List of Arup Design Deliverable of Pagbilao No.
Document Reference
Title
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
I LNG Storage Tank 1 Site Data 210427 -GEN -SP1 -GT 001 210427 -GEN -RP1 -GT 001 210427 -GEN -RP1 -GT 003 210427 -GEN -SP1 -GT 003 210427 -GEN -RP1 -GT 005
Onshore GI and Testing Specification LNG Tank GI Interpretative Report Site Specific Seismic Hazard Assessment Onshore Topographic Survey Specification Topographic Report (by others) Geological Review Report Storage Tank Specification for Geophysical Investigation
Review
17 May 12
Review Review
22 Feb 12 26 Sep 12
26 Sep 12
2 Specifications 210427 -GEN -SP1 -PG 001
Earthworks Specification
219768 -GEN -SP1 -PG 002
Concrete Specification
210427 -GEN -SP1 -PG 003 210427 -GEN -SP1 -PG 004 210427 -GEN -SP1 -PG 005 210427 -GEN -SP1 -PG 006 210427 -TAN -SP1 -ST 001
Prestressing Specification Steelwork Specification Corrosion Protection Specification Onshore Piling Specification Roof Ariflift Specification
Construction Review
28 Jun 13 21 May 12 19 Sep 14
3 Design Basis Documents 219768 -TAN -DB1 -PG 001 219768 -TAN -PR3 -GT 001
LNG Tank - Civil Design Basis LNG Tank - Foundation Design Philosophy
Review Review
05 Apr 12 17 Apr 12
15 Sep 12 15 Sep 12
219768 -TAN -PR3 -ST 001
LNG Tank - Analysis and Design Philosophy
Review
02 Oct 12
19 Oct 12
210427 -TAN -PR3 -ST 002 210427 -TAN -PR3 -ST 003 219768 -TAN -PR3 -GT 001
LNG Tank - Design Philosophy - Roof LNG Tank - Design Philosophy - Tower and Platform LNG Tank - Seismic Design Philosophy
Review
08 Feb 12
15 Sep 12
19 Oct 12
4 Design Reports and Calculations 219768 -TAN -RP1 -GT 001 219768-TAN -CA1 -GT 001 210427 -TAN -RP1 -ST 001
LNG Tank - Foundation Design Report LNG Tank - Foundation Design Calculations LNG Tank - Wall Design Report
Review Review
16 Apr 12 26 Mar 12
15 Sep 12 15 Sep 12
219768 -TAN -CA1 -ST 001
LNG Tank - Tank Design Calculations
Review
15 Jun 12
19 Oct 12
210427 -TAN -RP1 -ST 002 210427 -TAN -CA1 -ST 002 210427 -TAN -RP1 -ST 003 210427 -TAN -CA1 -ST 003 219768 -TAN -CA1 -ST 004 210427 -TAN -CA1 -ST 005 219768 -TAN -CA1 -ST 006 210427 -TAN -CA1 -ST 007 210427 -TAN -CA1 -ST 008
LNG Tank - Roof Design Report LNG Tank - Roof Design Calculations LNG Tank - Tower and Platform Design Report LNG Tank - Tower and Platform Design Calculations LNG Tank - Seismic Properties of tank LNG Tank - Pile Design Calculations LNG Tank - Base Slab Design Calculations LNG Tank - Nonlinear Design Calculations LNG Tank - Thermal Calculation
Review
27 Jun 12
29 Oct 12
Review
03 May 12
15 Sep 12
30 May 12 26 Jun 12 21 Jun 12
15 Sep 12 25 Oct 12 25 Oct 12
210427 -TAN -CA1 -ST 009
LNG Tank - Prestressed Anchor Analysis
Review Review Review Review Review
210427 -TAN -RP1 -AN 001
LNG Tank - Global Analysis Report
5 Drawings - GA and Details 5.1 General
27 Feb 15
05 Dec 12 05 Dec 12 9 Mar 15
Rev 2
Rev 3
Rev 4
No.
Document Reference
Title
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev 1
Rev 2
Rev 3
Review
15 Sep 12
19 Oct 12
29 Oct 12
Review Review Review
17 Jul 12
15 Sep 12
Construction Construction 219768 -TAN -DR1 -PG 001
219768 -TAN -DR1 -PG 002 219768-T1-DR1-GT-001 219768-T1-DR1-GT-002 219768 -TAN -DR1 -PG 003
General Notes
Site Layout and Location Plan LNG Tank 1 Site Investigation Layout Plan LNG Tank 1 Geophysical Survey Layout Plan Location of Bore Holes for Site Investigation
219768 -TAN -DR1 -PG 004
Rev C 30 Jan 15
Rev 0
7 Aug 13
Construction
Construction
Rev B
19 Apr 13
01 Sep 12
01 Jan 13
01 Sep 12 19 Apr 13
Tank General Arrangement Typical Tank Section Review
219768 -TAN -DR1 -PG 005
Reinforcing Bars Development Lengths
219768 -TAN -DR1 -PG 006
Reinforcing Bars Splice Lengths
15 Sep 12
Construction Review Construction Review
19 Apr 13
Construction Review Construction Review Review
19 Apr 13
Construction
7 Aug 13
15 Sep 12 19 Apr 13 15 Sep 12
5.2 Foundation and Base Slab 216768 -TAN -DR1 -ST 001
Base Slab General Arrangement
216768 -TAN -DR1 -ST 002
Base Slab Details Sheet 1
216768 -TAN -DR1 -ST 003 5.3 Wall and Ringbeam
Base Slab Details Sheet 2
219768 -TAN -DR1 -ST 010
Wall General Arrangement
210427 -TAN -DR1 -ST 011
31 Jan 14 7 Aug 13 19 Oct 12 25 Mar 14 7 Aug 13
Wall Elevation - Sheet 2 Review Construction Wall Elevation - Sheet 3
19 Oct 12 7 Aug 13
Review Construction Construction
210427 -TAN -DR1 -ST 014
15 Sep 12
Wall Elevation - Sheet 1
Construction Construction
210427 -TAN -DR1 -ST 013
16 May 12 15 Sep 12
19 Oct 12
Review
210427 -TAN -DR1 -ST 012
15 Sep 12
19 Apr 13
Review Construction Construction
16 May 12
19 Oct 12 30 Jan 14 7 Aug 13
Wall Elevation - Sheet 4 Review
19 Oct 12
02 Jan 13
Rev 4
No.
Document Reference
Title
Purpose Construction
Date of Deliverable IFR
Draft 1
Rev A 7 Aug 13
Review 210427 -TAN -DR1 -ST 015
Rev B
Rev C
Rev 0
Rev 1
Wall Details
Construction Wall Construction Access Opening Detail
Wall Construction Access Temporary Closure Details Sheet 1
Wall Construction Access Temporary Closure Details Sheet 2
Pretress Layout - Sheet 1
Pretress Layout - Sheet 2
Pretress Layout - Sheet 3
Pretress Layout - Sheet 4
Butress Details
219768-DR1-SK-006
Wall Prestress
5.4 Roof 219768 -TAN -DR1 -ST 030
Roof General Arrangement
219768 -TAN -DR1 -ST 031
Roof Details Sheet 1
219768 -TAN -DR1 -ST 032
Roof Details Sheet 2
19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13
Review Construction
210427 -TAN -DR1 -ST 026
7 Aug 13
Review Construction
210427 -TAN -DR1 -ST 024
19 Oct 12
Review Construction
210427 -TAN -DR1 -ST 023
7 Aug 13
Review Construction
210427 -TAN -DR1 -ST 022
19 Oct 12
Review Construction
210427 -TAN -DR1 -ST 021
7 Aug 13
Review Construction
210427 -TAN -DR1 -ST 018
10 Jan 13
Review Construction
210427 -TAN -DR1 -ST 017
19 Oct 12 7 Aug 13
Review
19 Oct 12
Preliminary
16 May 12
Review Review Review Review Review
29 Oct 12 4 Feb 14 29 Oct 12
22 Feb 13 4 Feb 13
29 Oct 12
5.5 Access Tower 219768-DR1-ME-001
Rev 3
19 Oct 12
Review
210427 -TAN -DR1 -ST 016
Rev 2
Tank Outfitting Roof General Arrangement
Review
2 Apr 17
Rev 4
No.
Document Reference 219768-DR1-ME-001
219768-DR1-ME-002
Title Tank Outfitting Roof General Arrangement
Pump Platform Details Sheet 1
Purpose Review Construction
Pump Platform Details Sheet 2
Pump Platform Details Sheet 3
Pump Platform Details Sheet 4
Rev A
VSV Platform Details Sheet 1
VSV Platform Details Sheet 2
VSV Platform Details Sheet 3
17 Jun 16 30 Jan 15 30 Jan 15 2 Apr 17 17 Jun 16 30 Jan 15 30 Jan 15 2 Apr 17 17 Jun 16 30 Jan 15 30 Jan 15
Materials Ordering
2 Apr 17 30 Jan 15
Materials Ordering
2 Apr 17
219768-DR1-ME-015
Materials Ordering
2 Apr 17 30 Jan 15 2 Apr 17 6 Oct 16
Materials Ordering Review Review Construction
219768-DR1-ME-602
17 Jun 16 31 Dec 15 30 Jan 15 2 Apr 17
Materials Ordering Tank Outfitting External Access Stairway Sheet 2
219768-DR1-ME-016
219768-DR1-ME-603
6 Oct 16
Materials Ordering
17 Jun 16
Review Review Construction
31 Dec 15
Materials Ordering Tank Outfitting External Access Stairway Sheet 3
219768-DR1-ME-017
30 Jan 15
Materials Ordering Tank Outfitting External Access Stairway Sheet 1
Rev 2
2 Apr 17
Materials Ordering
Review Construction 219768-DR1-ME-601
Rev 1 30 Jan 15
30 Jan 15 30 Jan 15
Review 219768-DR1-ME-012
Rev 0
17 Jun 16
Review 219768-DR1-ME-011
Rev C
2 Apr 17
Review Review 219768-DR1-ME-010
Rev B
Materials Ordering Review Review Construction
219768-DR1-ME-005
Draft 1
Materials Ordering Review Review Construction
219768-DR1-ME-004
IFR
Materials Ordering Review Review Construction
219768-DR1-ME-003
Date of Deliverable
30 Jan 15 2 Apr 17 6 Oct 16
Materials Ordering
17 Jun 16
Review
31 Dec 15
Rev 3
Rev 4
Tank Outfitting External Access Stairway Sheet 3 No. 219768-DR1-ME-017 Document Reference
Title
Purpose Review Construction
219768-DR1-ME-604
219768-DR1-ME-018
219768-DR1-ME-605
219768-DR1-ME-019
Tank Outfitting Access Tower Pipe Support
PSV Platform Details Sheet 1
PSV Platform Details Sheet 2
PSV Platform Details Sheet 3
2 Apr 17 6 Oct 16
30 Jan 15 2 Apr 17
31 Dec 15
Materials Ordering
Pipe Support Design Summary Sheet 1 Pipe Support Design Summary Sheet 2 Pipe Support Details 1 Pipe Support Details 2 Pipe Support Details 3 Pipe Support Details 4,5,6 & 7 General Notes for LNG Tank Piping External Steelwork
219768-DR1-ME-201
Floor Beams & Bracing Connections Sheet 1
219768-DR1-ME-202
Floor Beams & Bracing Connections Sheet 2
219768-DR1-ME-203
Vertical Bracing Connections
2 Apr 17 6 Oct 16 2 Apr 17 30 Jan 15
Materials Ordering
2 Apr 17 30 Jan 15
Materials Ordering
Review
219768-DR1-ME-100 219768-DR1-ME-101 219768-DR1-ME-102 219768-DR1-ME-103 219768-DR1-ME-104 219768-DR1-ME-105 219768-DR1-ME-200
30 Jan 15
Materials Ordering
Materials Ordering
Tank Outfitting External Access Stairway Sheet 5
6 Oct 16
Review Review Construction
Maintenance Platform 2 Details
219768-DR1-ME-040
Rev 2
17 Jun 16
219768-DR1-ME-028
Escape Ladder Details Sheet 1 Escape Ladder Details Sheet 2
Rev 1 30 Jan 15
Materials Ordering
Maintenance Platform 1 Details
219768-DR1-ME-035 219768-DR1-ME-036
Rev 0
31 Dec 15
219768-DR1-ME-025
Maintenance Platform 3 Details
Rev C
Review Review Construction
Review Review
219768-DR1-ME-031
Rev B
17 Jun 16
Review 219768-DR1-ME-022
Rev A
Materials Ordering
Review 219768-DR1-ME-021
Draft 1
Materials Ordering Tank Outfitting External Access Stairway Sheet 5
219768-DR1-ME-020
IFR
Materials Ordering Tank Outfitting External Access Stairway Sheet 4
219768-DR1-ME-606
Date of Deliverable
2 Apr 17 30 Jan 15 30 Jan 15 2 Apr 17 30 Jan 15
Materials Ordering Review Review Review
2 Apr 17 30 Jan 15 22 Sep 14 22 Sep 14
Materials Ordering Review Review Review Review Review Review Review Review Work In Progress Review Work In Progress Review
17 Jun 16 4 Apr 17 4 Apr 17 4 Apr 17 4 Apr 17 4 Apr 17 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17
Rev 3
Rev 4
No.
Document Reference
Title
219768-DR1-ME-203
Vertical Bracing Connections
219768-DR1-ME-204
Bracing Connection Details Sheet 1
219768-DR1-ME-205
Bracing Connection Details Sheet 2
219768-DR1-ME-206 219768-DR1-ME-207
Base Plates & Shear Keys Column & Beam Splices
219768-DR1-ME-208
Knee Braces & Monorails
219768-DR1-ME-209
Moment & Beam Over / Under Column Connections
219768-DR1-ME-210
Welded Connections
219768-DR1-ME-211
Stairs
219768-DR1-ME-212 219768-DR1-ME-213 219768-DR1-ME-214 210427 -TAN -DR1 -ST 061 210427 -TAN -DR1 -ST 062 210427 -TAN -DR1 -ST 063 210427 -TAN -DR1 -ST 064 210427 -TAN -DR1 -ST 065 210427 -TAN -DR1 -ST 066 210427 -TAN -DR1 -ST 067 5.6 Roof Platform 210427 -TAN -DR1 -ST 051 210427 -TAN -DR1 -ST 054
Handrails Details Grating & Floor Plate Details Sheet 1 Grating & Floor Plate Details Sheet 2 Access Tower GA Access Tower - Steel Framing Plans - Sheet 1 Access Tower - Steel Framing Plans - Sheet 2 Access Tower - Steel Steel Details - Sheet 1 Access Tower - Steel Steel Details - Sheet 2 Access Tower - Steel Stair Details - Sheet 1 Access Tower - Steel Stair Details - Sheet 2
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Work In Progress Review Work In Progress Review Work In Progress Work In Progress Work In Progress Review Work In Progress Review Work In Progress Review Work In Progress Review Work In Progress Work In Progress Work In Progress Work In Progress
Rev B
Rev C
Rev 0
Rev 1 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 30 Jan 15 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 30 Jan 15 30 Jan 15 30 Jan 15
Rev 2
15 Sep 12
02 Jan 13
Roof Platform GA Roof Details Sheet 1 Roof Concrete Layout General Arrangement
6 Drawings - Reinforcement 6.1 Base Slab 219768 -TAN -DR1 -RC 001
Base Slab Bottom Reinforcement
219768 -TAN -DR1 -RC 002
Base Slab Top Reinforcement
219768 -TAN -DR1 -RC 003
Base Slab Reinforcement Details Sheet 1
219768 -TAN -DR1 -RC 004
Base Slab Reinforcement Details Sheet 2
210427 -TAN -DR1 -RC 011
Wall Starters Reinforcement - Sheet 1
210427 -TAN -DR1 -RC 012
Wall Starters Reinforcement - Sheet 2 K32 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 013
Wall Starters Reinforcement - Sheet 3
210427 -TAN -DR1 -RC 014
Wall Starters Reinforcement - Sheet 4
Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction
19 Apr 13 19 Apr 13 15 Sep 12 19 Apr 13 15 Sep 12 19 Apr 13 15 Sep 12 19 Apr 13 19 Oct 12 19 Apr 13 19 Oct 12 19 Apr 13
Review Construction Review
19 Oct 12 19 Apr 13 19 Oct 12
02 Jan 13
Rev 3
Rev 4
No.
Document Reference
Title
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
Rev 2
6.2 Wall Reinforcement 210427 -TAN -DR1 -RC 020
Wall Reinforcement - Inner Face - Sheet 1 K25, K32 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 021
Wall Reinforcement - Inner Face - Sheet 2 K25 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 022
Wall Reinforcement - Inner Face - Sheet 3 K32 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 023
Wall Reinforcement - Outer Face - Sheet 1
210427 -TAN -DR1 -RC 024
Wall Reinforcement - Outer Face - Sheet 2
210427 -TAN -DR1 -RC 025
Wall Reinforcement - Outer Face - Sheet 3
210427 -TAN -DR1 -RC 026
Wall Reinforcement - Outer Face - Sheet 4
210427 -TAN -DR1 -RC 027
Wall Reinforcement - Outer Face - Sheet 5
210427 -TAN -DR1 -RC 028
Wall Reinforcement - Outer Face - Sheet 6
210427 -TAN -DR1 -RC 029
Wall Reinforcement - Outer Face - Sheet 7
210427 -TAN -DR1 -RC 030
Wall Reinforcement - Outer Face - Sheet 8
210427 -TAN -DR1 -RC 031
Wall Reinforcement - Outer Face - Sheet 9
210427 -TAN -DR1 -RC 033
Wall Shear Reinforcement
210427 -TAN -DR1 -RC 035
Wall Reinforcement - Details - Sheet 1 K32 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 036
Wall Reinforcement - Details - Sheet 2 K25, K32 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 037
Wall Reinforcement - Details - Sheet 3 K25, K32 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 038
Wall Reinforcement - Details - Sheet 4 K25 Cryogenic Bars in drawing
210427 -TAN -DR1 -RC 039
Wall Reinforcement - Details - Sheet 5 K25, K32 Cryogenic Bars in drawing
6.3 Roof 219768 -TAN -DR1 -RC 041 219768 -TAN -DR1 -RC 042
Roof Slab Reinforcement Bottom Face Roof Reinforcement Top Face
219768 -TAN -DR1 -RC 051
Roof Reinforcement Details Sheet 1
219768 -TAN -DR1 -RC 052 219768 -TAN -DR1 -RC 053 219768 -TAN -DR1 -RC 054 6.4 Tower and Platforms 210427 -TAN -DR1 -RC 091 210427 -TAN -DR1 -RC 092 210427 -TAN -DR1 -RC 093 210427 -TAN -DR1 -RC 094
Roof Reinforcement Details Sheet 2 Roof Reinforcement Details Sheet 3 Roof Reinforcement Details Sheet 4 Tower Foundation Reinforcement Details Platform Columns Reinforcement Details - Sheet 1 Platform Columns Reinforcement Details - Sheet 2 Platform Beam Reinforcement Details - Sheet 1
Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Review Review Review Review Review Review Review
7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 29 Oct 12 29 Oct 12 2 Jul 14 29 Oct 12 29 Oct 12 29 Oct 12 29 Oct 12
Rev 3
Rev 4
No.
