Monthly Progress Report No 2 (as Of Apr 30 2011).pdf

  • Uploaded by: shareyhou
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Monthly Progress Report No 2 (as Of Apr 30 2011).pdf as PDF for free.

More details

  • Words: 9,657
  • Pages: 76
Loading documents preview...
Page 1 of 1

PETROBEL

SETH ONSHORE DEVELOPMENT

4187-440

MONTHLY PROGRESS REPORT NO.2

EGYPT

Rev. 0

4187-440 SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT NO.2 AS OF 30 APRIL 2011

0

REV

18/05/2011

DATE

ISSUED FOR IMPLEMENTATION

REVISIONS

• If/' v

BY

v

I

I

I

/-,1'.- ....rI

CH'D

APPR



Enpp:l. PTB

SETH ONSHORE DEVELOPMENT

PAGE 1 OF5

4187-440

Rev. (0 Egypt

MONTHLY PROGRESS REPORT No.2

Contents I.

Project Description

2.

Parties Involved and Relevant Scope

3.

Schednle Milestones

4.

Major Activities Completed

5.

Major Activities in Progress

6.

Major Activities To Be Started During Next Reporting Period

7.

Area of concern

7.1. Progress summary Sheets With Relevant S-Curves 7.2.

Progress Control Sheets

7.3. Updated Schedule 7.4. Critical and Near Critical Activities 7.5. One Month Look Ahead Report 7. 6. Procurement Status.

7.7. Equipment and material status report 7.8. Alert report

18-MAY-2011

PAGE20F5 4187-440

SETH ONSHORE DEVELOPMENT

PTB

Rev. (0) 18-MAY-20II

MONTHLY PROGRESS REPORT No.2

Egypt

1.0 Project Description: The Temsah Pliocene Gas Gathering Network is in operation to collect the gas production from several Pliocene fields located in the Temsah area. Actually the only Denise A and Tuna productions are gathered by the new sealine, and in the following months also Denise B and Seth Fields. The whole new production is transported to the onshore El Gamil plant via a new 32" export pipeline. Denise A reservoir production (Pliocene "heavier" gas) is separated on TNW2 platform. The gas phase is conveyed to El Gamil plant through the new 32" trunk-line. Tuna and Denise B productions will be collected into a common subsea PLEM and conveyed via a new 24" sealine to the Denise A SSIV; Seth production will be routed via 16" sealines to the Tuna PLEM, Km 10.5 approximately. During the EI Gamil Upgrading Project Phase (I)a dedicated Slug Catcher for the Denise A Production has been foreseen and installed. With Seth Onshore Development Project, the installation of a new slug catcher operating in parallel with the existing Denise Slug Catcher has been foreseen.

2.0 Parties Involved and Relevant Scope: PTB:

Owner

ENPPI:

Contractor shall perfonn basic, detailed engineering and procurement services.

3.0 Schedule Milestones: Milestone

Planned

Actual

Expected

Project Coming Into Force

22-DEC-1O

22-DEC-IO

Complete Engineering Services

22-SEP-11

22-SEP-ll

Complete Procurement Services

20-JAN-12

20-JAN-12

4.0Major Activities Completed During the Current Reporting Period: 4.1. Engineering Basic engineering review completion -/ Process

• • • •

Hazardous Area Classification Schedule IFD HSE philosophy IFD Detection And Alarm Layout Drawings IFD Fire Fighting Layout Drawings IFD



E:n.pp.l. PTB

PAGE30F5

SETH ONSHORE DEVELOPMENT

4187-440 Rev. (0

MONTHLY PROGRESS REPORT No.2

Egypt

if

18-MAY-201I

Piping • • • •

Under Ground Composite Drawing IFD Under Ground Piping Standard Details IFD piping specification classes IFD Standard Piping Support Details IFD

if

Electrical • Earthing Layout IFD • Hazardous Area Classification Layout IFD

if

Civil



Standard Drawings IFA

4.2. Procurement •

Piping Bulk Bidding

5.0Major Activities in Progress During the Current Reporting Period: 5.1. Engineering if

Process • •

Fire Fighting System Technical Evaluation Detection and Alarm system Technical Evaluation

5.2. Procurement • Piping bulk Bidding

6.0Major Activities To Be Started / Completed During Next Reporting Period: 6.1. Engineering if

Process • Cause and effect IFD • Process cause and effect matrix IFD • Fire and gas cause and effect IFD • Fire and gas cable routing drawings IFD • Fire protection system TER

if

Piping •

Piping Bulk TER



Enpp1 PTB

SETH ONSHORE DEVELOPMENT

PAGE 4 OF 5

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

.{

Instrumentation

• • • • • • • • • • .{

.{

Field Instrument Cable Routing IFD Junction Box Interconnections IFD Field Instrument Layouts IFD Loop Diagrams IFD Instrument Index IFD Instrument Cable Schedule IFD Instrument Hook Up And Supporting Drawings IFD I/O list IFD Instrument Bulk Material MRQ's Instrument Cable Trays MRQ's

Electrical



Electrical Bulk MTO

• •

Standard Drawings IFC Miscellaneous pipe support Foundation Drawings IFA

Civil

6.2. Procurement

• • •

Instrument Bulk Material Bidding Electrical Bulk Bidding Piping bulk Bidding

18-MAY-2011



Enppa. PTB

SETH ONSHORE DEVELOPMENT

PAGE50F5

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.ATTACHMENTS

18-MAY-2011

I I

r

I



E:n.pp.l. PTB

SETH ONSHORE DEVELOPMENT

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.l.Progress summary Sheets With Relevant S-Curves

18-MAY-2011

Project No.: 4187-440

Summary Report

SETH ONSHORE PROJECT

As Of:

30-Apr-11

Overall Relative Weight

Item Description

Planned %

76.55%

"Engineering

39.98

,

";;:c-;;r~m:n~ ~

Total

During %

27.26

10.26

"

:

- - - - - - - - - - - - - -

Actual %

:

r---;:::--- ~ -- -275""; - - - t - - - ~.;; - - :

~

L

~

100.00%

35.66

:

-i - - - - : . ; - - _

~

25.25

8.86

Layout No.1

Monday, May 16. 2011

Page 1 of 1

Data'Nes Systems, Release 2.21

Project No.:

EDppt

4187.440

Progress Curve

SETH ONSHORE PROJECT Overall

As Of:

100 90

lp'a~ned % =

35.66

%=

25.25

IActual

:

80

....

I I

.;

. - -: •

30·Apr-11



:

70 ; ~ III III

"0 ~

60 50

Cl ~

0..

40 30



20

;

10

;. 0

..."

",'

~o

"

c:...

Qe

...... ')"C-<$

...... ",'

~e

...... ~~/

......

.,.q.:

......

..«

~

,,'"... .,.",<$......

......

~

)'"

)'"

......

G.;P"

......

"

0"

......

.J:

~o

...... c:

Qe

...'l":J'lJ.<$

...'l-

",'

~e

...'l-

~~.

Time I Date Actual ---"'-_.---

..._ . - - ..

-

-

• Planned

- - - - - - - - - ._--

:

. _ - - - - - - - - - ...•- - - _...

Layout NO.1 Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Ellppl

Summary Report

SETH ONSHORE PROJECT

AsOf:

30-Apr-11

Overall Enaineerina Relative Weight

Item Description

Planned %

Actual %

During %

...----------------------,...----------.-----------....,.-------------.--------· . . . . i Process

:

17.92%

:

45.98

;

34.09

;

12.38

: . : . : . : ·: . ---i~--------------------~--------~--------~--------~----Piping i 42.73% i 31.76 i 30.25 i 7.03

~--------------------~--------~--------~--------~----i Instrumentation i 12.40% i 38.27 i 5.19 i

5.19

i

40.00

~--------------------~--------~--------~--------~----Electrical i 5.51% i 73.33 i 40.00 1

L

· i

Pressure Vessels

L

L

L

j

. . . . i

4.90%

i

65.00

i

65.00

i

~--------------------~--------~--------~--------~----i Civil i 16.54% i 37.50 i 13.24 i L

Total

~

L

~

39.98

100.00%

Tuesday, May 17, 2011

----

----

- - __

0.00

----

13.24

~

27.26

_

10.26

Layout No.1 Page 1 of 2

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Progress Curve

SETH ONSHORE PROJECT Proffesional Services Engineering 100 90

,"" (Planned % = IActual

%=

39. 98 27.26

....

,

l

I

80 70 60

" ~

~

.. •

:

~

50

':

£'" 40 30

,

20

.•

,•



.•

:

10

o-l--~~=------i--~-~----:--~-~-~-:------i-------i----i-----i---i---1 Nov-10

Dec-10

Jan-11

Feb·11

Mar-11

Apr-11

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Time I Date Actual

-

-

• Planned

Layout No.1 Data'Nes Systems, Release 2.21

Project No.: 4187-440

Summary Report

SETH ONSHORE PROJECT

As Of:

30-Apr-11

Overall Procurement Relative Weight

Item Description

Purchasing

'i ~

i

42.00% ~

Expediting

Planned %

!

42.86 ~

34.00%

!

10.44

During %

Actual %

i

38.57

i

7.35

8.57

----

~

i

~--------------------~--------~--------~--------~----i Inspection ! 24.00% ! 0.00 ! 0.00 ! L L L l J Total

21.55

100.00%

Tuesday, May 17, 2011

18.70

2.06

----

0.00

_

4.30

Layout No.1 Page 20f2

Data'Nes Systems, Release 2.21

Project No,: 4187.440

Enppl

Progress Curve

SETH ONSHORE PROJECT As Of

Proffesional Services

30-Apr~11

Procurement 100 90

Iplanned % IActual

=

%=

,: , ,

21,551 18,70

I

80

,

70

. 0 0

~

60 •







o!l

.

.

'.

,

, -,



-;

50

Cl

e

0-

40 30

.'

:,

20 10

.. ,- ......

,

':

,;-"--~

o .jo....:.=--T..c.'-----;---;--~'---;_--;_--;_--.;_--.;_--..;_--..;_--.;..--.;..--..;..--_:_--_/ Nov~10

o.c-10

Feb-11

Mar-11

Apr-11

May-11

Jun-11

Jut-11

Aug-11

Sep-11

Ocl·11

Nov~11

o.c-11

Jan-12

Feb·12

Mar-12

Time I Date

,,__, '

"

,,

,

Actual





• Planned

",

I

J Layout No, 1

Data'Nes Systems, Release 2.21

4187·470 PTB, SETH ONSHORE PROJECT

Enppl

DELAY ANALYSIS AS OF 30-Apr·11

Process CaUse and effect matrix 11.89

1.54

fire & gas I/O IIsl Halardous area c1asslflcotion

s~hedule

Firefightlng system layout drawing

24-Mar-ll

26·May-l1

27-Feb·ll

20-May-ll

30·Mar-1l

26-M"y-U

24·Mar-ll

24-May-ll

24-M.r-ll

i6-Apr·n

Detection and alarm layout draWing

1.51

0.52

Pplping Valves Vendor prints review Instrument Index

33.0&

3.59

I/o list Instrument Hook Up And Supporting Drawings Field Instrumenllayouts Field Instrument Cable Routing Instrument Bulk MRQ

Instrument Cable T,a s MRQ 33.33

1.66

24.26

3.10

Electrical Bulk MTO Civil standard drawings IFe

Misc. Steel supports found"tion plan & details IFD

Instrument I Fire & gas cables RFQ 4.29

0.47

3.09

0.24

Electrical bulk material RFQ I....trument Bulk RFQ Instrument I Fire & gas Cable Trays RFQ

The delay of MRQ's issuance 13·Apr-ll

26-May-ll

17·Feb·ll

18·May·ll

In progress Piping Valves start fabrication



Enpp1 PTB

SETH ONSHORE DEVELOPMENT

4187-440

Rev. (0 Egypt

MONTHLY PROGRESS REPORT No.2

18-MAY-2011

7.2.Progress Control Sheets

~

I I

Project No.: 4187·440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone Planned

Actual

Expected

As Of : 30-Apr-11

Milestone

* Relative

Value

Weight

Process cause and effect matrix

Start

:ZO-Feb-11

· . "De~i~~ 'i24~Feb-;; . ~ ............. ., . T

Construction

Fire and

.

