Valeo India Pvt Ltd
End of stage PDC
Gat #: 24,744 & 745, Village Lonikand,
review report Valeo Requirements file number Project / Description
2613597
Pune.
VRF date
20.06.2010
TG12 C133 Front Housing Supplier
M/s.MAXOP ENGINEERING
General Information PA/FDP/MXP/2012-04
Index Index
A
Audit Date Date
15th Sep'12
FDP number
FDP/MXP/2012-12
Index
A
Date
15th Sep'12
Description
Objectives
Initial process audit number Follow-up process audit nbr
Full Day Production results Results
Acceptable
Production rate (pcs/h)
78 Pcs / Hr
Change-over time
45 Minutes
Y Y Y Y
2
Y
Quantity of produced parts
300
FDP time length
1 Shift
1 Shift
Comments
1397 Pcs / Day with 85% Efficiency
MTBF Rejects (ppm) Number of operators trained
Mr.Santosh KUMAR-4.5 Yrs experience.
DETAILS and ANALYSIS of NON CONFORMITIES Defect
Quantity
Root cause
Non-Filling
Comments
Setting Rejection
COMMENTS / REMARKS 1
MR.ASHOK
2
MR.BALJEET SINGH
3
MR.RAJEEV MITTAL
MAXOP 2613597
Auto: Laddle / Die Coat / Extraction / Plunger Lub Side Core: 2 & Hydraullic Cylinder. Machine #:
HPDC #13
Machine Name: ZITAI 420T Material Used: ADC 12 Shot Weight: Part Weight:
723 / 726 gms
Cavity: 1
FINAL DECISION FOR FDP PQA engineer
Accepted
Date Signature
U.KALAI SELVAN 13th Sep'12
Refused
Valeo Requirements File FDP template
Valeo confidential No copy or distribution without authorization
Group project May 10th 2006
Valeo India Pvt Ltd
End of stage TRIMMING
Gat #: 24,744 & 745, Village Lonikand,
review report Valeo Requirements file number
2613597
Pune.
VRF date
20.06.2010
TG12 C133 Front Housing Supplier
Project / Description
M/s.MAXOP ENGINEERING
General Information PA/FDP/MXP/2012-04
Index Index
A
Audit Date Date
15th Sep'12
FDP number
FDP/MXP/2012-12
Index
A
Date
15th Sep'12
Description
Objectives
Initial process audit number Follow-up process audit nbr
Full Day Production results Quantity of produced parts
300
FDP time length
1 Shift
Results
Acceptable
20
N
Comments
Trimming die breakdown.
Production rate (pcs/h) Change-over time MTBF Rejects (ppm)
0
Number of operators trained
1
DETAILS and ANALYSIS of NON CONFORMITIES Defect
Quantity
Root cause
Comments
COMMENTS / REMARKS 1
MR.ASHOK
2
MR.BALJEET SINGH
3
MR.RAJEEV MITTAL
MAXOP 2613597
Machine #:
40T Hydrullic Press
Trimming Die Location pin & Orientation pin broken while processing. Reason: Wrong Loading of part. Name Plate + Valeo Property to be added.
FINAL DECISION FOR FDP PQA engineer
Accepted
Date Signature
U.KALAI SELVAN 13th Sep'12
Refused
Valeo Requirements File FDP template
Valeo confidential No copy or distribution without authorization
Group project May 10th 2006
Valeo India Pvt Ltd
End of stage FETTLING
Gat #: 24,744 & 745, Village Lonikand,
review report Valeo Requirements file number Project / Description
2613597
Pune. 20.06.2010
VRF date
TG12 C133 Front Housing Supplier
M/s.MAXOP ENGINEERING
General Information PA/FDP/MXP/2012-04
Index Index
A
Audit Date Date
15th Sep'12
FDP number
FDP/MXP/2012-12
Index
A
Date
15th Sep'12
Description
Objectives
Initial process audit number Follow-up process audit nbr
Full Day Production results Quantity of produced parts
300
FDP time length
1 Shift
Results
Acceptable
1 Shift
Production rate (pcs/h)
