Loading documents preview...
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
EPCC -01 PACKAGE FOR CDU/VDU UNIT_HRRL BARMER, RAJASTHAN
2
3
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
992
Project Milestone
992
Schedule Milestone
992
MS1000
Project Start (Award of Work)
0
Project Start (Award of Work)
MS1025
Start Soil Investigation work
0
Start Soil Investigation work
MS1050
Kick off Meeting
0
Kick off Meeting
MS1100
P&ID -Preliminary
0
P&ID -Preliminary
MS1125
U/G Piping 1st MTO
0
U/G Piping 1st MTO
MS1120
P&ID - AFP
0
P&ID - AFP
MS1010
Award of Heater Package
0
Award of Heater Package
MS1035
0
Site Mobilization and Setting of Site office with posting of RCM
MS1135
Site Mobilization and Setting of Site office with posting of RCM UG Pipe 1st MTO Ordering Complete
0
UG Pipe 1st MTO Ordering Complete
MS1710
Plot Plan - AFP
0
Plot Plan - AFP
MS1150
Start of Piling Works
0
Start of Piling Works
MS1400
Start U/G Piping Work
0
MS1110
Ordering of Column and Desalter
0
Ordering of Column and Desalter
MS1175
30% Model Review Complete
0
30% Model Review Complete
MS1325
Place Order- Switchgears & Transformers
0
Place Order- Switchgears & Transformers
MS1720
AG Piping 1st MTO Ordering Complete
0
AG Piping 1st MTO Ordering Complete
MS1500
Start Heater Foundation Work
0
Start Heater Foundation Work
MS1200
P&ID - Issue for Hazop
0
P&ID - Issue for Hazop
Actual Work Remaining Work
Critical Remaining Work Milestone
Page 1 of 34
Start U/G Piping Work
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration
MS1905
Start Steel Str. Fabricati on Work
0
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Start Steel Str. Fabricati on Work
MS1250
HAZOP Review complete
0
HAZOP Review complete
MS1300
60% Model Review Complete
0
60% Model Review Complete
MS1700
Start Heater Field Erection Work
0
Start Heater Field Erection Work
MS1475
Start Issue A/G Piping Isometrics- AFC
0
MS1225
Plot PLan - AF D
0
MS1525
Start A/G Piping Prefabrication
0
Start A/G Piping Prefabrication
MS1375
P&ID - AFC ( For 90 % MR)
0
P&ID - AFC ( For 90 % MR)
MS1350
Plot Plan - AFC
0
MS1450
90% Model Review Complete
0
MS1915
Start Steel Str. Erection Work
0
MS1425
Completion of Foundation for CDU/VDU Column
0
MS1550
Start A/G Piping Erection
0
MS1885
Substn. Building Ready for Panel Erection
0
MS1635
Start DCS Installation in SRR Bldg. ( By Others )
0
Start DCS Installation in SRR Bldg. ( By Others )
MS1575
Completion Erection of CDU / VDU Column
0
Completion Erection of CDU / VDU Column
MS1020
Start Precommissioning flushing and blowing work
0
MS1895
Equipment Erection Completion
0
MS1625
Energization of Substation
0
MS1835
DCS Power On
0
DCS Power On
MS1775
Start Instrument Loop & Functoin Test
0
Start Instrument Loop & Functoin Test
-1 1
Actual Work Remaining Work
Critical Remaining Work Milestone
Page 2 of 34
2
3
4
5
6
7
8
Start Issue A/G Piping Isometrics- AFC Plot PLan - AF D
Plot Plan - AFC 90% Model Review Complete Start Steel Str. Erection Work Completion of Foundation for CDU/VDU Column Start A/G Piping Erection Substn. Building Ready for Panel Erection
Start Precommissioning flushing and blowing work Equipment Erection Completion Energization of Substation
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
MS1675
Heater Package Erection & Refractory Work Completion
0
MS1650
Completion of Motor Solo Run test
0
MS1725
Complete A/G Piping Er ection
0
MS1750
Completion of Piping Hydro-testing
0
MS1800
Completion of Piping Flushing, Blowing and ReinStatement
0
MS1825
Mechanical Completion
0
MS1810
Heater Dry Out Start
0
MS1875
Commissioning Completion
0
MS1925
Completion of 6 Months Post Commissioning Assistance and PGTR
0
2
3
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Heater Package Erection & Refractory Work Completion Completion of Motor Solo Run test Complete A/G Piping Er ection Completion of Piping Hydro-testing
Completion of Piping Flushing, Blowing and Rein Mechanical Completion Heater Dry Out Start Commissioning Completion
Interface: From Owner
782
Interface: From Owner Engineering
0
Engineering
OOE1000
CDU/VDU Column Loading Information for Civil Design
0
CDU/VDU Column Loading Information for Civil Design
OOE1010
Availability of Native Files ( P&ID, MFD, PFD, Equipment Data Sheet Etc.)
0
Availability of Native Files ( P&ID, MFD, PFD, Equipment Data Sheet Etc.)
Free Issue Material
Free Issue Material
61 0
Crude Distillation Column (CDU) from EIL/Owner (In Two Parts field welding at Site in vertical position by o
0
Vacuum Distillation Column (VDU) from EIL/Owner ( In Three Parts , field welding in vertical position at site
FIM1100
Crude Distillation Column (CDU) from EIL/Owner (In Two Parts field welding at Site in vertical position by others) Vacuum Distillation Column (VDU) from EIL/Owner ( In Three Parts , field welding in vertical position at site by FIM ( Substn ) : Detector, Hooters , Sirens etc.
0
FIM ( Substn ) : Detector, Hooters , Sirens etc.
FIM1275
FIM ( Field) : CCTV Etc.
0
FIM ( Field) : CCTV Etc.
FIM1265
FIM ( SRR) : Detector, Hooters, Sirects Etc.
