PETROBEL
EGYPT
SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT CONTENTS
1.0 EXECUTIVE SUMMARY 1.1 1.2 1.3 1.4 1.5
PROJECT DESCRIPTION. REPORT PERIOD. OVERALL PROJECT PROGRESS SUMMARY. QHSE SUMMARY AREA OF CONCERN
2.0 ATTACHMENTS
PJC 01-B3274-0908
ATTACHMENT (01)
Planning portion of monthly external progress report
3467-200 Rev.0 06/07/2011
PETROBEL
EGYPT
SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT
PJC 01-B3274-0908
1.0 EXECUTIVE SUMMARY
3467-200 Rev.0 06/07/2011
PETROBEL
EGYPT
SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT
3467-200 Rev.0 06/07/2011
1.1 Project Description PETROBEL is considering the development of new gas field in the RAS EL BARR concession, in the west Nile Delta area (Mediterranean Sea). The gas field SETH is located in water depth 83.3 m in the Mediterranean Sea, 11km west of Denise A, at about 60km off the Egyptian costs, North East of Damietta and North West of Port Said. The production shall be delivered to EL-GAMIL plant. SETH development plan includes D&C of two wells (i.e. SETH West Shallow & SETH West Deep) plus two future wells (SETH East Shallow & SETH East Deep), with total production flow rate of 4.5 MMSCFD.
Project comprises of the following facilities: 1)
4-legged unmanned platform (namely SETH, in approx. 83 m of water).
2)
Topside facilities (minimum production facilities).
3)
Construction of new dedicated sea line 16”x11 km length.
4)
Installation of SSIV close to platform.
The battery limit of this project Subsea Tie-in at Tuna PLEM by installation of new Seth PLEM
Major Scope Contents • • • • • • • • •
Project Management & Control. Design for Piles, Jacket, Risers, J-tube & Pre drilling template. Design for Deck and TSF. Construction of Piles, Jacket, Risers, J-tube & Pre drilling template. Construction of Deck and TSF. Construction of Pipeline rigid and Spools. Procurement Service for Subsea Equipment (PLEM & SSIV). Load-out & Sea-fastening. Offshore Hook-up & Commissioning.
PJC 01-B3274-0908
1.2 Report Period: This progress report covers the Work Performed during June 2011 Till the Cut-Off Date 25, June2011.
PETROBEL
SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT
EGYPT
3467-200 Rev.0 06/07/2011
1.3 Overall Project Progress Summary
Item Description
RW
Planned
Actual
ENPPI
44.83%
5.8%
6.5%
PETROJET
41.56%
18.0%
22.2%
TECNOMARE
13.61%
37.7%
39.5%
Total
100.00%
15.2%
17.5%
1.4 QHSE SUMMARY • Project Quality Plan is issued and in place • Project Scope and Procedures is issued and in place • HSE PLAN for engineering is in place • Project audit schedule is in place (periodical audit) • Review of Quality, HSE management system in suppliers’ offers is under implementation 1.5 AREA OF CONCERN A) Engineering Activities • Electrical load trend is showing increase in demand. A technical meeting will be arranged upon issuing the Electrical Load Analysis Report in order to discuss the possible solutions. B) Procurement Activities • Due to some delays of bidders response, and in order to avoid impact of August holidays with suppliers, it is important to maintain target to place FOC’s for critical items before the end of July.
PJC 01-B3274-0908
C) Construction Activities • None.
PETROBEL
EGYPT
SETH OFFSHORE DEVELOPMENT MONTHLY PROGRESS REPORT
PJC 01-B3274-0908
2.0 ATTACHEMENTS
3467-200 Rev.0 06/07/2011
PAGE 17 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4. Attachments
GFL 003-0405
3467-200
PAGE 18 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.1. PROGRESS SUMMARY TABLES WITH RELEVANT S-CURVES
GFL 003-0405
3467-200
PAGE 19 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.1.1 Overall
GFL 003-0405
3467-200
3467-200, PTB, SETH DEVELOPMENT EPC PROJECT OVERALL PROGRESS AS OF 25-JUNE-11 ITEM DESCRIPTION
Relative Weight (%)
PLANNED %
ACTUAL %
ENPPI
44.83%
5.8%
6.5%
PETROJET
41.56%
18.0%
22.2%
TECNOMARE
13.61%
37.7%
39.5%
TOTAL
100.00%
15.2%
17.5%
Project No:3467‐200 PTB, Seth Development EPC Project
Progress Curve
Overall
As of : 25‐Jun‐11
100
90
Planned % =15.2 Actual % = 17.5
80
70
Progress % ess %
60
50
40
30
20
10
0 Mar/11
Apr/11
May/11
Jun/11
Jul/11
Aug/11
Sep/11
Oct/11
Nov/11
Dec/11
Jan/12
Feb/12
Mar/12
Apr/12
May/12
Jun/12
Jul/12
Time / Date Planned
Actual
Layout No. 1 Data'Nes System Release 2.21
PAGE 20 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.1.2 ENPPI
GFL 003-0405
3467-200
3467-200 PTB, SETH OFFSHORE DEVELOPMENT EPC PROJECT DELAY ANALYSIS AS OF 25-JUN-11 Discipline
Process
Pipipng
weighted delay % from Overall Project
Delay %
7.9
0.17
4.8
0.17
DELAYED ACTIVITIES Flame arrestor TER Safety equipment and life saving TER Fire Fighting package TER Injection fitting TER Insulation joint Injection fitting TER
PLANNED DATE EXPECTED DATE
Suppliers replies delays on ENPPI clarifications 23‐Jun‐11
15‐Jun‐11
21‐Jul‐11
24‐Jul‐11
Service water pump TER
Mechanical
Electrical
Instrumentation
7.2
0.08
5.9
0.11
8.4
0.20
7‐Jun‐11
Power system study Single line diagram Electrical cable list Choke valve TER Electrical hook‐up Drawing Hydraulic instruments layouts H d li i t t l t
10‐Jul‐11
Purchasing
Overall Project
4.0
0.07
15‐Jun‐11
20‐Jun‐11
8.4
0.11
0.9
Nouva oma (one of the bidder) request to submit ISO5199 pump instead of ASME B73.1 as originally request in MR. instead of ASME B73.1 as originally request in MR. Received from Nouva Oma complete reply on 1st clarification, his reply based on ISO 5199. Ruhrpumpen (one of the bidder) submit his reply on 1st clarification, his offer based on pump ASME B73.1 . Receive acceptance from PTB on evaluating both pump types ISO5199 and ASME B73.1
17‐Jul‐11
1‐Aug‐11
Delay is due to revised H&M balance issued during the detailed engineering phase ‐The offered valves have noise levels exceeding the enviromental Th ff d l h i l l di th i t l low ‐In progress Suppliers replies delays on ENPPI clarifications
13‐Jun‐11
Delay in receiving the commercial offers for the folloowing commodities:Safety equipment and life saving ; Flame arrestor; Fire Fighting package ; Injection fitting ; Choke valves ; Electro hydraulic wellhead control panel ; Wing valves & Service water pump Service water pump
Delay in receiving the technical offers due to suppliers response delay
In progress
Survival Module TER Offshore
CAUSE OF DELAY
12‐Jul‐11
Delay of issuance of TERs
23‐Jun‐11
26‐Jul‐11
Overall project progress is ahead ( 6.52 % vs.5.75 %) because the material supply progress is ahead (1.99 % vs. 00%)
Project No.:
3467-200
Progress Curve
SETH Offshore EPC Project Overall
As Of :
25-Jun-11
100 90
Planned % =
5.75
Actual
%=
6.52
1-May11
1-Jun11
80
Progress %
70 60
50 40 30 20 10 0 1-Mar11
1-Apr11
1-Jul-11 1-Aug11
1-Sep- 1-Oct-11 1-Nov11 11
1-Dec- 1-Jan-12 1-Feb11 12
1-Mar12
1-Apr12
1-May12
1-Jun12
1-Jul-12
Time / Date Actual
Planned
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Summary Report
SETH Offshore EPC Project
As Of :
25-Jun-11
ENPPI Item Description
Relative Weight
Planned %
Actual %
During %
W.P.2 DETAILED ENGINEERING
13.05%
38.38
32.60
7.78
W.P.3 PROCUREMENT SERVICES
3.33%
22.29
19.00
7.01
W.P.5 DECK AND TSF SUPPLY & FABRICATION
81.45%
0.00
1.99
1.99
W.P.9 OFFSHORE HOOK-UP & COMMISSIONING
2.16%
0.00
0.00
0.00
100.00%
5.75
6.51
2.87
Total
Thursday, June 30, 2011
Layout No. 1 Page 1 of 1
Data'Nes Systems, Release 2.21
Project No.:
3467-200
Progress Curve
SETH Offshore EPC Project As Of
Work Package
25-Jun-11
W.P.2 DETAILED ENGINEERING 100 90
Planned % = Actual
38.38
%=
32.60
May-11
Jun-11
80
70
Progress %
60 50 40 30
20 10 0 Mar-11
Apr-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Tim e / Date Actual
Planned
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.:
3467-200
Progress Curve
SETH Offshore EPC Project As Of
Work Package
25-Jun-11
W.P.3 PROCUREMENT SERVICES 100 90
Planned % = Actual
22.29
%=
19.27
May-11
Jun-11
80
70
Progress %
60 50 40 30
20 10 0 Mar-11
Apr-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Tim e / Date Actual
Planned
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.:
3467-200
Progress Curve
SETH Offshore EPC Project As Of
Work Package
25-Jun-11
W.P.5 DECK AND TSF SUPPLY & FABRICATION 100 90
Planned % = Actual
%=
0.00 1.99
80
70
Progress %
60 50 40 30
20 10 0 Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Tim e / Date Actual
Planned
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.:
3467-200
Progress Curve
SETH Offshore EPC Project As Of
Work Package
25-Jun-11
W.P.9 OFFSHORE HOOK-UP & COMMISSIONING 100 90
Planned % = Actual
%=
0.00 0.00
80
70
Progress %
60 50 40 30
20 10 0 Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Tim e / Date Actual
Planned
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Summary Report
SETH Offshore EPC Project
As Of :
25-Jun-11
ENPPI W.P.2 DETAILED ENGINEERING Item Description
Relative Weight
Planned %
Actual %
During %
PROCESS TECHNOLOGY DIVISION
16.98%
55.58
47.67
8.06
INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT
17.92%
47.16
38.74
17.79
PIPING ENGINEERING DIVISION
25.94%
28.58
23.76
3.69
ELECTRICAL ENGINEERING DIVISION
14.15%
43.90
38.00
7.97
OFFSHORE ENGINEERING DIVISION
12.74%
17.00
13.00
0.00
MECHANICAL ENGINEERING DEPARTMENT
8.49%
46.42
39.20
10.11
PRESSURE VESSELS ENGINEERING DEPARTMENT
3.77%
20.00
20.00
0.00
100.00%
38.38
32.32
7.50
Total
Wednesday, July 06, 2011
Layout No. 1 Page 1 of 4
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Summary Report
SETH Offshore EPC Project
As Of :
25-Jun-11
ENPPI W.P.3 PROCUREMENT SERVICES Item Description
Relative Weight
Planned %
Actual %
During %
FOREIGN PURCHASING DEPARTMENT
39.66%
53.17
44.73
16.83
EXPEDITING DEPART.
39.64%
3.03
3.17
0.84
SUPPLIER QUALITY SRVEILLANCE DEPART.
10.07%
0.00
0.00
0.00
TRAFFIC & LOGISTICS DEPARTMENT
10.63%
0.00
0.00
0.00
100.00%
22.29
19.00
Total
Wednesday, July 06, 2011
7.01
Layout No. 1 Page 2 of 4
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Summary Report
SETH Offshore EPC Project
As Of :
25-Jun-11
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION Item Description
METERIAL SUPPLY
Total
Relative Weight
Planned %
Actual %
During %
100.00%
0.00
1.99
1.99
100.00%
0.00
1.99
1.99
Wednesday, July 06, 2011
Layout No. 1 Page 3 of 4
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Summary Report
SETH Offshore EPC Project
As Of :
25-Jun-11
ENPPI W.P.9 OFFSHORE HOOK-UP & COMMISSIONING Item Description
COMMISSIONING
Total
Relative Weight
Planned %
Actual %
During %
100.00%
0.00
0.00
0.00
100.00%
0.00
0.00
0.00
Wednesday, July 06, 2011
Layout No. 1 Page 4 of 4
Data'Nes Systems, Release 2.21
PAGE 21 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.1.3 TECNOMARE
GFL 003-0405
3467-200
OVERALL PROGRESS 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
% Monthly Planned
33,89 3,83 1,66 1,70 7,75 5,14 22,10 1,13 7,71 0,45 0,50 1,54 0,25 11,37 0,00 0,00 0,99
% Monthly Actual
33,89 5,57
% Forecast Monthly % Cumulative Planned 33,89 37,72 39,38 41,07 48,82 53,96 76,07 77,20 84,91 85,36 85,86 87,40 87,64 99,01 99,01 99,01 100,0 % Cumulative Actual % Forecast Cumulative
33,89 39,46
Dec -12
% Progress M Monthly
50,00
1.1.1 - PROJECT SERVICES 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
% Monthly Planned
33,89 3,83 1,66 1,70 7,75 5,14 22,10 1,13 7,71 0,45 0,50 1,54 0,25 11,37 0,00 0,00 0,99
% Monthly Actual
33,89 5,57
% Forecast Monthly % Cumulative Planned 33,89 37,72 39,38 41,07 48,82 53,96 76,07 77,20 84,91 85,36 85,86 87,40 87,64 99,01 99,01 99,01 100,0 % Cumulative Actual % Forecast Cumulative
33,89 39,46
Dec -12
% Progress M Monthly
50,00
1.2 - DETAILED ENGINEERING 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
% Monthly Planned
40,05 9,34 3,64 1,42 10,80 11,69 3,48 2,27 0,79 0,29 1,16 0,00 0,58 12,18 0,00 0,00 2,31
% Monthly Actual
40,05 11,60
% Forecast Monthly % Cumulative Planned 40,05 49,39 53,03 54,45 65,25 76,94 80,42 82,69 83,48 83,77 84,93 84,93 85,51 97,69 97,69 97,69 100,0 % Cumulative Actual % Forecast Cumulative
40,05 51,65
Dec -12
% Progress M Monthly
50,00
1.2.1.Deck 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
% Monthly Planned
49,82 13,11 5,10 2,00 2,35 16,40 4,88 3,19 1,11 0,41 1,63
% Monthly Actual
49,82 16,28
% Forecast Monthly % Cumulative Planned 49,82 62,93 68,03 70,03 72,38 88,78 93,66 96,85 97,96 98,37 100,0 % Cumulative Actual % Forecast Cumulative
49,82 66,10
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.2.2 - SSIV/PLEM (TECHNICAL FOLLOW-UP) 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
% Monthly Planned
20,00 0,00 0,00 0,00 80,00
% Monthly Actual
20,00 0,00
% Forecast Monthly % Cumulative Planned 20,00 20,00 20,00 20,00 100,0 % Cumulative Actual % Forecast Cumulative
20,00 20,00
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.2.8 - AS BUILT DOSSIER 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11 % Monthly Planned % Monthly Actual
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
20,00 0,00 0,00 0,00 80,00 0,00 0,00
% Forecast Monthly % Cumulative Planned % Cumulative Actual % Forecast Cumulative
20,00 20,00 20,00 20,00 100,0 0,00 0,00
Dec -12
% Progress M Monthly
50,00
1.2.9 - CERTIFICATION (ASSISTANCE) 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11 % Monthly Planned % Monthly Actual
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
20,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 80,00 0,00 0,00
% Forecast Monthly % Cumulative Planned % Cumulative Actual % Forecast Cumulative
20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 100,0 0,00 0,00
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.2.10 - TECHNICAL FOLLOW-ON FOR T&I CONTRACTS 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
% Monthly Planned
20,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 80,00
% Monthly Actual
20,00 0,00
% Forecast Monthly % Cumulative Planned 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 20,00 100,0 % Cumulative Actual % Forecast Cumulative
20,00 20,00
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.3 - PROCUREMENT SERVICES 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
% Monthly Planned
32,01 4,20 5,99 21,77 8,44 8,89 0,00 10,27 6,43
% Monthly Actual
32,01 5,06
% Forecast Monthly % Cumulative Planned 32,01 36,21 42,60 63,58 74,42 83,30 83,30 93,57 100,0 % Cumulative Actual % Forecast Cumulative
32,01 37,07
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.3.3 - PROCUREMENT SERVICES - PLEM/SSIV 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
% Monthly Planned
20,00 6,00 16,00 48,00 10,00
% Monthly Actual
20,00 6,66
% Forecast Monthly % Cumulative Planned 20,00 26,00 42,00 90,00 100,0 % Cumulative Actual % Forecast Cumulative
20,00 26,66
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.3.6 - PROCUREMENT SERVICES - PLC/RTU 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
% Monthly Planned
40,00 3,00 0,00 3,00 11,40 14,80 0,00 17,10 10,70
% Monthly Actual
40,00 4,00
% Forecast Monthly % Cumulative Planned 40,00 43,00 43,00 46,00 57,40 72,20 72,20 89,30 100,0 % Cumulative Actual % Forecast Cumulative
40,00 44,00
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.4.9 Grout Seals and Schock Cells 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
% Monthly Planned
23,33 11,67 0,00 0,00 65,00
% Monthly Actual
23,33 11,67
% Forecast Monthly % Cumulative Planned 23,33 35,00 35,00 35,00 100,0 % Cumulative Actual % Forecast Cumulative
23,33 35,00
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.5.17 Other Instrumentation - PLC/RTU & instrumentation bulks 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12
% Monthly Planned
35,00 0,00 0,00 0,00 0,00 0,00 50,00 0,00 15,00
% Monthly Actual
35,00 0,00
% Forecast Monthly % Cumulative Planned 35,00 35,00 35,00 35,00 35,00 35,00 85,00 85,00 100,0 % Cumulative Actual % Forecast Cumulative
35,00 35,00
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
1.8.1.3 - HOOCK-UP, COMMISSIONING ACTIVITIES AND START UP 100,00 80,00 90,00 70,00 80,00
60,00
70,00
% Progress Cumulative
60,00
50,00
40,00 40,00 30,00 30,00 20,00 20,00
10,00
10,00
0,00
0,00
May Jun-11 11 % Monthly Planned % Monthly Actual
Jul11
Aug -11
Sep Oct- Nov -11 11 -11
Dec Jan- Feb Mar- Apr- May Jun-11 12 -12 12 12 -12 12 20,00 0,00 80,00
0,00 0,00
% Forecast Monthly % Cumulative Planned % Cumulative Actual % Forecast Cumulative
20,00 20,00 100,0 0,00 0,00
Jul12
Aug -12
Sep Oct- Nov -12 12 -12
Dec -12
% Progress M Monthly
50,00
PAGE 22 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.1.4 PETROJET
GFL 003-0405
3467-200
SETH DEVELOPM,ENT PROJECT OVER ALL LEVEL I MONTH
25‐Mar‐11
25‐Apr‐11 25‐May‐11
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
24.33%
27.71%
34.62%
41.43%
48.66%
56.35%
64.58%
73.87%
82.79%
PLAN %
0.00%
2.31%
9.71%
18.00%
ACT %
0.00%
4.51%
14.27%
22.34%
25‐Apr‐12 25‐May‐12 88.50%
93.61%
25‐Jun‐12
31‐Jul‐12
97.39%
100.00%
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 18.00 % Actual : 22.23 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00%
% PLAN
% ACT
1/9
PROJECT MANAGEMENT WP1 MONTH
25‐Mar‐11
25‐Apr‐11 25‐May‐11
PLAN %
0.00%
6.00%
ACT %
0.00%
6.00%
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
12.00%
18.00%
24.00%
30.00%
36.00%
42.00%
48.00%
54.00%
60.00%
66.00%
72.00%
12.00%
18.00%
25‐Apr‐12 25‐May‐12 78.00%
84.00%
25‐Jun‐12
31‐Jul‐12
90.00%
100.00%
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 18.00 % Actual : 18.00 22.23 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00%
% PLAN
% ACT
2/9
PROCUREMENT SERVICES WP3 MONTH
25‐Mar‐11
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 6.00%
12.00%
18.00%
24.00%
30.00%
36.00%
42.00%
48.00%
54.00%
60.00%
66.00%
72.00%
ACT %
0.00%
6.00%
12.00%
18.00%
25‐Apr‐12 25‐May‐12 78.00%
84.00%
25‐Jun‐12
31‐Jul‐12
90.00%
100.00%
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 18.00 % Actual : 18.00 22.23 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00%
% PLAN
% ACT
3/9
SUBSTRUCTURE ( P.D.T, PILES AND JACKET ) FABRICATION WP4 MONTH
25‐Mar‐11
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 9.95%
23.30%
32.53%
42.05%
47.86%
58.92%
68.59%
77.98%
84.58%
89.46%
97.26%
100.00%
ACT %
0.00%
10.00%
30.66%
44.27%
25‐Apr‐12 25‐May‐12 100.00%
100.00%
25‐Jun‐12
31‐Jul‐12
100.00%
100.00%
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 32.53 18.00 % Actual : 44.27 22.23 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00%
% PLAN
% ACT
4/9
DECK & TSF MATERIAL/EQUIPMENT SUPPLY AND FABRICATION WP5 MONTH
25‐Mar‐11
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 1.11%
2.12%
15.01%
22.13%
24.22%
31.58%
39.16%
48.50%
61.08%
76.63%
92.21%
96.99%
ACT %
0.00%
2.12%
10.00%
16.82%
25‐Apr‐12 25‐May‐12 99.69%
100.00%
25‐Jun‐12
31‐Jul‐12
100.00%
100.00%
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 15.01 18.00 % Actual : 16.82 22.23 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00%
% PLAN
% ACT
5/9
PIPELINE SPOOLS FABRICATION WP6 MONTH
25‐Mar‐11
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
3.09%
56.69%
ACT %
0.00%
2.12%
10.00%
16.82%
25‐Apr‐12 25‐May‐12 100.00%
100.00%
25‐Jun‐12
31‐Jul‐12
100.00%
100.00%
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 00.00 % Actual : 00.00 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% 25‐Jan‐12
25‐Feb‐12
% PLAN
25‐Mar‐12
25‐Apr‐12
% ACT
6/9
LOAD OUT AND SEA FASTENING WP8 MONTH
25‐Mar‐11
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 0.00%
0.00%
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
0.00%
0.00%
0.00%
0.00%
3.06%
3.06%
3.06%
3.06%
3.06%
40.73%
25‐Apr‐12 25‐May‐12 68.56%
100.00%
25‐Jun‐12
31‐Jul‐12
100.00%
100.00%
ACT %
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 00.00 % Actual : 00.00 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% 25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
% PLAN
25‐Feb‐12
25‐Mar‐12
25‐Apr‐12
25‐May‐12
25‐Jun‐12
% ACT
7/9
OFFSHORE HOOK‐UP AND COMMISSIONING WP9 MONTH
25‐Mar‐11
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 0.00%
0.00%
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
25‐Apr‐12 25‐May‐12 0.00%
50.00%
25‐Jun‐12
31‐Jul‐12
100.00%
100.00%
ACT %
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 00.00 % Actual : 00.00 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% 25‐Apr‐12
25‐May‐12
% PLAN
25‐Jun‐12
% ACT
8/9
CRASHING COST MONTH
25‐Mar‐11
PLAN %
0.00%
25‐Apr‐11 25‐May‐11 0.00%
0.00%
25‐Jun‐11
25‐Jul‐11
25‐Aug‐11
25‐Sep‐11
25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
25‐Feb‐12
25‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
10.00%
30.00%
50.00%
70.00%
90.00%
25‐Apr‐12 25‐May‐12 100.00%
25‐Jun‐12
31‐Jul‐12
100.00%
ACT %
100.00% 90.00% 80.00%
As of Date : 25-06-2011 Plan : 00.00 % Actual : 00.00 %
70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% 25‐Oct‐11
25‐Nov‐11
25‐Dec‐11
25‐Jan‐12
% PLAN
25‐Feb‐12
25‐Mar‐12
25‐Apr‐12
25‐May‐12
% ACT
9/9
PAGE 23 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.2. CONTROL SHEETS
GFL 003-0405
3467-200
PAGE 24 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.2.1 ENPPI
GFL 003-0405
3467-200
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
9.44%
70.00%
70.00%
4.17%
70.00%
70.00%
1.39%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION DRAWING Process flow diagram
Start
03-Apr-11
06-Apr-11
Design
10-Apr-11
21-Apr-11
Final
19-Sep-11
20 50 20-Sep-11
30
Utility flow diagram
Start
06-Apr-11
03-Apr-11
Design
13-Apr-11
10-Apr-11
Final
26-Sep-11
20 50 27-Sep-11
30
Cause & Effect Chart
Start
09-May-11
25-Apr-11
Design
16-May-11
23-Jun-11
Construction
19-Sep-11
20 50 20-Sep-11
30
Process block diagram
Start
07-Jun-11
12-Jun-11
Design
14-Jun-11
20-Jun-11
Construction
26-Sep-11
20 50 27-Sep-11
30
Below Cellar deck Escape Route, safety and lifesaving equipment layout
Start
31-May-11
12-May-11
Design
07-Jun-11
17-May-11
Construction
03-Oct-11
20 50 04-Oct-11
30
Helideck - Escape way, safety and lifesaving equipment layout
Start
31-May-11
12-May-11
Design
07-Jun-11
17-May-11
Construction
20 50 04-Oct-11
03-Oct-11
30
Below Cellar deck - Firefighting System layout
Start
05-May-11
03-May-11
Design
12-May-11
08-May-11
Construction
20 50 27-Sep-11
26-Sep-11
30
Cellar Deck - Firefighting System layout
Start
05-May-11
03-May-11
Design
12-May-11
08-May-11
Construction
26-Sep-11
20 50 27-Sep-11
30
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 1 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
0.56%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION DRAWING Main deck - Firefighting System layout
Start
05-May-11
03-May-11
Design
12-May-11
08-May-11
Construction
26-Sep-11
20 50 27-Sep-11
30
Helideck - Firefighting System layout
Start
05-May-11
03-May-11
Design
12-May-11
08-May-11
Construction
26-Sep-11
20 50 27-Sep-11
30
Below Cellar deck - Safety signs layout
Start
31-May-11
09-May-11
Design
07-Jun-11
16-May-11
Construction
03-Oct-11
20 50 04-Oct-11
30
Cellar deck - Safety signs layout
Start
31-May-11
09-May-11
Design
07-Jun-11
16-May-11
Construction
03-Oct-11
20 50 04-Oct-11
30
Main deck - Safety signs layout
Start
31-May-11
09-May-11
Design
07-Jun-11
16-May-11
Construction
03-Oct-11
20 50 04-Oct-11
30
Helideck - Safety signs layout
Start
31-May-11
09-May-11
Design
07-Jun-11
16-May-11
Construction
20 50 04-Oct-11
03-Oct-11
30
21.11%
70.00%
70.00%
REPORTS / TECHNICAL LIST Basis of design
Start
10-Apr-11
08-Apr-11
Design
12-Apr-11
12-Apr-11
Final
11-Jun-11
03-Apr-11
04-Apr-11
10-Apr-11
11-Apr-11
Final
19-Sep-11
1.94%
70.00%
70.00%
50
20 50 20-Sep-11
30
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
70.00%
30
Heat & Material balance report
Design
100.00%
20
07-Jul-11
Start
1.94%
Page 2 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
1.94%
70.00%
70.00%
1.94%
70.00%
20.00%
1.94%
0.00%
0.00%
1.94%
20.00%
70.00%
1.94%
70.00%
70.00%
2.50%
0.00%
0.00%
1.94%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION REPORTS / TECHNICAL LIST Project master equipment list
Start
08-May-11
03-May-11
Design
15-May-11
10-May-11
Construction
15-Sep-11
20 50 18-Sep-11
30
Process & Utilities report 20
Start
05-Jun-11
Design
12-Jun-11
24-Jun-11 12-Jul-11
50
Final
19-Sep-11
20-Sep-11
30
Blow down reprot
Start
03-Jul-11
26-Jul-11
Design
10-Jul-11
01-Aug-11
20 50
Final
29-Sep-11
02-Oct-11
30
Utilities load summary
Start
19-Jun-11
16-Jun-11
Design
26-Jun-11
23-Jun-11
Final
25-Sep-11
20 50 26-Sep-11
30
Hazardous Area classification report
Start
26-Apr-11
10-May-11
Design
04-May-11
16-May-11
Construction
26-Sep-11
20 50 27-Sep-11
30
Hazop report
Start
21-Jul-11
25-Aug-11
20
Final
04-Aug-11
12-Sep-11
80
HSE philosophy
Start
20-Apr-11
10-May-11
Design
27-Apr-11
16-May-11
Final
09-Oct-11
20 50 10-Oct-11
30
18.06%
50.62%
47.38%
MRQ Chemical injection package MRQ
1.67%
Start
03-Apr-11
01-Apr-11
20
For inquiry
06-Apr-11
03-Apr-11
80
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 3 of 59
100.00%
100.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
1.67%
100.00%
100.00%
1.67%
100.00%
100.00%
1.67%
100.00%
100.00%
1.67%
100.00%
100.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION MRQ Flame arrestor MRQ
Start
20-Apr-11
15-Apr-11
20
For inquiry
27-Apr-11
19-Apr-11
80
Vent stack package MRQ
Start
02-May-11
25-Apr-11
20
For inquiry
09-May-11
28-Apr-11
80
Fire Fighting package MRQ
Start
06-Apr-11
01-Apr-11
20
For inquiry
12-Apr-11
03-Apr-11
80
Safety equipment and life saving MRQ
Start For inquiry
03-Apr-11 12-Apr-11
01-Apr-11
20
03-Apr-11
80
8.33%
100.00%
100.00%
TER Chemical injection package TER
Start
08-May-11
18-Apr-11
20
Finish
19-Jun-11
01-Jun-11
80
Flame arrestor TER
Start
26-May-11
Finish
23-Jun-11
06-Jun-11
Finish
04-Jul-11
21-Jul-11
11-May-11
Finish
09-Jun-11
Finish
08-May-11 12-Jun-11
3.06%
100.00%
20.00%
3.06%
20.00%
20.00%
3.06%
100.00%
20.00%
3.06%
100.00%
20.00%
20
01-Jun-11 26-Jul-11
80
20
26-Apr-11 05-Jul-11
80
Safety equipment and life saving TER
Start
100.00%
80
Fire Fighting package TER
Start
100.00%
20
02-Jun-11
Vent stack package TER
Start
3.06%
20
05-Apr-11 07-Jul-11
80
15.28%
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 4 of 59
84.00%
36.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION MRP Chemical injection package MRP
Start
10-Jul-11
03-Jul-11
20
For Purchase
17-Jul-11
07-Jul-11
80
Flame arrestor MRP
Start
21-Jul-11
07-Aug-11
20
For Purchase
28-Jul-11
09-Aug-11
80
Vent stack package MRP
Start
03-Aug-11
21-Aug-11
20
For Purchase
10-Aug-11
22-Aug-11
80
Fire Fighting package MRP
Start For Purchase
05-Jul-11
20-Jul-11
20
11-Jul-11
21-Jul-11
80
Safety equipment and life saving MRP
Start For Purchase
10-Jul-11
07-Aug-11
20
17-Jul-11
11-Aug-11
80
0.83%
0.00%
0.00%
0.83%
0.00%
0.00%
0.83%
0.00%
0.00%
0.83%
0.00%
0.00%
0.83%
0.00%
0.00%
4.17%
0.00%
0.00%
VENDOR PRINTS REVIEW Chemical injection package
Start
25-Jul-11
25-Jul-11
20
Finish
25-Dec-11
14-Dec-11
80
Flame arrestor
Start
07-Aug-11
04-Sep-11
20
Finish
07-Dec-11
01-Jan-12
80
Vent stack package
Start
23-Aug-11
20-Sep-11
20
Finish
26-Dec-11
17-Jan-12
80
Fire Fighting package
Start Finish
20-Jul-11
07-Aug-11
20
19-Dec-11
02-Jan-12
80
Safety signs,miscellaneous safety and life saving equipment package
Start Finish
25-Jul-11
21-Aug-11
20
24-Nov-11
21-Dec-11
80
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 5 of 59
5.28%
0.00%
0.00%
2.78%
0.00%
0.00%
2.78%
0.00%
0.00%
3.89%
0.00%
0.00%
3.33%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
18.06%
0.00%
0.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION VENDOR PRINTS REVIEW
P&ID's Symbols for P & ID instrumentation
Start
10-Apr-11
14-Apr-11
20
Design
17-Apr-11
21-Apr-11
50
Construction
12-Sep-11
13-Sep-11
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
10-Apr-11
14-Apr-11
17-Apr-11
21-Apr-11
Construction
12-Sep-11
10-Apr-11
14-Apr-11
17-Apr-11
21-Apr-11
Construction
12-Sep-11
10-Apr-11
14-Apr-11
17-Apr-11
21-Apr-11
Construction
12-Sep-11
10-Apr-11
14-Apr-11
17-Apr-11
21-Apr-11
Construction
12-Sep-11
70.00%
0.83%
70.00%
70.00%
0.69%
70.00%
70.00%
0.69%
70.00%
70.00%
20 50 30
20 50 30
20 50 13-Sep-11
30
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
70.00%
30
Unit 0230 - Blow-down system
Design
0.83%
50
13-Sep-11
Start
70.00%
20
Unit 0190 - Delivery system
Design
70.00%
50
13-Sep-11
Start
0.69%
30
Unit 0130 - Manifold
Design
70.00%
20
13-Sep-11
Start
70.00%
30
Unit 0120 - Chemical injection system (Corrosion inhibitor)
Design
0.69%
50
13-Sep-11
Start
70.00%
20
13-Sep-11
10-Apr-11
70.00%
30
Unit 0120 -Chem. Injec. Sys. (Hydrate inhibitor skid)
Start
0.69%
50 13-Sep-11
10-Apr-11
70.00%
20
Unit 0120 - Chemical injection system (Methanol skid)
Start
70.00%
30
Unit 0100 - Single completion wellhead DW001
Start
0.69%
Page 6 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
0.83%
70.00%
70.00%
0.69%
70.00%
70.00%
0.69%
70.00%
70.00%
0.83%
70.00%
70.00%
0.83%
70.00%
70.00%
0.83%
70.00%
70.00%
0.83%
70.00%
70.00%
0.83%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION P&ID's Unit 0300 -Test Multiphase Meter
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0420 -Fuel Gas system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0420 -Fuel Gas system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0470- Main Power Generation Package
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0430- Diesel Fuel system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0480- Diesel Electrical Generation Package
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
20 50 13-Sep-11
12-Sep-11
30
Unit 0730- Dry Firefighting system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
20 50 13-Sep-11
12-Sep-11
30
Unit 0540- Open Drain system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 7 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
0.69%
70.00%
70.00%
0.69%
70.00%
70.00%
0.69%
70.00%
70.00%
0.69%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION P&ID's Unit 0730- Helideck Foam Firefighting system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0520- Service water system
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
Unit 0570- Sanitary Discharge treatment package
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
TUTU Panel & SSIV
Start
10-Apr-11
14-Apr-11
Design
17-Apr-11
21-Apr-11
Construction
12-Sep-11
20 50 13-Sep-11
30
15.00%
Total
PROCESS TECHNOLOGY DIVISION
100.00%
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 8 of 59
70.00% 55.58%
70.00% 47.67%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
3.16%
70.00%
70.00%
1.58%
70.00%
70.00%
1.58%
70.00%
70.00%
1.58%
70.00%
0.00%
1.84%
70.00%
70.00%
1.32%
70.00%
0.00%
2.37%
70.00%
70.00%
1.32%
70.00%
0.00%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT DRAWING Interconnecting Wiring Diagram
Start
26-May-11
04-May-11
Design
02-Jun-11
11-May-11
Construction
14-Nov-11
20 50 15-Nov-11
30
Mechanical-Hook-up Drawing
Start
19-May-11
20-Apr-11
Design
26-May-11
27-Apr-11
Construction
10-Nov-11
20 50 13-Nov-11
30
Hydraulic hook-up Drawings
Start
19-May-11
20-Apr-11
Design
26-May-11
27-Apr-11
Construction
10-Nov-11
20 50 13-Nov-11
30
Electrical hook-up Drawing
Start
19-May-11
12-Jul-11
20
Design
26-May-11
19-Jul-11
50
Construction
10-Nov-11
13-Nov-11
30
Electrical instruments layout
Start
05-May-11
10-May-11
Design
12-May-11
16-May-11
Construction
25-Oct-11
20 50 26-Oct-11
30
Hydraulic instruments layouts
Start
05-May-11
06-Jul-11
Design
12-May-11
13-Jul-11
50
25-Oct-11
26-Oct-11
30
Construction
20
Electrical instrument cable routing layout
Start
12-May-11
07-Jun-11
Design
19-May-11
14-Jun-11
Construction
01-Nov-11
20 50 02-Nov-11
30
Hydraulic instruments Tube Routing layouts
Start
12-May-11
05-Jul-11
20
Design
19-May-11
12-Jul-11
50
01-Nov-11
02-Nov-11
30
Construction
14.74%
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTM Tuesday, July 05, 2011
Page 9 of 59
70.00%
50.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
2.11%
70.00%
70.00%
2.11%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT REPORTS / TECHNICAL LIST Instrument Index
Start
26-Apr-11
10-May-11
Design
04-May-11
16-May-11
Construction
21-Sep-11
20 50 22-Sep-11
30
Instrument cable list
Start
26-May-11
07-Jun-11
Design
02-Jun-11
15-Jun-11
Construction
25-Oct-11
20 50 26-Oct-11
30
4.21%
70.00%
70.00%
MRQ Multiphase flow meter MRQ
Start
03-Apr-11
07-Apr-11
20
For inquiry
10-Apr-11
10-Apr-11
80
Electro Hydraulic Well Head panel MRQ
Start For inquiry
04-Apr-11 12-Apr-11
01-Apr-11
20
03-Apr-11
80
Choke valve MRQ
Start For inquiry
06-Apr-11 13-Apr-11
01-Apr-11
20
03-Apr-11
80
HIPPS System MRQ
Start
31-Mar-11
01-Apr-11
20
For inquiry
07-Apr-11
03-Apr-11
80
Wing valve MRQ
Start
06-Apr-11
01-Apr-11
20
For inquiry
13-Apr-11
03-Apr-11
80
Loose Instrument MRQ
Start
18-May-11
01-Jun-11
20
For inquiry
25-May-11
06-Jun-11
80
Sand & Corrosion probes MRQ
Start
25-May-11
20-Jun-11
20
For inquiry
01-Jun-11
26-Jun-11
80
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTM Tuesday, July 05, 2011
Page 10 of 59
1.05%
100.00%
100.00%
1.05%
100.00%
100.00%
1.05%
100.00%
100.00%
1.05%
100.00%
100.00%
1.05%
100.00%
100.00%
0.92%
100.00%
100.00%
0.92%
100.00%
20.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
0.92%
100.00%
100.00%
0.92%
100.00%
100.00%
0.92%
100.00%
100.00%
0.92%
100.00%
20.00%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT MRQ Instrument & Mechanical bulk materialMRQ
Start
26-May-11
01-May-11
20
For inquiry
02-Jun-11
03-May-11
80
Instrument cable and cable glandsMRQ
Start
16-May-11
15-Jun-11
20
For inquiry
23-May-11
22-Jun-11
80
Inst. Junction Box MRQ
Start
02-Jun-11
01-Jun-11
20
For inquiry
09-Jun-11
06-Jun-11
80
Instrument cable trays MRQ
Start
24-May-11
19-Jun-11
20
For inquiry
31-May-11
26-Jun-11
80
10.79%
100.00%
86.34%
TER Multiphase flow meter TER
Start
15-May-11
28-Apr-11
20
Finish
12-Jun-11
25-May-11
80
Electro Hydraulic Well Head panel TER
Start
15-May-11
10-Apr-11
20
Finish
02-Jun-11
16-Jun-11
80
Choke valve TER
Start
18-May-11
Finish
12-Jun-11
05-Jul-11
03-May-11
10-Apr-11
20
Finish
31-May-11
09-Jun-11
80
Wing valve TER
Finish
08-Jun-11
02-May-11
20
15-Jun-11
80
Loose Instrument TER
Start Finish
12-Jun-11 26-Jun-11
3.95%
100.00%
100.00%
2.63%
100.00%
20.00%
5.00%
100.00%
100.00%
2.63%
100.00%
100.00%
1.84%
20.00%
20.00%
20
20-Jun-11 24-Jul-11
80
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTM Tuesday, July 05, 2011
100.00%
80
Start
16-May-11
100.00%
20
26-Apr-11
HIPPS System TER
Start
3.95%
Page 11 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
2.11%
20.00%
0.00%
2.11%
20.00%
20.00%
2.11%
100.00%
0.00%
2.11%
20.00%
20.00%
2.11%
20.00%
0.00%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT TER Sand & Corrosion probes TER
Start
16-Jun-11
11-Jul-11
20
Finish
07-Jul-11
04-Aug-11
80
Instrument & Mechanical bulk material TER
Start
19-Jun-11
Finish
03-Jul-11
20
26-May-11 14-Jul-11
80
Instrument cable and cable glandsTER
Start
06-Jun-11
10-Jul-11
20
Finish
20-Jun-11
01-Aug-11
80
Inst. Junction Box TER
Start Finish
23-Jun-11
20
21-Jun-11 21-Jul-11
07-Jul-11
80
Instrument cable trays TER
Start Finish
14-Jun-11
03-Jul-11
20
28-Jun-11
28-Jul-11
80
30.53%
73.10%
56.55%
1.05%
0.00%
100.00%
1.05%
0.00%
0.00%
1.05%
0.00%
0.00%
1.05%
0.00%
0.00%
1.05%
0.00%
0.00%
MRP Multiphase flow meter MRP
Start
10-Jul-11
16-Jun-11
20
For Purchase
17-Jul-11
23-Jun-11
80
Electro Hydraulic Well Head panel MRP
Start
04-Jul-11
13-Jul-11
20
For Purchase
11-Jul-11
14-Jul-11
80
Choke valve MRP
Start
05-Jul-11
27-Jul-11
20
For Purchase
12-Jul-11
02-Aug-11
80
HIPPS System MRP
Start For Purchase
28-Jun-11
07-Jul-11
20
05-Jul-11
13-Jul-11
80
Wing valve MRP
Start For Purchase
06-Jul-11
24-Jul-11
20
13-Jul-11
28-Jul-11
80
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTM Tuesday, July 05, 2011
Page 12 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT MRP Loose Instrument MRP
Start
17-Jul-11
18-Aug-11
20
For Purchase
24-Jul-11
21-Aug-11
80
Sand & Corrosion probes MRP
Start
01-Aug-11
04-Sep-11
20
For Purchase
08-Aug-11
06-Sep-11
80
Instrument & Mechanical bulk material MRP
Start
24-Jul-11
07-Aug-11
20
For Purchase
31-Jul-11
11-Aug-11
80
Instrument cable and cable glands MRP
Start For Purchase
11-Jul-11
23-Aug-11
20
18-Jul-11
25-Aug-11
80
Inst. Junction Box MRP
Start For Purchase
28-Jul-11
17-Aug-11
20
04-Aug-11
18-Aug-11
80
Instrument cable trays MRP
Start
14-Jul-11
24-Aug-11
20
For Purchase
21-Jul-11
25-Aug-11
80
1.05%
0.00%
0.00%
1.05%
0.00%
0.00%
0.79%
0.00%
0.00%
0.79%
0.00%
0.00%
0.79%
0.00%
0.00%
0.79%
0.00%
0.00%
10.53%
0.00%
10.00%
VENDOR PRINTS REVIEW Instrument & Mechanical bulk material Vendor prints review
Start
08-Aug-11
21-Aug-11
20
Finish
24-Nov-11
07-Dec-11
80
Junction boxes Vendor prints review
Start
14-Aug-11
28-Aug-11
20
Finish
30-Nov-11
14-Dec-11
80
HIPPS Vendor prints review
Start Finish
13-Jul-11
24-Jul-11
20
22-Feb-12
01-Mar-12
80
Choke valves Vendor prints review
Start Finish
20-Jul-11
11-Aug-11
20
21-Nov-11
13-Dec-11
80
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTM Tuesday, July 05, 2011
Page 13 of 59
0.79%
0.00%
0.00%
1.32%
0.00%
0.00%
3.95%
0.00%
0.00%
3.16%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT VENDOR PRINTS REVIEW Loose instrument Vendor prints review
Start
01-Aug-11
04-Sep-11
20
Finish
17-Nov-11
18-Dec-11
80
Instrument cable trays Vendor prints review
Start
31-Jul-11
04-Sep-11
20
Finish
15-Nov-11
18-Dec-11
80
Electro hydraulic wellhead control panel Vendor prints review
Start
25-Jul-11
21-Jul-11
20
Finish
24-Nov-11
21-Nov-11
80
Wing valves Vendor prints review
Start Finish
21-Jul-11
07-Aug-11
20
22-Nov-11
07-Dec-11
80
Instrument cable and cable glands Vendor prints review
Start Finish
26-Jul-11
28-Aug-11
20
28-Nov-11
28-Dec-11
80
Sand & Corrosion probes Vendor prints review
Start
16-Aug-11
14-Sep-11
20
Finish
05-Dec-11
28-Dec-11
80
Multi phase flow meter Vendor prints review
Start
25-Jul-11
20-Jul-11
20
Finish
25-Dec-11
07-Dec-11
80
Actuated valves Vendor prints review
Total
Start
04-May-11
Finish
10-Jan-12
0.00%
0.00%
1.05%
0.00%
0.00%
3.42%
0.00%
0.00%
3.16%
0.00%
0.00%
1.05%
0.00%
0.00%
1.84%
0.00%
0.00%
3.68%
0.00%
0.00%
3.95%
20.00%
20.00%
20
04-May-11 01-Mar-12
80
29.21%
2.70%
2.70%
100.00%
47.16%
38.74%
INSTRUMENTATION & CONTROLS ENGI
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTM Tuesday, July 05, 2011
1.84%
Page 14 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
1.82%
70.00%
70.00%
1.82%
70.00%
70.00%
1.64%
70.00%
70.00%
1.64%
70.00%
70.00%
1.64%
70.00%
70.00%
1.27%
0.00%
0.00%
1.27%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION DRAWING Heli deck plot plan
Start
17-Apr-11
01-Apr-11
Design
24-Apr-11
03-Apr-11
Construction
19-Sep-11
20 50 20-Sep-11
30
Main deck plot plan
Start
17-Apr-11
01-Apr-11
Design
24-Apr-11
03-Apr-11
Construction
19-Sep-11
20 50 20-Sep-11
30
Cellar deck plot plan
Start
17-Apr-11
01-Apr-11
Design
24-Apr-11
03-Apr-11
Construction
19-Sep-11
20 50 20-Sep-11
30
Below cellar deck plot plan
Start
17-Apr-11
01-Apr-11
Design
24-Apr-11
03-Apr-11
Construction
19-Sep-11
20 50 20-Sep-11
30
Vent boom plot plan
Start
17-Apr-11
01-Apr-11
Design
24-Apr-11
03-Apr-11
Construction
19-Sep-11
20 50 20-Sep-11
30
Looking west elevation
Start
31-Oct-11
02-Nov-11
20
Construction
28-Nov-11
29-Nov-11
80
Looking north elevation
Start
31-Oct-11
02-Nov-11
20
Construction
28-Nov-11
29-Nov-11
80
Helideck piping support plan
Start
12-Dec-11
14-Dec-11
20
Construction
19-Dec-11
20-Dec-11
80
Main deck piping support plan
Start
12-Dec-11
14-Dec-11
20
Construction
19-Dec-11
20-Dec-11
80
* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 15 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION DRAWING Cellar deck piping support plan
Start
12-Dec-11
14-Dec-11
20
Construction
19-Dec-11
20-Dec-11
80
Below cellar piping support plan
Start
12-Dec-11
14-Dec-11
20
Construction
19-Dec-11
20-Dec-11
80
Vent boom piping support plan
Start
12-Dec-11
14-Dec-11
20
Construction
19-Dec-11
20-Dec-11
80
Helideck piping support location
Start Construction
19-Dec-11
21-Dec-11
20
26-Dec-11
27-Dec-11
80
Main deck piping support location
Start Construction
19-Dec-11
21-Dec-11
20
26-Dec-11
27-Dec-11
80
Cellar deck piping support location
Start
19-Dec-11
21-Dec-11
20
Construction
26-Dec-11
27-Dec-11
80
Below cellar piping support location
Start
19-Dec-11
21-Dec-11
20
Construction
26-Dec-11
27-Dec-11
80
Vent boom piping support location
Start
19-Dec-11
21-Dec-11
20
Construction
26-Dec-11
27-Dec-11
80
Helideck piping penetration location
Start
26-Dec-11
28-Dec-11
20
Construction
02-Jan-12
03-Jan-12
80
Main deck piping penetration location
Start
26-Dec-11
28-Dec-11
20
Construction
02-Jan-12
03-Jan-12
80
* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 16 of 59
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION DRAWING Cellar deck piping penetration location
Start
26-Dec-11
28-Dec-11
20
Construction
02-Jan-12
03-Jan-12
80
Below cellar piping penetration location
Start
26-Dec-11
28-Dec-11
20
Construction
02-Jan-12
03-Jan-12
80
Vent boom piping penetration location
Start
26-Dec-11
28-Dec-11
20
Construction
02-Jan-12
03-Jan-12
80
Hydrotest maps
Start Construction
22-Nov-11
24-Nov-11
20
04-Dec-11
05-Dec-11
80
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
0.73%
0.00%
0.00%
1.82%
0.00%
0.00%
23.82%
25.11%
25.11%
REPORTS / TECHNICAL LIST Line designation table
4.55%
Start
12-May-11
23-May-11
20
Design
19-May-11
01-Jun-11
50
Final
19-Sep-11
20-Sep-11
70.00%
70.00%
30
4.55%
70.00%
70.00%
MRQ Piping bulk MRQ
Start
31-Mar-11
01-Apr-11
20
For inquiry
07-Apr-11
03-Apr-11
80
Insulation joint MRQ
Start
13-Apr-11
01-Apr-11
20
For inquiry
20-Apr-11
11-Apr-11
80
Injection fitting MRQ
Start For inquiry
28-Jul-11 30-Nov-11
08-Apr-11
20
13-Apr-11
80
2.73%
100.00%
100.00%
1.82%
100.00%
100.00%
1.82%
0.00%
100.00%
71.43%
100.00%
6.36%
* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 17 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
3.64%
100.00%
100.00%
2.73%
100.00%
0.00%
2.73%
100.00%
20.00%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION TER Piping bulk TER
Start
10-May-11
26-Apr-11
20
Finish
31-May-11
17-May-11
80
Injection fitting TER
Start
25-May-11
04-Jul-11
20
Finish
15-Jun-11
24-Jul-11
80
Insulation joint Injection fitting TER
Start
19-May-11
Finish
09-Jun-11
20
02-Jun-11 21-Jul-11
80
9.09%
100.00%
46.00%
MRP Piping bulk MRP
Start
19-Jun-11
05-Jul-11
20
For Purchase
26-Jun-11
07-Jul-11
80
Insulation Joint MRP
Start
10-Jul-11
14-Aug-11
20
For Purchase
17-Jul-11
16-Aug-11
80
Injection fitting MRP
Start
13-Jul-11
18-Aug-11
20
For Purchase
20-Jul-11
21-Aug-11
80
1.82%
20.00%
0.00%
1.45%
0.00%
0.00%
1.45%
0.00%
0.00%
4.73%
7.69%
0.00%
VENDOR PRINTS REVIEW Piping bulk Vendor prints review
Start Finish
04-Jul-11
20-Jul-11
20
04-Dec-11
07-Dec-11
80
Insulation Joint Vendor prints review
Start Finish
25-Jul-11
06-Sep-11
20
24-Nov-11
03-Jan-12
80
Injection fitting Vendor prints review
Start
28-Jul-11
06-Sep-11
20
Finish
30-Nov-11
03-Jan-12
80
* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 18 of 59
3.64%
0.00%
0.00%
2.73%
0.00%
0.00%
2.73%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
4.36%
20.00%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION VENDOR PRINTS REVIEW Production Manifold Vendor prints review
Start
04-May-11
Finish
24-Jan-12
20.00%
20
20-Jun-11 15-Mar-12
80
13.45%
6.49%
6.49%
GA's Helideck piping plan GA
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
Start
Below helideck piping plan GA
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
Start
Main deck piping plan GA
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
Start
Below main deck piping plan GA
Start
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
Celler deck piping plan GA
Start
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
Below celler deck piping plan GA
Start
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
Vent boom piping plan GA
Start
13-Sep-11
18-Sep-11
20
Design
25-Sep-11
27-Sep-11
50
Construction
28-Nov-11
29-Nov-11
30
2.55%
0.00%
0.00%
2.55%
0.00%
0.00%
2.55%
0.00%
0.00%
2.55%
0.00%
0.00%
2.55%
0.00%
0.00%
2.18%
0.00%
0.00%
2.18%
0.00%
0.00%
17.09% * Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 19 of 59
0.00%
0.00% Layout No. 1
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION ISO's Piping isometric drawings package
16.36%
Start
27-Oct-11
31-Oct-11
20
Final
16-Nov-11
17-Nov-11
80
16.36%
0.00%
0.00%
0.00%
0.00%
Specification Piping material classes
4.55%
Start
16-May-11
17-May-11
20
Design
23-May-11
22-May-11
50
Final
13-Jun-11
14-Jul-11
PIPING ENGINEERING DIVISION
100.00%
* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
70.00%
30
4.55%
Total
100.00%
Page 20 of 59
100.00%
70.00%
28.58%
23.76%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
1.67%
70.00%
70.00%
1.67%
70.00%
70.00%
1.33%
70.00%
70.00%
1.33%
70.00%
70.00%
1.00%
70.00%
70.00%
1.33%
70.00%
70.00%
1.33%
70.00%
70.00%
1.33%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION DRAWING Helideck lighting & navigational aids layout
Start
24-Apr-11
20-Apr-11
Design
02-May-11
26-Apr-11
Construction
19-Oct-11
20 50 17-Nov-11
30
Main deck lighting & navigational aids layout
Start
24-Apr-11
20-Apr-11
Design
02-May-11
26-Apr-11
Construction
19-Oct-11
20 50 17-Nov-11
30
Cellar deck lighting layout
Start
24-Apr-11
20-Apr-11
Design
02-May-11
26-Apr-11
Construction
19-Oct-11
20 50 17-Nov-11
30
Below cellar deck lighting layout
Start
24-Apr-11
20-Apr-11
Design
02-May-11
26-Apr-11
Construction
19-Oct-11
20 50 17-Nov-11
30
Vent boom lighting layout
Start
24-Apr-11
20-Apr-11
Design
02-May-11
26-Apr-11
Construction
19-Oct-11
20 50 17-Nov-11
30
Helideck hazard area classification layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
20 50 12-Oct-11
11-Oct-11
30
Main deck hazard area classification layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
20 50 12-Oct-11
11-Oct-11
30
Cellar deck hazard area classification layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
11-Oct-11
20 50 12-Oct-11
30
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 21 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
1.33%
70.00%
70.00%
1.33%
70.00%
70.00%
1.00%
70.00%
70.00%
1.00%
70.00%
70.00%
1.00%
70.00%
70.00%
1.00%
70.00%
70.00%
0.83%
70.00%
70.00%
0.83%
70.00%
70.00%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION DRAWING Below cellar deck hazard area classification layout
Start
10-May-11
13-May-11
Design
17-May-11
19-May-11
Construction
11-Oct-11
20 50 12-Oct-11
30
Vent boom hazard area classification layout
Start
10-May-11
10-May-11
Design
17-May-11
19-May-11
Construction
11-Oct-11
20 50 12-Oct-11
30
Helideck earthing layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
29-Sep-11
20 50 02-Oct-11
30
Main deck earthing layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
29-Sep-11
20 50 02-Oct-11
30
Cellar deck earthing layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
29-Sep-11
20 50 02-Oct-11
30
Below cellar deck earthing layout
Start
10-May-11
10-May-11
Design
17-May-11
16-May-11
Construction
20 50 02-Oct-11
29-Sep-11
30
Helideck cable routing layout
Start
19-May-11
15-Jun-11
Design
26-May-11
23-Jun-11
Construction
20 50 04-Oct-11
03-Oct-11
30
Main deck cable routing layout
Start
19-May-11
15-Jun-11
Design
26-May-11
23-Jun-11
Construction
03-Oct-11
20 50 04-Oct-11
30
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 22 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
0.83%
70.00%
70.00%
0.83%
70.00%
70.00%
0.83%
0.00%
0.00%
2.00%
70.00%
0.00%
1.67%
0.00%
0.00%
2.33%
70.00%
70.00%
1.00%
20.00%
0.00%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION DRAWING Cellar deck cable routing layout
Start
19-May-11
15-Jun-11
Design
26-May-11
23-Jun-11
Construction
03-Oct-11
20 50 04-Oct-11
30
Below cellar deck cable routing layout
Start
19-May-11
15-Jun-11
Design
26-May-11
23-Jun-11
Construction
03-Oct-11
20 50 04-Oct-11
30
Lighting block diagram
Start
21-Oct-11
01-Nov-11
20
Construction
26-Oct-11
24-Nov-11
80
Single line diagram
Start
23-May-11
14-Jul-11
Design
30-May-11
21-Jul-11
20 50
Construction
18-Oct-11
19-Oct-11
30
E&I module equipment layout
Start
03-Jul-11
08-Sep-11
Design
03-Jul-11
08-Sep-11
20 50
Construction
25-Nov-11
29-Jan-12
30
Interconnection & wiring diagram
Start
17-Jun-11
03-May-11
Design
24-Jun-11
11-May-11
Construction
04-Oct-11
20 50 05-Oct-11
30
Cable sections
Start
22-Jun-11
26-Jul-11
Design
29-Jun-11
21-Aug-11
20 50
Construction
04-Oct-11
05-Oct-11
30
28.83%
62.20%
56.65%
REPORTS / TECHNICAL LIST Electrical cable list
1.33%
Start
08-Jun-11
10-Jul-11
Design
15-Jun-11
17-Jul-11
50
Construction
03-Oct-11
04-Oct-11
30
0.00%
20
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
70.00%
Page 23 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
2.33%
70.00%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION REPORTS / TECHNICAL LIST Power system study
Start
15-May-11
30-Jun-11
Design
24-May-11
14-Jul-11
50
Final
09-Oct-11
10-Oct-11
30
0.00%
20
3.67%
70.00%
0.00%
MRQ Electrical cable trays MRQ
Start
24-Apr-11
01-Apr-11
20
For inquiry
02-May-11
03-Apr-11
80
Electrical cables MRQ
Start For inquiry
02-May-11 09-May-11
01-Apr-11
20
03-Apr-11
80
Navigational aids system MRQ
Start For inquiry
09-May-11 16-May-11
24-Apr-11
20
27-Apr-11
80
Lighting material MRQ
Start
26-May-11
15-Jun-11
20
For inquiry
02-Jun-11
22-Jun-11
80
Earthing material MRQ
Start
30-May-11
29-May-11
20
For inquiry
06-Jun-11
20-Jun-11
80
2.00%
100.00%
100.00%
2.00%
100.00%
100.00%
2.00%
100.00%
100.00%
2.00%
100.00%
100.00%
2.00%
100.00%
100.00%
10.00%
100.00%
100.00%
TER Navigational aids system TER
Start
30-May-11
Finish
27-Jun-11
20.00%
20.00%
4.33%
100.00%
100.00%
4.33%
100.00%
100.00%
20
16-May-11 10-Jul-11
80
Electrical cables TER
Start
23-May-11
05-Apr-11
20
Finish
20-Jun-11
10-Apr-11
80
Electrical cable trays TER
Start
22-May-11
05-Apr-11
20
Finish
19-Jun-11
10-Apr-11
80
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
8.33%
Page 24 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
4.33%
20.00%
0.00%
4.33%
20.00%
0.00%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION TER Lighting material TER
Start
08-Jun-11
10-Jul-11
20
Finish
06-Jul-11
04-Aug-11
80
Earthing material TER
Start
20-Jun-11
10-Jul-11
20
Finish
18-Jul-11
04-Aug-11
80
25.67%
47.01%
40.26%
MRP Electrical cables MRP
Start
13-Jul-11
10-Jul-11
20
For Purchase
20-Jul-11
14-Jul-11
80
Navigational aids system MRP
Start
19-Jul-11
07-Aug-11
20
For Purchase
26-Jul-11
08-Aug-11
80
Electrical Cable trays MRP
Start
10-Jul-11
30-Jun-11
20
For Purchase
17-Jul-11
30-Jun-11
80
Lighting material MRP
Start
27-Jul-11
28-Aug-11
20
For Purchase
01-Aug-11
04-Sep-11
80
Earthing material MRP
Start
08-Aug-11
28-Aug-11
20
For Purchase
15-Aug-11
06-Sep-11
80
2.00%
0.00%
0.00%
2.00%
0.00%
0.00%
2.00%
0.00%
0.00%
2.00%
0.00%
0.00%
2.00%
0.00%
0.00%
10.00%
0.00%
0.00%
VENDOR PRINTS REVIEW Earthing Vendor prints review
Start Finish
23-Aug-11
11-Sep-11
20
28-Nov-11
11-Dec-11
80
Lighting material Vendor prints review
Start
11-Aug-11
11-Sep-11
20
Finish
14-Dec-11
08-Jan-12
80
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 25 of 59
2.67%
0.00%
0.00%
2.50%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION VENDOR PRINTS REVIEW Electrical Cable trays Vendor prints review
Start
25-Jul-11
18-Jul-11
20
Finish
24-Nov-11
02-Nov-11
80
Electrical Cables Vendor prints review
Start
01-Aug-11
21-Jul-11
20
Finish
04-Dec-11
21-Nov-11
80
Navigation aids system Vendor prints review
Start
02-Aug-11
16-Aug-11
20
Finish
05-Dec-11
18-Dec-11
80
E&I Module Vendor prints review
Start Finish
Total
04-May-11 24-Jan-12
0.00%
0.00%
2.50%
0.00%
0.00%
5.00%
0.00%
0.00%
6.67%
20.00%
20.00%
20
03-May-11 29-Mar-12
80
ELECTRICAL ENGINEERING DIVISION
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
2.50%
Page 26 of 59
21.83%
6.11%
6.11%
100.00%
43.90%
38.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING OFFSHORE ENGINEERING DIVISION DRAWING Cable trays supports for deck plan at el. +9700 T.O.S.
Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Construction
01-Dec-11
01-Dec-11
30
Cable trays supports for cellar deck plan at el. +13500 T.O.S.
Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Construction
01-Dec-11
01-Dec-11
30
Cable trays supports for mezzanine deck plan at el. +16000 T.O.S.
Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Construction
01-Dec-11
01-Dec-11
30
Cable trays supports for main deck plan at el. +20500 T.O.S.
Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Construction
01-Dec-11
01-Dec-11
30
Cable trays supports for Helideck plan at el. +26500 T.O.S.
Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Construction
01-Dec-11
01-Dec-11
30
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
50.00%
0.00%
0.00%
MRQ Survival module MRQ
10.00%
Start
24-Apr-11
01-Apr-11
20
For inquiry
28-Apr-11
03-Apr-11
80
10.00%
100.00%
100.00%
100.00%
100.00%
TER Survival module TER
Start Finish
15.00%
01-Jun-11 28-Jun-11
20.00%
20
22-May-11 03-Jul-11
80
15.00%
* Weights of Activities are calculated relative to (OFFSHORE ENGINEERING DIVISION) Tuesday, July 05, 2011
20.00%
Page 27 of 59
20.00%
20.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING OFFSHORE ENGINEERING DIVISION MRP Survival module MRP
5.00%
Start
20-Jul-11
25-Jul-11
20
For Purchase
26-Jul-11
31-Jul-11
80
5.00%
0.00%
0.00%
0.00%
0.00%
VENDOR PRINTS REVIEW Survival module vendor prints review
Start Finish
20.00%
31-Mar-11
04-Aug-11
20
26-Jun-11
20-Sep-11
80
20.00%
Total
OFFSHORE ENGINEERING DIVISION
100.00%
* Weights of Activities are calculated relative to (OFFSHORE ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 28 of 59
20.00%
20.00% 17.00%
0.00%
0.00% 13.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
6.00%
70.00%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING MECHANICAL ENGINEERING DEPARTMENT DRAWING Material selection guide
Start
03-Jun-11
10-May-11
Design
18-Jun-11
17-May-11
Construction
19-Sep-11
70.00%
20 50 20-Sep-11
30
6.00%
70.00%
70.00%
REPORTS / TECHNICAL LIST Motor load list
10-Apr-11
20
19-Apr-11
14-Apr-11
30
21-Jul-11
23-Jun-11
Start
04-Apr-11
1st issue 2nd issue Final
22-Sep-11
02-May-11
02-Jul-11
09-May-11
09-Jun-11
Final
08-Jun-11
70.00%
7.78%
100.00%
50.00%
30
Maintenance and handling study
Design
50.00%
20 25-Sep-11
Start
6.67%
20 50 26-Jul-11
30
14.44%
76.92%
59.23%
MRQ Mono rail MRQ
Start
21-Jul-11
21-Aug-11
20
For inquiry
28-Jul-11
25-Aug-11
80
Turret crane MRQ
Start For inquiry
06-Apr-11 13-Apr-11
01-Apr-11
20
03-Apr-11
80
Service water pump MRQ
Start For inquiry
18-Apr-11 25-Apr-11
01-Apr-11
20
03-Apr-11
80
4.33%
0.00%
0.00%
4.00%
100.00%
100.00%
4.00%
100.00%
100.00%
12.33%
64.86%
64.86%
TER Turret crane TER
10.00%
Start
15-May-11
10-Apr-11
20
Finish
12-Jun-11
04-May-11
80
* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT) Tuesday, July 05, 2011
Page 29 of 59
100.00%
100.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING MECHANICAL ENGINEERING DEPARTMENT TER Service water pump TER
Start
17-May-11
Finish
07-Jun-11
10.00%
100.00%
20.00%
5.56%
0.00%
0.00%
20
28-Apr-11 03-Jul-11
80
Monorail crane TER
Start
11-Aug-11
14-Sep-11
20
Finish
06-Sep-11
04-Oct-11
80
25.56%
78.26%
46.96%
3.33%
0.00%
100.00%
3.33%
0.00%
0.00%
3.33%
0.00%
0.00%
MRP Turret crane MRP
Start
04-Jul-11
16-Jun-11
20
For Purchase
11-Jul-11
16-Jun-11
80
Service water pump MRP
Start
11-Jul-11
26-Jul-11
20
For Purchase
18-Jul-11
28-Jul-11
80
Monorail crane MRP
Start
04-Oct-11
03-Nov-11
20
For Purchase
10-Oct-11
13-Nov-11
80
10.00%
0.00%
33.33%
VENDOR PRINTS REVIEW Service water pump Vendor prints review
Start
26-Jul-11
14-Aug-11
20
Finish
28-Nov-11
14-Dec-11
80
Turret crane crane Vendor prints review
Start Finish
19-Jul-11
13-Jul-11
20
19-Dec-11
07-Dec-11
80
Micro Turbine Vendor prints review
Start Finish
04-May-11
15-Mar-12
04-May-11
Finish
24-Jan-12
7.78%
0.00%
0.00%
7.78%
20.00%
20.00%
7.78%
20.00%
20.00%
20
15-Jun-11 29-Mar-12
80
* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT) Tuesday, July 05, 2011
0.00%
80
Emergency GeneratorVendor prints review
Start
0.00%
20
24-May-11
24-Jan-12
4.44%
Page 30 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING MECHANICAL ENGINEERING DEPARTMENT VENDOR PRINTS REVIEW Monorail crane Vendor prints review
Total
3.89%
Start
04-Oct-11
03-Nov-11
20
Finish
01-Feb-12
01-Mar-12
80
MECHANICAL ENGINEERING DEPARTME
* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT) Tuesday, July 05, 2011
Page 31 of 59
0.00%
0.00%
31.67%
9.82%
9.82%
100.00%
46.42%
39.20%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.2 DETAILED ENGINEERING PRESSURE VESSELS ENGINEERING DEPARTMENT VENDOR PRINTS REVIEW Pressure vessels
100.00%
Start
10-May-11
Finish
16-Jan-12
16-Jan-12
80
PRESSURE VESSELS ENGINEERING DE
* Weights of Activities are calculated relative to (PRESSURE VESSELS ENGINEERING DEPARTMENT) Tuesday, July 05, 2011
20.00%
20
10-May-11
100.00%
Total
20.00%
Page 32 of 59
100.00%
20.00% 20.00%
20.00% 20.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
3.26%
60.00%
40.00%
3.26%
60.00%
40.00%
4.19%
60.00%
70.00%
3.49%
60.00%
40.00%
3.26%
40.00%
40.00%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE Safety equipment and life saving
RFQ
12-Apr-11
03-Apr-11
Tech. offers open
26-Apr-11
05-Apr-11
Comm. offers open
12-Jun-11
Bid tab
20 20 17-Jul-11
20
26-Jun-11
24-Jul-11
10
F.O.C.
10-Jul-11
04-Aug-11
20
P.O.
24-Jul-11
18-Aug-11
10
Flame arrestor
RFQ
27-Apr-11
21-Apr-11
20
Tech. offers open
19-May-11
02-Jun-11
20
Comm. offers open
23-Jun-11
26-Jul-11
20
Bid tab
07-Jul-11
02-Aug-11
10
F.O.C.
21-Jul-11
07-Aug-11
20
P.O.
04-Aug-11
11-Aug-11
10
Chemical injection package
RFQ
06-Apr-11
03-Apr-11
20
Tech. offers open
27-Apr-11
18-Apr-11
20
Comm. offers open
19-Jun-11
12-Jun-11
20
Bid tab
03-Jul-11
16-Jun-11
10
F.O.C.
10-Jul-11
30-Jun-11
20
P.O.
24-Jul-11
10-Jul-11
10
Fire Fighting package
RFQ
20
13-Apr-11
03-Apr-11
Tech. offers open
26-Apr-11
26-Apr-11
Comm. offers open
14-Jun-11
10-Jul-11
20
Bid tab
28-Jun-11
14-Jul-11
10
F.O.C.
04-Jul-11
20-Jul-11
20
18-Jul-11
24-Jul-11
10
P.O.
20
Vent stack tips
RFQ
09-May-11
09-May-11
20
01-Jun-11
20
Tech. offers open
06-Jun-11
Comm. offers open
06-Jul-11
02-Aug-11
20
Bid tab
20-Jul-11
10-Aug-11
10
F.O.C.
03-Aug-11
21-Aug-11
20
P.O.
17-Aug-11
24-Aug-11
10
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
Page 33 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
3.73%
90.00%
90.00%
3.26%
60.00%
40.00%
3.26%
60.00%
20.00%
3.49%
40.00%
20.00%
3.49%
40.00%
20.00%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE Piping bulk
RFQ
07-Apr-11
03-Apr-11
20
Tech. offers open
28-Apr-11
05-Apr-11
20
Comm. offers open 30-May-11
12-Jun-11
20
Bid tab
13-Jun-11
15-Jun-11
10
F.O.C.
19-Jun-11
22-Jun-11
20
P.O.
03-Jul-11
07-Jul-11
10
Insulation Joint
RFQ
20-Apr-11
11-Apr-11
20
Tech. offers open
19-May-11
30-May-11
20
Comm. offers open
12-Jun-11
27-Jul-11
20
Bid tab
26-Jun-11
04-Aug-11
10
F.O.C.