37 Pcs / Hr
Change-over time
30 Minutes
30 Minutes
Y Y Y Y
Comments
662 Pcs / Day with 85% Efficiency.
MTBF 0
Rejects (ppm) Number of operators trained
4
4
Y Y
4 Operators for Fettling Operation.
DETAILS and ANALYSIS of NON CONFORMITIES Defect
Quantity
Root cause
Comments
COMMENTS / REMARKS 1
MR.RAJEEV MITTAL
2
MR.ASHOK
3
MR.BALJEET SINGH
MAXOP 2613597
Outer Periphery -Parting Line Flash - (Half Round Flat File) Side Windows +Oval Hole- (Round Hole Ø5mm). Ejector Face
(Half round flat file)
All Holes & core pin faces - (Round Hole Ø5mm). Part Wt. (After Runner Breakage): 723 / 726 gms. Part Wt. (After Fettling): 719 / 719 / 716 / 723 / 719 gms
FINAL DECISION FOR FDP PQA engineer
Accepted
Date Signature
U.KALAI SELVAN 13th Sep'12
Refused
Valeo Requirements File FDP template
Valeo confidential No copy or distribution without authorization
Group project May 10th 2006
Valeo India Pvt Ltd
End of stage Shot Blasting
Gat #: 24,744 & 745, Village Lonikand,
review report Valeo Requirements file number Project / Description
2613597
Pune. 20.06.2010
VRF date
TG12 C133 Front Housing Supplier
M/s.MAXOP ENGINEERING
General Information PA/FDP/MXP/2012-04
Index Index
A
Audit Date Date
15th Sep'12
FDP number
FDP/MXP/2012-12
Index
A
Date
15th Sep'12
Description
Objectives
Initial process audit number Follow-up process audit nbr
Full Day Production results Quantity of produced parts
300
FDP time length
1 Shift
Results
Acceptable
1 Shift 563
Production rate (pcs/h) Change-over time
30 Minutes
15 Minutes
Y Y Y Y
Comments
10041 Pcs / Day with 85% Efficiency.
MTBF Rejects (ppm)
0
0
Number of operators trained
1
1
Y Y
DETAILS and ANALYSIS of NON CONFORMITIES Defect
Quantity
Root cause
Comments
COMMENTS / REMARKS 1
MR.RAJEEV MITTAL
2
MR.ASHOK
3
MR.BALJEET SINGH
MAXOP 2613597
1. Master Sample made for shade appearance. 2. Barrel Type Shot Blasting Machine. (27" x 36") 3. Cycle kept: 4' 4. Shot size followed: 0.5mm / Stainless Steel (SS) 5. Dust Collector - Yes 6. Current: 20A Part Weight (after shot blasting): 727 / 727 / 724.5 / 709.5 / 726 gms.
FINAL DECISION FOR FDP PQA engineer
Accepted
Date Signature
U.KALAI SELVAN 13th Sep'12
Refused
Valeo Requirements File FDP template
Valeo confidential No copy or distribution without authorization
Group project May 10th 2006
Valeo India Pvt Ltd
End of stage CNC Turining
Gat #: 24,744 & 745, Village Lonikand,
review report Valeo Requirements file number
2613597
Project / Description
Pune. 20.06.2010
VRF date
TG12 C133 Front Housing Supplier
M/s.MAXOP ENGINEERING
General Information PA/FDP/MXP/2012-04
Index Index
A
Audit Date Date
15th Sep'12
FDP number
FDP/MXP/2012-12
Index
A
Date
15th Sep'12
Description
Objectives
Initial process audit number Follow-up process audit nbr
Full Day Production results Quantity of produced parts
300
FDP time length
1 Shift
Results
Acceptable
1 Shift 22
Production rate (pcs/h)