0
FIM1000 FIM1255
Construction OOCO1000
Actual Work Remaining Work
FIM ( SRR) : Detector, Hooters, Sirects Etc. Construction
465 Handing Over of Site for Construction Work
Critical Remaining Work Milestone
0
Page 3 of 34
Handing Over of Site for Construction Work
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
OOCO1025 OOCO1035
Handing Over of land at site for setting up Project Office, Fabrication and Stoage Yard CDU & VDU COLUMN release for Piping Work
Precommissioning & Commissioning
Original Duration
Month -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Handing Over of land at site for setting up Project Office, Fabrication and Stoage Yard 0 CDU & VDU COLUMN release for Piping Work
0
Precommissioning & Commissioning
294
Availabiity of Raw Water , Plant water , Plant Air
A6670
Availabiity of Raw Water , Plant water , Plant Air
0
A6680
Availability of Cooling Water
0
A6710
Availabiity of Instrument Air
0
FIM1285
0
Availability of Incoming Power Supply for Substn Energization (66 Kv)
0
Availability of DCS, ESD, F&G PLC : FIM (Ready for loop check)
A6690
Availability of Incoming Power Supply for Substn Energization (66 Kv) Availability of DCS, ESD, F&G PLC : FIM (Ready for loop check) Avaiabiity of Nitrogen
A6320
Availability of HP, MP , LP Steam
0
Availability of HP, MP , LP Steam
A6720
Availability of DM Water
0
Availability of DM Water
A6740
Avaiability of Boiler Feed Water
0
Avaiability of Boiler Feed Water
A6730
Availability of Fuel Gas / Fuel Oil / Flushing Oil
0
Availability of Fuel Gas / Fuel Oil / Flushing Oil
A6340
Availability of Feed for Commissioning
0
Availability of Feed for Commissioning
A6330
Availability of Cooling Water Availabiity of Instrument Air
Avaiabiity of Nitrogen
0
Engineering
490
Engineering Process
263
Process
P&ID
263
P&ID
PID1
P&ID - Preliminary
14
PID13
P&ID - AFP
30
PID23
P&ID - AFP - For 60% Model Review ( incorporating S/R/P vendor data) P&ID - Issue for Hazop
21
PID4
Actual Work Remaining Work
Critical Remaining Work Milestone
24
Page 4 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
PID5 PID2
P&ID AF D ( With 60% Model Review Tag Resolution + Hazop Resolution ) P&ID - AFC ( For 90% Model Review)
Equipment Process Data Sheet PDS - LLI/ Critical Items
66
Equipment PDS - Heater
7
A5260
Equipment PDS - Air Cooler
7
A5270
Equipment PDS - Desalter
7
A5290
Equipment PDS - Ejector
10
Equipment PDS
Balance Equipment PDS
10
Equipment PDS - Column, Vessesl, Heat Exch., Rotating Equip, Pkg. Etc. (AFR Isssue) Instrument Process Data Sheet
84
Data Sheet for PSVs
20
EA190
Data Sheet for Analyzer System
65
EA200
Data Sheet for Balance Instruments
70
EA175
Data Sheet for Mass Flowmeters
70
EA185
Data Sheet for Control Valves
60
EA195
Data Sheet for In-line Instruments
70
A5320
Instrument Process Data Sheet (Balance)
70
Actual Work Remaining Work
6
7
Milestone
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Equipment Process Data Sheet PDS - LLI/ Critical Items
PDS - Vessel, Heat Exchangers, Pumps
Balance Equipment PDS
Instrument Process Data Sheet
Process Engineering
251
Critical Remaining Work
8
30
EA145
Process Engineering
5
10 30
A5300
4
20
A5280
A6420
3
14
34
PDS - Vessel, Heat Exchangers, Pu mps
2
Page 5 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
EP1260
Process List and Documents (Balance)
EP1270
Equipment List
11
EP1175
HAZOP
12
2
3
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
251
Civil
407
Civil Soil Investigation
74
A5360
Soil Investigation Plan
2
A5340
Soil Investigation Work
45
A5480
Soil Investigation report - Preliminary
14
A5350
Soil Investigation report - Final
20
Loading Data
132
A5410
Loading Data from Owner for CDU Column
A5420 A5470
Loading Data from Owner for VDU Column + Toyo - Piping Team Loading Data ( Others)
A5450
Loading Data for Substation Building
4
A5460
Loading Data for SRR Building
4
A5490
Loading Data for Tech Str. # 2
5
A5500
Loading Data for Tech Str. # 5
5
A5440
Loading Data from Heater Vendor
5
A5430
Loading Data from Air Cooler Vendor (Main Pipe Rack )
Pile and Foundation Location Plan - AFC Category Critical - Pile and Foundation Location Plan
Actual Work Remaining Work
Critical Remaining Work Milestone
Soil Investigation
Loading Data
2 26 130
14 Pile and Foundation Location Plan - AFC Category
205 149
Page 6 of 34
Critical - Pile and Foundation Location Plan
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
ENGPILE1000 CDU Column - Pile & Fdn. Location Plan
56
ENGPILE1010 Substation Bldg. - Pile & Fdn. Location Plan
50
ENGPILE1030 SRR Bldg. - Pile & Fdn. Location Plan
50
ENGPILE1060 VDU Collumn - Pile & Fdn. Location Plan
78
ENGPILE1040 Technological Structures 2 - Pile & Fdn. Location Plan
77
ENGPILE1050 Technological Structures 5 - Pile & Fdn. Location Plan
77
ENGPILE1020 Pipe Rack - Pile & Fdn. Location Plan
65
ENGPILE1070 Heaters - Pile & Fdn. Location Plan
72
ENGPILE1080 Technological Structures (1,3,4,6,7) - Pile & Fdn. Location Plan Balance - Pile and Foundation Location Plan A5540
Balance - Pile & Fdn. Location Plan
Foundation Drawings
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Balance - Pile and Foundation Location Plan
190 190
Foundation Drawings
365
Fdn Drgs for CDU Column (AFC)
40
A5570
Fdn Drgs for Main Pipe Rack (AFC)
58
A5580
Fdn Drgs for Heaters (AFC)
75
A5600
Fdn. Drawing for Substation Bldg.