•••••



«

cause and effect

: 07-Apr-11

,

. 19-May-11

· .. Co'n~lr'ucti~~ . -. -!24~Au~~11' . "

23-Au"g:11 .

." 11-Apr-11 . · 81art - - - - - :13-Mar-11 - .. Design : 17-Mar-11 · . -- -, ',' - ,- - 18-Apr-11 -Finish

«

: 17-Aug-11

08-Apr-11

Start

••

_

•••

_

•••

T

••

~e.si~~ •••••• Finish

16-Aug-11

_

22-May-11

20

31-Jul-11

40

27-Jul-11

20

02-Aug-11

40

:~~Jo6~De~-;1' •

" ••

:,~~:~8-AUi~~':_:_~.~ 40' ~

Commissioning procedure

:28-Nov-11 "

••••

_



•••

..............!, OS-Dec-11 . Design

Finish

4.27%

60.00%

0.00%

4.27%

0.00%

0.00%

4.27%

0.00%

0.00%

4.27%

60.00%

60.00%

. - - .... - .. - .... 40 . 2S-May-11 .

: 13-Nov-11

r

60.00%

40

,20-Nov-11

••

60.00%

20

Design

_

4.27%

40

Start

Start

20.00%

••••

Pre-commissioning procedure

•••

60.00%

....40- _.

Fire & gas 110 list

_

4.27%

. ... - - 40 _ ... _.-

"

••

20.00%

20 ••

Hazardous area classification schedule

Fi~is"h'

60.00%

: 27-Jul-11

Design

" •••

4.27%

•••

Start :03-Apr-11 . 25-Apr-11 .......... - -' "0"·············«

• ••

Actual Progress%

20

29-Mar-11 «

Planned Progress%

:21-Dec-11

11-Aug-11 ..... - .. 17-Aug-11 . .. ...

40

02-Sep-11

40

_

20

""

HSE philosophy specification

20 40 40

29.91%

I 42.86%

22.86%

Drawin s 3.42%

Fire fighting system layout drawing

Start

: 13-Mar-11

40

~o.n~tr.u:ti?~ • _ ~ .:!7:~u~-~~ •

40

•••

',' "

"

Layout NO.1

* Weights of Activities are calculated relative to (Process) Tuesday, May 17, 2011

60.00%

20

.. .. Design : 17-Mar-11 .............. , . "

60.00%

Page 1 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

I

Milestone

I Milestone

Dates

I

Expected

Actual

Planned

I

Value

I

As Of : 30-Apr-11

I

* Relative Weight

Planned Progress%

4.27%

60.00%

0.00%

4.27%

60.00%

60.00%

4.27%

60.00%

0.00%

Actual Progress%

Overall

~



«



Design «

12-May-11

:27-Mar-11

Start •••••••••

','









••



«««.«

••••

••••••••••••

",'

•••

«

"

•••••••

01-Sep-11

:04-Sep-11

Start "

•••••



-

••••

','

•••••

16.May-11

.... _. . . «_. ... .. _.

:03-Apr-11 -

Design

••••••

18-May-11 ....... .

:31-Mar-11

«

: 07-Apr-11

-.. C;n~t;ucti~~ ... '!11~Se~-11' .

20 ....... . .. 40 ... .

19-May-11

08-Sep-11

40

Detection and alarm layout drawing

Start •••

-

•••••••

,'OS-Mar-lt -



','

Design

!to-Mar-tt

Construction

:10-Aug-11

20

13-Apr-11

••••••••

,

«

•••

-

-

20-Apr-11

••••••••••••••, •••• -'. c - ••••••

Fire fighting, safety equipment and safety signs

~

.,

- Start -.-

••

a

Design ~

:20-Mar-11 ','

!24-Mar-11

C;n~t;ucti~~ ••• ·i24~Au;.;1·

15-May-11

.

;-

; a

,

. •••••••

"

y

20

26-May-11, 23-Aug:11 »

:

:

~



40 40· ••

20.51%

I 60.00% I 22.50%

20 40 10

30

Start

i27-Jan-11

Construction

: 20-Jul-11

20

10-Mar-11

40 19-Jul-11

40

Layout NO.1

... Weights of Activities are calculated relative to (Process) Tuesday, May 17, 2011

Page 2 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Milestone

i

I

I Milestone

Dates

II--'p"":-.-nn-e-d""'---A7"c:-t:-U-.:-,---:E:-x-p-e-ct:-e""'d-lI

Value

As Of : 30-Apr-11

I'"

Relative Weight

I

Planned Progress%

I

Actual Progress%

4.27%

Start

27-Jan-11

10-Mar-11

Design

17-Feb--11

17~Mar-11

Construction

20-Jul-11

. . . . . . . . . . . . . . . . . . . ..

Total

20

. 19-Jul-11

40

34.09%

Process

"" Weights of Activities are calculated relative to (Process) Tuesday, May 17, 2011

.

40

Layout No.1 Page 3 of 19

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone Planned

I

Milestone Value

Expected

Actual

As Of : 30-Apr-11

* Relative Weight

I

Planned Progress%

Actual Progress%

Overall

Specification for ins. Of UlG system.

·

Start

.. .21-Jul-11

"

"

Finish

ZQ-Jul-11

.

~

2.87%

0.00%

0.00%

2.87%

0.00%

0.00%

2.87%

60.00%

60.00%

30

27-Jul-11

Specification for field test of U/G system.

Start

28-Jul-11

•••••••••

«

••••••••••

"

•••••••

Finish

Piping Material Classes specification

:27-feb-11

Start ••••••••••

-

-

-

-

-.'

DesIgn "

•• -

~

-

-

-

:03-Mar-11

20

31-Mar-11

~

•••

••••••

,

«

.:.

20-Apr-11

Finish

..

..._.... ......__,'24-Aug-11 ......__..._..._._........-"-..... ~_

~

....



-

••

-

-

.

• • • • • • • • • ',' •••••• " ••••••• "

~~~~~~~ _-~

-

~-"-.-

,

-

-

•••

-



......

23~Aug-11

••••••• i

40

:20-Feb-11

Start •••••••••••

~

Design

',"

< ,

«

10-Mar-11 < •••••••

•••

", • • • • • • • •

:24-Feb-11

• •• Co
«

4



28-Mar-11 '!28~AU;-11' •." « « « « •••• ,. 25-Au·9:11"

:03-Mar-11

Start ••

<

"



<

,

••

«

••

',"

,



«

«

3.58%

60.00%

~

40

• " " " «

~

~

40

60.00%

20

15-Mar-11

••••••

--_._._------_._-_. 60.00% 60.00%

20 · .... .

Table



3.58%

~~~.~~~~~~""'''''''-'--_._~~.~~-~~----------------

Tie-In List

~

;

,40, •••••••• "

••••••••••••

~

"«.« •••

40

· - - 40 ---38.18%

:20-Feb-11 · -,' ..

Start

·.

Construction

..Start

·. ..

..

20 40

y

y

-

:10-Aug-11

.. 09--Aug-11

••

«

«

_

•••

~

_



~~n~t~u:ti?~

~

••• ,'

•••

•••

_

••

':~1.-~e~;~ _

~

«

•••

v

••

•••

"



5.02%

60.00%

60.00%

40

__

<

08-Sep-11

40

Layout NO.1

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17, 2011

60.00%

20

Start : 03-Apr-11 31-Mar-11 • - - De~i;~«' ~ ~ ~ ~ ·!Oi-Ap~-11· -:- - 07=A~;-1·1· •

60.00%

40

Underground composite drawing



4.30%

40

02-Aug-11

:27-Feb-11

-,'

Construction

60.00%

40

: 10-Mar-11

. . , 15-Mar-11 20-Mar-11 ... -« . .

60.00%

20

15--Mar~11

:03-Mar-11 .. .. 20-Mar-11 .. - . · ',":03-Aug-11

. Design . .-

_ ~~si~~

,

4.30%

Page4of19

Data'Nes Systems, Release 2.21

Issuance Status Report

Project No.: 4187·440

SETH ONSHORE PROJECT Dates

Milestone Planned

Actual

As Of : 30-Apr-11

Milestone Value

Expected

'It

Relative Weight

Planned Progress%

Actual Progress%

4.30%

60.00%

60.00%

4.30%

0.00%

0.00%

3.58%

60.00%

60.00%

3.58%

0.00%

0.00%

3.58%

0.00%

0.00%

Overall Engineering

Underground piping standard details 20 ...... . 40 ...... .

Start : 05-Apr-11 08-Apr-11 • •• De~i;~ •.•• " • 09-Ap~-:;1' • :. '14:A~;-1"1' •..• - " •••

·.

'i

~

','

"

Construction

. -

"

.

~

:06·Sep-.11

40

03-Sep-11

Hydrostatic test loops. Start :19-5ep-11 18-Sep-11 , ••• co'n~t;ucti~n' .•. ·i25~Se~11· • ~ .• - •••••:. 22-S~~11' .......................

~~_4~~_"__~_~'_

"-"_""_

_<..~~

__

___"__~

?_~

20

80 .. :

C

~L_~~~_~~~_~_

details

Standard

~.~

~

__

_ _" _ . _

~

~"_"_.~._.

20

Start : 14-Apr-11 31-Mar-11 • • ~ De~i~; •••••• '::;O~Ap;-11' • " • 21:A~:-1-1' • - • co'n~t;ucti~~ - - .

_"'"--~-'-

40

-i 03-0ct~:; 1" • , ••••.••

02-0ct-11

40

Special piping support Start : 02-0ct-11 29-Sep-11 • - • Co'n~t;u~i~n' ••• 1" • " .•••••••• l'

20 . 'OS-Oct-; . ...... 80

-i os-octo:;

Standard steel structure

list 20 ....... 80

32.97%

39.13%

39.13%

Commodities Piping Bulk

MRO

:17-Mar-11

22-Mar-11

3.58%

15.00%

15.00%

7.89%

65.00%

55.00%

....15.. .

