Gobierno Regional De Ucayali: Gerencia Regional De Infraestructura Sub Gerencia De Obras

  • Uploaded by: Larry Branny Pezo Perez
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Gobierno Regional De Ucayali: Gerencia Regional De Infraestructura Sub Gerencia De Obras as PDF for free.

More details

  • Words: 18,324
  • Pages: 28
Loading documents preview...
GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” INFORME Nº 171-2020-GRU-GRI-SGO/HKBC A

:

Ing. Jesús Augusto Málaga Poma Sub Gerente de Obras – GOREU

DE

:

Arq. Hansberg K. Benites Castañeda Especialista para Implementación de Mobililario Administrativo y Equipos Complementarios en el marco del proyecto: Saldo de Obra “Mejoramiento de la Capacidad Resolutiva del Establecimiento de Salud del Ámbito de Influencia de la Provincia de Atalaya, Región Ucayali”

ASUNTO

:

SOBRE SOLICITUD DE AMPLIACION EXCEPCIONAL DE PLAZO Obra: “Mejoramiento de los Servicios de Salud del Centro de Salud Campo Verde, del distrito de Campo Verde, provincia de Coronel Portillo, departamento de Ucayali - Código Unificado Nº 2340077"

REF

:

(1) Exp. N° 00641623; Reg. Doc. N° 00936350 (2) CARTA N° 023-2020-CR, de fecha 14-07-2020.

FECHA

:

Pucallpa, 24 de Julio del 2020.

Reg. 00939474

Documento:

Es grato dirigirme a Ud. Para saludarle y a la vez hacer de su conocimiento que mediante documentos de la referencia (1 y 2), el contratista CONSORCIO RENOVACION remite la solicitud de Ampliación Excepcional de Plazo por Adecuación COVI-19, ante el cual debo de manifestar lo siguiente: 1. DATOS GENERALES:  

EJECUCION DE OBRA ENTIDAD CONTRATANTE PROCESO DE SELECCIÓN

                             

SISTEMA DE CONTRATACION : CONTRATO DE OBRA : MONTO DE INVERSION : CONTRATISTA : REPRESENTANTE LEGAL : PLAZO DE EJECUCION DE OBRA : RESIDENTE DE OBRA : FIRMA DEL CONTRATO ACTA DE ENTREGA DE TERRENO INICIO DE OBRA FECHA TERMINO CONTRACTUAL AMPLIACION DE PLAZO Nº 01 RESOLUCION DE AMPLIACION DE PLAZO Nº 01 AMPLIACION DE PLAZO Nº 02 RESOLUCION DE AMPLIACION DE PLAZO Nº 02 AMPLIACION DE PLAZO Nº 03 RESOLUCION DE AMPLIACION DE PLAZO Nº 03 AMPLIACION DE PLAZO Nº 04 RESOLUCION DE AMPLIACION DE PLAZO Nº 04 AMPLIACION DE PLAZO Nº 05 RESOLUCION DE AMPLIACION DE PLAZO Nº 05 AMPLIACION DE PLAZO Nº 06 RESOLUCION DE AMPLIACION DE PLAZO Nº 06 AMPLIACION DE PLAZO Nº 07 RESOLUCION DE AMPLIACION DE PLAZO Nº 07 AMPLIACION DE PLAZO Nº 08 RESOLUCION DE AMPLIACION DE PLAZO Nº 08 AMPLIACION DE PLAZO Nº 09 RESOLUCION DE AMPLIACION DE PLAZO Nº 09 AMPLIACION DE PLAZO Nº 10

: :

Gobierno Regional de Ucayali ADJUDICACION SIMPLIFICADA Nº 004-2019-GRUGR-CS Derivada de la LICITACION PUBLICA N° 0172018-GRU-GR-CS. A SUMA ALZADA N° 088-2019-GRU-GGR S/. 32’837,882.03 (Incluye IGV) CONSORCIO RENOVACION CARLOS ALFONSO PEREYRA CASTRO 650 DIAS CALENDARIO ING. CHRISTIAN MURO LINARES : 20/06/2019 : 03/09/2019 : 04/09/2019 : 14/06/2021 : 03 DIAS CALENDARIOS : RGGR N° 289-2019-GRU-GGR : 00 DIAS CALENDARIOS : IMPROCEDENTE : 03 DIAS CALENDARIO : RGGR N° 325-2019-GRU-GGR : 04 DIAS CALENDARIO : RGGR N° 329-2019-GRU-GGR : 01 DIA CALENDARIO : RGGR N° 345-2019-GRU-GGR : 01 DIA CALENDARIO : RGGR N° 364-2020-GRU-GGR : 01 DIA CALENDARIOS : RGGR N° 370-2019-GRU-GGR : 01 DIA CALENDARIO : RGGR N° 373-2019-GRU-GGR : 01 DIA CALENDARIO : RGGR N° 394-2019-GRU-GGR : 01 DIA CALENDARIO

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”         

RESOLUCION DE AMPLIACION DE PLAZO Nº 10 AMPLIACION DE PLAZO Nº 11 RESOLUCION DE AMPLIACION DE PLAZO Nº 11 AMPLIACION DE PLAZO Nº 12 RESOLUCION DE AMPLIACION DE PLAZO Nº 12 NUEVO FIN PLAZO CONTRACTUAL ADELANTO DIRECTO (10%) ADELANTO DE MATERIALES (17.16%) ESTADO ACTUAL DE LA OBRA DESDE EL 16/03/2020.

 

SUPERVISION DE OBRA ENTIDAD CONTRATANTE PROCESO DE SELECCIÓN

: :

         

SISTEMA DE CONTRATACION CONTRATO DE SUPERVISION CONTRATISTA REPRESENTANTE LEGAL MONTO DE INVERSION FECHA DE CONTRATO EJECUCION DE SUPERVISION INICIO DE SUPERVISION ADELANTO DIRECTO JEFE DE SUPERVISION

: : : : : : : : : :

: : : : : : : : :

RGGR N° 417-2019-GRU-GGR 00 DIAS CALENDARIOS RGGR N° 006-2020-GRU-GGR 28 DIAS CALENDARIOS RGGR N° 057-2020-GRU-GGR 24/07/2021 3’283,399.83 5’633,909.05 PLAZO DE EJECUCION PARALIZADO

Gobierno Regional de Ucayali ADJUDICACION SIMPLIFICADA N° 008-2019-GRU-GR-CS Derivada del CONCURSO PUBLICO Nº 015-2018-GRU-GRCS-1RA CONVOCATORIA A SUMA ALZADA N° 0108-2019-GRU-GGR CONSORCIO SUPERVISOR CAMPO VERDE Sra. KATTERINE RIVERA ALFARO S/. 1’290,000.00 (Exon. IGV) 12/08/2019. 680 DIAS CALENDARIO 04/09/2019 S/. 0.00 Arq. WILFREDO YVAN CASTILLO QUEZADA – CAP Nº 7361.

2. BASE LEGAL: 

Mediante Decreto Supremo N° 044-2020-PCM, publicado el 15.03.20, se declara el Estado de Emergencia Sanitaria Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del COVID-19, habiendo prorrogado posteriormente dicho estado de emergencia mediante sucesivos mandatos normativos, hasta el 30 de junio 2020.



Mediante Decreto Legislativo N° 1486, publicado el 10.05.2020, se establece disposiciones para mejorar y optimizar la ejecución de las inversiones públicas. La Segunda Disposición Complementaria Transitoria del Decreto Legislativo contiene reglas importantes para el reinicio de obras públicas, las cuales se encuentran paralizadas por la declaratoria de Estado de Emergencia Nacional (cuarentena).



Mediante Decreto Supremo N° 080-2020-PCM, publicado el 02.05.20, se aprueba la reanudación de actividades económicas en forma gradual y progresiva dentro del marco de la declaratoria de Emergencia Sanitaria Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del COVID19.



Con fecha 19 de mayo, OSCE expidió la Directiva N° 005-2020-OSCE/CD, con la finalidad de dar los Alcances y disposiciones para la Reactivación de Obras Públicas y contratos de supervisión, en el marco de la segunda Disposición Complementaria Transitoria del Decreto Legislativo N° 1486.



Mediante Decreto Supremo N° 101-2020-PCM, publicado el 04.06.2020, se aprueba la Fase 2 de la Reanudación de Actividades Económicas dentro del marco de la declaratoria de Emergencia Sanitaria Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del COVID-19, y modifica el Decreto Supremo N° 080-20202-PCM.



Mediante Decreto Supremo N° 103-2020-PCM, publicado el 07.06.2020, se modifica el numeral 3.3 del artículo 3 del Decreto Supremo 080-2020-PCM el cual señala que, en los departamentos y provincias de alto riesgo, el inicio de actividades en la Fase 2 será determinada mediante Resolución Ministerial del Sector correspondiente.



Mediante Resolución Ministerial Nº 480-2020-MINSA, publicada en fecha 19.06.2020, el Ministerio de Salud resuelve determinar el inicio de las actividades de construcción, asociados a los proyectos de inversión

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”



pública priorizados del sector salud, de diversos departamentos en el cual se considera el departamento de Ucayali. Mediante Decreto Supremo N° 117-2020-PCM, publicado el 30.06.2020, decreta a través de las DISPOSICIONES COMPLEMENTARIAS FINALES - Primera Disposición para la reanudación de actividades - numeral 4., que señala: “A partir de la vigencia del presente Decreto Supremo, se encuentra autorizado el inicio de las fases 1 y 2 de Reanudación de Actividades a Nivel Nacional ”; Además, la DISPOSICION COMPLEMENTARIA DEROGATORIA - Única. - Derogación del artículo 3 del Decreto Supremo Nº 080-2020-PCM y del numeral 2.2 del artículo 2 del Decreto Supremo Nº 110-2020PCM.

3. ANTECEDENTES: Con fecha 03 de julio del 2020, mediante Carta Nº 563-2020-GRU-GRI-SGO se NOTIFICA a CONSORCIO RENOVACION en el marco de las normativas arriba señaladas, iniciar el procedimiento señalado en la Segunda Disposición Complementaria Transitoria del Decreto legislativo N°1486 y la Directiva N° 005-2020OSCE/CD, debiendo presentar dentro de los 15 días calendarios computarizados a partir del día 01.07.2020, la siguiente información:        



Constancia de Registro SISCOVID y “Plan para la vigilancia, prevención y control de COVID-19 en el trabajo” registrado. Cuantificación de la ampliación de plazo contractual, basada en la ruta crítica de la obra. Nuevo cronograma de ejecución, que incluye la fecha de inicio o reinicio del plazo de ejecución, según corresponda. Programa de ejecución de obra (CPM). Calendario de avance de obra actualizado. Nuevo calendario de adquisición de materiales y de utilización de equipos, teniendo en cuenta las medidas del sector competente. Plan de seguridad y salud para los trabajadores actualizado. Propuesta de reemplazo de personal clave, cuando se identifique la imposibilidad de este para continuar prestando servicios por razones de aislamiento social obligatorio o medida similar. El personal clave de reemplazo debe cumplir con los requisitos establecidos en las bases del procedimiento de selección que originaron la relación contractual. Otros documentos señalados en la Directiva N° 005-2020-OSCE/CD.

Con fecha 14 de julio del 2020 mediante CARTA N° 023-2020-CR, el CONSORCIO RENOVACION remite la documentación referida a la Solicitud de Ampliación Excepcional de Plazo, la misma que se encuentra amparada en el Decreto legislativo N°1486 y la Directiva N° 005-2020-OSCE/CD. 4. ANALISIS: 4.1 En el transcurso de la ejecución de la Obra el Gobierno Central decretó la Declaración de Estado de Emergencia Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del brote del COVID-19, ello a partir del 16 de marzo 2020, la cual se ha prorrogado hasta el 30 de junio 2020. Así también, no habiéndose hasta la el 30.06.2020 el Ministerio de Salud como lo hizo el 19.06.2020 a través de la Resolución Ministerial Nº 408-2020MINSA en la cual determino el inicio de las actividades de construcción para el Hospital Regional de Pucallpa y el Hospital de Atalaya. Es que mediante, Decreto Supremo N° 117-2020-PCM, publicado el 30.06.2020, decreta a través de las DISPOSICIONES COMPLEMENTARIAS FINALES - Primera Disposición para la reanudación de actividades - numeral 4., que señala: “A partir de la vigencia del presente Decreto Supremo, se encuentra autorizado el inicio de las fases 1 y 2 de Reanudación de Actividades a Nivel Nacional ”; Además, la DISPOSICION COMPLEMENTARIA DEROGATORIA - Única. - Derogación del artículo 3 del Decreto Supremo Nº 080-2020-PCM y del numeral 2.2 del artículo 2 del Decreto Supremo Nº 110-2020-PCM. 4.2 Por lo tanto, el inicio del cómputo de plazo para la presentación de la ampliación excepcional de plazo, en el marco de la reactivación de las obras publicas según la Segunda Disposición Complementaria Transitoria del Decreto Legislativo N° 1486, empezaría a regir desde la entrada en vigencia del Decreto Supremo N° 117-2020-PCM, ósea el 01 de julio del 2020, cumpliendo se de esta manera lo contemplado en la Directiva 005-2020-OSCE/CD.

