Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

MUNICIPALIDAD DISTRITAL DE EL TAMBO

INFORME DE SUPERVISION DE CORTE DE OBRA NOVIEMBRE, 2018

“MEJORAMIENTO DE LOS SERVICIO EDUCATIVOS DE LA I.E. DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO”

EL TAMBO – HUANCAYO – JUNIN Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

INDICE 1. INTRODUCCIÓN 1.1

GENERALIDADES

1.2

INFORMACIÓN BÁSICA DE OBRA

1.2.1 1.2.2 1.2.3

Aspectos Generales Ubicación Política y Geográfica Características de las Obras

1.3

ESTADO DE AVANCE DE OBRA

1.3.1 1.3.2

Estado de Avance Físico de Obra Estado de Avance Financiero de Obra

2. ACTIVIDADES DESARROLLADAS 2.1

ACTIVIDADES DESARROLLADAS EN EL PERIODO

2.1.1 2.1.2 2.1.3 2.1.4 2.1.5

Control de Aseguramiento de la Calidad en Obra Control de Calidad de la elaboración del Concreto en Obra Control de Plazo de Ejecución en Obra Control de la Gestión de Seguridad y Salud en Obra Control de la Gestión Ambiental en Obra

2.2 PROGRAMA DE ACTIVIDADES PARA EL MES SIGUIENTE 2.3 PERSONAL Y RECURSOS FISICOS 2.3.1 2.3.2 2.3.3 2.3.4

Personal Profesional Personal Técnico Auxiliar Personal Obrero Maquinaría y Equipos empleados durante el período

3. SUGERENCIAS, CONCLUSIONES Y RECOMENDACIONES 3.1 SUGERENCIAS 3.2 CONCLUSIONES 3.3 RECOMENDACIONES

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

INFORME DE SUPERVISION DE CORTE DE OBRA - NOVIEMBRE, 2018 - FICHA TECNICA DE OBRA 1

INTRODUCCIÓN

1.1

GENERALIDADES

La presente información corresponde al Informe de Supervisión de Obra(Corte de Obra) correspondiente al mes de Noviembre del 2018 con la Valorización de Avance Físico de Obra Nº 02, de la Obra:

“MEJORAMIENTO DE LOS SERVICIO EDUCATIVOS DE LA I.E. DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN - PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO” Que se ejecuta por la Modalidad de Administración Directa la Municipalidad Distrital de El Tambo, ascendiendo a un Presupuesto Total de S/. 189,902.04, con un Plazo de Ejecución de 60 Días Calendarios (2 meses), conforme al Disgregado de Expediente Técnico, priorizado en su presupuesto participativo PIA – 2018, siendo el Ejecutor de Obra la Municipalidad Distrital de El Tambo. La ejecución de la Obra comprende los siguientes Ítems: - Construcción. Aula, comedor escalera tramo primer piso. Siendo estos Ítems correspondientes de acuerdo a Expediente Técnico de Obra: 1.2

INFORMACION BASICA DE OBRA

1.2.1

Aspectos Generales

Obra

: “MEJORAMIENTO DE LOS SERVICIO EDUCATIVOS DE LA I.E.

DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN - PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO” Ubicación Región Departamento Província Distrito

: Zona Urbana del Distrito de El Tambo : Junín : Junín : Huancayo : El Tambo

“MEJORAMIENTO DE LOS SERVICIO EDUCATIVOS DE LA I.E. DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO”. Nombre de la Ejecución de la Obra

:

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

Ubicación

: Cullpa Baja

Distrito

: El Tambo

Província

: Huancayo

Departamento

: Junín

Pliego

: Municipalidad Distrital de El Tambo

Modalidad de Ejecución

: Administración Directa

Código SNIP

: Nº 374470

Monto Total de Obra según Exp. Tec.

: S/.189,902.04 Soles

Aprobación Exp. Técnico

: Resolución Gerencial N°650-2018-MDT/GDUR

Fecha de Aprobación de Exp. Técnico :21 de Setiembre del 2018 Fuente de Financiamiento

: Fondo de Compensación Municipal

Meta Presupuestaria

: 012

Costo Total de Obra

: S/. 189,902.04

Costo Directo total

: S/. 168,054.90

Gastos Generales (10.00% CD)

: S/. 16,805.40

Costos Supervisión de Obra (3.00% CD): S/.

5,041.65

Aporte Beneficiários (10%)

: S/.

18,990.20

Apertura Presupuestal 2018 (MDT)

: S/. 150,000.00

Fecha de Entrega de Terreno

: 03 de Octubre del 2018

Fecha de Inicio de Obra

: 03 de Octubre del 2018

Plazo Ejecución

: 60 Dias Calendarios

Término de Obra Prevista

: 30 de Noviembre del 2018

Paralizacion de Obra N.01

: 30 de Noviembre del 2018

Consultores: Proyectistas - Residencia y Supervisión de Obra Proyectista Nombre

: Victor Cosser de la Cruz

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

1.2.2

Profesión Especialidad Reg. Colegiatura

: Arquitecto : Arquitecto : 16916

Residente de Obra Nombre Profesión Especialidad Reg. Colegiatura Fecha de Designación de Cargo

: Elluzmary Glendy Limaylla Gutierrez : Arquitecto : Arquitecto : 18158 : 03/10/2018

Supervisor de Obra Nombre Profesión Especialidad Reg. Colegiatura Fecha de Designación de Cargo

: Jenny Marlene Blanco Quincho : Ingeniero : Ingeniero Civil : 71299 : 03/10/2018

Ubicación Política y Geográfica El Área donde se encuentran localizadas las obras, pertenece políticamente al Distrito de El Tambo, de la Provincia de Huancayo, Departamento y Región de Junín.

1.2.3

Características de las Obras La ejecución de la Obra comprende:

“MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E. DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN - PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO”. Teniendo programada para esto la ejecución de las siguientes partidas y sub partidas como meta física a ejecutar: ITEM

DESCRIPCION

UND

METR.

PRECIO (S/.)

COSTO PARCIAL (S/.)

MODULO ADMINISTRATIVO 01 01.01

ESTRUCTURAS

105,179.96

OBRAS PROVICIONALES Y TRABAJOS PRELIMINARES

13,178.84

01.01.01

LIMPIEZA DE TERRENO

m2

191.24

1.88

359.53

01.01.02

TRAZO NIVELES Y REPLANTEO PRELIMINAR

m2

191.24

2.59

495.31

01.01.03

CARTEL DE IDENTIFICACION DE OBRA

GLB

1.00

600.00

600.00

01.01.04

ALMACEN Y CASETA DE GUARDIANIA

mes

3.00

400.00

1,200.00

01.01.05

OBRAS PRELIMINARES VARIAS

mes

3.00

165.00

495.00

01.01.06

SEGURIDAD Y SALUD EN OBRA

GLB

1.00

10,029.00

10,029.00

01.02

MOVIMIENTO DE TIERRA

4,322.65

01.02.01

EXCAVACIONES PARA ZAPATAS DE 1.40M A 1.70M

m3

60.50

27.05

01.02.02

EXCAVACIONES DE ZANJAS PARA CIMIENTOS

m3

10.91

20.62

224.96

01.02.03

RELLENO CON MATERIAL PROPIO

m3

30.33

40.33

1,223.21

01.02.04

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=5KM

m3

53.40

14.88

794.59

01.02.05

NIVELACION Y APISONADO PARA FALSO PISO

m2

102.63

4.32

01.03

OBRAS DE CONCRETO SIMPLE

1,636.53

443.36 5,556.27

01.03.01

SOLADO PARA ZAPATAS E=4"