. ... 30... "." -MRp······· ·i09-J·u~-11···-····"· ....... 09-Jun-11 1S 1. Evaluation

;.

~~~~

~

19-May-11

:19-May-11.

,

VPR start

-::26-Jun-11

VPR finish

:04-Aug-11

~~~

"

:

26-Jun-11

. .. . . ... . . .. 10 - ... 30

Ppiping Valves MRQ

=

: 04-Jan-11

1S

04-Jan-11

I :" .. --r. E~alu~ti'o~ ••• 'io2~Feb-;1' - ~ • 08~F~b.1·1· ... •• - • • •••••••

~J

~

VPR's~art'

-:;7~Feb-;1'

40

~

16-May-11 "" ..... mml •... VPR'fi~i;h' •••• '!05-0ct-11" • " ••••••• ... 13-Dec-11

11..

10

"

....

35

I_

Layout No.1

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17,2011

_%_,_

-!._1_1_.4_7.;.%_,_.I. 4_9_._38_'_Y'_.l.-4_2_.5_O

Page 5 of 19

Data'Nes Systems, Release 2_21

Project No.: 4187·440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone Planned

Actual

* Relative Weight

Milestone Value

Expected

As Of : 30-Apr-11

Planned Progress%

Actual Progress%

Overall

....Start "."""

2B.Sep-11

Finish

09-0ct-11

.

.......

27-Sep-11

20

"

-.'

OS-Oct-11

0.00%

0.00%

3.58%

100.00%

80,00%

3.58%

100.00%

100.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

:

80

,

3.58%

,

--".-"-'--'~'.~""""~~--""~.""""'''---<''-''---''-''''''''''''"------

:27-Feb-11

:03-Mar~11

Start

20

27-Dec-11

15-Mar-11

20

,

. _._. _

L_:~_~ FI~I;h - .. ~_:~~M~'r-11'-~_~_~~~M~i~~_~:~:_: ~~~_: ~~~~_~~~_~ Piping bulk final MTO

~~_._._

Start Finish

Piping valves final MTO

Finish

........ ,

o o

19-Jul-11

--

29-Jun-11

66.67%

10.75%

60.00%

GA~

Piping GA drawing area

•••

~

«

«

»

»

»

»



«

••

','

Design •

-

•••••

•••••

»

»»»«««

-

-.-

-

«

«

«

«

-,

Construction

• • • • • • •

.».

-

-

-

-

•••

9.68%

0.00%

0.00%

_.«»

-,_

•••••••

19-5ep-.11

:20-Sep-11

Existing piping GA drawing area

20-Jul-11

Start

0.00%

10-Aug-11

: 28-Jul-11 -

0.00%

28-Aug-11

: 20-Jul-11

Start

~

.

8.60%

~""---"~'.'»'---'--

..28-Aug-11 - _ ..... ..28-Jul-11

••••

»»

20

»





-



»

~

0 I ~. ~ .~e.si~~ •• ~~-~u~-~1•• ...... 19-5ep-.11 80 ~I Construction 20-Sep-11 1lI1d==~~~~~==~~'='='===~::::==;==:=:=~~ 18.28% 0.00% 0.00% iii «



«

••





M



«

,

[ti~----------------------------------"'-----"'----"'---€Ij!j-F~;='==;===:='=================:::::::==;:=;=~::::=:::::::===='" ili~ i2ill Piping isometrics 10.75% 0.00% 0.00% ffJii/SO's

~

II

Bh "

~::;r~cti;~

----:~:~~:;~{ ~ ~

- -~~~;:f~~ ~ ~ ~ ~ .~~ ..

i;;lIIF====~='===~~~~~='=====r~::==F~==;=:===

1lI1------------------------------J-------J------..I,------10.75%

5.

., Weights of Activities are calculated relative to (Piping) Tuesday, May 17, 2011

0.00%

0.00%

Layout No.1 Page 6 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone Planned

Actual

Expected

Milestone Value

As Of : 30-Apr-11

* Relative Weight

Planned Progress%

Actual Progress%

Overall

I

b

* Weights of Activities are calculated relative to (Piping) Tuesday, May 17, 2011

Layout NO.1 Page 7 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

I Milestone

Dates

Milestone Planned

Actual

Expected

I

I

Value

* Relative Weight

Finish

18-May-11

.

· .. ~e.si~~ . • • • . • . ~4.-~e~~ 1. .

.

26-Jul-11

27-JuJ-11

40 40

Loose Instrument data sheets

:27-Feb-11

.--

· .. ~e.sj~~

3.70% 20

.

:?3:'~a:-~1.. !03:AU~-~1

Finish

Instrument Cable Schedule

. - _.

Start ~'-'--'.'

"

• • • • • • • •

:30-Mar-11 __



"

",

_

"

•••••

.

3.70%

60.00%

60.00%

~

20

••••

__

- .. ,

"

14-Apr-11

, •

_,

,40, T

• • • • • • •

~

• • • • •

_



_J.---,--_,,---,-.?~~~~~~~:~P-11....>.-.~-"-"-'-...~~._~~"---"---,,_,,_~.~,,-.-<-.,

,

.__..._ .._.

.__.

3.70%

Sand probes data sheets

_

: 60.00%

20.00%

20

Start

Start

i 10-Mar-11

Design

: 16-Mar-11

18-May-11 •••

.......... - - - -, - . - ....

z

20

•••

24-May-11

40

16-Aug-11

40

layout NO.1

* Weights of Activities are calculated relative to (Instrumentation) Tuesday, May 17, 2011

0.00%

"-19-M~Y~1;'

, 10-Apr-11 .. " - ' .:24-Mar-11 ""-'-'--"'"

Design

60.00%

...... ',' 23-Au"9:11 .

:24-Aug-11

Finish

3.70% 16-May-11

. _ . __ .. !~7.-~a!-~1..

· __ ~e.si~~ .... __ .!~3:~a!-~1. _

,

Actual Progress%

20

15-May-11

20-Feb-11

Start

Start

Planned Progress%

7.41%

Instrument Index

Start

As Of: 30-Apr-11

Page 8 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone

Milestone

Actual

Planned

Expected

Value

As Of : 30-Apr-11

'" Relative Weight

Planned Progress%

4.94%

60.00%

Actual Progress%

Overall

Junction Box Interconnections

;.

•••••

«

25-May-11

: 17-Mar-11

Start ~

•••••••

.. - Design

','

••••••

:23-Mar-11

",'



••

«

20

••••••••••••

.

:23:-AU~-11

Construction

0.00%

26-May-11

40

22-Aug-11

40

23.46%

60.00%

0.00%

Commodities Instrument I Fire &

19.75%

cables

MRQ ...... - . - - - - - : -07-Apr-11 - - - - .. T. Evaluation ............. ' ,:29-May-11 ' . s1art .. _.VPR - -' _ ..,: 14-Jul-11 . "

.

19-May-11

.

20

26-Jun-11

40

1B-Jul-11

10

"

VPR finish

17.28%

Instrument Bulk

20.00%

0.00%

20 40

10

30

Total

Instrumentation

5.19%

'" Weights of Activities are calculated relative to (Instrumentation) Tuesday, May 17, 2011

Layout No.1 Page 9 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

I

Milestone

I

Dates Planned

Actual

Expected

Milestone Value

As Of : 30-Apr-11

* Relative Weight

Planned Progress%

Actual Progress%

Overall

22.22%

60.00%

60.00%

22.22%

60.00%

60.00%

22.22%

60.00%

60.00%

20 ...

40

.. ....... 28-Apr-11

~~si~~ • • • • . . . ~0:~a!-!1 Construction 10-Aug-11

09-Aug-11

40

Electrical grounding layout

13-Apr-11 ....... 17-Apr-11 !~7:~a:-!1.. .... - --

Start "

20

: 13-Mar-11

••••••••••••• ',"'"«"

.... I?e.si~~ _ Construction - - - .....

:17-Aug-11

40 16-Aug-11

40

Hazardous area classification layout

Construction

14-Apr-11 .... - - - -.- - - - - - --

20-Mar-11

Start

. . . l?e.si~~ __ .. __ . ~4:~a!-~ i.

_

. ~S:A?~-1.1

. 23-Aug-11

.•• ~4-Aug-11

20

40 40

60.00%

33.33%

Electrical Lighting MRQ

Start

20-Mar-11

Finish

24-Mar-11

..• "" ••

~: ~ ~~-~~Y:1~ . 24-May-11

20

, 100.00%

0.00% 40.00%

Electrical

Layout No.1

., Weights of Activities are calculated relative to (Electrical) Tuesday, May 17, 2011

0.00%

80

33.33%

Total

100.00%

Page 10 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

I Milestone

Dates

Milestone Planned

Actual

Expected

1

Value

I

As Of : 30·Apr·11

I..

I

Relative Weight

Planned Progress%

Actual

Progress%

Overall

100.00%

MRO

04-Jan-11

04-Jan-11

15

T. Evaluation

02-Feb-11

13-Feb-11

40

VPR start

20-Mar-11

28-Mar-11

VPR finish

28-Jun-11

65.00%

65.00%

10 21-Jul-11

35

65.00% Total

65.00%

Pressure Vessels

Layout No.1

.. Weights of Activities are calculated relative to (Pressure Vessels) Tuesday, May 17, 2011

Page 11 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

As Of : 30-Apr-11

SETH ONSHORE PROJECT Dates

Milestone Planned

* Relative

Milestone Value

Expected

Actual

Weight

Planned Progress%

Actual Progress%

Overall Engineering

Concrete Specification



«

~t~rt• • • . • • . • . 9~-~p~-!1••



... 9,:Si~~ ...

«

•••

Finish

Start -

••••

»

.......

"

-

-

-



-



50.00%

50.00%

10 «

"

••

40

17-Apr~11

: 18-Apr-11 -

1.85%

50

: 06-Apr-11 . ~O:Ap~-~1» .' .... ...... - ",'" "" ... ••••••

50.00%

40

17-Apr-11

Shim and grouting Specification

Design

50.00%

10

" :O:Ap~-~1 . . .......

!~-~P~-!1•• 13-May-11

1.85%

.« ••••••.•••••.

»

Fi~is_h _ •• _ •••• :~3-May-11

50

«

:~-~aY-11

.

hqyF='::'=~~=c=~~==~===!==~====:=:::o:;===c:::~==::~= ..r.~.,.; structural st••1fabrication Sp.cification 1.85% 50.00% 50.00%

.-;:;\

III

_.» Start ••

»»

: 06-Apr-11 ••

_.

-

-

-,-

Design

-

_.

-

, 1D-Apr-11 -» •••••••• -.- - _. - - - -

: 18-Apr-11

II

.. -

1m i.~.J. ".,~.:.~~

••• ~t~rt_ _ • _

10

17-Apr-11:

!

-';

40

- .... _. >j3~Ma~'11' - -' ;8-M~Y~1;' . - - 50 -'; gl="S=ite::=p"r."p"'a"'ra=t:Oio"n"',"'e=a=rt:Oh"W"O"'rk:;=;&""ba"'ckfi"":~IiI"S"P"""'C:Cifi"'lc"a'"ti"'on""'=:=:====:=:""====::=±o=======1"."8"5'''~===;5::0:=.0:=0:=%;;=="5::0:=.0:'0"'::~=

§it

Fi~is-h

«

«

~ £?~si~~

T'

»

_



»



••

_.-

°

~O:A?~-1.1_

1. ~ ~ • _ •• , __ • " . • • •

~7:Ap~-1.1 . .... ~ ..

