Gs_ep_est_001_en-cost Estimating

  • Uploaded by: Mathias Onosemuode
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Gs_ep_est_001_en-cost Estimating as PDF for free.

More details

  • Words: 10,071
  • Pages: 28
Loading documents preview...
GENERAL SPECIFICATION COST ESTIMATING GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering.

01

06/2015

Organisation change – January 2015

00

10/2013

First issue

Rev.

Date

Owning entity: DSO/ED

Purpose of the revision

Managing entity: DSO/ED/IC

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 2 of 28

Contents 1. Scope ....................................................................................................................... 3 2. Reference documents ............................................................................................. 3 3. Abbreviations and Definition ................................................................................. 4 3.1

Abbreviations: ................................................................................................................. 4

3.2

Definition ......................................................................................................................... 5

4. List of required documents .................................................................................... 6 4.1

General Project Documents ............................................................................................ 6

4.2

Documents for Tendering ................................................................................................ 7

4.3

Technical Documents for all Types of Projects ................................................................ 7

4.4

Onshore Facilities ......................................................................................................... 10

4.5

Offshore facilities .......................................................................................................... 12

4.6

Brownfield / Revamping ................................................................................................ 15

Bibliography................................................................................................................. 21 Appendix 1

Equipment list.................................................................................................. 22

Appendix 2

Quantity Estimate Summary: All Units (ISBL &OSBL) .................................... 23

Appendix 3

Piping Qty Summary ....................................................................................... 25

Appendix 4

Electrical Material Summary: All Units ............................................................. 26

Appendix 5

Instrumentation Material Summary: All Units ................................................... 27

Appendix 6

Construction Breakdown (Qties & Direct Man-hours): All Units........................ 28

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 3 of 28

1. Scope This document defines the Company requirements to be applied in the execution and reporting of the FEED or the BED for a follow up/comparison with the previous estimates. The information delivered at the end of FEED/BED in term of quantities is expected to correspond to Class 2 estimates according to AACE Classification. This specification lists all drawings, sketches, specifications, quantities summary, assumptions, exclusions, and other technical deliverables used for the preparation of the estimate to ensure that it shall be as complete as possible and up-to-date. This specification is applicable for all facilities that Company intends to built or decommission, onshore and/or offshore. The delivery of the information to cost estimating entity of the project will be included in the FEED/BED work time schedule.

2. Reference documents The reference documents listed below form an integral part of this General Specification. External Documents Unless otherwise stipulated, the applicable version of these documents, including relevant appendices and supplements, is the latest revision published at the effective date of this document. Reference Title ACCE 17R-97

Cost Estimate Classification System

ACCE 31R-03

Reviewing, Validating, and Documenting the Estimate

ACCE 34R-05

Basis of Estimate

ACCE 36R-08

Development of Cost estimate Plans – as applied in engineering, procurement, and construction for the process industries

Total General Specifications Unless stipulated otherwise, the applicable version of these documents, including relevant appendices and supplements, is the latest revision published. Reference Title GS EP ECP 105

Process and Flow Assurance deliverables to be prepared by Contractor during engineering phase

GS EP EXP 501

Equipment and piping numbering

GS EP ELE 001

Electrical Design Criteria

GS EP INS 000

Minimum Contractor Documents Requirements

GS EP SAF 021

Layout (Cancelled Document)

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Reference

Page: 4 of 28

Title

GS EP SAF 380

Safety Engineering Requirements for an F(P)SO

GS EP PLR 001

Documentation requirements

GS EP PLR 100

Submarine pipeline systems

GS EP PLR 104

Onshore pipeline systems

GS EP SPS 001

Subsea Production Systems General Design Requirements

GS EP STR 001

Weight Monitoring and Weighing offshore units

GS EP STR 100

Offshore Steel Structure General

GS EP STR 631

CALM Buoy Terminals

GS EP STR 651

General Principles of a F(P)SO design

3. Abbreviations and Definition 3.1 Abbreviations: AACE :

Previously American Association of Cost Engineering which became the Association for the Advancement of Cost Engineering before adopting the current official title of AACE International

BED:

Basic Engineering Design

CAPEX :

CAPital EXpenditure

EPCC :

Engineering, Procurement, Construction, Commissioning

FEED :

Front End Engineering Design

ISBL :

InSide Battery Limit

MTO

Material Take Off

BOQ

Bill of Quantities

OPEX

OPerational EXpenditure

OSBL :

OutSide Battery Limit

PEP :

Project Execution Plan

RFSU :

Ready For Start Up

SOR :

Statement Of Requirement

SIMOPS

Simultaneous Operations, i.e. construction (or drilling) and production activities in the same perimeter at the same time.

TSF :

Temporary Site Facilities

WBS :

Work Breakdown Structure

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 5 of 28

3.2 Definition Company: Total or Total in joint venture and in the present case, the Cost Estimating entity. Contractor: Engineering Entity or Joint Venture under contract with Company for the FEED or BED. Sub-contractor: External firms in contract with Contractor (including Vendors). Engineering (E of EPC): Engineering services related to detailed studies (including procurement services), construction supervision services and contractor temporary site facilities. Procurement (P of EPC): refer to the main equipments and bulk purchasing activities Construction (C of EPC): Construction activities on site (civil works, structural steel, mechanical erection, electricity, instrumentation, painting, insulation..) or at yard Commissioning The integrated application of a set of engineering techniques and procedures to check, inspect and test every operational component of the PLANT. ISBL: InSide Boundary Limit; Geographical area where are concentrated process equipments (columns, exchangers, drums…). OSBL: OutSide Boundary Limit; External parts of ISBL area, corresponding to utilities (generation and distribution) and off sites (storages, product logistic, well pad, manifolds, remote compressions stations) Grass Root (or Greenfield): Project is defined as “grass-root” when works are executed in a free area where construction activities are under the full responsibility of the contractor. Brownfield: Project is defined as “Brownfield” when works are executed: • in a free space inside an existing production site, requiring safety permits and regulations for construction operations provided by the contractor under derogation of the company • or directly within the existing production site, with safety permits and regulations for construction operations provided by the Company (Simultaneous Operations-SIMOPS) Revamping: Project is defined as “revamping” when works concern modifications of existing process units ( ie debottlenecking). Material Take Off: Listing of material with specifications and dimensions potentially not summarized Bill of Quantities: Material Take Off, sorted, quantified and summarized according to a specific format. Each MTO must be issued with the corresponding BOQ. Direct Productive man-hours: Defined as hours spent by all disciplines teams from workers to foreman (i.e. Workforce) for construction of permanent installations. Hours related to staff management (supervision, secretaries) and hours related to temporary installations (like scaffolding) are excluded (= Indirect productive hours). Standard Man-hours are defined as US Gulf Coast basis (where local productivity = 1). Indirect Productive man-hours: Hours spent in support of the workforce performing the measurable work i.e. material handling, scaffolding, construction equipment maintenance, site cleaning, supervisors and inspectors.