45
A5610
Fdn. Drawing for SRR Bldg.
45
A5550
Fdn Drgs for VDU Column (AFC)
55
A5590
Fdn Drgs. for Tech. Structures 2 , 5
60
A5620
Fdn Drgs. for Remaining / Others / Misc. - Equipments
UG Composite
Remaining Work
3
77
A5370
Actual Work
2
200 85
Critical Remaining Work Milestone
Page 7 of 34
UG Composite
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A5380
Conceptual UG Composite Plan-IFR
40
A5390
U/G Composite Plans- IFC
45
Civil (Others) A5400
Other including Paving Works
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Civil (Others)
300 74
A5650
Sub-station Arch Drgs - 1st Issue
19
A5820
SRR Arch Drgs - 1st Issue
15
A5640
Sub-station Arch Drgs & details - AFC
55
A5660
SRR Arch Drgs & Details - AFC
45
A5630
Steel Str. 1st MTO
10
Architecture / Steel Structure
Piping
490
Piping EPIPE1299
Piping Engineering
EPIPE1230
Fire Fighting Drawing - 1st Issue
Plot Plan
490 20 Plot Plan
275
EPIPE1010
Plot Plan-Preliminary
20
EPIPE1000
Plot Plan - AFP
30
EPIPE1050
Plot Plan - AFD
21
EPIPE1150
Plot Plan - AFC
10
3 D Modelling
3 D Modelling
160
EPIPE1075
30 % Model Review
7
EPIPE1125
60 % Model Review
7
Remaining Work
3
300
Architecture / Steel Structure
Actual Work
2
Critical Remaining Work Milestone
Page 8 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
EPIPE1175
90 % Model Review
Piping MTO
EPIPE1035
AG Pipe - MTO (Preliminary)
10
EPIPE1100
AG Pipe - MTO 1
10
EPIPE1240
AG Pipe - MTO 2
6
EPIPE1250
AG Pipe - MTO 3 (Final)
6
Piping Isometric
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Piping MTO
7
Piping Isometric
222 55
EPIPE1270
AG Pipe Isometrics ( Pipe Rack, Priority T Section of Main Pipe Rack + Heater Rack) Isometric for VDU and CDU Column Piping
EPIPE1210
AG Pipe Isometrics - Tech Str. # 2
40
EPIPE1260
AG Pipe Isometrics - Tech Str. # 5
90
EPIPE1220
AG Pipe Isometrics ( Balance) - AFC
40
168 Electrical
297
Electrical A5850
Substation Eqp. Layout (Preliminary)
A5780
Single Line Diagram (AFP)
26
A5830
Electrical Load List (AFR)
45
A5810
Hazardous Area Classifi cation - AFR
40
A5790
Sub-station Eqpt Layout- AFP
60
A5860
Main Cable Route & Layout Plan: Overall & Key Plan - AFR
15
A5890
Main Cable Route & Layout Plan: Overall & Key Plan - AFC
20
Remaining Work
4
290 UG Pipe - MTO 1
Actual Work
3
7
EPIPE1025
EPIPE1200
2
Critical Remaining Work Milestone
5
Page 9 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A5840
Equip Sizing: Load Analysis/ Eqpt Sizing Calculations- AFR
21
A5870
Bulk Material Take Off - 1st
20
A5880
Bulk Material Take Off - final
15
EINST1000
Instrument Index- 1st Issue
EINST1010
SRR Bldg. Equipment Layout : Preliminary
EINST1050
I/O Point Summary/ Point Database
EINST1075 EINST1110
Input to Owner: DCS Hardware Finalization for DCS ( Indicative Only)) Instrument Layout - AFC
40
EINST1100
Bulk Material Take Off
21
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Instrumentation
50 5 30 Input to Owner:
0
DCS Hardware Finalization for DCS ( Indicative Only))
Procurement Engineering
387
Procurement Engineering Static
Static
147
Towers (CS, CS+Clad, Site Joint) Prepare & Issue MR
10
A2710
Receipt of Quotation
12
A2720
Technical Querry / TBE
15
A2730
Key Vendor Data Reci ept
40
A2740
Key Vendor Data Approval
60
Tower Internals_AXDB001
89
A2750
Prepare & Issue MR
10
A2760
Receipt of Quotation
14
Critical Remaining Work Milestone
Towers (CS, CS+Clad, Site Joint)
130
A2700
Remaining Work
3
283
Instrumentation
Actual Work
2
Page 10 of 34
Tower Internals_AXDB001
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A2770
Technical Querry / TBE
14
A2780
Key Vendor Data Reci ept
30
A2790
Key Vendor Data Approval
30
Heat Exchangers
4
5
6
7
Prepare & Issue MR
10
A6490
Receipt of Quotation
20
A6500
Technical Querry / TBE
20
A6510
Key Vendor Data Reci ept
20
A6520
Key Vendor Data Approval
55
SS Clad, Solid SS & Brass Exchanger_AXEA002 Prepare & Issue MR
10
A2860
Receipt of Quotation
20
A2870
Technical Querry / TBE
20
A2880
Key Vendor Data Reci ept
20
A2890
Key Vendor Data Approval
55
Helix heat exchanger_AXEA003 Prepare & Issue MR
10
A6590
Receipt of Quotation
21
A6600
Technical Querry / TBE
26
A6610
Key Vendor Data Reci ept
20
Critical Remaining Work Milestone
SS Clad, Solid SS & Brass Exchanger_AXEA002
Helix heat exchanger_AXEA003
137
A6580
Page 11 of 34
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
CS & LAS Heat Exchanger_AXEA001
135
A2850
8
Heat Exchangers
132
A6480
Remaining Work
3
137
CS & LAS Heat Exchanger_AXEA001
Actual Work
2
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A6620
Key Vendor Data Approval
125
A5680
Prepare & Issue MR
10
A5690
Receipt of Quotation
21
A5700
Technical Querry / TBE
21
A5710
Key Vendor Data Reci ept
45
A5720
Key Vendor Data Approval
45
Vessels Big Vessels (More than 2m Dia)
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Big Vessels (More than 2m Dia)
A2810
Receipt of Quotation
21
A2820
Technical Querry / TBE
26
A2830
Key Vendor Data Reci ept
30
A2840
Key Vendor Data Approval
60
Small Vessels ( Less than 2m Dia)
