    ENI - IRAQ  ZUBAIR OIL FIELD DEVELOPMENT PROJECT 

  MOD WATER TREATMENT PROJECT  INSPECTION & TEST PLAN    EX-DE

03

11/06/2020

Issued for Approval

Najm Raad

EX-DE

02

27/05/2020

Issued for Approval

Najm Raad

EX-DE

01

10/05/2020

Issued for Approval

Najm Raad

EX-DE

00

20/03/2020

Issued for Comments

Najm Raad

Validity Status

Rev. Number

Date

Prepared by

Description

Revision index Company logo and business name

Mouayed Zeadan Mouayed Zeadan Mouayed Zeadan Mouayed Zeadan

 

Approved by

Contractor Approval

Talal Ali Talal Ali

Checked by

Project name

Mazin Farman

Haqi Hassan Haqi Hassan Haqi Hassan Haqi Hassan

Talal Ali

Company Document ID

ZUBAIR OIL FIELD DEVELOPMENT PROJECT

eni iraq b.v.

Company Approval

252100DBQA00007 Job n. Contractor Document ID

Contractor logo and business name

Iraq General Company for Execution of Irrigation Projects

 MOD_QA_IGC_ENI_0001 Contract n. 4600039760

Vendor logo and business name

Vendor Document ID Order n.

Facility Name

Location

ZUBAIR FIELD -MOD WATER INTAKE AND TREATMENT PLANT Document Title

Scale ONSHORE

Inspection & Test Plan

Sheet of Sheets

N.A. Supersedes N. Supersedes by N. Plant area 2521

1 of 121

Plant unit N.A.

      This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

1 of 120 

    REVISION HISTORY      No. of sheets Description  105 ISSUED FOR COMMENTS 117 ISSUED FOR APPROVAL 121 ISSUED FOR APPROVAL 121 ISSUED FOR APPROVAL U

Rev.  EX‐DE 00  EX‐DE 01  EX‐DE 02  EX‐DE 03   

Date  20‐03‐2020  10‐05‐2020  27‐05‐2020  11‐06‐2020   

                                     

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

2 of 120 

  INDEX   

1.  INTRODUCTION ................................................................................................................................................................. 4  2.  DEFINITIONS ...................................................................................................................................................................... 4  3.  PROJECT SPECIFICATION DOCUMENTS AND STANDARDS ................................................................................................ 4      3.1 Hierarchy of Regulations .............................................................................................................................................. 5      3.2 Codes and Standards .................................................................................................................................................... 5      3.3 Contract Documents .................................................................................................................................................... 6      3.4 Quality Requirements .................................................................................................................................................. 6      3.5 Eni Iraq BV Specifications ............................................................................................................................................. 6  4.  RESPONSIBILITIES .............................................................................................................................................................. 7  4.1    Contractor ................................................................................................................................................................. 7  4.2    Subcontractor ............................................................................................................................................................ 7  5.  MEETING ........................................................................................................................................................................... 8  5.1  General Pre‐Inspection Meeting .................................................................................................................................. 8  5.2  Regular Inspection and Test Meeting .......................................................................................................................... 8  5.3 Special Quality Meeting ................................................................................................................................................ 8  6.  INSPECTION / TEST CONTROL ........................................................................................................................................... 9  6.1  Inspection/Test Schedule ............................................................................................................................................ 9  6.2  Performance of the inspections .................................................................................................................................. 9  7.  WITNESS INSPECTION ..................................................................................................................................................... 10  8.  WITNESSING GENERAL PRINCIPLES ................................................................................................................................ 11  9.  INSPECTION TEST / REPORT ............................................................................................................................................ 12  9.1 Document review items ............................................................................................................................................. 12  9.2  Inspection Report ........................................................................................................................................................ 12  9.3 Field Inspection Records .............................................................................................................................................. 12  10. APPENDIXES: .................................................................................................................................................................. 13  Appendix 1:  Civil Work .................................................................................................................................................... 14  Appendix 2:  Steel Structure Works ................................................................................................................................. 27  Appendix 3:   Mechanical Works ..................................................................................................................................... 31  Appendix 4:   Piping Works .............................................................................................................................................. 41 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

3 of 120 

Appendix 5:   Electrical Works ......................................................................................................................................... 50  Appendix 6:   Instrument Works ...................................................................................................................................... 67  Appendix 7:   Pipelines Works .......................................................................................................................................... 82  Appendix 8:   Painting Works ........................................................................................................................................... 92  Appendix 9:  Inspection and Test Records (ITR) .............................................................................................................. 96 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007    

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

4 of 120 

 

 

1. INTRODUCTION  This document shall apply to field inspection and test procedure / plan (ITP) for quality control during  construction for the EPC Projects.  Contractor already issued QAP. (Ref. 252100DBQA00003) which approved by ENI. and Considering:  ‐ ‐ ‐ ‐

All applicable discipline ITP’s;  All applicable inspection and testing procedures;  Control of Non Conformances;  Mechanical Completion & punch list management 

     

2. DEFINITIONS     

Company 

ENI IRAQ B.V. & ZFOD 

 

Contractor    

IGC 

 

Subcontractor    

To Be Specified Later 

ITP 

Inspection Test Plan 

NCR  

Non Conformance Report 

ITR 

Inspection Test Report 

QA  

Quality Assurance 

QC  

Quality Control 

QMS  

Quality Management System 

QAP 

Quality Assurance Plan 

QCP 

Quality Control Plan 

NDE 

Non Destructive Examination  

WPS 

Welding Procedure Specification 

PQR 

Procedure Qualification Record 

           

   

 

 

 

 

 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

_______________________________________________________________________________________________ _

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

5 of 120 

3. PROJECT SPECIFICATION DOCUMENTS AND STANDARDS    The Project specification's / International codes and standards will be mentioned clearly in the specified  ITP for each activity in accordance with project design documents include all the working steps with codes  and standards. This specified ITP will be submitted to the Company for approval before commencement of  the work.  The specified ITP's are included, but not limited to, the following listed activities:         

Description of the activities.  Inspection points for each of the activities.  Applicable reference documents.  Applicable check procedures and methods.  Acceptance criteria.  The frequency of inspection.  Remedial actions.  Persons required to be present at the inspections.     

3.1 Hierarchy of Regulations  Contractor will consider following regulations:  1. Local Regulations of the Country where the equipment is installed.  2. Project Specifications and Data Sheets.  3. Company General Specifications.  4. International Codes & Standards.   

  3.2 Codes and Standards 

  The codes and standards that are to be applicable to this project are, but not limited to:      This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

__________________________________________________________________________________________ ______ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Code ISO9001

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Description Quality Management System ISO

Sheet of Sheets

6 of 120 

Edition 2015

Standard and requirements OHSAS18007

Occupational Health and Safety

2007

Management Systems Requirements International Finance Corporation:

Community Health and Safety

04.2007

Environmental, Health and

Noise Management (Impacts of Noise

2007

Safety(EHS) Guidelines

Beyond the Property Boundary of The

General EHS Guidelines:

Facilities)

General EHS Guidelines

Environmental Noise Management Iraqi Standard Adopted of Ambient Air

Standard Adopted Project Air Quality

Quality

Standard

Iraqi Standard Maximum Allowable

Maximum Allowable Emission Limits of Air

Emission

Pollutants Emitted from Stationary

No reference No reference

Limits of Air Pollutants Iraqi Environmental Instruction Article

Regulation of Rivers Conservation/

16 and 25-1967

Regulations for Protecting Public Rivers

1967

and Water from Pollution Iraqi Regulation for the Preservation of

Regulation of Water Resources

Water Sources (Act Nub(2)-2001

Conservation

2001

Amendment)

   

3.3 Contract Documents  All Project activates will be comply with the Contract No. is 4600039760 and its appendixes.    

3.4 Quality Requirements  The Quality Requirements as in Appendix F – QUALITY REQUIREMENT of CONTRACT # 4600039760  “MOD CONSTRUCTION, OPERATION and MAINTENANCE” 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

__________________________________________________________________________________________ ______ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

7 of 120 

3.5 Eni Iraq BV Specifications  The following Eni Iraq BV Specifications:  20189.COO.GEN.SDS

IDENTIFICATION AND TITLE BLOCKS (IDENTIFICATION TABLES) [Eni]

20198.COO.GEN.SDS

ITEM NUMBERING [Eni]

27608.DOC.GEN.SDS

Management and approval of technical documentation

20203.DOC.GEN.SDS

Handover of plant component data and key documents for DBIMP

06215.DOC.GEN.SDS

Facility Functional Units

   

4. RESPONSIBILITIES   

 

4.1    Contractor  1) Contractor shall perform all required activities in contract.  2) Coordination of inspection with Company for control witness inspection, and for evaluation  of its records and results to verify conformance to any specific requirements.  3) Review and approval of the inspection schedule which is prepared and submitted by Sub‐ contractor.  4) Witness the inspection performed by Sub‐contractor at specific points, and for review of the  records and results to verify conformance to the specific requirements.  5) Assur all the inspection procedures will be done related to the Project specifications and  Company standards (and/or) International codes and standards.   

4.2    Subcontractor 

  1) Perform all tests and inspections according to approved ITP.  2) Prepare all necessary for tests and inspections including scaffolding for the witness of  3) Contractor and/or Company.  4) Submit the inspection and/or test records required for verifying conformance with specified  requirements to project.  5) Employ qualified inspection and test personnel to control the inspection, measuring and test  for material, equipment’s and construction.  6) Sub‐contractor under contractor responsibility, So the responsibilities in the plan are the  same for them    This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

 

Sheet of Sheets

8 of 120 

 

 

   

5. MEETING   

5.1  General Pre-Inspection Meeting   

Contractor shall hold a general Pre‐Inspection Meeting with Subcontractor prior to beginning any  specific inspection and test to mutual understand any specific requirements of project as follow:  

System method for communication between Contractor and Subcontractor 



Position and titles of key personnel in the communication channel 



Responsibilities of key personnel for conducting the witness inspection, reviewing result and solving  problems during construction 

    5.2  Regular Inspection and Test Meeting   

Contractor shall hold a regular inspection meeting on a monthly or any agreed period with Sub‐   

contractor to discuss the following items:   



Any problems found during inspection, examination or test 



Improvement of quality control system 



Comments on the inspection procedures 



Acceptance or rejection of qualified personnel 



Evaluation of inspection results 



Corrective actions for non‐conformance to preclude recurrence. 

 

   

5.3 Special Quality Meeting   

If required, Contractor will hold a Special Quality Meeting with Sub‐contractor to discuss the following;   



Special requirements/procedures for inspection and test of critical items 



A serious accident and/or damaged item during the construction stages 



Cause of the problem found during the inspection 



Disposition for the problem items found, etc.     

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

9 of 120 

6. INSPECTION / TEST CONTROL  6.1  Inspection/Test Schedule   

1) Sub‐contractor shall prepare the Inspection/Test Schedule for the following week and/or month based on  the construction progress and submit it to Contractor for review  2) QA/QC Manager shall assign QC Inspector to witness inspection of any item based on the Inspection/Test  Schedule submitted by Sub‐contractor. 

  6.2  Performance of the inspections   

1) Subcontractor shall perform the inspection required to verify conformance and prepare and maintain  the records of inspected items.  Inspection records will, as a minimum, identify following:   Item inspected  

Number of reference specification or drawing 



Date of inspection 



Name of inspector or operator 



Name of witness inspectors of Contractor and Company 



Type of observation 



Results of acceptability 

  2) Contractor shall evaluate the inspection results in accordance with acceptance criteria to verify  conformance of an item to the specific requirements and sign and date the records for an acceptable  item.    3) When required, Contractor may check the control sheets to verify that inspections have been performed  sequentially and to ensure that an unacceptable or non‐conforming item is inadvertently installed, used  or preceded to further construction sequence. 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

10 of 120 

   

7. WITNESS INSPECTION   

 

1) Contractor may select a witness item depending on a required quality level, past performance and site  condition. For a witness item, Contractor shall inform Subcontractor of the items according to the  approved Inspection & Test Plan     2) When a witness point is specified in construction sequence, Subcontractor shall submit the  inspection application for specific items to Contractor at least two (2) working days prior to  the inspection.    3) Contractor shall submit the inspection application to Company at least one (1) working day prior  to the inspection, and Company shall notify Contractor minimum 12 hours prior to the inspection  whether Company will attend the witness or not.    4) If there is no written confirmation of Company attendance within given period to Contractor, the  inspection of Company shall be automatically considered as waiver of Company inspection.    5) The QC Inspector shall witness the inspection and verification of the following:  

Adequate and calibrated measuring and test equipment are used 



Trained and qualified personnel conduct and perform with qualified equipment according to the  approved and qualified procedures. 



Necessary monitoring is performed 



Suitable environmental conditions are maintained for the duration of the testing 



Required date and result of inspection are correctly documented 

  6) The QC Inspector who witness inspection shall review records and results to verify conformance of  only for acceptable inspection criteria.    7) Contractor shall also have Company signature on the inspection records for Company witness  inspection items.   

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

11 of 120 

8. WITNESSING GENERAL PRINCIPLES    The following are the most common categories of inspection / test activity. Suggested  abbreviations are included in brackets:   

1) Hold Point (H):  U

Inspection, examination or test shall be notified by the inspection application in  advance and shall be performed under witness by Contractor and/or Company or his  Representative while the activity is performed. Witnessing and approval of  inspection/testing activity performed by Contractor is mandatory prior to proceed.     

2) Witness (W):  U

Contractor  must  notify  when  inspection/testing  activity  is  performed  in  due  time  to  allow Company or his Representative as a witness to the satisfactory completion of the  item.  Company  or  his  Representative  may  decide  not  to  witness  the  activity  allowing  Contractor to proceed.     

3) Surveillance (S):  U

Company  or  his  Representative  maintains  the  right  to  witness  inspection/testing  activities at its own convenience.  Every  week  Contractor  shall  issue  two  weeks  look  ahead  inspection/testing  activities  schedule for Company or his Representative follow up.     

4) Reports Review (R):  U

Company or his Representative shall review inspection/testing record or certificate after  activity is performed by Contractor.         

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

____________________________________________________________________________________ ____________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

12 of 120 

9. INSPECTION TEST / REPORT   

 

9.1 Document review items   

  1) Subcontractor shall submit copies of the inspection records to Contractor within two (2)  working days after inspection.  2) QA/QC Engineer shall evaluate the inspection records and certificated against acceptance  criteria to verify conformance to specified requirements      

3) For an unacceptable item, QA/QC Engineer shall immediately notify the reason to the    Subcontractor      

4) Contractor shall also have Company review on the inspection records when specified or  required.   

 

9.2 Inspection Report   

For the Inspection Reports being issued whenever specific inspection or test is performed  according to approved Inspection & Test Plan, Sub‐contractor shall submit the copies of it  to Contractor within 2 working days after inspection or test.   

 

9.3 Field Inspection Records   

Subcontractor shall compile all of Inspection and Test Records which have been issued   According to the Inspection & Test Plan after completion of all of specific inspection and  test, and submit it to Contractor within ten (10) days from the date of the final inspection  or test.  As a minimum, the following items will be included:  1. Cover sheet  2. Table of Contents  3. Mill certificates  4. Each inspection NDE/Test record, as specified  5. Heat treatment charts, as specified  6. Pressure test record (Hydrostatic, Pneumatic, etc.)  7. Other inspection and test records, as specified  8. WPS/PQR  9. Attachments 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

____________________________________________________________________________________ ____________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

13 of 120 

10. APPENDIXES:     Field Inspection and Test Plan and Records (examples):    1. Civil Works   2. Steel Structure Works   3. Mechanical Works  4. Piping Works   5. Electrical Works   6. Instrumentation Works  7. Pipeline Installation   8. Painting Works  9. Inspection and Test Records                           

      This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

____________________________________________________________________________________ ____________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

14 of 120 

  Appendix 1:  Civil Work      

a) Concrete Mix    b) Earth Works    c) Borrow Pit Certification    d) Blinding, Concreting, Coating Foundation and Backfilling    e) Precast Concrete    f) Inspection of Asphalt Roads Works    g) Underground Pipe & Backfill of Underground Service    h) Concrete Pavement    i) External & Internal Building Finishes   

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

____________________________________________________________________________________ ____________

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

15 of 120 

Page

INSPECTION AND TEST PLAN  Concrete Mix 

  Unit No  No. 

Contract No:  

 

Activity Description 

Work Pack No :  Test/Inspection Requirements 

Contractor  Reference Document 

1 of 1 

SYSTEM No 

Inspection and Acceptance Responsibility  Contractor 

Company 

   

   

ITR ‐ Report or Document:  (Note 1) 

 

 

    1 

 

  2 

  3 

Established a satisfactory quality supply of water  check that this is in full accordance with standards  and regulation about the limits for chlorides,  sulphates, alkali, sugars, phosphates, nitrates, lead,  zinc and total salt contents of the concrete 

Periodically tests with a portable electrical  conductivity probe calibrated against the  satisfactory supply.  Chemical tests shall be performed if the  conductivity exceed the satisfactory supply 

    Cement 

Manufacturer’s test certification supplied for each delivery of cement  Manufacturer’s test certification shall  confirm the cement complies and  shall be submitted by the  CONTRACTOR    Test certification for coarse aggregate Test  certification for fine aggregate Test  certification for sources 

Project Specification and Drawings  (note 3)  Code & Standard  Laboratory certificates 

  Aggregates 

Project Specification and Drawings  (note 3)  Code & Standard  Quality Control Plan  Procedure (note 3)  Laboratory Certificate 

Project Specification and Drawings  (note 3)  Code & Standard  Laboratory certificates 

W/R 

W/R 

 

 

    (B) Water chemical analysis 

 

W/R 

W/R 

W/R 

W/R 

(B) Materials Certificate (A) Aggregate Particle Size Report  (A)  Los Angeles Abrasion Test Report  (A) Soundness of Rock Test Report 

(B) Materials Certificate 



Admixtures (for air entraining, hot or cold  concreting as/if applicable) 

Review of datasheet and certificate

Project Specification and Drawings  (note 3) 

H/R 

W/R 

(B) Material Certificate 



Concrete Mix Design 

Review of documents 

Project Specification and Drawings  (note 3) 

H/R 

W/R 

(A) Mix Qualification 



  Trial Mixes 

  Qualification 

Project Specification and Drawings  (note 3)  Code & Standard  Laboratory certificates 





(C) Inspection check list  (B) Mix Qualification 



Crushing Strength Testing (7 and 28 days) 

Laboratory testing

Project Specification

H/R 

W/R 

(A) Laboratory report 



  Tests on the production 

  Production Review 

Project Specification and Drawings. (Note 3)  Tests Results. 

H/R 

W/R 

 

 

 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one item or group of item. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection  attendees & eventually signed off and dated here below for completion.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

16 of 120 

 

INSPECTION AND TEST PLAN  Earth Works

  Unit No   

Contract No    

Work Pack No : 

Contractor 

 

  No. 

Test/Inspection Requirements 

Activity Description 

Page 

Reference Document 

1 of 1

SYSTEM No  Inspection and Acceptance  Responsibility 

Contractor 

ITR ‐ Report or  Document:  (Note 1) 

Company 

     

 

  1 

 

Evaluation of In‐Situ Fill Material for suitability 

Evaluation Tests  Liquid &Plastic Limits 

Project  Specification and Drawings (note 3)  Code, Standard & Procedures Quality Control  Plan 

Compaction Tests  95% MDD  Moisture content percent of the  optimum moisture content 

Project Specification and Drawings (note 3)  Code, Standard & Procedures, Quality Control  Plan 

Surveyor inspection for setting out 

Review of Survey Report 

Latest revision of Drawings 

Final visual check & earthwork release 

Visual 

  2 

Earthworks Compaction 





  R 

  W/S 

  W/R 

  W 

S/R 



H/R 

W/R 

  (B) Laboratory report  (A) Evaluation of in‐situ fill materials 

(A)   Earth Work Compaction  Records 

(A) Surveyor report 

Document review of the inspection  and testing records 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one item or group of item. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection  attendees & eventually signed off and dated here below for completion.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

 

Sheet of Sheets

17 of 120 

INSPECTION AND TEST PLAN 

 

Page 1 of 1 

Borrow Pit Site Selection   Unit No  No. 

1  1.1  1.2 



Contract No: 

Work Pack No 

Contractor

Activity Description 

Test/Inspection Requirements

Reference Document

SYSTEM No Inspection and Acceptance Responsibility (2)

Contractor

Company

ITR ‐ Report or Document: (Note 1) 

Borrow pit location 

 

 

 

Specified and Define Location Borrow  pit coordinates  provide distance for the following  boundary:   grazing area    settlements    main graded and tarmac road    archaeological site    protected area   Location on very sloping terrain  Earthworks Compaction 

Review of Surveyor’s setting out

Relevant Job Drawings



S/R 

(A) Survey Report

Visual 

Survey Report



S/R 

(A) Survey Report

Project Specification and Drawings (note 3)  Code, Standard & Procedures, Quality  Control Plan  Latest revision of Drawings  Project Specification and Drawings (note 3)  Code, Standard & Procedures Quality Control  Plan 

  W/R 

  W/S 

S/R 



  R 

  W/S 

H/R 

W/S 



Surveyor inspection for setting out 

Compaction Tests 95% MDD  Moisture content percent of the  optimum moisture content Review of Survey Report 



Final depth of excavation and final grade  of slopes 

Evaluation Tests Liquid &Plastic Limits 



Final visual check & earthwork release 

Visual 

(A)   Earth Work Compaction  Records  (A) Surveyor report  (B) Laboratory report (A) Evaluation of in‐situ fill materials 

Document review of the  inspection and testing records  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review                 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

 

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

18 of 120 

   Page 

INSPECTION AND TEST PLAN 

  1 of 2 

Blinding, concreting, coating foundation and backfilling  Unit No    No. 

Contract No :  

Work Pack No : 

 

Contractor 

  Test/Inspection Requirements 

Activity Description 

Reference Document 

SYSTEM No  Inspection and Acceptance  Responsibility (2)  Contractor 

Company 

ITR ‐ Report or Document:  (Note 1) 

 

1. Concrete mix design and qualification  2. Blinding Concrete    2.1  Verify surveying setting out of Base location  and blinding concrete level is as per drawings 

Review of Surveyor’s setting out 

Relevant Job Drawings 



S/R 

Specifications (note3)  Project Procedure (note 3) 





Visual 

Drawings 





Visual  Material Conformity Certificate  review 

Project Specification and Drawings (note 3)  S 



    S 

    S 

Project  Specification  and  Drawings (note3)  Code & Standard  Quality Control Plan  Project Procedures (note 3) 

    H/R 

    W 

Project Specification and Drawings (note 3)  Code & Standard  Quality Control Plan  Project Procedures (note 3) 

    W 

    S 

    H/R 

    W/R 

  S/R 

  S 

2.2 

Blinding   Concrete   receipt   &   placement 

Adequate conveying & depositing  As per construction drawing

2.3 

inspection  Release    for  foundation 

Construction    of 

Concrete   

3. Concreting  3.1     

Membrane application (if applicable) 

 

 

3.2 

Check blinding and application of membrane in  full accordance with manufacturer’s instructions 

3.3 

Pre‐Pour   inspection   of   forms, rebar,  embeds etc.  Release for Concrete Order by  Construction and release for pouring.  Verify surveyors signature 

   

   

    3.4 

   

Concrete receipt & placement inspection     

3.5 

Verify concrete field test results conforming to  Specifications. 

  3.6 

  Concrete curing and protection 

Verify (Blinding Concrete)  complete  Apply sheeting waterproof  membrane (polyethylene or other)  Rebar Certificate check  Rebar free from rust, damage and  installed as per drawings Embedded  items installed as per drawing  Adequate conveying & depositing  Concrete vibration and surface  finishing   Correct placement (e.g. pumping, height) 

(A) Pre Pour Report 

Project Specification and Drawings (note 3) Code &  Standard Quality Control Plan  Project Procedures (note 3) 

Correct mix design ID  Max and Min concrete and ambient  temperature (ideal 30ºC ‐ 25ºC  for mass concrete)  Slump test 

Project Specification and Drawings (note 3) Code &  Standard Quality Control Plan  Project Procedures (note 3) 

Temperature measuring and control if  applicable  Wet curing minimum 7 days  Curing water shall comply with Job  Specifications 

Project Specification and Drawings (note 3) Code & Standard  Quality Control Plan  Project Procedures (note 3) 

  (B)   Material Certificate of  Conformity   

S

(B) Materials Certificate  (A) Rebar Inspection Report  (A) Pre Pour Report    (A) Concrete Pour Card  (A) Concrete Test Log Mix Qualification 

(A) Concrete Test Log 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

19 of 120 

INSPECTION AND TEST PLAN 

Blinding, concreting, coating foundation and backfilling   

Unit No    No. 