m2

40.33

27.16

1,095.36

01.03.02

CIMIENTO CORRIDO 1:10+30%PG

m3

13.75

206.34

2,837.18

01.03.03

CONCRETO 1:8+25%PM PARA SOBRECIMIENTOS

m3

3.18

262.52

834.81

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299 01.03.04 01.04 01.04.01

ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30M

m2

26.08

30.25

OBRAS DE CONCRETO ARMADO

81,822.20

ZAPATAS

11,198.37

01.04.01.01

CONCRETO PARA ZAPATAS FC=210KG/CM2

m3

24.20

345.47

01.04.01.02

ACERO PARA ZAPATAS FY=4200KG/CM2

kg

612.96

4.63

01.04.02

788.92

COLUMNAS

8,360.37 2,838.00 17,593.77

01.04.02.01

CONCRETO PARA COLUMNAS FC=210KG/CM2

m3

7.47

431.07

01.04.02.02

ENCOFRADO Y DESENCOFRADO PARA COLUMNAS

m2

99.37

40.32

4,006.60

01.04.02.03

ACERO ESTRUCTURAL PARA COLUMNA, FY=4200KG/CM2

kg

2,239.11

4.63

10,367.08

01.04.03

VIGAS

3,220.09

35,176.07

01.04.03.01

CONCRETO PARA VIGAS - FC=210KG/CM2

m3

62.36

364.54

22,732.71

01.04.03.02

ENCOFRADO Y DESENCOFRADO PARA VIGAS

m2

98.70

49.33

4,868.87

01.04.03.03

ACERO PARA VIGAS, FC=4200KG/CM2

kg

1,635.96

4.63

01.04.04

LOSAS ALIGERADAS

7,574.49 15,012.58

01.04.04.01

CONCRETO PARA LOSAS ALIGERADAS FC=210 KG/CM2

m3

10.86

364.54

3,958.90

01.04.04.02

LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO

m2

110.51

52.70

5,823.88

01.04.04.03

ACERO PARA LOSA ALIGERADA, FY'=4200KG/CM2

kg

664.30

4.63

3,075.71

01.04.04.04

BLOQUES HUECOS EN ALIGERADO .30x.30x.15

und

920.55

2.34

2,154.09

01.04.05

ESCALERAS

2,841.41

01.04.05.01

CONCRETO EN ESCALERAS FC=210KG/M2

m3

1.28

338.41

01.04.05.02

ESCALERAS ENCOFRADO Y DESENCOFRADO

m2

9.01

37.80

340.58

01.04.05.03

ESCALERAS ACERO F'Y=4200 KG/CM2

kg

446.58

4.63

2,067.67

und

12.00

25.00

01.05 01.05.01 02 02.01

OTROS

300.00

ROTURA DE PROBETAS ARQUITECTURA

300.00 50,514.30

MUROS Y TABIQUES

8,473.18

02.01.01

MURO DE CABEZA DE LADRILLO CORRIENTE DE 24X13X9

m2

65.70

87.50

02.01.02

MURO DE SOGA DE LADRILLO DE 24X13X9

m2

48.79

55.84

02.02

433.16

REVOQUES Y ENLUCIDOS

5,748.75 2,724.43 15,056.68

02.02.01

TARRAJEO PRIMARIO RAYADO

m2

23.82

21.21

505.22

02.02.02

TARRAJEO EN MUROS INTERIORES

m2

120.61

15.64

1,886.34

02.02.03

TARRAJEO EN MUROS EXTERIORES

m2

77.69

18.36

1,426.39

02.02.04

TARRAJEO EN COLUMNAS

m2

56.56

24.68

1,395.90

02.02.05

TARRAJEO DE COLUMNETAS

m2

16.38

24.68

404.26

02.02.06

TARRAJEO DE VIGAS

m2

60.31

31.30

1,887.70

02.02.07

TARRAJEO EN CIELO RASO

m2

110.51

31.60

3,492.12

02.02.08

VESTIDURA DE DERRAMES

ML

73.78

11.25

830.03

02.02.09

BRUÑAS EN INTERIORES Y EXTERIORES DE 1.0 CM

ML

283.47

11.39

3,228.72

02.03

PISOS Y PAVIMENTOS

5,799.06

02.03.01

FALSO PISO DE 4" DE CONCRETO DE 1:10

m2

102.63

28.14

2,888.01

02.03.02

CONTRAPISO DE 48MM

m2

90.87

25.54

2,320.82

02.03.03

PISO CERAMICO 45X45CM PEGADO Y FRAGUADO C/CEMENTO GRIS

m2

11.76

50.19

590.23

02.03.04

PISO DE CEMENTO PULIDO C/OCRE ROJO

m2

02.04 02.04.01 02.05

36.66

VEREDAS

283.67

PULIDO Y BRUÑADO DE VEREDAS

m2

73.11

3.88

JUNTAS DE DILATACION

283.67 289.85

02.05.01

RELLENO DE JUNTAS CON ASFALTO

ML

29.20

3.17

92.56

02.05.02

JUNTA DE CONSTRUCCIÓN CON TEKNOPOR

ML

49.20

4.01

197.29

02.06

ZOCALOS Y CONTRAZOCALOS

1,936.71

02.06.01

CONTRAZOCALO DE CEMENTO PULIDO

m2

5.16

73.06

02.06.02

CONTRAZOCALO DE CERAMICO DE 20 X 30

m2

5.01

41.55

208.17

m2

23.82

56.74

1,351.55

und

6.00

520.61

02.06.03 02.07 02.07.01 02.08

ZOCALO DE CERAMICO DE 20 x 30 CARPINTERIA DE MADERA

376.99

3,123.66

PUERTA DE MADERA APANELADA CARPINTERIA METALICA

3,123.66 3,922.39

02.08.01

CANTONERAS DE ALUMINIO

ML

26.40

33.58

886.51

02.08.02

BARANDAS Y PASAMANO DE ALUMINIO S/DETALLE

ML

10.80

281.10

3,035.88

pza

10.00

64.48

02.09 02.09.01

CERRAJERIA

1,318.90

CERRADURA PARA PUERTA

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

644.80

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299 02.09.02 02.10

BISAGRA ALUMINIZADA DE 4"X4"

und

22.47

674.10 3,433.74

02.10.01

VIDRIOS LAMINADO DE 6MM - INCOLORO INC. ALUMINIO

m2

02.10.02

VIDRIOS TEMPLEX INCOLORO DE 6MM INC. ACCESORIOS

m2

02.11

30.00

VIDRIOS 21.41

160.38

3,433.74

428.07

PINTURA

6,876.46

02.11.01

PINTURA LATEX EN MUROS INTERIORES

m2

120.61

9.86

1,189.21

02.11.02

PINTURA LATEX EN MUROS EXTERIORES

m2

77.69

8.99

698.43

02.11.03

PINTURA LATEX EN COLUMNAS

m2

56.56

9.27

524.31

02.11.04

PINTURA LATEX EN VIGAS

m2

60.31

10.52

634.46

02.11.05

PINTURA EN DERRAMES

m

124.75

2.54

316.87

02.11.06

PINTURA ESMALTE EN BRUÑAS

ML

422.87

2.81

1,188.26

PINTURA LTEX EN CIELO RASO

m2

221.00

10.52

2,324.92

02.11.07 03 03.01

INSTALACIONES SANITARIAS

4,813.64

APARATOS SANITARIOS Y ACCESORIOS

1,255.15

03.01.01

INODORO TANQUE BAJO COLOR

pza

2.00

204.23

408.46

03.01.02

LAVATORIO OVALIN DE LOSA INCL. INST. Y ACCESORIOS

pza

2.00

281.22

562.44

03.01.03

URINARIO

pza

1.00

194.23

194.23

03.01.04

ESPEJO DE SOBREPONER

und

2.00

45.01

03.02

SISTEMA DE DESAGUE Y VENTILACION

90.02 1,461.68

03.02.01

SALIDAS DE PVC SAL PARA DESAGUE DE 4"

