METHOD STATEMENT FOR EXCAVATION WORK Page No 1 of 5

MEDANTA HOSPITAL PROJECT

            

METHOD STATEMENT FOR EXCAVATION WORK

CLIENT : MEDANTA PMC: CUSHMAN & WAKEFIELD INDIA PVT. LTD. CONTRACTOR :SPCPL

METHOD STATEMENT NO.: SPCPL/MEDANTA/MS/01/PILE Re v no 0

Date

Description

22.04. 2017

METHOD STATEMENT FOR EXCAVATION WORK

Prepared By S Saha

Checked By

Approved By (C&W)

Approved By Client

A Garg

1. Purpose: The purpose of the procedure is to provide details of safe operating system of excavation operation for building work foundation, using excavator , construction plant

METHOD STATEMENT FOR EXCAVATION WORK MEDANTA HOSPITAL PROJECT

Page No 2 of 5

& manpower to ensured that excavation operation are carried out safe manner .This procedure will help to ensured a safe & healthy work environment at site at all time. 2. Scope:

In BOQ: 82000 cum Phase- 1 – 21000 cum Phase- 2 – 29000cum Phase- 3 – 24000 cum Misc - 8000 Cum 3.Role & Responsibility: The Construction Manager and the Execution Engineer shall be responsible for the Overall implementation of this method statement. 4. Reference Code:

.1 IS: 2911 (Part 1, Section 2) – 2010

.2 IS 456 – 2000 .3 IS 1786 – 2008 .4 IS 2720 (Part 5) -1985 .5 Project Specification / Schedule of Rates (SOR)

5. Machineries Used:

Excavation work will be undertaken by Earth Excavator, JCB & Dumpers. (Manually where & when require).

6.Pre information:   

Ground conditions underground structures or water courses / Table; and The location of existing services.

This information should be used to during the planning and preparation for excavation work.     7. Manpower Deployed for Piling Work. :      i)   Supervisor 01 No. ii) Excavator Operator 02 No. iii) Dumper Driver-06 nos

     8. Procedure: a) Survey Work : 1.Pre level that is EGL needs to be finalized and EGL level Sheet nedds to signed by  C/W. 2. Excavation Layout needs to finalized and checked by C/W. 

METHOD STATEMENT FOR EXCAVATION WORK Page No 3 of 5

MEDANTA HOSPITAL PROJECT b) Detail Procedure:

Work will be started from the Phase-1 that is from grid

by1

and

proceeds towards the grid 26 as per drawing. But before excavation of Phase 2 we required to keep in mind that phase 2 is pile zone. Before excavation of this zone the piling work and the maturity time needs to over. Required slope to be maintained for excavation & the excavated areas will be protected by hard barricading for safety purpose & temporary shoring (Barricading) to retain the slide earth (as per below fig.). After major excavation by Excavator, dressing will be done manually. At the time of excavation all levels and excavation areas will be checked by our Engineer and surveyor as per drawing jointly with C/W.

Minimum

600

working

Space

is

required

for

fixing

of

reinforcement & Shuttering. 9. Disposal:

The excavated top soil is sold to the nursery as per green building norms. Balance earth we shall stock as per instruction of the owner. 10. Dewatering:

All the water that may accumulate in excavations during the progress of work from rains, subsoil water, springs or any other cause shall be pumped-out completely by submergible or dewatering pump towards the outside drain or sump. The basement raft shall be kept dry during excavation and before the commencement of Brick flat soling and PCC.

11. Health Safety & Environment: Care shall be taken not to dump the excavated material near the excavation area and follow the safety norms. Barricading shall be provided around excavated area and signal light shall be provided at night hours. Excavated material shall not be dumped alongside the pit excavated. Excavated earth shall be disposed - off to designated locations as mentioned in contract. Some quantity of excavated earth shall be retained for backfilling if specified so.

METHOD STATEMENT FOR EXCAVATION WORK MEDANTA HOSPITAL PROJECT

Page No 4 of 5

Excavation pit shall be kept free from water by suitable means of dewatering as and when required. In case of mechanized excavator with excavators, work shall be continued till about 150mm above final level. Leveling and dressing shall be done manually with light compaction. Educate the workmen through pep-talk meeting. All persons engaged in job shall wear PPE and the equipment’s deployed will be checked by HSE Officer B. Equipment/ Machineries Safety:-

All equipment should be properly maintained and equipped with manufacturer-recommended safety devices. Disabling or removing safety devices is dangerous and should be avoided. All unsafe or inoperable equipment should be marked as such to prevent further use of the equipment. All workers should be trained and tested by the manager or superintendent before operating any equipment. Knowledge of the hazards associated with specific equipment is the first line of defence against injury.

G: Safety Requirement: Equipment’s & Tools [Submit Test Certificate before start of work wherever applicable]

List of Equipment’s, Tools & Tackles

Indicate Fitness Test & Certification Needed/TPT

Excavator,Dumper/Tripper

Checked By P & M Dept. of SPCPL.

Water Pump, Compactor Machines

Checked By safety and P & M Dept. Of SPCPL.

Non- acceptable Control Measures to be ensured against Hazards/Risks Hazards/Risks Engineering Administrative PPE [Attach HIRA] Controls Controls 1. Fall from Height 2. Fall of materials 3. Struck by Falling/ Moving Object

1. Stability of soil to be checked before erection. 2. All materials should be inspected before use. 3. Under ground cable or service lines should be checked before 4. Caught In start of work. 4. Maintained Safe procedure for Between materials handling. 5. Slip/Trips 5. Barricade & Fencing to be 6. Poor access ensured at working area. control 6. Proper illumination should be 7. Poor provided. housekeeping

1. Put sign board and alert worker. 2.Take rest for avoid fatigue & sunstroke. 3. Work should be carried out with proper supervision. 4. Trained worker & operator should be deployed.

Full body harness, Safety Helmet, fall arrester, Safety goggles, Hand Gloves, safety shoes/gum boot and reflective jacket as required as per safety norms.

METHOD STATEMENT FOR EXCAVATION WORK MEDANTA HOSPITAL PROJECT

Page No 5 of 5

8. Improper 7. Proper housekeeping & illumination suitable approach/access should 9. Fire /explosion be ensured. 10. Improper guarding arrangement of rotating parts 11. under ground cable/ service line. Hazardous Substances [Attach MSDS if required] Emergency Refer To HSE PLAN Plan/Procedures On-site Medical Aid Name & contact of First Aider Location of First Aid Box

To be decided.

Off-site Medical Aid Sri Ram Hospital

Ph no7781880022

First-Aid centre. Roles, Responsibility , Authority & Contact No.

Key Personnel Involved in work Execution

Assessment on Competency & Medical Fitness [Certificate to be submitted before start of work)

Mr. Subrata Parui

Project In charge

Mr. Binod Pandey

Construction Manager

To be decided

Sr. Supervisor

Mr.Bijit Sinha

Quality In Change

To be decided

Safely In charge Type

Specify Qualification/E xperience Certification needed

Specify Medical Fitness Certification Needed

Fabricator Gas Cutter & welder, Khalasi Gang,

Yes

General Health check-up.

Operator

Yes

General Health check-up

Skilled & Semi-skilled worker

NA

General Health check-up.