Monthly Progress Report - Template 000

CLIENT NAME

CLIENT LOGO

Agreement No: XXX/XX/XX/XX/XX

Project Title: EPC Works for XYZ Project

PROJECT TITLE

Location: CA, USA Client:

MONTHLY PROGRESS REPORT

XYZ Company

MPR No.: XX-XX-XX-xxx

Consultant:

Reporting Period: xx-Dec-xx to xx-Dec-xx

XYZ COMPANY Contractor: XYZ COMPANY Project Milestone: Award Date: xx-Feb-xx

CONTRACTOR NAME

Duration: XX Months Completion: XX-Mar-XX

Agreement Value: XXX Million US$ incl. Approved Variations

CONTRACTOR LOGO

Project Commence Date

Project Completion Date

Days Elapsed till Cut-off

Remaining Days for Milestone-1

Remaining Days for Milestone-2

Remaining Days for Completion

xx-OCT-xx

xx-JAN-xx

122

125

xxx

xxx

THIS IS SAMPLE REPORT ONLY, CHANGE, ADD, OR DELETE SECTIONS OF REPORT ACCORDING TO YOUR PROJECT REQUIREMENT.

Description

Date

Issued for Information

Originator/ Reviewer

Approved by

Mujahid Akhtar

XYZ

XX-Jan-XX Signature

1

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 TABLE OF CONTENT 1.

PROJECT INTRODUCTION ............................................................................................................................ 3

2.

EXECUTIVE SUMMARY................................................................................................................................ 3

3.

PROGRESS & EARNED VALUE ANALYSIS SUMMARY ..................................................................................... 4

4.

PROGRESS ANALYSIS .................................................................................................................................. 5

5.

KEY ISSUES & CONCERNS ............................................................................................................................ 8

6.

OPPERTUNITIES .......................................................................................................................................... 8

7.

PROJECT HSE STATISTICS ............................................................................................................................ 8

8.

DETAILED PROGRESS OVERVIEW............................................................................................................... 10

A.

ENGINEERING ....................................................................................................................................... 13

B.

PROCUREMENT INCL. ORDERING, MANUFACTURING AND DELIVERY ..................................................... 22

C.

CONSTRUCTION INCL. PRE-COMMISSIONING AND COMMISSIONG ........................................................ 23

D.

PROJECT, QUALITY AND CONTRACT MANAGEMENT .............................................................................. 32

9.

PROGRESS DELAY ANALYSIS...................................................................................................................... 34

10.

CRITICAL PATH...................................................................................................................................... 34

11.

ATTACHMENTS: .................................................................................................................................... 35

2

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 1. PROJECT INTRODUCTION Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your

If required, and you have PROJECT Schematic Diagram you can include here! (Fig-1)

2. EXECUTIVE SUMMARY Description

Controlled

Caution

Remarks

Critical

Project Deliverables

On-time

HSE/Safety

No LTI

Project Schedule

Write short top reason for Schedule slippage

Project Cost

Within Budget Give description of top Risk(s) which are to be monitored closely Write about overall project (schedule, cost, scope, quality etc.)

Risks / Uncertainties Overall Project

Current Progress Overview

Cumulative Progress (%) Remarks / Reasons for Delays B/L Plan

Actual

Variance

E – Engineering (15%)

99.00%

95.00%

-4.00%

P – Procurement (45%)

80.00%

70.75%

-9.25%

C – Construction (40%)

70.10%

71.00%

0.90%

OVERALL PROGRESS (100%)

78.89%

74.49%

-4.40%

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

Project Key Milestones Milestone-1

xx-Jan-xx

xx-Jan-xx

Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

Milestone-2

xx-Feb-xx

xx-Feb-xx

Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

Milestone-3

xx-Mar-xx

xx-Mar-xx

Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

3

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 3. PROGRESS & EARNED VALUE ANALYSIS SUMMARY RMN 5.0%

RMN 25.5% Plan: 49.48%

Plan: 49.48%

ACT 74.5%

RMN 29.0%

RMN 29.3% Plan: 49.48% ACT 70.8%

ACT 95.0%

OVERALL PROJECT

Plan: 49.48%

E - ENGINEERING

ACT 71.0%

P - PROCUREMENT

C- CONSTRUCTION

Reporting Month Variance

-4.40%

-4.00%

-9.25%

0.90%

-9.00%

1.00%

Last Month Variance

-5.00%

-4.25%

EXPLAIN ABOVE CHARTS FOR EACH PHASE OF PROJECT Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Budget at Completion (BAC)