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 6 of 28

Non Productive man-hours: Hours spent by the workforce not directly linked to the physical progress of the work i.e. which result from work interruptions/stand-by, waiting for material, interface problems, waiting on work permits, accidents, sickness. Local site travel and meal time may also considered as non-productive man-hours depending on the regulation and context. Non technical hours related to management i.e. project management team. Productivity: During cost estimating phase: Productivity is the ratio between the necessary number of manhours for the achievement of the given work on a given site and the necessary number of manhours to achieve the same work on the reference site (defined as US Gulf Coast basis.) During Project phase: Productivity is defined as the ratio between the realized or measured direct productive man-hours and the planned or anticipated direct productive man-hours which takes into account the local productivity. Note: If the realized productivity is =1 it means that the anticipated local productivity during estimation was correct. If it is <> 1 it means that the local productivity is better or worse. Technical Allowance: Percentage to be added to quantities to account for routing variations, lines diameter adjustment, plot rearrangements during detailed studies. The technical allowances are based on contractor’s experience on past projects. Material Take Off Allowances: Percentage to be added to the measured quantities because: • the relevant scope is not included in the FEED/ BED contract, • it would consume too much time and it does not worth it, • information is not available at this stage of development. For Offshore, the Material allowances are given by GS EP STR 001. Purchased Allowances: Percentage to be added to the quantities plus material take off allowances to take into account the cut and losses. The Purchased allowances are based on contractor’s experience on past projects.

4. List of required documents 4.1 General Project Documents 4.1.1 PEP • FEED/BED CONTRACTOR Project Execution Plan 4.1.2 Project General Conditions • Seismic study report • Geotechnical Site Investigation • Logistics reports • Split of work between greenfields / brownfield / SIMOPS areas

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 7 of 28

4.1.3 Risk Register • FEED/BED contractor risk register 4.1.4 Work Time Schedule • FEED/BED approved and updated level 3 work time schedule. 4.1.5 Documentation Management • Project Document Numbering Procedure • Project Master Document Register 4.1.6 Close Out Report • FEED or BED close out report if available

4.2 Documents for Tendering Should the scope of work of the FEED/BED contractor include the preparation of all or part of the documents for the invitation to tenders, the said documentation shall be provided to the cost estimating entity of the project. 4.2.1 Long Lead Items Invitation to Tenders related to the equipment/material(s) which will be or have been purchased by the Company, with all documents 4.2.2 EPC or EPCC Tender Documents The invitation to tenders shall be issued to the cost estimating entity of the project with all relevant exhibits. Particular attention shall be paid to: • The Work Breakdown Structure, • The scope of work / services requested to the Contractor, which are normally part of the company scope of work (facilities to Company, commissioning / pre-OPEX activities) • The interfaces between other contractors and company from Effective Date up to the RFSU dates. • The Temporary Site Facilities 4.2.3 Local Content Prequalification reports of potential local contractors/subcontractors or participants to the tender such as yard visits reports shall be provided.

4.3 Technical Documents for all Types of Projects The documents required at the end of the FEED or the BED to enable the update of the cost estimate shall be issued as summarized and as complete as possible under the format of the

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 8 of 28

BOQ’s attached in the Appendices, with dedicated explanatory notes or if already specified under the BOQ’s format requested in the Company specifications. Should derogations to the existing company specifications been granted or being requested with significant quantity/cost impact, the supporting documents shall be provided. 4.3.1 Process Following the requirements of GS EP ECP 105 the documents listed here after shall be provided in their latest revision in electronic format (pdf issued from native formats or preferably native format) for all type of facilities relevant to the project • Process design procedure • Process block flow diagram • Process heat and material balances • Process Flow Diagrams (PFD's) • Utilities balances • Utilities Flow diagrams (UFD's) • Piping and Instrumentation Diagrams (P&ID's) • Piping Material Classes • Process data sheets for equipments • Process instrument data sheets • Fluids list • Lines list • Process, Utilities and Offsites description (Basis of Design) • Process operating philosophy • Critical Spare parts 4.3.2 Lay out • Overall Plot Plan (Offshore and Onshore) • ISBL Units Plot Plan • OSBL Plot Plan (Well Pads, Manifold Station, Compressions Stations, tank farms, offloading stations, and the like) • Offshore and Onshore General Arrangement Key Plan • Plant Road Layout and Details • Overall Safety Distances Layouts • Structural Specification for interconnecting piperack (Concrete / Structural Steel) • Structural Specification for modularization

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 9 of 28

• Sewers and Drainage Construction Specification • Buildings layouts and specifications (lists with number of floors, elevation, dimensions, specifications blast proof, HVAC and the like) 4.3.3 Electrical As per GS EP ELE 001 the following documents shall be issued • Electrical Basis of Design • Single Line Diagram • Electrical Load Schedule • Specification for Electrical Control System • MTO’s & BOQ’s (See Appendix 4 Electrical material summary) 4.3.4 Instruments & telecommunications As per GS EP INS 000 the following documents shall be issued • Overall Control and Instrumentation Philosophy • Telecoms Philosophy • ICSS Functional & Instrumentation typical loop diagrams Block Diagram • Telecommunications System Block Diagram • Instruments MTO’s & BOQ’s (See Appendix 5 Instrumentation material summary) (IO’s, Control valves, On/Off Valves, Relief Valves ) • Analyzers shelters 4.3.5 Others • Painting and Corrosion Protection Specification • Insulation specification • Fireproofing specification • Heat and Electrical tracing specification • Safety Concept 4.3.6 Equipment list The equipment list of all main equipment by unit for onshore facilities - ISBL or OSBL – of offshore facilities shall be issued, fully loaded with the required information in Excel format according to the model attached in Appendix 1. The definition of main equipments concerns the equipment present in the succession of the operations in the fluid(s) processing to reach the required products specifications set in the objectives of the plant processing at the exception of valves, piping, fittings, electrical equipment (distribution) and instruments. The equipment list shall include for the “packages” equipment,