Contract No : 4600039760 

Work Pack No : 

Contractor 

Test/Inspection Requirements 

 

Page 

2 of 2 

SYSTEM No 

  Activity Description 

  

Inspection and Acceptance  Responsibility  Contractor  ( Company 

Reference Document 

ITR ‐ Report or Document: (Note 1) 

 

  3.7 

3.8 

Compressive crush strength test results  conforming to Specification 

Project Specification and Drawings (note  3)  Code & Standard  Quality Control Plan  Project Procedures (note 3) 

Major repairs completed after form  removal 

Form  striking,  surface  inspection  and  release  for repair, if required. 

 

 

 

 

Project Specification and   Drawings (note 3)  Code & Standard  Quality Control Plan  Project Procedures (note 3) 

  Achieving the minimum compressive  28‐ d a y   strength  result  to  the  required  concrete grade 





 

  H/R 

  (C) Inspection check list 

  W/R 

(B) Laboratory report 

4. 4. Coating Foundation and backfilling   

Underground Structure released for  coating. For Pre‐cast items Note the serial  Nos. of them relevant Concrete Test Log 

Check inspection forms in structural  and precast concrete ITPs are  properly signed off. 

4.2 

Coating applied as specified. 

Coating, including thickness, is  applied Specifications (note 3) as  per  the  Manufacturer’s  detailed  installation procedure   Quality control plan  Coat  material  certificate  review 

4.3 

Top  of  foundation  and  anchor  (bolts  and plates as applicable) dimensional  check 

Dimensional measurements 

4.4 

Backfill & Compaction as per requirements. 

  4.1 

 

 

 

  R 

Project specifications (note 3) and  ITPs 

  S 

 

 

(A) Concrete Test Log 

 

W/R 

W/R 

Drawings 

W/R 

W/R 

Verify   compliance   with   specified requirements. 

Project Specification and Drawings (note  3) 

W/R 

S/R 

(A) Earth Work Compaction Record 

Documents completeness 

Project Procedures (note 3) 





(A) Mechanical Completion Dossier 

(A) Concrete Coating Report 

5. Mechanical Completion  5.1 

Mechanical completion dossier completion  and approval. See Mechanical Completion  Procedure 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one item or group of item. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off  and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  S PD – Standard Proctor Density, MPD – Modified Proctor Density, MDD – Maximum Dry Density, OMC – Optimum Moisture Content, MC – Moisture Content  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point For Inspection R‐ Record Review 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

20 of 120 

 

 

   Page 

INSPECTION AND TEST PLAN 

Precast Concrete   

Unit No    No. 

Contract No :  

Work Pack No :   

Activity Description 

Test/Inspection Requirements 

Reference Document 

Contractor  Inspection and Acceptance Response  Contractor 

  1 of 1 

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Company 

 



Pre‐Pour inspection of forms, rebar, embeds etc.  Rebar free from rust, damage and  Release for Concrete Order by Construction and  installed as per drawings. Embedded  release for pouring.  items installed as per 

Specifications (note 3) Relevant Project  Drawings Quality Control Plan 

W

W

(A) Pre‐Pour Check‐list



Concrete receive & placement inspection 

Specifications (note 3) Quality Control Plan

H/R

W/R

(A) Concrete Pour Card



Verify  concrete  field  test  results conforming to  Correct mix Design ID Max concrete  Specifications.  temp. 30ºC (25ºC for mass concrete) 

Specifications (note 3) Quality Control Plan

H/R

W/R



Form striking, surface inspection and release for  repair, if required. 

Major repairs completed after form  removal 

Specifications (note 3) Quality Control Plan

H

W



Concrete curing and protection 

Wet curing minimum 7 days Curing  water shall comply with Job  Specifications 

Specifications (note 3) Quality Control Plan

S/R

S/R

Achieving the minimum compressive 28  day strength result to  the required  concrete grade 

Specifications (note 3) Quality Control Plan

Adequate conveying depositing

(A) Concrete Pour Card



Compressive  strength  test  results conforming  to Specification 

(A)  daily surveillance inspection  record  for curing 

H/R

W/R

(A) concrete test result log

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and (B) are included in  Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one item or group of item. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.    Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3:  Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend : S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point For Inspection R‐ Record Review 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007    

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

21 of 120 

Page

INSPECTION AND TEST PLAN  Inspection of Asphalt Roads Works  Unit No    No. 

Contract No :    Activity Description 

Work Pack No :

Contractor Inspection and Acceptance

Test/Inspection Requirements 

Reference Document 

Contractor

Company

1 of 1

SYSTEM No ITR ‐ Report or Document: (Note 1) 

1. Inspection of Asphalt Roads Works  1.1 

Setting out of road. 

Visual 

Survey Report

R

R

(A) Survey Report

1.2 

Earth works compaction conformant 

Verify lab. Test result

Quality Control Plan

R

R

(A) Earth Works compaction Report 

1.3 

Release for Geotextile and sand‐gravel laying 

Visual 

ITP‐714‐252

W

R

1.4 

Aggregate base course complete and  conformant. Release for prime coat  Prime coat applied as required.  Release  for  application of asphalt binder course 

Correct level, slope, etc.

ITP‐714‐252

R

R

(A) Earth Works compaction Report 

W

W

(A) Asphalt receive and laying Report 

Application of asphalt binder course complete  and conformant , Paving is permitted after a  period of minimum 24 hrs. from prime coat  application. 

Joints prepared correctly

Project Specifications (note 3) Quality Control Plan

W/R

W/R

(A) Asphalt core and density Report 

Asphalt temp., weather conditions 

Approved design mix 

1.7 

Asphalt  paving  materials  for  binder  course  conformant 

1.8 

Application   of   tack   coat   complete   and  conformant. Release for asphalt surface course 

C l l l Project Specifications (note 3) Laboratory results in line with spec. Mix  Design review  li C l Pl Rate and temperature of application as Q Project Specifications (note 3) Quality Control Plan

1.5    1.6 

gutters, manholes, etc. covered with thin  Project Specifications (note3) , Quality Control  uniform coat of liquid asphalt.  Plan 

ifi i Joints prepared correctly, Asphalt temp,  Project Specifications (note 3) Quality Control  weather conditions, Correct slope, level,  Plan, Approved design mix  etc.  1.10  Asphalt   paving   materials   for   Surface   course  Laboratory results in line with spec Project Specifications (note 3) Quality Control Plan  conformant  Approved design mix  1.9 

Application of asphalt surface course complete  and conformant 

1.11  Asphalt paving conformant. All repairs complete,  Correct slope, level, smoothness, etc. if required 

Project Specification (note

(A) Asphalt receive and laying  R

R

R (A) Test results of asphalt laying  Report 

W

S

(A) Asphalt receive and laying Report 

W

S

R

R

(A) Asphalt core and density report (A)  Asphalt receive and laying Report (A)  Asphalt smoothness Report  (A) Test results of asphalt laying report 

H/R

H/W

2. Mechanical Completion  2.1 

Project Procedures H H (A) Mechanical Completion Dossier  Mechanical completion dossier completion and  Documents completeness approval. See Mechanical Completion  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and (B) are included  in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one item or group of items. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off  and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.   Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review  

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

252100DBQA00007  

EX-DE 

03 

Sheet of Sheets

22 of 120 

Page

Underground Pipe & Backfill of Underground Service  

Unit No   No.

Contract No :

Work Pack No :

Contractor

Test/Inspection Requirements

Activity Description

1 of 2

SYSTEM No Inspection and Acceptance

  Reference Document

Contractor

ITR - Report or Document:

Company

(Note 1)

1. Underground Pipe Check concrete manhole installation is complete and conformant

As per Drawings

1.2

Check Lines / Levels / Slopes

Lines & Levels as per DWGs

Manufacturer’s Manual

1.3

Pipe Preparation and Jointing

Manufacturer’s Recommendations

1.4

Anchor supports/thrust installed(if applicable)

1.5

1.1

Survey Report

R

S

H/R

W/R

(A) Check-List

Drawings

H

W

(A) Check-List

As per Drawings

Drawings

W

W

(A) Check-List

Manhole Ladders Installed

Visual

Civil Underground Piping & Manholes ITP

W

W

(A) Check-List

1.6

Cleaning & Flushing

Visual

W

W/R

(A) Check-List

1.7

Release for Water leak Testing

Visual

Civil Underground Piping & Manholes

H

W

(A) Check-List

Water leak test of Manhole

Contract Specifications and ITP

Project specification (note 3) Civil Underground Piping &

H/R

W/R

(A) Check-List (A) Test Report

1.9

Water leak test of Pipes

Contract Specifications and ITP

H/R

W/R

(A) Check-List (A) Test Report

1.10

Reinstatement completed after test & Release for backfill compaction operations.

Visual

H

W

1.11

Marker / Posts installed. (if applicable)

Visual

W/R

W/R

1.12

Ensure that there is no water in pit and water disposed properly

Visual

W

S

1.13

Pipe & Manhole system Released

Visual

H

W/R

  1.8

 

blocks

 

 

Manholes ITP

 

             

  

Rev.  No. 

INSPECTION AND TEST PLAN

 

                                                         

Revision Index

Validity  Status 

ITP 

(A) Survey Report

(A) Check-List

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents            type (A) and (B) are included in Mechanical Completion.   Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

23 of 120 

 

 

  Page 

INSPECTION AND TEST PLAN 

Underground Pipe & Backfill of Underground Service  Unit No   

Contract No :   

  No. 

Work Pack No : 

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

  2 of 2 

SYSTEM No  Inspection and Acceptance  Responsibility (Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 

  2. Backfill of Underground Service  2.1 

Ensure  underground  services  have been    released for  backfill and compaction 

 

2.2 

Bedding material suitable and placed around  service as per requirements 

Imported bedding material specification as per  drawings 

Protection devices (Warning tapes etc.) to be  available and placed 

Bedding as per drawings around the  pipe or conduits Clean sand to  be  used  for bedding material for coated &  wrapped pipes, GRE pipes, PVC pipes  U/G electrical & instrument cables 

2.3 

Suitable material used for backfill 

Visual inspection

Imported fill materials for underground services  specification Relevant project drawings (note 3) 

2.4 

Backfill material placed and compacted as per 

Fill layers of maximum admissible  Thoroughly compacted 

Imported Fill materials for Underground Services  specification 



W/R 











S/R 

H

H/R

As per Manufacturer’s recommendations 

(A) Earth Works compaction report 

requirement above initial backfill for piping  2.5 

Backfilling and compaction operations 

Visual

(A) Release Report

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and (B) are  included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one item or group of item. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

  This document is property of eni iraq b.v. It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.

________________________________________________________________________________________________ 

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

24 of 120 

 

 

  Page 

INSPECTION AND TEST PLAN 

Concrete Pavement  Unit No   

Contract No :   

  No. 

Work Pack No 

Contractor   

Test/Inspection Requirements 

Activity Description 

  1 of 1 

SYSTEM No  Inspection and Acceptance

ITR ‐ Report or Document 

Responsibility (Note 2) 

(Note 1) 

Reference Document 

Contractor 

Company 

  1 





All   underground   services   such   as piping  vents, drains cables, etc. Complete &  conformant. Base course layer is released for  concrete pouring  Check that polyethylene film vapor / moisture  barrier is placed on base course to the required  specification. 

Compacted to 95% MDD

Quality control plan

See Relevant ITP for service if 

Relevant project drawings 

Polyethylene as per spec. requirement.  Overlap not less than 300mm at all joints  & intersections. 

Specifications (note 3) Relevant project  drawings 

Pre‐pour inspection of forms, rebar, embeds,  slope, screeds, joints, etc. 

Rebar free from rust, damage and  installed as per drawing Embedded items  installed as per drawing 

Quality control plan

R

R

(A) Earthworks compaction record 

W

W

H/R

W

(A) Pre Pour Inspection for concrete 

Specifications (note 3) 

Kerbstones Expansion & Construction  joints Cold weather precautions  4 

Concrete receive & placement inspection 

Adequate conveying & depositing

Quality control plan

S

S

(A) Concrete Pour Card



Verify   concrete   field   test   results 

Correct Mix design ID

Quality control plan

R

R

(A) Concrete Pour Card



Concrete curing, protection, clean up and  drainage. 

Wet curing minimum 7 days

Quality control plan

S/R

S/ R

(A) Daily surveillance Inspection  Record for Curing 



Compressive   strength   test   results items  conformant 

 

Quality control plan

H/R

W/ R

(A) Concrete Test Log

   Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion  Note 2: Case A ‐ ITP is assigned to one item or group of items. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis     Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

 

 

24 

Company Logo and business name  

Company Identification

252100DBQA00007  

 

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

25 of 120 

  Page 

INSPECTION AND TEST PLAN 

External & Internal Building Finishes  Unit No    No. 

Contract No : 

Work Pack No  Test/Inspection Requirements 

Activity Description 

Contractor  Reference Document 

Inspection and Acceptance  Responsibility ( Note 2)  Contractor 

  1 of 2 

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Company   

1. Material Acceptance  1.1 

Material  conforms  to  specification  and  drawings 

Review of material certificates and as built  Material Lists Construction Drawings Project  drawings for prefabricated items  Specifications Product standards 

H/R

S/R  

2. External Building Finishes  2.1  Inspection of Expansion /Contraction Joints 

 

Project   specification   and   Drawings  (note 3)

H/R

S

(A) External building check‐lists and  Inspection Reports  (A) External building check‐lists and  Inspection Reports 

2.2 

Inspection of Roof and Wall panels  Visual & Dimensional ,Review of  installation for buildings (Insulation ,Flashing  documentations  And water repellent) 

Project   specification   and   Drawings  (note 3)

H/R

S

2.3 

Inspection of Built up Roof Covering for  Buildings 

Visual & Dimensional, Review of  documentations 

Project   specification   and   Drawings  (note 3)

H/R

S

(A) External building check‐lists and  Inspection Reports 

2.4 

Inspection of Painting / Clear Finish for the  External of Buildings 

Visual & Dimensional, Review of  documentations 

Project   specification   and   Drawings  (note 3)

H/R

W

(A) External building check‐lists and  Inspection Reports 

Internal building check‐lists and  Inspection Reports  Internal building check‐lists and  Inspection Reports  Internal building check‐lists and  Inspection Reports 

3. Internal Building Finishes  3.1 

Concrete pavement 

 

Project   specification   and   Drawings  (note 3)

H/R

S

3.2 

Inspection of Masonry 

 

Project   specification   and   Drawings  (note 3)

H/R

S

3.3 

Inspection   for joints in   concrete  and  Masonry 

 

Project   specification   and   Drawings  (note 3)

H/R

S

3.4 

Inspection of Plastering 

 

Project   specification   and   Drawings  (note 3)

H/R

S

3.5 

Inspection of Gypsum drywall partition walls 

 

Project   specification   and   Drawings  (note 3)

H/R

S

3.6 

Inspection of floor and wall tile installation 

Visual & Dimensional, Review of  documentations 

Project   specification   and   Drawings  (note 3)

H/R

S

3.7 

Inspection of  painting /clear Finish 

Visual & Dimensional, Review of  documentations 

Project   specification   and   Drawings  (note 3)

H/R

W

Internal building check‐lists and  Inspection Reports 

3.8 

Inspection of window installation 

Visual & Dimensional, Review of  documentations 

Project   specification   and   Drawings  (note 3)

H/R

S

Internal building check‐lists and  Inspection Reports 

3.9 

Inspection of door installation 

Visual & Dimensional, Review of  documentations 

Project   specification   and   Drawings  (note 3)

H/R

S

Internal building check‐lists and  Inspection Reports 

Internal building check‐lists and  Inspection Reports  Internal building check‐lists and  Inspection Reports Internal building check‐lists and  Inspection Reports 

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

26 of 120 

  Page 

INSPECTION AND TEST PLAN 

External & Internal Building Finishes   

Unit No    No. 

Contract No : 

Work Pack No   

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

  2 of 2 

SYSTEM No  Inspection and Acceptance  Responsibility(Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 

       

 

Project specification and Drawings (note 3) 

H/R 



Internal building check‐lists and  Inspection Reports 

Inspection of sanitary fixtures & fittings 

Visual & Dimensional review of  documentations Leak  Visual & Dimensional review of documentations 

Project specification and Drawings (note 3) 

H/R 



3.12 

Inspection Record for Cavity/Raised Floor 

Visual & Dimensional 

Project specification and Drawings (note 3) 

H/R 



3.13 

Inspection Record for False/Suspended Ceiling 

Visual & Dimension 

Project specification and Drawings (note 3) 

H/R 



Internal building check‐lists and  Inspection Reports  Internal building check‐lists and Inspection Reports Internal building check‐lists and  Inspection Reports

3.14 

Inspection of Duct work Installation and other  components (Supports etc.)  Inspection of Insulation 

Visual & Dimensional review of  documentations 

Project specification and Drawings (note 3) 

W/R 

W/R 

Internal building check‐lists and  Inspection Reports 

Visual & Dimensional review of  documentations 

Project specification and Drawings (note 3) 

W/R 

W/R 

Internal building check‐lists and  Inspection Reports 

Installation of HVAC equipment and Control  Cables  Installation  of  Air  Terminal Devices  (Grilles, Diffusers) 

Visual & Dimensional review of  documentations 

Vendor Manual specification Project Drawings 

W/R 

W/R 

Internal building check‐lists and  Inspection Reports 

Visual & Dimensional review of  documentations 

Vendor Manual specification Project Drawings 

W/R 

W/R 

Internal building check‐lists and  Inspection Reports 

Punch list review 

Punch List Form 

W/R 

W/R 

Internal building check‐lists and  Inspection Reports 

Review of as built drawings 

Construction drawings Project Specification  (note 3) Project Procedures (note 3) 







H/R 

Mechanical Completion Dossier 

Procedure 



H/R 

 

3.10  3.11 

3.15  3.16  3.17  3.18 

Inspection & testing of plumbing works   

Punch list items to be prepared 

4. Mechanical Completion  4.1 

As Built drawings preparation 

4.2 

Mechanical completion dossier completion and  Documents completeness  approval. See Mechanical Completion  P d Test Run for HVAC system  Visual/ Test 

4.3 

(A) As Built Drawings 

 

   Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.      Documents type (A) and (B) are included in Mechanical Completion     Note 2: Case A ‐ ITP is assigned to one item or group of items. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.     Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis        Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review     

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

27 of 120 

 

      Appendix 2:  Steel Structure Works        

  a) Structural Steel Erection 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

03 

Sheet of Sheets

28 of 120 

 

 

   Page 

INSPECTION AND TEST PLAN 

Structural Steel Erection  Unit No  No. 

Contract No : 

Work Pack No 

Contractor 

Test/Inspection Requirements 

Activity Description 

SYSTEM No  Inspection and Acceptance  Responsibility(2) 

Reference Document 

Contractor 

  1. Material Acceptance and Control  Material conforms to specification and drawings:      ‐ Prefabricated items (frames, panels)  ‐ Steel structural profiles, beams, columns,  1.1  flange and anchor plates and others  ‐ Bolts, nuts and washers (including anchor bolts)  ‐ Grouting materials  ‐ Any other loose material (e.g. gratings,    Material  and  elements  identification  (e.g.  1.2  lots)  and  labeling/marking  including  preassembly marks if applicable    Material    and    elements    dimensions   1.3  and status (e.g.  straightness,  absence of  transportation damages, coating)       

  Review of material certificates and  as built drawings for prefabricated  items 

Material Lists  Construction Drawings  Project Specifications (note 3)   Product Standards 

Check marking for correspondence with  material certificate and  preassembly scheme if applicable  Check  dimensions,  packing  storing  and  status 

   1 of 3 

   

ITR ‐ Report or Document:  (Note 1) 

Company 

   

 

H/R 

S/R 

Material Certificate  Preassembly Scheme 





Construction Drawings  Project Specifications (note 3) 





B‐MTCs  B‐As Built for prefabricated items 

B‐Preassembly scheme and/or  report 

2. Preparatory activities  2.1    2.2    2..3 

  2.4 

2.5  2.6  2.7 

Check that drawings are latest revision  Check release of foundation.  Mechanical  Completion Dossier from ENI‐ITP‐CIV‐003. 

Review of applicable drawings   

Check  that  temporary  bolts  have  color   marked heads. 

R  R

Review of Mechanical Completion Report

  Check elevation & alignment of anchor bolts  Visual  & shims  Ensure that center lines & levels are marked  Review of survey report  on each foundation.  Ensure  that  surface  of  foundation  is  scabbed    &  Visual Inspection  pockets are clean.  Check  rust  is  removed  from  anchor  bolt  threads  &  nut/bolt  threads  are  in  Check that joint contact surfaces are  cleaned to bright   metal.  Check that primed surfaces are intact 

H/R  H/R

 

  S 



B‐Foundation Mechanical  Completion    (A) Survey Report  (A) Check Lists 

  Latest revision of Drawings Mechanical  Completion  Applicable Check List 

 

  S 



(A) Check Lists 





(A) Check Lists 

 





 





Visual check for cleanliness 

3. Assembly and Inspection  3.1 

Assemble items & carry out dimensional checks 

Dimensional check 





3.2 

Check that foundation is released by QC 

Survey within tolerance 





(A) Check Lists 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

03 

29 of 120 

 

 

   Page 

INSPECTION AND TEST PLAN 

Structural Steel Erection  Unit No 

Contract No : 

Work Pack No 

Contractor 

 

 

 

 

No. 

Activity Description 

Test/Inspection Requirements 

Reference Document 

  2 of 3 

SYSTEM No  Inspection and Acceptance 

ITR ‐ Report or Document: (Note 1) 

Responsibility(Note 2) Contract Company 

  3.3 

Check  that  plumpness/level  &  location  of columns is within tolerance. 

3.4 

Check that all interconnecting beams & bracings    Visual check  are  installed  correctly  to  the drawings. 

3.5 

If field welding necessary, ensure qualified  welder and correct WPS. 

3.6 

 

 

Dimensional Survey 

3.9   

  3.10 

 



  (A) Check Lists 

W/R 

Visual  examination  of  completed  weld(s),  seal welds, as applicable. 

Welding Inspection as per WPS 

Applicable welding code  Project Specification (note 3) 





 

RT, UT, DP and MPI (as applicable). 

NDT Procedures are approved NDT operators are qualified  NDT results are acceptable 

Project  Specifications  (note  3) NDT  Project procedures 



W/R 

 

Visual 

Project Specification (note 3) 





Visual Check  Curing time completed 

Mechanical Checklist 





Check torqueing system calibration  Review torqueing report 

Project Specification (note 3)  Applicable Drawings  Torque system datasheet 

S/R 

S/R 

Applicable Drawings 

H/R 

W/R 

 

Bolts tightening to the correct torque with a  calibrated wrench, if applicable. 

Visual and dimensional  Review of survey and dimensional  reports 

Final visual and dimensional inspection 

4 Mechanical Completion  4.1  As Built drawings preparation 

4.2 



(A) Survey Report  (A) Check Lists



  3.11 



Project Standards & Specification  (note 3) 

Check  that  all  temporary  bolts  have  been replaced  Grouting  pouring,  curing  and  final  check 

3.8 



Review of Welder ID, Welder  Qualification Table and WPS 

  3.7 

Latest    revision of Drawings  Mechanical Completion  Applicable Check List 

Mechanical  completion  dossier  completion  and  approval.  See  Mechanical  Completion  Procedure. 

(A) Check Lists 

(A) NDT Reports 

(A) Check Lists    (A) Torqueing Report  (A) Survey Report  (A) Dimensional Report 

Review of as built drawings 

Construction drawings  Project Specification (note 3) 





Documents completeness 

Project Procedures (note 3) 



H/R 

 

(A) Check Lists 

(A) As Built Drawings  Mechanical Completion Dossier 

5. Material Acceptance and Control    5.1 

5.2 

Material conforms to specification and drawings:  ‐ Prefabricated items (frames, panels)  ‐ Steel structural profiles, beams, columns, flange  and anchor plates and others  ‐ Bolts, nuts and washers (including anchor bolts)  ‐ Grouting materials  ‐ Any other loose material (e.g. gratings, handrails)  Material and elements identification (e.g. lots) and  labeling/marking   including   preassembly marks if  applicable 

Review of material certificates and as built  Material Lists drawings for prefabricated items  Construction Drawings  Project Specifications (note 3) Product Standards 

Check marking for correspondence with material certificate and preassembly  scheme if applicable 

Material Certificate Preassembly Scheme 

    H/R 

    S/R 





  B‐MTCs  B‐As Built for prefabricated items 

B‐Preassembly scheme and/or report 

    

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

30 of 120 

   

 

   Page 

INSPECTION AND TEST  PLAN  Unit No  No. 