• • • • • •

«

«

«

"

«

••

~o••

_

11=""==:"",F=;n";~'h==:=:====:.=:=."",,,,,,,,,,~,,,,,,,,,,::=,,,,,,,,,,=,,,,8=.,,M,,a,,,Y'=',,,,,,,,,,,,,,,,,,,,,,,,5,,0=='========7':0=:':='==:=:::=:'=:==0=::=:'",,=" Concrete paving Specification 1.85% 50.00% 50.00%

linE

:s2& ""lW

,[g~~. ~.c

___.•:

~:g

10 ~. ~,~t~rt• • • • • • • • • :?6"-~P~-!1•• ~. ~O:Ap~-1.1••:.. YTY«.«,. ••••••• ; Design

: 18-Apr-11

,

17-Apr-11

,

40

r.i.F.-~,=±'"·"·",·~F=·;"~",i;,,h=:~:~.·~~:.,,·.=·,,,,,:,,·~j1",3~:M,,'a~~~'-~"='"'='=='"'~',,,,,' "'",'",,,'".~.'='8-",'=M",a~'y=:,=;",'~'"',,,'=' -............... ........ "5",0'", ,',,'±=========:=::'::===='0=:0:7===':':':C:==

::::::t

II II

r.: t.,: · ~

...; "

£:::

~

-"---'-~-"-----"-"-"-..;,-"-

_,~_.......:.._."-

Soil & foundation investigation Specification

: : :

~::~~~

: : : : : : :

Finish.

~~:~:;:;::

:~3-May-11

:

----~-

2.78%

50.00%

50.00%

10

· ~0:Ap~.~1. · :7:Ap~.~1.

40 18--May-11

50

1l=='=Ex==:is"'t=in=g"p=/~RO=V"''''ri~fi''ca''ti~'o=n-2r''''p'''o'''rt±=±====:=:'''''-2==±::=="""""=====±=======~2~3~.~15~'~l\===~0~.0~0~%C===0:'.=0~0~%,:=,=

30 ;1 ~::'h - ·:~~1~;~;; . 70 f~1 I 11l------------------. . .-------------..I.----...l----..I.---02-Jun-11 15·Jun·11

35.19%

17.11%

17.11%

!;D~r.~.s~~~~~:~:~:~1g=.=n".=ra"l=n=ot:='='========================="3:=.7='0"%;;===;1=00='.:::0"0':=~==::60='.:::0=0'?~=

IZi §i !l1§j

a ej @ill.'i

_I

Start

. --De~i;~

............. Construction

!20-Feb-11 '!24~Feb-l1- • ','

.

10

• ~3:A'p~-1.1. 14-Apr-11

: 17-Mar-11

50 24·May·11

40

Layout NO.1

* Weights of Activities are calculated relative to (Civil) Tuesday, May 17, 2011

Page 12 of 19

Data'Nes Systems, Release 2.21

Project No.:

4187-440

Issuance Status Report

As Of:30-Apr-11

SETH ONSHORE PROJECT Dates

Milestone

I

Milestone Expected

Actual

Planned

Value

* Relative Weight

I

Planned Progress%

Actual Progress%

Drawings 2.76%

Anchor bolts standard details

:20-Feb-11

Start •••••••••••

«

•• , •••••••

Design •













:24-Feb-11 •











','

•••••

03-Apr-11 ...... .

10

~4:A?~-~1 •

50

«

«

40

24-MaY-11

Construction

2.78%

standard details

". - Start _

-' .,;20-Feb-11

Design •••••••••••

.

:24-Feb-11 "

•• , -

Construction

Start

«

•••••

: 17-Mar-11

:20-Feb-11

03-Apr-11 .... - - - .,, 14-Apr-11 ~ ~ ~ ~e:Si~~ : :: : :: :!~4:~e~-~1~ ~ ....... ' , " Construction

: 17-Mar-11

. . 24-May-11

:12-MaY-11

91 ~

",

;.

19-May-11,

••••••

60.00%

0.00%

11.11%

0.00%

0.00%

10

12.96%

: 60.00%

,

• ••••.

New slug catcher foundation plan & details

§

8.33%

40

~e.si9~ ••••.• • :~o:~ay-}~ ~:-~~Y:1~ ~ : ~ ~ • :0.••. Con:tr~~~~ ..".,"-,,-1~~~~~,,~.->--"-'C-,-~~:~~~-, __~~~4~~~: __ ~

;1_-...

60.00%

10

Valves foundation plan & details Start

100.00%

50

Misc. Steel supports foundation plan & details

~'"'_ • • • • • "*'*:_""'H~""'.'

2.78%

~

.__.

._

0.00%

ii!E

4QWf

1m

Start

05-Jun-11

: 19-Jan-11

til .--De'si~~ ••• ~ • - -i;6-J-a~-11"

II .

«

•••••••••••

••

T

••

«

-i18~Au~-;1·· ••..••

-

-,

-

««.

23-M~y~1; • 09-Au9:11 .

10

50 40

·§fjfF==;;;;=====":~=='==="'===~==='=======c===~o=====o==== ~ steel details 11.11 % 60.00%

"Wi

I ,

ill

St~rt

Design

!"Ap~.~,

' .. , ,: 26-Apr-1l ,

.

:~"~~Y:'~

26-May-11.

10 50

.

1I1==',=='"'"'=c"o,,'n,,;t,,;"=ct=i~=n,,",,',,'='=',,,!2,,'0,,:,,se,,;""",""'"',,'=',,,,,""',,'='=',,,,'"· "·='=9,,·.A, ·U, ·g, :,=', , ,·"',,',,'='=4,,'0, ',,'='''''=====r======r=====r=====

1I:... II

55.56%

56.67%

...l_;.;,~.;,;,_..l....;.:......;;.....l

.....,;,;,;.;.;;.,_ 13.00%

=MTO ~--

I

iliili

~

~I

9.26%

Civil MTO Start

:OS-May-11

,

19-May-11

20

'_.: ~ ~i~jS~: :: .. :: >o~~ar-}~·'····:::::: ~~-~~y~1;· r··· 80"

;~l:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::~:::9.:2:6:%:::~1::0:.0:0:'/.:'::~::0:.0:0:'/.:.:: Layout No.1

* Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011

Page 13 of 19

Dala'Nes Systems, Release 2.21

Project No.: 4187·440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone Planned

Actual

Expected

Milestone Value

As Of : 30-Apr-11

, * Relative Weight

I

Planned Progress%

Actual

Progress%

Overall

• Weights of Activities are calculated relative to (Civil) Tuesday, May 17, 2011

Layout NO.1 Page 14 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Actual

Planned

I

I Milestone

Dates

Milestone

* Relative

Value

t

Expected

As Of : 30-Apr-11

Weight

Planned Progress%

I

Actual Progress%

Overall Procurement

Fire detection

24-Feb-11

RFQ 11-Apr-11 .....................

I I I

Rec.Bids

.-

OZ·May-11

••••••••••••••••••

«

23-Mar-11

.-

••

C. Evaluation

13-Jun-11

F.OA

20-Jun-11

-"fi

fi

RFQ

40.00%

9.52%

40.00%

40.00%

9.52%

10.00%

0.00%

11.90%

40.00%

40.00%

9.52%

100.00%

100.00%

9.52%

40.00%

0.00%

10



10-Jul-11

---

---17-Jul-11

10

- .... - , -24-Mar-11 - ... . 11-Apr-11 18-Apr-11 ... - .. - " ..... "

10.00%

30

Piping Bulk

Rec.Bids

9.52%

~

~

C. Evaluation

02-Jun-11

30

F.GA

09-Jun-11

30

16.67%

Catcher

·

30

20-Jan-11

Rec.Bids

22-Dec-10

RFQ

OS-Feb-11

03-Jan-11

10

17-Feb-11

10-Mar-11

30

15-Mar-11

30

-. - - -

---

"

C. Evaluation

F.OA

Instrument I Fire & gas cables

RFQ •

••

-



11-Apr-11

-

-

-

••••

~

••••

-



02-Jun-11 -

-

Rec.Bids

· - ...

.. - - - -

,

"

~

c. Evaluation

12-Jun~11

F.OA

19-Jun-11

-

••

...

"

"

••

~

,

••

<

-

-

-

10 -

29-May-11

30

10-Jul-11

30

- ..... ".. . ...

---

30

Fire protection system

· .. RFQ - " . - ... ,

"

,

!-04-Apr-11 ... .. -24-Feb-11 . -. .

.,

"

"

~

........... ". ",." C Evaluation

:17-May-11, 10-Jun-11 !;5-J·u~-11· • ~ • " ••••••,' ·15-ju~-;1 •

4

••

:22-Dec-10

Rec.Bids ••

»

"

,

"

••

28-Mar-11

30

: 07-Apr-11

· ~ ~ F.O.A." ....



10

"

Rec.Bids

"

RFQ



"

"

-, • • • •

-

••

:OS-Feb-11

~

"

18-Jan-11 "

••••

"

"

30 30

30

"

_

05-Jan-11

-:

10

· . .. - . - - - ... .... - ...- - - - - - .. .... - - - -,- - - - _ ... "

~

· - RFQ ... - . .. - :28-Mar-11 --- - . Rec.Bids 18-Apr-11 - .. - ... - - .. - -,: .... -. C. Evaluation :OS-May-11 - .. - - . ' , ' .. - - - ..... · . "~''?~ __ . __:~2~~ar-}: . "

,

~

~

"

~

02-Jun-11

10

02-Jun-11

30

, ,'

~

"

~

"

_.

..28-May·11 - - . . .. 04-Jun-11

_

30 .... -. 30

., Weights of Activities are calculated relative to (Purchasing) Tuesday, May 17, 2011

layout No.1 Page 15 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone

Actual

Planned

Milestone Value

Expected

As Of : 30-Apr-11

,., Relative

Planned Progress%

Weight

Actual Progress%

Overall

11.90%

Instrument Bulk

RFQ «

11-Apr-11

•••••

«

••

««.«

••

Rec.Bids «

«

•••••

_

«

26--Jun-11

•••••••••

«««««.

«««

01-MaY-11 •••••••

«

•••

_

10 •••

05-Jun-11

"

«

••

«

••

«

A

A

•••

«

«

«

C. Evaluation

12-Jun-11

17-Jul-11

F.G.A.

19-Jun-11

24-Jul-11

«««

«

Instrument I Fire & gas Cable Trays

I

~~I

RFQ "

«

«

••

«

«

«-«

-

11.90%

: 13-Apr-11 -

«

«

••

Rec.Bids

C.·E~u~t;o~

«

«

".'