Desciption

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

Schedule Variance (SV)

Cost Variance (CV)

Cost Performance Index (CPI = EV/AC)

Schedule Performance Index (SPI = EV/PV)

Estimated Cost at Completion (EAC)

ENGINEERING

PROCUREMENT

CONSTRUCTION

OVERALL PROJECT

Explain Above Table for Each Phase of Project (Either show for Overall Project or for each Phase) Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Your

4

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 PROJECT MONTHLY S-CURVE (with or without EVA) – ADD HERE YOUR PROJECT S-CURVE (Also can add for each phase)

4. PROGRESS ANALYSIS Current MONTH (%) DESCRIPTION

Wtg.

Plan

CUMMULATIVE (%) Variance

Plan

Variance

Actual Baseline

Forecast

Actual Baseline

Forecast

Baseline

Forecast

Baseline

Forecast

E- ENGINEERING

15%

99.00%

98.95%

95.00%

-4.00%

-3.95%

P-PROCUREMENT

45%

80.00%

79.00%

70.75%

-9.25%

-8.25%

CCONSTRUCTION

40%

70.10%

68.10%

71.00%

0.90%

2.90%

Overall Progress

100%

78.89%

77.63%

74.49%

-4.40%

-3.15%

Explain above table and provide brief interpretation of progress for the MONTH. Mention key activities performed during the reporting period below: ENGINEERING: • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

5



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 PROCUREMENT: • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

CONSTRUCTION/ COMMISSIONING: •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

4.1 MONTHLY Baseline vs Actual Trend

Explain above graphs as per progress on your project. I have given snapshot of few months only. Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

6

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 4.2 Negative Variance Trend w.r.t. Baseline Plan

Explain above graphs as per progress on your project. I have given snapshot of few months only. Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

4.3 MONTHLY S-curve (Actual vs Baseline Plan)

Explain above S-Curve as per progress on your project. I have given snapshot of few months only.

7

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 5. KEY ISSUES & CONCERNS Sr. No.

Key Issues

Impacted Activities

Actions Required

Action By

Action Date

1.

Your Text Here Your Text Your Text Here Your Text Here Here

Your Text Here Your Text Here

CONTRACTOR

xx-Jan-17

2.

Your Text Here Your Text Your Text Here Your Text Here Here

Your Text Here Your Text Here

CONTRACTOR

xx-Jan-17

Your Text Here Your Text Your Text Here Your Text Here Here

Your Text Here Your Text Here

CONTRACTOR

xx-Jan-17

Your Text Here Your Text Here

CONTRACTOR

xx-Jan-17

Your Text Here Your Text Here

CLIENT

xx-Jan-17

Your Text Here Your Text Here

CLIENT

xx-Jan-17

Your Text Here Your Text Here

CLIENT

xx-Jan-17

3.

4.

Your Text Here Your Text Your Text Here Your Text Here Here

5.

Your Text Here Your Text Your Text Here Your Text Here Here

6.

Your Text Here Your Text Your Text Here Your Text Here Here

7.

Your Text Here Your Text Your Text Here Your Text Here Here

6. OPPERTUNITIES

8



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 7. PROJECT HSE STATISTICS Project XYZ Sr. No.

PROJECT HSE STATISTICS

1

Total number of employees

2

Man-hours worked

3

Fatalities (death)

4

Fatal accident rate (FAR)

5

Permanent total disabilities (PTD)

6

Permanent partial disabilities (PPD)

7

Lost workday cases (LWDC)

8

Lost time injuries (LTI)

9

Lost time injury frequency rate (LTIFR)

10

Lost workdays (days lost)

11

Severity rate

12

Restricted workday cases (RWC)

13

Restricted workdays

14

Medical treatment cases (MTC)

15

Total recordable cases (TRC)

16

Total recordable cases frequency (TRCF)

17

Total number of vehicles

18

Vehicle incident, category 1 (serious)

19

Cost of vehicle damage ($)

20

Vehicles kilometers driven

21

Vehicle accident frequency rate (VAFR) VAFR

22

Total employees trained (actual)

23

Total training hours

24

Total training hours/employee (average)

25

First aid cases

26

Near misses

27

Fires

28

Property damage or process loss

29

Cost of property damage and process loss including fires ($)

30

HSE meetings conducted

31

HSE inspections carried out

32

Emergency exercises / drills conducted

33

Total road safety violations by IVMS

This Month

Cumulative

Change above table as per your project requirement.