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Extraído de Directiva 005-2020-OSCE/CD

4.3 Mediante Decreto Supremo 044-2020-PCM. Publicada el 15/03/2020. Se decreta: “(…) Artículo 1. – Declaración de Estado de Emergencia Nacional Declárese el Estado de Emergencia Nacional por el plazo de quince (15) días calendario, y dispóngase el aislamiento social obligatorio (cuarentena), por las graves circunstancias que afectan la vida de la Nación a consecuencia del brote del COVID-19 (…)” 4.4 Mediante Decreto Supremo 051-2020-PCM. Publicada el 27/03/2020. Se decreta: “(…) Artículo 1. – Prórroga de Estado de Emergencia Nacional Prorrogar el Estado de Emergencia Nacional declarado mediante Decreto Supremo N° 044-2020PCM y precisado por los Decretos Supremos N° 045-2020-PCM y N° 046-2020-PCM, por el término de trece (13) días calendario, a partir del 31 de marzo de 2020. (…)” 4.5 Decreto Supremo 064-2020-PCM. Publicada el 10/04/2020. Se decreta: “(…) Artículo 1. – Prórroga de Estado de Emergencia Nacional Prorrogar el Estado de Emergencia Nacional declarado mediante Decreto Supremo N° 044-2020PCM y ampliado temporalmente mediante el Decreto Supremo N° 051-2020-PCM y precisado por los Decretos Supremos N° 045-2020-PCM, N° 046-2020-PCM, N° 051-2020-PCM, N° 053-2020-PCM, N° 0572020-PCM, N° 058-2020-PCM, y N° 061-2020-PCM y N° 063-2020-PCM, por el término de catorce (14) días calendario, a partir del 13 de abril de 2020 hasta el 26 de abril del 2020. (…)” 4.6 Decreto Supremo 075-2020-PCM. Publicada el 10/04/2020. Se decreta: “(…) Artículo 1. – Prórroga de Estado de Emergencia Nacional Prorrogar el Estado de Emergencia Nacional declarado mediante Decreto Supremo N° 044-2020PCM, ampliado temporalmente mediante los Decretos Supremos N° 051-2020-PCM y N° 064-2020-PCM; y precisado o modificado por los Decretos Supremos N° 045-2020-PCM, N° 046-2020-PCM, N° 051-2020PCM, N° 053-2020-PCM, N° 057-2020-PCM, N° 058-2020-PCM, N° 061-2020-PCM, N° 063-2020-PCM, N° 064-2020-PCM, N° 068-2020-PCM y N° 072-2020-PCM por el término de catorce (14) días calendario, a partir del 27 de abril de 2020 hasta el 10 de mayo del 2020. (…)” 4.7 Decreto Supremo 083-2020-PCM. Publicada el 10/05/2020. Se decreta: “(…) Artículo 1. – Prórroga de Estado de Emergencia Nacional

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” Prorrogar el Estado de Emergencia Nacional declarado mediante Decreto Supremo N° 044-2020PCM, ampliado temporalmente mediante los Decretos Supremos N° 051-2020-PCM, N° 064-2020-PCM y N° 075-2020-PCM; y precisado o modificado por los Decretos Supremos N° 045-2020-PCM, N° 046-2020PCM, N° 051-2020-PCM, N° 053-2020-PCM, N° 057-2020-PCM, N° 058-2020-PCM, N° 061-2020-PCM, N° 063-2020-PCM, N° 064-2020-PCM, N° 068-2020-PCM y N° 072-2020-PCM por el término de catorce (14) días calendario, a partir del lunes 11 de mayo de 2020 hasta el domingo 24 de mayo del 2020. (…)” 4.8 Decreto Supremo 094-2020-PCM. Publicada el 23/05/2020. Se decreta: “(…) Artículo 2. – Prórroga de Estado de Emergencia Nacional Prorrogar el Estado de Emergencia Nacional declarado mediante Decreto Supremo N° 044-2020PCM, ampliado temporalmente mediante los Decretos Supremos N° 051-2020-PCM, N° 064-2020-PCM, N° 075-2020-PCM y 083-2020-PCM; y precisado o modificado por los Decretos Supremos N° 045-2020-PCM, N° 046-2020-PCM, N° 051-2020-PCM, N° 053-2020-PCM, N° 057-2020-PCM, N° 058-2020-PCM, N° 0612020-PCM, N° 063-2020-PCM, N° 064-2020-PCM, N° 068-2020-PCM, N° 072-2020-PCM y N° 083-2020PCM, a partir del lunes 25 de mayo de 2020 hasta el martes 30 de junio de 2020; dispóngase el aislamiento social obligatorio (cuarentena), por las graves circunstancias que afectan la vida de la Nación a consecuencia del COVID-19. Durante la presente prórroga del Estado de Emergencia Nacional queda restringido el ejercicio de los derechos constitucionales relativos a la libertad y la seguridad personales, la inviolabilidad del domicilio, y la libertad de reunión y de tránsito en el territorio comprendidos en los incisos 9, 11 y 12 del artículo 2 y en el inciso 24, apartado f del mismo artículo de la Constitución Política del Perú (…)” 4.9 Mediante la entrada en vigencia del Decreto Supremo N° 117-2020-PCM, publicado el 30.06.2020, se decreta a través de las DISPOSICIONES COMPLEMENTARIAS FINALES - Primera Disposición para la reanudación de actividades - numeral 4., que señala: “A partir de la vigencia del presente Decreto Supremo, se encuentra autorizado el inicio de las fases 1 y 2 de Reanudación de Actividades a Nivel Nacional ”; Además, la DISPOSICION COMPLEMENTARIA DEROGATORIA - Única. - Derogación del artículo 3 del Decreto Supremo Nº 080-2020-PCM y del numeral 2.2 del artículo 2 del Decreto Supremo Nº 110-2020-PCM. 4.10 Mediante Directiva N° 005-2020-OSCE/CD, de fecha 19 de mayo de 2020, el Organismo Supervisor de las Contrataciones con el Estado reguló los “Alcances y Disposiciones para la Reactivación de Obras Públicas y Contratos de Supervisión, en el marco de la segunda disposición complementaria transitoria del decreto legislativo N° 1486”. 4.11 De acuerdo a las condiciones señaladas en el artículo 41 de la Ley de Contrataciones del Estado, aprobada por Decreto Legislativo N° 1017 y sus modificatorias, el Decreto Legislativo N° 1486 y la Directiva N° 005-2020-OSCE/CD en el caso concreto, se verifica que “Estado de Emergencia Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del brote del COVID-19” modifica la Ruta Crítica del Programa de Ejecución de Obra. 4.12 Con fecha 16/03/2020, la Entidad notificó al contratista la Resolución Gerencial General Regional N° 0100-2020GRU-GGR, mediante el cual declara procedente la solicitud de Ampliación de Plazo N° 12 por VEINTIOCHO (28) días calendarios, llevando la fecha fin de obra al 24/07/2021. 4.13 Según DL 1486 y Directiva N° 005-2020-OSCE/CD: i) Impacto por Cuarentena – Paralización de infraestructura del Hospital. ii) Impacto de paralización por trámites administrativos, Removilización de personal y equipos, adecuación y adaptaciones de los ambientes de trabajo – Paralización de infraestructura del Hospital. iii) Impacto en plazo por ejecución de obra con rendimientos reducidos por las medidas de prevención y control COVID-19 – nuevas condiciones en ejecución de infraestructura del Centro de Salud. 4.14 Según lo indicado en el ítem 7.2.2 de la Directiva 005-2020-OSCE/CD, para poder plantear los cronogramas se debe considerar la situación real de avance; por tal motivo, el análisis de afectación se realizará tomando en cuenta la última extensión de plazo aprobada por la Entidad (AP 12 por 28 días calendarios)

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Extraído de Directiva 005-2020-OSCE/CD 4.15 SOBRE LOS PLAZOS SOLICITADOS EN LAS FASES I, II Y III: SOBRE LA CUANTIFICACIÓN DE LA AMPLIACIÓN EXCEPCIONAL DE PLAZO, Y COSTOS DE LA IMPLEMENTACIÓN DE LAS MEDIDAS PARA LA PREVENCIÓN Y CONTROL FRENTE A LA PROPAGACIÓN DEL COVID-19 DISPUESTAS POR LOS SECTORES COMPETENTES PARA LA REANUDACIÓN DE LOS TRABAJOS, de acuerdo al Decreto Legislativo 1486 y la Directiva N° 005-2020-OSCE/CD.

Fuente: Extraído de Directiva 005-2020-OSCE/CD I) Fase 1: EL IMPACTO EN EL PLAZO DE EJECUCIÓN PRODUCIDO POR LA PARALIZACIÓN DE OBRA QUE SE HUBIESE GENERADO A PARTIR DE LA DECLARATORIA DEL ESTADO DE EMERGENCIA NACIONAL – T1: Paralización. Ejecutor solicita 107 días calendario.  Con fecha 15 de marzo del 2020, se publicó el Decreto Supremo N° 044-2020-PCM, en el cual el Gobierno Nacional decretó el Estado de Emergencia Sanitaria Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del COVID-19, incluyendo días más tarde el toque de queda y prolongaciones de cuarentena siendo: 1° Prolongación: 16 de marzo hasta el 29 de marzo, 2° Prolongación: 30 de Marzo hasta el 12 de Abril, 3° Prolongación: 13 de Abril hasta el 26 de Abril, 4° Prolongación: 27 de Abril hasta el 10 de Mayo, 5° Prolongación: 11 de Mayo hasta el 24 de Mayo, y 6° Prolongación 25 de Mayo hasta el 30 de junio 2020.  En marco del Decreto Supremo N° 080-2020-PCM, que aprueba la reanudación de actividades económicas en forma gradual y progresiva dentro del marco de la declaratoria de Emergencia Sanitaria Nacional por las graves circunstancias que afectan la vida de la Nación a consecuencia del COVID-19; el Decreto Supremo Nº 101-2020-PCM que modifican el Decreto Supremo Nº 080-2020- PCM y que aprueba la Fase 2 de la Reanudación de Actividades Económicas; el Decreto Supremo Nº 103-2020-PCM que modifica el numeral 3.3 del artículo 3 del Decreto Supremo 080-2020-PCM el cual señala que en los departamentos y provincias de alto riesgo, el inicio de actividades en la Fase 2 será determinada mediante Resolución Ministerial del Sector correspondiente y el Decreto Supremo N° 117-2020-PCM, publicado el 30.06.2020, que decreta a través de las DISPOSICIONES COMPLEMENTARIAS FINALES Primera Disposición para la reanudación de actividades - numeral 4., que señala: “A partir de la vigencia del presente Decreto Supremo, se encuentra autorizado el inicio de las fases 1 y 2 de Reanudación de Actividades a Nivel Nacional”; Además, la DISPOSICION COMPLEMENTARIA DEROGATORIA - Única. - Derogación del artículo 3 del Decreto Supremo Nº 080-2020-PCM y del numeral 2.2 del artículo 2 del Decreto Supremo Nº 1102020-PCM.  Con la entrada en vigencia del Decreto Supremo N° 117-2020-PCM, ósea el 01 de julio del 2020 se inicia del cómputo de plazo para la presentación de la ampliación excepcional de plazo.  El Contratista solicita 107 días calendarios, esto en virtud a que lo suscitado por el estado de emergencia, son hechos de carácter excepcional que configura el “CASO DE FUERZA MAYOR”, estos no son previsibles por el gobierno local ni tampoco nacional; el D.S. Nº 0442020-PCM, tiene rango de Ley, pues ordena el aislamiento social obligatorio (cuarentena).  Por consiguiente, respecto al impacto en el plazo de ejecución producido por la paralización de obra que se hubiese generado a partir de la declaratoria del estado de emergencia Nacional contabilizada desde el 16 de marzo del 2020 hasta el 30 de junio del 2020, es Procedente la solicitud de Ampliación de Plazo por 107 días calendario. Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” DURANTE EL ESTADO DE EMERGENCIA D.S. Nº 044-2020-PCM hasta D.S. Nº 117-2020-PCM 16.03.2020

30.06.2020

107 d.c

II) Fase 2: Reactivación: EL IMPACTO EN PLAZO QUE PODRÍA SIGNIFICAR LA RE-MOVILIZACIÓN DE PERSONAL Y EQUIPOS, ASÍ COMO POR LAS ADECUACIONES Y ADAPTACIONES DE LOS AMBIENTES DE TRABAJO, EN CASO SEAN NECESARIAS – T2: Ejecutor Solicita 59 días calendario. (29 d.c. por presentación y aprobación de AEP + 30 d.c. por adecuación y adaptación de ambientes).  IMPACTO DE PARALIZACIÓN POR TRÁMITE ADMINISTRATIVO RELACIONADO AMPLIACIÓN EXCEPCIONAL DE PLAZO: Ejecutor solicita 29 días calendario.

A

LA

 Con la entrada en vigencia del Decreto Supremo N° 117-2020-PCM, ósea el 01 de julio del 2020 se empieza a computar el plazo para la presentación de la Ampliación Excepcional de Plazo.  Sobre la Presentación: El ejecutor debió presentar la Solicitud de Ampliación Excepcional de Plazo el 15 de julio del 2020; sin embargo, presento su solicitud el día 14 de julio del 2020 mediante Registro Nº 00936350 y Expediente Nº 641623.  Sobre la Aprobación: La Entidad inicio la evaluación el día 15 de julio del 2020 y tiene como plazo máximo para la comunicación del acto resolutivo hasta el día 29 de julio del 2020.

Fuente: Extraído de Directiva 005-2020-OSCE/CD  Por consiguiente, respecto al periodo de presentación y aprobación se tienen los plazos por trámites administrativos siguientes: Plazo para presentación de la AEP Plazo máximo para aprobación de AEP

: 14 días calendarios. (Desde el 01.07.2020) : 15 días calendarios. (Hasta el 29.07.2020)

 IMPACTO EN PLAZO POR REMOVILIZACIÓN DE PERSONAL Y EQUIPOS – ADECUACIÓN Y ADAPTACIONES DE LOS AMBIENTES DE TRABAJO: Ejecutor solicita 30 días calendario. a) Por Re movilización de personal y equipos.  El Contratista no especifica el plazo para el traslado; sin embargo, si señala que la incorporación del staff de profesionales, personal técnico /administrativo, teniendo en cuenta que provienen de la ciudad de Lima y otras provincias, se requiere 01 día calendario para dicha re movilización periodo q formara parte del plazo total. Es necesario precisar que solo se procederá al traslado de personal una vez realizada la prueba rápida tenga con resultado Negativo al COVID-19. Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” b) Por adecuación y adaptaciones de los ambientes de trabajo. El Contratista señala que se realizaran las siguientes actividades o tareas: 01

PLAN DE SEGURIDAD Y SALUD OCUPACIONAL COVID 19

01.01

OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES

01.01.01

CONSTRUCCIONES PROVISIONALES

01.01.01.01

CONSTRUCCION DE COMEDOR PROVISIONAL PARA COVID 19

01.01.01.02

CONSTRUCCION DE ZONA DE CONTROL DE DESINFECCION PARA COVID 19

01.01.01.03

CONSTRUCCION DE ZONA DE CONTROL PREVIO PARA COVID 19

01.01.01.04

CONSTRUCCION DE ZONA DE CONTROL DE VESTUARIOS PARA COVID 19

01.01.01.05

CONSTRUCCION DE ZONA DE DESCARGA DE MATERIALES - COVID 19

01.01.02

INSTALACIONES PROVISIONALES

01.01.02.01

INSTALACION DE APARATOS SANITARIOS - COVID 19

01.01.03

IMPLEMENTACION DE AREAS - COVID 19

01.01.03.01

IMPLEMENTACION DE COMEDOR PROVISIONAL PARA COVID 19

01.01.03.02

IMPLEMENTACION DE ZONA DE CONTROL PREVIO PARA COVID 19

01.01.03.03

IMPLEMENTACION DE ZONA DE CONTROL DE DESINFECCION PARA COVID 19

01.01.03.04

IMPLEMENTACION DE ZONA DE CONTROL DE VESTUARIOS PARA COVID 19

01.01.03.05

IMPLEMENTACION DE ZONA DE DESCARGA DE MATERIALES COVID 19

01.01.04

TRABAJOS PRELIMINARES

01.01.04.01

LIMPIEZA DEL TERRENO CON MAQUINARIA

01.01.05

TRANSPORTE DE MATERIALES Y EQUIPOS

01.01.05.01

TRANSPORTE DE EQUIPOS, MATERIALES Y HERRAMIENTAS - COVID 19

01.02

SEGURIDAD Y SALUD

01.02.01

IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE VIGILANCIA, PREVENCION Y CONTROL DE COVID-19 EN EL TRABAJO

01.02.01.01

EQUIPOS DE PROTECCION INDIVIDUAL - COVID 19

01.02.01.01.01

EQUIPOS DE PROTECCION PARA PERSONAL STAFF/ADMINISTRATIVOS

01.02.01.01.02

EQUIPOS DE PROTECCION PARA PERSONAL OBRERO

01.02.01.01.03

EQUIPOS DE PROTECCION PARA PERSONAL DE SEGURIDAD OCUPACIONAL

01.02.01.01.04 01.02.01.02

OTROS EQUIPOS DE PROTECCION PERSONAL PRUEBAS Y EXAMENES MEDICOS - COVID 19

01.02.01.02.01

SERVICIO DE PROTOCOLO DE REINGRESO LABORAL (INC. FICHAS, RAYOS X, PRUEBA COVID 19)