10-Jul-11
14-Aug-11
20
P.O.
24-Jul-11
17-Aug-11
10
Injection fitting 20
RFQ
24-Apr-11
Tech. offers open
23-May-11
13-Apr-11 04-Jul-11
20
Comm. offers open
15-Jun-11
01-Aug-11
20
Bid tab
29-Jun-11
08-Aug-11
10
F.O.C.
13-Jul-11
18-Aug-11
20
P.O.
27-Jul-11
23-Aug-11
10
Earthing material 20
RFQ
06-Jun-11
Tech. offers open
20-Jun-11
07-Jul-11
20
Comm. offers open
18-Jul-11
10-Aug-11
20
Bid tab
01-Aug-11
21-Aug-11
10
F.O.C.
08-Aug-11
25-Aug-11
20
24-Aug-11
15-Sep-11
10
P.O.
21-Jun-11
Lighting material
RFQ
25-May-11
20
22-Jun-11
Tech. offers open
08-Jun-11
07-Jul-11
20
Comm. offers open
06-Jul-11
10-Aug-11
20
Bid tab
20-Jul-11
21-Aug-11
10
F.O.C.
27-Jul-11
25-Aug-11
20
P.O.
22-Aug-11
13-Sep-11
10
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
Page 34 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
3.73%
60.00%
90.00%
3.49%
60.00%
70.00%
3.49%
40.00%
40.00%
3.49%
40.00%
40.00%
3.49%
40.00%
40.00%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE Electrical Cable trays
RFQ
02-May-11
03-Apr-11
20
Tech. offers open
16-May-11
05-Apr-11
20
Comm. offers open
19-Jun-11
15-May-11
20
Bid tab
03-Jul-11
20-May-11
10
F.O.C.
10-Jul-11
30-May-11
20
P.O.
24-Jul-11
07-Jul-11
10
Electrical Cables
RFQ
09-May-11
03-Apr-11
20
Tech. offers open
23-May-11
05-Apr-11
20
Comm. offers open
22-Jun-11
07-Jun-11
20
Bid tab
06-Jul-11
15-Jun-11
F.O.C.
13-Jul-11
03-Jul-11
20
P.O.
27-Jul-11
10-Jul-11
10
10
Navigation aids system 20
RFQ
16-May-11
28-Apr-11
Tech. offers open
30-May-11
16-May-11
Comm. offers open
27-Jun-11
17-Jul-11
20
Bid tab
11-Jul-11
26-Jul-11
10
F.O.C.
18-Jul-11
01-Aug-11
20
P.O.
02-Aug-11
10-Aug-11
10
20
Instrument & Mechanical bulk material
RFQ
05-Jun-11
04-May-11
Tech. offers open
19-Jun-11
26-May-11
Comm. offers open
03-Jul-11
20 20 21-Jul-11
20
Bid tab
17-Jul-11
31-Jul-11
10
F.O.C.
24-Jul-11
04-Aug-11
20
07-Aug-11
18-Aug-11
10
P.O.
Inst. Junction Box
RFQ
09-Jun-11
07-Jun-11
Tech. offers open
23-Jun-11
20-Jun-11
20 20
Comm. offers open
07-Jul-11
27-Jul-11
20
Bid tab
21-Jul-11
07-Aug-11
10
F.O.C.
28-Jul-11
17-Aug-11
20
P.O.
11-Aug-11
21-Aug-11
10
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
Page 35 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
4.19%
70.00%
70.00%
3.73%
60.00%
40.00%
3.45%
40.00%
40.00%
3.49%
40.00%
0.00%
3.54%
70.00%
40.00%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE HIPPS
RFQ
07-Apr-11
03-Apr-11
20
Tech. offers open
28-Apr-11
05-Apr-11
20
Comm. offers open 31-May-11
16-Jun-11
20
Bid tab
23-Jun-11
14-Jun-11
10
F.O.C.
28-Jun-11
06-Jul-11
P.O.
12-Jul-11
14-Jul-11
20 10
Choke valves
RFQ
13-Apr-11
03-Apr-11
20
Tech. offers open
12-May-11
26-Apr-11
20
Comm. offers open
14-Jun-11
12-Jul-11
20
Bid tab
28-Jun-11
20-Jul-11
10
F.O.C.
05-Jul-11
26-Jul-11
20
P.O.
19-Jul-11
09-Aug-11
10
Loose instrument 20
RFQ
29-May-11
07-Jun-11
Tech. offers open
12-Jun-11
20-Jun-11
Comm. offers open
26-Jun-11
01-Aug-11
20
Bid tab
10-Jul-11
10-Aug-11
10
F.O.C.
17-Jul-11
21-Aug-11
20
P.O.
31-Jul-11
25-Aug-11
10
20
Instrument cable trays
RFQ
31-May-11
20
27-Jun-11
Tech. offers open
14-Jun-11
04-Jul-11
20
Comm. offers open
30-Jun-11
07-Aug-11
20
Bid tab
14-Jul-11
16-Aug-11
10
F.O.C.
14-Jul-11
24-Aug-11
20
28-Jul-11
29-Aug-11
10
P.O.
Electro hydraulic wellhead control panel
RFQ
14-Apr-11
05-Apr-11
Tech. offers open
15-May-11
05-Apr-11
20 20
Comm. offers open
06-Jun-11
30-Jun-11
20
Bid tab
20-Jun-11
06-Jul-11
10
F.O.C.
04-Jul-11
12-Jul-11
20
P.O.
14-Jul-11
18-Jul-11
10
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
Page 36 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
3.54%
70.00%
40.00%
3.49%
60.00%
20.00%
3.49%
40.00%
0.00%
3.73%
60.00%
90.00%
3.49%
60.00%
40.00%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE Wing valves 20
RFQ
13-Apr-11
03-Apr-11
Tech. offers open
12-May-11
02-May-11
Comm. offers open
08-Jun-11
03-Jul-11
20
Bid tab
22-Jun-11
10-Jul-11
10
F.O.C.
06-Jul-11
21-Jul-11
20
P.O.
20-Jul-11
04-Aug-11
10
20
Instrument cable and cable glands
RFQ
23-May-11
20
23-Jun-11
Tech. offers open
06-Jun-11
07-Jul-11
20
Comm. offers open
20-Jun-11
07-Aug-11
20
Bid tab
04-Jul-11
16-Aug-11
10
F.O.C.
11-Jul-11
23-Aug-11
20
P.O.
25-Jul-11
28-Aug-11
10
Sand & Corrosion probes 20
RFQ
02-Jun-11
Tech. offers open
16-Jun-11
10-Jul-11
20
Comm. offers open
11-Jul-11
11-Aug-11
20
25-Jul-11
23-Aug-11
10
F.O.C.
01-Aug-11
29-Aug-11
20
P.O.
15-Aug-11
11-Sep-11
10
Bid tab
27-Jun-11
Multi phase flow meter
10-Apr-11
20
09-May-11
28-Apr-11
20
12-Jun-11
09-Jun-11
20
Bid tab
26-Jun-11
13-Jun-11
10
F.O.C.
10-Jul-11
16-Jun-11
RFQ
10-Apr-11
Tech. offers open Comm. offers open
P.O.
20 03-Jul-11
24-Jul-11
10
Service water pump
RFQ
25-Apr-11
03-Apr-11
Tech. offers open
17-May-11
28-Apr-11
20 20
Comm. offers open
13-Jun-11
10-Jul-11
20
Bid tab
27-Jun-11
18-Jul-11
10
F.O.C.
11-Jul-11
25-Jul-11
20
P.O.
25-Jul-11
02-Aug-11
10
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
Page 37 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
4.19%
60.00%
100.00%
3.49%
0.00%
0.00%
3.73%
40.00%
40.00%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE Turret crane crane
RFQ
13-Apr-11
03-Apr-11
20
Tech. offers open
12-May-11
10-Apr-11
20
Comm. offers open
12-Jun-11
11-May-11
20
Bid tab
26-Jun-11
03-May-11
10
F.O.C.
10-Jul-11
29-May-11
20
P.O.
18-Jul-11
21-Jun-11
10
Monorail crane
28-Jul-11
28-Jul-11
20
Tech. offers open
11-Aug-11
11-Aug-11
20
Comm. offers open
06-Sep-11
06-Sep-11
20
Bid tab
20-Sep-11
20-Sep-11
10
F.O.C.
04-Oct-11
04-Oct-11
20
P.O.
17-Oct-11
17-Oct-11
10
RFQ
Survival module 20
RFQ
02-May-11
03-Apr-11
Tech. offers open
31-May-11
22-May-11
Comm. offers open
29-Jun-11
10-Jul-11
20
Bid tab
13-Jul-11
18-Jul-11
10
20
F.O.C.
19-Jul-11
24-Jul-11
20
P.O.
02-Aug-11
07-Aug-11
10
100.00%
Total
FOREIGN PURCHASING DEPARTMENT
100.00%
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
Page 38 of 59
53.17% 53.17%
44.73% 44.73%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES EXPEDITING DEPART. COMMODITIES ONE BY ONE Safety equipment and life saving
Start
10-Jul-11
04-Aug-11
10
Receiv. Supp. Key
29-Aug-11
25-Sep-11
20
Place Main Mat. S/
18-Sep-11
17-Oct-11
10
Receiv. Main Mat.s
17-Nov-11
13-Dec-11
20
07-Dec-11
01-Jan-12
40
Fabrication Finish
Flame arrestor
Start
21-Jul-11
11-Aug-11
10
Receiv. Supp. Key
09-Sep-11
10-Oct-11
20
Place Main Mat. S/
29-Sep-11
26-Oct-11
10
Receiv. Main Mat.s
29-Oct-11
27-Nov-11
20
Fabrication Finish
28-Nov-11
26-Dec-11
40
Chemical injection package
Start
10-Jul-11
05-Jul-11
Receiv. Supp. Key
18-Sep-11
11-Sep-11
20
Place Main Mat. S/
23-Sep-11
14-Sep-11
10
Receiv. Main Mat.s
27-Nov-11
20-Nov-11
20
Fabrication Finish
06-Jan-12
27-Dec-11
40
Start
05-Jul-11
20-Jul-11
Receiv. Supp. Key
03-Sep-11
19-Sep-11
20
Place Main Mat. S/
23-Sep-11
09-Oct-11
10
Receiv. Main Mat.s
12-Nov-11
24-Nov-11
20
Fabrication Finish
31-Dec-11
04-Jan-12
40
Start
08-Aug-11
05-Sep-11
10
Receiv. Supp. Key
07-Oct-11
06-Nov-11
20
Place Main Mat. S/
27-Oct-11
24-Nov-11
10
Fabrication Finish
06-Dec-11
02-Jan-12
40
Receiv. Main Mat.s
06-Dec-11
03-Jan-12
20
Piping bulk
19-Jun-11 05-Jan-12
1.86%
0.00%
0.00%
4.66%
0.00%
0.00%
3.73%
0.00%
0.00%
1.86%
0.00%
0.00%
3.50%
20.00%
0.00%
20
26-Jun-11 10-Jan-12
80
Layout No. 1
* Weights of Activities are calculated relative to (EXPEDITING DEPART.) Tuesday, July 05, 2011
0.00%
10
Vent stack tips
Fabrication Finish
0.00%
10
Fire Fighting package
Start
1.86%
Page 39 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES EXPEDITING DEPART. COMMODITIES ONE BY ONE Insulation Joint
Start
10-Jul-11
22-Aug-11
10
Receiv. Supp. Key
08-Sep-11
23-Oct-11
20
Place Main Mat. S/
18-Sep-11
31-Oct-11
10
Receiv. Main Mat.s
18-Oct-11
30-Nov-11
20
07-Dec-11
18-Jan-12
40
Fabrication Finish
Injection fitting
Start
13-Jul-11
18-Aug-11
10
Receiv. Supp. Key
11-Sep-11
23-Oct-11
20
Place Main Mat. S/
21-Sep-11
31-Oct-11
10
Receiv. Main Mat.s
21-Oct-11
30-Nov-11
20
Fabrication Finish
10-Dec-11
18-Jan-12
40
Earthing material
Start
08-Aug-11
25-Aug-11
20
Fabrication Finish
26-Dec-11
26-Dec-11
80
Lighting material
Start
27-Jul-11
24-Aug-11
20
Fabrication Finish
14-Dec-11
23-Dec-11
80
Electrical Cable trays
Start Fabrication Finish
10-Jul-11
06-Jul-11
20
18-Oct-11
02-Oct-11
80
Electrical Cables
Start Fabrication Finish
17-Jul-11
06-Jul-11
20
04-Dec-11
22-Nov-11
80
Navigation aids system
Start
18-Jul-11
01-Aug-11
10
Receiv. Supp. Key
16-Sep-11
27-Sep-11
20
Place Main Mat. S/
06-Oct-11
20-Oct-11
10
Receiv. Main Mat.s
26-Oct-11
09-Nov-11
20
Fabrication Finish
05-Dec-11
18-Dec-11
40
Instrument & Mechanical bulk material
Start
24-Jul-11
04-Aug-11
20
Fabrication Finish
01-Nov-11
05-Nov-11
80
0.00%
0.00%
1.86%
0.00%
0.00%
1.86%
0.00%
0.00%
2.33%
0.00%
0.00%
1.86%
0.00%
0.00%
2.33%
0.00%
0.00%
3.73%
0.00%
0.00%
1.86%
0.00%
0.00%
Layout No. 1
* Weights of Activities are calculated relative to (EXPEDITING DEPART.) Tuesday, July 05, 2011
1.86%
Page 40 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES EXPEDITING DEPART. COMMODITIES ONE BY ONE Inst. Junction Box
Start
28-Jul-11
17-Aug-11
20
Finish
05-Nov-11
09-Nov-11
80
HIPPS
28-Jun-11
07-Jul-11
10
Receiv. Supp. Key
26-Oct-11
06-Nov-11
20
Place Main Mat. S/
15-Nov-11
24-Nov-11
10
Receiv. Main Mat.s
24-Jan-12
02-Feb-12
20
Fabrication Finish
24-Mar-12
17-Mar-12
40
Start
Choke valves
Start
05-Jul-11
27-Jul-11
Receiv. Supp. Key
02-Nov-11
24-Nov-11
20
Place Main Mat. S/
22-Nov-11
14-Dec-11
10
Receiv. Main Mat.s
31-Jan-12
22-Feb-12
20
Fabrication Finish
31-Mar-12
21-Apr-12
40
Start
17-Jul-11
15-Aug-11
20
Fabrication Finish
13-Jan-12
20-Feb-12
80
Instrument cable trays
Fabrication Finish
14-Jul-11
24-Aug-11
20
22-Oct-11
18-Nov-11
80
Electro hydraulic wellhead control panel
10-Jul-11
12-Jul-11
10
Receiv. Supp. Key
08-Oct-11
04-Oct-11
20
Place Main Mat. S/
07-Nov-11
03-Nov-11
10
Receiv. Main Mat.s
17-Dec-11
13-Dec-11
20
Fabrication Finish
06-Jan-12
01-Jan-12
40
Start
Wing valves
Start
06-Jul-11
24-Jul-11
10
Receiv. Supp. Key
04-Oct-11
20-Oct-11
20
Place Main Mat. S/
03-Nov-11
21-Nov-11
10
Receiv. Main Mat.s
13-Dec-11
29-Dec-11
20
Fabrication Finish
01-Apr-12
16-Apr-12
40
Instrument cable and cable glands
Start
11-Jul-11
14-Aug-11
20
Fabrication Finish
28-Nov-11
08-Nov-11
80
0.00%
4.66%
0.00%
0.00%
3.73%
0.00%
0.00%
1.86%
0.00%
0.00%
1.86%
0.00%
0.00%
3.73%
0.00%
0.00%
3.26%
0.00%
0.00%
1.86%
0.00%
0.00%
Layout No. 1
* Weights of Activities are calculated relative to (EXPEDITING DEPART.) Tuesday, July 05, 2011
0.00%
10
Loose instrument
Start
1.86%
Page 41 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES EXPEDITING DEPART. COMMODITIES ONE BY ONE Sand & Corrosion probes
Start
01-Aug-11
30-Aug-11
10
Receiv. Supp. Key
30-Sep-11
27-Oct-11
20
Place Main Mat. S/
30-Oct-11
28-Nov-11
10
Receiv. Main Mat.s
09-Dec-11
07-Jan-12
20
Fabrication Finish
29-Dec-11
08-Jan-12
40
Multi phase flow meter
10-Jul-11
Receiv. Supp. Key
28-Sep-11
12-Sep-11
20
Place Main Mat. S/
08-Oct-11
20-Sep-11
10
Receiv. Main Mat.s
27-Nov-11
09-Nov-11
20
Fabrication Finish
06-Jan-12
21-Dec-11
40
20-Jun-11
Service water pump
Start
11-Jul-11
28-Jul-11
10
Receiv. Supp. Key
19-Sep-11
06-Oct-11
20
Place Main Mat. S/
09-Oct-11
26-Oct-11
10
Receiv. Main Mat.s
18-Nov-11
05-Dec-11
20
Fabrication Finish
28-Nov-11
14-Dec-11
40
Turret crane crane
10-Jul-11
Receiv. Supp. Key
01-Nov-11
Place Main Mat. S/
0.00%
3.73%
0.00%
10.00%
3.26%
0.00%
0.00%
4.66%
0.00%
10.00%
1.86%
0.00%
0.00%
3.26%
0.00%
0.00%
10
21-Jun-11 27-Sep-11
20
11-Nov-11
09-Oct-11
10
Receiv. Main Mat.s
20-Jan-12
18-Dec-11
20
Fabrication Finish
29-Feb-12
19-Feb-12
40
Monorail crane
Start
04-Oct-11
04-Oct-11
10
Receiv. Supp. Key
13-Dec-11
13-Dec-11
20
Place Main Mat. S/
23-Dec-11
23-Dec-11
10
Receiv. Main Mat.s
12-Jan-12
12-Jan-12
20
Fabrication Finish
01-Feb-12
01-Feb-12
40
Survival module
Start
11-Jul-11
28-Jul-11
10
Receiv. Supp. Key
09-Oct-11
26-Oct-11
20
Place Main Mat. S/
29-Oct-11
15-Nov-11
10
Fabrication Finish
28-Nov-11
14-Dec-11
40
Receiv. Main Mat.s
08-Dec-11
25-Dec-11
20
Layout No. 1
* Weights of Activities are calculated relative to (EXPEDITING DEPART.) Tuesday, July 05, 2011
0.00%
10
Start
Start
1.86%
Page 42 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
4.66%
10.00%
10.00%
4.66%
10.00%
10.00%
4.66%
10.00%
10.00%
4.66%
10.00%
10.00%
4.66%
10.00%
10.00%
ENPPI W.P.3 PROCUREMENT SERVICES EXPEDITING DEPART. COMMODITIES ONE BY ONE Production Manifold 10
Start
19-Apr-11
Receiv. Supp. Key
17-Aug-11
17-Aug-11
20
Place Main Mat. S/
27-Aug-11
27-Aug-11
10
Receiv. Main Mat.s
15-Nov-11
15-Nov-11
20
15-Dec-11
15-Dec-11
40
Fabrication Finish
24-May-11
E&I Module 10
Start
19-Apr-11
Receiv. Supp. Key
17-Aug-11
03-May-11 07-Sep-11
20
Place Main Mat. S/
27-Aug-11
27-Aug-11
10
Receiv. Main Mat.s
15-Nov-11
15-Nov-11
20
Fabrication Finish
15-Dec-11
15-Dec-11
40
Actuated valves 10
Start
19-Apr-11
19-Apr-11
Receiv. Supp. Key
17-Aug-11
05-Sep-11
20
Place Main Mat. S/
06-Sep-11
06-Sep-11
10
Receiv. Main Mat.s
15-Nov-11
15-Nov-11
20
Fabrication Finish
15-Dec-11
15-Dec-11
40
Emergency Generator 10
Start
19-Apr-11
Receiv. Supp. Key
17-Aug-11
23-May-11 03-Sep-11
20
Place Main Mat. S/
06-Sep-11
06-Sep-11
10
Receiv. Main Mat.s
15-Nov-11
15-Nov-11
20
Fabrication Finish
15-Dec-11
15-Dec-11
40
Micro Turbine 10
Start
19-Apr-11
03-May-11
Place Main Mat. S/
16-Sep-11
16-Sep-11
10
Receiv. Supp. Key
16-Sep-11
16-Sep-11
20
Receiv. Main Mat.s
25-Nov-11
25-Nov-11
20
Fabrication Finish
15-Dec-11
15-Dec-11
40
100.00%
Total
EXPEDITING DEPART.
100.00%
3.03%
3.17% 3.17%
Layout No. 1
* Weights of Activities are calculated relative to (EXPEDITING DEPART.) Tuesday, July 05, 2011
3.03%
Page 43 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES SUPPLIER QUALITY SRVEILLANCE DEPART. COMMODITIES ONE BY ONE Safety equipment and life saving
NFI
30-Nov-11
25-Dec-11
20
RFS
07-Dec-11
01-Jan-12
80
Flame arrestor
NFI
21-Nov-11
19-Dec-11
20
RFS
28-Nov-11
26-Dec-11
80
Chemical injection package
NFI
30-Dec-11
20-Dec-11
20
RFS
06-Jan-12
27-Dec-11
80
Fire Fighting package
NFI RFS
24-Dec-11
28-Dec-11
20
31-Dec-11
04-Jan-12
80
Vent stack tips
NFI RFS
29-Nov-11
26-Dec-11
20
06-Dec-11
02-Jan-12
80
Piping bulk
NFI
29-Dec-11
03-Jan-12
20
RFS
05-Jan-12
10-Jan-12
80
Insulation Joint
NFI
30-Nov-11
11-Jan-12
20
RFS
07-Dec-11
18-Jan-12
80
Injection fitting
NFI
03-Dec-11
11-Jan-12
20
RFS
10-Dec-11
18-Jan-12
80
Earthing material
NFI
19-Dec-11
19-Dec-11
20
RFS
26-Dec-11
26-Dec-11
80
Lighting material
NFI
07-Dec-11
16-Dec-11
20
RFS
14-Dec-11
23-Dec-11
80
* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.) Tuesday, July 05, 2011
Page 44 of 59
2.75%
0.00%
0.00%
2.75%
0.00%
0.00%
4.59%
0.00%
0.00%
3.67%
0.00%
0.00%
2.75%
0.00%
0.00%
4.59%
0.00%
0.00%
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES SUPPLIER QUALITY SRVEILLANCE DEPART. COMMODITIES ONE BY ONE Electrical Cable trays
NFI
11-Oct-11
25-Sep-11
20
RFS
18-Oct-11
02-Oct-11
80
Electrical Cables
NFI
27-Nov-11
15-Nov-11
20
RFS
04-Dec-11
22-Nov-11
80
Navigation aids system
NFI
28-Nov-11
11-Dec-11
20
RFS
05-Dec-11
18-Dec-11
80
Instrument & Mechanical bulk material
NFI RFS
25-Oct-11
25-Oct-11
20
01-Nov-11
03-Nov-11
80
Inst. Junction Box
NFI RFS
29-Oct-11
02-Nov-11
20
05-Nov-11
09-Nov-11
80
HIPPS
NFI
17-Mar-12
10-Mar-12
20
RFS
24-Mar-12
17-Mar-12
80
Choke valves
NFI
24-Mar-12
14-Apr-12
20
RFS
31-Mar-12
21-Apr-12
80
Loose instrument
NFI
06-Jan-12
04-Jan-12
20
RFS
13-Jan-12
10-Jan-12
80
Instrument cable trays
NFI
15-Oct-11
08-Nov-11
20
RFS
22-Oct-11
18-Nov-11
80
Electro hydraulic wellhead control panel
NFI
30-Dec-11
25-Dec-11
20
RFS
06-Jan-12
01-Jan-12
80
* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.) Tuesday, July 05, 2011
Page 45 of 59
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
2.75%
0.00%
0.00%
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
4.59%
0.00%
0.00%
3.67%
0.00%
0.00%
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
3.67%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES SUPPLIER QUALITY SRVEILLANCE DEPART. COMMODITIES ONE BY ONE Wing valves
NFI
25-Mar-12
09-Apr-12
20
RFS
01-Apr-12
16-Apr-12
80
Instrument cable and cable glands
NFI
21-Nov-11
15-Nov-11
20
RFS
28-Nov-11
11-Dec-11
80
Sand & Corrosion probes
NFI
22-Dec-11
01-Jan-12
20
RFS
29-Dec-11
08-Jan-12
80
Multi phase flow meter
NFI RFS
30-Dec-11
14-Dec-11
20
06-Jan-12
21-Dec-11
80
Service water pump
NFI RFS
21-Nov-11
07-Dec-11
20
28-Nov-11
14-Dec-11
80
Turret crane crane
NFI
22-Feb-12
12-Feb-12
20
RFS
29-Feb-12
19-Feb-12
80
Monorail crane
NFI
25-Jan-12
25-Jan-12
20
RFS
01-Feb-12
01-Feb-12
80
Survival module
NFI
19-Dec-11
26-Dec-11
20
RFS
26-Dec-11
29-Dec-11
80
Production Manifold
NFI
08-Dec-11
08-Dec-11
20
RFS
15-Dec-11
15-Dec-11
80
E&I Module
NFI
08-Dec-11
08-Dec-11
20
RFS
15-Dec-11
15-Dec-11
80
* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.) Tuesday, July 05, 2011
Page 46 of 59
3.67%
0.00%
0.00%
1.83%
0.00%
0.00%
1.83%
0.00%
0.00%
3.67%
0.00%
0.00%
2.75%
0.00%
0.00%
4.59%
0.00%
0.00%
2.75%
0.00%
0.00%
3.67%
0.00%
0.00%
2.75%
0.00%
0.00%
4.59%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES SUPPLIER QUALITY SRVEILLANCE DEPART. COMMODITIES ONE BY ONE Actuated valves
NFI
08-Dec-11
08-Dec-11
20
RFS
15-Dec-11
15-Dec-11
80
Emergency Generator
NFI
08-Dec-11
08-Dec-11
20
RFS
15-Dec-11
15-Dec-11
80
Micro Turbine
NFI
08-Dec-11
08-Dec-11
20
RFS
15-Dec-11
15-Dec-11
80
4.59%
0.00%
0.00%
4.59%
0.00%
0.00%
4.59%
0.00%
0.00%
100.00%
Total
SUPPLIER QUALITY SRVEILLANCE DEP
* Weights of Activities are calculated relative to (SUPPLIER QUALITY SRVEILLANCE DEPART.) Tuesday, July 05, 2011
Page 47 of 59
100.00%
0.00% 0.00%
0.00% 0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES TRAFFIC & LOGISTICS DEPARTMENT COMMODITIES ONE BY ONE Safety equipment and life saving
Mat. Deliv.to Dest. P 07-Dec-11
02-Jan-12
20
Mat. Deliv.to Ship. P 28-Dec-11
22-Jan-12
30
Customs Cleared
08-Jan-12
02-Feb-12
30
Material At Site
11-Jan-12
05-Feb-12
20
Flame arrestor
Mat. Deliv.to Dest. P 28-Nov-11
27-Dec-11
20
Mat. Deliv.to Ship. P 19-Dec-11
16-Jan-12
30
Customs Cleared
30-Dec-11
27-Jan-12
30
02-Jan-12
30-Jan-12
20
Material At Site
Chemical injection package
Mat. Deliv.to Dest. P 06-Jan-12
28-Dec-11
20
Mat. Deliv.to Ship. P 27-Jan-12
17-Jan-12
30
Customs Cleared
07-Feb-12
28-Jan-12
30
Material At Site
10-Feb-12
31-Jan-12
20
Fire Fighting package 05-Jan-12
20
Mat. Deliv.to Ship. P 21-Jan-12
25-Jan-12
30
Customs Cleared
01-Feb-12
05-Feb-12
30
Material At Site
04-Feb-12
08-Feb-12
20
Mat. Deliv.to Dest. P 01-Jan-12
Vent stack tips
Mat. Deliv.to Dest. P 06-Dec-11
03-Jan-12
20
Mat. Deliv.to Ship. P 27-Dec-11
23-Jan-12
30
Customs Cleared
07-Jan-12
03-Feb-12
30
Material At Site
10-Jan-12
06-Feb-12
20
Piping bulk 3rd batch
Mat. Deliv.to Dest. P 05-Jan-12
11-Jan-12
20
Mat. Deliv.to Ship. P 26-Jan-12
31-Jan-12
30
Customs Cleared
06-Feb-12
11-Feb-12
30
09-Feb-12
14-Feb-12
20
Material At Site
Insulation Joint
Mat. Deliv.to Dest. P 07-Dec-11
19-Jan-12
20
Mat. Deliv.to Ship. P 28-Dec-11
08-Feb-12
30
Customs Cleared
08-Jan-12
19-Feb-12
30
Material At Site
11-Jan-12
22-Feb-12
20
* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT) Tuesday, July 05, 2011
Page 48 of 59
3.48%
0.00%
0.00%
3.48%
0.00%
0.00%
4.35%
0.00%
0.00%
4.35%
0.00%
0.00%
2.61%
0.00%
0.00%
1.74%
0.00%
0.00%
1.74%
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES TRAFFIC & LOGISTICS DEPARTMENT COMMODITIES ONE BY ONE Injection fitting
Mat. Deliv.to Dest. P 10-Dec-11
19-Jan-12
20
Mat. Deliv.to Ship. P 31-Dec-11
08-Feb-12
30
Customs Cleared
11-Jan-12
19-Feb-12
30
Material At Site
14-Jan-12
22-Feb-12
20
Earthing material
Mat. Deliv.to Dest. P 26-Dec-11
28-Dec-11
20
Mat. Deliv.to Ship. P 24-Jan-12
22-Jan-12
30
Customs Cleared
11-Feb-12
12-Feb-12
30
14-Feb-12
14-Feb-12
20
Material At Site
Lighting material
Mat. Deliv.to Dest. P 14-Dec-11
26-Dec-11
20
Mat. Deliv.to Ship. P 04-Jan-12
13-Jan-12
30
Customs Cleared
15-Jan-12
23-Dec-12
30
Material At Site
18-Jan-12
27-Jan-12
20
Electrical Cable trays 03-Oct-11
20
Mat. Deliv.to Ship. P 08-Nov-11
23-Oct-11
30
Customs Cleared
19-Nov-11
03-Nov-11
30
Material At Site
22-Nov-11
06-Nov-11
20
Mat. Deliv.to Dest. P 18-Oct-11
Electrical Cables
Mat. Deliv.to Dest. P 04-Dec-11
23-Nov-11
20
Mat. Deliv.to Ship. P 25-Dec-11
13-Dec-11
30
Customs Cleared
05-Jan-12
22-Dec-11
30
Material At Site
08-Jan-12
27-Dec-11
20
Navigation aids system
Mat. Deliv.to Dest. P 05-Dec-11
19-Dec-11
20
Mat. Deliv.to Ship. P 26-Dec-11
08-Jan-12
30
Customs Cleared
06-Jan-12
19-Jan-12
30
09-Jan-12
22-Jan-12
20
Material At Site
Instrument & Mechanical bulk material
Mat. Deliv.to Dest. P 01-Nov-11
03-Nov-11
Mat. Deliv.to Ship. P 22-Nov-11
23-Nov-11
30
Customs Cleared
03-Dec-11
07-Dec-11
30
Material At Site
06-Dec-11
07-Dec-11
20
0.00%
0.00%
1.74%
0.00%
0.00%
1.74%
0.00%
0.00%
1.74%
0.00%
0.00%
1.74%
0.00%
0.00%
3.48%
0.00%
0.00%
1.74%
0.00%
0.00%
20
* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT) Tuesday, July 05, 2011
1.74%
Page 49 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES TRAFFIC & LOGISTICS DEPARTMENT COMMODITIES ONE BY ONE Inst. Junction Box
Mat. Deliv.to Dest. P 05-Nov-11
10-Nov-11
Mat. Deliv.to Ship. P 26-Nov-11
30-Nov-11
30
Customs Cleared
07-Dec-11
11-Dec-11
30
Material At Site
10-Dec-11
14-Dec-11
20
Mat. Deliv.to Dest. P 24-Mar-12
18-Mar-12
20
Mat. Deliv.to Ship. P 14-Apr-12
07-Apr-12
30
Customs Cleared
25-Apr-12
18-Apr-12
30
28-Apr-12
21-Apr-12
20
Choke valves 01-May-12
Mat. Deliv.to Ship. P 31-Mar-12
22-May-12
30
Customs Cleared
18-Apr-12
08-Jun-12
30
Material At Site
21-Apr-12
11-Jun-12
20
Loose instrument
Mat. Deliv.to Dest. P 13-Jan-12
10-Jan-12
20
Mat. Deliv.to Ship. P 10-Feb-12
06-Feb-12
30
Customs Cleared
21-Feb-12
18-Feb-12
30
Material At Site
24-Feb-12
20-Feb-12
20
Instrument cable trays
Mat. Deliv.to Dest. P 22-Oct-11
18-Nov-11
Mat. Deliv.to Ship. P 29-Oct-11
17-Nov-11
30
Customs Cleared
09-Nov-11
04-Dec-11
30
Material At Site
12-Nov-11
04-Nov-11
20
4.35%
0.00%
0.00%
3.48%
0.00%
0.00%
1.74%
0.00%
0.00%
1.74%
0.00%
0.00%
3.48%
0.00%
0.00%
2.61%
0.00%
0.00%
20
Electro hydraulic wellhead control panel
Mat. Deliv.to Dest. P 06-Jan-12
02-Jan-12
20
Mat. Deliv.to Ship. P 27-Jan-12
22-Jan-12
30
Customs Cleared
08-Feb-12
02-Feb-12
30
11-Feb-12
05-Feb-12
20
Wing valves
Mat. Deliv.to Dest. P 01-Apr-12
17-Apr-12
20
Mat. Deliv.to Ship. P 22-Apr-12
07-May-12
30
Customs Cleared
03-May-12
18-May-12
30
Material At Site
06-May-12
21-May-12
20
* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT) Tuesday, July 05, 2011
0.00%
20
Mat. Deliv.to Dest. P 10-Mar-12
Material At Site
0.00%
20
HIPPS
Material At Site
1.74%
Page 50 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES TRAFFIC & LOGISTICS DEPARTMENT COMMODITIES ONE BY ONE Instrument cable and cable glands
Mat. Deliv.to Dest. P 28-Nov-11
25-Nov-11
20
Mat. Deliv.to Ship. P 19-Dec-11
17-Dec-11
30
Customs Cleared
30-Dec-11
11-Jan-12
30
Material At Site
02-Jan-12
13-Jan-12
20
Sand & Corrosion probes
Mat. Deliv.to Dest. P 29-Dec-11
09-Jan-12
20
Mat. Deliv.to Ship. P 19-Jan-12
28-Jan-12
30
Customs Cleared
30-Jan-12
09-Feb-12
30
02-Feb-12
11-Feb-12
20
Material At Site
Multi phase flow meter
Mat. Deliv.to Dest. P 06-Jan-12
22-Dec-11
20
Mat. Deliv.to Ship. P 27-Jan-12
11-Jan-12
30
Customs Cleared
07-Feb-12
22-Jan-12
30
Material At Site
10-Feb-12
25-Jan-12
20
Service water pump
Mat. Deliv.to Dest. P 28-Nov-11
15-Dec-11
20
Mat. Deliv.to Ship. P 19-Dec-11
04-Jan-12
30
Customs Cleared
01-Jan-12
17-Jan-12
30
Material At Site
04-Jan-12
20-Jan-12
20
Turret crane crane
Mat. Deliv.to Dest. P 29-Feb-12
20-Feb-12
20
Mat. Deliv.to Ship. P 14-Mar-12
04-Mar-12
30
Customs Cleared
25-Mar-12
15-Mar-12
30
Material At Site
28-Mar-12
18-Mar-12
20
Monorail crane
Mat. Deliv.to Dest. P 01-Feb-12
01-Feb-12
Mat. Deliv.to Ship. P 22-Feb-12
22-Feb-12
30
Customs Cleared
04-Mar-12
04-Mar-12
30
Material At Site
07-Mar-12
07-Mar-12
20
0.00%
0.00%
1.74%
0.00%
0.00%
3.48%
0.00%
0.00%
2.61%
0.00%
0.00%
4.35%
0.00%
0.00%
2.61%
0.00%
0.00%
3.48%
0.00%
0.00%
20
Survival module
Mat. Deliv.to Dest. P 27-Dec-11
01-Jan-12
20
Mat. Deliv.to Ship. P 16-Jan-12
21-Jan-12
30
Customs Cleared
27-Jan-12
01-Feb-12
30
Material At Site
30-Jan-12
04-Feb-12
20
* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT) Tuesday, July 05, 2011
1.74%
Page 51 of 59
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES TRAFFIC & LOGISTICS DEPARTMENT COMMODITIES ONE BY ONE Piping bulk 1st batch
Mat. Deliv.to Dest. P 09-Oct-11
10-Oct-11
20
Mat. Deliv.to Ship. P 30-Oct-11
30-Oct-11
30
Customs Cleared
10-Nov-11
10-Nov-11
30
Material At Site
13-Nov-11
13-Nov-11
20
Piping bulk 2nd batch
Mat. Deliv.to Dest. P 16-Nov-11
22-Nov-11
20
Mat. Deliv.to Ship. P 07-Dec-11
12-Dec-11
30
Customs Cleared
18-Dec-11
21-Dec-11
30
21-Dec-11
26-Dec-11
20
Material At Site
Micro Turbine
26-Dec-11
26-Dec-11
30
29-Dec-11
29-Dec-11
20
Mat. Deliv.to Dest. P 29-Dec-11
29-Dec-11
20
Mat. Deliv.to Ship. P 26-Jan-12
26-Jan-12
30
Customs Cleared Material At Site
Emergency Generator
26-Dec-11
26-Dec-11
30
Mat. Deliv.to Dest. P 29-Dec-11
29-Dec-11
20
Material At Site
29-Dec-11
29-Dec-11
20
Mat. Deliv.to Ship. P 26-Jan-12
26-Jan-12
30
Customs Cleared
E&I Module
Mat. Deliv.to Dest. P 15-Dec-11
15-Dec-11
20
Mat. Deliv.to Ship. P 12-Jan-12
12-Jan-12
30
Customs Cleared
23-Jan-12
23-Jan-12
30
Material At Site
26-Jan-12
26-Jan-12
20
Production Manifold
Mat. Deliv.to Dest. P 15-Dec-11
15-Dec-11
20
Mat. Deliv.to Ship. P 12-Jan-12
12-Jan-12
30
Customs Cleared
23-Jan-12
23-Jan-12
30
26-Jan-12
26-Jan-12
20
Material At Site
Actuated valves
Mat. Deliv.to Dest. P 15-Dec-11
15-Dec-11
20
Mat. Deliv.to Ship. P 12-Jan-12
12-Jan-12
30
Customs Cleared
23-Jan-12
23-Jan-12
30
Material At Site
26-Jan-12
26-Jan-12
20
1.74%
0.00%
0.00%
1.74%
0.00%
0.00%
4.35%
0.00%
0.00%
4.35%
0.00%
0.00%
4.35%
0.00%
0.00%
4.35%
0.00%
0.00%
4.35%
0.00%
0.00%
100.00%
* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT) Tuesday, July 05, 2011
Page 52 of 59
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.3 PROCUREMENT SERVICES TRAFFIC & LOGISTICS DEPARTMENT Total
TRAFFIC & LOGISTICS DEPARTMENT
100.00%
* Weights of Activities are calculated relative to (TRAFFIC & LOGISTICS DEPARTMENT) Tuesday, July 05, 2011
Page 53 of 59
0.00%
0.00%
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION METERIAL SUPPLY COMMODITIES ONE BY ONE Safety equipment and life saving
P.O.
24-Jul-11
18-Aug-11
15
Receiv. Supp. Key
29-Aug-11
26-Sep-11
20
Place Main Mat. S/
18-Sep-11
16-Oct-11
15
RFS
07-Dec-11
01-Jan-12
35
11-Jan-12
05-Feb-12
15
Material At Site
Flame arrestor
P.O.
04-Aug-11
11-Aug-11
15
Receiv. Supp. Key
09-Sep-11
10-Oct-11
20
Place Main Mat. S/
29-Sep-11
26-Oct-11
15
RFS
28-Nov-11
26-Dec-11
35
Material At Site
02-Jan-12
30-Jan-12
15
Chemical injection package
P.O.
24-Jul-11
10-Jul-11
Receiv. Supp. Key
18-Sep-11
11-Sep-11
20
Place Main Mat. S/
23-Sep-11
14-Sep-11
15
RFS
06-Jan-12
27-Dec-11
35
Material At Site
10-Feb-12
31-Jan-12
15
0.00%
0.00%
0.17%
0.00%
0.00%
9.06%
0.00%
0.00%
1.94%
0.00%
0.00%
1.30%
0.00%
0.00%
3.48%
0.00%
0.00%
15
Fire Fighting package
P.O.
18-Jul-11
24-Jul-11
Receiv. Supp. Key
03-Sep-11
19-Sep-11
20
Place Main Mat. S/
23-Sep-11
09-Oct-11
15
RFS
31-Dec-11
04-Jan-12
35
Material At Site
04-Feb-12
08-Feb-12
15
15
Vent stack tips
P.O.
17-Aug-11
24-Aug-11
15
Receiv. Supp. Key
07-Oct-11
06-Nov-11
20
Place Main Mat. S/
27-Oct-11
24-Nov-11
15
RFS
06-Dec-11
02-Jan-12
35
Material At Site
10-Jan-12
06-Feb-12
15
Piping bulk 3rd batch
P.O.
03-Jul-11
07-Jul-11
Place Main Mat. S/
26-Oct-11
02-Nov-11
15
RFS
05-Jan-12
11-Jan-12
35
Material At Site
09-Feb-12
14-Feb-12
15
35
Layout No. 1
* Weights of Activities are calculated relative to (METERIAL SUPPLY) Tuesday, July 05, 2011
2.99%
Page 54 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION METERIAL SUPPLY COMMODITIES ONE BY ONE Insulation Joint
P.O.
24-Jul-11
17-Aug-11
35
Place Main Mat. S/
18-Sep-11
31-Oct-11
15
RFS
07-Dec-11
18-Jan-12
35
Material At Site
11-Jan-12
22-Feb-12
15
Injection fitting
P.O.
27-Jul-11
23-Aug-11
35
Place Main Mat. S/
21-Sep-11
31-Oct-11
15
RFS
10-Dec-11
18-Jan-12
35
14-Jan-12
22-Feb-12
15
Material At Site
Earthing material
24-Aug-11
20-Aug-11
35
Place Main Mat. S/
13-Sep-11
10-Sep-11
15
RFS
26-Dec-11
23-Dec-11
35
Material At Site
14-Feb-12
22-Jan-12
15
P.O.
Lighting material 13-Sep-11
35
28-Sep-11
23-Oct-11
15
14-Dec-11
24-Dec-11
35
18-Jan-12
27-Jan-12
15
P.O.
22-Aug-11
Place Main Mat. S/ RFS Material At Site
Electrical Cable trays
P.O.
24-Jul-11
07-Jul-11
Place Main Mat. S/
19-Aug-11
07-Aug-11
15
RFS
18-Oct-11
02-Oct-11
35
Material At Site
22-Nov-11
06-Nov-11
15
P.O.
27-Jul-11
10-Jul-11
35
Place Main Mat. S/
13-Sep-11
28-Aug-11
15
RFS
04-Dec-11
22-Nov-11
35
08-Jan-12
27-Dec-11
15
Navigation aids system
02-Aug-11
15-Aug-11
15
Receiv. Supp. Key
16-Sep-11
28-Sep-11
20
Place Main Mat. S/
06-Oct-11
20-Oct-11
15
RFS
05-Dec-11
18-Dec-11
35
Material At Site
09-Jan-12
22-Jan-12
15
P.O.
0.00%
0.09%
0.00%
0.00%
0.15%
0.00%
0.00%
1.39%
0.00%
0.00%
2.78%
0.00%
0.00%
1.49%
0.00%
0.00%
8.17%
0.00%
0.00%
Layout No. 1
* Weights of Activities are calculated relative to (METERIAL SUPPLY) Tuesday, July 05, 2011
0.00%
35
Electrical Cables
Material At Site
0.18%
Page 55 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION METERIAL SUPPLY COMMODITIES ONE BY ONE Instrument & Mechanical bulk material
P.O.
07-Aug-11
18-Aug-11
35
Place Main Mat. S/
30-Aug-11
05-Sep-11
15
RFS
01-Nov-11
06-Nov-11
35
Material At Site
06-Dec-11
07-Dec-11
15
Inst. Junction Box
P.O.
11-Aug-11
21-Aug-11
35
Place Main Mat. S/
13-Sep-11
28-Sep-11
15
RFS
05-Nov-11
09-Nov-11
35
10-Dec-11
14-Dec-11
15
Material At Site
HIPPS
12-Jul-11
14-Jul-11
15
23-Oct-11
01-Nov-11
20
Place Main Mat. S/
15-Nov-11
24-Nov-11
15
RFS
24-Mar-12
17-Mar-12
35
Material At Site
28-Apr-12
21-Apr-12
15
P.O. Receiv. Supp. Key
Choke valves
19-Jul-11
09-Aug-11
Receiv. Supp. Key
02-Nov-11
24-Nov-11
20
Place Main Mat. S/
22-Nov-11
14-Dec-11
15
RFS
31-Mar-12
21-Apr-12
35
21-Apr-12
11-Jun-12
15
Loose instrument
P.O.
31-Jul-11
25-Aug-11
35
Place Main Mat. S/
26-Oct-11
23-Oct-11
15
RFS
13-Jan-12
10-Jan-12
35
Material At Site
24-Feb-12
20-Feb-12
15
Instrument cable trays
P.O. Place Main Mat. S/
28-Jul-11
05-Aug-11
35
22-Aug-11
08-Sep-11
15
RFS
22-Oct-11
08-Nov-11
35
Material At Site
12-Nov-11
04-Dec-11
15
Electro hydraulic wellhead control panel
P.O.
18-Jul-11
18-Jul-11
15 20
Receiv. Supp. Key
08-Oct-11
04-Oct-11
Place Main Mat. S/
07-Nov-11
03-Nov-11
15
RFS
06-Jan-12
01-Jan-12
35
Material At Site
11-Feb-12
05-Feb-12
15
0.00%
0.33%
0.00%
0.00%
7.71%
0.00%
0.00%
3.32%
0.00%
0.00%
0.92%
0.00%
0.00%
1.68%
0.00%
0.00%
5.41%
0.00%
0.00%
Layout No. 1
* Weights of Activities are calculated relative to (METERIAL SUPPLY) Tuesday, July 05, 2011
0.00%
15
P.O.
Material At Site
1.44%
Page 56 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION METERIAL SUPPLY COMMODITIES ONE BY ONE Wing valves
P.O.
20-Jul-11
04-Aug-11
15
Receiv. Supp. Key
04-Oct-11
20-Oct-11
20
Place Main Mat. S/
06-Dec-11
03-Jan-12
15
RFS
01-Apr-12
16-Apr-12
35
06-May-12
21-May-12
15
Material At Site
Instrument cable and cable glands
P.O.
25-Jul-11
28-Aug-11
35
Place Main Mat. S/
01-Sep-11
01-Sep-11
15
RFS
28-Nov-11
11-Dec-11
35
Material At Site
02-Jan-12
13-Jan-12
15
Sand & Corrosion probes
15-Aug-11
15-Sep-11
35
Place Main Mat. S/
30-Oct-11
09-Nov-11
15
RFS
29-Dec-11
09-Jan-12
35
Material At Site
02-Feb-12
11-Feb-12
15
P.O.
Multi phase flow meter
P.O.
24-Jul-11
03-Jul-11
Receiv. Supp. Key
18-Sep-11
18-Sep-11
20
Place Main Mat. S/
08-Oct-11
20-Sep-11
15
RFS
06-Jan-12
21-Dec-11
35
10-Feb-12
25-Jan-12
15
Material At Site
0.00%
0.00%
0.83%
0.00%
0.00%
0.50%
0.00%
0.00%
10.97%
0.00%
0.00%
0.54%
0.00%
0.00%
13.25%
0.00%
15.00%
15
Service water pump
P.O.
02-Aug-11
02-Aug-11
15
Receiv. Supp. Key
19-Sep-11
06-Oct-11
20
Place Main Mat. S/
09-Oct-11
26-Oct-11
15
RFS
28-Nov-11
14-Dec-11
35
Material At Site
04-Jan-12
20-Jan-12
15
Turret crane crane 15
P.O.
24-Jul-11
Receiv. Supp. Key
01-Nov-11
27-Sep-11
20
Place Main Mat. S/
11-Nov-11
09-Oct-11
15
RFS
29-Feb-12
19-Feb-12
35
Material At Site
28-Mar-12
18-Mar-12
15
21-Jun-11
Layout No. 1
* Weights of Activities are calculated relative to (METERIAL SUPPLY) Tuesday, July 05, 2011
2.70%
Page 57 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION METERIAL SUPPLY COMMODITIES ONE BY ONE Monorail crane
P.O.
17-Oct-11
17-Oct-11
15
Receiv. Supp. Key
13-Dec-11
13-Dec-11
20
Place Main Mat. S/
23-Dec-11
23-Dec-11
15
RFS
01-Feb-12
01-Feb-12
35
07-Mar-12
07-Mar-12
15
Material At Site
Survival module
P.O.
02-Aug-11
07-Aug-11
15
Receiv. Supp. Key
09-Oct-11
26-Oct-11
20
Place Main Mat. S/
29-Oct-11
15-Nov-11
15
RFS
26-Dec-11
29-Dec-11
35
Material At Site
30-Jan-12
04-Feb-12
15
Piping bulk 1st batch
P.O.
03-Jul-11
07-Jul-11
Place Main Mat. S/
28-Aug-11
04-Sep-11
15
RFS
09-Oct-11
10-Oct-11
35
Material At Site
13-Nov-11
13-Nov-11
15
0.00%
0.00%
3.10%
0.00%
0.00%
8.70%
0.00%
0.00%
5.22%
0.00%
0.00%
35
Piping bulk 2nd batch
P.O.
03-Jul-11
07-Jul-11
35
Place Main Mat. S/
16-Oct-11
23-Oct-11
15
RFS
16-Nov-11
22-Nov-11
35
21-Dec-11
26-Dec-11
15
Material At Site
0.17%
100.00%
Total
METERIAL SUPPLY
100.00%
0.00%
1.99% 1.99%
Layout No. 1
* Weights of Activities are calculated relative to (METERIAL SUPPLY) Tuesday, July 05, 2011
0.00%
Page 58 of 59
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Issuance Status Report
SETH Offshore EPC Project Dates
Milestone Planned
Actual
Expected
Milestone Value
As Of : 25-Jun-11
* Relative Weight
Planned Progress%
Actual Progress%
ENPPI W.P.9 OFFSHORE HOOK-UP & COMMISSIONING COMMISSIONING SYSTEM BY SYSTEM Commissioning activities
100.00%
Start
01-Jun-12
01-Jun-12
20
Finish
30-Jun-12
30-Jun-12
80
100.00%
Total
COMMISSIONING
100.00%
0.00% 0.00%
0.00%
0.00% 0.00%
Layout No. 1
* Weights of Activities are calculated relative to (COMMISSIONING) Tuesday, July 05, 2011
0.00%
Page 59 of 59
Data'Nes Systems, Release 2.21
PAGE 25 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.2.2 TECNOMARE
GFL 003-0405
3467-200
ITEM DESCRIPTION
1.1
PROJECT MANAGEMENT
1.2
DETAILED ENGINEERING
1.3
PROCUREMENT SERVICES
1.4
SUBSTRUCTURE ( PREDRILLING TEMPLATE , PILES AND JACKET) FABRICATION
1.5
DECK AND TSF MATERIAL/EQUIPMENT SUPPLY AND FABRICATION
1.6
PIPELINE SPOOLS FABRICATION
1.7
LOAD OUT AND SEA FASTENING
1.8
OFFSHORE HOOK-UP AND COMMISSIONING
1.9
COST IMPACT DUE TO CRASHING THE SCHEDULE TO MEET TARGET DATE INCLUDING (INTERNALS BONUS FOR LABORS , THREE SHIFT WITH COMPLETE NDT , OVERTIME, ADDITIONAL SHIFTS , LABOR DAILY LOGISTICS ,..ETC )
TOTAL
Weight
Progress @ cut-off date
Monthly progress
Previous month Progress
%
%
%
%
14,17% 36,71% 1,35% 3,91% 37,25%
39,46% 51,65% 37,07% 35,00% 35,00%
5,57% 11,60% 5,06% 11,67% 0,00%
33,89% 40,05% 32,01% 23,33% 35,00%
6,61%
0,00%
0,00%
0,00%
100,00%
39,46%
5,57%
33,89%
14,17%
39,46%
5,57%
33,89%
14,17%
39,46%
5,57%
33,89%
26,16% 3,90%
66,10% 20,00%
16,28% 0,00%
49,82% 20,00%
1,06% 1,14% 4,45%
0,00% 0,00% 20,00%
0,00% 0,00% 0,00%
0,00% 0,00% 20,00%
36,71%
51,65%
11,60%
40,05%
0,54%
26,66%
6,66%
20,00%
1.1. PROJECT MANAGEMENT 1.1.1.
PROJECT SERVICES
1.1.2
QA/QC
1.1.3
HSE
1.1.4
SYSTEM INTEGRITY ASSURANCE
1.1.5
CLIENT FACILITIES
1.1.6
CONSORTIUM FACILITES
SUBTOTAL 1.1 1.2. DETAILED ENGINEERING 1.2.1
DECK
1.2.2
SSIV/PLEM (TECHNICAL FOLLOW UP)
1.2.4
LOAD OUT AND SEAFASTENING
1.2.5
OFFSHORE TRANSPORTATION
1.2.6
HOOKUP AND COMMISSIONING
1.2.7
MANUALS
1.2.8
AS BUILT DOSSIER
1.2.9
CERTIFICATION ( ASSISTANCE)
1.2.10
TECHNICAL FOLLOW ON FOR T & I CONTRACTS
SUBTOTAL 1.2 1.3. PROCUREMENT SERVICES 1.3.1
COMPANY PROVIDED ITEMS
1.3.2
CONTRACTOR PROVIDED ITEMS
1.3.3
PLEM/SSIV
1.3.4
HOOK-UP AND COMMISSIONING
1.3.5
LOAD OUT AND SEA FASTENING
1.3.6
PLC/RTU
0,81%
44,00%
4,00%
40,00%
SUBTOTAL 1.3
1,35%
37,07%
5,06%
32,01%
3,91%
35,00%
11,67%
23,33%
3,91%
35,00%
11,67%
23,33%
1.4. SUBSTRUCTURE 1.4.1
YARD MOBILIZATION
1.4.2
PRE_DRILLING TEMPLATE
1.4.3
PILES
1.4.4
JACKET STRUCTURES
1.4.5
BOAT LANDING, BARGE BUMPERS
1.4.6
ANODES INSTALLATION
1.4.7
RISERS, CAISSONS AND SUPPORTS,
1.4.8
BUOYANCY TANKS FABRICATION & ERECTION
1.4.9
GROUT SEALS AND SHOCK CELLS
1.4.10
WEIGHT CONTROL
1.4.11
SURFACE PREPARATION AND PAINTING
1.4.12
INSPECTIONS, TESTING AND PRE-COMMISSIONING
1.4.13
INSTALLATION AIDS ,BALLASTING AND GROUTING SYSTEM, WALK WAY ,STAIRS UPENDING TRENNIONS
1.4.14
BARGE PREPARATION (BERTHING , CLEANING , BLASTING , TEFLON, GRILLAGE LOAD AND OFFLOAD,..)
1.4.15
GRILLAGE SUPPLY, FABRICATION
SUBTOTAL 1.4
1.5 DECK MATERIAL/EQUIPMENT SUPPLY AND FABRICATION 1.5.1.
YARD MOBILIZATION
1.5.2.
MAIN STRUCTURES
1.5.3.
SECONDARY STRUCTURES
1.5.4.
MECHANICAL EQUIPMENT
1.5.5.
PIPING AND MANUAL VALVES
1.5.6
ELECTRICAL
1.5.7
INSTRUMENTATION
1.5.8
SURFACE PREPARATION AND PAINTING
1.5.9
INSULATION
1.5.10
MECHANICAL COMPLETION AND PRECOMMISSIONING
1.5.11
WEIGHT CONTROL
1.5.12
INSTALLATION AIDS FABRICATION AND GRILLAGE SUPPLY
1.5.13
BARGE PREPARATION (BERTHING , CLEANING , BLASTING , GRILLAGE LOAD AND OFFLOAD,..)
1.5.14
FIRE FIGHTING AND SAFETY EQUIPMENT
1.5.15
ARCHITECTURE
1.5.16
ELECTRICAL POWER GENERATION
1.5.17
OTHER INSTRUMENTATION
a.
MATERIAL/EQUIPMENT SUPPLY a.1 PLC/RTU
37,25%
35,00%
0,00%
35,00%
37,25%
35,00%
0,00%
35,00%
6,61%
0,00%
0,00%
0,00%
6,61%
0,00%
0,00%
0,00%
a.2 NAV AIDS a.3 INSTRUMENTATION BULKS b. 1.5.18
INSULATION UTILITY EQUIPMENT, FIRE FIGHTING SYSTEM
SUBTOTAL 1.5 1.6 PIPELINE AND SPOOLS SUBTOTAL 1.6 1.7 LOAD OUT AND SEAFASTENING SUBTOTAL 1.7 1.8 OFFSHORE HOOK - UP AND COMMISSIONING 1.8.1
OFFSHORE HOOK - UP AND COMMISSIONING
JACKET AND DECK
1.8.1.1 HOOK-UP AND COMMISSIONING SUPPLY OF MATERIALS 1.8.1.2 COMMISSIONING SPARE PARTS 1.8.1.3 HOOK-UP, COMMISSIONING ACTIVITIES AND TESTS 1.8.1.4 FIRST FILLING FOR DIESEL 1.8.1.5 ASISTANT DURING START UP
SUBTOTAL 1.8
PAGE 26 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.23 PETROJET
GFL 003-0405
3467-200
LEVEL I OVERALL WP
PETROJET
CLIENT :PETROBEL PROJECT : SETH DEVELOPMENT PROJECT
WK
14
R.W %
R.W %
25‐Jun‐11
DATE : ACTUAL %
Activity Name
Total Budgete Units (Hrs)
PETROJET WORK PACKAGE
€ 16,500,000
WEEK NO.
13
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
ITEM
OVERALL
ITEM
OVERALL
100%
22.34%
22.34%
18.00%
18.00%
31-Mar-11
31-Oct-12
4.34%
4.34%
WP1
PROJECT MANAGEMENT
€
2,125,000
13%
18.00%
2.32%
18.00%
2.32%
31-Mar-11
31-Oct-12
0.00%
0.00%
WP3
PROCUREMENT SERVICES
€
100,000
1%
18.00%
0.11%
18.00%
0.11%
31-Mar-11
31-Oct-12
0.00%
0.00%
WP4
SUBSTRUCTURE ( P.D.T, PILES AND JACKET ) FABRICATION
€
5,195,000
31%
44.27%
13.94%
32.53%
10.24%
31-Mar-11
15-Mar-12
11.74%
3.69%
WP5
DECK & TSF MATERIAL/EQUIPMENT SUPPLY AND FABRICATION
€
5,860,000
36%
16.82%
5.97%
15.01%
5.33%
31-Mar-11
29-Apr-12
1.81%
0.64%
WP6
PIPELINE SPOOLS FABRICATION
€
620,000
4%
0.00%
0.00%
0.00%
0.00%
23-Feb-12
25-Apr-12
0.00%
0.00%
WP8
LOAD OUT AND SEA FASTENING
€
1,400,000
8%
0.00%
0.00%
0.00%
0.00%
18-Oct-11
08-May-12
0.00%
0.00%
WP9
OFFSHORE HOOK-UP AND COMMISSIONING
€
900,000
5%
0.00%
0.00%
0.00%
0.00%
16-May-12
15-Jun-12
0.00%
0.00%
COST IMPACT DUE TO CRASHING THE SCHEDULE TO MEET TARGET DATE….
€
300,000
2%
0.00%
0.00%
0.00%
0.00%
15-Nov-11
15-Apr-12
0.00%
0.00%
8
1/40
WP1 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL
PROJECT : SETH DEVELOPMENT PROJECT
Act ID
Activity Name
W.P.1: PROJECT MANAGEMENT
WK
WEEK NO.
25‐Jun‐11
DATE :
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
580
18.00%
18.00%
18.00%
R.W %
ACTUAL %
13
PLANNED % DEV/ITEM
DEV/ OVERALL
Start Date
Finish Date
18.00%
31-Mar-11
31-Oct-12
0.00%
0.00%
M01
Apr-11
6.00%
25
100.00%
6.00%
100.00%
6.00%
31-Mar-11
25-Apr-11
0.00%
0.00%
M02
May-11
6.00%
29
100.00%
6.00%
100.00%
6.00%
26‐Apr‐11
25‐May‐11
0.00%
0.00%
M03
Jun-11
6.00%
30
100.00%
6.00%
100.00%
6.00%
26‐May‐11
25‐Jun‐11
0.00%
0.00%
M04
Jul-11
6.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Jun‐11
25‐Jul‐11
0.00%
0.00%
M05
Aug-11
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jul‐11
25‐Aug‐11
0.00%
0.00%
M06
Sep-11
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Aug‐11
25‐Sep‐11
0.00%
0.00%
M07
Oct-11
6.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Sep‐11
25‐Oct‐11
0.00%
0.00%
M08
Nov-11
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Oct‐11
25‐Nov‐11
0.00%
0.00%
M09
Dec-11
6.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Nov‐11
25‐Dec‐11
0.00%
0.00%
M10
Jan-12
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Dec‐11
25‐Jan‐12
0.00%
0.00%
M11
Feb-12
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jan‐12
25‐Feb‐12
0.00%
0.00%
M12
Mar-12
6.00%
28
0.00%
0.00%
0.00%
0.00%
26‐Feb‐12
25‐Mar‐12
0.00%
0.00%
M13
Apr-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Mar‐12
25‐Apr‐12
0.00%
0.00%
M14
May-12
4.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Apr‐12
25‐May‐12
0.00%
0.00%
M15
Jun-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐May‐12
25‐Jun‐12
0.00%
0.00%
M16
Jul-12
4.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Jun‐12
25‐Jul‐12
0.00%
0.00%
M17
Aug-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jul‐12
25‐Aug‐12
0.00%
0.00%
M18
Sep-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Aug‐12
25‐Sep‐12
0.00%
0.00%
M19
Oct-12
4.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Sep‐12
25‐Oct‐12
0.00%
0.00%
02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
2/40
WP3 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL
PROJECT : SETH DEVELOPMENT PROJECT
Act ID
Activity Name
W.P.3: PROCUREMENT SERVICES
WK
WEEK NO.
25‐Jun‐11
DATE :
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
580
18.00%
18.00%
18.00%
R.W %
ACTUAL %
13
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
18.00%
31-Mar-11
31-Oct-12
0.0%
0.0%
M01
Apr-11
6.00%
25
100.00%
6.00%
100.00%
6.00%
31-Mar-11
25-Apr-11
0.0%
0.0%
M02
May-11
6.00%
29
100.00%
6.00%
100.00%
6.00%
26‐Apr‐11
25‐May‐11
0.0%
0.0%
M03
Jun-11
6.00%
30
100.00%
6.00%
100.00%
6.00%
26‐May‐11
25‐Jun‐11
0.0%
0.0%
M04
Jul-11
6.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Jun‐11
25‐Jul‐11
0.0%
0.0%
M05
Aug-11
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jul‐11
25‐Aug‐11
0.0%
0.0%
M06
Sep-11
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Aug‐11
25‐Sep‐11
0.0%
0.0%
M07
Oct-11
6.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Sep‐11
25‐Oct‐11
0.0%
0.0%
M08
Nov-11
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Oct‐11
25‐Nov‐11
0.0%
0.0%
M09
Dec-11
6.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Nov‐11
25‐Dec‐11
0.0%
0.0%
M10
Jan-12
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Dec‐11
25‐Jan‐12
0.0%
0.0%
M11
Feb-12
6.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jan‐12
25‐Feb‐12
0.0%
0.0%
M12
Mar-12
6.00%
28
0.00%
0.00%
0.00%
0.00%
26‐Feb‐12
25‐Mar‐12
0.0%
0.0%
M13
Apr-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Mar‐12
25‐Apr‐12
0.0%
0.0%
M14
May-12
4.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Apr‐12
25‐May‐12
0.0%
0.0%
M15
Jun-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐May‐12
25‐Jun‐12
0.0%
0.0%
M16
Jul-12
4.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Jun‐12
25‐Jul‐12
0.0%
0.0%
M17
Aug-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jul‐12
25‐Aug‐12
0.0%
0.0%
M18
Sep-12
4.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Aug‐12
25‐Sep‐12
0.0%
0.0%
M19
Oct-12
4.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Sep‐12
25‐Oct‐12
0.0%
0.0%
02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
3/40
WP4 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL PROJECT : SETH DEVELOPMENT PROJECT Total Budgete Units (Hrs)
R.W %
262712
JACKET STRUCTURE FABRICATION MAIN STRUCTURE FABRICATION
Act ID
Activity Name
W.P.4: SUBSTRUCTURES (PILES, JACKET & PDT) FABRICATION
General
25‐Jun‐11
DATE :
WK
WEEK NO.
