INSPECTION AND TEST PLAN

Revision: Date:

Activity Description

21.05.2019

Description: Installation of HDPE pipes for underground service

ITP NO: ACO-9-3004-013-T7-4-B

Item No.

00

Acceptance Criteria

Frequency

As per Project Specification

Once

As per MAS

Reference Document

Inspection Authority and Codes

Quality Record

Remarks

MC

Consultant

Project Specification

H/R

R

Approved MS

Each Delivery

Project Specification / Approved MS

H/R

R

MAR Approval/s

As per Project Specification

Each Delivery

Project / Approved MS

H/R

R

MAR Approval/s

1.0

MS/Material Approvals

1.1

MS for Installation of HDPE pipes for underground service

1.2

HDPE Pipes & Fittings

1.3

Supports

2.0

Installation

2.1

HDPE Pipe Welding

As per Approved Drawing

Each Section

Project Specification / Approved MS

W/R

W/R

Checklist

2.2

HDPE Pipe Laying

As per Approved Drawing

Each Section

Project Specification / Approved MS

W/R

W/R

Checklist

Page 1 of 2 Legend: S – Surveillance Inspection

W- Witness Inspection Point

H- Mandatory Hold Point for Inspection

R- Record Review

INSPECTION AND TEST PLAN

Revision: Date:

ITP NO: ACO-9-3004-013-T7-4-B

Item No.

Activity Description

2.2

Supports

3.0

Testing

3.1

Pressure Testing

4.0

Quality Record

Prepared By:

Frequency

As per specification

Each Section

As per Approved Drawing

Each Section

Reviewed by:

21.05.2019

Description: Installation of HDPE pipes for underground service

Acceptance Criteria

Complete Record

00

Reference Document

Inspection Authority and Codes

Quality Record

MC

Consultant

Project Specification / Approved MS

W/R

W/R

Checklist

Project Specification / Approved MS

W/R

W/R

Checklist

R

R

All Reports

After Complete Activities Reviewed and Approved By:

Remarks

Reviewed and Accepted by Engineer’s Representative:

Sign:

Sign& Position:

Date:

Date:

Page 2 of 2 Legend: S – Surveillance Inspection

W- Witness Inspection Point

H- Mandatory Hold Point for Inspection

R- Record Review