01.02.01.02.02

APLICACION DE PRUEBA SEROLOGICA PARA DESCARTE DE COVID 19

01.02.01.02.03 01.02.01.03

EXAMEN MEDICO OCUPACIONAL - COVID 19 LIMPIEZA Y DESINFECCION - COVID 19

01.02.01.03.01 01.02.01.03.02 01.02.01.04

LIMPIEZA Y DESINFECCION DE AMBIENTES - COVID 19 EQUIPOS DE LIMPIEZA Y DESINFECCION - COVID 19 OTROS IMPLEMENTOS - COVID 19

01.02.01.04.01

SEÑALIZACION TEMPORAL DE SEGURIDAD- COVID 19

01.02.01.04.02

CAPACITACION EN SEGURIDAD Y SALUD - COVID 19

01.02.01.04.03

RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO - COVID 19

01.02.01.04.05 01.03

PERSONAL PROFESIONAL DE SEGURIDAD Y SALUD MEDIDAS DE MITIGACION DE IMPACTO AMBIENTAL

01.03.01

PLAN DE MANEJO AMBIENTAL (PROGRAMA DE MITIGACION)

01.03.01.01

PLAN DE RESIDUOS SOLIDOS Y LIQUIDOS (PROGRAMA DE MADEJO DE RESIDUOS SOLIDOS)

01.03.01.01.01

ADECUACION DE LUGAR DE ALMACENAMIENTO TEMPORAL DE RESIDUOS SOLIDOS - COVID 19

01.03.01.01.02

TRANSFERENCIA Y DISPOSICION FINAL DE RESIDUOS SOLIDOS - COVID 19

01.03.01.01.03 01.03.01.02

SEÑALIZACION DE LAS AREAS A UTILIZAR DE LA OBRA - COVID 19 PLAN DE ABANDONO Y CIERRE

01.03.01.02.01

DESMONTAJE DE OBRAS PROVISIONALES -COVID 19

01.03.01.02.02

MANEJO DE RESIDUOS DE OBRA - COVID 19

01.03.01.02.03 01.03.01.02.04

RELLENO Y COMPACTACION DEL TERRENO DONDE SE INTERVINO CON EL PROYECTO - COVID 19 RESTAURACION DE LAS AREAS UTILIZADAS POR LA OBRA - COVID 19

01.03.01.02.05

TRANSFERENCIA Y DISPOSICION FINAL DE MATERIAL DEMOLIDO Y/O EXCEDENTE - COVID 19

Fuente: Extraído de solicitud de Contratista

 Respecto al impacto en el plazo de ejecución producido por las ADECUACIONES Y ADAPTACIONES DE LOS AMBIENTES DE TRABAJO, el Contratista indica en su solicitud que requiere de 30 d.c.:

HITO

CONCEPTO

DIAS

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

S 01 02 03

Impacto en el plazo de ejecución producido por la paralización de obra generado por la declaración del Estado de Emergencia Nacional. Impacto en el plazo por la re-movilización de personal y equipos, así como por las adecuaciones y adaptaciones de los ambientes de trabajo. Impacto en el plazo por la ejecución de la obra bajo las medidas para la prevención y control frente a la propagación del Covid-19. TOTAL

136 30 128 294

Fuente: Extraído de solicitud de Contratista

 Por lo consiguiente, luego de la evaluación y optimización del plazo según cronograma reformulado, el plazo total POR REMOVILIZACIÓN DE PERSONAL Y EQUIPOS – ADECUACIÓN Y ADAPTACIONES DE LOS AMBIENTES DE TRABAJO, es de 24 días calendarios, para las adecuaciones y adaptaciones de los ambientes de trabajo. Fase 3: EL IMPACTO EN PLAZO POR LA EJECUCIÓN DE LA OBRA BAJO LAS MEDIDAS PARA LA PREVENCIÓN Y CONTROL FRENTE A LA PROPAGACIÓN DEL COVID-19 DISPUESTAS POR LOS SECTORES COMPETENTES, Y TODA OTRA MEDIDA QUE RESULTE NECESARIA PARA LA REACTIVACIÓN DE LA OBRA Y SU EJECUCIÓN, QUE DERIVE DIRECTAMENTE DEL ESTADO DE EMERGENCIA NACIONAL; Ejecución de la Obra con Rendimiento Reducido por las medidas de prevención del COVID-19: Ejecutor solicita 128 d.c. por rendimientos reducidos)  El Contratista, presenta el sustento siguiente:

Fuente: Extraído de solicitud de Contratista

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Extraído de solicitud de Contratista

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Extraído de solicitud de Contratista

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Extraído de solicitud de Contratista

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

 Sobre el análisis de la cuantificación por reprogramaciones y cambio de duraciones esta dependencia señala lo siguiente: -

La cuantificación del plazo es en función de la afectación de la ruta crítica considerando los “rendimientos que se estiman para la ejecución de los trabajos”, con la implementación de las medidas para prevención y control frente a la propagación del COVID-19, de acuerdo a lo indicado en el ítem 7.2.1 de la Directiva N° 005-2020-OSCE/CD).

-

El distanciamiento social obligatorio de 1.5 ml. afectará el rendimiento de las partidas que conforman la ruta crítica, pero de aquellas en especial que tienen una cantidad de 3 a más obreros, teniendo en cuenta además el tipo de trabajo o actividad. Así también, se han encontrados partidas que no presentan rendimiento en el APU, pero; sin embargo, su ejecución será afectada en su rendimiento, tales como: CONCRETO F´C=175 KG/CM2 EN SOBRECIMIENTOS REFORZADOS, PUERTA CORTA FUEGO CON PLANCHA DE ACERO INOXIDABLE 1/32" y QUIEBRAVISTA CON CELOSIAS DE ALUZINC C40. En conclusión, se ha determinado que el porcentaje de reducción de rendimiento es del 20% y será aplicable solo a las siguientes partidas:

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” ITEM

PARTIDAS DE RUTA CRITICAS DEL SALDO DE OBRA

UNIDAD

DURACION CANTIDAD CANTIDAD % REDUCCION x % REDUCCION x % TOTAL DIAS CONTRACTUAL SALDO OBREROS DISTANCIAMIENTO RENDIMIENTOS REDUCCION AMPLIADOS

02.01.01.01 EXCAVACION MASIVA CON MAQUINARIA

m3

39

3,126.80

3.0

20.00%

8.81%

28.81%

02.03.02.01 CONCRETO F´C=210 KG/CM2 EN PLATEA DE CIMENTACION

m3

15

533.40

16.0

20.00%

8.81%

28.81%

02.03.03.01 CONCRETO F'C=210 KG/CM2 EN VIGA DE CONEXION

m3

30

103.30

16.0

20.00%

8.81%

28.81%

02.03.04.01 CONCRETO F´C=175 KG/CM2 EN SOBRECIMIENTOS REFORZADOS

m3

45

97.70

0 (*)

20.00%

8.81%

28.81%

03.01.01

m2

90

4,970.30

1.5

0.00%

8.81%

8.81%

03.02.01.01 TARRAJEO EN INTERIORES

m2

80

5,959.10

1.5

0.00%

8.81%

8.81%

03.06.01.01 ZOCALO DE CERAMICO VITRIFICADO

m2

50

1,572.00

1.3

0.00%

8.81%

8.81%

03.09.01.01 PUERTA CORTA FUEGO CON PLANCHA DE ACERO INOXIDABLE 1/32"

m2

60

52.00

0 (*)

20.00%

8.81%

28.81%

03.09.02.01 QUIEBRAVISTA CON CELOSIAS DE ALUZINC C40

m2

70

253.50

0 (**)

20.00%

8.81%

28.81%

03.09.05.01 REJILLA METALICA CON PLATINA DE FIERRO E= 1/8" PARA CANALETAS INTERIORES

m

9

1.60

5.0

20.00%

8.81%

28.81%

03.09.05.15 PLANCHA DE ACERO INOXIDABLE DE 12"x3/32", PARA CANALETA DE RAYOS X

m

8

8.30

2.0

0.00%

8.81%

8.81%

11.2359 4.3215 8.643 12.9645 7.929 7.048 4.405 17.286 20.167 2.5929 0.7048

TOTAL

97.2976

REDONDEO

97

(*) (**)

MURO DE LADRILLO TUBULAR DE ARCILLA (12X15X24 CM.) ASENTADO DE SOGA

A pesar de que en el APU no se ha considerado el rendimiento por dia, la ejecucion de esta partida sera sera afectada en su rendimiento. A pesar de que en el APU no se ha considerado el rendimiento por dia, la instalacion de este tipo materiales en fachadas sera afectada en su rendimiento.

Fuente: Elaboración propia

-

Respecto a la aplicación de los lineamientos establecidos en “Plan de vigilancia, prevención, y control de COVID-19 en el trabajo”, en la ejecución de obra producto del análisis se ha determinado que la jornada diaria se ha reducido un promedio de 2,535 segundos, equivalentes a 0.70 horas y afectando la productividad de las partidas en general en 8.81%, según el cuadro adjunto: TIEMPO DE INEFICIENCIA EN HH DEL PERSONAL AL APLICAR PROTOCOLOS COVID-19 DESCRIPCIÓN A. INICIO DE LA JORNADA 1. Control y registro de tem peratura y pulxiometria al ingreso + Entrega de Mascarillas 2. Desinfección al ingreso 3. Lavado de manos de personal 4. Colocación de uniforme. Acceso a vestuarios 5. Entrega de mascarillas 6. Charla de sensibilización COVID-19 7. Recojo de herramientas 8. Desinfección de herramientas ALMACEN 1. Lavado de manos de personal (Obligatorio, por ser area comun) 2. Recojo de materiales y/o equipos. Distanciamiento y Aforo. (1 min. Desinfeccion de almacenero, 1.5min. Llenado de formato, 1.5m in. Buscar y despachar). En promedio tiempo de espera 4 min. COMEDOR 1. Entrega Lavado de de personal. 2. de manos mascarillas, guantesAly ingreso disposición de lo que usaron. (Retiro de mascarilla al ingreso, deposito, entrega de nueva mascarilla y guante, colocacion de mascarilla y guante) 3. Lavado de manos de personal. A la salida B. DURANTE JORNADA 1. Tiempo de espera luego de desinfeccion de area de trabajo. 2. Lavado de manos 7 veces al dia * Tiempo estimado por cada lavado de manos: (Movilización a punto de lavado: 20 seg, lavado y secado de m anos: 25seg, 65 seg. Movilizacion retorno del punto de lavado: 20 seg. * Repeticion al dia 7.00 455 seg. * Tiempo Total 3. Desinfeccion con alcohol gel uso: (Movilización a punto: 15 seg, * Tiempo estimado por cada lavado y secado de manos: 10seg, Movilizacion retorno del punto de 40 seg. lavado: 15 seg. * Repeticion al dia. Estimado 8.00 320 seg. * Tiempo Total C. FIN DE JORNADA 1. Disposicion de mascarillas, traje, guantes que se emplearon en la segunda parte 2. Desinfección de herramientas 3. Depósito de herramientas 4. Depósito de equipos en almacen. (1 min. desinfección de almacenero, 2 min. llenado de formato, 2 min. para recepcionar y guardar). En promedio tiempo de espera. 5. Retiro10 demin. uniforme. Acceso a vestuarios / duchas / baños 6. Control y registro de tem pertura a salida 7. Lavado de manos de personal

TIEMPO POR TOTAL DE ACTIVIDAD TIEMPO PLAN COVID PERDIDO

TIEMPO DE ESPERA 10 seg. 10 seg. 10 seg. 10 seg. -

120 seg. 10 seg. 30 seg. 900 seg. -

130 seg. 20 seg. 40 seg. 910 seg. -

-

-

-

-

-

-

10 seg.

30 seg.

40 seg.

-

-

-

10 seg.

30 seg.

40 seg.

120 seg.

300 seg. 455 seg.

300 seg. 575 seg.

60 seg.

320 seg.

380 seg.

-

-

-

-

-

-

10 seg. 10 seg.

60 seg. 20 seg.

70 seg. 30 seg.

TOTAL

2535 seg.

Fuente: Elaboración propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

 Por todo lo arriba señalado, el saldo de obra contractual y los nuevos rendimientos teniendo en cuenta el impacto 1 y 2 analizados por aplicación de Protocolos COVID-19 obtenida en el ítem 5.2.3. IMPACTO EN PLAZO POR EJECUCIÓN DE OBRA BAJO MEDIDAS DE PREVENCIÓN Y CONTROL COVID-19, generaron nuevas duraciones en las actividades que forman parte de la ruta crítica, determinando finalmente que la cuantificación del plazo con rendimientos reducidos, considera 97 días calendario de ejecución para el saldo de obra contractual, acorde al siguiente detalle: ITEM

PARTIDAS DE RUTA CRITICAS DEL SALDO DE OBRA

UNIDAD

DURACION CANTIDAD CANTIDAD % REDUCCION x % REDUCCION x % TOTAL DIAS CONTRACTUAL SALDO OBREROS DISTANCIAMIENTO RENDIMIENTOS REDUCCION AMPLIADOS

02.01.01.01 EXCAVACION MASIVA CON MAQUINARIA

m3

39

3,126.80

3.0

20.00%

8.81%

28.81%

02.03.02.01 CONCRETO F´C=210 KG/CM2 EN PLATEA DE CIMENTACION

m3

15

533.40

16.0

20.00%

8.81%

28.81%

02.03.03.01 CONCRETO F'C=210 KG/CM2 EN VIGA DE CONEXION

m3

30

103.30

16.0

20.00%

8.81%

28.81%

02.03.04.01 CONCRETO F´C=175 KG/CM2 EN SOBRECIMIENTOS REFORZADOS

m3

45

97.70

0 (*)

20.00%

8.81%

28.81%

03.01.01

m2

90

4,970.30

1.5

0.00%

8.81%

8.81%

03.02.01.01 TARRAJEO EN INTERIORES

m2

80

5,959.10

1.5

0.00%

8.81%

8.81%

03.06.01.01 ZOCALO DE CERAMICO VITRIFICADO

m2

50

1,572.00

1.3

0.00%

8.81%

8.81%

03.09.01.01 PUERTA CORTA FUEGO CON PLANCHA DE ACERO INOXIDABLE 1/32"

m2

60

52.00

0 (*)

20.00%

8.81%

28.81%

03.09.02.01 QUIEBRAVISTA CON CELOSIAS DE ALUZINC C40

m2

70

253.50

0 (**)

20.00%

8.81%

28.81%

03.09.05.01 REJILLA METALICA CON PLATINA DE FIERRO E= 1/8" PARA CANALETAS INTERIORES

m

9

1.60

5.0

20.00%

8.81%

28.81%

03.09.05.15 PLANCHA DE ACERO INOXIDABLE DE 12"x3/32", PARA CANALETA DE RAYOS X

m

8

8.30

2.0

0.00%

8.81%

8.81%

11.2359 4.3215 8.643 12.9645 7.929 7.048 4.405 17.286 20.167 2.5929 0.7048

TOTAL

97.2976

REDONDEO

97

(*) (**)

MURO DE LADRILLO TUBULAR DE ARCILLA (12X15X24 CM.) ASENTADO DE SOGA

A pesar de que en el APU no se ha considerado el rendimiento por dia, la ejecucion de esta partida sera sera afectada en su rendimiento. A pesar de que en el APU no se ha considerado el rendimiento por dia, la instalacion de este tipo materiales en fachadas sera afectada en su rendimiento.