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
351
44.27%
44.27%
32.53%
246356
93.77%
351
45.22%
42.41%
133676
54.26%
344
70.65%
864
0.65%
344
ACTUAL %
13
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
32.53%
31-Mar-11
15-Mar-12
11.74%
11.74%
34.69%
32.53%
31‐Mar‐11
15‐Mar‐12
10.53%
9.87%
38.33%
54.94%
29.81%
31‐Mar‐11
08‐Mar‐12
15.70%
8.52%
0.00%
0.00%
0.00%
0.00%
31-Mar-11
08-Mar-12
0.00%
0.00%
100.00%
0.00%
100.00%
0.00%
31-Mar-11
31-Mar-11
0.00%
0.00%
PTJ2000
Jacket main structure fabrication start
0
0.00%
0
PTJ2210
Jacket main structure fabrication finish
0
0.00%
0
0.00%
0.00%
0.00%
29-Feb-12
29-Feb-12
0.00%
0.00%
PTJ2230
Jacket weighing
864
100 00% 100.00%
2
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
07‐Mar‐12
08‐Mar‐12
0 00% 0.00%
0 00% 0.00%
42224
31.59%
88
94.95%
29.99%
99.86%
31.54%
31-Mar-11
26-Jun-11
-4.91%
-1.55%
1596
3.78%
21
90.00%
3.40%
100.00%
3.78%
31-Mar-11
26-Apr-11
-10.00%
-0.38%
JACKET LEGS FABRICATION PTJ5000
PREPARATION OF SKID WAY
PTJ5010
PREPARATION LEG FOR ROW A & B TRIAL FIT
LEG A1 DIM 1400
544
1.29%
8
100.00%
1.29%
88.89%
1.15%
18-Jun-11
26-Jun-11
11.11%
0.14%
9992
23.66%
78
91.61%
21.68%
100.00%
23.66%
31-Mar-11
16-Jun-11
-8.39%
-1.98%
5520
55.24%
53
87.50%
48.34%
100.00%
55.24%
31-Mar-11
22-May-11
-12.50%
-6.91%
PTJ5160
LEG SPLICE FIT UP
1224
22.17%
9
95.00%
21.07%
100.00%
22.17%
31-Mar-11
10-Apr-11
-5.00%
-1.11%
PTJ5170
CANS FIT UP
1224
22.17%
9
80.00%
17.74%
100.00%
22.17%
11-Apr-11
21-Apr-11
-20.00%
-4.43%
PTJ5180
LEG SPLICE WELDING & NDT
1536
27.83%
12
95.00%
26.43%
100.00%
27.83%
23-Apr-11
8-May-11
-5.00%
-1.39%
PTJ5190
CAN WELDING & NDT
1536
27.83%
12
80.00%
22.26%
100.00%
27.83%
9-May-11
22-May-11
-20.00%
-5.57%
2564
25.66%
47
100.00%
25.66%
100.00%
25.66%
23-Apr-11
8-Jun-11
0.00%
0.00%
23-Apr-11
04-May-11
0.00%
0.00%
DIM 1200 PTJ5090
LEG SPLICE FIT UP
612
23.87%
9
100.00%
23.87%
100.00%
23.87%
PTJ5110
CANS FIT UP
272
10.61%
4
100.00%
10.61%
100.00%
10.61%
5-May-11
9-May-11
0.00%
0.00%
PTJ5100
CONE FIT UP
272
10.61%
4
100.00%
10.61%
100.00%
10.61%
10-May-11
14-May-11
0.00%
0.00%
PTJ5120
LEG SPLICE WELDING & NDT
768
29.95%
12
100.00%
29.95%
100.00%
29.95%
15-May-11
28-May-11
0.00%
0.00%
PTJ5130
CONE WELDING & NDT
320
12.48%
5
100.00%
12.48%
100.00%
12.48%
29-May-11
2-Jun-11
0.00%
0.00%
PTJ5140
CAN WELDING & NDT
320
12.48%
5
100.00%
12.48%
100.00%
12.48%
04-Jun-11
08-Jun-11
0.00%
0.00% -1.48%
1908
19.10%
33
92.24%
17.61%
100.00%
19.10%
15-May-11
16-Jun-11
-7.76%
PTJ5020
LEG SPLICE FIT UP
340
17.82%
5
100.00%
17.82%
100.00%
17.82%
15-May-11
19-May-11
0.00%
0.00%
PTJ5040
CANS FIT UP
272
14.26%
4
75.00%
10.69%
100.00%
14.26%
21-May-11
24-May-11
-25.00%
-3.56%
PTJ5030
CONE FIT UP
272
14.26%
4
100.00%
14.26%
100.00%
14.26%
25-May-11
29-May-11
0.00%
0.00%
DIM 1000
4/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
30-May-11
05-Jun-11
0.00%
0.00%
PTJ5050
LEG SPLICE WELDING & NDT
384
20.13%
6
100.00%
20.13%
100.00%
20.13%
PTJ5060
CONE WELDING & NDT
320
16.77%
5
100.00%
16.77%
100.00%
16.77%
6-Jun-11
11-Jun-11
0.00%
0.00%
PTJ5070
CAN WELDING & NDT
320
16.77%
5
75.00%
12.58%
100.00%
16.77%
12-Jun-11
16-Jun-11
-25.00%
-4.19%
10172
24.09%
78
98.55%
23.74%
100.00%
24.09%
31-Mar-11
16-Jun-11
-1.45%
-0.35%
5556
54.62%
53
100.00%
54.62%
100.00%
54.62%
31-Mar-11
22-May-11
0.00%
0.00%
LEG A2 DIM 1400 PTJ5350
LEG SPLICE FIT UP
1260
22.68%
9
100.00%
22.68%
100.00%
22.68%
31‐Mar‐11
10‐Apr‐11
0.00%
0.00%
PTJ5360
CANS FIT UP
1224
22.03%
9
100.00%
22.03%
100.00%
22.03%
11-Apr-11
21-Apr-11
0.00%
0.00%
PTJ5370
LEG SPLICE WELDING & NDT
1536
27.65%
12
100.00%
27.65%
100.00%
27.65%
23-Apr-11
08-May-11
0.00%
0.00%
PTJ5380
CAN WELDING & NDT
1536
27.65%
12
100.00%
27.65%
100.00%
27.65%
09-May-11
22-May-11
0.00%
0.00%
2772
27.25%
55
100.00%
27.25%
100.00%
27.25%
23‐Apr‐11
16‐Jun‐11
0.00%
0.00%
DIM 1200 PTJ5280
LEG SPLICE FIT UP
612
22.08%
9
100.00%
22.08%
100.00%
22.08%
23-Apr-11
04-May-11
0.00%
0.00%
PTJ5300
CANS FIT UP
272
9.81%
4
100.00%
9.81%
100.00%
9.81%
5-May-11 y
9-May-11 y
0.00%
0.00%
PTJ5290
CONE FIT UP
288
10.39%
8
100.00%
10.39%
100.00%
10.39%
10-May-11
18-May-11
0.00%
0.00%
PTJ5310
LEG SPLICE WELDING & NDT
832
30.01%
13
100.00%
30.01%
100.00%
30.01%
19-May-11
2-Jun-11
0.00%
0.00%
PTJ5320
CONE WELDING & NDT
384
13.85%
6
100.00%
13.85%
100.00%
13.85%
04-Jun-11
09-Jun-11
0.00%
0.00%
PTJ5330
CAN WELDING & NDT
DIM 1000
384
13.85%
6
100.00%
13.85%
100.00%
13.85%
11-Jun-11
16-Jun-11
0.00%
0.00%
1844
18.13%
33
91.97%
16.67%
100.00%
18.13%
10-May-11
11-Jun-11
-8.03%
-1.45%
PTJ5210
LEG SPLICE FIT UP
340
18.44%
5
100.00%
18.44%
100.00%
18.44%
10-May-11
15-May-11
0.00%
0.00%
PTJ5230
CANS FIT UP
272
14.75%
4
75.00%
11.06%
100.00%
14.75%
16-May-11
19-May-11
-25.00%
-3.69%
PTJ5220
CONE FIT UP
272
14.75%
4
100.00%
14.75%
100.00%
14.75%
21-May-11
24-May-11
0.00%
0.00%
PTJ5240
LEG SPLICE WELDING & NDT
384
20.82%
6
100.00%
20.82%
100.00%
20.82%
25-May-11
31-May-11
0.00%
0.00%
PTJ5250
CONE WELDING & NDT
256
13.88%
4
100.00%
13.88%
100.00%
13.88%
1-Jun-11
5-Jun-11
0.00%
0.00%
PTJ5260
CAN WELDING & NDT
320
17.35%
5
75.00%
13.02%
100.00%
17.35%
06‐Jun‐11
11‐Jun‐11
‐25.00%
‐4.34%
10072
23.85%
78
91.68%
21.87%
100.00%
23.85%
31-Mar-11
16-Jun-11
-8.32%
-1.98%
5520
54.81%
53
87.50%
47.95%
100.00%
54.81%
31-Mar-11
22-May-11
-12.50%
-6.85%
1224
22.17%
9
95.00%
21.07%
100.00%
22.17%
31-Mar-11
10-Apr-11
-5.00%
-1.11%
LEG B1 DIM 1400 PTJ5540
LEG SPLICE FIT UP
PTJ5550
CANS FIT UP
1224
22.17%
9
80.00%
17.74%
100.00%
22.17%
11-Apr-11
21-Apr-11
-20.00%
-4.43%
PTJ5560
LEG SPLICE WELDING & NDT
1536
27.83%
12
95.00%
26.43%
100.00%
27.83%
23-Apr-11
8-May-11
-5.00%
-1.39%
PTJ5570
CAN WELDING & NDT
1536
27.83%
12
80.00%
22.26%
100.00%
27.83%
9-May-11
22-May-11
-20.00%
-5.57%
2644
26.25%
50
100.00%
26.25%
100.00%
26.25%
23-Apr-11
11-Jun-11
0.00%
0.00%
DIM 1200 PTJ5470
LEG SPLICE FIT UP
612
23.15%
9
100.00%
23.15%
100.00%
23.15%
23‐Apr‐11
04‐May‐11
0.00%
0.00%
PTJ5490
CANS FIT UP
272
10.29%
4
100.00%
10.29%
100.00%
10.29%
05-May-11
09-May-11
0.00%
0.00%
5/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
PTJ5480
CONE FIT UP
272
10.29%
4
100.00%
10.29%
100.00%
10.29%
10-May-11
14-May-11
0.00%
0.00%
PTJ5500
LEG SPLICE WELDING & NDT
768
29.05%
12
100.00%
29.05%
100.00%
29.05%
15-May-11
28-May-11
0.00%
0.00%
PTJ5510
CONE WELDING & NDT
384
14.52%
6
100.00%
14.52%
100.00%
14.52%
29‐May‐11
04‐Jun‐11
0.00%
0.00%
PTJ5520
CAN WELDING & NDT
336
12.71%
6
100.00%
12.71%
100.00%
12.71%
05-Jun-11
11-Jun-11
0.00%
0.00%
1908
18.94%
33
92.24%
17.47%
100.00%
18.94%
15-May-11
16-Jun-11
-7.76%
-1.47%
PTJ5400
LEG SPLICE FIT UP
340
17.82%
5
100.00%
17.82%
100.00%
17.82%
15-May-11
19-May-11
0.00%
0.00%
PTJ5420
CANS FIT UP
272
14.26%
4
75.00%
10.69%
100.00%
14.26%
21-May-11
24-May-11
-25.00%
-3.56%
PTJ5410
CONE FIT UP
272
14.26%
4
100.00%
14.26%
100.00%
14.26%
25-May-11
29-May-11
0.00%
0.00%
PTJ5430
LEG SPLICE WELDING & NDT
384
20.13%
6
100.00%
20.13%
100.00%
20.13%
30-May-11
5-Jun-11
0.00%
0.00%
PTJ5440
CONE WELDING & NDT
320
16.77%
5
100.00%
16.77%
100.00%
16.77%
6-Jun-11
11-Jun-11
0.00%
0.00%
PTJ5450
CAN WELDING & NDT
320
16.77%
5
75.00%
12.58%
100.00%
16.77%
12-Jun-11
16-Jun-11
-25.00%
-4.19%
9848
23.32%
76
98.50%
22.97%
100.00%
23.32%
31-Mar-11
14-Jun-11
-1.50%
-0.35%
DIM 1000
LEG B2
5248
53 29% 53.29%
50
100 00% 100.00%
53 29% 53.29%
100 00% 100.00%
53 29% 53.29%
31 M 11 31-Mar-11
19 M 11 19-May-11
0.00%
0.00%
PTJ5730
LEG SPLICE FIT UP
1088
20.73%
8
100.00%
20.73%
100.00%
20.73%
31-Mar-11
9-Apr-11
0.00%
0.00%
PTJ5740
CANS FIT UP
1088
20.73%
8
100.00%
20.73%
100.00%
20.73%
10-Apr-11
19-Apr-11
0.00%
0.00%
PTJ5750
LEG SPLICE WELDING & NDT
1536
29.27%
12
100.00%
29.27%
100.00%
29.27%
20‐Apr‐11
05‐May‐11
0.00%
0.00%
PTJ5760
CAN WELDING & NDT
1536
29.27%
12
100.00%
29.27%
100.00%
29.27%
07-May-11
19-May-11
0.00%
0.00%
DIM 1400
2692
27.34%
50
100.00%
27.34%
100.00%
27.34%
20-Apr-11
8-Jun-11
0.00%
0.00%
PTJ5660
LEG SPLICE FIT UP
612
22.73%
9
100.00%
22.73%
100.00%
22.73%
20-Apr-11
2-May-11
0.00%
0.00%
PTJ5680
CANS FIT UP
272
10.10%
4
100.00%
10.10%
100.00%
10.10%
03-May-11
07-May-11
0.00%
0.00%
PTJ5670
CONE FIT UP
272
10.10%
4
100.00%
10.10%
100.00%
10.10%
8-May-11
11-May-11
0.00%
0.00%
PTJ5690
LEG SPLICE WELDING & NDT
768
28.53%
12
100.00%
28.53%
100.00%
28.53%
12-May-11
25-May-11
0.00%
0.00%
PTJ5700
CONE WELDING & NDT
384
14.26%
6
100.00%
14.26%
100.00%
14.26%
26‐May‐11
1‐Jun‐11
0.00%
0.00%
PTJ5710
CAN WELDING & NDT
DIM 1200
DIM 1000
384
14.26%
6
100.00%
14.26%
100.00%
14.26%
2‐Jun‐11
8‐Jun‐11
0.00%
0.00%
1908
19.37%
34
92.24%
17.87%
100.00%
19.37%
12-May-11
14-Jun-11
-7.76%
-1.50%
340
17.82%
5
100.00%
17.82%
100.00%
17.82%
12‐May‐11
17‐May‐11
0.00%
0.00%
PTJ5590
LEG SPLICE FIT UP
PTJ5610
CANS FIT UP
272
14.26%
4
75.00%
10.69%
100.00%
14.26%
18‐May‐11
22‐May‐11
‐25.00%
‐3.56%
PTJ5600
CONE FIT UP
272
14.26%
4
100.00%
14.26%
100.00%
14.26%
23‐May‐11
26‐May‐11
0.00%
0.00%
PTJ5620
LEG SPLICE WELDING & NDT
384
20.13%
6
100.00%
20.13%
100.00%
20.13%
28‐May‐11
2‐Jun‐11
0.00%
0.00%
PTJ5630
CONE WELDING & NDT
320
16.77%
5
100.00%
16.77%
100.00%
16.77%
4‐Jun‐11
8‐Jun‐11
0.00%
0.00%
PTJ5640
CAN WELDING & NDT
320
16.77%
5
75.00%
12.58%
100.00%
16.77%
9‐Jun‐11
14‐Jun‐11
‐25.00%
‐4.19%
35012
26.19%
189
86.21%
22.58%
33.60%
8.80%
31-Mar-11
05-Oct-11
52.61%
13.78%
8996
25.69%
59
88.67%
22.78%
0.00%
0.00%
8‐Aug‐11
5‐Oct‐11
88.67%
22.78%
JACKET BRACING FABRICATION BRACING ROW 1
6/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
SPLICING HORIZONTAL
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
8996
100.00%
59
88.67%
88.67%
0.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
8‐Aug‐11
5‐Oct‐11
88.67%
88.67%
3304
36.73%
53
100.00%
36.73%
0.00%
0.00%
8‐Aug‐11
29‐Sep‐11
100.00%
36.73%
PTJ3180
FITUP HORIZONTAL BRACES ATELEV ‐56.2
324
9.81%
9
100.00%
9.81%
0.00%
0.00%
8‐Aug‐11
17‐Aug‐11
100.00%
9.81%
PTJ3170
FITUP HORIZONTAL BRACES AT ELEV ‐33.4
324
9.81%
9
100.00%
9.81%
0.00%
0.00%
18‐Aug‐11
28‐Aug‐11
100.00%
9.81%
PTJ3200
FITUP HORIZONTAL BRACES AT ELEV ‐79.0
324
9.81%
9
100.00%
9.81%
0.00%
0.00%
18‐Aug‐11
28‐Aug‐11
100.00%
9.81%
PTJ3270
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐56.2
384
11.62%
12
100.00%
11.62%
0.00%
0.00%
18‐Aug‐11
4‐Sep‐11
100.00%
11.62%
PTJ3160
FITUP HORIZONTAL BRACES AT ELEV ‐10.6
288
8.72%
8
100.00%
8.72%
0.00%
0.00%
29‐Aug‐11
10‐Sep‐11
100.00%
8.72%
PTJ3260
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐33.4
384
11.62%
12
100.00%
11.62%
0.00%
0.00%
29‐Aug‐11
14‐Sep‐11
100.00%
11.62%
PTJ3290
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐79.0
384
11.62%
12
100.00%
11.62%
0.00%
0.00%
29‐Aug‐11
14‐Sep‐11
100.00%
11.62%
PTJ3190
FITUP HORIZONTAL BRACES AT ELEV +6.4
252
7.63%
7
100.00%
7.63%
0.00%
0.00%
11‐Sep‐11
18‐Sep‐11
100.00%
7.63%
PTJ3250
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐10.6
320
9.69%
10
100.00%
9.69%
0.00%
0.00%
11‐Sep‐11
21‐Sep‐11
100.00%
9.69%
10
100.00%
9.69%
0.00%
0.00%
19‐Sep‐11
29‐Sep‐11
100.00%
9.69% 51.95%
PTJ3280
WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4
DIAGONAL BRACES
320
9.69%
5692
63.27%
49
82.10%
51.95%
0.00%
0.00%
18‐Aug‐11
5‐Oct‐11
82.10%
PTJ3140
FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
720
12.65%
20
100.00%
12.65%
0.00%
0.00%
18‐Aug‐11
13‐Sep‐11
100.00%
12.65%
PTJ3150
FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
792
13.91%
22
75.00%
10.44%
0.00%
0.00%
18‐Aug‐11
15‐Sep‐11
75.00%
10.44%
PTJ3130
FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
576
10.12%
16
75.00%
7.59%
0.00%
0.00%
29‐Aug‐11
19‐Sep‐11
75.00%
7.59%
PTJ3120
FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
468
8.22%
13
75.00%
6.17%
0.00%
0.00%
11‐Sep‐11
25‐Sep‐11
75.00%
6.17%
PTJ3230
WELDING & NDT DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
896
15.74%
14
100.00%
15.74%
0.00%
0.00%
14‐Sep‐11
29‐Sep‐11
100.00%
15.74%
PTJ3240
WELDING & NDT DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
960
16.87%
15
75.00%
12.65%
0.00%
0.00%
17‐Sep‐11
3‐Oct‐11
75.00%
12.65%
PTJ3220
WELDING & NDT DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
704
12.37%
11
75.00%
9.28%
0.00%
0.00%
20‐Sep‐11
2‐Oct‐11
75.00%
9.28%
PTJ3210
WELDING & NDT DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
BRACING ROW 2 SPLICING HORIZONTAL
576
10.12%
9
75.00%
7.59%
0.00%
0.00%
26‐Sep‐11
5‐Oct‐11
75.00%
7.59%
9964
28.46%
91
94.38%
26.86%
98.83%
28.13%
31‐Mar‐11
29‐Jun‐11
‐4.45%
‐1.27%
9964
100.00%
91
94.38%
94.38%
98.83%
98.83%
31‐Mar‐11
29‐Jun‐11
‐4.45%
‐4.45%
2428
24.37%
20
100.00%
24.37%
100.00%
24.37%
31‐Mar‐11
19‐Apr‐11
0.00%
0.00%
PTJ3340
FITUP HORIZONTAL BRACES AT ELEV ‐10.6
180
7.41%
5
100.00%
7.41%
100.00%
7.41%
31‐Mar‐11
5‐Apr‐11
0.00%
0.00%
PTJ3350
FITUP HORIZONTAL BRACES AT ELEV ‐33.4
252
10.38%
7
100.00%
10.38%
100.00%
10.38%
31‐Mar‐11
7‐Apr‐11
0.00%
0.00%
PTJ3360
FITUP HORIZONTAL BRACES AT ELEV ‐56.2
252
10.38%
7
100.00%
10.38%
100.00%
10.38%
31‐Mar‐11
7‐Apr‐11
0.00%
0.00%
PTJ3370
FITUP HORIZONTAL BRACES AT ELEV +6.4
180
7.41%
5
100.00%
7.41%
100.00%
7.41%
31‐Mar‐11
5‐Apr‐11
0.00%
0.00%
PTJ3380
FITUP HORIZONTAL BRACES AT ELEV ‐79.0
252
10.38%
7
100.00%
10.38%
100.00%
10.38%
31‐Mar‐11
7‐Apr‐11
0.00%
0.00%
PTJ3430
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐10.6
224
9.23%
7
100.00%
9.23%
100.00%
9.23%
6‐Apr‐11
13‐Apr‐11
0.00%
0.00%
PTJ3470
WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4
224
9.23%
7
100.00%
9.23%
100.00%
9.23%
6‐Apr‐11
13‐Apr‐11
0.00%
0.00%
PTJ3440
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐33.4
288
11.86%
9
100.00%
11.86%
100.00%
11.86%
9‐Apr‐11
19‐Apr‐11
0.00%
0.00%
PTJ3450
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐56.2
288
11.86%
9
100.00%
11.86%
100.00%
11.86%
9‐Apr‐11
19‐Apr‐11
0.00%
0.00%
PTJ3460
WELDING & NDT HORIZONTAL BRACES AT ELEV ‐79.0
288
11.86%
9
100.00%
11.86%
100.00%
11.86%
9‐Apr‐11
19‐Apr‐11
0.00%
0.00%
5988
60.10%
65
100.00%
60.10%
100.00%
60.10%
6‐Apr‐11
9‐Jun‐11
0.00%
0.00%
DIAGONAL BRACES
7/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
8
100.00%
9.08%
100.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
9.08%
6‐Apr‐11
14‐Apr‐11
0.00%
0.00%
PTJ3300
FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
544
9.08%
PTJ3310
FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
612
10.22%
9
100.00%
10.22%
100.00%
10.22%
9‐Apr‐11
19‐Apr‐11
0.00%
0.00%
PTJ3320
FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
816
13.63%
12
100.00%
13.63%
100.00%
13.63%
9‐Apr‐11
23‐Apr‐11
0.00%
0.00%
PTJ3330
FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
816
13.63%
12
100.00%
13.63%
100.00%
13.63%
9‐Apr‐11
23‐Apr‐11
0.00%
0.00%
PTJ3390
WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
512
8.55%
8
100.00%
8.55%
100.00%
8.55%
16‐Apr‐11
26‐Apr‐11
0.00%
0.00%
PTJ3400
WELDING DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
768
12.83%
12
100.00%
12.83%
100.00%
12.83%
20‐Apr‐11
5‐May‐11
0.00%
0.00%
PTJ3410
WELDING DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
896
14.96%
14
100.00%
14.96%
100.00%
14.96%
7‐May‐11
22‐May‐11
0.00%
0.00%
PTJ3420
WELDING DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
1024
17.10%
16
100.00%
17.10%
100.00%
17.10%
23‐May‐11
9‐Jun‐11
0.00%
0.00%
1548
15.54%
54
63.84%
9.92%
92.48%
14.37%
7‐May‐11
29‐Jun‐11
‐28.65%
‐4.45%
VERTICAL PTJ3970
FITUP VERTICAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
180
11.63%
5
75.00%
8.72%
100.00%
11.63%
7‐May‐11
11‐May‐11
‐25.00%
‐2.91%
PTJ8040
WELDING VERTICAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
224
14.47%
7
55.00%
7.96%
100.00%
14.47%
12‐May‐11
19‐May‐11
‐45.00%
‐6.51%
16.28%
7
75.00%
12.21%
100.00%
16.28%
23‐May‐11
30‐May‐11
‐25.00%
‐4.07% ‐9.30%
PTJ3980
FITUP VERTICAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
PTJ8050
WELDING VERTICAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
320
20.67%
10
55.00%
11.37%
100.00%
20.67%
31‐May‐11
11‐Jun‐11
‐45.00%
PTJ3990
FITUP VERTICAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
252
16.28%
7
75.00%
12.21%
100.00%
16.28%
11‐Jun‐11
18‐Jun‐11
‐25.00%
‐4.07%
PTJ8060
WELDING VERTICAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
‐1.79%
BRACING ROW 3
252
320
20.67%
10
55.00%
11.37%
63.64%
13.15%
19‐Jun‐11
29‐Jun‐11
‐8.64%
1716
4.90%
19
75.00%
3.68%
100.00%
4.90%
21‐May‐11
8‐Jun‐11
‐25.00%
‐1.23%
PTJ8120
FITUP BRACES BETWEEN ELEV ‐10.6 & ‐33.4
252
14.69%
7
75.00%
11.01%
100.00%
14.69%
21‐May‐11
28‐May‐11
‐25.00%
‐3.67%
PTJ8130
FITUP BRACES BETWEEN ELEV ‐33.4 & ‐56.2
252
14.69%
7
75.00%
11.01%
100.00%
14.69%
21‐May‐11
28‐May‐11
‐25.00%
‐3.67%
PTJ8140
FITUP BRACES BETWEEN ELEV ‐56.2 & ‐79.0
252
14.69%
7
75.00%
11.01%
100.00%
14.69%
21‐May‐11
28‐May‐11
‐25.00%
‐3.67%
PTJ8150
WELDING VERTICAL BRACES BETWEEN ELEV +10.6 & ‐33.4
320
18.65%
10
75.00%
13.99%
100.00%
18.65%
29‐May‐11
8‐Jun‐11
‐25.00%
‐4.66%
PTJ8160
WELDING VERTICAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
320
18.65%
10
75.00%
13.99%
100.00%
18.65%
29‐May‐11
8‐Jun‐11
‐25.00%
‐4.66%
PTJ8170
WELDING VERTICAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
320
18.65%
10
75.00%
13.99%
100.00%
18.65%
29‐May‐11
8‐Jun‐11
‐25.00%
‐4.66%
BRACING ROW A
5516
15.75%
59
76.52%
12.05%
0.00%
0.00%
27‐Jun‐11
24‐Aug‐11
76.52%
12.05%
FABRICATION
5516
100.00%
59
76.52%
76.52%
0.00%
0.00%
27‐Jun‐11
24‐Aug‐11
76.52%
76.52%
PTJ8210
FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
408
7.40%
6
95.00%
7.03%
0.00%
0.00%
27‐Jun‐11
3‐Jul‐11
95.00%
7.03%
PTJ8220
FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
544
9.86%
8
95.00%
9.37%
0.00%
0.00%
4‐Jul‐11
12‐Jul‐11
95.00%
9.37%
PTJ8250
WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
576
10.44%
9
85.00%
8.88%
0.00%
0.00%
4‐Jul‐11
13‐Jul‐11
85.00%
8.88%
PTJ8230
FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
680
12.33%
10
85.00%
10.48%
0.00%
0.00%
13‐Jul‐11
25‐Jul‐11
85.00%
10.48%
PTJ8260
WELDING DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
704
12.76%
11
85.00%
10.85%
0.00%
0.00%
13‐Jul‐11
26‐Jul‐11
85.00%
10.85%
PTJ8240
FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
748
13.56%
11
85.00%
11.53%
0.00%
0.00%
26‐Jul‐11
7‐Aug‐11
85.00%
11.53%
PTJ8270
WELDING DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
896
16.24%
14
65.00%
10.56%
0.00%
0.00%
26‐Jul‐11
10‐Aug‐11
65.00%
10.56%
PTJ8280
WELDING DIAGONAL BRACES BETWEEN ELEV ‐ 56.2 & ‐79.0
960
17.40%
15
45.00%
7.83%
0.00%
0.00%
8‐Aug‐11
24‐Aug‐11
45.00%
7.83%
BRACING ROW B
5516
15.75%
59
83.94%
13.22%
0.00%
0.00%
27‐Jun‐11
24‐Aug‐11
83.94%
13.22%
FABRICATION
5516
100.00%
59
83.94%
83.94%
0.00%
0.00%
27‐Jun‐11
24‐Aug‐11
83.94%
83.94%
408
7.40%
6
100.00%
7.40%
0.00%
0.00%
27‐Jun‐11
3‐Jul‐11
100.00%
7.40%
PTJ8330
FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
8/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
8
100.00%
9.86%
0.00%
0.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
4‐Jul‐11
12‐Jul‐11
100.00%
9.86%
PTJ8340
FITUP DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
544
9.86%
PTJ8370
WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & ‐10.6
576
10.44%
9
100.00%
10.44%
0.00%
0.00%
4‐Jul‐11
13‐Jul‐11
100.00%
10.44%
PTJ8350
FITUP DIAGONAL BRACES BETWEEN ELEV ‐33.4 & ‐56.2
680
12.33%
10
100.00%
12.33%
0.00%
0.00%
13‐Jul‐11
25‐Jul‐11
100.00%
12.33%
PTJ8380
WELDING DIAGONAL BRACES BETWEEN ELEV ‐10.6 & ‐33.4
704
12.76%
11
100.00%
12.76%
0.00%
0.00%
13‐Jul‐11
26‐Jul‐11
100.00%
12.76%
PTJ8360
FITUP DIAGONAL BRACES BETWEEN ELEV ‐56.2 & ‐79.0
748
13.56%
11
65.00%
8.81%
0.00%
0.00%
26‐Jul‐11
7‐Aug‐11
65.00%
8.81%
PTJ8390
WELDING DIAGONAL BRACES BETWEEN ELEV ‐ 33.4 & ‐56.2
896
16.24%
14
100.00%
16.24%
0.00%
0.00%
26‐Jul‐11
10‐Aug‐11
100.00%
16.24%
PTJ8400
WELDING DIAGONAL BRACES BETWEEN ELEV ‐ 56.2 & ‐79.0
960
17.40%
15
35.00%
6.09%
0.00%
0.00%
8‐Aug‐11
24‐Aug‐11
35.00%
6.09%
1856
5.30%
26
85.00%
4.51%
5.16%
0.27%
25‐Jun‐11
20‐Jul‐11
79.84%
4.23%
PTJ8450
FITUP BRACES BETWEEN ELEV ‐10.6 & ‐33.4
252
13.58%
7
85.00%
11.54%
12.50%
1.70%
25‐Jun‐11
2‐Jul‐11
72.50%
9.84%
PTJ8460
FITUP BRACES BETWEEN ELEV ‐33.4 & ‐56.2
360
19.40%
10
85.00%
16.49%
9.09%
1.76%
25‐Jun‐11
5‐Jul‐11
75.91%
14.72%
PTJ8470
FITUP BRACES BETWEEN ELEV ‐56.2 & ‐79.0
252
13.58%
7
85.00%
11.54%
12.50%
1.70%
25‐Jun‐11
2‐Jul‐11
72.50%
9.84%
13.19%
0.00%
0.00%
3‐Jul‐11
12‐Jul‐11
85.00%
13.19%
BRACING ROW C
PTJ8480
WELDING BRACES BETWEEN ELEV ‐10.6 & ‐33.4
288
15.52%
9
85.00%
PTJ8490
WELDING BRACES BETWEEN ELEV ‐56.2 & ‐79.0
288
15.52%
9
85.00%
13.19%
0.00%
0.00%
3‐Jul‐11
12‐Jul‐11
85.00%
13.19%
PTJ8500
WELDING BRACES BETWEEN ELEV ‐33.4 & ‐56.2
416
22.41%
13
85.00%
19.05%
0.00%
0.00%
6‐Jul‐11
20‐Jul‐11
85.00%
19.05%
1448
4.14%
22
75.00%
3.10%
7.18%
0.30%
25‐Jun‐11
16‐Jul‐11
67.82%
2.80%
BRACING ROW D PTJ8540
FITUP BRACES BETWEEN ELEV ‐10.6 & ‐33.4
180
12.43%
5
75.00%
9.32%
20.00%
2.49%
25‐Jun‐11
29‐Jun‐11
55.00%
6.84%
PTJ8550
FITUP BRACES BETWEEN ELEV ‐33.4 & ‐56.2
288
19.89%
8
75.00%
14.92%
11.11%
2.21%
25‐Jun‐11
3‐Jul‐11
63.89%
12.71%
PTJ8560
FITUP BRACES BETWEEN ELEV ‐56.2 & ‐79.0
180
12.43%
5
75.00%
9.32%
20.00%
2.49%
25‐Jun‐11
29‐Jun‐11
55.00%
6.84%
PTJ8570
WELDING BRACES BETWEEN ELEV ‐10.6 & ‐33.4
224
15.47%
7
75.00%
11.60%
0.00%
0.00%
30‐Jun‐11
7‐Jul‐11
75.00%
11.60%
PTJ8580
WELDING BRACES BETWEEN ELEV ‐56.2 & ‐79.0
224
15.47%
7
75.00%
11.60%
0.00%
0.00%
30‐Jun‐11
7‐Jul‐11
75.00%
11.60%
PTJ8590
WELDING BRACES BETWEEN ELEV ‐33.4 & ‐56.2
352
24.31%
11
75.00%
18.23%
0.00%
0.00%
4‐Jul‐11
16‐Jul‐11
75.00%
18.23%
31088
23.26%
227
74.72%
17.38%
61.66%
14.34%
31-Mar-11
12-Nov-11
13.05%
3.04%
4280
13.77%
91
100.00%
13.77%
90.51%
12.46%
4‐Apr‐11
3‐Jul‐11
9.49%
1.31%
JACKET ELEVATIONS FABRICATION ELEV + 6400 FITUP
1260
29.44%
34
100.00%
29.44%
100.00%
29.44%
4‐Apr‐11
7‐May‐11
0.00%
0.00%
PTJ8630
FITUP OF SIZE 24"
720
57.14%
20
100.00%
57.14%
100.00%
57.14%
4‐Apr‐11
28‐Apr‐11
0.00%
0.00%
PTJ8640
FITUP OF SIZE 16"
324
25.71%
9
100.00%
25.71%
100.00%
25.71%
23‐Apr‐11
4‐May‐11
0.00%
0.00%
PTJ8650
FITUP OF SIZE 20"
WELDING&NDT
216
17.14%
6
100.00%
17.14%
100.00%
17.14%
30‐Apr‐11
7‐May‐11
0.00%
0.00%
1344
31.40%
23
100.00%
31.40%
100.00%
31.40%
8‐May‐11
30‐May‐11
0.00%
0.00% 0.00%
PTJ8660
WELDING OF SIZE 24"
768
57.14%
12
100.00%
57.14%
100.00%
57.14%
8‐May‐11
21‐May‐11
0.00%
PTJ8670
WELDING OF SIZE 16"
320
23.81%
5
100.00%
23.81%
100.00%
23.81%
22‐May‐11
26‐May‐11
0.00%
0.00%
PTJ8680
WELDING OF SIZE 20"
256
19.05%
4
100.00%
19.05%
100.00%
19.05%
26‐May‐11
30‐May‐11
0.00%
0.00%
CONDUCTORS AT ELEV + 6400 FITUP
1676
39.16%
44
100.00%
39.16%
75.77%
29.67%
21‐May‐11
3‐Jul‐11
24.23%
9.49%
504
30.07%
24
100.00%
30.07%
100.00%
30.07%
21‐May‐11
13‐Jun‐11
0.00%
0.00%
PTJ9100
FITUP OF CONDUCTOR
324
64.29%
9
100.00%
64.29%
100.00%
64.29%
21‐May‐11
30‐May‐11
0.00%
0.00%
PTJ9110
FITUP OF CONDUCTOR SUPPORT
180
35.71%
5
100.00%
35.71%
100.00%
35.71%
8‐Jun‐11
13‐Jun‐11
0.00%
0.00%
9/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
WELDING & NDT
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
512
30.55%
21
100.00%
30.55%
100.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
30.55%
31‐May‐11
20‐Jun‐11
0.00%
0.00% 0.00%
PTJ9120
WELDING OF CONDUCTOR
320
62.50%
10
100.00%
62.50%
100.00%
62.50%
31‐May‐11
11‐Jun‐11
0.00%
PTJ9130
WELDING OF CONDUCTOR SUPPORT
192
37.50%
6
100.00%
37.50%
100.00%
37.50%
14‐Jun‐11
20‐Jun‐11
0.00%
0.00%
61.54%
24.23%
CONDUCTORS ERECTION PTJ9140
ERECTION OF CONDUCTOR WITH ELEVATIONS
ELEV ‐ 10600
660
39.38%
13
100.00%
39.38%
38.46%
15.15%
21‐Jun‐11
3‐Jul‐11
660
100.00%
11
100.00%
100.00%
38.46%
38.46%
21‐Jun‐11
3‐Jul‐11
61.54%
61.54%
6716
21.60%
148
30.82%
6.66%
62.51%
13.50%
31-Mar-11
25-Aug-11
-31.69%
-6.85%
2448
36.45%
48
35.00%
12.76%
100.00%
36.45%
31-Mar-11
17-May-11
-65.00%
-23.69%
PTJ8700
FITUP OF SIZE 28"
1044
42.65%
29
35.00%
14.93%
100.00%
42.65%
31‐Mar‐11
7‐May‐11
‐65.00%
‐27.72%
PTJ8710
FITUP OF SIZE 20"
936
38.24%
26
35.00%
13.38%
100.00%
38.24%
12‐Apr‐11
15‐May‐11
‐65.00%
‐24.85%
PTJ8720
FITUP OF SIZE 16"
288
11.76%
8
35.00%
4.12%
100.00%
11.76%
2‐May‐11
10‐May‐11
‐65.00%
‐7.65%
PTJ8730
FITUP OF SIZE 14"
180
7.35%
5
35.00%
2.57%
100.00%
7.35%
12‐May‐11
17‐May‐11
‐65.00%
‐4.78%
5.79%
67.52%
26.06%
18‐May‐11
12‐Jul‐11
‐52.52%
‐20.27%
FITUP
2592
38.59%
56
15.00%
PTJ8740
WELDING OF SIZE 28"
1120
43.21%
35
15.00%
6.48%
95.12%
41.10%
18‐May‐11
27‐Jun‐11
‐80.12%
‐34.62%
PTJ8750
WELDING OF SIZE 20"
992
38.27%
31
15.00%
5.74%
61.11%
23.39%
4‐Jun‐11
9‐Jul‐11
‐46.11%
‐17.65%
PTJ8760
WELDING OF SIZE 16"
288
11.11%
9
15.00%
1.67%
27.27%
3.03%
23‐Jun‐11
3‐Jul‐11
‐12.27%
‐1.36%
PTJ8770
WELDING OF SIZE 14"
WELDING&NDT
CONDUCTORS AT ELEV ‐ 10600 FITUP
192
7.41%
6
15.00%
1.11%
0.00%
0.00%
6‐Jul‐11
12‐Jul‐11
15.00%
1.11%
1676
24.96%
54
49.16%
12.27%
0.00%
0.00%
3‐Jul‐11
25‐Aug‐11
49.16%
12.27%
504
30.07%
35
100.00%
30.07%
0.00%
0.00%
3‐Jul‐11
6‐Aug‐11
100.00%
30.07%
PTJ9150
FITUP OF CONDUCTOR
324
64.29%
9
100.00%
64.29%
0.00%
0.00%
3‐Jul‐11
12‐Jul‐11
100.00%
64.29%
PTJ9160
FITUP OF CONDUCTOR SUPPORT
180
35.71%
5
100.00%
35.71%
0.00%
0.00%
1‐Aug‐11
6‐Aug‐11
100.00%
35.71%
WELDING & NDT
512
30.55%
32
62.50%
19.09%
0.00%
0.00%
13‐Jul‐11
13‐Aug‐11
62.50%
19.09%
PTJ9170
WELDING OF CONDUCTOR
320
62.50%
10
100.00%
62.50%
0.00%
0.00%
13‐Jul‐11
25‐Jul‐11
100.00%
62.50%
PTJ9180
WELDING OF CONDUCTOR SUPPORT
192
37.50%
6
0.00%
0.00%
0.00%
0.00%
7‐Aug‐11
13‐Aug‐11
0.00%
0.00% 0.00%
CONDUCTORS ERECTION PTJ9190
ERECTION OF CONDUCTOR WITH ELEVATIONS
ELEV ‐ 33400 FITUP
660
39.38%
12
0.00%
0.00%
0.00%
0.00%
14‐Aug‐11
25‐Aug‐11
0.00%
660
100.00%
11
0.00%
0.00%
0.00%
0.00%
14‐Aug‐11
25‐Aug‐11
0.00%
0.00%
7092
22.81%
120
66.64%
15.20%
85.07%
19.41%
31-Mar-11
28-Jul-11
-18.43%
-4.20%
2664
37.56%
36
100.00%
37.56%
100.00%
37.56%
31-Mar-11
5-May-11
0.00%
0.00%
PTJ8790
FITUP OF SIZE 28"
1008
37.84%
14
100.00%
37.84%
100.00%
37.84%
31‐Mar‐11
16‐Apr‐11
0.00%
0.00%
PTJ8810
FITUP OF SIZE 16"
396
14.86%
11
100.00%
14.86%
100.00%
14.86%
9‐Apr‐11
21‐Apr‐11
0.00%
0.00%
PTJ8800
FITUP OF SIZE 24"
720
27.03%
10
100.00%
27.03%
100.00%
27.03%
17‐Apr‐11
30‐Apr‐11
0.00%
0.00%
PTJ8820
FITUP OF SIZE 20"
288
10.81%
8
100.00%
10.81%
100.00%
10.81%
23‐Apr‐11
3‐May‐11
0.00%
0.00%
PTJ8830
FITUP OF SIZE 18"
WELDING&NDT
252
9.46%
7
100.00%
9.46%
100.00%
9.46%
27‐Apr‐11
5‐May‐11
0.00%
0.00%
2752
38.80%
39
45.00%
17.46%
100.00%
38.80%
7-May-11
14-Jun-11
-55.00%
-21.34%
PTJ8840
WELDING OF SIZE 28"
1024
37.21%
16
45.00%
16.74%
100.00%
37.21%
7‐May‐11
24‐May‐11
‐55.00%
‐20.47%
PTJ8860
WELDING OF SIZE 16"
384
13.95%
6
45.00%
6.28%
100.00%
13.95%
24‐May‐11
30‐May‐11
‐55.00%
‐7.67%
10/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
27.91%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
26‐May‐11
8‐Jun‐11
‐55.00%
‐15.35%
PTJ8850
WELDING OF SIZE 24"
768
27.91%
12
45.00%
12.56%
PTJ8870
WELDING OF SIZE 20"
320
11.63%
5
45.00%
5.23%
100.00%
11.63%
7‐Jun‐11
12‐Jun‐11
‐55.00%
‐6.40%
PTJ8880
WELDING OF SIZE 18"
256
9.30%
4
45.00%
4.19%
100.00%
9.30%
11‐Jun‐11
14‐Jun‐11
‐55.00%
‐5.12%
1676
23.63%
54
49.16%
11.62%
36.83%
8.70%
5-Jun-11
28-Jul-11
12.33%
2.91%
504
30.07%
33
100.00%
30.07%
64.29%
19.33%
5‐Jun‐11
7‐Jul‐11
35.71%
10.74%
9
100.00%
64.29%
100.00%
64.29%
5‐Jun‐11
14‐Jun‐11
0.00%
0.00%
CONDUCTORS AT ELEV ‐ 33400 FITUP PTJ9200
FITUP OF CONDUCTOR
324
64.29%
PTJ9210
FITUP OF CONDUCTOR SUPPORT
180
35.71%
5
100.00%
35.71%
0.00%
0.00%
3‐Jul‐11
7‐Jul‐11
100.00%
35.71%
512
30.55%
30
62.50%
19.09%
57.29%
17.50%
15‐Jun‐11
14‐Jul‐11
5.21%
1.59%
PTJ9220
WELDING OF CONDUCTOR
320
62.50%
10
100.00%
62.50%
91.67%
57.29%
15‐Jun‐11
26‐Jun‐11
8.33%
5.21%
PTJ9230
WELDING OF CONDUCTOR SUPPORT
192
37.50%
6
0.00%
0.00%
0.00%
0.00%
9‐Jul‐11
14‐Jul‐11
0.00%
0.00%
660
39.38%
13
0.00%
0.00%
0.00%
0.00%
16‐Jul‐11
28‐Jul‐11
0.00%
0.00%
100.00%
11
0.00%
0.00%
0.00%
0.00%
16‐Jul‐11
28‐Jul‐11
0.00%
0.00%
7520
24.19%
140
94.34%
22.82%
67.34%
16.29%
31-Mar-11
17-Aug-11
27.00%
6.53%
2772
36.86%
54
100.00%
36.86%
100.00%
36.86%
31-Mar-11
23-May-11
0.00%
0.00% 0.00%
WELDING & NDT
CONDUCTORS ERECTION PTJ9240
ERECTION OF CONDUCTOR WITH ELEVATIONS
ELEV ‐ 56200 FITUP
660
PTJ8900
FITUP OF SIZE 28"
1044
37.66%
29
100.00%
37.66%
100.00%
37.66%
31‐Mar‐11
7‐May‐11
0.00%
PTJ8910
FITUP OF SIZE 24"
684
24.68%
19
100.00%
24.68%
100.00%
24.68%
26‐Apr‐11
18‐May‐11
0.00%
0.00%
PTJ8920
FITUP OF SIZE 16"
396
14.29%
11
100.00%
14.29%
100.00%
14.29%
28‐Apr‐11
11‐May‐11
0.00%
0.00%
PTJ8930
FITUP OF SIZE 20"
396
14.29%
11
100.00%
14.29%
100.00%
14.29%
9‐May‐11
21‐May‐11
0.00%
0.00%
PTJ8940
FITUP OF SIZE 18"
252
9.09%
7
100.00%
9.09%
100.00%
9.09%
16‐May‐11
23‐May‐11
0.00%
0.00%
3072
40.85%
42
100.00%
40.85%
73.55%
30.05%
24-May-11
4-Jul-11
26.45%
10.81%
WELDING&NDT PTJ8950
WELDING OF SIZE 28"
1152
37.50%
18
100.00%
37.50%
100.00%
37.50%
24‐May‐11
13‐Jun‐11
0.00%
0.00%
PTJ8970
WELDING OF SIZE 16"
448
14.58%
7
100.00%
14.58%
100.00%
14.58%
12‐Jun‐11
19‐Jun‐11
0.00%
0.00%
PTJ8960
WELDING OF SIZE 24"
768
25.00%
12
100.00%
25.00%
78.57%
19.64%
15‐Jun‐11
28‐Jun‐11
21.43%
5.36%
PTJ8980
WELDING OF SIZE 20"
448
14.58%
7
100.00%
14.58%
12.50%
1.82%
25‐Jun‐11
2‐Jul‐11
87.50%
12.76%
PTJ8990
WELDING OF SIZE 18"
256
8.33%
4
100.00%
8.33%
0.00%
0.00%
30‐Jun‐11
4‐Jul‐11
100.00%
8.33%
1676
22.29%
54
74.58%
16.62%
1.93%
0.43%
25-Jun-11
17-Aug-11
72.65%
16.19%
504
30.07%
34
100.00%
30.07%
6.43%
1.93%
25‐Jun‐11
CONDUCTORS AT ELEV ‐ 56200 FITUP
28‐Jul‐11
93.57%
28.14%
PTJ9250
FITUP OF CONDUCTOR
324
64.29%
9
100.00%
64.29%
10.00%
6.43%
25‐Jun‐11
4‐Jul‐11
90.00%
57.86%
PTJ9260
FITUP OF CONDUCTOR SUPPORT
180
35.71%
5
100.00%
35.71%
0.00%
0.00%
24‐Jul‐11
28‐Jul‐11
100.00%
35.71%
WELDING & NDT
512
30.55%
31
81.25%
24.82%
0.00%
0.00%
5‐Jul‐11
4‐Aug‐11
81.25%
24.82%
PTJ9270
WELDING OF CONDUCTOR
320
62.50%
10
100.00%
62.50%
0.00%
0.00%
5‐Jul‐11
16‐Jul‐11
100.00%
62.50%
PTJ9280
WELDING OF CONDUCTOR SUPPORT
192
37.50%
6
50.00%
18.75%
0.00%
0.00%
30‐Jul‐11
4‐Aug‐11
50.00%
18.75%
660
39.38%
12
50.00%
19.69%
0.00%
0.00%
6‐Aug‐11
17‐Aug‐11
50.00%
19.69%
660
100.00%
11
50.00%
50.00%
0.00%
0.00%
6‐Aug‐11
17‐Aug‐11
50.00%
50.00%
5480
17.63%
82
92.29%
16.27%
0.00%
0.00%
23-Aug-11
12-Nov-11
92.29%
16.27%
CONDUCTORS ERECTION PTJ9290 ELEV ‐ 79000
ERECTION OF CONDUCTOR WITH ELEVATIONS
11/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
FITUP
Total Budgete Units (Hrs)
R.W %
2664
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
48.61%
35
100.00%
48.61%
0.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
23-Aug-11
26-Sep-11
100.00%
48.61%
PTJ9010
FITUP OF SIZE 28"
1080
40.54%
15
100.00%
40.54%
0.00%
0.00%
23‐Aug‐11
12‐Sep‐11
100.00%
40.54%
PTJ9020
FITUP OF SIZE 16"
648
24.32%
9
100.00%
24.32%
0.00%
0.00%
7‐Sep‐11
17‐Sep‐11
100.00%
24.32%
PTJ9030
FITUP OF SIZE 24"
720
27.03%
10
100.00%
27.03%
0.00%
0.00%
13‐Sep‐11
24‐Sep‐11
100.00%
27.03%
PTJ9040
FITUP OF SIZE 20"
WELDING&NDT
216
8.11%
6
100.00%
8.11%
0.00%
0.00%
20‐Sep‐11
26‐Sep‐11
100.00%
8.11%
2816
51.39%
47
85.00%
43.68%
0.00%
0.00%
27-Sep-11
12-Nov-11
85.00%
43.68%
PTJ9050
WELDING OF SIZE 28"
1152
40.91%
18
85.00%
34.77%
0.00%
0.00%
27‐Sep‐11
18‐Oct‐11
85.00%
34.77%
PTJ9060
WELDING OF SIZE 16"
640
22.73%
10
85.00%
19.32%
0.00%
0.00%
13‐Oct‐11
24‐Oct‐11
85.00%
19.32%
PTJ9070
WELDING OF SIZE 24"
768
27.27%
12
85.00%
23.18%
0.00%
0.00%
20‐Oct‐11
2‐Nov‐11
85.00%
23.18%
PTJ9080
WELDING OF SIZE 20"
256
9.09%
4
85.00%
7.73%
0.00%
0.00%
2‐Nov‐11
12‐Nov‐11
85.00%
7.73%
12832
9.60%
87
7.29%
0.70%
0.00%
0.00%
05-Dec-11
29-Feb-12
7.29%
0.70%
3208
25.00%
64
0.22%
0.06%
0.00%
0.00%
5-Dec-11
6-Feb-12
0.22%
0.06%
5.00%
PILE SLEEVES FABRICATION AT LEG B1 PTJ9460
CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
144
4.49%
4
0.22%
0.00%
0.00%
5‐Dec‐11
8‐Dec‐11
5.00%
0.22%
PTJ9500
GIRTH WELD OF PILE SLEEVE
1152
35 91% 35.91%
24
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
14‐Dec‐11
11‐Jan‐12
0 00% 0.00%
0 00% 0.00%
PTJ9470
CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS
144
4.49%
4
0.00%
0.00%
0.00%
8‐Jan‐12
11‐Jan‐12
0.00%
0.00%
PTJ9510
ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE
1248
38.90%
12
0.00%
0.00%
0.00%
12‐Jan‐12
25‐Jan‐12
0.00%
0.00%
PTJ9520
ERECTION OF PILE SLEEVE WITH LEGS
520
16.21%
10
0.00%
0.00%
0.00%
26‐Jan‐12
6‐Feb‐12
0.00%
0.00% 7.24%
3208
25.00%
64
28.95%
7.24%
0.00%
0.00%
5-Dec-11
6-Feb-12
28.95%
PTJ9320
CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
144
4.49%
4
5.00%
0.22%
0.00%
0.00%
5‐Dec‐11
8‐Dec‐11
5.00%
0.22%
PTJ9360
GIRTH WELD OF PILE SLEEVE
1152
35.91%
24
80.00%
28.73%
0.00%
0.00%
14‐Dec‐11
11‐Jan‐12
80.00%
28.73%
PTJ9330
CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS
144
4.49%
4
0.00%
0.00%
0.00%
8‐Jan‐12
11‐Jan‐12
0.00%
0.00%
PTJ9370
ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE
1248
38.90%
12
0.00%
0.00%
0.00%
12‐Jan‐12
25‐Jan‐12
0.00%
0.00%
PTJ9380
ERECTION OF PILE SLEEVE WITH LEGS
AT LEG A1
AT LEG A2
520
16.21%
10
3208
25.00%
64
0.00%
0.00%
0.00%
0.00%
26‐Jan‐12
6‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
28-Dec-11
29-Feb-12
0.00%
0.00%
PTJ9390
CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
144
4.49%
4
0.00%
0.00%
0.00%
28‐Dec‐11
1‐Jan‐12
0.00%
0.00%
PTJ9430
GIRTH WELD OF PILE SLEEVE
1152
35.91%
24
0.00%
0.00%
0.00%
8‐Jan‐12
4‐Feb‐12
0.00%
0.00%
PTJ9400
CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS
144
4.49%
4
0.00%
0.00%
0.00%
31‐Jan‐12
4‐Feb‐12
0.00%
0.00%
PTJ9440
ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE
1248
38.90%
12
0.00%
0.00%
0.00%
5‐Feb‐12
18‐Feb‐12
0.00%
0.00%
PTJ9450
ERECTION OF PILE SLEEVE WITH LEGS
AT LEG B2
520
16.21%
10
3208
25.00%
64
0.00%
0.00%
0.00%
0.00%
19‐Feb‐12
29‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
28-Dec-11
29-Feb-12
0.00%
0.00%
PTJ9530
CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
144
4.49%
4
0.00%
0.00%
0.00%
28‐Dec‐11
1‐Jan‐12
0.00%
0.00%
PTJ9570
GIRTH WELD OF PILE SLEEVE
1152
35.91%
24
0.00%
0.00%
0.00%
8‐Jan‐12
4‐Feb‐12
0.00%
0.00%
PTJ9540
CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PLATE & STIFFENERS
144
4.49%
4
0.00%
0.00%
0.00%
31‐Jan‐12
4‐Feb‐12
0.00%
0.00%
12/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
OVERALL
ITEM
OVERALL
0.00%
0.00%
5‐Feb‐12
18‐Feb‐12
0.00%
0.00%
PTJ9580
ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEEVE
1248
38.90%
12
0.00%
PTJ9590
ERECTION OF PILE SLEEVE WITH LEGS
520
16.21%
10
0.00%
0.00%
0.00%
19‐Feb‐12
29‐Feb‐12
0.00%
0.00%
11656
8.72%
257
0.00%
0.00%
3.00%
0.26%
18-Jun-11
29-Feb-12
-3.00%
-0.26%
476
4.08%
8
0.00%
0.00%
0.00%
0.00%
21-Nov-11
28-Nov-11
0.00%
0.00%
476
100.00%
8
0.00%
0.00%
0.00%
0.00%
21‐Nov‐11
28‐Nov‐11
0.00%
0.00%
476
100.00%
7
0.00%
0.00%
0.00%
21‐Nov‐11
28‐Nov‐11
0.00%
0.00%
476
4.08%
9
0.00%
0.00%
0.00%
0.00%
4-Jan-12
12-Jan-12
0.00%
0.00%
476
100.00%
9
0.00%
0.00%
0.00%
0.00%
4‐Jan‐12
12‐Jan‐12
0.00%
0.00%
476
100.00%
7
0.00%
0.00%
0.00%
4‐Jan‐12
12‐Jan‐12
0.00%
0.00%
476
4.08%
8
0.00%
0.00%
0.00%
0.00%
13-Nov-11
20-Nov-11
0.00%
0.00%
476
100.00%
8
0.00%
0.00%
0.00%
0.00%
13‐Nov‐11
20‐Nov‐11
0.00%
0.00%
476
100.00%
7
0.00%
0.00%
0.00%
13‐Nov‐11
20‐Nov‐11
0.00%
0.00%
476
4.08%
8
0.00%
0.00%
0.00%
0.00%
30-Nov-11
7-Dec-11
0.00%
0.00%
476
100 00% 100.00%
8
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
30‐Nov‐11
7‐Dec‐11
0 00% 0.00%
0 00% 0.00%
476
100.00%
7
0.00%
0.00%
0.00%
30‐Nov‐11
7‐Dec‐11
0.00%
0.00%
2040
17.50%
148
0.00%
0.00%
17.16%
3.00%
18-Jun-11
12-Nov-11
-17.16%
-3.00%
2000
98.04%
146
0.00%
0.00%
17.50%
17.16%
18‐Jun‐11
10‐Nov‐11
‐17.50%
‐17.16%
0.00%
‐13.00%
JACKET ERECTION ELEV ‐79.0 ERECTION ON ROW2 PTJ9090
ERECTION OF ELEV AT ‐79 ON ROW 2
ELEV +6.4 ERECTION ON ROW2 PTJ8690
ERECTION OF ELEV AT + 6.4 ON ROW 2
ELEV ‐56.2 ERECTION ON ROW2 PTJ9000
ERECTION OF ELEV AT ‐56.2 ON ROW 2
ELEV ‐ 33.4 ERECTION ON ROW2 PTJ8890
ERECTION OF ELEV AT ‐33.4 ON ROW 2
ROW 2 ERECTION HORIZONTAL
500
25.00%
17
0.00%
52.00%
13.00%
18‐Jun‐11
4‐Jul‐11
‐52.00%
PTJ9340
FITUP OF HORIZONTAL ON LEG
180
36.00%
5
0.00%
100.00%
36.00%
18‐Jun‐11
22‐Jun‐11
‐100.00%
‐36.00%
PTJ9350
WELDING OF HORIZONTAL ON LEG
320
64.00%
10
0.00%
25.00%
16.00%
23‐Jun‐11
4‐Jul‐11
‐25.00%
‐16.00%
DIAGONAL BRACES
1000
50.00%
36
0.00%
9.00%
4.50%
23‐Jun‐11
28‐Jul‐11
‐9.00%
‐4.50%
PTJ8070
FITUP OF DIAGONAL ON LEG
360
36.00%
10
0.00%
25.00%
9.00%
23‐Jun‐11
4‐Jul‐11
‐25.00%
‐9.00%
PTJ8080
WELDING OF DIAGONAL ON LEG
640
64.00%
20
0.00%
0.00%
0.00%
5‐Jul‐11
28‐Jul‐11
0.00%
0.00%
VERTICAL
0.00%
500
25.00%
23
0.00%
0.00%
0.00%
19‐Oct‐11
10‐Nov‐11
0.00%
0.00%
PTJ8090
FITUP OF VERTICAL BRACES WITH ROW 2 BRACES
180
36.00%
5
0.00%
0.00%
0.00%
19‐Oct‐11
24‐Oct‐11
0.00%
0.00%
PTJ8100
WELDING OF VERTICAL BRACES WITH ROW 2 BRACES
320
64.00%
10
0.00%
0.00%
0.00%
25‐Oct‐11
10‐Nov‐11
0.00%
0.00%
0.00%
0.00%
0.00%
12‐Nov‐11
12‐Nov‐11
0.00%
0.00%
0.00%
0.00%
0.00%
12‐Nov‐11
12‐Nov‐11
0.00%
0.00%
0.00%
0.00%
18‐Dec‐11
25‐Dec‐11
0.00%
0.00%
LIFTING OVER TRUSS RUNNER PTJ8110
LIFTING OVER TRUSS RUNNERS
ELEV ‐10.6 ERECTION ON ROW2
0.00%
40
1.96%
1
40
100.00%
1
476
4.08%
8
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
18‐Dec‐11
25‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
18‐Dec‐11
25‐Dec‐11
0.00%
0.00%
0.00%
476
100.00%
8
476
100.00%
7
1224
10.50%
108
0.00%
0.00%
0.00%
0.00%
13‐Sep‐11
29‐Dec‐11
0.00%
0.00%
1224
100.00%
108
0.00%
0.00%
0.00%
0.00%
13‐Sep‐11
29‐Dec‐11
0.00%
0.00%
PTJ8300
ERECTION X BRACES BETWEEN ‐56.2 & ‐79.0
408
33.33%
6
0.00%
0.00%
0.00%
13‐Sep‐11
19‐Sep‐11
0.00%
0.00%
PTJ8320
ERECTION X BRACES BETWEEN ‐33.4 & ‐56.2
272
22.22%
4
0.00%
0.00%
0.00%
21‐Nov‐11
24‐Nov‐11
0.00%
0.00%
PTJ8780
ERECTION OF ELEV AT ‐10.6 ON ROW 2
ROW A ERECTION
13/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
PTJ8310
ERECTION X BRACES BETWEEN ‐10.6 & ‐33.4
PTJ8290
ERECTION X BRACES BETWEEN +6.4 & ‐10.6
ROW B ERECTION
Total Budgete Units (Hrs)
R.W %
272
22.22%
Original Duration (Days)
ACTUAL % ITEM
4
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
OVERALL
ITEM
OVERALL
0.00%
0.00%
0.00%
8‐Dec‐11
12‐Dec‐11
0.00%
0.00%
272
22.22%
4
0.00%
0.00%
0.00%
26‐Dec‐11
29‐Dec‐11
0.00%
0.00%
1224
10.50%
106
0.00%
0.00%
0.00%
0.00%
20‐Sep‐11
3‐Jan‐12
0.00%
0.00%
1224
100.00%
106
0.00%
0.00%
0.00%
0.00%
20‐Sep‐11
3‐Jan‐12
0.00%
0.00%
PTJ8420
ERECTION X BRACES BETWEEN ‐56.2 & ‐79.0
408
33.33%
6
0.00%
0.00%
0.00%
20‐Sep‐11
26‐Sep‐11
0.00%
0.00%
PTJ8440
ERECTION X BRACES BETWEEN ‐33.4 & ‐56.2
272
22.22%
4
0.00%
0.00%
0.00%
26‐Nov‐11
29‐Nov‐11
0.00%
0.00%
PTJ8430
ERECTION X BRACES BETWEEN ‐10.6 & ‐33.4
272
22.22%
4
0.00%
0.00%
0.00%
13‐Dec‐11
17‐Dec‐11
0.00%
0.00%
PTJ8410
ERECTION X BRACES BETWEEN +6.4 & ‐10.6
272
22.22%
4
0.00%
0.00%
0.00%
31‐Dec‐11
3‐Jan‐12
0.00%
0.00%
816
7.00%
22
0.00%
0.00%
0.00%
21‐Nov‐11
12‐Dec‐11
0.00%
0.00%
ROW C
0.00%
PTJ8510
ERECTION ROW C BRACES BETWEEN ‐56.2 & ‐79.0
272
33.33%
4
0.00%
0.00%
0.00%
21‐Nov‐11
24‐Nov‐11
0.00%
0.00%
PTJ8520
ERECTION ROW C BRACES BETWEEN ‐33.4 & ‐56.2
272
33.33%
4
0.00%
0.00%
0.00%
8‐Dec‐11
12‐Dec‐11
0.00%
0.00%
PTJ8530
ERECTION ROW C BRACES BETWEEN ‐ 10.6 & ‐33.4
272
33.33%
4
0.00%
0.00%
0.00%
8‐Dec‐11
12‐Dec‐11
0.00%
0.00%
408
3.50%
29
0.00%
0.00%
0.00%
29‐Nov‐11
27‐Dec‐11
0.00%
0.00%
PTJ8600
ERECTION ROW D BRACES BETWEEN ‐56.2 & ‐79.0
136
33.33%
2
0.00%
0.00%
0.00%
29‐Nov‐11
30‐Nov‐11
0.00%
0.00%
PTJ8610
ERECTION ROW D BRACES BETWEEN ‐33.4 & ‐56.2
136
33.33%
2
0.00%
0.00%
0.00%
8‐Dec‐11
10‐Dec‐11
0.00%
0.00%
PTJ8620
ERECTION ROW D BRACES BETWEEN ‐10.6 & ‐33.4
136
33.33%
2
816
7.00%
5
ROW D
ROW 3
0.00%
0.00%
0.00%
0.00%
0.00%
26‐Dec‐11
27‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
2‐Feb‐12
6‐Feb‐12
0.00%
0.00%
PTJ8180
ERECTION ROW 3 BRACES BETWEEN ‐10.6 & ‐33.4
272
33.33%
4
0.00%
0.00%
0.00%
2‐Feb‐12
6‐Feb‐12
0.00%
0.00%
PTJ8190
ERECTION ROW 3 BRACES BETWEEN ‐33.4 & ‐56.2
272
33.33%
4
0.00%
0.00%
0.00%
2‐Feb‐12
6‐Feb‐12
0.00%
0.00%
PTJ8200
ERECTION ROW 3 BRACES BETWEEN ‐56.2 & ‐79.0
272
33.33%
4
0.00%
0.00%
0.00%
2‐Feb‐12
6‐Feb‐12
0.00%
0.00%
2748
23.58%
152
0.00%
0.00%
0.00%
0.00%
1‐Oct‐11
29‐Feb‐12
0.00%
0.00%
500
18.20%
18
0.00%
0.00%
0.00%
0.00%
1‐Oct‐11
18‐Oct‐11
0.00%
0.00%
180
36.00%
5
0.00%
0.00%
0.00%
1‐Oct‐11
5‐Oct‐11
0.00%
0.00%
ROW 1 HORIZONTAL PTJ9480
FITUP OF HORIZONTAL ON LEG
PTJ9490
WELDING OF HORIZONTAL ON LEG
DIAGONAL BRACES PTJ9410
FITUP OF DIAGONAL ON LEG
PTJ9420
WELDING OF DIAGONAL ON LEG
ERECTION ROW 1
320
64.00%
10
1000
36.39%
40
360
36.00%
10
0.00%
0.00%
0.00%
0.00%
8‐Oct‐11
18‐Oct‐11
0.00%
0.00%
0.00%
0.00%
0.00%
8‐Oct‐11
16‐Nov‐11
0.00%
0.00%
0.00%
0.00%
0.00%
8‐Oct‐11
18‐Oct‐11
0.00%
0.00%
0.00%
0.00%
0.00%
19‐Oct‐11
16‐Nov‐11
0.00%
0.00%
0.00%
0.00%
0.00%
7‐Feb‐12
29‐Feb‐12
0.00%
0.00%
1
0.00%
0.00%
0.00%
7‐Feb‐12
7‐Feb‐12
0.00%
0.00%
640
64.00%
20
1248
45.41%
23
128
10.26%
0.00%
PTJ8000
LIFTING OF ROW 1 OVER ELAVATIONS & ROW A,B
PTJ8010
FITUP OF ROW 1 OVER ELAVATIONS & ROW A,B
160
12.82%
4
0.00%
0.00%
0.00%
8‐Feb‐12
12‐Feb‐12
0.00%
0.00%
PTJ8020
WELDING OF ROW 1 OVER ELAVATIONS & ROW A,B
960
76.92%
15
0.00%
0.00%
0.00%
13‐Feb‐12
29‐Feb‐12
0.00%
0.00%
108888
44.20%
342
6.89%
11.04%
4.88%
31‐Mar‐11
06‐Mar‐12
4.55%
2.01%
JACKET MISCELLANEOUS FABRICATION
15.59%
PTJ9600
Jacket miscellaneous fabrication start
0
0.00%
0
0.00%
0.00%
0.00%
3‐Sep‐11
3‐Sep‐11
0.00%
0.00%
PTJ11020
Jacket miscellaneous fabrication finish
0
0.00%
0
0.00%
0.00%
0.00%
6‐Mar‐12
6‐Mar‐12
0.00%
0.00%
8804
8.09%
65
0.00%
0.00%
0.00%
02-Jan-12
06-Mar-12
0.00%
0.00%
BOAT LAND
0.00%
14/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Main Legs
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
236
2.68%
5
0.00%
0.00%
0.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
2‐Jan‐12
6‐Jan‐12
0.00%
0.00%
BL1000
Cutting & Assembly
108
45.76%
3
0.00%
0.00%
0.00%
2‐Jan‐12
4‐Jan‐12
0.00%
0.00%
BL1010
Welding & NDT
128
54.24%
4
0.00%
0.00%
0.00%
3‐Jan‐12
6‐Jan‐12
0.00%
0.00%
880
10.00%
20
0.00%
0.00%
0.00%
7‐Jan‐12
26‐Jan‐12
0.00%
0.00%
Back Elevation
0.00%
BL1040
Cutting & Assembly
400
45.45%
10
0.00%
0.00%
0.00%
7‐Jan‐12
16‐Jan‐12
0.00%
0.00%
BL1050
Welding & NDT
480
54.55%
15
0.00%
0.00%
0.00%
12‐Jan‐12
26‐Jan‐12
0.00%
0.00%
Front Elevation
3552
40.35%
21
0.00%
0.00%
0.00%
11‐Feb‐12
2‐Mar‐12
0.00%
0.00%
BL1020
Cutting & Assembly
1632
45.95%
12
0.00%
0.00%
0.00%
11‐Feb‐12
22‐Feb‐12
0.00%
0.00%
BL1030
Welding & NDT
1920
54.05%
15
0.00%
0.00%
0.00%
17‐Feb‐12
2‐Mar‐12
0.00%
0.00%
Plan at Elev. +2.6
0.00%
336
3.82%
14
0.00%
0.00%
0.00%
28‐Jan‐12
10‐Feb‐12
0.00%
0.00%
BL1060
Cutting & Assembly
144
42.86%
4
0.00%
0.00%
0.00%
28‐Jan‐12
31‐Jan‐12
0.00%
0.00%
BL1070
Welding & NDT
192
57.14%
6
0.00%
0.00%
0.00%
5‐Feb‐12
10‐Feb‐12
0.00%
0.00%
Plan at Elev. +2.4
0.00%
404
4.59%
15
0.00%
0.00%
0.00%
27‐Jan‐12
10‐Feb‐12
0.00%
0.00%
BL1080
Cutting & Assembly
180
44.55%
5
0.00%
0.00%
0.00%
27‐Jan‐12
31‐Jan‐12
0.00%
0.00%
BL1090
Welding & NDT
224
55.45%
7
0.00%
0.00%
0.00%
4‐Feb‐12
10‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
27‐Jan‐12
10‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
27‐Jan‐12
31‐Jan‐12
0.00%
0.00%
Plan at Elev. ‐30
404
4.59%
15
BL1100
Cutting & Assembly
180
44.55%
5
BL1110
Welding & NDT
224
55.45%
7
336
3.82%
10
BL1120
Cutting & Assembly
144
42.86%
4
BL1130
Welding & NDT
192
57.14%
6
56
0.64%
18
36
64.29%
1
Boat landing Sections (a,b.c,d,e)
Grating BL1140
Trial Fit and Grating Stopper Fixation
BL1150
Final Installation
Stairs & Ladders BL1160
Fabrication
BL1170
Installation
Handrails BL1200
Fabrication
BL1210
Installation
Mooring Cleat
20
35.71%
1
268
3.04%
8
160
59.70%
5
108
40.30%
3
200
2.27%
16
128
64.00%
4
72
36.00%
2
68
0.77%
2
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4‐Feb‐12
10‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
1‐Feb‐12
10‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
1‐Feb‐12
4‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
5‐Feb‐12
10‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
18‐Feb‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
18‐Feb‐12
18‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
6‐Mar‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
24‐Feb‐12
2‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
24‐Feb‐12
28‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
29‐Feb‐12
2‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
20‐Feb‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
20‐Feb‐12
23‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
5‐Mar‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
1‐Mar‐12
2‐Mar‐12
0.00%
0.00%
BL1220
Fabrication
32
47.06%
1
0.00%
0.00%
0.00%
1‐Mar‐12
1‐Mar‐12
0.00%
0.00%
BL1230
Installation
36
52.94%
1
0.00%
0.00%
0.00%
2‐Mar‐12
2‐Mar‐12
0.00%
0.00%
72
0.82%
1
0.00%
0.00%
0.00%
6‐Mar‐12
6‐Mar‐12
0.00%
0.00%
72
100.00%
1
0.00%
0.00%
0.00%
6‐Mar‐12
6‐Mar‐12
0.00%
0.00%
Rubber BL1240
Installation of Rubber & Tightening
0.00%
15/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Lower Support Fabrication
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
716
8.13%
27
0.00%
0.00%
0.00%