Document Reference
210427 -TAN -DR1 -RC 095 210427 -TAN -DR1 -RC 096 210427 -TAN -DR1 -RC 097 210427 -TAN -DR1 -RC 098 6.5 Other Drawings DR1-ME-001 DR1-ME-003 DR1-ME-004 DR1-ME-010 DR1-ME-011 DR1-ME-015 DR1-ME-016 DR1-ME-020 DR1-ME-021 DR1-ME-025 DR1-ME-026 DR1-ME-030
Title
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
04 Jun 12
28 Aug 12
Rev C
Rev 0
Rev 1
Rev 2
29 Aug 12
03 Jan 13
Platform Beam Reinforcement Details - Sheet 2 Platform Slab Reinforcement Details - Sheet 1 Platform Slab Reinforcement Details - Sheet 2 Platform Slab Reinforcement Details - Sheet 3 Tank Outfitting Foof General Arrangement Pump Platform Details Sheet 1 Pump Platform Details Sheet 2 Safety Valve Platform Details Sheet 1 Safety Valve Platform Details Sheet 2 Access Stairway And Pipe Support Tower Details Sheet 1 Access Stairway And Pipe Support Tower Details Sheet 2 Safety Valve Platform Details Sheet 1 Safety Valve Platform Details Sheet 2 Maintenance Platform Details Sheet 1 Maintenance Platform Details Sheet 2 Emergency Escape Details Sheet 1
II LNG Jetty 1 Site Data 210427 -GEN -SP1 -GT 002 210427 -GEN -RP1 -GT 002 210427 -GEN -RP1 -GT 004 210427 -GEN -RP1 -MA 001 SPEC/MGI/001 SPEC/223866/G004 SPEC/223866/M002 210427 -GEN -RP1 -MA 002
Offshore GI and Testing Specification Offshore GI Interpretative Report Preliminary Offshore Geotechnical Desk Study Metocean Report Jetty Marine Geophysical Survey Specification Specification for Geophysical Investigation of Pipeline Route Topographical Survey Specification Bathymetric Report (by others)
Review
30 Apr 12
Review Review Review
19 Apr 12 10 Dec 12 27 Apr 12
2 Specifications 223866-JET-SP1-GT-001 210427 -JET -SP1 -MA 001
210427 -JET -SP1 -MA 004
Onshore Piling Specification for Jetty Navigation Aids Specification Fender System Specification Mooring System Specification Docking System Specification
Draft
25 Feb 14
Design Basis Report LNG Jetty - Civil Design Basis LNG Jetty - Design Philosophy - Embankment LNG Jetty - Design Philosophy - Abutment and Trestle LNG Jetty - Design Philosophy - Loading Platform LNG Jetty - Design Philosophy - Dolphins and Catwalks LNG Jetty - Design Philosophy - Tug Berth LNG Jetty - Trestle and LP Analysis Philosophy Vessel Geometry Report Navigational Concept Design Metocean Modelling Report Wave and Current Load Report Dolphin Concept Design Loading Platform Calculation Report
Draft
08 Oct 12
7 Jul 14
Review Review Review Review Review Review
25 Apr 12 21 Aug 12 24 Aug 12 24 Aug 12 29 Aug 12 05 Oct 12
06 Aug 12
Draft Draft
17 Oct 14 17 Oct 14
3 Design Basis Documents REP/223866/S005 210427 -JET -DB1 -PG 001 210427 -JET -PR3 -ST 002 210427 -JET -PR3 -ST 001 210427 -JET -PR3 -ST 002 210427 -JET -PR3 -ST 003 210427 -JET -PR3 -ST 004 210427 -JET -PR3 -AN 001 REP/223866/M001 REP/223866/M005 REP/223866/M004 REP/223866/M006 REP/223866/M011 REP/223866/S009
25 Jun 14 4 Jul 14
13 Aug 12
Rev 3
Rev 4
No.
Document Reference REP/223866/S010 REP/223866/S012 REP/223866/S013 223866-20/CKC 223866-00/JT 223866-20/CKC/BFT 223866-00/JT
Title Trestle Concept Design Report Catwalk Concept Design Report Shoreline Protection Concept Design Report Note on Mooring Hooks File Note - Design of Marine Fendering Notes on Gangways Marine Loading Arm Elevation
Purpose Review Review Review
Date of Deliverable IFR 05 Oct 12 08 Oct 12 19 Nov 12 29 Jun 12 29 May 12 28 Jun 12 09 May 12
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
Rev 2
Rev 3
Rev 4
4 Design Reports and Calculations 210427 -JET -RP1 -GT 001 210427 -JET -CA1 -GT 001 210427 -JET -RP1 -ST 001 210427 -JET -CA1 -ST 001 210427 -JET -CA1 -ST 003 210427 -JET -RP1 -ST 004 210427 -JET -CA1 -ST 004 210427 -JET -RP1 -AN 001
LNG Jetty - Embankment Design Report LNG Jetty - Embankment Design Calculations LNG Jetty - Abutment and Trestle Design Report LNG Jetty - Abutment and Trestle Design Calculations LNG Jetty - Dolphins and Catwalks Design Calculations LNG Jetty - Tug Berth Design Report LNG Jetty - Tug Berth Design Calculations LNG Jetty - Trestle and LP Analysis Report
5 Drawings - GA and Details 5.1 General 210427 -JET -DR1 -PG 002 223866_JET_DR1_SK_107 223886-JET -DR1-GT-001 223886-JET -DR1-GT-002 223886-JET -DR1-GT-003 210427 -JET -DR1 -GT 003 223866/GEN/001 223866/GEN/002 223866/GEN/003 223866/GEN/004 223866/GEN/010 223866/GEN/011 223866/GEN/012 223886/SPN/600 223866/SPN/601 223886/SPN/610 223886/SPN/611 5.2 Embankment 210427 -JET -DR1 -GT 011 210427 -JET -DR1 -GT 012 210427 -JET -DR1 -GT 013 210427 -JET -DR1 -GT 014 210427 -JET -DR1 -GT 015 210427 -JET -DR1 -GT 016 210427 -JET -DR1 -GT 017 210427 -JET -DR1 -GT 018 210427 -JET -DR1 -GT 019 5.3 Abutment and Trestle 210427 -JET -DR1 -ST 021 210427 -JET -DR1 -ST 022
Site Layout and Location Plan Site Investigation Layout Plan Site Investigation Layout Plan - Sheet 1 Site Investigation Layout Plan - Sheet 2 Pipeline Geophysical Survey Layout Plan Layout of Site Investigation & Trials Master Layout Plan Project Layout Plan - Sheet 1 Project Layout Plan - Sheet 2 Project Layout Plan - Sheet 3 General Notes Reinforcing Bars Development Lengths Reinforcing Bars Splice Lengths
Review Review Review Review
26 Sep 13 01 Aug 12 01 Aug 12 01 Dec 12
Review Review Review Review Construction Construction Construction
01 Sep 12 01 Sep 12 01 Sep 12 01 Sep 12 1 Feb 14 1 Feb 14 1 Feb 14
Manoevring And Berthing Areas - Aids To Navigation & Dredged Area Plan
Conceptual
01 Oct 12
Navigation Channel - Aids To Navigation & Dredged Area Plan Shoreline Protection General Layout Plan Pagbilao Shoreline Protection Details
Conceptual Conceptual Conceptual
01 Sep 12 01 Nov 12 01 Nov 12
Embankment Plan Layout and Sections - Sheet 1 Embankment Plan Layout and Sections - Sheet 2 Embankment Plan Layout and Sections - Sheet 3 Embankment Plan Layout and Sections - Sheet 4 Embankment Plan Layout and Sections - Sheet 5 Embankment Road Details Embankment Drainage Details Embankment Piperack Details Embankment Miscellaneous Details Abutment GA Abutment Sections
31 Jul 14 31 Jul 14 31 Jul 14
01 Oct 12
No.
Document Reference
Title
210427 -JET -DR1 -ST 023 210427 -JET -DR1 -ST 024 223866/CWY/700 223866/CWY/701 223866/CWY/702 223866/CWY/703
Abutment Details Abutment Shore Protection Details Causeway Plan Causeway General Arrangement Details Dredging Layout Dredging Layout General Arrangement Details
223866/TLE/100
Trestle GA
223866/TLE/101
Trestle Deck Layout (Sheet 1 of 3)
223866/TLE/102
Trestle Deck Layout (Sheet 2 of 3)
223866/TLE/103
Trestle Deck Layout (Sheet 3 of 3)
223866/TLE/101 223866/TLE/110 223866/TLE/111 223866/TLE/112 223866/TLE/120 210427 -JET -DR1 -ST 025 210427 -JET -DR1 -ST 026 210427 -JET -DR1 -ST 027 210427 -JET -DR1 -ST 028 210427 -JET -DR1 -ST 029 210427 -JET -DR1 -ST 030 210427 -JET -DR1 -ST 031 210427 -JET -DR1 -ST 032 223866/TKE/SK/202 223866/TLE/103 223866/TLE/123 223866/TLE/124 223866/TLE/125 223866/TLE/180 210427 -JET -DR1 -ST 036 210427 -JET -DR1 -ST 037 210427 -JET -DR1 -ST 038 210427 -JET -DR1 -ST 039 210427 -JET -DR1 -ST 040 210427 -JET -DR1 -ST 041 210427 -JET -DR1 -ST 042 210427 -JET -DR1 -ST 043 210427 -JET -DR1 -ST 044 5.4 Loading Platform
Trestle Functional Cross Section Trestle Abutment GA - Sheet 1 Trestle Abutment GA - Sheet 2 Trestle Abutment GA - Sheet 3 Trestle Piling Layout Trestle Pile Schedule and Details Trestle Pile Layout - Sheet 1 Trestle Pile Layout - Sheet 2 Trestle Pilecap Layout - Sheet 1 Trestle Pilecap Layout - Sheet 2 Trestle Pilecap Details - Sheet 1 Trestle Pilecap Details - Sheet 2 Trestle Pilecap Details - Sheet 3 Trestle Deck Level Options Trestle Deck Layout - Sheet 1 Trestle Deck Layout - Sheet 1 Trestle Deck Layout - Sheet 2 Trestle Deck Layout - Sheet 3 Trestle Pile Reinforcement Details Trestle Deck Layout - Sheet 4 Trestle Deck Layout - Sheet 5 Trestle Deck Layout - Sheet 6 Trestle Deck Layout - Sheet 7 Trestle Deck Layout - Sheet 8 Trestle Deck Details - Sheet 1 Trestle Deck Details - Sheet 2 Trestle Precast Beam Details - Sheet 1 Trestle Precast Beam Details - Sheet 2
Purpose
Review Review Review Review Review Conceptual Review Conceptual Review Conceptual Review Conceptual Conceptual Conceptual Conceptual Conceptual Construction
Conceptual Conceptual Conceptual Conceptual Construction
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
Rev 2
Rev 3
Rev 4
31 Jul 14 31 Jul 14 31 Jul 14 31 Jul 14 31 Jul 14 30 May 14 31 Jul 14 30 May 14 31 Jul 14 30 May 14 31 Jul 14 30 May 14 01 Sep 12 01 Oct 12 01 Oct 12 01 Oct 12 31 Mar 14
01 Sep 12 01 Sep 12 01 Sep 12 01 Sep 12 01 Sep 12 31 Mar 14
Construction 223866/LPT/200
210427 -JET -DR1 -ST 052
Loading Platform GA
Construction Preliminary Conceptual
16 Oct 13 01 Sep 12
Loading Platform Pile Schedule and Details Construction
223866/LPT/202
26 Feb 14
Loading Platform Piling Layout
30 Oct 14
No.
Document Reference 223866/LPT/202
Title Loading Platform Piling Layout
210427 -JET -DR1 -ST 054 210427 -JET -DR1 -ST 055
Loading Platform Pile Cap Layout Loading Platform Pile Cap Details
223866/LPT/203
Loading Platform Deck Framing
223866/LPT/204
Loading Platform Deck Framing Section
223866/LPT/205
Loading Platform and Loading Assumptions
223866/LPT/213
Loading Platform Pile Reinforcement Details
223866/LPT/230
Loading Platform Concrete Plinth Details
223866/LPT/231
Concrete Plinth Details
223866/LPT/232
Concrete Plinth Details
223866/LPT/240 223866/LPT/241 210427 -JET -DR1 -ST 056 210427 -JET -DR1 -ST 057 210427 -JET -DR1 -ST 058 210427 -JET -DR1 -ST 059 210427 -JET -DR1 -ST 060 210427 -JET -DR1 -ST 061 210427 -JET -DR1 -ST 062 210427 -JET -DR1 -ST 063 210427 -JET -DR1 -ST 064 223866/JET/DR1/SK/106A 223866/JET/DR1/SK/106B 5.5 Dolphins and Catwalks
Loading Platform Pile Reinforcement Details Beam Reinforcement Details Loading Platform Deck Layout and Sections Loading Platform Deck Details - Sheet 1 Loading Platform Deck Details - Sheet 2 Loading Platform Precast Beam Details Loading Platform Topside Layout and Sections Loading Platform Topside Details - Sheet 1 Loading Platform Topside Details - Sheet 2 Loading Platform Control Room - Sheet 1 Loading Platform Control Room - Sheet 2 Loading Arm At +5.500mCD Option A Loading Arm At +7.000mCD Option B
223866/DAC/300
Dolphins and Catwalk GA
223886/DAC/301
Plan and Section of Typical Berthing Dolphin
223886/DAC/302
Plan and Section of Typical Mooring Dolphin
210427 -JET -DR1 -MA 071 210427 -JET -DR1 -MA 072 210427 -JET -DR1 -MA 073 210427 -JET -DR1 -MA 074 210427 -JET -DR1 -MA 075 223866/DAC/315 210427 -JET -DR1 -ST 081 210427 -JET -DR1 -ST 082
Berth Layout LNG Mooring Arrangement Plan for Vessel 1 LNG Mooring Arrangement Plan for Vessel 2 LNG Mooring Arrangements Vertical Alignment Navigation Aids Details Mooring Dolphins Pile Reinforcement Details Mooring Dolphin - MD1 Mooring Dolphin - MD2
Purpose Construction Preliminary Conceptual
Preliminary Conceptual Construction Preliminary Conceptual Construction Review Review Construction Preliminary Construction Review Review Review Construction Review Review Construction Construction
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
Rev 2
Construction
Rev 4
16 Oct 13 01 Jul 12
16 Oct 13 01 Sep 12 26 Feb 14 16 Oct 13 01 Sep 12 30 Oct 14 25 Jun 14 22 Apr 14 26 Feb 14 16 Oct 13 30 Oct 14 25 Jun 14 22 Apr 14 22 Apr 14 1 Jul 15 19 Dec 14 22 Apr 14 10 Apr 14 10 Apr 14
01 May 12 01 May 12 Construction Conceptual Construction Conceptual Construction Conceptual
Rev 3 26 Feb 14
01 Sep 12
19 Mar 14 01 Sep 12 19 Mar 14
01 Sep 12
01 Sep 12 19 Mar 14
01 Sep 12
01 Sep 12
19 Mar 14
No.