3 Hrs
Change-over time
Y Y Y Y
Comments
387 Pcs / Day with 85% Efficiency.
MTBF Rejects (ppm)
0
Number of operators trained
1
100 Pcs rejected during Maxop trial. 1
Y
Operator: Mr.Sanjay Setter: Mr.Mohammed Azad Ali
DETAILS and ANALYSIS of NON CONFORMITIES Defect
Quantity
Root cause
Comments
COMMENTS / REMARKS 1
MR.RAJEEV MITTAL
2
MR.ASHOK
3
MR.SANJEEV
MAXOP
4
MR.PRADEEP SARASWAT
2613597
5
MR.SHYAM SINGH
Master Sample made for CNC Operation. Machine: LMW - SMARturn Machine #: MSCL-07 Machine Sl#: 55-00522 (Yr: 2005 Mfg) Clamping Pressure: 6 Kg/Cm²
FINAL DECISION FOR FDP PQA engineer
Accepted
Date Signature
U.KALAI SELVAN 18th Aug'12
Refused
Valeo Requirements File FDP template
Valeo confidential No copy or distribution without authorization
Group project May 10th 2006
Valeo India Pvt Ltd
End of stage VMC Machining
Gat #: 24,744 & 745, Village Lonikand,
review report Valeo Requirements file number Project / Description
2613597
Pune. 20.06.2010
VRF date
TG12 C133 Front Housing Supplier
M/s.MAXOP ENGINEERING
General Information PA/FDP/MXP/2012-04
Index Index
A
Audit Date Date
15th Sep'12
FDP number
FDP/MXP/2012-12
Index
A
Date
15th Sep'12
Description
Objectives
Initial process audit number Follow-up process audit nbr
Full Day Production results Quantity of produced parts
300
FDP time length
1 Shift
Results
Acceptable
30 Pcs / Hr
Production rate (pcs/h) Change-over time
Y Y Y Y
Comments
542 Pcs / Day with 85% Efficiency.
MTBF Rejects (ppm) Number of operators trained
1
1
Y Y
Setting Rejection Operator: Mr.Dharmpaul SINGH Setter: Sushant SAHOO
DETAILS and ANALYSIS of NON CONFORMITIES Defect
Quantity
Root cause
Comments
COMMENTS / REMARKS 1
MR.RAJEEV MITTAL
Machined PART WEIGHT
2
MR.ASHOK
1
3
MR.SANJEEV
2
704gms
MAXOP
4
MR.PRADEEP SARASWAT
3
706gms
2613597
4
703gms
5
703gms
700gms
1. Master Sample made for VMC Operation. 2. Machine: brother - TC - R2B (cnc tapping center) 3. Machine #: MSVM - 10 4. M/c Sl #: 111139, Yr: 2010-03 5. 2 Pcs / Cycle 6. Station # - Not identified. 7. Clamping Pressure: 5 Kg/Cm² (Line pressure)
FINAL DECISION FOR FDP PQA engineer
Accepted
Date Signature
U.KALAI SELVAN 14th Sep'12
Refused
Valeo Requirements File FDP template
Valeo confidential No copy or distribution without authorization
Group project May 10th 2006
FDPR Process: TG12 C133 Front, Part #: 2613597 PDC Casting Machine:
Material:
ZITAI - 420T Machine Cold Chamber Brick Wall Holding Furnace - 450T Capacity ADC 12
As per agreed material.
Degassing:
Nitrogen Degassing Gas Spare maintained Spindle Spare Maintained 12.5 N2 pressure level maintained.
Process parameter:
Refer Valeo process Parameter sheet
Die coat:
Water base & Centralized Frequency: Each shot Process: Manually
Extraction: Manual unloading Die surface Treatment: While start-up : First Piece Approval: Shot Wt in gms
Runner Wt
Over Flow Wt
Part Wt
719 719 716 723 719 1st Operation: CNC Turning
2nd Operation VMC Machining Fix-1
Pre-drilling of M5 Tap Holes_8 Holes_Ø4.2 Drill (Carbide) M5 Tapping_Roll Tap_Tin Coated_5 Flute Spot Facing_End Mill_Ø25 Cutter Indexable-2 Flute_Insert Type Ø10.4 Drilling_Carbide_2 Flute Through Drain Holes drilling Ø6.7 - 2 Holes - HSS- 2 Flute ( Repassing) 1 Piece / Loading Refer "Standardized Work Combination Table" of VMC sequence.
Page: 7 of 8
FDPR Process: TG12 C133 Front, Part #: 2613597 Fix-2 Spot Facing x 2 - End Mill_Ø25 Cutter Indexable-2 Flute_Insert Type Ø12.7mm Drilling_2 Holes_Carbide_2 Flute_Through till bottom boss End. Both Fix1 & Fix2 loaded in same machine in single pallet. During mass production, this will be loaded on different machine.
Page: 8 of 8