0.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
5‐Feb‐12
2‐Mar‐12
0.00%
0.00%
540
75.42%
16
0.00%
0.00%
0.00%
5‐Feb‐12
20‐Feb‐12
0.00%
0.00%
BL1250
Cutting & Assembly
252
46.67%
7
0.00%
0.00%
0.00%
5‐Feb‐12
11‐Feb‐12
0.00%
0.00%
BL1260
Welding & NDT
288
53.33%
9
0.00%
0.00%
0.00%
12‐Feb‐12
20‐Feb‐12
0.00%
0.00%
176
24.58%
4
0.00%
0.00%
0.00%
28‐Feb‐12
2‐Mar‐12
0.00%
0.00%
80
45.45%
2
0.00%
0.00%
0.00%
28‐Feb‐12
29‐Feb‐12
0.00%
0.00%
Installation with Jacket legs BL1270
Profiling Template & Assembly with Legs
BL1280
Welding & NDT
Upper Support Fabrication
0.00%
96
54.55%
3
0.00%
0.00%
0.00%
29‐Feb‐12
2‐Mar‐12
0.00%
0.00%
972
11.04%
23
0.00%
0.00%
0.00%
0.00%
9‐Feb‐12
2‐Mar‐12
0.00%
0.00%
636
65.43%
19
0.00%
0.00%
0.00%
0.00%
9‐Feb‐12
27‐Feb‐12
0.00%
0.00%
BL1290
Cutting & Assembly
252
39.62%
7
0.00%
0.00%
0.00%
9‐Feb‐12
15‐Feb‐12
0.00%
0.00%
BL1300
Welding & NDT
384
60.38%
12
0.00%
0.00%
0.00%
16‐Feb‐12
27‐Feb‐12
0.00%
0.00%
336
34.57%
4
0.00%
0.00%
0.00%
28‐Feb‐12
2‐Mar‐12
0.00%
0.00%
Installation with Jacket legs
0.00%
BL1310
Profiling Template & Assembly with Legs
144
42.86%
2
0.00%
0.00%
0.00%
28‐Feb‐12
29‐Feb‐12
0.00%
0.00%
BL1320
Welding & NDT
192
57.14%
3
0.00%
0.00%
0.00%
29‐Feb‐12
2‐Mar‐12
0.00%
0.00%
304
3.45%
2
0.00%
0.00%
0.00%
3‐Mar‐12
4‐Mar‐12
0.00%
0.00%
304
100.00%
2
0.00%
0.00%
0.00%
3‐Mar‐12
4‐Mar‐12
0.00%
0.00%
2952
2.71%
30
0.00%
0.00%
0.00%
0.00%
06-Feb-12
06-Mar-12
0.00%
0.00%
0.00%
Boat landing trial fit BL1330
Boat Landing Trial Fit
BARGE BUMPER Main Pipe
0.00%
504
17.07%
15
0.00%
0.00%
0.00%
6‐Feb‐12
20‐Feb‐12
0.00%
0.00%
BB1000
Cutting & Assembly
216
42.86%
6
0.00%
0.00%
0.00%
6‐Feb‐12
11‐Feb‐12
0.00%
0.00%
BB1010
Welding & NDT
288
57.14%
9
0.00%
0.00%
0.00%
12‐Feb‐12
20‐Feb‐12
0.00%
0.00%
Upper Support
1312
44.44%
28
0.00%
0.00%
0.00%
0.00%
6‐Feb‐12
4‐Mar‐12
0.00%
0.00%
976
74.39%
23
0.00%
0.00%
0.00%
0.00%
6‐Feb‐12
28‐Feb‐12
0.00%
0.00%
BB1060
Cutting & Assembly
432
44.26%
12
0.00%
0.00%
0.00%
6‐Feb‐12
17‐Feb‐12
0.00%
0.00%
BB1070
Welding & NDT
544
55.74%
17
336
25.61%
5
42.86%
2
Fabrication
Installation with Jacket legs
0.00%
0.00%
0.00%
0.00%
12‐Feb‐12
28‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
29‐Feb‐12
4‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
29‐Feb‐12
1‐Mar‐12
0.00%
0.00%
BB1080
Profiling Template & Assembly with Legs
144
BB1090
Welding & NDT
192
57.14%
3
0.00%
0.00%
0.00%
2‐Mar‐12
4‐Mar‐12
0.00%
0.00%
976
33.06%
24
0.00%
0.00%
0.00%
0.00%
10‐Feb‐12
4‐Mar‐12
0.00%
0.00%
336
34.43%
5
0.00%
0.00%
0.00%
0.00%
29‐Feb‐12
4‐Mar‐12
0.00%
0.00%
Lower Support Installation with Jacket legs BB1040
Profiling Template & Assembly with Legs
144
42.86%
2
0.00%
0.00%
0.00%
29‐Feb‐12
1‐Mar‐12
0.00%
0.00%
BB1050
Welding & NDT
192
57.14%
3
0.00%
0.00%
0.00%
2‐Mar‐12
4‐Mar‐12
0.00%
0.00%
Fabrication
640
65.57%
19
0.00%
0.00%
0.00%
10‐Feb‐12
28‐Feb‐12
0.00%
0.00%
BB1020
Cutting & Assembly
288
45.00%
8
0.00%
0.00%
0.00%
10‐Feb‐12
17‐Feb‐12
0.00%
0.00%
BB1030
Welding & NDT
352
55.00%
11
0.00%
0.00%
0.00%
18‐Feb‐12
28‐Feb‐12
0.00%
0.00%
160
5.42%
2
0.00%
0.00%
0.00%
5‐Mar‐12
6‐Mar‐12
0.00%
0.00%
Barge Bumper Trial Fit
0.00%
0.00%
16/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
BB1100
Activity Name Barge Bumper Trial Fit
RISER 16" & CLAMPS
Total Budgete Units (Hrs)
R.W %
160
100.00%
2
2472
2.27%
62
Original Duration (Days)
ACTUAL % ITEM
0.00%
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
OVERALL
ITEM
OVERALL
0.00%
0.00%
0.00%
5‐Mar‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
03-Sep-11
03-Nov-11
0.00%
0.00%
PTJ10590
RISER 16 " FABRICATION
792
32.04%
22
0.00%
0.00%
0.00%
3‐Sep‐11
27‐Sep‐11
0.00%
0.00%
PTJ10620
CLAMPS FOR RISER 16 " FABRICATION
648
26.21%
18
0.00%
0.00%
0.00%
3‐Sep‐11
22‐Sep‐11
0.00%
0.00%
PTJ10600
RISER COATING
168
6.80%
7
0.00%
0.00%
0.00%
28‐Sep‐11
5‐Oct‐11
0.00%
0.00%
PTJ10630
CLAMPS FOR RISER 16 " INSTALLATION
504
20.39%
14
0.00%
0.00%
0.00%
8‐Oct‐11
23‐Oct‐11
0.00%
0.00%
PTJ10610
RISER 16 " INSTALLATION
360
14.56%
10
0.00%
0.00%
0.00%
24‐Oct‐11
3‐Nov‐11
0.00%
0.00%
1440
1.32%
51
0.00%
0.00%
0.00%
03-Sep-11
23-Oct-11
0.00%
0.00%
504
35.00%
14
0.00%
0.00%
0.00%
3‐Sep‐11
18‐Sep‐11
0.00%
0.00%
J‐TUBE 16 " & CLAMPS
0.00%
PTJ10640
J‐TUBE16 " FABRICATION
PTJ10650
CLAMPS FOR J‐TUBE16 " FABRICATION
432
30.00%
12
0.00%
0.00%
0.00%
3‐Sep‐11
15‐Sep‐11
0.00%
0.00%
PTJ10660
CLAMPS FOR J‐TUBE16 " INSTALLATION
360
25.00%
10
0.00%
0.00%
0.00%
8‐Oct‐11
18‐Oct‐11
0.00%
0.00%
PTJ10680
J‐TUBE16 " INSTALLATION
144
10.00%
4
0.00%
0.00%
0.00%
19‐Oct‐11
23‐Oct‐11
0.00%
0.00%
504
0.46%
41
0.00%
0.00%
0.00%
03-Sep-11
13-Oct-11
0.00%
0.00%
FUTURE J‐TUBE CLAMPS
0.00%
PTJ10690
CLAMPS FOR FUTURE J‐TUBE FABRICATION
288
57.14%
8
0.00%
0.00%
0.00%
3‐Sep‐11
11‐Sep‐11
0.00%
0.00%
PTJ10700
CLAMPS FOR FUTURE J‐TUBE INSTALLATION
216
42.86%
6
0.00%
0.00%
0.00%
8‐Oct‐11
13‐Oct‐11
0.00%
0.00%
1384
1.27%
21
0.00%
0.00%
0.00%
14-Feb-12
05-Mar-12
0.00%
0.00%
SUMP CAISSON 30"
0.00%
PTJ10710
SUMP CAISSON 30 " FABRICATION
952
68.79%
14
0.00%
0.00%
0.00%
14‐Feb‐12
29‐Feb‐12
0.00%
0.00%
PTJ10720
SUPPORTS SUMP CAISSON 30 " FABRICATION
72
5.20%
2
0.00%
0.00%
0.00%
21‐Feb‐12
22‐Feb‐12
0.00%
0.00%
PTJ10730
SUPPORTS SUMP CAISSON 30 " INSTALLATION
216
15.61%
6
0.00%
0.00%
0.00%
23‐Feb‐12
29‐Feb‐12
0.00%
0.00%
PTJ10740
SUPPORTS SUMP CAISSON 30 " INSTALLATION
144
10.40%
4
0.00%
0.00%
0.00%
1‐Mar‐12
5‐Mar‐12
0.00%
0.00%
2880
2.64%
100
0.00%
0.00%
0.00%
03-Sep-11
11-Dec-11
0.00%
0.00%
MUD MAT
0.00%
PTJ10750
MUD MAT FABRICATION
2160
75.00%
60
0.00%
0.00%
0.00%
3‐Sep‐11
17‐Nov‐11
0.00%
0.00%
PTJ10760
MUD MAT INSTALLATION
720
25.00%
20
0.00%
0.00%
0.00%
19‐Nov‐11
11‐Dec‐11
0.00%
0.00%
1712
1.57%
55
0.00%
0.00%
0.00%
03-Sep-11
27-Oct-11
0.00%
0.00%
WALK WAY & STAIRS
0.00%
PTJ10350
FITUP OF WALK WAY & STARIR
384
22.43%
12
0.00%
0.00%
0.00%
3‐Sep‐11
15‐Sep‐11
0.00%
0.00%
PTJ10360
WELDING & NDT OF WALK WAY & STARIRS
512
29.91%
16
0.00%
0.00%
0.00%
17‐Sep‐11
4‐Oct‐11
0.00%
0.00%
PTJ10370
ERECTION WALK WAY ON TOP ELEVATION
816
47.66%
12
0.00%
0.00%
0.00%
15‐Oct‐11
27‐Oct‐11
0.00%
0.00%
19224
17.65%
141
85.67%
15.13%
62.53%
11.04%
31-Mar-11
18-Aug-11
23.14%
4.09%
9612
50.00%
141
85.67%
42.84%
62.53%
31.27%
31-Mar-11
18-Aug-11
23.14%
11.57%
3204
33.33%
59
85.67%
28.56%
100.00%
33.33%
31-Mar-11
28-May-11
LAUNCH RUNNERS AT ROW D FROM EL. ‐33400 TO ‐10600
-14.33%
-4.78%
PTJ9820
FITUP OF LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6
2100
65.54%
35
95.00%
62.27%
100.00%
65.54%
31‐Mar‐11
14‐May‐11
‐5.00%
‐3.28%
PTJ9830
WELDING & NDT LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6
1000
31.21%
25
75.00%
23.41%
100.00%
31.21%
26‐Apr‐11
25‐May‐11
‐25.00%
‐7.80%
PTJ9840
LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY
104
3.25%
2
0.00%
100.00%
3.25%
26‐May‐11
28‐May‐11
‐100.00%
‐3.25%
17/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
FROM EL. ‐56200 TO ‐33400
Total Budgete Units (Hrs)
R.W %
3204
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
33.33%
54
85.67%
28.56%
85.99%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
28.66%
15-May-11
7-Jul-11
-0.32%
-0.11%
PTJ9790
FITUP OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4
2100
65.54%
35
95.00%
62.27%
100.00%
65.54%
15‐May‐11
23‐Jun‐11
‐5.00%
‐3.28%
PTJ9800
WELDING & NDT OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4
1000
31.21%
25
75.00%
23.41%
65.52%
20.45%
7‐Jun‐11
5‐Jul‐11
9.48%
2.96%
PTJ9810
LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY
104
3.25%
2
0.00%
0.00%
0.00%
6‐Jul‐11
7‐Jul‐11
0.00%
0.00%
3204
33.33%
55
85.67%
28.56%
1.60%
0.53%
25-Jun-11
18-Aug-11
84.08%
28.03%
PTJ9760
FITUP OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56
2100
65.54%
35
95.00%
62.27%
2.44%
1.60%
25‐Jun‐11
4‐Aug‐11
92.56%
60.67%
PTJ9770
WELDING & NDT OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56
1000
31.21%
25
75.00%
23.41%
0.00%
0.00%
18‐Jul‐11
16‐Aug‐11
75.00%
23.41%
PTJ9780
LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY
104
3.25%
2
0.00%
0.00%
0.00%
17‐Aug‐11
18‐Aug‐11
0.00%
0.00%
9612
50.00%
141
85.67%
42.84%
62.53%
31.27%
31-Mar-11
18-Aug-11
23.14%
11.57%
3204
33.33%
59
85.67%
28.56%
100.00%
33.33%
31-Mar-11
28-May-11
-14.33%
-4.78%
2100
65.54%
35
95.00%
62.27%
100.00%
65.54%
31‐Mar‐11
14‐May‐11
‐5.00%
‐3.28%
25
75.00%
23.41%
100.00%
31.21%
26‐Apr‐11
25‐May‐11
‐25.00%
‐7.80%
FROM EL. ‐79000 TO ‐56200
AT ROW C FROM EL. ‐33400 TO ‐10600 PTJ9730
FITUP OF LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6
PTJ9740
WELDING & NDT LUNCH TRUSS FROM EL ‐33.4 UP TO ‐10.6
PTJ9750
LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY
FROM EL. ‐79000 TO ‐56200
1000
31.21%
104
3.25%
2
0.00%
100.00%
3.25%
26‐May‐11
28‐May‐11
‐100.00%
‐3.25%
3204
33.33%
55
85.67%
28.56%
1.60%
0.53%
25-Jun-11
18-Aug-11
84.08%
28.03%
2.44%
1.60%
25‐Jun‐11
4‐Aug‐11
92.56%
60.67%
PTJ9670
FITUP OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56
2100
65.54%
35
95.00%
62.27%
PTJ9680
WELDING & NDT OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56
1000
31.21%
25
75.00%
23.41%
0.00%
0.00%
18‐Jul‐11
16‐Aug‐11
75.00%
23.41%
PTJ9690
LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY
104
3.25%
2
0.00%
0.00%
0.00%
17‐Aug‐11
18‐Aug‐11
0.00%
0.00%
3204
33.33%
54
85.67%
28.56%
85.99%
28.66%
15-May-11
7-Jul-11
-0.32%
-0.11%
PTJ9700
FITUP OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4
2100
65.54%
35
95.00%
62.27%
100.00%
65.54%
15‐May‐11
23‐Jun‐11
‐5.00%
‐3.28%
PTJ9710
WELDING & NDT OF LUNCH TRUSS FROM EL ‐56 UP TO ‐33.4
1000
31.21%
25
75.00%
23.41%
65.52%
20.45%
7‐Jun‐11
5‐Jul‐11
9.48%
2.96%
PTJ9720
LIFTING OF LUNCH TRUSS FROM EL ‐79 UP TO ‐56 ON SKID WAY
104
3.25%
2
0.00%
0.00%
0.00%
6‐Jul‐11
7‐Jul‐11
0.00%
0.00%
0.46%
0.00%
0.00%
25-Aug-11
06-Mar-12
14.04%
0.46%
0.00%
0.00%
0.00%
25‐Aug‐11
12‐Sep‐11
0.00%
0.00%
FROM EL. ‐56200 TO ‐33400
3564
3.27%
195
PTJ10000
INSTALL ANODES FOR ROW A
468
13.13%
13
PTJ10140
INSTALL ANODES FOR ROW B
576
16.16%
8
10.51%
0.00%
0.00%
11‐Sep‐11
19‐Sep‐11
65.00%
10.51%
PTJ10220
INSTALL ANODES FOR ELEV ‐56.2
252
7.07%
7
0.00%
0.00%
0.00%
30‐Oct‐11
12‐Nov‐11
0.00%
0.00%
PTJ10230
INSTALL ANODES FOR ELEV ‐79.0
252
7.07%
7
0.00%
0.00%
0.00%
13‐Nov‐11
20‐Nov‐11
0.00%
0.00%
PTJ10180
INSTALL ANODES FOR ROW C
216
6.06%
6
0.00%
0.00%
0.00%
14‐Nov‐11
20‐Nov‐11
0.00%
0.00%
PTJ10190
INSTALL ANODES FOR ROW D
216
6.06%
6
0.00%
0.00%
0.00%
22‐Nov‐11
28‐Nov‐11
0.00%
0.00%
PTJ10210
INSTALL ANODES FOR ELEV ‐33.4
180
5.05%
5
0.00%
0.00%
0.00%
24‐Nov‐11
29‐Nov‐11
0.00%
0.00%
PTJ10200
INSTALL ANODES FOR ELEV ‐10.6
180
5.05%
5
0.00%
0.00%
0.00%
12‐Dec‐11
17‐Dec‐11
0.00%
0.00%
PTJ10150
INSTALL ANODES FOR ROW 1
360
10.10%
10
0.00%
0.00%
0.00%
18‐Jan‐12
29‐Jan‐12
0.00%
0.00%
PTJ10170
INSTALL ANODES FOR ROW 3
216
6.06%
6
0.00%
0.00%
0.00%
26‐Jan‐12
1‐Feb‐12
0.00%
0.00%
PTJ10160
INSTALL ANODES FOR ROW 2
360
10.10%
10
3.54%
0.00%
0.00%
11‐Feb‐12
21‐Feb‐12
35.00%
3.54%
PTJ10240
INSTALL ANODES FOR MUD MAT
252
7.07%
7
0.00%
0.00%
0.00%
28‐Feb‐12
6‐Mar‐12
0.00%
0.00%
PTJ10250
INSTALL ANODES FOR SUMP CASSOIN
36
1.01%
1
0.00%
0.00%
0.00%
6‐Mar‐12
6‐Mar‐12
0.00%
0.00%
ANODES
14.04%
65.00%
35.00%
18/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
BOUNCY TANKS
Total Budgete Units (Hrs)
R.W %
47488
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
43.61%
102
0.00%
0.00%
0.00%
0.00%
ACTUAL %
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
03-Sep-11
13-Dec-11
0.00%
0.00%
11872
25.00%
102
0.00%
0.00%
0.00%
3-Sep-11
13-Dec-11
0.00%
0.00%
PTJ9850
CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
408
3.44%
6
0.00%
0.00%
0.00%
3‐Sep‐11
8‐Sep‐11
0.00%
0.00%
PTJ9860
CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPORTS & STIFFENERS
816
6.87%
12
0.00%
0.00%
0.00%
3‐Sep‐11
15‐Sep‐11
0.00%
0.00%
PTJ9870
ROLLING OF BOUNCY TANK PLATE
720
6.06%
20
0.00%
0.00%
0.00%
10‐Sep‐11
2‐Oct‐11
0.00%
0.00%
PTJ9880
SEAM WELD & REROLLING OF BOUNCY TANK PLATE
2304
19.41%
24
0.00%
0.00%
0.00%
14‐Sep‐11
12‐Oct‐11
0.00%
0.00%
PTJ9890
ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUNCY TANK
3744
31.54%
24
0.00%
0.00%
0.00%
13‐Oct‐11
15‐Nov‐11
0.00%
0.00%
PTJ9900
GIRTH WELD OF BOUNCY TANK
3360
28.30%
24
0.00%
0.00%
0.00%
16‐Nov‐11
13‐Dec‐11
0.00%
0.00%
PTJ9910
ERECTION OF BOUNCY TANK WITH LEGS
520
4.38%
10
0.00%
0.00%
0.00%
16‐Nov‐11
27‐Nov‐11
0.00%
0.00%
AT LEG A1
11872
25.00%
102
0.00%
0.00%
0.00%
3-Sep-11
13-Dec-11
0.00%
0.00%
PTJ9920
CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
408
3.44%
6
0.00%
0.00%
0.00%
3‐Sep‐11
8‐Sep‐11
0.00%
0.00%
PTJ9930
CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPORTS & STIFFENERS
816
6.87%
12
0.00%
0.00%
0.00%
3‐Sep‐11
15‐Sep‐11
0.00%
0.00%
PTJ9940
ROLLING OF BOUNCY TANK PLATE
720
6.06%
20
0.00%
0.00%
0.00%
10‐Sep‐11
2‐Oct‐11
0.00%
0.00%
PTJ9950
SEAM WELD & REROLLING OF BOUNCY TANK PLATE
2304
19.41%
24
0.00%
0.00%
0.00%
14‐Sep‐11
12‐Oct‐11
0.00%
0.00%
PTJ9960
ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUNCY TANK
3744
31.54%
24
0.00%
0.00%
0.00%
13‐Oct‐11
15‐Nov‐11
0.00%
0.00%
PTJ9970
GIRTH WELD OF BOUNCY TANK
3360
28.30%
24
0.00%
0.00%
0.00%
16‐Nov‐11
13‐Dec‐11
0.00%
0.00%
PTJ9980
ERECTION OF BOUNCY TANK WITH LEGS
520
4.38%
10
0.00%
0.00%
0.00%
16‐Nov‐11
27‐Nov‐11
0.00%
0.00%
AT LEG A2
0.00%
11872
25.00%
102
0.00%
0.00%
0.00%
3-Sep-11
13-Dec-11
0.00%
0.00%
PTJ10010
CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPRTS & STIFFENERS
816
6.87%
12
0.00%
0.00%
0.00%
3‐Sep‐11
15‐Sep‐11
0.00%
0.00%
PTJ9990
CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
408
3.44%
6
0.00%
0.00%
0.00%
3‐Sep‐11
8‐Sep‐11
0.00%
0.00%
PTJ10020
ROLLING OF BOUNCY TANK PLATE
720
6.06%
20
0.00%
0.00%
0.00%
10‐Sep‐11
2‐Oct‐11
0.00%
0.00%
PTJ10030
SEAM WELD & REROLLING OF BOUNCY TANK PLATE
2304
19.41%
24
0.00%
0.00%
0.00%
14‐Sep‐11
12‐Oct‐11
0.00%
0.00%
PTJ10040
ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUNCY TANK
3744
31.54%
24
0.00%
0.00%
0.00%
13‐Oct‐11
15‐Nov‐11
0.00%
0.00%
PTJ10050
GIRTH WELD OF BOUNCY TANK
3360
28.30%
24
0.00%
0.00%
0.00%
16‐Nov‐11
13‐Dec‐11
0.00%
0.00%
PTJ10060
ERECTION OF BOUNCY TANK WITH LEGS
520
4.38%
10
0.00%
0.00%
0.00%
16‐Nov‐11
27‐Nov‐11
0.00%
0.00%
102
0.00%
0.00%
0.00%
3-Sep-11
13-Dec-11
0.00%
0.00%
AT LEG B1
0.00%
11872
25.00%
PTJ10070
CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
408
3.44%
6
0.00%
0.00%
0.00%
3‐Sep‐11
8‐Sep‐11
0.00%
0.00%
PTJ10080
CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPORTS & STIFFENERS
816
6.87%
12
0.00%
0.00%
0.00%
3‐Sep‐11
15‐Sep‐11
0.00%
0.00%
PTJ10090
ROLLING OF BOUNCY TANK PLATE
720
6.06%
20
0.00%
0.00%
0.00%
10‐Sep‐11
2‐Oct‐11
0.00%
0.00%
PTJ10100
SEAM WELD & REROLLING OF BOUNCY TANK PLATE
2304
19.41%
24
0.00%
0.00%
0.00%
14‐Sep‐11
12‐Oct‐11
0.00%
0.00%
PTJ10110
ERECTION OF SUPPORTS& STIFFENERS PLATE WITH BOUNCY TANK
3744
31.54%
24
0.00%
0.00%
0.00%
13‐Oct‐11
15‐Nov‐11
0.00%
0.00%
PTJ10120
GIRTH WELD OF BOUNCY TANK
3360
28.30%
24
0.00%
0.00%
0.00%
16‐Nov‐11
13‐Dec‐11
0.00%
0.00%
PTJ10130
ERECTION OF BOUNCY TANK WITH LEGS
520
4.38%
10
0.00%
0.00%
0.00%
16‐Nov‐11
27‐Nov‐11
0.00%
0.00%
2160
1.98%
40
0.00%
0.00%
0.00%
15-Jan-12
23-Feb-12
0.00%
0.00%
AT LEG B2
BALLASTING & GROUTING SYSTEM
0.00%
0.00%
19/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
6‐Feb‐12
0.00%
0.00%
OVERALL
ITEM
OVERALL
0.00%
0.00%
15‐Jan‐12
PTJ10790
BALASTING INSTALLATION
720
33.33%
20
0.00%
PTJ10970
GROUTING INSTALLATION ON ROW 1
720
33.33%
20
0.00%
0.00%
0.00%
15‐Jan‐12
6‐Feb‐12
0.00%
0.00%
PTJ10980
GROUTING INSTALLATION ON ROW 2
720
33.33%
20
0.00%
0.00%
0.00%
1‐Feb‐12
23‐Feb‐12
0.00%
0.00%
12000
11.02%
148
0.00%
0.00%
0.00%
0.00%
15-Sep-11
09-Feb-12
0.00%
0.00%
12000
100.00%
120
0.00%
0.00%
0.00%
0.00%
15‐Sep‐11
9‐Feb‐12
0.00%
0.00%
1152
1.06%
38
0.00%
0.00%
0.00%
0.00%
03-Sep-11
10-Oct-11
0.00%
0.00%
GRILLAGE & SEA FASTENING PTJ10800
GRILLAGE & SEA FASTENING FABRICATION
INSTALLATION AIDS PTJ10770
INSTALLATION AIDS FABRICATION
792
68.75%
22
0.00%
0.00%
0.00%
3‐Sep‐11
27‐Sep‐11
0.00%
0.00%
PTJ10780
INSTALLATION AIDS INSTALLATION
360
31.25%
10
0.00%
0.00%
0.00%
28‐Sep‐11
10‐Oct‐11
0.00%
0.00%
1152
1.06%
19
0.00%
0.00%
0.00%
14-Jan-12
01-Feb-12
0.00%
0.00%
PTJ9300
FITUP OF PREBENT CONDUCTOR
576
50.00%
8
0.00%
0.00%
0.00%
14‐Jan‐12
22‐Jan‐12
0.00%
0.00%
PTJ9310
WELDING OF PREBENT CONDUCTOR
576
50.00%
9
0.00%
0.00%
0.00%
23‐Jan‐12
1‐Feb‐12
0.00%
0.00%
3312
1.34%
163
0.00%
0.00%
0.00%
05‐Oct‐11
15‐Mar‐12
0.00%
0.00%
0 00% 0.00%
0 00% 0.00%
5 Oct 11 5‐Oct‐11
13 Oct 11 13‐Oct‐11
0 00% 0.00%
0 00% 0.00%
PREBENT CONDUCTOR
PAINTING
0.00%
0.00%
PTJ10320
SPLASH PAINTING FOR MISC MISC. (H.R, (H R STAIRS, STAIRS ...ETC) ETC)
168
5 07% 5.07%
7
0 00% 0.00%
PTJ10300
SPLASH PAINTING FOR ROW A
168
5.07%
7
0.00%
0.00%
0.00%
18‐Dec‐11
25‐Dec‐11
0.00%
0.00%
PTJ10310
SPLASH PAINTING FOR ROW B
168
5.07%
7
0.00%
0.00%
0.00%
22‐Dec‐11
29‐Dec‐11
0.00%
0.00%
PTJ10340
ATMOSPHERIC PAINTING FOR TOP ELEV
336
10.14%
7
0.00%
0.00%
0.00%
27‐Dec‐11
3‐Jan‐12
0.00%
0.00%
PTJ10280
SPLASH PAINTING FOR ROW 1
168
5.07%
7
0.00%
0.00%
0.00%
30‐Jan‐12
6‐Feb‐12
0.00%
0.00%
PTJ10330
PILE MARKING
1344
40.58%
28
0.00%
0.00%
0.00%
13‐Feb‐12
15‐Mar‐12
0.00%
0.00%
PTJ10260
SPLASH PAINTING FOR BOAT LAND
672
20.29%
14
0.00%
0.00%
0.00%
19‐Feb‐12
5‐Mar‐12
0.00%
0.00%
PTJ10290
SPLASH PAINTING FOR ROW 2
168
5.07%
7
0.00%
0.00%
0.00%
22‐Feb‐12
29‐Feb‐12
0.00%
0.00%
PTJ10270
SPLASH PAINTING FOR BARGE BUMPER
120
3.62%
5
0.00%
0.00%
0.00%
11‐Mar‐12
15‐Mar‐12
0.00%
0.00%
480
0.19%
11
0.00%
0.00%
0.00%
25‐Feb‐12
06‐Mar‐12
0.00%
0.00%
INSPECTION, TESTING & PRE‐COMMISIONING
0.00%
PTJ10990
RISER HYDRO TEST
160
33.33%
10
0.00%
0.00%
0.00%
25‐Feb‐12
6‐Mar‐12
0.00%
0.00%
PTJ11000
BALLASTING SYSTEM TEST
160
33.33%
10
0.00%
0.00%
0.00%
25‐Feb‐12
6‐Mar‐12
0.00%
0.00%
PTJ11010
GROUTING SYSTEM TEST
PILES FABRICATION
160
33.33%
10
0.00%
0.00%
0.00%
25‐Feb‐12
6‐Mar‐12
0.00%
0.00%
11872
4.52%
178
15.95%
0.72%
0.00%
0.00%
02‐Jul‐11
26‐Dec‐11
15.95%
0.72%
100.00%
0.00%
0.00%
0.00%
2‐Jul‐11
2‐Jul‐11
100.00%
0.00%
0.00%
0.00%
0.00%
26‐Dec‐11
26‐Dec‐11
0.00%
0.00%
51.48%
12.87%
0.00%
0.00%
02‐Jul‐11
05‐Sep‐11
51.48%
12.87%
PTJ2030
Piiles fabrication start
0
0.00%
0
PTJ10380
Piiles fabrication finish
0
0.00%
0
2968
25.00%
66
AT LEG A1 PTJ10390
Manual fitup & welding 8 joints
1440
48.52%
24
50.00%
24.26%
0.00%
0.00%
2‐Jul‐11
30‐Jul‐11
50.00%
24.26%
PTJ10420
Automatic welding 4 joints
576
19.41%
24
100.00%
19.41%
0.00%
0.00%
6‐Jul‐11
3‐Aug‐11
100.00%
19.41%
PTJ10430
back weld manual 4 joints
192
6.47%
16
100.00%
6.47%
0.00%
0.00%
17‐Jul‐11
4‐Aug‐11
100.00%
6.47%
PTJ10410
Welding beads (41 joints)
160
5.39%
10
25.00%
1.35%
0.00%
0.00%
4‐Aug‐11
15‐Aug‐11
25.00%
1.35%
20/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
PTJ10400
Activity Name Welding for manual joint (4 joints)
AT LEG A2
Total Budgete Units (Hrs)
R.W %
600
20.22%
10
2968
25.00%
102
Original Duration (Days)
ACTUAL % ITEM
0.00%
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
OVERALL
ITEM
OVERALL
0.00%
0.00%
0.00%
22‐Aug‐11
5‐Sep‐11
0.00%
0.00%
0.00%
0.00%
0.00%
02‐Jul‐11
11‐Oct‐11
0.00%
0.00%
PTJ10440
Manual fitup & welding 8 joints
1440
48.52%
24
0.00%
0.00%
0.00%
2‐Jul‐11
30‐Jul‐11
0.00%
0.00%
PTJ10450
Automatic welding 4 joints
576
19.41%
24
0.00%
0.00%
0.00%
11‐Aug‐11
11‐Sep‐11
0.00%
0.00%
PTJ10460
back weld manual 4 joints
192
6.47%
16
0.00%
0.00%
0.00%
22‐Aug‐11
12‐Sep‐11
0.00%
0.00%
PTJ10480
Welding beads (41 joints)
160
5.39%
10
0.00%
0.00%
0.00%
12‐Sep‐11
22‐Sep‐11
0.00%
0.00%
PTJ10470
Welding for manual joint (4 joints)
AT LEG B1
600
20.22%
10
0.00%
0.00%
0.00%
29‐Sep‐11
11‐Oct‐11
0.00%
0.00%
2968
25.00%
143
12.33%
3.08%
0.00%
0.00%
02‐Jul‐11
21‐Nov‐11
12.33%
3.08%
PTJ10490
Manual fitup & welding 8 joints
1440
48.52%
24
23.75%
11.52%
0.00%
0.00%
2‐Jul‐11
30‐Jul‐11
23.75%
11.52%
PTJ10500
Automatic welding 4 joints
576
19.41%
24
0.00%
0.00%
0.00%
0.00%
19‐Sep‐11
17‐Oct‐11
0.00%
0.00%
PTJ10510
back weld manual 4 joints
192
6.47%
16
0.00%
0.00%
0.00%
0.00%
29‐Sep‐11
18‐Oct‐11
0.00%
0.00%
PTJ10530
Welding beads (41 joints)
160
5.39%
10
15.00%
0.81%
0.00%
0.00%
18‐Oct‐11
29‐Oct‐11
15.00%
0.81%
PTJ10520
Welding for manual joint (4 joints)
0.00%
0.00%
0.00%
10‐Nov‐11 10 Nov 11
21‐Nov‐11 21 Nov 11
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
02‐Jul‐11
26‐Dec‐11
0.00%
0.00%
AT LEG B2
600
20.22%
10
2968
25.00%
178
PTJ10540
Manual fitup & welding 8 joints
1440
48.52%
24
0.00%
0.00%
0.00%
2‐Jul‐11
30‐Jul‐11
0.00%
0.00%
PTJ10550
Automatic welding 4 joints
576
19.41%
24
0.00%
0.00%
0.00%
25‐Oct‐11
27‐Nov‐11
0.00%
0.00%
PTJ10560
back weld manual 4 joints
192
6.47%
16
0.00%
0.00%
0.00%
10‐Nov‐11
28‐Nov‐11
0.00%
0.00%
PTJ10580
Welding beads (41 joints)
160
5.39%
10
0.00%
0.00%
0.00%
28‐Nov‐11
8‐Dec‐11
0.00%
0.00%
PTJ10570
Welding for manual joint (4 joints)
600
20.22%
10
0.00%
0.00%
0.00%
15‐Dec‐11
26‐Dec‐11
0.00%
0.00%
4484
1.71%
85
66.77%
1.14%
0.00%
0.00%
16‐Jul‐11
08‐Oct‐11
66.77%
1.14%
0
0.00%
0
100.00%
0.00%
0.00%
0.00%
16‐Jul‐11
16‐Jul‐11
100.00%
0.00%
6.69%
0.00%
0.00%
16‐Jul‐11
20‐Jul‐11
100.00%
6.69%
PRE‐DRILLING TEMPLATE PTD000
Pre‐drilling template fabrication start
PTJ10810
cutting & assembly of bottom plate
300
6.69%
5
100.00%
PTJ10900
fabrication of cones
1020
22.75%
15
100.00%
22.75%
0.00%
0.00%
16‐Jul‐11
2‐Aug‐11
100.00%
22.75%
PTJ10820
welding & NDT of bottom plate
240
5.35%
6
100.00%
5.35%
0.00%
0.00%
3‐Aug‐11
9‐Aug‐11
100.00%
5.35%
PTJ10830
cutting, rolling and assembly of outer frame
360
8.03%
6
100.00%
8.03%
0.00%
0.00%
3‐Aug‐11
9‐Aug‐11
100.00%
8.03%
PTJ10840
welding & NDT of outer frame
200
4.46%
5
95.00%
4.24%
0.00%
0.00%
10‐Aug‐11
15‐Aug‐11
95.00%
4.24%
PTJ10850
fabrication of beams ( built up section )
360
8.03%
10
95.00%
7.63%
0.00%
0.00%
16‐Aug‐11
27‐Aug‐11
95.00%
7.63%
PTJ10860
installation of beams with bottom frame
252
5.62%
7
55.00%
3.09%
0.00%
0.00%
28‐Aug‐11
7‐Sep‐11
55.00%
3.09%
PTJ10870
cutting of conductor pipe
120
2.68%
2
75.00%
2.01%
0.00%
0.00%
8‐Sep‐11
10‐Sep‐11
75.00%
2.01%
PTJ10920
fabrication of pad eyes
180
4.01%
5
35.00%
1.40%
0.00%
0.00%
8‐Sep‐11
13‐Sep‐11
35.00%
1.40%
PTJ10880
fabrication & installation of shims plates
144
3.21%
4
25.00%
PTJ10930
installation of pad eyes
180
4.01%
5
PTJ10890
installation of conductor pipe
180
4.01%
5
35.00%
0.80%
0.00%
0.00%
11‐Sep‐11
14‐Sep‐11
25.00%
0.80%
0.00%
0.00%
0.00%
14‐Sep‐11
19‐Sep‐11
0.00%
0.00%
1.40%
0.00%
0.00%
15‐Sep‐11
20‐Sep‐11
35.00%
1.40%
21/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP4 PROGRESS Sheet
Act ID
Activity Name
Total Budgete Units (Hrs)
R.W %
360
8.03%
Original Duration (Days)
ACTUAL % ITEM
PLANNED %
OVERALL
ITEM
OVERALL
0.00%
0.00%
0.00%
Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
18‐Sep‐11
28‐Sep‐11
0.00%
0.00%
PTJ10940
fabrication of lifting tool
PTJ10910
installation of cones
252
5.62%
7
3.37%
0.00%
0.00%
21‐Sep‐11
28‐Sep‐11
60.00%
3.37%
PTJ10950
painting of template
336
7.49%
7
0.00%
0.00%
0.00%
29‐Sep‐11
8‐Oct‐11
0.00%
0.00%
PTJ2010
Pre‐drilling template fabrication finish
0
0.00%
0
0.00%
0.00%
0.00%
8‐Oct‐11
8‐Oct‐11
0.00%
0.00%
10 60.00%
22/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL PROJECT : SETH DEVELOPMENT PROJECT Total Budgete Units (Hrs)
R.W %
165152
DECK FABRICATION General Activities
Activity Name
Act ID
W.P.5: DECK & TSF FABRICATION
25‐Jun‐11
DATE :
WK
WEEK NO.
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
396
16.82%
16.82%
15.01%
129068
78.15%
396
21.52%
16.82%
8768
6.79%
337
0.00% 100.00%
ACTUAL %
13
PLANNED %
DEV/ OVERALL
Start Date
Finish Date
DEV/ITEM
15.01%
31-Mar-11
29-Apr-12
1.81%
1.81%
19.20%
15.01%
31‐Mar‐11
29‐Apr‐12
2.32%
1.81%
0.00%
0.00%
0.00%
28‐May‐11
28‐Apr‐12
0.00%
0.00%
0.00%
100.00%
0.00%
28-May-11
28-May-11
0.00%
0.00%
0.00%
0.00%
0.00%
10-Aug-11
08-Dec-11
0.00%
0.00%
0.00%
0.00%
0.00%
03-Sep-11
03-Sep-11
100.00%
0.00%
PTJ2040
Deck primary structure fabrication start
0
0.00%
0
PTJ1150
Static equipment (by petrojet)
0
0.00%
120
PTJ2160
Deck secondray structure fabrication start
0
0.00%
0
PTJ1160
Piping & E&I supports (by petrojet)
0
0.00%
30
0.00%
0.00%
0.00%
16‐Nov‐11
16‐Dec‐11
0.00%
0.00%
PTJ2060
Deck pre-commisioning
6400
72.99%
40
0.00%
0.00%
0.00%
11-Feb-12
27-Mar-12
0.00%
0.00%
PTJ2090
Deck commisioning
2080
23.72%
26
0.00%
0.00%
0.00%
28-Mar-12
28-Apr-12
0.00%
0.00%
PTJ2065
Crane assembly and erection
0
0.00%
20
0.00%
0.00%
0.00%
28-Mar-12
21-Apr-12
0.00%
0.00%
PTJ2220
Deck weighing
288
3.28%
1
0.00%
0.00%
0.00%
21-Apr-12
22-Apr-12
0.00%
0.00%
104416
80.90%
395
26.60%
21.52%
23.74%
19.20%
31‐Mar‐11
29‐Apr‐12
2.86%
2.32%
3504
3.36%
56
100.00%
3.36%
100.00%
3.36%
31-Mar-11
25-May-11
0.00%
0.00%
22
100.00%
45.21%
100.00%
45.21%
31-Mar-11
27-Apr-11
0.00%
0.00%
Deck Structure Fabrication Deck Legs Fabrication
100.00%
PTD1000
Cutting & Assembly
1584
45.21%
PTD1005
Welding & NDT
1920
54.79%
30
100.00%
54.79%
100.00%
54.79%
19-Apr-11
25-May-11
0.00%
0.00%
728
0.70%
241
7.03%
0.05%
17.58%
0.12%
28-May-11
23-Jan-12
-10.55%
-0.07%
40.00%
7.03%
100.00%
17.58%
28-May-11
31-May-11
-60.00%
-10.55%
0.00%
0.00%
0.00%
05-Jan-12
12-Jan-12
0.00%
0.00%
Braces Below Cellar PTJD1020
Profiling Template
128
17.58%
4
PTD1030
Assembly
216
29.67%
6
PTD1040
Welding & NDT
384
52.75%
12
20912
20.03%
186
3776
18.06%
Cellar Deck Fabrication (+11.000) Joints Fabrication
0.00%
0.00%
0.00%
10-Jan-12
23-Jan-12
0.00%
0.00%
44.70%
8.95%
45.70%
9.15%
28-May-11
29-Nov-11
-1.00%
-0.20%
30
86.02%
15.53%
97.85%
17.67%
28-May-11
26-Jun-11
-11.83%
-2.14%
16
100.00%
44.07%
100.00%
44.07%
28-May-11
14-Jun-11
0.00%
0.00%
75.00%
41.95%
96.15%
53.78%
01-Jun-11
26-Jun-11
-21.15%
-11.83%
PTD1050
Cutting & Assembly
1664
44.07%
PTD1060
Welding & NDT
2112
55.93%
22
10784
51.57%
61
45.40%
23.41%
54.36%
28.03%
28-May-11
27-Jul-11
-8.96%
-4.62%
4896
45.40%
36
100.00%
45.40%
70.73%
32.11%
28-May-11
7-Jul-11
29.27%
13.29%
Main Beams Fabrication PTD1070
Cutting & Assembly
23/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
PTD1080
Welding & NDT
Secondary Beams Fabrication
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
PLANNED % Start Date
ITEM
OVERALL
ITEM
OVERALL
Finish Date
DEV/ITEM
DEV/ OVERALL
5888
54.60%
46
0.00%
40.74%
22.24%
4-Jun-11
27-Jul-11
-40.74%
-22.24%
3376
16.14%
40
35.66%
5.76%
0.00%
0.00%
3-Sep-11
12-Oct-11
35.66%
5.76%
76.00%
35.66%
0.00%
0.00%
03-Sep-11
27-Sep-11
76.00%
35.66%
0.00%
0.00%
0.00%
10-Sep-11
12-Oct-11
0.00%
0.00%
0.00%
0.00%
0.00%
13-Oct-11
29-Nov-11
0.00%
0.00%
PTD1090
Cutting & Assembly
1584
46.92%
22
PTD1100
Welding & NDT
1792
53.08%
28
2976
14.23%
48
Embossed Plates
ACTUAL %
0.00%
PTD1110
Cutting & Assembly
1440
48.39%
20
0.00%
0.00%
0.00%
13-Oct-11
10-Nov-11
0.00%
0.00%
PTD1120
Welding & NDT
1536
51.61%
24
0.00%
0.00%
0.00%
27-Oct-11
29-Nov-11
0.00%
0.00%
716
0.69%
19
34.36%
0.24%
0.00%
0.00%
03‐Sep‐11
21‐Sep‐11
34.36%
0.24%
236
32.96%
8
49.32%
16.26%
0.00%
0.00%
03-Sep-11
10-Sep-11
49.32%
16.26%
PLAN AT EL. + 9.200 Main Beams Fabrication PTD1710
Cutting & Assembly
108
45.76%
3
90.00%
41.19%
0.00%
0.00%
03-Sep-11
05-Sep-11
90.00%
41.19%
PTD1720
Welding & NDT
128
54.24%
4
15.00%
8.14%
0.00%
0.00%
06-Sep-11
10-Sep-11
15.00%
8.14%
240
33.52%
5
54.00%
18.10%
0.00%
0.00%
11-Sep-11
15-Sep-11
54.00%
18.10%
90.00%
54.00%
0.00%
0.00%
11-Sep-11
12-Sep-11
90.00%
54.00%
0.00%
0.00%
0.00%
13-Sep-11
15-Sep-11
0.00%
0.00%
0.00%
0.00%
0.00%
17-Sep-11
21-Sep-11
0.00%
0.00%
Secondary Beams Fabrication PTD1730
Cutting & Assembly
144
60.00%
2
PTD1740
Welding & NDT
96
40.00%
3
240
33.52%
5
GRATING
0.00%
PTD1750
Cutting & Assembly
144
60.00%
2
0.00%
0.00%
0.00%
17-Sep-11
18-Sep-11
0.00%
0.00%
PTD1760
Welding & NDT
96
40.00%
3
0.00%
0.00%
0.00%
19-Sep-11
21-Sep-11
0.00%
0.00%
1824
1.75%
44
33.95%
0.59%
0.00%
0.00%
03‐Sep‐11
16‐Oct‐11
33.95%
0.59%
1184
64.91%
20
41.35%
26.84%
0.00%
0.00%
03-Sep-11
22-Sep-11
41.35%
26.84%
90.00%
41.35%
0.00%
0.00%
3-Sep-11
11-Sep-11
90.00%
41.35%
0.00%
0.00%
0.00%
12-Sep-11
22-Sep-11
0.00%
0.00%
PLAN AT EL. + 9.700 Main Beams Fabrication PTD1630
Cutting & Assembly
544
45.95%
8
PTD1640
Welding & NDT
640
54.05%
10
336
18.42%
11
38.57%
7.11%
0.00%
0.00%
24-Sep-11
04-Oct-11
38.57%
7.11%
90.00%
38.57%
0.00%
0.00%
24-Sep-11
27-Sep-11
90.00%
38.57%
0.00%
0.00%
0.00%
28-Sep-11
4-Oct-11
0.00%
0.00%
0.00%
0.00%
0.00%
05-Oct-11
16-Oct-11
0.00%
0.00%
Secondary Beams Fabrication PTD1650
Cutting & Assembly
144
42.86%
4
PTD1660
Welding & NDT
192
57.14%
6
304
16.67%
12
GRATING
0.00%
PTD1670
Cutting & Assembly
144
47.37%
4
0.00%
0.00%
0.00%
5-Oct-11
10-Oct-11
0.00%
0.00%
PTD1680
Welding & NDT
160
52.63%
5
0.00%
0.00%
0.00%
11-Oct-11
16-Oct-11
0.00%
0.00%
2704
2.59%
71
0.00%
0.00%
0.00%
03‐Sep‐11
12‐Nov‐11
0.00%
0.00%
WELL HEAD MEZZANINE AT (+ 16.000)
0.00%
24/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
Joints Fabrication
Total Budgete Units (Hrs)
R.W %
548
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
20.27%
12
0.00%
0.00%
0.00%
ACTUAL %
PLANNED % DEV/ITEM
DEV/ OVERALL
Start Date
Finish Date
0.00%
03-Sep-11
14-Sep-11
0.00%
0.00%
PTD1530
Cutting & Assembly
260
47.45%
5
0.00%
0.00%
0.00%
3-Sep-11
7-Sep-11
0.00%
0.00%
PTD1540
Welding & NDT
288
52.55%
6
0.00%
0.00%
0.00%
8-Sep-11
14-Sep-11
0.00%
0.00%
1380
51.04%
26
0.00%
0.00%
0.00%
15-Sep-11
10-Oct-11
0.00%
0.00%
Main Beams Fabrication
0.00%
PTD1550
Cutting & Assembly
612
44.35%
9
0.00%
0.00%
0.00%
15‐Sep‐11
25‐Sep‐11
0.00%
0.00%
PTD1560
Welding & NDT
768
55.65%
12
0.00%
0.00%
0.00%
26-Sep-11
10-Oct-11
0.00%
0.00%
404
14.94%
14
0.00%
0.00%
0.00%
11-Oct-11
24-Oct-11
0.00%
0.00%
Secondary Beams Fabrication
0.00%
PTD1570
Cutting & Assembly
180
44.55%
5
0.00%
0.00%
0.00%
11-Oct-11
16-Oct-11
0.00%
0.00%
PTD1580
Welding & NDT
224
55.45%
7
0.00%
0.00%
0.00%
17‐Oct‐11
24‐Oct‐11
0.00%
0.00%
372
13.76%
19
0.00%
0.00%
0.00%
25-Oct-11
12-Nov-11
0.00%
0.00%
GRATING
0.00%
PTD1590
C tti & A bl Cutting & Assembly
180
48 39% 48.39%
5
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
25 O t 11 25-Oct-11
30 O t 11 30-Oct-11
0 00% 0.00%
0 00% 0.00%
PTD1600
Welding & NDT
192
51.61%
6
0.00%
0.00%
0.00%
31-Oct-11
12-Nov-11
0.00%
0.00%
6592
6.31%
187
0.00%
27.18%
1.72%
28-May-11
30-Nov-11
-27.18%
-1.72%
28-May-11
12-Jun-11
-100.00%
-27.18%
Braces & Legs between Cellar and Main
0.00%
PTD1130
Profiling Template
1792
27.18%
14
0.00%
100.00%
27.18%
PTD1140
Assembly
1728
26.21%
24
0.00%
0.00%
0.00%
4-Oct-11
1-Nov-11
0.00%
0.00%
PTD1150
Welding & NDT
3072
46.60%
32
0.00%
0.00%
0.00%
19-Oct-11
30-Nov-11
0.00%
0.00%
21696
20.78%
170
37.79%
7.85%
28.38%
5.90%
28-May-11
13-Nov-11
9.41%
1.96%
4576
21.09%
53
78.18%
16.49%
56.36%
11.89%
28-May-11
19-Jul-11
21.82%
4.60%
2080
45.45%
20
100.00%
45.45%
100.00%
45.45%
28-May-11
19-Jun-11
0.00%
0.00%
Main Deck Fabrication (+17.000) Joints Fabrication PTD1160
Cutting & Assembly
PTD1170
Welding & NDT
Main Beams Fabrication
2496
54.55%
26
60.00%
32.73%
20.00%
10.91%
20-Jun-11
19-Jul-11
40.00%
21.82%
11040
50.88%
80
35.48%
18.05%
32.41%
16.49%
30-May-11
17-Aug-11
3.06%
1.56%
80.00%
35.48%
64.29%
28.51%
30‐May‐11
10‐Jul‐11
15.71%
6.97%
0.00%
7.02%
3.91%
22-Jun-11
17-Aug-11
-7.02%
-3.91%
PTD1180
Cutting & Assembly
4896
44.35%
36
PTD1190
Welding & NDT
6144
55.65%
48
3104
14.31%
38
22.73%
3.25%
0.00%
0.00%
3-Sep-11
10-Oct-11
22.73%
3.25%
PTD1200
Cutting & Assembly
1440
46.39%
20
49.00%
22.73%
0.00%
0.00%
3-Sep-11
25-Sep-11
49.00%
22.73%
PTD1210
Welding & NDT
1664
53.61%
26
0.00%
0.00%
0.00%
10-Sep-11
10-Oct-11
0.00%
0.00%
2976
13.72%
50
0.00%
0.00%
0.00%
25-Sep-11
13-Nov-11
0.00%
0.00%
Secondary Beams Fabrication
Embossed Plates
0.00%
PTD1220
Cutting & Assembly
1440
48.39%
20
0.00%
0.00%
0.00%
25-Sep-11
18-Oct-11
0.00%
0.00%
PTD1230
Welding & NDT
1536
51.61%
24
0.00%
0.00%
0.00%
11‐Oct‐11
13‐Nov‐11
0.00%
0.00%
2048
1.96%
255
0.00%
25.00%
0.49%
28-May-11
6-Feb-12
-25.00%
-0.49%
Braces & Legs Above Main
0.00%
25/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED %
OVERALL
ITEM
OVERALL
Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
PTD1240
Profiling Template
512
25.00%
8
0.00%
100.00%
25.00%
28-May-11
5-Jun-11
-100.00%
-25.00%
PTD1250
Assembly
576
28.13%
8
0.00%
0.00%
0.00%
24‐Jan‐12
1‐Feb‐12
0.00%
0.00%
PTD1260
Welding & NDT
960
46.88%
10
0.00%
0.00%
0.00%
26‐Jan‐12
6‐Feb‐12
0.00%
0.00%
3.78%
15.09%
1.35%
28-May-11
20-Dec-11
27.20%
2.43%
9328
8.93%
207
42.29%
PTD1270
Profiling Template
1408
15.09%
22
92.00%
13.89%
100.00%
15.09%
28‐May‐11
21‐Jun‐11
‐8.00%
‐1.21%
PTD1280
Assembly
2880
30.87%
40
92.00%
28.40%
0.00%
0.00%
18‐Oct‐11
8‐Dec‐11
92.00%
28.40%
PTD1290
Welding & NDT
5040
54.03%
35
0.00%
0.00%
0.00%
10‐Nov‐11
20‐Dec‐11
0.00%
0.00%
9440
9.04%
136
19.73%
1.78%
0.00%
0.00%
07-Aug-11
20-Dec-11
19.73%
1.78%
704
7.46%
33
50.91%
3.80%
0.00%
0.00%
7‐Aug‐11
8‐Sep‐11
50.91%
3.80%
Braces Below Heli Deck
Heli Deck Fabrication (+29.125) Joints Fabrication PTD1300
Cutting & Assembly
320
45.45%
8
100.00%
45.45%
0.00%
0.00%
7‐Aug‐11
15‐Aug‐11
100.00%
45.45%
PTD1310
Welding & NDT
384
54.55%
12
10.00%
5.45%
0.00%
0.00%
23‐Aug‐11
8‐Sep‐11
10.00%
5.45%
1408
14.92%
38
45.45%
6.78%
0.00%
0.00%
16‐Aug‐11
22‐Sep‐11
45.45%
6.78%
PTD1320
Cutting & Assembly
640
45 45% 45.45%
16
100 00% 100.00%
45 45% 45.45%
0 00% 0.00%
0 00% 0.00%
16 Aug 11 16‐Aug‐11
6 Sep 11 6‐Sep‐11
100 00% 100.00%
45 45% 45.45%
PTD1330
Welding & NDT
768
54.55%
24
0.00%
0.00%
0.00%
23‐Aug‐11
22‐Sep‐11
0.00%
0.00%
3776
40.00%
45
22.88%
9.15%
0.00%
0.00%
3‐Sep‐11
17‐Oct‐11
22.88%
9.15%
50.00%
22.88%
0.00%
0.00%
3‐Sep‐11
29‐Sep‐11
50.00%
22.88%
0.00%
0.00%
0.00%
10‐Sep‐11
17‐Oct‐11
0.00%
0.00%
0.00%
0.00%
0.00%
12‐Oct‐11
20‐Nov‐11
0.00%
0.00%
Main Beams Fabrication
Secondary Beams Fabrication PTD1340
Cutting & Assembly
1728
45.76%
24
PTD1350
Welding & NDT
2048
54.24%
32
2832
30.00%
40
Covering Plates
0.00%
PTD1360
Cutting & Assembly
1296
45.76%
18
0.00%
0.00%
0.00%
12‐Oct‐11
1‐Nov‐11
0.00%
0.00%
PTD1370
Welding & NDT
1536
54.24%
24
0.00%
0.00%
0.00%
18‐Oct‐11
20‐Nov‐11
0.00%
0.00%
472
5.00%
16
PTD1380
Cutting & Assembly
216
45.76%
6
PTD1390
Welding & NDT
Gutter
Landing Area
256
54.24%
8
248
2.63%
30
0.00%
0.00%
0.00%
0.00%
0.00%
21‐Nov‐11
6‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
21‐Nov‐11
27‐Nov‐11
0.00%
0.00%
0.00%
0.00%
0.00%
28‐Nov‐11
6‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
21‐Nov‐11
20‐Dec‐11
0.00%
0.00%
PTD1400
Cutting & Assembly
120
48.39%
6
0.00%
0.00%
0.00%
21‐Nov‐11
27‐Nov‐11
0.00%
0.00%
PTD1410
Welding & NDT
128
51.61%
8
0.00%
0.00%
0.00%
12‐Dec‐11
20‐Dec‐11
0.00%
0.00%
Misellaneuos
15820
15.15%
162
0.00%
0.00%
0.00%
0.00%
19-Nov-11
29-Apr-12
0.00%
0.00%
Fabrication
10656
67.36%
155
0.00%
0.00%
0.00%
0.00%
19‐Nov‐11
22‐Apr‐12
0.00%
0.00%
PTMD1010
Handrails & Cups
1536
14.41%
24
0.00%
0.00%
0.00%
19‐Nov‐11
15‐Dec‐11
0.00%
0.00%
PTMD1060
Safety Net
1792
16.82%
28
0.00%
0.00%
0.00%
21‐Nov‐11
22‐Dec‐11
0.00%
0.00%
PTMD1040
Monorail Beam
720
6.76%
10
0.00%
0.00%
0.00%
30‐Nov‐11
11‐Dec‐11
0.00%
0.00%
PTMD1020
Hatches
640
6.01%
20
0.00%
0.00%
0.00%
22‐Dec‐11
15‐Jan‐12
0.00%
0.00%
PTMD1090
Fire Wall
2448
22.97%
18
0.00%
0.00%
0.00%
25‐Dec‐11
15‐Jan‐12
0.00%
0.00%
26/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED %
OVERALL
ITEM
OVERALL
Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
PTMD1050
Name Plate
256
2.40%
8
0.00%
0.00%
0.00%
2‐Jan‐12
11‐Jan‐12
0.00%
0.00%
PTMD1000
Stairs & Walkways
2400
22.52%
24
0.00%
0.00%
0.00%
3‐Jan‐12
31‐Jan‐12
0.00%
0.00%
PTMD1030
Crane Boom Rest
192
1.80%
6
0.00%
0.00%
0.00%
9‐Jan‐12
15‐Jan‐12
0.00%
0.00%
PTMD1070
Pad Eyes
672
6.31%
6
0.00%
0.00%
0.00%
15‐Apr‐12
22‐Apr‐12
0.00%
0.00%
5164
32.64%
139
0.00%
0.00%
0.00%
12‐Dec‐11
29‐Apr‐12
0.00%
0.00% 0.00%
Installation
0.00%
PTMD1140
Monorail Beam
360
6.97%
10
0.00%
0.00%
0.00%
12‐Dec‐11
22‐Dec‐11
0.00%
PTMD1110
Handrails & Cups
864
16.73%
24
0.00%
0.00%
0.00%
2‐Jan‐12
30‐Jan‐12
0.00%
0.00%
PTMD1160
Safety Net
1152
22.31%
16
0.00%
0.00%
0.00%
4‐Jan‐12
23‐Jan‐12
0.00%
0.00%
PTMD1100
Stairs & Walkways
1080
20.91%
15
0.00%
0.00%
0.00%
24‐Jan‐12
9‐Feb‐12
0.00%
0.00%
PTMD1120
Hatches
288
5.58%
8
0.00%
0.00%
0.00%
24‐Jan‐12
1‐Feb‐12
0.00%
0.00%
PTMD1130
Crane Boom Rest
72
1.39%
2
0.00%
0.00%
0.00%
24‐Jan‐12
25‐Jan‐12
0.00%
0.00%
PTMD1150
Name Plate
144
2.79%
4
0.00%
0.00%
0.00%
24‐Jan‐12
28‐Jan‐12
0.00%
0.00%
PTMD1190
Fire Wall
864
16.73%
12
0.00%
0.00%
0.00%
24‐Jan‐12
6‐Feb‐12
0.00%
0.00%
PTMD1170
Pad Eyes
340
6.58%
5
0.00%
0.00%
0.00%
22‐Apr‐12
29‐Apr‐12
0.00%
0.00%
952
0.91%
79
0.00%
0.00%
0.00%
24‐Jan‐12
11‐Apr‐12
0.00%
0.00%
Deck Flare
0.00%
PTD1500
Cutting & Assembly
400
42.02%
20
0.00%
0.00%
0.00%
24‐Jan‐12
15‐Feb‐12
0.00%
0.00%
PTD1510
Welding & NDT
512
53.78%
32
0.00%
0.00%
0.00%
16‐Feb‐12
24‐Mar‐12
0.00%
0.00%
PTD1520
Trial Fit
40
4.20%
2
0.00%
0.00%
0.00%
10‐Apr‐12
11‐Apr‐12
0.00%
0.00%
8152
7.81%
241
0.00%
0.00%
21.20%
1.65%
28‐May‐11
23‐Jan‐12
‐21.20%
‐1.65%
1728
21.20%
27
0.00%
0.00%
100.00%
21.20%
28‐May‐11
23‐Jun‐11
‐100.00%
‐21.20%
1728
100.00%
24
0.00%
100.00%
100.00%
28‐May‐11
23‐Jun‐11
‐100.00%
‐100.00%
304
3.73%
2
0.00%
0.00%
0.00%
17‐Dec‐11
18‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
17‐Dec‐11
18‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
19‐Dec‐11
4‐Jan‐12
0.00%
0.00%
Deck Assembly Skid Beams & Shoes Preparation PTD1420
Skid Beams & Shoes Preparation
Lifting Deck Legs Over Skid Beams & Skid Shoes PTD1430
Lifting Deck Legs Over Skid Beams & Skid Shoes
Lifting Cellar Deck Over Deck Legs
304
100.00%
2
1584
19.43%
17
0.00%
0.00%
PTD1440
Lifting
592
37.37%
1
0.00%
0.00%
0.00%
19‐Dec‐11
19‐Dec‐11
0.00%
0.00%
PTD1450
Assembly
480
30.30%
6
0.00%
0.00%
0.00%
20‐Dec‐11
26‐Dec‐11
0.00%
0.00%
PTD1460
Welding & NDT
512
32.32%
8
0.00%
0.00%
0.00%
27‐Dec‐11
4‐Jan‐12
0.00%
0.00%
692
8.49%
6
0.00%
0.00%
0.00%
5‐Jan‐12
10‐Jan‐12
0.00%
0.00%
lifting of plan at + 9.2
0.00%
PTD1700
Lifting
592
85.55%
1
0.00%
0.00%
0.00%
5‐Jan‐12
5‐Jan‐12
0.00%
0.00%
PTD1770
Assembly
36
5.20%
1
0.00%
0.00%
0.00%
8‐Jan‐12
8‐Jan‐12
0.00%
0.00%
PTD1780
Welding & NDT
64
9.25%
2
0.00%
0.00%
0.00%
9‐Jan‐12
10‐Jan‐12
0.00%
0.00%
692
8.49%
6
592
85.55%
1
lifting of plan at + 9.7 PTD1610
Lifting
0.00%
0.00%
0.00%
0.00%
5‐Jan‐12
10‐Jan‐12
0.00%
0.00%
0.00%
0.00%
0.00%
5‐Jan‐12
5‐Jan‐12
0.00%
0.00%
27/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL %
PLANNED % Start Date
ITEM
OVERALL
ITEM
OVERALL
Finish Date
DEV/ITEM
DEV/ OVERALL
PTD1620
Assembly
36
5.20%
1
0.00%
0.00%
0.00%
8‐Jan‐12
8‐Jan‐12
0.00%
0.00%
PTD1690
Welding & NDT
64
9.25%
2
0.00%
0.00%
0.00%
9‐Jan‐12
10‐Jan‐12
0.00%
0.00%
800
9.81%
6
lifting of mezzanine deck at + 16
0.00%
0.00%
0.00%
5‐Jan‐12
10‐Jan‐12
0.00%
0.00%
1
0.00%
0.00%
0.00%
5‐Jan‐12
5‐Jan‐12
0.00%
0.00%
10.00%
1
0.00%
0.00%
0.00%
8‐Jan‐12
8‐Jan‐12
0.00%
0.00%
128
16.00%
2
0.00%
0.00%
0.00%
9‐Jan‐12
10‐Jan‐12
0.00%
0.00%
2352
28.85%
13
0.00%
0.00%
0.00%
11‐Jan‐12
23‐Jan‐12
0.00%
0.00%
PTD1790
Lifting
592
74.00%
PTD1800
Assembly
80
PTD1810
Welding & NDT
Lifting Main Deck Over cellar Deck
0.00%
0.00%
PTD1470
Lifting
736
31.29%
1
0.00%
0.00%
0.00%
11‐Jan‐12
11‐Jan‐12
0.00%
0.00%
PTD1480
Assembly
720
30.61%
5
0.00%
0.00%
0.00%
12‐Jan‐12
17‐Jan‐12
0.00%
0.00%
PTD1490
Welding & NDT
896
38.10%
7
0.00%
0.00%
0.00%
16‐Jan‐12
23‐Jan‐12
0.00%
0.00%
15548
12.05%
201
0.00%
0.00%
0.00%
22‐Sep‐11
09‐Apr‐12
0.00%
0.00%
Atmosphric Painting
0.00%
PT1110
Plane at + 9.2
960
6.17%
5
0.00%
0.00%
0.00%
22‐Sep‐11
27‐Sep‐11
0.00%
0.00%
PT1120
97 Plane at + 9.7
960
6 17% 6.17%
5
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
17 Oct 11 17‐Oct‐11
22 Oct 11 22‐Oct‐11
0 00% 0.00%
0 00% 0.00%
PT1130
Wellhead mezzanine
1920
12.35%
10
0.00%
0.00%
0.00%
13‐Nov‐11
23‐Nov‐11
0.00%
0.00%
PT1030
Cellar Deck & Braces Above Cellar
2880
18.52%
15
0.00%
0.00%
0.00%
1‐Dec‐11
18‐Dec‐11
0.00%
0.00%
PT1080
Piping Support
108
0.69%
9
0.00%
0.00%
0.00%
6‐Dec‐11
17‐Dec‐11
0.00%
0.00%
PT1010
Deck Legs
432
2.78%
6
0.00%
0.00%
0.00%
10‐Dec‐11
15‐Dec‐11
0.00%
0.00%
PT1020
Braces Below Cellar
120
0.77%
5
0.00%
0.00%
0.00%
13‐Dec‐11
18‐Dec‐11
0.00%
0.00%
PT1050
Heli Deck & Braces Below Heli
1728
11.11%
12
0.00%
0.00%
0.00%
21‐Dec‐11
3‐Jan‐12
0.00%
0.00%
PT1040
Main Deck
2880
18.52%
15
0.00%
0.00%
0.00%
24‐Dec‐11
10‐Jan‐12
0.00%
0.00%
PT1090
Cable Trays Supports
120
0.77%
10
0.00%
0.00%
0.00%
11‐Jan‐12
23‐Jan‐12
0.00%
0.00%
PT1045
Braces Above Main
80
0.51%
5
0.00%
0.00%
0.00%
18‐Jan‐12
23‐Jan‐12
0.00%
0.00%
PT1070
Piping painting
1008
6.48%
14
0.00%
0.00%
0.00%
18‐Jan‐12
4‐Feb‐12
0.00%
0.00%
PT1060
Miscellaneous (Stairs,H/R,...etc)
1344
8.64%
14
0.00%
0.00%
0.00%
22‐Jan‐12
6‐Feb‐12
0.00%
0.00%
PT1100
Deck Flare
1008
6.48%
14
0.00%
0.00%
0.00%
25‐Mar‐12
9‐Apr‐12
0.00%
0.00%
336
0.26%
9
0.00%
0.00%
0.00%
21‐Apr‐12
29‐Apr‐12
0.00%
0.00%
336
100.00%
7
0.00%
0.00%
0.00%
21‐Apr‐12
29‐Apr‐12
0.00%
0.00%
13280
8.04%
84
0.00%
0.00%
0.00%
16‐Dec‐11
09‐Mar‐12
0.00%
0.00%
Anti Skid Painting PT1000
Heli Deck
E&I
0.00%
0.00%
PTJ2080
E & I Work start
0
0.00%
0
0.00%
0.00%
0.00%
16‐Dec‐11
16‐Dec‐11
0.00%
0.00%
PTJ2100
E & I Work finish
0
0.00%
0
0.00%
0.00%
0.00%
9‐Mar‐12
9‐Mar‐12
0.00%
0.00%
13280
100.00%
84
0.00%
0.00%
0.00%
0.00%
16‐Dec‐11
09‐Mar‐12
0.00%
0.00%
6424
48.37%
84
0.00%
0.00%
0.00%
0.00%
16-Dec-11
09-Mar-12
0.00%
0.00%
E&I (onshore) Instrumentation
28/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM 0.00%
ACTUAL %
PLANNED % Start Date
OVERALL
ITEM
Finish Date
DEV/ITEM
OVERALL
DEV/ OVERALL
1336
20.80%
52
0.00%
0.00%
0.00%
16‐Dec‐11
6‐Feb‐12
0.00%
0.00%
E&I1090
Fabrication
832
62.28%
26
0.00%
0.00%
0.00%
16‐Dec‐11
11‐Jan‐12
0.00%
0.00%
E&I1100
Installation
504
37.72%
14
0.00%
0.00%
0.00%
23-Jan-12
06-Feb-12
0.00%
0.00%
1248
19.43%
26
0.00%
0.00%
0.00%
23‐Jan‐12
18‐Feb‐12
0.00%
0.00%
1248
100.00%
26
0.00%
0.00%
0.00%
23‐Jan‐12
18‐Feb‐12
0.00%
0.00%
800
12.45%
20
0.00%
0.00%
0.00%
10‐Feb‐12
1‐Mar‐12
0.00%
0.00%
Installation
800
100.00%
20
0.00%
0.00%
0.00%
10‐Feb‐12
1‐Mar‐12
0.00%
0.00%
HCU & Local Panels Activities
256
3.99%
16
256
100.00%
16
720
11.21%
18
720
100.00%
18
320
4.98%
20
320
100 00% 100.00%
20
160
2.49%
10
160
100.00%
10
128
1.99%
8
128
100.00%
8
1200
18.68%
25
1200
100.00%
25
128
1.99%
8
Cable Trays Supports
Cable Trays E&I1110
Installation
Tubing Activities E&I1120
E&I1130
HCU & Local Panels Activities
Fusible Plug & ESD Puch Bottons E&I1140
Fusible Plug & ESD Puch Bottons
J. Box Activities E&I1150
J Box Activities J.
Instrument Installation & Calibration E&I1160
Instrument Installation & Calibration
Air Gas Header E&I1170
Air Gas Header
Cable Laying & Termination E&I1180
Cable Laying & Termination
Fire & Gas activities E&I1190
Fire & Gas activities
Telecommunication System E&I1200
Telecommunication System
Electrical Cable Trays Supports
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
6‐Feb‐12
24‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
6‐Feb‐12
24‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
6‐Feb‐12
26‐Feb‐12
0.00%
0.00%
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
6 Feb 12 6‐Feb‐12
26 Feb 12 26‐Feb‐12
0 00% 0.00%
0 00% 0.00%
0.00%
0.00%
0.00%
25‐Feb‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
25‐Feb‐12
6‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
24‐Feb‐12
3‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
24‐Feb‐12
3‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
12‐Feb‐12
8‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
12‐Feb‐12
8‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1‐Mar‐12
9‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
1‐Mar‐12
9‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1-Mar-12
9-Mar-12
0.00%
0.00%
0.00%
0.00%
0.00%
1-Mar-12
9-Mar-12
0.00%
0.00%
0.00%
0.00%
16-Dec-11
01-Mar-12
0.00%
0.00%
8
6856
51.63%
76
0.00%
0.00%
1336
19.49%
52
0.00%
0.00%
0.00%
0.00%
16-Dec-11
6-Feb-12
0.00%
0.00%
26
0.00%
0.00%
0.00%
16‐Dec‐11
11‐Jan‐12
0.00%
0.00%
0.00%
0.00%
0.00%
23‐Jan‐12
6‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
23-Jan-12
18-Feb-12
0.00%
0.00%
0.00%
0.00%
0.00%
23‐Jan‐12
18‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
16-Dec-11
23-Jan-12
0.00%
0.00%
0.00%
0.00%
0.00%
16‐Dec‐11
23‐Jan‐12
0.00%
0.00%
0.00%
0.00%
0.00%
31-Dec-11
25-Jan-12
0.00%
0.00%
0.00%
0.00%
0.00%
31‐Dec‐11
25‐Jan‐12
0.00%
0.00%
14
1248
18.20%
26
1248
100.00%
26
912
13.30%
38
912
100.00%
38
1000
14.59%
25
1000
100.00%
25
Lighting Activities
0.00%
5‐Mar‐12
100.00%
37.72%
E&I1040
0.00%
5‐Mar‐12
128
504
Lighting Activities
0.00%
18‐Feb‐12 18‐Feb‐12
8
Installation
Installation
0.00%
0.00% 0.00%
8
E&I1010
E&I1030
0.00%
0.00% 0.00%
1.99%
832
Conduit Activities
0.00%
0.00% 0.00%
100.00%
Fabrication
Installation
0.00%
128
62.28%
E&I1020
0.00%
128
E&I1000
Cable Trays
0.00%
0.00%
0.00%
0.00%
29/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP5 PROGRESS Sheet
Activity Name
Act ID
Navigation Aids E&I1050
Navigation Aids
Earthing Activities E&I1060
Earthing Activities
Power & Small Equip. Inst. E&I1070
Power & Small Equip. Inst.