Document Reference
Title
210427 -JET -DR1 -ST 083 210427 -JET -DR1 -ST 084 210427 -JET -DR1 -ST 085 210427 -JET -DR1 -ST 086 210427 -JET -DR1 -ST 087 210427 -JET -DR1 -ST 088 223866/DAC/316 223866/DAC/317 223866/DAC/318 210427 -JET -DR1 -ST 089 210427 -JET -DR1 -ST 090 210427 -JET -DR1 -ST 091 210427 -JET -DR1 -ST 092
Mooring Dolphin - MD3 Mooring Dolphin - MD4 Mooring Dolphin - MD5 Mooring Dolphin - MD6 Mooring Dolphin - MD7 Mooring Dolphin - MD8 Berthing Dolphins Pile Reinforcement Details R.C. Details of Mooring Dolphin R.C. Details of Berthing Dolphin Breasting Dolphin - BD1 Breasting Dolphin - BD2 Breasting Dolphin - BD3 Breasting Dolphin - BD4
223866/DAC/320
Typical Catwalk
223866/DAC/330 223866/DAC/331 223866/DAC/332 223866/DAC/333 223866/DAC/341 223866/DAC/342 223866/DAC/343 210427 -JET -DR1 -ST 093 210427 -JET -DR1 -ST 094 210427 -JET -DR1 -ST 095 210427 -JET -DR1 -ST 096 210427 -JET -DR1 -ST 097 210427 -JET -DR1 -ST 098 223866/JET/DR1/SK/104 223866/JET/DR1/SK/105 5.6 Tug Berth 210427 -JET -DR1 -ST 101 210427 -JET -DR1 -ST 102 210427 -JET -DR1 -ST 103 210427 -JET -DR1 -ST 104 210427 -JET -DR1 -ST 105 210427 -JET -DR1 -ST 106
Catwalk Details Catwalk Details Typical Staircase Typical RC Details of Staircase Loading Platform Catwalk - Bearing Layout Plan (Sheet 1 of 2) Loading Platform Catwalk - Bearing Layout Plan (Sheet 2 of 2) Loading Platform Catwalk - Bearing Connection Detail Catwalks - CW1 and CW12 Catwalks - CW2 and CW11 Catwalks - CW3 and CW10 Catwalks - CW4 and CW9 Catwalks - CW5 and CW8 Catwalks - CW6 and CW7 Elevation Showing Design Vessels Fenders and Spring Lines (1 of 2) Elevation Showing Design Vessels Fenders and Spring Lines (2 of 2) Tug Berth GA Tug Berth Piling and Details Tug Berth Mooring and Berthing Details - Sheet 1 Tug Berth Mooring and Berthing Details - Sheet 2 Tug Berth Platforms and Stairs - Sheet 1 Tug Berth Platforms and Stairs - Sheet 2
6 Drawings - Reinforcement 6.1 Embankment 210427 -JET -DR1 -RC 001 210427 -JET -DR1 -RC 002 210427 -JET -DR1 -RC 003 210427 -JET -DR1 -RC 004 210427 -JET -DR1 -RC 005 210427 -JET -DR1 -RC 006
Road Slab Reinforcement Piperack Reinforcement - Sheet 1 Piperack Reinforcement - Sheet 2 Embankment Drainage Details - Sheet 1 Embankment Drainage Details - Sheet 2 Miscellaneous Reinforcement Details
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Construction Construction Construction
26 May 14 26 May 14
Construction Conceptual Construction Construction Construction Construction Construction Construction Construction
18 Sep 15 01 Sep 12 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15
Review Review
Rev 1
Rev 2
19 Mar 14
25 Jun 12
1 Aug 12 1 Aug 12
Rev 3
Rev 4
No.
Document Reference
6.2 Abutment and Trestle 210427 -JET -DR1 -RC 011 210427 -JET -DR1 -RC 012 210427 -JET -DR1 -RC 013 210427 -JET -DR1 -RC 014 210427 -JET -DR1 -RC 015 210427 -JET -DR1 -RC 016 210427 -JET -DR1 -RC 017 210427 -JET -DR1 -RC 018 210427 -JET -DR1 -RC 019 210427 -JET -DR1 -RC 020 210427 -JET -DR1 -RC 021 210427 -JET -DR1 -RC 022 210427 -JET -DR1 -RC 023 210427 -JET -DR1 -RC 024 210427 -JET -DR1 -RC 025 210427 -JET -DR1 -RC 026 210427 -JET -DR1 -RC 027 210427 -JET -DR1 -RC 028 6.3 Loading Platform 210427 -JET -DR1 -RC 031 210427 -JET -DR1 -RC 032 210427 -JET -DR1 -RC 033 210427 -JET -DR1 -RC 034 210427 -JET -DR1 -RC 035 210427 -JET -DR1 -RC 036 210427 -JET -DR1 -RC 037 210427 -JET -DR1 -RC 038 210427 -JET -DR1 -RC 039 210427 -JET -DR1 -RC 040 210427 -JET -DR1 -RC 041 6.4 Dolphins 210427 -JET -DR1 -RC 051 210427 -JET -DR1 -RC 052 210427 -JET -DR1 -RC 053 210427 -JET -DR1 -RC 054 210427 -JET -DR1 -RC 055 210427 -JET -DR1 -RC 056 210427 -JET -DR1 -RC 057 210427 -JET -DR1 -RC 058 210427 -JET -DR1 -RC 059 210427 -JET -DR1 -RC 060 210427 -JET -DR1 -RC 061 210427 -JET -DR1 -RC 062 6.5 Tug Berth 210427 -JET -DR1 -RC 071 210427 -JET -DR1 -RC 072
III Power Plant Foundation
Title Abutment Pilecap Reinforcement Details Abutmenet Wall Reinforcement Details - Sheet 1 Abutmenet Wall Reinforcement Details - Sheet 2 Abutmenet Wall Reinforcement Details - Sheet 3 Trestle Pilecap Reinforcement Details - Sheet 1 Trestle Pilecap Reinforcement Details - Sheet 2 Trestle Pilecap Reinforcement Details - Sheet 3 Trestle Pilecap Reinforcement Details - Sheet 4 Trestle Precast Beam Reinforcement Details - Sheet 1 Trestle Precast Beam Reinforcement Details - Sheet 2 Trestle Precast Beam Reinforcement Details - Sheet 3 Trestle Precast Beam Reinforcement Details - Sheet 4 Trestle Road Reinforcement Details - Sheet 1 Trestle Road Reinforcement Details - Sheet 2 Trestle Piperack Reinforcement Details - Sheet 1 Trestle Piperack Reinforcement Details - Sheet 2 Trestle Passing Bay Reinforcement Details - Sheet 1 Trestle Passing Bay Reinforcement Details - Sheet 2 Loading Platform Pilecap Reinforcement Details - Sheet 1 Loading Platform Pilecap Reinforcement Details - Sheet 2 Loading Platform Precast Beam Reinforcement Details - Sheet 1 Loading Platform Precast Beam Reinforcement Details - Sheet 2 Loading Platform Precast Beam Reinforcement Details - Sheet 3 Loading Platfrom Deck Reinforcement Details - Sheet 1 Loading Platfrom Deck Reinforcement Details - Sheet 2 Loading Platform Topsides Column Details Loading Platform Topsides Beam Details Loading Platform Topsides Slab Details - Sheet 1 Loading Platform Topsides Slab Details - Sheet 2 Mooring Dolphins MD1 Reinforcement Details Mooring Dolphins MD2 Reinforcement Details Mooring Dolphins MD3 Reinforcement Details Mooring Dolphins MD4 Reinforcement Details Mooring Dolphins MD5 Reinforcement Details Mooring Dolphins MD6 Reinforcement Details Mooring Dolphins MD7 Reinforcement Details Mooring Dolphins MD8 Reinforcement Details Breasting Dolphins BD1 Reinforcement Details Breasting Dolphins BD2 Reinforcement Details Breasting Dolphins BD3 Reinforcement Details Breasting Dolphins BD4 Reinforcement Details Tug Berth Reinforcement Details - Sheet 1 Tug Berth Reinforcement Details - Sheet 2
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
Rev 2
Rev 3
Rev 4
No.
Document Reference
Title
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
Rev 2
Rev 3
15 Oct 14
1 Site Data 223866/PWS/DR1/GI/100
Pagbilao Power Station Site Investigation Layout Plan
Review
30 Jun 14
223866/PWS/DR1/GI/200
Pagbilao Power Station Site Investigation Layout Plan for Transformers Pump Station, & Oil Interceptors
Review
30 Nov 16
236981/MPS/DR1/FI/100
CCGT Pumping Station & Re-gas Pumping Station Site Investigation Layout Plan
Review
Specification for Ground Investigation
Review
30 Apr 14 14 Jul 16
2 Foundation 236981/PWS/DR1/GEN/GN/001
General Notes (Sheet 1 of 2)
Construction
15 Oct 14
236981/PWS/DR1/GEN/GN/002
General Notes (Sheet 2 of 2)
Construction
15 Oct 14
236981/PWS/DR1/PB/X/011
Anchor Bolt Details
Construction
15 Oct 14
236981/PWS/DR1/PB/X/021
Anchor Bolt Sections & Details
Construction
15 Oct 14
236981/PWS/DR1/PB/X/022
Anchor Bolt Sections & Details
Construction
15 Oct 14
236981/PWS/DR1/PB/GA/011
Gas Turbine Power Block Foundation Arrangement
Construction
30 Sep 14
236981/PWS/DR1/PB/RC/011
Gas Turbine Power Block Foundation R.C. Details (Sheet 1 of 2)
Preliminary
30 Sep 14
236981/PWS/DR1/PB/RC/012
Gas Turbine Power Block Foundation R.C. Details (Sheet 2 of 2)
Construction
15 Oct 14
236981/PWS/DR1/PB/RC/021
Gas Turbine Power Block Anchor Bolt Arrangement
Construction
15 Oct 14
236981/PWS/DR1/PB/RC/022
Generator Power Block Anchor Bolt Arrangement
Construction
15 Oct 14
236981/PWS/DR1/AUX/GA/021
Diverter Damper Foundaiton Arrangement (Sheet 1 of 2)
Preliminary
236981/PWS/DR1/AUX/GA/031
Rotor Air Cooler Foundation
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/032
Rotor Cooler Air Pipe Support Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/041
Instrument Air Compressor Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/061
Electrical Package Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/071
CO2 Fire Cylinder Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/091
SFC & SEE Excitation Package Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/101
SFC Transformer Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/111
SEE Transformer Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/121
VT Surge Cubicle with SFC Switch Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/131
Control Oil Skid Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/151
Exhaust Diffuser Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/161
Fuel Gas Main Filter Separator Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/GA/171
Generator Air Filter Foundation Arrangement
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/021
Diverter Damper Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/031
Rotor Air Cooler Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/032
Rotor Cooler Air Pipe Support Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/041
Instrument Air Compressor Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/061
Electrical Package Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/071
CO2 Fire Cylinder Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/091
SFC & SEE Excitation Package Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/101
SFC Transformer Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/111
SEE Transformer Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/121
VT Surge Cubicle with SFC Switch Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/131
Control Oil Skid Foundation R.C. Details
Preliminary
21 Nov 14
236981/PWS/DR1/AUX/RC/151
Exhaust Diffuser Foundation R.C. Details
Preliminary
21 Nov 14
30 Dec 14
Rev 4
No.
Document Reference
Title
Purpose
Date of Deliverable IFR
Draft 1
Rev A
Rev B
Rev C
Rev 0
236981/PWS/DR1/AUX/RC/161
Fuel Gas Main Filter Separator Foundation R.C. Details
Preliminary
Rev 1 21 Nov 14
Rev 2
Rev 3
236981/PWS/DR1/AUX/RC/171
Generator Air Filter Foundation R.C. Details
Preliminary
21 Nov 14
Draft Draft
30 Jul 15 30 Jul 15
30 Oct 15
Review
21 Jul 14
3 Drainage 223866-DRG-100 223866-DRG-101 223866-DRG-102 223866-DRG-103 223866-DRG-104
Details of Drainage Works Details of Drainage Works Details of Drainage Works Layout Plan - Gas Fired Power Station Process Area Site - Proposed Drainage Schedule
Review Review Review Review Review
30 Sep 16 30 Sep 16 30 Sep 16 30 Sep 16 30 Sep 16
VI Transformer Blast Wall 236981/PWS/DR1/XFMR/GA/001
Transformer Foundation & Blast Wall General Arrangement (Sheet 1 of 2)
Issue for Approval
30 Apr 17
236981/PWS/DR1/XFMR/GA/002
Transformer Foundation & Blast Wall General Arrangement (Sheet 2 of 2)
Preliminary
11 Jul 16
236981/PWS/DR1/XFMR/RC/001
Transformer Foundation & Blast Wall RC Drawing (Sheet 1 of 2)
Issue for Approval
21 Apr 17
236981/PWS/DR1/XFMR/RC/002
Transformer Foundation & Blast Wall RC Drawing (Sheet 2 of 2)
Issue for Approval
21 Apr 17
V Pump House 23698110/MPS/GA/001 23698110/RPS/GA/001
CCGT Pumping Station Layout Regas Pumping Station Layout
VI Seawater Intake Cooling Water System Options Scoping Cooling Water System Hydralic Analysis Layout of Power Plant Cooling Water Intake Chamber Layout of Regas Intake Chamber
VII Kanan Hydropower Project Geohazard Desk Study & Seismic Assessment Technical Proposal of Water Supply Pipeline from Hydropower Site to Manila
Rev 4
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status
Forwarded Rev A to Dominic & Toto on 29 Sep 15
Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15
Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 3 Oct 14
Forwarded Rev B to Dominic & Toto on 29 Sep 15 Forwarded Rev A to Dominic & Toto on 29 Sep 15 ***Forwarded Rev A Extraction to Freyssinet on 5 Mar 13 ****Forwarded Rev A Extraction to VSL on 14 May 13
Forwarded Rev A to Dominic & Toto on 29 Sep 15 Forwarded Rev A to Dominic & Toto on 29 Sep 15 Forwarded Rev A to Dominic & Toto on 29 Sep 15 ***Forwarded Rev A Extraction to Freyssinet on 5 Mar 13 ****Forwarded Rev A Extraction to VSL on 14 May 13 Forwarded Rev A to Dominic & Toto on 29 Sep 15
* Forwarded Rev A to GTT on 27 Sep 12 Forwarded Rev A to Dominic & Toto on 29 Sep 15 Forwarded Rev B to Dominic & Toto on 29 Sep 15 Forwarded Rev B to Dominic & Toto on 29 Sep 15 Forwarded Rev B to Dominic & Toto on 29 Sep 15 Forwarded Rev A to Dominic & Toto on 29 Sep 15
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Forward Rev C to Dominic & Toto on 4 Feb 15 Rev B Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 **** Forwarded Rev A to VSL on 14 May 13 Rev 3 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 ***Forwarded Rev 3 to Freyssinet on 5 Mar 13 Rev 2 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 Rev B Soft & Hard copies given to Mr. Cheung on 01 Jan 13 IFR Soft & Hard copies given to Mr. Cheung on 01 Sep 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 **** Forwarded Rev A to VSL on 14 May 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 * Forwarded Rev 1 to GTT on 22 Sep 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 15 Sep12 Rev A Soft & Hard copies given to Mr. Cheung on 19 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 2 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 3 Soft & Hard copies given to Mr. Cheung on 2 Jan 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ** Forwarded Rev 1 to Justin on 14 Dec 12 & 22 Nov 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev B Soft & Hard copies given to Mr. Cheung on 6 Feb 14 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Forwarded Rev B to Dominic & Toto on 29 Sep 15 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev B Soft & Hard copies given to Mr. Cheung on 4 Feb 14 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ** Forwarded Rev 1 to Justin on 14 Dec 12 & 22 Nov 12 Rev 2 Soft & Hard copies given to Mr. Cheung on 10 Jan 13 ***Forwarded Rev 2 to Freyssinet on 5 Mar 13 **** Forwarded Rev 2 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ** Forwarded Rev 1 to Justin on 14 Dec 12 & 22 Nov 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 16 May 12 ***Forwarded Rev 1 to Freyssinet on 5 Mar 13 **** Forwarded Rev 1 to VSL on 14 May 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Rev 3 Soft & Hard copies given to Mr. Cheung on 6 Feb 14 Rev 2 Soft & Hard copies given to Mr. Cheung on 22 Feb 13 Rev 2 Soft & Hard copies given to Mr. Cheung on 6 Feb 12 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Forward Rev 2 to PBL on 7 Apr 2017