pto

4.00

51.51

206.04

03.02.02

TUBERIA DE PVC SAL 4"

m

19.39

10.32

200.10

03.02.03

SALIDA DE PVC SAL PARA DESGUE DE 2"

pto

7.00

47.52

332.64

03.02.04

TUBERIA DE PVC SAL 2"

m

7.60

6.97

52.97

03.02.05

SALIDAS DE PVC SAL PARA VENTILACION DE 2"

pto

2.00

47.52

95.04

03.02.06

TUBERIA DE PVC SAL 2"

m

8.30

6.97

57.85

03.02.07

SUMIDERO DE 2"

pza

3.00

35.22

105.66

03.02.08

CAJA DE REGISTRO DE DESAGUE 12" X 24"

pza

2.00

76.44

152.88

03.02.09

REGISTROS DE BRONCE DE 4"

pza

2.00

41.89

83.78

03.02.10

YEE PVC SAL 4"

und

2.00

16.17

32.34

03.02.11

YEE DE P.V.C. SAL C/REDUCCION DE 4" - 2"

und

6.00

19.34

116.04

03.02.12

YEE PVC SAL 2"

und

2.00

13.17

26.34

03.02.13

CODO PVC SAL 4"X45°

pza

03.03

17.33

SISTEMA DE AGUA FRIA

1,510.10

03.03.01

SALIDA DE AGUA FRIA CON TUB. DE PVC-SAP1/2"

pto

6.00

27.73

03.03.02

RED DE DISTRIBUCION TUBERIA DE 1/2" PVC SAP

m

18.00

3.70

66.60

03.03.03

VALVULA DE COMPUERTA Ø1/2"

und

3.00

79.31

237.93

03.03.04

TEE PVC DE 1/2"

und

5.00

7.61

38.05

03.03.05

CODO PVC SA´P 1/2" 90°

und

10.00

7.31

73.10

03.03.06

CAJA DE VALVULAS

und

1.00

68.80

68.80

03.03.07

TANQUE ELEVADO

und

1.00

859.24

859.24

m

21.90

11.87

259.95

03.04

SISTEMA DE DRENAJE PLUVIAL

166.38

284.25

03.04.01

TUBERIA DE PVC SAL 3"

03.04.02

YEE DE 3"

und

1.00

12.15

12.15

03.04.03

CODO PVC SAL 3" X 45°

pza

1.00

12.15

12.15

03.04.04

SUMIDERO DE BRONCE DE 3"

pza

03.05

38.21

SUM. E INST. DE ACCESORIOS (RED PUBLICA)

302.46

03.05.01

SUM. E INST. DE ACCESORIOS (RED PUBLICA)

und

1.00

80.88

80.88

03.05.02

PRUEBA HIDRAULICA DE RED

GLB

1.00

221.58

221.58

04 04.01

INSTALACIONES ELECTRICAS

7,547.00

REDES DE ALIMENTACION

95.86

04.01.01

CONDUCTOR LSOH 4mm

ML

25.00

3.31

04.01.02

CONDUCTOR LSOH 4mm - TABLEROS

ML

5.80

2.26

04.02

CABLES Y/O CONDUCTORES

82.75 13.11 559.65

04.02.01

CABLE ELECTRICO 4mm² LSOH TOMACORRIENTES

ML

65.70

2.65

174.11

04.02.02

CONDUCTOR 2.5 mm² LSOH ALUMBRADO

ML

166.90

2.31

385.54

04.03

TUBERIAS Y ACCESORIOS

1,299.30

04.03.01

TUBO PVC-SEL ø 25mm

ML

25.50

11.87

302.69

04.03.02

TUBO PVC-SEL ø 19mm

ML

105.35

9.46

996.61

und

11.00

25.41

04.04 04.04.01

EQUIPOS Y ARTEFACTOS

444.81

SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

279.51

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299 04.04.02

SALIDA PARA INTERRUPTOR SIMPLE

und

3.00

21.20

63.60

04.04.03

SALIDA PARA INTERRUPTOR DOBLE

und

3.00

24.70

74.10

04.04.04

INTERRUPTOR EN CONMUTACION

und

1.00

27.60

04.05

ARTEFACTOS DE ILUMINACION

27.60 3,138.63

04.05.01

ARTEFACTO FLUORESCENTES TCS 300 / TLD 400W

und

12.00

97.25

1,167.00

04.05.02

ECM BOTE FLUORESCENTE (EMPOTRADO)

und

19.00

103.77

1,971.63

04.06

TABLEROS E INTERRUPTORES TERMOMAGNETICOS

2,008.75

04.06.01

TABLERO GENERAL TIPO ENGRAMPE 6 CIRCUITOS

und

1.00

164.34

164.34

04.06.02

TABLERO DE DISTRIBUCION TIPO ENGRAMPE

und

1.00

139.35

139.35

04.06.03

INTERRUPTOR THERMOMGNETICO AUTOMATICO 2X30A X220V

und

3.00

74.06

222.18

04.06.04

INTERRUPTOR THERMOMAGNETICO AUTOMATICO 2X25AX220V

und

3.00

60.12

180.36

04.06.05

INTERRUPTOR THERMOMAGNETICO AUTOMATICO 2X16AX220V

pza

3.00

60.12

180.36

04.06.06

SISTEMA DE LUCES DE EMERGENCIA

GLB

1.00

1,122.16

1,122.16

S/. 168,054.90 S/. 16,805.49 S/. 5,041.65 S/. 189,902.04

COSTO DIRECTO GASTOS GENERALES (10%) SUPERVISION

(3%)

SUB TOTAL

S/. 189,902.04

PRESUPUESTO DE OBRA

1.3

ESTADO DE AVANCE DE OBRA

1.3.1

Estado de Avance Físico de Obra: El Proceso de Ejecución para la Obra: “MEJORAMIENTO DE LOS SERVICIOS

EDUCATIVOS DE LA I.E. DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN - PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO”. al 30 de Noviembre del 2018, se encuentra con el siguiente Avance Físico: Avance Físico Actual - Valorización Avance Físico de Corte de Obra Nº 02, Noviembre - 2018 al 42.61%. 1.3.2

Estado de Avance Financiero de Obra: El Proceso de Ejecución para la Obra: “MEJORAMIENTO DE LOS SERVICIOS

EDUCATIVOS DE LA I.E. DE NIVEL PRIMARIO 30215 DEL ANEXO DE CULLPA BAJA DEL DISTRITO DE EL TAMBO – HYO – JUNIN - PRIMERA ETAPA – CONSTRUCCION DE MODULO ADMINISTRATIVO”. al 30 de Noviembre del 2018, se encuentra con el siguiente Avance Financiero: Avance Financiero Actual 85.3% Informe Avance Físico de Obra Nº 02, Noviembre 2018 – 42.61% acumulado.