Cable Laying & Termination E&I1080
Cable Laying & Termination
EQUIPMENT
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ITEM
OVERALL
0.00%
240
3.50%
15
240
100.00%
15
280
4.08%
14
280
100.00%
14
240
3.50%
12
240
100.00%
12
1600
23.34%
25
1600
100.00%
25
5232
3.17%
71
ACTUAL %
0.00%
0.00%
0.00%
0.00%
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
ITEM
OVERALL
0.00%
0.00%
0.00%
16-Dec-11
31-Dec-11
0.00%
0.00%
0.00%
0.00%
0.00%
16‐Dec‐11
31‐Dec‐11
0.00%
0.00%
0.00%
0.00%
0.00%
16-Feb-12
1-Mar-12
0.00%
0.00%
0.00%
0.00%
0.00%
16‐Feb‐12
1‐Mar‐12
0.00%
0.00%
0.00%
0.00%
0.00%
16-Feb-12
28-Feb-12
0.00%
0.00%
0.00%
0.00%
0.00%
16‐Feb‐12
28‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
31-Jan-12
25-Feb-12
0.00%
0.00%
0.00%
0.00%
0.00%
31‐Jan‐12
25‐Feb‐12
0.00%
0.00%
0.00%
0.00%
0.00%
07‐Dec‐11
16‐Feb‐12
0.00%
0.00%
PTJ2070
Equipment installation start
0
0.00%
0
0.00%
0.00%
0.00%
23-Dec-11
23-Dec-11
0.00%
0.00%
PTJ2130
Equipment installation finish
0
0.00%
0
0.00%
0.00%
0.00%
16‐Feb‐12
16‐Feb‐12
0.00%
0.00%
5232
100.00%
71
0.00%
0.00%
0.00%
07‐Dec‐11
16‐Feb‐12
0.00%
0.00%
Equipement Installation (onshore)
0.00%
TSF1110
Installation of production manifold module on celler deck
288
5.50%
4
0.00%
0.00%
0.00%
7‐Dec‐11
10‐Dec‐11
0.00%
0.00%
TSF1090
Equipment Installation on Heli Deck
288
5.50%
4
0.00%
0.00%
0.00%
23‐Dec‐11
27‐Dec‐11
0.00%
0.00%
TSF1100
Installation of E & I module on main deck
288
5.50%
4
0.00%
0.00%
0.00%
7‐Jan‐12
10‐Jan‐12
0.00%
0.00%
TSF1070
Equipment Installation on Cellar Deck
2040
38.99%
15
0.00%
0.00%
0.00%
1-Feb-12
16-Feb-12
0.00%
0.00%
TSF1080
Equipment Installation on Main Deck
2040
38.99%
15
0.00%
0.00%
0.00%
1‐Feb‐12
16‐Feb‐12
0.00%
0.00%
TSF1060
Equipment Installation Below Cellar Deck
288
5.50%
4
0.00%
0.00%
0.00%
12‐Feb‐12
16‐Feb‐12
0.00%
0.00%
17572
10.64%
113
0.00%
0.00%
0.00%
19‐Nov‐11
11‐Mar‐12
0.00%
0.00%
PIPING
0.00%
PTJ2050
Piping & piping support fabrication start
0
0.00%
0
0.00%
0.00%
0.00%
19‐Nov‐11
19‐Nov‐11
0.00%
0.00%
PTJ2110
Piping & piping support erection finish
0
0.00%
0
0.00%
0.00%
0.00%
11‐Mar‐12
11‐Mar‐12
0.00%
0.00%
17572
100.00%
113
0.00%
0.00%
0.00%
19‐Nov‐11
11‐Mar‐12
0.00%
0.00%
C.S Piping Fab. & Erec., Valves Erection (onshore)
0.00%
TSF1000
Piping Fabrication
8960
50.99%
70
0.00%
0.00%
0.00%
19‐Nov‐11
28‐Jan‐12
0.00%
0.00%
TSF1010
Piping Supports Fabrication
1408
8.01%
22
0.00%
0.00%
0.00%
19‐Nov‐11
11‐Dec‐11
0.00%
0.00%
TSF1020
Piping Erection
4760
27.09%
35
0.00%
0.00%
0.00%
26‐Jan‐12
1‐Mar‐12
0.00%
0.00%
TSF1030
Piping Supports Erection
800
4.55%
20
0.00%
0.00%
0.00%
10‐Feb‐12
1‐Mar‐12
0.00%
0.00%
TSF1040
Valve Installation
300
1.71%
15
0.00%
0.00%
0.00%
15‐Feb‐12
1‐Mar‐12
0.00%
0.00%
PTJ2120
Piping hydrotest
1344
7.65%
21
0.00%
0.00%
0.00%
19‐Feb‐12
11‐Mar‐12
0.00%
0.00%
30/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL PROJECT : SETH DEVELOPMENT PROJECT Total Budgete Units (Hrs)
R.W %
W.P.6: PIPELINE SPOOLS FABRICATION
21752
SETH PLEM & EXISTING TUNA PLEM
25‐Jun‐11
DATE :
WK
WEEK NO.
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
59
0.00%
0.00%
0.00%
10992
50.53%
59
0.00%
0.00%
1948
17.72%
59
0.00%
BEFORE METROLOGY
1652
84.80%
59
PIPE LINE & BENDS
1652
100.00%
59
Activity Name
Act ID
SPOOL NO. S1 (CLOSING) ( P.L ‐ S2 )
ACTUAL %
13
PLANNED % DEV/ITEM
DEV/ OVERALL
Start Date
Finish Date
0.00%
23-Feb-12
25-Apr-12
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
25‐Apr‐12
0.00%
0.00%
0.00%
0.00%
0.00%
24‐Mar‐12
25‐Apr‐12
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
SS740
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.91%
48
0.00%
0.00%
0.00%
16-Apr-12 p
18-Apr-12 p
0.00%
0.00%
SS750
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.87%
48
0.00%
0.00%
0.00%
18‐Apr‐12
21‐Apr‐12
0.00%
0.00%
SS690
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.81%
48
0.00%
0.00%
0.00%
24-Mar-12
26-Mar-12
0.00%
0.00%
SS760
APPLY SHRINKABLE SLEEVE
128
7.75%
60
0.00%
0.00%
0.00%
21-Apr-12
23-Apr-12
0.00%
0.00%
SS700
CUTTING & BEVELING BEFORE METROLOGY
180
10.90%
48
0.00%
0.00%
0.00%
26-Mar-12
29-Mar-12
0.00%
0.00%
SS710
FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
240
14.53%
48
0.00%
0.00%
0.00%
29-Mar-12
4-Apr-12
0.00%
0.00%
SS730
COATING OF BENDS
384
23.24%
48
0.00%
0.00%
0.00%
14‐Apr‐12
21‐Apr‐12
0.00%
0.00%
SS720
WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY
512
30.99%
48
0.00%
0.00%
0.00%
04-Apr-12
14-Apr-12
0.00%
0.00%
296
15.20%
59
0.00%
0.00%
0.00%
15-Apr-12
25-Apr-12
0.00%
0.00%
0
0.00%
60
0.00%
0.00%
0.00%
15-Apr-12
15-Apr-12
0.00%
0.00%
AFTER METROLOGY
0.00%
SS770
RECEVING METROLOGY
SS810
APPLY SHRINKABLE SLEEVE
32
10.81%
60
0.00%
0.00%
0.00%
23-Apr-12
24-Apr-12
0.00%
0.00%
SS800
PIGGING & HYDRO TEST
32
10.81%
60
0.00%
0.00%
0.00%
21-Apr-12
23-Apr-12
0.00%
0.00%
SS820
LIFTING TEST
32
10.81%
60
0.00%
0.00%
0.00%
24-Apr-12
25-Apr-12
0.00%
0.00%
SS780
FIT UP AFTER METROLOGY
72
24.32%
60
0.00%
0.00%
0.00%
15-Apr-12
17-Apr-12
0.00%
0.00%
SS790
WELDING & NDT AFTER METROLOGY
128
43.24%
60
0.00%
0.00%
0.00%
17-Apr-12
21-Apr-12
0.00%
0.00%
1716
15.61%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
1716
100.00%
59
0.00%
0.00%
0.00%
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00%
32
1.86%
60
0.00%
0.00%
0.00%
22-Mar-12
23-Mar-12
0.00%
0.00%
SPOOL NO. S2 ( S1 ‐ S3 ) PIPE LINE & BENDS SS910
PIGGING & HYDRO TEST
31/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED %
OVERALL
ITEM
OVERALL
Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
SS920
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24-Mar-12
24-Mar-12
0.00%
0.00%
SS880
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18-Mar-12
19-Mar-12
0.00%
0.00%
SS890
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20-Mar-12
21-Mar-12
0.00%
0.00%
SS830
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23-Feb-12
25-Feb-12
0.00%
0.00%
SS900
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22-Mar-12
23-Mar-12
0.00%
0.00%
SS840
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26-Feb-12
28-Feb-12
0.00%
0.00%
SS850
FIT UP FOR LINE PIPE & BENDS
240
13.99%
47
0.00%
0.00%
0.00%
29-Feb-12
5-Mar-12
0.00%
0.00%
SS870
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15-Mar-12
21-Mar-12
0.00%
0.00%
SS860
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
6-Mar-12
14-Mar-12
0.00%
0.00%
1948
17.72%
59
0.00%
0.00%
0.00%
0.00%
24‐Mar‐12
25‐Apr‐12
0.00%
0.00%
BEFORE METROLOGY
1652
84.80%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
PIPE LINE & BENDS
1652
100 00% 100.00%
59
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
24 12 24-Mar-12
23 A 12 23-Apr-12
0 00% 0.00%
0 00% 0.00%
SPOOL NO. S3 (CLOSING) ( S2 ‐ S4 )
SS980
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.91%
48
0.00%
0.00%
0.00%
16-Apr-12
18-Apr-12
0.00%
0.00%
SS990
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.87%
48
0.00%
0.00%
0.00%
18-Apr-12
21-Apr-12
0.00%
0.00%
SS930
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.81%
48
0.00%
0.00%
0.00%
24-Mar-12
26-Mar-12
0.00%
0.00%
SS1000
APPLY SHRINKABLE SLEEVE
128
7.75%
60
0.00%
0.00%
0.00%
21-Apr-12
23-Apr-12
0.00%
0.00%
SS940
CUTTING & BEVELING BEFORE METROLOGY
180
10.90%
48
0.00%
0.00%
0.00%
26-Mar-12
29-Mar-12
0.00%
0.00%
SS950
FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
240
14.53%
48
0.00%
0.00%
0.00%
29-Mar-12
4-Apr-12
0.00%
0.00%
SS970
COATING OF BENDS
384
23.24%
48
0.00%
0.00%
0.00%
14-Apr-12
21-Apr-12
0.00%
0.00%
SS960
WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY
512
30.99%
48
0.00%
0.00%
0.00%
04‐Apr‐12
14‐Apr‐12
0.00%
0.00%
296
15.20%
59
0.00%
0.00%
0.00%
15-Apr-12
25-Apr-12
0.00%
0.00%
0
0.00%
60
0.00%
0.00%
0.00%
15-Apr-12
15-Apr-12
0.00%
0.00%
AFTER METROLOGY
0.00%
SS1010
RECEVING METROLOGY
SS1050
APPLY SHRINKABLE SLEEVE
32
10.81%
60
0.00%
0.00%
0.00%
23-Apr-12
24-Apr-12
0.00%
0.00%
SS1040
PIGGING & HYDRO TEST
32
10.81%
60
0.00%
0.00%
0.00%
21-Apr-12
23-Apr-12
0.00%
0.00%
SS1060
LIFTING TEST
32
10.81%
60
0.00%
0.00%
0.00%
24-Apr-12
25-Apr-12
0.00%
0.00%
SS1020
FIT UP AFTER METROLOGY
72
24.32%
60
0.00%
0.00%
0.00%
15-Apr-12
17-Apr-12
0.00%
0.00%
SS1030
WELDING & NDT AFTER METROLOGY
128
43.24%
60
0.00%
0.00%
0.00%
17-Apr-12
21-Apr-12
0.00%
0.00%
1716
15.61%
59
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
SPOOL NO. S4 ( S4 ‐ SETH PLEM )
0.00%
32/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
Activity Name
Act ID
PIPE LINE & BENDS
Total Budgete Units (Hrs)
R.W %
1716
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
59
0.00%
0.00%
0.00%
ACTUAL %
PLANNED %
DEV/ OVERALL
Start Date
Finish Date
DEV/ITEM
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00%
SS1150
PIGGING & HYDRO TEST
32
1.86%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS1160
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24-Mar-12
24-Mar-12
0.00%
0.00%
SS1120
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18-Mar-12
19-Mar-12
0.00%
0.00%
SS1130
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20-Mar-12
21-Mar-12
0.00%
0.00%
SS1070
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23-Feb-12
25-Feb-12
0.00%
0.00%
SS1140
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS1080
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26-Feb-12
28-Feb-12
0.00%
0.00%
SS1090
FIT UP FOR LINE PIPE & BENDS
240
13.99%
47
0.00%
0.00%
0.00%
29-Feb-12
05-Mar-12
0.00%
0.00%
SS1110
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15-Mar-12
21-Mar-12
0.00%
0.00%
SS1100
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
06‐Mar‐12
14‐Mar‐12
0.00%
0.00%
1716
15.61%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
1716
100.00%
59
0.00%
0.00%
0.00%
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00%
SPOOL NO. S5 ( SETH PLEM ‐ S6 ) PIPE LINE & BENDS SS1250
PIGGING & HYDRO TEST
32
1.86%
60
0.00%
0.00%
0.00%
22-Mar-12
23-Mar-12
0.00%
0.00%
SS1260
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24-Mar-12
24-Mar-12
0.00%
0.00%
SS1220
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18-Mar-12
19-Mar-12
0.00%
0.00%
SS1230
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20-Mar-12
21-Mar-12
0.00%
0.00%
SS1170
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23-Feb-12
25-Feb-12
0.00%
0.00%
SS1240
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22-Mar-12
23-Mar-12
0.00%
0.00%
SS1180
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26-Feb-12
28-Feb-12
0.00%
0.00%
SS1190
FIT UP FOR LINE PIPE & BENDS
240
13.99%
47
0.00%
0.00%
0.00%
29-Feb-12
5-Mar-12
0.00%
0.00%
SS1210
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15-Mar-12
21-Mar-12
0.00%
0.00%
SS1200
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
6-Mar-12
14-Mar-12
0.00%
0.00%
1948
17.72%
59
0.00%
0.00%
0.00%
0.00%
24‐Mar‐12
25‐Apr‐12
0.00%
0.00%
BEFORE METROLOGY
1652
84.80%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
PIPE LINE & BENDS
1652
100.00%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
SPOOL NO. S6 (CLOSING) ( S5 ‐ TUNA PLEM )
SS1320
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.91%
48
0.00%
0.00%
0.00%
16-Apr-12
18-Apr-12
0.00%
0.00%
SS1330
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.87%
48
0.00%
0.00%
0.00%
18-Apr-12
21-Apr-12
0.00%
0.00%
33/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
Activity Name
Act ID
SS1270
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
Total Budgete Units (Hrs)
R.W %
96
5.81%
Original Duration (Days)
ACTUAL % ITEM
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
24-Mar-12
26-Mar-12
0.00%
0.00%
OVERALL
ITEM
OVERALL
48
0.00%
0.00%
SS1340
APPLY SHRINKABLE SLEEVE
128
7.75%
60
0.00%
0.00%
0.00%
21-Apr-12
23-Apr-12
0.00%
0.00%
SS1280
CUTTING & BEVELING BEFORE METROLOGY
180
10.90%
48
0.00%
0.00%
0.00%
26‐Mar‐12
29‐Mar‐12
0.00%
0.00%
SS1290
FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
240
14.53%
48
0.00%
0.00%
0.00%
29-Mar-12
4-Apr-12
0.00%
0.00%
SS1310
COATING OF BENDS
384
23.24%
48
0.00%
0.00%
0.00%
14-Apr-12
21-Apr-12
0.00%
0.00%
SS1300
WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY
512
30.99%
48
0.00%
0.00%
0.00%
4‐Apr‐12
14‐Apr‐12
0.00%
0.00%
296
15.20%
59
0.00%
0.00%
0.00%
15-Apr-12
25-Apr-12
0.00%
0.00%
RECEVING METROLOGY
0
0.00%
60
0.00%
0.00%
0.00%
15-Apr-12
15-Apr-12
0.00%
0.00%
SS1390
APPLY SHRINKABLE SLEEVE
32
10.81%
60
0.00%
0.00%
0.00%
23‐Apr‐12
24‐Apr‐12
0.00%
0.00%
SS1380
PIGGING & HYDRO TEST
32
10.81%
60
0.00%
0.00%
0.00%
21‐Apr‐12
23‐Apr‐12
0.00%
0.00%
SS1400
LIFTING TEST
32
10.81%
60
0.00%
0.00%
0.00%
24‐Apr‐12
25‐Apr‐12
0.00%
0.00%
SS1360
FIT UP AFTER METROLOGY
72
24.32%
60
0.00%
0.00%
0.00%
15-Apr-12
17-Apr-12
0.00%
0.00%
SS1370
WELDING & NDT AFTER METROLOGY
128
43.24%
60
0.00%
0.00%
0.00%
17‐Apr‐12
21‐Apr‐12
0.00%
0.00%
10760
49.47%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
25‐Apr‐12
0.00%
0.00%
1948
18.10%
59
0.00%
0.00%
0.00%
0.00%
24‐Mar‐12
25‐Apr‐12
0.00%
0.00%
BEFORE METROLOGY
1652
84.80%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
PIPE LINE & BENDS
1652
100.00%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
AFTER METROLOGY SS1350
SETH P/F & NEW SSIV SPOOL NO. S6 (CLOSING) ( S5 ‐ SETH P/F )
0.00%
SS600
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.91%
48
0.00%
0.00%
0.00%
16‐Apr‐12
18‐Apr‐12
0.00%
0.00%
SS610
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.87%
48
0.00%
0.00%
0.00%
18‐Apr‐12
21‐Apr‐12
0.00%
0.00%
SS550
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.81%
48
0.00%
0.00%
0.00%
24‐Mar‐12
26‐Mar‐12
0.00%
0.00%
SS620
APPLY SHRINKABLE SLEEVE
128
7.75%
60
0.00%
0.00%
0.00%
21‐Apr‐12
23‐Apr‐12
0.00%
0.00%
SS560
CUTTING & BEVELING BEFORE METROLOGY
180
10.90%
48
0.00%
0.00%
0.00%
26‐Mar‐12
29‐Mar‐12
0.00%
0.00%
SS570
FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
240
14.53%
48
0.00%
0.00%
0.00%
29‐Mar‐12
4‐Apr‐12
0.00%
0.00%
SS590
COATING OF BENDS
384
23.24%
48
0.00%
0.00%
0.00%
14‐Apr‐12
21‐Apr‐12
0.00%
0.00%
SS580
WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY
512
30.99%
48
0.00%
0.00%
0.00%
4‐Apr‐12
14‐Apr‐12
0.00%
0.00%
296
15.20%
59
0.00%
0.00%
0.00%
15-Apr-12
25-Apr-12
0.00%
0.00%
AFTER METROLOGY
0.00%
SS630
RECEVING METROLOGY
0
0.00%
60
0.00%
0.00%
0.00%
15‐Apr‐12
15‐Apr‐12
0.00%
0.00%
SS670
APPLY SHRINKABLE SLEEVE
32
10.81%
60
0.00%
0.00%
0.00%
23‐Apr‐12
24‐Apr‐12
0.00%
0.00%
SS660
PIGGING & HYDRO TEST
32
10.81%
60
0.00%
0.00%
0.00%
21‐Apr‐12
23‐Apr‐12
0.00%
0.00%
SS680
LIFTING TEST
32
10.81%
60
0.00%
0.00%
0.00%
24‐Apr‐12
25‐Apr‐12
0.00%
0.00%
34/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED %
OVERALL
ITEM
OVERALL
Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
SS640
FIT UP AFTER METROLOGY
72
24.32%
60
0.00%
0.00%
0.00%
15-Apr-12
17-Apr-12
0.00%
0.00%
SS650
WELDING & NDT AFTER METROLOGY
128
43.24%
60
0.00%
0.00%
0.00%
17‐Apr‐12
21‐Apr‐12
0.00%
0.00%
1716
15.95%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
1716
100.00%
59
0.00%
0.00%
0.00%
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00% 0.00%
SPOOL NO. S2 ( S1 ‐ SSIV ) PIPE LINE & BENDS SS230
PIGGING & HYDRO TEST
32
1.86%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
SS240
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24‐Mar‐12
24‐Mar‐12
0.00%
0.00%
SS200
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18‐Mar‐12
19‐Mar‐12
0.00%
0.00%
SS210
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS150
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23‐Feb‐12
25‐Feb‐12
0.00%
0.00%
SS220
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS160
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26‐Feb‐12
28‐Feb‐12
0.00%
0.00%
SS170
FIT UP FOR LINE PIPE & BENDS
240
13 99% 13.99%
47
0 00% 0.00%
0 00% 0.00%
0 00% 0.00%
29 Feb 12 29‐Feb‐12
5 Mar 12 5‐Mar‐12
0 00% 0.00%
0 00% 0.00%
SS190
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS180
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
6‐Mar‐12
14‐Mar‐12
0.00%
0.00%
1716
15.95%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
1716
100.00%
59
0.00%
0.00%
0.00%
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00%
SPOOL NO. S3 ( SSIV ‐S4 ) PIPE LINE & BENDS SS330
PIGGING & HYDRO TEST
32
1.86%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS340
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24‐Mar‐12
24‐Mar‐12
0.00%
0.00%
SS300
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18‐Mar‐12
19‐Mar‐12
0.00%
0.00%
SS310
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS250
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23‐Feb‐12
25‐Feb‐12
0.00%
0.00%
SS320
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS260
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26‐Feb‐12
28‐Feb‐12
0.00%
0.00%
SS270
FIT UP FOR LINE PIPE & BENDS
240
13.99%
47
0.00%
0.00%
0.00%
29‐Feb‐12
5‐Mar‐12
0.00%
0.00%
SS290
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS280
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
6‐Mar‐12
14‐Mar‐12
0.00%
0.00%
1948
18.10%
59
0.00%
0.00%
0.00%
0.00%
24‐Mar‐12
25‐Apr‐12
0.00%
0.00%
BEFORE METROLOGY
1652
84.80%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
PIPE LINE & BENDS
1652
100.00%
59
0.00%
0.00%
0.00%
0.00%
24-Mar-12
23-Apr-12
0.00%
0.00%
48
2.91%
48
0.00%
0.00%
0.00%
16‐Apr‐12
18‐Apr‐12
0.00%
0.00%
SPOOL NO. S1 (CLOSING) ( P.L ‐ SETH PLEM )
SS060
FIT UP FLANGES AND FITTING WITH LINE PIPE
35/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
64
3.87%
Original Duration (Days)
ACTUAL % ITEM
PLANNED % DEV/ITEM
DEV/ OVERALL
Start Date
Finish Date
0.00%
18‐Apr‐12
21‐Apr‐12
0.00%
0.00%
OVERALL
ITEM
OVERALL
48
0.00%
0.00%
SS070
WELDING & NDT FOR FLANGES WITH LINE PIPE
SS 10
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.81%
48
0.00%
0.00%
0.00%
24‐Mar‐12
26‐Mar‐12
0.00%
0.00%
SS080
APPLY SHRINKABLE SLEEVE
128
7.75%
60
0.00%
0.00%
0.00%
21‐Apr‐12
23‐Apr‐12
0.00%
0.00%
SS020
CUTTING & BEVELING BEFORE METROLOGY
180
10.90%
48
0.00%
0.00%
0.00%
26‐Mar‐12
29‐Mar‐12
0.00%
0.00%
SS030
FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
240
14.53%
48
0.00%
0.00%
0.00%
29‐Mar‐12
4‐Apr‐12
0.00%
0.00%
SS050
COATING OF BENDS
384
23.24%
48
0.00%
0.00%
0.00%
14‐Apr‐12
21‐Apr‐12
0.00%
0.00%
SS040
WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROLOGY
512
30.99%
48
0.00%
0.00%
0.00%
4‐Apr‐12
14‐Apr‐12
0.00%
0.00%
296
15.20%
59
0.00%
0.00%
0.00%
15-Apr-12
25-Apr-12
0.00%
0.00%
AFTER METROLOGY
0.00%
SS090
RECEVING METROLOGY
0
0.00%
60
0.00%
0.00%
0.00%
15‐Apr‐12
15‐Apr‐12
0.00%
0.00%
SS130
APPLY SHRINKABLE SLEEVE
32
10.81%
60
0.00%
0.00%
0.00%
23‐Apr‐12
24‐Apr‐12
0.00%
0.00%
SS120
PIGGING & HYDRO TEST
32
10.81%
60
0.00%
0.00%
0.00%
21‐Apr‐12
23‐Apr‐12
0.00%
0.00%
SS140
LIFTING TEST
32
10.81%
60
0.00%
0.00%
0.00%
24‐Apr‐12
25‐Apr‐12
0.00%
0.00%
SS100
FIT UP AFTER METROLOGY
72
24.32%
60
0.00%
0.00%
0.00%
15‐Apr‐12
17‐Apr‐12
0.00%
0.00%
SS110
WELDING & NDT AFTER METROLOGY
128
43.24%
60
0.00%
0.00%
0.00%
17‐Apr‐12
21‐Apr‐12
0.00%
0.00%
1716
15.95%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
1716
100.00%
59
0.00%
0.00%
0.00%
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00%
SPOOL NO. S5 ( S4 ‐ S6 ) PIPE LINE & BENDS SS530
PIGGING & HYDRO TEST
32
1.86%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS540
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24‐Mar‐12
24‐Mar‐12
0.00%
0.00%
SS500
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18‐Mar‐12
19‐Mar‐12
0.00%
0.00%
SS510
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS450
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23‐Feb‐12
25‐Feb‐12
0.00%
0.00%
SS520
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS460
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26‐Feb‐12
28‐Feb‐12
0.00%
0.00%
SS470
FIT UP FOR LINE PIPE & BENDS
240
13.99%
47
0.00%
0.00%
0.00%
29‐Feb‐12
5‐Mar‐12
0.00%
0.00%
SS490
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS480
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
6‐Mar‐12
14‐Mar‐12
0.00%
0.00%
1716
15.95%
59
0.00%
0.00%
0.00%
0.00%
23‐Feb‐12
24‐Mar‐12
0.00%
0.00%
1716
100.00%
59
0.00%
0.00%
0.00%
0.00%
23-Feb-12
24-Mar-12
0.00%
0.00%
SPOOL NO. S4 ( S3 ‐ S5 ) PIPE LINE & BENDS SS430
PIGGING & HYDRO TEST
32
1.86%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS440
LIFTING TEST
32
1.86%
60
0.00%
0.00%
0.00%
24‐Mar‐12
24‐Mar‐12
0.00%
0.00%
36/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP6 PROGRESS Sheet
Activity Name
Act ID
Total Budgete Units (Hrs)
R.W %
Original Duration (Days)
ACTUAL % ITEM
PLANNED %
OVERALL
ITEM
OVERALL
Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
SS400
FIT UP FLANGES AND FITTING WITH LINE PIPE
48
2.80%
47
0.00%
0.00%
0.00%
18‐Mar‐12
19‐Mar‐12
0.00%
0.00%
SS410
WELDING & NDT FOR FLANGES WITH LINE PIPE
64
3.73%
47
0.00%
0.00%
0.00%
20‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS350
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
96
5.59%
47
0.00%
0.00%
0.00%
23‐Feb‐12
25‐Feb‐12
0.00%
0.00%
SS420
APPLY SHRINKABLE SLEEVE
128
7.46%
60
0.00%
0.00%
0.00%
22‐Mar‐12
23‐Mar‐12
0.00%
0.00%
SS360
CUTTING & BEVELING
180
10.49%
47
0.00%
0.00%
0.00%
26‐Feb‐12
28‐Feb‐12
0.00%
0.00%
SS370
FIT UP FOR LINE PIPE & BENDS
240
13.99%
47
0.00%
0.00%
0.00%
29‐Feb‐12
05‐Mar‐12
0.00%
0.00%
SS390
COATING OF BENDS
384
22.38%
47
0.00%
0.00%
0.00%
15‐Mar‐12
21‐Mar‐12
0.00%
0.00%
SS380
WELDING & NDT FOR LINE PIPE & BENDS
512
29.84%
47
0.00%
0.00%
0.00%
06‐Mar‐12
14‐Mar‐12
0.00%
0.00%
37/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP8 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL PROJECT : SETH DEVELOPMENT PROJECT
Activity Name
Act ID
W.P.8: LOAD‐OUT, SEA‐FASTENING, TRANSPORTATION & INSTALLATION
Total Budgete Units (Hrs)
R.W %
27456
25‐Jun‐11
DATE :
WK
WEEK NO.
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
204
0.00%
0.00%
0.00%
ACTUAL %
13
PLANNED % Start Date
Finish Date
DEV/ITEM
DEV/ OVERALL
0.00%
18-Oct-11
08-May-12
0.00%
0.00%
PTJ1070
Pre-drilling template seafastening and load out
840
3.06%
7
0.00%
0.00%
0.00%
18‐Oct‐11
24‐Oct‐11
0.00%
0.00%
PTJ1170
Sub Sea Spools Load out first trip
840
3.06%
7
0.00%
0.00%
0.00%
25‐Mar‐12
31‐Mar‐12
0.00%
0.00%
PTJ1180
Sub Sea Spools Load out second trip for closing spools
840
3.06%
7
0.00%
0.00%
0.00%
25-Apr-12
02-May-12
0.00%
0.00%
PTJ1060
Deck seafastening and load out
7896
28.76%
7
0.00%
0.00%
0.00%
02-May-12
08-May-12
0.00%
0.00%
PTJ1050
Jacket & Piles seafastening and load out
17040
62.06%
15
0.00%
0.00%
0.00%
17-Mar-12
31-Mar-12
0.00%
0.00%
38/40 02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
WP9 PROGRESS Sheet
PETROJET
CLIENT : PETROBEL PROJECT : SETH DEVELOPMENT PROJECT
Act ID
Activity Name
W.P.9: OFFSHORE HOOKUP, COMMISSIONING AND ASSISTANT FOR START UP
25‐Jun‐11
DATE :
WK
WEEK NO.
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
46
0.00%
0.00%
0.00%
R.W %
ACTUAL %
13
PLANNED % DEV/ITEM
DEV/ OVERALL
Start Date
Finish Date
0.00%
15-May-12
30-Jun-12
0.00%
0.00%
M01
May-12
50.00%
16
0.00%
0.00%
0.00%
0.00%
15-May-12
31-May-12
0.00%
0.00%
M02
Jun-12
50.00%
30
0.00%
0.00%
0.00%
0.00%
01-Jun-12
30-Jun-12
0.00%
0.00%
02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
39/40
CRASHING COST
PETROJET
CLIENT : PETROBEL PROJECT : SETH DEVELOPMENT PROJECT
Act ID
Activity Name
W.P.1: PROJECT MANAGEMENT
25‐Jun‐11
DATE :
WK
WEEK NO.
Original Duration (Days)
ITEM
OVERALL
ITEM
OVERALL
100.00%
182
0.00%
0.00%
0.00%
R.W %
ACTUAL %
13
PLANNED % DEV/ITEM
DEV/ OVERALL
Start Date
Finish Date
0.00%
01-Nov-11
01-May-12
0.00%
0.00%
M01
Nov-11
10.00%
24
0.00%
0.00%
0.00%
0.00%
01-Nov-11
25-Nov-11
0.00%
0.00%
M02
Dec-11
20.00%
29
0.00%
0.00%
0.00%
0.00%
26‐Nov‐11
25‐Dec‐11
0.00%
0.00%
M03
Jan-12
20.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Dec‐11
25‐Jan‐12
0.00%
0.00%
M04
Feb-12
20.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Jan‐12
25‐Feb‐12
0.00%
0.00%
M05
Mar-12
20.00%
28
0.00%
0.00%
0.00%
0.00%
26‐Feb‐12
25‐Mar‐12
0.00%
0.00%
M06
Apr-12
10.00%
30
0.00%
0.00%
0.00%
0.00%
26‐Mar‐12
25‐Apr‐12
0.00%
0.00%
02/07/201110:32 ص
E:\SETH\WEEKLY & MONTHLY REPORT\MONTHLY\MONTHLY 25‐06‐11\
40/40
PAGE 27 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.3. UPDATED SCHEDULE
GFL 003-0405
3467-200
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
SETH OFFSHORE OFFS EPC PROJECT UPDATED SCHEDULE CONTRACTUAL MILESTONES CONTRACT
BL Project Finish
Start
335 31-Mar-11
31-Jul-12
28-Mar-11 A
31-Jul-12
335 31-Mar-11
31-Jul-12
31-Mar-11 A
31-Jul-12
Finish
Project start
0 31-Mar-11
A1030
Finishing the basic engineering review and Endorsement report iss...
0
31-Mar-11
31-Mar-11 A
A2320
Recieve PTB LLI's Technical Offers from PTB
0
31-Mar-11
31-Mar-11 A
A17
Recieving LOI from PTB
0
31-Mar-11
31-Mar-11 A
A2290
All LLI's awarded (By Petrobel)
0
19-Apr-11
19-Apr-11 A
A2330
PTB LLI's TER's by Enppi
0 19-Apr-11
A2360
EPC Contract Signature
0
29-Apr-11
29-Apr-11 A
ART6.1
Authorization for Predrilling template ready for sail out: transportati...
0
24-Oct-11
24-Oct-11*
ART6.7
Pipeline spools ready for load out in four weeks from company req...
0
23-Mar-12
23-Mar-12
ART6.3
Deck Mechanical Completion
0
01-Apr-12
31-Mar-12*
ART6.2.1
Jacket and Piles ready for load out
0
14-Apr-12
14-Apr-12*
ART6.2.2
Company Authorization for Jacket & Piles ready for Sail out
0
21-Apr-12
21-Apr-12*
ART6.4.1
Deck and Flare Ready for Load out
0
01-May-12
30-Apr-12*
ART6.4.2
Company authorization for ready for sail out of Deck and flare
0
10-May-12
08-May-12
ART6.5
Offshore hook up and Final commissioning
0
02-Jul-12
30-Jun-12
A6.6
Assistance for start up (1) week from Company request
0
31-Jul-12
30-Jul-12
A2
Project completion
0
31-Jul-12
31-Jul-12*
W.P.1: PRO PROJECT MANAGEMENT A2380
Design review (Internal meeting)
A1010
Management activities
W.P.2: ENG ENGINEERING PROCESS
31-Mar-11 A
31-Jul-12
335 31-Mar-11
31-Jul-12
31-Mar-11 A
31-Jul-12
12-Jul-11
21-Aug-11
23-Aug-11
335 31-Mar-11
31-Jul-12
31-Mar-11 A
31-Jul-12
255 31-Mar-11
21-Mar-12
31-Mar-11 A
08-Apr-12
254 03-Apr-11
21-Mar-12
03-Apr-11 A
08-Apr-12
Primary Baseline Actual Work
Baseline ...
Remaining...
2012 F M A M J JulA
19-Apr-11 A
31-Jul-12
Start Date:28-Mar-11 Finish Date:31-Jul-12 Critical Re... Data Date:25-Jun-11
Remaining Level of Effort
J
31-Mar-11 A
335 31-Mar-11
3 07-Jul-11
2011 A M J Jul A S O N D
A1
ENPPI
Page 1 of 64
By: Haytham A.Rahman Date 25-May-11
Revision Rev.0
Checked A.Maghawry
Approved A.Fathy
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID A2230
Activity Name HAZOP meeting
Drawings
Original BL Project Duration Start
BL Project Finish
Start
Finish
0 13-Jun-11
16-Jun-11
21-Jul-11
21-Jul-11
129 03-Apr-11
05-Oct-11
03-Apr-11 A
04-Oct-11
2011 A M J Jul A S O N D
A2420
UFD's IFD
5 06-Apr-11
13-Apr-11
06-Apr-11 A
10-Apr-11 A
A1410
PFD's IFD
5 03-Apr-11
10-Apr-11
03-Apr-11 A
10-Apr-11 A
A2430
Heat and material balance IFD
5 03-Apr-11
10-Apr-11
03-Apr-11 A
10-Apr-11 A
A1420
P&ID's IFD
5 10-Apr-11
17-Apr-11
10-Apr-11 A
21-Apr-11 A
A2570
Escape route and safety signs layouts IFD
5 31-May-11
07-Jun-11
10-May-11 A
16-May-11 A
A2560
Fire fighting and safety layouts IFD
5 05-May-11
12-May-11
05-May-11 A
17-May-11 A
A2410
Process block diagram IFD
5 07-Jun-11
14-Jun-11
12-Jun-11 A
20-Jun-11 A
A2190
Cause & Effect IFD
5 09-May-11
16-May-11
19-May-11 A
23-Jun-11 A
A1570
P&ID's IFC
7 05-Sep-11
14-Sep-11
05-Sep-11
13-Sep-11
A2200
Cause & Effect IFC
5 14-Sep-11
21-Sep-11
14-Sep-11
20-Sep-11
A1560
PFD's IFF
5 14-Sep-11
21-Sep-11
14-Sep-11
20-Sep-11
A4750
UFD's IFF
5 21-Sep-11
28-Sep-11
21-Sep-11
27-Sep-11
A4760
Fire fighting and safety layouts IFC
5 21-Sep-11
28-Sep-11
21-Sep-11
27-Sep-11
A4740
Process block flow diagram IFF
5 21-Sep-11
28-Sep-11
21-Sep-11
27-Sep-11
A4770
Escape route and safety signs layouts IFC
Technical Lists
Page 2 of 64
5 28-Sep-11
05-Oct-11
28-Sep-11
04-Oct-11
249 10-Apr-11
21-Mar-12
10-Apr-11 A
08-Apr-12
A5320
Design basis IFD
3 10-Apr-11
12-Apr-11
10-Apr-11 A
12-Apr-11 A
A2550
Safety philosophy IFD
5 20-Apr-11
27-Apr-11
20-Apr-11 A
27-Apr-11 A
A2540
Hazardous area classification schedule IFD
5 26-Apr-11
04-May-11
26-Apr-11 A
05-May-11 A
A2210
Equipment list IFD
5 08-May-11
15-May-11
08-May-11 A
11-May-11 A
A2460
Utility load summary IFD
3 19-Jun-11
26-Jun-11
15-Jun-11 A
23-Jun-11 A
A2440
Process report IFD
13 05-Jun-11
12-Jun-11
26-Jun-11
12-Jul-11
A2450
Blow down report IFD
5 03-Jul-11
10-Jul-11
26-Jul-11
01-Aug-11
A2240
HAZOP Report
10 21-Jul-11
04-Aug-11
25-Aug-11
12-Sep-11
A2220
Equipment list IFF
5 12-Sep-11
19-Sep-11
12-Sep-11
18-Sep-11
A4790
Process report IFF
5 14-Sep-11
21-Sep-11
14-Sep-11
20-Sep-11
A4810
Utility load summary IFF
5 20-Sep-11
27-Sep-11
20-Sep-11
26-Sep-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Hazardous area classification schedule IFC
5 21-Sep-11
28-Sep-11
21-Sep-11
27-Sep-11
A4800
Blow down report IFF
5 26-Sep-11
03-Oct-11
26-Sep-11
02-Oct-11
A4830
Safety philosophy IFF
5 03-Oct-11
11-Oct-11
03-Oct-11
10-Oct-11
A2580
Precommissioning procedures IFD
5 22-Feb-12
29-Feb-12
11-Mar-12
15-Mar-12
A2590
Plant operating guide IFD
5 29-Feb-12
07-Mar-12
18-Mar-12
22-Mar-12
A4840
Precommissioning procedures IFF
5 07-Mar-12
14-Mar-12
25-Mar-12
29-Mar-12
A4850
Plant operating guide IFF
5 14-Mar-12
21-Mar-12
01-Apr-12
08-Apr-12
52 03-Apr-11
09-May-11
03-Apr-11 A
29-May-11 A
A2470
Chemical injection package MRQ
3 03-Apr-11
06-Apr-11
03-Apr-11 A
06-Apr-11 A
A2490
Safety equipment and life saving MRQ
7 03-Apr-11
12-Apr-11
03-Apr-11 A
12-Apr-11 A
A2480
Fire protection system MRQ
5 06-Apr-11
12-Apr-11
06-Apr-11 A
12-Apr-11 A
A2510
Flame arrestor MRQ
5 20-Apr-11
27-Apr-11
13-Apr-11 A
17-Apr-11 A
A2500
Vent stack tips MRQ
5 02-May-11
09-May-11
01-May-11 A
09-May-11 A
A1440
Process commodities MRQ's (Other equipment)
15 10-Apr-11
02-May-11
06-Apr-11 A
29-May-11 A
78 08-May-11
11-Jul-11
18-Apr-11 A
26-Jul-11
TER's A2600
Chemical injection package TER
30 08-May-11
19-Jun-11
18-Apr-11 A
01-Jun-11 A
A2610
Fire protection system TER
25 11-May-11
14-Jun-11
26-Apr-11 A
05-Jul-11
A2620
Safety equipment and life saving TER
25 08-May-11
12-Jun-11
26-Apr-11 A
07-Jul-11
A2640
Flame arrestor TER
20 26-May-11
23-Jun-11
26-Jun-11
21-Jul-11
A1450
Process commodities TER's
45 09-May-11
11-Jul-11
22-Apr-11 A
26-Jul-11
A2630
Vent stack tips TER
13 06-Jun-11
04-Jul-11
01-Jun-11 A
26-Jul-11
MRP
43 10-Jul-11
29-Aug-11
03-Jul-11
04-Sep-11
A2660
Chemical injection package MRP
5 10-Jul-11
17-Jul-11
03-Jul-11
07-Jul-11
A2670
Fire protection system MRP
5 10-Jul-11
14-Jul-11
19-Jul-11
25-Jul-11
A2680
Safety equipment and life saving MRP
5 10-Jul-11
17-Jul-11
07-Aug-11
11-Aug-11
A2700
Flame arrestor MRP
5 21-Jul-11
28-Jul-11
21-Aug-11
25-Aug-11
A1460
Process commodities MRP's
25 25-Jul-11
29-Aug-11
27-Jul-11
04-Sep-11
A2690
Vent stack tips MRP
10-Aug-11
24-Aug-11
04-Sep-11
5 03-Aug-11
2011 A M J Jul A S O N D
A4820
MRQ's
Page 3 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Vendor pr prints review A2720
Chemical injection package Vendor prints review
A2740
Safety equipment and life saving Vendor prints review
A1470
Vendor prints review
A2760
Flame arrestor Vendor prints review
A2730
Fire protection system Vendor prints review
A2750
Vent stack tips Vendor prints review
PIPING Drawings
Original BL Project Duration Start
BL Project Finish
Start
119 24-Jul-11
26-Dec-11
17-Jul-11
10-Jan-12
100 25-Jul-11
25-Dec-11
17-Jul-11
14-Dec-11
80 25-Jul-11
24-Nov-11
21-Aug-11
21-Dec-11
100 25-Jul-11
25-Dec-11
26-Jul-11
25-Dec-11
07-Dec-11
04-Sep-11
01-Jan-12
21-Dec-11
03-Aug-11
02-Jan-12
80 23-Aug-11
26-Dec-11
13-Sep-11
10-Jan-12
240 31-Mar-11
24-Jan-12
31-Mar-11 A
03-Jan-12
178 17-Apr-11
04-Jan-12
05-Apr-11 A
03-Jan-12
80 07-Aug-11 100 24-Jul-11
Finish
Plot Plan IFD
5 17-Apr-11
24-Apr-11
05-Apr-11 A
10-Apr-11 A
A1670
Plot Plan IFC
5 14-Sep-11
21-Sep-11
14-Sep-11
20-Sep-11
A6220
GA's IFD
8 15-Sep-11
27-Sep-11
18-Sep-11
27-Sep-11
A1680
ISO's
10 31-Oct-11
20-Nov-11
31-Oct-11
17-Nov-11
A1690
GA's IFC
15 02-Nov-11
30-Nov-11
02-Nov-11
29-Nov-11
A2790
Hydro test maps IFC
7 24-Nov-11
06-Dec-11
24-Nov-11
05-Dec-11
A6190
Piping support plan IFC
5 14-Dec-11
21-Dec-11
14-Dec-11
20-Dec-11
A6200
Piping support location IFC
5 21-Dec-11
28-Dec-11
21-Dec-11
27-Dec-11
A6210
Piping penetration location IFC
5 28-Dec-11
04-Jan-12
28-Dec-11
03-Jan-12
145 12-May-11
14-Dec-11
19-May-11 A
13-Dec-11
A2780
Line Designation table (LDT) IFD
5 12-May-11
19-May-11
19-May-11 A
01-Jun-11 A
A4920
Line Designation table (LDT) IFC
5 14-Sep-11
21-Sep-11
14-Sep-11
20-Sep-11
A6180
Piping support list IFC
Specifications Specificat A6230
Piping material classes IFD
A6240
Final Piping material classes
Model
2011 A M J Jul A S O N D
A1660
Technical Lists
Page 4 of 64
5 07-Dec-11
14-Dec-11
07-Dec-11
13-Dec-11
44 16-May-11
13-Jun-11
16-May-11 A
14-Jul-11
5 16-May-11
23-May-11
16-May-11 A
23-May-11 A
15 06-Jun-11
13-Jun-11
26-Jun-11
14-Jul-11
100 23-May-11
23-Nov-11
26-Jun-11
22-Nov-11
A1990
Model Review (30%)
14 23-May-11
26-May-11
26-Jun-11
13-Jul-11
A2000
Model Review (60%)
3 21-Jul-11
26-Jul-11
13-Sep-11
15-Sep-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID A2010
Activity Name Model Review (90%)
MRQ's
Original BL Project Duration Start
BL Project Finish
Start
Finish
3 20-Nov-11
23-Nov-11
20-Nov-11
22-Nov-11
16 31-Mar-11
24-Apr-11
31-Mar-11 A
29-May-11 A
Piping bulk MRQ
5 31-Mar-11
07-Apr-11
31-Mar-11 A
07-Apr-11 A
A5410
Injection fitting MRQ
5 17-Apr-11
24-Apr-11
17-Apr-11 A
24-Apr-11 A
A5400
Insulation Joint MRQ
5 13-Apr-11
20-Apr-11
22-May-11 A
29-May-11 A
55 10-May-11
15-Jun-11
28-Apr-11 A
24-Jul-11
A1730
Piping bulk TER
15 10-May-11
31-May-11
28-Apr-11 A
17-May-11 A
A5420
Insulation Joint TER
15 19-May-11
09-Jun-11
30-May-11 A
21-Jul-11
A5430
Injection fitting TER
19 25-May-11
15-Jun-11
28-Jun-11
24-Jul-11
46 20-Jun-11
20-Jul-11
26-Jun-11
28-Aug-11
MRP A1740
Piping bulk MRP
5 20-Jun-11
27-Jun-11
26-Jun-11
30-Jun-11
A5530
Injection fitting MRP
5 13-Jul-11
20-Jul-11
22-Aug-11
28-Aug-11
A5540
Insulation Joint MRP
5 10-Jul-11
17-Jul-11
22-Aug-11
28-Aug-11
180 04-May-11
24-Jan-12
14-Jun-11 A
03-Jan-12
Vendor pr prints review A6110
Production Manifold Vendor prints review
180 04-May-11
24-Jan-12
14-Jun-11 A
05-Dec-11
A1750
Piping bulk Vendor prints review
100 05-Jul-11
05-Dec-11
10-Jul-11
07-Dec-11
A5550
Injection fitting Vendor prints review
80 28-Jul-11
30-Nov-11
06-Sep-11
03-Jan-12
A5560
Insulation Joint Vendor prints review
80 25-Jul-11
24-Nov-11
06-Sep-11
03-Jan-12
224 24-Apr-11
24-Jan-12
04-Apr-11 A
08-Jan-12
141 24-Apr-11
20-Oct-11
20-Apr-11 A
17-Nov-11
ELECTRICAL ELECTRIC Drawings
2011 A M J Jul A S O N D
A1720
TER's
Page 5 of 64
A3210
Lighting and navigational aids layouts IFD
5 24-Apr-11
02-May-11
20-Apr-11 A
26-Apr-11 A
A5290
Earthing layouts IFD
5 10-May-11
17-May-11
10-May-11 A
16-May-11 A
A3190
Hazardous area classification layout IFD
5 10-May-11
17-May-11
10-May-11 A
19-May-11 A
A1240
Electrical layouts IFD
15 09-May-11
30-May-11
25-May-11 A
23-Jun-11 A
A3200
Cable routing layouts IFD
5 19-May-11
26-May-11
16-Jun-11 A
23-Jun-11 A
A1230
Single line diagram IFD
20 23-May-11
30-May-11
26-Jun-11
21-Jul-11
A3220
Earthing layouts IFC
5 21-Sep-11
28-Sep-11
21-Sep-11
27-Sep-11
A1600
Electrical layouts IFC
8 21-Sep-11
03-Oct-11
21-Sep-11
02-Oct-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Cable routing layouts IFC
5 28-Sep-11
05-Oct-11
28-Sep-11
04-Oct-11
A5300
Interconnecting wiring diagram IFC
5 29-Sep-11
09-Oct-11
29-Sep-11
05-Oct-11
A5270
Hazardous area classification schedule IFC
5 05-Oct-11
13-Oct-11
05-Oct-11
12-Oct-11
A1590
Single line diagram IFF
7 11-Oct-11
20-Oct-11
11-Oct-11
19-Oct-11
A5280
Lighting and navigational aids layouts IFC
5 12-Oct-11
19-Oct-11
13-Nov-11
17-Nov-11
73 15-May-11
11-Oct-11
26-Jun-11
10-Oct-11
A1580
Power system study IFD
15 15-May-11
24-May-11
26-Jun-11
14-Jul-11
A1250
Power system study IFF
10 26-Sep-11
11-Oct-11
26-Sep-11
10-Oct-11
52 24-Apr-11
20-Jun-11
04-Apr-11 A
22-Jun-11 A
MRQ's A3030
Electrical Cables MRQ
5 02-May-11
09-May-11
04-Apr-11 A
10-Apr-11 A
A3040
Electrical Cable trays MRQ
5 24-Apr-11
02-May-11
05-Apr-11 A
10-Apr-11 A
A3050
Navigation aids system MRQ
5 09-May-11
16-May-11
20-Apr-11 A
26-Apr-11 A
A6130
Earthing material MRQ
17 30-May-11
06-Jun-11
29-May-11 A
20-Jun-11 A
A1980
Electrical commodities MRQ
15 30-May-11
20-Jun-11
10-Apr-11 A
22-Jun-11 A
A3060
Lighting material MRQ
18 26-May-11
02-Jun-11
25-May-11 A
22-Jun-11 A
55 22-May-11
18-Jul-11
20-Apr-11 A
04-Aug-11
TER's A3080
Electrical Cable trays TER
20 22-May-11
19-Jun-11
20-Apr-11 A
02-May-11 A
A3070
Electrical Cables TER
20 23-May-11
20-Jun-11
25-Apr-11 A
29-May-11 A
A3090
Navigation aids system TER
20 30-May-11
27-Jun-11
16-May-11 A
10-Jul-11
A1210
Electrical commodities TER
25 13-Jun-11
18-Jul-11
03-Jul-11
04-Aug-11
A3100
Lighting material TER
20 08-Jun-11
06-Jul-11
10-Jul-11
04-Aug-11
A6250
Earthing material TER
20 20-Jun-11
18-Jul-11
10-Jul-11
04-Aug-11
75 10-Jul-11
15-Sep-11
19-Jun-11 A
04-Oct-11
MRP
2011 A M J Jul A S O N D
A5310
Technical Lists
Page 6 of 64
A3110
Electrical Cables MRP
5 13-Jul-11
20-Jul-11
19-Jun-11 A
20-Jun-11 A
A3120
Electrical Cable trays MRP
8 10-Jul-11
17-Jul-11
26-Jun-11
05-Jul-11
A3130
Navigation aids system MRP
5 19-Jul-11
26-Jul-11
02-Aug-11
08-Aug-11
A3140
Lighting material MRP
3 27-Jul-11
01-Aug-11
28-Aug-11
04-Sep-11
A6310
Earthing material MRP
5 08-Aug-11
15-Aug-11
28-Aug-11
06-Sep-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID A1700
Activity Name Electrical commodities MRP
Vendor pr prints review
Original BL Project Duration Start
BL Project Finish
Start
Finish
15 22-Aug-11
15-Sep-11
14-Sep-11
04-Oct-11
170 04-May-11
24-Jan-12
09-Jun-11 A
08-Jan-12
Electrical Cable trays Vendor prints review
80 25-Jul-11
24-Nov-11
10-Jul-11
02-Nov-11
A3150
Electrical Cables Vendor prints review
80 01-Aug-11
04-Dec-11
21-Jul-11
21-Nov-11
A6100
E&I Module Vendor prints review
170 04-May-11
24-Jan-12
09-Jun-11 A
05-Dec-11
A3250
Earthing Vendor prints review
60 23-Aug-11
28-Nov-11
11-Sep-11
11-Dec-11
A3170
Navigation aids system Vendor prints review
80 02-Aug-11
05-Dec-11
16-Aug-11
18-Dec-11
A3180
Lighting material Vendor prints review
80 11-Aug-11
14-Dec-11
11-Sep-11
08-Jan-12
235 31-Mar-11
22-Feb-12
31-Mar-11 A
08-Mar-12
131 05-May-11
16-Nov-11
20-Apr-11 A
16-Nov-11
Drawings A3280
Instrumenthook up drawing IFD
5 19-May-11
26-May-11
20-Apr-11 A
28-Apr-11 A
A3310
Instrument junction box and wiring diagram IFD
5 26-May-11
02-Jun-11
02-May-11 A
08-May-11 A
A3290
Field instrument layout IFD
5 05-May-11
12-May-11
05-May-11 A
19-May-11 A
A3300
Cable drawings IFD
16 12-May-11
19-May-11
25-May-11 A
14-Jun-11 A
A1270
Instrument Layouts & Wiring drawings IFD
15 19-May-11
09-Jun-11
20-Apr-11 A
15-Jun-11 A
A5660
Field instrument layout IFC
5 20-Oct-11
27-Oct-11
20-Oct-11
26-Oct-11
A5670
Cable drawings IFC
5 27-Oct-11
03-Nov-11
27-Oct-11
02-Nov-11
A5690
Instrumenthook up drawing IFC
5 01-Nov-11
14-Nov-11
01-Nov-11
13-Nov-11
A5680
Instrument junction box and wiring diagram IFC
5 03-Nov-11
16-Nov-11
03-Nov-11
15-Nov-11
A1280
Instrument Layouts & Wiring drawings IFC
15 20-Oct-11
16-Nov-11
20-Oct-11
16-Nov-11
104 26-Apr-11
25-Sep-11
26-Apr-11 A
22-Sep-11
Technical Lists A1290
Instrument Index IFD
5 26-Apr-11
04-May-11
26-Apr-11 A
03-May-11 A
A2250
Instrument data sheets
8 26-May-11
07-Jun-11
01-Jun-11 A
12-Jun-11 A
A3320
Instrument cable schedule IFD
0 26-May-11
02-Jun-11
08-Jun-11 A
15-Jun-11 A
A1610
Instrument Index IFC
7 14-Sep-11
25-Sep-11
14-Sep-11
22-Sep-11
74 31-Mar-11
09-Jun-11
31-Mar-11 A
26-Jun-11
MRQ's
2011 A M J Jul A S O N D
A3640
INSTRUMENTATION INSTRUME
Page 7 of 64
A3330
HIPPS MRQ
5 31-Mar-11
07-Apr-11
01-Apr-11 A
03-Apr-11 A
A3340
Electro hydraulic wellhead control panel MRQ
5 04-Apr-11
12-Apr-11
31-Mar-11 A
07-Apr-11 A
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
10 03-Apr-11
17-Apr-11
02-Apr-11 A
10-Apr-11 A
Instrument commodities MRQ (HIPPS , Multiphase Flow Meter .....)
A3350
Multi phase flow meter MRQ
5 03-Apr-11
10-Apr-11
03-Apr-11 A
10-Apr-11 A
A3360
Wing valves MRQ
5 06-Apr-11
13-Apr-11
03-Apr-11 A
10-Apr-11 A
A3370
Choke valves MRQ
5 06-Apr-11
13-Apr-11
03-Apr-11 A
10-Apr-11 A
A5710
Instrument & Mechanical bulk material MRQ
5 26-May-11
02-Jun-11
25-Apr-11 A
03-May-11 A
A3380
Loose instrument MRQ
9 18-May-11
25-May-11
25-May-11 A
06-Jun-11 A
A5720
Junction boxes MRQ
0 02-Jun-11
09-Jun-11
25-May-11 A
06-Jun-11 A
A3390
Instrument cable and cable glands MRQ
22 16-May-11
23-May-11
25-May-11 A
23-Jun-11 A
A2310
Instrument commodities MRQ (Trays ,Bulks ,Cables .....)
35 20-Apr-11
09-Jun-11
25-May-11 A
26-Jun-11
A3400
Instrument Cable trays MRQ
20 24-May-11
31-May-11
31-May-11 A
26-Jun-11
A2820
Sand & Corrosion probes MRQ
22 25-May-11
01-Jun-11
25-May-11 A
26-Jun-11
73 24-Apr-11
07-Jul-11
02-Apr-11 A
18-Aug-11
A3430
Multi phase flow meter TER
20 15-May-11
12-Jun-11
28-Apr-11 A
25-May-11 A
A3410
HIPPS TER
20 03-May-11
31-May-11
26-Apr-11 A
09-Jun-11 A
A3440
Wing valves TER
20 16-May-11
13-Jun-11
02-May-11 A
15-Jun-11 A
A3420
Electro hydraulic wellhead control panel TER
20 15-May-11
12-Jun-11
21-Apr-11 A
16-Jun-11 A
A3450
Choke valves TER
20 18-May-11
15-Jun-11
26-Apr-11 A
05-Jul-11
A5950
Instrument & Mechanical bulk material TER
10 19-Jun-11
03-Jul-11
26-May-11 A
14-Jul-11
A3470
Instrument cable and cable glands TER
10 06-Jun-11
20-Jun-11
10-Jul-11
21-Jul-11
A5780
Junction boxes TER
10 23-Jun-11
07-Jul-11
21-Jun-11 A
21-Jul-11
A3460
Loose instrument TER
10 12-Jun-11
26-Jun-11
20-Jun-11 A
24-Jul-11
A3480
Instrument Cable trays TER
25 14-Jun-11
28-Jun-11
26-Jun-11
28-Jul-11
A5870
Sand & Corrosion probes TER
20 16-Jun-11
07-Jul-11
10-Jul-11
04-Aug-11
A2300
Instrument commodities TER's (Trays ,Bulks ,Cables .....)
35 19-May-11
07-Jul-11
26-Jun-11
11-Aug-11
A1340
Instrument commodities TER's (HIPPS , Multiphase Flow Meter .....)
40 24-Apr-11
20-Jun-11
02-Apr-11 A
18-Aug-11
57 16-Jun-11
08-Aug-11
22-Jun-11 A
13-Sep-11
MRP
2011 A M J Jul A S O N D
A1310
TER's
Page 8 of 64
A3510
Multi phase flow meter MRP
5 10-Jul-11
17-Jul-11
22-Jun-11 A
23-Jun-11 A
A3500
Electro hydraulic wellhead control panel MRP
5 12-Jul-11
19-Jul-11
06-Jul-11
12-Jul-11
A3490
HIPPS MRP
5 28-Jun-11
05-Jul-11
07-Jul-11
13-Jul-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Wing valves MRP
5 11-Jul-11
18-Jul-11
24-Jul-11
28-Jul-11
A3530
Choke valves MRP
5 10-Jul-11
17-Jul-11
27-Jul-11
02-Aug-11
A5960
Instrument & Mechanical bulk material MRP
5 24-Jul-11
31-Jul-11
07-Aug-11
11-Aug-11
A5790
Junction boxes MRP
5 28-Jul-11
04-Aug-11
14-Aug-11
18-Aug-11
A3550
Instrument cable and cable glands MRP
5 11-Jul-11
18-Jul-11
14-Aug-11
18-Aug-11
A3540
Loose instrument MRP
5 17-Jul-11
24-Jul-11
15-Aug-11
21-Aug-11
A3560
Cable trays MRP
5 14-Jul-11
21-Jul-11
16-Aug-11
22-Aug-11
A5380
Instrument cable trays MRP
5 14-Jul-11
21-Jul-11
16-Aug-11
22-Aug-11
A5880
Sand & Corrosion probes MRP
5 01-Aug-11
08-Aug-11
28-Aug-11
06-Sep-11
A1350
Instrument commodities MRP's
35 16-Jun-11
04-Aug-11
24-Jul-11
13-Sep-11
175 04-May-11
22-Feb-12
13-Jun-11 A
08-Mar-12
A3580
Electro hydraulic wellhead control panel Vendor prints review
80 27-Jul-11
29-Nov-11
21-Jul-11
21-Nov-11
A3600
Wing valves Vendor prints review
80 26-Jul-11
28-Nov-11
04-Aug-11
06-Dec-11
A6120
Shutdown and blowdown valves Vendor prints review
170 04-May-11
10-Jan-12
13-Jun-11 A
07-Dec-11
A3590
Multi phase flow meter Vendor prints review
100 25-Jul-11
25-Dec-11
10-Jul-11
07-Dec-11
A5970
Instrument & Mechanical bulk material Vendor prints review
70 08-Aug-11
24-Nov-11
21-Aug-11
07-Dec-11
A3610
Choke valves Vendor prints review
80 25-Jul-11
24-Nov-11
11-Aug-11
13-Dec-11
A5800
Junction boxes Vendor prints review
70 14-Aug-11
30-Nov-11
28-Aug-11
14-Dec-11
A3620
Loose instrument Vendor prints review
70 01-Aug-11
17-Nov-11
04-Sep-11
18-Dec-11
A5770
Instrument cable trays Vendor prints review
70 31-Jul-11
15-Nov-11
04-Sep-11
18-Dec-11
A5890
Sand & Corrosion probes Vendor prints review
70 16-Aug-11
05-Dec-11
11-Sep-11
25-Dec-11
A3630
Instrument cable and cable glands Vendor prints review
80 26-Jul-11
28-Nov-11
28-Aug-11
28-Dec-11
A3570
HIPPS Vendor prints review
150 13-Jul-11
22-Feb-12
24-Jul-11
01-Mar-12
A1360
Vendor prints Review
120 04-Aug-11
01-Feb-12
14-Sep-11
08-Mar-12
239 03-Apr-11
01-Feb-12
03-Apr-11 A
01-Feb-12
120 04-Apr-11
26-Sep-11
04-Apr-11 A
25-Sep-11
MECHANICAL MECHANIC Technical Lists
2011 A M J Jul A S O N D
A3520
Vendor pr prints review
Page 9 of 64
A1050
Issue motor load list 1st issue
10 04-Apr-11
19-Apr-11
04-Apr-11 A
14-Apr-11 A
A6320
Issue motor load list 2nd issue
0 07-Jul-11
21-Jul-11
14-Jun-11 A
23-Jun-11 A
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
A5480
Handling Study
A2390
Issue motor load list IFF
MRQ's
Original BL Project Duration Start
BL Project Finish
Start
Finish
0 02-May-11
09-May-11
26-Jun-11
26-Jun-11
10 12-Sep-11
26-Sep-11
12-Sep-11
25-Sep-11
84 03-Apr-11
28-Jul-11
03-Apr-11 A
28-Jul-11
5 06-Apr-11
13-Apr-11
03-Apr-11 A
10-Apr-11 A
10 03-Apr-11
17-Apr-11
03-Apr-11 A
25-Apr-11 A
Turret crane MRQ
A1060
Mechanical commodities MRQ's (Excluding Monorail crane)
A3650
Service water pump MRQ
5 18-Apr-11
25-Apr-11
18-Apr-11 A
25-Apr-11 A
A3680
Monorail crane MRQ
5 21-Jul-11
28-Jul-11
24-Jul-11
28-Jul-11
84 08-May-11
06-Sep-11
20-Apr-11 A
06-Sep-11
A3710
Turret crane TER
20 15-May-11
12-Jun-11
20-Apr-11 A
04-May-11 A
A3690
Service water pump TER
15 17-May-11
07-Jun-11
10-May-11 A
03-Jul-11
A1070
Mechanical commodities TER (Excluding Monorail crane)
25 08-May-11
12-Jun-11
20-Apr-11 A
04-Jul-11
A3720
Monorail crane TER
15 11-Aug-11
06-Sep-11
14-Aug-11
06-Sep-11
92 10-Jul-11
10-Oct-11
10-May-11 A
10-Oct-11
5 10-Jul-11
17-Jul-11
10-May-11 A
15-Jun-11 A
10 10-Jul-11
24-Jul-11
21-Jul-11
03-Aug-11
MRP A3750
Turret crane MRP
A1100
Mechanical commodities MRP
A3730
Service water pump MRP
5 11-Jul-11
18-Jul-11
28-Jul-11
03-Aug-11
A3760
Monorail crane MRP
3 04-Oct-11
10-Oct-11
05-Oct-11
10-Oct-11
181 04-May-11
01-Feb-12
26-May-11 A
01-Feb-12
Vendor pr prints review A6330
Receiving final weights and dimensions for mechanical equipment
A3810
Micro Turbine Vendor prints review
180 04-May-11
24-Jan-12
26-May-11 A
22-Nov-11
A3820
Emergency GeneratorVendor prints review
160 04-May-11
24-Jan-12
12-Jun-11 A
05-Dec-11
A3790
Turret crane crane Vendor prints review
100 25-Jul-11
25-Dec-11
10-Jul-11
07-Dec-11
A3770
Service water pump Vendor prints review
80 26-Jul-11
28-Nov-11
14-Aug-11
14-Dec-11
A1120
Vendor prints review
100 25-Jul-11
25-Dec-11
15-Aug-11
12-Jan-12
A3800
Monorail crane Vendor prints review
80 04-Oct-11
01-Feb-12
05-Oct-11
01-Feb-12
OFFSHORE OFFSHOR
155 31-Mar-11
05-Dec-11
10-Apr-11 A
04-Dec-11
Drawings
126 30-May-11
05-Dec-11
30-May-11 A
04-Dec-11
10 30-May-11
13-Jun-11
30-May-11 A
13-Jun-11 A
A2350
Tray / Piping Supports Drawings IFD
0 20-Sep-11
2011 A M J Jul A S O N D
A3670
TER's
Page 10 of 64
21-Sep-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
A5340
Tray / Piping Supports Drawings IFC
Model
Original BL Project Duration Start
BL Project Finish
Start
Finish
10 20-Nov-11
05-Dec-11
20-Nov-11
04-Dec-11
145 18-Apr-11
20-Nov-11
18-Apr-11 A
17-Nov-11
Generate PDS Modeling For Topsides
20 18-Apr-11
17-May-11
18-Apr-11 A
17-May-11 A
A5360
Finalize PDS Modeling For Topsides based on Tecnomare IFC dw...
15 24-Oct-11
20-Nov-11
24-Oct-11
17-Nov-11
5 24-Apr-11
28-Apr-11
10-Apr-11 A
14-Apr-11 A
5 24-Apr-11
28-Apr-11
10-Apr-11 A
14-Apr-11 A
20 01-Jun-11
28-Jun-11
22-May-11 A
03-Jul-11
20 01-Jun-11
28-Jun-11
22-May-11 A
03-Jul-11
5 20-Jul-11
26-Jul-11
25-Jul-11
31-Jul-11
5 20-Jul-11
26-Jul-11
25-Jul-11
31-Jul-11
60 31-Mar-11
26-Jun-11
26-Jun-11
20-Sep-11
60 31-Mar-11
26-Jun-11
26-Jun-11
20-Sep-11
261 06-Apr-11
11-May-12
03-Apr-11 A
21-Apr-12
261 06-Apr-11
28-Apr-12
03-Apr-11 A
21-Apr-12
261 06-Apr-11
28-Apr-12
03-Apr-11 A
21-Apr-12
87 06-Apr-11
02-Aug-11
03-Apr-11 A
07-Aug-11
A1490
Survival module MRQ
TER's A1500
Survival module TER
MRP A1510
Survival module MRP
Vendor pr prints review A1530
Vendor prints review
W.P.3: PROCUREMENT PRO SERVICES & MATERIAL SUPPLY EQUIPMENT EQUIPMEN ENPPI LO LONG LEAD ITEMS (Cranes ,Chemical unjec.,Fire protec. , Survival M... PURCHASING PURCHA
2011 A M J Jul A S O N D
A5350
MRQ's
Page 11 of 64
A3860
Chemical injection package Bidding
15 06-Apr-11
27-Apr-11
06-Apr-11 A
18-Apr-11 A
A4610
Turret crane Bidding
20 13-Apr-11
12-May-11
10-Apr-11 A
20-Apr-11 A
A4360
Electro hydraulic wellhead control panel Bidding
15 14-Apr-11
15-May-11
07-Apr-11 A
21-Apr-11 A
A4350
HIPPS Bidding
15 07-Apr-11
28-Apr-11
03-Apr-11 A
26-Apr-11 A
A3870
Fire protection system Bidding
10 13-Apr-11
26-Apr-11
13-Apr-11 A
26-Apr-11 A
A4370
Multi phase flow meter Bidding
20 10-Apr-11
09-May-11
10-Apr-11 A
28-Apr-11 A
A2080
Bidding (Multi phase flow , Chemical unjec.,Fire protec. , Survival ...
30 19-Apr-11
31-May-11
19-Apr-11 A
22-May-11 A
A4710
Survival module Bidding
22 02-May-11
31-May-11
14-Apr-11 A
22-May-11 A
A5140
Turret crane Issue Fax of commitment
3 12-Jun-11
10-Jul-11
25-May-11 A
29-May-11 A
B1040
Turret crane Issue PO
5 17-Jul-11
24-Jul-11
15-Jun-11 A
21-Jun-11 A
A5130
Multi phase flow meter Issue Fax of commitment
20 12-Jun-11
10-Jul-11
25-May-11 A
21-Jun-11 A
A4860
Chemical injection package Issue Fax of commitment
15 19-Jun-11
10-Jul-11
12-Jun-11 A
30-Jun-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Multi phase flow meter Issue PO
6 17-Jul-11
24-Jul-11
26-Jun-11
03-Jul-11
A5250
Electro hydraulic wellhead control panel Issue Fax of commitment
8 14-Jun-11
12-Jul-11
26-Jun-11
05-Jul-11
A5120
HIPPS Issue Fax of commitment
20 31-May-11
28-Jun-11
20-Jun-11 A
06-Jul-11
B1050
Chemical injection package Issue PO
1 17-Jul-11
24-Jul-11
10-Jul-11
10-Jul-11
B1010
HIPPS Issue PO
0 05-Jul-11
12-Jul-11
14-Jul-11
14-Jul-11
A5330
Fire protection system Issue Fax of commitment
9 19-Jun-11
07-Jul-11
06-Jul-11
18-Jul-11
A5150
Survival module Issue Fax of commitment
15 29-Jun-11
19-Jul-11
04-Jul-11
24-Jul-11
A1020
Fire protection system Issue PO
5 17-Jul-11
21-Jul-11
26-Jul-11
01-Aug-11
A2090
Issue Fax of commitments (Multi phase flow , Chemical unjec.,Fir...
30 08-Jun-11
19-Jul-11
03-Apr-11 A
04-Aug-11
B1030
Survival module Issue PO
5 27-Jul-11
02-Aug-11
01-Aug-11
07-Aug-11
267 28-Jun-11
24-Mar-12
25-Jun-11
17-Mar-12
A4450
Multi phase flow meter Fabrication up to release for shipment
180 10-Jul-11
06-Jan-12
25-Jun-11
21-Dec-11
A3920
Chemical injection package Fabrication up to release for shipment
180 10-Jul-11
06-Jan-12
01-Jul-11
27-Dec-11
A4720
Survival module Fabrication up to release for shipment
160 20-Jul-11
26-Dec-11
25-Jul-11
31-Dec-11
A4440
Electro hydrolic wellhead control panel Fabrication up to release fo...
180 12-Jul-11
08-Jan-12
06-Jul-11
01-Jan-12
A3930
Fire protection system Fabrication up to release for shipment
170 08-Jul-11
03-Jan-12
19-Jul-11
04-Jan-12
A2100
Fabrication up to release for shipment (Multi phase flow , Chemica...
200 29-Jun-11
14-Jan-12
26-Jun-11
11-Jan-12
A4650
Turret crane Fabrication up to release for shipment
240 10-Jul-11
06-Mar-12
25-Jun-11
19-Feb-12
A2260
Fabrication up to release for shipment (HIPPS)
255 28-Jun-11
24-Mar-12
07-Jul-11
17-Mar-12
144 30-Nov-11
28-Apr-12
30-Nov-11
21-Apr-12
SHIPPING SHIPPIN
2011 A M J Jul A S O N D
A1000
FABRICATION FABRICA
Page 12 of 64
A4480
Multi phase flow meter Shipping
21 06-Jan-12
27-Jan-12
22-Dec-11
11-Jan-12
A5210
Chemical injection package Shipping
21 06-Jan-12
27-Jan-12
28-Dec-11
17-Jan-12
A4730
Survival module Shipping
21 27-Dec-11
16-Jan-12
01-Jan-12
21-Jan-12
A4470
Electro hydraulic wellhead control panel Shipping
21 08-Jan-12
29-Jan-12
02-Jan-12
22-Jan-12
A5170
Multi phase flow meter Custom clearance & inland transportation
14 27-Jan-12
10-Feb-12
12-Jan-12
25-Jan-12
A2110
Shipping (Multi phase flow ,Chemical unjec.,Fire protec. , Survival...