Air Cooler
142 10
Small Vessels (Less than 2m Dia)
142
A6530
Prepare & Issue MR
10
A6540
Receipt of Quotation
21
A6550
Technical Querry / TBE
26
A6560
Key Vendor Data Reci ept
30
A6570
Key Vendor Data Approval
60
HTAT _Fired Heaters ( Crud e Heater101- F-101A/B an d Vacuum Heater 101-F-102)
Milestone
5
Vessels
Prepare & Issue MR
Remaining Work
4
142
A2800
Critical Remaining Work
3
55
Air Cooler
Actual Work
2
HTAT _Fired Heaters ( Crude Heater101-F-101A/B and Vacuum Heater 101-F-102)
169
Page 12 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A5140
Prepare & Issue MR
5
A5150
Receipt of Quotation
10
A5160
Technical Querry / TBE
15
A5170
Key Vendor Data Reci ept
60
A5180
Key Vendor Data Approval
120
Rotating & Package
2
3
4
5
6
7
Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR 189 PDT + Quench Pump, RCO Prepare & Issue MR
10
A3560
Receipt of Quotation
21
A3570
Technical Querry / TBE
26
A3580
Key Vendor Data Reci ept
30
A3590
Key Vendor Data Approval
100
Centrifugal Pumps Remaining All (API) Prepare & Issue MR
10
A7300
Receipt of Quotation
21
A7310
Technical Querry / TBE
24
A7320
Key Vendor Data Reci ept
20
A7330
Key Vendor Data Approval
100
High speed Centrifugal Pumps (SUNDYNE) Prepare & Issue MR
10
A7350
Receipt of Quotation
21
Actual Work Remaining Work
Critical Remaining Work Milestone
High speed Centrifugal Pumps (SUNDYNE)
178
A7340
Page 13 of 34
Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR PDT + Quench Pump, RCO
Centrifugal Pumps Remaining All (API)
177
A7290
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Rotating & Package
236
A3550
8
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A7360
Technical Querry / TBE
25
A7370
Key Vendor Data Reci ept
21
A7380
Key Vendor Data Approval
100
Positive dispacement Pumps (Diaphragm) Prepare & Issue MR
10
A7600
Receipt of Quotation
21
A7610
Technical Querry / TBE
24
A7620
Key Vendor Data Reci ept
18
A7630
Key Vendor Data Approval
100
Prepare & Issue MR
10
A7550
Receipt of Quotation
21
A7560
Technical Querry / TBE
24
A7570
Key Vendor Data Reci ept
18
A7580
Key Vendor Data Approval
100
Prepare & Issue MR
10
A7500
Receipt of Quotation
20
A7510
Technical Querry / TBE
20
A7520
Key Vendor Data Reci ept
20
A7530
Key Vendor Data Approval
100
Remaining Work
Critical Remaining Work Milestone
5
6
7
Page 14 of 34
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Positive dispacement Pumps (Diaphragm)
Positive dispacement Pumps (Rotary)
Centrifugal Pumps (NON-API)
173
A7490
Actual Work
4
182
A7540
Centrifugal Pumps (NON-API)
3
177
A7590
Positive dispacement Pumps (Rotary)
2
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
Reciprocating Air Compressor Prepare & Issue MR
10
A7450
Receipt of Quotation
20
A7460
Technical Querry / TBE
20
A7470
Key Vendor Data Reci ept
30
A7480
Key Vendor Data Approval
100
Prepare & Issue MR
7
A7400
Receipt of Quotation
20
A7410
Technical Querry / TBE
20
A7420
Key Vendor Data Reci ept
30
A7430
Key Vendor Data Approval
100
Package
99
A5080
Prepare & Issue MR
5
A5090
Receipt of Quotation
10
A5100
Technical Querry / TBE
12
A5110
Key Vendor Data Reci ept
50
A5120
Key Vendor Data Approval
50
Ejector
Remaining Work
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Reciprocating Air Compressor
Purge Oil Mist System
Package
177
Desalter Package
Actual Work
4
169
A7390
A3100
3
173
A7440
Purge Oil Mist System
2
Desalter Package
Ejector
122 Prepare & Issue MR
Critical Remaining Work Milestone
10
Page 15 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A3110
Receipt of Quotation
15
A3120
Technical Querry / TBE
20
A3130
Key Vendor Data Reci ept
55
A3140
Key Vendor Data Approval
55
Others Prepare & Issue MR
10
A7660
Receipt of Quotation
10
A7670
Technical Querry / TBE
25
A7680
Key Vendor Data Reci ept
55
A7640
Key Vendor Data Approval
55
Fire Fighting Equipment / Clean Agent/ Others
4
5
6
7
Prepare & Issue MR
15
A3910
Receipt of Quotation
21
A3920
Technical Querry / TBE
20
A3930
Key Vendor Data Reci ept
30
A3940
Key Vendor Data Approval
60
HVAC Package Prepare & Issue MR
10
A3810
Receipt of Quotation
16
A3820
Technical Querry / TBE
25
A3830
Key Vendor Data Reci ept
40
Critical Remaining Work Milestone
Page 16 of 34
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Fire Fighting Equipment / Clean Agent/ Others
HVAC Package
191
A3800
8
Others
156
A3900
Remaining Work
3
130
A7650
Actual Work
2
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A3840
Key Vendor Data Approval
Piping
20
A3600
Prepare & Issue MR
5
A3610
Receipt of Quotation
10
A3620
TBE/CBE
25
A3650
Prepare & Issue MR
5
A3660
Receipt of Quotation
12
A3670
TBE/CBE
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Piping U/G Piping Material 1st
A/G Piping Material 1st
8
Electrical
Electrical
382
EHV & HV Switchgear (ICOG) Prepare & Issue MR
10
A3960
Receipt of Quotation
15
A3970
Technical Querry / TBE
14
A3980
Key Vendor Data Reci ept
25
A3990
Key Vendor Data Approval
50
Transformers (Power, Lighting, Distribuition) Prepare & Issue MR