Fuente: Elaboración propia

FASE I: 107 días calendario (del 16/03/2020 hasta el 30/06/2020) por paralización de obra; FASE II: a) 14 d.c. por presentación y 15 d.c. por aprobación de AEP (del 01/07/2020 al 29/07/2020) + b) 24 d.c. por adecuación y adaptación de ambientes (del 30/07/2020 al 22/08/2020); FASE III: 496 d.c. de saldo contractual y 97 d.c. por la ejecución de la obra bajo las medidas para la prevención y control frente a la propagación del covid-19 (del 23/08/2020 al 07/04/2022), haciendo un total de 753 d.c. En conclusión, la Ampliación Excepcional de Plazo presenta el siguiente desagregado:

SOBRE EL SUSTENTO DE CUANTIFICACIÓN DE COSTOS, de acuerdo al Decreto Legislativo 1486 y la Directiva N° 005-2020-OSCE/CD

Fuente: Extraído de Directiva 005-2020-OSCE/CD

Fase 1: Paralización. Ejecutor solicita S/ 634,697.7.3 soles (sin IGV), de los cuales S/. 375,201.25 corresponden a Costo Directo por materiales deteriorados, maquinarias en stand by / servicios varios y S/. 259,496.48 corresponden a Gastos Generales Variables.  Respecto a los costos por materiales deteriorados, maquinarias en stand by / servicios varios, se determinan los costos acreditados en los que se haya incurrido o que se haya devengado como consecuencia de la paralización, acorde al siguiente detalle: El contratista solicita el reconocimiento de S/. 375,201.25, acorde al siguiente desagregado:

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Extraído de solicitud de Contratista

Sobre Materiales Deteriorados: - Del análisis realizado, la cantidad de cemento es mucho menor al que se debió emplear en el periodo de paralización; así también, si bien es cierto el cemento en bolsa tiene un periodo de caducidad promedio de 45 a 60 días luego de ser empacado, no se ha sustentado a través de ensayos que dicho lote ha perdido todas sus propiedades, su utilidad y calidad. Sobre Maquinarias en Stand By:- Del análisis realizado al Presupuesto de Obra, se ha encontrado que durante el periodo de paralización del 16.03.2020 al 30.06.2020, se han encontrado partidas que contemplan la utilización de Maquinaria Pesada a excepción de la Excavadora y acorde a los siguientes extractos: PARTIDAS EJECUTADAS DURANTE EL PERIODO 16.03.2020 AL 30.06.2020 Item 01.01.07.01 01.01.08.02 01.02.01.03 01.02.01.04 01.02.01.05 01.02.01.06 01.03.01.01.01 01.03.01.01.02 01.03.01.01.03 01.03.01.01.04 01.03.01.01.05 01.03.01.01.06 01.03.01.01.07 01.03.01.01.08 01.03.01.02.01 01.03.01.02.02 01.03.01.02.03 01.03.01.02.04 01.03.01.02.05 01.03.01.03.01 01.03.01.03.02 01.03.01.04.01 01.03.01.04.02 01.03.01.04.03 01.03.01.04.04 01.03.01.04.05 01.03.01.04.06 01.03.01.04.07 01.03.01.04.08 02.01.01.01 02.01.01.02 02.01.02.01 02.01.02.02 02.01.05.01 02.02.01.01 02.02.02.01 02.02.02.02 02.03.01.01 02.03.01.02 02.03.01.03

Descripción Und.Metrado Precio (S/.) Parcial (S/.) Dura Partida TRANSPORTE DE EQUIPOS MATERIALES Y HERRAMIENTAS TON 2,901.00 75.00 217,575.00 500 REPLANTEO DURANTE EL PROCESO m2 2,958.00 2.73 8,075.34 500 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 10,000.00 10,000.00 500 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 11,804.40 11,804.40 500 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD glbY SALUD DURANTE 1.00 10,500.00 EL TRABAJO10,500.00 500 SEGURIDAD, SALUD EN EL TRABAJO Y MEDIO AMBIENTE glb 1.00 20,000.00 20,000.00 500 REMOJO DE VIAS DIA 250.00 76.93 19,232.50 200 CHARLAS DE SENSIBILIDAD EN MANEJO DE RESIDUOS SOLIDOS PARA und PERSONAL 100.00 DE LA OBRA 31.63C/SEMANA 3,163.00 200 CHARLAS DE SENSIBILIDAD EN SALUD OCUPACIONAL PARA PERSONAL und DE LA 100.00 OBRA 31.63 3,163.00 200 CHARLAS DE EDUCACION AMBIENTAL und 100.00 31.63 3,163.00 200 PROGRAMA DE ASUNTOS AMBIENTALES und 1.00 4,000.00 4,000.00 200 SEÑALIZACION DE LAS AREAS A UTILIZAR DE LA OBRA und 30.00 51.25 1,537.50 200 IMPLEMENTACION DE LETREROS INFORMATIVOS DE EMERGENCIA UBICADOS und 10.00 EN ZONAS VISIBLES 81.25 812.50 200 ELABORACION E IMPLEMENTACION DEL PLAN DE SEGURIDAD Y SALUD und OCUPACIONAL 1.00 2,000.00 2,000.00 200 ELABORACION E IMPLEMENTACION DEL PLAN DE MANEJO DE RESIDUOS und SOLIDOS 1.00 2,500.00 2,500.00 60 IMPLEMENTACION E INSTALACION DE 4 JUEGOS DE 5 CILIDROS DEund COLORES (BLOQUES 4.00 1,000.00 SANITARIOS)4,000.00 60 INSTALACION E IMPLEMENTACION DE SS.HH PORTATILES (URINARIO) undE INSUMOS 4.00 1,500.00 6,000.00 60 ADECUACION DE LUGAR DE ALMACENAMIENTO TEMPORAL DE RESIDUOS und SOLIDOS 1.00 1,550.77 1,550.77 60 TRANSFERENCIA Y DISPOSICION FINAL DE RESIDUOS SOLIDOS und 1.00 3,480.61 3,480.61 60 MONITOREO DE LA CALIDAD DE AIRE (PM10 Y PM2.5, GASES)- ETAPAund DE EJECUCION 4.00 (SEMESTRAL) 8,049.28 32,197.12 60 MONITOREO DE RUIDO (TRIMESTRAL) und 8.00 2,549.52 20,396.16 60 RESPUESTA ANTE INCENDIOS(CAPACITACIONES Y/O TALLERES) und 6.00 1,030.16 6,180.96 60 INSTALACIONES DE EXTINTORES und 30.00 70.00 2,100.00 60 RESPUESTA ANTE MOVIMIENTOS SISMICOS und 4.00 1,030.16 4,120.64 60 RESPUESTA ANTE DERRAMES DE COMBUSTIBLES (CAPACITACIONES) und 3.00 1,030.16 3,090.48 60 RESPUESTA ANTE ACCIDENTES LABORALES (TALLERES Y/O CAPACITACIONES und 1.00 EN PERIMETROS 5,130.56 AUXILIARES) 5,130.56 60 SEÑALIZACION DE ZONAS SEGURA EN CASO DE DESASTRES und 1.00 1,516.16 1,516.16 60 BOTIQUIN DE OBRA und 6.00 250.00 1,500.00 60 COLOCACION DE LETREROS DE SEGURIDAD und 1.00 808.08 808.08 60 EXCAVACION MASIVA CON MAQUINARIA m3 3,126.80 8.80 27,515.84 60 EXCAVACION SIMPLE MANUAL m3 920.90 50.01 46,054.21 80 RELLENO COMPACTADO CON MATERIAL PROPIO CON EQUIPO m3 1,622.70 63.77 103,479.58 100 RELLENO COMPACTADO CON MATERIAL PROPIO CON MAQUINARIA m3 1,150.00 23.08 26,542.00 70 TABLAESTACADO PARA EXCAVACIONES m2 3,138.10 34.32 107,699.59 80 CONCRETO F´C=175KG/CM2 PARA CIMIENTOS CORRIDOS m3 192.70 432.21 83,286.87 20 CONCRETO F´C=100KG/CM2 PARA SOLADO E=0.10 M. m2 916.70 43.50 39,876.45 30 CONCRETO F´C=100KG/CM2 PARA SOLADO E=0.05 M. m2 184.90 32.76 6,057.32 30 CONCRETO F'C=210 KG/CM2 EN ZAPATAS m3 533.40 548.45 292,543.23 50 ENCOFRADO Y DESENCOFRADO NORMAL EN ZAPATAS m2 496.70 54.56 27,099.95 50 ACERO CORRUGADO FY=4200 KG/CM2. kg 26,818.20 4.59 123,095.54 50

FI partida 25/02/2020 16/02/2020 01/03/2020 01/03/2020 01/03/2020 01/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 11/03/2020 24/02/2020 25/03/2020 08/06/2020 23/06/2020 15/03/2020 21/06/2020 05/03/2020 15/03/2020 26/03/2020 15/03/2020 10/03/2020

FF partida 08/07/2021 29/06/2021 13/07/2021 13/07/2021 13/07/2021 13/07/2021 26/09/2020 26/09/2020 26/09/2020 26/09/2020 26/09/2020 26/09/2020 26/09/2020 26/09/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 09/05/2020 23/04/2020 12/06/2020 15/09/2020 31/08/2020 02/06/2020 10/07/2020 03/04/2020 13/04/2020 14/05/2020 03/05/2020 28/04/2020

Fecha corte 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020

30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020

Fuente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

saldo días 107 107 107 107 107 107 107 107 107 107 107 107 107 107 55 55 55 55 55 55 55 55 55 55 55 55 55 55 55 39 80 23 8 79 10 19 29 50 49 44

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

02.03.02.01 02.03.02.02 02.03.02.03 02.03.03.01 02.03.03.02 02.03.03.03 02.03.04.01 02.03.04.03 02.03.05.01.01 02.03.05.01.02 02.03.05.01.03 02.03.06.01 02.03.06.02 02.03.06.03 02.03.07.01 02.03.07.02 02.03.07.03 02.03.08.02 02.03.08.03 02.03.09.01 02.03.09.02 02.03.09.03 02.03.10.01 02.03.10.02 02.03.10.03 02.03.11.01 02.03.11.02 02.03.11.03 02.03.12.01.01 02.03.12.01.02 02.03.12.01.03 02.03.12.02.02 02.03.12.02.03 02.03.15.01 02.03.15.02 02.03.15.03 02.03.16.01 02.03.16.02 02.03.16.03 02.05.02.01 03.13.01.01 04.01.01 04.02.01.01 04.02.01.02 04.02.01.03 04.02.01.04 04.02.02.01 04.02.02.02 04.02.02.03 04.02.02.04 04.02.02.05 04.02.02.06 04.02.02.07 04.02.03.01 04.04.03.01 04.04.03.02 04.04.03.03 04.04.03.04 04.04.04.01 04.04.04.02 04.04.04.05 04.04.04.06 04.04.04.07 04.04.04.08 04.04.04.10 04.04.04.11 04.04.04.12 04.04.04.15 04.04.04.16 04.04.04.17 04.04.04.18 04.04.04.19 04.04.04.20 04.04.04.21 04.09.01.01.01 04.09.01.01.02 04.09.01.01.03 04.09.01.01.04 04.09.01.01.05 04.09.01.02.01 04.09.01.02.02 04.09.01.02.03 04.09.01.02.04 04.09.01.03.01 04.09.01.03.02 04.09.01.03.03 04.09.01.03.04