60 30-Nov-11
29-Jan-12
30-Nov-11
28-Jan-12
A3990
Fire protection system Shipping
21 04-Jan-12
24-Jan-12
08-Jan-12
28-Jan-12
A3980
Chemical injection package Custom clearance & inland transportat...
14 27-Jan-12
10-Feb-12
18-Jan-12
31-Jan-12
A5200
Survival module Custom clearance & inland transportation
14 17-Jan-12
30-Jan-12
22-Jan-12
04-Feb-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Electro hydraulic wellhead control panel Custom clearance & inla...
14 29-Jan-12
12-Feb-12
23-Jan-12
05-Feb-12
A2120
Custom clearance & inland transportation (Multi phase flow ,Che...
45 29-Dec-11
12-Feb-12
29-Dec-11
11-Feb-12
A5190
Fire protection system Custom clearance & inland transportation
14 25-Jan-12
07-Feb-12
29-Jan-12
11-Feb-12
A4690
Turret crane Shipping
14 06-Mar-12
20-Mar-12
20-Feb-12
04-Mar-12
A5180
Turret crane Custom clearance & inland transportation
14 20-Mar-12
03-Apr-12
05-Mar-12
18-Mar-12
A4460
HIPPS Shipping
21 24-Mar-12
14-Apr-12
18-Mar-12
07-Apr-12
A2280
HIPPS Custom clearance & inland transportation
14 14-Apr-12
28-Apr-12
08-Apr-12
21-Apr-12
226 12-Apr-11
07-Mar-12
12-Apr-11 A
07-Mar-12
129 12-Apr-11
17-Oct-11
12-Apr-11 A
17-Oct-11
PURCHASING PURCHA A3880
Safety equipment and life saving Bidding
10 12-Apr-11
26-Apr-11
12-Apr-11 A
26-Apr-11 A
A3910
Service water pumps Bidding
15 25-Apr-11
17-May-11
25-Apr-11 A
10-May-11 A
A3900
Flame arrestor Bidding
15 27-Apr-11
19-May-11
17-Apr-11 A
19-May-11 A
A3890
Vent stack tips Bidding
20 09-May-11
06-Jun-11
09-May-11 A
01-Jun-11 A
B1060
Electro hydraulic wellhead control panel Issue PO
5 19-Jul-11
26-Jul-11
13-Jul-11
19-Jul-11
A1370
Bidding (Service pumps,Flame arrestor,Vent ,....).
25 02-May-11
06-Jun-11
25-Apr-11 A
21-Jul-11
A4900
Service water pumps Issue Fax of commitment
18 13-Jun-11
11-Jul-11
04-Jul-11
27-Jul-11
A4870
Safety equipment and life saving Issue Fax of commitment
20 12-Jun-11
10-Jul-11
10-Jul-11
04-Aug-11
B1080
Service water pumps Issue PO
5 18-Jul-11
25-Jul-11
04-Aug-11
10-Aug-11
A4620
Monorail crane Bidding
10 28-Jul-11
11-Aug-11
31-Jul-11
11-Aug-11
A4890
Flame arrestor Issue Fax of commitment
20 23-Jun-11
21-Jul-11
24-Jul-11
18-Aug-11
B1070
Safety equipment and life saving Issue PO
5 17-Jul-11
24-Jul-11
14-Aug-11
18-Aug-11
A1380
Issue Fax of commitments(Service pumps,Flame arrestor,Vent ,....).
25 29-Jun-11
03-Aug-11
20-Jul-11
23-Aug-11
A4880
Vent stack tips Issue Fax of commitment
20 06-Jul-11
03-Aug-11
27-Jul-11
23-Aug-11
B1090
Flame arrestor Issue PO
5 28-Jul-11
04-Aug-11
28-Aug-11
06-Sep-11
B1100
Issue POs (HCU.,Sea water pumps....).
25 13-Jul-11
17-Aug-11
03-Aug-11
11-Sep-11
B1110
Vent stack tips Issue PO
5 10-Aug-11
17-Aug-11
05-Sep-11
11-Sep-11
A5230
Monorail crane Issue Fax of commitment
20 06-Sep-11
04-Oct-11
07-Sep-11
04-Oct-11
B1120
Monorail crane Issue PO
5 10-Oct-11
17-Oct-11
11-Oct-11
17-Oct-11
189 10-Jul-11
01-Feb-12
28-Jul-11
01-Feb-12
FABRICATION FABRICA
2011 A M J Jul A S O N D
A5700
OTHER E EQUIPMENT (Service pumps,Flame arrestor,Vent ,....).
Page 13 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Service water pump Fabrication up to release for shipment
140 11-Jul-11
28-Nov-11
28-Jul-11
14-Dec-11
A3950
Vent stack tips Fabrication up to release for shipment
120 08-Aug-11
06-Dec-11
29-Aug-11
26-Dec-11
A3960
Flame arrestorFabrication up to release for shipment
130 21-Jul-11
28-Nov-11
19-Aug-11
26-Dec-11
A1390
Fabrication up to release for shipment (Service pumps,Flame arre...
150 10-Jul-11
07-Dec-11
05-Aug-11
01-Jan-12
A3940
Safety equipment and life saving Fabrication up to release for ship...
150 10-Jul-11
07-Dec-11
05-Aug-11
01-Jan-12
A4660
Monorail crane Fabrication up to release for shipment
120 04-Oct-11
01-Feb-12
05-Oct-11
01-Feb-12
88 15-Nov-11
07-Mar-12
11-Dec-11
07-Mar-12
A4670
Service water pump Shipping
21 28-Nov-11
19-Dec-11
15-Dec-11
04-Jan-12
A4010
Vent stack tips Shipping
21 06-Dec-11
27-Dec-11
27-Dec-11
16-Jan-12
A4020
Flame arrestor Shipping
21 28-Nov-11
19-Dec-11
27-Dec-11
16-Jan-12
A6030
Service water pump Custom clearance & inland transportation
14 21-Dec-11
04-Jan-12
07-Jan-12
20-Jan-12
A4000
Safety equipment and life saving Shipping
21 07-Dec-11
28-Dec-11
02-Jan-12
22-Jan-12
A1400
Shipping (Service pumps,Flame arrestor,Vent ,....).
50 15-Nov-11
04-Jan-12
11-Dec-11
29-Jan-12
A5510
Flame arrestor Custom clearance & inland transportation
14 19-Dec-11
02-Jan-12
17-Jan-12
30-Jan-12
A5520
Vent stack tips Custom clearance & inland transportation
14 27-Dec-11
10-Jan-12
17-Jan-12
30-Jan-12
A5500
Safety equipment and life saving Custom clearance & inland trans...
14 28-Dec-11
11-Jan-12
23-Jan-12
05-Feb-12
A1710
Custom clearance & inland transportation (Service pumps,Flame a...
35 14-Dec-11
18-Jan-12
09-Jan-12
12-Feb-12
A4700
Monorail crane Shipping
21 01-Feb-12
22-Feb-12
02-Feb-12
22-Feb-12
A6040
Monorail crane Custom clearance & inland transportation
14 22-Feb-12
07-Mar-12
23-Feb-12
07-Mar-12
318 19-Apr-11
26-Jan-12
29-Apr-11 A
01-Mar-12
307 19-Apr-11
15-Dec-11
29-Apr-11 A
15-Dec-11
PETROBEL LONG LEAD ITEMS PETROBE FABRICATION FABRICA
2011 A M J Jul A S O N D
A4630
SHIPPING SHIPPIN
Page 14 of 64
A6150
Manual Valves Fabrication up to release for shipment
240 19-Apr-11
15-Dec-11
23-Jun-11 A
12-Dec-11
A2160
Fabrication up to release for shipment
240 19-Apr-11
15-Dec-11
25-May-11 A
15-Dec-11
A4040
Micro Turbine Fabrication up to release for shipment
240 19-Apr-11
15-Dec-11
26-May-11 A
15-Dec-11
A4050
Diesel generator Fabrication up to release for shipment
240 19-Apr-11
15-Dec-11
20-Jun-11 A
15-Dec-11
A4060
E&I Module Fabrication up to release for shipment
240 19-Apr-11
15-Dec-11
21-Jun-11 A
15-Dec-11
A4070
Production Manifold Fabrication up to release for shipment
240 19-Apr-11
15-Dec-11
26-May-11 A
15-Dec-11
A4080
Shutdown and blowdown valves Fabrication up to release for ship...
240 19-Apr-11
15-Dec-11
29-Apr-11 A
15-Dec-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
SHIPPING SHIPPIN
Original BL Project Duration Start
BL Project Finish
Start
Finish
77 15-Dec-11
26-Jan-12
16-Dec-11
01-Mar-12
Micro Turbine Custom clearance & inland transportation
14 12-Jan-12
26-Jan-12
16-Dec-11
29-Dec-11
A6060
Diesel generator Custom clearance & inland transportation
14 12-Jan-12
26-Jan-12
16-Dec-11
29-Dec-11
A4130
Shutdown and blowdown valves Shipping
21 15-Dec-11
12-Jan-12
16-Dec-11
05-Jan-12
A6160
Manual Valves Shipping
21 15-Dec-11
05-Jan-12
16-Dec-11
05-Jan-12
A4110
E&I Module Shipping
28 15-Dec-11
12-Jan-12
16-Dec-11
12-Jan-12
A4120
Production Manifold Shipping
28 15-Dec-11
12-Jan-12
16-Dec-11
12-Jan-12
A6090
Shutdown and blowdown valves & inland transportation
14 12-Jan-12
26-Jan-12
06-Jan-12
19-Jan-12
A6170
Manual Valves & inland transportation
14 05-Jan-12
19-Jan-12
06-Jan-12
19-Jan-12
A4090
Micro Turbine Shipping
28 15-Dec-11
12-Jan-12
30-Dec-11
26-Jan-12
A4100
Diesel generator Shipping
28 15-Dec-11
12-Jan-12
30-Dec-11
26-Jan-12
A6070
E&I Module Custom clearance & inland transportation
14 12-Jan-12
26-Jan-12
13-Jan-12
26-Jan-12
A6080
Production Manifold Custom clearance & inland transportation
14 12-Jan-12
26-Jan-12
13-Jan-12
26-Jan-12
A2170
Shipping
35 15-Dec-11
19-Jan-12
20-Jan-12
23-Feb-12
A2180
Custom clearance & inland transportation
25 01-Jan-12
26-Jan-12
06-Feb-12
01-Mar-12
259 13-Apr-11
11-May-12
09-Apr-11 A
21-Apr-12
111 13-Apr-11
25-Aug-11
09-Apr-11 A
15-Sep-11
PURCHASING PURCHA
2011 A M J Jul A S O N D
A6050
E&I BULK
Page 15 of 64
A5390
Electrical Cable trays Bidding
10 02-May-11
16-May-11
10-Apr-11 A
20-Apr-11 A
A4240
Electrical Cables Bidding
10 09-May-11
23-May-11
09-Apr-11 A
25-Apr-11 A
A4390
Choke valves Bidding
20 13-Apr-11
12-May-11
10-Apr-11 A
26-Apr-11 A
A4380
Wing valves Bidding
20 13-Apr-11
12-May-11
10-Apr-11 A
02-May-11 A
A4250
Navigation aids system Bidding
10 16-May-11
30-May-11
26-Apr-11 A
16-May-11 A
A5980
Instrument & Mechanical bulk material Bidding
10 05-Jun-11
19-Jun-11
03-May-11 A
26-May-11 A
A5070
Electrical Cable trays Issue Fax of commitments
15 19-Jun-11
10-Jul-11
02-May-11 A
30-May-11 A
A4400
Loose instrument Bidding
10 29-May-11
12-Jun-11
09-Jun-11 A
20-Jun-11 A
A5810
Junction boxes Bidding
10 09-Jun-11
23-Jun-11
07-Jun-11 A
20-Jun-11 A
A4420
Instrument Cable trays Bidding
10 31-May-11
14-Jun-11
23-Jun-11 A
26-Jun-11
A5080
Electrical Cables Issue Fax of commitments
6 22-Jun-11
13-Jul-11
26-Jun-11
03-Jul-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Page 16 of 64
2011 A M J Jul A S O N D
A4410
Instrument cable and cable glands Bidding
10 23-May-11
06-Jun-11
26-Jun-11
07-Jul-11
A4260
Lighting material Bidding
10 25-May-11
08-Jun-11
22-Jun-11 A
07-Jul-11
A5900
Sand & Corrosion probes Bidding
10 02-Jun-11
16-Jun-11
27-Jun-11 A
07-Jul-11
A6260
Earthing material Bidding
10 06-Jun-11
20-Jun-11
21-Jun-11 A
07-Jul-11
C1040
Electrical Cables P.O
5 20-Jul-11
27-Jul-11
04-Jul-11
10-Jul-11
A1880
Bidding
35 09-May-11
27-Jun-11
20-Apr-11 A
11-Jul-11
C1020
Electrical Cable trays P.O
5 17-Jul-11
24-Jul-11
06-Jul-11
12-Jul-11
A5030
Wing valves Issue Fax of commitments
20 13-Jun-11
11-Jul-11
26-Jun-11
21-Jul-11
A5040
Choke valves Issue Fax of commitments
15 19-Jun-11
10-Jul-11
06-Jul-11
26-Jul-11
A5100
Navigation aids system Issue Fax of commitments
15 27-Jun-11
18-Jul-11
11-Jul-11
31-Jul-11
A5990
Instrument & Mechanical bulk material Issue Fax of commitments
15 03-Jul-11
24-Jul-11
17-Jul-11
04-Aug-11
C1000
Wing valves P.O
5 18-Jul-11
25-Jul-11
31-Jul-11
04-Aug-11
C1010
Choke valves P.O
5 17-Jul-11
24-Jul-11
03-Aug-11
09-Aug-11
A5060
Instrument cable and cable glands Issue Fax of commitments
15 20-Jun-11
11-Jul-11
24-Jul-11
11-Aug-11
A5830
Junction boxes Issue Fax of commitments
15 07-Jul-11
28-Jul-11
24-Jul-11
11-Aug-11
A5050
Loose instrument Issue Fax of commitments
15 26-Jun-11
17-Jul-11
25-Jul-11
14-Aug-11
A5090
Instrument Cable trays Issue Fax of commitments
10 30-Jun-11
14-Jul-11
02-Aug-11
15-Aug-11
C1060
Navigation aids system P.O
5 26-Jul-11
02-Aug-11
09-Aug-11
15-Aug-11
C1030
Instrument & Mechanical bulk material P.O
5 31-Jul-11
07-Aug-11
14-Aug-11
18-Aug-11
A5110
Lighting material Issue Fax of commitments
15 06-Jul-11
27-Jul-11
07-Aug-11
25-Aug-11
A5910
Sand & Corrosion probes Issue Fax of commitments
15 11-Jul-11
01-Aug-11
07-Aug-11
25-Aug-11
A6270
Earthing material Issue Fax of commitments
15 18-Jul-11
08-Aug-11
07-Aug-11
25-Aug-11
C1070
Instrument cable and cable glands P.O
5 18-Jul-11
25-Jul-11
21-Aug-11
25-Aug-11
C1050
Junction boxes P.O
5 04-Aug-11
11-Aug-11
21-Aug-11
25-Aug-11
A1890
E&I Bulk issue Fax of commitments
30 14-Jul-11
25-Aug-11
18-Jul-11
28-Aug-11
C1090
Loose instrument P.O
5 24-Jul-11
31-Jul-11
22-Aug-11
28-Aug-11
C1100
Instrument Cable trays P.O
5 21-Jul-11
28-Jul-11
23-Aug-11
29-Aug-11
C1080
Lighting material P.O
5 15-Aug-11
22-Aug-11
07-Sep-11
13-Sep-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Sand & Corrosion probes P.O
5 08-Aug-11
15-Aug-11
07-Sep-11
13-Sep-11
C1120
Earthing material P.O
5 17-Aug-11
24-Aug-11
11-Sep-11
15-Sep-11
267 10-Jul-11
06-Apr-12
25-Jun-11
17-Mar-12
100 10-Jul-11
18-Oct-11
25-Jun-11
02-Oct-11
A4530
Electrical Cable trays Fabrication up to release for shipment
A6000
Instrument & Mechanical bulk material Fabrication up to release fo...
90 24-Jul-11
01-Nov-11
05-Aug-11
02-Nov-11
A5820
Junction boxes Fabrication up to release for shipment
90 28-Jul-11
05-Nov-11
12-Aug-11
09-Nov-11
A4280
Instrument Cable trays Fabrication up to release for shipment
90 14-Jul-11
22-Oct-11
16-Aug-11
13-Nov-11
A4270
Electrical Cables Fabrication up to release for shipment
140 17-Jul-11
04-Dec-11
06-Jul-11
22-Nov-11
A4520
Instrument cable and cable glands Fabrication up to release for shi...
120 11-Jul-11
28-Nov-11
12-Aug-11
09-Dec-11
A4290
Navigation aids system Fabrication up to release for shipment
140 18-Jul-11
05-Dec-11
01-Aug-11
18-Dec-11
A4300
Lighting material Fabrication up to release for shipment
120 27-Jul-11
14-Dec-11
26-Aug-11
23-Dec-11
A6280
Earthing material Fabrication up to release for shipment
120 08-Aug-11
26-Dec-11
26-Aug-11
23-Dec-11
A5920
Sand & Corrosion probes Fabrication up to release for shipment
135 01-Aug-11
29-Dec-11
26-Aug-11
07-Jan-12
A4510
Loose instrument Fabrication up to release for shipment
155 17-Jul-11
13-Jan-12
15-Aug-11
16-Jan-12
A1900
E&I Bulk Fabrication up to release for shipment
180 20-Jul-11
16-Jan-12
22-Jul-11
17-Jan-12
A4500
Choke valves Fabrication up to release for shipment
210 10-Jul-11
05-Apr-12
27-Jul-11
21-Feb-12
A4490
Wing valves Fabrication up to release for shipment
240 11-Jul-11
06-Apr-12
22-Jul-11
17-Mar-12
136 18-Oct-11
11-May-12
03-Oct-11
21-Apr-12
SHIPPING
2011 A M J Jul A S O N D
C1110
FABRICATION FABRICA
Page 17 of 64
A4320
Electrical Cable trays Shipping
21 18-Oct-11
08-Nov-11
03-Oct-11
23-Oct-11
A4580
Electrical Cable trays Custom clearance & inland transportation
14 08-Nov-11
22-Nov-11
24-Oct-11
06-Nov-11
A5750
Instrument Cable trays Shipping
7 22-Oct-11
29-Oct-11
14-Nov-11
20-Nov-11
A6010
Instrument & Mechanical bulk material Shipping
21 01-Nov-11
22-Nov-11
03-Nov-11
23-Nov-11
A1910
1st batch of the E&I Bulk Shipping
21 05-Nov-11
26-Nov-11
10-Nov-11
30-Nov-11
A5840
Junction boxes Shipping
21 05-Nov-11
26-Nov-11
10-Nov-11
30-Nov-11
A5760
Instrument Cable trays Custom clearance & inland transportation
14 29-Oct-11
12-Nov-11
21-Nov-11
04-Dec-11
A6020
Instrument & Mechanical bulk material Custom clearance & inland ...
14 22-Nov-11
06-Dec-11
24-Nov-11
07-Dec-11
A4310
Electrical Cables Shipping
21 04-Dec-11
25-Dec-11
23-Nov-11
13-Dec-11
A1920
1st batch of the E&I Bulk Custom clearance & inland transportation
14 26-Nov-11
10-Dec-11
01-Dec-11
14-Dec-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Junction boxes Custom clearance & inland transportation
14 26-Nov-11
10-Dec-11
01-Dec-11
14-Dec-11
A5630
Electrical Cables Custom clearance & inland transportation
14 25-Dec-11
08-Jan-12
14-Dec-11
27-Dec-11
A4570
Instrument cable and cable glands Shipping
21 28-Nov-11
19-Dec-11
10-Dec-11
30-Dec-11
A4330
Navigation aids system Shipping
21 05-Dec-11
26-Dec-11
19-Dec-11
08-Jan-12
A4340
Lighting material Shipping
21 14-Dec-11
04-Jan-12
24-Dec-11
13-Jan-12
A5740
Instrument cable and cable glands Custom clearance & inland tran...
14 19-Dec-11
02-Jan-12
31-Dec-11
13-Jan-12
A5640
Navigation aids system Custom clearance & inland transportation
14 26-Dec-11
09-Jan-12
09-Jan-12
22-Jan-12
A6300
Earthing material Shipping
21 26-Dec-11
24-Jan-12
25-Dec-11
22-Jan-12
A5650
Lighting material Custom clearance & inland transportation
14 04-Jan-12
18-Jan-12
14-Jan-12
27-Jan-12
A5930
Sand & Corrosion probes Shipping
21 29-Dec-11
19-Jan-12
08-Jan-12
28-Jan-12
A4560
Loose instrument Shipping
21 13-Jan-12
10-Feb-12
17-Jan-12
06-Feb-12
A5940
Sand & Corrosion probes Custom clearance & inland transportation
14 19-Jan-12
02-Feb-12
29-Jan-12
11-Feb-12
A6290
Earthing material Custom clearance & inland transportation
14 24-Jan-12
14-Feb-12
23-Jan-12
12-Feb-12
A2020
2nd batch of the E&I Bulk Shipping
40 06-Jan-12
15-Feb-12
08-Jan-12
16-Feb-12
A5860
Loose instrument Custom clearance & inland transportation
14 10-Feb-12
24-Feb-12
07-Feb-12
20-Feb-12
A2030
2nd batch of the E&I Bulk Custom clearance & inland transportation
28 02-Feb-12
01-Mar-12
04-Feb-12
02-Mar-12
A6340
Choke valves Shipping
21
22-Feb-12
21-Mar-12
A4540
Wing valves Shipping
21 06-Apr-12
27-Apr-12
18-Mar-12
07-Apr-12
A4550
Choke valves Custom clearance & inland transportation
21 05-Apr-12
26-Apr-12
22-Mar-12
11-Apr-12
A5730
Wing valves Custom clearance & inland transportation
14 27-Apr-12
11-May-12
08-Apr-12
21-Apr-12
220 07-Apr-11
10-Feb-12
07-Apr-11 A
22-Feb-12
PURCHASING PURCHA
2011 A M J Jul A S O N D
A5850
PIPING BULK BU
Page 18 of 64
106 07-Apr-11
27-Jul-11
07-Apr-11 A
07-Sep-11
A4930
Piping Bulk Bidding
15 07-Apr-11
28-Apr-11
07-Apr-11 A
28-Apr-11 A
A5440
Insulation Joint Bidding
20 20-Apr-11
19-May-11
29-May-11 A
30-May-11 A
A1940
Piping Bulk Issue Fax of commitment
14 31-May-11
20-Jun-11
05-Jun-11 A
22-Jun-11 A
A5450
Injection fitting Bidding
20 24-Apr-11
23-May-11
24-Apr-11 A
26-Jun-11
C2000
Piping Bulk P.O
5 27-Jun-11
04-Jul-11
03-Jul-11
07-Jul-11
A5470
Insulation Joint Issue Fax of commitment
20 12-Jun-11
10-Jul-11
25-Jul-11
21-Aug-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
20 15-Jun-11
13-Jul-11
25-Jul-11
21-Aug-11
Injection fitting Issue Fax of commitment
C2010
Insulation Joint P.O
5 17-Jul-11
24-Jul-11
29-Aug-11
07-Sep-11
C2020
Injection fitting P.O
5 20-Jul-11
27-Jul-11
29-Aug-11
07-Sep-11
208 20-Jun-11
06-Jan-12
25-Jun-11
18-Jan-12
A1950
piping Bulk Fabrication up to release for shipment
200 20-Jun-11
06-Jan-12
25-Jun-11
10-Jan-12
A5570
Insulation Joint Fabrication up to release for shipment
150 10-Jul-11
07-Dec-11
22-Aug-11
18-Jan-12
A5580
Injection fitting Fabrication up to release for shipment
150 13-Jul-11
10-Dec-11
22-Aug-11
18-Jan-12
136 10-Oct-11
10-Feb-12
10-Oct-11
22-Feb-12
SHIPPING A1960
1st batch of the piping Bulk Shipping
21 10-Oct-11
31-Oct-11
10-Oct-11
30-Oct-11
A1970
1st batch of the piping Bulk Custom clearance & inland transport...
14 31-Oct-11
14-Nov-11
31-Oct-11
13-Nov-11
A2050
2nd batch of the piping Bulk Shipping
21 17-Nov-11
08-Dec-11
22-Nov-11
12-Dec-11
A2060
2nd batch of the piping Bulk Custom clearance & inland transport...
14 08-Dec-11
22-Dec-11
13-Dec-11
26-Dec-11
A2040
Last batch of the piping Bulk Shipping
21 06-Jan-12
27-Jan-12
11-Jan-12
31-Jan-12
A5590
Insulation Joint Shipping
21 07-Dec-11
28-Dec-11
19-Jan-12
08-Feb-12
A5620
Injection fitting Shipping
21 10-Dec-11
31-Dec-11
19-Jan-12
08-Feb-12
A2070
Last batch of the piping Bulk Custom clearance & inland transport...
14 27-Jan-12
10-Feb-12
01-Feb-12
14-Feb-12
A5600
Insulation Joint Custom clearance & inland transportation
14 28-Dec-11
11-Jan-12
09-Feb-12
22-Feb-12
A5610
Injection fitting Custom clearance & inland transportation
14 31-Dec-11
14-Jan-12
09-Feb-12
22-Feb-12
26 31-Mar-11
30-Apr-11
25-Jun-11
24-Jul-11
26 31-Mar-11
30-Apr-11
25-Jun-11
24-Jul-11
30 02-Jun-12
02-Jul-12
01-Jun-12
30-Jun-12
30 02-Jun-12
02-Jul-12
01-Jun-12
30-Jun-12
315 31-Mar-11
04-Jul-12
28-Mar-11 A
02-Jul-12
W.P.5: DEC DECK & TSF FABRICATION PTJ2200
Deck commisioning (Onshore)
W.P.9: OFF OFFSHORE HOOK-UP, COMMISSIONING AND ASSISTANCE TO STA... A2370
Deck Offshore Commissioning
TECNOMARE TECNOMAR 2
Start of project
TECNOMARE DRIVING MILESTONES TECNOMAR STRUCTURAL STRUCTU
0 31-Mar-11
2011 A M J Jul A S O N D
A5460
FABRICATION FABRICA
Page 19 of 64
31-Mar-11 A
293 31-Mar-11
04-Jun-12
28-Mar-11 A
03-Jun-12
293 31-Mar-11
04-Jun-12
31-Mar-11 A
03-Jun-12
19
Soil Data (PTB)
0 31-Mar-11
31-Mar-11 A
16
input - deck plot plan & equipment list IFD (ENPPI)
0 24-Apr-11
24-Apr-11 A
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Input- T&I contract ITT (PTB)
0 26-Jun-11
26-Jun-11*
64
Pressure Vessels Vendor Print out review (ENPPI)
0 31-Mar-11
26-Jun-11
69
Piping bulk & Valves MRP's (ENPPI)
0 27-Jun-11
03-Jul-11
54
Process Commodities MRP's (ENPPI)
0 29-Aug-11
05-Sep-11
17
input - deck final plot plan & equipment list (ENPPI)
0 21-Sep-11
21-Sep-11
13
input - crane barge (PTB)
0 24-Sep-11
24-Sep-11*
14
input - launching barge for jacket (PTB)
0 24-Sep-11
24-Sep-11*
79
Mechanical Vendor print review (ENPPI)
0 25-Dec-11
15-Jan-12
300
As built Markup documents (PTJ) for Jacket
0 07-May-12
07-May-12*
9
Load out structures
0 10-May-12
09-May-12*
310
As built Markup documents (PTJ) for deck
0 04-Jun-12
03-Jun-12
160 31-Mar-11
23-Nov-11
28-Mar-11 A
22-Nov-11
276
Plot Plan IFD (ENPPI)
0
24-Apr-11
28-Mar-11 A
106
Review of Basic Documents (Consortium feed endorsement)
0
31-Mar-11
31-Mar-11 A
158
SSIV vendor documents (PTB)
0
31-Mar-11
31-Mar-11 A
107
P & ID's ( IFD ) (ENPPI/PTB for LLI)
0
17-Apr-11
27-Apr-11 A
148
fire and gas requirements- HSE philosophy Fire Fighting Safety La...
0
24-Apr-11
02-May-11 A
112
C & E - issue for Design (ENPPI/PTB for LLI)
0
16-May-11
08-May-11 A
206
junction box wiring diagram for control & safety system IFD (ENPPI)
0
09-Jun-11
08-May-11 A
302
T4 for Radio Bridge (PTB)
0
08-Jun-11
08-Jun-11 A
128
Electrical interface with PLC/RTU (I/O list) (ENPPI)
0
30-May-11
08-Jun-11 A
138
Control and safety cable routing IFD (ENPPI)
0
09-Jun-11
20-Jun-11 A
136
Instrument TDS (ENPPI)
0
07-Jun-11
26-Jun-11
208
P & ID's ( IFC) (ENPPI/PTB for LLI)
0
14-Sep-11
13-Sep-11
286
Plot Plan IFC (ENPPI)
0
21-Sep-11
20-Sep-11
117
C & E - Issue for Construction (ENPPI/PTB for LLI)
0
21-Sep-11
20-Sep-11
198
3D model Review 90% Report (ENPPI)
0
23-Nov-11
22-Nov-11
W.P.1: PRO PROJECT MANAGEMENT
444 31-Mar-11
17-Jun-12
2011 A M J Jul A S O N D
59
INSTRUMENTATION INSTRUME
Finish
Page 20 of 64
31-Mar-11 A
15-Jun-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
technical coordination
444 31-Mar-11
17-Jun-12
31-Mar-11 A
15-Jun-12
43
engineering assistance to fab, load out & transportation home office
428 15-Apr-11
17-Jun-12
14-Apr-11 A
15-Jun-12
305
project services
444 31-Mar-11
17-Jun-12
31-Mar-11 A
15-Jun-12
315 31-Mar-11
04-Jul-12
31-Mar-11 A
02-Jul-12
196 31-Mar-11
01-Feb-12
31-Mar-11 A
31-Jan-12
STRUCTURAL STRUCTU
306 31-Mar-11
21-Jun-12
31-Mar-11 A
19-Jun-12
MILESTONES MILESTO
209 31-Mar-11
01-Feb-12
31-Mar-11 A
31-Jan-12
20
weight control
4
jacket main structure AFC dwg.s + MTO
0 31-Mar-11
31-Mar-11 A
6
deck AFC dwg.s + MTO main structure
0 04-Jul-11
12-Jul-11
5
jacket secondary structures AFC dwg.s + MTO
0 31-Jul-11
31-Jul-11*
7
deck AFC + MTO secondary structures (no equip. supports)
0 25-Sep-11
25-Sep-11
28
Weight Control Report 1st issue
0 25-Sep-11
25-Sep-11
8
deck AFC + MTO equip. supports
0 24-Oct-11
23-Oct-11
10
weight control report 2nd issue
0 24-Oct-11
23-Oct-11
11
weight control report 3rd issue
0 01-Feb-12
31-Jan-12
DECK DETAIL DE DESIGN
127 24-Apr-11
24-Oct-11
21-Apr-11 A
23-Oct-11
31
deck in service final analysis
15 24-Apr-11
16-May-11
21-Apr-11 A
09-Jun-11 A
29
deck & helideck lifting final analysis
20 24-Apr-11
23-May-11
21-Apr-11 A
15-Jun-11 A
32
deck seismic analysis
15 16-May-11
06-Jun-11
15-May-11 A
16-Jun-11 A
30
deck & helideck load out & transportation structural analysis updat...
15 23-May-11
13-Jun-11
22-May-11 A
22-Jun-11 A
33
deck & helideck joints local checks
15 13-Jun-11
04-Jul-11
23-Jun-11 A
11-Jul-11
34
deck main structure AFC dwg.s & MTO
50 24-Apr-11
04-Jul-11
24-Apr-11 A
11-Jul-11*
35
deck secondary structures design (no equipment support)
50 04-Jul-11
25-Sep-11
20-Jun-11 A
18-Sep-11
36
deck secondary structure AFC dwg.s & MTO (no equipment support)
100 24-Apr-11
25-Sep-11
24-Apr-11 A
22-Sep-11
45
Deck equipment supports design
15 21-Sep-11
13-Oct-11
21-Sep-11
12-Oct-11
44
Deck equipment supports & AFC dwg and MTO
22 21-Sep-11
24-Oct-11
21-Sep-11
23-Oct-11
178 25-Sep-11
21-Jun-12
25-Sep-11
19-Jun-12
105 25-Sep-11
06-Mar-12
25-Sep-11
06-Mar-12*
ASSISTANCE TO COMPANY ASSISTAN 38
liaison with Certifying Authority
2011 A M J Jul A S O N D
18
W.P.2: ENG ENGINEERING
Page 21 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
39
liason with Marine Warranty Surveyor
FOLLOW-ON OF T&I CONTRACT FOLLOW Analysis Finalization
Original BL Project Duration Start
BL Project Finish
Start
Finish
105 23-Jan-12
21-Jun-12
22-Jan-12
19-Jun-12
293 31-Mar-11
21-Jun-12
21-Apr-11 A
19-Jun-12
101 25-Sep-11
01-Mar-12
25-Sep-11
29-Feb-12
jacket launching naval final analysis
20 25-Sep-11
20-Oct-11
25-Sep-11
20-Oct-11
24
jacket launching structural analysis updating
15 23-Oct-11
10-Nov-11
23-Oct-11
10-Nov-11
25
jacket docking naval final analysis
20 13-Nov-11
08-Dec-11
13-Nov-11
08-Dec-11
27
jacket free floating & upending naval analysis - final analysis
20 01-Feb-12
01-Mar-12
31-Jan-12
29-Feb-12
293 31-Mar-11
21-Jun-12
21-Apr-11 A
19-Jun-12
49
ITT scope of work for T&I Contract
20 31-Mar-11
28-Apr-11
21-Apr-11 A
17-Jul-11
50
technical evaluation of the offers, clarification meetings & KOM
50 26-Jun-11
14-Sep-11
18-Jul-11
06-Oct-11
52
installation - transportation & installation procedures/manuals
39 17-Nov-11
29-Jan-12
16-Nov-11
25-Jan-12
51
post-award assistance
120 15-Sep-11
19-Mar-12
09-Oct-11
11-Apr-12
53
installation - engineering assistance during installation (at home of...
30 10-May-12
21-Jun-12
09-May-12
19-Jun-12
205 31-Mar-11
26-Jan-12
31-Mar-11 A
25-Jan-12
205 31-Mar-11
26-Jan-12
31-Mar-11 A
25-Jan-12
205 31-Mar-11
26-Jan-12
31-Mar-11 A
25-Jan-12
INSTRUMENTATION INSTRUME PLC/RTU - Telecom System CONTROL CONTRO
2011 A M J Jul A S O N D
26
Follow-up
Page 22 of 64
108
Review of PLC/RTU -ICSS Spec's
20 31-Mar-11
28-Apr-11
31-Mar-11 A
28-Apr-11 A
336
Junction Box wiring Diagram for SSIV issue for Design
21 17-Apr-11
17-May-11
14-Apr-11 A
17-May-11 A
246
F&G system layout issue for Design
22 02-May-11
01-Jun-11
21-Apr-11 A
24-May-11 A
156
ESD System Layout- issue for design
22 02-May-11
01-Jun-11
21-Apr-11 A
25-May-11 A
111
Functional / logic diagrams - issue for design
35 26-Apr-11
15-Jun-11
26-Apr-11 A
20-Jun-11 A
346
Junction Box wiring diagram for Seth ESD Pushbuttons issue for d...
26 18-May-11
23-Jun-11
10-May-11 A
22-Jun-11 A
188
Operator console - issue for design
18 29-May-11
22-Jun-11
22-May-11 A
22-Jun-11 A
110
I / O Database - issue for design
17 23-May-11
15-Jun-11
10-May-11 A
26-Jun-11
113
Simplified loop diagrams - issue for design
16 24-May-11
15-Jun-11
25-May-11 A
26-Jun-11
133
ESD/F&G - cable list issue for design
20 01-Jun-11
29-Jun-11
25-May-11 A
26-Jun-11
168
F&G cable routing layout - issue for design
22 09-Jun-11
11-Jul-11
01-Jun-11 A
19-Jul-11
178
ESD Pushbuttons cable routing layout - issue for design
22 09-Jun-11
11-Jul-11
01-Jun-11 A
19-Jul-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Functional / Logic diagrams - issue for construction
19 14-Sep-11
11-Oct-11
13-Sep-11
10-Oct-11
356
Junction Box wiring Diagram for SSIV issue for Construction
18 14-Sep-11
11-Oct-11
14-Sep-11
10-Oct-11
266
F&G system layout issue for Construction
18 21-Sep-11
18-Oct-11
21-Sep-11
17-Oct-11
386
ESD System Layout- issue for construction
18 21-Sep-11
18-Oct-11
21-Sep-11
17-Oct-11
115
I / O database - issue for construction
20 27-Sep-11
25-Oct-11
26-Sep-11
24-Oct-11
118
Simplified loop diagrams - issue for construction
14 12-Oct-11
01-Nov-11
11-Oct-11
31-Oct-11
121
Operator Console Layout - issue for construction
18 25-Oct-11
20-Nov-11
24-Oct-11
17-Nov-11
396
Junction Box wiring diagram for Seth ESD Pushbuttons issue for c...
21 28-Nov-11
26-Dec-11
28-Nov-11
26-Dec-11
236
F&G cable routing layout- issue for construction
23 23-Nov-11
11-Jan-12
22-Nov-11
10-Jan-12
326
ESD Pushbuttons cable routing layout- issue for construction
29 23-Nov-11
19-Jan-12
22-Nov-11
18-Jan-12
131
ESD / F&G - cable list - issue for construction
18 02-Jan-12
26-Jan-12
02-Jan-12
25-Jan-12
105 10-Apr-11
18-Aug-11
10-Apr-11 A
15-Sep-11
256
Review of Telecom Specs
23 10-Apr-11
11-May-11
10-Apr-11 A
10-May-11 A
166
J. B Wiring Diagram for Telecom System for Seth
23 08-May-11
07-Jun-11
10-May-11 A
20-May-11 A
126
Telecom System Layout for Seth
23 28-Apr-11
31-May-11
24-Apr-11 A
24-May-11 A
296
Telecommunication Cables List
20 31-May-11
28-Jun-11
19-May-11 A
21-Jun-11 A
226
Telecom cable routing layout
22 12-Jun-11
12-Jul-11
21-Jun-11 A
19-Jul-11
366
TDS for electrical bulk material/ Telecom Bulks
25 07-Jun-11
12-Jul-11
05-Jul-11
22-Aug-11
196
Electrical Bulk Material Requisition for Telecom Sys. Seth
23 03-Jul-11
16-Aug-11
31-Jul-11
13-Sep-11
306
SOW of Modification on El Gamil Plant
24 04-Jul-11
18-Aug-11
14-Aug-11
15-Sep-11
35 08-Jun-11
28-Jul-11
15-May-11 A
15-Aug-11
RADIO LINK LI ON T4 186
J. B Wiring Diagram for Telecom System for Temsah - 4
23 08-Jun-11
10-Jul-11
15-May-11 A
20-Jul-11
176
Telecom System Layout for Temsah - 4
23 08-Jun-11
10-Jul-11
26-Jun-11
26-Jul-11
297
SOW of Modification of Bridge Platform
24 27-Jun-11
28-Jul-11
20-Jun-11 A
15-Aug-11
114 31-May-11
13-Dec-11
26-Jun-11
13-Dec-11
114 31-May-11
13-Dec-11
26-Jun-11
13-Dec-11
41 07-May-12
04-Jul-12
07-May-12
02-Jul-12
22 07-May-12
05-Jun-12
07-May-12
05-Jun-12
TECHNICAL FOLLOW-UP TECHNIC 122
Vendor Print Review
AS-BUILT DRAWINGS 46
template, piles, jacket
2011 A M J Jul A S O N D
116
TELECOM TELECO
Page 23 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID 47
Activity Name deck, helideck & flare
SUBSEA S SYSTEM 103
Vendor Print Review
W.P.3: PROCUREMENT PRO SERVICES & MATERIAL SUPPLY PLC/RTU
Original BL Project Duration Start
BL Project Finish
Start
Finish
30 04-Jun-12
04-Jul-12
03-Jun-12
02-Jul-12
119 31-Mar-11
28-Sep-11
31-Mar-11 A
27-Sep-11
119 31-Mar-11
28-Sep-11
31-Mar-11 A
27-Sep-11
269 31-Mar-11
29-Apr-12
31-Mar-11 A
26-Apr-12
261 13-Apr-11
29-Apr-12
13-Apr-11 A
26-Apr-12
15 13-Apr-11
04-May-11
13-Apr-11 A
03-May-11 A
Technical Evaluation for PLC/RTU
143
Revised commercial submission by supplier
5 05-May-11
11-May-11
05-May-11 A
11-May-11 A
144
Commercial Evaluation
5 12-May-11
18-May-11
12-May-11 A
18-May-11 A
145
PO issuance for PLC/RTU
9 19-May-11
31-May-11
19-May-11 A
31-May-11 A
195
Submital of C&E IFD , Instrument commodities vendor print review...
0
04-Sep-11
14-Aug-11
185
Submital of I/O list IFD, TDS, JB wiring diag to th PLC/RTU Vendor
0
04-Sep-11
18-Aug-11
376
FAT Test
146
Expediting & Inspection for PLC/RTU
216 137
11 20-Dec-11
22-Jan-12
09-Jan-12
23-Jan-12
133 20-Jun-11
22-Jan-12
15-Jun-11 A
23-Jan-12
Delivery to Construction Yard
28 23-Jan-12
23-Feb-12
24-Jan-12
25-Feb-12
Onshore Precommissioning / Commissioning Assistance
42 11-Mar-12
29-Apr-12
10-Mar-12
26-Apr-12
11-Jan-12
31-Jul-11
19-Jan-12
7 13-Jul-11
24-Jul-11
31-Jul-11
09-Aug-11
10 24-Jul-11
07-Aug-11
09-Aug-11
23-Aug-11
116 13-Jul-11
189
RFQ Issuance for Telecom materials
190
Bidding for Telecom materials
241
Technical Evaluation for Telecom materials
7 07-Aug-11
16-Aug-11
23-Aug-11
01-Sep-11
202
Revised commercial submission by supplier
7 16-Aug-11
25-Aug-11
01-Sep-11
12-Sep-11
213
Commercial Evaluation
5 25-Aug-11
01-Sep-11
12-Sep-11
19-Sep-11
214
PO issuance for Telecom materials
3 01-Sep-11
06-Sep-11
19-Sep-11
22-Sep-11
235
Expediting & Inspection for Telecom materials
56 06-Sep-11
23-Nov-11
22-Sep-11
11-Dec-11
265
Transportation to site
28 23-Nov-11
10-Jan-12
11-Dec-11
18-Jan-12
275
Delivery to yard
GROUT SE SEALS
0
2011 A M J Jul A S O N D
142
TELECOM BULK MATERIALS
Page 24 of 64
11-Jan-12
19-Jan-12
119 31-Mar-11
28-Sep-11
31-Mar-11 A
28-Sep-11
150
Bidding for G S
5 31-Mar-11
07-Apr-11
31-Mar-11 A
07-Apr-11 A
151
Technical Evaluation for G S
5 10-Apr-11
14-Apr-11
10-Apr-11 A
14-Apr-11 A
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Revised commercial submission by supplier
5 17-Apr-11
21-Apr-11
17-Apr-11 A
21-Apr-11 A
153
Commercial Evaluation
5 24-Apr-11
28-Apr-11
24-Apr-11 A
28-Apr-11 A
154
PO issuance for G S
11 02-May-11
16-May-11
02-May-11 A
16-May-11 A
155
Expediting & Inspection for G S
68 17-May-11
31-Aug-11
25-May-11 A
31-Aug-11
165
Transportation to site
20 01-Sep-11
28-Sep-11
01-Sep-11
28-Sep-11
175
Delivery to yard
SHOCK CELLS CE
28-Sep-11
28-Sep-11
117 31-Mar-11
28-Sep-11
31-Mar-11 A
26-Sep-11
5 31-Mar-11
07-Apr-11
31-Mar-11 A
07-Apr-11 A
15 10-Apr-11
28-Apr-11
10-Apr-11 A
28-Apr-11 A
179
RFQ Issuance for Shock Cells
180
Bidding for Shock Cells
191
Technical Evaluation for Shock Cells
7 02-May-11
10-May-11
02-May-11 A
10-May-11 A
192
Revised commercial submission by supplier
5 11-May-11
17-May-11
11-May-11 A
17-May-11 A
203
Commercial Evaluation
7 18-May-11
26-May-11
18-May-11 A
26-May-11 A
204
PO issuance for Shock Cells
3 29-May-11
31-May-11
25-May-11 A
29-May-11 A
225
Expediting & Inspection for Shock Cells
57 01-Jun-11
31-Aug-11
30-May-11 A
29-Aug-11
245
Transportation to site
20 01-Sep-11
28-Sep-11
30-Aug-11
26-Sep-11
255
Delivery to yard
W.P.9: OFF OFFSHORE HOOK-UP, COMMISSIONING AND ASSISTANCE TO STA... ONSHORE FACILITIES
0
28-Sep-11
26-Sep-11
50 19-Apr-12
17-Jun-12
19-Apr-12
17-Jun-12
50 19-Apr-12
17-Jun-12
19-Apr-12
17-Jun-12
A1650
Installation Telephone System Uopgrading in El Gamil Plant
30 19-Apr-12
24-May-12
19-Apr-12*
24-May-12
A1640
Installation of Radio Link Upgrading in El gamil Plant
30 19-Apr-12
24-May-12
19-Apr-12
24-May-12
A1620
Installation of DCS Node Upgrading in El gamil Plant
30 19-Apr-12
24-May-12
19-Apr-12
24-May-12
A1630
Installation of CCTV Upgrading in El gamil Plant
30 19-Apr-12
24-May-12
19-Apr-12
24-May-12
A1040
Connecting cables (Including Emergency, control and F&G signals)
30 13-May-12
17-Jun-12
13-May-12
17-Jun-12
335 31-Mar-11
31-Jul-12
31-Mar-11 A
31-Jul-12
340 31-Mar-11
01-Mar-12
31-Mar-11 A
02-Mar-12
339 31-Mar-11
01-Mar-12
31-Mar-11 A
02-Mar-12
PETROJET PETROJET DRIVING MILESTONES PROCUREMENT PROCURE
2011 A M J Jul A S O N D
152
0
Page 25 of 64
PTJ1000
Structural material 1st & 2 nd batch (jacket primary, pile & deck leg...
0 31-Mar-11
31-Mar-11 A
PTJ1015
Structural material 3 rd batch (PDT) (PTB)
0 28-Apr-11
28-Apr-11 A
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Structural material 4 rd batch, deck primary (main beams, legs, no...
0 21-May-11
30-Apr-11 A
PTJ1020
Structural material 5 th batch (jacket secondary & deck secondary)...
0 31-Aug-11
31-Aug-11*
PTJ1080
Piping bulk material (1st batch) (ENPPI)
0 14-Nov-11
14-Nov-11
PTJ1110
E & I 1st batch) (ENPPI)
0 10-Dec-11
15-Dec-11
PTJ1100
Start receiving equipment (ENPPI)
0 17-Dec-11
12-Jan-12
PTJ1120
Equipment (100%) (PTB)
0
24-Jan-12
24-Jan-12*
PTJ4010
Equipment by (100%) (ENPPI)
0
12-Feb-12
11-Feb-12
PTJ4000
Piping bulk material (Last batch) (ENPPI)
0
10-Feb-12
14-Feb-12
PTJ4020
E & I (Last batch) (ENPPI)
0
01-Mar-12
02-Mar-12
234 31-Mar-11
20-Nov-11
31-Mar-11 A
PTJ150
Pre-drilling template AFC dwg's (by techno)
0 31-Mar-11
31-Mar-11 A
PTJ100
Jacket main structure AFC dwg's (by techno)
0 31-Mar-11
31-Mar-11 A
PTJ110
Deck main structure AFC dwg's (by techno)
0 04-Jul-11
15-Apr-11 A
PTJ140
Jacket secondary structure AFC dwg's (by techno)
0 31-Jul-11
31-Jul-11
PTJ130
E & I AFC dwg's (by ENPPI)
0 16-Nov-11
16-Nov-11
PTJ120
Piping AFC dwg's (by ENPPI)
0 20-Nov-11
18-Nov-11
W.P.1: PRO PROJECT MANAGEMENT PTJ000
Project managment
W.P.2: ENG ENGINEERING JACKET PTJ2170
Jacket main structure mark up drawing drawing
TSF PTJ2240
Rec final weight & dimension for static equipment
PTJ2190
TSF mark up drawing
DECK PTJ2180
Deck structure mark up drawing
W.P.4: SUBSTRUCTURES SUB (PILES, JACKET & PDT) FABRICATION JACKET STRUCTURE S FABRICATION
18-Nov-11
490 31-Mar-11
31-Jul-12
31-Mar-11 A
31-Jul-12
490 31-Mar-11
31-Jul-12
31-Mar-11 A
31-Jul-12
222 15-Sep-11
04-Jun-12
15-Sep-11
02-Jun-12
15 01-Apr-12
17-Apr-12
01-Apr-12
17-Apr-12
15 01-Apr-12
17-Apr-12
01-Apr-12
17-Apr-12
222 15-Sep-11
04-Jun-12
15-Sep-11
02-Jun-12
0
2011 A M J Jul A S O N D
PTJ1010
DESIGN
Page 26 of 64
15-Sep-11
15-Sep-11*
21 10-May-12
04-Jun-12
09-May-12
02-Jun-12
16 10-May-12
29-May-12
09-May-12
27-May-12
16 10-May-12
29-May-12
09-May-12
27-May-12
240 31-Mar-11
15-Mar-12
31-Mar-11 A
15-Mar-12
240 31-Mar-11
15-Mar-12
31-Mar-11 A
15-Mar-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
MAIN STR STRUCTURE FABRICATION General
Original BL Project Duration Start
BL Project Finish
Start
Finish
259 31-Mar-11
23-Feb-12
31-Mar-11 A
29-Jan-12
259 31-Mar-11
23-Feb-12
31-Mar-11 A
29-Jan-12
0 31-Mar-11
PTJ2210 Jacket main structure fabrication finish
0
15-Feb-12
PTJ2230 Jacket weighing
2 22-Feb-12
23-Feb-12
28-Jan-12
29-Jan-12
75 31-Mar-11
22-Jun-11
31-Mar-11 A
29-Jun-11
8 14-Jun-11
22-Jun-11
15-May-11 A
08-Jun-11 A
PTJ5000 PREPARATION OF SKID WAY
20 31-Mar-11
24-Apr-11
31-Mar-11 A
26-Jun-11
LEG A1
67 31-Mar-11
13-Jun-11
31-Mar-11 A
29-Jun-11
45 31-Mar-11
18-May-11
31-Mar-11 A
29-Jun-11
PTJ51 LEG SPLICE FIT UP
9 31-Mar-11
10-Apr-11
31-Mar-11 A
25-Jun-11
PTJ51 CANS FIT UP
8 11-Apr-11
20-Apr-11
11-Apr-11 A
27-Jun-11
PTJ51 LEG SPLICE WELDING & NDT
10 21-Apr-11
04-May-11
23-Apr-11 A
27-Jun-11
PTJ51 CAN WELDING & NDT
12 05-May-11
18-May-11
09-May-11 A
29-Jun-11
41 21-Apr-11
05-Jun-11
23-Apr-11 A
04-Jun-11 A
PTJ50 LEG SPLICE FIT UP
7 21-Apr-11
01-May-11
23-Apr-11 A
31-May-11 A
PTJ51 CANS FIT UP
4 02-May-11
05-May-11
05-May-11 A
31-May-11 A
PTJ51 CONE FIT UP
4 07-May-11
10-May-11
10-May-11 A
01-Jun-11 A
12 11-May-11
24-May-11
15-May-11 A
02-Jun-11 A
PTJ51 CONE WELDING & NDT
5 25-May-11
30-May-11
22-May-11 A
02-Jun-11 A
PTJ51 CAN WELDING & NDT
5 31-May-11
05-Jun-11
19-May-11 A
04-Jun-11 A
PTJ5010 PREPARATION LEG FOR ROW A & B TRIAL FIT
DIM 14 1400
DIM 12 1200
PTJ51 LEG SPLICE WELDING & NDT
DIM 10 1000
2011 A M J Jul A S O N D
PTJ2000 Jacket main structure fabrication start
JACKET LEGS FABRICATION
Page 27 of 64
31-Mar-11 A 21-Jan-12
36 11-May-11
13-Jun-11
15-Apr-11 A
29-Jun-11
PTJ50 CONE WELDING & NDT
5 02-Jun-11
07-Jun-11
07-May-11 A
11-May-11 A
PTJ50 LEG SPLICE WELDING & NDT
6 26-May-11
01-Jun-11
30-Apr-11 A
12-May-11 A
PTJ50 CONE FIT UP
4 22-May-11
25-May-11
18-May-11 A
24-May-11 A
PTJ50 LEG SPLICE FIT UP
5 11-May-11
16-May-11
15-Apr-11 A
02-Jun-11 A
PTJ50 CANS FIT UP
4 17-May-11
21-May-11
21-May-11 A
28-Jun-11
PTJ50 CAN WELDING & NDT
5 08-Jun-11
13-Jun-11
12-May-11 A
29-Jun-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
67 31-Mar-11
13-Jun-11
31-Mar-11 A
28-Jun-11
45 31-Mar-11
18-May-11
31-Mar-11 A
01-Jun-11 A
PTJ53 LEG SPLICE FIT UP
9 31-Mar-11
10-Apr-11
31-Mar-11 A
26-May-11 A
PTJ53 CANS FIT UP
8 11-Apr-11
20-Apr-11
11-Apr-11 A
28-May-11 A
PTJ53 LEG SPLICE WELDING & NDT
10 21-Apr-11
04-May-11
23-Apr-11 A
30-May-11 A
PTJ53 CAN WELDING & NDT
12 05-May-11
18-May-11
09-May-11 A
01-Jun-11 A
48 21-Apr-11
13-Jun-11
23-Apr-11 A
19-Jun-11 A
PTJ52 LEG SPLICE FIT UP
7 21-Apr-11
01-May-11
23-Apr-11 A
30-May-11 A
PTJ53 CANS FIT UP
4 02-May-11
05-May-11
05-May-11 A
30-May-11 A
PTJ52 CONE FIT UP
8 07-May-11
15-May-11
10-May-11 A
31-May-11 A
13 16-May-11
30-May-11
19-May-11 A
02-Jun-11 A
PTJ53 CAN WELDING & NDT
6 07-Jun-11
13-Jun-11
14-May-11 A
05-Jun-11 A
PTJ53 CONE WELDING & NDT
6 31-May-11
06-Jun-11
19-Jun-11 A
19-Jun-11 A
28 07-May-11
07-Jun-11
17-Apr-11 A
28-Jun-11
PTJ52 CONE FIT UP
4 17-May-11
21-May-11
07-May-11 A
02-Jun-11 A
PTJ52 LEG SPLICE WELDING & NDT
6 22-May-11
28-May-11
15-May-11 A
02-Jun-11 A
PTJ52 CONE WELDING & NDT
4 29-May-11
01-Jun-11
17-Apr-11 A
04-Jun-11 A
PTJ52 LEG SPLICE FIT UP
5 07-May-11
11-May-11
10-May-11 A
25-Jun-11
PTJ52 CANS FIT UP
4 12-May-11
16-May-11
16-May-11 A
26-Jun-11
PTJ52 CAN WELDING & NDT
5 02-Jun-11
07-Jun-11
06-May-11 A
28-Jun-11
67 31-Mar-11
13-Jun-11
31-Mar-11 A
29-Jun-11
LEG A2 DIM 14 1400
DIM 12 1200
PTJ53 LEG SPLICE WELDING & NDT
DIM 10 1000
LEG B1 DIM 14 1400
Finish
45 31-Mar-11
18-May-11
31-Mar-11 A
29-Jun-11
9 31-Mar-11
10-Apr-11
31-Mar-11 A
25-Jun-11
PTJ55 CANS FIT UP
8 11-Apr-11
20-Apr-11
11-Apr-11 A
27-Jun-11
PTJ55 LEG SPLICE WELDING & NDT
10 21-Apr-11
04-May-11
23-Apr-11 A
27-Jun-11
PTJ55 CAN WELDING & NDT
12 05-May-11
18-May-11
09-May-11 A
29-Jun-11
43 21-Apr-11
07-Jun-11
23-Apr-11 A
04-Jun-11 A
7 21-Apr-11
01-May-11
23-Apr-11 A
29-May-11 A
PTJ54 LEG SPLICE FIT UP
2011 A M J Jul A S O N D
PTJ55 LEG SPLICE FIT UP
DIM 12 1200
Page 28 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ54 CANS FIT UP
4 02-May-11
05-May-11
05-May-11 A
30-May-11 A
PTJ54 CONE FIT UP
4 07-May-11
10-May-11
10-May-11 A
30-May-11 A
12 11-May-11
24-May-11
15-May-11 A
01-Jun-11 A
PTJ55 CONE WELDING & NDT
6 25-May-11
31-May-11
14-May-11 A
02-Jun-11 A
PTJ55 CAN WELDING & NDT
6 01-Jun-11
07-Jun-11
20-May-11 A
04-Jun-11 A
29 11-May-11
13-Jun-11
14-May-11 A
29-Jun-11
PTJ54 LEG SPLICE FIT UP
5 11-May-11
16-May-11
15-May-11 A
31-May-11 A
PTJ54 CONE FIT UP
4 22-May-11
25-May-11
16-May-11 A
02-Jun-11 A
PTJ54 LEG SPLICE WELDING & NDT
6 26-May-11
01-Jun-11
19-May-11 A
02-Jun-11 A
PTJ54 CONE WELDING & NDT
5 02-Jun-11
07-Jun-11
14-May-11 A
04-Jun-11 A
PTJ54 CANS FIT UP
4 17-May-11
21-May-11
21-May-11 A
28-Jun-11
PTJ54 CAN WELDING & NDT
5 08-Jun-11
13-Jun-11
18-May-11 A
29-Jun-11
65 31-Mar-11
11-Jun-11
31-Mar-11 A
27-Jun-11
43 31-Mar-11
16-May-11
31-Mar-11 A
31-May-11 A
PTJ57 LEG SPLICE FIT UP
8 31-Mar-11
09-Apr-11
31-Mar-11 A
26-May-11 A
PTJ57 CANS FIT UP
7 10-Apr-11
18-Apr-11
10-Apr-11 A
28-May-11 A
PTJ57 LEG SPLICE WELDING & NDT
10 19-Apr-11
02-May-11
20-Apr-11 A
30-May-11 A
PTJ57 CAN WELDING & NDT
12 03-May-11
16-May-11
07-May-11 A
31-May-11 A
43 19-Apr-11
05-Jun-11
20-Apr-11 A
18-Jun-11 A
PTJ56 LEG SPLICE FIT UP
8 19-Apr-11
28-Apr-11
20-Apr-11 A
29-May-11 A
PTJ56 CANS FIT UP
4 30-Apr-11
03-May-11
03-May-11 A
30-May-11 A
PTJ55 LEG SPLICE WELDING & NDT
DIM 10 1000
LEG B2 DIM 14 1400
DIM 12 1200
PTJ56 CONE FIT UP
Finish
4 04-May-11
08-May-11
08-May-11 A
30-May-11 A
22-May-11
12-May-11 A
01-Jun-11 A
PTJ57 CONE WELDING & NDT
6 23-May-11
29-May-11
21-May-11 A
02-Jun-11 A
PTJ57 CAN WELDING & NDT
6 30-May-11
05-Jun-11
18-Jun-11 A
18-Jun-11 A
29 09-May-11
11-Jun-11
12-May-11 A
27-Jun-11
PTJ55 LEG SPLICE FIT UP
5 09-May-11
14-May-11
12-May-11 A
31-May-11 A
PTJ56 CONE FIT UP
4 19-May-11
23-May-11
19-May-11 A
02-Jun-11 A
DIM 10 1000
2011 A M J Jul A S O N D
12 09-May-11
PTJ56 LEG SPLICE WELDING & NDT
Page 29 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ56 LEG SPLICE WELDING & NDT
6 24-May-11
30-May-11
21-May-11 A
04-Jun-11 A
PTJ56 CONE WELDING & NDT
5 31-May-11
05-Jun-11
18-Jun-11 A
18-Jun-11 A
PTJ56 CANS FIT UP
4 15-May-11
18-May-11
18-May-11 A
25-Jun-11
PTJ56 CAN WELDING & NDT
5 06-Jun-11
11-Jun-11
21-May-11 A
27-Jun-11
161 31-Mar-11
28-Sep-11
31-Mar-11 A
16-Jul-11
50 03-Aug-11
28-Sep-11
11-Apr-11 A
14-Jul-11
50 03-Aug-11
28-Sep-11
11-Apr-11 A
14-Jul-11
45 03-Aug-11
22-Sep-11
11-Apr-11 A
18-Jun-11 A
PTJ3 FITUP HORIZONTAL BRACES ATELEV -56.2
9 03-Aug-11
13-Aug-11
08-May-11 A
26-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -79.0
9 14-Aug-11
23-Aug-11
18-May-11 A
30-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -33.4
9 14-Aug-11
23-Aug-11
18-May-11 A
03-Jun-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES ATN ELEV -56.2
10 14-Aug-11
27-Aug-11
18-May-11 A
03-Jun-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -79.0
10 24-Aug-11
07-Sep-11
21-May-11 A
07-Jun-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -10.6
6 24-Aug-11
03-Sep-11
29-Apr-11 A
10-Jun-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV +6.4
7 04-Sep-11
11-Sep-11
11-Apr-11 A
13-Jun-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -33.4
10 24-Aug-11
07-Sep-11
21-May-11 A
13-Jun-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -10.6
10 04-Sep-11
14-Sep-11
11-May-11 A
14-Jun-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4
10 12-Sep-11
22-Sep-11
19-May-11 A
18-Jun-11 A
41 14-Aug-11
28-Sep-11
18-Apr-11 A
14-Jul-11
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2
18 14-Aug-11
06-Sep-11
18-May-11 A
09-Jun-11 A
PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV -33.4 ...
14 07-Sep-11
22-Sep-11
14-May-11 A
20-Jun-11 A
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
13 04-Sep-11
18-Sep-11
11-May-11 A
07-Jul-11
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
14 24-Aug-11
12-Sep-11
14-May-11 A
09-Jul-11
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0
20 14-Aug-11
08-Sep-11
18-Apr-11 A
10-Jul-11
PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV +6.4 &...
9 19-Sep-11
28-Sep-11
15-May-11 A
11-Jul-11
PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV -10.6 ...
11 13-Sep-11
25-Sep-11
20-May-11 A
11-Jul-11
PTJ3 WELDING & NDT DIAGONAL BRACES BETWEEN ELEV -56.2 ...