2.

ACTIVIDADES DESARROLLADAS

2.1

ACTIVIDADES DESARROLLADAS EN EL PERIODO En el presente mes se han desarrollo las actividades correspondientes a los Procedimientos de Supervisión para el Control de Obras Públicas, con el control de los trabajos en la obra, Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

cautelando de forma directa y permanentemente la correcta ejecución de la obra y el cumplimiento del Expediente Técnico, siendo estas las siguientes partidas ejecutadas durante el presente mes de Octubre del 2018: OBRAS PROVISIONALES, TRABAJOS PRELIMINARES: Limpieza de Terreno manual, Trazo, Nivel y Replanteo Preliminar, Trazo, nivelación y Replanteo durante el proceso, MOVIMIENTO DE TIERRAS: Excavación para zapatas, Relleno y Compactación con material propio, Acarreo de material excedente, Eliminación de material excedente, OBRAS DE CONCRETO SIMPLE: Concreto para cimientos, solado de concreto, concreto para sobrecimientos, encofrado para sobrecimiento, , concreto y acero en Zapatas, Concreto, Encofrado y Acero en Columnas, Vigas concreto, encofrado, acero, Losa Aligerada: Concreto, Encofrado, Acero, Escaleras: Concreto, Encofrado, acero de acuerdo a lo siguiente: ITEM

DESCRIPCION

UND

ACTUAL METR.

ACUMULADO METR.

VALORIZADO

%

MODULO ADMINISTRATIVO 01 01.01

ESTRUCTURAS OBRAS PROVICIONALES Y TRABAJOS PRELIMINARES

01.01.01

LIMPIEZA DE TERRENO

m2

01.01.02

TRAZO NIVELES Y REPLANTEO PRELIMINAR

m2

01.01.03

CARTEL DE IDENTIFICACION DE OBRA

GLB

01.01.04

ALMACEN Y CASETA DE GUARDIANIA

mes

01.01.05

OBRAS PRELIMINARES VARIAS

mes

01.01.06

SEGURIDAD Y SALUD EN OBRA

GLB

01.02

57.37

0.14

191.24

359.53

100%

191.24

495.31

100%

3.00

495.00

100%

0.80

8023.20

80%

MOVIMIENTO DE TIERRA

01.02.01

EXCAVACIONES PARA ZAPATAS DE 1.40M A 1.70M

m3

60.50

1636.53

100%

01.02.02

EXCAVACIONES DE ZANJAS PARA CIMIENTOS

m3

10.91

224.96

100%

01.02.03

RELLENO CON MATERIAL PROPIO

m3

15.17

30.33

1223.21

100%

01.02.04

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA HASTA D=5KM

m3

2.67

45.39

675.40

85%

01.02.05

NIVELACION Y APISONADO PARA FALSO PISO

m2

20.53

61.58

266.02

60%

01.03

OBRAS DE CONCRETO SIMPLE

01.03.01

SOLADO PARA ZAPATAS E=4"