5.3 

Contract No: 

Work Pack No 

Contractor 

Test/Inspection Requirements 

Activity Description 

Check  dimensions,  packing  storing  and  status 

Material   and   elements dimensions and status  (e.g. straightness, absence of transportation  damages, coating) 

Construction Drawings  Project Specifications (note 3) 

3 of 3 

SYSTEM No 

Inspection and Acceptance  Responsibility (2) 

Reference Document 

 

Contractor 

Company 





ITR ‐ Report or Document:  (Note 1) 

     

6. Preparatory activities  6.1 

Check that drawings are latest revision 

6.2 

Check release  of foundation.  Mechanical  Completion Dossier from ENI‐ITP‐CIV‐003. 

  6..3 

  6.4 

6.5  6.6  6.7 

  Review of applicable drawings        Review of Mechanical Completion Report         Visual    Review of survey report   

Check elevation & alignment of anchor bolts  & shims  Ensure that center lines & levels are marked  on each foundation.  Ensure  that  surface  of  foundation  is  scabbed    & pockets are clean.  Check  rust  is  removed   Visual Inspection  from anchor bolt threads & nut/bolt threads are  in good condition.  Check that joint contact surfaces are  cleaned to bright   metal.  Check that primed surfaces are intact  Check  that  temporary  bolts  have  color  marked heads. 

H/R 



H

H/R  

B‐Foundation Mechanical Completion 

 

Dossier.   

  S 

(A) Survey Report 



 

(A) Check Lists 

  Latest revision of Drawings Mechanical  Completion  Applicable Check List 

 

  S 







 





 





Visual check for cleanliness 

 

  (A) Check Lists 

(A) Check Lists 

   

7. Assembly and Inspection  7.1 

Assemble items & carry out dimensional checks 

Dimensional check 





7.2 

Check that foundation is released by QC 

Survey within tolerance 





 

(A) Check Lists 

     

   

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion  Note 2: Case A ‐ ITP is assigned to one item or group of items. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

31 of 120 

   

  Appendix 3:   Mechanical Works          

a. Pressure Vessel and Pressure Retaining Component – Installation    b. Rotating Equipment Installation    c. Fire Fighting System‐ Installation    d. Package Equipment                                     

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

32 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

 

Pressure Vessel and Pressure Retaining Component - Installation  Unit No  No. 

Contract No : 

Work Pack No Test/Inspection Requirements 

Activity Description 

Contractor Reference Document 

  1 of 3   

SYSTEM No

Inspection and Acceptance  Responsibility (2)  Contractor 

ITR ‐ Report or Document:   (Note 1) 

Company 

 

1  1.1  1.2  1.3 

General Activities  Check foundations released for equipment  erection  Ensure technical passport with equipment 

  Visual / Review of As‐Built Survey Report Document Review

Foundation Drawings As‐Built Survey  Report  Project Procedure

H

W

A‐Installation Check List

W

S

A‐Installation Check List

Vender Manual, Equipment Technical  Passport 

W

S

A‐Installation Check List

1.4 

  Check name plate for correctness and secure  attachments, check flanges, facings, and gaskets  Visual  are clean.  Installed a t correct elevation and orientation  Visual/Survey Report

Survey Report

H

S

A‐Installation Check List

1.5 

Foundation bolts tight and grouting complete 

Visual 

Vender drawing & Specification ITP 

H

W

A‐Installation Check List

1.6 

Preservation to be as per manufacturer’s  procedure 

Visual/Document Review

Manufacturer’s procedure Project  Specification (Note3) 

W

S

A‐Installation Check List

1.7 

Visual 

Vendor and Project Drawing 

W

S

A‐Installation Check List

1.8 

Verify installation of ladders access, platforms  etc.  Slide plate for horizontal equipment only 

Visual 

Vendor and Project Drawing 

W

S

A‐Installation Check List

1.9 

Davit unobstructed movement and greased 

Visual 

Vendor and Project Drawing 

W

S

A‐Installation Check List

1.10 

Check installation and cleanliness of internals  per checklist specific for vessel internals as  necessary. 

Visual 

Vendor and Project Drawing 

H

W/R

A‐Installation Check List

1.11 

Cleanliness 

Visual 

Project Procedures

W

W/R

A‐Installation Check List

1.12 

External opening closed with new gaskets after  pressure test of piping.  Weep holes in reinforcing pads filled with  suitable compound. 

Visual 

Vendor and Project Drawing 

H

S

A‐Installation Check List

Visual 

Project Specification(Note3) ITP for  grounding 

W

S

A‐Installation Check List

1.14 

Grounding connection installed 

Visual 

Project Procedures

H

S

A‐Installation Check List

1.15 

Final visual inspection Conduct temporary/final  closure checklist and 

Visual 

Project Procedures

H

H/R

A‐Installation Check List

1.13 

   

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

33 of 120 

     

INSPECTION AND TEST  PLAN

 

  2 of 3 

Pressure Vessel and Pressure Retaining Component - Installation  Unit No  No. 

2   

Contract No: 

Work Pack No Test/Inspection Requirements 

Activity Description 

 

 

Columns & Towers 

Visual  Review of Documents 

Vessel, Drum, Filter & Tanks 

Visual  Review of Documents 

Heat Exchangers 

Visual  Review of Documents 

Fire equipment and Flare 

Visual  Review of Documents 

Hydro‐cyclone / Inertial Separator 

Visual  Review of Documents 

Air Drier and Package equipment 

Visual  Review of Documents 

  2.2 

 

  2.3 

 

  2.4 

  2.5   

 

  2.6 

3    3.1            3.2 

Contractor

SYSTEM No ITR ‐ Report or Document: (Note 1) 

Inspection and Acceptance  Responsibility (2) 

Reference Document 

 

Contractor

Company 













A‐Specific Component Check list 





A‐Specific Component Check list 





A‐Specific Component Check list 





 Specific Components (as applicable) 

2.1 

   

    Page 

 Specific Activities    Paint  work  touch‐up/trace  heating  complete  Release for insulation(where applicable)  Loss Prevention(Safety) Equipment  (as applicable)  Automatic Sprinkler/Deluge System  Safety Showers and Eye baths  Hose Reel  Fire Water/Foam Monitors  Hydrant and Hydrant Cabinet  Dry Powder System  Portable Fire Extinguishers  Fireman’s Cabinet  Breathing Apparatus  Safety Signs

  Visual and Review of Documents          Visual  Review of Documents 

Project Procedure  Specification (Note3) Manufacturer  Installation Manual  Project Procedure  Specification (Note3) Manufacturer  Installation Manual  Project Procedure  Specification (Note3) Manufacturer  Installation Manual  Project Procedure  Specification (Note3) Manufacturer  Installation Manual  Project Procedure  Specification (Note3) Manufacturer  Installation Manual Project Procedure  Specification (Note3) Manufacturer  Installation Manual 

A‐Specific Component Check list 

A‐Specific Component Check list   

Project Procedure and  Specification (Note3)  ITP for Coating and Painting 

 

    Project Procedure and Specification  (Note3) 

     

Local Regulation as applicable  Manufacturer Installation Manual 

 

 

  W 

  S 

      H 

A‐Specific Component Check list 

A‐Paint Application Report 

  W 

A‐Installation and Testing Report (as  applicable)  B‐Equipment Passport or Certificate 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

34 of 120 

     

   Page 

INSPECTION AND TEST PLAN 

 

     3 of 3 

Pressure Vessel and Pressure Retaining Component - Installation  Unit No  No. 

Contract No : 

Work Pack No  Test/Inspection Requirements 

Activity Description 

Contractor 

SYSTEM No 

Inspection and Acceptance  Responsibility (2) 

Reference Document 

Contractor

ITR ‐ Report or Document:  (Note 1)

Company 

  4 

4.1 

  4.2 

Pre-Commissioning  Pre‐Commissioning activities for pressure retaining components are defined in accordance with Project Specific design (piping spec, and fluid  service). Note 3. Here below a selected and not exhaustive listing    Chemical Cleaning 

Review of chemicals certificate Cleaning parameters 

Chemical Datasheet 

  Leak Testing (N or He) 

Review of gas certificate

Project Procedures

 

 

 

Project Procedures H/R 

H/R 

A‐Inspection Report 

H/R 

W/R 

A‐Leak Test Report 

Testing parameters  Type, size, rating, Material  certificate 

P&I Project Procedures

W/R 

S/R 

A‐P&I ‐ Red Line Mark Up 

4.4 

Installation  or  verification of  miscellaneous  items  (e.g.  orifice  flanges, spectacles  blinds,  blinds)  Functional test of miscellaneous items (e.g. valves) 

Correct functionality

Project procedures

W/R 

W/R 

A‐Test Report 

4.5 

Preservation re‐instatement or application 

Visual

Project Procedures, Manufacturer  procedure 

W/R 

S/R 

A‐Preservation report 

Interim Mechanical Completion 

 

Inspection reports and documentation to be included  in the Mechanical Completion package of the  relevant system or sub‐system. See Mechanical  Completion Procedure. 

Documents completeness

4.3 

5  5.1 

  Project Procedures

  H

  H

Mechanical Completion Dossier

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and   (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees  & eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.   

Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

35 of 120 

     

    Page 

INSPECTION  AND TEST PLAN 

 

    1 of 3 

Rotating Equipment Installation  Unit No 

Contract No : 

 

 

No. 

Activity Description 

Work Pack No

Contractor

SYSTEM No Inspection and Acceptance

Test/Inspection Requirements 

Reference Document 

Responsibility(Note 2)  Contractor Company

ITR ‐ Report or Document: (Note 1) 

 

 



Preparation activities 

 

 

 

1.1 

Check foundations released for equipment  erection 

Visual / As‐Built Survey Report

Foundation As‐Built Survey Report 

1.2 

Ensure technical passport with equipment 

Document Review

Equipment Technical Passport 

2  2.1 

 

 

H/R

R

A‐Installation Check List

W

S

A‐Installation Check List

H

W

A‐Installation Report, A‐ Installation Check List 

Equipment Installation  Check base plate leveling and equipment  installed. Check name plate for correctness and  secure 

Visual Check / Survey Report

2.2 

Foundation bolts tight 

Visual or torqueing dynamometer (as

2.3 

Preliminary  alignment  complete  and  release   for grouting  Preservation reinstatement or application 

Vendor Manual, Project Standards (see Note 3) Equipment Regulatory Standard 

H

S

Visual and dimensional

Vendor Manual, Project Standards (see Note 3)  Equipment Regulatory Standard  Vendor Manual

H

S

A‐Installation Check List, A‐  Torqueing Report (if applicable)  A‐Installation Report

Visual Document Review

Vendor Manual

W

S

A‐Preservation Report

Visual and minimum time elapsed

Project Procedure

H

S

A‐Installation Check List

2.6 

Grouting completed (remove jack screws after  grout  Grounding check 

Visual or grounding resistivity measure  (as applicable) 

Project Procedure

H/R

R

A‐Installation Check List

2.7 

Auxiliary piping installed correctly. 

Visual 

Vendor Manual

W

W

A‐Installation Check List

2.8 

Verify cleanliness of suction and discharge  piping  Lube oil system flushed clean and filled with  correct 

Visual 

Vendor Manual

H

W/R

A‐Installation Check List

Visual/Test

Vendor Manual, Technical Data Sheet 

W

W/R

A‐Installation Check List

Visual/Test

Vendor Manual

W

W

A‐Installation Check List

Visual/Test

Vendor Manual

H/R

W

A‐Installation Check List

2.12 

Mechanical seal or packing correctly installed.  Check seal oil system  Checking gear box casing cleanliness and filled   with  correct lubricants  Connection of pipe work to equipment nozzles 

Visual/Test

Vendor Manual

H

S

A‐Installation Check List

2.13 

Machinery piping installation flange alignment 

Visual/Test

Vendor Manual

H

S

A‐Dimensional Report

2.14 

Paint work touch‐up/trace heating complete 

Visual 

Vendor Manual & Drawings

H

H

A‐Installation Check List

2.4  2.5 

2.9  2.10  2.11 

 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

36 of 120 

     

 

     Page 

INSPECTION  AND TEST PLAN 

 

   2 of 3 

Rotating Equipment Installation  Unit No 

Contract No : 

No. 

Activity Description 

Work Pack No

Contractor

Test/Inspection Requirements

Reference Document 

SYSTEM No

Inspection and Acceptance  Responsibility (2)  Contractor

Company

ITR ‐ Report or Document: (Note 1)

  3 

Pre-commissioning 

3.1  3.2 

Shaft rotates freely and in correct direction  Visual/Test Check Vibration systems installed and functional  Visual/Test

H

W

Vendor Manual, Data Sheet, Project  Standards (see Note 3) 

3.3 

Coupling and guards installed 

A‐ Pre‐commissioning Check List A‐ Pre‐commissioning Check List





Visual/Test

Vendor Manual, Project Standards (see  Note 3) 





Vendor Manual





A‐Pre‐Commissioning Report





A‐ Pre‐commissioning Check List

Procedure



W/R 

A‐Pre‐Commissioning Report

Check belt tensions and pulley alignment on belt  3.4 

Final alignment pipe work loose tight 

Visual/Test

3.5 

Final Visual inspection 

Visual 

3.6 

Test Run (no load run), check vibration, temp 

Visual/Test



Specific Equipment (below listing in indicative only) 

4.1 

Submersible Pump 

Visual and Project Drawings

Mechanical Construction Checklist 

H

H

A‐ Mechanical Construction Check List

4.2 

Air Compressors 

Visual and Project Drawings

Mechanical Construction Checklist 

H

H

A‐ Mechanical Construction Check List

4.3 

Centrifugal Compressors 

Visual and Project Drawings

Mechanical Construction Checklist 

H

H

A‐ Mechanical Construction Check List

4.4 

Centrifugal Pumps 

Visual and Project Drawings

Mechanical Construction Checklist 

H

H

A‐ Mechanical Construction Check List

4.5 

Gear Box 

Visual and Project Drawings

Mechanical Construction Checklist 

H

H

A‐ Mechanical Construction Check List

4.6 

Positive Displacement Pump 

Visual and Project Drawings

Mechanical Construction Checklist 

H

H

A‐ Mechanical Construction Check List

4.7 

Diesel Engine 

Visual and Project Drawings

Project Standards (see Note 3) 

H

H

A‐ Mechanical Construction Check List

4.8 

Gas Turbine 

Visual and Project Drawings

Project Standards (see Note 3) 

H

H

A‐ Mechanical Construction Check List

4.9 

Fan and Air Cooler 

Visual and Project Drawings

Vendor Manuals and Drawings 

H

H

A‐ Mechanical Construction Check List

4.10 

Overhead Travelling Crane (Lifting Equipment) 

Visual and Project Drawings

Project Standards (see Note 3) 

H

H

A‐ Mechanical Construction Check List

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

37 of 120 

     

 

INSPECTION  AND TEST PLAN 

 

  Page 

   3 of 3 

Rotating Equipment Installation  Unit No 

 

Contract No : 

Work Pack No   

  No. 

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

SYSTEM No 

Inspection and Acceptance                Responsibility(Note 2)  Contractor 

Company 

ITR ‐ Report or Document:  (Note 1) 

 

 

Steam Turbine 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

Belt Conveyor 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.13 

Centrifuge 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.14 

In‐line Strainer/Filter 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.15 

Bellows 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.16 

Constant Load Pipe Supports 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.17 

A C Units 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.18 

Reciprocating compressors 

Visual and Project Drawings 

Vendor Manuals and Drawings 





A‐  Mechanical  Construction  Check  List (Specific for the equipment) 

4.11  4.12 

5    5.1 

 

  Interim Mechanical Completion  Inspection report and documentation to be    included   in   the   Mechanical Completion  Documents completeness  package   of   the   relevant piping line or system.  See Mechanical Completion 

 

  Project Procedures 

  H 

  H 

Mechanical Completion Dossier 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and  (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees  & eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend : S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point For Inspection R‐ Record Revie

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

38 of 120 

    INSPECTION AND TEST PLAN 

 

Page 1 of 2 

Fire Fighting System- Installation  Unit No 

Contract No: 

No. 

Work Pack No 

Contractor

Activity Description 

Test/Inspection  Requirements 

Reference Document

Inspection and Acceptance  Responsibility (2)  Contractor



Documents Review 

Company

SYSTEM No ITR ‐ Report or Document:  (Note 1) 

 

 

1.1 

Review of Installation Drawings, Vendor's Manual &  Document Review

Drawing & Vendor Manual

W

S

A‐Installation report 

1.2 

Installation of Equipment Method Statement  Review & Approval 

Visual/Document Review

Project Standards (see Note 3)  Drawing & Vendor Manual 

W

S

A‐Installation report  (B) Material Certificate 

2  2.1 

Material Receipt  Check Equipment Tag Number Identification 

  Visual/Document Review

Packing Lists

2.2 

Check Incoming Material 

Visual/Specifications

Material Test Reports

Installation Activities 

 

3  3.1 

3.2  3.3 

3.4  4 

Pipe Physical  Cleaning:   Free from dirt and foreign material.   The pipe end Cap/Seal will not be removed until  the pipe is to be installed.   At openings for branches in pipe, all material,  which falls into the pipe, will be removed before  Grooving/Threading in the branch fittings.   Internal and external part of pipe and pipe  fittings will be clean and free from oil, rust, scale,  and other material, the ends of all pipes being  installed shall be sealed.  Installation of Fire Fighting Equipment 

      Visual Inspection 

    Project Standards (see Note 3)   Drawing & Vendor Manual  Method Statement 

W

S

H/R

W/R





A‐Installation report  (B) Material Certificate          A‐Installation report  Material Test Reports  C‐Installation Check List 

Visual/ leveling Reports

Project Standards (see Note 3)  Method Statement & Equipment Drawing 





A‐Installation report  C‐Installation Check List 

Piping works:   Piping network   Valves and Instruments   Installation   Pipe Support   painting  Identification and Labeling Pipe and fittings, valve  etc. by tagged or label. 

Visual

Method Statement & P&ID drawing Piping  Isometric Drawing   Instruments hookup drawings  Valve Installation Report  Pipe Support Report 





A‐Installation report  C‐Installation Check List 

Visual

Project documents

W/R

S

A‐Installation report 

Pressure Test 

test procedure

Method Statement & Pressure Test  Report 

H/R

W/R

A‐Pressure Test Report 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

39 of 120 

    INSPECTION AND TEST PLAN 

 

Page 2 of 2 

Fire Fighting System- Installation  Unit No  No. 



Contract No: 

Work Pack No 

Contractor

Activity Description 

Test/Inspection  Requirements 

Reference Document

  Visual 



Check Functional Operational Tests:   Detection circuits (alarm functions)   Second alarm circuit, if present   Manual release   Test all valves, unless testing the valve will  release agent or damage the valve.   Test time delay to check time limit    Complete closer of dampers in time    Check doors; check for any doors blocked open.   Verify equipment shutdown properly  Remote Monitoring Operations 

Visual



Check Control Panel (Primary Power Source) 

Visual



Check Emergency Power:    battery condition   charger operation    automatic changeover  Ensure all Mechanical Completion Check List is  Completed  Punch List Clearance 

Visual

Method Statement & Project documents 

Documents completeness  Check List   Documents completeness  Punch List  

9  10 

Inspection and Acceptance  Responsibility (2)  Contractor Company

SYSTEM No ITR ‐ Report or Document:  (Note 1) 

 

 

 





Method Statement & Project documents 

W

W

Method Statement & Project documents 

W

W

A‐ Pre‐commissioning Check List





A‐ Pre‐commissioning Check List

As Per Mechanical Completion Check List 

H/R

W/R

Mechanical Completion Dossier 

AS Per Punch List

H/R

W/R

Punch List

Method Statement   Vendor Manual 

A‐ Pre‐commissioning Check List 

Data Sheet  Project Standards (see Note 3) 

A‐ Pre‐commissioning Check List

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

   

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets

40 of 120 

    Page  1 of 1

INSPECTION AND TEST PLAN 

 

Package Equipment- Installation  Unit No  No. 

Contract No: 

Work Pack No 

Activity Description 

Contractor Test/Inspection  Requirements 

SYSTEM No Inspection and Acceptance  Responsibility 

Reference Document

Company

 



Documents Review 

1.1 

Drawing & Vendor Manual

W

S

(B) Material Certificate 

Drawing & Vendor Manual

W

S

A‐Installation report 



Review of Installation Drawings, Vendor's  Document Review Manual & Technical Documents  Installation of Equipment Method Statement  Visual/Document Review Review & Approval  Material Receipt   

2.1 

Check Equipment Tag Number Identification 

Visual/Document Review

Packing Lists

A‐Installation report 

2.2 

Check Incoming Material 

Visual/Specifications

Packing Lists & Material certificates



Pre-Installation Activities 

 

3.1 

3.3 

Check Foundation for Location & Orientation  Visual/Survey Report  of Anchor Bolts, Bolt Pocket Leveling, Sole  Plates, Axis Marks of Foundation  Check Chipping & Brushing of Foundation  Visual/Grout Report  Surface under Base Plates  Check Cleanliness of Pocket  Visual/Grout Report 

3.4 

Check Base Plate Elevation 

Visual/Leveling Report 

Equipment Drawing



Installation of Equipment 

  

4.1 

Check Verticality, Orientation & Leveling  after Tightening of Anchor Bolts 

Visual/Leveling Report 

4.2 

Equipment Base Grouting 

Visual/Grout Report 

4.3 

Ensure all Mechanical Completion Check List  is Completed  Punch List Clearance 

1.2 

3.2 

 

Contractor

ITR ‐ Report or Document: (Note 1)

 

  W

S

H/R

W/R

(B) Material Certificate 

Installation Drawings





A‐Installation Check List 

Method Statement





A‐Installation Check List 

Method Statement





A‐Installation Check List 





(A) Survey Report 

Equipment Drawing





A‐Installation report 

Equipment Drawing & Method Statement





A‐Installation Check List

 

 

Documents completeness  As Per Mechanical Completion Check List Mechanical Completion Dossier H  W  Check List   5  Documents completeness AS Per Punch List   A‐Punch List Punch List   Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

41 of 120 

   

      Appendix 4:   Piping Works    

a) Piping Fabrication & Erection Plan    b) Installation of PSV Valves    c) Process Piping Pressure Test   

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

42 of 120 

     

Page 

Piping Fabrication & Erection Plan   

Unit No    No. 

Contract No : 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

1 of 5 

SYSTEM No 

Inspection and  Acceptance  bl Contractor  Company 

 

ITR ‐ Report or Document:  (Note 1) 

Material Acceptance - Control - Preparation 



As   per   applicable   isometric   DWG  material list and piping specification 

Mill  Certificates,  Manufacturer  Material  Certificate  or    other    as  applicable

Correct isometric drawings 

Check isometric is controlled copy and  latest revision 

Isometric index 

1.3 

Material (pipe and pipe fittings) marking 

Check marking for correspondence with  material certificate 

1.4 

Check dimensions 

1.5 

Material  rating  and  dimensions  (diameter  /  thickness / schedule)  Pipe Material Mark up for cutting (if applicable) 

1.6 

Transfer of markings (if applicable) 

1.7 

Cutting and beveling (as applicable) 

 

 

 

INSPECTION AND TEST PLAN 

  1.1 

Material  conforms  to  specification  (pipe  and  pipe fittings) 

1.2 

  Correct Markings  Correct cutting, cleaning and testing  procedure 

 

  H/R 

S/R 

H/R 

S/R 

Material Certificate 





Isometric   material   list and piping  specification 





B‐MTCs  A‐Isometric Control Sheet ,Weld  Register A‐Isometric   Control   Sheet, Weld  Register 

A‐Isometric   Control   Sheet, Weld  Register

Project Procedure 

S/R 

Project Procedure 

S/R 

Project Procedure 



Welding Book  Project Procedure  Welders Qualification List and Welders’  Certifications 





B‐WPSs/PQRs 





B‐WQTR (welder qualification) B‐ Welders List 

Project Procedure 





C‐Consumable control log  B‐Consumable Certificate 



 Welding 

2  2.1 

Welding procedures appropriately qualified 

Review of the applicable WPS/PQR's 

2.2 

Check welder is qualified 

Review  of  the  Welders  Qualification  and validity 

2.3 

Electrode  control,  for  holding  and  storage  temperature, and storage conditions 

Check  storage  and  conditions and log book 

Check  joint  fit  up  for  cleanliness,  geometry  and    alignment.    Internal    gas    purge    as  applicable   WPS 

Visual  and  dimensional  check  as  per  Applicable WPS 

Project Procedure  Register 





A‐Isometric   Control   Sheet, Weld  Register 

2.5 

Preheat (if required) 

Visual as per applicable WPS. 





A‐Isometric   Control   Sheet, Weld  Register

2.6 

Check production welding for environmental  conditions, correct consumables, inter‐pass  temperatures, welding parameters.  Weld identification as to welder, weld N° and  other weld identification data 

Visual 

Project Procedure  Applicable WPS  Project Procedure  Applicable WPS 





Project Procedure Marked up ISO’s 

W/R

S

 

 

Project Procedure 

2.4 

2.7 

Visual 

treatment 

A‐Isometric    Control    Sheet    –Weld  Register 

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

43 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Piping Fabrication & Erection Plan 

  2 of 5 

 

Unit No  No. 