15 10-Sep-11
26-Sep-11
17-May-11 A
14-Jul-11
78 31-Mar-11
26-Jun-11
31-Mar-11 A
02-Jul-11
JACKET BRACING FABRICATION BRACING ROW 1 BRACIN SPLICING SPLIC HORIZONTAL HORI
DIAGONAL BRACES DIAG
BRACING ROW 2 BRACIN
Finish
Page 30 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
78 31-Mar-11
26-Jun-11
31-Mar-11 A
02-Jul-11
15 31-Mar-11
18-Apr-11
31-Mar-11 A
28-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV +6.4
5 31-Mar-11
05-Apr-11
31-Mar-11 A
25-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -10.6
5 31-Mar-11
05-Apr-11
31-Mar-11 A
25-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -33.4
7 31-Mar-11
07-Apr-11
31-Mar-11 A
26-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -56.2
7 31-Mar-11
07-Apr-11
31-Mar-11 A
26-May-11 A
PTJ3 FITUP HORIZONTAL BRACES AT ELEV -79.0
7 31-Mar-11
07-Apr-11
31-Mar-11 A
26-May-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV +6.4
7 06-Apr-11
13-Apr-11
06-Apr-11 A
26-May-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -10.6
7 06-Apr-11
13-Apr-11
06-Apr-11 A
26-May-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -33.4
8 09-Apr-11
18-Apr-11
09-Apr-11 A
28-May-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -56.2
8 09-Apr-11
18-Apr-11
09-Apr-11 A
28-May-11 A
PTJ3 WELDING & NDT HORIZONTAL BRACES AT ELEV -79.0
8 09-Apr-11
18-Apr-11
09-Apr-11 A
28-May-11 A
56 06-Apr-11
06-Jun-11
06-Apr-11 A
25-Jun-11
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
8 06-Apr-11
14-Apr-11
06-Apr-11 A
31-May-11 A
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
8 09-Apr-11
18-Apr-11
09-Apr-11 A
31-May-11 A
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2
11 09-Apr-11
21-Apr-11
09-Apr-11 A
02-Jun-11 A
PTJ3 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0
11 09-Apr-11
21-Apr-11
09-Apr-11 A
02-Jun-11 A
PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
7 16-Apr-11
24-Apr-11
16-Apr-11 A
05-Jun-11 A
PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
10 19-Apr-11
02-May-11
20-Apr-11 A
08-Jun-11 A
PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2
14 03-May-11
18-May-11
07-May-11 A
18-Jun-11 A
PTJ3 WELDING DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0
16 19-May-11
06-Jun-11
23-May-11 A
25-Jun-11
SPLICING SPLIC HORIZONTAL HORI
DIAGONAL BRACES DIAG
VERTICAL VERT
Finish
Page 31 of 64
2011 A M J Jul A S O N D
47 03-May-11
26-Jun-11
07-May-11 A
02-Jul-11
PTJ3 FITUP VERTICAL BRACES BETWEEN ELEV -10.6 & -33.4
5 03-May-11
08-May-11
07-May-11 A
26-Jun-11
PTJ3 FITUP VERTICAL BRACES BETWEEN ELEV -33.4 & -56.2
7 19-May-11
26-May-11
23-May-11 A
26-Jun-11
PTJ3 FITUP VERTICAL BRACES BETWEEN ELEV -56.2 & -79.0
7 07-Jun-11
14-Jun-11
11-Jun-11 A
26-Jun-11
PTJ8 WELDING VERTICAL BRACES BETWEEN ELEV -10.6 & -33.4
7 09-May-11
16-May-11
12-May-11 A
29-Jun-11
PTJ8 WELDING VERTICAL BRACES BETWEEN ELEV -33.4 & -56.2
10 28-May-11
07-Jun-11
31-May-11 A
02-Jul-11
PTJ8 WELDING VERTICAL BRACES BETWEEN ELEV -56.2 & -79.0
10 15-Jun-11
26-Jun-11
19-May-11 A
02-Jul-11
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
17 17-May-11
05-Jun-11
21-May-11 A
29-Jun-11
PTJ812 FITUP BRACES BETWEEN ELEV -10.6 & -33.4
7 17-May-11
24-May-11
21-May-11 A
26-Jun-11
PTJ813 FITUP BRACES BETWEEN ELEV -33.4 & -56.2
7 17-May-11
24-May-11
21-May-11 A
26-Jun-11
PTJ814 FITUP BRACES BETWEEN ELEV -56.2 & -79.0
7 17-May-11
24-May-11
21-May-11 A
26-Jun-11
PTJ815 WELDING VERTICAL BRACES BETWEEN ELEV +10.6 & -33.4
10 25-May-11
05-Jun-11
21-May-11 A
29-Jun-11
PTJ816 WELDING VERTICAL BRACES BETWEEN ELEV -33.4 & -56.2
10 25-May-11
05-Jun-11
22-May-11 A
29-Jun-11
PTJ817 WELDING VERTICAL BRACES BETWEEN ELEV -56.2 & -79.0
10 25-May-11
05-Jun-11
22-May-11 A
29-Jun-11
51 23-Jun-11
20-Aug-11
27-Apr-11 A
13-Jul-11
51 23-Jun-11
20-Aug-11
27-Apr-11 A
13-Jul-11
PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
6 23-Jun-11
29-Jun-11
27-Apr-11 A
30-Jun-11
PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
8 30-Jun-11
09-Jul-11
04-May-11 A
30-Jun-11
PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
9 30-Jun-11
10-Jul-11
04-May-11 A
02-Jul-11
PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2
9 10-Jul-11
20-Jul-11
13-May-11 A
02-Jul-11
PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
10 10-Jul-11
21-Jul-11
13-May-11 A
03-Jul-11
PTJ82 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0
11 21-Jul-11
02-Aug-11
15-May-11 A
04-Jul-11
PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2
14 21-Jul-11
06-Aug-11
14-May-11 A
07-Jul-11
PTJ82 WELDING DIAGONAL BRACES BETWEEN ELEV - 56.2 & -79.0
15 03-Aug-11
20-Aug-11
08-May-11 A
13-Jul-11
103 23-Jun-11
20-Aug-11
13-Apr-11 A
16-Jul-11
103 23-Jun-11
20-Aug-11
13-Apr-11 A
16-Jul-11
PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
5 23-Jun-11
29-Jun-11
27-Apr-11 A
09-Jun-11 A
PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
8 30-Jun-11
09-Jul-11
04-May-11 A
12-Jun-11 A
9 30-Jun-11
BRACING ROW 3 BRACIN
BRACING ROW A BRACIN FABRICATION FABRI
BRACING ROW B BRACIN FABRICATION FABRI
PTJ83 WELDING DIAGONAL BRACES BETWEEN ELEV +6.4 & -10.6
Finish
10-Jul-11
04-May-11 A
12-Jun-11 A
21-Jul-11
13-Apr-11 A
15-Jun-11 A
9 10-Jul-11
20-Jul-11
13-Apr-11 A
18-Jun-11 A
PTJ83 WELDING DIAGONAL BRACES BETWEEN ELEV - 33.4 & -56.2
14 21-Jul-11
06-Aug-11
10-May-11 A
29-Jun-11
PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV -56.2 & -79.0
11 21-Jul-11
02-Aug-11
16-May-11 A
04-Jul-11
PTJ84 WELDING DIAGONAL BRACES BETWEEN ELEV - 56.2 & -79.0
15 03-Aug-11
20-Aug-11
08-May-11 A
16-Jul-11
23 21-Jun-11
17-Jul-11
25-Apr-11 A
28-Jun-11
PTJ83 FITUP DIAGONAL BRACES BETWEEN ELEV -33.4 & -56.2
BRACING ROW C BRACIN
2011 A M J Jul A S O N D
10 10-Jul-11
PTJ83 WELDING DIAGONAL BRACES BETWEEN ELEV -10.6 & -33.4
Page 32 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ845 FITUP BRACES BETWEEN ELEV -10.6 & -33.4
7 21-Jun-11
28-Jun-11
25-Apr-11 A
26-Jun-11
PTJ847 FITUP BRACES BETWEEN ELEV -56.2 & -79.0
7 21-Jun-11
28-Jun-11
25-Apr-11 A
26-Jun-11
PTJ846 FITUP BRACES BETWEEN ELEV -33.4 & -56.2
10 21-Jun-11
02-Jul-11
25-Apr-11 A
26-Jun-11
PTJ848 WELDING BRACES BETWEEN ELEV -10.6 & -33.4
9 29-Jun-11
09-Jul-11
03-May-11 A
27-Jun-11
PTJ849 WELDING BRACES BETWEEN ELEV -56.2 & -79.0
9 29-Jun-11
09-Jul-11
03-May-11 A
27-Jun-11
13 03-Jul-11
17-Jul-11
06-May-11 A
28-Jun-11
19 21-Jun-11
12-Jul-11
25-Apr-11 A
29-Jun-11
PTJ854 FITUP BRACES BETWEEN ELEV -10.6 & -33.4
5 21-Jun-11
26-Jun-11
25-Apr-11 A
26-Jun-11
PTJ856 FITUP BRACES BETWEEN ELEV -56.2 & -79.0
5 21-Jun-11
26-Jun-11
25-Apr-11 A
26-Jun-11
PTJ855 FITUP BRACES BETWEEN ELEV -33.4 & -56.2
8 21-Jun-11
29-Jun-11
25-Apr-11 A
26-Jun-11
PTJ857 WELDING BRACES BETWEEN ELEV -10.6 & -33.4
7 27-Jun-11
04-Jul-11
30-Apr-11 A
27-Jun-11
PTJ858 WELDING BRACES BETWEEN ELEV -56.2 & -79.0
7 27-Jun-11
04-Jul-11
30-Apr-11 A
27-Jun-11
PTJ859 WELDING BRACES BETWEEN ELEV -33.4 & -56.2
11 30-Jun-11
12-Jul-11
04-May-11 A
29-Jun-11
185 31-Mar-11
30-Oct-11
31-Mar-11 A
03-Oct-11
78 04-Apr-11
29-Jun-11
04-Apr-11 A
23-Jun-11 A
28 04-Apr-11
03-May-11
04-Apr-11 A
02-Jun-11 A
PTJ86 FITUP OF SIZE 24"
18 04-Apr-11
26-Apr-11
04-Apr-11 A
26-May-11 A
PTJ86 FITUP OF SIZE 16"
7 21-Apr-11
01-May-11
23-Apr-11 A
31-May-11 A
PTJ86 FITUP OF SIZE 20"
5 27-Apr-11
03-May-11
30-Apr-11 A
02-Jun-11 A
17 04-May-11
26-May-11
08-May-11 A
14-Jun-11 A
PTJ86 WELDING OF SIZE 24"
12 04-May-11
17-May-11
08-May-11 A
05-Jun-11 A
PTJ86 WELDING OF SIZE 16"
5 18-May-11
23-May-11
22-May-11 A
11-Jun-11 A
PTJ86 WELDING OF SIZE 20"
4 23-May-11
26-May-11
08-May-11 A
14-Jun-11 A
CONDUCTORS AT ELEV + 6400 COND
38 17-May-11
29-Jun-11
08-May-11 A
23-Jun-11 A
18 28-May-11
16-Jun-11
14-May-11 A
20-Jun-11 A
10 28-May-11
07-Jun-11
19-May-11 A
16-Jun-11 A
6 11-Jun-11
16-Jun-11
14-May-11 A
20-Jun-11 A
11 18-Jun-11
29-Jun-11
21-May-11 A
23-Jun-11 A
PTJ850 WELDING BRACES BETWEEN ELEV -33.4 & -56.2 BRACING ROW D BRACIN
JACKET ELEVATIONS FABRICATION ELEV + 6400 FITUP
WELDING&NDT WELD
WELDING & NDT WELD PTJ9 WELDING OF CONDUCTOR PTJ9 WELDING OF CONDUCTOR SUPPORT CONDUCTORS ERECTION COND
Finish
Page 33 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
11 18-Jun-11
29-Jun-11
21-May-11 A
23-Jun-11 A
21 17-May-11
09-Jun-11
08-May-11 A
19-Jun-11 A
PTJ9 FITUP OF CONDUCTOR
9 17-May-11
26-May-11
18-May-11 A
14-Jun-11 A
PTJ9 FITUP OF CONDUCTOR SUPPORT
5 05-Jun-11
09-Jun-11
08-May-11 A
19-Jun-11 A
159 31-Mar-11
21-Aug-11
31-Mar-11 A
03-Oct-11
41 31-Mar-11
14-May-11
31-Mar-11 A
24-Jul-11
PTJ87 FITUP OF SIZE 28"
26 31-Mar-11
03-May-11
31-Mar-11 A
13-Jul-11
PTJ87 FITUP OF SIZE 16"
8 28-Apr-11
07-May-11
02-May-11 A
17-Jul-11
PTJ87 FITUP OF SIZE 20"
23 12-Apr-11
11-May-11
12-Apr-11 A
21-Jul-11
PTJ87 FITUP OF SIZE 14"
5 09-May-11
14-May-11
12-May-11 A
24-Jul-11
48 15-May-11
09-Jul-11
15-May-11 A
13-Sep-11
PTJ87 WELDING OF SIZE 28"
35 15-May-11
23-Jun-11
18-May-11 A
28-Aug-11
PTJ87 WELDING OF SIZE 16"
9 20-Jun-11
29-Jun-11
23-May-11 A
04-Sep-11
PTJ87 WELDING OF SIZE 20"
31 31-May-11
05-Jul-11
15-May-11 A
10-Sep-11
PTJ87 WELDING OF SIZE 14"
6 03-Jul-11
09-Jul-11
15-May-11 A
13-Sep-11
CONDUCTORS AT ELEV - 10600 COND
79 29-Jun-11
21-Aug-11
13-May-11 A
03-Oct-11
30 29-Jun-11
01-Aug-11
15-May-11 A
18-Jun-11 A
PTJ9 FITUP OF CONDUCTOR
9 29-Jun-11
09-Jul-11
15-May-11 A
15-Jun-11 A
PTJ9 FITUP OF CONDUCTOR SUPPORT
5 27-Jul-11
01-Aug-11
15-May-11 A
18-Jun-11 A
59 10-Jul-11
08-Aug-11
13-May-11 A
20-Sep-11
9 10-Jul-11
20-Jul-11
13-May-11 A
23-Jun-11 A
PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS FITUP
ELEV - 10600 FITUP
WELDING&NDT WELD
FITUP
WELDING & NDT WELD PTJ9 WELDING OF CONDUCTOR PTJ9 WELDING OF CONDUCTOR SUPPORT
Finish
6 02-Aug-11
08-Aug-11
13-Sep-11
20-Sep-11
21-Aug-11
20-Sep-11
03-Oct-11
11 09-Aug-11
21-Aug-11
20-Sep-11
03-Oct-11
117 31-Mar-11
24-Jul-11
31-Mar-11 A
14-Aug-11
30 31-Mar-11
02-May-11
31-Mar-11 A
21-Jun-11 A
PTJ87 FITUP OF SIZE 28"
14 31-Mar-11
16-Apr-11
31-Mar-11 A
05-Jun-11 A
PTJ88 FITUP OF SIZE 16"
10 09-Apr-11
20-Apr-11
09-Apr-11 A
09-Jun-11 A
PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS ELEV - 33400 FITUP
2011 A M J Jul A S O N D
11 09-Aug-11
CONDUCTORS ERECTION COND
Page 34 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ88 FITUP OF SIZE 24"
8 17-Apr-11
27-Apr-11
17-Apr-11 A
16-Jun-11 A
PTJ88 FITUP OF SIZE 20"
6 21-Apr-11
30-Apr-11
23-Apr-11 A
19-Jun-11 A
PTJ88 FITUP OF SIZE 18"
6 25-Apr-11
02-May-11
27-Apr-11 A
21-Jun-11 A
34 03-May-11
11-Jun-11
24-Apr-11 A
25-Jul-11
PTJ88 WELDING OF SIZE 28"
16 03-May-11
21-May-11
07-May-11 A
04-Jul-11
PTJ88 WELDING OF SIZE 16"
6 21-May-11
26-May-11
24-Apr-11 A
10-Jul-11
PTJ88 WELDING OF SIZE 24"
12 23-May-11
05-Jun-11
26-Apr-11 A
19-Jul-11
PTJ88 WELDING OF SIZE 20"
5 04-Jun-11
08-Jun-11
07-May-11 A
23-Jul-11
PTJ88 WELDING OF SIZE 18"
4 07-Jun-11
11-Jun-11
11-May-11 A
25-Jul-11
CONDUCTORS AT ELEV - 33400 COND
61 01-Jun-11
24-Jul-11
05-May-11 A
14-Aug-11
29 01-Jun-11
04-Jul-11
05-May-11 A
19-Jun-11 A
PTJ9 FITUP OF CONDUCTOR
9 01-Jun-11
11-Jun-11
05-May-11 A
18-Jun-11 A
PTJ9 FITUP OF CONDUCTOR SUPPORT
5 29-Jun-11
04-Jul-11
08-May-11 A
19-Jun-11 A
41 12-Jun-11
11-Jul-11
15-May-11 A
01-Aug-11
10 12-Jun-11
22-Jun-11
15-May-11 A
20-Jun-11 A
6 05-Jul-11
11-Jul-11
25-Jul-11
01-Aug-11
11 12-Jul-11
24-Jul-11
01-Aug-11
14-Aug-11
11 12-Jul-11
24-Jul-11
01-Aug-11
14-Aug-11
133 31-Mar-11
13-Aug-11
31-Mar-11 A
03-Aug-11
46 31-Mar-11
19-May-11
31-Mar-11 A
22-Jun-11 A
PTJ89 FITUP OF SIZE 28"
26 31-Mar-11
03-May-11
31-Mar-11 A
15-Jun-11 A
PTJ89 FITUP OF SIZE 24"
18 24-Apr-11
15-May-11
26-Apr-11 A
16-Jun-11 A
PTJ89 FITUP OF SIZE 16"
10 26-Apr-11
08-May-11
28-Apr-11 A
20-Jun-11 A
PTJ89 FITUP OF SIZE 20"
11 05-May-11
17-May-11
09-May-11 A
21-Jun-11 A
PTJ89 FITUP OF SIZE 18"
7 12-May-11
19-May-11
16-May-11 A
22-Jun-11 A
36 21-May-11
30-Jun-11
07-May-11 A
13-Jul-11
PTJ89 WELDING OF SIZE 28"
18 21-May-11
09-Jun-11
17-May-11 A
22-Jun-11 A
PTJ89 WELDING OF SIZE 24"
12 12-Jun-11
25-Jun-11
15-May-11 A
24-Jun-11 A
WELDING&NDT WELD
FITUP
WELDING & NDT WELD PTJ9 WELDING OF CONDUCTOR PTJ9 WELDING OF CONDUCTOR SUPPORT CONDUCTORS ERECTION COND PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS ELEV - 56200 FITUP
WELDING&NDT WELD
Finish
Page 35 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ89 WELDING OF SIZE 16"
7 08-Jun-11
15-Jun-11
12-May-11 A
28-Jun-11
PTJ89 WELDING OF SIZE 20"
7 21-Jun-11
28-Jun-11
14-May-11 A
11-Jul-11
PTJ89 WELDING OF SIZE 18"
4 27-Jun-11
30-Jun-11
07-May-11 A
13-Jul-11
CONDUCTORS AT ELEV - 56200 COND
60 21-Jun-11
13-Aug-11
15-May-11 A
03-Aug-11
30 21-Jun-11
24-Jul-11
15-May-11 A
24-Jun-11 A
PTJ9 FITUP OF CONDUCTOR
9 21-Jun-11
30-Jun-11
15-May-11 A
23-Jun-11 A
PTJ9 FITUP OF CONDUCTOR SUPPORT
5 19-Jul-11
24-Jul-11
19-May-11 A
24-Jun-11 A
38 02-Jul-11
31-Jul-11
21-May-11 A
27-Jul-11
10 02-Jul-11
12-Jul-11
21-May-11 A
13-Jul-11
6 25-Jul-11
31-Jul-11
22-Jun-11 A
27-Jul-11
13 01-Aug-11
13-Aug-11
22-Jun-11 A
03-Aug-11
11 01-Aug-11
13-Aug-11
22-Jun-11 A
03-Aug-11
61 18-Aug-11
30-Oct-11
07-Apr-11 A
09-Aug-11
29 18-Aug-11
19-Sep-11
07-Apr-11 A
18-Jul-11
PTJ90 FITUP OF SIZE 28"
13 18-Aug-11
05-Sep-11
23-Apr-11 A
12-Jun-11 A
PTJ90 FITUP OF SIZE 16"
9 31-Aug-11
10-Sep-11
07-Apr-11 A
17-Jun-11 A
PTJ90 FITUP OF SIZE 24"
10 06-Sep-11
17-Sep-11
13-Apr-11 A
16-Jul-11
PTJ90 FITUP OF SIZE 20"
6 13-Sep-11
19-Sep-11
20-Apr-11 A
18-Jul-11
32 20-Sep-11
30-Oct-11
02-May-11 A
09-Aug-11
PTJ90 WELDING OF SIZE 28"
18 20-Sep-11
11-Oct-11
21-May-11 A
21-Jul-11
PTJ90 WELDING OF SIZE 16"
10 05-Oct-11
17-Oct-11
13-May-11 A
27-Jul-11
PTJ90 WELDING OF SIZE 24"
12 13-Oct-11
26-Oct-11
20-May-11 A
06-Aug-11
PTJ90 WELDING OF SIZE 20"
2 26-Oct-11
30-Oct-11
02-May-11 A
09-Aug-11
72 22-Nov-11
15-Feb-12
07-May-11 A
21-Jan-12
46 22-Nov-11
23-Jan-12
07-May-11 A
28-Dec-11
PTJ932 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
4 22-Nov-11
26-Nov-11
19-Jun-11 A
23-Nov-11
PTJ933 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL...
4 25-Dec-11
28-Dec-11
29-Nov-11
03-Dec-11
23 01-Dec-11
28-Dec-11
07-May-11 A
03-Dec-11
FITUP
WELDING & NDT WELD PTJ9 WELDING OF CONDUCTOR PTJ9 WELDING OF CONDUCTOR SUPPORT CONDUCTORS ERECTION COND PTJ9 ERECTION OF CONDUCTOR WITH ELEVATIONS ELEV - 79000 FITUP
WELDING&NDT WELD
PILE SLEEVES SLE FABRICATION AT LEG A1
PTJ936 GIRTH WELD OF PILE SLEEVE
Finish
Page 36 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ937 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE...
12 29-Dec-11
11-Jan-12
04-Dec-11
17-Dec-11
PTJ938 ERECTION OF PILE SLEEVE WITH LEGS
10 12-Jan-12
23-Jan-12
18-Dec-11
28-Dec-11
52 22-Nov-11
23-Jan-12
20-Jun-11 A
28-Dec-11
PTJ946 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
4 22-Nov-11
26-Nov-11
20-Jun-11 A
31-Oct-11
PTJ947 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL...
4 25-Dec-11
28-Dec-11
29-Nov-11
03-Dec-11
PTJ950 GIRTH WELD OF PILE SLEEVE
24 01-Dec-11
28-Dec-11
06-Nov-11
03-Dec-11
PTJ95
12 29-Dec-11
11-Jan-12
04-Dec-11
17-Dec-11
10 12-Jan-12
23-Jan-12
18-Dec-11
28-Dec-11
54 15-Dec-11
15-Feb-12
20-Nov-11
21-Jan-12
PTJ939 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
4 15-Dec-11
19-Dec-11
20-Nov-11
23-Nov-11
PTJ940 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL...
4 17-Jan-12
21-Jan-12
22-Dec-11
26-Dec-11
PTJ943 GIRTH WELD OF PILE SLEEVE
24 25-Dec-11
21-Jan-12
29-Nov-11
26-Dec-11
PTJ944 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE...
12 22-Jan-12
04-Feb-12
27-Dec-11
09-Jan-12
PTJ945 ERECTION OF PILE SLEEVE WITH LEGS
10 05-Feb-12
15-Feb-12
10-Jan-12
21-Jan-12
54 15-Dec-11
15-Feb-12
20-Nov-11
21-Jan-12
PTJ953 CUTTING & EDGE PREPARATION OF PILE SLEEVE PLATE
4 15-Dec-11
19-Dec-11
20-Nov-11
23-Nov-11
PTJ954 CUTTING & EDGE PREPARATION OF PILE SLEEVE SHEAR PL...
4 17-Jan-12
21-Jan-12
22-Dec-11
26-Dec-11
PTJ957 GIRTH WELD OF PILE SLEEVE
24 25-Dec-11
21-Jan-12
29-Nov-11
26-Dec-11
PTJ958 ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE...
12 22-Jan-12
04-Feb-12
27-Dec-11
09-Jan-12
PTJ959 ERECTION OF PILE SLEEVE WITH LEGS
10 05-Feb-12
15-Feb-12
10-Jan-12
21-Jan-12
176 14-Jun-11
15-Feb-12
28-Jun-11
21-Jan-12
7 22-Dec-11
29-Dec-11
26-Oct-11
02-Nov-11
7 22-Dec-11
29-Dec-11
26-Oct-11
02-Nov-11
7 22-Dec-11
29-Dec-11
26-Oct-11
02-Nov-11
7 31-Oct-11
07-Nov-11
09-Aug-11
17-Aug-11
7 31-Oct-11
07-Nov-11
09-Aug-11
17-Aug-11
7 31-Oct-11
07-Nov-11
09-Aug-11
17-Aug-11
7 08-Nov-11
15-Nov-11
17-Aug-11
25-Aug-11
AT LEG B1
ERECTION OF SHEAR & STIFFENERS PLATE WITH PILE SLEE...
PTJ952 ERECTION OF PILE SLEEVE WITH LEGS AT LEG A2
AT LEG B2
JACKET ERECTION ELEV +6.4 + ERECTION ON ROW2 ERECT PTJ86 ERECTION OF ELEV AT + 6.4 ON ROW 2 ELEV -5 -56.2 ERECTION ON ROW2 ERECT PTJ90 ERECTION OF ELEV AT -56.2 ON ROW 2 ELEV -7 -79.0
Finish
Page 37 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
7 08-Nov-11
15-Nov-11
17-Aug-11
25-Aug-11
7 08-Nov-11
15-Nov-11
17-Aug-11
25-Aug-11
7 17-Nov-11
24-Nov-11
27-Aug-11
05-Sep-11
7 17-Nov-11
24-Nov-11
27-Aug-11
05-Sep-11
7 17-Nov-11
24-Nov-11
27-Aug-11
05-Sep-11
7 05-Dec-11
12-Dec-11
03-Oct-11
12-Oct-11
7 05-Dec-11
12-Dec-11
03-Oct-11
12-Oct-11
7 05-Dec-11
12-Dec-11
03-Oct-11
12-Oct-11
37 14-Jun-11
30-Oct-11
28-Jun-11
09-Aug-11
36 14-Jun-11
29-Oct-11
28-Jun-11
08-Aug-11
15 14-Jun-11
30-Jun-11
28-Jun-11
16-Jul-11
5 14-Jun-11
19-Jun-11
28-Jun-11
04-Jul-11
10 20-Jun-11
30-Jun-11
04-Jul-11
16-Jul-11
30 20-Jun-11
24-Jul-11
04-Jul-11
08-Aug-11
PTJ8 FITUP OF DIAGONAL ON LEG
10 20-Jun-11
30-Jun-11
04-Jul-11
16-Jul-11
PTJ8 WELDING OF DIAGONAL ON LEG
20 02-Jul-11
24-Jul-11
16-Jul-11
08-Aug-11
15 12-Oct-11
29-Oct-11
21-Jul-11
08-Aug-11
5 12-Oct-11
17-Oct-11
21-Jul-11
27-Jul-11
10 18-Oct-11
29-Oct-11
27-Jul-11
08-Aug-11
1 30-Oct-11
30-Oct-11
08-Aug-11
09-Aug-11
1 30-Oct-11
30-Oct-11
08-Aug-11
09-Aug-11
ERECTION ON ROW2 ERECT PTJ90 ERECTION OF ELEV AT -79 ON ROW 2 ELEV - 33.4 ERECTION ON ROW2 ERECT PTJ88 ERECTION OF ELEV AT -33.4 ON ROW 2 ELEV -1 -10.6 ERECTION ON ROW2 ERECT PTJ87 ERECTION OF ELEV AT -10.6 ON ROW 2 ROW 2 ERECTION ERECT HORIZONTAL HORI PTJ9 FITUP OF HORIZONTAL ON LEG PTJ9 WELDING OF HORIZONTAL ON LEG DIAGONAL BRACES DIAG
VERTICAL VERT PTJ8 FITUP OF VERTICAL BRACES WITH ROW 2 BRACES PTJ8 WELDING OF VERTICAL BRACES WITH ROW 2 BRACES LIFTING OVER TRUSS RUNNER LIFTIN PTJ81 LIFTING OVER TRUSS RUNNERS ROW C
Finish
19 08-Nov-11
29-Nov-11
17-Aug-11
10-Sep-11
4 08-Nov-11
12-Nov-11
17-Aug-11
22-Aug-11
PTJ853 ERECTION ROW C BRACES BETWEEN - 10.6 & -33.4
4 26-Nov-11
29-Nov-11
05-Sep-11
10-Sep-11
PTJ852 ERECTION ROW C BRACES BETWEEN -33.4 & -56.2
4 26-Nov-11
29-Nov-11
05-Sep-11
10-Sep-11
67 06-Sep-11
17-Dec-11
28-Jul-11
17-Oct-11
67 06-Sep-11
17-Dec-11
28-Jul-11
17-Oct-11
6 06-Sep-11
12-Sep-11
28-Jul-11
04-Aug-11
ROW A ERECTION ERECT PTJ83 ERECTION X BRACES BETWEEN -56.2 & -79.0
2011 A M J Jul A S O N D
ERECTION ROW C BRACES BETWEEN -56.2 & -79.0
PTJ85
Page 38 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ83 ERECTION X BRACES BETWEEN -33.4 & -56.2
4 08-Nov-11
12-Nov-11
17-Aug-11
22-Aug-11
PTJ83 ERECTION X BRACES BETWEEN -10.6 & -33.4
4 26-Nov-11
29-Nov-11
05-Sep-11
10-Sep-11
PTJ82 ERECTION X BRACES BETWEEN +6.4 & -10.6
4 13-Dec-11
17-Dec-11
12-Oct-11
17-Oct-11
65 13-Sep-11
21-Dec-11
04-Aug-11
22-Oct-11
65 13-Sep-11
21-Dec-11
04-Aug-11
22-Oct-11
PTJ84 ERECTION X BRACES BETWEEN -56.2 & -79.0
6 13-Sep-11
19-Sep-11
04-Aug-11
11-Aug-11
PTJ84 ERECTION X BRACES BETWEEN -33.4 & -56.2
4 13-Nov-11
16-Nov-11
22-Aug-11
27-Aug-11
PTJ84 ERECTION X BRACES BETWEEN -10.6 & -33.4
4 30-Nov-11
04-Dec-11
10-Sep-11
14-Sep-11
PTJ84 ERECTION X BRACES BETWEEN +6.4 & -10.6
4 18-Dec-11
21-Dec-11
17-Oct-11
22-Oct-11
41 16-Nov-11
14-Dec-11
25-Aug-11
15-Oct-11
PTJ860 ERECTION ROW D BRACES BETWEEN -56.2 & -79.0
2 16-Nov-11
17-Nov-11
25-Aug-11
28-Aug-11
PTJ86
ERECTION ROW D BRACES BETWEEN -33.4 & -56.2
2 26-Nov-11
27-Nov-11
05-Sep-11
07-Sep-11
PTJ862 ERECTION ROW D BRACES BETWEEN -10.6 & -33.4
2 13-Dec-11
14-Dec-11
12-Oct-11
15-Oct-11
4 19-Jan-12
23-Jan-12
23-Nov-11
27-Nov-11
PTJ818 ERECTION ROW 3 BRACES BETWEEN -10.6 & -33.4
4 19-Jan-12
23-Jan-12
23-Nov-11
27-Nov-11
PTJ819 ERECTION ROW 3 BRACES BETWEEN -33.4 & -56.2
4 19-Jan-12
23-Jan-12
23-Nov-11
27-Nov-11
PTJ820 ERECTION ROW 3 BRACES BETWEEN -56.2 & -79.0
4 19-Jan-12
23-Jan-12
23-Nov-11
27-Nov-11
170 24-Sep-11
15-Feb-12
04-Jul-11
21-Jan-12
15 24-Sep-11
11-Oct-11
04-Jul-11
21-Jul-11
5 24-Sep-11
28-Sep-11
04-Jul-11
10-Jul-11
10 29-Sep-11
11-Oct-11
10-Jul-11
21-Jul-11
ROW B ERECTION ERECT
ROW D
ROW 3
ROW 1 HORIZONTAL HORIZ PTJ94 FITUP OF HORIZONTAL ON LEG PTJ94 WELDING OF HORIZONTAL ON LEG DIAGONAL BRACES DIAGO
Finish
30 29-Sep-11
03-Nov-11
10-Jul-11
14-Aug-11
10 29-Sep-11
11-Oct-11
10-Jul-11
21-Jul-11
PTJ94 WELDING OF DIAGONAL ON LEG
20 12-Oct-11
03-Nov-11
21-Jul-11
14-Aug-11
20 24-Jan-12
15-Feb-12
29-Dec-11
21-Jan-12
PTJ80 LIFTING OF ROW 1 OVER ELAVATIONS & ROW A,B
1 24-Jan-12
24-Jan-12
29-Dec-11
29-Dec-11
PTJ80 FITUP OF ROW 1 OVER ELAVATIONS & ROW A,B
4 25-Jan-12
29-Jan-12
31-Dec-11
03-Jan-12
15 30-Jan-12
15-Feb-12
04-Jan-12
21-Jan-12
PTJ80 WELDING OF ROW 1 OVER ELAVATIONS & ROW A,B
2011 A M J Jul A S O N D
PTJ94 FITUP OF DIAGONAL ON LEG
ERECTION ROW 1 ERECT
Page 39 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
JACKET M MISCELLANEOUS FABRICATION
Original BL Project Duration Start
BL Project Finish
Start
206 31-Mar-11
21-Feb-12
31-Mar-11 A
PTJ9600 Jacket miscellaneous fabrication start
0 31-Aug-11
PTJ11020 Jacket miscellaneous fabrication finish
0
Finish 26-Jan-12
31-Aug-11 21-Feb-12
26-Jan-12
65 19-Dec-11
21-Feb-12
23-Nov-11
26-Jan-12
Main Le Legs
5 19-Dec-11
23-Dec-11
23-Nov-11
27-Nov-11
BL1000 Cutting & Assembly
3 19-Dec-11
21-Dec-11
23-Nov-11
25-Nov-11
BL1010 Welding & NDT
4 20-Dec-11
23-Dec-11
24-Nov-11
27-Nov-11
20 24-Dec-11
12-Jan-12
28-Nov-11
17-Dec-11
BL1040 Cutting & Assembly
10 24-Dec-11
02-Jan-12
28-Nov-11
07-Dec-11
BL1050 Welding & NDT
15 29-Dec-11
12-Jan-12
03-Dec-11
17-Dec-11
21 28-Jan-12
17-Feb-12
02-Jan-12
22-Jan-12
BL1020 Cutting & Assembly
12 28-Jan-12
08-Feb-12
02-Jan-12
13-Jan-12
BL1030 Welding & NDT
15 03-Feb-12
17-Feb-12
08-Jan-12
22-Jan-12
14 14-Jan-12
27-Jan-12
19-Dec-11
01-Jan-12
BL1060 Cutting & Assembly
4 14-Jan-12
17-Jan-12
19-Dec-11
22-Dec-11
BL1070 Welding & NDT
6 22-Jan-12
27-Jan-12
27-Dec-11
01-Jan-12
15 13-Jan-12
27-Jan-12
18-Dec-11
01-Jan-12
BL1080 Cutting & Assembly
5 13-Jan-12
17-Jan-12
18-Dec-11
22-Dec-11
BL1090 Welding & NDT
7 21-Jan-12
27-Jan-12
26-Dec-11
01-Jan-12
15 13-Jan-12
27-Jan-12
18-Dec-11
01-Jan-12
5 13-Jan-12
17-Jan-12
18-Dec-11
22-Dec-11
Front Elevation El
Plan at Elev. +2.6
Plan at Elev. +2.4
Plan at Elev. -30 BL1100 Cutting & Assembly BL1110 Welding & NDT
7 21-Jan-12
27-Jan-12
26-Dec-11
01-Jan-12
10 18-Jan-12
27-Jan-12
23-Dec-11
01-Jan-12
BL1120 Cutting & Assembly
4 18-Jan-12
21-Jan-12
23-Dec-11
26-Dec-11
BL1130 Welding & NDT
6 22-Jan-12
27-Jan-12
27-Dec-11
01-Jan-12
18 04-Feb-12
21-Feb-12
09-Jan-12
26-Jan-12
BL1140 Trial Fit and Grating Stopper Fixation
1 04-Feb-12
04-Feb-12
09-Jan-12
09-Jan-12
BL1150 Final Installation
1 21-Feb-12
21-Feb-12
26-Jan-12
26-Jan-12
Boat lan landing Sections (a,b.c,d,e)
Grating
2011 A M J Jul A S O N D
BOAT LAND LA
Back El Elevation
Page 40 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
8 10-Feb-12
17-Feb-12
15-Jan-12
22-Jan-12
BL1160 Fabrication
5 10-Feb-12
14-Feb-12
15-Jan-12
19-Jan-12
BL1170 Installation
3 15-Feb-12
17-Feb-12
20-Jan-12
22-Jan-12
16 06-Feb-12
21-Feb-12
11-Jan-12
26-Jan-12
BL1200 Fabrication
4 06-Feb-12
09-Feb-12
11-Jan-12
14-Jan-12
BL1210 Installation
2 20-Feb-12
21-Feb-12
25-Jan-12
26-Jan-12
2 16-Feb-12
17-Feb-12
21-Jan-12
22-Jan-12
BL1220 Fabrication
1 16-Feb-12
16-Feb-12
21-Jan-12
21-Jan-12
BL1230 Installation
1 17-Feb-12
17-Feb-12
22-Jan-12
22-Jan-12
1 21-Feb-12
21-Feb-12
26-Jan-12
26-Jan-12
1 21-Feb-12
21-Feb-12
26-Jan-12
26-Jan-12
27 22-Jan-12
17-Feb-12
27-Dec-11
22-Jan-12
4 14-Feb-12
17-Feb-12
19-Jan-12
22-Jan-12
BL127 Profiling Template & Assembly with Legs
2 14-Feb-12
15-Feb-12
19-Jan-12
20-Jan-12
BL128 Welding & NDT
3 15-Feb-12
17-Feb-12
20-Jan-12
22-Jan-12
16 22-Jan-12
06-Feb-12
27-Dec-11
11-Jan-12
BL125 Cutting & Assembly
7 22-Jan-12
28-Jan-12
27-Dec-11
02-Jan-12
BL126 Welding & NDT
9 29-Jan-12
06-Feb-12
03-Jan-12
11-Jan-12
23 26-Jan-12
17-Feb-12
31-Dec-11
22-Jan-12
19 26-Jan-12
13-Feb-12
31-Dec-11
18-Jan-12
7 26-Jan-12
01-Feb-12
31-Dec-11
06-Jan-12
12 02-Feb-12
13-Feb-12
07-Jan-12
18-Jan-12
4 14-Feb-12
17-Feb-12
19-Jan-12
22-Jan-12
BL131 Profiling Template & Assembly with Legs
2 14-Feb-12
15-Feb-12
19-Jan-12
20-Jan-12
BL132 Welding & NDT
3 15-Feb-12
17-Feb-12
20-Jan-12
22-Jan-12
2 18-Feb-12
19-Feb-12
23-Jan-12
24-Jan-12
2 18-Feb-12
19-Feb-12
23-Jan-12
24-Jan-12
30 23-Jan-12
21-Feb-12
28-Dec-11
26-Jan-12
Stairs & Ladders
Handrails Handrai
Mooring Cleat
Rubber BL1240 Installation of Rubber & Tightening Lower Support S Installation with Jacket legs Installa
Fabrication Fabrica
Upper Support S Fabrication Fabrica BL129 Cutting & Assembly BL130 Welding & NDT Installation with Jacket legs Installa
Boat lan landing trial fit BL1330 Boat Landing Trial Fit BARGE B BUMPER
Finish
Page 41 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
15 23-Jan-12
06-Feb-12
28-Dec-11
11-Jan-12
BB1000 Cutting & Assembly
6 23-Jan-12
28-Jan-12
28-Dec-11
02-Jan-12
BB1010 Welding & NDT
9 29-Jan-12
06-Feb-12
03-Jan-12
11-Jan-12
28 23-Jan-12
19-Feb-12
28-Dec-11
24-Jan-12
23 23-Jan-12
14-Feb-12
28-Dec-11
19-Jan-12
BB10 Cutting & Assembly
12 23-Jan-12
03-Feb-12
28-Dec-11
08-Jan-12
BB10 Welding & NDT
17 29-Jan-12
14-Feb-12
03-Jan-12
19-Jan-12
5 15-Feb-12
19-Feb-12
20-Jan-12
24-Jan-12
BB10 Profiling Template & Assembly with Legs
2 15-Feb-12
16-Feb-12
20-Jan-12
21-Jan-12
BB10 Welding & NDT
3 17-Feb-12
19-Feb-12
22-Jan-12
24-Jan-12
24 27-Jan-12
19-Feb-12
01-Jan-12
24-Jan-12
5 15-Feb-12
19-Feb-12
20-Jan-12
24-Jan-12
BB10 Profiling Template & Assembly with Legs
2 15-Feb-12
16-Feb-12
20-Jan-12
21-Jan-12
BB10 Welding & NDT
3 17-Feb-12
19-Feb-12
22-Jan-12
24-Jan-12
19 27-Jan-12
14-Feb-12
01-Jan-12
19-Jan-12
8 27-Jan-12
03-Feb-12
01-Jan-12
08-Jan-12
11 04-Feb-12
14-Feb-12
09-Jan-12
19-Jan-12
2 20-Feb-12
21-Feb-12
25-Jan-12
26-Jan-12
2 20-Feb-12
21-Feb-12
25-Jan-12
26-Jan-12
42 31-Aug-11
27-Oct-11
31-Aug-11
19-Oct-11
PTJ106 CLAMPS FOR RISER 16 " FABRICATION
18 31-Aug-11
20-Sep-11
31-Aug-11
20-Sep-11
PTJ105 RISER 16 " FABRICATION
22 31-Aug-11
25-Sep-11
31-Aug-11
25-Sep-11
7 26-Sep-11
03-Oct-11
26-Sep-11
03-Oct-11
PTJ106 CLAMPS FOR RISER 16 " INSTALLATION
14 29-Sep-11
16-Oct-11
21-Sep-11
08-Oct-11
PTJ106 RISER 16 " INSTALLATION
10 17-Oct-11
27-Oct-11
09-Oct-11
19-Oct-11
26 31-Aug-11
16-Oct-11
31-Aug-11
29-Sep-11
PTJ106 CLAMPS FOR J-TUBE16 " FABRICATION
12 31-Aug-11
13-Sep-11
31-Aug-11
13-Sep-11
PTJ106 J-TUBE16 " FABRICATION
14 31-Aug-11
15-Sep-11
31-Aug-11
15-Sep-11
Main Pi Pipe
Upper Support S Fabrication Fabrica
Installation with Jacket legs Installa
Lower Support S Installation with Jacket legs Installa
Fabrication Fabrica BB10 Cutting & Assembly BB10 Welding & NDT Barge Bumper B Trial Fit BB1100 Barge Bumper Trial Fit RISER 16" 1 & CLAMPS
PTJ106 RISER COATING
J-TUBE 16 " & CLAMPS
Finish
Page 42 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
10 29-Sep-11
11-Oct-11
14-Sep-11
25-Sep-11
4 12-Oct-11
16-Oct-11
26-Sep-11
29-Sep-11
14 31-Aug-11
05-Oct-11
31-Aug-11
15-Sep-11
PTJ106 CLAMPS FOR FUTURE J-TUBE FABRICATION
8 31-Aug-11
08-Sep-11
31-Aug-11
08-Sep-11
PTJ107 CLAMPS FOR FUTURE J-TUBE INSTALLATION
6 29-Sep-11
05-Oct-11
10-Sep-11
15-Sep-11
18 31-Jan-12
20-Feb-12
05-Jan-12
25-Jan-12
2 07-Feb-12
08-Feb-12
12-Jan-12
14-Jan-12
14 31-Jan-12
15-Feb-12
05-Jan-12
21-Jan-12
PTJ107 SUPPORTS SUMP CAISSON 30 " INSTALLATION
6 09-Feb-12
15-Feb-12
15-Jan-12
21-Jan-12
PTJ107 SUPPORTS SUMP CAISSON 30 " INSTALLATION
4 16-Feb-12
20-Feb-12
22-Jan-12
25-Jan-12
80 31-Aug-11
03-Dec-11
31-Aug-11
03-Dec-11
PTJ107 MUD MAT FABRICATION
60 31-Aug-11
09-Nov-11
31-Aug-11
09-Nov-11
PTJ107 MUD MAT INSTALLATION
20 10-Nov-11
03-Dec-11
10-Nov-11
03-Dec-11
47 31-Aug-11
25-Oct-11
31-Aug-11
25-Oct-11
PTJ103 FITUP OF WALK WAY & STARIR
12 31-Aug-11
13-Sep-11
31-Aug-11
13-Sep-11
PTJ103 WELDING & NDT OF WALK WAY & STARIRS
16 14-Sep-11
02-Oct-11
14-Sep-11
02-Oct-11
PTJ103 ERECTION WALK WAY ON TOP ELEVATION
12 12-Oct-11
25-Oct-11
12-Oct-11
25-Oct-11
118 31-Mar-11
14-Aug-11
31-Mar-11 A
14-Jul-11
118 31-Mar-11
14-Aug-11
31-Mar-11 A
14-Jul-11
87 31-Mar-11
24-May-11
31-Mar-11 A
10-Jul-11
PTJ98 FITUP OF LUNCH TRUSS FROM EL -33.4 UP TO -10.6
32 31-Mar-11
10-May-11
31-Mar-11 A
26-Jun-11
PTJ98 WELDING & NDT LUNCH TRUSS FROM EL -33.4 UP TO -10.6
24 24-Apr-11
22-May-11
26-Apr-11 A
07-Jul-11
2 23-May-11
24-May-11
07-Jul-11
10-Jul-11
50 11-May-11
04-Jul-11
15-Apr-11 A
12-Jul-11
PTJ97 FITUP OF LUNCH TRUSS FROM EL -56 UP TO -33.4
35 11-May-11
20-Jun-11
15-Apr-11 A
28-Jun-11
PTJ98 WELDING & NDT OF LUNCH TRUSS FROM EL -56 UP TO -33.4
25 04-Jun-11
02-Jul-11
07-May-11 A
10-Jul-11
PTJ98 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ...
2 03-Jul-11
04-Jul-11
10-Jul-11
12-Jul-11
45 21-Jun-11
14-Aug-11
25-Apr-11 A
14-Jul-11
PTJ106 CLAMPS FOR J-TUBE16 " INSTALLATION PTJ106 J-TUBE16 " INSTALLATION FUTURE J-TUBE CLAMPS
SUMP C CAISSON 30" PTJ107 SUPPORTS SUMP CAISSON 30 " FABRICATION PTJ107 SUMP CAISSON 30 " FABRICATION
MUD MAT MA
WALK W WAY & STAIRS
LAUNCH RUNNERS AT ROW D FROM EL. -33400 TO -10600
PTJ98 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... FROM EL. -56200 TO -33400
FROM EL. -79000 TO -56200
Finish
Page 43 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
34 21-Jun-11
31-Jul-11
25-Apr-11 A
30-Jun-11
PTJ97 WELDING & NDT OF LUNCH TRUSS FROM EL -79 UP TO -56
24 14-Jul-11
11-Aug-11
18-May-11 A
12-Jul-11
2 13-Aug-11
14-Aug-11
12-Jul-11
14-Jul-11
118 31-Mar-11
14-Aug-11
31-Mar-11 A
14-Jul-11
87 31-Mar-11
24-May-11
31-Mar-11 A
10-Jul-11
PTJ97 FITUP OF LUNCH TRUSS FROM EL -33.4 UP TO -10.6
32 31-Mar-11
10-May-11
31-Mar-11 A
26-Jun-11
PTJ97 WELDING & NDT LUNCH TRUSS FROM EL -33.4 UP TO -10.6
24 24-Apr-11
22-May-11
26-Apr-11 A
07-Jul-11
2 23-May-11
24-May-11
07-Jul-11
10-Jul-11
45 21-Jun-11
14-Aug-11
25-Apr-11 A
14-Jul-11
PTJ96 FITUP OF LUNCH TRUSS FROM EL -79 UP TO -56
34 21-Jun-11
31-Jul-11
25-Apr-11 A
30-Jun-11
PTJ96 WELDING & NDT OF LUNCH TRUSS FROM EL -79 UP TO -56
24 14-Jul-11
11-Aug-11
18-May-11 A
12-Jul-11
2 13-Aug-11
14-Aug-11
12-Jul-11
14-Jul-11
50 11-May-11
04-Jul-11
01-May-11 A
12-Jul-11
PTJ97 FITUP OF LUNCH TRUSS FROM EL -56 UP TO -33.4
35 11-May-11
20-Jun-11
01-May-11 A
28-Jun-11
PTJ97 WELDING & NDT OF LUNCH TRUSS FROM EL -56 UP TO -33.4
25 04-Jun-11
02-Jul-11
14-May-11 A
10-Jul-11
PTJ97 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ...
2 03-Jul-11
04-Jul-11
10-Jul-11
12-Jul-11
167 21-Aug-11
21-Feb-12
11-Jun-11 A
26-Jan-12
PTJ100 INSTALL ANODES FOR ROW A
13 21-Aug-11
05-Sep-11
13-Jul-11
28-Jul-11
PTJ101 INSTALL ANODES FOR ROW B
8 04-Sep-11
12-Sep-11
14-Jun-11 A
04-Aug-11
PTJ102 INSTALL ANODES FOR ELEV -56.2
7 23-Oct-11
30-Oct-11
01-Aug-11
09-Aug-11
PTJ101 INSTALL ANODES FOR ROW C
6 01-Nov-11
07-Nov-11
10-Aug-11
17-Aug-11
PTJ102 INSTALL ANODES FOR ELEV -79.0
7 31-Oct-11
07-Nov-11
09-Aug-11
17-Aug-11
PTJ101 INSTALL ANODES FOR ROW D
6 09-Nov-11
15-Nov-11
18-Aug-11
25-Aug-11
PTJ102 INSTALL ANODES FOR ELEV -33.4
5 12-Nov-11
16-Nov-11
21-Aug-11
27-Aug-11
PTJ102 INSTALL ANODES FOR ELEV -10.6
5 29-Nov-11
04-Dec-11
27-Sep-11
03-Oct-11
PTJ101 INSTALL ANODES FOR ROW 3
6 12-Jan-12
18-Jan-12
16-Nov-11
22-Nov-11
PTJ101 INSTALL ANODES FOR ROW 1
10 04-Jan-12
15-Jan-12
10-Dec-11
20-Dec-11
PTJ101 INSTALL ANODES FOR ROW 2
10 28-Jan-12
07-Feb-12
11-Jun-11 A
12-Jan-12
AT ROW C FROM EL. -33400 TO -10600
PTJ97 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... FROM EL. -79000 TO -56200
PTJ96 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ... FROM EL. -56200 TO -33400
ANODES
2011 A M J Jul A S O N D
PTJ97 FITUP OF LUNCH TRUSS FROM EL -79 UP TO -56
PTJ97 LIFTING OF LUNCH TRUSS FROM EL -79 UP TO -56 ON SKID ...
Page 44 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ102 INSTALL ANODES FOR MUD MAT
7 14-Feb-12
21-Feb-12
19-Jan-12
26-Jan-12
PTJ102 INSTALL ANODES FOR SUMP CASSOIN
1 21-Feb-12
21-Feb-12
26-Jan-12
26-Jan-12
82 31-Aug-11
05-Dec-11
31-Aug-11
05-Dec-11
82 31-Aug-11
05-Dec-11
31-Aug-11
05-Dec-11
6 31-Aug-11
06-Sep-11
31-Aug-11
06-Sep-11
PTJ986 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPOR...
12 31-Aug-11
13-Sep-11
31-Aug-11
13-Sep-11
PTJ987 ROLLING OF BOUNCY TANK PLATE
20 07-Sep-11
29-Sep-11
07-Sep-11
29-Sep-11
PTJ988 SEAM WELD & REROLLING OF BOUNCY TANK PLATE
24 12-Sep-11
10-Oct-11
12-Sep-11
10-Oct-11
PTJ989 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUN...
24 11-Oct-11
07-Nov-11
11-Oct-11
07-Nov-11
PTJ99
10 08-Nov-11
19-Nov-11
08-Nov-11
19-Nov-11
24 08-Nov-11
05-Dec-11
08-Nov-11
05-Dec-11
82 31-Aug-11
05-Dec-11
31-Aug-11
05-Dec-11
6 31-Aug-11
06-Sep-11
31-Aug-11
06-Sep-11
PTJ993 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPOR...
12 31-Aug-11
13-Sep-11
31-Aug-11
13-Sep-11
PTJ994 ROLLING OF BOUNCY TANK PLATE
20 07-Sep-11
29-Sep-11
07-Sep-11
29-Sep-11
PTJ995 SEAM WELD & REROLLING OF BOUNCY TANK PLATE
24 12-Sep-11
10-Oct-11
12-Sep-11
10-Oct-11
PTJ996 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUN...
24 11-Oct-11
07-Nov-11
11-Oct-11
07-Nov-11
PTJ998 ERECTION OF BOUNCY TANK WITH LEGS
10 08-Nov-11
19-Nov-11
08-Nov-11
19-Nov-11
PTJ997 GIRTH WELD OF BOUNCY TANK
24 08-Nov-11
05-Dec-11
08-Nov-11
05-Dec-11
82 31-Aug-11
05-Dec-11
31-Aug-11
05-Dec-11
6 31-Aug-11
06-Sep-11
31-Aug-11
06-Sep-11
PTJ100 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPRT...
12 31-Aug-11
13-Sep-11
31-Aug-11
13-Sep-11
PTJ100 ROLLING OF BOUNCY TANK PLATE
20 07-Sep-11
29-Sep-11
07-Sep-11
29-Sep-11
PTJ100 SEAM WELD & REROLLING OF BOUNCY TANK PLATE
24 12-Sep-11
10-Oct-11
12-Sep-11
10-Oct-11
PTJ100 ERECTION OF SUPPORTS & STIFFENERS PLATE WITH BOUN...
24 11-Oct-11
07-Nov-11
11-Oct-11
07-Nov-11
PTJ100 ERECTION OF BOUNCY TANK WITH LEGS
10 08-Nov-11
19-Nov-11
08-Nov-11
19-Nov-11
PTJ100 GIRTH WELD OF BOUNCY TANK
24 08-Nov-11
05-Dec-11
08-Nov-11
05-Dec-11
82 31-Aug-11
05-Dec-11
31-Aug-11
05-Dec-11
BOUNCY TANKS AT LEG A1 PTJ985 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
ERECTION OF BOUNCY TANK WITH LEGS
PTJ990 GIRTH WELD OF BOUNCY TANK AT LEG A2 PTJ992 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
AT LEG B1 PTJ999 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
AT LEG B2
Finish
Page 45 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
6 31-Aug-11
06-Sep-11
31-Aug-11
06-Sep-11
PTJ100 CUTTING & EDGE PREPARATION OF BOUNCY TANK SUPPOR...
12 31-Aug-11
13-Sep-11
31-Aug-11
13-Sep-11
PTJ100 ROLLING OF BOUNCY TANK PLATE
20 07-Sep-11
29-Sep-11
07-Sep-11
29-Sep-11
PTJ10
SEAM WELD & REROLLING OF BOUNCY TANK PLATE
24 12-Sep-11
10-Oct-11
12-Sep-11
10-Oct-11
PTJ10
ERECTION OF SUPPORTS& STIFFENERS PLATE WITH BOUN...
24 11-Oct-11
07-Nov-11
11-Oct-11
07-Nov-11
PTJ10
ERECTION OF BOUNCY TANK WITH LEGS
10 08-Nov-11
19-Nov-11
08-Nov-11
19-Nov-11
PTJ10
GIRTH WELD OF BOUNCY TANK
24 08-Nov-11
05-Dec-11
08-Nov-11
05-Dec-11
35 01-Jan-12
09-Feb-12
06-Dec-11
15-Jan-12
PTJ107 BALASTING INSTALLATION
20 01-Jan-12
23-Jan-12
06-Dec-11
28-Dec-11
PTJ109 GROUTING INSTALLATION ON ROW 1
20 01-Jan-12
23-Jan-12
06-Dec-11
28-Dec-11
PTJ109 GROUTING INSTALLATION ON ROW 2
20 18-Jan-12
09-Feb-12
24-Dec-11
15-Jan-12
120 22-Sep-11
09-Feb-12
08-Sep-11
26-Jan-12
120 22-Sep-11
09-Feb-12
08-Sep-11
26-Jan-12
32 31-Aug-11
08-Oct-11
31-Aug-11
08-Oct-11
PTJ107 INSTALLATION AIDS FABRICATION
22 31-Aug-11
25-Sep-11
31-Aug-11
25-Sep-11
PTJ107 INSTALLATION AIDS INSTALLATION
10 26-Sep-11
08-Oct-11
26-Sep-11
08-Oct-11
17 31-Dec-11
18-Jan-12
03-Nov-11
22-Nov-11
PTJ9300 FITUP OF PREBENT CONDUCTOR
8 31-Dec-11
08-Jan-12
03-Nov-11
12-Nov-11
PTJ9310 WELDING OF PREBENT CONDUCTOR
9 09-Jan-12
18-Jan-12
13-Nov-11
22-Nov-11
141 03-Oct-11
15-Mar-12
03-Oct-11
15-Mar-12
PTJ10320 SPLASH PAINTING FOR MISC. (H.R, STAIRS, ...ETC)
7 03-Oct-11
11-Oct-11
03-Oct-11
11-Oct-11
PTJ10300 SPLASH PAINTING FOR ROW A
7 05-Dec-11
12-Dec-11
03-Oct-11
12-Oct-11
PTJ10310 SPLASH PAINTING FOR ROW B
7 10-Dec-11
17-Dec-11
09-Oct-11
17-Oct-11
PTJ10340 ATMOSPHERIC PAINTING FOR TOP ELEV
7 14-Dec-11
21-Dec-11
18-Oct-11
25-Oct-11
PTJ10280 SPLASH PAINTING FOR ROW 1
7 16-Jan-12
23-Jan-12
21-Dec-11
28-Dec-11
PTJ10290 SPLASH PAINTING FOR ROW 2
7 08-Feb-12
15-Feb-12
14-Jan-12
21-Jan-12
14 05-Feb-12
20-Feb-12
10-Jan-12
25-Jan-12
5 11-Mar-12
15-Mar-12
11-Mar-12
15-Mar-12
PTJ100 CUTTING & EDGE PREPARATION OF BOUNCY TANK PLATE
BALLASTING & GROUTING SYSTEM BALLAS
GRILLAGE & SEA FASTENING GRILLAG PTJ108 GRILLAGE & SEA FASTENING FABRICATION INSTALLATION AIDS INSTALL
PREBENT CONDUCTOR PREBEN
PAINTING
PTJ10260 SPLASH PAINTING FOR BOAT LAND PTJ10270 SPLASH PAINTING FOR BARGE BUMPER
Finish
Page 46 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
28 13-Feb-12
15-Mar-12
13-Feb-12
15-Mar-12
10 11-Feb-12
21-Feb-12
16-Jan-12
26-Jan-12
PTJ10990 RISER HYDRO TEST
10 11-Feb-12
21-Feb-12
16-Jan-12
26-Jan-12
PTJ11000 BALLASTING SYSTEM TEST
10 11-Feb-12
21-Feb-12
16-Jan-12
26-Jan-12
PTJ11010 GROUTING SYSTEM TEST
10 11-Feb-12
21-Feb-12
16-Jan-12
26-Jan-12
17-Dec-11
15-Apr-11 A
17-Nov-11
PTJ10330 PILE MARKING INSPECTION, TESTING & PRE-COMMISIONING INSPECT
PILES FAB FABRICATION PTJ2030
Piiles fabrication start
PTJ10380 Piiles fabrication finish AT LEG A1
123 02-Jul-11 0 02-Jul-11 0
Finish
15-Apr-11 A 17-Dec-11
17-Nov-11
31-Aug-11
15-Apr-11 A
28-Jul-11
PTJ10420 Automatic welding 6 joints
24 06-Jul-11
02-Aug-11
24-Apr-11 A
11-Jun-11 A
PTJ10430 back weld manual 6 joints
16 16-Jul-11
02-Aug-11
02-May-11 A
12-Jun-11 A
PTJ10390 Manual fitup & welding 6 joints
23 02-Jul-11
28-Jul-11
15-Apr-11 A
06-Jul-11
PTJ10410 Welding beads (41 joints)
10 03-Aug-11
14-Aug-11
04-May-11 A
19-Jul-11
PTJ10400 Fitup & welding for manual joint (2 joints)
10 20-Aug-11
31-Aug-11
17-Jul-11
28-Jul-11
61 02-Jul-11
04-Oct-11
25-Jun-11
05-Sep-11
PTJ10440 Manual fitup & welding automatic 6 joints
24 02-Jul-11
28-Jul-11
25-Jun-11
21-Jul-11
PTJ10460 back weld manual 6 joints
16 18-Aug-11
06-Sep-11
19-Jul-11
07-Aug-11
PTJ10450 Automatic welding 6 joints
24 10-Aug-11
07-Sep-11
11-Jul-11
08-Aug-11
PTJ10480 Welding beads (41 joints)
10 08-Sep-11
19-Sep-11
08-Aug-11
20-Aug-11
PTJ10470 Fitup & welding for manual joint (2 joints)
10 24-Sep-11
04-Oct-11
23-Aug-11
05-Sep-11
87 02-Jul-11
12-Nov-11
02-May-11 A
13-Oct-11
PTJ10490 Manual fitup & welding automatic 6 joints
23 02-Jul-11
28-Jul-11
02-May-11 A
14-Jul-11
PTJ10500 Automatic welding 6 joints
24 15-Sep-11
13-Oct-11
15-Aug-11
13-Sep-11
PTJ10510 back weld manual 6 joints
16 26-Sep-11
15-Oct-11
25-Aug-11
14-Sep-11
PTJ10530 Welding beads (41 joints)
10 15-Oct-11
25-Oct-11
06-Jun-11 A
22-Sep-11
PTJ10520 Fitup & welding for manual joint (2 joints)
10 01-Nov-11
12-Nov-11
01-Oct-11
13-Oct-11
123 02-Jul-11
17-Dec-11
25-Jun-11
17-Nov-11
24 02-Jul-11
28-Jul-11
25-Jun-11
21-Jul-11
AT LEG B1
AT LEG B2 PTJ10540 Manual fitup & welding automatic 6 joints
2011 A M J Jul A S O N D
39 02-Jul-11
AT LEG A2
Page 47 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ10550 Automatic welding 6 joints
24 22-Oct-11
17-Nov-11
20-Sep-11
19-Oct-11
PTJ10560 back weld manual 6 joints
16 01-Nov-11
19-Nov-11
01-Oct-11
20-Oct-11
PTJ10580 Welding beads (41 joints)
10 19-Nov-11
29-Nov-11
19-Oct-11
31-Oct-11
PTJ10570 Fitup & welding for manual joint (2 joints)
10 06-Dec-11
17-Dec-11
06-Nov-11
17-Nov-11
79 16-Jul-11
03-Oct-11
02-Apr-11 A
17-Jul-11
PRE-DRILLING TEMPLATE PRE-DRIL PTD000
Pre-drilling template fabrication start
0 16-Jul-11
Finish
02-Apr-11 A
5 16-Jul-11
20-Jul-11
02-Apr-11 A
07-Apr-11 A
PTJ10820 welding & NDT of bottom plate
6 02-Aug-11
08-Aug-11
03-May-11 A
25-May-11 A
PTJ10830 cutting, rolling and assembly of outer frame
6 02-Aug-11
08-Aug-11
03-May-11 A
25-May-11 A
01-Aug-11
16-Apr-11 A
25-May-11 A
5 09-Aug-11
14-Aug-11
10-May-11 A
25-Jun-11
PTJ10850 fabrication of beams ( built up section )
10 15-Aug-11
25-Aug-11
16-May-11 A
25-Jun-11
PTJ10860 installation of beams with bottom frame
5 27-Aug-11
04-Sep-11
14-May-11 A
27-Jun-11
PTJ10870 cutting of conductor pipe
2 05-Sep-11
06-Sep-11
08-May-11 A
28-Jun-11
PTJ10920 fabrication of pad eyes
5 05-Sep-11
10-Sep-11
08-May-11 A
02-Jul-11
PTJ10880 fabrication & installation of shims plates
4 07-Sep-11
11-Sep-11
11-May-11 A
02-Jul-11
PTJ10890 installation of conductor pipe
5 12-Sep-11
17-Sep-11
15-May-11 A
05-Jul-11
PTJ10930 installation of pad eyes
5 11-Sep-11
15-Sep-11
02-Jul-11
07-Jul-11
PTJ10910 installation of cones
7 18-Sep-11
25-Sep-11
21-May-11 A
09-Jul-11
10 14-Sep-11
25-Sep-11
27-Jun-11
09-Jul-11
PTJ10840 welding & NDT of outer frame
PTJ10940 fabrication of lifting tool PTJ2010
Pre-drilling template fabrication finish
PTJ10950 painting of template W.P.5: DEC DECK & TSF FABRICATION DECK FABRICATION FAB General Activities A
14 16-Jul-11
0
03-Oct-11
17-Jul-11
7 26-Sep-11
03-Oct-11
09-Jul-11
17-Jul-11
271 31-Mar-11
03-May-12
31-Mar-11 A
01-May-12
271 31-Mar-11
03-May-12
31-Mar-11 A
01-May-12
268 28-May-11
29-Apr-12
03-Apr-11 A
26-Apr-12
PTJ2040 Deck primary structure fabrication start
0 28-May-11
03-Apr-11 A
PTJ2160 Deck secondray structure fabrication start
0 31-Aug-11
19-May-11 A
PTJ1150 Static equipment (by petrojet)
120 10-Aug-11
07-Dec-11
2011 A M J Jul A S O N D
PTJ10810 cutting & assembly of bottom plate
PTJ10900 fabrication of cones
Page 48 of 64
10-Aug-11
07-Dec-11*
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTJ1160 Piping & E&I supports (by petrojet)
30 20-Nov-11
20-Dec-11
18-Nov-11
17-Dec-11
PTJ2060 Deck pre-commisioning
40 12-Feb-12
29-Mar-12
11-Feb-12
27-Mar-12
PTJ2065 Crane assembly and erection
20 03-Apr-12
26-Apr-12
19-Mar-12
10-Apr-12
1 26-Apr-12
28-Apr-12
11-Apr-12
11-Apr-12
26 29-Mar-12
29-Apr-12
28-Mar-12
26-Apr-12
327 31-Mar-11
03-May-12
31-Mar-11 A
17-Apr-12
46 31-Mar-11
22-May-11
31-Mar-11 A
31-May-11 A
PTD100 Cutting & Assembly
20 31-Mar-11
25-Apr-11
31-Mar-11 A
27-Apr-11 A
PTD100 Welding & NDT
28 18-Apr-11
22-May-11
19-Apr-11 A
31-May-11 A
199 28-May-11
14-Jan-12
25-May-11 A
14-Jan-12
PTJD10 Profiling Template
4 28-May-11
31-May-11
25-May-11 A
27-Jun-11
PTD103 Assembly
6 28-Dec-11
03-Jan-12
28-Dec-11
03-Jan-12
12 01-Jan-12
14-Jan-12
01-Jan-12
14-Jan-12
145 28-May-11
21-Nov-11
28-Apr-11 A
14-Nov-11
26 28-May-11
26-Jun-11
28-Apr-11 A
30-Jun-11
PTD10 Cutting & Assembly
16 28-May-11
14-Jun-11
28-Apr-11 A
30-May-11 A
PTD10 Welding & NDT
22 01-Jun-11
26-Jun-11
01-May-11 A
30-Jun-11
70 28-May-11
26-Jul-11
28-Apr-11 A
16-Aug-11
PTD10 Cutting & Assembly
36 28-May-11
07-Jul-11
28-Apr-11 A
06-Jun-11 A
PTD10 Welding & NDT
46 04-Jun-11
26-Jul-11
25-Jun-11
16-Aug-11
Secondary Beams Fabrication Second
28 31-Aug-11
10-Oct-11
19-May-11 A
02-Oct-11
PTD10 Cutting & Assembly
22 31-Aug-11
25-Sep-11
19-May-11 A
06-Sep-11
PTD11 Welding & NDT
28 07-Sep-11
10-Oct-11
31-Aug-11
02-Oct-11
36 11-Oct-11
21-Nov-11
03-Oct-11
14-Nov-11
PTD11 Cutting & Assembly
20 11-Oct-11
02-Nov-11
03-Oct-11
26-Oct-11
PTD11 Welding & NDT
24 25-Oct-11
21-Nov-11
18-Oct-11
14-Nov-11
10 31-Aug-11
19-Sep-11
19-May-11 A
13-Sep-11
7 31-Aug-11
07-Sep-11
19-May-11 A
04-Sep-11
PTJ2220 Deck weighing PTJ2090 Deck commisioning Deck Structure Stru Fabrication Deck Leg Legs Fabrication
Braces Below B Cellar
PTD104 Welding & NDT Cellar De Deck Fabrication (+11.000) Joints Fabrication F
Main Be Beams Fabrication
Embossed Plates Emboss
PLAN AT EL. + 9.200 Main Be Beams Fabrication
Finish
Page 49 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
PTD17 Cutting & Assembly
3 31-Aug-11
03-Sep-11
19-May-11 A
31-Aug-11
PTD17 Welding & NDT
4 04-Sep-11
07-Sep-11
21-May-11 A
04-Sep-11
Secondary Beams Fabrication Second
7 08-Sep-11
13-Sep-11
19-May-11 A
07-Sep-11
PTD17 Cutting & Assembly
2 08-Sep-11
10-Sep-11
19-May-11 A
04-Sep-11
PTD17 Welding & NDT
3 11-Sep-11
13-Sep-11
04-Sep-11
07-Sep-11
5 14-Sep-11
19-Sep-11
07-Sep-11
13-Sep-11
PTD17 Cutting & Assembly
2 14-Sep-11
15-Sep-11
07-Sep-11
10-Sep-11
PTD17 Welding & NDT
3 17-Sep-11
19-Sep-11
10-Sep-11
13-Sep-11
25 31-Aug-11
13-Oct-11
19-May-11 A
01-Oct-11
10 31-Aug-11
20-Sep-11
19-May-11 A
12-Sep-11
8 31-Aug-11
08-Sep-11
19-May-11 A
31-Aug-11
10 10-Sep-11
20-Sep-11
31-Aug-11
12-Sep-11
Secondary Beams Fabrication Second
8 21-Sep-11
02-Oct-11
18-Jun-11 A
20-Sep-11
PTD16 Cutting & Assembly
4 21-Sep-11
25-Sep-11
18-Jun-11 A
13-Sep-11
PTD16 Welding & NDT
6 26-Sep-11
02-Oct-11
13-Sep-11
20-Sep-11
9 03-Oct-11
13-Oct-11
20-Sep-11
01-Oct-11
PTD16 Cutting & Assembly
4 03-Oct-11
08-Oct-11
20-Sep-11
25-Sep-11
PTD16 Welding & NDT
5 09-Oct-11
13-Oct-11
25-Sep-11
01-Oct-11
55 31-Aug-11
03-Nov-11
31-Aug-11
03-Nov-11
11 31-Aug-11
12-Sep-11
31-Aug-11
12-Sep-11
5 31-Aug-11
05-Sep-11
31-Aug-11
05-Sep-11
GRATING GRATIN
PLAN AT EL. + 9.700 Main Be Beams Fabrication PTD16 Cutting & Assembly PTD16 Welding & NDT
GRATING GRATIN
WELL HEAD H MEZZANINE AT (+ 16.000) Joints Fabrication F PTD15 Cutting & Assembly PTD15 Welding & NDT
Finish
6 06-Sep-11
12-Sep-11
06-Sep-11
12-Sep-11
08-Oct-11
13-Sep-11
08-Oct-11
9 13-Sep-11
22-Sep-11
13-Sep-11
22-Sep-11
12 24-Sep-11
08-Oct-11
24-Sep-11
08-Oct-11
Secondary Beams Fabrication Second
12 09-Oct-11
22-Oct-11
09-Oct-11
22-Oct-11
PTD15 Cutting & Assembly
5 09-Oct-11
13-Oct-11
09-Oct-11
13-Oct-11
PTD15 Welding & NDT
7 15-Oct-11
22-Oct-11
15-Oct-11
22-Oct-11
PTD15 Cutting & Assembly PTD15 Welding & NDT
2011 A M J Jul A S O N D
21 13-Sep-11
Main Be Beams Fabrication
Page 50 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
11 23-Oct-11
03-Nov-11
23-Oct-11
03-Nov-11
PTD15 Cutting & Assembly
5 23-Oct-11
27-Oct-11
23-Oct-11
27-Oct-11
PTD16 Welding & NDT
6 29-Oct-11
03-Nov-11
29-Oct-11
03-Nov-11
128 28-May-11
22-Nov-11
25-Jun-11
22-Nov-11
PTD113 Profiling Template
14 28-May-11
12-Jun-11
25-Jun-11
10-Jul-11
PTD114 Assembly
24 02-Oct-11
30-Oct-11
02-Oct-11
30-Oct-11
PTD115 Welding & NDT
32 17-Oct-11
22-Nov-11
17-Oct-11
22-Nov-11
131 28-May-11
05-Nov-11
28-Apr-11 A
29-Oct-11
46 28-May-11
19-Jul-11
28-Apr-11 A
06-Jul-11
PTD11 Cutting & Assembly
20 28-May-11
19-Jun-11
28-Apr-11 A
31-May-11 A
PTD11 Welding & NDT
26 20-Jun-11
19-Jul-11
07-May-11 A
06-Jul-11
70 30-May-11
16-Aug-11
30-Apr-11 A
18-Aug-11
PTD11 Cutting & Assembly
36 30-May-11
10-Jul-11
30-Apr-11 A
03-Jul-11
PTD11 Welding & NDT
48 22-Jun-11
16-Aug-11
25-Jun-11
18-Aug-11
Secondary Beams Fabrication Second
26 31-Aug-11
08-Oct-11
21-May-11 A
29-Sep-11
PTD12 Cutting & Assembly
20 31-Aug-11
22-Sep-11
21-May-11 A
12-Sep-11
PTD12 Welding & NDT
26 07-Sep-11
08-Oct-11
31-Aug-11
29-Sep-11
37 22-Sep-11
05-Nov-11
15-Sep-11
29-Oct-11
PTD12 Cutting & Assembly
20 22-Sep-11
16-Oct-11
15-Sep-11
09-Oct-11
PTD12 Welding & NDT
24 09-Oct-11
05-Nov-11
01-Oct-11
29-Oct-11
Braces & Legs Above Main
185 28-May-11
28-Jan-12
25-Jun-11
28-Jan-12
PTD124 Profiling Template
8 28-May-11
05-Jun-11
25-Jun-11
03-Jul-11
PTD125 Assembly
8 15-Jan-12
23-Jan-12
15-Jan-12
23-Jan-12
10 17-Jan-12
28-Jan-12
17-Jan-12
28-Jan-12
164 28-May-11
12-Dec-11
25-May-11 A
17-Nov-11
PTD127 Profiling Template
22 28-May-11
21-Jun-11
25-May-11 A
26-Jun-11
PTD128 Assembly
40 16-Oct-11
30-Nov-11
13-Jun-11 A
12-Oct-11
PTD129 Welding & NDT
35 02-Nov-11
12-Dec-11
09-Oct-11
17-Nov-11
GRATING GRATIN
Braces & Legs between Cellar and Main
Main Dec Deck Fabrication (+17.000) Joints Fabrication F
Main Be Beams Fabrication
Embossed Plates Emboss
PTD126 Welding & NDT Braces Below B Heli Deck
Finish
Page 51 of 64
2011 A M J Jul A S O N D
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
90 07-Aug-11
12-Dec-11
07-May-11 A
21-Nov-11
24 07-Aug-11
06-Sep-11
07-May-11 A
22-Aug-11
8 07-Aug-11
15-Aug-11
07-May-11 A
14-Jun-11 A
12 23-Aug-11
06-Sep-11
18-Jun-11 A
22-Aug-11
24 16-Aug-11
20-Sep-11
16-May-11 A
06-Sep-11
PTD13 Cutting & Assembly
14 16-Aug-11
04-Sep-11
16-May-11 A
23-Jun-11 A
PTD13 Welding & NDT
24 23-Aug-11
20-Sep-11
09-Aug-11
06-Sep-11
Secondary Beams Fabrication Second
32 31-Aug-11
15-Oct-11
21-May-11 A
08-Oct-11
PTD13 Cutting & Assembly
24 31-Aug-11
27-Sep-11
21-May-11 A
13-Sep-11
PTD13 Welding & NDT
32 07-Sep-11
15-Oct-11
31-Aug-11
08-Oct-11
29 10-Oct-11
12-Nov-11
02-Oct-11
05-Nov-11
PTD13 Cutting & Assembly
18 10-Oct-11
30-Oct-11
02-Oct-11
23-Oct-11
PTD13 Welding & NDT
24 16-Oct-11
12-Nov-11
09-Oct-11
05-Nov-11
14 13-Nov-11
28-Nov-11
06-Nov-11
21-Nov-11
PTD13 Cutting & Assembly
6 13-Nov-11
19-Nov-11
06-Nov-11
12-Nov-11
PTD13 Welding & NDT
8 20-Nov-11
28-Nov-11
13-Nov-11
21-Nov-11
14 13-Nov-11
12-Dec-11
06-Nov-11
21-Nov-11
PTD14 Cutting & Assembly
6 13-Nov-11
19-Nov-11
06-Nov-11
12-Nov-11
PTD14 Welding & NDT
8 04-Dec-11
12-Dec-11
13-Nov-11
21-Nov-11
Misellaneuos Misellane
153 10-Nov-11
03-May-12
23-Oct-11
17-Apr-12
Installation Installat
117 04-Dec-11
03-May-12
04-Dec-11
17-Apr-12
Heli Dec Deck Fabrication (+29.125) Joints Fabrication F PTD13 Cutting & Assembly PTD13 Welding & NDT Main Be Beams Fabrication
Covering Plates Coverin
Gutter
Landing Area
Finish
Page 52 of 64
2011 A M J Jul A S O N D
PTMD
Monorail Beam
10 04-Dec-11
14-Dec-11
04-Dec-11
14-Dec-11
PTMD
Safety Net
16 27-Dec-11
14-Jan-12
06-Dec-11
24-Dec-11
PTMD
Crane Boom Rest
2 15-Jan-12
16-Jan-12
15-Jan-12
16-Jan-12
PTMD
Name Plate
4 15-Jan-12
18-Jan-12
15-Jan-12
18-Jan-12
PTMD
Handrails & Cups
24 25-Dec-11
21-Jan-12
25-Dec-11
21-Jan-12
PTMD
Hatches
8 15-Jan-12
23-Jan-12
15-Jan-12
23-Jan-12
PTMD
Fire Wall
12 15-Jan-12
28-Jan-12
15-Jan-12
28-Jan-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name PTMD
Stairs & Walkways
PTMD
Pad Eyes
Fabrication Fabrica
Original BL Project Duration Start
BL Project Finish
Start
Finish
15 15-Jan-12
31-Jan-12
15-Jan-12
31-Jan-12
5 28-Apr-12
03-May-12
12-Apr-12
17-Apr-12
148 10-Nov-11
28-Apr-12
23-Oct-11
11-Apr-12
Safety Net
28 13-Nov-11
14-Dec-11
23-Oct-11
23-Nov-11
PTMD
Monorail Beam
10 22-Nov-11
03-Dec-11
22-Nov-11
03-Dec-11
PTMD
Handrails & Cups
24 10-Nov-11
07-Dec-11
10-Nov-11
07-Dec-11
PTMD
Name Plate
8 25-Dec-11
02-Jan-12
25-Dec-11
02-Jan-12
PTMD
Hatches
20 14-Dec-11
05-Jan-12
14-Dec-11
05-Jan-12
PTMD
Crane Boom Rest
6 31-Dec-11
05-Jan-12
31-Dec-11
05-Jan-12
PTMD
Fire Wall
18 17-Dec-11
05-Jan-12
17-Dec-11
05-Jan-12
PTMD
Stairs & Walkways
24 26-Dec-11
22-Jan-12
26-Dec-11
22-Jan-12
PTMD
Pad Eyes
6 21-Apr-12
28-Apr-12
05-Apr-12
11-Apr-12
68 29-Jan-12
17-Apr-12
28-Jan-12
15-Apr-12
PTD150 Cutting & Assembly
20 29-Jan-12
21-Feb-12
28-Jan-12
19-Feb-12
PTD151 Welding & NDT
32 21-Feb-12
29-Mar-12
20-Feb-12
27-Mar-12
2 15-Apr-12
17-Apr-12
14-Apr-12
15-Apr-12
173 28-May-11
14-Jan-12
25-Jun-11
14-Jan-12
24 28-May-11
23-Jun-11
25-Jun-11
21-Jul-11
24 28-May-11
23-Jun-11
25-Jun-11
21-Jul-11
2 08-Dec-11
10-Dec-11
08-Dec-11
10-Dec-11
2 08-Dec-11
10-Dec-11
08-Dec-11
10-Dec-11
PTD152 Trial Fit Deck Assembly Ass Skid Beams Be & Shoes Preparation PTD14 Skid Beams & Shoes Preparation Lifting Deck D Legs Over Skid Beams & Skid Shoes PTD14 Lifting Deck Legs Over Skid Beams & Skid Shoes Lifting Cellar C Deck Over Deck Legs
15 11-Dec-11
27-Dec-11
11-Dec-11
27-Dec-11
PTD14 Lifting
1 11-Dec-11
11-Dec-11
11-Dec-11
11-Dec-11
PTD14 Assembly
6 12-Dec-11
18-Dec-11
12-Dec-11
18-Dec-11
PTD14 Welding & NDT
8 19-Dec-11
27-Dec-11
19-Dec-11
27-Dec-11
4 28-Dec-11
01-Jan-12
28-Dec-11
01-Jan-12
PTD17 Lifting
1 28-Dec-11
28-Dec-11
28-Dec-11
28-Dec-11
PTD17 Assembly
1 29-Dec-11
29-Dec-11
29-Dec-11
29-Dec-11
lifting of plan at + 9.2
2011 A M J Jul A S O N D
PTMD
Deck Flare Fla
Page 53 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
2 31-Dec-11
01-Jan-12
31-Dec-11
01-Jan-12
4 28-Dec-11
01-Jan-12
28-Dec-11
01-Jan-12
PTD16 Lifting
1 28-Dec-11
28-Dec-11
28-Dec-11
28-Dec-11
PTD16 Assembly
1 29-Dec-11
29-Dec-11
29-Dec-11
29-Dec-11
PTD16 Welding & NDT
2 31-Dec-11
01-Jan-12
31-Dec-11
01-Jan-12
4 28-Dec-11
01-Jan-12
28-Dec-11
01-Jan-12
PTD17 Lifting
1 28-Dec-11
28-Dec-11
28-Dec-11
28-Dec-11
PTD18 Assembly
1 29-Dec-11
29-Dec-11
29-Dec-11
29-Dec-11
PTD18 Welding & NDT
2 31-Dec-11
01-Jan-12
31-Dec-11
01-Jan-12
11 02-Jan-12
14-Jan-12
02-Jan-12
14-Jan-12
PTD14 Lifting
1 02-Jan-12
02-Jan-12
02-Jan-12
02-Jan-12
PTD14 Assembly
5 03-Jan-12
08-Jan-12
03-Jan-12
08-Jan-12
PTD14 Welding & NDT
7 07-Jan-12
14-Jan-12
07-Jan-12
14-Jan-12
181 20-Sep-11
15-Apr-12
13-Sep-11
12-Apr-12
PTD17 Welding & NDT lifting of plan at + 9.7
lifting of mezzanine deck at + 16
Lifting Main M Deck Over cellar Deck
Atmosphric Painting Atmosphr
Finish
Page 54 of 64
2011 A M J Jul A S O N D
PT1110
Plane at + 9.2
5 20-Sep-11
25-Sep-11
13-Sep-11
19-Sep-11
PT1120
Plane at + 9.7
5 15-Oct-11
19-Oct-11
01-Oct-11
08-Oct-11
PT1130
Wellhead mezzanine
10 05-Nov-11
15-Nov-11
05-Nov-11
15-Nov-11
PT1050
Heli Deck & Braces Below Heli
12 13-Dec-11
26-Dec-11
22-Nov-11
05-Dec-11
PT1010
Deck Legs
6 01-Dec-11
07-Dec-11
01-Dec-11
07-Dec-11
PT1020
Braces Below Cellar
5 05-Dec-11
10-Dec-11
05-Dec-11
10-Dec-11
PT1030
Cellar Deck & Braces Above Cellar
15 23-Nov-11
10-Dec-11
23-Nov-11
10-Dec-11
PT1080
Piping Support
PT1040
Main Deck
PT1045
Braces Above Main
PT1090
9 06-Dec-11
17-Dec-11
06-Dec-11
17-Dec-11
15 15-Dec-11
01-Jan-12
15-Dec-11
01-Jan-12
5 09-Jan-12
14-Jan-12
09-Jan-12
14-Jan-12
Cable Trays Supports
10 15-Jan-12
26-Jan-12
16-Jan-12
26-Jan-12
PT1060
Miscellaneous (Stairs,H/R,...etc)
14 12-Jan-12
28-Jan-12
12-Jan-12
28-Jan-12
PT1070
Piping painting
14 19-Jan-12
05-Feb-12
19-Jan-12
04-Feb-12
PT1100
Deck Flare
14 29-Mar-12
15-Apr-12
28-Mar-12
12-Apr-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Anti Skid Painting P PT1000
Heli Deck
E&I
Original BL Project Duration Start
BL Project Finish
Start
7 25-Apr-12
03-May-12
24-Apr-12
01-May-12
7 25-Apr-12
03-May-12
24-Apr-12
01-May-12
80 16-Dec-11
11-Mar-12
21-Dec-11
09-Mar-12
PTJ2080
E & I Work start
0 16-Dec-11
PTJ2100
E & I Work finish
0
E&I (onsh (onshore)
Finish
21-Dec-11 11-Mar-12
09-Mar-12
11-Mar-12
21-Dec-11
09-Mar-12
72 16-Dec-11
02-Mar-12
21-Dec-11
01-Mar-12
Cable Trays T Supports
51 20-Dec-11
09-Feb-12
21-Dec-11
09-Feb-12
E&I100 Fabrication
26 20-Dec-11
15-Jan-12
21-Dec-11
15-Jan-12
E&I101 Installation
14 26-Jan-12
09-Feb-12
27-Jan-12
09-Feb-12
26 24-Jan-12
19-Feb-12
24-Jan-12
18-Feb-12
26 24-Jan-12
19-Feb-12
24-Jan-12
18-Feb-12
38 16-Dec-11
23-Jan-12
21-Dec-11
27-Jan-12
38 16-Dec-11
23-Jan-12
21-Dec-11
27-Jan-12
25 31-Dec-11
25-Jan-12
05-Jan-12
29-Jan-12
25 31-Dec-11
25-Jan-12
05-Jan-12
29-Jan-12
15 16-Dec-11
31-Dec-11
21-Dec-11
04-Jan-12
15 16-Dec-11
31-Dec-11
21-Dec-11
04-Jan-12
14 17-Feb-12
02-Mar-12
17-Feb-12
01-Mar-12
14 17-Feb-12
02-Mar-12
17-Feb-12
01-Mar-12
12 17-Feb-12
29-Feb-12
17-Feb-12
28-Feb-12
12 17-Feb-12
29-Feb-12
17-Feb-12
28-Feb-12
25 01-Feb-12
26-Feb-12
01-Feb-12
25-Feb-12
25 01-Feb-12
26-Feb-12
01-Feb-12
25-Feb-12
80 20-Dec-11
11-Mar-12
21-Dec-11
09-Mar-12
Cable Trays T Supports
51 20-Dec-11
09-Feb-12
21-Dec-11
09-Feb-12
E&I109 Fabrication
26 20-Dec-11
15-Jan-12
21-Dec-11
15-Jan-12
E&I110 Installation
14 26-Jan-12
09-Feb-12
27-Jan-12
09-Feb-12
Cable Trays T E&I102 Installation Conduit Activities E&I103 Installation Lighting Activities E&I104 Lighting Activities Navigation Aids Navigat E&I105 Navigation Aids Earthing Activities E&I106 Earthing Activities Power & Small Equip. Inst. E&I107 Power & Small Equip. Inst. Cable Laying L & Termination E&I108 Cable Laying & Termination Instrumentation Instrume
2011 A M J Jul A S O N D
80 16-Dec-11
Electrical
Page 55 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
26 24-Jan-12
19-Feb-12
24-Jan-12
18-Feb-12
26 24-Jan-12
19-Feb-12
24-Jan-12
18-Feb-12
20 12-Feb-12
03-Mar-12
11-Feb-12
01-Mar-12
20 12-Feb-12
03-Mar-12
11-Feb-12
01-Mar-12
16 20-Feb-12
07-Mar-12
19-Feb-12
05-Mar-12
16 20-Feb-12
07-Mar-12
19-Feb-12
05-Mar-12
18 09-Feb-12
27-Feb-12
10-Feb-12
27-Feb-12
18 09-Feb-12
27-Feb-12
10-Feb-12
27-Feb-12
20 09-Feb-12
29-Feb-12
10-Feb-12
29-Feb-12
20 09-Feb-12
29-Feb-12
10-Feb-12
29-Feb-12
10 27-Feb-12
08-Mar-12
26-Feb-12
06-Mar-12
10 27-Feb-12
08-Mar-12
26-Feb-12
06-Mar-12
8 26-Feb-12
05-Mar-12
25-Feb-12
03-Mar-12
E&I117 Air Gas Header
8 26-Feb-12
05-Mar-12
25-Feb-12
03-Mar-12
Cable Laying L & Termination
25 14-Feb-12
10-Mar-12
13-Feb-12
08-Mar-12
25 14-Feb-12
10-Mar-12
13-Feb-12
08-Mar-12
8 03-Mar-12
11-Mar-12
02-Mar-12
09-Mar-12
8 03-Mar-12
11-Mar-12
02-Mar-12
09-Mar-12
8 03-Mar-12
11-Mar-12
02-Mar-12
09-Mar-12
8 03-Mar-12
11-Mar-12
02-Mar-12
09-Mar-12
72 07-Dec-11
17-Feb-12
07-Dec-11
16-Feb-12
Cable Trays T E&I111 Installation Tubing Activities A E&I112 Installation HCU & Local Panels Activities E&I113 HCU & Local Panels Activities Fusible Plug & ESD Puch Bottons E&I114 Fusible Plug & ESD Puch Bottons J. Box A Activities E&I115 J. Box Activities Instrument Installation & Calibration Instrum E&I116 Instrument Installation & Calibration Air Gas Header
E&I118 Cable Laying & Termination Fire & G Gas activities E&I119 Fire & Gas activities Telecommunication System Telecom E&I120 Telecommunication System EQUIPMENT EQUIPMEN PTJ2070
Equipment installation start
0 23-Dec-11
PTJ2130
Equipment installation finish
0
Equipement Installation (onshore) Equipeme
Finish
Page 56 of 64
2011 A M J Jul A S O N D
18-Jan-12 17-Feb-12
16-Feb-12
72 07-Dec-11
17-Feb-12
07-Dec-11
16-Feb-12
TSF1110 Installation of production manifold module on celler deck
4 07-Dec-11
10-Dec-11
07-Dec-11*
10-Dec-11
TSF1100 Installation of E & I module on main deck
4 07-Jan-12
10-Jan-12
07-Jan-12*
10-Jan-12
TSF1090 Equipment Installation on Heli Deck
4 23-Dec-11
27-Dec-11
18-Jan-12
21-Jan-12
TSF1060 Equipment Installation Below Cellar Deck
4 13-Feb-12
17-Feb-12
13-Feb-12
16-Feb-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
TSF1070 Equipment Installation on Cellar Deck
15 02-Feb-12
17-Feb-12
02-Feb-12
16-Feb-12
TSF1080 Equipment Installation on Main Deck
15 02-Feb-12
17-Feb-12
02-Feb-12
16-Feb-12
113 20-Nov-11
13-Mar-12
20-Nov-11
11-Mar-12
PIPING PTJ2050
Piping & piping support fabrication start
0 20-Nov-11
PTJ2110
Piping & piping support erection finish
0
C.S Piping Fab. & Erec., Valves Erection (onshore)
Finish
20-Nov-11 13-Mar-12
11-Mar-12
13-Mar-12
20-Nov-11
11-Mar-12
TSF1010 Piping Supports Fabrication
22 20-Nov-11
12-Dec-11
20-Nov-11
11-Dec-11
TSF1000 Piping Fabrication
70 20-Nov-11
29-Jan-12
20-Nov-11
28-Jan-12
TSF1020 Piping Erection
35 28-Jan-12
03-Mar-12
27-Jan-12
01-Mar-12
TSF1030 Piping Supports Erection
20 12-Feb-12
03-Mar-12
11-Feb-12
01-Mar-12
TSF1040 Valve Installation
15 17-Feb-12
03-Mar-12
16-Feb-12
01-Mar-12
PTJ2120 Piping hydrotest
21 21-Feb-12
13-Mar-12
20-Feb-12
11-Mar-12
44 23-Feb-12
25-Apr-12
23-Feb-12
25-Apr-12
44 23-Feb-12
25-Apr-12
23-Feb-12
25-Apr-12
23 24-Mar-12
25-Apr-12
24-Mar-12
25-Apr-12
BEFORE METROLOGY
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
PIPE LINE LI & BENDS
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
SS690 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 24-Mar-12
26-Mar-12
24-Mar-12
26-Mar-12
SS700 CUTTING & BEVELING BEFORE METROLOGY
3 26-Mar-12
29-Mar-12
26-Mar-12
29-Mar-12
SS710 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
5 29-Mar-12
04-Apr-12
29-Mar-12
04-Apr-12
SS720 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL...