9

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 8. DETAILED PROGRESS OVERVIEW 8.1 PROJECT MILESTONE SUMMARY Number of Milestones

Milestones Scheduled during this Month

Milestones Completed during this Month

Milestones Scheduled till Date (A)

Milestones Completed till To-Date (B)

Milestone Variance (B-A)

E - Engineering

20

2

1

10

9

-1

P - Procurement

20

2

0

10

9

-1

C - Construction

20

2

1

10

9

-1

Total:

70

7

3

35

31

-4*

Milestone Category

*Following milestones have not achieved; 1. 2. 3. 4. 5.

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

8.2 PROJECT MAJOR MILESTONES MILESTONES DESCRIPTION

BASELINE

FORECAST

ACTUAL

Your Text Here Your Text Here

xx-Oct-xx

-

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

-

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

-

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

-

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

-

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

Your Text Here Your Text Here

xx-Oct-xx

xx-Oct-xx

For detailed Milestones List, Refer ATTACHMENT - PROJECT MILESTONES

10

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 8.3 PROJECT RISKS MATRIX & TOP TEN (10) RISKS 1. PROJECT RISKS MATRIX

Consequence

5

4

1

2

6

3

1

7

5

2

3

D

E

2

1

5

1

2

2

A

B

C Probability

2. TOP TEN (10) RISKS Following are major project risks that were identified during workshop conducted on xx-Dec-xx; Risk Rank

Risk No.

Risk Description (Top Ten)

19

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

2

25

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

3

10

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

36

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

51

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

40

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

1

4

5

6

11

EPC WORKS FOR XYZ PROJECT

Mitigation Action

RAM

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000

7

8

9

10

14

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

16

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

D4

25

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

E3

46

Your Text Here Your Text Here Your Text Here

• • •

Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text Your Text Here Your Text Here Your Text

E3

Refer ATTACHMENT - PROJECT RISK REGISTER

12

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 8.4 NOC (NO OBJECTION CERTIFICATES) SUMMARY STATUS NOC Status

Activity-2

Activity-1

Activity-3

Activity-4

Activity-5

Activity-6

Activity-7

Total

Total Default NOC NOC with conditions NOC without conditions Conditions to Issue NOC Objections In Progress No Answer

*Following NOCs’ are critical for the project however have not received. 1. 2. 3. 4.

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

For details, refer ATTACHMENT XX – NOC REGISTER 8.5 MAJOR ACTIVITIES PERFORMED DURING REPORTING PERIOD A. ENGINEERING 1. ENGINEERING Progress (%) Summary Current MONTH (%) DESCRIPTION

Wtg.

Plan

CUMMULATIVE (%) Variance

Plan

Variance

Actual Baseline

Forecast

Actual Baseline

Forecast

Baseline

Forecast

Baseline

Forecast

Project Management

10%

99.00%

98.95%

95.00%

-4.00%

-3.95%

Detailed Engineering

70%

80.00%

79.00%

70.75%

-9.25%

-8.25%

Procurement Support

15%

70.10%

68.10%

71.00%

0.90%

2.90%

Subcontracting

05%

70.10%

68.10%

71.00%

0.90%

2.90%

100%

78.89%

77.63%

74.49%

-4.40%

-3.15%

E - Engineering

Amend above table as per your project Work Breakdown Structure (WBS).