m2

40.33

1095.36

100%

01.03.02

CIMIENTO CORRIDO 1:10+30%PG

m3

4.13

13.75

2837.18

100%

01.03.03

CONCRETO 1:8+25%PM PARA SOBRECIMIENTOS

m3

1.59

3.33

874.17

105%

01.03.04

ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30M

m2

13.04

26.08

788.92

100%

01.04 01.04.01

OBRAS DE CONCRETO ARMADO ZAPATAS

01.04.01.01

CONCRETO PARA ZAPATAS FC=210KG/CM2

m3

24.20

8360.37

100%

01.04.01.02

ACERO PARA ZAPATAS FY=4200KG/CM2

kg

612.96

2838.00

100%

01.04.02

COLUMNAS

01.04.02.01

CONCRETO PARA COLUMNAS FC=210KG/CM2

m3

4.48

7.47

3220.09

100%

01.04.02.02

ENCOFRADO Y DESENCOFRADO PARA COLUMNAS

m2

59.62

99.37

4006.60

100%

01.04.02.03

ACERO ESTRUCTURAL PARA COLUMNA, FY=4200KG/CM2

kg

2239.11

10367.08

100%

01.04.03

VIGAS

01.04.03.01

CONCRETO PARA VIGAS - FC=210KG/CM2

m3

62.36

62.36

22732.71

100%

01.04.03.02

ENCOFRADO Y DESENCOFRADO PARA VIGAS

m2

98.70

98.70

4868.87

100%

01.04.03.03

ACERO PARA VIGAS, FC=4200KG/CM2

kg

1635.96

1635.96

7574.49

100%

01.04.04

LOSAS ALIGERADAS

01.04.04.01

CONCRETO PARA LOSAS ALIGERADAS FC=210 KG/CM2

m3

10.86

10.86

3958.90

100%

01.04.04.02

LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO

m2

110.51

110.51

5823.88

100%

01.04.04.03

ACERO PARA LOSA ALIGERADA, FY'=4200KG/CM2

kg

664.30

664.30

3075.71

100%

01.04.04.04

BLOQUES HUECOS EN ALIGERADO .30x.30x.15

und

920.55

920.55

2154.09

100%

01.04.05

ESCALERAS

01.04.05.01

CONCRETO EN ESCALERAS FC=210KG/M2

m3

1.28

1.28

433.16

100%

01.04.05.02

ESCALERAS ENCOFRADO Y DESENCOFRADO

m2

9.01

9.01

340.58

100%

01.04.05.03

ESCALERAS ACERO F'Y=4200 KG/CM2

kg

446.58

446.58

2067.67

100%

und

12.00

12.00

300.00

100%

01.05 01.05.01 02 02.01

OTROS ROTURA DE PROBETAS ARQUITECTURA MUROS Y TABIQUES

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299 02.01.01

MURO DE CABEZA DE LADRILLO CORRIENTE DE 24X13X9

m2

65.70

65.70

5748.75

100%

02.01.02

MURO DE SOGA DE LADRILLO DE 24X13X9

m2

19.52

19.52

1089.77

40%

02.02

REVOQUES Y ENLUCIDOS

02.02.01

TARRAJEO PRIMARIO RAYADO

m2

02.02.02

TARRAJEO EN MUROS INTERIORES

m2

02.02.03

TARRAJEO EN MUROS EXTERIORES

m2

02.02.04

TARRAJEO EN COLUMNAS

m2

02.02.05

TARRAJEO DE COLUMNETAS

m2

02.02.06

TARRAJEO DE VIGAS

m2

02.02.07

TARRAJEO EN CIELO RASO

m2

02.02.08

VESTIDURA DE DERRAMES

ML

02.02.09

BRUÑAS EN INTERIORES Y EXTERIORES DE 1.0 CM

ML

02.03

PISOS Y PAVIMENTOS

02.03.01

FALSO PISO DE 4" DE CONCRETO DE 1:10

m2

71.84

71.84

2021.61

70%

02.03.02

CONTRAPISO DE 48MM

m2

63.61

63.61

1624.57

70%

02.03.03

PISO CERAMICO 45X45CM PEGADO Y FRAGUADO C/CEMENTO GRIS

m2

PISO DE CEMENTO PULIDO C/OCRE ROJO

m2

02.03.04 02.04 02.04.01 02.05

VEREDAS PULIDO Y BRUÑADO DE VEREDAS

m2

JUNTAS DE DILATACION

02.05.01

RELLENO DE JUNTAS CON ASFALTO

ML

02.05.02

JUNTA DE CONSTRUCCIÓN CON TEKNOPOR

ML

02.06

ZOCALOS Y CONTRAZOCALOS

02.06.01

CONTRAZOCALO DE CEMENTO PULIDO

m2

02.06.02

CONTRAZOCALO DE CERAMICO DE 20 X 30

m2

02.06.03 02.07 02.07.01 02.08

ZOCALO DE CERAMICO DE 20 x 30

m2

CARPINTERIA DE MADERA PUERTA DE MADERA APANELADA

und

CARPINTERIA METALICA

02.08.01

CANTONERAS DE ALUMINIO

ML

02.08.02

BARANDAS Y PASAMANO DE ALUMINIO S/DETALLE

ML

02.09

CERRAJERIA

02.09.01

CERRADURA PARA PUERTA

pza

02.09.02

BISAGRA ALUMINIZADA DE 4"X4"

und

02.10

VIDRIOS

02.10.01

VIDRIOS LAMINADO DE 6MM - INCOLORO INC. ALUMINIO

m2

02.10.02

VIDRIOS TEMPLEX INCOLORO DE 6MM INC. ACCESORIOS

m2

02.11

PINTURA

02.11.01

PINTURA LATEX EN MUROS INTERIORES

m2

02.11.02

PINTURA LATEX EN MUROS EXTERIORES

m2

02.11.03

PINTURA LATEX EN COLUMNAS

m2

02.11.04

PINTURA LATEX EN VIGAS

m2

02.11.05

PINTURA EN DERRAMES

m

02.11.06

PINTURA ESMALTE EN BRUÑAS

ML

PINTURA LTEX EN CIELO RASO

m2

02.11.07 03 03.01

INSTALACIONES SANITARIAS APARATOS SANITARIOS Y ACCESORIOS

03.01.01

INODORO TANQUE BAJO COLOR

pza

03.01.02

LAVATORIO OVALIN DE LOSA INCL. INST. Y ACCESORIOS

pza

03.01.03

URINARIO

pza

03.01.04

ESPEJO DE SOBREPONER

und

03.02

SISTEMA DE DESAGUE Y VENTILACION

03.02.01

SALIDAS DE PVC SAL PARA DESAGUE DE 4"

pto

1.60

82.42

40%

03.02.02

TUBERIA DE PVC SAL 4"

m

3.88

40.02

20%

03.02.03

SALIDA DE PVC SAL PARA DESGUE DE 2"

pto

1.40

66.53

20%

03.02.04

TUBERIA DE PVC SAL 2"

m

03.02.05

SALIDAS DE PVC SAL PARA VENTILACION DE 2"

pto

03.02.06

TUBERIA DE PVC SAL 2"

03.02.07

SUMIDERO DE 2"

pza

03.02.08

CAJA DE REGISTRO DE DESAGUE 12" X 24"

pza

m

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299 03.02.09

REGISTROS DE BRONCE DE 4"

pza

03.02.10

YEE PVC SAL 4"

und

03.02.11

YEE DE P.V.C. SAL C/REDUCCION DE 4" - 2"

und

03.02.12

YEE PVC SAL 2"

und

03.02.13

CODO PVC SAL 4"X45°

pza

03.03

SISTEMA DE AGUA FRIA

03.03.01

SALIDA DE AGUA FRIA CON TUB. DE PVC-SAP1/2"

03.03.02

RED DE DISTRIBUCION TUBERIA DE 1/2" PVC SAP

03.03.03

VALVULA DE COMPUERTA Ø1/2"

und

03.03.04

TEE PVC DE 1/2"

und

03.03.05

CODO PVC SA´P 1/2" 90°

und

03.03.06

CAJA DE VALVULAS

und

03.03.07

TANQUE ELEVADO

und

03.04

pto m

SISTEMA DE DRENAJE PLUVIAL

03.04.01

TUBERIA DE PVC SAL 3"

03.04.02

YEE DE 3"

und

03.04.03

CODO PVC SAL 3" X 45°

pza

03.04.04

SUMIDERO DE BRONCE DE 3"

pza

03.05

m

SUM. E INST. DE ACCESORIOS (RED PUBLICA)

03.05.01

SUM. E INST. DE ACCESORIOS (RED PUBLICA)

und

03.05.02

PRUEBA HIDRAULICA DE RED

GLB

04 04.01

INSTALACIONES ELECTRICAS REDES DE ALIMENTACION

04.01.01

CONDUCTOR LSOH 4mm

ML

04.01.02

CONDUCTOR LSOH 4mm - TABLEROS

ML

04.02

CABLES Y/O CONDUCTORES

04.02.01

CABLE ELECTRICO 4mm² LSOH TOMACORRIENTES

ML

04.02.02

CONDUCTOR 2.5 mm² LSOH ALUMBRADO

ML

04.03

TUBERIAS Y ACCESORIOS

04.03.01

TUBO PVC-SEL ø 25mm

ML

5.10

5.10

60.54

20%

04.03.02

TUBO PVC-SEL ø 19mm

ML

21.07

21.07

199.32

20%

04.04

EQUIPOS Y ARTEFACTOS

04.04.01

SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE

und

04.04.02

SALIDA PARA INTERRUPTOR SIMPLE

und

04.04.03

SALIDA PARA INTERRUPTOR DOBLE

und

04.04.04

INTERRUPTOR EN CONMUTACION

und

04.05

ARTEFACTOS DE ILUMINACION

04.05.01

ARTEFACTO FLUORESCENTES TCS 300 / TLD 400W

und

04.05.02

ECM BOTE FLUORESCENTE (EMPOTRADO)

und

04.06

TABLEROS E INTERRUPTORES TERMOMAGNETICOS

04.06.01

TABLERO GENERAL TIPO ENGRAMPE 6 CIRCUITOS

und

04.06.02

TABLERO DE DISTRIBUCION TIPO ENGRAMPE

und

04.06.03

INTERRUPTOR THERMOMGNETICO AUTOMATICO 2X30A X220V

und

04.06.04

INTERRUPTOR THERMOMAGNETICO AUTOMATICO 2X25AX220V

und

04.06.05

INTERRUPTOR THERMOMAGNETICO AUTOMATICO 2X16AX220V

pza

04.06.06

SISTEMA DE LUCES DE EMERGENCIA

GLB

S/. 71,613.20

COSTO DIRECTO GASTOS GENERALES (10%) SUPERVISION

S/. 7,161.32

(3%)

S/. 2,148.40

SUB TOTAL

S/. 80,922.22

PRESUPUESTO DE OBRA PORCENTAJE DE AVANCE MENSUAL

3.

