DAILY ACTIVITY REPORT (MECHANICAL- CPP) SL NO.
1
PACKAGE
CHP
EQUIPMENT CENTRE
ACTIVITY AT SITE
PRIMARY CRUSHER/COAL SHED
Monorail beam erection work in progress &rafter bracing erection in progress
TRANSFER HOUSE 1
Sheeting work started&final welding in progress
TRANSFER TOWER 2
No activity
CONVEYOR 1A & 1B
Gallery-5 welding completed & idler frame erection work in progress
CONVEYOR 2A &2B
Trussel TR-3 chequered plate for flooring erection in progress & floor beams final welding in progress.
DATE-17.08.1
2
BOILER & ESP
CONVEYOR 3A &3B
No activity
CONVEYOR 4A & 4B
No activity
CONVEYOR 5A & 5B
No activity
SECONDARY CRUSHER HOUSE
One no.Primary screen received from Hari Machines
BOILER -I STRUCTURAL
Completed
PRESSURE PART
Completed
ROTATING EQUIPMENTS
Completed
HOT AIR PATH
Completed
COLD AIR PATH
Completed
FLUE GAS PATH
Sand filling for RDO in progress.Ducting support for drag chain feeder welding work in progress.
FUEL PATH
Completed
INSULATION
SA FAN delivery side duct insulation In progress. Insulation work of MDC in progress
ESP
Placing of insert plates &checking completed ready for casting.
BOILER -II
STRUCTURAL
Bunker welding in progress. Erection of ID fan monorail structure in progress.Erection of bed material &lime stone outlet chute in progress.
PRESSURE PART
DM water filling for internal hydro.Erection of piping support for drain line & feed water line in progress.
ROTATING EQUIPMENTS
id fan foundation modification in progress & foundation work for PA & SA FAN in progress.
HOT AIR DUCTING
No activity
COLD AIR DUCTING
Erection of secondary air ducting work started with 80T Crane placed outside the foundation area under pressure from RFTL.
3
LP PIPING
FLUE GAS DUCTING
ID FAN ducting erection &welding work in progress. Erection of economiser casing started.Connecting duct from boiler to economiser work in progress.
FUEL PATH
burner ducting completed & MDC welding in progress.
INSULATION
No activity
ESP
Emitting electrode erection in progress & hopper erection in progress.
RAW WATER PUMP HOUSE
Side sheeting work completed.
CLARIFIER WATER PUMP HOUSE
No activity
CW AND ACW PUMP HOUSE
Erection of remaining 4 nos of columns completed.
UTILITY WATER PUMP HOUSE
No activity as monitoring basin work yet to start.
COMPRESSOR HOUSE
Pipe headers of all conveying compressors erection completed.Erection of instrument air pipe line in progress.
FIRE FIGHTING SYSTEM LDO SYSTEM
No activity
PIPE RACK
Fabrication of racks between clarified water pump house &main rack, in progress. Doubling with welding on pipe rack in progress.
250 mmcooling water makeup pipeline erection in progress ,400mm ACW pipe FABRICATION &ERECTION OF PIPING painting wrapping in progress & fabrication of 300NB Bend completed.
4
5
COOLING TOWER
TG BUILDING
FANS ,GEAR BOXES PROPELLER SHAFT & STRUCTURALS
No activity
DISTRIBUTION PIPE LINES
No activity
DRIFT ELIMINATORS & SPLASH GUARDS
No activity
STRUCTURAL
Staircase erection in progress.Chipping work for staircase head room work in progress.
TURBINE
No activity
TURBOGENERATOR
No activity
CONDENSER
Expansion of tubing in progress
AUXILLARIES
Erection of Condensate float tank to be taken up.
Fabrication of boiler feed FABRICATION &ERECTION OF PIPING pump delivery line taken up
6
ASH SILO
LUBE OIL SYSTEM
Overhead oil tank erection completed.
AC DUCTING WORK
Insulation work of 10.5 M control room roof in progress. Duct fabrication nearing completion.
STRUCTURAL
Staircase erection in progress
7
WATER TREATMENT PLANT
ERECTION OF EMBEDED PLATES & OPENING
Insert plates for hopper liner plate have been completed & placing of edge angle for opening in progress.
ASH HANDLING EQUIPMENT
No activity
ASH TRANFER PIPE LINE
Insert plates for pipe line fixing progress .
STRUCTURAL
Completed
EQUIPMENT ERECTION
Electrical panels received at site
FABRICATION &ERECTION OF PIPING
DM Water production in progress for boiler-II hydro test.
CHEMICAL HOUSE
Truss erection work completed
MANPOWER DETAILS SL NO
CONTRACTOR
MANPOWER
1
22
2 3 4 5
GIRI CONSTRUCTIONS (HAZEMAG) THERMAX GPR APT SUVENDU SAHU
220 18 20 12
6
JOSEPH CONSTRUCTIONS
8
DATE-17.08.13 PLANNED FOR TOMORROW
REMARK
Same to continue
Hoppers, railings & chutes for feeder breaker awaited at site
Same to continue
All matreials received at site
16 TON materials have not been despatched by party despite of repeated reminders.They are emphasising on payment.
Same to continue
Same to continue
Civil foundation work yet to be completed
Trussel fabrication completed & gallery to be received.party not despatching further materials despite of repeated reminders.
Material not received at site Civil work yet to be completed
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Erection work awaiting completion of fan foundation.
Same as above
Same to continue
Same to continue Insulation work to start after hydro test.
Same to continue
clearing of raw water pump house area for starting of vertical pump erection. Purlins still awaited.
allignment of columns to be completed
Purlins still awaited.
Same to continue
No activity
Same to continue
Civil foundation work to start.fabricated tank awaited at site
400mm ACW pipe painting wrapping to continue & fabrication of bends inside cooling tower forbay ot be done.
No activity
Civil work yet to be completed & mobilisation to be started by Paltech
No activity
same as above
No activity
same as above
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
All other available equipments have been placed in position.
Same to continue
Same to continue
No activity
Erection of remaining small pumps to be taken up during erection of panels
Same to continue
No activity
Purlin erection to start after gable wall completion.