10
A4060
Receipt of Quotation
15
A4070
Technical Querry / TBE
30
Milestone
Transformers (Power, Lighting, Distribuition)
188
A4050
Critical Remaining Work
EHV & HV Switchgear (ICOG)
132
A3950
Remaining Work
4
5
A/G Piping Material 1st
Actual Work
3
90 63
U/G Piping Material 1st
2
Page 17 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A4080
Key Vendor Data Reci ept
25
A4090
Key Vendor Data Approval
90
66 KV GIS (Gas Insulated S/gear) Eqpt Prepare & Issue MR
10
A4160
Receipt of Quotation
20
A4170
Technical Querry / TBE
20
A4180
Key Vendor Data Reci ept
25
A4190
Key Vendor Data Approval
90
Prepare & Issue MR
15
A4110
Receipt of Quotation
14
A4120
Technical Querry / TBE
14
A4130
Key Vendor Data Reci ept
25
A4140
Key Vendor Data Approval
90
EHV, HV & MV Cables
5
6
7
Prepare & Issue MR
25
A5740
Receipt of Quotation
21
A5750
Technical Querry / TBE
30
A5760
Key Vendor Data Reci ept
30
A5770
Key Vendor Data Approval
90
AC UPS
Milestone
Page 18 of 34
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
415V MV Switchgear
EHV, HV & MV Cables
AC UPS
222
Critical Remaining Work
8
66 KV GIS (Gas Insulated S/gear) Eqpt
222
A5730
Remaining Work
4
178
A4100
Actual Work
3
183
A4150
415V MV Switchgear
2
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A7040
Prepare & Issue MR
30
A7050
Receipt of Quotation
30
A7060
Technical Querry / TBE
30
A7070
Key Vendor Data Reci ept
30
A7080
Key Vendor Data Approval
90
AC & DC UPS and Battery Charger Prepare & Issue MR
90
A7150
Receipt of Quotation
90
A7160
Technical Querry / TBE
90
A7170
Key Vendor Data Reci ept
60
A7180
Key Vendor Data Approval
90
Prepare & Issue MR
30
A7200
Receipt of Quotation
30
A7210
Technical Querry / TBE
30
A7220
Key Vendor Data Reci ept
145
A7230
Key Vendor Data Approval
150
Instrumentation
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
AC & DC UPS and Battery Charger
Cathodic Protection System
Instrumentation
328
Control Valves
Control Valves
173
A4450
Prepare & Issue MR
25
A4460
Receipt of Quotation
14
Remaining Work
4
252
A7190
Actual Work
3
282
A7140
Cathodic Protection System
2
Critical Remaining Work Milestone
Page 19 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A4470
Technical Querry / TBE
14
A4480
Key Vendor Data Reci ept
25
A4490
Key Vendor Data Approval
75
On-Off/ Self Regulating Valves Prepare & Issue MR
25
A4510
Receipt of Quotation
14
A4520
Technical Querry / TBE
14
A4530
Key Vendor Data Reci ept
25
A4540
Key Vendor Data Approval
75
Prepare & Issue MR
25
A4560
Receipt of Quotation
14
A4570
Technical Querry / TBE
14
A4580
Key Vendor Data Reci ept
25
A4590
Key Vendor Data Approval
75
Analyzer System
5
6
7
Prepare & Issue MR
25
A4610
Receipt of Quotation
14
A4620
Technical Querry / TBE
14
A4630
Key Vendor Data Reci ept
25
A4640
Key Vendor Data Approval
90
Critical Remaining Work Milestone
Page 20 of 34
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
On-Off/ Self Regulating Valves
Pressure Safety Valves
Analyzer System
188
A4600
Remaining Work
4
173
A4550
Actual Work
3
173
A4500
Pressure Safety Valves
2
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
In-line Instruments Prepare & Issue MR
25
A4760
Receipt of Quotation
14
A4770
Technical Querry / TBE
14
A4780
Key Vendor Data Reci ept
25
A4790
Key Vendor Data Approval
75
Field Instruments
4
5
6
7
Prepare & Issue MR
25
A4810
Receipt of Quotation
14
A4820
Technical Querry / TBE
14
A4830
Key Vendor Data Reci ept
25
A4840
Key Vendor Data Approval
75
Instrument Cable Duct/Trays/ Fittings / Others Prepare & Issue MR
25
A4860
Receipt of Quotation
14
A4870
Technical Querry / TBE
14
A4880
Key Vendor Data Reci ept
25
A4890
Key Vendor Data Approval
50
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 In-line Instruments
Instrument Cable Duct/Trays/ Fittings / Others
148
A4850
8
Field Instruments
168
A4800
Procurement
591
Procurement HTAT Fired Heaters ( Crude Heater101-F-101A/B and Vacuum Heater 101-F -102)
Remaining Work
3
168
A4750
Actual Work
2
Critical Remaining Work Milestone
425
HTAT
425
Fired Heaters ( Crude Heater101-F-101A/B and Vacuum Heater 101-F-102)
Page 21 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
PM2801
Ordering / LOI ISsue
PM2803
Heaters Manufacturing & Delivery to Site
2
3
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
5 420 Static
424
Static Towers (CS, CS+Clad, Site Joint) PM2662
Ordering / LOI Issue
PM2672
Manufacturing & Delivery to Site
Tower Internals Ordering / LOI Issue
PM3032
Manufacturing & Delivery to Site
Heat Exchanger CS & LAS Heat Exchanger PM2782
Ordering / LOI ISsue
PM2822
Part 1 : Manufacturing & Delivery to Site (TS2, TS 5 )
PM2792
Part 2 :Manufacturing & Delivery to Site (Remain Heat Exch.) SS Clad, Solid SS & Brass Exchanger PM3212
Ordering / LOI ISsue
PM3232
Part 1 : Manufacturing & Delivery to Site (TS2, TS 5 )
PM3222
Part 2 :Manufacturing & Delivery to Site (Remain Heat Exch.) Helix heat exchanger PM3172
Ordering / LOI ISsue
PM3182
Manufacturing & Delivery to Site (Remain Heat Exch.)
