HERVE BARON

Oil & Gas Engineering Training

HERVE BARON

Dear colleague, I am glad to share with your this educative material on the Engineering of Oil & Gas facilities. I developed it for classroom training sessions which I have been conducting since 2009. This material will give you an overview of the work and deliverables of the different engineering disciplines. I also thrived to produce workflow visuals to help understand the work sequence of each discipline and how they interface. I wish you an enjoyable journey within Engineering…

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON

Training Objectives • To give a detailed knowledge of what engineering of oil and gas facilities consist of •To describe the activities and show a sample deliverable in the various disciplines •To explain the challenges

Scope

HERVE BARON

HERVE BARON

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE Design BARON

Installation

Procurement

Manufacturing

Construction & erection

Inspection & tests

Shipping

Hand-over

HERVE BARON Home office (Paris) •Project management •Detail Engineering (part) •Procurement

Engineering SubContractor (Delhi) Detail Engineering (part)

Shipyard (Korea) Hull Engineering & Fabrication

Satellite office (Pau) •Detail Engineering (part)

Fabrication yard (Nigeria): Fabrication (part)

Offshore (Nigeria):

Installation, commissioning, start-up

Shipyards (Singapore & Malaysia) Topsides Fabrication & Integration

HERVE BARON

Project

Engineering

Procurement

Construction

HERVE BARON

HERVE BARON

Project

Instrumentation & Control

Layout & Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

HERVE BARON

Engineering document register Document revision

Discipline code A

Instrumentation & Control

C

Civil engineering

E

Electrical

G

Project general documents

J

Mechanical

K

Safety

M

Piping & Layout

P

Processes

S

Steel Structures

V

Vessels – Heat exchangers

W

Materials – Welding

Document number

Document title

A

1

48104

Service building instrument. rooms cables routing

B

A

2

48102

Trouble shooting diagrams

D

A

3

48134

F&G system architecture drawing

E

A

4

50100

Instrument index

B

A

7

50003

Spec for instrument installation works and service

C

A

8

50960

Instrument Data sheets for temperature switches

B

A

9

50110

Requisition for pressure relief valves

B

M

1

62059

General plot plan

B

M

2

62020

Piping details standard

C

1

Installation drawings

M

2

62070

Piping general arrangement Area 1

D

2

Detail drawings

M

4

60100

Special items list

D

3

Diagrams

M

5

62250

Piping isometrics booklet

C

4

Lists – Bill of Quantities

M

6

60000

Pipes and fittings thickness calculation

A

5

Isometrics

M

6

62351

Calculation note CN1 - piping stress analysis

A

6

Calculation notes

M

7

60001

General piping specification

C

7

Specifications

M

8

60103

Data sheets for station piping material

B

8

Data sheets

M

9

60200

Requisition for pipes

F

9

Requisitions

Document code

HERVE BARON

Diagram

Key plan

Drawing

HERVE BARON

Drawings common sizes & scales

A0 = 840x1188

A1 = 594x840 A2 = 420x594 A4 = 210x 297

A3 = 297x 420

Scale

1m =

1/1000

1 mm

1/500

2 mm

1/250

4 mm

1/100

1 cm

1/50

2 cm

1/33

3 cm

HERVE BARON

Engineering schedule

HERVE BARON

Engineering resources

Commissioning 9%

Electrical 9%

Mechanical Equipment 6%

Instrumentation /ICSS/Telecom 10%

Naval 4% Process 2% Others 6%

Structural 23%

~1,000,000 man-hours Piping 31%

HERVE BARON

Client Documents submitted to client

Approval/ Comments

Design basis:

Documents for Construction:

- Functional requirements

Construction drawings & specifications

Engineering

- Client specifications

Documents for Purchase: bill of quantity & specification

- Design codes Documents submission

Comments

Vendors

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON

Design Basis Infrastructure:

Feedstock and products flow Feedstock composition Battery limit conditions Equipment Spare

Pressure (bar)