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Rev 2 was received from Arup on 18 Jun 2016 Rev 1 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Rev 2 was received from Arup on 18 Jun 2016 Rev 1 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Rev 2 was received from Arup on 18 Jun 2016 Rev 1 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Rev 2 was received from Arup on 18 Jun 2016 Rev 1 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Forward Rev 1 to Toto & Diana on 6 Dec 16 Rev 2 was received from Arup on 18 Jun 2016 Rev 2 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Forward Rev 1 to Toto & Diana on 6 Dec 16 Rev 2 was received from Arup on 18 Jun 2016 Rev 2 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Forward Rev 1 to Toto & Diana on 6 Dec 16 Rev 2 was received from Arup on 18 Jun 2016 Rev 2 was received from Arup on 1 Jun 2016
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Forward Rev 1 to Toto & Diana on 6 Dec 16 Rev 2 was received from Arup on 18 Jun 2016 Rev 2 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Forward Rev 1 to Toto & Diana on 6 Dec 16 Rev 2 was received from Arup on 18 Jun 2016 Rev 2 was received from Arup on 1 Jun 2016 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev A to PBL on 7 Apr 2017 Forward Rev 1 to Toto & Diana on 6 Dec 16 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 2 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Rev 2 was received from Arup on 18 Jun 2016 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to PBL on 7 Apr 2017 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15 Forward Rev 1 to Dominic & Toto on 4 Feb 15
Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 2 Soft & Hard copies given to Mr. Cheung on 2 Jan 13 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 2 Soft & Hard copies given to Mr. Cheung on 2 Jan 13 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 15 Sep 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 ** Forwarded Rev 1 to Justin on 14 Dec 12 & 22 Nov 12 Rev A Soft & Hard copies given to Mr. Cheung on 24 Apr 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev A Soft & Hard copies given to Mr. Cheung on 07 Aug 13 Rev 1 Soft & Hard copies given to Mr. Cheung on 19 Oct 12 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Forwarded Rev 2 to Dominic & Toto on 29 Sep 15 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12 Rev 1 Soft & Hard copies given to Mr. Cheung on 29 Oct 12
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status
Forwarded Rev B to Dominic & Toto on 29 Sep 15
Forwarded Rev 2 to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15
Rev 1 Softcopy has been forwarded to site by Mr. Cheung Rev 1 Softcopy forwarded to Dominic & Toto on 22 Dec 14 Rev 1 Softcopy forwarded to Dominic & Toto on 22 Dec 14
Forwarded Rev 1 to Dominic & Toto on 29 Sep 15
Forwarded Rev 2 to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15
29 Jun 2017 Date of Deliverable Rev 5
Status
Rev 6
Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15 Forwarded IFR to Dominic & Toto on 29 Sep 15
Obsoleted Obsoleted Obsoleted Obsoleted 31 Jul 14
Forwarded Rev 5 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Forwarded Rev 4 to Dominic & Toto on 29 Sep 15 Forwarded Rev 3 to Dominic & Toto on 29 Sep 15 Rev 0 Softcopy has been forwarded to site by Mr. Cheung Rev 0 Softcopy has been forwarded to site by Mr. Cheung Rev 0 Softcopy has been forwarded to site by Mr. Cheung Obsoleted Obsoleted Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Nov 12 Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Nov 12
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status
Forwarded Rev 0 to Dominic & Toto on 29 Sep 15 Forwarded Rev 0 to Dominic & Toto on 29 Sep 15 Forwarded Rev 0 to Dominic & Toto on 29 Sep 15 Forwarded Rev 0 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft copies given to Mr. Cheung on 30 May 14 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft copies given to Mr. Cheung on 30 May 14 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft copies given to Mr. Cheung on 30 May 14 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft copies given to Mr. Cheung on 30 May 14 Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Obsoleted Obsoleted Obsoleted Rev 0 Softcopy has been forwarded to site by Mr. Cheung
Obsoleted Obsoleted Obsoleted Obsoleted Obsoleted Rev 0 Softcopy has been forwarded to site by Mr. Cheung
25 Jun 14
30 Oct 14 Rev 6 Soft copies forwarded to Dominics & Toto on 8 Jan 15 Rev 5 Soft copies forwarded to Dominics & Toto on 26 Jun 14
Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Rev 4 Soft copies forwarded to Dominics & Toto on 8 Jan 15
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Forwarded Rev 3 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Jul 12
Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Forwarded Rev 4 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Rev 2 Soft copies forwarded to Dominics & Toto on 8 Jan 15 Rev 1 Soft copies forwarded to Dominics & Toto on 26 Jun 14 Rev 0 Soft copy given to Mr. Cheung on 22 Apr 14 Forwarded Rev 3 to Dominic & Toto on 29 Sep 15 Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 2 Soft copies forwarded to Dominics & Toto on 8 Jan 15 Rev 1 Soft copies forwarded to Dominics & Toto on 26 Jun 14 Rev 0 Soft copy given to Mr. Cheung on 22 Apr 14 Rev 0 Soft copy given to Mr. Cheung on 22 Apr 14 Rev 1 Softcopy forwarded to Dominic & Toto on 19 Dec 14 Rev 0 Soft copy given to Mr. Cheung on 22 Apr 14 Rev 0 Soft copy given to Mr. Cheung on 10 Apr 14 Rev 0 Soft copy given to Mr. Cheung on 10 Apr 14
Rev 0 Hardcopy only. No Softcopy available Rev 0 Hardcopy only. No Softcopy available Forwarded Rev 1 to Dominic & Toto on 29 Sep 15 Rev 1 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Forwarded Rev 2 to Dominic & Toto on 29 Sep 15 Rev 1 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Forwarded Rev 2 to Dominic & Toto on 29 Sep 15 Rev 1 Soft & Hard copies given to Mr. Cheung on 1 Sep 12
Forwarded Rev 1 to Dominic & Toto on 29 Sep 15
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status
Forwarded Rev 2 to Dominic & Toto on 29 Sep 15 Rev 0 Soft copy given to Mr. Cheung on 26 May 14 Rev 0 Soft copy given to Mr. Cheung on 26 May 14
Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Soft & Hard copies given to Mr. Cheung on 1 Sep 12 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15 Rev 0 Softcopy was forwarded to Dom & Toto on 21 Sep 15
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status
Rev 1 Softcopy was forwarded to Diana & Toto on 25 Jul 16 Rev 0 Softcopy was forwarded to Diana & Manolo on 15 Mar 17 Rev 0 Softcopy was forwarded to Diana & Toto on 25 Jul 16 Rev A Softcopy was forwarded to Diana & Toto on 25 Jul 16 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 3 softcopy was forwarded to PBL in 2014 Rev 2 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 2 softcopy was forwarded to PBL in 2015 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014
29 Jun 2017 Date of Deliverable Rev 5
Rev 6
Status Rev 1 softcopy was forwarded to PBL in 2014 Rev 1 softcopy was forwarded to PBL in 2014 Rev 0 softcopy was received from Arup on 05 Jul 17 Rev 0 softcopy was received from Arup on 05 Jul 17 Rev 0 softcopy was received from Arup on 05 Jul 17 Rev 0 softcopy was received from Arup on 05 Jul 17 Rev 0 softcopy was received from Arup on 05 Jul 17
Rev 1 softcopy was forwarded to John & Nilo on 12 May 17 Rev 1 softcopy was received from Arup on 11 Jul 2016 Rev 1 softcopy was received from Arup on 21 Jul 2017 Rev 1 softcopy was received from Arup on 21 Jul 2017
Rev 2 softcopy was received from Arup on 02 Sep 2015 Rev 3 softcopy was received from Arup on 03 Nov 2015
Rev 2 softcopy was received from Arup on 21 Jul 2014
ORIGIN
DISCIPLINE
ARUP
CIVIL
ARUP
CIVIL
ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP
CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL
Document Reference
LNG Storage Tank Site Data 210427 -GEN -SP1 -GT 001 210427 -GEN -RP1 -GT 001 210427 -GEN -RP1 -GT 003 210427 -GEN -SP1 -GT 003 210427 -GEN -RP1 -GT 005
Specifications 210427 -GEN -SP1 -PG 001 219768 -GEN -SP1 -PG 002 210427 -GEN -SP1 -PG 003 210427 -GEN -SP1 -PG 004 210427 -GEN -SP1 -PG 005 210427 -GEN -SP1 -PG 006 210427 -TAN -SP1 -ST 001
Design Basis Documents 219768 -TAN -DB1 -PG 001 219768 -TAN -PR3 -GT 001 219768 -TAN -PR3 -ST 001 210427 -TAN -PR3 -ST 002 210427 -TAN -PR3 -ST 003 219768 -TAN -PR3 -GT 001
Design Reports and Calculations 219768 -TAN -RP1 -GT 001 219768-TAN -CA1 -GT 001 210427 -TAN -RP1 -ST 001 219768 -TAN -CA1 -ST 001 210427 -TAN -RP1 -ST 002 210427 -TAN -CA1 -ST 002 210427 -TAN -RP1 -ST 003 210427 -TAN -CA1 -ST 003 219768 -TAN -CA1 -ST 004
ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP
CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL
210427 -TAN -CA1 -ST 005 219768 -TAN -CA1 -ST 006 210427 -TAN -CA1 -ST 007 210427 -TAN -CA1 -ST 008 210427 -TAN -CA1 -ST 009 210427 -TAN -RP1 -AN 001
Drawings - GA and Details General 219768 -TAN -DR1 -PG 001 219768 -TAN -DR1 -PG 002 219768-T1-DR1-GT-001 219768-T1-DR1-GT-002 219768 -TAN -DR1 -PG 003 219768 -TAN -DR1 -PG 004 219768 -TAN -DR1 -PG 005 219768 -TAN -DR1 -PG 006 Foundation and Base Slab 216768 -TAN -DR1 -ST 001 216768 -TAN -DR1 -ST 002 216768 -TAN -DR1 -ST 003 Wall and Ringbeam 219768 -TAN -DR1 -ST 010 210427 -TAN -DR1 -ST 011
210427 -TAN -DR1 -ST 012 210427 -TAN -DR1 -ST 013 210427 -TAN -DR1 -ST 014
ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP ARUP
CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL CIVIL
ARUP ARUP ARUP ARUP
CIVIL CIVIL CIVIL CIVIL
219768-DR1-ME-002
ARUP ARUP ARUP ARUP
CIVIL CIVIL CIVIL CIVIL
219768-DR1-ME-003
ARUP ARUP
CIVIL CIVIL
219768-DR1-ME-004
210427 -TAN -DR1 -ST 015 210427 -TAN -DR1 -ST 016 210427 -TAN -DR1 -ST 017 210427 -TAN -DR1 -ST 018 210427 -TAN -DR1 -ST 021 210427 -TAN -DR1 -ST 022 210427 -TAN -DR1 -ST 023 210427 -TAN -DR1 -ST 024 210427 -TAN -DR1 -ST 026 219768-DR1-SK-006 Roof 219768 -TAN -DR1 -ST 030 219768 -TAN -DR1 -ST 031 219768 -TAN -DR1 -ST 032 Access Tower 219768-DR1-ME-001
219768-DR1-ME-004
ARUP ARUP
CIVIL CIVIL
ARUP ARUP ARUP
CIVIL CIVIL CIVIL
219768-DR1-ME-005
ARUP ARUP
CIVIL CIVIL
219768-DR1-ME-010
ARUP ARUP
CIVIL CIVIL
219768-DR1-ME-011
ARUP ARUP ARUP
CIVIL CIVIL CIVIL
219768-DR1-ME-012
219768-DR1-ME-601
ARUP
CIVIL
ARUP ARUP ARUP ARUP
CIVIL CIVIL CIVIL CIVIL
219768-DR1-ME-015
219768-DR1-ME-602
ARUP
CIVIL 219768-DR1-ME-016
219768-DR1-ME-603 219768-DR1-ME-017
219768-DR1-ME-604
219768-DR1-ME-018
219768-DR1-ME-605
219768-DR1-ME-019
219768-DR1-ME-606
219768-DR1-ME-020
219768-DR1-ME-021
219768-DR1-ME-022 219768-DR1-ME-025 219768-DR1-ME-028
219768-DR1-ME-031 219768-DR1-ME-035 219768-DR1-ME-036 219768-DR1-ME-040 219768-DR1-ME-100 219768-DR1-ME-101 219768-DR1-ME-102 219768-DR1-ME-103 219768-DR1-ME-104 219768-DR1-ME-105 219768-DR1-ME-200 219768-DR1-ME-201 219768-DR1-ME-202 219768-DR1-ME-203 219768-DR1-ME-204 219768-DR1-ME-205
219768-DR1-ME-206 219768-DR1-ME-207 219768-DR1-ME-208 219768-DR1-ME-209 219768-DR1-ME-210 219768-DR1-ME-211 219768-DR1-ME-212 219768-DR1-ME-213 219768-DR1-ME-214 210427 -TAN -DR1 -ST 061 210427 -TAN -DR1 -ST 062 210427 -TAN -DR1 -ST 063 210427 -TAN -DR1 -ST 064 210427 -TAN -DR1 -ST 065 210427 -TAN -DR1 -ST 066 210427 -TAN -DR1 -ST 067 Roof Platform 210427 -TAN -DR1 -ST 051 210427 -TAN -DR1 -ST 054
Drawings - Reinforcement Base Slab 219768 -TAN -DR1 -RC 001 219768 -TAN -DR1 -RC 002 219768 -TAN -DR1 -RC 003 219768 -TAN -DR1 -RC 004 210427 -TAN -DR1 -RC 011 210427 -TAN -DR1 -RC 012 210427 -TAN -DR1 -RC 013 210427 -TAN -DR1 -RC 014
Wall Reinforcement 210427 -TAN -DR1 -RC 020 210427 -TAN -DR1 -RC 021 210427 -TAN -DR1 -RC 022 210427 -TAN -DR1 -RC 023 210427 -TAN -DR1 -RC 024 210427 -TAN -DR1 -RC 025 210427 -TAN -DR1 -RC 026 210427 -TAN -DR1 -RC 027 210427 -TAN -DR1 -RC 028 210427 -TAN -DR1 -RC 029 210427 -TAN -DR1 -RC 030 210427 -TAN -DR1 -RC 031 210427 -TAN -DR1 -RC 033 210427 -TAN -DR1 -RC 035 210427 -TAN -DR1 -RC 036 210427 -TAN -DR1 -RC 036 210427 -TAN -DR1 -RC 037 210427 -TAN -DR1 -RC 038 210427 -TAN -DR1 -RC 039 Roof 219768 -TAN -DR1 -RC 041 219768 -TAN -DR1 -RC 042 219768 -TAN -DR1 -RC 051
219768 -TAN -DR1 -RC 052 219768 -TAN -DR1 -RC 053 219768 -TAN -DR1 -RC 054 Tower and Platforms 210427 -TAN -DR1 -RC 091 210427 -TAN -DR1 -RC 092 210427 -TAN -DR1 -RC 093 210427 -TAN -DR1 -RC 094 210427 -TAN -DR1 -RC 095 210427 -TAN -DR1 -RC 096 210427 -TAN -DR1 -RC 097 210427 -TAN -DR1 -RC 098 Other Drawings DR1-ME-001 DR1-ME-003 DR1-ME-004 DR1-ME-010 DR1-ME-011 DR1-ME-015 DR1-ME-016 DR1-ME-020 DR1-ME-021 DR1-ME-025 DR1-ME-026 DR1-ME-030
LNG Jetty Site Data 210427 -GEN -SP1 -GT 002 210427 -GEN -RP1 -GT 002 210427 -GEN -RP1 -GT 004 210427 -GEN -RP1 -MA 001 SPEC/MGI/001 SPEC/223866/G004 SPEC/223866/M002 210427 -GEN -RP1 -MA 002
Specifications 223866-JET-SP1-GT-001 210427 -JET -SP1 -MA 001
210427 -JET -SP1 -MA 004
Design Basis Documents
REP/223866/S005 210427 -JET -DB1 -PG 001 210427 -JET -PR3 -ST 002 210427 -JET -PR3 -ST 001 210427 -JET -PR3 -ST 002 210427 -JET -PR3 -ST 003 210427 -JET -PR3 -ST 004 210427 -JET -PR3 -AN 001 REP/223866/M001 REP/223866/M005 REP/223866/M004 REP/223866/M006 REP/223866/M011 REP/223866/S009 REP/223866/S010 REP/223866/S012 REP/223866/S013 223866-20/CKC 223866-00/JT 223866-20/CKC/BFT 223866-00/JT
Design Reports and Calculations 210427 -JET -RP1 -GT 001 210427 -JET -CA1 -GT 001 210427 -JET -RP1 -ST 001 210427 -JET -CA1 -ST 001 210427 -JET -CA1 -ST 003 210427 -JET -RP1 -ST 004 210427 -JET -CA1 -ST 004 210427 -JET -RP1 -AN 001
Drawings - GA and Details General 210427 -JET -DR1 -PG 002 223866_JET_DR1_SK_107 223886-JET -DR1-GT-001 223886-JET -DR1-GT-002 223886-JET -DR1-GT-003 210427 -JET -DR1 -GT 003 223866/GEN/001 223866/GEN/002 223866/GEN/003 223866/GEN/004 223866/GEN/010
223866/GEN/011 223866/GEN/012 223886/SPN/600 223866/SPN/601 223886/SPN/610 223886/SPN/611 Embankment 210427 -JET -DR1 -GT 011 210427 -JET -DR1 -GT 012 210427 -JET -DR1 -GT 013 210427 -JET -DR1 -GT 014 210427 -JET -DR1 -GT 015 210427 -JET -DR1 -GT 016 210427 -JET -DR1 -GT 017 210427 -JET -DR1 -GT 018 210427 -JET -DR1 -GT 019 Abutment and Trestle 210427 -JET -DR1 -ST 021 210427 -JET -DR1 -ST 022 210427 -JET -DR1 -ST 023 210427 -JET -DR1 -ST 024 223866/CWY/700 223866/CWY/701 223866/CWY/702 223866/CWY/703 223866/TLE/100 223866/TLE/101 223866/TLE/102 223866/TLE/103 223866/TLE/101 223866/TLE/110 223866/TLE/111 223866/TLE/112 223866/TLE/120 210427 -JET -DR1 -ST 025 210427 -JET -DR1 -ST 026 210427 -JET -DR1 -ST 027 210427 -JET -DR1 -ST 028