Contract No :  Activity Description 

Work Pack No  Test/Inspection Requirements 

Contractor  Reference Document 

SYSTEM No 

Inspection and Acceptance  Responsibility(2)  Contractor 

ITR ‐ Report or Document: (Note  1)

Company 

  2.8 

Welds completed and cleaned for NDT 

Visual acceptance

Project Procedure Applicable WPS, Applicable code 





A‐Isometric    Control    Sheet    –Weld  Register 

2.9 

Weld repairs completed in a satisfactory manner 

As per applicable WPS

Project Procedure Applicable WPS 





A‐Isometric    Control    Sheet    –Weld  Register 

2.10 

Post weld heat treatment (If required ‐ see point  Correct parameters as per WPS 2.11)  In case of project specific additional essential variables or requirements a separate ITP shall be  prepared and referred to or additional inspection line item shall be added    e.g. : non‐conventional welding process, special fluid service, PWHT, hardness test, chemical  passivation and others. 

Project Procedure Applicable WPS 

W/R 

S/R 

A‐Isometric    Control    Sheet    –Weld  Register 

    2.11 

  Project Standards (see Note 3) 

3  3.1 

 Non-Destructive Testing  NDT procedures appropriately approved and  qualified 

Review of the applicable NDT Procedures

Project Procedure NDT Procedures 





  3.2 

  Check NDT operators are qualified 

Review of the NDT operators certificates  and validity 

NDT operators Qualification List and  Certifications Project Procedure 

  H 

  R 

B‐NDT Operators List B‐NDT Operators Certification 

3.3 

Check NDT equipment and consumables 

Review   of   documents,   calibration   and  NDT Project Procedures conformity certificates, labels  Applicable codes 





B‐List of NDT Equipment B‐Calibration Certificates 

3.4 

Visual Inspection 

Inspection and reporting



S/R 

  3.5 

  R.T/U.T/P.T/M.T, as applicable and results  acceptable 

W/R 

W/R 

3.6 

  Witness NDT execution (done by NDT  company) and/or Review of NDT reports  for weld acceptance As per applicable WPS

Weld repairs completed in a satisfactory manner.  See point 2.9    Witness NDT execution (done by NDT  R.T/U.T/P.T/M.T, after weld repair as applicable  company) and/or Review of NDT reports  and results acceptable  for weld acceptance  In case of project specific requirements or non‐conventional NDT method/technique a separate  ITP shall be prepared and referred to    e.g.  :  UT  phased  array,  TOFD,  automated system, digital radiography, defect sizing for ECA  and others 

Project Procedure Applicable WPS 





NDT Project Procedure 



W/R 



W/R 

  3.7    3.8 

NDT Project Procedure NDT Project Procedure 

B‐NDT Procedure List

A‐Isometric    Control    Sheet    –Weld  Register  A‐NDT Test Reports  A‐Isometric    Control    Sheet    –Weld  Register  A‐NDT Test Reports 

Project Standards (see Note 3) 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

44 of 120 

     

 

 

 

INSPECTION AND TEST PLAN 

Page 

Piping Fabrication & Erection Plan 

3 of 5 

 

Unit No  No. 

Contract No : 

Work Pack No 

Contractor 

Test/Inspection Requirements 

Activity Description 

SYSTEM No  Inspection and Acceptance  Responsibility (2) 

Reference Document 

Contractor 

 

ITR ‐ Report or Document:  (Note 1) 

Company 

Final Inspection of spool 

4  4.1  4.2   

Dimensional control for tolerances and flange  alignments 

As per isometric drawing 

Preliminary pressure test if applicable. See point  12.1. 

Visual 

Final release for painting, store and erection, as  applicable. Spool tag No. correct and flanges / 

4.3 

Isometric 



S/R 

A‐Red Line Mark Up (update) 

H/R 

W/R 

A‐Pressure Test Report 

Project Procedures 

 

Project Procedures   

 

 

 

Visual 

Project Procedures 

H/R 

S/R 

  Visual 

  Project Procedures 

W

S

  Visual 

  Project Procedures 

W

S

Isometric index  Project Procedures 

H/R 

S/R 

A‐Inspection Release Note (IRN) 

open ends protection  Painting 



Spool painting is controlled by a separate ITP 

5.1 

Storing and transportation 



Spool temporary storing and transportation  are controlled if applicable by a separate ITP  to be prepared by project organization 

6.1 

Spool Erection 



As per isometric drawing

7.1 

Check isometric is controlled copy and latest  revision 

7.2 

Check spool release identification and  painting 

Visual. As per installation drawings 

Drawings. Fabrication report 





7.3 

Check spool for internal cleanliness. Check  flange facings (where applicable) 

Visual  Project Procedures 

Project Procedures 





  8.1 

A‐Isometric Control Sheet –Weld  Register 

Welding in Spool Erection 

8   

B‐Inspection Release Note and ITRs  from Painting 

  Repeat from point 2.1 to 2.11 

  Review of the applicable WPS PQR's 

Project Procedures 





A‐Form‐001  B‐WPSs/PQRs  B‐WQTR (welder qualifications)   B‐Welders List 

     

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

45 of 120 

      Contract No : 

Work Pack No 

4 of 5 

Page 

Piping Fabrication & Erection Plan  Unit No 

 

 

INSPECTION AND TEST PLAN 

Contractor 

SYSTEM No 

 

No. 

Test/Inspection Requirements 

Activity Description 

Inspection and Acceptance 

Reference Document 

ITR ‐ Report or 

Responsibility (2)  Contractor 

Document:  Company 

 

  Non Destructive Testing 

9     

   

 

B‐NDT Procedure List  B‐NDT Operators List  B‐NDT Operators Certification  B‐List of NDT Equipment   B‐Calibration Certificates   A‐Form‐001  A‐NDT Test Reports 

  9.1 

Repeat from point 3.1 to 3.6 

Installation and welding of supports 

10  10.1 

Material conforms to specification 

As per applicable isometric and typical  Mill Certificates  DWG 

10.2 

Cutting and beveling (as applicable) 

Correct cutting 

10.3 

Check of prefabricated supports  Welding.  Repeat  from  point  2.1  to  2.11  as  applicable 

As per applicable typical DWG   

See point 2.1 to 2.10 as applicable 

Repeat from point 3.1 to 3.6 as applicable 

 

See point 3.1 to 3.6 as applicable 

10.4  10.5 

H/R 

S/R 

Project Procedure 





Typical DWG 





Installation of spools (flanged joint) and miscellaneous items

11  11.1 

Fit loose items, blinds, Spacers, Valves installed 

As per Isometric drawing 

Isometric drawing 





11.2 

Flange  bolting  installation 

Dimensions and tolerances 

Isometric drawings  Project Standards (see Note 3) 



S/R 

 

and 

temporary    gasket 

Special   items   and   valves   with   specific  requirements are controlled if applicable by a  separate ITP to be prepared by project  organization 

11.3 

 

  12 

B‐MTCs 

Flange management ‐ Torqueing 

 

B‐MTCs A‐Red Line Mark Up (update)  A‐Installation record 

 

Torqueing sequence and parameters  Gasket   rating, type, material   and  certificate 

Project Procedure  Torqueing tables 

  H/ R 

  W/R 

A‐Torqueing report  A‐Flange management log 

     

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

46 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Piping Fabrication & Erection Plan  Unit No 

Contract No : 

No. 

Work Pack No  Test/Inspection Requirements 

Activity Description 

Contractor  Reference Document 

  5 of 5 

SYSTEM No  Inspection and Acceptance  Responsibility (Note 2) 

Contractor 

ITR ‐ Report or Document: (Note 1) 

Company 

    Final Inspection  13  Release for Pressure Testing 

Visual and Review of Pressure Test Packs

Project Procedure 

H/ R 

H/R 

A‐Red Line Mark Up (final) A‐Test  Package Release  A‐Pre Test Component Removal  A‐Punch List 

14  15     

Flushing and/or Flashing 

Visual on fluid at piping discharge end 

Project Procedure 

H/R 

H/R 

Pressure test performed and completed 

Joints and fittings inspected 100% visually  for leaks 

Project Procedure 

H/R 

H/R 

  15.1 

16 

Visual and Review of Pressure Test  document 

Project Procedure 

  H/ R 

  H/R 

Post Test / Reinstatement completed 

Visual inspection and document review 

Project Procedure and Check List 

H/R 

W/R 

A‐Pipe Cleaning Flushing Report  A‐Post Test Reinstatement Report 

H/R

W/R

B‐Inspection Release Note and ITRs from  Painting 





Weld Joint Painting and Paint Touch Up  See point 5.1 

 

Mechanical Completion 

18  18.1 

C‐Pre‐Test Checklist  A‐Pressure Test Record  A‐Pressure Recording Chart  B‐Gauge Calibration Certificate 

Pressure testing is controlled by a separate ITP 

17  17.1 

A‐Inspection Report

Mechanical completion dossier completion and  approval.  See Mechanical Completion Procedure 

Documents completeness 

Project Procedures 

Mechanical Completion Dossier 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:   Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes. 

  Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

47 of 120 

     

Page 

Installation of PSV Valves  Unit No  No. 

Contract No : 

Work Pack No 

Contractor 

Test/Inspection Requirements 

Activity Description 

Reference Document 

Contractor      1.1 

Company 

    Valve Passport 

Project Standards (see Note 3) AFC  Drawings 

Review for Compliance 

 

  H/R 



Code & Standard  Project Procedure  

 

 

Calibration of safety relief valve. 

Review for Compliance form 

1.3 

Safety relief valve installed correctly 

As for P&ID  Tag No. correct  Visual Inspection 

1.4 

Verify shipping stoppers are removed 

Visual Inspection 

1.5 

Calibration tampers proof seal intact 

1.6 

Final inspection  for correct bolt material, size  and gaskets 

1.7 

Safety  relief  valve  installation  complete  and  conformant. Vent piping complete and correct. 

1.2   

 

2    2.1 

3  3.1 

ITR ‐ Report or Document:  (Note 1) 

Valve Installation 



 

1 of 1 

SYSTEM No  Inspection and Acceptance  Responsibility(2) 

     

 

 

INSPECTION AND TEST PLAN 

  As above 

 

  H/R 

 

    B‐Passport and material certificate 



B‐Manufacturer Calibration  Certificate  A‐Site Calibration Certificate

 

As above 





A‐Installation report  C‐Installation Check List 

As above 





C‐Installation Check List 

Visual Inspection 

As above 





C‐Installation Check List 

As per requirements Isometric‐BOM 

As above 





C‐Installation Check List 

As per drawings  Release 

As above 





A‐Installation report 

Project Procedures 





Mechanical Completion Dossier 

Project Procedures 

W/R 

Interim Mechanical Completion  Inspection  report  and  documentation  to  be  included   in   the   Mechanical   Completion  package of the relevant piping line or vessel.  See Mechanical Completion Procedure  Pre-commissioning 

Documents Completeness 

Functional test or recalibration if required  Correct functionality  before turn‐over to  commissioning  (e.g. valves) 

S/R 

A‐Test Report 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes  and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend : S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point For Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

48 of 120 

     

 

 

INSPECTION AND TEST PLAN 

Process Piping Pressure Test   

Unit No    No. 

Contract No : 

Work Pack No 

Contractor 

  Activity Description 

Reference Document 

1 of 2 

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Inspection and Acceptance  Responsibility (2)  Test/Inspection Requirements

 

Page 

Contractor 

Company 

H/R 

H/R 





H/R 

  W/R 

H/R 

  R 

A‐Pre‐Test Check List  B‐Calibration Certificate 





A‐Punch List 

H/R 



B‐Laboratory certificate 

Pressure Test Procedure  Pressure Test Scheme 





C‐Check List 

   

Pre-test checks 

1  1.1 

Test pack acceptance 

Test pack review 

1.2 

Installation of piping spool/line in accordance  With pressure test approved scheme. 

Visual inspection 

1.3 

Main and miscellaneous materials for pressure  testing inspection (pumps, valves, hoses, coupling,  blinds, bolts/nuts) 

Visual inspection  Review of material certificates for  correct rating 

Project Standards (see Note 3) Project  Procedures 

1.4 

Pressure   and   temperature   gauges   and  recorders are correct and installed in the correct  position 

Visual inspection  Review  of  calibration  certificates  Correct measuring range 

Pressure Test Procedure  Pressure Test Scheme 

1.5 

Punching of the test section complete 

Visual As per drawings 

Pressure Test Procedure  Pressure Test Scheme 

1.6 

Test medium certificate 

Review of laboratory analysis  certificate 

Project Standards (see Note 3)  Pressure Test Procedure 

 

 

Project Standards (see Note 3) Project  Procedures  Pressure Test Procedure Pressure Test Scheme  P&I mark‐up  

 

B‐Test Package Release 

A‐Pre‐Test Check List    A‐Pre‐Test Check List 

Test preparation 

2  2.1 

  All valves in the section of the line are in the  correct (open/close) position. (Part or fully opened  Visual inspection  dependent of valve type). 

2.2 

Pre‐test removal of components 

Visual inspection 

Pressure Test Procedure  Pressure Test Scheme 





A‐Pre‐test Components Removal 

2.3 

Piping Line filling complete. Control rate and air  content check. 

Visual inspection 

Pressure Test Procedure  Pressure Test Scheme 





C‐Check list 



  H 

Test pressure execution 

3   

  3.1 

Hydro testing operations as per limits of test  package 

Rate of pressurization  Strength test ‐ Pressure  Holding Time and leak absence  Sign on test chart 

Project Standards (see Note 3) Project  Procedures 

 

  C‐Check List 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

49 of 120 

 

INSPECTION AND TEST PLAN 

Page 

Process Piping Pressure Test  Unit No  No. 

Contract No : 

Activity Description 

Work Pack No 

Contractor 

Test/Inspection Requirements

Reference Document

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

   2 of 2 

Company 

    3.2 

Pressure test complete 

3.3 

De‐watering activities complete 

3.4 

Drying (if required) 



Pressure Test Acceptance 

4.1 

Final Acceptance of Test Package 

    4.2 

Controlled rate of depressurization sign of  Project Standards (see Note 3)  Project Procedures  charts  Project Standards (see Note 3) Visual  Project Procedures 





A‐Pressure Test Report 





A‐Pressure Test Report 

Check of air at pipe end for drying (dew  point) 

Pressure Test Procedure  Piping Specification 





A‐Pressure Test Report 

Signature of Pressure Test Report and Test Package front page 

Project Standards (see Note 3) Project Procedures 





A‐Test Package 

  H 

  H/R 

  Test Package to be included in the Mechanical    Completion package of the relevant piping line See  Documents completeness  Mechanical Completion Procedure 

  Project Procedures 

  Test Package Dossier 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents   type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.    Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

     

 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

50 of 120 

     

Appendix 5:   Electrical Works    

a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) p)

Installation of Generators  Installation of Batteries, Battery Charger & UPS Systems  Installation of Lighting System  Installation of Earthling & Lightning Protection System  Installation of Low and High Voltage Motors  Installation of Power Transformer  Installation of Switchgear and Motor Control Center  Installation of Small Power Distribution Equipment  Installation of Cable Racks, Trays and Conduit System  Cable Pulling Termination Jointing and Conduit ‐ Installation  Jointing, Glanding and Termination of Power and Control Cables  Installation of Motor Operated Valves  Installation of Neutral Earth Resistors  Installation of Electrical Heat Tracing  Pin Brazing of Cable Connection  Installation of Cathodic Protection System 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

51 of 120 

     

 

 

INSPECTION AND TEST PLAN 

 Page 

Installation of Generators  Unit No   

Contract No :   

  No. 

Work Pack No 

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

  1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

ITR ‐ Report or Document: (Note 1) 

Company 

  1 

Equipment specification and rating correct 

Data sheets

Data sheets

S

S

A‐Generator inspection 



Equipment fixing and Mounting checked 

Visual 

Details layout

S

S

A‐Generator inspection



Glanding and termination correct 

Visual 

Termination, details / vendors  documents 

W

W



Anti‐condensation  heaters  installed  as  per design  Design specification

Vendor documents

S

S

A‐Generator inspection



Equipment earthling completed and tested 

Note 3

W

W

A‐Equipment earth inspection

Visual/Test

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:   Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes    Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

         

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

52 of 120 

     

 

  Page 

INSPECTION AND TEST PLAN 

  1 of 1 

Installation of Batteries, Battery Charger & UPS  Unit No      No. 

Contract No : 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

SYSTEM No 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

ITR ‐ Report or Document:   (Note 1) 

Company 

   



Equipment Classification and IP rating checked 

Visual  Design Drawings 

Vendor Data Sheet 





A‐ Batteries charger & Ups  Inspection 



Name plate checked against datasheets and  equipment  checked for external damage 

Vendor Data Sheet 

Note 3 





A‐ Batteries charger & Ups  Inspection 



Equipment fixing and mounting are secure and  aligned 

Visual 

Installation details and layout 





A‐ Batteries charger & Ups  Inspection 



Earthling checked against design requirement 

Testing 

Note 3 



W/R 



Inside   of   the   equipment   checked   for  cleanliness and any damage 

Visual 

Note 3 







All connections, cable marking, glanding and  identifications checked 

Vendor Data Sheet 

Note 3 





A‐  Batteries charger & Ups  Inspection 



Batteries polarity checked  Ensure outgoing  isolators/MCBs  are  isolated  and main isolator is lockable  Door gaskets and seals checked  Doors openings are not obstructed 

Test 

Note 3 





A‐Batteries Inspection 

Visual 

Note 3 





Visual 

Specifications and drawings 





A‐Batteries & Ups Inspection 

10 

Battery stands installation checked 

Visual 

Vendor documents recommendation 





A‐Batteries Inspection 

11 

Battery   links   fitted,   grease   applied   and  electrolyte level is correct 

Visual 

Vendor document and specifications 





A‐Batteries Inspection 

8  9 

A‐Equipment earth inspection  A‐  Batteries charger & Ups  Inspection 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and  (B) are included in Mechanical Completion. 

 

  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and  matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”. 

  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

53 of 120 

     

  Unit No 

Contract No : 

No. 

Work Pack No   

 

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

      1 

     

      Insulation resistance Test on Drums 

    Cable Schedule  Note 3 

Megger and Continuity Tests 

SYSTEM No 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

 

1 of 1 

Page 

Installation of Power and Control   

 

 

INSPECTION AND TEST PLAN 

    W 

ITR ‐ Report or Document: (Note 1) 

Company      S/R 

A‐Cable drum inspection protocol for measurement of  power cables over and up to 1000V insulation  resistance on the drum  A‐Cable drum inspection protocol for measurement  control cables insulation resistance on the drum 



Check Trench depth and correct bedding for   Cable Installation 

Visual Inspection 

Note 3 





A‐ Cable trench inspection 



Check Cable and Cutting Schedules to latest  Revision prior Installation 

Visual Inspection 

Note 3 





B‐ Cable Schedule to last Revision 

  4 

Check Cable Dressing, Marking, Segregation and   Spacing as per Project Procedures/Specs  Visual Inspection 

Standard Installation Details 

  W 

  W/S 



Continuity and Meggering Test for Cables  prior   Megger and Continuity Tests  to Backfilling 

Note 3 



W/R 

  6 

  Perform Continuity, Meggering Test after  Glanding and check final Installation 

Megger and Continuity Tests 

Note 3 

  W 

  W 



High Voltage Injection test only for HV Cables  after Glanding 

High ‐Pot Test 

Note 3 



W/R 



Final Inspection for Closed Trench including   Cable Markers, and warning signs 

Visual Inspection 

Note 3 





 

 

 

A‐ Cable inspection before covering 

A‐HV power cables (above 1000V) A‐LV power and control cables Protocol for  measurements   of power cables up to 1000Vand  control cables  A‐Insulation resistance after glanding A‐HV test record 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and  (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis     

     

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

54 of 120 

     

INSPECTION AND TEST PLAN 

Installation of Lighting System   

Unit No    No. 

Contract No : 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

 

 

 Page 

1 of 1  

SYSTEM No  Inspection and Acceptance Responsibility (Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 

  1 

Equipment checked for any damages 

Visual 

Note 3 





A‐Lighting circuit 



Equipment rating and specification checked 

Visual 

Layout drawing and zone classification 





A‐Lighting circuit 



Equipment  installation,  orientation  and  alignment checked against design drawings 

Visual 

Standard details 

W/S 



A‐Lighting circuit 



Check Final Installations for all lighting devices 

Visual 

Note 3 





A‐Lighting circuit  A‐Control station/Junction 



Cable  and  wire  connections  checked  at  JB’s 

Visual 

Note 3 





A‐Lighting circuit 



Cables tested and laying checked per circuit 

Visual 

Note 3 



W/S 



Check lighting distribution  panel termination   and installation are completed 

Visual 

Note 3 

W/S 





Earthling completed and tested 

Visual 

Note 3 



W/R 



Circuit list and labels installed 

Visual 

Standard details and specifications 





Visual /physical installation checks 

Standard details and specifications (Note 3) 



W/R 

Visual 

Standard details and specifications 



W/R 

  10 

Verify equipment installation in accordance  with Ex requirements (Example: Switches,  lights, fittings, junction boxes, etc.). Where 

11 

lighting illumination test is controlled by a  separate ITP shall be prepared and referred to  e.g. Adequate illumination during the night and  Glare from light source. 

 

A‐Lighting and distribution board 

A‐Lighting circuit  A‐Hazardous  area  equipment, ex  type enclosures 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and  (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection   attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis        Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

55 of 120 

     

INSPECTION AND TEST PLAN 

Installation of Earthling & Lightning Protection System   

Unit No    No. 

Contract No: 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

   

   

   

 

 

Page 

1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

 

 

ITR ‐ Report or Document:  (Note 1) 

Company  A‐Equipment earth cables inspection  A‐Earth network inspection and  resistance measurement  A‐Earthling pit inspection  A‐Test record of earthling system 



Earth Cable and pits located correctly as per  drawings and to specified depth 

Visual 

Design drawings 

  W 

  W 



Earth conductor size is correct 

Visual 

Design drawings 





A‐Test record of earthling system 



Cad  weld  and  connections  checked,  joints  greased 

Visual 

Note 3 





A‐Test record of earthling system 



Check   Earth    Bar   installed   correctly   as  location   and service where required 

Visual 

Design drawings 





A‐Test record of earthling system  A‐Equipment earth inspection 

 

 

 



Underground work Inspection completed 

Inspection 

Project Specifications 





A‐Circuit inspection between earthling  conductors and earthling elements 



Pit inspection completed 

Inspection 

Project Specifications 





A‐Earth pit inspection prior to backfilling 

Inspection 

Project Specifications 





Test 

Note 3 





 

  7 

Earthling conductor and earthling element  completed 



Earth rod and network earth resistance  checked 

 

A‐Circuit inspection between earthling  conductors and earthling elements  A‐Test record of earthling system  A‐Test record of earthling system 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

56 of 120 

     

 

   Page 

INSPECTION AND TEST PLAN 

Installation of Low and High Voltage Motors  Unit No   

Contract No : 

No. 

Work Pack No   

  Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

  1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility (Note 2)  Contractor

Company

ITR ‐ Report or Document:  (Note 1) 

 

 



Name plate, equipment classification and  IP   rating checked 

Visual  Data sheets 

Data Sheet  Note 3 





A‐Inspection and Test Record for  Electric Motor 



Equipment checked for any damages and carries  correct circuit identification 

Visual 

Note 3 





A‐Inspection and Test Record for  Electric Motor 



Equipment fixing and mounting are secure 

Visual 

Note 3 





A‐Inspection and Test Record for  Electric Motor 



Earthling completed and checked against design  requirements 

Visual/ Design specifications 

Note 3  





A‐Inspection and Test Record for  Electric Motor 



All connections including RTD or thermostats  checked 

Visual 

Note 3 





A‐Inspection and Test Record for  Electric Motor 



Fan is free to rotate and motor shaft rotated by  hand 

Test 

Note 3 







Terminal box  gaskets  and  seals  are present   and  not damaged 

Visual 

Note 3 







Glanding completed, spare entries plugged and  bolts are correct 

Visual 

Note 3 







Motor Solo Run (uncoupled) to check vibrations,  temp., rpm, etc.. 

visual/Test 

Procedure 



W/R 

A‐Inspection and Test Record for  Electric Motor A‐Inspection and Test Record for  Electric Motor  A‐Inspection and Test Record for  Electric Motor  A‐Inspection and Test Record for  Electric Motor 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and  (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and  matrixes.    Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

   

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

57 of 120 

     

   Page 

INSPECTION AND TEST PLAN 

Installation of Power Transformer   

Unit No    No. 

