Mechanical Equipment Procedure Tse

  • Uploaded by: spazzbgt
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Mechanical Equipment Procedure Tse as PDF for free.

More details

  • Words: 1,758
  • Pages: 11
Loading documents preview...
JOINT OPERATING BODY

DOCUMENT NO :

PERTAMINA - TALISMAN JAMBI MERANG

CONSORTIUM PT. SULUH ARDHI ENGINEERING -

-

PROJECT NO : 4500001473

PT. MEGA PRATAMA UNGGUL

11 pages

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK MECHANICAL EQUIPMENT ERECTION PROCEDURE PROJECT

: EPC GAS METERING AT GRISSIK

LOCATION

: GRISSIK, MUSI BANYUASIN – SUMATERA SELATAN

OWNER

: JOB PERTAMINA – TALISMAN JAMBI MERANG

CONTRACTOR

: CONSORTIUM PT. SAE – PT. MPU

PO. NO.

: GRS-CT-N-002

PO. DESCRIPTION : PIPING, MECHANICAL AND STEEL SRUCTURE WORK REQUISITION NO. : VENDOR NAME

: PT. TRISERAPHIM ENGINEERING

VENDOR DOC. NO : TSE-GRS-PR-006

A

01/04/2014

Issued for Approval

Rev.

Date

Description

BY

CHK’D

APP’D

CONTRACTOR

APP’D CLIENT

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Date : 01/04/2014

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Rev: A

Page 2 of 11

REVISION TABLE REVISION

REVISION

PAGE

REVISION

PAGE A

B

0

1

2

3

4

ATTACHMENT A

1

X

31

2

X

32

3

X

33

4

X

34

5

X

35

6

X

36

7

X

37

8

X

38

9

X

39

10

X

40

11

41

12

42

13

43

14

44

15

45

16

46

15

47

18

48

19

49

20

50

21

51

22

52

23

53

24

54

25

55

26

56

27

57

28

58

29

59

30

60

B

0

1

2

3

4

A

B

0

1

2

3

4

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Rev: A

Date : 01/04/2014 Page 3 of 11

RECORD OF REVISION Rev No

Section

Page

Company Comment

Implemented (Y/N)

Explanation

A

All

All

-

-

-

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 4 of 11

TABLE OF CONTENTS 1.

GENERAL

5

2.

PURPOSE

5

3.

REFFERENCE

5

4.

DESCRIPTION OF PROCEDURE

5

4.1

Receipt and Storage

5

4.2

Inspection before Installation

5

5.

6.

7.

EQUIPMENT INSTALLATION

6

5.1

Equipment

6

a

Sales Gas Filter

6

b

Vent CO2 Snuffing Package

6

c

Vent Stack

6

d

Emergency Diesel Generator Package

6

e

Diesel Supply Tank

6

f

Potable Water Overhead Tank

6

g

Fire Fighting and Safety System

6

h

Sales Gas Metering Package

6

GROUTING

7

6.1

Chipping

7

6.2

Cleaning

7

6.3

Making Formwork

7

6.4

Preparing Grouting Equipment and Water

7

6.5

Clean Up

7

6.6

Grouting Process

7

ATTACHMENT Table 1.1.

8

Drawing 1.1.

8

Flow Chart of Static Equipment Erection Procedure

9

SikaGrout 125

10

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 5 of 11

1. General Installation of Sales Gas Metering Package, Venting System, Power Generation system,Potable Water and Fire Fighting and Safety System for EPC Gas Metering at Grissik’s project, JOB Pertamina - Talisman, Jambi. 2. Purpose This procedure covers the installation Mechanical with reference to specifications, standards and drawings provided by the client and as a guide for companies to carry out the above work. 3. Refference 3.1. PQP 3.2. Flow Chart Mechanical Prosedur 3.3. Equipment Installation Procedure Manual Book. 3.4 Equipment Construction Drawing. 4. Description of Procedure 4.1 .

Receipt and Storage All Equipment must be checked before being installed first. Inspection is done together with the client and vendor equipment. Check is performed to see whether the condition of the equipment is damaged or accessories missing. In the inspection process must be tailored to the list by taking into account the size of the shipment. In the event of damage or loss of the components to be made in the form of a written report MRR. In the work JOB Pertamina-Talisman Jambi company has the scope of work on the truck then mounted admission to the foundation.

4.2.

Inspection before Installation. The following are the steps that must be done prior to installation: - Assure that the foundation has been properly inspected in accordance with the dimensions given in the drawings and have markers at the point coordinates. (Accompanied by the report of the surveyor and the results of the inspection along with the client). - Ensure that it is raining at the time of installation - Check the position of the anchor bolt and tilt tolerance is in accordance with the specifications and construction drawings and compare it to the dimensions of the bolt holes on the equipment that will be installed. - Setting up the instrument in the form of cranes, chain blocks, slings wire / belt slings, sackle and others that will be used in accordance with the capacity to convince and adoptive.