Remaining Work
26 290 Tower Internals
264
PM3022
Actual Work
Towers (CS, CS+Clad, Site Joint)
316
Critical Remaining Work Milestone
14 250 408
Heat Exchanger
408
CS & LAS Heat Exchanger
20 240 305 SS Clad, Solid SS & Brass Exchanger
390 20 240 290
Helix heat exchanger
320 15 290
Page 22 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
Air Cooler
3
4
5
6
7
395
PM2922
Ordering / LOI ISsue
PM2942
Part 1. Manufacturing & Delivery to Site ( AIR COOLER 101-A-101 A~D , 101-A-102 A ~D) Part 2. Manufacturing & Delivery to Site (Remaining)
PM2932
2
Big Vessels (More than 2m Dia)
290 300 Big Vessels (More than 2m Dia)
384
Ordering / LOI Issue
PM2832
Part 1 : Manufacturing & Delivery to Site (TS2, TS 5 )
250
PM2812
Part 2 :Manufacturing & Delivery to Site (Remain Vessel)
290
15
Small Vessels (Less than 2m Dia)
384
PM3132
Ordering / LOI Issue
PM3152
Part 1 : Manufacturing & Delivery to Site (TS2, TS 5 )
250
PM3142
Part 2 :Manufacturing & Delivery to Site (Remain Vessel)
290
15
Rotating Equipments
329
Rotating Equipments
Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR PDT 329+ Quench Pump, RCO PM3272
Ordering / LOI ISsue
PM3282
Manufacturing & Delivery to Site
Centrifugal Pumps Remaining All (API) PM3002
Ordering / LOI ISsue
PM3012
Manufacturing & Delivery to Site
High speed Centrifugal Pumps (SUNDYNE) PM3292
Actual Work Remaining Work
Ordering / LOI ISsue
Critical Remaining Work Milestone
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Air Cooler
14
PM2802
Small Vessels ( Less than 2m Dia)
8
Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR PDT +
25 304 Centrifugal Pumps Remaining All (API)
273 15 258
High speed Centrifugal Pumps (SUNDYNE)
273 15
Page 23 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
PM3302
Manufacturing & Delivery to Site
Positive dispacement Pumps (Diaphragm) PM3252
Ordering / LOI ISsue
PM3262
Manufacturing & Delivery to Site
Positive dispacement Pumps (Rotary) PM3312
Ordering / LOI ISsue
PM3322
Manufacturing & Delivery to Site
Centrifugal Pumps (NON-API) Ordering / LOI ISsue
PM3342
Manufacturing & Delivery to Site
Reciprocating Air Compressor
4
5
6
7
Ordering / LOI ISsue
PM3362
Manufacturing & Delivery to Site
Purge Oil Mist System Ordering / LOI ISsue
PM3532
Manufacturing & Delivery to Site
15 250 Positive dispacement Pumps (Rotary)
265 20 245
Centrifugal Pumps (NON-API)
15 258 Reciprocating Air Compressor
15 255 Purge Oil Mist System
14 255 Package
355
Package Desalter Package
Desalter Package
313
PM3062
Ordering / LOI ISsue
PM3072
Manufacturing & Delivery to Site
Ejector
8 305 Ejector
317
Critical Remaining Work Milestone
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Positive dispacement Pumps (Diaphragm)
265
269
PM3522
8
258
270
PM3352
Remaining Work
3
273
PM3332
Actual Work
2
Page 24 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
PM2702
Ordering / LOI ISsue
PM2712
Manufacturing & Delivery to Site
Others Ordering / LOI ISsue
PM3552
Manufacturing & Delivery to Site
Fire Fighting Equipment / Clean Agent/ Others PM1622
Ordering / LOI ISsue
PM1632
Manufacturing & Delivery to Site
PM1662
Ordering / LOI ISsue
PM1672
Manufacturing Ex. Work
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
12 305 Others
20 255 Fire Fighting Equipment / Clean Agent/ Others
195 10 185
HVAC Package
10 195 Piping
213
Piping U/G Piping Material 1st
U/G Piping Material 1st
129
PM1702
Ordering / LOI ISsue
PM1712
Manufacturing & Delivery to Site (Part Delivery)
60
PM1722
Manufacturing & Delivery to Site (Balance)
50
A/G Piping Material 1st
6
A/G Piping Material 1st
162
PP135
Pipe/ Fittings/ Flanges / Valves A/G 1st- LOI
PP140
Pipe/ Fittings/ Flanges / Valves A/G 1st-Manufacturing & Delivery to Site (Part Delivery) Pipe/ Fittings/ Flanges / Valves A/G 1st-Manufacturing & Delivery to Site (Complete Delivery)
7 75 90 Electrical
381
Electrical
Remaining Work
4
205
HVAC Package
Actual Work
3
275
PM3542
PP150
2
Critical Remaining Work Milestone
Page 25 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
EHV & HV Switchgear (ICOG) Ordering / LOI ISsue
PM1932
Manufacturing & Delivery to Site
Transformers (Power, Lighting, Distribuition) PM1882
Ordering / LOI ISsue
PM1892
Manufacturing & Delivery to Site
66 KV GIS (Gas Insulated S/gear) Eqpt PM1842
Ordering / LOI ISsue
PM1852
Manufacturing & Delivery to Site
415V MV Switchgear
4
5
6
7
Ordering / LOI ISsue
PM1832
Manufacturing & Delivery to Site
EHV, HV & MV Cables Ordering / LOI ISsue
PM3382
Manufacturing & Delivery to Site (Progressivley Delivered)
AC UPS
Transformers (Power, Lighting, Distribuition)
198 18 180
66 KV GIS (Gas Insulated S/gear) Eqpt
218 18 200
415V MV Switchgear
20 200 EHV, HV & MV Cables
60 180 AC UPS
207
PM3412
Ordering / LOI ISsue
PM3422
Manufacturing & Delivery to Site
AC & DC UPS and Battery Charger PM3392
Ordering / LOI ISsue
PM3402
Manufacturing & Delivery to Site
Critical Remaining Work Milestone
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 EHV & HV Switchgear (ICOG)
200
187
PM3372
8
18
207
PM1822
Remaining Work
3
218
PM1922
Actual Work
2
60 200 AC & DC UPS and Battery Charger
207 60 200
Page 26 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
Cathodic Protection System Ordering / LOI ISsue
PM3482
Manufacturing & Delivery to Site
5
6
7
Control Valves
230
PM2162
Ordering / LOI ISsue
PM2172
Manufacturing & Delivery to Site
On-Off/ Self Regulating Valves Ordering / LOI ISsue
PM2152
Manufacturing & Delivery to Site
Pressure Safety Valves
Control Valves
20 210 On-Off/ Self Regulating Valves
20 210 Pressure Safety Valves
230
PM2122
Ordering / LOI ISsue
PM2132
Manufacturing & Delivery to Site
Analyzer System
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Cathodic Protection System