66.11%

Control de Aseguramiento de la Calidad en la Ejecución Física de Obra En el proceso de Ejecución de Obra, se verifico la calidad de todos los Materiales, Insumos, Equipos y Herramientas ingresados a Almacén General, por parte del Residente de Obra, tal Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

como consta en anotaciones de Cuaderno de Obra, este verifico también los Procesos Constructivos respecto a la ejecución de las partidas ejecutadas, solicitándose a la Residencia previo a los vaciados de concreto hidráulico, la obtención del Ensayo de Diseño de Mezcla (ASTM D- 1556), para vaciado de vereda de concreto fc=175 kg/cm2, ya que por la configuración del suelo en la zona geomorfológica del Distrito de El Tambo, este cuenta históricamente con suelos de característica de buena graduación, ya que en su mayoría corresponden al grupo de grabas bien graduadas, del tipo GP y GM, en la clasificación del SUCS, teniéndose en la norma del AASHTO, los tipos A-1-a, y el A-1-b, de igual forma se solicitó la obtención de moldeo de muestras representativas de concreto - Testigos (ASTM C39-192), refrendadas en probetas cilíndricas reglamentarias - Probetas (ASTM C-617), para su posterior ensayo a Compresión Simple (ASTM C-31-39-172), para evaluar la resistencia de diseño del concreto elaborado y producido en campo. Topográficamente la Ejecución Física de Obra se encuentra bajo control, ya que se tienen definidos los trazos de los niveles y alineamientos de todos los componentes del proyecto a ejecutarse, los que guardan relación a lo planteado en los Planos de Obra, contemplados en el Expediente Técnico. 3.1.1

Control de Calidad de la Elaboración del Concreto en la Ejecución Física de Obra En el proceso constructivo de la elaboración del concreto simple F’c= 140, 175, y 210 Kg/cm2, se siguieron los controles para concretos en climas fríos (climas fríos temperaturas bajo de 0 °C):      

3.1.2

Recopilación y verificación de las condiciones ambientales locales de temperatura, humedad relativa, lluvia, presión atmosférica etc. para establecer los ciclos del clima híbrido y su trascendencia en cada caso particular. Evaluar y planificar la temperatura de colocación en el rango de 10ºC a 13ºC para una temperatura ambiente no menor de 7ºC. (Alternativas: cemento, agua, agregados). Estimar la temperatura pico adiabática, siendo recomendable que no sea menor de 30ºC. (Tipo de cemento, en este caso cemento Portland Tipo I). Decidir el sistema de protección en base a las consideraciones y condiciones particulares. Evaluación experimental previa en el sitio de obra de diseños de mezcla, aditivos y técnicas de curado y protección en periodo mínimo de 48 horas. Determinar la duración del periodo de protección en función del tiempo en que el concreto alcanza 35 kg/cm2 de resistencia en compresión bajo las condiciones de curado en obra.

Control del Plazo de Ejecución en la Ejecución Física de Obra Se hace Entrega de Terreno el 03 de Octubre del 2018 y se da Inicio de Obra el mismo 03/10/2018, de acuerdo a Expediente Técnico de Obra se tiene un Plazo de Ejecución de Obra contractual de 60 Días Calendarios, por lo que la Ejecución Física de la Obra debería concluirse el 01/12/2018, cumpliendo con las partidas programadas de acuerdo al Expediente técnico.

3.1.3

Control de la Gestión de Seguridad y Salud en el Trabajo Se realizaron los procedimientos para el seguimiento y la implementación de las Normas Peruanas de Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

Seguridad y Salud en el Trabajo en Obras Públicas, con la gestión de la seguridad y salud ocupacional mediante la implementación de la Norma OHSAS 18001:2007, realizándose los reportes de las charlas de seguridad diaria de 5 minutos a todo el personal profesional, técnico y obrero, antes del inicio de la jornada de labor diaria, con la finalidad de solicitar si fuera el caso los reportes de incidentes y evitar en gran medida llegar a los accidentes no deseados, además de la exigencia de controlar el uso de implementos de seguridad (EPP’s), para todo el Personal en Obra, , se está poniendo de conocimiento a la Sub Gerencia de Obras Publicas de la Entidad, el cumplimiento estricto de la implementación de los Procedimientos Técnicos Administrativos de la Ley Nº 29783, Ley de Seguridad y Salud en el Trabajo, realizándose en el mes de Julio del 2018, la elección del representante del Comité de Seguridad y Salud en el Trabajo, siendo este elegido por mayoría el Sr. Solano Maestro de Obra, el cual fue elegido y designado mediante proceso electoral, ya que por tener menos de 20 trabajadores, en este caso de 06 trabajadores, se eligió al Supervisor de Seguridad y Salud en el Trabajo, además de la elaboración del IPERC, Mapa de Riesgos, Plan de Seguridad y Salud en el Trabajo, Reglamento Interno, así como haber realizado los Registros de capacitaciones diarias de inducción en temas de seguridad y salud en el trabajo a todo el personal profesional, técnico y obrero, conforme a las exigencias de la Norma de Seguridad y Salud en el Trabajo (Ley 29783 y su Reglamento D.S. 005-2012-TR, R.M. 148-2012-TR), fiscalizadas y auditadas por el Ministerio de Trabajo, Promoción y Empleo, a través de la Superintendencia Nacional de Fiscalización Laboral (SUNAFIL), además de permitir que cada trabajador ingrese con la Constancia de Evaluación Medico Ocupacional, concerniente a los programas de vacunación y exámenes médicos ocupacionales a los trabajadores con el seguro en convenio con la Empresa SALUD OCUPACIONAL “LABORAL CARE SST”; así como de haber considerado en el Presupuesto Analítico los costos para el Seguro Complementario de Trabajo de Riesgo (SCTR), cual genero la solicitud de un anticipo de gasto a cargo de la Residencia de Obra, para realizar los pagos ante una aseguradora para todo personal que viene laborando en la Ejecución de Obra. 3.1.4

Control de la Gestión Ambiental en la Ejecución Física de Obra La Obra cuenta con una Evaluación de Impacto Ambiental la que se ha alcanzado junto con el Expediente Técnico, el cual se utiliza para la mitigación de impactos ambientales negativos, que en el caso del Proceso de Ejecución de Obra son impactos leves; se ha instruido y capacitado oportunamente a los responsables de cada frente de trabajo conforme a los avances de sus partidas, que se cumpla con la limpieza y reciclaje de residuos sólidos durante la Ejecución de la Obra, mediante la utilización de tachos de residuos, clasificados por colores, vinculados a la construcción y operación del proyecto, presentando las medidas de manejo ambiental que deberán tomarse en cuenta para prevenir, mitigar o controlar posibles impactos que se puedan presentar en el proceso constructivo de la Ejecución de Obra; y en cumplimiento a la Ley Nº 28245, Ley marco del Sistema Nacional de Gestión Ambiental, Ley Nº 27446, Ley del Sistema Nacional de Evaluación de Impacto Ambiental, Decreto Legislativo Nº 1078, Modificatoria de la Ley del Sistema Nacional de Evaluación de Impacto Ambiental, Decreto Supremo Nº 019-2009-MINAM, Reglamento de la Ley del Sistema Nacional de Evaluación de Impacto Ambiental, y las Resoluciones Ministeriales Resolución Ministerial N° 239-2010-MINAM, Procedimiento denominado “Disposiciones para la revisión aleatoria de Estudios de Impacto Ambiental aprobados por las Autoridades Competentes”, Resolución Ministerial Nº 157-2011-MINAM, cual aprueban la primera actualización del listado de inclusión de los proyectos de inversión sujetos al Sistema Nacional de Evaluación de Impacto Ambiental.