CONCRETO F´C=210 KG/CM2 EN PLATEA DE CIMENTACION m3 30.80 532.50 16,401.00 ENCOFRADO Y DESENCOFRADO NORMAL EN PLATEA DE CIMENTACION m2 18.30 38.34 701.62 ACERO CORRUGADO FY=4200 KG/CM2. kg 1,469.50 4.59 6,745.01 CONCRETO F'C=210 KG/CM2 EN VIGA DE CONEXION m3 103.30 549.00 56,711.70 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CONEXION m2 656.90 54.56 35,840.46 ACERO CORRUGADO FY=4200 KG/CM2. kg 9,052.80 4.59 41,552.35 CONCRETO F´C=175 KG/CM2 EN SOBRECIMIENTOS REFORZADOS m3 97.70 552.85 54,013.45 ACERO CORRUGADO FY=4200 KG/CM2. kg 6,083.30 4.59 27,922.35 CONCRETO F'C = 210 Kg/cm2 MUROS DE CONCRETO m3 243.60 565.82 137,833.75 ENCOFRADO Y DESENCOFRADO NORMAL EN MURO DE CONCRETO m2 2,750.80 65.75 180,865.10 ACERO CORRUGADO FY=4200 KG/CM2. kg 34,771.40 4.59 159,600.73 CONCRETO F'C = 210 kg/cm2 EN COLUMNAS m3 155.50 589.16 91,614.38 ENCOFRADO Y DESENCOFRADO NORMAL COLUMNAS m2 1,563.80 60.70 94,922.66 ACERO CORRUGADO FY=4200 KG/CM2. kg 25,198.60 4.59 115,661.57 CONCRETO F'C = 175 Kg/cm2 COLUMNAS DE CONFINAMIENTO m3 90.50 557.37 50,441.99 ENCOFRADO Y DESENCOFRADO NORMAL COLUMNAS DE CONFINAMIENTO m2 2,207.00 54.53 120,347.71 ACERO CORRUGADO FY=4200 KG/CM2. kg 14,871.50 4.59 68,260.19 ENCOFRADO Y DESENCOFRADO NORMAL FALSA COLUMNA m2 400.70 54.53 21,850.17 ACERO CORRUGADO FY=4200 KG/CM2. kg 4,398.20 4.59 20,187.74 CONCRETO F'C = 210 kg/cm2 VIGAS m3 301.80 592.07 178,686.73 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGAS m2 1,817.60 53.17 96,641.79 ACERO CORRUGADO FY=4200 KG/CM2. kg 36,184.00 4.59 166,084.56 CONCRETO F'C = 175 Kg/cm2 VIGAS DE CONFINAMIENTO m3 40.70 552.35 22,480.65 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGAS DE CONFINAMIENTO m2 742.20 53.17 39,462.77 ACERO CORRUGADO FY=4200 KG/CM2. kg 7,902.70 4.59 36,273.39 CONCRETO F´C=210 KG/CM2 EN COLGAJOS m3 25.20 552.35 13,919.22 ENCOFRADO Y DESENCOFRADO NORMAL DE COLGAJOS m2 457.90 53.17 24,346.54 ACERO CORRUGADO FY=4200 KG/CM2. kg 622.70 4.59 2,858.19 CONCRETO F'C = 210 Kg/cm2 LOSA MACIZA m3 458.90 558.21 256,162.57 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA MACIZA m2 2,480.10 59.88 148,508.39 ACERO CORRUGADO FY=4200 KG/CM2. kg 45,159.80 4.59 207,283.48 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA ALIGERADAS, Hm2 = 0.20 m989.80 ( EN 1 DIRECCION 53.81 ) 53,261.14 ACERO CORRUGADO FY=4200 KG/CM2. kg 5,977.80 4.59 27,438.10 CONCRETO F'C = 280 Kg/cm2 CISTERNAS m3 49.40 648.66 32,043.80 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA m2 351.80 48.35 17,009.53 ACERO CORRUGADO FY=4200 KG/CM2. kg 4,132.30 4.59 18,967.26 CONCRETO F'C = 280 Kg/cm2 TANQUE ELEVADO m3 14.20 648.66 9,210.97 ENCOFRADO Y DESENCOFRADO NORMAL EN TANQUE ELEVADO m2 110.30 48.35 5,333.01 ACERO CORRUGADO FY=4200 KG/CM2. kg 2,007.60 4.59 9,214.88 WATER STOP DE 8" m 42.80 26.15 1,119.22 LIMPIEZA PERMANENTE DE OBRA glb 1.00 6,943.20 6,943.20 TRAZO, NIVELACION Y REPLANTEO C/EQUIPO m 676.10 1.95 1,318.40 EXCAVACION DE ZANJA P/RED DE AGUA TN. A= 0.40M H<0.50 M. m 147.00 43.34 6,370.98 EXCAVACION DE ZANJA, MANUAL P/RED. DESAGUE TN. A=0.40M H=0.30-1.50M m 166.10 37.15 6,170.62 EXCAVACION DE ZANJA P/RED PLUVIAL TN. A=0.40M H=0.30M-0.60M m 363.10 52.02 18,888.46 EXCAVACION PARA CAJAS DE REGISTRO m3 3.50 32.51 113.79 REFINE Y NIVELACION FONDO DE ZANJAS P/RED DE AGUA A=0.40M. m 147.00 2.16 317.52 REFINE Y NIVELACION FONDO DE ZANJAS P/RED DE DESAGUE A=0.40M. m 166.10 2.60 431.86 REFINE Y NIVELACION FONDO DE ZANJAS P/RED DE PLUVIAL A=0.40M. m 363.10 2.37 860.55 RELLENO Y CAMA DE ARENA MANUAL P/RED DE AGUA E=0.10M. A=0.40M. m 147.00 3.15 463.05 RELLENO Y CAMA DE ARENA MANUAL P/RED DE DESAGUE E=0.15M. A=0.40M. m 166.10 6.96 1,156.06 RELLENO Y CAMA DE ARENA MANUAL P/RED PLUVIAL E=0.10M. A=0.40M. m 363.10 3.55 1,289.01 RELLENO COMPACTADO DE ZANJA C/MAT. PROPIO SELEC. P/RED DEmAGUA H<0.50M. 147.00 1.48 217.56 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 167.70 27.41 4,596.66 SUMINISTRO E INSTALACIÓN DE TUBERIA DE COBRE TIPO "L" Ø 1" m 21.60 178.83 3,862.73 SUMINISTRO E INSTALACIÓN DE TUBERIA DE COBRE TIPO "L" Ø 1 1/4" m 77.70 193.65 15,046.61 SUMINISTRO E INSTALACIÓN DE TUBERIA DE COBRE TIPO "L" Ø 1 1/2" m 13.20 206.68 2,728.18 SUMINISTRO E INSTALACIÓN DE TUBERIA DE COBRE TIPO "L" Ø 2" m 68.60 239.74 16,446.16 SUMINISTRO E INSTALACIÓN DE TEE DE COBRE Ø 2" und 25.00 175.30 4,382.50 SUMINISTRO E INSTALACIÓN DE TEE DE COBRE Ø 1 1/2" und 1.00 166.96 166.96 SUMINISTRO E INSTALACIÓN DE TEE DE COBRE Ø 3/4" und 14.00 154.52 2,163.28 SUMINISTRO E INSTALACIÓN DE TEE DE COBRE Ø 1/2" und 68.00 151.27 10,286.36 SUMINISTRO E INSTALACIÓN DE REDUCCIÓN DE COBRE Ø 2" X 1 1/4"und 4.00 155.98 623.92 SUMINISTRO E INSTALACIÓN DE REDUCCIÓN DE COBRE Ø 2" X 1" und 23.00 155.98 3,587.54 SUMINISTRO E INSTALACIÓN DE REDUCCIÓN DE COBRE Ø 1 1/4" X 1"und 4.00 154.98 619.92 SUMINISTRO E INSTALACIÓN DE REDUCCIÓN DE COBRE Ø 1 1/4" X 3/4" und 9.00 168.96 1,520.64 SUMINISTRO E INSTALACIÓN DE REDUCCIÓN DE COBRE Ø 1 1/4" X 1/2" und 15.00 168.96 2,534.40 SUMINISTRO E INSTALACIÓN DE REDUCCIÓN DE COBRE Ø 3/4" X 1/2"und 64.00 165.96 10,621.44 SUMINISTRO E INSTALACIÓN DE CODO DE COBRE Ø 2"X90° und 5.00 165.52 827.60 SUMINISTRO E INSTALACIÓN DE CODO DE COBRE Ø 1 1/2"X90° und 1.00 160.76 160.76 SUMINISTRO E INSTALACIÓN DE CODO DE COBRE Ø 1 1/4"X90º und 17.00 157.89 2,684.13 SUMINISTRO E INSTALACIÓN DE CODO DE COBRE Ø 1"X90º und 28.00 154.19 4,317.32 SUMINISTRO E INSTALACIÓN DE CODO DE COBRE Ø 3/4"x 90° und 62.00 152.10 9,430.20 SUMINISTRO E INSTALACIÓN DE CODO DE COBRE Ø 1/2"x 90° und 70.00 154.11 10,787.70 PERFORACION ROTACIONAL D=6" (CON EQUIPO SEMIPESADO) m 110.00 155.08 17,058.80 PERFORACION ROTACIONAL D=12" (CON EQUIPO SEMIPESADO) m 110.00 31.01 3,411.10 PERFORACION ROTACIONAL D=20" (CON EQUIPO SEMIPESADO) m 20.00 206.77 4,135.40 REGISTRO GEOFISICO (DIAGRAFIA ELECTRICA Y RAYOS GAMMA) und 2.00 77.54 155.08 ANALISIS GRANULOMETRICOS und 110.00 15.50 1,705.00 SUMINISTRO E INSTALACION DE TUBERIA PARA COLUMNA CIEGA EN m PVC CLASE 75.00 10 - Ø6" 62.04 4,653.00 SUMINISTRO E INSTALACION DE FILTRO DE PVC CLASE 10 - RANURA m CONTINUA, 35.00 Ø6" - ABERTURA 310.15 = 1.5MM 10,855.25 SUMINISTRO E INSTALACION DE TUBERIA PARA SELLO SANITARIO EN m ACERO20.00 NEGRO - ASTM 155.08 A36 - Ø18" 3,101.60 - E=5/32" SUMINISTRO E INSTALACION DE GRAVA SELECCIONADA GRANO E=2MM m3 - 4.7MM 2.70 310.15 837.41 TRANSPORTE, INSTALACION Y RETIRO DE EQUIPO DE BOMBEO glb 1.00 310.15 310.15 DESARROLLO DEL POZO POR AIRE COMPRIMIDO O PISTONEO hm 50.00 15.50 775.00 PROVISION Y COLOCADO DE TRIPOLIFOSFATO SODICO kg 65.00 15.50 1,007.50 PRUEBA DE BOMBEO C/CAUDALES VARIABLES Y NIVEL DINAMICO ESTABILIZADO hm 50.00 15.50 775.00

15 15 15 30 50 50 45 50 65 70 70 65 70 70 50 50 50 40 25 65 70 70 50 50 50 30 30 30 40 40 40 40 40 15 20 20 15 15 15 10 460 10 30 30 30 30 30 30 30 30 30 30 90 60 45 45 45 45 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10 10 10 10 7 7 7 7 7 7 5 5 5

24/04/2020 18/04/2020 15/04/2020 09/05/2020 02/05/2020 27/04/2020 08/06/2020 07/05/2020 26/04/2020 27/03/2020 20/03/2020 09/05/2020 19/04/2020 20/03/2020 21/06/2020 06/06/2020 29/05/2020 13/06/2020 03/06/2020 28/06/2020 29/05/2020 09/05/2020 23/06/2020 29/05/2020 19/05/2020 20/06/2020 10/06/2020 03/06/2020 25/06/2020 05/06/2020 29/05/2020 25/06/2020 18/06/2020 15/05/2020 05/05/2020 30/04/2020 22/05/2020 14/05/2020 09/05/2020 20/05/2020 24/02/2020 31/03/2020 10/04/2020 10/05/2020 10/05/2020 15/04/2020 15/04/2020 10/05/2020 10/05/2020 15/04/2020 10/05/2020 10/05/2020 15/05/2020 19/06/2020 10/05/2020 18/05/2020 26/05/2020 03/06/2020 23/05/2020 15/05/2020 07/06/2020 07/06/2020 07/06/2020 30/05/2020 30/05/2020 07/06/2020 30/05/2020 14/06/2020 14/06/2020 14/06/2020 14/06/2020 14/06/2020 14/06/2020 14/06/2020 24/04/2020 04/05/2020 14/05/2020 24/05/2020 24/05/2020 03/06/2020 03/06/2020 10/06/2020 17/06/2020 17/06/2020 17/06/2020 22/06/2020 22/06/2020

08/05/2020 02/05/2020 29/04/2020 07/06/2020 20/06/2020 15/06/2020 22/07/2020 25/06/2020 29/06/2020 04/06/2020 28/05/2020 12/07/2020 27/06/2020 28/05/2020 09/08/2020 25/07/2020 17/07/2020 22/07/2020 27/06/2020 31/08/2020 06/08/2020 17/07/2020 11/08/2020 17/07/2020 07/07/2020 19/07/2020 09/07/2020 02/07/2020 03/08/2020 14/07/2020 07/07/2020 03/08/2020 27/07/2020 29/05/2020 24/05/2020 19/05/2020 05/06/2020 28/05/2020 23/05/2020 29/05/2020 28/05/2021 09/04/2020 09/05/2020 08/06/2020 08/06/2020 14/05/2020 14/05/2020 08/06/2020 08/06/2020 14/05/2020 08/06/2020 08/06/2020 12/08/2020 17/08/2020 23/06/2020 01/07/2020 09/07/2020 17/07/2020 06/06/2020 29/05/2020 21/06/2020 21/06/2020 21/06/2020 13/06/2020 13/06/2020 21/06/2020 13/06/2020 28/06/2020 28/06/2020 28/06/2020 28/06/2020 28/06/2020 28/06/2020 28/06/2020 03/05/2020 13/05/2020 23/05/2020 02/06/2020 30/05/2020 09/06/2020 09/06/2020 16/06/2020 23/06/2020 23/06/2020 21/06/2020 26/06/2020 26/06/2020

16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020

30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

15 15 15 30 50 50 23 50 65 70 70 53 70 70 10 25 33 18 25 3 33 53 8 33 43 11 21 28 6 26 33 6 13 15 20 20 15 15 15 10 107 10 30 30

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

04.09.01.03.05 04.09.01.04.01 04.09.01.04.02 04.09.01.05.01 04.09.01.05.02 04.11.01.02 04.11.01.04 04.11.02.01 04.11.02.02 04.11.02.03 04.11.02.04 04.11.03.02 04.11.03.05 04.11.03.06 04.11.03.07 04.11.03.10 04.11.03.12 04.11.03.13 04.11.03.14 04.11.03.17 04.11.05.01.01 04.12.01.01 04.12.01.02 05.01.01.01 05.01.02.01 05.01.02.02 05.01.02.03 05.01.03.01 05.01.04.01 05.01.04.02 05.01.04.03 05.01.04.04 05.01.04.10 05.01.04.11 05.01.04.12 05.01.04.13 05.01.04.29 05.01.04.30