210427 -JET -DR1 -ST 029 210427 -JET -DR1 -ST 030 210427 -JET -DR1 -ST 031 210427 -JET -DR1 -ST 032 223866/TKE/SK/202 223866/TLE/103 223866/TLE/123 223866/TLE/124 223866/TLE/125 223866/TLE/180 210427 -JET -DR1 -ST 036 210427 -JET -DR1 -ST 037 210427 -JET -DR1 -ST 038 210427 -JET -DR1 -ST 039 210427 -JET -DR1 -ST 040 210427 -JET -DR1 -ST 041 210427 -JET -DR1 -ST 042 210427 -JET -DR1 -ST 043 210427 -JET -DR1 -ST 044 Loading Platform
223866/LPT/200
210427 -JET -DR1 -ST 052 223866/LPT/202 210427 -JET -DR1 -ST 054 210427 -JET -DR1 -ST 055 223866/LPT/203 223866/LPT/204
223866/LPT/205 223866/LPT/213 223866/LPT/230
223866/LPT/230 223866/LPT/231 223866/LPT/232 223866/LPT/240 223866/LPT/241 210427 -JET -DR1 -ST 056 210427 -JET -DR1 -ST 057 210427 -JET -DR1 -ST 058 210427 -JET -DR1 -ST 059 210427 -JET -DR1 -ST 060 210427 -JET -DR1 -ST 061 210427 -JET -DR1 -ST 062 210427 -JET -DR1 -ST 063 210427 -JET -DR1 -ST 064 223866/JET/DR1/SK/106A 223866/JET/DR1/SK/106B Dolphins and Catwalks 223866/DAC/300 223886/DAC/301 223886/DAC/302 210427 -JET -DR1 -MA 071 210427 -JET -DR1 -MA 072 210427 -JET -DR1 -MA 073 210427 -JET -DR1 -MA 074 210427 -JET -DR1 -MA 075 223866/DAC/315 210427 -JET -DR1 -ST 081 210427 -JET -DR1 -ST 082 210427 -JET -DR1 -ST 083 210427 -JET -DR1 -ST 084 210427 -JET -DR1 -ST 085 210427 -JET -DR1 -ST 086 210427 -JET -DR1 -ST 087 210427 -JET -DR1 -ST 088 223866/DAC/316 223866/DAC/317 223866/DAC/318
210427 -JET -DR1 -ST 089 210427 -JET -DR1 -ST 090 210427 -JET -DR1 -ST 091 210427 -JET -DR1 -ST 092 223866/DAC/320 223866/DAC/330 223866/DAC/331 223866/DAC/332 223866/DAC/333 223866/DAC/341 223866/DAC/342 223866/DAC/343 210427 -JET -DR1 -ST 093 210427 -JET -DR1 -ST 094 210427 -JET -DR1 -ST 095 210427 -JET -DR1 -ST 096 210427 -JET -DR1 -ST 097 210427 -JET -DR1 -ST 098 223866/JET/DR1/SK/104 223866/JET/DR1/SK/105 Tug Berth 210427 -JET -DR1 -ST 101 210427 -JET -DR1 -ST 102 210427 -JET -DR1 -ST 103 210427 -JET -DR1 -ST 104 210427 -JET -DR1 -ST 105 210427 -JET -DR1 -ST 106
Drawings - Reinforcement Embankment 210427 -JET -DR1 -RC 001 210427 -JET -DR1 -RC 002 210427 -JET -DR1 -RC 003 210427 -JET -DR1 -RC 004 210427 -JET -DR1 -RC 005 210427 -JET -DR1 -RC 006 Abutment and Trestle 210427 -JET -DR1 -RC 011 210427 -JET -DR1 -RC 012 210427 -JET -DR1 -RC 013 210427 -JET -DR1 -RC 014 210427 -JET -DR1 -RC 015 210427 -JET -DR1 -RC 016
210427 -JET -DR1 -RC 017 210427 -JET -DR1 -RC 018 210427 -JET -DR1 -RC 019 210427 -JET -DR1 -RC 020 210427 -JET -DR1 -RC 021 210427 -JET -DR1 -RC 022 210427 -JET -DR1 -RC 023 210427 -JET -DR1 -RC 024 210427 -JET -DR1 -RC 025 210427 -JET -DR1 -RC 026 210427 -JET -DR1 -RC 027 210427 -JET -DR1 -RC 028 Loading Platform 210427 -JET -DR1 -RC 031 210427 -JET -DR1 -RC 032 210427 -JET -DR1 -RC 033 210427 -JET -DR1 -RC 034 210427 -JET -DR1 -RC 035 210427 -JET -DR1 -RC 036 210427 -JET -DR1 -RC 037 210427 -JET -DR1 -RC 038 210427 -JET -DR1 -RC 039 210427 -JET -DR1 -RC 040 210427 -JET -DR1 -RC 041 Dolphins 210427 -JET -DR1 -RC 051 210427 -JET -DR1 -RC 052 210427 -JET -DR1 -RC 053 210427 -JET -DR1 -RC 054 210427 -JET -DR1 -RC 055 210427 -JET -DR1 -RC 056 210427 -JET -DR1 -RC 057 210427 -JET -DR1 -RC 058 210427 -JET -DR1 -RC 059 210427 -JET -DR1 -RC 060 210427 -JET -DR1 -RC 061 210427 -JET -DR1 -RC 062 Tug Berth 210427 -JET -DR1 -RC 071 210427 -JET -DR1 -RC 072
Power Plant Foundation
Site Data 223866/PWS/DR1/GI/100 223866/PWS/DR1/GI/200 236981/MPS/DR1/FI/100
Foundation 236981/PWS/DR1/GEN/GN/001 236981/PWS/DR1/GEN/GN/002 236981/PWS/DR1/PB/X/011 236981/PWS/DR1/PB/X/021 236981/PWS/DR1/PB/X/022 236981/PWS/DR1/PB/GA/011 236981/PWS/DR1/PB/RC/011 236981/PWS/DR1/PB/RC/012 236981/PWS/DR1/PB/RC/021 236981/PWS/DR1/PB/RC/022 236981/PWS/DR1/AUX/GA/021 236981/PWS/DR1/AUX/GA/031 236981/PWS/DR1/AUX/GA/032 236981/PWS/DR1/AUX/GA/041 236981/PWS/DR1/AUX/GA/061 236981/PWS/DR1/AUX/GA/071 236981/PWS/DR1/AUX/GA/091 236981/PWS/DR1/AUX/GA/101 236981/PWS/DR1/AUX/GA/111 236981/PWS/DR1/AUX/GA/121 236981/PWS/DR1/AUX/GA/131 236981/PWS/DR1/AUX/GA/151 236981/PWS/DR1/AUX/GA/161 236981/PWS/DR1/AUX/GA/171 236981/PWS/DR1/AUX/RC/021 236981/PWS/DR1/AUX/RC/031 236981/PWS/DR1/AUX/RC/032 236981/PWS/DR1/AUX/RC/041 236981/PWS/DR1/AUX/RC/061 236981/PWS/DR1/AUX/RC/071 236981/PWS/DR1/AUX/RC/091 236981/PWS/DR1/AUX/RC/101 236981/PWS/DR1/AUX/RC/111 236981/PWS/DR1/AUX/RC/121 236981/PWS/DR1/AUX/RC/131
236981/PWS/DR1/AUX/RC/151 236981/PWS/DR1/AUX/RC/161 236981/PWS/DR1/AUX/RC/171
Drainage 223866-DRG-100 223866-DRG-101 223866-DRG-102 223866-DRG-103 223866-DRG-104
Transformer Blast Wall 236981/PWS/DR1/XFMR/GA/001 236981/PWS/DR1/XFMR/GA/002 236981/PWS/DR1/XFMR/RC/001 236981/PWS/DR1/XFMR/RC/002
Pump House 23698110/MPS/GA/001 23698110/RPS/GA/001
Seawater Intake
Kanan Hydropower Project
Title
Purpose IFR
Onshore GI and Testing Specification LNG Tank GI Interpretative Report Site Specific Seismic Hazard Assessment Onshore Topographic Survey Specification Topographic Report (by others) Geological Review Report Storage Tank Specification for Geophysical Investigation
Review
17 May 12
Review Review
22 Feb 12 26 Sep 12
Earthworks Specification Concrete Specification
Construction Review
Prestressing Specification Steelwork Specification Corrosion Protection Specification Onshore Piling Specification Roof Ariflift Specification LNG Tank - Civil Design Basis LNG Tank - Foundation Design Philosophy LNG Tank - Analysis and Design Philosophy LNG Tank - Design Philosophy - Roof LNG Tank - Design Philosophy - Tower and Platform LNG Tank - Seismic Design Philosophy
Review Review Review
Review
Calculations LNG Tank - Foundation Design Report LNG Tank - Foundation Design Calculations LNG Tank - Wall Design Report LNG Tank - Tank Design Calculations LNG Tank - Roof Design Report LNG Tank - Roof Design Calculations LNG Tank - Tower and Platform Design Report LNG Tank - Tower and Platform Design Calculations LNG Tank - Seismic Properties of tank
Review Review Review Review
Review
LNG Tank - Pile Design Calculations LNG Tank - Base Slab Design Calculations LNG Tank - Nonlinear Design Calculations LNG Tank - Thermal Calculation LNG Tank - Prestressed Anchor Analysis
Review Review Review Review Review
LNG Tank - Global Analysis Report
General Notes Site Layout and Location Plan LNG Tank 1 Site Investigation Layout Plan LNG Tank 1 Geophysical Survey Layout Plan Location of Bore Holes for Site Investigation Tank General Arrangement Typical Tank Section Reinforcing Bars Development Lengths Reinforcing Bars Splice Lengths
Base Slab General Arrangement Base Slab Details Sheet 1 Base Slab Details Sheet 2 Wall General Arrangement Wall Elevation - Sheet 1
Wall Elevation - Sheet 2 Wall Elevation - Sheet 3 Wall Elevation - Sheet 4
Construction Construction Construction Review Review Review Review Construction Review Construction Review Construction Review Construction Review Construction Review Review Construction Review Construction Construction Review Construction Construction Review Construction Review Construction Construction Review
01 Sep 12
Wall Details Wall Construction Access Opening Detail Wall Construction Access Temporary Closure Details Sheet 1 Wall Construction Access Temporary Closure Details Sheet 2 Pretress Layout - Sheet 1 Pretress Layout - Sheet 2 Pretress Layout - Sheet 3 Pretress Layout - Sheet 4 Butress Details Wall Prestress Roof General Arrangement Roof Details Sheet 1 Roof Details Sheet 2
Tank Outfitting Roof General Arrangement
Pump Platform Details Sheet 1
Construction Review Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Preliminary Review Review Review Review Review Review Review Construction Materials Ordering Review Review Construction
Pump Platform Details Sheet 2
Materials Ordering Review Review Construction
Pump Platform Details Sheet 3
Materials Ordering Review
Pump Platform Details Sheet 3 Review Construction Pump Platform Details Sheet 4
Materials Ordering Review Review
VSV Platform Details Sheet 1
Materials Ordering Review
VSV Platform Details Sheet 2
Materials Ordering Review
VSV Platform Details Sheet 3
Materials Ordering Review Construction Materials Ordering
Tank Outfitting External Access Stairway Sheet 1
Materials Ordering Review Review Construction Materials Ordering
Tank Outfitting External Access Stairway Sheet 2
Tank Outfitting External Access Stairway Sheet 3
Materials Ordering Review Review Construction Materials Ordering Materials Ordering Review Review Construction Materials Ordering
Tank Outfitting External Access Stairway Sheet 4
Materials Ordering Review Review Construction Materials Ordering
Tank Outfitting External Access Stairway Sheet 5
Tank Outfitting External Access Stairway Sheet 5
Materials Ordering Review Review Construction
Tank Outfitting Access Tower Pipe Support
PSV Platform Details Sheet 1
Materials Ordering Materials Ordering Review
PSV Platform Details Sheet 2
Materials Ordering Review
PSV Platform Details Sheet 3
Materials Ordering
Maintenance Platform 1 Details
Review Review
Maintenance Platform 2 Details
Materials Ordering Review
Maintenance Platform 3 Details Escape Ladder Details Sheet 1 Escape Ladder Details Sheet 2 Tank Outfitting External Access Stairway Sheet 5 Pipe Support Design Summary Sheet 1 Pipe Support Design Summary Sheet 2 Pipe Support Details 1 Pipe Support Details 2 Pipe Support Details 3 Pipe Support Details 4,5,6 & 7 General Notes for LNG Tank Piping External Steelwork Floor Beams & Bracing Connections Sheet 1 Floor Beams & Bracing Connections Sheet 2 Vertical Bracing Connections Bracing Connection Details Sheet 1 Bracing Connection Details Sheet 2
Materials Ordering Review Review Review Materials Ordering Review Review Review Review Review Review Review Review Work In Progress Review Work In Progress Review Work In Progress Review Work In Progress Review Work In Progress
Base Plates & Shear Keys Column & Beam Splices Knee Braces & Monorails Moment & Beam Over / Under Column Connections Welded Connections Stairs Handrails Details Grating & Floor Plate Details Sheet 1 Grating & Floor Plate Details Sheet 2 Access Tower GA Access Tower - Steel Framing Plans - Sheet 1 Access Tower - Steel Framing Plans - Sheet 2 Access Tower - Steel Steel Details - Sheet 1 Access Tower - Steel Steel Details - Sheet 2 Access Tower - Steel Stair Details - Sheet 1 Access Tower - Steel Stair Details - Sheet 2
Work In Progress Work In Progress Review Work In Progress Review Work In Progress Review Work In Progress Review Work In Progress Work In Progress Work In Progress Work In Progress
Roof Platform GA Roof Details Sheet 1 Roof Concrete Layout General Arrangement
Base Slab Bottom Reinforcement Base Slab Top Reinforcement Base Slab Reinforcement Details Sheet 1 Base Slab Reinforcement Details Sheet 2 Wall Starters Reinforcement - Sheet 1 Wall Starters Reinforcement - Sheet 2 K32 Cryogenic Bars in drawing Wall Starters Reinforcement - Sheet 3 Wall Starters Reinforcement - Sheet 4
Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review
Wall Reinforcement - Inner Face - Sheet 1 K25, K32 Cryogenic Bars in drawing Wall Reinforcement - Inner Face - Sheet 2 K25 Cryogenic Bars in drawing Wall Reinforcement - Inner Face - Sheet 3 K32 Cryogenic Bars in drawing Wall Reinforcement - Outer Face - Sheet 1 Wall Reinforcement - Outer Face - Sheet 2 Wall Reinforcement - Outer Face - Sheet 3 Wall Reinforcement - Outer Face - Sheet 4 Wall Reinforcement - Outer Face - Sheet 5 Wall Reinforcement - Outer Face - Sheet 6 Wall Reinforcement - Outer Face - Sheet 7 Wall Reinforcement - Outer Face - Sheet 8 Wall Reinforcement - Outer Face - Sheet 9 Wall Shear Reinforcement Wall Reinforcement - Details - Sheet 1 K32 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 2 Wall Reinforcement - Details - Sheet 2 K25, K32 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 3 K25, K32 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 4 K25 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 5 K25, K32 Cryogenic Bars in drawing Roof Slab Reinforcement Bottom Face Roof Reinforcement Top Face Roof Reinforcement Details Sheet 1
Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Construction Review Review Construction Review Construction Review Construction Review Construction Review Review Review Review Review
Roof Reinforcement Details Sheet 2 Roof Reinforcement Details Sheet 3 Roof Reinforcement Details Sheet 4
Review Review Review
Tower Foundation Reinforcement Details Platform Columns Reinforcement Details - Sheet 1 Platform Columns Reinforcement Details - Sheet 2 Platform Beam Reinforcement Details - Sheet 1 Platform Beam Reinforcement Details - Sheet 2 Platform Slab Reinforcement Details - Sheet 1 Platform Slab Reinforcement Details - Sheet 2 Platform Slab Reinforcement Details - Sheet 3 Tank Outfitting Foof General Arrangement Pump Platform Details Sheet 1 Pump Platform Details Sheet 2 Safety Valve Platform Details Sheet 1 Safety Valve Platform Details Sheet 2 Access Stairway And Pipe Support Tower Details Sheet 1 Access Stairway And Pipe Support Tower Details Sheet 2 Safety Valve Platform Details Sheet 1 Safety Valve Platform Details Sheet 2 Maintenance Platform Details Sheet 1 Maintenance Platform Details Sheet 2 Emergency Escape Details Sheet 1
Offshore GI and Testing Specification Offshore GI Interpretative Report Preliminary Offshore Geotechnical Desk Study Metocean Report Jetty Marine Geophysical Survey Specification Specification for Geophysical Investigation of Pipeline Route Topographical Survey Specification Bathymetric Report (by others) Onshore Piling Specification for Jetty Navigation Aids Specification Fender System Specification Mooring System Specification Docking System Specification
Review
30 Apr 12
Review Review Review
19 Apr 12 10 Dec 12 27 Apr 12
Draft Draft Draft
Design Basis Report LNG Jetty - Civil Design Basis LNG Jetty - Design Philosophy - Embankment LNG Jetty - Design Philosophy - Abutment and Trestle LNG Jetty - Design Philosophy - Loading Platform LNG Jetty - Design Philosophy - Dolphins and Catwalks LNG Jetty - Design Philosophy - Tug Berth LNG Jetty - Trestle and LP Analysis Philosophy Vessel Geometry Report Navigational Concept Design Metocean Modelling Report Wave and Current Load Report Dolphin Concept Design Loading Platform Calculation Report Trestle Concept Design Report Catwalk Concept Design Report Shoreline Protection Concept Design Report Note on Mooring Hooks File Note - Design of Marine Fendering Notes on Gangways Marine Loading Arm Elevation
Draft
08 Oct 12