13

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000  Following are the highlights of Engineering activities during the month. ➢ PROCESS Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

• Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ HSE Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ QUALITY Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ PIPELINE Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ MECHANICAL (ROTARY) Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

14

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 ➢ MECHANICAL (STATIC) Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ MECHANICAL (PACKAGE) Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ INSTRUMENTATION Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ ELECTRICAL Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ TELECOM Documents Issued for IFC / Issued for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issued for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

15

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ OTHER DISCIPLINE • Add as per your Project. 2. CUMULATIVE DELIVERABLE STATUS SUMMARY (CLASS WISE) Total Nos

IFR

IFA

Final Issue

Document Class (Baseline)

(Latest)

Plan

Actual

Plan

Actual

Plan

Actual

Class - 1 Class - 2 Class - 3 Class - 4 Total

3. THIS MONTH DELIVERABLE STATUS SUMMARY (CLASS WISE) Total

Document Class Plan

IFR Act

Plan

IFA Act

Plan

Final Issue Act

Plan

IFC with Hold

Act

Class - 1 Class - 2 Class - 3 Class - 4

Total 4. THIS MONTH CLIENT REVIEW /APPROVAL STATUS SUMMARY (CLASS WISE) Document Class

Total Nos

Code 1

2

3

4

5

Class - 1 Class - 2 Class - 3 Class - 4 Total

5. CUMULATIVE DELEIVRABLE STATUS TILL FIRST ISSUANCE (IFR) Discipline

Document Stated

Draft Completed

Plan

Plan

Actual

Actual

Squad Check Completed Plan Actual

IFR Plan

Actual

HSE Instrumentation Mechanical Package Mechanical Rotary Mechanical Static Pipeline Piping

16

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 Process Telecom Total

6. DELIVERABLES ISSUED DURING THIS MONTH Discipline

IFR

IFA

IFC with Hold

Total

Final Issue

HSE Instrumentation Mechanical Package Mechanical Rotary Mechanical Static Pipeline Piping Process Total

7. DELIVERABLES RESPONDED DURING THIS MONTH BY CLIENT WITH REVIEW / APPROVAL CODE IFR – Review Code

IFA – Approval Code

Discipline 1

2

3

4

5

Total

1

2

3

4

5

Total

HSE Instrumentation Mechanical Package Mechanical Rotary Mechanical Static Pipeline Piping Process Total

8. TECHNICAL QUERY SUMMARY STATUS Last Month

This Month

Cumulative

Description Received

Answered

Received

Answered

Received

Answered

Cumulative Pending

TQ

9. CUMULATIVE PROCUREMENT SUPPORT SERVICES SUMMARY STATUS Start Enquiry Package Description (WBS)

Enquiry Floated

Receive Offers

Total No. Plan

For

Act

Plan

For

Act

Plan

For

Act

Submit TBE for COMPANY Approval Plan

For

TBE Approved by Company

Act

Plan

For

Act

Issue Purchase Order

Plan

For

Equipment (Stationary/Roraty) Bulks Materials Pipeline/ Flow lines

17

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Act

Monthly Progress Report - Template 000 Overhead Lines

Total:

10. CUMULATIVE SUBCONTRACTING SUPPORT SERVICES SUMMARY STATUS

Total No.

Description

Start Enquiry Package

Plan

For

Enquiry Floated

Act

Plan

For

Act

Receive Offers

Plan

For

Act

Submit TBE for COMPANY Approval Plan

For

Act

TBE Approved by Company

Issued Subcontract Agreement

Plan

Plan

For

Act

For

Act

Detailed Engineering Construction/ Commissioning Others Total:

Change above tables as per your project Work Breakdown Structure (WBS).

11. DELIVERABLES ISSUANCE, REVIEW/APPROVAL TRENDS

Briefly explain the above graph. • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

12. RECEIVED/PENDING DELIVERABLES SUMMARY - COMPANY Total Deliverable

18

Total Deliverable Received

Deliverables Due Status Over Due Deliver.