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

-

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 6 of 11

Ensure that the crane had a solid foundation, if it should be necessary hardening or setting up a steel plate that corresponds to the capacity. Perform chipping at the foundation approximately 3-5 cm. Then mark the position of the padding plate The surface to be cleaned, and the former chipping moistened, then given cemen grouting for padding plate and make sure that the elevation of padding plate in accordance with the specifications or drawing.

5. Equipment Installation 5.1 Equipment : a. b. c. d. e. f. g.

Sales Gas Filter 38 Inch (OD), 120 Inch (H), Weight 4.800 Kg Vent CO2 Snuffing Package Vent Stack Emergency Diesel Generator Package Dim. 2 m x 1.2 m x 1.35 m, Weight 1.100 Kg Diesel Supply Tank Dimension 2.54 m x 76.2 m x 1.35 m, Weight 330 Kg Potable Water Overhead Tank Equipment Fire Fighting and Safety System

Installation procedure as follows: - Installation of using a crane with a capacity of 10 tons (for load above 50 Kg) - Position the crane in a safe place, where there are no objects or disturbing material at the time of swing - Use as a spreader and chain block lifting aids if necessary - Setting up a sling and sackle according to capacity and there should be no damage to the lifting tools - Assure that sackle accordance with the dimensions of the hole in the lifting lug equipment - Taking into account the position of the direction of the equipment is in conformity with the specifications and drawings - Install the Equipment - Assure that at the time of installation in accordance with the specification and the desired elevation - Install the anchor bolt nut - When the installation is in accordance with the drawings and specifications, then remove the sling and other tools - Have a general elevation in accordance with the specifications and drawings (accompanied by the inspection report with clients) - Grouting (See Grouting Procedure)

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 7 of 11

h. Equipment Sales Gas Metering Package Dim. : 12.55 m x 2.8 m x 2.16 m, Weight 17.500 kg Installation procedure as follows: - Installation of using a crane with a capacity of 10 tons - Position the crane in a safe place, where there are no objects or disturbing material at the time of swing - Use as a spreader and chain block lifting aids if necessary - Setting up a sling and sackle according to capacity and there should be no damage to the lifting tools - Assure that sackle accordance with the dimensions of the hole in the lifting lug Gas Metering equipment skid. - Taking into account the position of the direction of the equipment is in conformity with the specifications and drawings - Install the Gas Metering equipment - Assure that at the time of installation in accordance with the specification and the desired elevation - Install the anchor bolt nut - When the installation is in accordance with the drawings and specifications, then remove the sling and other tools - Have a general elevation in accordance with the specifications and drawings (accompanied by the inspection report with clients) - Grouting (See Grouting Procedure) 6. Grouting Preparation : a. Chipping Perform cipping the concrete surface is still flat, so it can penetrate the grout cement slurry and blend with the concrete base. b. Cleaning After chipping activities done then proceed with cleaning the floor surface until no dust, and other materials to cause the cement grout that may not converge c. Making Formwork Formwork need to be made so that at the time of pouring cement grout did not come out of the foundation going in the grout d. Preparing Grouting Equipment and Water Prepare all equipment for the preparation of a grouting cement mixers, clean water. e. Clean up After all the preparation is done, then pour water into the location that will digrouting and let the condition for about 2 hours, then dry the area.

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 8 of 11

f. Grouting Process - After all the preparation is done, it should be noted that the temperature of the water must follow the appropriate temperature required in the procedure (procedure parbik). - Ensure that the results of mixing cement grout according to manufacturer's standards - Add water into the mixing vessel and stir slowly until the condition completely fused cement with water for approximately 5 minutes. (See table 1.1) - Once the mixture is completely blended, pour cement grout mixture is stirred slowly into bagasting that has been provided on one side (see figure 1.1). - Mortar shall evenly to fill every pore under the base plate - After all the grouting process is done, then let the cars for 3 days (72) hours and the condition should be kept moist by watering.

Table. (1.1) SikaGrout 215 No 01 02

Water Requirement ( Litres / 25 Kg bag ) 2.75 4.25

Flow Condition Trowellable Flowllable

Drawing 1.1

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 9 of 11

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 10 of 11

JAMBI MERANG DEVELOPMENT PROJECT EPC GAS METERING AT GRISSIK Doc. No : -

Rev: A

MECHANICAL EQUIPMENT ERECTION PROCEDURE

Date : 01/04/2014 Page 11 of 11

Related Documents


More Documents from "arifadha446"