Review Review Review Review Review Review Review Review Review
25 Apr 12 21 Aug 12 24 Aug 12 24 Aug 12 29 Aug 12 05 Oct 12 05 Oct 12 08 Oct 12 19 Nov 12 29 Jun 12 29 May 12 28 Jun 12 09 May 12
Review Review Review Review
26 Sep 13
Calculations LNG Jetty - Embankment Design Report LNG Jetty - Embankment Design Calculations LNG Jetty - Abutment and Trestle Design Report LNG Jetty - Abutment and Trestle Design Calculations LNG Jetty - Dolphins and Catwalks Design Calculations LNG Jetty - Tug Berth Design Report LNG Jetty - Tug Berth Design Calculations LNG Jetty - Trestle and LP Analysis Report
Site Layout and Location Plan Site Investigation Layout Plan Site Investigation Layout Plan - Sheet 1 Site Investigation Layout Plan - Sheet 2 Pipeline Geophysical Survey Layout Plan Layout of Site Investigation & Trials Master Layout Plan Project Layout Plan - Sheet 1 Project Layout Plan - Sheet 2 Project Layout Plan - Sheet 3 General Notes
Review Review Review Review Construction
01 Dec 12
Reinforcing Bars Development Lengths Reinforcing Bars Splice Lengths
Construction Construction
Manoevring And Berthing Areas - Aids To Navigation & Dredged Area Plan
Conceptual
Navigation Channel - Aids To Navigation & Dredged Area Plan Shoreline Protection General Layout Plan Pagbilao Shoreline Protection Details
Conceptual Conceptual Conceptual
Embankment Plan Layout and Sections - Sheet 1 Embankment Plan Layout and Sections - Sheet 2 Embankment Plan Layout and Sections - Sheet 3 Embankment Plan Layout and Sections - Sheet 4 Embankment Plan Layout and Sections - Sheet 5 Embankment Road Details Embankment Drainage Details Embankment Piperack Details Embankment Miscellaneous Details Abutment GA Abutment Sections Abutment Details Abutment Shore Protection Details Causeway Plan Causeway General Arrangement Details Dredging Layout Dredging Layout General Arrangement Details Trestle GA Trestle Deck Layout (Sheet 1 of 3) Trestle Deck Layout (Sheet 2 of 3) Trestle Deck Layout (Sheet 3 of 3) Trestle Functional Cross Section Trestle Abutment GA - Sheet 1 Trestle Abutment GA - Sheet 2 Trestle Abutment GA - Sheet 3 Trestle Piling Layout Trestle Pile Schedule and Details Trestle Pile Layout - Sheet 1 Trestle Pile Layout - Sheet 2 Trestle Pilecap Layout - Sheet 1
Review Review Review Review Review Conceptual Review Conceptual Review Conceptual Review Conceptual Conceptual Conceptual Conceptual Conceptual Construction
Trestle Pilecap Layout - Sheet 2 Trestle Pilecap Details - Sheet 1 Trestle Pilecap Details - Sheet 2 Trestle Pilecap Details - Sheet 3 Trestle Deck Level Options Trestle Deck Layout - Sheet 1 Trestle Deck Layout - Sheet 1 Trestle Deck Layout - Sheet 2 Trestle Deck Layout - Sheet 3 Trestle Pile Reinforcement Details Trestle Deck Layout - Sheet 4 Trestle Deck Layout - Sheet 5 Trestle Deck Layout - Sheet 6 Trestle Deck Layout - Sheet 7 Trestle Deck Layout - Sheet 8 Trestle Deck Details - Sheet 1 Trestle Deck Details - Sheet 2 Trestle Precast Beam Details - Sheet 1 Trestle Precast Beam Details - Sheet 2
Conceptual Conceptual Conceptual Conceptual Construction
Construction Loading Platform GA
Construction Preliminary Conceptual
Loading Platform Pile Schedule and Details Loading Platform Piling Layout
Construction Construction Preliminary Conceptual
Loading Platform Pile Cap Layout Loading Platform Pile Cap Details Loading Platform Deck Framing Loading Platform Deck Framing Section
Loading Platform and Loading Assumptions Loading Platform Pile Reinforcement Details Loading Platform Concrete Plinth Details
Preliminary Conceptual Construction Preliminary Conceptual Construction Review Review Construction Preliminary Construction
Loading Platform Concrete Plinth Details Concrete Plinth Details Concrete Plinth Details Loading Platform Pile Reinforcement Details Beam Reinforcement Details Loading Platform Deck Layout and Sections Loading Platform Deck Details - Sheet 1 Loading Platform Deck Details - Sheet 2 Loading Platform Precast Beam Details Loading Platform Topside Layout and Sections Loading Platform Topside Details - Sheet 1 Loading Platform Topside Details - Sheet 2 Loading Platform Control Room - Sheet 1 Loading Platform Control Room - Sheet 2 Loading Arm At +5.500mCD Option A Loading Arm At +7.000mCD Option B Dolphins and Catwalk GA Plan and Section of Typical Berthing Dolphin Plan and Section of Typical Mooring Dolphin Berth Layout LNG Mooring Arrangement Plan for Vessel 1 LNG Mooring Arrangement Plan for Vessel 2 LNG Mooring Arrangements Vertical Alignment Navigation Aids Details Mooring Dolphins Pile Reinforcement Details Mooring Dolphin - MD1 Mooring Dolphin - MD2 Mooring Dolphin - MD3 Mooring Dolphin - MD4 Mooring Dolphin - MD5 Mooring Dolphin - MD6 Mooring Dolphin - MD7 Mooring Dolphin - MD8 Berthing Dolphins Pile Reinforcement Details R.C. Details of Mooring Dolphin R.C. Details of Berthing Dolphin
Review Review Review Construction Review Review Construction Construction
Construction Conceptual Construction Conceptual Construction Conceptual
Construction
Construction Construction Construction
Breasting Dolphin - BD1 Breasting Dolphin - BD2 Breasting Dolphin - BD3 Breasting Dolphin - BD4 Typical Catwalk Catwalk Details Catwalk Details Typical Staircase Typical RC Details of Staircase Loading Platform Catwalk - Bearing Layout Plan (Sheet 1 of 2) Loading Platform Catwalk - Bearing Layout Plan (Sheet 2 of 2) Loading Platform Catwalk - Bearing Connection Detail Catwalks - CW1 and CW12 Catwalks - CW2 and CW11 Catwalks - CW3 and CW10 Catwalks - CW4 and CW9 Catwalks - CW5 and CW8 Catwalks - CW6 and CW7 Elevation Showing Design Vessels Fenders and Spring Lines (1 of 2) Elevation Showing Design Vessels Fenders and Spring Lines (2 of 2) Tug Berth GA Tug Berth Piling and Details Tug Berth Mooring and Berthing Details - Sheet 1 Tug Berth Mooring and Berthing Details - Sheet 2 Tug Berth Platforms and Stairs - Sheet 1 Tug Berth Platforms and Stairs - Sheet 2
Road Slab Reinforcement Piperack Reinforcement - Sheet 1 Piperack Reinforcement - Sheet 2 Embankment Drainage Details - Sheet 1 Embankment Drainage Details - Sheet 2 Miscellaneous Reinforcement Details Abutment Pilecap Reinforcement Details Abutmenet Wall Reinforcement Details - Sheet 1 Abutmenet Wall Reinforcement Details - Sheet 2 Abutmenet Wall Reinforcement Details - Sheet 3 Trestle Pilecap Reinforcement Details - Sheet 1 Trestle Pilecap Reinforcement Details - Sheet 2
Construction Conceptual Construction Construction Construction Construction Construction Construction Construction
Review Review
1 Aug 12 1 Aug 12
Trestle Pilecap Reinforcement Details - Sheet 3 Trestle Pilecap Reinforcement Details - Sheet 4 Trestle Precast Beam Reinforcement Details - Sheet 1 Trestle Precast Beam Reinforcement Details - Sheet 2 Trestle Precast Beam Reinforcement Details - Sheet 3 Trestle Precast Beam Reinforcement Details - Sheet 4 Trestle Road Reinforcement Details - Sheet 1 Trestle Road Reinforcement Details - Sheet 2 Trestle Piperack Reinforcement Details - Sheet 1 Trestle Piperack Reinforcement Details - Sheet 2 Trestle Passing Bay Reinforcement Details - Sheet 1 Trestle Passing Bay Reinforcement Details - Sheet 2 Loading Platform Pilecap Reinforcement Details - Sheet 1 Loading Platform Pilecap Reinforcement Details - Sheet 2 Loading Platform Precast Beam Reinforcement Details - Sheet 1 Loading Platform Precast Beam Reinforcement Details - Sheet 2 Loading Platform Precast Beam Reinforcement Details - Sheet 3 Loading Platfrom Deck Reinforcement Details - Sheet 1 Loading Platfrom Deck Reinforcement Details - Sheet 2 Loading Platform Topsides Column Details Loading Platform Topsides Beam Details Loading Platform Topsides Slab Details - Sheet 1 Loading Platform Topsides Slab Details - Sheet 2 Mooring Dolphins MD1 Reinforcement Details Mooring Dolphins MD2 Reinforcement Details Mooring Dolphins MD3 Reinforcement Details Mooring Dolphins MD4 Reinforcement Details Mooring Dolphins MD5 Reinforcement Details Mooring Dolphins MD6 Reinforcement Details Mooring Dolphins MD7 Reinforcement Details Mooring Dolphins MD8 Reinforcement Details Breasting Dolphins BD1 Reinforcement Details Breasting Dolphins BD2 Reinforcement Details Breasting Dolphins BD3 Reinforcement Details Breasting Dolphins BD4 Reinforcement Details Tug Berth Reinforcement Details - Sheet 1 Tug Berth Reinforcement Details - Sheet 2
Pagbilao Power Station Site Investigation Layout Plan
Review
Pagbilao Power Station Site Investigation Layout Plan for Transformers Pump Station, & Oil Interceptors
Review
CCGT Pumping Station & Re-gas Pumping Station Site Investigation Layout Plan
Review
Specification for Ground Investigation
Review
General Notes (Sheet 1 of 2) General Notes (Sheet 2 of 2) Anchor Bolt Details Anchor Bolt Sections & Details Anchor Bolt Sections & Details Gas Turbine Power Block Foundation Arrangement Gas Turbine Power Block Foundation R.C. Details (Sheet 1 of 2) Gas Turbine Power Block Foundation R.C. Details (Sheet 2 of 2) Gas Turbine Power Block Anchor Bolt Arrangement Generator Power Block Anchor Bolt Arrangement Diverter Damper Foundaiton Arrangement (Sheet 1 of 2) Rotor Air Cooler Foundation Rotor Cooler Air Pipe Support Foundation Arrangement Instrument Air Compressor Foundation Arrangement Electrical Package Foundation Arrangement CO2 Fire Cylinder Foundation Arrangement SFC & SEE Excitation Package Foundation Arrangement SFC Transformer Foundation Arrangement SEE Transformer Foundation Arrangement VT Surge Cubicle with SFC Switch Foundation Arrangement Control Oil Skid Foundation Arrangement Exhaust Diffuser Foundation Arrangement Fuel Gas Main Filter Separator Foundation Arrangement Generator Air Filter Foundation Arrangement Diverter Damper Foundation R.C. Details Rotor Air Cooler Foundation R.C. Details Rotor Cooler Air Pipe Support Foundation R.C. Details Instrument Air Compressor Foundation R.C. Details Electrical Package Foundation R.C. Details CO2 Fire Cylinder Foundation R.C. Details SFC & SEE Excitation Package Foundation R.C. Details SFC Transformer Foundation R.C. Details SEE Transformer Foundation R.C. Details VT Surge Cubicle with SFC Switch Foundation R.C. Details Control Oil Skid Foundation R.C. Details
Construction Construction Construction Construction Construction Construction Preliminary Construction Construction Construction Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary Preliminary
Exhaust Diffuser Foundation R.C. Details Fuel Gas Main Filter Separator Foundation R.C. Details Generator Air Filter Foundation R.C. Details Details of Drainage Works Details of Drainage Works Details of Drainage Works Layout Plan - Gas Fired Power Station Process Area Site - Proposed Drainage Schedule
Preliminary Preliminary Preliminary Review Review Review Review Review
Transformer Foundation & Blast Wall General Arrangement (Sheet 1 of 2)
Issue for Approval
Transformer Foundation & Blast Wall General Arrangement (Sheet 2 of 2)
Preliminary
Transformer Foundation & Blast Wall RC Drawing (Sheet 1 of 2)
Issue for Approval
Transformer Foundation & Blast Wall RC Drawing (Sheet 2 of 2)
Issue for Approval
CCGT Pumping Station Layout Regas Pumping Station Layout
Cooling Water System Options Scoping Cooling Water System Hydralic Analysis Layout of Power Plant Cooling Water Intake Chamber Layout of Regas Intake Chamber
wer Project Geohazard Desk Study & Seismic Assessment Technical Proposal of Water Supply Pipeline from Hydropower Site to Manila
Draft Draft
Review
PAGBILAO LNG HUB DELIVERABLE LIST ( ARUP 2013.08.07) Date of Deliverable Draft 1
Rev A
Rev B
Rev C
Rev 0
Rev 1
26 Sep 12
28 Jun 13 21 May 12 19 Sep 14
05 Apr 12 17 Apr 12 02 Oct 12
15 Sep 12 15 Sep 12 19 Oct 12
08 Feb 12
15 Sep 12
16 Apr 12 26 Mar 12
15 Sep 12 15 Sep 12
15 Jun 12
19 Oct 12
27 Jun 12
29 Oct 12
03 May 12
15 Sep 12
19 Oct 12
Rev 2
Rev 3
Rev 4
30 May 12 26 Jun 12 21 Jun 12
15 Sep 12 25 Oct 12 25 Oct 12
05 Dec 12 05 Dec 12 9 Mar 15
27 Feb 15
30 Jan 15 7 Aug 13 19 Apr 13 15 Sep 12 17 Jul 12 01 Sep 12
19 Oct 12 15 Sep 12
29 Oct 12
01 Jan 13
19 Apr 13 15 Sep 12 19 Apr 13 15 Sep 12 19 Apr 13 15 Sep 12 19 Apr 13 16 May 12
15 Sep 12
16 May 12 15 Sep 12
15 Sep 12
19 Apr 13
7 Aug 13 19 Oct 12 31 Jan 14 7 Aug 13 19 Oct 12 25 Mar 14 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 30 Jan 14 7 Aug 13 19 Oct 12
02 Jan 13
7 Aug 13 19 Oct 12 10 Jan 13 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 16 May 12 29 Oct 12 4 Feb 14 29 Oct 12
22 Feb 13 4 Feb 13
29 Oct 12 2 Apr 17 30 Jan 15 2 Apr 17 17 Jun 16 30 Jan 15 30 Jan 15 2 Apr 17 17 Jun 16 30 Jan 15 30 Jan 15 2 Apr 17 17 Jun 16 30 Jan 15
30 Jan 15 2 Apr 17 17 Jun 16 30 Jan 15 30 Jan 15 2 Apr 17 30 Jan 15 2 Apr 17 30 Jan 15 2 Apr 17 30 Jan 15 2 Apr 17 6 Oct 16 17 Jun 16 31 Dec 15 30 Jan 15 2 Apr 17 6 Oct 16 17 Jun 16 31 Dec 15 30 Jan 15 2 Apr 17 6 Oct 16 17 Jun 16 31 Dec 15 30 Jan 15 2 Apr 17 6 Oct 16 17 Jun 16 31 Dec 15 30 Jan 15 2 Apr 17 6 Oct 16
17 Jun 16 31 Dec 15 30 Jan 15 2 Apr 17 6 Oct 16 2 Apr 17 30 Jan 15 2 Apr 17 30 Jan 15 2 Apr 17 30 Jan 15 30 Jan 15 2 Apr 17 30 Jan 15 2 Apr 17 30 Jan 15 22 Sep 14 22 Sep 14 17 Jun 16 4 Apr 17 4 Apr 17 4 Apr 17 4 Apr 17 4 Apr 17 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15
30 Jan 15 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 4 Apr 17 30 Jan 15 30 Jan 15 30 Jan 15 30 Jan 15
19 Apr 13 15 Sep 12
02 Jan 13
19 Apr 13 15 Sep 12 19 Apr 13 15 Sep 12 19 Apr 13 15 Sep 12 19 Apr 13 19 Oct 12 19 Apr 13 19 Oct 12 19 Apr 13 19 Oct 12 19 Apr 13 19 Oct 12
02 Jan 13
7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 7 Aug 13 19 Oct 12 29 Oct 12 29 Oct 12 2 Jul 14 29 Oct 12
29 Oct 12 29 Oct 12 29 Oct 12
04 Jun 12
28 Aug 12
29 Aug 12
25 Feb 14 17 Oct 14 17 Oct 14
03 Jan 13
7 Jul 14
06 Aug 12
13 Aug 12
25 Jun 14 4 Jul 14
01 Aug 12 01 Aug 12
01 Sep 12 01 Sep 12 01 Sep 12 01 Sep 12 1 Feb 14
31 Jul 14 31 Jul 14 31 Jul 14
1 Feb 14 1 Feb 14 01 Oct 12 01 Sep 12 01 Nov 12 01 Nov 12
01 Oct 12
31 Jul 14 31 Jul 14 31 Jul 14 31 Jul 14 31 Jul 14 30 May 14 31 Jul 14 30 May 14 31 Jul 14 30 May 14 31 Jul 14 30 May 14 01 Sep 12 01 Oct 12 01 Oct 12 01 Oct 12 31 Mar 14
01 Sep 12 01 Sep 12 01 Sep 12 01 Sep 12 01 Sep 12 31 Mar 14
26 Feb 14 16 Oct 13 01 Sep 12 30 Oct 14 26 Feb 14 16 Oct 13 01 Jul 12
16 Oct 13 01 Sep 12 26 Feb 14 16 Oct 13 01 Sep 12 30 Oct 14 25 Jun 14 22 Apr 14 26 Feb 14 16 Oct 13 30 Oct 14
25 Jun 14 22 Apr 14 22 Apr 14 1 Jul 15 19 Dec 14 22 Apr 14 10 Apr 14 10 Apr 14
01 May 12 01 May 12
01 Sep 12
19 Mar 14 01 Sep 12 19 Mar 14
01 Sep 12
01 Sep 12 19 Mar 14