•••

-

-

-

«



«

«

«



:03-May-11

- "i 14-jU~-11- «

••

30

-

«

«

«



0.00%

10

25-MaYc11

---

10.00%

«

07-Jun-11

30

19-Jul-11

30

IIill=",'=·=·=·~,:~.o"·."A,,.·=·=·=·=·=·==·.:·i";='~,;,J·U,,;=-;~,'==',='"'='=-='='=='='='2=6='J=~='-=;'='=-,,,='='='=3=0='='='~====r=======T=======;======= ...--..-- ...... 100.00%

Total

38.57%

38.57%

Purchasing

Layout No.1

"Weights of Activities are calculated relative to (Purchasing) Tuesday, May 17, 2011

42.86%

Page 16 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT Dates

Milestone

Actual

Planned

Expected

Milestone Value

As Of :30-Apr-11

* Relative Weight

Planned Progress%

Actual

Progress%

20

24-Dec~11

30

16-Jan-12 16-Jan-12

12-Feb-12

20

10

Start

09-Jun-l1

VPR start

26-Jun-11

..

10

VPR finish

04-Aug-11

20

SID.Award

16-Nov-l1

20

Fab. Finish

26-Dec-11

30

Fab. Start

17-Mar-l1

10

VPR start

2a-Mar-It

10

.

VPR finish

21-Jul-l1

S/D.Award

14-0ct-l1

20

23-Dec-l1

30

.

20

17-Jul-l1

10

03-Jan-12

20

12-feb-12

30

18-Jul-!1

17·Jul-l1

Fab. Finish

....... , 16-Jan-12 .... - ..

-

~

10

28-Jul-1!

20

03-Jan-12

20

12-Feb-12 '

10

17-Jul-l1

.

30

." Weights of Activities are calculated relative to (Expediting) Tuesday, May 17, 2011

Layout NO.1 Page 17 of 19

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Planned

I

I Milestone

Dates

Milestone

Expected!

Actual

Value

As Of : 30-Apr-11

I

* Relative

Planned Progress%

Weight

Actual Progress%

Overall Procurement

10.29% Fab. Start ••••••••



_

~

•••••••••

",'

• • • • •



•••••••

"

.......

4

•••••

«



,

10

18-Apr-11

: 17-Feb-11

• • • • • • • • • • • • •

10

24-Apr-11 .......

: 17-Feb-11 ••

Start

VPR start ....... - - , - - . ' ,:06-Mar-11 ' .. - ...

18-MaY-11,

10

,

· 22-Ju~-·11· "- .. 20' - . ; "-. -SjO.A~rd .. -. '!06~AU~-11- • ~ ..... _. . "14-0d-11- ~ ... 20' . , ~

VPR finish

" 14-Apr-11

,

I ~~~~~a~ !~n~~~~~i~-~i~~~~_~~~_~~~~ ~_~_;;1~:_~~~_L_~ Electrical bulk material

- .. ',':12-May-11 .

Start

05-Jun-11

•••••Fab. ». Start _." -, ..•,:12-May-11 .••.•• "

· ·

,~ •• ~~R"s!a~

· _

,.

y

k

S/O.Award

~

«

"

.. .. "

VPR finish

','

.



........ :

: 09-0c1-11

•• "

10 10

10.29%

0.00%

0.00%

10.29%

0.00%

0.00%

:

.

10 ,.""."."

22-Sep-11:

:30-Aug-11

09-0ct-11- -

~

05-Jun-11

)~2:~ay-.1~.

Fab"Finish • - • " ":

....... " ••

~

05-Jun-11

_

"

•• -

~

01-Nov-11

20

,

,. • • • • • • • i

01-Nov-11

30

:

20'

100.00%

Total

Expediting

7.35% 7.35%

* Weights of Activities are calculated relative to (Expediting) Tuesday, May 17, 2011

1 10 .44 %

layout NO.1 Page 18 of 19

Data'Nes Systems, Release 2_21

Project No.: 4187-440

Issuance Status Report

As Of : 30-Apr-11

SETH ONSHORE PROJECT Dates

Milestone Planned

Actual

Expected

Milestone Value

* Relative

Planned

Weight

Progress%

Actual Progress%

Overall Procurement

Fire detection system

NFl RFS Bulk

«

•••••••••

«

OS-Feb-12 . .......

••

..

«

....

RFS'

!19-Dec-11 «



,

«

••

NFl RFS

««.

_

0.00%

8.33%

0.00%

0.00%

16.67%

0.00%

0.00%

12.50%

0.00%

0.00%

12.50%

0.00%

0.00%

v««.

60

19-Dec-11,

40

._"

~ ~~J.~~~~~_~~_~:~~~_~_:_~_~2i~~:~~~_~_~.~~?~~:

«

Slug Catcher

_

0.00%

40 ••

12-Feb-12

NFl

8.33%

v.««

_

__

Instrument I Fire & gas cables

NFl

RFS

Fire protection system

NFl

!!11=;;;::;~RF~Sc====d~~~=====~~~±=~====~==;;o:~==;=~===;;o:===; Piping valves 8.33% 0.00% 0.00% ~

1'=

!6W

III ~

NFl

til ~ .. -RFS' --

: 08-0ct-11

T

-



-

-j15-o~-;1"

~

PiF~~'''-~,,-=,·-=-=·,,-:==·::;.-=~=-'''--,,~'C--,,·-'''=-=·=·-=-'-=--'~~"-=.-=.,-=,.=

•II= """"

Electrical bulk material

16-Dec-11

...

40

60' -«: .•=-.=.-=",-='=,'".•,,.= . -..-=.-=' ,, =.=-.~=-="".-='-=."-=.=. ,"-="-=.--=--=-,,-.,,--=.-=--=-'~-.~~=-~-==-~"'~~--~--~-,,-'=-'::c_:=-~-c;-=-=c-~--,,-~--=-~-=-~--=c=",,-:== ««

••

-:-

23-6~c~1; - ~«- -

8.33%

0.00%

0.00%

=

illtH

""

NFl

: 02-0ct-11

25-0cl-11

,

40

RFS···· ~. ·'09-0ct-11"·'·· 60 01-Nov-11 IFC±I"n"st:=ru=m~e"n:=t;:;B=U;;.lk====~~~~<±====""======'====='=======':1"2".5"0:::%""==0"."0"0:::%""==:0 0".0"0:::.."',=

I,-

II iii

¥

~ ... ~~I . • • • _ •

a

-

*

_

RFS

y

.:

~O.-?~-~1_ •

v

" ...•

•••

~

••



.1~-~~V-.1~.

• ••

~Oy

•.

60

21-Nov-11

: 17-0ct·11

¥,§Fo\:'='===:7:==:=;;'7==!:::~~=~=========='====='=====;==';;;:;;;:::f===;::;;;:::f==::'::::::""=; §Ii Instrument I Fire & gas Cable Trays 12.50% 0.00% 0.00%

n $Wi II

~

. " .

~~I . . . . . . . . •: ~2..C?C:-~1. . ~ ...

1~-~~V~1~ _

.'.

~o.. _

IIF=,==R=F=s==-=.=-=-=-=-=.,=:~~9.=-O=.ct=:='='.=-<±'=.=_=.=.=.=.=.=.=.=2=3-=N=~=V'=.'='=.====6=0=""'=====;=1~O~O~.O~O~,~y,,==r=O~.O~O~'''y,,==;=O~.~O~O~'I.~,= Total

y

•••

_:

••

0.00%

Inspection

layout No.1

* Weights of Activities are calculated relative to (Inspection) Tuesday, May 17, 2011

Page 190f19

Data'Nes Systems, Release 2.21



E:n.PP1 PTB

SETH ONSHORE DEVELOPMENT

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.3. Updated Schedule

18-MAY-2011

4187.440, PETROBEL

Enppl

04-Jan-11

Slug Catcher Data Sheets

Evaluation (Slug Catcher) VPR (Slug Catcher)

. . . Actual Work 1_00:';'/";;>:1 Remaining Work

I!iBIIIIIIIl Critical Remaining Work: •

• Milestone

Page 1 of10

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30·Apr-11

Summary

30

02-Feb-11

70 20-Mar-11

28-Jun-11

Start Date: 22..Dec-10 Finish Date : 26·Feb~12 Data Date: 30·Ap....11

Date 18-May-11

Rav.O

By: Haytham A.Rahman Revision Checked A.Fathy

Approved M. Abushanab

Print Date: 16-May-11

'~~-"'-'---

4187-440, PETROBEL

Enppl

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

HSE philosophy IFD

18 06 Mar-11

03-Apr-11 A

cause and effect

5 20-Feb-11

31-Mar 11 A

Fire

5 03-Apr-11

09-May-11

cause and effect IFC

5 21-Jul-11

M

Com missioning

M

R

M

M

20 Nov-11 M

IFF

M

27 Jul 11 28 Jul 11 M

M

-Aug-11 Hazardous Area Classification

02 May 11

03-Aug-11 10-Aug-11

17-Aug-11

11-Aug-11

17-Aug-11

Page 2 of 10

Enppl

4187.440, PETROBEL SETH ONSHORE DEVELOPMENT PRO~ECT UPDATED SCHEDULE AS OF 30-Apr-11

10 06 Mar·11 M

10 Mar-11 M

5 A2200

0 20-Mar-11

24-Mar-11

02-May-11

02-May-11

A2240

5 27-Mar-11

31-Mar-11

02-May-11

08-May-11

5 03-Apr-11

07-Apr-11

09-May-11

15-May-11

20-Jul-11

07-Jul-11

20-Jul-11

10-Aug-11

04-Aug-11

A2260

Junction Box Interconnecting Wiring Diagram IFD

A1560

P&ID's IFC

A2230 A1570

And Alarm Layout DraVllings IFe Fire Fighting

Drawings IFe

11-Aug-11 24-Aug-11

A2250

5 25-Aug-11

A2270

5 05-Sep-11

Fighting System MRQ A1990 A1590

Technical Fire Fighting System VPR

DETECTION AND GAS SYSTEM

18-Aug-1.1

11-Sep-11

24-Aug-11

11-Sep-11

24-Mar-11

18-Feb-11 A

24-Feb-11 A

10-May-11

28-Mar-11 A

15-May-11 01-Aug-11

Page 3 of 10

4187-440, PETROBEL

Enppl

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

5

20

23-Mar-11 A

03-Aug-ll

A3180 A3200

Under Ground Piping Standard Details IFD

l4-Apr-1l

A1630 A3290

03-Aug-11

Under Ground Composite Drawing IFe (Header)

6 25 04-Aug-l 5 05-Sep-ll

ll-Aug-ll

04-Aug-ll

ep-ll

04-Aug-ll

ll-Sep-ll

05-Sep-ll

ll-Sep-ll

24-Feb-ll A2330

piping specification

IFD

03-Mar-11

Page 4 of 10

Enppl A3220

Under Ground Specification

A2340

piping specification dasses IFe

4187-440, PETROBEL SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

A2380 A2360

Line Designation Tables JFC

A3250 A2400

IFe Standard Steel Structure Support List IFC

A3230 A3260

Cable Routing IFD

16-Mar-11

,J'7~"~;:,:i-------- i2;;3':_'Mi~a;r:_;1-11 --I n09Q'-'M,ia~;Y;:-:'1 11 -I-,;;:"i~;;:; A2450

Loop Diagrams

30-Mar-11

16-May-11

Page 5 of 10

Enpp l

4187.440, PETROBEL SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30.Apr-11

A2410 A2440

Aug-11

A2460

11-Aug-11

17-Aug-11

17-Aug-11

23-Aug-11

24-Aug-11

Instrument Hook Up And Supporting Drawings IFD

--CO"~,:: ------- 'Instrument Index IFD

"."