Process facilities: 50

Administrative and technical buildings

45 40

Control room

35

Access road

30

Site fencing, gates, check point

25 20

Performance:

15

Products specifications

10

Energy efficiency, emissions

Design criteria: % of over design

5 0 -85

Utilities: Electric power supply Other utilities

-80

-75

-70

-65

-60

-55

Environment data: Min/max temperature Rain/snow fall Wind Geological conditions

Systems: Process control Fire/gas alarm Public address, LAN, PABX

Applicable codes and standards: International standards Local rules

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON

Engineering disciplines Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Functional requirements – example of a gas compression station Gas composition

Performance

HERVE BARON

TEG

HP Compression & TEG Gas Injection

1200 psig 3000 psig

500 psig

200 psig

IP Compression From Wells 165 - 205 F

HP Separator 500 psig

5500 psig

50 psig

LP Compression

5 psig

Cooler

Emul. Treater 50 psig 150 F

Process Scheme Optimization

Degasser 5 psig

Oil Production

HERVE BARON

Process simulations

HERVE BARON

Process Flow Diagram (PFD)

HERVE BARON

Equipment list

HERVE BARON

Thermodynamic calculations

Heat & Material balance

HERVE BARON

Equipment sizing

HERVE BARON

Process data sheet

HERVE BARON

Fluid list

HERVE BARON

Piping & Instrumentation Diagram (P&ID)

Line List

HERVE BARON

Piping & Instrumentation Diagram (P&ID)

HERVE BARON

P&IDs legend & symbols

HERVE BARON

Line sizing

HERVE BARON

Process automations: Cause & effect chart

HERVE BARON

Process control

HERVE BARON

Process safety

HERVE BARON

ESD logic diagram

HERVE BARON

ESD simplified diagram

HERVE BARON

Flare Report

HERVE BARON

HERVE BARON

Operating manual

HERVE BARON

Quiz: Is this a P&ID? a PFD?

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Process design PFDs H&M balance

Process data sheet

Equipment specification Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.

HERVE BARON

Equipment list

HERVE BARON

Rotating machinery

HERVE BARON

Pressure vessels

HERVE BARON

Heat exchangers

HERVE BARON

Packages

HERVE BARON

Process data sheet Mechanical data sheet

HERVE BARON

Vessel guide drawing

HERVE BARON

Material Requisition

HERVE BARON

HERVE BARON

Bid technical evaluation

HERVE BARON

Vendor design

HERVE BARON

Equipment summary

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

HAZOP Review RISK LEVEL RISK MATRIX

FREQENCY

SEVERITY

HERVE BARON

HAZOP Action sheet

HERVE BARON

HERVE BARON

Fire Fighting

HERVE BARON

Fire Water demand calculation note

HERVE BARON

Fire Water P&IDs

HERVE BARON

Deluge system arrangement drawings

HERVE BARON

Fire fighting equipment location drawing

HERVE BARON

Passive fire protection drawing

HERVE BARON

Passive fire protection

HERVE BARON

Fire & Gas detection layout

Hazardous HERVE area BARON classification drawing

HERVE BARON

Quantitative Risk Analysis (QRA)

Case stuy: Gas leak from random piping component rupture Cause: installation error, corrosion, material defect… Possible consequence: Dispersion without ignition / jet fire / flash fire / explosion Section considered: Compressor building

HERVE BARON

Quantitative Risk Analysis (QRA)

Step 1: Identification and characterisation of initiating events

Σ risk components *failure rate (from statistics)

Gas leak inside compressor buidling due to component rupture

Frequency (event/year) Outflow rate (kg/s)

Hole size (% of component section) 5%

20%

Full

1,11E-01

5,06E-04

6,83E-05

5,7

90,8

2270,0

HERVE BARON

Quantitative Risk Analysis (QRA) Step 2: Event tree analysis Release Frequency

Probability of immediate ignition for 1-50 kg/s release rate is 7% (from statistical data)

Immediate ESD & Fire Fighting ignition

0,998 0,070

Delayed Ignition

Explosion/ Flash-fire

Consequence Event

Frequency (ev/y)

Gas detectors are provided inside the building, that activate isolation and depressurization. It is Jet fire ESD & FF 7,779E-03 assumed that they operate 95% of the time.