Due Today

EPC WORKS FOR XYZ PROJECT

Due in next 5 Days

Deliverables Pending with Company Total Doc. Pending

<1 Week

1-2 Week

3-4 Weeks

>4 Weeks

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 13. RECEIVED/PENDING DELIVERABLES SUMMARY - CONTRACTOR Total Deliverable

Total Deliverable Received from Company

Deliverables Pending with Contractor Total Doc. Pending

<1 Week

1-2 Week

3-4 Weeks

>4 Weeks

Document Review Code Status Code 1

Code 2

Code 3

Code 4

Code 5

 Following are the major activities planned for Home Office activities during the next MONTH; ➢ PROCESS Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here



Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

• Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ HSE Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ QUALITY Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ PIPELINE Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ MECHANICAL (ROTARY)

19

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ MECHANICAL (STATIC) Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ MECHANICAL (PACKAGE) Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ INSTRUMENTATION Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ ELECTRICAL Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

20

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 ➢ TELECOM Documents Issue for IFC / Issue for Implementation • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Re-IFR/ IFA incorporating company comments • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Documents Issue for Review (IFR) • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here • Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ OTHER DISCIPLINES • Add as per your Project.

21

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 B. PROCUREMENT INCL. ORDERING, MANUFACTURING AND DELIVERY 1. PROCUREMENT Progress (%) Summary Current MONTH (%) DESCRIPTION

Wtg.

Plan

CUMMULATIVE (%) Variance

Plan

Variance

Actual Baseline

Forecast

Actual Baseline

Forecast

Baseline

Forecast

Baseline

Forecast

Equipment

10%

99.00%

98.95%

95.00 %

-4.00%

-3.95%

Bulks Materials

70%

80.00%

79.00%

70.75 %

-9.25%

-8.25%

Pipeline/ Flow lines

15%

70.10%

68.10%

71.00 %

0.90%

2.90%

Overhead Lines

05%

70.10%

68.10%

71.00 %

0.90%

2.90%

PROCUREMENT

100%

78.89%

77.63%

74.49 %

-4.40%

-3.15%

Change above table as per your project Work Breakdown Structure (WBS).  Following are the highlights of Procurement activities during the month;

2. Pre-Order • • • • • • • •

Equipment (Static/Rotary) Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Bulks Materials Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Pipeline/ Flow lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Overhead Lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

3. Post-Order Note: I would suggest segregating activtiies e.g. FAT Complete, Ex-Wors Delivery, Received at Local Port, Received at Site etc. for each WBS element • • • • • •

22

Equipment (Static/Rotary) Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Bulks Materials Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Pipeline/ Flow lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Overhead Lines

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

4. CUMULATIVE PROCUREMENT SUMMARY STATUS

Description

Scope

Plan

For

Submission of KVD for COMPANY Approval

Receive Key Vendor Documents

Issue Purchase Order Act

Plan

For

Act

Plan

For

KVD Approved by COMPANY

Act

Plan

For

Act

Fabrication documents are Approved Plan

For

Sub-orders are Completed

Act

Plan

For

Act

Equipment (Static/Rotary) Bulks Materials Pipeline/ Flow lines Overhead Lines Total

Issue Purchase Order Description

Manufacturing

Final acceptance EXW

FOB delivery

Material Receipt at site

Scope Plan

For

Act

Plan

For

Act

Plan

For

Act

Plan

For

Act

Plan

For

Equipment (Static/Rotary) Bulks Materials Pipeline/ Flow lines Overhead Lines Total

Change above table as per your project requirments, Work Breakdown Structure (WBS) and Rule of Credit.  Following are the highlights of Procurement activities during the month;

5. CRITICAL EQUIPMENT & MATERIALS (Long Lead Items) STATUS ➢ Pumps • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ Package Equipment • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ ESD Valves • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ DCS System • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ Power Skids • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ Others •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

 Following major activities are planned for Procurement activities during the next month;

23

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Act

Monthly Progress Report - Template 000 6. Pre-Order • • • • • • • •

Equipment (Static/Rotary) Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Bulks Materials Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Pipeline/ Flow lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Overhead Lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

7. Post-Order Note: I would suggest segregating activtiies e.g. FAT Complete, Ex-Wors Delivery, Received at Local Port, Received at Site etc. for each WBS element • • • • • • • •

Equipment (Static/Rotary) Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Bulks Materials Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Pipeline/ Flow lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Overhead Lines Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

8. CRITICAL EQUIPMENT & MATERIALS (LONG LEAD ITEMS) STATUS ➢ Pumps • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ Package Equipment • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ ESD Valves • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ DCS System • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ Power Skids • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

➢ Others • •

24

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 C. CONSTRUCTION INCL. PRE-COMMISSIONING AND COMMISSIONG 1. Construction/Pre-com/Comm. Progress (%) Summary Current MONTH (%) DESCRIPTION

Plan

Wtg.

