Hydro Power Plant Project Report

  • Uploaded by: yogesh dhaker
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Hydro Power Plant Project Report as PDF for free.

More details

  • Words: 4,856
  • Pages: 28
Loading documents preview...
Project 1273: Someshwara small hydropower project (24.75 MW) in Karnataka, India

MONITORING REPORT Ver. 01, 11 Jan 2010 [The Monitoring period is chosen from 27 May 2008 to 30 Sep 2009 both days included]

Net Emission Reductions: 140020 tCO2e

Registered Office Pioneer Genco Limited P.O. Box# 156, Golf Link Road, Amarajyoti Layout, Koramangala Road, Domulr , Bangalore - 560071 Telephone:+91-80-41300550

Project Site Someshwara Small Hydro Power Project Panchayath : Hosahalli Village : Shivasamudram, Taluk : Malavalli District : Mandya Karnataka, India

24.75 MW Someshswara SHP

Monitoring Report

CONTENTS Page No

1.

Current Status of the Project

4

2.

Reference

4

3.

Monitoring Period

4

4.

Abbreviations

4

5.

General Description of the Project

5

6.

Details of Major Equipment of the Project & Plant shut downs for the Reported Period

7

7.

Statement to what extent the project has been implemented as planned

7

8.

Sustainability – Economic and Social Well Being

8

9.

Parameters being monitored according to Monitoring Plan

8

10. GHG Calculations

12

11. Net Emission Reductions

13

12. Measures to ensure the results/uncertainty analysis

15

13. Details of Monitoring team and Responsibilities

15

Page No. 2

24.75 MW Someshswara SHP

Monitoring Report

List of Tables: Table - 1

Detail of Plant Major Equipments of the Project and Suppliers of a project activity

Table - 2

Running & Non –Running Hours of Each Unit

Table - 3

Details of Electricity exported to grid, electricity imported from grid and net electricity displaced for the Reported period.

Table - 4

Net Emission Reductions for the Reported Period

Table - 5

Monitoring Team

List of Annexures: Annex – 1

Unit wise Details for Plant Shut downs & Reasons

Annex – 2

Justification for Excess Net Electricity Generation during the Reported Period

Page No. 3

24.75 MW Someshswara SHP

1.

Monitoring Report

Current Status of the Project Pioneer Genco Limited has established a 24.75 MW (3x8.25 MW) Someshwara small hydropower project Scheme at Shivasamudram Village, Hosahalli Panchayath, Malavalli Taluk in Mandya District of Karnataka, India. The project is a run of the river scheme, utilizing a gradient of about 20 meters downstream of the existing 42 MW Shivasamudram hydroelectric project at Gaganchukki branch of Cauvery river. The generated electricity will be exported to a grid system of Karnataka Power Transmission Corporation Limited (KPTCL).

The purpose of this Monitoring Report (MR) is to calculate the Green House Gas (GHG) emission reductions occurred for the net electricity exported to grid. During the reported period the plant displaced 162.65 GWh of net electricity to the KPTCL.

2.

Reference The project has registered with UNFCCC on 27 May 2008 and the crediting period from 27 May 2008 to 26 May 2018 (fixed). For more details on the project, please refer to the following links on the UNFCCC web site: Project.1273: Someshwara small hydropower project (24.75 MW) in Karnataka, India

http://cdm.unfccc.int/Projects/DB/DNV-CUK1185945016.76/view

3.

Monitoring Period The Monitoring period is chosen from 27 May 2008 to 30 Sep 2009.

4.

Abbreviations CEA

: Central Electricity Authority, Government of India.

GHG

: Greenhouse Gases

IPCC

: Intergovernmental Panel on Climate Changes

KPTCL

: Karnataka Power Transmission Corporation Limited

PGL

: Pioneer Genco Limited

PP

: Project Proponent

SSHPP

: Someshwara Small Hydel power plant

SR Grid

: Southern Region Grid

Page No. 4

24.75 MW Someshswara SHP

5.