5 27-Feb-11

03 Mar 11

02-May-11

08-May-11

17~Mar~11

23-Mar~11

09-May-11

15-MaY-11

27-Jul-11

21-Jul-11

M

A2510

Instrument Cable Schedule IFD

5

A1970

Instrument Index [Fe

5 21-Jul-11

A2500

~.,~,~-~~"~"

24~FebM11

R

A2490

..

0 20 Feb 11

R

M

02 MaY 11 w

03-Aug-11

M

03-Aug-11

Drawings 18-Aug-11

Page 6 of 10

Enppl A2850

Instrument Cable Trays MRQ's

AZ860

Instrument

AZ870

Instrument Cable Trays VPR

A2570

Trays

4187-440, PETROBEL SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

30 Mar-11 R

Evaluation

HazardousArea Classification Layout IFD

31-May-11

16-May-1

31-0CI-11

16-May

16-May-11

9-Jun-11

06-Ju~11

8-Aug-11

31-0cl-11

0 20-Mar-11

28-Apr-l1 A

0 06-Mar-11

10-Mar-11

5 20·Mar-11

24-Mar-11

5 04-Aug-11

10-Aug-11

02-May-11 02-May-11

08-May-11

04-Aug-11

10-Aug-11

w · · , ' n n n n n m m " , _ •• ,

IFe AZ580 A3310

AZ050

11-Aug-11

Layout [Fe

18-Aug-11

11-Aug-11

17-Aug-11

24-Aug-11

18-Aug-11

24-Aug-11

24-Aug-l1

18-Aug-11

30-Apr-11

Page 7 of 10

Enppl

AZ670

4187-440, PETROBEL SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Ap....11

Drawings

A1740

Drawings

A1750

Slug catcher Foundation Drawings IFe

AZ6S0

Valves Foundation Drawings JFC

support Foundation Drawings

A17S0 A1790 •.•.... :A;;'l"S:OOOO

A2730

.. !F~i;;i~,;ti~~lu:Pt:o" 'R"F"S·····

Bidding

....•...........

,

~;~f;,;., ;~:;; ................• ;Z'O"-';D~'e"c'-·'1"1··········· i ··'Z·'Z-'M'·a"'y'- ;1;1

20 1Z·Apr·11

02-May·11

24-Feb-11 A

i

;1 'S-;D'e'c'-';1';1

i

Page 8 of 10

Enppl

A1860 A1870 A1880 A3280

4187-440, PETROBEL SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

Page 9 of 10

Enppt

4187.440, PETROBEL

Page 10 of 10

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr·11

A1940

21

A1950

Electrical Bulk Commercial Evaluation Upto PO Issuance By PTS

A1960

Electrical Bulk Fabrication Upto RFS

15 19·Apr-11

12-May-11

12-May-11

09-0cl-11

23-May-11 03~Nov-11

I

I:



E:n.PP1 PTB

SETH ONSHORE DEVELOPMENT

4187-440

Rev. (0 Egypt

MONTHLY PROGRESS REPORT No.2

7A.Critical and Near Critical Activities

18-MAY-2011

E.nppl

4187-440, PETROBEL

Page 1 of 2

SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30·Apr-11

Commercial Evaluation Upto PO Issuance By

PTS

. . . . Actual Work !.;",,+ x,',;, ! Remaining Work

_ •

Critical Remaining Work •

Milestone

Summary

Start Date: 22·Dec-10 Finish Date: 26-Feb-12 Data Date: 30-Apr..11 Print Date: 16-May-11

By: Haytham A.Rahman Date 1S·May-11

Revision

Rev.O

Checked A.Fathy

Approved M. Abushanab

Enppl

4187.440, PETROBEL SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30·Apr·11

Page 2 of 2

PTB

SETII ONSHORE DEVELOPMENT

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7. S. One Month Look Ahead Report

18-MAY-2011

Project No.: 4187-440

Lookahead Report As Of:

SETH ONSHORE PROJECT

Forecast Date: Dates Milestone

Expected

Planned

" Relative Weight

Milestone Value

Planned Progress%

30-Apr-11 28-May~11

Actual Progress%

Overall

Process cause and effect matrix

Design

Fire and gas cause and effect

07-Apr-11

Design

19-May-11

Start D';Sig~

08-Apr-11

22-May-11

20.00%

4.27%

: 60.00%

0.00%

4.27%

60.00%

0.00%

4.27%

60.00%

0.00%

4.27%

60.00%

0.00%

11.11%

20.00%

20.00%

20

- - - - ~ -,' . ;2-AP~-11- -: - 25-M~Y=11- . - . -40 - - -

Fire and gas cable routing drawings

.. -

: 60.00%

40

Fire & gas 110 list

r - - -

4.27%

27-Mar-11

Start ','

Design

12-May-11

20

18-May-11

40

','

31-Mar-11

.

Fire and gas cable wiring diagram

Start

03·Apr-11

... ~ De~ig~ ..... ',' . Oi-Ap·r.11·

16-May-11

20

-i- "19-M~Y:1; - ... '40' ..

Fire fighting, safety equipment and safety signs

- - . - Start

Design

20-Mar-11

_.

24-Mar-11

."15-May-11- - . - - -2026-May-11

.

40

1. Evaluation

"Weights of Activities are calculated relative to (Process) Tuesday, May 17, 2011

Layout No.1 Page 1 ofS

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report

SETH ONSHORE PROJECT Dates Milestone

Planned

Expected

Milestone Value

* Relative

Planned

Weight

Progress%

As Of:

30-Apr-11

Forecast Date:

28-May-11

Actual Progress%

I

Overall

Bulk

II

T. Evaluation

7.89%

Ppiping Valves VPR start

27-Feb-11

16-May-11

65.00%

55.00%

10

II

r

layout No.1

* Weights of Activities are calculated relative to (Piping) Tuesday, May 17, 2011

Page 2 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report As Of: Forecast Date:

SETH ONSHORE PROJECT

I Milestone

Dates

Milestone

Planned

Expected!

* Relative Weight

Value

II

Planned Progress%

7.41%

Instrument Index

30-Apr-11 28-May-11

Actual Progress%

0.00%

Start

Design

Instrument Cable Schedule

3.70%

60.00%

0.00%

3.70%

60.00%

9.88%

60.00%

0.00%

4.94%

60.00%

0.00%

3.70%

60.00%

0.00%

Start

Design

data sheets

03-Mar-11

Design

22-MaY-11

40

Instrument Hook Up And Supporting Drawings

Start

~

06-Mar-11

22-May-11

.. ·6e"Si9~··'· <, ·10·-M~r-l1· .:. H

25~M~Y~11

20 H'"

"40' --

Field Instrument Layouts

Start

06-Mar-11

... 6;Si9~···'· .:.

'10'-M~r-;1'

19-May-11

.:.

20

26~M~Y~1;····

"40"-

Field Instrument Cable Routing

Star!

t ••• 6e"sig~

10-Mar-11

- ...

>

":'



;6·-Ma~r-;1·

:

18-May~11

·i· 24.M~y~1;



Junction Box Interconnections Start

17-Mar·11

Design

23-Mar·11

IIl~c~o~m~m~O~d~1~'t~ie~S~====::;======================:=:3:::::===:=:3:::::===::=::='='====== Instrument! Fire & gas cables

19.75%

20.00%

0.00%

ilif@

mill MRQ 07-Apr·11 19·May-11 20 IF=':oln"s"'tru=m"e=n':t"BC'U"lk"'===~"'========"":==:==~==="'='======:=C;=;';;;='='=7~';;;='='=::;==;:';;;='='======;

IF iiliili

1illti 'B3E-

M~~~~: ~"--:~~~

24-May-11

x.'-,,-_,-~~~~_.__ ~,_,_.

,

~

,_.

_

=':oln"sO'tru=m"e"n':t7t"'F;'ir:'e';&C'e9caC'S=;:cC'a"bC'le"T;:ra=ys==============='=======:="1:;7".2"8"0/<7,=0=';;2"0".0"0"0/<7,=::;==;:0".0"0"%;=::;======: MRQ •••••• _ •

.

-

_

30·Mar-11

'

..24-May-11

20

Layout No.1

* Weights of Activities are calculated relative to (Instrumentation) Tuesday, May 17, 2011

Page 3 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report

SETH ONSHORE PROJECT Dates Milestone

Planned

* Relative

Milestone Value

Expected

Weight

Planned Progress%

As Of:

30~Apr~11

Forecast Date:

28~May~11

Actual Progress%

Overall

33.33%

Electrical Lighting MRQ

Start

Finish

2Q...Mar~11

.. i4-M;r~; 1" "i'

.

80

layout NO.1

* Weights of Activities are calculated relative to (Electrical) Tuesday, May 17, 2011

0.00%

20

2Q...May~11

24-M~Y:1;

100.00%

Page 4 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187·440

Lookahead Report

SETH ONSHORE PROJECT

Milestone

I

Dates

Planned

Milestone Value

Expected

I

* Relative Weight

Planned Progress%

As Of:

30-Apr-11

Forecast Date:

28-May-11

Actual Progress%

1.85%

50.00%

50.00%

1.85%

50.00%

50.00%

Structural steel fabrication Specification

1.85%

50.00%

50.00%

Site preparation, earth work & backfill Specification

1.85%

50.00%

: 50.00%

1.85%

50.00%

50.00%

2.78%

50.00%

50.00%

2.76%

100.00%

60.00%

2.78%

100.00%

60.00%

8.33%

60.00%

0.00%

Shim and grouting Specification

Finish

Finish

Concrete paving Specification

18-May-11

13-MaY-11

Finish

50

Soil & foundation investigation Specification

13-MaY-11

Finish

18-May-11

50

notes Construction

Anchor bolts standard details

Construction

17-Mar-11

40

24-May-11

Paving standard details

Construction

17-Mar-11

40

24-May-11

Standard connections details

40

Construction

Misc. Steel supports foundation plan & details

Start 20-Mar-11 - ••• De'sig~ . - • • • • . . 24.M~r-;1·

r

18-May-11 25-M~Y:1;'