8 04-Apr-12
14-Apr-12
04-Apr-12
14-Apr-12
SS740 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 16-Apr-12
18-Apr-12
16-Apr-12
18-Apr-12
SS730 COATING OF BENDS
6 14-Apr-12
21-Apr-12
14-Apr-12
21-Apr-12
SS750 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 18-Apr-12
21-Apr-12
18-Apr-12
21-Apr-12
SS760 APPLY SHRINKABLE SLEEVE
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
11 15-Apr-12
25-Apr-12
15-Apr-12
25-Apr-12
SETH PLEM PLE & EXISTING TUNA PLEM SPOOL N NO. S1 (CLOSING) ( P.L - S2 )
AFTER M METROLOGY SS770
RECEVING METROLOGY
0 15-Apr-12
SS780
FIT UP AFTER METROLOGY
3 15-Apr-12
15-Apr-12 17-Apr-12
2011 A M J Jul A S O N D
113 20-Nov-11
W.P.6: PIPELINE PIPE SPOOLS FABRICATION
Page 57 of 64
15-Apr-12
17-Apr-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
WELDING & NDT AFTER METROLOGY
4 17-Apr-12
21-Apr-12
17-Apr-12
21-Apr-12
SS800
PIGGING & HYDRO TEST
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
SS810
APPLY SHRINKABLE SLEEVE
1 23-Apr-12
24-Apr-12
23-Apr-12
24-Apr-12
SS820
LIFTING TEST
1 24-Apr-12
25-Apr-12
24-Apr-12
25-Apr-12
SPOOL N NO. S2 ( S1 - S3 )
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
SS830
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS840
CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS850
FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS860
WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS880
FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
SS870
COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS890
WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS900
APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS910
PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS920
LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
SPOOL N NO. S3 (CLOSING) ( S2 - S4 )
23 24-Mar-12
25-Apr-12
24-Mar-12
25-Apr-12
BEFORE METROLOGY
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
PIPE LINE LI & BENDS
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
SS930 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 24-Mar-12
26-Mar-12
24-Mar-12
26-Mar-12
SS940 CUTTING & BEVELING BEFORE METROLOGY
3 26-Mar-12
29-Mar-12
26-Mar-12
29-Mar-12
SS950 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
5 29-Mar-12
04-Apr-12
29-Mar-12
04-Apr-12
SS960 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL...
8 04-Apr-12
14-Apr-12
04-Apr-12
14-Apr-12
SS980 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 16-Apr-12
18-Apr-12
16-Apr-12
18-Apr-12
SS970 COATING OF BENDS
6 14-Apr-12
21-Apr-12
14-Apr-12
21-Apr-12
SS990 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 18-Apr-12
21-Apr-12
18-Apr-12
21-Apr-12
SS1000 APPLY SHRINKABLE SLEEVE
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
11 15-Apr-12
25-Apr-12
15-Apr-12
25-Apr-12
AFTER M METROLOGY
2011 A M J Jul A S O N D
SS790
PIPE LINE LIN & BENDS
Page 58 of 64
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
0 15-Apr-12
SS1020 FIT UP AFTER METROLOGY
3 15-Apr-12
17-Apr-12
15-Apr-12
17-Apr-12
SS1030 WELDING & NDT AFTER METROLOGY
4 17-Apr-12
21-Apr-12
17-Apr-12
21-Apr-12
SS1040 PIGGING & HYDRO TEST
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
SS1050 APPLY SHRINKABLE SLEEVE
1 23-Apr-12
24-Apr-12
23-Apr-12
24-Apr-12
SS1060 LIFTING TEST
1 24-Apr-12
25-Apr-12
24-Apr-12
25-Apr-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
SS1070 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS1080 CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS1090 FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS1100 WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS1120 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
SS1110 COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS1130 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS1140 APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS1150 PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS1160 LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
SS1170 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS1180 CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS1190 FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS1200 WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS1220 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
SS1210 COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS1230 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS1240 APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
PIPE LINE LIN & BENDS
SPOOL N NO. S5 ( SETH PLEM - S6 ) PIPE LINE LIN & BENDS
2011 A M J Jul A S O N D
SS1010 RECEVING METROLOGY
SPOOL N NO. S4 ( S4 - SETH PLEM )
Page 59 of 64
15-Apr-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
SS1250 PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS1260 LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
23 24-Mar-12
25-Apr-12
24-Mar-12
25-Apr-12
BEFORE METROLOGY
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
PIPE LINE LI & BENDS
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
SS1270 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 24-Mar-12
26-Mar-12
24-Mar-12
26-Mar-12
SS1280 CUTTING & BEVELING BEFORE METROLOGY
3 26-Mar-12
29-Mar-12
26-Mar-12
29-Mar-12
SS1290 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
5 29-Mar-12
04-Apr-12
29-Mar-12
04-Apr-12
SS1300 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL...
8 04-Apr-12
14-Apr-12
04-Apr-12
14-Apr-12
SS1320 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 16-Apr-12
18-Apr-12
16-Apr-12
18-Apr-12
SS1310 COATING OF BENDS
6 14-Apr-12
21-Apr-12
14-Apr-12
21-Apr-12
SS1330 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 18-Apr-12
21-Apr-12
18-Apr-12
21-Apr-12
SS1340 APPLY SHRINKABLE SLEEVE
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
11 15-Apr-12
25-Apr-12
15-Apr-12
25-Apr-12
SPOOL N NO. S6 (CLOSING) ( S5 - TUNA PLEM )
AFTER M METROLOGY
Finish
0 15-Apr-12
SS1360 FIT UP AFTER METROLOGY
3 15-Apr-12
17-Apr-12
15-Apr-12
17-Apr-12
SS1370 WELDING & NDT AFTER METROLOGY
4 17-Apr-12
21-Apr-12
17-Apr-12
21-Apr-12
SS1380 PIGGING & HYDRO TEST
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
SS1390 APPLY SHRINKABLE SLEEVE
1 23-Apr-12
24-Apr-12
23-Apr-12
24-Apr-12
SS1400 LIFTING TEST
1 24-Apr-12
25-Apr-12
24-Apr-12
25-Apr-12
44 23-Feb-12
25-Apr-12
23-Feb-12
25-Apr-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
SPOOL N NO. S3 ( SSIV -S4 ) PIPE LINE LIN & BENDS
2011 A M J Jul A S O N D
SS1350 RECEVING METROLOGY
SETH P/F & NEW SSIV
Page 60 of 64
15-Apr-12
SS250
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS260
CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS270
FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS280
WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS300
FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS310
WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS320
APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS330
PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS340
LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
PIPE LINE LIN & BENDS SS150
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS160
CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS170
FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS180
WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS200
FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
SS190
COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS210
WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS220
APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS230
PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS240
LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
SPOOL N NO. S4 ( S3 - S5 )
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
PIPE LINE LIN & BENDS
2011 A M J Jul A S O N D
SS290
SPOOL N NO. S2 ( S1 - SSIV )
Page 61 of 64
SS350
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS360
CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS370
FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS380
WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS400
FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
SS390
COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS410
WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS420
APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS430
PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
SPOOL N NO. S5 ( S4 - S6 )
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
21 23-Feb-12
24-Mar-12
23-Feb-12
24-Mar-12
SS440
PIPE LINE LIN & BENDS
Finish
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 23-Feb-12
25-Feb-12
23-Feb-12
25-Feb-12
SS460
CUTTING & BEVELING
3 26-Feb-12
28-Feb-12
26-Feb-12
28-Feb-12
SS470
FIT UP FOR LINE PIPE & BENDS
5 29-Feb-12
05-Mar-12
29-Feb-12
05-Mar-12
SS480
WELDING & NDT FOR LINE PIPE & BENDS
8 06-Mar-12
14-Mar-12
06-Mar-12
14-Mar-12
SS500
FIT UP FLANGES AND FITTING WITH LINE PIPE
2 18-Mar-12
19-Mar-12
18-Mar-12
19-Mar-12
SS490
COATING OF BENDS
6 15-Mar-12
21-Mar-12
15-Mar-12
21-Mar-12
SS510
WELDING & NDT FOR FLANGES WITH LINE PIPE
2 20-Mar-12
21-Mar-12
20-Mar-12
21-Mar-12
SS520
APPLY SHRINKABLE SLEEVE
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS530
PIGGING & HYDRO TEST
2 22-Mar-12
23-Mar-12
22-Mar-12
23-Mar-12
SS540
LIFTING TEST
1 24-Mar-12
24-Mar-12
24-Mar-12
24-Mar-12
23 24-Mar-12
25-Apr-12
24-Mar-12
25-Apr-12
BEFORE METROLOGY
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
PIPE LINE LI & BENDS
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
2 24-Mar-12
26-Mar-12
24-Mar-12
26-Mar-12
SS020 CUTTING & BEVELING BEFORE METROLOGY
3 26-Mar-12
29-Mar-12
26-Mar-12
29-Mar-12
SS030 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
5 29-Mar-12
04-Apr-12
29-Mar-12
04-Apr-12
SS040 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL...
8 04-Apr-12
14-Apr-12
04-Apr-12
14-Apr-12
SS060 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 16-Apr-12
18-Apr-12
16-Apr-12
18-Apr-12
SS050 COATING OF BENDS
6 14-Apr-12
21-Apr-12
14-Apr-12
21-Apr-12
SS070 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 18-Apr-12
21-Apr-12
18-Apr-12
21-Apr-12
SS080 APPLY SHRINKABLE SLEEVE
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
11 15-Apr-12
25-Apr-12
15-Apr-12
25-Apr-12
SS 10
SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
AFTER M METROLOGY
2011 A M J Jul A S O N D
SS450
SPOOL N NO. S1 (CLOSING) ( P.L - SETH PLEM )
Page 62 of 64
SS090
RECEVING METROLOGY
0 15-Apr-12
15-Apr-12
SS100
FIT UP AFTER METROLOGY
3 15-Apr-12
17-Apr-12
15-Apr-12
17-Apr-12
SS110
WELDING & NDT AFTER METROLOGY
4 17-Apr-12
21-Apr-12
17-Apr-12
21-Apr-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
PIGGING & HYDRO TEST
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
SS130
APPLY SHRINKABLE SLEEVE
1 23-Apr-12
24-Apr-12
23-Apr-12
24-Apr-12
SS140
LIFTING TEST
1 24-Apr-12
25-Apr-12
24-Apr-12
25-Apr-12
23 24-Mar-12
25-Apr-12
24-Mar-12
25-Apr-12
BEFORE METROLOGY
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
PIPE LINE LI & BENDS
21 24-Mar-12
23-Apr-12
24-Mar-12
23-Apr-12
SS550 SPOOLS & BENDS PLACED ON SUITABLE SUPPORTS
2 24-Mar-12
26-Mar-12
24-Mar-12
26-Mar-12
SS560 CUTTING & BEVELING BEFORE METROLOGY
3 26-Mar-12
29-Mar-12
26-Mar-12
29-Mar-12
SS570 FIT UP FOR LINE PIPE & BENDS BEFORE METROLOGY
5 29-Mar-12
04-Apr-12
29-Mar-12
04-Apr-12
SS580 WELDING & NDT FOR LINE PIPE & BENDS BEFORE METROL...
8 04-Apr-12
14-Apr-12
04-Apr-12
14-Apr-12
SS600 FIT UP FLANGES AND FITTING WITH LINE PIPE
2 16-Apr-12
18-Apr-12
16-Apr-12
18-Apr-12
SS590 COATING OF BENDS
6 14-Apr-12
21-Apr-12
14-Apr-12
21-Apr-12
SS610 WELDING & NDT FOR FLANGES WITH LINE PIPE
2 18-Apr-12
21-Apr-12
18-Apr-12
21-Apr-12
SS620 APPLY SHRINKABLE SLEEVE
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
11 15-Apr-12
25-Apr-12
15-Apr-12
25-Apr-12
AFTER M METROLOGY SS630
RECEVING METROLOGY
0 15-Apr-12
SS640
FIT UP AFTER METROLOGY
3 15-Apr-12
17-Apr-12
15-Apr-12
17-Apr-12
SS650
WELDING & NDT AFTER METROLOGY
4 17-Apr-12
21-Apr-12
17-Apr-12
21-Apr-12
SS660
PIGGING & HYDRO TEST
2 21-Apr-12
23-Apr-12
21-Apr-12
23-Apr-12
SS670
APPLY SHRINKABLE SLEEVE
1 23-Apr-12
24-Apr-12
23-Apr-12
24-Apr-12
SS680
LIFTING TEST
1 24-Apr-12
25-Apr-12
24-Apr-12
25-Apr-12
61 21-Feb-12
29-Mar-12
26-Jan-12
27-Mar-12
W.P.7: CER CERTIFICATION
15-Apr-12
PTJ1130
Jacket completion certificate
0
21-Feb-12
26-Jan-12
PTJ1090
Deck completion certificate
0
29-Mar-12
27-Mar-12
W.P.8: LOA LOAD-OUT, SEA-FASTENING, TRANSPORTATION & INSTALLATION PTJ1070
Pre-drilling template seafastening and load out
PTJ1050
Jacket & Piles seafastening and load out
PTJ1170
Sub Sea Spools Load out first trip
2011 A M J Jul A S O N D
SS120
SPOOL N NO. S6 (CLOSING) ( S5 - SETH P/F )
Page 63 of 64
204 18-Oct-11
10-May-12
18-Oct-11
08-May-12
7 18-Oct-11
24-Oct-11
18-Oct-11
24-Oct-11*
15 17-Mar-12
31-Mar-12
17-Mar-12
31-Mar-12*
7 25-Mar-12
31-Mar-12
25-Mar-12
31-Mar-12
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT UPDATED SCHEDULE AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
Finish
Sub Sea Spools Load out second trip for closing spools
7 25-Apr-12
02-May-12
25-Apr-12
02-May-12*
PTJ1060
Deck seafastening and load out
7 03-May-12
10-May-12
02-May-12
08-May-12*
31 17-May-12
17-Jun-12
16-May-12
15-Jun-12
31 17-May-12
17-Jun-12
16-May-12
15-Jun-12
PTJ1140
TSF Offshore hook-up activities
2011 A M J Jul A S O N D
PTJ1180
W.P.9: OFF OFFSHORE HOOK-UP, COMMISSIONING AND ASSISTANCE TO STA...
Page 64 of 64
J
2012 F M A M J JulA
PAGE 28 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.4. CRITICAL AND NEAR CRITICAL ACTIVITIES
GFL 003-0405
3467-200
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
SETH OFFSHORE OFFS EPC PROJECT UPDATED SCHEDULE CONTRACTUAL MILESTONES CONTRACT
BL Project Finish
Start
Finish
311 11-May-11
31-Jul-12
26-Apr-11 A
31-Jul-12
122 01-Apr-12
31-Jul-12
31-Mar-12
31-Jul-12
Deck Mechanical Completion
0
01-Apr-12
31-Mar-12*
ART6.4.1
Deck and Flare Ready for Load out
0
01-May-12
30-Apr-12*
A2
Project completion
0
31-Jul-12
31-Jul-12*
199 11-May-11
05-Apr-12
26-Apr-11 A
21-Feb-12
164 11-May-11
21-Dec-11
26-Apr-11 A
02-Jan-12
PROCESS
163 11-May-11
21-Dec-11
26-Apr-11 A
02-Jan-12
Drawings
7 05-Sep-11
14-Sep-11
05-Sep-11
13-Sep-11
7 05-Sep-11
14-Sep-11
05-Sep-11
13-Sep-11
25 11-May-11
14-Jun-11
26-Apr-11 A
05-Jul-11
25 11-May-11
W.P.2: ENG ENGINEERING
A1570
P&ID's IFC
TER's A2610
Fire protection system TER
Vendor pr prints review A2730
Fire protection system Vendor prints review
PIPING Drawings A1670
Plot Plan IFC
A1680
ISO's
INSTRUMENTATION INSTRUME TER's A3450
Choke valves TER
Vendor pr prints review A3610
Choke valves Vendor prints review
MECHANICAL MECHANIC Vendor pr prints review
14-Jun-11
26-Apr-11 A
05-Jul-11
100 24-Jul-11
21-Dec-11
03-Aug-11
02-Jan-12
100 24-Jul-11
21-Dec-11
03-Aug-11
02-Jan-12
42 14-Sep-11
20-Nov-11
14-Sep-11
17-Nov-11
42 14-Sep-11
20-Nov-11
14-Sep-11
17-Nov-11
5 14-Sep-11
21-Sep-11
14-Sep-11
20-Sep-11
10 31-Oct-11
20-Nov-11
31-Oct-11
17-Nov-11
144 18-May-11
24-Nov-11
26-Apr-11 A
13-Dec-11
20 18-May-11
15-Jun-11
26-Apr-11 A
05-Jul-11
20 18-May-11
15-Jun-11
26-Apr-11 A
05-Jul-11
80 25-Jul-11
24-Nov-11
11-Aug-11
13-Dec-11
80 25-Jul-11
24-Nov-11
11-Aug-11
13-Dec-11
81 26-Jul-11
28-Nov-11
14-Aug-11
14-Dec-11
81 26-Jul-11
28-Nov-11
14-Aug-11
14-Dec-11
Primary Baseline
Start Date:28-Mar-11 Finish Date:31-Jul-12 Critical Re... Data Date:25-Jun-11
Actual Work
Baseline ...
Remaining Level of Effort
Remaining...
2011 A M J Jul A S O N D
ART6.3
ENPPI
Page 1 of 5
J
2012 F M A M J JulA
By: Haytham A.Rahman Date 25-May-11
Revision Rev.0
Checked A.Maghawry
Approved A.Fathy
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11 Activity ID
Activity Name
A6330
Receiving final weights and dimensions for mechanical equipment
A3770
Service water pump Vendor prints review
OFFSHORE OFFSHOR Model A5360
Finalize PDS Modeling For Topsides based on Tecnomare IFC dw...
W.P.3: PROCUREMENT PRO SERVICES & MATERIAL SUPPLY EQUIPMENT EQUIPMEN ENPPI LO LONG LEAD ITEMS (Cranes ,Chemical unjec.,Fire protec. , Survival M... PURCHASING PURCHA A5330
Fire protection system Issue Fax of commitment
FABRICATION FABRICA A3930
Fire protection system Fabrication up to release for shipment
SHIPPING SHIPPIN
Original BL Project Duration Start
BL Project Finish
0 20-Sep-11
Start
Finish
80 26-Jul-11
28-Nov-11
14-Aug-11
14-Dec-11
15 24-Oct-11
20-Nov-11
24-Oct-11
17-Nov-11
15 24-Oct-11
20-Nov-11
24-Oct-11
17-Nov-11
15 24-Oct-11
20-Nov-11
24-Oct-11
17-Nov-11
164 19-Jun-11
05-Apr-12
25-Jun-11
21-Feb-12
148 19-Jun-11
12-Feb-12
06-Jul-11
11-Feb-12
148 19-Jun-11
12-Feb-12
06-Jul-11
11-Feb-12
9 19-Jun-11
07-Jul-11
06-Jul-11
18-Jul-11
9 19-Jun-11
07-Jul-11
06-Jul-11
18-Jul-11
170 08-Jul-11
03-Jan-12
19-Jul-11
04-Jan-12
170 08-Jul-11
03-Jan-12
19-Jul-11
04-Jan-12
45 29-Dec-11
12-Feb-12
29-Dec-11
11-Feb-12
A3990
Fire protection system Shipping
21 04-Jan-12
24-Jan-12
08-Jan-12
28-Jan-12
A2120
Custom clearance & inland transportation (Multi phase flow ,Che...
45 29-Dec-11
12-Feb-12
29-Dec-11
11-Feb-12
A5190
Fire protection system Custom clearance & inland transportation
14 25-Jan-12
07-Feb-12
29-Jan-12
11-Feb-12
156 19-Jun-11
05-Apr-12
06-Jul-11
21-Feb-12
15 19-Jun-11
10-Jul-11
06-Jul-11
26-Jul-11
15 19-Jun-11
10-Jul-11
06-Jul-11
26-Jul-11
210 10-Jul-11
05-Apr-12
27-Jul-11
21-Feb-12
210 10-Jul-11
05-Apr-12
27-Jul-11
21-Feb-12
200 20-Jun-11
06-Jan-12
25-Jun-11
10-Jan-12
200 20-Jun-11
06-Jan-12
25-Jun-11
10-Jan-12
200 20-Jun-11
06-Jan-12
25-Jun-11
10-Jan-12
35 10-Oct-11
14-Nov-11
10-Oct-11
13-Nov-11
E&I BULK PURCHASING PURCHA A5040
Choke valves Issue Fax of commitments
FABRICATION FABRICA A4500
Choke valves Fabrication up to release for shipment
PIPING BULK BU FABRICATION FABRICA A1950
piping Bulk Fabrication up to release for shipment
SHIPPING A1960
1st batch of the piping Bulk Shipping
21 10-Oct-11
31-Oct-11
10-Oct-11
30-Oct-11
A1970
1st batch of the piping Bulk Custom clearance & inland transport...
14 31-Oct-11
14-Nov-11
31-Oct-11
13-Nov-11
22 21-Sep-11
24-Oct-11
21-Sep-11
23-Oct-11
TECNOMARE TECNOMAR
2011 A M J Jul A S O N D
21-Sep-11
Page 2 of 5
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11 Activity ID
Activity Name
TECNOMARE DRIVING MILESTONES TECNOMAR STRUCTURAL STRUCTU 17
input - deck final plot plan & equipment list (ENPPI)
W.P.2: ENG ENGINEERING STRUCTURAL STRUCTU DECK DETAIL DE DESIGN 44
Deck equipment supports & AFC dwg and MTO
PETROJET PETROJET DRIVING MILESTONES PROCUREMENT PROCURE
Original BL Project Duration Start
BL Project Finish
Start
0 21-Sep-11
21-Sep-11
21-Sep-11
21-Sep-11
0 21-Sep-11
21-Sep-11
21-Sep-11
21-Sep-11
0 21-Sep-11
Finish
22 21-Sep-11
24-Oct-11
21-Sep-11
23-Oct-11
22 21-Sep-11
24-Oct-11
21-Sep-11
23-Oct-11
22 21-Sep-11
24-Oct-11
21-Sep-11
23-Oct-11
22 21-Sep-11
24-Oct-11
21-Sep-11
23-Oct-11
169 31-Aug-11
10-May-12
31-Aug-11
08-May-12
165 31-Aug-11
12-Feb-12
31-Aug-11
11-Feb-12
165 31-Aug-11
12-Feb-12
31-Aug-11
11-Feb-12
PTJ1020
Structural material 5 th batch (jacket secondary & deck secondary)...
0 31-Aug-11
31-Aug-11*
PTJ1080
Piping bulk material (1st batch) (ENPPI)
0 14-Nov-11
14-Nov-11
PTJ1120
Equipment (100%) (PTB)
0
24-Jan-12
24-Jan-12*
PTJ4010
Equipment by (100%) (ENPPI)
0
12-Feb-12
11-Feb-12
0 15-Sep-11
15-Sep-11
15-Sep-11
15-Sep-11
0 15-Sep-11
15-Sep-11
15-Sep-11
15-Sep-11
0
15-Sep-11
W.P.2: ENG ENGINEERING TSF PTJ2240
Rec final weight & dimension for static equipment
W.P.4: SUBSTRUCTURES SUB (PILES, JACKET & PDT) FABRICATION JACKET STRUCTURE S FABRICATION PAINTING PTJ10270 SPLASH PAINTING FOR BARGE BUMPER PTJ10330 PILE MARKING
15-Sep-11*
28 13-Feb-12
15-Mar-12
13-Feb-12
15-Mar-12
28 13-Feb-12
15-Mar-12
13-Feb-12
15-Mar-12
28 13-Feb-12
15-Mar-12
13-Feb-12
15-Mar-12
5 11-Mar-12
15-Mar-12
11-Mar-12
15-Mar-12
28 13-Feb-12
15-Mar-12
13-Feb-12
15-Mar-12
114 20-Nov-11
03-May-12
20-Nov-11
01-May-12
89 19-Jan-12
03-May-12
19-Jan-12
01-May-12
66 12-Feb-12
29-Apr-12
11-Feb-12
26-Apr-12
PTJ2060 Deck pre-commisioning
40 12-Feb-12
29-Mar-12
11-Feb-12
27-Mar-12
PTJ2090 Deck commisioning
26 29-Mar-12
29-Apr-12
28-Mar-12
26-Apr-12
68 29-Jan-12
17-Apr-12
28-Jan-12
15-Apr-12
W.P.5: DEC DECK & TSF FABRICATION DECK FABRICATION FAB General Activities A
Deck Structure Stru Fabrication
2011 A M J Jul A S O N D
21-Sep-11
Page 3 of 5
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11 Activity ID
Activity Name
Original BL Project Duration Start
BL Project Finish
Start
68 29-Jan-12
17-Apr-12
28-Jan-12
15-Apr-12
PTD150 Cutting & Assembly
20 29-Jan-12
21-Feb-12
28-Jan-12
19-Feb-12
PTD151 Welding & NDT
32 21-Feb-12
29-Mar-12
20-Feb-12
27-Mar-12
PTD152 Trial Fit
2 15-Apr-12
17-Apr-12
14-Apr-12
15-Apr-12
Atmosphric Painting Atmosphr
73 19-Jan-12
15-Apr-12
19-Jan-12
12-Apr-12
Deck Flare Fla
Finish
Piping painting
14 19-Jan-12
05-Feb-12
19-Jan-12
04-Feb-12
PT1100
Deck Flare
14 29-Mar-12
15-Apr-12
28-Mar-12
12-Apr-12
7 25-Apr-12
03-May-12
24-Apr-12
01-May-12
7 25-Apr-12
03-May-12
24-Apr-12
01-May-12
72 07-Dec-11
17-Feb-12
07-Dec-11
16-Feb-12
72 07-Dec-11
17-Feb-12
07-Dec-11
16-Feb-12
TSF1110 Installation of production manifold module on celler deck
4 07-Dec-11
10-Dec-11
07-Dec-11*
10-Dec-11
TSF1100 Installation of E & I module on main deck
4 07-Jan-12
10-Jan-12
07-Jan-12*
10-Jan-12
TSF1060 Equipment Installation Below Cellar Deck
4 13-Feb-12
17-Feb-12
13-Feb-12
16-Feb-12
TSF1070 Equipment Installation on Cellar Deck
15 02-Feb-12
17-Feb-12
02-Feb-12
16-Feb-12
TSF1080 Equipment Installation on Main Deck
15 02-Feb-12
17-Feb-12
02-Feb-12
16-Feb-12
113 20-Nov-11
13-Mar-12
20-Nov-11
11-Mar-12
Anti Skid Painting P PT1000
Heli Deck
EQUIPMENT EQUIPMEN Equipement Installation (onshore) Equipeme
PIPING PTJ2050
Piping & piping support fabrication start
0 20-Nov-11
C.S Piping Fab. & Erec., Valves Erection (onshore)
113 20-Nov-11
13-Mar-12
20-Nov-11
11-Mar-12
TSF1000 Piping Fabrication
70 20-Nov-11
29-Jan-12
20-Nov-11
28-Jan-12
TSF1020 Piping Erection
35 28-Jan-12
03-Mar-12
27-Jan-12
01-Mar-12
TSF1040 Valve Installation
15 17-Feb-12
03-Mar-12
16-Feb-12
01-Mar-12
PTJ2120 Piping hydrotest
21 21-Feb-12
13-Mar-12
20-Feb-12
11-Mar-12
0 29-Mar-12
29-Mar-12
27-Mar-12
27-Mar-12
0
29-Mar-12
W.P.7: CER CERTIFICATION PTJ1090
Deck completion certificate
W.P.8: LOA LOAD-OUT, SEA-FASTENING, TRANSPORTATION & INSTALLATION PTJ1070
Pre-drilling template seafastening and load out
PTJ1050
Jacket & Piles seafastening and load out
2011 A M J Jul A S O N D
PT1070
20-Nov-11
27-Mar-12
204 18-Oct-11
10-May-12
18-Oct-11
08-May-12
7 18-Oct-11
24-Oct-11
18-Oct-11
24-Oct-11*
15 17-Mar-12
31-Mar-12
17-Mar-12
31-Mar-12*
Page 4 of 5
J
2012 F M A M J JulA
3467-200, PETROBEL SETH DEVELOPMENT EPC PROJECT CRITICAL AND NEAR CRITICAL ACTIVITIES AS OF 25-JUNE-11 Activity ID PTJ1060
Activity Name Deck seafastening and load out
Original BL Project Duration Start
BL Project Finish
Start
7 03-May-12
10-May-12
02-May-12
Finish
2011 A M J Jul A S O N D
08-May-12*
Page 5 of 5
J
2012 F M A M J JulA
PAGE 29 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.5. ONE MONTH LOOKAHEAD SCHEDULE
GFL 003-0405
3467-200
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING PROCESS TECHNOLOGY DIVISION REPORTS / TECHNICAL LIST Basis of design Final
11-Jun-11
07-Jul-11
12-Jun-11
12-Jul-11
100.00%
70.00%
1.94%
70.00%
20.00%
3.06%
100.00%
20.00%
3.06%
100.00%
20.00%
3.06%
100.00%
20.00%
0.83%
0.00%
0.00%
0.83%
0.00%
0.00%
5.28%
0.00%
0.00%
30
Process & Utilities report Design
1.94%
50
TER Flame arrestor TER Finish
23-Jun-11
21-Jul-11
80
Fire Fighting package TER Finish
09-Jun-11
05-Jul-11
80
Safety equipment and life saving TER Finish
12-Jun-11
07-Jul-11
80
MRP Chemical injection package MRP Start
10-Jul-11
03-Jul-11
20
For Purchase
17-Jul-11
07-Jul-11
80
Fire Fighting package MRP Start
05-Jul-11
20-Jul-11
20
For Purchase
11-Jul-11
21-Jul-11
80
VENDOR PRINTS REVIEW Chemical injection package Start
25-Jul-11
25-Jul-11
20
* Weights of Activities are calculated relative to (PROCESS TECHNOLOGY DIVISION) Tuesday, July 05, 2011
Page 1 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT DRAWING Electrical hook-up Drawing Start
19-May-11
12-Jul-11
20
Design
26-May-11
19-Jul-11
50
Hydraulic instruments layouts Start
05-May-11
06-Jul-11
20
Design
12-May-11
13-Jul-11
50
Hydraulic instruments Tube Routing layouts Start
12-May-11
05-Jul-11
20
Design
19-May-11
12-Jul-11
50
1.58%
70.00%
0.00%
1.32%
70.00%
0.00%
1.32%
70.00%
0.00%
2.63%
100.00%
20.00%
1.84%
20.00%
20.00%
2.11%
20.00%
0.00%
2.11%
20.00%
20.00%
2.11%
100.00%
0.00%
2.11%
20.00%
20.00%
2.11%
20.00%
0.00%
1.05%
0.00%
0.00%
TER Choke valve TER Finish
12-Jun-11
05-Jul-11
80
Loose Instrument TER Finish
26-Jun-11
24-Jul-11
80
Sand & Corrosion probes TER Start
16-Jun-11
11-Jul-11
20
Instrument & Mechanical bulk material TER Finish
03-Jul-11
14-Jul-11
80
Instrument cable and cable glandsTER Start
06-Jun-11
10-Jul-11
20
Inst. Junction Box TER Finish
07-Jul-11
21-Jul-11
80
Instrument cable trays TER Start
14-Jun-11
03-Jul-11
20
MRP Electro Hydraulic Well Head panel MRP Start
04-Jul-11
13-Jul-11
20
For Purchase
11-Jul-11
14-Jul-11
80
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTME Tuesday, July 05, 2011
Page 2 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING INSTRUMENTATION & CONTROLS ENGINEERING DEPARTMENT MRP HIPPS System MRP Start
28-Jun-11
07-Jul-11
20
For Purchase
05-Jul-11
13-Jul-11
80
Wing valve MRP Start
06-Jul-11
24-Jul-11
1.05%
0.00%
0.00%
1.05%
0.00%
0.00%
3.95%
0.00%
0.00%
3.42%
0.00%
0.00%
3.68%
0.00%
0.00%
20
VENDOR PRINTS REVIEW HIPPS Vendor prints review Start
13-Jul-11
24-Jul-11
20
Electro hydraulic wellhead control panel Vendor prints review Start
25-Jul-11
21-Jul-11
20
Multi phase flow meter Vendor prints review Start
25-Jul-11
20-Jul-11
20
* Weights of Activities are calculated relative to (INSTRUMENTATION & CONTROLS ENGINEERING DEPARTME Tuesday, July 05, 2011
Page 3 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING PIPING ENGINEERING DIVISION TER Injection fitting TER Start
25-May-11
04-Jul-11
20
Finish
15-Jun-11
24-Jul-11
80
Insulation joint Injection fitting TER Finish
09-Jun-11
21-Jul-11
2.73%
100.00%
0.00%
2.73%
100.00%
20.00%
1.82%
20.00%
0.00%
3.64%
0.00%
0.00%
4.55%
100.00%
70.00%
80
MRP Piping bulk MRP Start
19-Jun-11
05-Jul-11
20
For Purchase
26-Jun-11
07-Jul-11
80
VENDOR PRINTS REVIEW Piping bulk Vendor prints review Start
04-Jul-11
20-Jul-11
20
Specification Piping material classes Final
13-Jun-11
14-Jul-11
30
* Weights of Activities are calculated relative to (PIPING ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 4 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION DRAWING Single line diagram Start
23-May-11
14-Jul-11
20
Design
30-May-11
21-Jul-11
50
2.00%
70.00%
0.00%
1.33%
70.00%
0.00%
2.33%
70.00%
0.00%
8.33%
20.00%
20.00%
4.33%
20.00%
0.00%
4.33%
20.00%
0.00%
2.00%
0.00%
0.00%
2.00%
0.00%
0.00%
2.50%
0.00%
0.00%
2.50%
0.00%
0.00%
REPORTS / TECHNICAL LIST Electrical cable list Start
08-Jun-11
10-Jul-11
20
Design
15-Jun-11
17-Jul-11
50
Power system study Start
15-May-11
30-Jun-11
20
Design
24-May-11
14-Jul-11
50
TER Navigational aids system TER Finish
27-Jun-11
10-Jul-11
80
Lighting material TER Start
08-Jun-11
10-Jul-11
20
Earthing material TER Start
20-Jun-11
10-Jul-11
20
MRP Electrical cables MRP Start
13-Jul-11
10-Jul-11
20
For Purchase
20-Jul-11
14-Jul-11
80
Electrical Cable trays MRP Start
10-Jul-11
30-Jun-11
20
For Purchase
17-Jul-11
30-Jun-11
80
VENDOR PRINTS REVIEW Electrical Cable trays Vendor prints review Start
25-Jul-11
18-Jul-11
20
Electrical Cables Vendor prints review Start
01-Aug-11
21-Jul-11
20
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 5 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING ELECTRICAL ENGINEERING DIVISION VENDOR PRINTS REVIEW
* Weights of Activities are calculated relative to (ELECTRICAL ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 6 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING OFFSHORE ENGINEERING DIVISION DRAWING Cable trays supports for deck plan at el. +9700 T.O.S. Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Cable trays supports for cellar deck plan at el. +13500 T.O.S. Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Cable trays supports for mezzanine deck plan at el. +16000 T. Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Cable trays supports for main deck plan at el. +20500 T.O.S. Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
Cable trays supports for Helideck plan at el. +26500 T.O.S. Start
28-Jun-11
03-Jul-11
20
Design
05-Jul-11
10-Jul-11
50
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
10.00%
0.00%
0.00%
15.00%
20.00%
20.00%
5.00%
0.00%
0.00%
TER Survival module TER Finish
28-Jun-11
03-Jul-11
80
MRP Survival module MRP Start
20-Jul-11
25-Jul-11
20
* Weights of Activities are calculated relative to (OFFSHORE ENGINEERING DIVISION) Tuesday, July 05, 2011
Page 7 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.2 DETAILED ENGINEERING MECHANICAL ENGINEERING DEPARTMENT TER Service water pump TER Finish
07-Jun-11
03-Jul-11
10.00%
100.00%
20.00%
7.78%
0.00%
0.00%
80
VENDOR PRINTS REVIEW Turret crane crane Vendor prints review Start
19-Jul-11
13-Jul-11
20
* Weights of Activities are calculated relative to (MECHANICAL ENGINEERING DEPARTMENT) Tuesday, July 05, 2011
Page 8 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
* Relative Weight
Milestone Value
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE Safety equipment and life saving Comm. offers open
12-Jun-11
17-Jul-11
20
Bid tab
26-Jun-11
24-Jul-11
10
Chemical injection package F.O.C.
10-Jul-11
30-Jun-11
20
P.O.
24-Jul-11
10-Jul-11
10
Fire Fighting package Comm. offers open
14-Jun-11
10-Jul-11
20
Bid tab
28-Jun-11
14-Jul-11
10
F.O.C.
04-Jul-11
20-Jul-11
20
P.O.
18-Jul-11
24-Jul-11
10
Piping bulk P.O.
03-Jul-11
07-Jul-11
23-May-11
04-Jul-11
20-Jun-11
07-Jul-11
08-Jun-11
07-Jul-11
24-Jul-11
07-Jul-11
F.O.C.
13-Jul-11
03-Jul-11
20
P.O.
27-Jul-11
10-Jul-11
10
Navigation aids system 27-Jun-11
17-Jul-11
03-Jul-11
21-Jul-11
60.00%
40.00%
3.73%
90.00%
90.00%
3.26%
60.00%
20.00%
3.49%
40.00%
20.00%
3.49%
40.00%
20.00%
3.73%
60.00%
90.00%
3.49%
60.00%
70.00%
3.49%
40.00%
40.00%
3.49%
40.00%
40.00%
20
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
3.49%
20
Instrument & Mechanical bulk material Comm. offers open
70.00%
10
Electrical Cables
Comm. offers open
60.00%
20
Electrical Cable trays P.O.
4.19%
20
Lighting material Tech. offers open
40.00%
20
Earthing material Tech. offers open
60.00%
10
Injection fitting Tech. offers open
3.26%
Page 9 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
Milestone Value
* Relative Weight
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.3 PROCUREMENT SERVICES FOREIGN PURCHASING DEPARTMENT COMMODITIES ONE BY ONE HIPPS F.O.C.
28-Jun-11
06-Jul-11
20
P.O.
12-Jul-11
14-Jul-11
10
Choke valves Comm. offers open
14-Jun-11
12-Jul-11
20
Bid tab
28-Jun-11
20-Jul-11
10
Instrument cable trays Tech. offers open
14-Jun-11
04-Jul-11
Comm. offers open
06-Jun-11
30-Jun-11
20
Bid tab
20-Jun-11
06-Jul-11
10
F.O.C.
04-Jul-11
12-Jul-11
20
P.O.
14-Jul-11
18-Jul-11
10
Wing valves Comm. offers open
08-Jun-11
03-Jul-11
20
Bid tab
22-Jun-11
10-Jul-11
10
F.O.C.
06-Jul-11
21-Jul-11
20
Instrument cable and cable glands 06-Jun-11
07-Jul-11
16-Jun-11
10-Jul-11
24-Jul-11
03-Jul-11
60.00%
40.00%
3.49%
40.00%
0.00%
3.54%
70.00%
40.00%
3.54%
70.00%
40.00%
3.49%
60.00%
20.00%
3.49%
40.00%
0.00%
3.73%
60.00%
90.00%
3.49%
60.00%
40.00%
3.73%
40.00%
40.00%
10
Service water pump Comm. offers open
13-Jun-11
10-Jul-11
20
Bid tab
27-Jun-11
18-Jul-11
10
F.O.C.
11-Jul-11
25-Jul-11
20
Survival module Comm. offers open
29-Jun-11
10-Jul-11
20
Bid tab
13-Jul-11
18-Jul-11
10
F.O.C.
19-Jul-11
24-Jul-11
20
* Weights of Activities are calculated relative to (FOREIGN PURCHASING DEPARTMENT) Tuesday, July 05, 2011
3.73%
20
Multi phase flow meter P.O.
70.00%
20
Sand & Corrosion probes Tech. offers open
70.00%
20
Electro hydraulic wellhead control panel
Tech. offers open
4.19%
Page 10 of 12
Layout No. 1 Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
Milestone Value
* Relative Weight
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.3 PROCUREMENT SERVICES EXPEDITING DEPART. COMMODITIES ONE BY ONE Chemical injection package Start
10-Jul-11
05-Jul-11
05-Jul-11
20-Jul-11
10-Jul-11
06-Jul-11
17-Jul-11
06-Jul-11
28-Jun-11
07-Jul-11
10-Jul-11
12-Jul-11
06-Jul-11
24-Jul-11
0.00%
0.00%
2.33%
0.00%
0.00%
4.66%
0.00%
0.00%
3.73%
0.00%
0.00%
3.26%
0.00%
0.00%
10
Layout No. 1
* Weights of Activities are calculated relative to (EXPEDITING DEPART.) Tuesday, July 05, 2011
1.86%
10
Wing valves Start
0.00%
10
Electro hydraulic wellhead control panel Start
0.00%
20
HIPPS Start
3.73%
20
Electrical Cables Start
0.00%
10
Electrical Cable trays Start
0.00%
10
Fire Fighting package Start
4.66%
Page 11 of 12
Data'Nes Systems, Release 2.21
Project No.: 3467-200
Lookahead Report
SETH Offshore EPC Project Dates Milestone
Planned
Expected
Milestone Value
* Relative Weight
As Of :
25-Jun-11
Forecast Date :
25-Jul-11
Planned Actual Progress% Progress%
ENPPI W.P.5 DECK AND TSF SUPPLY & FABRICATION METERIAL SUPPLY COMMODITIES ONE BY ONE Chemical injection package P.O.
24-Jul-11
10-Jul-11
18-Jul-11
24-Jul-11
03-Jul-11
07-Jul-11
24-Jul-11
07-Jul-11
27-Jul-11
10-Jul-11
12-Jul-11
14-Jul-11
18-Jul-11
18-Jul-11
24-Jul-11
03-Jul-11
03-Jul-11
07-Jul-11
03-Jul-11
07-Jul-11
0.00%
0.00%
1.49%
0.00%
0.00%
7.71%
0.00%
0.00%
5.41%
0.00%
0.00%
10.97%
0.00%
0.00%
8.70%
0.00%
0.00%
5.22%
0.00%
0.00%
35
Layout No. 1
* Weights of Activities are calculated relative to (METERIAL SUPPLY) Tuesday, July 05, 2011
2.78%
35
Piping bulk 2nd batch P.O.
0.00%
15
Piping bulk 1st batch P.O.
0.00%
15
Multi phase flow meter P.O.
3.48%
15
Electro hydraulic wellhead control panel P.O.
0.00%
35
HIPPS P.O.
0.00%
35
Electrical Cables P.O.
1.94%
35
Electrical Cable trays P.O.
0.00%
15
Piping bulk 3rd batch P.O.
0.00%
15
Fire Fighting package P.O.
9.06%
Page 12 of 12
Data'Nes Systems, Release 2.21
PAGE 30 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.6. PROCUREMENT STATUS
GFL 003-0405
3467-200
PAGE 31 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.6.1 ENPPI
GFL 003-0405
3467-200
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM MRQ
Commodity Name
TER
F.O.C
P.O
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
(Supplier)
Process VENT STOCK TIPS PL
09-May-11
EXP
(112-04)
CHEMICAL INJECTION PACKAGE (115-01)
FLAME ARRESTORS
ACT
09-May-11
PL
06-Apr-11
27-Dec-11
10-Jan-12
26-Jul-11
23-Aug-11
11-Sep-11
26-Dec-11
16-Jan-12
30-Jan-12
19-Jun-11
10-Jul-11
24-Jul-11
06-Jan-12
27-Jan-12
10-Feb-12
30-Jun-11
10-Jul-11
27-Dec-11
17-Jan-12
31-Jan-12
01-Jun-11
PL
27-Apr-11
23-Jun-11
21-Jul-11
04-Aug-11
28-Nov-11
19-Dec-11
02-Jan-12
21-Jul-11
18-Aug-11
06-Sep-11
26-Dec-11
16-Jan-12
30-Jan-12
14-Jun-11
07-Jul-11
21-Jul-11
03-Jan-12
24-Jan-12
07-Feb-12
05-Jul-11
18-Jul-11
01-Aug-11
04-Jan-12
28-Jan-12
11-Feb-12
12-Jun-11
10-Jul-11
24-Jul-11
07-Dec-11
28-Dec-11
11-Jan-12
07-Jul-11
04-Aug-11
18-Aug-11
01-Jan-12
22-Jan-12
05-Feb-12
EXP
12-Apr-11
Tuesday, July 05, 2011
06-Dec-11
06-Apr-11
PL FIRE PROTECTION EXP SYSTEM PACKGE ACT (190-01)
(190-03)
17-Aug-11
ACT
17-Apr-11
LIFE SAVING EQUIPMENT
03-Aug-11
EXP
ACT
(119-02)
04-Jul-11
PL
12-Apr-11
12-Apr-11
EXP ACT
12-Apr-11
Page 1 of 7
PL: Planned EXP: Expect ACT: Actual
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM MRQ
Commodity Name
TER
F.O.C
P.O
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
(Supplier) SURVIVAL MODULE (197-02)
28-Apr-11
28-Jun-11
19-Jul-11
02-Aug-11
26-Dec-11
16-Jan-12
30-Jan-12
03-Jul-11
24-Jul-11
07-Aug-11
31-Dec-11
21-Jan-12
04-Feb-12
07-Jun-11
11-Jul-11
25-Jul-11
28-Nov-11
19-Dec-11
04-Jan-12
03-Jul-11
27-Jul-11
10-Aug-11
14-Dec-11
04-Jan-12
20-Jan-12
PL
15-Dec-11
12-Jan-12
26-Jan-12
EXP
15-Dec-11
26-Jan-12
29-Dec-11
PL EXP ACT
14-Apr-11
PL
25-Apr-11
Mechanical SERVICE WATER PUMPS (131-15)
DIESEL GENERATOR (135-03)
MONORAIL CRANE (137-01)
EXP ACT
25-Apr-11
ACT
PL
28-Jul-11
06-Sep-11
04-Oct-11
17-Oct-11
01-Feb-12
22-Feb-12
07-Mar-12
EXP
28-Jul-11
06-Sep-11
04-Oct-11
17-Oct-11
01-Feb-12
22-Feb-12
07-Mar-12
13-Apr-11
12-Jun-11
10-Jul-11
24-Jul-11
06-Mar-12
20-Mar-12
03-Apr-12
19-Feb-12
04-Mar-12
18-Mar-12
ACT
TURRENT CRANE PL EXP
(137-02)
Tuesday, July 05, 2011
ACT
10-Apr-11
04-May-11
29-May-11
21-Jun-11
Page 2 of 7
PL: Planned EXP: Expect ACT: Actual
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM MRQ
Commodity Name
TER
F.O.C
P.O
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
(Supplier) MICROTURBINE
(172-01)
PL
15-Dec-11
12-Jan-12
26-Jan-12
EXP
15-Dec-11
26-Jan-12
29-Dec-11
24-Jul-11
18-Oct-11
08-Nov-11
22-Nov-11
12-Jul-11
02-Oct-11
23-Oct-11
06-Nov-11
ACT
Electrical ELECTRICAL CABLE TRAYS (500-02)
NAVIGATIONAL AIDS (510-10)
E& I MODULE
(510-16)
ELECTRICAL CABLES (510-22)
Tuesday, July 05, 2011
PL
02-May-11
19-Jun-11
10-Jul-11
EXP ACT
10-Apr-11
02-May-11
30-May-11
PL
16-May-11
27-Jun-11
18-Jul-11
02-Aug-11
05-Dec-11
26-Dec-11
09-Jan-12
10-Jul-11
31-Jul-11
15-Aug-11
18-Dec-11
08-Jan-12
22-Jan-12
PL
15-Dec-11
12-Jan-12
26-Jan-12
EXP
15-Dec-11
12-Jan-12
26-Jan-12
EXP ACT
26-Apr-11
ACT
PL
09-May-11
20-Jun-11
EXP ACT
10-Apr-11
13-Jul-11
27-Jul-11
04-Dec-11
25-Dec-11
08-Jan-12
03-Jul-11
10-Jul-11
22-Nov-11
13-Dec-11
27-Dec-11
29-May-11
Page 3 of 7
PL: Planned EXP: Expect ACT: Actual
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM MRQ
TER
F.O.C
P.O
02-Jun-11
06-Jul-11
27-Jul-11
22-Aug-11
04-Aug-11
25-Aug-11
18-Jul-11
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
14-Dec-11
04-Jan-12
18-Jan-12
13-Sep-11
23-Dec-11
13-Jan-12
27-Jan-12
08-Aug-11
24-Aug-11
26-Dec-11
24-Jan-12
14-Feb-12
04-Aug-11
25-Aug-11
15-Sep-11
23-Dec-11
22-Jan-12
12-Feb-12
26-Jun-11
17-Jul-11
31-Jul-11
13-Jan-12
10-Feb-12
24-Feb-12
24-Jul-11
14-Aug-11
28-Aug-11
16-Jan-12
06-Feb-12
20-Feb-12
15-Dec-11
05-Jan-12
19-Jan-12
12-Dec-11
05-Jan-12
19-Jan-12
PL
15-Dec-11
12-Jan-12
26-Jan-12
EXP
15-Dec-11
05-Jan-12
19-Jan-12
Commodity Name (Supplier) LIGHTING MATERIAL (529-01)
EARTHING MATERIAL (550-01)
PL EXP ACT
22-Jun-11
PL
06-Jun-11
EXP ACT
20-Jun-11
PL
25-May-11
Instrument LOOSE INSTRUMENT (210-01)
EXP ACT
06-Jun-11
MANUAL VALVES PL EXP
(212-01)
SHUTDOWN & BLOWDOWN VALVES (212-04)
Tuesday, July 05, 2011
ACT
ACT
Page 4 of 7
PL: Planned EXP: Expect ACT: Actual
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM Commodity Name
MRQ
TER
F.O.C
P.O
10-Apr-11
12-Jun-11
10-Jul-11
24-Jul-11
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
06-Jan-12
27-Jan-12
10-Feb-12
03-Jul-11
21-Dec-11
11-Jan-12
25-Jan-12
(Supplier) MULTIPHASE FLOW METERS (221-06)
CHOKE VALVES
PL EXP ACT
10-Apr-11
25-May-11
21-Jun-11
PL
13-Apr-11
15-Jun-11
10-Jul-11
24-Jul-11
05-Apr-12
26-Apr-12
05-Jul-11
26-Jul-11
09-Aug-11
21-Feb-12
11-Apr-12
13-Jun-11
11-Jul-11
25-Jul-11
06-Apr-12
27-Apr-12
11-May-12
21-Jul-11
04-Aug-11
17-Mar-12
07-Apr-12
21-Apr-12
12-Jul-11
26-Jul-11
08-Jan-12
29-Jan-12
12-Feb-12
05-Jul-11
19-Jul-11
01-Jan-12
22-Jan-12
05-Feb-12
28-Jun-11
12-Jul-11
24-Mar-12
14-Apr-12
28-Apr-12
06-Jul-11
14-Jul-11
17-Mar-12
07-Apr-12
21-Apr-12
EXP
(234-06)
WING VALVES
ACT
10-Apr-11
PL
13-Apr-11
EXP
(239-02)
WELLHEAD CONTROL PANEL
ACT
10-Apr-11
15-Jun-11
PL
12-Apr-11
12-Jun-11
EXP ACT
07-Apr-11
16-Jun-11
HIGH INTEGRITY PL PRESSURE EXP PROTECTION ACT (252-14)
07-Apr-11
31-May-11
(252-10)
Tuesday, July 05, 2011
03-Apr-11
09-Jun-11
Page 5 of 7
PL: Planned EXP: Expect ACT: Actual
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM MRQ
TER
PL
01-Jun-11
07-Jul-11
01-Aug-11
15-Aug-11
EXP
26-Jun-11
04-Aug-11
25-Aug-11
02-Jun-11
03-Jul-11
Commodity Name
F.O.C
P.O
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
29-Dec-11
19-Jan-12
02-Feb-12
13-Sep-11
07-Jan-12
28-Jan-12
11-Feb-12
24-Jul-11
07-Aug-11
01-Nov-11
22-Nov-11
06-Dec-11
14-Jul-11
04-Aug-11
18-Aug-11
02-Nov-11
23-Nov-11
07-Dec-11
07-Jul-11
28-Jul-11
11-Aug-11
05-Nov-11
26-Nov-11
10-Dec-11
21-Jul-11
11-Aug-11
25-Aug-11
09-Nov-11
30-Nov-11
14-Dec-11
20-Jun-11
11-Jul-11
25-Jul-11
28-Nov-11
19-Dec-11
02-Jan-12
21-Jul-11
11-Aug-11
25-Aug-11
09-Dec-11
30-Dec-11
13-Jan-12
(Supplier) SAND PROBES
(281-08)
ACT
INSTRUMENT/ME PL CHANICAL BULK EXP MATERIAL ACT (291-01)
03-May-11
JUNCTION BOXES PL
09-Jun-11
EXP
(295-01)
INSTRUMENT CABLES (298-01)
INSTRUMENT CABLE TRAYS / CHANNELS (298-03)
ACT
06-Jun-11
PL
23-May-11
EXP ACT
23-Jun-11
PL
31-May-11
28-Jun-11
14-Jul-11
28-Jul-11
22-Oct-11
29-Oct-11
12-Nov-11
EXP
26-Jun-11
28-Jul-11
15-Aug-11
29-Aug-11
13-Nov-11
20-Nov-11
04-Dec-11
ACT
Piping Tuesday, July 05, 2011
Page 6 of 7
PL: Planned EXP: Expect ACT: Actual
Project: 3467-200 PTB
Procurement Status Repo
PETROBEL, EPC FOR SEITH OFFSHORE PLATFORM MRQ
Commodity Name
TER
F.O.C
P.O
As of: Fab. Upto RFS
25-Jun
Shipping
Delivery at Site
(Supplier) PIPING BULK MATERIAL (400-01)
INJECTION FITTINGS (400-02)
PL
07-Apr-11
31-May-11
20-Jun-11
EXP
04-Jul-11
06-Jan-12
27-Jan-12
10-Feb-12
07-Jul-11
10-Jan-12
31-Jan-12
14-Feb-12
ACT
07-Apr-11
17-May-11
22-Jun-11
PL
24-Apr-11
15-Jun-11
13-Jul-11
27-Jul-11
10-Dec-11
31-Dec-11
14-Jan-12
24-Jul-11
21-Aug-11
07-Sep-11
18-Jan-12
08-Feb-12
22-Feb-12
09-Jun-11
10-Jul-11
24-Jul-11
07-Dec-11
28-Dec-11
11-Jan-12
21-Jul-11
21-Aug-11
07-Sep-11
18-Jan-12
08-Feb-12
22-Feb-12
PL
15-Dec-11
12-Jan-12
26-Jan-12
EXP
15-Dec-11
12-Jan-12
26-Jan-12
EXP ACT
24-Apr-11
PL
20-Apr-11
Pipeline INSULATING JOINTS (Pipeline) (612-03)
PRODUCTION MANIFOLD (642-03)
Tuesday, July 05, 2011
EXP ACT
29-May-11
ACT
Page 7 of 7
PL: Planned EXP: Expect ACT: Actual
PAGE 32 OF 33
PTB
SETH OFFSHORE DEVELOPMENT EPC PROJECT PLANNING PORTION IN THE MONTHLY PROGRESS REPORT
Egypt
Rev. (0) Jun 2011
4.6.2 TECNOMARE
GFL 003-0405
3467-200
SETH DEVELOPMENT PROJECT Procurement Summary Status Report as of June 25th, 2011 Sr.
Commodity
Phase
1
PLC /RTU
Forecast
Plan
2
3
GROUT SEALS
SHOCK CELLS
RFQ's Tech. Open Tech. Report Issued Date 11‐Mar‐11
13‐Apr‐11
3‐May‐11
Comm. Open
Comm. Report
Fax Of Comm.
MRP Issued
P.O. Date
11‐May‐11
17‐May‐11
30‐May‐11
30‐May‐11
30‐May‐11
Delivery at Delivery Ex‐ Delivery FOB site Work 12‐Jan‐12
27‐Jan‐12
25‐Feb‐12 23‐Feb‐12
Actual
11‐Mar‐11
25‐Mar‐11
20‐Apr‐11
21‐Apr‐11
29‐Apr‐11
2‐May‐11
2‐May‐11
2‐May‐11
Plan
31‐Mar‐11
10‐Apr‐11
14‐Apr‐11
24‐Apr‐11
28‐Apr‐11
15‐May‐11
15‐May‐11
15‐May‐11
4‐Sep‐11
18‐Sep‐11
28‐Sep‐11
4‐Sep‐11
18‐Sep‐11
28‐Sep‐11
Forecast Actual
15‐Mar‐11
5‐Apr‐11
14‐Apr‐11
14‐Apr‐11
26‐May‐11
26‐May‐11
26‐May‐11
26‐May‐11
Plan
31‐Mar‐11
29‐Apr‐11
9‐May‐11
17‐May‐11
25‐May‐11
30‐May‐11
30‐May‐11
30‐May‐11
21‐Mar‐11
14‐Apr‐11
4‐May‐11
9‐May‐11
6‐Jun‐11
9‐Jun‐11
9‐Jun‐11
9‐Jun‐11
Forecast Actual