Monitoring Report

General Description of the Project Pioneer Genco Limited has established a 24.75 MW Someshwara Mini Hydel scheme at Shivasamudram Village, Mandya District, Karnataka state, India. The Purpose of the Project activity is utilizing the available head at Gaganchukki branch of Cauvery river located at downstream of the existing 42 MW Shivasamudram Hydroelectric Project. The Project is expected to export 81.48 GWh of energy for an optimum year to the state utility grid. The Units of the project activity have been synchronized with 66/11KV grid of KPTCL as mentioned below and the same are in operation till date.  Unit – 1 : Synchronized on 26 Jul 2005  Unit – 2 : Synchronized on 07 Jul 2005  Unit – 3 : Synchronized on 26 Jul 2005 Location of the Project The project is located downstream of existing 42 MW Shivasamudram hydroelectric project at a distance of 2 kms from Shivasamudram Village, Hosahalli Panchayath, Malavalli Taluk in Mandya District of Karnataka. The nearest airport is at Bangalore located at a distance of 130 kms. The geographical location of the project is between Longitude 77° 11’.437 East and Latitude 12° 18’.603 North.

Physical Location address of the project activity: Someshwara small hydropower project Across Cauvery River Sy .No: 371 Shivasamudram village, Malavalli taluk, Mandya District, Karnataka

Page No. 5

24.75 MW Someshswara SHP

Monitoring Report

Map.2 : Location of Mandya in the Karnataka

Map.1 : Location of Karnataka in India

Map.3: Location of 24.75 MW Someswara Small Hydel Power Project in Mandya District of Karnataka State.

Page No. 6

24.75 MW Someshswara SHP

6.

Monitoring Report

Details of Major Equipment of the Project & Plant shut downs for the Reported Period. The details of major equipment of the project and suppliers are presented below: Table 1 – Details of Major Equipment of the Project and Suppliers of a project activity

1

Name of the Equipment Turbine

2

Generator

3

Power Transformer

S.No

Specifications Make: Boving Fouress Ltd. Model: K305 Type: Vertical Full Kaplan Turbine Rated discharge per Unit : 56 cumecs Rated Head : 17.5 m Rated Power : 8500 KW No. of Units: 3 Nos. Serial Nos.: 190/1, 190/2 & 190/3 Make: UCM RECITA, Type: HVS 450/72-78 Rated Power : 8250 KW, Rated Speed : 214.3 RPM, P.F. 0.85, No. of Units : 3 Nos. Make : Kirlosker, S.No: 032XJ-003/1 and 032XJ-003/2

Rated Power : 25 / 30 MVA

7.

Statement to what extent the Project has been implemented as Planned The Project has been completed as planned and the monitoring equipments were installed to monitor the parameters as described in the CDM Project Design Document (CDM PDD). The Units are in operation continuously (with outages – forced & planned) since its commercial operations.

The details of forced shut down periods, planned shut down periods and reasons for shut down are mentioned in the Annex-1. The Details of Running & Non-Running Hrs of Each unit is tabulated in the given below Table 2: Running & Non –Running Hours of Each Unit 27 May 08 to 31 Mar 09 S.No. 1

Description Total No. of Hours available (Hrs:Min)

01 Apr 09 to 30 Sep 2009

Unit-I

Unit-II

Unit-III

Unit-I

Unit-II

Unit-III

7416:00

7416:00

7416:00

4392:00

4392:00

4392:00

Page No. 7

24.75 MW Someshswara SHP 2 3 4 5 6

8.

Non-availability of water (Hrs:Min) Planned Shut downs (Hrs:Min) Forced Shut downs (Hrs:Min) Total Non Running hours (Hrs:Min) Total Running hours (Hrs:Min)

Monitoring Report

2112:45

3105:25

2276:10

1743:35

1503:40

2181:00

90:50

58:25

91:20

61:50

72:35

92:10

131:30

101:45

70:40

99:45

107:05

107:40

2335:05

3264:55

2438:10

1905:10

1683:20

2380:50

5080:55

4151:05

4977:50

2486:50

2708:40

2011:10

Sustainability – Economic and Social Well Being The project activity has resulted in sustainable development in the region as follows:

9.