EVACUACION DE AGUA POR PRUEBA DE BOMBEO glb 1.00 310.15 310.15 PRUEBA DE VERTICALIDAD Y ALINEAMIENTO DE POZO und 1.00 310.15 310.15 ANALISIS FISICO QUIMICO Y BACTEOROLOGIA und 2.00 310.15 620.30 SELLO SANITARIO EN ESPACIO ANULAR (ENTRE HOYO PERFORADOglb Y ADEME DE 1.00 FIERRO 310.15 NEGRO Ø 18" 310.15 SELLADO DEL FONDO DEL POZO glb 1.00 310.15 310.15 SALIDA DE DESAGUE DE PVC Ø 4" pto 51.00 276.37 14,094.87 SALIDA DE DESAGUE Cu DE 4" pto 4.00 301.25 1,205.00 SUMINISTRO E INSTALACIÓN DE TUBERÍA PVC-CP,NTP 399.003 Ø 2" m 328.50 22.80 7,489.80 SUMINISTRO E INSTALACIÓN DE TUBERÍA PVC-CP,NTP 399.003 Ø 4" m 501.70 32.65 16,380.51 SUMINISTRO E INSTALACIÓN DE TUBERIA Cu Ø 2" m 3.10 170.12 527.37 SUMINISTRO E INSTALACIÓN DE TUBERIA Cu Ø 4" m 29.70 302.44 8,982.47 SUMINISTRO E INSTALACION DE REGISTRO ROSCADO DE BRONCE CROMADO und 65.00 Ø 4" 30.02 1,951.30 SUMINISTRO E INSTALACIÓN DE YEE SANITARIA DE PVC,NTP 399.003und Ø 4"X4" 84.00 31.01 2,604.84 SUMINISTRO E INSTALACIÓN DE YEE SANITARIA DE REDUCCIÓN PVC,NTP und 399.003 161.00 Ø 4" A 2" 31.01 4,992.61 SUMINISTRO E INSTALACIÓN DE CODO DE PVC,NTP 399.003 Ø 4"X45ºund 53.00 31.01 1,643.53 SUMINISTRO E INSTALACIÓN DE CODO DE PVC,NTP 399.003 Ø 2"X45ºund 69.00 31.01 2,139.69 SUMINISTRO E INSTALACIÓN DE YEE DE Cu Ø 4"X4" und 3.00 31.01 93.03 SUMINISTRO E INSTALACIÓN DE YEE CON REDUCCIÓN DE Cu Ø 4" Aund 2" 1.00 31.01 31.01 SUMINISTRO E INSTALACIÓN DE CODO DE Cu Ø 4"X45º und 6.00 31.01 186.06 COLGADOR PARA TUBERIA DE DESAGUE TIPO GOTA und 485.00 39.00 18,915.00 SUMINISTRO E INSTALACIÓN DE CAJA DE REGISTRO DE DESAGUE und 25 X 50CM12.00 174.02 2,088.24 CUNETA DE EVACUACION PLUVIAL DE CºAº ABIERTA C/ REJILLA ANCHO m 0.40M188.50 400.53 75,499.91 CUNETA DE EVACUACION PLUVIAL DE CºAº CERRADA TECHADA ANCHO m 0.40M.48.30 265.53 12,825.10 TRAZO, NIVELACION Y REPLANTEO C/EQUIPO m 480.00 1.59 763.20 EXCAVACION DE ZANJA MANUAL H=0.60 M. A=0.40 M. m 160.00 43.34 6,934.40 EXCAVACION PARA POSTES DE 5M. D=0.45M. und 13.00 18.57 241.41 RELLENO DE ZANJA CON MATERIAL PROPIO COMPACTADO m 160.00 60.09 9,614.40 SUMINISTRO E INSTALACIÓN DE POSTES DE F°G° H=5.00M. SEGÚN DISEÑO und 13.00 503.01 6,539.13 SALIDA DE CENTRO DE LUZ pto 432.00 90.49 39,091.68 SALIDA PARA TOMACORRIENTE DOBLE C/PUESTAA TIERRA pto 373.00 94.15 35,117.95 SALIDA PARA TOMACORRIENTE ESTABILIZADOS pto 93.00 94.15 8,755.95 SALIDA PARA TOMACORRIENTE EQUIPAMIENTO MEDICO pto 37.00 94.15 3,483.55 INTERRUPTOR UNIPOLAR SIMPLE und 122.00 81.15 9,900.30 INTERRUPTOR UNIPOLAR DOBLE und 59.00 88.25 5,206.75 INTERRUPTOR UNIPOLAR TRIPLE und 3.00 89.25 267.75 INTERRUPTOR DE CONMUTACIÓN SIMPLE und 64.00 88.25 5,648.00 CAJA DE PASE DE 100X100X50 mm F°G° PESADA und 4.00 53.30 213.20 CAJA DE PASE DE 200X200X100 mm F°G° PESADA und 16.00 10.71 171.36

5 5 5 5 5 10 10 20 20 20 20 7 7 7 7 7 10 10 10 10 10 30 30 7 15 15 15 10 40 40 30 30 30 30 30 30 30 30

22/06/2020 17/06/2020 22/06/2020 22/06/2020 27/06/2020 29/06/2020 29/06/2020 12/06/2020 09/06/2020 12/06/2020 09/06/2020 29/06/2020 29/06/2020 29/06/2020 29/06/2020 29/06/2020 29/06/2020 29/06/2020 29/06/2020 17/06/2020 29/06/2020 09/06/2020 17/06/2020 01/05/2020 08/05/2020 23/05/2020 17/06/2020 07/06/2020 17/06/2020 08/05/2020 18/05/2020 18/05/2020 07/06/2020 17/06/2020 17/06/2020 17/06/2020 17/06/2020 22/06/2020

26/06/2020 21/06/2020 26/06/2020 26/06/2020 01/07/2020 08/07/2020 08/07/2020 01/07/2020 28/06/2020 01/07/2020 28/06/2020 05/07/2020 05/07/2020 05/07/2020 05/07/2020 05/07/2020 08/07/2020 08/07/2020 08/07/2020 26/06/2020 08/07/2020 08/07/2020 16/07/2020 07/05/2020 22/05/2020 06/06/2020 01/07/2020 16/06/2020 26/07/2020 16/06/2020 16/06/2020 16/06/2020 06/07/2020 16/07/2020 16/07/2020 16/07/2020 16/07/2020 21/07/2020

16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020 16/03/2020

30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020 30/06/2020

PARTIDAS QUE CONCIBEN MAQUINARIA PESADA Item 01.03.01.02.05 02.01.01.01 04.02.03.01

Descripción TRANSFERENCIA Y DISPOSICION FINAL DE RESIDUOS SOLIDOS EXCAVACION MASIVA CON MAQUINARIA ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA

FI partida 11/03/2020 24/02/2020 19/06/2020

FF partida 09/05/2020 23/04/2020 17/08/2020

Fecha corte saldo días 16/03/2020 30/06/2020 55 16/03/2020 30/06/2020 39 16/03/2020 30/06/2020 12

Maq pesada Volquete Retroexcava Volquete

Por lo consiguiente, se concluye que corresponde reconocer costos directos por maquinaria stand by, acorde a lo siguiente:

Recurso Retroexcavador S/Llantas Excavadora Camión volquete 15m3

Maquinaria Pesada Saldo HHm días m/dia

Precio

Total

107

2

214

220

S/47,080.00

0 107

0 2

0 214

0 190

S/0.00 S/40,660.00

SUBOTOTA L IGV (18%) TOTAL

S/87,740.00 S/. 15,793.20 S/. 103,533.20

Fuente: Elaboracion propia

Sobre Gasto de Servicios Varios: - No existen partidas que conciban el recurso “Servicio de Energía para la Construcción”, pues la partida “01.01.02.03 ENERGÍA ELÉCTRICA PROVISIONAL” culminó el jueves 27 de febrero del 2020, no perteneciendo al periodo paralizado.

Recurso Energía eléctrica para la Construcción

Otros Saldo días H-m/dia Hm Precio 107 0 0 20

Total S/0.00 S/0.00

uente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”  Respecto a los costos por Gastos Generales Variables, se determinan los costos acreditados en los que se haya incurrido o que se haya devengado como consecuencia de la paralización, acorde al siguiente detalle: DESAGREGADO DE GASTOS GENERALES - PERIODO DEL16- 03- 2020 HASTA EL31-03-2020 ( B ) GASTOS GENERALES VARIABLES ITEM

B.1

PERSONAL TECNICO 1.01 1.02 1.05 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18

B.2

Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o

d e G e re nt e d e O b ra d e Ad min ist ra d o r d e O b ra d e Ing e nie ro Re sid e n t e d e Ing e nie ro Se g urid a d In d ust ria l d e Arq uit e c t o e sp e c ia list a Ho sp it a le s d e Ing e nie ro Esp e c ia list a e n Est ruc t ura s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s Sa nit a ria s d e Ing e nie ro Esp e c ia list a Inst a la c io ne s Ele c t ric a s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s M e c a nic a s d e Ing e nie ro Esp e c ia list a e n C o m un ic a c io n e s d e Esp e c ia list a e n Eq uip a m ie nt o M e d ic o d e Je fe d e Eq uip o M e c a nic o d e l M a e st ro d e O b ra d e Alma c e ne ro d e G ua rd ia ne s d e Alma c e n e s

Und

VALOR OFERTADO PRECIO x DIA S/ . S/ .

COSTO GLOBAL

OBSERVACIONES

me s me s me s me s me s me s me s me s me s me s me s me s me s me s me s

95,000.00 54,000.00 351,500.00 144,000.00 38,400.00 24,000.00 32,000.00 32,000.00 25,600.00 25,600.00 12,000.00 4,700.00 81,000.00 49,500.00 97,200.00

EST EST EST EST EST M ES M ES M ES EST EST EST EST EST EST EST

1,000.00 1,500.00 4,500.00 2,500.00 4,000.00 4,500.00 13,500.00 4,500.00 6,400.00 5,000.00 2,500.00 7,000.00 7,500.00 2,500.00 9,000.00

EST M ES M ES M ES M ES M ES

4,000.00 55,091.63 73,455.51 22,036.65 146,911.02 44,073.31

100.00 266.67

180.00

2,580.65 Costo equivalente según comprobante Se m antiene costo ofertado 9,250.00 Costo equivalente según comprobante Se m antiene costo ofertado No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento 2322.58 Costo equivalente según comprobante 1032.26 Costo equivalente según comprobante Se m antiene costo ofertado

GASTOS DE OFICINA Y SERVICIOS 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.12 2.12 2.12

B.3

Do c um e n t a c ió n C O NSUC O DE C e rt ific a d o s C IP y o t ro s Fo t o g ra fía y C o p ia s Liq u id a c ió n d e O b ra Pla no s d e Re p la nt e o Amo rt iza c ió n d e e q u ip o s d e o fic ina Alq uile r d e C a mio ne t a y o t ro s Ut ile s d e e sc rit o rio y a se o Lic e nc ia d e C o n st ru c c io n Tra m it e s y Se rv ic io s a nt e e l c o n se c io n a rio e le c t ric o Tra m it e s y Se rv ic io s a nt e e l c o n se c io n a rio Sa ne a m ie n t o Tra m it e s y Se rv ic io s d e C o m unic a c io n e s Tra m it e s a nt e O sin e rming Tra m it e a n t e la M unic ip a lid a d Va rio s Se rv ic io Va rio s

12.96

No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento Se m antiene costo ofertado No presento sustento No presento sustento 100.00 Costo equivalente según comprobante

GASTOS FINANCIEROS 4.01 4.02 4.03 4.04 4.05 4.06

B.4

DESCRIPCION

CARTA FIANZA Vig e n c ia d e Po d e r y g a st o s no t a ria le s Prim a C a rt a Fia n za Fie l C ump limie nt o Prim a C a rt a Fia n za d e Ad e la nt o Dire c t o Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o Dire c t o Prim a C a rt a Fia n za Ad e la nt o M a t e ria le s Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o M a t e ria le s

136.03 40.81 272.06 81.62

No presento sustento 1579.69 Costo equivalente según comprobante Se m antiene costo ofertado Se m antiene costo ofertado Se m antiene costo ofertado Se m antiene costo ofertado

50.00

No presento sustento No presento sustento Se m antiene costo ofertado

SEGUROS Y SALUD EN OBRA 6.01 C o nt ra a c c id e nt e s ind iv id ua le s 6.02 C o nt ra a c c id e nt e s ind iv id ua le s 6.03 C o nt ra inst a la c io n e s, re sp o n sa b ilid a d c iv il e t c .

18,000.00 6,480.00 27,000.00

SUB-TOTAL GASTOS GENERALES (B)

1,140.14 AMPLIAC IO N DE PLAZO SUBTO TAL 1 IG V (18%) SUBTO TAL 2 TOTAL

16,865.17

16 d .c . 18,242.27 16,865.17 3,283.61 3,035.73 21,525.87 19,900.91 41,426.78

Fuente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

DESAGREGADO DE GASTOS GENERALES - PERIODO DEL01- 04- 2020 HASTA EL30-04-2020 ( B ) GASTOS GENERALES VARIABLES ITEM

B.1 1.01 1.02 1.05 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18

B.2

Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o

d e G e re nt e d e O b ra d e Ad minist ra d o r d e O b ra d e Ing e nie ro Re sid e nt e d e Ing e nie ro Se g urid a d Ind ust ria l d e Arq uit e c t o e sp e c ia list a Ho sp it a le s d e Ing e nie ro Esp e c ia list a e n Est ruc t ura s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s Sa nit a ria s d e Ing e nie ro Esp e c ia list a Inst a la c io ne s Ele c t ric a s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s M e c a nic a s d e Ing e nie ro Esp e c ia list a e n C o m unic a c io ne s d e Esp e c ia list a e n Eq uip a m ie nt o M e d ic o d e Je fe d e Eq uip o M e c a nic o d e l M a e st ro d e O b ra d e Alma c e ne ro d e G ua rd ia ne s d e Alm a c e ne s

Und

VALOR OFERTADO PRECIO x DIA S/ . S/ .

COSTO GLOBAL

OBSERVACIONES

me s me s me s me s me s me s me s me s me s me s me s me s me s me s me s

95,000.00 54,000.00 351,500.00 144,000.00 38,400.00 24,000.00 32,000.00 32,000.00 25,600.00 25,600.00 12,000.00 4,700.00 81,000.00 49,500.00 97,200.00

EST EST EST EST EST M ES M ES M ES EST EST EST EST EST EST EST

1,000.00 1,500.00 4,500.00 2,500.00 4,000.00 4,500.00 13,500.00 4,500.00 6,400.00 5,000.00 2,500.00 7,000.00 7,500.00 2,500.00 9,000.00

EST M ES M ES M ES M ES M ES

4,000.00 55,091.63 73,455.51 22,036.65 146,911.02 44,073.31

100.00 266.67

180.00

5,000.00 Costo equivalente según comprobante Se mantiene costo ofertado 18,500.00 Costo equivalente según comprobante Se mantiene costo ofertado No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento 4500.00 Costo equivalente según comprobante 2000.00 Costo equivalente según comprobante Se mantiene costo ofertado

GASTOS DE OFICINA Y SERVICIOS 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.12 2.12 2.12

B.3

Do c um e nt a c ió n C O NSUC O DE C e rt ific a d o s C IP y o t ro s Fo t o g ra fía y C o p ia s Liq uid a c ió n d e O b ra Pla no s d e Re p la nt e o Am o rt iza c ió n d e e q uip o s d e o fic ina Alq uile r d e C a mio ne t a y o t ro s Ut ile s d e e sc rit o rio y a se o Lic e nc ia d e C o nst ruc c io n Tra m it e s y Se rv ic io s a nt e e l c o nse c io na rio e le c t ric o Tra m it e s y Se rv ic io s a nt e e l c o nse c io na rio Sa ne a m ie nt o Tra m it e s y Se rv ic io s d e C o m unic a c io ne s Tra m it e s a nt e O sine rming Tra m it e a nt e la M unic ip a lid a d Va rio s Se rv ic io Va rio s

12.96

No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento 9.00 Costo equivalente según comprobante No presento sustento No presento sustento No presento sustento Se mantiene costo ofertado No presento sustento No presento sustento 253.33 Costo equivalente según comprobante 100.00 Costo equivalente según comprobante

GASTOS FINANCIEROS 4.01 4.02 4.03 4.04 4.05 4.06

B.4

DESCRIPCION

PERSONAL TECNICO

CARTA FIANZA Vig e nc ia d e Po d e r y g a st o s no t a ria le s Prim a C a rt a Fia nza Fie l C um p limie nt o Prim a C a rt a Fia nza d e Ad e la nt o Dire c t o Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o Dire c t o Prim a C a rt a Fia nza Ad e la nt o M a t e ria le s Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o M a t e ria le s

136.03 40.81 272.06 81.62

No presento sustento 3060.65 Costo equivalente según comprobante Se mantiene costo ofertado Se mantiene costo ofertado Se mantiene costo ofertado Se mantiene costo ofertado

50.00

No presento sustento No presento sustento Se mantiene costo ofertado

SEGUROS Y SALUD EN OBRA 6.01 C o nt ra a c c id e nt e s ind iv id ua le s 6.02 C o nt ra a c c id e nt e s ind iv id ua le s 6.03 C o nt ra inst a la c io ne s, re sp o nsa b ilid a d c iv il e t c .