0,002

Jet fire no ESD & FF

1,520E-05

Probability of explosion vs flash fire depends on mass of gas and degree of confinement

1,11E-01 Release/yr 0,949

Dispersion

9,827E-02

0,120

Explosion

1,774E-05

0,880

Flash fire

1,301E-04

Dispersion

5,133E-03

0,930 0,028 0,051 0,972

Frequency (event/year) Jet fire ESD & FF 7,779E-03 Jet fire no ESD & FF 1,520E-05 Explosion 1,774E-05 1,301E-04 Flash Fire Dispersion 1,034E-01

Yes

No B04a/b/c/d

5%

Probability of delayed ignition takes into account equipment explosion protection (Ex)

HERVE BARON

Quantitative Risk Analysis (QRA)

Step 3: Consequence evalutation

Overpresssure (bar)

0.2

0.1

0.01

Distance (m)

96

167

1270

CONSEQUENCE CLASS

QUANTITATIVE CRITERIA

EFFECTS

MINOR

≤0.1 bar locally (within 10m)

No effect, no damage

SIGNIFICANT

≤0.1 bar locally (within 50m)

Limited damage to plant and operators

SEVERE

> 0.1 bar within plant

Damage to plant and operators

MAJOR

> 0.1 bar on populated areas

Damage to plant, operators & public

HERVE BARON

Quantitative Risk Analysis (QRA)

Unacceptable risk area– Design change necessary

Final step: classification of risk Release Frequency

Immediate ESD & Fire Fighting ignition

Delayed Ignition

Explosion/ Flash-fire

Consequence Event

As Low As Reasonably Practicable – Plant Management measures Acceptable risk area

Frequency (ev/y)

0,998

Jet fire ESD & FF

7,779E-03

0,002

Jet fire no ESD & FF

1,520E-05

0,070

1.0E-02

1,11E-01 Release/yr Dispersion

9,827E-02

0,120

Explosion

1,774E-05

0,880

Flash fire

1,301E-04

Dispersion

5,133E-03

0,949 0,930 0,028 0,051 0,972 Yes

Frequency (event/year) Jet fire ESD & FF 7,779E-03 1,520E-05 Jet fire no ESD & FF Explosion 1,774E-05 1,301E-04 Flash Fire Dispersion 1,034E-01

No B04a/b/c/d

5%

1.0E-03

1.0E-04 Unlikely 1.0E-05 Rare 1.0E-06

Minor

Significant

CONSEQUENCE CLASS

QUANTITATIVE CRITERIA

EFFECTS

MINOR

≤0.1 bar locally (within 10m)

No effect, no damage

SIGNIFICANT

≤0.1 bar locally (within 50m)

Limited damage to plant and operators

SEVERE

> 0.1 bar within plant

Damage to plant and operators

MAJOR

> 0.1 bar on populated areas

Damage to plant, operators & public

Severe

Major

HERVE BARON

Environmental Impact Assessment (Air quality dispersion analysis)

HERVE BARON

Noise Map

dB(A)

HERVE BARON

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Process design PFDs

P&IDs

H&M balance

Piping Instrumentation

Process data sheet

Equipment specification Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.

Vendor drawings

Layout Civil Electrical

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

Grading plan

Required finish level

Native soil elevation

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

Vendor information

HERVE BARON

Foundation Calculation

HERVE BARON

Foundation drawing/ re-inforcement

HERVE BARON

Foundation drawing/ Formwork

HERVE BARON

Civil works specification

HERVE BARON

HERVE BARON

Loading data

HERVE BARON

Structural design

HERVE BARON

Calculation note

HERVE BARON

Structural drawings

HERVE BARON

Architectural drawings

Equipment layout drawing

HERVE BARON

HERVE BARON

HERVE BARON

Heating, Ventilation &Air Conditioning (HVAC)

HERVE BARON

Civil Works Installation Drawings

HERVE BARON

HERVE BARON

Standard drawings

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Process design PFDs

P&IDs

H&M balance

Piping Instrumentation

Process data sheet

Equipment specification Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.