Alleviation of poverty by generating direct and indirect employment in the area. The project generated indirect employment during the construction of the project activity and also permanent employment during operation of the project.



The power generation from the project activity stabilizes the local grid and helped in providing uninterrupted power for farmers.



The project activity contributed to the development of infrastructure in and around the project like roads, buildings and communication systems in the rural area.



The project activity reduced the migration of the rural populace to urban areas, as the project activity generated employment opportunities.



The project does not lead to any GHG emissions. So, the project doesn’t have its influence on the microclimate of the region by non-polluting, entails no wastes or production of toxic gases; environmentally benign and reduce global warming impacts.

Parameters being monitored according to Monitoring Plan As described in Registered PDD, the project activity uses the approved ACM 0002 - “Consolidated baseline methodology for grid-connected electricity generation from renewable sources” Version 6, Sectoral scope: 1 .

Page No. 8

24.75 MW Someshswara SHP

Monitoring Report

The following parameters were monitored on continuous basis Data / Parameter: Data unit: Description: Source of data to be used: Value of data applied for the purpose of calculating expected emission reductions Description of measurement methods and procedures to be applied: QA/QC procedures to be applied:

Any comment:

EGy GWh Net electricity export to the grid by the project On-site measurements

The Measured monthly using calibrated meters and aggregated annually. Meters will be calibrated as per industry standards. Sales records to the grid and other records are used to ensure consistency. Electric power sold to the grid will be measured by main meter and check meter by both PGL and KPTCL as specified in the PPA and records maintained. To be cross-checked with monthly invoices or receipts of payments.

Information Used for Emission Reduction Calculations S. No. 1.

2.

Key information/data Source of data/information used for baseline Net Electricity Exported to Monthly Meter Readings recorded and certified by grid KPTCL & plant personnel. Baseline Emission Factor

The project has considered the ex-ante emission factor for the combined margin of the Southern regional grid from Regd. PDD (UNFCCC Project Activity Ref. No.1273) wherein the validated Baseline emission factor is 860.87 tCO2/GWh.

Methods of data transfer and archiving policy The data have been recorded both at the project site as well as at the grid sub-station, which is under the control of KPTCL. The electricity export / import readings have been measured using calibrated trivector meters and recorded manually by the representatives of KPTCL and PGL as a proof of export and import of electricity by the project activities. Those meter readings are the basis for the invoices raised by PGL. These readings are also considered for emission estimations. Sales bills / receipts may be compared as an alternative proof of the electricity exported to the grid. And the data will be stored for a period of 2 years after the crediting period.

Page No. 9

24.75 MW Someshswara SHP

Monitoring Report

Technical details of monitoring instruments like type, make, accuracy class, etc. Description Type Make Accuracy class MF Multiplying Constant Connected CTR Connected PTR Serial No. Year of Manufacturing Calibration Tests

Main meter Trivector Meter L&T 0.2 1 240000 400/1A 66kV/110V S.No 04249044 2004 23.09.2008 & 20.11.2009

Check meter Trivector Meter L&T 0.2 1 240000 400/1A 66kV/110V S.No. 04249047 2004 23.09.2008 & 20.11.2009

Management system and quality assurance: Electricity: (Quality check & assurance is as per Article 7 of PPA signed between Pioneer Genco Limited (PGL) & Karnataka Power Transmission Corporation Limited (KPTCL). Both Main Meter and Check Meters (export & import) installed by PGL are of 0.2 accuracy class. Each meter is jointly inspected and sealed on behalf of the parties. As per the billing period, the Month wise data on electricity generation, auxiliary power consumption, electricity exported to grid and electricity imported from grid are presented in the table given below.

Table – 3:

S.No.