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 10 of 28

the auxiliary equipment (ie for a compressor, its driver(s), lube oil console). These equipment lists concern ISBL units but also OSBL units. However, it is acknowledged that the equipment lists may include some equipment which are considered as main equipment due to their importance in the operations or due to their costs or their manufacturing duration (Crane, transformers, HV motors, special valves etc). Should these equipments be included in the equipment list, they shall be however clearly segregated from the previous ones to prevent distortions on application of estimating ratios. All other equipments not listed in the equipments list but incorporated in the plant shall be considered as “bulk material” At the end of FEED/BED, the equipment lists are deemed to be complete. Should this stage not been reached, an explanatory note shall be issued. The equipment list should include the capital spares ie spare for which the manufacturing time is as long as the item itself. 4.3.7 Summary Units For each process package (ISBL and OSBL) (storages, product logistic, well pad, manifolds, remote compressions stations), a summary unit shall be prepared. (See Appendix 2);

4.4 Onshore Facilities 4.4.1 ISBL / OSBL Units If the equipment lists are deemed to be complete, it is understood that at the end of FEED/BED, all bulk material quantities for a grass roots project for all disciplines shall not be measured through complete MTO’s prior to the detailed engineering phase. For brownfield / revamping projects, it is expected that the MTOs / BOQs shall have a level of detail corresponding to what is usually obtained in detailed engineering. All MTO’s shall be accompanied with BOQ’s.(See Appendices) Four methodologies are expected for the estimating of the quantities: • Parametric Models: This methodology uses parametric factors based on main equipment technical data to calculate for each disciplines (civil works, structural steel, mechanical erection, electricity, instrumentation…) quantities and construction man-hours. Such method can be implemented only if a process equipment list is issued and includes exhaustively all design data for each piece of equipment, such as physical dimensions, capacity, metallurgy, electrical power, pressure, temperature, etc…. • Semi detailed methodology: Quantities estimate is based on preliminary materials take off or analogy multiplied by take-off allowances to take into account all non measured quantities and additional quantities during detailed engineering. The take-off allowances are either based on contractor’s experience or specified by Company in the case of offshore facilities. The quantities generated by these allowances shall be always shown separately.

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 11 of 28

• Detailed methodology This method is based on detailed and more complete MTO for the considered discipline and shall be applied for Revamping / Brownfield projects. For the detailed methodology, smaller take off allowances than for semi detailed methodology shall be applied. • Internal and supplier’s tenders: This method is based on the use of internal bases or tools developed by engineering and by consultation with suppliers. Parametrics

Semi Detailed

Site preparation

Internal and Detailed

Supplier tenders

X

ISBL Facilities Main equipment

X

Bulks material X

Piping Ab gr and Und Gr Electricity

X

Instrumentation

X

Protection against fire

X (Br)

X

Sub-contracts Civil Works

X

Structural steel

X

Painting

X

Insulation and Fire-proofing

X

Tracing

X

OSBL Wellpads

As ISBL above

Manif & Compr Stations

As ISBL above

Interconnecting

X

Utilities

As ISBL above

Storage (Tanks, Bullets ...)

As ISBL above

Export fac. (pump load arm)

As ISBL above

Buildings incl E/I stations

X

Camps

X

Roads

X

Jetty

X

Others (Pits, Basin)

X

Technical Allowances for each discipline

X

For each unit – plant component, the methodology used for the generation of the quantities shall be explained through a dedicated report for each discipline mentioned in the tabulation here above and more specifically for: • Piping: the report shall indicate, what has been the extent of the material take off via which mean it has been performed, which diameter has been considered, not considered, what has been counted or generated by ratios. It shall segregate Above ground and Underground, Piping, Valves, Fittings, Flanges, Miscellaneous, Supports. Electrical: what has been the methodology used for generation of the quantities for electrical generation and distribution Special attention shall be made to HV/MV/LV Installed power, HV/MV/LV

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 12 of 28

transformers – switchgears , Diesel Generator , UPS , cables lengths, lighting fixtures, earthing) • Instruments: what has been the methodology used for generation of the quantities MTO Instruments. Special attention shall be made to Control- Relief- On/Off Automatic Valves, I/O schedules - PCS – Fire & Gas System - ESD System, Metering Systems, Analyzers • Civil Works: Special attention shall be paid to the all civil works other than equipment foundations (site preparation, piling, paving, and others) • Structural Steel: Primary, secondary & miscellaneous structure By discipline, the various allowances applied to the MTO’s to reach the erected quantities shall be listed in the report in a specific tabulation. 4.4.2 Onshore Pipelines As per GS EP PLR 001 and GS EP PLR 104, the design report with the associated follow-up data sheet shall be issued with relevant and as complete as possible MTO’s and drawings. The items not measured shall be clearly highlighted. • Preliminary survey • Preliminary geotechnical data • Preliminary environmental information • Export Pipeline Overall Route • Export Pipeline Overall and Alignment Maps • Specific (River, Road, and the like) Crossings Design, Lists & drawings if any • Pig Stations and Isolation Valves • Export Line Protection Design (Cathodic and Anticorrosion external/ internal) • Pipelay Analysis • Export Pipeline Landfall Layout if any • Typical and particular Trench Layout Details (in particular in difficult environment – mountains) • MTO’s & BOQ’s

4.5 Offshore facilities For Offshore facilities, most of the information required for the cost estimating update are listed in several specifications which are prescriptive in term of format and content of information. 4.5.1 Fixed Platforms As per GS EP STR 100 & GS EP STR 001 the following reports shall be issued • Weight report showing the applied contingency. The piping weight report shall address the different material of piping.