Contract No : 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

  1 of 1 

SYSTEM No  Inspection and Acceptance  Responsibility (Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 



Transformer   specification &  name  plate  checked against data sheets 

Visual Inspection  Data Sheet 

Data Sheet and specification 





A‐Inspection  and  Test  Record  for  Power Transformer 



Transformers checked for any damage 

Visual Inspection 

Note 3 





A‐Inspection and Test Record  for  Power Transformer



Correct orientation, alignment and installation 

Layout  and  standard  details  Vendor  Drawing 

Vendor Drawings 





A‐Inspection  and  Test  Record  for  Power Transformer 



Manual  operation  of  tap  changer  in  all  positions correct 

Vendor Drawings 

Vendor Drawings  Note 3 



W/S 

A‐Inspection  and  Test  Record  for  Power Transformer 



Primary,  Secondary  and  wiring  connection  correct 

Visual Inspection 

Visual Inspection  Note 3 



W/S 

A‐Inspection  and  Test  Record  for  Power Transformer 



Equipment earthling completed 

Visual Inspection 

Testing  Note 3 



W/S 

A‐Equipment earth inspection 



Check oil level 

Visual Inspection 

Data Sheet and specification 





A‐Inspection  and  Test  Record  for  Power Transformer 



Check resistance between phases    Check auxiliary wiring if connection correctly  completed prior commissioning 

Visual Inspection    Vendor’s Drawings  Visual Inspection 

Data Sheet and specification





A‐Inspection  and  Test  Record  for  Power Transformer 

Visual Inspection  Note 3 





A‐Inspection  and  Test  Record  for  Power Transformer 

10 

Check and Verify the color of  silica gel prior  commissioning 

Visual Inspection 

Visual Inspection Data Sheet 





A‐Inspection and Test Record  for  Power Transformer 

11 

Testing of transformer 

Test 

Procedure



W/R 

A‐Inspection and Test Record  for  Power Transformer 



 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and  (B) are included in Mechanical Completion. 

 

Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed of f and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”. 

  Legend : S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point For Inspection R‐ Record Review

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

58 of 120 

     

 

INSPECTION AND TEST PLAN 

Installation of Switchgear and Motor Control Center  Unit No   

Contract No: 

No. 

Work Pack No   

 

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

 

 Page 

1 of 1 

SYSTEM No  Inspection and Acceptance  Responsibility (Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 



Check   equipment   is   suitable   for   area  classification and IP rating 

Visual Inspection 

Specification/Data sheet 



S/R 



Name plate checked against data sheets 

Visual Inspection 

Data sheet 







Orientation, alignment and fixation correct 

Visual Inspection 

Installation details 





  4 

Equipment checked for  internal damage and  cleanliness 

  Visual Inspection 

  Note 3 

  W 

  S 



Equipment earthling completed and tested 

Visual Inspection 

Note 3 



W/R 



Identification and labeling correct 

Visual Inspection 

Installation Layout Drawings 







Bus Duct correctly installed and Duct test  completed on bus bar joints 

Testing 

Note 3 

H/W 

W/R 

Testing of MCC 

Test 

Procedure 



W/R 



 

A‐Inspection and Test Record  for  switchgear  A‐Inspection  and  Test  Record  for  motor control A‐Inspection and Test Record  for  switchgear  A‐Inspection  and  Test  Record  for  motor control A‐Inspection and Test Record  for  switchgear  A‐Inspection  and  Test  Record  for  motor control A‐Inspection and Test Record  for  switchgear  A‐Inspection  and  Test  Record  for  motor control A‐Equipment earth inspection  A‐Inspection and Test Record  for  switchgear  A‐Inspection  and  Test Record  for  motor control A‐Inspection and Test Record  for  switchgear  A‐Inspection  and  Test  Record  for  motor control

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

59 of 120 

     

 

INSPECTION AND TEST PLAN 

Installation of Small Power Distribution Equipment  Unit No  No. 

Contract No :  Activity Description 

Work Pack No 

Contractor 

Test/Inspection Requirements 

  Installation of Panel Completed Power  Distribution Board Installation completed Misc.  Visual / Test  Equipment. Installation completed 

 

  2 

  230V AC/16A, Check Socket Outlet  Installation and circuit is completed and checked  Visual / Test 

 



Check Welding Socket Outlet Installation.  (400V/63A) 



Check All Equipment including Junction Boxes   for Hazardous Classification 

 

Page 

1 of 1 

SYSTEM No  Inspection and Acceptance  Responsibility (Note 2)  Contractor  Company 

Reference Document 

  1 

 

  Note 3 



A‐Distribution Board A‐Miscellaneous equipment  A‐Hazardous   area   equipment‐ex  type enclosures  A‐Hazardous   area   equipment‐ex  type enclosures  A‐Small power circuit Inspection  A‐230V AC socket outlets 

  W 

 

ITR ‐ Report or Document:  (Note 1)  

 

Note 3 





Visual / Test 

Note 3 





A‐Hazardous   area   equipment‐ex  type enclosures  A‐Welding socket outlets 

Visual 

Note 3 





A‐Hazardous   area   equipment‐ex  type enclosures  A‐Miscellaneous equipment 



Check  if all fuse links/ MCB/ Protection devices   Visual  are correct 

Note 3 







Confirm Earthling Connections 

Note 3 





Visual 

A‐Distribution board A‐Small power circuit  A‐Miscellaneous equipment  A‐Equipment earth inspection 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review    

         

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

60 of 120 

     

Installation of Cable Racks, Trays and Conduit System  Unit No      No. 

Contract No : 

Work Pack No   

Activity Description 

Contractor 

SYSTEM No 

  Test/Inspection Requirements 

Inspection and Acceptance  Responsibility (Note 2) 

Reference Document 

Contractor  As per construction drawings and project  Standard details  specifications 



Support Installed As required 



As per standard drawings Cable trays/racks, clamps, fittings, connectors,  hanger clamps, expansion guides are installed as  specified  Project Specifications and tray layout Check if cable trays/racks installation correctly 



completed and can be released for cable 

Standard details  Note 3   

  1 of 1 

   Page 

INSPECTION AND TEST PLAN 

Company 

S   



A‐Cable ladder & tray/dressing /  transits  A‐Cable ladder & tray/dressing /  transits  A‐Cable ladder & tray/dressing /  transits 

S   

S   

ITR ‐ Report or Document:  (Note 1) 

 

Note 3 







Cable  Tray/Rack  Release  for  installation  of  covers 

Check cables are installed as per  specifications and drawings 

Note 3 



W/S 

A‐Cable inspection before covering 



Cable   tray/rack covers installed as per  requirement 

Drawings and Specification 

Standard details 



S/R 

A‐Cable ladder & tray/dressing /  transits 



Cable   tray/rack   system   bonding   to  the  main  earthling  system 

the main  Note 3 





A‐Cable ladder & tray/dressing /  transits 



Conduit support structure secure 

Check continuity with  earthling system  Installation Drawings

Note 3 







Conduit Routing clear from heat sources 

Installation Drawings

Note 3 







Conduit Junction Boxes/Pull Boxes installed    where  required  Conduit ends are free from sharp edges 

Installation Drawings

Note 3 





Visual Inspection

Note 3 





A‐Cable ladder & tray/dressing /  transits A‐Cable ladder & tray/dressing /  transits A‐Cable ladder & tray/dressing /  transits A‐Cable ladder & tray/dressing /  transits

10   

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP. Documents type (A) and (B) are  included in Mechanical Completion. 

 

Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

 

   

Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

61 of 120 

    INSPECTION AND TEST PLAN 

 

Page 1 of 1 

Cable Pulling Termination Jointing and Conduit - Installation  Unit No 

Contract No: 

No. 

Work Pack No 

Activity Description 



GENERAL 

1.1  1.2 

Review of Technical Documents  (Drawings, Specs,  Method statements etc.)  Material Inspection 



Cable Conduit Installation 

2.1 

Contractor Test/Inspection Requirements

Reference Document 

Inspection and Acceptance  Responsibility (2)

Contractor

Company

SYSTEM No ITR ‐ Report or Document:  (Note 1) 

Document Review 

Standard Installation Details

W

W/S

Visual& Dimension Inspection

Material Certificate Submission 

W

S

(B) Material Certificate 

Visual Inspection

Installation Drawings (Note 3) 

S

S

A‐cable insulation Drawings



Cable conduit route and box installation check for  lPower and Control Cable Installation  bl ll k

3.1 

Cable route readiness check for cable installation 

Visual Inspection

Installation Drawings (Note 3) 

S

S

A‐cable insulation Drawings

3.2 

Cable installation check 

Visual and Dimensional 

Installation Drawings (Note 3) 

S

S

A‐cable insulation Drawings



Cable Tests 

4.1 

Insulation resistance checks 

Controlling Test Results

Test Report Submission

W

W

A‐cable test report

W

A‐cable insulation and continuity test report 

A‐ Cable inspection Check List 

4.2 

Point to point and Continuity check 

Controlling Test Results 

 Megger and Continuity Tests 

W

4.3 

High pot test for HV cables 

Controlling Test Results

Test Report Submission

W

W

A‐cable test report

4.4 

Megger test for LV cables 

Controlling Test Results

Test Report Submission

W

W

A‐cable test report

4.5 

Termination Point Bolt Torque Test 

Visual

Termination, details / vendors documents

W

W

A‐cable insulation report

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review                                 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

62 of 120 

           

 

 Page 

Jointing, Glanding and Termination of Power and Control Cables   

Unit No    No. 

Contract No : 

Work Pack No   

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

 

 

INSPECTION AND TEST PLAN 

SYSTEM No ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

Company 

1 of 1 

  1 

Check  if  material  type,  size  comply  with  certification 

Visual Inspection 

Note 3 







Check joints installation at terminations, if done  properly 

Visual Inspection 

Note 3  Manufacturer Sheets 





Visual Inspection 

Note 3 





Visual Inspection 

Note 3 





A‐HV power cables (Above 1000V) A‐LV  power and control cables 

A‐Material list   



Check terminations and color of heat  shrinks‐if  applicable  Check if cable glands sealed, tightened and  correctly installed. 



Check Installation of gland earth tag and IP  washer 

Visual Inspection 

Note 3 





A‐HV power cables (Above 1000V) A‐LV  power and control cables 



Check cables if no loose connection at terminals  and torque as per Vendor's  and Engineering  Recommendations 

Torque Test   /   Visual Inspection 

Note 3 





A‐HV power cables (Above 1000V) A‐LV  power and control cables 



Check Cables and Termination Wiring ‐ Tags,  Labels, Ferrules 

Visual Inspection 

Note 3 





A‐HV power cables (Above 1000V)  A‐LV power and control cables 



 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and  matrixes.    Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

                 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

63 of 120 

     

INSPECTION AND TEST PLAN 

Installation of Motor Operated Valves  Unit No   

Contract No : 

Work Pack No   

  No. 

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

 

 

 Page 

1 of 1 

SYSTEM No ITR ‐ Report or Document:   (Note 1) 

Company 

  1 

Name plate, equipment classification and  IP   rating checked 

Visual  Data sheets 

QCP‐714‐321  Data Sheet 





A‐Equipment installation check list 



Equipment checked for any damages and  carries correct circuit identification 

Visual 

PP‐714‐409 





A‐Equipment installation check list 



Equipment fixing and mounting are secure 

Visual 

By Mechanical Group 





A‐Equipment installation check list 



Earthling completed and   checked against  design requirements 

Visual/ Design specifications 

QCP‐714‐309 







Check all connections are correct including  cable Testing and marking 

Visual 

QCP‐714‐312 







Check and verify if all installations conform to  data sheet 

Data Sheets and Specifications 

Data Sheet/Specifications 





A‐Equipment installation check list 



Function test 

Visual/Test 

Vendor Manual 





A‐ Pre‐commissioning Check List 

Data Sheet  Project Standards (see Note 3)    Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed of f and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.    Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review     

           

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

64 of 120 

     

 

   Page 

INSPECTION AND TEST PLAN 

Installation of Neutral Earth Resistors  Unit No      No. 

Contract No : 

Work Pack No   

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

  1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 

  1 

Equipment   classification,   IP   rating   and name   Visual Data Sheet  plate checked against data sheets 

Data Sheet and Specifications 





A‐Equipment earth inspection 



Equipment inspection for external damage 

Visual 

Note 3 





A‐Equipment earth inspection 



Fixing, orientation and mounting are secure 

Visual 

Layout Drawings and vendor details 



W/S 

A‐Equipment earth inspection 



All  connections  checked  and  correct  labels  installed 

Visual/ Drawings 

Vendor Details 





A‐Equipment earth inspection 



Earthling checked against design  requirements 

Visual 

Note 3 





A‐Equipment earth inspection 



Gasket and seals are not damaged, bolts are  correct 

Visual 

Note 3 





A‐Equipment earth inspection 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.   Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually   signed off and dated here below for completion.   Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and   matrixes.     Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”. 

  legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

     

 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

65 of 120 

     

INSPECTION AND TEST PLAN 

Pin Brazing of Cable Connection   

Unit No    No. 

Contract No : 

Work Pack No 

Contractor 

 

  Reference Document 

Test/Inspection Requirements 

Activity Description 

Material Inspected for mage and according  to  Specification 

    2 

Attachments for Pin Brazing  1. Brazing Procedure Specification to be  approved  2. Pin Brazer to be qualified  3. Pin to be correct size & type  4. Preheating to be as per BPS 

QCP‐ 714‐409 

Visual Inspection   

  Check BPS is approved    Check Brazer ID Card / Certificate  Check Pin size & type is correct  Check Preheating is correct 

Appropriate WPS    ID Card / Certificate  As BPS  As BPS 

Distance of Pins from weld and between Pins is  correct  Pipe Coating at connection removed properly   and exposed area cleaned 

Visual Inspection 

 

Page 

1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 



 

ITR ‐ Report or Document:  (Note 1) 

Company 









‐ 

 

 













Note 3 





A‐Pin brazing record inspection 

Visual Inspection 

Note 3 





A‐Pin brazing record inspection 

Brazed Pin checked for fastness and quality of  joint Perform holiday test on repair portion of pipe  line and stud checked (if applicable) 

Test 

Note 3 





A‐Pin brazing record inspection 

Test 

Note 3 





A‐Pin brazing record inspection 



Coating reinstatement carried out properly 

Visual Inspection 

Note 3 





A‐Pin brazing record inspection 



Holiday Test carried out 



A‐Pin brazing record inspection 

3  4  5  6 

  9 

Test      Check  Insulation  Resistance  Test  /  Continuity  Test  test/  for  power  supply  cables  to  transformer  rectifier 

Note 3  Note 3

W   

  W 

W/S 

A‐Protocol of measurements of power  cables up to 1000V Insulation resistance  after laying   A‐Protocol of measurements of power  cables up to 1000V Insulation resistance  after glanding  (Use forms as applicable) 

   Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2:   Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and dated  here   below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable. Hierarchy of documents in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

66 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Installation of Cathodic Protection System  Unit No 

Contract No : 

No. 

Activity Description 



Equipment checked for damages and name plate  verified against data sheets  Equipment IP rating and hazardous area  classification checked. 



Work Pack No 

Contractor 

Test/Inspection Requirements 

SYSTEM No 

Inspection and Acceptance  Responsibility(2)  Contractor  Company 

Reference Document 

  Note 3 





A‐Cathodic   Protection   Inspection   and test record 

Visual Inspection 

Note 3  Data Sheets 





A‐Cathodic   Protection   Inspection   and  test record 

Equipment earthling completed to rectifier 

Visual Inspection 

Note 3 



W/S 



Anode  vertical  well  bed  installed  properly  and  correct depth and coke breeze backfilled properly 

Visual Inspection 

Note 3   Detail Drawing 



W/R 



Sacrificial buried anode installed to correct depth  and distance from structure 

Visual Inspection 



W/S 



Anode cable routing, bonding and depth checked 

Visual Inspection 



W/S 



Sacrificial immersed anodes fixing points checked 

Visual Inspection 

Note 3  Detail Drawing 



W/S 



Reference electrode installation, cable routing and  depth are correct 

Visual Inspection 



W/S 



Junction boxes and test posts  installation, cable  routing and connection checked. 

Visual Inspection 

Note 3  Detail Drawing  Note 3  Connection Diagram Drawings 





10 

Isolating joints installed properly and insulation  efficiency checked 

Visual Inspection 



W/S 







W/S 



W/R 

  12  13 

  Check and verify Cathodic Protection Installation  Vendor Check List  completion and conformance to Vendor  Documents and  Check Cable Installations for Underground Work    and/or   Tray   Applications.   Confirm   Installation  Visual Inspection  Requirements  Testing of cathodic protection 

ITR ‐ Report or Document:  (Note 1) 

Visual Inspection 



11 

  1 of 1 

Test 

Note 3  Detail Drawing  Note 3  Detail Drawing 

Note 3  Detail Drawing  Vendor Detail Drawings 

 

Note 3 

 

Procedure 

A‐Cathodic   Protection   Inspection   and  test record  A‐Cathodic   Protection   Inspection   and  test record A‐Cathodic   Protection   Inspection   and  test record  A‐Cathodic   Protection   Inspection   and  test record  A‐Cathodic   Protection   Inspection   and  test record A‐Cathodic   Protection   Inspection   and  test record  A‐Cathodic   Protection   Inspection   and  test record   

A‐Underground work inspection  A‐Cable trench inspection  A‐Cable inspection before covering   

 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification 

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

67 of 120 

   

           Appendix 6:   Instrument Works    

a) Installation of Field Mounted Instruments  b) Installation of Instrument Cables  c) Installation of Instrument Interface Panels & Junction Boxes  d) Installation of Instrument Panels, Consoles & Desks  e) Installation of Fiber Optic Cables  f) Installation of Fire & Gas Detection System  g) Instrument Loop Continuity Check  h) Installation of Actuated Valves (control valves, on/off valves)  i) Installation of Water analyzer  j) Field Instruments – Installation  k) Installation of PAGA System  l) Telecommunication and Security Systems ‐ Installation 

               

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

     

Sheet of Sheets 

68 of 120 

  Page 

INSPECTION AND TEST PLAN 

Installation of Field Mounted Instruments  Unit No   

Contract No :   

No. 

Work Pack No   

Activity Description 

Contractor 

SYSTEM No ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(Note 2) 

  Test/Inspection Requirements 

Reference Document 

Contractor 

  1 of 1 

Company 

 

  1  2    3  4  5    6  7  8    9 

10 

Instrument inspected for external damage,  classification and IP rating checked before  Check instrument calibration completed prior to  installation.  Instrument supports installation and grounding  checked  Check instrument installation, mounting,  orientation, position and elevations.  Check instrument if will required for Sunshade  Check instrument installed clear of obstructions  and accessible.  Impulse and hydraulic lines supporting and  installation  Impulse, hydraulic and air lines tested  Instrument installation complete, 

Visual 

note 3 

Testing 

note 3 

Visual 

note 3 

Visual 

note 3 

Visual 

note 3 

Visual 

note 3 

Visual 

note 3 

Testing 

note 3 

Visual 

note 3 

conformant and proper label installed  Verify Equipment Installation in accordance with    requirements (Example: Pressure, Switches,  Junction Boxes   and Other field devices /  Instruments) Where 

 

 

  W 







 

 

   





A‐instrument installation checklist 





A‐instrument installation checklist 





A‐instrument installation checklist 





A‐instrument installation checklist 





A‐instrument installation checklist 

W/R 

W/R 

A‐instrument installation checklist   tubing/hose pressure test/flush 





A‐instrument installation checklist 



W/R 

note 3  Visual/ Physical Installation Checks  Standard detailed and specification 

A‐hazardous area equipment  Ex) type enclosures 

 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007  

     

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

69 of 120 

  Page 

INSPECTION AND TEST PLAN 

Installation of Instrument Cables  Unit No   

Contract No : 

  No. 

Work Pack No   

Contractor  Reference Document 

1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility(Note 2) 

  Test/Inspection Requirements 

Activity Description 

 

Contractor 

ITR ‐ Report or Document: (Note 1) 

Company 

 



Cable drums checked for any damage 



Cable  insulation  resistance  and  continuity  checked on drum before laying 



Trench and soft sand bedding inspected. 

4    5 

Visual inspection 

note 3 





Test 

note 3 

W/R 

S/R 

note 3 





Visual  Check  instrument  installation,  mounting,  Visual  orientation, position and elevations and installation  Check cable insulation resistance and continuity    Test  after laying. (only in trench application) 

note 3  Detailed standards   

W   

W/S   

note 3 

W/R 

S/R 

  A‐cable  insulation  and  continuity test  report  A‐cable trench inspection     

A‐cable  insulation  and  continuity test report 

Visual  Perform Activities only when applicable 

note 3 



W/S 

A‐cable inspection before covering 



Soft sand and tile backfilling checked before final  backfilling and cable route marker tape installed  Glanding and termination checked 

Visual 

note 3 



W/S 

A‐ LV power and control cables 



Confirm earth tag and IP washer are installed,  where applicable 

Visual 

note 3 



W/S 

A‐ LV power and control cables 

Visual 

Detailed Drawings 





A‐ LV power and control cables 

Visual 

note 3 





A‐ LV power and control cables 

Test 

note 3 

W/R 

W/R 



9  10  11 

Confirm spare cores and screens are earthed  Check termination is correct and conformant  Final I/R Test then Reconnect Cables 

A‐cable insulation and continuity test report 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion  Note 2:   Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed  off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and  matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification 

252100DBQA00007

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets 

70 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Installation of Instrument Interface Panels & Junction Boxes  Unit No   

Contract No : 

  No. 

Work Pack No   

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

SYSTEM No 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

  1 of 1 

ITR ‐ Report or Document: (Note 1) 

Company 

  1 

Pre‐installation equipment check of console and  system cabinets 

Visual Checks for damage 





A‐Control of relay panel / cubicle control  station / junction box 





A‐ Control of relay panel / cubicle control  station / junction box hazardous area  equipment, Ex) Type Enclosures 

Layout drawing note 3 





A‐Equipment earth inspection 

Layout drawing and specs note 3 

Check for correct tag no 





4  5  6 

As per specifications  note 3  Control panel/ Racks/ Junction box installed correctly  and fully complied to Project Specifications  As per installation details Holding down  Vendor Drawings  clamp tightened Air conditioning operational Check all electrical connection to grounding system  correctly installed and clean earth is bounded to      the specified network 

As per vendor instructions 

Confirm spare cores are terminated and screens are  earthed as per approved drawing  Check  Pneumatic  /  Hydraulic  lines  are installed  correctly as applicable 

As per specification Wiring details 

Termination Detail 



W/S 

As per vendor information Applicable  Specifications 

Vendor details 





Check final installations for acceptance 

Release for pre‐commissioning 



W/S 

As per installation details 

Layout drawing

A‐Control of relay panel / cubicle control  station / junction box    A‐Control of relay panel / cubicle control  station / junction box 

Vendor data sheet     Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and dated here  below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review             

   

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets 

71 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Installation of Instrument Panels, Consoles & Desks  Unit No  No.   

Contract No : 

Work Pack No  Test/Inspection Requirements 

Activity Description   

Contractor 

 

Reference Document   

  1 of 1 

SYSTEM No  Inspection and Acceptance  Responsibility(Note 2)  Contractor 

ITR ‐ Report or Document: 

Company 

(Note 1) 

 



Control room inspected prior to installation 

Visual 

note 3 





A‐cabinet & panels inspection 



Pre‐installation equipment checked for any  damages 

Visual 

note 3 





A‐cabinet & panels inspection 

  3 

Check all electrical connection to grounding  system. 

Visual 

note 3 





A‐cabinet & panels inspection 



Interconnecting wiring completed 

Visual 

Wiring Diagram 





A‐cabinet & panels inspection 



Check fuses, protection devices, switches and  indicating lamps 

Visual 

note 3 





A‐cabinet & panels inspection 



Check installation is rigid and secure 

Visual 

note 3 



W/S 

A‐cabinet & panels inspection 

Visual 

note 3  Detailed drawings 

H/W 



A‐cabinet & panels inspection 



Check orientation and alignment of equipment 

 

 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are include in Mechanical Completion.  Note 2:   Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis”  

  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification 

252100DBQA00007

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets 

72 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Installation of Fiber Optic Cables  Unit No   

Contract No : 

Work Pack No   

  No. 

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

  1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

ITR ‐ Report or Document: (Note 1) 

Company 

 

1  2 

Cable drums inspected for external damage 

Visual 

NOTE 3 





 

Cables tested on drum prior to installation 

Test 

NOTE 3 



W/R 

 

Visual 

NOTE 3  Detail drawing 





NOTE 3 





Test 

NOTE 3  Vendor document



W/R 

(OTDR Test)   

 



Trench, depth, layout and soft sand bedding  inspected prior to cable pulling 



Cable   laying   correct,   marking   installed, segregation  Visual  correct 

 

 



OTDR test of the cable after laying carried out. 