1 2 3 4

Details of Electricity exported to grid, Electricity imported from grid and net electricity displaced for the Reported period

Monitored Period

27 to 31 May See Note:1 June July August

Electricity Exported to Grid

Electricity Imported from Grid

(kWh)

(kWh)

(kWh)

(GWh)

2008

1276800

0

1276800

1.277

2008 2008 2008

6036000 8983200 17558400

2400 0 2400

6033600 8983200 17556000

6.034 8.983 17.556

Year

Page No. 10

Total Electricity Displaced

24.75 MW Someshswara SHP 5 6 7 8 9 10 11 12 13 14 15 16 17

Monitoring Report

September 2008 October 2008 November 2008 December 2008 January 2009 February 2009 March 2009 Sub-Total for 2008-09 April 2009 May 2009 June 2009 July 2009 August 2009 September 2009 Sub-Total

17911200 18470400 16608000 11016000 2863200 2904000 3612000 107239200 3026400 3782400 1867200 10437600 18513600 17844000 55471200

2400 0 0 0 7200 2400 2400 19200 7200 4800 14400 12000 2400 0 40800

17908800 18470400 16608000 11016000 2856000 2901600 3609600 107220000 3019200 3777600 1852800 10425600 18511200 17844000 55430400

17.909 18.470 16.608 11.016 2.856 2.902 3.610 107.220 3.019 3.778 1.853 10.426 18.511 17.844 55.430

Grand Total

162710400

60000

162650400

162.650

Note-1: As the crediting period started from the date of project registration with UNFCCC i.e. 27 May 2008, we have considered the figures of electricity exported to grid from the log sheets maintained at project site for the period from 27 to 31 May 2008. Copies of log sheets are being provided to the DOE for verification.

The plant has been operated with excess electricity generation on rated capacity for the following months to utilize the available water flows for electricity generation. The details are furnished below:

Monitored Period

Sep-08 Oct-08 Aug-09 Sep-09

Installed Rated Capacity, kWh

17820000 18414000 18414000 17820000

Gross Electricity Generation, kWh

Excess Generation on Rated Cap.

Recorded by KPTCL Personnel

Recorded at Project site 18212110 18777250 18807230 18096670

Net Excess Electricity Net Elec. Generation, Gen on kWh Rated Cap.

2.2% 2.0% 2.1% 1.6%

17911200 18470400 18513600 17844000

0.5% 0.3% 0.5% 0.1%

The project activity has utilized the available water flows for electricity generation by utilizing the TG inbuilt capacity which has capable to generate power 8500 KW at generator terminals. A copy of

Page No. 11

24.75 MW Someshswara SHP

Monitoring Report

Technical specification of Turbo generator Purchase Order placed on M/s Boving Fouress Limited is being provided to DOE for verification. As there is no restriction on the monthly plant load factor from the state electricity board authorities, the excess electricity generation is deemed acceptable.

10.

GHG Calculations The following formula is adopted for calculating emission reductions generated by the project activity: The emission reductions for a given year are baseline emissions minus the project emissions and leakage. ERy = BEy -

PEy -

Ly

Where

ERy BEy PEy Ly

= Emission reductions in a given year = Baseline emissions in a given year = Project emissions in a given year = Leakage in a given year

Baseline Emissions The baseline emissions are calculated as follows: BE y = EG y ⋅ EFy

Where EGy = Net electricity export to grid in a given year (GWh) EFy is = Emission factor for a given year (tCO2/GWh) As mentioned under sec. B.2 of registered PDD (UNFCCC Project Activity Ref. No.1273), the project has considered the ex-ante emission factor for the combined margin of the Southern regional grid and the details are furnished below: Operating Margin (OM) in t CO2 / GWh

1003.76

Build Margin (BM), in t CO2 / GWh

717.98

Combined Margin (CM) Simple average of OM and BM in t CO2 / GWh

860.87

Project emissions (PEy): The project emissions are considered zero. Leakage As specified in ACM 0002, project participants do not need to consider these emission sources as leakage in applying this methodology. Hence the leakage emissions are considered zero. Using the above formulas, the Emission reductions from the project activity are shown below.

Page No. 12

24.75 MW Someshswara SHP

11.