18,000.00 6,480.00 27,000.00

SUB-TOTAL GASTOS GENERALES (B)

1,140.14 AMPLIAC IO N DE PLAZO SUBTO TAL 1 IG V (18%) SUBTO TAL 2 TOTAL

33,422.98

30 d .c . 34,204.25 33,422.98 6,156.76 6,016.14 40,361.01 39,439.12 79,800.13

Fuente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

DESAGREGADO DE GASTOS GENERALES - PERIODO DEL01- 05- 2020 HASTA EL31-05-2020 ( B ) GASTOS GENERALES VARIABLES ITEM

B.1 1.01 1.02 1.05 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18

B.2

Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o

d e G e re nt e d e O b ra d e Ad minist ra d o r d e O b ra d e Ing e nie ro Re sid e nt e d e Ing e nie ro Se g urid a d Ind ust ria l d e Arq uit e c t o e sp e c ia list a Ho sp it a le s d e Ing e nie ro Esp e c ia list a e n Est ruc t ura s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s Sa nit a ria s d e Ing e nie ro Esp e c ia list a Inst a la c io ne s Ele c t ric a s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s M e c a nic a s d e Ing e nie ro Esp e c ia list a e n C o m unic a c io ne s d e Esp e c ia list a e n Eq uip a m ie nt o M e d ic o d e Je fe d e Eq uip o M e c a nic o d e l M a e st ro d e O b ra d e Alma c e ne ro d e G ua rd ia ne s d e Alm a c e ne s

Und

VALOR OFERTADO PRECIO x DIA S/ . S/ .

COSTO GLOBAL

OBSERVACIONES

me s me s me s me s me s me s me s me s me s me s me s me s me s me s me s

95,000.00 54,000.00 351,500.00 144,000.00 38,400.00 24,000.00 32,000.00 32,000.00 25,600.00 25,600.00 12,000.00 4,700.00 81,000.00 49,500.00 97,200.00

EST EST EST EST EST M ES M ES M ES EST EST EST EST EST EST EST

1,000.00 1,500.00 4,500.00 2,500.00 4,000.00 4,500.00 13,500.00 4,500.00 6,400.00 5,000.00 2,500.00 7,000.00 7,500.00 2,500.00 9,000.00

EST M ES M ES M ES M ES M ES

4,000.00 55,091.63 73,455.51 22,036.65 146,911.02 44,073.31

100.00 266.67

180.00

5,000.00 Costo equivalente según comprobante Se mantiene costo ofertado 18,500.00 Costo equivalente según comprobante Se mantiene costo ofertado No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento 4500.00 Costo equivalente según comprobante 2000.00 Costo equivalente según comprobante Se mantiene costo ofertado

GASTOS DE OFICINA Y SERVICIOS 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.12 2.12 2.12

B.3

Do c um e nt a c ió n C O NSUC O DE C e rt ific a d o s C IP y o t ro s Fo t o g ra fía y C o p ia s Liq uid a c ió n d e O b ra Pla no s d e Re p la nt e o Am o rt iza c ió n d e e q uip o s d e o fic ina Alq uile r d e C a mio ne t a y o t ro s Ut ile s d e e sc rit o rio y a se o Lic e nc ia d e C o nst ruc c io n Tra m it e s y Se rv ic io s a nt e e l c o nse c io na rio e le c t ric o Tra m it e s y Se rv ic io s a nt e e l c o nse c io na rio Sa ne a m ie nt o Tra m it e s y Se rv ic io s d e C o m unic a c io ne s Tra m it e s a nt e O sine rming Tra m it e a nt e la M unic ip a lid a d Va rio s Se rv ic io Va rio s

12.96

No presento sustento No presento sustento 109.20 Costo equivalente según comprobante No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento Se mantiene costo ofertado No presento sustento No presento sustento 404.73 Costo equivalente según comprobante 100.00 Costo equivalente según comprobante

GASTOS FINANCIEROS 4.01 4.02 4.03 4.04 4.05 4.06

B.4

DESCRIPCION

PERSONAL TECNICO

CARTA FIANZA Vig e nc ia d e Po d e r y g a st o s no t a ria le s Prim a C a rt a Fia nza Fie l C um p limie nt o Prim a C a rt a Fia nza d e Ad e la nt o Dire c t o Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o Dire c t o Prim a C a rt a Fia nza Ad e la nt o M a t e ria le s Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o M a t e ria le s

136.03 40.81 272.06 81.62

No presento sustento 3060.65 Costo equivalente según comprobante Se mantiene costo ofertado Se mantiene costo ofertado Se mantiene costo ofertado Se mantiene costo ofertado

50.00

No presento sustento No presento sustento Se mantiene costo ofertado

SEGUROS Y SALUD EN OBRA 6.01 C o nt ra a c c id e nt e s ind iv id ua le s 6.02 C o nt ra a c c id e nt e s ind iv id ua le s 6.03 C o nt ra inst a la c io ne s, re sp o nsa b ilid a d c iv il e t c .

18,000.00 6,480.00 27,000.00

SUB-TOTAL GASTOS GENERALES (B)

1,140.14 AMPLIAC IO N DE PLAZO SUBTO TAL 1 IG V (18%) SUBTO TAL 2 TOTAL

33,674.58

31 d .c . 35,344.39 33,674.58 6,361.99 6,061.42 41,706.38 39,736.01 81,442.39

Fuente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” DESAGREGADO DE GASTOS GENERALES - PERIODO DEL01- 06- 2020 HASTA EL30-06-2020 ( B ) GASTOS GENERALES VARIABLES ITEM

B.1

PERSONAL TECNICO 1.01 1.02 1.05 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18

Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o

d e G e re nt e d e O b ra d e Ad minist ra d o r d e O b ra d e Ing e nie ro Re sid e nt e d e Ing e nie ro Se g urid a d Ind ust ria l d e Arq uit e c t o e sp e c ia list a Ho sp it a le s d e Ing e nie ro Esp e c ia list a e n Est ruc t ura s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s Sa nit a ria s d e Ing e nie ro Esp e c ia list a Inst a la c io ne s Ele c t ric a s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s M e c a nic a s d e Ing e nie ro Esp e c ia list a e n C o m unic a c io ne s d e Esp e c ia list a e n Eq uip a m ie nt o M e d ic o d e Je fe d e Eq uip o M e c a nic o d e l M a e st ro d e O b ra d e Alma c e ne ro d e G ua rd ia ne s d e Alm a c e ne s

Und

VALOR OFERTADO PRECIO x DIA S/ . S/ .

COSTO GLOBAL

OBSERVACIONES

me s me s me s me s me s me s me s me s me s me s me s me s me s me s me s

95,000.00 54,000.00 351,500.00 144,000.00 38,400.00 24,000.00 32,000.00 32,000.00 25,600.00 25,600.00 12,000.00 4,700.00 81,000.00 49,500.00 97,200.00

2.01 Do c um e nt a c ió n C O NSUC O DE 2.02 C e rt ific a d o s C IP y o t ro s 2.03 Fo t o g ra fía y C o p ia s

EST EST EST

1,000.00 1,500.00 4,500.00

2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.12 2.12 2.12

EST EST M ES M ES M ES EST EST EST EST EST EST EST

2,500.00 4,000.00 4,500.00 13,500.00 4,500.00 6,400.00 5,000.00 2,500.00 7,000.00 7,500.00 2,500.00 9,000.00

EST M ES M ES M ES M ES M ES

4,000.00 55,091.63 73,455.51 22,036.65 146,911.02 44,073.31

B.2

100.00

180.00

5,000.00 Costo equivalente según comprobante Se mantiene costo ofertado 18,500.00 Costo equivalente según comprobante No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento No presento sustento 4500.00 Costo equivalente según comprobante 2000.00 Costo equivalente según comprobante Se mantiene costo ofertado

GASTOS DE OFICINA Y SERVICIOS

B.3

Liq uid a c ió n d e O b ra Pla no s d e Re p la nt e o Am o rt iza c ió n d e e q uip o s d e o fic ina Alq uile r d e C a mio ne t a y o t ro s Ut ile s d e e sc rit o rio y a se o Lic e nc ia d e C o nst ruc c io n Tra m it e s y Se rv ic io s a nt e e l c o nse c io na rio e le c t ric o Tra m it e s y Se rv ic io s a nt e e l c o nse c io na rio Sa ne a m ie nt o Tra m it e s y Se rv ic io s d e C o m unic a c io ne s Tra m it e s a nt e O sine rming Tra m it e a nt e la M unic ip a lid a d Va rio s Se rv ic io Va rio s

12.96

No presento sustento No presento sustento 165.02 Costo equivalente según comprobante 8.00 Costo equivalente según comprobante No presento sustento No presento sustento No presento sustento No presento sustento 9.60 Costo equivalente según comprobante No presento sustento No presento sustento No presento sustento Se mantiene costo ofertado No presento sustento No presento sustento 395.26 Costo equivalente según comprobante 100.00 Costo equivalente según comprobante

GASTOS FINANCIEROS 1.00 4.01 4.02 4.03 4.04 4.05 4.06

B.4

DESCRIPCION

CARTA FIANZA Vig e nc ia d e Po d e r y g a st o s no t a ria le s Prim a C a rt a Fia nza Fie l C um p limie nt o Prim a C a rt a Fia nza d e Ad e la nt o Dire c t o Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o Dire c t o Prim a C a rt a Fia nza Ad e la nt o M a t e ria le s Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o M a t e ria le s

136.03 40.81 272.06 81.62

No presento sustento 3060.65 Costo equivalente según comprobante Se mantiene costo ofertado Se mantiene costo ofertado Se mantiene costo ofertado Se mantiene costo ofertado

50.00

No presento sustento No presento sustento Se mantiene costo ofertado

SEGUROS Y SALUD EN OBRA 6.01 C o nt ra a c c id e nt e s ind iv id ua le s 6.02 C o nt ra a c c id e nt e s ind iv id ua le s 6.03 C o nt ra inst a la c io ne s, re sp o nsa b ilid a d c iv il e t c .

18,000.00 6,480.00 27,000.00

SUB-TOTAL GASTOS GENERALES (B)

873.47 AMPLIAC IO N DE PLAZO SUBTO TAL 1 IG V (18%) SUBTO TAL 2 TOTAL

33,738.53

30 d .c . 26,204.25 33,738.53 4,716.76 6,072.94 30,921.01 39,811.47 70,732.48

Fuente: Elaboracion propia

 Se determina, en virtud a los costos concordantes con las condiciones originales del contrato y la documentación sustentatoria presentada que, el monto alcanza los S/. 273,401.78 (Doscientos Setenta y Tres Mil Cuatrocientos Uno y 78/100 Soles), el cual incluye IGV. Fase 2: Reactivación, Removilización y Adecuación COVID-19: Ejecutor solicita S/ 1’875,211.11 soles. (S/. 88,135.11 por tramites administrativo de presentación y aprobación de AEP; S/. 70,000.00 por el costo directo de elaboración de documentos exigidos por el sector competente – plan COVID-19; S/. 1’625,901.74 por el costo directo por la Adecuación y Adaptación de los ambientes de trabajo y S/. 91,174.26 por los Gastos Generales Variables q bue se generan por la Adecuación y Adaptación de los ambientes de trabajo).

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

 El análisis realizado por esta dependencia determina que por los trámites administrativos de presentación y aprobación de AEP, el monto alcanza hasta S/. 83,569.56 (Ochenta y Tres Mil Quinientos Sesenta y Nueve y 56/100), que incluye IGV, acorde al siguiente detalle: -

El análisis se elabora en virtud al costo ofertado y a lo requerido en esta etapa, habiéndose actualizado a 29 d.c. acorde con lo determinado en la cuantificación por presentación y aprobación de AEP. DESAGREGADO DE GASTOS GENERALES - PERIODO DEL 01-07-2020 HASTA EL 29- 07-2020

( B ) GASTOS GENERALES VARIABLES ITEM

B.1

VALOR OFERTADO S/ .