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 13 of 28

• Topsides Equipment List (as per Appendix 1 format)

• Structural materials take off. 4.5.2 Living Quarters • Living Quarter Equipment List • Living Quarter Layouts (plan views, sections and elevations) • Living Quarter design report & specification • Living Quarter weight report 4.5.3 Floating platforms (FPSO) As per GS EP STR 651 the following information shall be provided • FPSO General Arrangement • FPSO Weight Control Procedure • FPSO Weight Control Report • FPSO Capital Spare part list • Topsides Equipment List (as per Appendix 1 format) • FPSO Topside Structural Design Brief • Topside Overall Layout Artistic Views (from 3 D model) • FPSO Overall lay-out drawings (all Decks, including Hull Deck) • FPSO Overall elevation drawings (North, South, East, West) • Process & Utility modules lay-out drawings • Process & Utility modules elevation drawings (North, South, East, West) • Technical Buildings lay-out drawings for all Levels (Electrical, Instrument, and Telecom) • Technical Buildings elevation drawings (North, South, East, West) • Hull Naval Architecture and Structure Design Brief • Hull Equipment List (as per Appendix 1 format) • Hull & appurtenances weight report • Hull PFD+UFD+P&ID’s • Mooring (& Turret if any) Equipment List • Mooring (& Turret if any) General Description • Mooring General Arrangement (plan views, sections and elevations) • Mooring (& Turret if any) Installation and Hook-up Philosophy • Mooring System MTO’s & BOQ’s

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 14 of 28

4.5.4 Catenary Anchor Leg Mooring Buoy systems As per GS EP STR 631 the following information shall be provided • Buoy System Design study report (including PLEM, Risers, Mooring, Anchors, monitoring system) • Buoy System design load • Buoy System drawings • Buoy System datasheets 4.5.5 Subsea Umbilicals Risers Flowlines As per GS EP PLR 001 & GS EP PLR 100 • SURF Design Reports and specifications including field layout, SURF material and types, bends, valves, fittings, tees, forgings, spools and jumpers, flying leads, mid water arches, Subsea distribution units and umbilical termination units, Supporting, Tie-ins, Crossing, Capital spares, • MTO’s & BOQ’s, • Cathodic protection • Internal and External Anti Corrosion Coating • Installation engineering report 4.5.6 Subsea Production or injection Systems As per GS EP SPS 001 the following information shall be made available • Design specification for X-Mas tree Wellhead, SPS control system including topside equipment, installation and workover system, structures including manifold, tie-in systems , MPFM, connection, valves, tools, ROV, capital spares and the like • Subsea Field lay out, • SPS Production or injection PFD’s and P&ID’s • SPS Control systems Block Diagram (Electrical, Hydraulic, Chemicals, Fiber Optic) • External Anti-corrosion Coating Specification • Cathodic Protection Specification • MTO & BOQ 4.5.7 Export Pipelines As per GS EP PLR 001 & GS EP PLR 100, the design report with the associated follow-up data sheet shall be issued with relevant and as complete as possible MTO’s and drawings. The items not measured shall be clearly highlighted. • Export Pipeline Overall Route including shore approach / land fall • Export Pipeline Overall and Alignment maps

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 15 of 28

• Crossing and free span Design & lists if any • Export Line Protection Design (Cathodic and Anticorrosion external/ internal) • Installation engineering report • Export Pipeline Landfall Layout

4.6 Brownfield / Revamping The brownfield or revamping activities at site are considered challenging by Company in terms of HSEQ, schedule slippage and cost overruns. In order to mitigate those risks, it is required to develop the engineering studies at the maximum level of detail possible at FEED/BED by conducting all necessary surveys and improving the quality of all take offs. This section deals with the methodology on Man-hour and POB estimates, and provides a list of required documents in line with this methodology. 4.6.1 Methodology of man-hour Estimates Man-hour estimates of brownfield modifications are normally conducted according 4 steps. 1. Definition of the (detailed) Scope of Work per discipline 2. Definition of quantities / volumes of per discipline by BOQ / MTO 3. Estimate of the required direct productive man-hours in the reference site by standard man-hour ratios with split between work to be prefabricated vs erected 4. Estimate of the total required man-hours on site by application of the following factors -

-

A local productivity factor related to the country of execution, to compensate for cultural/social differences ( tea breaks / unions obligations etc) but also due to climate aspects (hot, artic, monsoon). A site productivity factor, which takes into account:

For Onshore brownfield works: • The site conditions: Access to site, confined space, congested area • The operating conditions, SIMOPS or shutdown For Offshore brownfield works: • The Site conditions: inboard, overboard, confined space, congested area • The operating conditions: SIMOPS or shutdown. This gives the total of productive direct man-hours • A ratio of direct / indirect productive man-hours to allow for material handling, scaffolding, construction equipment maintenance, site cleaning, supervisors and inspectors. This gives the total of productive man-hours (direct + indirect) • A ratio of productive versus non productive hours or downtime coefficient to allow for interruptions/stand-by, waiting for material, interface problems, waiting on work permits,

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 16 of 28

repairs and reworks, accidents, sickness. Local site travel and meal time might also be considered as non-productive man-hours. Non technical hours related to management i.e. project management team are excluded. This gives the total amount of construction man-hours which shall be split into Direct and Indirect. Note 1: Particular attention shall be brought to the buildup of those factors: the Local Productivity factor sometimes also includes part of the downtime and even part of the site conditions. It shall be explained which effect is taken into account in which factor to avoid a doubling effect. Note 2: The man-hours provided shall concern the number of paid man-hours only. E.g. if transport from / to site is paid, it shall be noted if they are included in the downtime or compensated in the rate. Note 3: Management, Coordination, Engineering and any activities that are not related to construction are not part of this estimate. Example: 2000 meter cable (incl. contingency) needs to be pulled on a platform offshore Congo. According standard man-hour estimates this will take 0,3 hr/m and thus 600 hours. The local productivity factor for Congo is taken as 1.8 [-]. The site productivity factor for the offshore location is typically 2 during SIMOPS. The total of required productive direct man-hours is 2160 hrs. On average workers spend about 20% of their time on material handling and site cleaning. For every 10 workers there is a safety watch plus a supervisor. A total of 500 productive hrs of scaffolding is required, which is about 25 %. The total direct / Indirect ratio is 1.25x1.25x1.25 = 1.95 [-]. The total of productive direct + indirect man-hours is 4220 hrs. Daily the workers spend 4 hours on safety talks, breaks, permit signature and transfer from the bridge linked flotel. Mob / demob, occasional drills or standby due to heavy lifts count for an additional half an hour per day standby. The overall downtime coefficient is 12/7.5 =1.6 [-]. The total amount of estimated construction man-hours in this example is 6752 hrs or 563 mandays. 4.6.2 Methodology on manpower / POB estimates The number and distribution of POB on site/worksite determines the available workforce to execute the total amount of construction man-hours, and thus the duration of the work. For the construction period a manpower-planning shall be issued for the distinct phases of the work. Typical phases are before-shutdown/shutdown/after-shutdown phases or pre-work (e.g. Civil) / construction / commissioning and start-up phases. Phases can also depend on the available bedding at site. For each phase it shall be estimated what people are to be expected on site and their respective functions. Distinctions shall be made between Contractor and Company and those