CUMMULATIVE (%) Variance

Variance Fore cast

Actual

Base line

Fore cast

Temporary Office & Campe Facilities

99.00%

98.95%

95.00%

-4.00%

-3.95%

Procedures & Fabrication Drawings

80.00%

79.00%

70.75%

-9.25%

-8.25%

Pre-fabrication / Fabrication

70.10%

68.10%

71.00%

0.90%

2.90%

Construction Work

70.10%

68.10%

71.00%

0.90%

2.90%

Pre-commissioning

80.00%

79.00%

70.75%

-9.25%

-8.25%

Commissioning

70.10%

68.10%

71.00%

0.90%

2.90%

As Built, Final Doc.

70.10%

68.10%

71.00%

0.90%

2.90%

78.89%

77.63%

74.49%

-4.40%

-3.15%

C - CONSTRUCTION

Fore cast

Actual

Plan Base line

Base line

Base line

100%

Fore cast

Change above table as per your project Work Breakdown Structure (WBS).  Following are the highlights of Construction activities during the month;

2. General: • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

3. Temporary Office & Site Facilities: • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

4. Procedures & Fabrication Drawings etc. • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

5. Pre-Fabrication / Fabrication (Piping, Steel etc.): • • • • •

25

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 6. Construction Including Mechanical Completion: Major Construction Commodities & Productivities:

Work Item Description

UOM

Concrete Works

M3

Structural Fabrication

MT

Structural Erection

MT

Equipment Erection

MT

A/G Piping -Fabrication

ID

A/G Piping - Erection

ID

U/G Piping - Laying

ID

Cable Laying - Electrical

KM

Cable Laying - Instrumentation

KM

Cable Laying - Telecom

KM

Pipeline/Flow-line

KM

Overheal Lines (132kV)

KM

Roads (Gatch)

KM

Painting

M2

Insulation

M2

Total QTY

Cumulative

Plan

Act

During the Month

Plan

Productivity

Act

Planned for Next Month

Others

Change above table and below activities breakdown as per your project scope and WBS.  Following are the highlights of Construction activities during the month; Pre-fabrication (Piping/Steel) Works: • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Concreting Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Equipment (Stationary/Rotary) Works:

• • • •

26

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 Road Works: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Pipeline Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Flow Line Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Electrical Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Instrumentation Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Telecom Works:

• • • • • •

27

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 Over Head Power Line Works: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Other Works: (as per your Project Scope & WBS)

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

7. Pre-Commissioning: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

8. Commissioning: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

9. As-Built & Final Documentation • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

 Following major activities for Construction are planned during the next month; Pre-fabrication (Piping/Steel) Works: • • • • • •

28

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 Concreting Works: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Equipment (Stationary/Rotary) Works:

• • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Road Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Pipeline Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Flow Line Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Electrical Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Instrumentation Works:

• • •

29

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Telecom Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Over Head Power Line Works:

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Other Works: (as per your Project Scope & WBS)

• • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

10. Pre-Commissioning: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

11. Commissioning: • • • • • •

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

12. As-Built & Final Documentation • • • • •

30

Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here Your Text Here

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 13. MANPOWER DEPLOYMENT SUMMARY Last Month Description

Baseline

Forecast

This Month Actual

Baseline

Forecast

Cumulative Actual

Baseline

Forecast

Actual

Engineering Procurement Construction (Indirect) Construction (Direct) Total:

14. CONSTRUCTION EQUIPMENT DEPLOYMENT SUMMARY Last Month

This Month

Cumulative

Description Baseline

Forecast

Actual

Baseline

Forecast

Actual

Baseline

Forecast

Actual

Civil Works Mechanical Works Road Works OHL Works Total:

31

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 D. PROJECT, QUALITY AND CONTRACT MANAGEMENT 1. INVOICING STATUS Sr. No.

Invoice Received Date

Invoice No.

Invoicing Month

Invoice Amount (US$)

VAT Amount (AED)

Total Invoice Amount incl. VAT (US$)

Payment Received

1 2 3 4 5 TOTAL

2.