Vendor drawings

Layout Civil Electrical

HERVE BARON

HERVE BARON

HERVE BARON

Layout/ principles

HERVE BARON

Layout/vendor drawings

HERVE BARON

Layout/consideration for all networks

HERVE BARON

General Plot Plan

HERVE BARON

Unit Plot Plan

HERVE BARON

HERVE BARON

HERVE BARON

3D modelling

HERVE BARON

3D model clash check

HERVE BARON

3D model review

HERVE BARON

Equipment handling

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Process design PFDs

P&IDs

H&M balance

Piping Instrumentation

Process data sheet

Equipment specification Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.

Vendor drawings

Layout Civil Electrical

HERVE BARON

Line Diagram

HERVE BARON

HERVE BARON

Piping Layout drawing

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

Isometric drawing

HERVE BARON

Piping Pre-fabrication

HERVE BARON

Post Weld Heat Treatment

HERVE BARON

Piping Inspection and testing

HERVE BARON

Piping General Arrangement drawing

HERVE BARON

Calculations

HERVE BARON

HERVE BARON

Standard Pipe Support drawings

HERVE BARON

HERVE BARON

HERVE BARON

Plot Plan

Piping line diagram

Piping installation work process

Piping studies & layout

Piping 3D modelling

Piping stress analysis

Piping isometric drawing

Stress OK?

Process OK?

Piping isometric drawing IFC

HERVE BARON

HERVE BARON

Material Selection

HERVE BARON

Material Selection Diagram

HERVE BARON

HERVE BARON

Process Fluids list

Piping material classes

HERVE BARON

Piping material classes

Piping material class specification

HERVE BARON

Piping material classes specification

HERVE BARON

Piping material classes specification

HERVE BARON

Piping material classes specification

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

HERVE BARON

Σ

HERVE BARON

Piping material requisition

HERVE BARON

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Piping & Instrumentation Diagram (P&ID)

HERVE BARON

HERVE BARON

HERVE BARON

Instrument list

HERVE BARON

Level sketch

HERVE BARON

Instrument data sheet

HERVE BARON

Process Control System

HERVE BARON

System Architecture drawing

HERVE automations Process BARON

HERVE BARON

Control narrative

HERVE BARON

Mechanical Equipment Control

HERVE BARON

Emergency shutdown

HERVE BARON

The instrument hardware Instrument room Marshalling

Controller

cabinet

cabinet

Control room

VDU

PT

JB

Process line

CPU

LAN Secondary cable Multi cable

HERVE BARON

Junction Box drawing

HERVE BARON

Instrument location drawing

HERVE BARON

Building detail drawing/ Telecom and PAGA layout

HERVE BARON

Instrument standard installation drawings

HERVE BARON

Junction box wiring

HERVE BARON

Cable routing drawings

Cable list

HERVE BARON

Instrument bulk Material Take-Off

ITEM

QUANTITY

DESIGNATION

1

195

Gauge adapter – ½” x ½”

2

37

Block manifold 2 valves (Gas) – ½”

3

23

Block manifold 5 valves (Gas) –½”

4

0

Ball valve ½” – 12mm

5

300m

6

200

Reducer – 12mm x ¼”

7

50

Union tee – 12 x 12 x 12mm

8

50

Female connector – 12mm x ½”

9

350

Male connector – 12mm x ½”