Monitoring Report

Net Emission Reductions The emission reductions for the chosen monitored period i.e. from 27 May 2008 to 30 Sep 2009 are furnished below: Table-4: Net Emission Reductions for the Reported Period

Monitored Period

27 to 31 May June July August September October November December January February March

Year

2008 2008 2008 2008 2008 2008 2008 2008 2009 2009 2009

Sub –Total April May June July August September

2009 2009 2009 2009 2009 2009

Sub –Total Total

Total Electricity Displaced

Emission Factor

Baseline Emissions

Project Emissions

Net Emission Reductions

(GWh)

tCO2/GWh

tCO2e

tCO2e

tCO2e

1.277 6.034 8.983 17.556 17.909 18.470 16.608 11.016 2.856 2.902 3.610 107.220

860.87 860.87 860.87 860.87 860.87 860.87 860.87 860.87 860.87 860.87 860.87

1099.2 5194.1 7733.4 15113.4 15417.1 15900.6 14297.3 9483.3 2458.6 2497.9 3107.4 92302.5

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

1099.2 5194.1 7733.4 15113.4 15417.1 15900.6 14297.3 9483.3 2458.6 2497.9 3107.4

92302

0

2599.1 3252.0 1595.0 8975.1 15935.7 15361.4 47718.4

0.0 0.0 0.0 0.0 0.0 0.0 0.0

47718

0

47718.4 47718

140020.8

0.0

140020.8

140020

0

140020

3.019 3.778 1.853 10.426 18.511 17.844 55.430

860.87 860.87 860.87 860.87 860.87 860.87

162.650

Project Considered

92302.5 92302

2599.1 3252.0 1595.0 8975.1 15935.7 15361.4

The net emission reductions occurred during the reported period are more than the estimated net emission reductions in the registered PDD and the details are furnished below:

Parameters

Units

27 May 08 to 31 Mar 09

Page No. 13

01 Apr 09 to 30 Sep 09

24.75 MW Someshswara SHP

Monitoring Report As per Regd. PDD

Actual

As per Regd. PDD

Actual

GWh

83.500

109.195

43.300

56.435

GWh

2.505

1.956

1.299

1.005

GWh

80.995

107.239

42.001

55.430

Electricity Imported to grid

GWh

0

0.019

0

0.0001

Net electricity Exported to grid

GWh

80.995

107.220

42.001

55.430

tCO2e/GWh

860.87

860.870

860.87

860.870

Baseline emissions

tCO2e

69726

92302

36157

47718

Project emissions

tCO2e

0

0

0

0

Net emission reductions

tCO2e

69726

92302

36157

47718

Gross electricity generation Aux. consumption incl. Transform & Transmission losses Net electricity generation (Exported to grid)

Baseline emission factor

Variation

32.4%

32.0%

Net emission reductions for the reported period = (140020 – 105883) x 100 / 105883 = 32.24%

The net emission reductions for the reported period is + 32.24% more than the estimated in the registered PDD due to more net electricity generation (exported to grid). The reasons for the excess net electricity generations are  Excess rainfall in the catchments area of river  Power generation during the lean / off season  Reduction in the Losses The uncertainty relating to water discharges was in fact one of the key risk factors affecting the project. Most of the above factors keep changing on year to year basis. Due to favorable discharges from the above-mentioned factors and availability of plant, which could not be relied upon at the time of PDD writing, actual water flows during the monitored period were higher and thereby the power generations are higher than the estimated power generations. Justification for excess net electricity generations is furnished as Annex-2.

The detailed calculation of emission reductions is provided in excel spread sheet.

Page No. 14

24.75 MW Someshswara SHP

12.

Monitoring Report

Measures to ensure the results/uncertainty analysis The energy exported by Someshwara small hydropower project is recorded from independent main meter installed at the 66/11 KV substation. In the event, the Main Meter is not in operation, the reading from Check Meter is used for billing.

The calibration of monitoring equipment is being maintained as per the requirement of Electricity Board and the same is being done regularly. Power generation, export, and energy import are being recorded daily and the same is being verified by the respective officials. Both meters are of same specifications & frequency and approved by KPTCL. The accuracy clause of these meters is 0.2.

13.