Monthly Accrual Contract Value Category

Accrual to Date

Latest Forecast

Original

Cumulative to Date

Cum. Previous

For the Month

Lump Sum Element Provisional Sum Optional Sum TOTAL

3. MANAGEMENT OF CHANGE Impact Assessment Description of Variation

Cost (*$1,000)

Schedule (days)

Originator

Issue Date

Status

4. MOC PERFORMANCE EPORT (FOR CLIENT) MoC Process Performance

32

Average Time (days)

Evaluation

N/A

Approval / Rejection

N/A

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000

Number of Changes/Variations

Number

Submitted Under evaluation Waiting for approval Approved Rejected 5. INSPECTION STATUS Total Inspections Notification Scheduled CONTRACTOR This Month

Cumulative

Total Inspections Performed

CLIENT This Month

CONTRACTOR Cumulative

This Month

CLIENT

Cumulative

This Month

Cumulative

6. NCR & CAR STATUS Description

Total Raised

Last Month Open

This Month Close

Open

Cumulative Close

Open

Close

NCR CAR Total:

7. CORRESPONDANCE SUMMARY STATUS Description

Total Letters Issued

Response Required

Response Received/ Issued

Yet to Response

COMPANY to Contractor CONTRACTOR to Company

33

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 9. PROGRESS DELAY ANALYSIS– Major or critical activities if appicable Baseline Activity Name

10.

Early Start

Early Finish

Current Month Total Float

Start

Finish

Total Float

Variance (Finish Date)

Delay Caused By

Mitigation

CRITICAL PATH (Total Float =<xx Days) Extract from Primavera or MS Project and Include as Attachment to Report (Only Include here Key Activities on Critical Path)

34

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)

Monthly Progress Report - Template 000 YOU CAN ADD OTHER SECTIONS AS PER YOUR PROJECT

11.

35

ATTACHMENTS: •

ATTACHMENT NO. I:

Monthly Progress Summary Tables



ATTACHMENT NO. II:

Monthly Project S-Curves



ATTACHMENT NO. III:

Overall Project Milestones



ATTACHMENT NO. IV:

Updated L-III/IV Schedule & Critical Path



ATTACHMENT NO. V:

Next Month Lookahead Schedule



ATTACHMENT NO. VI:

Home Office Deliverable Status



ATTACHMENT NO. VII:

List of Deliverables Issued During the Month



ATTACHMENT NO. VIII:

List of Deliverables Responded with Review/Approval Code by Cleint



ATTACHMENT NO. IX:

List of Deliverables Overdue with Contractor (IFR, IFA & Final)



ATTACHMENT NO. X:

List of Deliverables Overdue/Potential Overdue with Client (IFR, IFA)



ATTACHMENT NO. XI:

List of Deliverables Commented by Client but Not Issued Further



ATTACHMENT NO. XI:

List of Documents Started, Draft Completed but Not Yet Issued



ATTACHMENT NO. XII:

Technical Queries Register



ATTACHMENT NO. XIII:

Procurement Status Register (Detailed Item Wise)



ATTACHMENT NO. XIV:

Variation Control Log



ATTACHMENT NO. XV:

Detailed Correspondance Log



ATTACHMENT NO. XVI:

Project Risk Register (Detailed)



ATTACHMENT NO. XVII:

NOC Register (Detailed)



ATTACHMENT NO. XVIII:

Engineering Workshops Status Register



ATTACHMENT NO. XX:

Major Construction Commodities Curves



ATTACHMENT NO. XXI:

Construction Manpower Deploaymen & Histogram (Plan vs Actual)



ATTACHMENT NO. XXII:

Construction Equipment Deployment & Histogram (Plan vs Actual)



ATTACHMENT NO. XXIII:

Site Instructions Register



ATTACHMENT NO. XXIV:

NCR/CAR Register



ATTACHMENT NO.XXV:

Backlog Analysis - Engineering, Procurement and Construction



ATTACHMENT NO.XXVI:

Project Quality KPI’s Status



ATTACHMENT NO.XXVII:

Project Invoicing Register

EPC WORKS FOR XYZ PROJECT

Prepared by: Mujahid Akhtar)