3.1.5

Control Económico Financiero en la Ejecución Física de Obra

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

Se cuenta de acuerdo a Valorización Final de Obra , Noviembre del 2018, correspondiente al periodo del 01/11/2018 al 30/11/2018, con un Avance Físico Acumulado del 66.67%, frente al 67.40% de Avance Financiero, de acuerdo a Informe de Avance Financiero de Obra Nº 02, Noviembre del 2018, lo cual indica una estabilidad, sustentado gastos de mano de obra, materiales y equipos trabajando con el aporte del comité de gestión correspondiente al 10% de su cofinanciamiento, siendo este la suma de S/.0.00 Nuevos Soles y los materiales, indumentarias (implementos de seguridad), herramientas, etc, de parte de la Municipalidad Distrital de El Tambo y el aporte de los beneficiarios, los cuales son sustentados financieramente. 3.1.6

Control de la Gestión de Riesgos en la Planificación de Obras Se prevé necesario incorporar una norma por extensión al tipo de modalidad de la presente Ejecución de Obra, observando lo que entro en vigencia el 03 de abril del 2017, con las modificaciones a la Ley y el Reglamento, mediante Decreto Legislativo Nº 1341, y Decreto Supremo N° 056-2017-EF, en este contexto, el numeral 32.2 del artículo 32 de la Ley, incorporado mediante Decreto Legislativo Nº 1341, precisa que la planificación de obras deberá realizarse siguiendo el enfoque de la denominada “administración de riesgos”, conforme a lo siguiente: “En los contratos de obra deben identificarse y asignarse los riesgos previsibles de ocurrir durante su ejecución, según el análisis realizado en la planificación. Dicho análisis forma parte del expediente técnico y se realizará conforme a las directivas que se emitan para tal efecto, según los criterios establecidos en el reglamento, en esa misma línea, el numeral 8.2 del artículo 8 del Reglamento, incorporado por el Decreto Supremo N° 056-2017-EF señala que: “Para la contratación de obras, la planificación debe incluir la identificación y asignación de riesgos previsibles de ocurrir durante la ejecución, así como las acciones y planes de intervención para reducirlos o mitigarlos, conforme a los formatos que apruebe el OSCE. El análisis de riesgos implica clasificarlos por niveles en función a: (i) su probabilidad de ocurrencia y (ii) su impacto en la ejecución de la obra”, de acuerdo con las disposiciones citadas, el Expediente Técnico de Obra elaborado durante la etapa de planificación, debe incorporar un estudio de todos aquellos riesgos previsibles que pudiesen afectar la correcta y oportuna ejecución de la obra, con la finalidad de que, a partir de dicho análisis, se determinen las acciones o planes de intervención a seguir durante la etapa de ejecución, y de ese modo, se puedan evitar, reducir y/o asignar aquellos riesgos previamente identificados.

3.2

PERSONAL Y RECURSOS FISICOS Se detalla el personal que labora en la Obra en el mes que se informa, tanto Profesional y Técnico a cargo, así como Mano de Obra calificada y No calificada.

2.3.1

Personal Profesional - Ing. Jenny Marlene, BLANCO QUINCHO - Arq. Elluzmary Glendy LIMAYLLA GUTIERREZ

: :

Supervisor de Obra Residente de Obra

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

2.3.2

Personal Técnico Auxiliar - 01 Técnico Administrativo - 01 Maestro de Obra - 01 Almacenero de Obra

2.3.3

Personal Obrero 

Personal Obrero - Mano de Obra No Calificada (Planilla): Al 31/10/2018: - 04 Operarios - 02 Peones - 02 Oficial 2.3.4

Maquinarías y Equipos empleados durante el período 

Equipos pesados y Equipo liviano: Se detallan a las maquinarias pesadas y los equipos livianos proporcionados por la Entidad, en calidad de apoyo en la Ejecución de Obra, que se utilizaron en la misma en el mes de Octubre del 2018, de acuerdo a los Requerimientos del Presupuesto Analítico de Obra y Especificaciones Técnicas del Expediente Técnico, según las partidas que se ejecutaron, los cuales son:  01 Mezclador de Concreto tipo trompo



Materiales, Insumos y Herramientas: Los beneficiarios a la fecha no realizan ningún aporte los que retrasa las actividades programadas, solicitando urgentemente que abastezcan los materiales solicitados con la finalidad de culminar la obra en la fecha prevista.,

3.00.- SUGERENCIAS, CONCLUSIONES Y RECOMENDACIONES 3.1 SUGERENCIAS: 1)

Se sugiere en experiencias futuras, reproducir experimentalmente las condiciones más desfavorables para el vaciado en altura e instrumentar la medición del comportamiento termodinámico.

2)

Se sugiere en experiencias futuras, establecer con precisión los periodos de clima híbrido y el comportamiento del concreto en cada rango.

3)

Se sugiere en experiencias futuras, como regla general aprovechar la naturaleza exotérmica de la hidratación del cemento aislándolo en el período frío y exponiéndolo al medio ambiente durante el periodo cálido para concentrar calor e incrementar la temperatura promedio de curado.

4)

Se sugiere en experiencias futuras, considerar al definir el F’c criterios de durabilidad basados en relaciones A/C máximas antes que resistencias requeridas en obra por criterios de expectativa de falla.

3.2 CONCLUSIONES:

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

1) En cuanto al seguimiento del control de la Calidad del Concreto en su proceso constructivo, se verificaron las Normas ASTM C-150 (Cementos Standard), ASTM C-33 (Limites Granulométricos), ASTM C-94 (Especificaciones para Concreto Premezclado); así como las condiciones de almacenaje. 2) En cuanto al Avance Físico, del Mes de Noviembre del 2018, es del 43.06%, y el Avance Físico Acumulado Actual del 66.67%, y siendo el Avance Físico Programado Acumulado Actual del 67.80%, por lo que la obra presenta ATRASADO en cuanto a lo programado. 3) En cuanto al Plazo de Ejecución de Obra, se indica que el plazo previsto es de 60 D/C, sin considerar el plazo para la elaboración del Informe Final de Obra, el cual viene siendo afectado por la falta de aporte de beneficiarios, el desabastecimiento de maquinarias. 4) Se está presentando a la Sub Gerencia de Obras Publicas de esta Municipalidad el INFORME DE CORTE DE SUPERVISION DE OBRA , correspondiente al Mes de Noviembre - 2018, con la Valorización de Obra Nº 02 de Avance de Ejecución Física y Financiera de Obra. 5) Se acompaña al presente informe mensual toda la documentación técnica y financiera requerida al Residente de Obra, tales como: Informe Mensual de Residente de Obra, Asientos de Cuaderno de Obra, Copia de Acta de Entrega de Terreno, Copia de Acta de Inicio de Obra, Datos Generales del Proyecto, Memoria Descriptiva, Avance Financiero, Planilla de Metrados Ejecutados, Resumen de Valorización, Hechos Importantes, Hechos que alteran la Ejecución de Obra, Hoja de Tareo, Movimiento de Almacén, Utilización de Maquinarias, Salida de Combustible, Copia de Kardex, Curva de Reporte S, Vistas Fotográficas del Proceso Constructivo, y Copia de Resolución de Aprobación de Expediente Técnico. 6) La obra está PARALIZADA por motivo de falta de aprobación de la Ampliación de Plazo N.01.