Details of Monitoring team and Responsibilities CDM team has been formed in SSHP for monitoring and verification of all the monitoring parameters as per the guidelines formatted by the management of SSHP. Qualified and trained people monitor the parameters and emission reduction calculations. In the complete implementation and monitoring Plan, SSHP is the sole agency responsible for implementation and monitoring. The details of monitoring team are detailed below. Table 5: Monitoring Team S.No. 1

Name of the Person Mr. P.Prathap Reddy

Designation Managing Director

2

Mr. D.Raghunath

General Manager

3

Mr. S.S.Hussain

Shift Incharge

4

Mr. S.Jagadeesh

Shift Incharge

5

Mr. Gangi Reddy

Shift Incharge

Roles and Responsibilities – Monitoring Team Managing Director Managing Director is responsible for the total monitoring plan. The Managing Director will examine the reports generated by the General Manger w.r.t, the monthly electricity generated, exported and annual emission reduction calculations as per the monitoring plan. He also examines the internal audit reports prepared by internal auditor and will in particular take note of any deviations in data over the norms and monitor that the corrective actions have resulted in adherence to standards.

Page No. 15

24.75 MW Someshswara SHP

Monitoring Report

General Manager General Manager is assisting and reporting to Managing Director for completing the task discussed above. The General Manager is responsible for the electricity generations at their individual locations. He will cross check, sign the log book regularly, and report to Managing Director for any abnormality. The calibration of the meters installed will be taken care by him as per the monitoring plan. The responsibility of storage and archiving of information in good condition also lies with the General Manager. He also generate internal audit reports as per the monitoring plan and when ever necessary, and will be submitted to the Managing Director. Shift Incharges Shift Incharges are responsible for recording the total electricity generation, auxiliary consumption, electricity export, electricity import, plant shut down times, diesel consumption, if any etc. The monthly reports will be generated and submitted to the General Manager for verification and emission reduction calculations.

Page No. 16

24.75 MW Someshswara SHP

Monitoring Report Annex-1

Unit wise Details for Plant Shut downs & Reasons

Outage Details for UNIT -1 Date 28.05.08 to 29.05.08 05.06.08 to 29.06.08 01.07.08 to 28.07.08 14.08.08 to 15.08.08 29.09.08 to 30.09.08 29.10.08 to 31.10.08 16.12.08 to 31.12.08 01.01.09 to 31.01.09 01.02.09 to 24.02.09 05.03.09 to 13.03.09 Other short interruptions Sub-Total for 27 May 08 to 31 Mar 09 02.04.09 to14.04.09 15.04.09 to 30.04.09 01.05.09 to 17.05.09 18.05.09 to 31.05.09 1.06.09 to 30.06.09 1.07.09 to 12.07.09 17.07.09 to 21.07.09 29.08.09 to 31.08.09 30.09.09 Other short interruptions Sub-Total for 01 Apr 09 to 30 Sep 09

Type of shut down (in Hr:Min) Planned Forced Others 33:45 481:05 244:00 43:00

Line Maintenance

379:35 454:55 490:00 63:10

Plant stopped due Low Head Unit Maintenance Unit Maintenance Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient Water Flow

2112:45

2335:05

146:10 384:00 408:00 75:35 629:10 100:40

Insufficient Water Flow Insufficient Water Flow Insufficient Water Flow Insufficient Water Flow Insufficient water inflow Insufficient water inflow Trash gate repair Elec/Mech Maintenance

1743:35

1905:10

35:25 55:25 454.55

Reason

54:45 90:50

131:30

89:55 53:40 8:10 9:50 61:50

99:45

Page No. 17

24.75 MW Someshswara SHP

Monitoring Report

Outage Details for UNIT -2 Date 28.05.08 to 29.05.08 05.06.08 to 29.06.08 04.07.08 to 29.07.08 14.08.08 to 15.08.08 28.09.08 to 30.09.08 29.10.08 to 31.10.08 13.12.08 to 31.12.09 01.01.09 to 15.01.09 16.01.09 to 31.01.09 16.01.09 to 22.02.09 23.02.09 to 28.02.09 01.03.09 to 31.03.09 Other short interruptions Sub-Total for 27 May 08 to 31 Mar 09 01.04.09 to 30.04.09 01.05.09 to 31.05.09 06.06.09 to 30.06.09 1.07.09 to 12.07.09 17.07.09 to 21.07.09 30.09.09 to 31.09.09 29.09.09 to 30.09.09 Other short interruptions Sub-Total for 01 Apr 09 to 30 Sep 09