Instrumentation
230
PM2142
8
200 498
20 210 Analyzer System
370
PM2102
Ordering / LOI ISsue
PM2112
Manufacturing & Delivery to Site
In-line Instruments
20 350 In-line Instruments
265
PM2042
Ordering / LOI ISsue
PM2052
Manufacturing & Delivery to Site
Field Instruments
Remaining Work
4
30
Instrumentation
Actual Work
3
237
PM3472
PM2022
2
15 250 Field Instruments
265 Ordering / LOI ISsue
Critical Remaining Work Milestone
15
Page 27 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
PM2032
Manufacturing & Delivery to Site
Instrument Cable Duct/Trays/ Fittings / Other remain PM2062
Ordering / LOI ISsue (Final)
PM2072
Manufacturing and Delivery to Site (Final)
PM2002
Ordering / LOI ISsue
PM2012
Manufacturing and Delivery to Site
Temporary Construction Facility ( Overall)
Piling Work
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
250 Instrument Cable Duct/Trays/ Fittings / Other remain
200 10 120 20 120
Construction Temporary Facility
140
52
PILE1000
Piling Work Subcontract (LOI within 1week from EDC)
14
PILE1010
Piling Contractor Mobilization
45
Civil Works
78
A6010
Civil / Bldg. Work Subcontract(RFQ,TBE,CBE,Ordering)
26
A6020
Civil/Bldg. Contractor Mobilization
52
Mechanical and PIping Work Subcontractor
Subcontracting & Mobilization
Piping / Mech Work Subcontract (RFQ,TBE,CBE,Ordering)
30
CONPIP1025
Piping /Mech Work Subcontract Mobilization
30
E&I
Piling Work
Civil Works
Mechanical and PIping Work Subcontractor
60
CONPIP1000
Remaining Work
5
380
Subcontracting & Mobilization
Actual Work
4
140
Temporary Facility
A6230
3
782
Construction
A5920
2
E&I
105 Electrical Work Subcontract (RFQ,TBE,CBE,Ordering)
Critical Remaining Work Milestone
60
Page 28 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A6240
Electrical Work Subcontract Mobilization
Insulation A6290 A6300
Insulation, Painting & Fireproofing Work Subcontract (RFQ,TBE,CBE,Ordering) Insulation, Painting & Fireproofing Work Subcontract Mobilization
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Insulation
60 Steel Structure Fabrication Work
426
A5200
Shop Drawing
250
A5250
Shop Drawing Approv al
250
A5210
Shop Fabrication and Delivery to Site
330
26
AG Piping Fabrication Work
330
AG Piping Fabrication Work AG Piping : Shop Fabrication
330 Major Ar ea
670
Major Area Area 1. CDU Column
Area 1. CDU Column
555
PILE1030
CDU Column Fdn. Piling
30
A6040
CDU Column-Equip. Fdn.
140
A6050
Erection of CDU Column (in-situ circumferential seam included) AG Piping Erection
Area 2. Building
37 210 Area 2. Building
597
66 Kv SubStation Building (Building Size 110 M x 31 M ) PILE1040
Substation Building Fdn. Piling
CC500
1st Part Sub-station ( Excavation for Fdn , Pile treatment upto 1st Floor Slab Casting )
Remaining Work
5
60
RFQ/TBE/CBE / PO Issue
Actual Work
4
45
A5220
A6060
3
120
Steel Structure Fabrication Work
CONPIP1110
2
Critical Remaining Work Milestone
66 Kv SubStation Building (Building Size 110 M x 31 M )
590 35 170
Page 29 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
CC510 CC840
2nd Part Sub-station ( Excavation for Fdn , Pile treatment upto 1st Floor Slab Casting plus stair case upto top level ) Finishing Item
CC740
Sub-station Bldg Ready for Panel Installation
CC820
Substation Equipment Installation
186
CC760
Substation bldg HVAC installation work , Commissioning and Performance Test Substation Energization
205
CC830
Sattelite Rack Room Building (Building Size 35 M x 36 M )
35
CC580
SRR building Fdn
CC590
SRR building Columns/ Blast-proof Outer Walls
45
CC595
SRR building Roof Slab concreting complete
35
CC610
SRR building Masonry Work/ Plastering
60
CC615
SRR building Flooring/ Tiling complete
75
CC605
SRR bldg Door/ Window Fabrication
CC620
SRR bldg Door/ Window/ Carpentry work
50
CC635
SRR bldg False Flooring/ Ceiling
50
CC675
SRR bldg Final Paint/ Finish work/ Stone Clad ( if Sated in ITB) SRR bldg Ready for Instrument Eqpt /Panel Installation
80
Remaining Work
Critical Remaining Work Milestone
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Sub-station Bldg Ready for Panel Installation
Sattelite Rack Room Building (Building Size 35 M x 36 M )
597
SRR building Excavation for Fdn
Actual Work
6
26
CC570
CC655
5
0
45
SRR Building Equipments / Panels Installation ( Including DCS by Others) SRR bldg HVAC installation work , Commissioning and Performance Test
4
208
SRR Building Fdn. Piling
CC695
3
190
PILE1060
CC645
2
104
100
SRR bldg Ready for Instrument Eqpt /Panel Installation
0 150 180
Page 30 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
CC685
Roof Treatment
60
CC705
DCS Power On
0
Area 3. Piperack Main Pipe Rack Fdn. Piling Works
A6080
Main Piperack Fdn. Work
130
A6070
Main Pipe Rack : RCC Precast Works
155
A6090
Main Piperack RCC Precast Erection
210
A6460
AG Piping Erection
350
A6440
Steel Str. Erection Work
260
A6450
Equipment Erection ( AIR COOLER 101-A- 101 A~D , 101-A-102 A ~D) Area 4. VDU Column PILE1090
VDU Column Fdn. Piling
A6100
VDU Column-Equip. Fdn. + Superstructure (~ 5M Duration Considered) Erection of VDU Column (in-situ circumferential seam included) AG Pipe Erection
CONHTR1065
Area 5. Tech. Structures
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
DCS Power On Area 3. Piperack
85
26 Area 4. VDU Column
571 30 180 52 210
Area 5. Tech. Structures TS # 2
530
PILE1070
Tech. Structures (# 2) Fdn. Piling
45
A6120
Tech Str.-2 FDN. Work
60
A6360
Steel Str. Erection Work TS # 2
A6390
Equipment Erection
Remaining Work
4
611
TS # 2
Actual Work
3
475
PILE1050
CONHTR1055
2
Critical Remaining Work Milestone
170 90
Page 31 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A6400
Stair, Ladder, Platform, Grating, Handrail etc.