PRECIO x DIA S/ .

me s me s me s me s me s me s me s me s me s me s me s me s me s me s me s

95,000.00 54,000.00 351,500.00 144,000.00 38,400.00 24,000.00 32,000.00 32,000.00 25,600.00 25,600.00 12,000.00 4,700.00 81,000.00 49,500.00 97,200.00

175.93 100.00 650.93 266.67 150.00 91.67 180.00

EST EST EST EST EST M ES M ES M ES EST EST EST EST EST EST EST

1,000.00 1,500.00 4,500.00 2,500.00 4,000.00 4,500.00 13,500.00 4,500.00 6,400.00 5,000.00 2,500.00 7,000.00 7,500.00 2,500.00 9,000.00

8.33 4.63 7.41 8.33 25.00 8.33 12.96 16.67

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

11,250.00 7,500.00 18,000.00 10,000.00

-

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

4,000.00 55,091.63 73,455.51 22,036.65 146,911.02 44,073.31

7.41 102.02 136.03 40.81 272.06 81.62

18,000.00 6,480.00 27,000.00

33.33 12.00 50.00

Und

SUELDOS Y SALARIOS 1.01 1.02 1.05 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18

B.2

Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o

d e G e re nt e d e O b ra d e Ad m inist ra d o r d e O b ra d e Ing e nie ro Re sid e n t e d e Ing e nie ro Se g urid a d Ind ust ria l d e Arq uit e c t o e sp e c ia list a Ho sp it a le s d e Ing e nie ro Esp e c ia list a e n Est ruc t ura s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s Sa nit a ria s d e Ing e nie ro Esp e c ia list a Inst a la c io ne s Ele c t ric a s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s M e c a n ic a s d e Ing e nie ro Esp e c ia list a e n C o m unic a c io ne s d e Esp e c ia list a e n Eq uip a m ie nt o M e d ic o d e Je fe d e Eq uip o M e c a nic o d e l Ma e st ro d e O b ra d e Alm a c e ne ro d e G ua rd ia ne s d e Alma c e ne s

OBSERVACIONES

-

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

GASTOS DE OFICINA Y SERVICIOS 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.12 2.12 2.12

B.3

Do c um e nt a c ió n C O NSUC O DE C e rt ific a d o s C IP y o t ro s Fo t o g ra fía y C o p ia s Liq uid a c ió n d e O b ra Pla no s d e Re p la nt e o Am o rt iza c ió n d e e q uip o s d e o fic ina Alq uile r d e C a m io ne t a y o t ro s Ut ile s d e e sc rit o rio y a se o Lic e nc ia d e C o nst ruc c io n Tra mit e s y Se rv ic io s a nt e e l c o nse c io na rio e le c t ric o Tra mit e s y Se rv ic io s a nt e e l c o nse c io na rio Sa ne a mie n t o Tra mit e s y Se rv ic io s d e C o m unic a c io ne s Tra mit e s a nt e O sine rm ing Tra mit e a nt e la M unic ip a lid a d Va rio s Se rv ic io Va rio s

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

GASTOS DE CONTROL DE CALIDAD 3.01 3.02 3.03 3.04

B.4

Ro t ura d e p ro b e t a s y c o nst a nc ia G a st o s e n d ise ño d e m e zc la s G a st o s d e t e rm ina c ió n p ro c t o r m o d ific a d o G a st o s d e c o nt ro l d e d e nsid a d e s e n t o d o e l p ro ye c t o

GASTOS FINANCIEROS 4.01 4.02 4.03 4.04 4.05 4.06

B.5

DESCRIPCION

C ARTA FIANZA Vig e nc ia d e Po d e r y g a st o s no t a ria le s Prim a C a rt a Fia nza Fie l C um p lim ie nt o Prim a C a rt a Fia nza d e Ad e la nt o Dire c t o Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o Dire c t o Prim a C a rt a Fia nza Ad e la nt o M a t e ria le s Prim e ra Re no v a c ió n C a rt a Fia nza Ad e la nt o M a t e ria le s

EST M ES M ES M ES M ES M ES

SEGUROS Y SALUD EN OBRA 6.01 C o nt ra a c c id e nt e s ind iv id ua le s 6.02 C o nt ra a c c id e nt e s ind iv id ua le s 6.03 C o nt ra inst a la c io ne s, re sp o nsa b ilid a d c iv il e t c .

SUB-TOTAL GASTOS GENERALES (B)

2,442.13 AMPLIAC IO N DE PLAZO SUBTO TAL 1 IG V (18%) TOTAL

29 d .c . 70,821.66 12,747.90 83,569.56

Fuente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

 El análisis realizado por esta dependencia determina que, por la elaboración de documentos exigidos por el sector competente – plan COVID-19, se encuentra sustentado solo S/. 30,000.00 Veinte Mil y 00/100 Soles, exonerado de IGV, hecho que se puede corroborar con el contrato y comprobante de pago adjunto, además el plan se encuentra refrendado por dicho profesional encargado de su elaboración.  El análisis realizado por esta dependencia determina que, por los Gastos por el costo directo por la Adecuación y Adaptación de los ambientes de trabajo, el monto alcanza hasta S/. 186,553.65 (Ciento Ochenta y Seis Mil Quinientos Cincuenta y Tres y 65/100), que incluyen iGV, acorde al siguiente detalle: 1

El Contratista solicita las Adecuaciones y Adaptaciones, Insumos entre otros, por el periodo total de ejecución de obra:

Fuente: Extraído de solicitud de Contratista

2

Sobre el Costo Directo por Adecuación y Adaptación de los ambientes de trabajo luego del análisis se ha realizado los ajustes al presupuesto solicitado (APU y Metrados), adecuando varias actividades al periodo correspondiente de 24 días calendarios y agregando componentes esenciales para atenciones COVID-19, acorde a lo siguiente: -

-

Construcción de Tópico. - Este ambiente es de necesidad primordial para garantizar el cumplimiento de los protocolos de seguridad establecidos en la normativa vigente del sector. Implementación de Tópico. - Además, se agregó el equipamiento mínimo para la atención del personal de obra en caso se requiera, con esto se garantizará una respuesta rápida por parte del personal de SALUD considerado para el proyecto. Se optimizaron las cantidades del metrado de la partida de insumos, teniendo en cuenta solo el periodo de Adecuación y Adaptación de los ambientes de trabajo. Optimización de las cantidades de los Equipos de protección Individual solicitados por el contratista. Se agregó la CARETA FACIAL, ya que se cambiaron las mascarillas N95, no exigidas según norma, por mascarillas comunitarias. Se cambió el insumo MASCARILLA TELA NOTEX 80 G, por la mascarilla de uso comunitario (TELA REUTILIZABLE), por su mayor tiempo de vida útil en condiciones de trabajo pesado.

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

Fuente: Elaboracion propia

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud”

 El análisis realizado por esta dependencia determina que, por los Gastos Generales Variables que se generan por la Adecuación y Adaptación de los ambientes de trabajo, el monto alcanza hasta S/. 73,776.12 (Setenta y Tres Mil Setecientos Setenta y Seis y 12/100 soles), que incluyen IGV, acorde al siguiente detalle: 1

Sobre los Gastos Variables, el análisis se elabora en virtud al costo ofertado y las especialidades requeridas para esta etapa, habiéndose actualizado a 24 d.c. acorde con lo determinado en la cuantificación por Re movilización, Adecuación y Adaptación de Ambientes se determina un monto de S/. 73,776.12 (Setenta y Tres Mil Setecientos Setenta y Seis y 12/100 soles), que incluye IGV; habiéndose deducido lo siguiente por no requerirse en este periodo:       

Arquitecto especialista Hospitales Ingeniero Especialista en Instalaciones Mecánicas. Ingeniero Especialista en Comunicaciones Especialista en Equipamiento Medico Jefe de Equipo Mecánico Gastos de Oficina y Varios (Licencia de Construcción, Tramites ante concesionarios y otros) Gastos de Control de Calidad

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” DESAGREGADO DE GASTOS GENERALES - PERIODO DEL30- 07-2020 HASTA EL22- 08-2020 ( B ) GASTOS GENERALES VARIABLES ITEM

B.1

VALOR OFERTADO S/ .

PRECIO x DIA S/ .

me s me s me s me s me s me s me s me s me s me s me s me s me s me s me s

95,000.00 54,000.00 351,500.00 144,000.00 38,400.00 24,000.00 32,000.00 32,000.00 25,600.00 25,600.00 12,000.00 4,700.00 81,000.00 49,500.00 97,200.00

175.93 100.00 650.93 266.67 44.44 59.26 59.26 150.00 91.67 180.00

EST EST EST EST EST M ES M ES M ES EST EST EST EST EST EST EST

1,000.00 1,500.00 4,500.00 2,500.00 4,000.00 4,500.00 13,500.00 4,500.00 6,400.00 5,000.00 2,500.00 7,000.00 7,500.00 2,500.00 9,000.00

8.33 4.63 7.41 8.33 25.00 8.33 12.96 16.67 -

Und

SUELDOS Y SALARIOS 1.01 1.02 1.05 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18

B.2

Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o Sue ld o

d e G e re nt e d e O b ra d e Ad m inist ra d o r d e O b ra d e Ing e nie ro Re sid e nt e d e Ing e nie ro Se g urid a d Ind u st ria l d e Arq uit e c t o e sp e c ia list a Ho sp it a le s d e Ing e nie ro Esp e c ia list a e n Est ruc t ura s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s Sa nit a ria s d e Ing e nie ro Esp e c ia list a Inst a la c io ne s Ele c t ric a s d e Ing e nie ro Esp e c ia list a e n Inst a la c io ne s M e c a nic a s d e Ing e nie ro Esp e c ia list a e n C o m unic a c io ne s d e Esp e c ia list a e n Eq uip a mie nt o M e d ic o d e Je fe d e Eq uip o M e c a nic o d e l M a e st ro d e O b ra d e Alma c e n e ro d e G ua rd ia ne s d e Alma c e n e s

OBSERVACIONES

-

No se considera la especialidad en esta etapa.

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

GASTOS DE OFICINA Y SERVICIOS 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.12 2.12 2.12

B.3

Do c um e nt a c ió n C O NSUC O DE C e rt ific a d o s C IP y o t ro s Fo t o g ra fía y C o p ia s Liq uid a c ió n d e O b ra Pla no s d e Re p la nt e o Am o rt iza c ió n d e e q uip o s d e o fic ina Alq uile r d e C a m io n e t a y o t ro s Ut ile s d e e sc rit o rio y a se o Lic e nc ia d e C o nst ruc c io n Tra m it e s y Se rv ic io s a nt e e l c o n se c io na rio e le c t ric o Tra m it e s y Se rv ic io s a nt e e l c o n se c io na rio Sa ne a mie nt o Tra m it e s y Se rv ic io s d e C o m unic a c io ne s Tra m it e s a nt e O sine rm in g Tra m it e a n t e la M u nic ip a lid a d Va rio s Se rv ic io Va rio s

GASTOS DE CONTROL DE CALIDAD 3.01 3.02 3.03 3.04

B.4

Ro t ura d e p ro b e t a s y c o nst a nc ia G a st o s e n d ise ño d e m e zc la s G a st o s d e t e rm ina c ió n p ro c t o r mo d ific a d o G a st o s d e c o nt ro l d e d e nsid a d e s e n t o d o e l p ro ye c t o

11,250.00 7,500.00 18,000.00 10,000.00

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa. No se considera la especialidad en esta etapa.

GASTOS FINANCIEROS 4.01 4.02 4.03 4.04 4.05 4.06

B.5

DESCRIPCION

CARTA FIANZA Vig e nc ia d e Po d e r y g a st o s no t a ria le s Prim a C a rt a Fia nza Fie l C um p lim ie nt o Prim a C a rt a Fia nza d e Ad e la nt o Dire c t o Prim e ra Re no v a c ió n C a rt a Fia n za Ad e la nt o Dire c t o Prim a C a rt a Fia nza Ad e la n t o M a t e ria le s Prim e ra Re no v a c ió n C a rt a Fia n za Ad e la nt o M a t e ria le s

EST M ES M ES M ES M ES M ES

4,000.00 55,091.63 73,455.51 22,036.65 146,911.02 44,073.31

SEGUROS Y SALUD EN OBRA 6.01 C o nt ra a c c id e nt e s ind iv id u a le s 6.02 C o nt ra a c c id e nt e s ind iv id u a le s 6.03 C o nt ra inst a la c io ne s, re sp o nsa b ilid a d c iv il e t c .

18,000.00 6,480.00 27,000.00

SUB-TOTAL GASTOS GENERALES (B)

7.41 102.02 136.03 40.81 272.06 81.62 33.33 12.00 50.00

2,605.09 AMPLIAC IO N DE PLAZO SUBTO TAL 1 IG V (18%) TOTAL

24 d .c . 62,522.14 11,253.98 73,776.12

5. CONCLUSIONES y RECOMENDACIONES:  El contratista, CONSORCIO RENOVACION, ha presentado la solicitud de Ampliación Excepcional de Plazo en concordancia con Directiva N° 005-2020-OSCE/CD, por lo tanto, luego de la evaluación realizada por esta dependencia se recomienda a la Entidad, Gobierno Regional de Ucayali, declarar PROCEDENTE PARCIALMENTE la solicitud de Ampliación Excepcional de Plazo por 257 días calendarios, de acuerdo al siguiente detalle:

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

GOBIERNO REGIONAL DE UCAYALI GERENCIA REGIONAL DE INFRAESTRUCTURA SUB GERENCIA DE OBRAS “Año de la universalización de la salud” FASE

DIAS SOLICITADOS

CONCEPTO

FASE 1 PARALIZACION TRAMITE ADMINISTRATIVO A.E.P. FASE 2 ADECUACIONES Y ADAPTACIONES AMBIENTES EJECUCION DE OBRAS CON RENDIMIENTO REDUCIDO POR LAS FASE 3 MEDIDAS DE PREVENCION COVID-19 TOTAL SALDO DE PLAZO

DIAS DETERMINADOS 107 29 (14+15) 24

107 29 30

(14+15)

624

(496+128)

593

(496+97)

790 496 294

(*)

753 496 257

(*)

(*) Saldo de plazo contractual

 Así también, respecto a los costos se ha determinado que LOS COSTOS DE LA IMPLEMENTACIÓN DE LAS MEDIDAS PARA LA PREVENCIÓN Y CONTROL FRENTE A LA PROPAGACIÓN DEL COVID-19 DISPUESTAS POR LOS SECTORES COMPETENTES PARA LA REANUDACIÓN DE LOS TRABAJOS, de acuerdo al Decreto Legislativo 1486 y la Directiva N° 005-2020-OSCE/CD, presenta el siguiente detalle: FASE

COSTO SOLICITADO

CONCEPTO

MATERIALES, MAQUINARIAS EN STAND BY Y SERVICIOS PARALIZACION TRAMITE ADMINISTRATIVO A.E.P. COSTO DIRECTO POR DOCUMENTOS COVID-19 FASE 2 ADECUACIONES Y ADAPTACIONES AMBIENTES GASTOS VARIABLES POR ADECUACION Y ADAPTACION AMBIENTES FASE 1

S/ S/ S/ S/ S/

375,201.25 259,496.48 88,135.11 70,000.00 1,625,901.74

S/

91,174.26

FASE 3 EJECUCION DE OBRAS CON RENDIMIENTO REDUCIDO POR S/ LAS MEDIDAS DE PREVENCION COVID-19 TOTAL S/ 2,509,908.84

SIN IGV SIN IGV SIN IGV SIN IGV SIN IGV SIN IGV

COSTO DETERMINADO S/ S/ S/ S/ S/ S/ S/

103,533.20 CON IGV 273,401.78 CON IGV 83,569.56 CON IGV 30,000.00 EXON IGV 186,553.65 CON IGV 73,776.12 -

CON IGV (*)

S/ 750,834.31

(*) No lo ha solicitado el Contratista y tampoco forma parte de esta evaluacion.

 Finalmente se recomienda NOTIFICAR al Contratista CONSORCIO RENOVACION a más tardar hasta el día 29 DE JULIO DEL 2020 sobre la Procedencia de la solicitud de ampliación excepcional de plazo de acuerdo a la evaluación realizada por esta dependencia, de acuerdo al detalle mostrado en los cuadros precedentes y 02 archivadores de palanca que suman 667 folios. Atentamente, Cc: Archivo Personal/File de Obra

Dirección: Jr. Raymondi Nº 220 - Pucallpa Teléf. (061)57-1627/Av. Arequipa Nº 810. Oficina 901 - Lima Telef. (01) 424-6320

Related Documents


More Documents from "Estevan Leonardo"