10

.••

~~~_".....>.--L-"---"-~,,:,,,,--,--~

·50' .. ~"-""""-"-'-

Start

12-May-11

19-May-11

~ - - -De·si~~ -' _ ••• : •• 2o:.Ma~-;1- - 25-M~Y:1;· .:. -

.

.~.

0.00%

_

0.00%

rf

I

10

-50-"

* Weights of Activities are calculated relative to (Civil) Tuesday, May 17, 2011

..

11.11%

Valves foundation plan & details

Layout No.1

Page 5 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report As Of: Forecast Date:

SETH ONSHORE PROJECT Dates

Milestone

Planned

Expected

I

Milestone Value

* Relative Weight

Planned Progress%

30-Apr-11 28-May~11

Actual Progress%

Overall Engineering Drawings New slug catcher foundation plan & details

Design

26-Jan-11

23-May-11

18-Apr-11

Start •

Start

__

••••

a

26-Apr-11

05-May-11 • • • • •

Finish

;0

1Q..MaY-11

18-May-11 •••••

_



26-May-11

19-May-11 T

T

_

11.11%

60.00%

0.00%

_

"

••

50

20 __

80

Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011

0.00%

10 ••

• • • • • • • •

26-May-11

60.00%

50

Misc. Steel supports steel details

Design

12.96%

Layout No.1 Page 6 of 8

Data'Nes Systems. Release 2.21

Project No.: 4187·440

Lookahead Report

SETH ONSHORE PROJECT Dates

Milestone

Planned

Expected

Milestone

* Relative

Value

Weight

Electrical bulk material

Instrument I Fire & gas Cable Trays RFQ

13.Apr-11

25-May-11

30~Apr-11

28-May-11

Actual

Progress%

9.52%

40.00%

0.00%

11.90%

10.00%

0.00%

10

* Weights of Activities are calculated relative to (Purchasing) Tuesday, May 17,2011

Planned Progress%

As Of : Forecast Date:

Layout No.1 Page 7 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report

SETH ONSHORE PROJECT Dates Milestone

Planned

Expected

,., Relative Weight

Milestone Value

As Of:

30-Apr-11

Forecast Date:

28-May-11

Planned

Actual

Progress%

Progress'%

Overall Procurement Commodities 10.29%

Valves VPR start

06-Mar-11

10

Layout NO.1

• Weights of Activities are calculated relative to (Expediting) Tuesday, May 17, 2011

50.00%

Page 8 of8

Data'Nes Systems, Release 2.21



Enpp.J. PTB

SETH ONSHORE DEVELOPMENT

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.6.Procurement Status.

18-MAY-2011

As of:

18 Mav 2011

PROCUREMENT DIVISION FOREIGN PURCHASING SECTION PTB, SETH OFFSHORE DEVELOPMENT PROJECT PROJECT NO.: 4187-440

Serial no.

1

Commodity

SLUG CATCHER

No. of invited bidders I

Bid due date and its extensions lOll 112010

No. of bidders quoted 1

Technical opening date

1111112010

2

MANUAL VALVES

8

20112/2010

8

21/12/2010

3

FIRE & GAS DETECTION

1

6/3/2011

1

23/03/2011

9

6/3/2011 EXT TILL 14/03/2011 EXT TILL 24/03/2011

5

28/03/2011

13

5/4/2011 EXT TILL 12/04/2011

12

17/04/2011

4

5

FIRE FIGHTING SYSTEM

PIPING BULK

Technical report date

14/02/2011

10/2/2011

Revised commercial bid due date

F.O.ADATE

21102/2011

AWARDED TO PTJ IN 17/03/2011

LCM 05B Awarded to 17/0212011 LVF 05C Awarded to

PTB, SETH ONSHORE DEVELOPMENT PROJECT Project no.: 4187-440 R.F.Q 4187-440 Commodity: SLUG CATCHER SETH - 03 R.F.Q issuance date: 02/11/2010

Serial Supplier name

I

PTJ

Country

EGYPT

Technical Technical Technical Technical clarification clarification Bidder clarification Bid due date actual reply response opening date issuance due date date date

11/10/2010

6/1/2011 26/01/2011

16/01/2011 01/02/2011

16/01/2011 06/02/2011

Technical report date

14/02/2011

Revised commercial bid due date

Remarks

21102/2011

AWARDED IN 17/03/2011 WITH DELIVERY 9.5 - 11 MONTHS F.O.T

PTB, SETH ONSHORE DEVELOPMENT PROJECT Project no.: 4187-440 R.F.Q no. 4187-440-SETH - 05 Commodity: MANUAL VALVES R.F.Q issuance date: 01112/2010

Bid due date

Bidder response

Technical opening date

Technical clarification issuance date

Technical Technical Revised Technical report clarification due clarification commercial date actual reply date bid due date date

Serial

Supplier name

Country

1

THARWA BREDA

EGYPT

Q

9/1/2011

12/1/2011

2

TLPR

ITALY

Q

13/01/2011 26101/2011

16101/2011 29/01/2011

23/01/2011 06102/2011

3

TRP-PERAR

ITALY

Q

9/112011

12/1/201 I

23/01/2011

4

DAFRAM

ITALY

Q

13/01/2011

16101/2011

19/01/2011

5

LVF

ITALY

1211/2011 26101/2011

1610112011 29/0112011

26101/2011 07/02/2011

6

DRV

U.S.A

Q

1211/2011

16101/2011

7

LCM

ITALY

Q

11/1/2011 20101/2011

15/0112011 23/0112011

16101/2011 23/01/2011

8

QUALIVAL

EGYPT

Q

6/1/2011

101112011

101112011

20/12/2010

Q

21/12/2010

10/212011

17/02/2011

Remarks

FOROSA AWARDED TO LCMIN 20104/2011 WITH DELIVERY 1826wksEXW FOROSB AWARDED TO LVFIN 20/04/2011 WITH DELIVERY 2426wks FOB FOROSC AWARDED TO QUALIVALIN 20/04/2011 WITH DELIVERY 2426 EXFACTORY IN 10th of Ramadan city, Egypt

PTB, SETH ONSHORE DEVELOPMENT PROJECT Project No.: 4187-440 SPEC NO.: 00192700 - BMSF - 13205 Commodity: SETH - 21 /PIPING BULK MATERIALS R F Q Issuance Date' 22/03/2011

Serial

Supplier name

Country

Bid due date Bidder response

Technical opening date

Technical

Technical

Technical

clarification

clarification

issuance date

clarification due date

actual reply date

1

AR TECHNOLOGY

ITALY

Quoted

2/5/2011

5/5/2011

3/5/2011

2

HPF

UK

Quoted

2/5/2011

5/5/2011

10/5/2011

3

FAD

ITALY

Quoted

2/5/2011

5/5/2011

10/5/2011

4

DYLAN

NL

Quoted

2/5/2011 8/5/2011

5/5/2011 9/5/2011

3/5/2011 9/5/2011

5

CHEROP1PING

ITALY

Quoted

2/5/2011

5/5/2011

4/5/2011

6

IPS

ITALY

Quoted

2/5/2011

5/5/2011

8/5/2011

7

IGAMM

ITALY

2/5/2011

5/5/2011

4/5/2011

8

TLPR

ITALY

Quoted

2/5/2011

5/5/2011

5/5/2011

9

EJSW

EGYPT

Quoted

2/5/2011

5/512011

8/5/2011

10

TUXOR

ITALY

Regret

11

MINTA

EGYPT

Quoted

2/5/2011

5/5/2011

9/5/2011

12

FERRARI

ITALY

Quoted

2/5/2011

5/5/2011

5/5/2011

13

STEEL TRADE

ITALY

Quoted

2/5/2011

5/5/2011

4/5/2011

05/04/2011 EXT TILL 12/04/2011 EXT. TILL 14/04/2011

Quoted

17/04/2011

Technical report date

Revised commercial opening date

Remarks

PTB, SETH ONSHORE DEVELOPMENT PROJECT Project No.: 4187·440 SPEC NO.: 00192700·BISF·24204 Commodity: FIRE & GAS DETECTION / SETH· 27 R.F.Q Issuance Date: 24/0212011 Serial

1

Supplier name

FORESENG

Country

ITALY

Bid due date

06/03/2011

Bidder response

Technical opening date

Technical clarification issuance date

Technical clarification due

Technical clarification

date

actual reply date

Q

23/03/2011

3/4/2011 ll/5/2011

6/4/2011 12/5/2011

11/4/2011

Technical report date

Revised commercial

opening date

Remarks

PTB, SETH ONSHORE DEVELOPMENT PROJECT Project No.: 4187-440 SPEC NO.:00192700-BMSF-13206 Commodity: FIRE FIGHTING SYSTEM SETH - 28 R F Q Issuance Date' 24/02/2011

..

Technical clarification issuance date

Technical clarification due date

Technical clarification actual reply date

Q

5/4/2011 10/5/2011

9/4/20 II 12/5/2011

10/4/2011

REGRET

10/5/2011

12/5/2011

5/4/2011 10/5/2011

9/4/20 II 12/5/2011

5/4/2011 10/5/2011 5/4/2011 10/5/201 I

9/4/2011 10/5/2011 9/4/20 II 10/5/2011

5/4/2011

9/4/2011

Serial

Supplier name

Country

1

SAFCO

ITALY

REGRET

2

DETRONICS

UAE

REGRET

3

EUSEBI

ITALY

4

FORESENG

ITALY

5

GENERAL MONITORS

U.S.A

6

SILVANI

ITALY

7

SANCO

ITALY

Q

8

MINTA

EGYPT

Q

9

FAS

ITALY

Q

Bid dne date

06/03/2011 EXTENDED TILL 14/03/2011 EXTENDED TILL 24/03/2011

Bidder response

REGRET

Q

Technical opening date

28/03/2011 11/4/2011 10/4/2011 12/4/201 I 10/4/2011

Technical report date

Revised commercial opening date

Remarks



E:n.pp.J. PTB

SETH ONSHORE DEVELOPMENT

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

18-MAY-2011

7. 7.Equipment and material status report

I

PROJE.CT COMMITME.NTS STATISTICAL OVERVIEW

STATISTII

COMMITMENTS COUNT:

A.

TOTAL NO. OF ISSUED COMMITMENTS: F.D.C ISSUED.

4

=

B. C.

P.Oo'S COMPLETED/RELEASED FOR SHIPMENT P.Oo'S FOR SERVICES.

D.

P.Oo'S FABRICATION IN PROGRESS.

4

o

P.Oo'S ISSUED.

=

o o 4

,

I i

,

r,

.

- ... ;

I

<

...

,

----

..-

i

;

I

, , • 1---.-

-

• -'

..

I

I

,~

'" i--'-.

I

" " ... ~

" "

"

.

.

,I

.

Enpp!

• •;nu

~'i~.... r,,1bo~Uw..,

SETH DEVElOPMENT PROJECT RA5!EL.BAR CONCESSION

REPORT NO. 1

AS Of 28/4/2011

FROM 9.S MONTH TO 11 MONTHS

'"

SlUG CATCHERPAcKAG,

,ETHOSA

EX·WORKS/ITAlV MANUAL VALVES

20-4-2011

I

lB-26WEEKS ,PLUS ONt WEEK FO~ AUGUST SHUTDOWN

FDA WAS ISSUEOTO PTJ ON 17/3 fOR THE SUPPLY OF ONE SLUG CATCHER PACKAGES, COMPLETE WITllTHE INST~UMENTS, VALVES, INTERCONNECTING PiPiNG SKID AND lOCAL CONTROL PANEl. KOM WAS CONDUCTED ON 4/4/l0U. PTJ suaCONTRACTED I.M.S.• Indu,lric MCe<'ni'he ON ~3/3 S'''doliato S.p,A.FORTHE OESIGN,SUPPLYOF lOOSE MATERIALS AND MECHANICAL GARANTEE FOR THE SLUG CATCHER WITH INTE~PIPING SKID AND LDOSE INSTRUEMENTS AND VALVES ON S SHIPMENTS fROM 21/7 fOR FLANGES ,PI PIES AND flnlNGS TILL 20/2/1.012 fOR All VALVES AND CONTROL PANEl., ENGINEERING DOCUMENTS STARETDTD B, RECEIVED FROM 29/3 ANQ 20/4 FoRTHE; VESSElCAlCUAtTlON, PFo, QUAtlT'I PLAN. VDeF.OATA SHEET. PROCUREMENT SU~ORDERING IS SCH,OUlEO FROM l/4 Tlll29/4 IWAITING FO~ CONFIRMIITIONI FAe~leATION IS EXPECTED fROM 14/9 Fo~ NOULE wonKS TILL 1/l/l0U.

FoA WAS ISlum TO SUPPLIER ON 1.0/4/2011 FOR lllTEMS OF MANUAL VALVES ITOTAllB VALVE). DRAWINGS APPROVAL IS 10 DAYS E·MAIL WAS SENT TO SUPPlIfR ON ~8/4 TO SUBMIT THE ACKNOWLEDGMENT AND ,NGINEE;RING DOCUMENTS AND ORDER SCHEDULE

l~-~6

WEEKS,PLUS ONE WEEHORAUGUST SHUTDOWN

LVF/ITALV

fDA WA5ISSUED TOSUPPUER ON VALVES ITOTAL 36 VAlVEI. SETH 058

FOB ITALY

MANUAL VALVES

24·l6 WEEKS FROM

24-l6 WEI'K5 FROM

'"

'"

"

"

:!OI~/2011

FOR U ITEMS OF MANUAL

,-MAil WAS SENT TO SUPPlIER ON 28/4 TO SUBMIT THE

ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORDER SCHeDULE

20·4-2011

QUAUVAl/,GYPT FOA WAS ISSUED

TOSU~PtlER

ON 20/4/Z011 FORS ITEMS OF MANUAL

VAlVES{TOTAL ,VALVE) E~·WORKS

sF;THOSC

MANUAL VAlVES

jlOTH Of

RAMADAN £(;YPT

24·1.6 WEEKS fROM

24·26 WEEKS fROM

'"

'"

"

"

"

E'MAll WAS SENTlO SUPPLIER ON 28/4 TO SUBMITrHE ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORD,R

SCHEDULE.



Enppa PTB

SETH ONSHORE DEVELOPMENT

4187-440 Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

18-MAY-2011

7. 8.Alert report

I

rI

r

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT

Milestone

I Milestone

Dates

Expected!

Planned

J

Value

* Relative

I i Planned. 1

Weight

Progress%

3.70%

Structural general notes

.

Construction

24-May-11 -"--

As Of :

100.00%

Actual Progress%

60.00%

30-Apr-11

Weighted Delay

1.48%

40

..--........--'---"-~-"---"---"---"-------------_._----_._-------------_._----

2.78%

100.00%

60.00%

1.11%

Paving standard details

2.78%

100.00%

60.00%

1.11%

Standard connections details

2.78%

100.00%

60.00%

1.11%

8.33%

60.00%

0.00%

5.00%

12.96%

60.00%

0.00%

7.78%

11.11%

60.00%

0.00% :

6.67%

Anchor bolts standard details

Construction

Construction

17-Mar-11

24-May-11

40

17-Mar-11

Misc. steel supports foundation plan & details

.. Start . - . . . . . ..

. 19..May-11

20-Mar-11

~

Design

~.

24-Mar-11

10

.

25-May-11

.

50

New slug catcher foundation plan & details OS-Jun-11

Start

10

Misc. steel supports steel details

Start -

-

-

-

-

18~Apr-11

•••••••••••••••

Design

-

26-Apr-11

18-May-11 •

<

•••••••••

26-May-11

10 "

"

••••

50

Layout No.1

* Weights of Activities are calculated relative to (Civil) Tuesday, May 17, 2011

Page 5 of7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT

Milestone

I

I Milestone

Dates Planned

Expected

I

I

Value

Instrument I Fire & gas cables

RFQ

11-Apr-11

02-Jun-11

RFQ

- ..........

~

02-Jun-11

11-Apr-11

..

26-Jun-11

Weighted Delay

9.52%

10.00%

0.00%

0.95%

9.52%

40.00%

0.00%

3.81%

11.90%

10.00%

0.00%

1.19%

11.90%

10.00%

0.00%

1.19%

10

13-Apr-11

25-May-11

10

layout No.1

• Weights of Activities are calculated relative to (Purchasing) Tuesday, May 17, 2011

Actual

Progress%

30

Instrument I Fire & gas Cable Trays

RFQ

J

~

Instrument Bulk

RFQ

I

OZ-Jun-11 10 - - - 28-Mar-11 - - . - . ..... - - - - - ......

18-Apr-11

Ree.Bids

Planned

Progress%

30-Apr-11

10

Electrical bulk material

"

* Relative Weight

As Of :

Page6of7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT Dates

Milestone

Planned

Expected

* Relative

Milestone Value

Weight

As Of : 30·Apr·11

I

Planned

Progress%

Actual Progress%

Weighted Delay

Overall Procurement

10.29% VPR start

06-Mar-11

18-May-11

10

VPR finish

14-Apr-11

22-Jun-11

20

50.00%

20.00%

3.09%

!

I .. Weights of Activities are calculated relative to (Expediting) Tuesday, May 17, 2011

Layout No.1 Page 7 of 7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT Dates Milestone

Planned

Expected

I

Milestone Value

Process cause and effect matrix

24-Feb-11

Design

---"--"----"_"-".'-.....L ......."'-..... _ ......

16-MaY-11

Fire &

07-Apr-11

A

27-Mar-11

20.00%

1.71%

60.00%

20.00%:

1.71 %

4.27%

60.00%

0.00%

2.56%

4.27%

60.00%

0.00%

2.56%

4.27%

60.00%

0.00%

2_56%

4.27%

60.00%

0.00% :

2.56%

?~-~P!-~1 i. ;~~~Y:1~.

" " •••• : •• •• '07-Apr-11 '

19-May-11

Fire fighting, safety equipment and safety signs

Start

20-Mar-11

Design

24-Mar-11

15-May-11

..

"".

--

26-May-11

_

20

.

40

Layout NO.1

* Weights of Activities are calculated relative to (Process) Tuesday, May 17, 2011

4.27%

:

20

12-May-11

Fire and gas cable wiring diagram

Design

60.00%

Weighted Delay

20 "40""

Fire and gas cable routing drawings

:t~rt".

4.27%

Actual Progress%

40

Start 08-Apr-11 ,22-May-11 "_. De~ig~ ••••• ', •• 1i-Ap'r-11- -,- 25-M~Y~1;···

••••

Planned Progress%

40

1/0 list

Start

'" Relative Weight

-"-,~'~_"--'-"-,"--'-"......:... ..................

Fire and gas cause and effect

Design

I

As Of : 30-Apr-11

Page 1 of7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT Dates Milestone

Planned

Expected

* Relative

Milestone Value

Weight

As Of : 30-Apr-11

Planned Progress%

Actual Progress%

Weighted Delay

Overall Engineering

7.89%

Ppiping Valves VPR start

27-Feb-11

16-May-11

55.00%

0.79%

10

layout NO.1

* Weights of Activities are calculated relative to {Piping) Tuesday, May 17, 2011

65.00%

Page 2 of?

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT Dates Milestone

Expected

Planned

* Relative

Milestone Value

Weight

As Of : 30-Apr-11

Planned Progress%

Start

,20-Feb-11