Type of shut down (in Hr:Min) Planned Forced Others 33:50 485:40 258:10

Reason

202:40 358:55 384:00 528:00 144:00 744:00

Line Maintenance Insufficient water inflow Insufficient water inflow Plant Stopped due Low Head Unit Maintenance Unit Maintenance Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient water inflow

3105:25

3264:55

354:45 383:55 490:50 274:10

Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient water inflow Trash gate repair Elec/Mech Maintenance Plant Stopped for the Maintenance

1503:40

1683:20

42:15 30:55 27:30

25:00 58:25

101:05

98:25 40:10 32:25 8:40 72:35

107:05

Page No. 18

24.75 MW Someshswara SHP

Monitoring Report

Outage Details for UNIT -3 Date 27.05.08 to 31.05.08 01.06.08 to 30.06.08 1.07.08 to 25.07.08 14.08.08 to 15.08.08 29.09.08 to 30.09.08 29.10.08 to 31.10.08 02.01.09 to 31.01.09 05.02.09 to 28.02.09 01.03.09 to 10.03.09 11.03.09 to 31.03.09 Other short interruptions Sub-Total for 27 May 08 to 31 Mar 09 01.04.09 to 11.04.09 12.04.09 to 30.04.09 01.05.09 to 31.05.09 01.06.09 to 31.06.09 1.07.09 to 17.07.09 18.07.09 to 21.07.09 29.08.09 to 31.08.09 29.09.09 to 30.09.09 Other short interruptions Sub-Total for 01 Apr 09 to 30 Sep 09

Type of shut down (in Hr:Min) Planned Forced Others 120:00 339:50 514:10 42:20 37:00 54:20 365:20 230:45 202:05 504:00 28:20 91:20

70:40

Reason Insufficient water inflow Insufficient water inflow Insufficient water inflow Plant Stopped due Low Head Unit Maintenance Unit Maintenance Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient water inflow

2276:10

2438:10

264:00 349:10 659:10 635:10 273:30

Insufficient water inflow Insufficient water inflow Insufficient water inflow Insufficient Water inflow Insufficient Water inflow Trash gate repair Elec/Mech Maintenance Plant Stopped for the Maintenance

2181:00

2380:50

72:55 59:50 32:20 34:45 92:10

107:40

Page No. 19

24.75 MW Someshswara SHP

Monitoring Report Annex-2

Justification for Excess Net Electricity Generation during the Reported Period The projected power generation (in GWh) in the Detailed Project Report (DPR), as reflected in the registered PDD and the actual generations during the reported period are furnished below:

27 May 08 to 31 Mar 09

01 Apr 09 to 30 Sep 09

As per Regd. PDD

Actual

As per Regd. PDD

Actual

a

109.195

43.300 a

56.435

GWh

2.505

1.956

1.299

1.005

GWh

80.995 b

107.239 c

42.001 b

55.430 c

Electricity Imported to grid

GWh

0

0.019 c

0

0.0001 c

Net electricity Exported to grid

GWh

80.995

107.220

42.001

55.430

Parameters

Gross electricity generation Aux. consumption incl. Transform & Transmission losses Net electricity generation (Exported to grid)

Units

GWh

83.500

Variation

+ 32.4%

+ 32.0%

Net emission reductions for the reported period = (140020 – 105883) x 100 / 105883 = 32.24%

a b c

As per Hydrology study carried out which forms part of the DPR. Adjusted by taking 3% as Aux. consumption & other losses as projected in the PDD. Computed based on Monthly electricity readings recorded & certified by KPTCL personnel.

