTURALS

No activity

DISTRIBUTION PIPE LINES

No activity

DRIFT ELIMINATORS & SPLASH GUARDS

No activity

STRUCTURAL

Staircase erection in progress.Chipping work for staircase head room work in progress.

TURBINE

No activity

TURBOGENERATOR

No activity

CONDENSER

Expansion of tubing in progress

AUXILLARIES

Erection of Condensate float tank to be taken up.

Fabrication of boiler feed FABRICATION &ERECTION OF PIPING pump delivery line taken up

6

ASH SILO

LUBE OIL SYSTEM

Overhead oil tank erection completed.

AC DUCTING WORK

Insulation work of 10.5 M control room roof in progress. Duct fabrication nearing completion.

STRUCTURAL

Staircase erection in progress

7

WATER TREATMENT PLANT

ERECTION OF EMBEDED PLATES & OPENING

Insert plates for hopper liner plate have been completed & placing of edge angle for opening in progress.

ASH HANDLING EQUIPMENT

No activity

ASH TRANFER PIPE LINE

Insert plates for pipe line fixing progress .

STRUCTURAL

Completed

EQUIPMENT ERECTION

Electrical panels received at site

FABRICATION &ERECTION OF PIPING

DM Water production in progress for boiler-II hydro test.

CHEMICAL HOUSE

Truss erection work completed

MANPOWER DETAILS SL NO

CONTRACTOR

MANPOWER

1

22

2 3 4 5

GIRI CONSTRUCTIONS (HAZEMAG) THERMAX GPR APT SUVENDU SAHU

220 18 20 12

6

JOSEPH CONSTRUCTIONS

8

DATE-17.08.13 PLANNED FOR TOMORROW

REMARK

Same to continue

Hoppers, railings & chutes for feeder breaker awaited at site

Same to continue

All matreials received at site

16 TON materials have not been despatched by party despite of repeated reminders.They are emphasising on payment.

Same to continue

Same to continue

Civil foundation work yet to be completed

Trussel fabrication completed & gallery to be received.party not despatching further materials despite of repeated reminders.

Material not received at site Civil work yet to be completed

Same to continue

Same to continue

Same to continue

Same to continue

Same to continue

Erection work awaiting completion of fan foundation.

Same as above

Same to continue

Same to continue Insulation work to start after hydro test.

Same to continue

clearing of raw water pump house area for starting of vertical pump erection. Purlins still awaited.

allignment of columns to be completed

Purlins still awaited.

Same to continue

No activity

Same to continue

Civil foundation work to start.fabricated tank awaited at site

400mm ACW pipe painting wrapping to continue & fabrication of bends inside cooling tower forbay ot be done.

No activity

Civil work yet to be completed & mobilisation to be started by Paltech

No activity

same as above

No activity

same as above

Same to continue

Same to continue

Same to continue

Same to continue

Same to continue

Same to continue

All other available equipments have been placed in position.

Same to continue

Same to continue

No activity

Erection of remaining small pumps to be taken up during erection of panels

Same to continue

No activity

Purlin erection to start after gable wall completion.