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 17 of 28

contributing to the construction man-hours of the project and those who are not. In more detail, manpower can be looked at on a discipline level (e.g. Painting, Scaffolding, Electrical and Instrumentation, Piping/Mechanical, Etc.). By estimating the number of workers on the worksite (i.e. in direct vicinity of the works), it shall be verified a reasonable number will not be exceeded. Working in a congested area affects the site productivity factor and can compromise safety. A distinction shall be made between day and nightshift. Moreover for Offshore works, the logistic to be mobilized shall be investigated: • Availibility and use of a Flotel in the area • Mobilisation of a Flotel dedicated to the scope of work • Type of connection of the Flotel to the platform (Transfer by Gangway / speed boat / helicopter) which has a direct impact on both POB and productivity Example: The previously mentioned job offshore Congo is part of a bigger project. For execution of the offshore works a Flotel has been mobilized with 200 POB with a gangway for connection between the Flotel and the platform. In SIMOPS the maximum platform POB is temporarily raised up to 75. (see the figure below)

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 18 of 28

The following manpower plan has been made for the pre shutdown SIMOPS phase: Activity

Shift

Bedding

AVG POB on Platform

Flotel Service Crew

Dayshift

18

-

(VM, Vessel crew, Catering services)

Nightshift

7

-

Dayshift

8

6

(RSES, operators, crane driver, field engineer) Nightshift

3

3

ON-site Support team (logistics & coordination)

Dayshift

4

On-site project team

Dayshift

6

4

4

4

Dayshift

4

4

Nightshift

2

2

Dayshift

3

3

Dayshift

4

3

2

2

8

8

Nightshift

16

16

Dayshift

15

15

Nightshift

4

4

Dayshift

8

8

Nightshift

3

3 24

COMPANY Personnel On-site Field Operations team

(Project Site Superintendent, Field engineer, Nightshift project controls engineer, Supervisors) Safety Supervisors and Watches CONTRACTOR 1: On-site Engineering support

-

CONTACTOR 2: Project Construction Project Management

(Superintendent, timekeeper, project engineer) Nightshift Piping & Mechanical Crew Electrical & Mechanical Crew CONTRACTOR 3: Scaffolding Services

Dayshift

CONTRACTOR 4: Painting campaign

Dayshift

24

Bedding for Infield shuttling teams & maintenance crew

Dayshift

16

Dayshift

118

75

41

34

Total Flotel

Nightshift Total

159

-

NA

Due to the limited number of platform POB, a nightshift has been installed for some of the piping & mechanical activities. Safety watches, scaffolders and some E&I crew have been put in the nightshift to support their activities. The cables will be installed by the electrical crew in dayshift. Without supervisor safety watch or scaffolding the total construction hours for the electrical crew is 4321 hrs (=6752/(1.25x1.25)).

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 19 of 28

With a realistic maximum E&I POB on the worksite of 10 people, the cable pulling will take approximately 36 days. The scaffolding (before and after) will take about 500 productive hours, which is about 1000 construction hours (again, excluding the safety watch and supervisor). With 8 scaffolders this will take approximately 10 days (e.g. 7 to built, 3 to dismantle). Note that Project Management of both Company and Contractor is not included in the Manhours, but does take a significant part of the bedding and POB. 4.6.3 Required data For an adequate detailed estimate of the required man-hours for a brownfield work or project it is required to list and detail the following parameters (where applicable). • Number, weight and discipline quantities in mt, m, m², m3 or unit, which are to be -

dismantled, scrapped, revamped reused or temporary relocated

-

prefabricated as part of a module

-

estimated location off construction yard newly installed or erected on site

-

part of the hook-up / integration works of prefab modules or equipment packages (* see note)

• List of the equipment units and their installation method (included in a prefabricated module onshore or separately installed offshore) • Type of mechanical work considered (Connection by flanges / Welded connections) • Scheduling conditions of the brownfield works, e.g. -

Before or After Shutdown (BSD/ASD) generally in SIMOPS with production

-

During Shutdown (DSD)

-

Seasonality, if applicable (winter, summer, rain or monsoon season, etc)

-

day shift and night shifts or daylight only, etc.

• Conditions of site logistics of the workforce, e.g. -

Bedding of the workforce (bridge linked Flotel / distance to the worksite)

-

Daily Helicopter shuttle from Hotel / Flotel / Shorebase

-

Surfer shuttle

• A detailed Manpower-planning for distinct phase of the work, incorporating -

Bedding levels

-

POB levels

-

Company and Contractor personnel

-

Service and Support personnel

-

Construction Disciplines

-

Day and night shift

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 20 of 28

• The physical conditions of the worksite e.g. inboard, overboard, confined space, congested area. • Quantity of temporary works required, e.g. -

access scaffolding in m³ or mt

-

facilities such as accommodation, workshop, storage

-

temporary lifting equipment, winches, cranes, etc.

-

temporary (HSE) provisions on site for FiFi, Escape evacuation and rescue, PA system, lighting, etc.

• Details on special operations, such as heavy lifting, riser installation. • Details on “non measurable” works e.g. ICSS modification * NOTE: For the hook-up of modules or packages the Mhrs are calculated as follows: If the hook-up weight is included in the module weight: • Module hook up Mhrs (h)= Total module weight(t) x Hook up Mhrs (h/t) If the hook-up weight is not included in the module weight but its composition is not given: • Module hook up Mhrs (h)= hook-up weight x 150 (h/t) If the hook-up is not included in the module weight and it composition is given the man-hours are calculated as being a classical integration works.

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 21 of 28

Bibliography Reference GS EP EXP 501

Title of the publication Equipment and piping numbering

GS EP SAF 021

Layout (Cancelled Document)

GS EP SAF 380

Safety Engineering Requirements for an F(P)SO

ACCE 17R-97

Cost Estimate Classification System

ACCE 31R-03

Reviewing, Validating, and Documenting the Estimate

ACCE 34R-05

Basis of Estimate

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 22 of 28 Appendix 1

Appendix 1 Equipment list ID

Column name General comment:

1 2 3 4 5 6

Revision Equipment tag Equipment type Designation System/Subsystem name Module (yes/no)

7 8 9

Number of items % Design capacity per equipment Equipment design parameters

9.1. 9.2. 9.3. 9.4. 9.5. 9.6. 9.7. 9.8.