First layer backfill and cable tiles/warning tape placed. 

Visual 

NOTE 3 







OTDR test of cable after backfill 

Test 

NOTE 3 



W/R 



Insertion loss measurement carried out 

Visual 

NOTE 3 



W/R 



Field cable installation checked 

Visual 

NOTE 3 





A‐cable installation inspection 

10 

Confirm   transits   and   cable   tray/ladder installation  

Visual 

NOTE 3  Vendor document 





A‐cable installation inspection 

Visual 

NOTE 3 





Visual 

NOTE 3  Vendor document 





Visual 

NOTE 3 





 

 

is correct  11 

Confirm  that  pulling  tension  is  as  per specification 

12 

Check that EMS installed where required 

13 

Cable route marker installation, with installation of 

 

   

B‐Reflect graphs    B‐Reflect graphs  B‐Reflect graphs 

 

warningly tape before backfill for buried cables.  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion. 

 

Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes. 

 

   Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

73 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Installation of Fire & Gas Detection System  Unit No 

Contract No : 

No. 

Work Pack No 

Contractor 

Test/Inspection Requirements 

Activity Description 

Reference Document 

  1 of 1 

SYSTEM No  Inspection and Acceptance  Responsibility(Note 2)  Contractor 

ITR ‐ Report or Document:  (Note 1) 

Company 

 



Equipment checked for any damages 

Visual 

NOTE 3

S

S



Support fabrication and Installation correct 

Visual 

NOTE 3 





A‐cabinet & panels inspection 

Data Sheets 

 

 

A‐cabinet & panels inspection hazardous area  equipment 



Detectors / Manual Call Points Tag No. and 

Visual 

type checked against area classification and IP 

NOTE 3 



W/S 

Visual 

NOTE 3 



W/S 



Confirm all equipment  installations if  they are  correct and complied with Project Specifications  Visual and audible alarm installation correct 

Visual 

NOTE 3 



W/S 



Sunshade installed where applicable 

Visual 

NOTE 3

S

S



Check cable glanding and termination 

Visual 

NOTE 3 



W/S 

A‐LV power and control cables 



Check IP washer and earthling tag installation 

Visual 

NOTE 3 



W/S 

 



Confirm spare cores are terminated and screens  are earthed as per approved drawing 

Visual 

NOTE 3 





 

10 

Confirm earthling of equipment is correct 

Visual/ Testing 

NOTE 3 



W/S 

11 

Confirm cables have been tested 

Visual 

NOTE 3

S/R

S/R

12 

Loop Check 

Test 

Procedure

W

W/R

13 

Function test 

Test 

Procedure

W

W/R



A‐hazardous area equipment Ex. Type  Enclosures cabinet & panels inspection  A‐hazardous area equipment Ex. Type  Enclosures cabinet & panels inspection  A‐cabinet & panels inspection

A‐equipment earth inspection 

     Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

   

Company Logo and business name  

Company Identification 

252100DBQA00007

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets 

74 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Calibration of Instruments  Unit No   

Contract No : 

No. 

Work Pack No   

 

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

SYSTEM No  Inspection and Acceptance  Responsibility(Note 2)  Contractor 



 

Instrument inspected for external damage. 

 



  3 

 

Check    instrument   certification   and    tag  number 

Company 

Visual 

note 4 





Visual 

Data Sheets  P&ID 





note 4  Data Sheets 



S/R 

 

Check calibration of instrument, operation and range    Test  setting according to process data 

  1 of 1 

ITR ‐ Report or Document: (Note 1)   

  B‐inspection & calibration  B‐valve & ancillaries  B‐orifice plate inspection  B‐instruments calibration report  B‐inspection & calibration  B‐valve & ancillaries  B‐orifice plate inspection  B‐instruments calibration report 



Check calibration test certificate and labeling 

Visual 

Test Certificates (Note 3) 



S/R 

 

     Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

   

Company Logo and business name  

Company Identification 

252100DBQA00007

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets 

75 of 120 

     

  Page 

INSPECTION AND TEST PLAN 

Instrument Loop Continuity Check  Unit No   

Contract No : 

  No. 

2   



Contractor   

Test/Inspection Requirements 

Activity Description 

1   



Work Pack No   

Reference Document 

   1 of 1 

SYSTEM No 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

Company 

ITR ‐ Report or Document: (Note 1)   

Loop components installation completion check 

Test 

note 3 

W/R 

W/S 

A‐Inspection   &   test   report   for   loop  checks 

Termination and core identification correct 

Visual 

note 3   



W/R 

A‐Inspection   &   test   report   for   loop  checks 

Instrument Loop Continuity check 

  Test 

note 3 



W/R 

A‐Inspection & test report for loop  checks 

  Test 

Procedure 



W/R 

 

 

Instrument control function test 

     

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually  signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Specifications and/or International Codes as applicable Hierarchy of documents in accordance with project design basis  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review                 

   

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

76 of 120 

    INSPECTION AND TEST PLAN 

 

Page 1 of 1 

Actuated Valves (control valves, on/off valves) - Installation  Unit No 

Contract No: 

No. 

Work Pack No 

Contractor

Activity Description 

Test/Inspection  Requirements 

Reference Document 

Inspection and Acceptance  Responsibility (2)  Contractor  Company 

SYSTEM No ITR ‐ Report or Document: (Note 1) 



Documents Review 

 

1.1 

Review of Installation Drawings, Vendor's Manual,  Technical Documents & Vendor's Inspection  

Document Review 

Drawing, certificates & Vendor Manual 





A‐Installation report 

1.2 

Material and Test certificates for body, trim, seat,  plug, disc or ball, bolting, gasket/packing & actuator 

Document Review 

Drawing, certificates & Vendor Manual 





(B) Material Certificate 



Material Receipt 

 

  

2.1 

Check Equipment Tag Number Identification 

Visual/Document Review 

Packing Lists 

2.2 

Check Incoming Material 

Visual/Specifications 

Packing Lists & Material certificates 



Check of Non- Destructive Examination  

 

  

3.1 

Pressure test of body  

Visual/Test 

Project Procedures 

H/R 

W/R 

3.2 

Pneumatic test 

Visual/Test 

Project Procedures 

H/R 

W/R 

A‐Pressure Test Report 

3.3 

Seat leakage test 

Visual/Test 

Project Procedures 

H/R 

W/R 

3.4 

Calibration test 

Visual/Test 

H/R 

S/R 

3.5 

Performance/function test 

Visual/Test 





A‐ Pre‐commissioning Check List 

3.6 

Stroke test 

Visual/Test 

Test Certificates (Note 3)  Vendor Manual  Data Sheet  Project Standards (see Note 3)  Project Procedures 

A‐Pressure Test Report  Visual/Test 

H/R 

W/R 

 

3.7  3.8  3.9 

Air failure test  Linearity check and stabilization time and hysteresis  Insulation resistance test 

Visual/Test  Visual/Test  Visual/Test 

Project Procedures  Project Procedures  Project Procedures 

H/R  H/R  H/R 

W/R  W/R  W/R 

A‐Pressure Test Report     

3.10 

Final visual / Dimension Inspection 

Visual/Document Review  inspection and testing records 

Applicable Drawings 

H/R 

W/R 

Mechanical Completion Dossier 

 

 

 

 

 

 





H/R 

W/R 

 

 

A‐Installation report  (B) Material Certificate    A‐Pressure Test Report 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.  Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and  dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

       

Company Logo and business name  

Company Identification 

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

77 of 120 

     

Unit No 

INSPECTION AND TEST PLAN  Water Analyzer- Installation  Contract No: 

No. 

Work Pack No 

Activity Description 

Page  1 of 1 

Contractor 

Test/Inspection Requirements

SYSTEM No 

Reference Document

Inspection and Acceptance  Responsibility (2)  Contractor 



Documents Review 

 

Review of Installation Drawings, Vendor's Manual, Technical  Documents & Vendor's Inspection  

Document Review 

Drawing, certificates & Vendor  Manual 

Material Receipt 

 

  

2.1 

Check Equipment Tag Number Identification 

Visual/Document Review 

Packing Lists 

2.2 

Check Incoming Material 

Visual/Specifications 

Packing Lists & Material certificates 

Check of Non- Destructive Examination  

 

  

3.1 

Checking of Analyzer characteristics including Inlet and outlet  connection of the water sample 

Visual and Project Drawings 

Vendor Manuals and Drawings 

3.2 

Pressure test, if applicable 

Visual/Test 

3.3 

Pneumatic test 

1.1  2 



3.4 

Performance test including function test 

3.5 

Final visual / Dimension Inspection 



 

Check calibration test certificate and labeling 

Company   

W   

  S 

 

(B) Material Certificate   





H/R 

W/R 

 

ITR ‐ Report or Document: (Note 1) 

 

A‐Installation report  (B) Material Certificate    A‐  Mechanical  Construction  Check  List (Specific for the equipment) 





Project Procedures 

H/R 

W/R 

A‐Pressure Test Report 

Visual/Test 

Project Procedures 

H/R 

W/R 

A‐Pressure Test Report 

Visual/Test 

Vendor Manual Data Sheet  Project Standards (see Note 3) 





A‐ Pre‐commissioning Check List 

Visual/Document Review inspection and  testing records 

Applicable Drawings 

H/R 

W/R 

Mechanical Completion Dossier 

Visual/Test 

Test Certificates (Note 3) 

H/R 

S/R 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off  and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review           

   

Company Logo and business name  

Company Identification 

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

78 of 120 

      Unit No  No. 

Contract No: 

INSPECTION AND TEST PLAN  Field Instruments - Installation  Work Pack No 

Activity Description 

Page 1 of 1 

Contractor  Test/Inspection  Requirements 

Reference Document

Inspection and Acceptance Responsibility  (2) Contractor  Company 

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Instrument type and class per P&ID and specification (data  sheets) 

As for P&ID Visual Inspection 

Project Standards (see Note 3)  Drawing & Vendor Manual  





A‐Installation report  C‐Installation Check List 



Instrument checked for any damage 

Visual Inspection 

Project Standards (see Note 3) 





A‐Installation report 



Instrument tag(s) installed and correct 

As for P&ID Visual Inspection 

Project Standards (see Note 3)  Drawing & Vendor Manual  





A‐Installation report  C‐Installation Check List 



Installation of sensor complete and correct 

Visual Inspection 

Drawing & Vendor Manual  





C‐Installation Check List 



Block and drain valves ; check position, elevation, direction  and orientation 

Visual Inspection 

Drawing & Vendor Manual 







Pneumatic / hydraulic tubing leak tested 

Visual/Test 

Project Procedures 

H/R 

W/R 



Heat tracing / insulation / instrument housing 

Visual/Test



W



Impulse lines pressure tested 

Visual/Test 

Vendor Manual Data Sheet  Project Procedures 

H/R 

W/R 



Wiring correct;   check cable proper installation with loop,   check gland to be tighten and earth connection. 

Visual Inspection





10 

Drawings marked up as‐built 





A‐Installation Check List 

11 

HMI Graphic symbol and tag correct 

Visual / Review of As‐ Built  Visual Inspection

Project Standards (see Note 3)





C‐Installation Check List 

12 

check if required for canopy or supports when required. 

Visual Inspection

Project Standards (see Note 3)





C‐Installation Check List 



Drawing & Project Standards (see  Note 3)  As‐Built Drawings

C‐Installation Check List  A‐Pressure Test Report  A‐ Pre‐commissioning Check List  A‐Pressure Test Report  C‐Installation Check List 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and  dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

       

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

79 of 120 

       

INSPECTION AND TEST PLAN 

Page 1 of 1 

Installation of PAGA  System  Unit No 

Contract No: 

No. 

Work Pack No  Activity Description 



Equipment checked for any damages 



Support fabrication and Installation correct  

  3    4 

Contractor 

Speakers  Tag  No.  and type checked against area  classification and IP rating (indoor/outdoor)  Confirm all equipment   installations  if   they are correct and  complied with Project Specifications 

Test/Inspection  Requirements 

Reference Document

Visual

NOTE 3

Visual

NOTE 3

  Visual 

Data Sheets  NOTE 3  Vendor Documents 

Visual  Visual 

Inspection and Acceptance Responsibility  (2) Contractor  Company  S 

S

S   

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

S  



W/S 

NOTE 3 



W/S 

NOTE 3



W/S

A‐cabinet & panels inspection  A‐cabinet & panels inspection hazardous area equipment  A‐ Ex. Type Enclosures  A‐hazardous area equipment Ex. Type Enclosures cabinet &  panels inspection 



Visual and audible alarm installation correct elevation,  location as per design.  



Sunshade installed where applicable 

Visual

NOTE 3



S

A‐cabinet & panels inspection 



Check cable glanding and termination ,Junction Boxes. 

Visual

NOTE 3



W/S

A‐LV power and control cables 



Check IP washer and earthling tag installation 

Visual

NOTE 3



W/S

 



Confirm spare cores are terminated and screens are earthed  as per approved drawing 

Visual 

NOTE 3 





 

10 

Confirm earthling of equipment is correct 

Visual/ Testing

NOTE 3



W/S

A‐equipment earth inspection 

11 

Confirm cables have been tested 

Visual

NOTE 3

S/R 

S/R

 

Loop Check 

Test

Procedure



W/R

 

Function test 

Test

Procedure



W/R

 

12  13 

A‐hazardous area equipment Ex. Type Enclosures cabinet &  panels inspection 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and  dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

       

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

80 of 120 

      Unit No 

Contract No: 

No. 



INSPECTION AND TEST PLAN  Telecommunication and Security Systems - Installation  Work Pack No 

Page  1 of 2 

Contractor 

Activity Description 

Test/Inspection  Requirements 

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Reference Document

Documents Review 

Inspection and Acceptance  Responsibility (2)  Contractor 

Company 

 

1.1 

Review of Installation Drawings, Vendor's Manual & Technical  Documents 

Document Review

Drawing & Vendor Manual

W

S

A‐Installation report 

1.2 

Installation of Equipment Method Statement Review & Approval 

Visual/Document Review

Project Standards (see Note 3)   Drawing & Vendor Manual 

W

S

A‐Installation report  (B) Material Certificate 

Material Receipt 

 

  

2.1 



Check Equipment Tag Number Identification 

Visual/Document Review 

Packing Lists 

2.2 

Check Incoming Material 

Visual/Specifications

2.3 

Material Certificates received for all components 

Visual/Document Review 

3  3.1 

3.2 

      Visual Inspection 

Install Cable Pathways:   Type of cable tray, conduits, ladders, junction boxes & fittings  are to meet area classification requirements and specification.   Installation of cable tray (routing and elevation) is as per the  drawings 

      Visual Inspection 

 

 





Material Test Reports

H/R

W/R

(B) Material Certificate 

Packing Lists & Material certificates 

H/R 

W/R 

(B) Material Certificate 

 

 

Installation Activities  Install Communications Equipment (Rack):    Prepare room/area for installation of data, communications and  security equipment   Installation of data, communications rack as per construction  drawings   Fixing and alignment of data/ communications rack   Earthing and bonding of equipment   Final inspections of installation, per room/area. 

 

      Project Standards (see Note 3)   Drawing & Vendor Manual  Method Statement 





  Project Standards (see Note 3)   Method Statement & Equipment  Drawing  H 



A‐Installation report 

          A‐Installation report  C‐Installation Check List 

        A‐Installation report  C‐Installation Check List 

   

Company Logo and business name  

Company Identification 

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets 

81 of 120 

      Unit No 

Contract No: 

INSPECTION AND TEST PLAN  Telecommunication and Security Systems - Installation  Work Pack No 

No. 

Activity Description 

3.3 

Install & Terminate Communications Cables:   Check cable type, size & tag No.    check cable not damaged or snagged before and during cable  pulling.   Check cable segregation and separations requirement are as per the drawings and Specification   Check CAT6A F/UTP and fiber optical cable‐bending radius as per  specification    Complete cable fiber optical terminations.   Check mechanical protection is installed to both ends.   Check the cable separation as per drawing and specification   Check clearance as per drawings and specification    Ensuring installation of PA/GA, security cable (2 core, 4 core and 6  core) and MATV cable is undamaged, has correct support and  segregation.    Carry out Site Acceptance test for all cable types and components  as per required drawing and specification 

3.4 

Completion and Handover / Delivery:   Final visual inspection   Ensure the tests under Specification ‐ Structured Cabling and  Equipment Rooms for CAT6A F/UTP, Fiber optic and PA/GA cables  are all performed, complete and recorded accordingly.   Completion and handover/delivery of relevant QA documentation. 

Page  2 of 2 

Contractor Test/Inspection  Requirements 

      Visual Inspection 

    Visual/Document Review  inspection and testing  records 

Reference Document 

    Project Standards (see Note 3)   Method Statement & Equipment  Drawing 

    Project documents  Applicable Drawings 

Inspection and Acceptance  Responsibility (2)  Contractor

Company

        H 

        W 

    H/R 

    W/R 

SYSTEM No ITR ‐ Report or Document: (Note 1) 

        A‐Installation report  C‐Installation Check List 

    Mechanical Completion Dossier 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.  Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees & eventually signed off and  dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.  Note 3: Project Standards and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”.  Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

 

   

  Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

82 of 120 

 

  Appendix 7:   Pipelines Works  

    a) b)      

Pipelines Installation  Cleaning, Gauging, Hydro‐testing, Dewatering, Drying & Purging of Pipeline 

 

   

  Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

83 of 120 

 

 

INSPECTION AND TEST PLAN  Pipelines Installation 

   

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering, Holiday  Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation Work Pack No  Contractor 

 

 

Unit No  No. 

Test/Inspection Requirements 

Activity Description 

Reference Document 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

Company 

H/R 

S/R 

Material Acceptance - Control - Preparation 

1   

Contract No : 

Page 1 of 7 

Pipe and bends conforms to specification 

As  per  applicable  pipeline  material  list  and specification 

Mill Certificates, Manufacturer Material  Certificate and other as applicable 

1.2 

Pipe and bends marking 

Check   marking   for   correspondence   with material certificate 

Material Certificate 





C‐Check List 

1.3 

Material rating and dimensions (diameter /  thickness 

Check dimensions 

Isometric   material list   and  piping  specification 





C‐Check List 

1.4 

Transfer of markings (if applicable) 

Correct Markings 

Project Procedure 

S/R 



C‐Check List 

1.5 

Cutting and re‐beveling (as applicable) 

Correct   cutting,   cleaning   and    testing procedure 

Project Procedure 



S

1.6 

Long radius bend ‐ Cold bending 

procedure

Project Procedure

S

S

C‐Check List C‐Check List

1.1 

1.7   

 

Offloading and handling utilizing correct lifting 

Visual 

Project Procedure 



S

Visual 

Project Procedure 





 

1.8 

Storing as per storing plan.  Number of maximum row  Sawdust bags or wood timber 



ROW and Trenching 

2.1 

ROW and Trench bench marked by Surveyor 

Review of Survey Report  Review of Surveyed route as staked 

Latest revision of applicable  Drawings 





Top soil  stripping to  the  specified  depth and  ROW  width and level 

Visual    for    depth    and    absence    of mineral soil  Review of survey 

Applicable Drawings  Local Regulations 





Top soil and excavated material stored in  designated areas, as applicable 

Visual   for   absence   of   mineral   soil 

Applicable Drawings  Local Regulations 



S

Excavated  trench  is  to  the  required  dimensions  /  shape and trench bottom free from debris.  Rocks to be excavated. 

Visual inspection  Review of survey 

Applicable Drawings (Typical drawings for  R.O.W. and trench) 





  2.2 

2.3    2.4 

B‐MTCs 

C‐Check List 

  C‐Check List Closed Out 

B‐Survey report    C‐Check List 

C‐Check List    C‐Check List 

 

   

  Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

84 of 120 

 

 

INSPECTION AND TEST PLAN  Pipelines Installation 

 

     Page  2 of 7 

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering, Holiday  Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation  Unit No  No. 

Contract No :  Activity Description 

Work Pack No  Test/Inspection Requirements 

Contractor  Reference Document 

Contractor    2.4   

Bedding  material  suitable  and  placed  as  per  Visual Inspection  Bedding  material  free  from  sharp  requirements  objects, debris, etc.  Trench released for installation of pipelines 

Visual 

2.5  3        3.1 

 

Stringing  Stringing of pipeline pipes and bends as per  approved stringing plan  Positioning pipes and bends at correct level  from ground (sawdust bags or wood timber)  and distance from trench border) 

Visual  Correct  pipe  handling  and  protection  from debris.  No rolling, dropping, dragging of pipes. 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(2)  Company 

Latest revision of applicable Drawings  Project Standards (see Note 3) 





Latest revision of applicable Drawings  Project Standards (see Note 3) 







    S 

Stringing Plan 





  Project Standards (see Note 3)  Project Procedures  Stringing Plan 

   

Inspection of stringed pipes and bends  3.2 

  3.3 

Visual for correct dimension  (diameter/thickness) and end protection.  Any additional requirements for crossings (road,    river, railways, OH lines, pipelines, others).  See  dedicated ITPs 



Preparatory works 

4.1 

Re‐bevel, when necessary ‐ beveling machine 

Visual 

Project Standards (see Note 3) Project  Procedures 





4.2 

Check bevel visually 

Visual 

Project Standards (see Note 3) Project  Procedures 





4.3 

Visual, MPI, check of bevel 

Visual 

Project Standards (see Note 3) Project  Procedures 

S/R 

S/R 

4.4 

Lamination  check    if    pipe    end    cut(dimensions to   be specified) 

UT testing 

Project Standards (see Note 3) Project  Procedures 

S/R 

S

4.5 

Cleaning (swabbing) 

Visual 

Project Standards (see Note 3) Project  Procedures 





  C‐Check List 

C‐Check List Closed Out 

    C‐Check List 

  C‐Check List 

A‐Inspection Report  A‐Inspection Report  C‐Check List 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

85 of 120 

INSPECTION AND TEST PLAN  Pipelines Installation 

 

     Page  3 of 7 

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering, Holiday  Unit No    No. 

Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation  Contractor Work Pack No  Inspection and Acceptance  Test/Inspection Requirements  Reference Document  Responsibility(2) 

Contract No :  Activity Description 

Contractor  Stringing 

4.6  5 

SYSTEM No ITR ‐ Report or Document: (Note 1) 

Company 

Visual   Record on Pipe Book 

Project Standards (see Note 3)   Project Procedures 





A‐Pipe Book  C‐Check List Closed Out 

 Welding 

5.1 

Fit‐up of pipes for welding 

Compliance with WPS 

Project Standards (see Note 3)   WPS 





5.2 

WPS applicability 

WPS & Welding Book Review 

Project Standards (see Note 3)   Project Procedures 

H/R 



B‐WPS  A‐Pipe Book 

5.3 

Welders qualifications 

Qualifications and List review 

Project Standards (see Note 3)   Project Procedures 

H/R 



B‐Welders Qualifications and List  A‐Pipe Book 

5.4 

Welding Consumables Control 

Visual  Review of consumable records 

Project Standards (see Note 3)   Project Procedures 





C‐Consumable control log  B‐Consumable Certificate 

5.5 

Pre‐heat of joint 

Visual  Temperature check 

Project Procedures WPS 





A‐Pipe Book 

5.6 

Cartridge control, for automatic welding as  well as parameter checking 

Visual  Welding Machine 

Project Procedures  WPS 

W/R 

S/R 

5.7 

Welding 

Correct sequence Welding parameters 

Project Procedures WPS 





5.8 

Visual joint inspection 

Visual 

Project Standards (see Note 3)  Project Procedures & WPS 



S/R 

     

  In case of project specific additional essential  variables or requirements a separate ITP shall be  prepared and referred to or an additional  inspection line item shall be added 

5.9 

C‐Welding Machine Print out  A‐Pipe Book  A‐Pipe Book  A‐Inspection report 

    Project Standards (see Note 3) 

 e.g. : automated welding process, internal line‐ 6 

 Non-Destructive Testing 

6.1   

NDT procedures appropriately approved and  qualified 

Review of the applicable NDT  Procedures 

Project Procedure NDT Procedures 





B‐NDT Procedure List 

Check NDT operators are qualified 

Review of the NDT operators certificates  and validity 

NDT    operators    Qualification    List    and  Certifications Project Procedure 





B‐NDT Operators List  B‐NDT Operators Certification 

  6.2 

 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

86 of 120 

INSPECTION AND TEST PLAN 

     Page 4 0f 7 

Pipelines Installation 

 

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering, Holiday  Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation  Unit No   

Contract No : 

No. 