01 Sep 12
01 Sep 12
19 Mar 14
19 Mar 14 26 May 14 26 May 14
25 Jun 12
18 Sep 15 01 Sep 12 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15 18 Sep 15
30 Jun 14 30 Nov 16 30 Apr 14 14 Jul 16 15 Oct 14 15 Oct 14 15 Oct 14 15 Oct 14 15 Oct 14 30 Sep 14 30 Sep 14 15 Oct 14 15 Oct 14 15 Oct 14 30 Dec 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14 21 Nov 14
15 Oct 14
21 Nov 14 21 Nov 14 21 Nov 14 30 Sep 16 30 Sep 16 30 Sep 16 30 Sep 16 30 Sep 16
30 Apr 17 11 Jul 16 21 Apr 17 21 Apr 17
30 Jul 15 30 Jul 15
21 Jul 14
30 Oct 15
2013.08.07) DOCUMENT TYPE Rev 5
REVISION
Document Reference
Rev 6
LNG Storage Tank Site Data
Rev A
210427 -GEN -SP1 -GT 001 210427 -GEN -RP1 -GT 001 210427 -GEN -RP1 -GT 003 210427 -GEN -SP1 -GT 003 210427 -GEN -RP1 -GT 005
IFR IFR
Specifications 210427 -GEN -SP1 -PG 001 219768 -GEN -SP1 -PG 002 210427 -GEN -SP1 -PG 003 210427 -GEN -SP1 -PG 004 210427 -GEN -SP1 -PG 005 210427 -GEN -SP1 -PG 006 210427 -TAN -SP1 -ST 001
Design Basis Documents 219768 -TAN -DB1 -PG 001 219768 -TAN -PR3 -GT 001 219768 -TAN -PR3 -ST 001 210427 -TAN -PR3 -ST 002 210427 -TAN -PR3 -ST 003 219768 -TAN -PR3 -GT 001
Design Reports and Calculations 219768 -TAN -RP1 -GT 001 219768-TAN -CA1 -GT 001 210427 -TAN -RP1 -ST 001 219768 -TAN -CA1 -ST 001 210427 -TAN -RP1 -ST 002 210427 -TAN -CA1 -ST 002 210427 -TAN -RP1 -ST 003 210427 -TAN -CA1 -ST 003 219768 -TAN -CA1 -ST 004
210427 -TAN -CA1 -ST 005 219768 -TAN -CA1 -ST 006 210427 -TAN -CA1 -ST 007 210427 -TAN -CA1 -ST 008 210427 -TAN -CA1 -ST 009 210427 -TAN -RP1 -AN 001
Drawings - GA and Details General 219768 -TAN -DR1 -PG 001 219768 -TAN -DR1 -PG 002 219768-T1-DR1-GT-001 219768-T1-DR1-GT-002 219768 -TAN -DR1 -PG 003 219768 -TAN -DR1 -PG 004 219768 -TAN -DR1 -PG 005 219768 -TAN -DR1 -PG 006 Foundation and Base Slab 216768 -TAN -DR1 -ST 001 216768 -TAN -DR1 -ST 002 216768 -TAN -DR1 -ST 003 Wall and Ringbeam 219768 -TAN -DR1 -ST 010 210427 -TAN -DR1 -ST 011
210427 -TAN -DR1 -ST 012 210427 -TAN -DR1 -ST 013 210427 -TAN -DR1 -ST 014
210427 -TAN -DR1 -ST 015 210427 -TAN -DR1 -ST 016 210427 -TAN -DR1 -ST 017 210427 -TAN -DR1 -ST 018 210427 -TAN -DR1 -ST 021 210427 -TAN -DR1 -ST 022 210427 -TAN -DR1 -ST 023 210427 -TAN -DR1 -ST 024 210427 -TAN -DR1 -ST 026 219768-DR1-SK-006 Roof 219768 -TAN -DR1 -ST 030 219768 -TAN -DR1 -ST 031 219768 -TAN -DR1 -ST 032 Access Tower 219768-DR1-ME-001
219768-DR1-ME-002
219768-DR1-ME-003
219768-DR1-ME-004
219768-DR1-ME-004
219768-DR1-ME-005
219768-DR1-ME-010
219768-DR1-ME-011
219768-DR1-ME-012
219768-DR1-ME-601
219768-DR1-ME-015
219768-DR1-ME-602
219768-DR1-ME-016
219768-DR1-ME-603 219768-DR1-ME-017
219768-DR1-ME-604
219768-DR1-ME-018
219768-DR1-ME-605
219768-DR1-ME-019
219768-DR1-ME-606
219768-DR1-ME-020
219768-DR1-ME-021
219768-DR1-ME-022 219768-DR1-ME-025 219768-DR1-ME-028
219768-DR1-ME-031 219768-DR1-ME-035 219768-DR1-ME-036 219768-DR1-ME-040 219768-DR1-ME-100 219768-DR1-ME-101 219768-DR1-ME-102 219768-DR1-ME-103 219768-DR1-ME-104 219768-DR1-ME-105 219768-DR1-ME-200 219768-DR1-ME-201 219768-DR1-ME-202 219768-DR1-ME-203 219768-DR1-ME-204 219768-DR1-ME-205
219768-DR1-ME-206 219768-DR1-ME-207 219768-DR1-ME-208 219768-DR1-ME-209 219768-DR1-ME-210 219768-DR1-ME-211 219768-DR1-ME-212 219768-DR1-ME-213 219768-DR1-ME-214 210427 -TAN -DR1 -ST 061 210427 -TAN -DR1 -ST 062 210427 -TAN -DR1 -ST 063 210427 -TAN -DR1 -ST 064 210427 -TAN -DR1 -ST 065 210427 -TAN -DR1 -ST 066 210427 -TAN -DR1 -ST 067
210427 -TAN -DR1 -ST 051 210427 -TAN -DR1 -ST 054
Drawings - Reinforcement Base Slab 219768 -TAN -DR1 -RC 001 219768 -TAN -DR1 -RC 002 219768 -TAN -DR1 -RC 003 219768 -TAN -DR1 -RC 004 210427 -TAN -DR1 -RC 011 210427 -TAN -DR1 -RC 012 210427 -TAN -DR1 -RC 013 210427 -TAN -DR1 -RC 014
Wall Reinforcement 210427 -TAN -DR1 -RC 020 210427 -TAN -DR1 -RC 021 210427 -TAN -DR1 -RC 022 210427 -TAN -DR1 -RC 023 210427 -TAN -DR1 -RC 024 210427 -TAN -DR1 -RC 025 210427 -TAN -DR1 -RC 026 210427 -TAN -DR1 -RC 027 210427 -TAN -DR1 -RC 028 210427 -TAN -DR1 -RC 029 210427 -TAN -DR1 -RC 030 210427 -TAN -DR1 -RC 031 210427 -TAN -DR1 -RC 033 210427 -TAN -DR1 -RC 035 210427 -TAN -DR1 -RC 036 210427 -TAN -DR1 -RC 036 210427 -TAN -DR1 -RC 037 210427 -TAN -DR1 -RC 038 210427 -TAN -DR1 -RC 039 Roof 219768 -TAN -DR1 -RC 041 219768 -TAN -DR1 -RC 042 219768 -TAN -DR1 -RC 051
219768 -TAN -DR1 -RC 052 219768 -TAN -DR1 -RC 053 219768 -TAN -DR1 -RC 054 Tower and Platforms 210427 -TAN -DR1 -RC 091 210427 -TAN -DR1 -RC 092 210427 -TAN -DR1 -RC 093 210427 -TAN -DR1 -RC 094 210427 -TAN -DR1 -RC 095 210427 -TAN -DR1 -RC 096 210427 -TAN -DR1 -RC 097 210427 -TAN -DR1 -RC 098 Other Drawings DR1-ME-001 DR1-ME-003 DR1-ME-004 DR1-ME-010 DR1-ME-011 DR1-ME-015 DR1-ME-016 DR1-ME-020 DR1-ME-021 DR1-ME-025 DR1-ME-026 DR1-ME-030
LNG Jetty Site Data 210427 -GEN -SP1 -GT 002 210427 -GEN -RP1 -GT 002 210427 -GEN -RP1 -GT 004 210427 -GEN -RP1 -MA 001 SPEC/MGI/001 SPEC/223866/G004 SPEC/223866/M002 210427 -GEN -RP1 -MA 002
Specifications 223866-JET-SP1-GT-001 210427 -JET -SP1 -MA 001
210427 -JET -SP1 -MA 004
Design Basis Documents
REP/223866/S005 210427 -JET -DB1 -PG 001 210427 -JET -PR3 -ST 002 210427 -JET -PR3 -ST 001 210427 -JET -PR3 -ST 002 210427 -JET -PR3 -ST 003 210427 -JET -PR3 -ST 004 210427 -JET -PR3 -AN 001 REP/223866/M001 REP/223866/M005 REP/223866/M004 REP/223866/M006 REP/223866/M011 REP/223866/S009 REP/223866/S010 REP/223866/S012 REP/223866/S013 223866-20/CKC 223866-00/JT 223866-20/CKC/BFT 223866-00/JT
Design Reports and Calculations 210427 -JET -RP1 -GT 001 210427 -JET -CA1 -GT 001 210427 -JET -RP1 -ST 001 210427 -JET -CA1 -ST 001 210427 -JET -CA1 -ST 003 210427 -JET -RP1 -ST 004 210427 -JET -CA1 -ST 004 210427 -JET -RP1 -AN 001
Drawings - GA and Details
31 Jul 14
General 210427 -JET -DR1 -PG 002 223866_JET_DR1_SK_107 223886-JET -DR1-GT-001 223886-JET -DR1-GT-002 223886-JET -DR1-GT-003 210427 -JET -DR1 -GT 003 223866/GEN/001 223866/GEN/002 223866/GEN/003 223866/GEN/004 223866/GEN/010
223866/GEN/011 223866/GEN/012 223886/SPN/600 223866/SPN/601 223886/SPN/610 223886/SPN/611 Embankment 210427 -JET -DR1 -GT 011 210427 -JET -DR1 -GT 012 210427 -JET -DR1 -GT 013 210427 -JET -DR1 -GT 014 210427 -JET -DR1 -GT 015 210427 -JET -DR1 -GT 016 210427 -JET -DR1 -GT 017 210427 -JET -DR1 -GT 018 210427 -JET -DR1 -GT 019 Abutment and Trestle 210427 -JET -DR1 -ST 021 210427 -JET -DR1 -ST 022 210427 -JET -DR1 -ST 023 210427 -JET -DR1 -ST 024 223866/CWY/700 223866/CWY/701 223866/CWY/702 223866/CWY/703 223866/TLE/100 223866/TLE/101 223866/TLE/102 223866/TLE/103 223866/TLE/101 223866/TLE/110 223866/TLE/111 223866/TLE/112 223866/TLE/120 210427 -JET -DR1 -ST 025 210427 -JET -DR1 -ST 026 210427 -JET -DR1 -ST 027 210427 -JET -DR1 -ST 028
210427 -JET -DR1 -ST 029 210427 -JET -DR1 -ST 030 210427 -JET -DR1 -ST 031 210427 -JET -DR1 -ST 032 223866/TKE/SK/202 223866/TLE/103 223866/TLE/123 223866/TLE/124 223866/TLE/125 223866/TLE/180 210427 -JET -DR1 -ST 036 210427 -JET -DR1 -ST 037 210427 -JET -DR1 -ST 038 210427 -JET -DR1 -ST 039 210427 -JET -DR1 -ST 040 210427 -JET -DR1 -ST 041 210427 -JET -DR1 -ST 042 210427 -JET -DR1 -ST 043 210427 -JET -DR1 -ST 044 Loading Platform 30 Oct 14 25 Jun 14 223866/LPT/200
210427 -JET -DR1 -ST 052 223866/LPT/202 210427 -JET -DR1 -ST 054 210427 -JET -DR1 -ST 055 223866/LPT/203 223866/LPT/204
223866/LPT/205 223866/LPT/213 223866/LPT/230
223866/LPT/230 223866/LPT/231 223866/LPT/232 223866/LPT/240 223866/LPT/241 210427 -JET -DR1 -ST 056 210427 -JET -DR1 -ST 057 210427 -JET -DR1 -ST 058 210427 -JET -DR1 -ST 059 210427 -JET -DR1 -ST 060 210427 -JET -DR1 -ST 061 210427 -JET -DR1 -ST 062 210427 -JET -DR1 -ST 063 210427 -JET -DR1 -ST 064 223866/JET/DR1/SK/106A 223866/JET/DR1/SK/106B Dolphins and Catwalks 223866/DAC/300 223886/DAC/301 223886/DAC/302 210427 -JET -DR1 -MA 071 210427 -JET -DR1 -MA 072 210427 -JET -DR1 -MA 073 210427 -JET -DR1 -MA 074 210427 -JET -DR1 -MA 075 223866/DAC/315 210427 -JET -DR1 -ST 081 210427 -JET -DR1 -ST 082 210427 -JET -DR1 -ST 083 210427 -JET -DR1 -ST 084 210427 -JET -DR1 -ST 085 210427 -JET -DR1 -ST 086 210427 -JET -DR1 -ST 087 210427 -JET -DR1 -ST 088 223866/DAC/316 223866/DAC/317 223866/DAC/318
210427 -JET -DR1 -ST 089 210427 -JET -DR1 -ST 090 210427 -JET -DR1 -ST 091 210427 -JET -DR1 -ST 092 223866/DAC/320 223866/DAC/330 223866/DAC/331 223866/DAC/332 223866/DAC/333 223866/DAC/341 223866/DAC/342 223866/DAC/343 210427 -JET -DR1 -ST 093 210427 -JET -DR1 -ST 094 210427 -JET -DR1 -ST 095 210427 -JET -DR1 -ST 096 210427 -JET -DR1 -ST 097 210427 -JET -DR1 -ST 098 223866/JET/DR1/SK/104 223866/JET/DR1/SK/105 Tug Berth 210427 -JET -DR1 -ST 101 210427 -JET -DR1 -ST 102 210427 -JET -DR1 -ST 103 210427 -JET -DR1 -ST 104 210427 -JET -DR1 -ST 105 210427 -JET -DR1 -ST 106
Drawings - Reinforcement Embankment 210427 -JET -DR1 -RC 001 210427 -JET -DR1 -RC 002 210427 -JET -DR1 -RC 003 210427 -JET -DR1 -RC 004 210427 -JET -DR1 -RC 005 210427 -JET -DR1 -RC 006 Abutment and Trestle 210427 -JET -DR1 -RC 011 210427 -JET -DR1 -RC 012 210427 -JET -DR1 -RC 013 210427 -JET -DR1 -RC 014 210427 -JET -DR1 -RC 015 210427 -JET -DR1 -RC 016
210427 -JET -DR1 -RC 017 210427 -JET -DR1 -RC 018 210427 -JET -DR1 -RC 019 210427 -JET -DR1 -RC 020 210427 -JET -DR1 -RC 021 210427 -JET -DR1 -RC 022 210427 -JET -DR1 -RC 023 210427 -JET -DR1 -RC 024 210427 -JET -DR1 -RC 025 210427 -JET -DR1 -RC 026 210427 -JET -DR1 -RC 027 210427 -JET -DR1 -RC 028 Loading Platform 210427 -JET -DR1 -RC 031 210427 -JET -DR1 -RC 032 210427 -JET -DR1 -RC 033 210427 -JET -DR1 -RC 034 210427 -JET -DR1 -RC 035 210427 -JET -DR1 -RC 036 210427 -JET -DR1 -RC 037 210427 -JET -DR1 -RC 038 210427 -JET -DR1 -RC 039 210427 -JET -DR1 -RC 040 210427 -JET -DR1 -RC 041 Dolphins 210427 -JET -DR1 -RC 051 210427 -JET -DR1 -RC 052 210427 -JET -DR1 -RC 053 210427 -JET -DR1 -RC 054 210427 -JET -DR1 -RC 055 210427 -JET -DR1 -RC 056 210427 -JET -DR1 -RC 057 210427 -JET -DR1 -RC 058 210427 -JET -DR1 -RC 059 210427 -JET -DR1 -RC 060 210427 -JET -DR1 -RC 061 210427 -JET -DR1 -RC 062 Tug Berth 210427 -JET -DR1 -RC 071 210427 -JET -DR1 -RC 072
Power Plant Foundation
Site Data 223866/PWS/DR1/GI/100 223866/PWS/DR1/GI/200 236981/MPS/DR1/FI/100
Foundation 236981/PWS/DR1/GEN/GN/001 236981/PWS/DR1/GEN/GN/002 236981/PWS/DR1/PB/X/011 236981/PWS/DR1/PB/X/021 236981/PWS/DR1/PB/X/022 236981/PWS/DR1/PB/GA/011 236981/PWS/DR1/PB/RC/011 236981/PWS/DR1/PB/RC/012 236981/PWS/DR1/PB/RC/021 236981/PWS/DR1/PB/RC/022 236981/PWS/DR1/AUX/GA/021 236981/PWS/DR1/AUX/GA/031 236981/PWS/DR1/AUX/GA/032 236981/PWS/DR1/AUX/GA/041 236981/PWS/DR1/AUX/GA/061 236981/PWS/DR1/AUX/GA/071 236981/PWS/DR1/AUX/GA/091 236981/PWS/DR1/AUX/GA/101 236981/PWS/DR1/AUX/GA/111 236981/PWS/DR1/AUX/GA/121 236981/PWS/DR1/AUX/GA/131 236981/PWS/DR1/AUX/GA/151 236981/PWS/DR1/AUX/GA/161 236981/PWS/DR1/AUX/GA/171 236981/PWS/DR1/AUX/RC/021 236981/PWS/DR1/AUX/RC/031 236981/PWS/DR1/AUX/RC/032 236981/PWS/DR1/AUX/RC/041 236981/PWS/DR1/AUX/RC/061 236981/PWS/DR1/AUX/RC/071 236981/PWS/DR1/AUX/RC/091 236981/PWS/DR1/AUX/RC/101 236981/PWS/DR1/AUX/RC/111 236981/PWS/DR1/AUX/RC/121 236981/PWS/DR1/AUX/RC/131
236981/PWS/DR1/AUX/RC/151 236981/PWS/DR1/AUX/RC/161 236981/PWS/DR1/AUX/RC/171
Drainage 223866-DRG-100 223866-DRG-101 223866-DRG-102 223866-DRG-103 223866-DRG-104
Transformer Blast Wall 236981/PWS/DR1/XFMR/GA/001 236981/PWS/DR1/XFMR/GA/002 236981/PWS/DR1/XFMR/RC/001 236981/PWS/DR1/XFMR/RC/002
Pump House 23698110/MPS/GA/001 23698110/RPS/GA/001
Seawater Intake
Kanan Hydropower Project
DATE ISSUED
Title
26 Sep 12
22 Feb 12 26 Sep 12
Onshore GI and Testing Specification LNG Tank GI Interpretative Report Site Specific Seismic Hazard Assessment Onshore Topographic Survey Specification Topographic Report (by others) Geological Review Report Storage Tank Specification for Geophysical Investigation Earthworks Specification Concrete Specification Prestressing Specification Steelwork Specification Corrosion Protection Specification Onshore Piling Specification Roof Ariflift Specification LNG Tank - Civil Design Basis LNG Tank - Foundation Design Philosophy LNG Tank - Analysis and Design Philosophy LNG Tank - Design Philosophy - Roof LNG Tank - Design Philosophy - Tower and Platform LNG Tank - Seismic Design Philosophy LNG Tank - Foundation Design Report LNG Tank - Foundation Design Calculations LNG Tank - Wall Design Report LNG Tank - Tank Design Calculations LNG Tank - Roof Design Report LNG Tank - Roof Design Calculations LNG Tank - Tower and Platform Design Report LNG Tank - Tower and Platform Design Calculations LNG Tank - Seismic Properties of tank
LNG Tank - Pile Design Calculations LNG Tank - Base Slab Design Calculations LNG Tank - Nonlinear Design Calculations LNG Tank - Thermal Calculation LNG Tank - Prestressed Anchor Analysis LNG Tank - Global Analysis Report
General Notes Site Layout and Location Plan LNG Tank 1 Site Investigation Layout Plan LNG Tank 1 Geophysical Survey Layout Plan Location of Bore Holes for Site Investigation Tank General Arrangement Typical Tank Section Reinforcing Bars Development Lengths Reinforcing Bars Splice Lengths
Base Slab General Arrangement Base Slab Details Sheet 1 Base Slab Details Sheet 2 Wall General Arrangement Wall Elevation - Sheet 1
Wall Elevation - Sheet 2 Wall Elevation - Sheet 3 Wall Elevation - Sheet 4
Wall Details Wall Construction Access Opening Detail Wall Construction Access Temporary Closure Details Sheet 1 Wall Construction Access Temporary Closure Details Sheet 2 Pretress Layout - Sheet 1 Pretress Layout - Sheet 2 Pretress Layout - Sheet 3 Pretress Layout - Sheet 4 Butress Details Wall Prestress Roof General Arrangement Roof Details Sheet 1 Roof Details Sheet 2
Tank Outfitting Roof General Arrangement
Pump Platform Details Sheet 1
Pump Platform Details Sheet 2
Pump Platform Details Sheet 3
Pump Platform Details Sheet 3
Pump Platform Details Sheet 4
VSV Platform Details Sheet 1
VSV Platform Details Sheet 2
VSV Platform Details Sheet 3
Tank Outfitting External Access Stairway Sheet 1
Tank Outfitting External Access Stairway Sheet 2
Tank Outfitting External Access Stairway Sheet 3
Tank Outfitting External Access Stairway Sheet 4
Tank Outfitting External Access Stairway Sheet 5
Tank Outfitting External Access Stairway Sheet 5
Tank Outfitting Access Tower Pipe Support
PSV Platform Details Sheet 1
PSV Platform Details Sheet 2
PSV Platform Details Sheet 3 Maintenance Platform 1 Details Maintenance Platform 2 Details