The first reason for the excess electricity generation compared to the projection in the PDD is that the rainfall in the catchment area of rivers Cauvery and Kabini was above normal for the region and also due to consecutive depressions in the ocean of Bay of Bengal and Arabian sea which resulted in heavy rain fall during monsoon (June to September). As per Annual climate summary 20081 published by India Meteorological Department, Govt. of India and the Seasonal rainfall2 published by India Meteorological Department, Pune, the cumulative rainfall

1

2

Page No. 22: Rainfall Statistics – Table-1 vide web link http://www.imdpune.gov.in/research/ncc/climatebulletin/annual%20summary%202008.pdf http://www.imdpune.gov.in/mons_monitor/mm_index.html Page No. 20

24.75 MW Someshswara SHP

Monitoring Report

in the catchments area of Cauvery river for the reported period are above of its Long Period Average (LPA). The details of rain fall in South Interior Karnataka (Covered Cauvery river catchments area) are presented below:

Year 2008 Period

Normal

Winter (Jan – Feb)

5.4

19.6

% Excess 260

Pre-Monsoon (Mar-May)

150.4

219.2

46

May

97.3

Monsoon (Jun to Sep)

659.3

721.7

9

Post-Monsoon (Oct to Dec)

199.7

145.2

-27

Actual

Year 2009 Actual

% Excess

109.53

13

855.3

30

Apart from the above, the pp also reviewed the discharge data was recorded for the period of 10 years i.e. from 1985-86 to 1995-96 at Dhanagere anicut by Central Water Commission (CWC) at time of Detailed project report (DPR) and in the absence of relevant data for the following are not accounted in the estimated average annual export power to grid of 81.48 MW.

 No corrections to the recorded data for the additional catchment area made at Dhanagere anicut.  The releases into Dhanagere irrigation canal The uncertainty relating to water discharges was in fact one of the key risk factors affecting the project. The investment decision, and hence the projected power generation in the PDD, were based on a conservative average water discharge level of 56.0 cubic meters per second (cumec) as reflected in PDD, corresponding to an average plant load factor of 38.7%. The Second reason for net electricity generation is that the Actual losses recorded during the reported period and the projected losses in the registered PDD are 1.8% against 3% which was projected in the registered PDD.

3

Table 1: Meteorological subdivision wise rainfall statistics for the month of may 2009 based on operational data vide web link http://www.imdpune.gov.in/research/ncc/climatebulletin/may09.pdf

Page No. 21

24.75 MW Someshswara SHP

Monitoring Report

In light of higher water flows in the river from the above-mentioned factors which could not be relied upon at the time of PDD writing and reduction in auxiliary power including losses, the net electricity generations are about +32.24% higher than the estimated electricity generations in the registered PDD. As there is no restriction on the plant load factor (PLF) from the state electricity board authorities (Karnataka Power Transmission Corporation Limited), the project activity has utilized the available water flows and generated excess electricity generation is deemed acceptable.

Page No. 22

24.75 MW Someshswara SHP

Monitoring Report

Enclosure -1

Page No. 22: Rainfall Statistics – Table-1 vide web link http://www.imdpune.gov.in/research/ncc/climatebulletin/annual%20summary%202008.pdf

TABLE – 1 METROLOGICAL SUB-DIVISION WISE SEASONAL AND ANNUAL RAINFALL STATISTICS FOR THE YEAR 2008 BASED ON OPERATIONAL DATA

Page No. 23

24.75 MW Someshswara SHP

Monitoring Report

Page No. 24

24.75 MW Someshswara SHP

Monitoring Report

Page No. 25

24.75 MW Someshswara SHP

Monitoring Report

Source: http://www.imdpune.gov.in/mons_monitor/mm_index.html

Page No. 26

24.75 MW Someshswara SHP

Monitoring Report

Table 1: Meteorological subdivision wise rainfall statistics for the month of may 2009 based on operational data vide web link http://www.imdpune.gov.in/research/ncc/climatebulletin/may09.pdf

Page No. 27

24.75 MW Someshswara SHP

Monitoring Report

Page No. 28

Related Documents


More Documents from "pramods_8"