A6470
AG Pipe Erection
TS # 5
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TS # 5
551
A6380
Tech Str.-5 FDN Work and Concrete Works
A6640
Steel Str. Erection Work TS # 5 (Part 1)
80
A6660
Equipment Erection - Part 1
80
A6630
AG Pipe Erection
300
A6410
Stair, Ladder, Platform, Grating, Handrail etc.
220
A6370
Steel Str. Erection Work TS # 5 (Part 2)
148
A6430
Equipment Erection - Part 2
130
TS Others (1,3,4,6,7)
50 170
TS Others (1,3,4,6,7)
562
PILE1120
Tech. Structures (# 1,3,4,6,7) Fdn. Piling
A7690
Tech Str.-(# 1,3,4,6,7) FDN Work.
100
A7700
Steel Str. Erection Work TS # (# 1,3,4,6,7)
150
A7710
Equipment Erection
100
A7720
AG Pipe Erection
200
A7730
Stair, Ladder, Platform, Grating, Handrail etc.
Area 6. Heaters Heater (CDU Heater : 2 Nos; VDU Heater : 1 Nos; Common Stack ~85 Meter)
Remaining Work
4
250
Tech. Structures (# 5) Fdn. Piling
Actual Work
3
90
PILE1080
PILE1100
2
Heater Fdn. Piling
Critical Remaining Work Milestone
70
90 535
Area 6. Heaters
535
Heater (CDU Heater : 2 Nos; VDU Heater : 1 Nos; Common S
80
Page 32 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
A6110
Heater-Equip. Fdn.
A6130
Heater Erection
460
A6180
Heater Piping Erection Work
245
Area 7. LPGTU Area
4
5
6
7
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Area 7. LPGTU Area
532
Piling Work
A7760
Fdn Work
200
A7780
Steel Str. Erection Work
150
A7800
Equipment Erection
A7790
AG Pipe Erection Work
60
Area 8. FGTU Area
90 200 Area 8. FGTU Area
449
A7810
Piling Work
A7820
Fdn Work
A7850
Equipment Erection
A7830
Steel Str. Erection Work
150
A7840
AG Pipe Erection Work
200
60 150
Area 9. Desalter
90
Area 9. Desalter
258
A7870
Civil Works FDN
A7880
Equipment Erection
A7890
AG Piping Work
Common Piping Work (Common)
Remaining Work
3
90
A7750
Actual Work
2
Critical Remaining Work Milestone
104 48 104 707
Common
657
Piping Work (Common)
Page 33 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT. FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA. (BIDDING DOCUMENT NO.: AKR/B224-101-PM-T-7201/2001) PROJECT SCHEDULE Activity ID
Activity Name
Original Duration -1 1
CONPIP1050
UG Pipe : Fabrication and Laying
250
CONPIP1100
AG Pipe: Hydrotest & Reinstatement
300
Electrical Work A6150
Electrical Tray & Cabling Work
270
A6220
Inline and Field Instrument Installation Work
230
Insulation , Painting & Fireproofing Execution of Insulation, Painting & Fireproofing Work
8
Month 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Electrical Work
Instrument Work
Insulation , Painting & Fireproofing
402
250
PRECOM1050 PRECOM1025
Loop Check & Function Check
149
PRECOM1150
Mechanical Run Test for Rotating Machines
70
PRECOM1075
Precom Works (Others; Boil out , Steam Blowing , Chemical loading etc. ) Mechanical Completion
75
Commissioning
Precommissioning Overall
45
0
Mechanical Completion
52
Commissioning
PRECOM1085
Heater Refractory Dryout
40
A6350
Commissioning
60
Post Commissioning Service & PGTR
Remaining Work
7
402
Flushing/Blowing and Reinstatement of Process and Utility Piping ( Initially using portable Compressor on HIRE) Motor Solo Run
Actual Work
6
268
Precommissioning Overall
A7900
5
338 Instrument Tray & Cabling Work
PRECOM1095
4
270
A7860
PRECOM1000
3
270
Instrument Work
A6310
2
6 Months Post Commissioning assistance Service and PGTR
Critical Remaining Work Milestone
158 158
Page 34 of 34
Date 01-Jun-19
Revision ISSUE FOR PROPOSAL
Checked UCY
Approved RC