Work Pack No   

  Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

Contractor   

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(Note 2)  Company 

Check NDT equipment and consumables 

Review   of   documents,   calibration    and conformity certificates, labels 

NDT Project Procedures  Applicable codes 





B‐List of NDT Equipment 

Visual Inspection 

Inspection and reporting 

NDT Project Procedure 



S/R 

B‐Calibration Certificates  A‐Inspection report A‐Pipe Book

6.5 

R.T/U.T/P.T/M.T, as applicable and results  acceptable 

Witness NDT execution (done  by  NDT  company) and/or Review of NDT reports  NDT Project Procedure  for weld acceptance 

W/R 

W/R 

A‐NDT Test Reports 

6.6 

Weld repairs completed in a satisfactory manner.    See point 5 





H/R 

W/R 

S/R 

S/R 

6.3  6.4   

 

 

R.T/U.T/P.T/M.T,  after  weld  repair  as  applicable  Witness NDT execution (done  by  NDT  company) and/or Review of NDT reports  NDT Project Procedure  and results acceptable  for weld acceptance  In case of project specific requirements or non‐       conventional NDT method/techniques a separate  Project Standards (see Note 3)  ITP shall be prepared and referred to 

6.7      6.8 



A‐Pipe Book    A‐NDT Test Reports 

e.g. : UT phased array, TOFD, automated system,  di i l di h d f i i f C d  Joint Coating 

 

Blast‐cleaning  or  other  approved  cleaning  method  (e.g. wire brush) 

Anchor Pattern  Free from dust and oil 

Project Standards (see Note 3)  Project Procedures  Manufacturer datasheet 

Field Joint (coat and sleeve or wrap) application 

Visual 

Project Procedures  Manufacturer datasheet 





A‐Field Joint Coating Report  A‐Joint Coating Log 

7.3 

Field Joint Coating thickness and overlap check 

Thickness on weld bead and on pipe  wall. Overlap on pipe coating 

Project Standards (see Note 3)  Project Procedures  Manufacturer datasheet 





A‐Field Joint Coating Report  A‐Joint Coating Log 

7.4 

Holiday Detection on sleeves 

No  holidays  and  all  holidays  repaired  and retested 

Project Procedures  Manufacturer datasheet 

W/R 



A‐Holiday Test Report 

7.1 

7.2   

 

  C‐Check List 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

87 of 120 

INSPECTION AND TEST PLAN  Pipelines Installation 

 

     Page 5 of 7 

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering,  Holiday Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation   

Unit No    No. 

Contract No : 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

Company 



 Release for lowering 

8.1 

Holiday Detection on Pipeline Coating  Coating Repairs if applicable 

No  holidays  and  all  holidays  repaired  and retested 

Project Procedures  Coat Repair Manufacturer instructions 

W/R 

W/R 

A‐Inspection Report 

8.2 

Pipeline section released for lowering‐in 

Review of interim pipe book and  inspection reports for completeness 

Project Standards (see Note 3)  Project Procedures 

H/R 

H/R 

A‐Check List ‐ Closed out  A‐Pipe Book 



Lowering 

9.1 

Lowering  equipment  (side‐boom  and  lifting  loose gears ‐ roll cradle‐canvass belt) 

Correct type, size, positioning, number 

Method Statement 





9.2 

Holiday  Detection  during  lowering‐in  (pipe  bottom section) 

No  holidays  and  all  holidays  repaired  and retested 

Project Procedures  Coat Repair Manufacturer instructions 

W/R 

W/R 

Trench and Bedding as completed and released.     No deterioration occurred (e.g. debris, rocks,  Visual Inspection  stones, water, collapse) 

  9.3      9.4 

Lowering execution in accordance with  approved method statement and scheme:  ‐ Lowered section length  ‐ Distance between side booms  ‐ Control of S‐curve and maximum sagging  ‐ Correct positioning at trench bottom  ‐ Distance from trench edges  ‐ Radius of curvature at long radius bend 

9.5 

Lowering and laying at crossings (road, river,  railways, OH lines, pipelines, others). See 

 

   

    9.6 

   

  Project Standards (see Note 3) 

  Visual 

Visual 

  S 

   

   

Visual  Release for lowering complete 

 

Method statement and scheme  Applicable Drawings 

Method statement and scheme Applicable Drawings  Project Standards (see Note 3)  Project Procedure  Applicable Drawings 

A‐Holiday Test Report   

S     

 

C‐Check List 

  S 



S

S

S

S

C‐Check List        C‐Check List 

C‐Check List A‐Check List ‐ Closed Out  A‐Survey Report  A‐Pipe Book Released  A‐Test Pack 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

88 of 120 

INSPECTION AND TEST PLAN  Pipelines Installation 

 

    Page  6 of 7 

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering,  Holiday Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation   

Unit No    No. 

Contract No : 

Work Pack No   

Contractor   

Test/Inspection Requirements 

Activity Description 

Reference Document 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

10 

Backfilling 

10.1 

Confirm pipeline has been   released for backfill  and compaction 

Check ITP  phases up  to  17.6 are closed,  Mechanical Completion Procedure  signed   off and Mechanical Completion 

10.2 

Bedding  material  available and suitable  Placed  with correct layer thickness 

Visual  Documents review 

Backfilling  material  suitable  (mineral  soil and  top soil from ROW excavation)  Any additional material is approved  Backfill material placed  and  compacted as per  requirement, above initial backfill for pipeline and  for any cables, conduit etc.  Verify compaction test results are conformant 

Visual inspection  Document review 

10.5 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Company 





W/R 

W/R 

Imported fill materials for underground services 





C‐Check List  B‐Material Certificate 

Fill layers’ thickness  Compaction rate 

Imported   Fill   materials   for   Underground  Services Specification  

  W 

  S/R 

  A‐Compaction Reports 

Warning tapes etc. to be available and placed 

Visual and dimensional 

Project Standards (see Note 3) 

 

 

10.6 

Backfilling    and   compaction    operations  complete    and conformant 

Visual 

Project Standards (see Note 3)   Project Procedure 



H/R 

11 

Flushing, Pressure Testing, Dewatering 

11.1 

See dedicated ITPs 

 

 

12 

Installation of  valves, fittings,  cathodic protection, signalization systems and other parts or utilities

  10.3    10.4 

12.1 

See dedicated ITPs. 

13 

Mechanical Completion 

13.1 

Mechanical completion dossier completion and  approval  See Mechanical Completion Procedure 

Project Procedure 

 

 

Documents completeness 

Project Procedures 

 

 

 

 





C‐Check List

A‐Backfilling report and release 

A‐Test Pack completed

Mechanical Completion Dossier 

 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

89 of 120 

INSPECTION AND TEST PLAN  Pipelines Installation 

 

    Page 7 of 7 

ROW & Top Soil Stripping, Trench Excavation, Material Acceptance, Stringing, Welding, NDT, Joint Coating, Lowering,  Holiday Testing, Pressure Testing, Mechanical Completion, Reinstatement & Re‐cultivation 

 

Unit No    No. 

Contract No : 

Work Pack No   

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

Inspection and  Acceptance  R ibili (N 2) Contractor  Company 

SYSTEM No  ITR ‐ Report or  Document:  (N t 1)

 

14   Reinstatement and Recultivation  14.1 

Reinstatement of ROW and any affected areas 

Visual and dimensional Review of  documents 

Project Standards (see Note 3) Applicable  Drawings 

14.2 

Recultivation 

Visual and dimensional 

Project Standards (see Note 3)    Local 





W/R 

W/R 



H/R 

A‐Reinstatement Report A‐ Survey  A‐Recultivation Report 

15   Final Mechanical Completion  15.1 

Mechanical Completion Dossier 

Review of documents 

Mechanical Completion Procedure 

Mechanical Completion Dossier 

  Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees  & eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.    Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis”    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

                             

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

90 of 120 

 

 

INSPECTION AND TEST PLAN 

   

Cleaning, Gauging, Hydro testing, Dewatering, Drying 

Page    1 of 2 

& Purging of Pipeline  Unit No   

Contract No :   

  No. 

Work Pack No  Test/Inspection Requirements 

Activity Description 

Contractor   

SYSTEM No  ITR ‐ Report or Document:   (Note 1) 

Inspection and Acceptance  Responsibility(Note 2) 

Reference Document 

Contractor 

Company 

 



Cleaning and Gauging 

1.1 

Installation  of  pipeline  section  complete  and  conformant.  Review of Pipe Book and Test Pack 

1.2  1.3 

Water source identified and approved  Temporary test head connection checked  Correct type and number of pigs are used  Gauging plate inspected visual and  dimensional  Pipeline test section released for cleaning. 

1.4 

 

1.5 

Project Standards (see Note 3) Project  Procedures 

H/R 

Review laboratory analysis    Visual & Dimensional  Review of document 

Cleaning of test section satisfactory 

Flushing time respected  Visual volume of debris checked 

Gauging/Pigging of test section complete 

 

H/R   

 

H/R 

W/R 

Project Standards (see Note 3) Project  Procedures 





A‐Pipeline Pig Report  A‐Cleaning and Gauging report 

Visual  Reports  of  gauging  plates  and  dimensional check 

Project Standards (see Note 3) Project  Procedures 





A‐Cleaning and Gauging report 

Water analysis certificate Project  Standards (see Note 3) Project  Procedures  Testing Scheme 

Procedures  Testing Scheme 

C‐Check List 

Pressure Test     

     

2.1 

Verify all required instruments are fitted  Valves in the line are in the open position Line  filling complete. 2nd gauge plate if applicable. 

  Testing scheme correct  Pressure  gauge,  thermometers,  charts  calibration certificates  Air content checked  Temperature stabilization period achieved

Verify that all required instruments are fitted at  each pressure reading point. 

Sign on test charts  Controlled rate of pressurization 

Project Standards (see Note 3) Project  Procedures 

 

2.2 

Project Standards (see Note 3) Project  Procedures 

 

 

H/R 

H/R  Project Standards (see Note 3) Project 

 

2       

Review of document 

      H/R 

H/R 

 

      C‐Check List 



C‐Check List  A‐Pressure Test Report 





C‐Check List  A‐Pressure Test Report 



S/R 



Pressurizing activity    2.3 

Hydro testing Operations  Including  pre‐test  or  tests  on  above  ground  items. 

Strength test 4/12/24 hour holds.  No pressure drops. No leaks. 

2.4 

Pressure test complete 

Controlled rate of depressurization sign of  Project Standards (see Note 3) Project  charts  Procedures 

 

C‐Check List  A‐Pressure Test Report and Charts 

  

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

91 of 120 

INSPECTION AND TEST PLAN 

     Page 2 of 2 

Cleaning, Gauging, Hydro testing, Dewatering, Drying  & Purging of Pipeline  Unit No   

Contract No : 

Work Pack No   

  No. 

Activity Description 

Contractor   

Test/Inspection Requirements 

Reference Document 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(Note 2)  Contractor 

Company 

 

Dewatering Drying Purging 



De‐watering Activity  Inspect 2nd  gauge plate where applicable 

Visual  Check dimensions and for damage 

Project Standards (see Note 3) Project  Procedures 

3.2 

Drying 

Verify foam pigs  Compressed Air (humidity and T)  Air at pipeline end 

Project Standards (see Note 3) Project  Procedures 

3.3 

Final drying (If applicable) 

Purge with super‐dry air soak for 24 Hrs   check dew point. 

3.4 

Soak for 24 Hrs and re‐check dew point 

Filling by Nitrogen 

3.1   

 

 

  3.5 

H   

C‐Check List  A‐Dewatering Report 

H   

  H 



A‐Air Drying Log 

Project Standards (see Note 3) Project  Procedures 





A‐Air Drying Report 

Check Dew Point 

Project Standards (see Note 3) Project  Procedures 





A‐Drying Report 

Pipe containing a positive pressure of  dry air and filling by nitrogen 

Project Standards (see Note 3) Project  Procedures 

Review of N certificate 

Nitrogen Certificate 

 

 

  H 



A‐Purging Report 

 

Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2: Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.    Note 3: Project Standards (see Note 3) s and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis.    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review   

           

   

  Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

92 of 120 

         

Appendix 8:   Painting Works  

  a) Painting of Steel Surfaces 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

93 of 120 

 

 

INSPECTION AND TEST PLAN  Painting of Steel Surfaces  Unit No  No. 

Contract No :  Activity Description 

Work Pack No 

   Page  1 of 3  

Contractor 

Test/Inspection Requirements 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Inspection and Acceptance  Responsibility(2) 

Reference Document 

Contractor 

Company 

 



Pre-activity checks 

1.1 

Paint, components and thinner type, brand name,  Review of material certificate  lot  number  and  material  certificate  as  per  Review of paint labels  approved paint cycle 

Project Standards (see Note 3) Project  Procedures 

Blasting  material  (sand,  grit,  slag)  and/or  wire  Review of material certificate  brushing  tools  as  per  approved  paint  cycle  and  Review of material labels  specifications 

Project Standards (see Note 3) Project  Procedures 

Storing  conditions  of  paint  and  blasting  material 

Visual check  Review ambient conditioning records 

Project Standards (see Note 3) Project  Procedures 

Paint shelf life and expiring date / First in‐First  out 

Visual check 

Project Standards (see Note 3) Project  Procedures 

 

  1.2    1.3 

 

 

  H/R 

B‐Material Certificates 

H/R 

Vendor Data Sheet/Recommendation   

 

  H/R 

B‐Material Certificates 

H/R 

Vendor Data Sheet/Recommendation   

  W 



Vendor Data Sheet/Recommendation  1.4 

   

Measuring equipment availability, compliance  with   specification   and   calibration   validity 

1.5 

(thermometer humidity gauge, dew point gauge,  thickness tester rugose meter, press‐o‐test,  surface salt tester, adhesion tester and any other  as applicable) 

Surfaces  clear  of  oil,  grease,  contaminates,  Visual Inspection  sand, dust, cleaned with solvent, brush or air, if  Salt tests  necessary 

2.1 

  2.2 

Visual check for availability and status  Review  of  equipment  datasheet  and  calibration certificates/ labels/ ID 

 

  R 

B‐Material Certificates 

S/R 

Vendor Data Sheet/Recommendation    Project Standards (see Note 3) Project  Procedures 

 

Project Standards (see Note 3) Project  Procedures 

 

 

  H/R 

B‐Measuring Equipment List  B‐Calibration Certificates 

W/R 

Surface preparation 

2   

 

Review of storing records, material  certificate and labels 

 

Ambient conditions 

  S 



Vendor Data Sheet/Recommendation 

Ambient  conditions  (temperature  Project Standards (see Note 3) Project  Procedures  humidity) within specified ranges 

 

 

  S/R 

A‐Surface Preparation Report 



W/R 

A‐Surface Preparation Report  A‐Press‐o‐test strip (if applicable) 







Steel surface T > 00 above dew point    2.3 

2.4 

Blasted/wire brushed surface meets profile  requirements and surface preparation level  (e.g. SA 3)  Area masked appropriately 

One profile measurement per batch  Surface preparation level for each  surface/area 

Project Standards (see Note 3) Project  Procedures 

Masked   to   prevent   overspray   on  uncoated surfaces (e.g. weld bevels) 

Project Procedures 

 

 

Vendor Data Sheet/Recommendation 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007    

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

94 of 120 

INSPECTION AND TEST PLAN 

  Page 2 of 3  

Painting of Steel Surfaces   

Unit No    No. 

Contract No : 

Work Pack No   

Activity Description 

Contractor   

Test/Inspection Requirements 

Inspection and Acceptance  Responsibility(Note 2) 

Reference Document 

Contractor   

 

SYSTEM No  ITR ‐ Report or Document: (Note 1) 

Company 

Paint application (to be repeated for primer, first coat, second/final coat)

3  3.1 

Primer  /Paint  mixed,  agitated,  used  within  specified pot life, correct paint and thinner, etc. 

Visual inspection 

Project Standards (see Note 3)   Project Procedures  Vendor Data Sheet/Recommendation 

3.2 

For  primer  ‐  Surface  preparation  to  correct  level and time after blasting not exceeded 

Visual / Pictorial comparator Check of  time from blast finish 

Project Standards (see Note 3) Project  Procedures 

 



A‐Painting Application Report 



  A‐Painting Application Report 

Vendor Data Sheet/Recommendation   

 

Ambient conditions 

3.3 

Ambient conditions (temperature  humidity) within specified ranges Steel 

Project Standards (see Note 3) Project  Procedures 

 

Project Standards (see Note 3) Project  Procedures 

 

  R 

  S/R 

A‐Painting Application Report 

surface T > 00 above dew point   

For paint ‐ Surface status (clean from dust and  salt) and correct time (min/max) elapsed after 

3.4 

Visual / Salt Test  Curing time 

Primer/paint applied as per specification 

3.5 

Curing time, ambient conditions and protection 

3.6   

    3.7 

Final  paint  acceptable.  Release  for  erection,  insulation testing, as applicable 

Test Panel (if applicable) 

4.1 

Test  panel  preparation  and  painting  as  per  points from 2.1 to 3.7. 

Project Standards (see Note 3) Project  Procedures 

WFT within min/max  DFT within min/max  Adhesion test 

 

Total DFT within min/max of specified  value 

Visual 

 

  H 



A‐Painting Application Report 

  H 

  W 

A‐Painting Application Report 

Vendor Data Sheet/Recommendation 

Visual 

Adhesion test  Area cleaned properly and  protected/covered up as required 



A‐Painting Application Report 

S/R 

Vendor Data Sheet/Recommendation 

previous layer application.   

 

 

  R 

  Project Standards (see Note 3) Project  Procedures  Vendor Data Sheet/Recommendation 

Project Standards (see Note 3) 

 

 

 

 

   



W/R 

A‐Painting Application Report 



W/R 

A‐Test Panel Report 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

95 of 120 

 

 

INSPECTION AND TEST PLAN  Painting of Steel Surfaces  Unit No 

 

Contract No :   

  No. 

Work Pack No 

Activity Description 

Contractor   

Test/Inspection Requirements 

   Page 3 of 3 

Reference Document 

Inspection and Acceptance  Responsibility (Note 2)  Contractor 

SYSTEM No  ITR ‐ Report or Document:  (Note 1) 

Company 

Interim Mechanical Completion 

5  5.1 

Final Acceptance paint document package 

Signature of documents 

Project Standards (see Note 3)  Project Procedures 



H/R 

A‐Paint Package 

5.2 

Test Package to be included in the Mechanical  Completion  package  of  the  relevant  line  or  system. See Mechanical Completion Procedure 

Documents completeness 

Project Procedures 



H/R 

A‐Paint Package 

    Note 1: (A) ITR & As‐Built / (B) Certificate or Report from previous or separate phase (MTC, FAT, Passport, Procedure, Qualification, Calibration Certificates) / (C) Generic Record not attached to ITP.   Documents type (A) and (B) are included in Mechanical Completion.    Note 2:  Case A ‐ ITP is assigned to one specific spool or line. In this case the inspection & acceptance responsibility columns can be initiated & dated for each completed activity by the actual inspection attendees &  eventually signed off and dated here below for completion.  Case B ‐ The ITP is considered a generic check list (not specific for one item) and the activities completion is monitored in the Mechanical Completion by means of indexes and matrixes.    Note 3: Project Standards (see Note 3) and/or International Codes as applicable. Hierarchy of documents to be in accordance with project design basis.    Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R‐ Record Review 

               

 

   

  Company Logo and business name  

Company Identification

252100DBQA00007  

Revision Index 

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

96 of 120 

 

Appendix 9:  Inspection and Test Records (ITR) 

  a) Inspection and Test Record (ITR) for Blinding, concreting, coating foundation and backfilling.    b) Inspection and Test Record (ITR) for Cable Trays/Ladders/Conduit.    c) Inspection and Test Record (ITR) for Concrete Mix.    d) Inspection and Test Record (ITR) for Concrete Pavement.    e) Inspection and Test Record (ITR) for Earthing & Lightning Protection System.    f)

Inspection and Test Record (ITR) for Earth Works. 

  g) Inspection and Test Record (ITR) for External & Internal Building Finishes.    h) Inspection and Test Record (ITR) for HV/LV Cables    i) Inspection and Test Record (ITR) for Pre‐Cast Concrete.    j)

Inspection and Test Record (ITR) for Steel Structures. 

  k) Inspection and Test Record (ITR) for Underground Pipe & Backfill of Underground Service    l)

Inspection and Test Record (ITR) for Generators. 

  m) Inspection and Test Record (ITR) for Installation of Low and High Voltage Motors.    n) Inspection and Test Record (ITR) for Installation of Power Transformer.    o) Inspection and Test Record (ITR) for Installation of Switchgear and Motor Control Centre.    p) Inspection and Test Record (ITR) for Jointing, Glanding and Termination of Power and  Control Cables.    q) Inspection and Test Record (ITR) for Lighting Installation.    r) Inspection and Test Record (ITR) for Pipelines Installation.    s) Inspection and Test Record (ITR) for Installation of Field Instruments    t) Inspection and Test Record (ITR) for Loop‐Check of Field Instruments                   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

97 of 120 

         

Inspection and Test Record (ITR) for Blinding,  concreting, coating foundation and backfilling  CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:    Reference Document: 

                      Record No.: ––––– 

  Contractor\tester

Items to inspect 

Contractor QA/QC Hold  inspected*  Point  initials/date 

inspected  initials/date  1.0 Concrete mix design and qualification    2.0 Blinding Concrete  2.1 Review of Surveyor’s setting out  2.2 Adequate conveying & depositing  2.3 Release for Construction of Concrete  Foundation Visual    3.0 Concreting  3.1 Membrane application  3.2 Check blinding and application of  membrane  3.3 Pre‐Pour inspection of forms, rebar,  embeds etc.  3.4 Concrete receipt & placement inspection  3.5 Verify concrete field test results conforming  to Specifications.  3.6 Concrete curing and protection  3.7 Form striking, surface inspection  3.8 Compressive crush strength test results    4.0 Coating Foundation and backfilling  4.1 Underground Structure released for coating 4.2 Coating applied as specified  4.3 Top of foundation and anchor (bolts and  plates as applicable) dimensional check  4.4 Backfill & Compaction as per requirements    5.0 Mechanical completion and approval. 