9.10. 10 10.1. 10.2. 10.3.

Pressure Generic/Pressure Shell (barg) Shell side/FV rating (yes/no) Pressure tube (barg) Tube side/FV rating (yes/no) Max temp generic/Temp shell (0C) Min temp generic/Temp shell (0C) Max temp/ Temp Tube (0C) Min Temp/Temp Tube (0C) Design capacity (MMSCMD)/Flowrate (Sm3/h) Capacity (m3)/Static head (m)/Bare tube surface (m2)/Heat transfer area (m2) Equipment General Parameters Construction Code Equipment position Length TL-TL

10.4. 10.4.1 10.4.2 10.5. 10.5.1

Internal Diameter/Width: Top (mm) Bottom (mm/") Height TL-TL: Top (mm)

13

Heat Exchanger Specific Parameters:

9.9.

Comments: All information is required for proper weight and cost estimates; default values will be used where not provided. Keep tracking and highlighting all modifications from one revision to the other using revision mumber and bold red font. indication of the Equipment List revision number of each equipment as per GS EP EXP 501 as per GS EP EXP 501 description of the equipment function/service as per GS EP EXP 501 integrated in a module or not preference should be given for one row - one equipment; in case of multiple occurrences of an equipment - indicate the number % of design capacity per equipment item design pressure or design pressure of shellside (for shell & tubes heat exchanger) design pressure of tubeside (for shell & tube heat exchanger) design temperature (max) or design temperature of shellside (max) design temperature (min) or design temperature of shellside (min) design temperature of tubeside (max) design temperature of tubeside (min) MMSCMD for gas/Sm3/h for liquid for Platform Cranes indicate lifting capacity in metric tonne; for N2 generation packages indicate capacity in Nm3/h filled by ICS: AMSE VIII Div 1, ASME VIII Div 2, BS 5500 horizontal or vertical Length TL-TL = tangent line to tangent line if only one diameter: input same dia for Top and Bottom - input height for Bottom and nothing for Top if only width: - input width for Bottom and nothing for Top in inches for pigs only Height TL-TL = tangent line to tangent line

input height for Bottom and nothing for Top; For Column (>4000 mm if 10.5.2 Bottom (mm) packing) 11 Material General Parameters: Casing Material/Shell Material/Plate 11.1 Material Rotor Material/Tube Material/Tray 11.2 material 11.3 Corrosion Allowance (mm) 3 mm CS, 0 mm alloys, 0 mm if cladding 11.4 Cladding or lining 11.5 Internals of Column/Filter/Reactor/Dryer: 11.6 Internals type 11.7 Trays: 11.7.1 Number 11.7.2 Type usual: valves 11.8 Pack ing type 12 Rotating Specific Parameters 12.1 Driver type Driver Installed power/Total fan power for 12.2 air cooler (k W) ISO Power/No. Of motors for air cooler/ 12.3 Duty (k W)

13.1 13.2 13.3 13.4 13.5 13.6 13.7 13 14 15 16 17 18

TEMA (usual: AEL, for reboiler AKL); Plate& Frame Model from TEMA/Model/Plate&Frame Model dropdown list No of Rows number of rows for air coolers Nb of tube pass/shell/No. of bays/ Nb of number of tube passes per shell; number of bays for air coolers plates Tube OD (mm) Tube Outside diameter (usual: 19,05 mm(3/4")) Tube Length (usual: 6096 mm (20')), Standard lenght for Air Cooler Tube Length (mm) Tubes are 3, 6, 9 & 12m only Tube thick ness/Plate thick ness (mm) Tube thickness (usual: CS, LTCS: 14, Alloy, SS:16, Ti: 18) Tube Pitch usual: triangular add any necessary comments as benchmark/analogue source of Comments information, details and etc; Envelope Length Envelope Diameter/Width Envelope Height Unit Dry Weight Total Dry Weight

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 23 of 28 Appendix 2

Appendix 2 Quantity Estimate Summary: All Units (ISBL &OSBL) Installation : location :

USA

Estimation N°- :

XXXX

Capacity :

1 000 T/D

Date :

18/09/11

Licensor :

NASA

Revision :

0

Plot Area :

8 000 m2

By :

Me

Project duration:

21 months

QTY ESTIMATE SUMMARY : ALL UNITS ENG. COST CODES

DESIGNATION

QTY (Main Criteria)

QTY (Second Criteria)

EQUIPMENTS

(pieces)

(w eight)

1u 5u 2u 5u 12 u 5u

500 T 200 T 700 T

2u 1u 1u 5u

2T 40 T 4T 3T

39 u

1 801 T

600 T 30 CV 3u 600 I/O 500 Kw 500 Kw

6" / schedule 60 -

-

-

Heaters Columns Columns Internals Reactors Reactors Internals Exchangers Aircoolers Drums Storages Pumps & Motors Compressors & Motors Turbines Packages

Sub/Total Equipments BULK MATERIAL Piping (AG+UG pressurized) Instrumentation (local) Instrumentation Analysers Instrumentation (DCS) Electricity (local) Electricity (Substations)

Sub/Total Bulk material CONSTRUCTION Mechanical erection Heavy Lifting (Crane) Dismantling works Piping Installation Scaffolding Piping dismantling Instrumentation Installation (in unit) Instrumentation Installation (DCS) Electricity Installation (in unit) Electricity Installation (Substations) E/I dismantlings works Technical allowances & reworks SUBCONTRACTS Site Preparation Piling Civil Works Buildings Structural Steel Fireproofing Insulation Painting Technical allowances & reworks

Site Facilities

187 T 70 T 95 T

5 km

1801 T 300 T 560 T 50 T 30 CV 600 I/O 500 Kw 500 Kw

5 000 m2 200 u 4 000 m3 150 m2 300 T 300 m3 2 500 m2 5 000 m2

5 ON/OFF 5 km

2 400 lm 2 500 m2 3u

300 m2

Note: One summary unit shall be prepared for each unit ISBL, each unit OSBL, one for all ISBL, all OSBL and one ISBL plus ISBL

