Loading documents preview...
IRAQ GATES CONTRACTING COMPANY Method Statement
Rev: A
Testing MV Cables at Um-Qasr xxxxxxxxxxxxx
Doc. Cat.
EXT
Method Statement of Testing MV Cables at Um-Qasr
0
14-Aug-2018
Issued for Review
B.R
W.A
A.M.
REV
DATE
DESCRIPTION
PREPARED BY
REVIEWED BY
APPROVED
1 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
TABLE OF CONTENTS 1.
Introduction
2.
Definitions
3.
Abbreviations
4.
Methodology
5.
MTO
6.
HSE Requirements
7.
Attachments
2 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
Method Statement
Testing MV Cables at Um-Qasr 1. Introduction As part of BGC development plan, Work Order (WO-026) to perform Refrigerated Export Project (Testing MV Cables at Um-Qasr) at Um-Qasr Storage Terminal has been issued to IGCC. This Method Statement, aims to provide sufficient definition for Refrigerated Export Project (Testing MV Cables at Um-Qasr) Storage Terminal. Its intent is to also facilitate implementation in a safe and efficient manner and for all involved parties to understand the risks, roles and responsibilities associated with the Testing MV Cables at Um-Qasr.
2. Definitions COMPANY
BGC (Basra Gaz Company)
PROJECT
Refrigerated Export Project Testing MV Cables at Um-Qasr
CONTRACTOR
(IGCC) Iraq Gates Contracting Company
WORK
Shall mean all and any of the work andor services andor materials required to be provided by the CONTRACTOR under contract with COMPANY.
SHALL AND MUST
Indicates mandatory requirements.
SHOULD
Indicates that a provision is not mandatory but recommended as good practice.
3. Abbreviations Abbreviation
Definition
SOW
Scope of Work
BGC
Basra Gas Company
3 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
4. Methodology 4.1 Engineering Phase - Preparation and Submission of Method Statement. - Preparation and Submission of all HSE Deliverables. - Preparation and Submission of all QA/QC Deliverables.
4.2 Procurement Phase - N/A
4.3 Mobilization Phase - Transportation to site all Manpower & Equipment. - Establishment of Site Office for IGCC’s Staff.
4.4 Dismantling Phase 4.4.1 Prior to Start the Works - Having valid PTW with approved method statement. - Having Electrical isolation certificate from client. - Isolation point must be checked to prove correct isolation. - Area Barricaded with all HSE signs. - Having a valid confined space entry permit, with people trained & authorized to work in confined space. - Having approved rescue plan and to be discussed with the CSE team. - Having trained & authorized rescue team. - Make sure all the control system mentioned in JHA for CSE is in place.
4.4.2 Testing of MV Cables at Storage Terminal 4.4.2.1 Preparation Works - Perform zero voltage verification for all circuit elements using HV tester. - Earthing the electrical elements inside termination box remotely using earth stick and to be connected to solid earth. 4 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
- Cable disconnecting from both sides, BGC operation team to disconnect the cable from SS side, IGCC will disconnect the cable at the field site. - Men Observers to avoid people near, through testing for both sides. - 3 personnel will enter CS at maximum.
4.4.2.2 Continuity Test - By utilizing calibrated multi-meter tester, continuity test will be performed by qualified electrician. 4.4.2.3
IR Test - By utilizing calibrated Megger tester, IR test will be performed by qualified electrician. - IR Testing voltage shall not exceed the cable operating voltage; for 3.3KV cables the test will be done at 2.5KV and the 11KV cables will be tested at 5KV. - Record the measured value on related ITR form.
4.4.2.4 Hi-Pot Test - By utilizing calibrated Hi-Pot Very Low Frequency (VLF) tester, Hi-Pot test will be performed by qualified electrician - Hi-Pot DC voltage is not to be used, under any circumstances - VLF voltage must not exceed the nominal / operating voltage - Record the Hi-Pot measured value on related ITR form 4.4.2.5 List of Cables FROM 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1
TO Refrigeration Compressor Refrigeration Compressor Refrigeration Compressor Refrigeration Compressor Refrigeration Compressor Propane Shipping Pump
TAG 6100MK-1A 6100MK-1B 6100MK-1C 6100MK-1D 6100MK-1E 6100MP-10A
Cable Sizes 2 x 3 core 150mm2 2 x 3 core 150mm2 2 x 3 core 150mm2 2 x 3 core 150mm2 2 x 3 core 150mm2 1 x 3 core 70mm2 5 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
FROM 11kV Switchboard MMS1 11kV Switchboard MMS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1
TO Propane Shipping Pump Propane Shipping Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Gasoline Booster Pump Gasoline Booster Pump Gasoline Booster Pump Gasoline Booster Pump Butane Shipping Pump Butane Shipping Pump Butane Shipping Pump Gasoline Shipping Pump Gasoline Shipping Pump Gasoline Shipping Pump
Rev: A Doc. Cat.
TAG 6100MP-10B 6100MP-10C 6100MP-3A 6100MP-3B 6100MP-3C 6100MP-3D 6100MP-4A 6100MP-4B 6100MP-4C 6100MP-4D 6100MP-5A 6100MP-5B 6100MP-5C 6100MP-5D 6100MP-6A 6100MP-6B 6100MP-6C 6100MP-6D 6100MP-7A 6100MP-7B 6100MP-7C 6100MP-7D 6100MP-8A 6100MP-8B 6100MP-8C 6100MP-8D 6100MP-11A 6100MP-11B 6100MP-11C 6100MP-9A 6100MP-9B 6100MP-9C
EXT
Cable Sizes 1 x 3 core 70mm2 1 x 3 core 70mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 95mm2 1 x 3 core 95mm2 1 x 3 core 95mm2 1 x 3 core 95mm2 1 x 3 core 120mm2 1 x 3 core 95mm2
Preservation of Cables - Ensure cables are supported and secure away from walkways and high traffic areas. Cables ends to be sealed to prevent moisture ingress.
6 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
4.5 Final Documentation - Preparation and Submission of all Final Documentation.
5. MTO N/A
6. HSE Requirements
Site Induction.
HITRA, JHA, C.S & PTW, including approved Method of Statements.
Energy Isolation to be confirmed as per PTW procedure
Where it is not possible to isolate the cable from other equipment, ensure that Surge Arresters and VT’s are disconnected from the cable
The ‘Cable Tester’ must be the authorized tester who has been appropriately trained and authorized to conduct Testing of HV Cables in accordance with accepted standards. It is the responsibility of the ‘Cable Tester’ to have a clear understanding and comply with the requirements of this ‘Voltage Testing of HV Cables’ technique
Job Risk Analysis must be done by the work team before commencing any switching and tests near the underground cables and all parties concerned are in agreement upon that assessment
The tester in charge shall ensure that drawings are made available to familiarize himself with the work area and equipment locations prior to commencing work
Ensure to connect a local earth on the test equipment, if practicable. The case earth must remain connected to the system earth in order to maintain an acceptable single earth potential
After the cable is tested (SI, IR and VLF) cable cores must be then discharged. If applicable, close the Earth switch and then the test set leads may be removed
PPE Requirement:
7 OF 8
IRAG GATES CONTRACTING COMPANY
Method Statement
Testing MV Cables at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
Use suitable barriers, barricades and warning signs on both sides of the cable to prevent access to the cable by persons not involved with the testing. If there is any danger of exposing the public or staff to energized conductors or equipment a safety observer must be used.
Housekeeping.
8 OF 8