 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

 

Remarks 

 

Attachments, No. of pages: 

Tested By Contractor    Name:   

Approved By Contractor QC    Name:   

   Approved By Company    Name:   

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

98 of 120 

   

Record No.: ––––– 

Inspection and Test Record (ITR) for  Cable Trays/Ladders/Conduit  CONTRACTOR:  Location of works:  

COMPANY:   Project No.:   Project Name:   

Additional Information:    Reference Document:  U

U

Contractor\tester

Items to inspect 

Contractor QA/QC 

inspected  initials/date  1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0

9.0

10.0 11.0 12.0

13.0

Specified material used    Location, routing, spacing, width    Vertical runs plumb and parallel    Cut edges painted    Assembly correctly bolted up    Supports, hot‐dip galvanized    Covers on HV cable trays    Tray and ladder runs adequately  supported    Trays, ladders and supports bonded and  earthed    Conduit Support Structure Secure  Conduit Routing clear from heat sources    Conduit Junction Boxes/Pull Boxes  installed where required    13.0 Conduit ends are free from sharp  edges 

 

Remarks 

Hold Inspected  Point initials/date 

 

 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.         Attachments, No. of pages:  h ‐ QA/QC Inspector's presence is mandatory.  Tested By Contractor    Name:   

Approved By Contractor QC    Name:   

   Approved By Company    Name:   

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

99 of 120 

   

 

Inspection and Test Record (ITR) for Concrete Mix 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document:    Contractor\tester

Items to inspect 

Contractor QA/QC 

Inspected  Initials/Date 

 

1.0 Water chemical analysis 

Hold  Point 

 

Remarks 

Inspected  Initials/Date 

 

 

Periodically tests with a portable electrical  conductivity probe calibrated against the  satisfactory supply. Chemical tests shall be  performed if the conductivity exceed the  satisfactory supply    2.0 Cement  Manufacturer’s test certification complies with  approved submittal.    3.0 Aggregates  Test certification for coarse  aggregate Test certification for  fine aggregate Test certification  for sources    4.0 Admixtures (for air entraining, hot or cold  concreting as/if applicable)  Review of datasheet and certificate    5.0 Concrete Mix Design  Review of documents    6.0 Trial Mixes  Mix Qualification    7.0 Crushing Strength Testing (7 and 28  days) Lab Tests    8.0 Tests on the production    Production Review   

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor 

Approved By Contractor QC 

   Approved By Company 

  Name:   

  Name:   

Name: 

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

100 of 120 

   

 

 

Inspection and Test Record (ITR) for Concrete Pavement 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect 

Inspected  Initials/Date 

1.0 All underground services such as piping vents,  drains cables, etc, are complete & conformant.  Authorization in place 

 

 

Contractor QA/QC  Inspected  Hold  Initials/Date  Point 

 

 

Remarks 

 

for base course layer concrete pouring – earthworks  compaction to 95% MDD.  2.0 Check that polyethylene film moisture barrier is  placed on base course to the required specification.  3.0 Pre‐pour inspection of formwork, rebar, embeds,  slope, screeds, joints, etc.  4.0 Concrete receive & placement inspection  5.0 Verify concrete field test results conformant  6.0 Concrete curing, protection, clean up and drainage.  W et curing, minimum 7 days  7.0 Compressive strength test results items conformant 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor    Name:   

Approved By Contractor QC  Name:   

   Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

101 of 120 

   

Inspection and Test Record (ITR) for Earthing & Lightning  Protection System 

  Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect 

Inspected  Initials/Date 

    1.0 Earth Cable and pits located correctly as  per drawings and to specified depth ‐ visual    2.0 Earth conductor size is correct – visual    3.0 Cad weld and connections checked,  joints greased – visual    4.0 Check Earth Bar installed correctly as  location and service where required –  visual    5.0 Underground work Inspection  completed – inspection    6.0 Pit inspection completed – inspection    7.0 Earthing conductor and earthling  element completed –  inspection    8.0 Earth rod and network earth resistance  checked – test 

 

  H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

 

Contractor QA/QC  Inspected  Hold  Initials/Date  Point 

 

Remarks 

 

  Attachments, No. of pages: 

Tested By Contractor    Name:   

Approved By Contractor QC  Name:   

   Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

102 of 120 

 

Inspection and Test Record (ITR) for Earth Works 

  Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect  1.0 Evaluation of In‐Situ Fill Material for  suitability 

 

 

Contractor QA/QC  Hold  Inspected  Point  Initials/Date 

Inspected  Initials/Date 

 

 

Remarks 

 

1.1 Evaluation Tests Liquid & Plastic Limits  Project Specification & Drawings Code,  Standard & Procedures QC Plan  2.0 Earthworks Compaction  2.1 Compaction Tests 95% MDD Project  Specification & Drawings Code, Standard &  Procedures QC Plan  3.0 Surveyor inspection for setting out  3.1 Review of Survey Report Latest revision  of Drawings  4.0 Final visual check & earthwork release  Visual Document review of the inspection  and testing 

  H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

  Attachments, No. of pages: 

Tested By Contractor    Name:   

Approved By Contractor QC  Name:   

   Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

103 of 120 

   

Inspection and Test Record (ITR) for  External & Internal Building Finishes 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:  Reference  Document: 

Contractor\tester Contractor QA/QC   Inspected  Hold  Inspected  Initials/Date Point Initials/Date 

  Items to inspect 

 

Material Acceptance  U

 

 

Remarks 

 

1.0 Material conforms to specification and drawings 

 

External Building Finishes  U

2.0 Inspection of Expansion /Contraction Joints  2.1 Inspection of Roof and W all panels installation for  buildings  (Insulation, Flashing and water repellent)  2.2 Inspection of Built up Roof Covering for Buildings  2.3 Inspection of Painting / Clear Finish for the External of  Buildings  Internal Building Finishes  U

3.0 Concrete pavement – Refer Concrete Paving ITP  3.1 Inspection of Masonry  3.2 Inspection for joints in concrete and Masonry  3.3 Inspection of Plastering  3.4 Inspection of Gypsum drywall partition walls  3.5 Inspection of floor and wall tile installation  3.6 Inspection of painting /clear Finish  3.7 Inspection of window installation  3.8 Inspection of door installation  3.9 Inspection & testing of plumbing works  3.10 Inspection of sanitary fixtures & fittings  3.11 Inspection Record for Cavity/Raised Floor  3.12 Inspection Record for False/Suspended Ceiling  3.13 Inspection of Duct Work Installation and other  components (Supports etc)  3.14 Inspection of Insulation  3.15 Installation of HVAC equipment and Control Cables  3.16 Installation of Air Terminal Devices (Grilles, Diffusers)  3.17 Punch list items to be prepared  Mechanical Completion  U

4.0 As Built drawings preparation  4.1 Mechanical completion dossier completion and  approval. See Mechanical Completion Procedure.   

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Tested By Contractor    Name:   

Name:   

Signature:    Date: 

Signature:    Date:    

Attachments, No. of pages: 

Approved By Contractor QC 

 

   Approved By Company   Name:    Signature:    Date: 

   

  Company Logo and business name  

Company Identification

Revision Index

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

104 of 120 

 

COMPANY:   Project No.:   Project Name:  CONTRACTOR:   Location of works: 

Record No.:                        page ––––– of ––––– 

Inspection and Test Record for HV/LV Cables   

 Manufacturer  Test Voltage 

Cable Tag No /  Cable Drum No   

Cable Type   

Continuity  

Rated  voltage 

No of cores & Size   

Ambient temperature  Humidity  INSULATION RESISTANCE OF POWER CABLES  Three Phase/Single Phase L2‐all other  L3‐All other  N‐All other  Cores +E  Cores +E  Cores +E 

L1‐All other  Cores +E 

IR of control cables (XΩ)  Shield –E/A 

CORE‐CORE 

All Core‐E 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Test Equipment Type 

 

Reference Document:   

  Make

Model no. 

Sl. no.

Calibration Date

Cable identification checked at both ends............................  Grounding of cable checked ..............................................  Remarks: 

  Attachments, No. of pages: 

Tested By Contractor 

Approved By Contractor QC 

Approved By Company 

Name:   

Name:   

Name:   

Signature:    Date:   

Signature:    Date:    

Signature:    Date:    

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

105 of 120 

   

Inspection and Test Record (ITR) for                     Record No.: ––  Pre-cast Concrete  CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

  Reference Document: 

Items to inspect 

––––– 

Contractor\tester  Contractor QA/QC  Hold  inspected* Point  initials/date

inspected  initials/date  1.0 Pre‐Pour inspection of forms, rebar, embeds    etc.  Rebar free from rust, damage Embedded  items installed as per drawing.    2.0 Concrete receive & placement inspection  Adequate conveying depositing    3.0 Verify concrete field test results    4.0 Form striking, surface inspection and release  for repair, if required.    5.0 Concrete curing and protection    6.0  Compressive strength test results  conforming to Specification 

Remarks 

 

  H ‐ QA/QC Inspector's presence is mandatory for all activities in section.   h ‐ QA/QC Inspector's presence is mandatory. 

 

 

Attachments, No. of pages: 

Tested By Contractor      Name:   

Approved By Contractor QC    Name:   

  Name: 

Approved By Company 

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets

106 of 120 

 

Inspection and Test Record (ITR) for                     Record No.: ––  Steel Structures  CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:   

Reference Document: 

 

Contractor\tester Contractor QA/QC

Items to inspect 

inspected  initials/date  1.0 Steelwork inspected and released from  prefabrication shop  2.0 Check foundation and anchor bolts for  levels, positions, configuration and  3.0 Primary steelwork  3.1 Conformity to drawing  3.2 Verticality  3.3 Elevations  3.4 Bolted field joints; torqueing  3.5 Welded field joints  3.6 Shimming and grouting  3.7 Anchor bolts; torqueing  4.0 Secondary steelwork  4.1 Structures  4.2 Hand railing, ladders, stairs  4.3 Floor grating  5.0 Painting  5.1 Repairs  5.2 Final coat 

 

Remarks 

Hold  inspected*  Point  initials/date 

 

  H ‐ QA/QC Inspector's presence is mandatory for all activities in section.   h ‐ QA/QC Inspector's presence is mandatory. 

 

 

Attachments, No. of pages: 

Tested By Contractor      Name:   

Approved By Contractor QC  Name:   

  Name: 

Approved By Company 

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

107 of 120 

 

Inspection and Test Record (ITR) for                     Record No.: ––  Underground Pipe & Backfill of Underground Service  CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:   

Reference Document: 

  Contractor\test

Items to inspect 

Underground Pipe    1. Check concrete manhole installation is complete  and conformant, as per Drawings  2. Check Lines & Levels (As per Drawings) / Slopes  3. Pipe Preparation and Jointing  4. Anchor supports/thrust blocks installed (if  applicable)  5. Manhole Ladders Installed ‐ visual  6. Cleaning & Flushing ‐ visual  7. Release for Water Leak Testing ‐ visual  8. Water leak test of Manhole – contract specs & ITP  9. Water leak test of Pipes – contract specs & ITP  10. Reinstatement completed after test & Release for  backfill compaction operations ‐ visual  11. Marker / Posts installed (if applicable) ‐ visual  12. Ensure that there is no water in pit and water  disposed properly ‐ visual  13. Pipe & Manhole system Released ‐ visual  Backfill of Underground Service  1. Ensure underground services have been released  for backfill and compaction.  2. Bedding material suitable and placement as  required. Protection devices (Warning tapes etc.) to  be available and placed (if required) – refer  drawings and manufacturer  3. Suitable material used for backfill – visual  4. Backfill material placed and compacted as per  Requirement. Verify compaction test results are  conformant  5. Backfilling and compaction operations complete  and conformant ‐ visual  U

Remarks 

Contractor QA/QC

inspected  initials/date 

Hold  Point 

 

inspected  initials/date

 

 

U

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.   h ‐ QA/QC Inspector's presence is mandatory.  Tested By Contractor    Name:    Signature:    Date:   

 

Attachments, No. of pages: 

Approved By Contractor QC    Name:   

Approved By Company  Name: 

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

108 of 120 

   

Record No.: ––––– 

Inspection and Test Record (ITR)  for Generators 

page 1 of 2 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:  Additional information :  U

U

 Reference Document:  Contractor\tester

Sequential inspection list 

inspected  initials/date  9.3.1 Nameplate date in accordance with  drawings, specifications and requisitions    9.3.2 Location and orientation    9.3.3 Access and fixing correct    9.3.4 Check diesel, generator panels and  enclosure for any visible signs of damage    9.3.5 Measure insulation resistance prior to  starting and record    9.3.6 Check electrical panel labelling    9.3.7 Check pilot lamp test    9.3.8 All connections are tight    9.3.9 Grounding connected and tight    9.3.10 Check make and type of battery    9.3.11 Check load circuit    9.3.12 Make visual inspection during test run  and record any unusual vibration and  unusual noise in “Remarks” space 

 

Contractor 

Remarks 

Hold  inspected  Point initials/date

 

 

 

  H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor      Name:   

Approved By Contractor QC    Name:   

Approved By Company  Name: 

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

109 of 120 

  Record No.: ––––– 

Inspection and Test Record (ITR)  for Generators 

page 2 of 2 

CONTRACTOR: 

COMPANY:    Project No.:   Project Name: 

Location of works:  

Additional information:   Reference Document:  Contractor\tester Contractor QA/QC

Sequential inspection list 

inspected  initials/date  9.3.13 All the starting systems, protections,  alarms, functional tests to be checked  (see manufacturer’s forms attached) when  installation is completed with vendor and  Company’s Supervisor 

 

Remarks 

Hold  inspected  Point initials/date 

 

 

 

  9.3.14 Check and record details:     Alternator:  U

Make and type:  Output: 

KVA: 

Voltage:  Frequency : RPM:  Cos phi:  Winding connections:    H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor      Name:   

Approved By Contractor  QC    Name:   

Approved By Company  Name: 

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

110 of 120 

   

 

Inspection and Test Record (ITR) for  Installation of Low and High Voltage Motors 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:  Reference  Document: 

 

Contractor\tester

Items to inspect    1.0 Name plate, equipment classification and IP  rating checked  – visual / datasheet    2.0 Equipment checked for any damages and  carries correct circuit identification   – visual    3.0 Equipment fixing and mounting are secure   – visual    4.0 Earthling completed and checked against  design requirements   – visual / spec    5.0 All connections including RTD or thermostats Checked   – visual    6.0 Fan is free to rotate and motor shaft rotated  by hand   – test    7.0 Terminal box gaskets and seals are present  and not damaged   – visual    8.0 Glanding completed, spare entries plugged  and bolts are correct  ‐visual 

Contractor QA/QC

Inspected  Initials/Date 

 

Hold  Point 

 

Remarks 

Inspected  Initials/Date 

 

 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor     Name:   

Approved By Contractor QC  Name:   

Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

111 of 120 

   

 

Inspection and Test Record (ITR) for  Installation of Power Transformer 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect  1.

2. 3. 4.

5.

6. 7.

8.

Contractor QA/QC

Transformer specification & name plate    checked against data sheets    Transformers checked for any damage    Correct orientation, alignment and installation   Manual operation of tap changer in all  positions correct    Primary, Secondary and wiring connection  correct    Equipment earthing completed    Check auxiliary wiring if connection correctly  completed prior commissioning    Check & verify the cooler of silica gel prior  commissioning 

 

Remarks 

Inspected  Initials/Date 

Hold  Point 

Inspected  Initials/Date 

 

 

 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor     Name:   

Approved By Contractor  QC  Name:   

Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

112 of 120 

 

Inspection and Test Record (ITR) for  Installation of Switchgear and Motor Control Centre 

  Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect  1.

2. 3. 4.

5. 6.

Check equipment is suitable for area  classification and IP rating    Name plate checked against data sheets    Orientation, alignment and fixation correct    Equipment checked for internal damage and  cleanliness    Equipment earthing completed and tested    Identification and labelling correct 

Contractor QA/QC

 

 

  Remarks 

Inspected  Initials/Date 

Hold  Point 

Inspected  Initials/Date 

 

 

 

7.

Bus Duct correctly installed and Duct test  completed on bus bar joints 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor     Name:   

Approved By Contractor  QC  Name:   

Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

113 of 120 

 

Inspection and Test Record (ITR) for Jointing, Glanding and  Termination of Power and Control Cables 

  Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect  1.

2.

3.

4.

5.

6.

7.

Check if material type, size comply with  certification    Check joints installation at terminations,  if done properly    Check terminations and color of heat  shrinks‐if applicable    Check if cable glands sealed, tightened  and correctly installed.    Check Installation of gland earth tag and  IP washer    Check cables if no loose connection at  terminals and torque as per  Manufacturers and Engineering  Recommendations    Check Cables and Termination Wiring ‐  Tags, Labels, Ferrules 

Contractor QA/QC  

 

 

Remarks 

Inspected  Initials/Date 

Hold  Point 

Inspected  Initials/Date 

 

 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor     Name:   

Approved By Contractor  QC  Name:   

Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

114 of 120 

   

Record No.: ––––– 

Inspection and Test Record (ITR)  for Lighting Installation 

page 1 of 2 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:   

Additional information :    Reference Document:  U

U

Items to inspect 

Contractor\tester

Contractor QA/QC

inspected  initials/date 

Inspected  Hold Point initials/date 

Note: Tests marked (C) and (M) are required   

 

 

Remarks 

 

for pre‐ commissioning and/or maintenance  inspections only.  1.1 Lighting distribution board  1.2 Establish and record the following:     

area classification   type of ex‐protection  type of enclosure protection  circuit fuse size 

1.3 Test the insulation resistance at 500 V (C)  (M)  R‐E     Mohm, R‐S     Mohm, R‐N     Mohm  S‐E     Mohm, S‐T     Mohm, S‐N     Mohm   T‐E     Mohm, R‐T     Mohm, T‐N     Mohm  1.4 Check the following items and note any  deviations/defects under remarks:     

correct labelling  good general condition ‐ no  mechanical damage  no unauthorized modifications  no undue accumulation of dust and  dirt adequate protection of board and  cables against corrosion ‐ the  weather, vibration etc. 

  H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor    Name:   

Approved By Contractor  QC    Name:   

Approved By Company  Name: 

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Sheet of Sheets

Validity  Status 

Rev.  No. 

EX-DE 

02 

115 of 120 

   

Record No.: ––––– 

Inspection and Test Record (ITR)  for Lighting Installation 

page 2 of 2 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name:    Additional  information: 

Contractor\tester

Items to inspect 

Contractor QA/QC 

inspected  initials/date  1. 2. 3. 4. 5. 6.

correct wiring       Earthing in good condition     correct operation earth leakage protection    Lighting fittings and receptacles    Inspection list lighting fittings and receptacles   Remedial action completed 

Remarks 

inspected  Hold  Point  initials/date   

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

 

 

Attachments, No. of pages: 

Tested By Contractor      Name:   

Approved By Contractor  QC    Name:   

Approved By Company    Name:   

Signature:    Date:   

Signature:    Date:    

Signature:    Date: 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

116 of 120 

   

Inspection and Test Record (ITR) for  Painting of Steel Surfaces 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect 

Inspected  Initials/Date 

 

 1.0 Pre-activity checks  U

Contractor QA/QC    Hold  Point 

 

Remarks 

Inspected  Initials/Date 

 

 

1.1 Paint, components and thinner type, brand name,  lot number and material certificate as per approved  paint cycle  1.2 Blasting material (sand, grit, slag) and/or wire brushing  tools as per approved paint cycle and specifications  1.3 Storing conditions of paint and blasting material  1.4 Paint shelf life and expiring date / First in‐First out  1.5 Measuring equipment availability,  compliance with specification and calibration  validity.  2.0 Surface preparation  U

2.1 Surfaces clear of oil, grease, contaminates, sand,  dust, cleaned with solvent, brush or air, if necessary  2.2 Ambient conditions  2.3 Blasted/wire brushed surface  meets profile  requirements and surface preparation  level (e.g. SA 3)  2.4 Area masked appropriately  3.0 Paint application (to be repeated for primer, first  coat, second/final coat)  3.1 Primer /Paint mixed, agitated, used within specified  pot life, correct paint and thinner, etc.  3.2 For primer ‐ Surface preparation to correct level and  time  after blasting not exceeded  U

U

U

3.3 Ambient conditions  3.4 For paint ‐ Surface status (clean from dust and salt)  and correct time (min/max) elapsed after previous layer  application.  3.5 Primer/paint applied as per specification  3.6 Curing time, ambient conditions and protection  3.7 Final paint acceptable. Release for erection,  insulation testing, as applicable  4.0 Test Panel (if applicable)  U

4.1 Test panel preparation and painting as per points  from 2.1 to 3.7.  5.0 Interim Mechanical Completion    5.1 Final Acceptance paint document package  U

5.2 Test Package to be included in the Mechanical  Completion package of the relevant line or system. 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor     Name:   

Approved By Contractor  QC  Name:   

Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

117 of 120 

   

Inspection and Test Record (ITR) for  Pipelines Installation

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor\tester

Items to inspect  Material Acceptance - Control - Preparation  1. Pipe and bends conforms to specification  2. Pipe and bends marking  3. Material rating and dimensions  (diameter/thickness/schedule)  4. Transfer of markings (if applicable)  5. Cutting and re‐beveling (as applicable)  6. Long radius bend ‐ Cold bending  7. Offloading and handling utilizing correct lifting gears  8. Storing as per storing plan. Number of maximum row  Sawdust bags or wood timber    ROW and Trenching  1. ROW and Trench bench marked by Surveyor  2. Top soil stripping to the specified depth and ROW  width and level  3. Top soil and excavated material stored in designated  areas, as applicable  4. Excavated trench is to the required dimensions /  shape and trench bottom free from debris. Rocks to  be excavated.  5. Bedding material suitable and placed requirements  6. Trench released for installation of pipelines    Stringing  1. Stringing of pipeline pipes and bends as per approved  stringing plan; Positioning pipes and bends at correct  level from ground (sawdust bags or wood timber) and  distance from trench border); Longitudinal weld  position (if applicable)  2. Inspection of stringed pipes and bends  3. Any additional requirements for crossings (road, river,  railways, OH lines, pipelines, others).    Preparatory works  1. Re‐bevel, when necessary ‐ beveling machine  2. Check bevel visually  3. Visual, MPI, check of bevel  4. Lamination check if pipe end cut (dimensions to be  specified)  5. Cleaning (swabbing)  6. Stringing  U

Inspected  Initials/Date

 

Remarks 

Contractor QA/QC 

Hold  Point

 

Inspected  Initials/Date 

 

 

U

U

U

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages:  

Tested By Contractor     Name:   

Approved By Contractor  QC  Name:   

Approved By Company    Name:   

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007

Validity  Status 

Rev.  No. 

EX-DE 

02 

 

Sheet of Sheets

118 of 120 

 

Inspection and Test Record (ITR) for  Pipelines Installation 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

 Contractor\tester 

Items to inspect 

Contractor QA/QC  

Lowering    1. Lowering equipment (side‐boom and lifting loose  gears ‐ roll cradle‐canvass belt)  2. Holiday Detection during lowering‐in (pipe bottom  section)  3. Trench and Bedding as completed and released. See 2.5. No deterioration occurred (e.g. debris, rocks,  stones, water, collapse)  4. Lowering execution in accordance with approved  method statement and scheme (refer ITP)  5. Lowering and laying at crossings (road, river,  railways, lines, pipelines, others).  6. Release for lowering complete    Backfilling  1. Confirm pipeline has been released for backfill and  compaction  2. Bedding material available and suitably placed with  correct layer thickness  3. Backfilling material suitable (mineral soil and top  soil from ROW excavation). Any additional material  is approved  4. Backfill material placed and compacted as per  requirement, above initial backfill for pipeline and  for any cables, conduit etc. Verify compaction test  results are conformant  5. Warning tapes etc. to be available and placed as  necessary  6. Backfilling and compaction operations complete  and conformant 

 

U

Remarks 

Inspected  Initials/Date 

Hold  Point 

Inspected  Initials/Date 

 

 

U

 

Flushing, Pressure Testing, Dewatering  Refer relevant ITP, as applicable  U

 

Installation of valves, fittings, cathodic protection,  signalization systems and other parts or utilities  Refer relevant ITP, as applicable  U

 

Mechanical Completion  Mechanical completion dossier completion and  Approval.  U

 

Reinstatement and Re-cultivation  1. Reinstatement of ROW and any affected areas  2. Re‐cultivation  U

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.  h ‐ QA/QC Inspector's presence is mandatory. 

Attachments, No. of pages: 

Tested By Contractor     Name:   

Approved By Contractor  QC  Name:   

Name: 

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

Approved By Company   

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

119 of 120 

 

Inspection and Test Record (ITR) for  Installation of Field Instruments 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

 Contractor\tester

Items to inspect 

Contractor QA/QC 

1. Instrument type and class per P&ID and    specification (data sheets)    2‐ Instrument checked for any damage    3. Instrument tag(s) installed and correct    4. Installation of sensor complete and correct    5. Block and drain valves    6. Pneumatic / hydraulic tubing leak tested    7. Heat tracing / insulation / instrument housing    8. Impulse lines pressure tested    9. Wiring correct    10. Drawings marked up as‐built    11. HMI Graphic symbol and tag correct     

 

  Remarks 

Inspected  Initials/Date 

Hold  Point 

Inspected  Initials/Date 

 

 

H ‐ QA/QC Inspector's presence is mandatory for all activities  in section. Attachments, No. of pages:  h ‐ QA/QC Inspector's presence is mandatory. 

Tested By Contractor    Name:   

Approved By Contractor  QC  Name:   

Name: 

Signature:    Date: 

Signature:    Date:    

Signature:    Date: 

 

Approved By Company   

       

   

  Company Logo and business name  

Company Identification

Revision Index 

252100DBQA00007  

Validity  Status 

Rev.  No. 

EX-DE 

02 

Sheet of Sheets

120 of 120 

   

Inspection and Test Record (ITR) for  Loop-Check of Field Instruments 

Record No.:   

 

CONTRACTOR:  Location of works:  

COMPANY:    Project No.:   Project Name: 

Reference  Document: 

 

Contractor QA/QC  

 Contractor\tester

Items to inspect  Visual Inspection:  1.Check all the instruments are installed properly   2.Check wiring is done correctly  3.Check wiring is done with wiring rule & electrical  requirements  Earth & Continuity test:  1.Check all the points of electrical installation are  connected to earth  2.Check the resistance value of protective earthling  conductor using ohm meter   3.Resistance between earthing electrode & main  earthing conductor should not exceed 5 ohm  4.Check continuity of each circuit   Insulation resistance test:  1.Check the insulation resistance b/w live parts &  earth contacts is above 0.01mega ohm  2.If the insulation resistance is less than 0.01mega  ohm, check the circuit insulation and appliances  insulation separately:  1) Circuit insulation    2) Appliances insulation resistance  3.Reconnect the circuit  4.Recheck the insulation resistance  Circuit correction and Polarity check:  1.Check earthing conductor do not carry current  2.Conform there is no short circuit  3.Check the polarity of devices connected in the  circuit  Fault impedance test:  Measure the impedance using fault loop impedance  meter:   Less than the maximum values as the  U

Inspected  Initials/Date

 

Hold  Point

 

  Remarks 

Inspected  Initials/Date

 

 

U

U

U

U

 

H ‐ QA/QC Inspector's presence is mandatory for all activities in section.   h ‐ QA/QC Inspector's presence is mandatory. 

Tested By Contractor    Name:    Signature:    Date: 

 

Attachments, No. of pages: 

Approved By Contractor  QC 

 

Name:   

Approved By Company    Name:   

Signature:    Date:    

Signature:    Date: 

   

   