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 24 of 28 Appendix 2

QUANTITY ESTIMATE SUMMARY : ALL UNITS SPECIFIC INSTRUCTIONS TO FILL ESTIMATE SUMMARY

QUANTITY (MAIN CRITERIA) EQUIPMENTS - For Exchangers : 1 shell = 1 piece - For Aircoolers : 1 bay = 1 piece BULK MATERIAL - For Piping : purchased weight of piping aboveground and underground pressurized in metric tons including tubes, valves, fittings, flanges, miscellaneous and supports - For Instrumentation (local) : Number of Control valves, On/off Valves, Automatic valves - For Instrumentation (Analysers) : Number of analysors - For Instrumentation (DCS) : Number of Input / Output - For Electricity (local) : Power installed in kW CONSTRUCTION - For Mechanical Erection : Erected weight of equipment in metric tons - For Dismantling : Erected weight of equipment dismantled in metric tons - For Piping : Erected weight of piping aboveground and underground pressurized in metric tons including tubes, valves, fittings, flanges, miscellaneous and supports - For Piping Dismantling : Erected weight of piping aboveground and underground pressurized in metric tons including tubes, valves, fittings, flanges, miscellaneous and supports - For Instrumentation (in site) : Number of Control valves - For Instrumentation (DCS) : Number of Input / Output - For Electricity (in site) : Power installed in kW SUBCONTRACTS - For Site preparation : Area in m2 to prepare - For Piling : Number of piles - For Civil works : Cubic meter of concrete for foundations works, excluding fireproofing quantities - For Buildings : Area in square meter including footprint and stages areas. - For Structural steel : Erected Weight of Structure in metric tons including heavy, secondary and miscellaneous (stairs, monrials…) structure - For Insulation : Area in m2 of piping and equipment to insulate. - For Painting : Area in m2 of piping and equipment to paint. ENGINEERING - For Site facilties : Plot Area in m2 for temporary buildings

QUANTITY (SECOND CRITERIA) EQUIPMENTS - For Equipment : Erected weight of equipment in metric tons BULK MATERIAL - For Piping : Average diameter in inches and average schedule - For Instrument : Number of ON/OFF Valves - For Electricity (in site) : Total Lenght of cables in linear meter between unit and substation SUBCONTRACTS - For Piling : total linear meter of piles - For Civil works : Paving area in square meter - For Buildings : Number of buildings

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 25 of 28 Appendix 3

Appendix 3 Piping Qty Summary Installation :

Refinery

location : Capacity :

USA 1 000 T/D

Estimation N°- XXXX

Licensor :

NASA

Qty estimate level:

Level 2, +/- 10%

Plot Area :

8 000 m2

Project duration :

21 months

Date :

18/09/2011

Revision :

0

By :

Me

PIPING AG MATERIAL SUMMARY : ALL UNITS Cost Codes

PIPING

PIPING

ENG

MATERIAL

TYPE

CS

VALVE

CS

VALVE

CS

VALVE

CS

VALVE

RANGE DIA

QUANTITIES TAKE OFF QUANTITY

(Inches) 2"÷12" 14"÷24" =>26" S / T O T A L VALVES

QUANTITY

pieces 26 958

pieces

696,0

4 377

pieces

554,0

942

pieces

268,0

32 277 pieces

CS

PIPE

<2"

CS

PIPE

2"÷12"

2 413

ml

CS

PIPE

14"÷24"

1 532

CS

PIPE

=>26"

391

S / T O T A L PIPE

QUANTITIES ERECTED

WEIGHT (tons)

<2"

1 518

ml

QUANTITIES PURCHASED

WEIGHT

WEIGHT

(tons)

(tons)

47 702

pieces

109,0

127,0

26 958

pieces

696,0

751,0

4 377

pieces

554,0

587,0

942

pieces

268,0

278,0

79 979 pieces

1 627

1 743

154

ml

1,0

150,0

2 413

ml

150,0

162,0

ml

206,0

1 532

ml

206,0

218,0

ml

239,0

391

ml

239,0

248,0

596

629

<2"

pieces

20

pieces

-

-

CS

FITTINGS

2"÷12"

pieces

436

pieces

3,0

3,0

CS

FITTINGS

14"÷24"

pieces

53

pieces

2,0

2,0

pieces

-

-

CS

FITTINGS

4 336 m l

=>26"

595

pieces

-

CS

FITTINGS

CS

FLANGES

<2"

CS

FLANGES

2"÷12"

1 631

pieces

8,0

CS

FLANGES

14"÷24"

55

pieces

-

597

pieces

S / T O T A L FITTINGS

CS

=>26"

FLANGES

S / T O T A L FLANGES CS

MISCELLANEOUS &SUPPORTS

CS

TOTAL PIPING AG CS

CS

AVERAGE DIAMETER > 2"

4 490 m l

1,0

0 pieces

509 pieces

pieces

39,0

2 283 pieces

47

5

5

103

pieces

0,0

0,0

1 631

pieces

8,0

8,0

55

pieces

-

1,0

597

pieces

39,0

2 386 pieces

40,0

47

49 200 2 426

8 inches

LTCS

VALVE

<2"

47 702

pieces

109,0

127,0

LTCS

VALVE

2"÷12"

26 958

pieces

696,0

26 958

pieces

696,0

751,0

LTCS

VALVE

14"÷24"

4 377

pieces

554,0

4 377

pieces

554,0

587,0

LTCS

VALVE

=>26"

942

pieces

268,0

942

pieces

268,0

278,0

S / T O T A L VALVES

pieces

32 277 pieces

LTCS

PIPE

<2"

LTCS

PIPE

2"÷12"

2 413

ml

LTCS

PIPE

14"÷24"

1 532

LTCS

PIPE

=>26"

391

S / T O T A L PIPE

1 518

ml

79 979 pieces

1 627

1 743

154

ml

1,0

1,0

150,0

2 413

ml

150,0

162,0

ml

206,0

1 532

ml

206,0

218,0

ml

239,0

391

ml

239,0

248,0

596

629

LTCS

FITTINGS

<2"

pieces

20

pieces

-

-

LTCS

FITTINGS

2"÷12"

pieces

436

pieces

3,0

3,0

LTCS

FITTINGS

14"÷24"

pieces

53

pieces

2,0

2,0

pieces

-

-

LTCS

4 336 m l

=>26"