~~~~:~?~~~~~~£Feb.;1»

15-May·11:

Weighted Delay

60.00%

0.00%

4.44%

3.70%

60.00%

20.00%

1.48%

9.88%

60.00%

0.00%

5.93%

4.94%

60.00%

0.00%

2.96%

3.70%

60.00%

0.00%

2.22%

4.94%

60.00%

0.00%

2.96%

7.41%

Instrument Index

Actual Progress%

20

":' ;8-0~Y:1~ ~ :i :_~:~~~~_: __~~ __~~. __."~._". _ 3.70%

Instrument Cable Schedule

Start

Design

22·May·11

03-Mar-11

40

..

Instrument Hook Up And Supporting Drawings

Start

06~Mar·11

.

" " - - De~i~~ ..

»

H • H;' •

10·.Ma"r-11"

i 22-May-11 20 "i' i5-M~Y=1; .... "40 - - "

Field Instrument Layouts

Start

,06-Mar-11

r " - - 6e~i~~

...

H



":'



10·-M';r-11"

r!

19-May-11 26-M~Y=1;

20

.... "40 - . "

Field Instrument Cable Routing Start

Design

Junction Box Interconnections

_.

Design

_

••

-

-

-

_.".

-

-

-

23-Mar-11

20

25-May-11

17-Mar-11

Start • • • • • •

.,_

:

• • • • • • •

A,A

26-May-11

A

•••••

40

~l",c;o~m;m;;;O;d;i;ti~e~s=.=::;:===;:=;:===================::::==::::;===========:::== ;If

i

I

Instru:::tI Fire & gas ca:~_:P'_11

19.May-11

20

19.75%

20.00%

=::====:::==~:::::;;=.=:::; 0.00%

3.95%

F"I"n"'struO=m""e"n"t=B"'U:'lk=:="'=:-=~:=·~""=··"""'=:=:=""'=~"~"·~""C:C=:=""=c.=-=-="",,~~~=--~~~=-~~=:~1=7-=;.~2':'8"':'%:'-==-=-="':2"':'0-=.O:'0':%7==~~'--~0=.0='-;;-=""l\==~-==3-=.~4':'6"':'~l\""~-=;·

$1

!=F""="",M"R=Q"""'=:""'""",7'""",~~,,,""=~=--3,,0=.M,,="',,-~,,,'...~,,,,,2=4-,,,M,,a=y,,-""="==",2"0",,,.~,,,,.~=_=_==~=_=_=-=-=-==:_::,:7'=.-=-=-=_=-=-7'._""'_7'~_=.~-'--=-=O-""'~~=-=7~"7,,"=-=; __

Instrument! Fire & gas Cable Trays

17.28%

20.00%:

0.00%

3.46%

~

= mm

MRQ

30-Mar-11

layout NO.1

* Weights of Activities are calculated relative to (Instrumentation)

Tuesday, May 17, 2011

Page30f7

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT Dates Milestone

Planned

Expected

I

Milestone Value

* Relative Weight

As Of : 30-Apr-11

II

I

Planned D

Progress%

Actual

Progress%

I

Weighted

Delay

Overall

Electrical Lighting MRQ

Start

33.33% 20-Mar-11

..2o-May-11

20

24-May-11

80

"."

Finish

0.00%

33.33%

.

layout No.1

* Weights of Activities are calculated relative to (Electrical) Tuesday, May 17, 2011

100.00%

Page 4 of?

Data'Nes Systems, Release 2.21

Related Documents


More Documents from "uud nasrulloh"