3.3 RECOMENDACIONES: 1) Se recomienda a la Municipalidad notificar a las partes interesadas Residente de Obra y Supervisor de Obra, a fin de cumplir con las Normas y Leyes vigentes enmarcadas en la Seguridad y Salud en el Trabajo, así como en cumplimiento de las metas previstas en el Expediente Técnico. 2) Se recomienda a la Municipalidad que una vez presentado los requisitos con fines de Recepción de Obra, en su oportunidad, esta nombre y/o designe a la Comisión de Recepción de Obra, para que se fije fecha y hora para el acto de Recepción de Obra; así mismo se notifique formalmente a las partes interesadas. 3) Se recomendó al Residente de Obra informar sobre el avance de la ejecución del gasto financiero que representa la ejecución física, a fin de evaluar el balance de la ejecución física Vs. Financiera, y determinar que los gastos se ejecuten de acuerdo a lo programado. 4) Se recomendó al Residente de Obra llevar el control adecuado en cuanto al manejo de materiales mediante el movimiento de almacén, kardex, vincar y otros necesarios. 5) Se recomendó al Residente de Obra llevar el control adecuado en cuanto al manejo de insumos como es el caso del combustible D2 y Gasolina, mediante el movimiento de Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

almacén, con el control de horas máquinas de los equipos empleados, así como el ratio por cada uno y otros necesarios. 6) Se recomendó al Residente de Obra dar estricto cumplimiento al Sistema de Gestión de Seguridad y Salud en el Trabajo, Ley 29783, realizando obligatoriamente todos los días las charlas diarias de seguridad de 5 minutos para todo el personal de Técnico, Administrativo, y Mano de Obra calificada y no calificada. 7) Se recomendó al Residente de Obra, llevar el control de la Gestión Ambiental en Obra, con la Evaluación de Impacto Ambiental en el Proceso de Ejecución de Obra, con la instrucción y capacitación oportuna a los responsables de cada frente de trabajo conforme a los avances de sus partidas, para que se cumpla con la limpieza y reciclaje de residuos sólidos durante la Ejecución de la Obra, vinculados a la construcción y operación del proyecto, presentando las medidas de manejo ambiental que deberán tomarse en cuenta para prevenir, mitigar o controlar posibles impactos que se puedan presentar en el proceso constructivo de la Ejecución de Obra. 8) Se recomendó al Residente de obra presentar a esta Supervisión los certificados de calidad correspondientes de las actividades en obra, con la finalidad de concluir en la fecha prevista y sin mayores contratiempos. 9) Se presenta el informe de Corte de Obra, con el avance físico y financiero, con la finalidad que pueda ser culminada, de acuerdo al expediente técnico de la obra. 10) Se presenta la solicitud de Ampliación de plazo N.01 por 15 días y la Ampliación de plazo N.02 por 6 días, los cuales están en proceso de tramite 11) Se presenta el Expedientillo de Adicional de obra, el cual está en trámite de aprobación. 12) Se solicita el Complemento Presupuestal por S/.20,000.00, los cuales ya están en proceso de trámite. Es todo lo que informo a Ud. para los fines pertinentes. Atentamente;

--------------------------------------------------------------------------------JENNY MARLENE BLANCO QUINCHO SUPERVISOR DE OBRA Reg. del CIP Nº 71299.

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

PANEL FOTOGRAFICO

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

VISTA FOTOGRAFICA N° 01: Se aprecian los trabajos de verificación de la calidad de materiales, en este caso el agregado piedra chancada y hormigón, a ser utilizados en la producción de concreto hidráulico F’c= 140, 175, 210 Kg/cm2.

VISTA FOTOGRAFICA N° 02: Se aprecian los trabajos de verificación de la calidad de materiales, en este caso el Cemento Portland Tipo I, viéndose que la Entidad suministro la marca CEMENTOS NACIONAL, por lo cual se tubo a la vista el certificado de las características físico técnicas del producto, cumpliendo con la Norma ASTM C-150 (Cementos Standard).

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

VISTA FOTOGRAFICA N° 03: Se aprecian los trabajos de verificación de dosificación de mezcla en trabajos de preparación y producción de concreto hidráulico F’c= 175 Kg/cm2, para aceras peatonales, y sardineles, teniéndose a la vista el Diseño de Mezcla de Concreto

VISTA FOTOGRAFICA N° 04: Se aprecian los trabajos de verificación previa a la autorización de vaciado de concreto hidráulico, de densidades de campo en base conformada para aceras peatonales, con el Ensayo de Densidad de Campo, a cargo de personal especializado que se ha contratado por servicios, el cual será afectado a la partida del aporte económico del Comité de Gestión de Pistas y Veredas.

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

VISTA FOTOGRAFICA N° 05: Se aprecian los trabajos de verificación de encofrados en aceras peatonales en Cuadra 01 del Jr. Libertad, viéndose las condiciones operativas de las maderas para los encofrados, así como el vaciado de concreto hidráulico F’c=175 Kg/cm2.

VISTA FOTOGRAFICA N° 06: Se aprecian los trabajos de verificación de acabados en aceras peatonales, distanciamiento de bruñas y textura de superficies, así como las indicaciones sobre la necesidad de la hidratación del concreto fresco, frente a variaciones térmicas propias de la región Sierra.

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

VISTA FOTOGRAFICA N° 07: Se aprecian los trabajos de verificación de toma de testigos de mezcla de concreto, con el moldeo, en probeta cilíndrica reglamentaria, para luego pasar al proceso de hidratación sumergida en un periodo de 07 días, para posterior a ello ser llevadas a un Laboratorio de Ensayo de Materiales, para la realización del Ensayo de Compresión Simple, y determinar su esfuerzo a compresión simple F’c.

VISTA FOTOGRAFICA N° 08: Se aprecian los trabajos de verificación de base compactada a nivel de sub rasante, así como de las recomendaciones a la Residencia de Obra, que frente a las lluvias continuas que se vienen presentando, tengan que proteger los trabajos correspondientes a la compactación de la sub rasante, puesto que esta aun no alcanza el porcentaje necesario del 95% del CBR.

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

VISTA FOTOGRAFICA N° 09: Se aprecia panorámicamente los efectos catastróficos que deja la inclemencia del clima, con la caída de lluvias torrenciales, cuales dañan los trabajos realizados en la Ejecución Física de Obra, afectando severamente el Plazo de Ejecución, poniendo en conocimiento a la Sub Gerencia de Obras de la Entidad, que próximamente se estará solicitando la Ampliación de Plazo Nº 01, por las causales señaladas. EL TAMBO, 05 de Marzo del 2018.

Atentamente;

--------------------------------------------------------------------------------CHRISTIAN ENRIQUE AMES CAMARGO SUPERVISOR DE OBRA Reg. del CIP Nº 84274 - Reg. Cap. Consultoría C7935

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Jenny Marlene Blanco Quincho INGENIERO CIVIL REG. CIP. Nº 71299

Jr. El Agracejo Lote 14 Mz L-Umuto – El tambo-Huancayo Telf. 064750599 Cel.: 954462294 E-mail: [email protected]

Related Documents

Informe De Corte De Obra
February 2021 1
Corte De Obra
March 2021 0
Corte De Obra
February 2021 1
Infor Corte De Obra
February 2021 1
Informe- De Corte Directo
January 2021 1

More Documents from "Evans Arce Garcia"

Informe De Corte De Obra
February 2021 1
Aminoglucosidos
February 2021 0
Norma Din 1052 - Maderas
January 2021 4
Plan De Marketing
January 2021 2
Curso De Test Stand_ni
January 2021 2
January 2021 1