FITTINGS

S / T O T A L FITTINGS

595

pieces

-

0 pieces

509 pieces

LTCS

FLANGES

<2"

LTCS

FLANGES

2"÷12"

1 631

pieces

8,0

LTCS

FLANGES

14"÷24"

55

pieces

-

597

pieces

LTCS

=>26"

FLANGES

S / T O T A L FLANGES LTCS

MISCELLANEOUS &SUPPORTS

LTCS

TOTAL PIPING AG LTCS

LTCS

AVERAGE DIAMETER > 2"

4 490 m l

pieces

39,0

2 283 pieces

47

5

5

103

pieces

0,0

0,0

1 631

pieces

8,0

8,0

55

pieces

-

1,0

597

pieces

39,0

2 386 pieces

40,0

47

49 200 2 426

8 inches

AS

VALVE

<2"

47 702

pieces

109,0

127,0

AS

VALVE

2"÷12"

26 958

pieces

696,0

26 958

pieces

696,0

751,0

AS

VALVE

14"÷24"

4 377

pieces

554,0

4 377

pieces

554,0

587,0

AS

VALVE

=>26"

942

pieces

268,0

942

pieces

268,0

278,0

S / T O T A L VALVES

pieces

32 277 pieces

AS

PIPE

<2"

AS

PIPE

2"÷12"

2 413

ml

AS

PIPE

14"÷24"

1 532

AS

PIPE

=>26"

391

S / T O T A L PIPE

1 518

ml

1 627

1 743

154

ml

1,0

150,0

2 413

ml

150,0

162,0

ml

206,0

1 532

ml

206,0

218,0

ml

239,0

391

ml

239,0

248,0

4 336 m l

595

4 490 m l

1,0

596

629

-

-

pieces

20

pieces

AS

FITTINGS

2"÷12"

pieces

436

pieces

3,0

3,0

AS

FITTINGS

14"÷24"

pieces

53

pieces

2,0

2,0

pieces

-

-

AS

<2"

79 979 pieces

FITTINGS

=>26"

pieces

-

AS

FITTINGS

AS

FLANGES

<2"

AS

FLANGES

2"÷12"

1 631

pieces

8,0

AS

FLANGES

14"÷24"

55

pieces

-

597

pieces

S / T O T A L FITTINGS

AS

=>26"

FLANGES

S / T O T A L FLANGES AS

MISCELLANEOUS &SUPPORTS

AS

TOTAL PIPING AG AS

AS

AVERAGE DIAMETER > 2"

0 pieces

509 pieces

pieces

39,0

2 283 pieces

47

5

5

103

pieces

0,0

1 631

pieces

8,0

8,0

55

pieces

-

1,0

597

pieces

39,0

2 386 pieces

0,0

40,0

47

49 200 2 426

8 inches

SS

VALVE

<2"

47 702

pieces

109,0

127,0

SS

VALVE

2"÷12"

26 958

pieces

696,0

26 958

pieces

696,0

751,0

SS

VALVE

14"÷24"

4 377

pieces

554,0

4 377

pieces

554,0

587,0

SS

VALVE

=>26"

942

pieces

268,0

942

pieces

268,0

278,0

S / T O T A L VALVES

pieces

32 277 pieces

1 518

1 627

1 743

SS

PIPE

<2"

SS

PIPE

2"÷12"

2 413

ml

SS

PIPE

14"÷24"

1 532

SS

PIPE

=>26"

391

596

629

SS

FITTINGS

<2"

pieces

20

pieces

-

-

SS

FITTINGS

2"÷12"

pieces

436

pieces

3,0

3,0

SS

FITTINGS

14"÷24"

pieces

53

pieces

2,0

2,0

pieces

-

-

S / T O T A L PIPE

ml

79 979 pieces 154

ml

1,0

150,0

2 413

ml

150,0

162,0

ml

206,0

1 532

ml

206,0

218,0

ml

239,0

391

ml

239,0

248,0

4 336 m l

=>26"

595

pieces

-

SS

FITTINGS

SS

FLANGES

<2"

SS

FLANGES

2"÷12"

1 631

pieces

8,0

SS

FLANGES

14"÷24"

55

pieces

-

597

pieces

S / T O T A L FITTINGS

SS

=>26"

FLANGES

S / T O T A L FLANGES SS

MISCELLANEOUS &SUPPORTS

SS

TOTAL PIPING AG SS

SS

AVERAGE DIAMETER > 2"

SPECIAL SUPPORTS

TOTAL PIPING AG MATERIAL

0 pieces

509 pieces

pieces

2 283 pieces

4 490 m l

39,0 47

5

1,0

5

103

pieces

0,0

0,0

1 631

pieces

8,0

8,0

55

pieces

-

1,0

597

pieces

2 386 pieces

39,0 47

40,0 49 200 2 426

8 inches

500

10 204

Notes: Idem for Underground Piping One piping summary unit shall be prepared for each unit ISBL, each unit OSBL, one for all ISBL, all OSBL and one ISBL plus ISBL

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 26 of 28 Appendix 4

Appendix 4 Electrical Material Summary: All Units

Notes: The BOQ shall include the take off allowances ie be equal to the “erected” quantities One Electrical summary unit shall be prepared for each unit ISBL, each unit OSBL, one for all ISBL, all OSBL and one ISBL plus ISBL

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 27 of 28 Appendix 5

Appendix 5 Instrumentation Material Summary: All Units

Notes: The BOQ shall include the take off allowances ie be equal to the “erected” quantities One Instrument summary unit shall be prepared for each unit ISBL, each unit OSBL, one for all ISBL, all OSBL and one ISBL plus ISBL

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

General Specification

GS EP EST 001

Documents necessary for Cost Estimating at the end of a FEED or a Basic Engineering. Rev.: 01

Effective date: 06/2015

Page: 28 of 28 Appendix 6

Appendix 6 Construction Breakdown (Qties & Direct Man-hours): All Units

Notes: The BOQ shall include the take off allowances i.e. be equal to the “erected” quantities One construction breakdown unit shall be prepared for each unit ISBL, each unit OSBL, one for all ISBL, all OSBL and one ISBL plus ISBL

This document is the property of TOTAL S.A., it contains confidential information which may not be disclosed to any third party, reproduced, stored or transmitted without the prior written consent of TOTAL S.A. The information contained in this document does not substitute to the applicable laws and regulations.

Related Documents


More Documents from "Peter Bourne"