Maintenance Platform 3 Details Escape Ladder Details Sheet 1 Escape Ladder Details Sheet 2 Tank Outfitting External Access Stairway Sheet 5 Pipe Support Design Summary Sheet 1 Pipe Support Design Summary Sheet 2 Pipe Support Details 1 Pipe Support Details 2 Pipe Support Details 3 Pipe Support Details 4,5,6 & 7 General Notes for LNG Tank Piping External Steelwork Floor Beams & Bracing Connections Sheet 1 Floor Beams & Bracing Connections Sheet 2 Vertical Bracing Connections Bracing Connection Details Sheet 1 Bracing Connection Details Sheet 2
Base Plates & Shear Keys Column & Beam Splices Knee Braces & Monorails Moment & Beam Over / Under Column Connections Welded Connections Stairs Handrails Details Grating & Floor Plate Details Sheet 1 Grating & Floor Plate Details Sheet 2 Access Tower GA Access Tower - Steel Framing Plans - Sheet 1 Access Tower - Steel Framing Plans - Sheet 2 Access Tower - Steel Steel Details - Sheet 1 Access Tower - Steel Steel Details - Sheet 2 Access Tower - Steel Stair Details - Sheet 1 Access Tower - Steel Stair Details - Sheet 2 Roof Platform GA Roof Details Sheet 1 Roof Concrete Layout General Arrangement
Base Slab Bottom Reinforcement Base Slab Top Reinforcement Base Slab Reinforcement Details Sheet 1 Base Slab Reinforcement Details Sheet 2 Wall Starters Reinforcement - Sheet 1 Wall Starters Reinforcement - Sheet 2 K32 Cryogenic Bars in drawing Wall Starters Reinforcement - Sheet 3 Wall Starters Reinforcement - Sheet 4
Wall Reinforcement - Inner Face - Sheet 1 K25, K32 Cryogenic Bars in drawing Wall Reinforcement - Inner Face - Sheet 2 K25 Cryogenic Bars in drawing Wall Reinforcement - Inner Face - Sheet 3 K32 Cryogenic Bars in drawing Wall Reinforcement - Outer Face - Sheet 1 Wall Reinforcement - Outer Face - Sheet 2 Wall Reinforcement - Outer Face - Sheet 3 Wall Reinforcement - Outer Face - Sheet 4 Wall Reinforcement - Outer Face - Sheet 5 Wall Reinforcement - Outer Face - Sheet 6 Wall Reinforcement - Outer Face - Sheet 7 Wall Reinforcement - Outer Face - Sheet 8 Wall Reinforcement - Outer Face - Sheet 9 Wall Shear Reinforcement Wall Reinforcement - Details - Sheet 1 K32 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 2 Wall Reinforcement - Details - Sheet 2 K25, K32 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 3 K25, K32 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 4 K25 Cryogenic Bars in drawing Wall Reinforcement - Details - Sheet 5 K25, K32 Cryogenic Bars in drawing Roof Slab Reinforcement Bottom Face Roof Reinforcement Top Face Roof Reinforcement Details Sheet 1
Roof Reinforcement Details Sheet 2 Roof Reinforcement Details Sheet 3 Roof Reinforcement Details Sheet 4 Tower Foundation Reinforcement Details Platform Columns Reinforcement Details - Sheet 1 Platform Columns Reinforcement Details - Sheet 2 Platform Beam Reinforcement Details - Sheet 1 Platform Beam Reinforcement Details - Sheet 2 Platform Slab Reinforcement Details - Sheet 1 Platform Slab Reinforcement Details - Sheet 2 Platform Slab Reinforcement Details - Sheet 3 Tank Outfitting Foof General Arrangement Pump Platform Details Sheet 1 Pump Platform Details Sheet 2 Safety Valve Platform Details Sheet 1 Safety Valve Platform Details Sheet 2 Access Stairway And Pipe Support Tower Details Sheet 1 Access Stairway And Pipe Support Tower Details Sheet 2 Safety Valve Platform Details Sheet 1 Safety Valve Platform Details Sheet 2 Maintenance Platform Details Sheet 1 Maintenance Platform Details Sheet 2 Emergency Escape Details Sheet 1
Offshore GI and Testing Specification Offshore GI Interpretative Report Preliminary Offshore Geotechnical Desk Study Metocean Report Jetty Marine Geophysical Survey Specification Specification for Geophysical Investigation of Pipeline Route Topographical Survey Specification Bathymetric Report (by others) Onshore Piling Specification for Jetty Navigation Aids Specification Fender System Specification Mooring System Specification Docking System Specification
Design Basis Report LNG Jetty - Civil Design Basis LNG Jetty - Design Philosophy - Embankment LNG Jetty - Design Philosophy - Abutment and Trestle LNG Jetty - Design Philosophy - Loading Platform LNG Jetty - Design Philosophy - Dolphins and Catwalks LNG Jetty - Design Philosophy - Tug Berth LNG Jetty - Trestle and LP Analysis Philosophy Vessel Geometry Report Navigational Concept Design Metocean Modelling Report Wave and Current Load Report Dolphin Concept Design Loading Platform Calculation Report Trestle Concept Design Report Catwalk Concept Design Report Shoreline Protection Concept Design Report Note on Mooring Hooks File Note - Design of Marine Fendering Notes on Gangways Marine Loading Arm Elevation LNG Jetty - Embankment Design Report LNG Jetty - Embankment Design Calculations LNG Jetty - Abutment and Trestle Design Report LNG Jetty - Abutment and Trestle Design Calculations LNG Jetty - Dolphins and Catwalks Design Calculations LNG Jetty - Tug Berth Design Report LNG Jetty - Tug Berth Design Calculations LNG Jetty - Trestle and LP Analysis Report
Site Layout and Location Plan Site Investigation Layout Plan Site Investigation Layout Plan - Sheet 1 Site Investigation Layout Plan - Sheet 2 Pipeline Geophysical Survey Layout Plan Layout of Site Investigation & Trials Master Layout Plan Project Layout Plan - Sheet 1 Project Layout Plan - Sheet 2 Project Layout Plan - Sheet 3 General Notes
Reinforcing Bars Development Lengths Reinforcing Bars Splice Lengths Manoevring And Berthing Areas - Aids To Navigation & Dredged Area Plan Navigation Channel - Aids To Navigation & Dredged Area Plan Shoreline Protection General Layout Plan Pagbilao Shoreline Protection Details Embankment Plan Layout and Sections - Sheet 1 Embankment Plan Layout and Sections - Sheet 2 Embankment Plan Layout and Sections - Sheet 3 Embankment Plan Layout and Sections - Sheet 4 Embankment Plan Layout and Sections - Sheet 5 Embankment Road Details Embankment Drainage Details Embankment Piperack Details Embankment Miscellaneous Details Abutment GA Abutment Sections Abutment Details Abutment Shore Protection Details Causeway Plan Causeway General Arrangement Details Dredging Layout Dredging Layout General Arrangement Details Trestle GA Trestle Deck Layout (Sheet 1 of 3) Trestle Deck Layout (Sheet 2 of 3) Trestle Deck Layout (Sheet 3 of 3) Trestle Functional Cross Section Trestle Abutment GA - Sheet 1 Trestle Abutment GA - Sheet 2 Trestle Abutment GA - Sheet 3 Trestle Piling Layout Trestle Pile Schedule and Details Trestle Pile Layout - Sheet 1 Trestle Pile Layout - Sheet 2 Trestle Pilecap Layout - Sheet 1
Trestle Pilecap Layout - Sheet 2 Trestle Pilecap Details - Sheet 1 Trestle Pilecap Details - Sheet 2 Trestle Pilecap Details - Sheet 3 Trestle Deck Level Options Trestle Deck Layout - Sheet 1 Trestle Deck Layout - Sheet 1 Trestle Deck Layout - Sheet 2 Trestle Deck Layout - Sheet 3 Trestle Pile Reinforcement Details Trestle Deck Layout - Sheet 4 Trestle Deck Layout - Sheet 5 Trestle Deck Layout - Sheet 6 Trestle Deck Layout - Sheet 7 Trestle Deck Layout - Sheet 8 Trestle Deck Details - Sheet 1 Trestle Deck Details - Sheet 2 Trestle Precast Beam Details - Sheet 1 Trestle Precast Beam Details - Sheet 2
Loading Platform GA
Loading Platform Pile Schedule and Details Loading Platform Piling Layout Loading Platform Pile Cap Layout Loading Platform Pile Cap Details Loading Platform Deck Framing Loading Platform Deck Framing Section
Loading Platform and Loading Assumptions Loading Platform Pile Reinforcement Details Loading Platform Concrete Plinth Details
Loading Platform Concrete Plinth Details Concrete Plinth Details Concrete Plinth Details Loading Platform Pile Reinforcement Details Beam Reinforcement Details Loading Platform Deck Layout and Sections Loading Platform Deck Details - Sheet 1 Loading Platform Deck Details - Sheet 2 Loading Platform Precast Beam Details Loading Platform Topside Layout and Sections Loading Platform Topside Details - Sheet 1 Loading Platform Topside Details - Sheet 2 Loading Platform Control Room - Sheet 1 Loading Platform Control Room - Sheet 2 Loading Arm At +5.500mCD Option A Loading Arm At +7.000mCD Option B Dolphins and Catwalk GA Plan and Section of Typical Berthing Dolphin Plan and Section of Typical Mooring Dolphin Berth Layout LNG Mooring Arrangement Plan for Vessel 1 LNG Mooring Arrangement Plan for Vessel 2 LNG Mooring Arrangements Vertical Alignment Navigation Aids Details Mooring Dolphins Pile Reinforcement Details Mooring Dolphin - MD1 Mooring Dolphin - MD2 Mooring Dolphin - MD3 Mooring Dolphin - MD4 Mooring Dolphin - MD5 Mooring Dolphin - MD6 Mooring Dolphin - MD7 Mooring Dolphin - MD8 Berthing Dolphins Pile Reinforcement Details R.C. Details of Mooring Dolphin R.C. Details of Berthing Dolphin
Breasting Dolphin - BD1 Breasting Dolphin - BD2 Breasting Dolphin - BD3 Breasting Dolphin - BD4 Typical Catwalk Catwalk Details Catwalk Details Typical Staircase Typical RC Details of Staircase Loading Platform Catwalk - Bearing Layout Plan (Sheet 1 of 2) Loading Platform Catwalk - Bearing Layout Plan (Sheet 2 of 2) Loading Platform Catwalk - Bearing Connection Detail Catwalks - CW1 and CW12 Catwalks - CW2 and CW11 Catwalks - CW3 and CW10 Catwalks - CW4 and CW9 Catwalks - CW5 and CW8 Catwalks - CW6 and CW7 Elevation Showing Design Vessels Fenders and Spring Lines (1 of 2) Elevation Showing Design Vessels Fenders and Spring Lines (2 of 2) Tug Berth GA Tug Berth Piling and Details Tug Berth Mooring and Berthing Details - Sheet 1 Tug Berth Mooring and Berthing Details - Sheet 2 Tug Berth Platforms and Stairs - Sheet 1 Tug Berth Platforms and Stairs - Sheet 2
Road Slab Reinforcement Piperack Reinforcement - Sheet 1 Piperack Reinforcement - Sheet 2 Embankment Drainage Details - Sheet 1 Embankment Drainage Details - Sheet 2 Miscellaneous Reinforcement Details Abutment Pilecap Reinforcement Details Abutmenet Wall Reinforcement Details - Sheet 1 Abutmenet Wall Reinforcement Details - Sheet 2 Abutmenet Wall Reinforcement Details - Sheet 3 Trestle Pilecap Reinforcement Details - Sheet 1 Trestle Pilecap Reinforcement Details - Sheet 2
Trestle Pilecap Reinforcement Details - Sheet 3 Trestle Pilecap Reinforcement Details - Sheet 4 Trestle Precast Beam Reinforcement Details - Sheet 1 Trestle Precast Beam Reinforcement Details - Sheet 2 Trestle Precast Beam Reinforcement Details - Sheet 3 Trestle Precast Beam Reinforcement Details - Sheet 4 Trestle Road Reinforcement Details - Sheet 1 Trestle Road Reinforcement Details - Sheet 2 Trestle Piperack Reinforcement Details - Sheet 1 Trestle Piperack Reinforcement Details - Sheet 2 Trestle Passing Bay Reinforcement Details - Sheet 1 Trestle Passing Bay Reinforcement Details - Sheet 2 Loading Platform Pilecap Reinforcement Details - Sheet 1 Loading Platform Pilecap Reinforcement Details - Sheet 2 Loading Platform Precast Beam Reinforcement Details - Sheet 1 Loading Platform Precast Beam Reinforcement Details - Sheet 2 Loading Platform Precast Beam Reinforcement Details - Sheet 3 Loading Platfrom Deck Reinforcement Details - Sheet 1 Loading Platfrom Deck Reinforcement Details - Sheet 2 Loading Platform Topsides Column Details Loading Platform Topsides Beam Details Loading Platform Topsides Slab Details - Sheet 1 Loading Platform Topsides Slab Details - Sheet 2 Mooring Dolphins MD1 Reinforcement Details Mooring Dolphins MD2 Reinforcement Details Mooring Dolphins MD3 Reinforcement Details Mooring Dolphins MD4 Reinforcement Details Mooring Dolphins MD5 Reinforcement Details Mooring Dolphins MD6 Reinforcement Details Mooring Dolphins MD7 Reinforcement Details Mooring Dolphins MD8 Reinforcement Details Breasting Dolphins BD1 Reinforcement Details Breasting Dolphins BD2 Reinforcement Details Breasting Dolphins BD3 Reinforcement Details Breasting Dolphins BD4 Reinforcement Details Tug Berth Reinforcement Details - Sheet 1 Tug Berth Reinforcement Details - Sheet 2
Pagbilao Power Station Site Investigation Layout Plan Pagbilao Power Station Site Investigation Layout Plan for Transformers Pump Station, & Oil Interceptors CCGT Pumping Station & Re-gas Pumping Station Site Investigation Layout Plan Specification for Ground Investigation General Notes (Sheet 1 of 2) General Notes (Sheet 2 of 2) Anchor Bolt Details Anchor Bolt Sections & Details Anchor Bolt Sections & Details Gas Turbine Power Block Foundation Arrangement Gas Turbine Power Block Foundation R.C. Details (Sheet 1 of 2) Gas Turbine Power Block Foundation R.C. Details (Sheet 2 of 2) Gas Turbine Power Block Anchor Bolt Arrangement Generator Power Block Anchor Bolt Arrangement Diverter Damper Foundaiton Arrangement (Sheet 1 of 2) Rotor Air Cooler Foundation Rotor Cooler Air Pipe Support Foundation Arrangement Instrument Air Compressor Foundation Arrangement Electrical Package Foundation Arrangement CO2 Fire Cylinder Foundation Arrangement SFC & SEE Excitation Package Foundation Arrangement SFC Transformer Foundation Arrangement SEE Transformer Foundation Arrangement VT Surge Cubicle with SFC Switch Foundation Arrangement Control Oil Skid Foundation Arrangement Exhaust Diffuser Foundation Arrangement Fuel Gas Main Filter Separator Foundation Arrangement Generator Air Filter Foundation Arrangement Diverter Damper Foundation R.C. Details Rotor Air Cooler Foundation R.C. Details Rotor Cooler Air Pipe Support Foundation R.C. Details Instrument Air Compressor Foundation R.C. Details Electrical Package Foundation R.C. Details CO2 Fire Cylinder Foundation R.C. Details SFC & SEE Excitation Package Foundation R.C. Details SFC Transformer Foundation R.C. Details SEE Transformer Foundation R.C. Details VT Surge Cubicle with SFC Switch Foundation R.C. Details Control Oil Skid Foundation R.C. Details
Exhaust Diffuser Foundation R.C. Details Fuel Gas Main Filter Separator Foundation R.C. Details Generator Air Filter Foundation R.C. Details Details of Drainage Works Details of Drainage Works Details of Drainage Works Layout Plan - Gas Fired Power Station Process Area Site - Proposed Drainage Schedule
Transformer Foundation & Blast Wall General Arrangement (Sheet 1 of 2) Transformer Foundation & Blast Wall General Arrangement (Sheet 2 of 2) Transformer Foundation & Blast Wall RC Drawing (Sheet 1 of 2) Transformer Foundation & Blast Wall RC Drawing (Sheet 2 of 2)
CCGT Pumping Station Layout Regas Pumping Station Layout
Cooling Water System Options Scoping Cooling Water System Hydralic Analysis Layout of Power Plant Cooling Water Intake Chamber Layout of Regas Intake Chamber
Geohazard Desk Study & Seismic Assessment Technical Proposal of Water Supply Pipeline from Hydropower Site to Manila
To be provided/ Pending Document