10

9

Plug – ½” NPTF

11

8

Plug – ½” NPTM

Tubing – 12mm OD x 1mm

HERVE BARON

Cable routing inside technical room

HERVE BARON

Instrumentation & control rooms layout

HERVE BARON

Screen displays

HERVE BARON

Instrument loop diagram

HERVE BARON

Engineering Process Equipment HSE Civil Layout Piping Instrumentation Electrical

HERVE BARON

Electrical consumer list

HERVE BARON

Electrical Load Summary

HERVE BARON

HERVE BARON

General One Line Diagram

HERVE BARON

Generators

Switchgear

Transformer

HERVE BARON

Equipment data sheet

HERVE BARON

Switchboard Single Line Diagram

HERVE BARON

Switchgear Typical Diagram

VOLTAGE OF MS-001 (STUDY1)

HERVE 10000 BARON 9900 9800

Bus Volt a ge (Volt s )

9700 9600 9500 9400 9300 9200 9100 9000 8900 8800 0.0

2.5

5.0

7.5

10.0 Time (Seconds)

12.5

15.0

17.5

20.0

FREQUENCY OF MS-001 (STUDY1) 50.0

Bus Frequency (Hz)

49.5

49.0

48.5

Calculations

48.0

47.5

47.0 0.0

2.5

5.0

7.5

10.0 Time (Seconds)

12.5

15.0

17.5

20.0

HERVE BARON Cable

routing drawing

Cable schedule

HERVE BARON

Typical installation drawings

HERVE BARON

Block Diagram

HERVE BARON

Trouble shooting diagrams

HERVE BARON

Lighting layout

HERVE BARON

Lighting illumination level

Iso lux curves

HERVE BARON

Electrical equipment layout

HERVE BARON

Electrical Control System

HERVE BARON

Electrical Control System

HERVE BARON

From main power generators

From emergency (diesel) generators

Electrical load shedding

To normal consummers e.g. pumps in process and utility units

To essential consummers e.g. fire water pump

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON

Field Engineering

HERVE BARON

Site Query

HERVE BARON

Site MASTER set of documents

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON PROJECT SCHEDULE PLANT START-UP PIPING PRE-FABRICATION & INSTALLATION PIPING MATERIAL & DRAWINGS AT SITE PIPING MATERIAL MANUFACTURING & SHIPPING PURCHASE OF PIPING MATERIAL TECHNICAL & COMMERCIAL CLARIFICATIONS CALL FOR TENDER FOR PIPING MATERIAL PREPARE PIPING MATERIAL TAKE-OFF PIPING ROUTING STUDIES PIPING & INSTRUMENTATION DIAGRAMS (PIDs)

1

MONTH 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

5

4 X X X X X X

1X

2 3X

X X

X X

5

3

4 2

X X X X X X X X X X

5

HERVE Process BARON

simulations Process data sheet Equipment selection & purchase Vendor data

Foundation drawings

HERVE BARON

HERVE BARON

Engineering schedule

Safety valves duty & data sheet (Process)

Size & weight estimates

Safety valves inquiry and purchase (procurement)

Safety valves location & piping routing (piping/layout)

Estimates must be done to meet the schedule

Piping calcs & supports (piping/stress) Steel structure design and drawings (civil)

Supports & loads estimates Purchase steel (manufacturer)

Safety valves sizing & drawings (vendor)

Fabrication (manufacturer) Shipping

Structure at Site

HERVE BARON

HERVE BARON

What the Vendor supplied

What Engineering designed

HERVE BARON

HERVE BARON

Oil & Gas Engineering Training HSE Moment Intro, scope & objectives Project Engineering The Design Basis Discipline presentations Field engineering Schedule Quality

HERVE BARON

Engineering Quality Assurance: Engineering document register

Document number

Document title

Document revision

A

1

48104

Service building instrument. rooms cables routing

B

A

2

48102

Trouble shooting diagrams

D

A

3

48134

F&G system architecture drawing

E

A

4

50100

Instrument index

B

A

7

50003

Spec for instrument installation works and service

C

A

8

50960

Instrument Data sheets for temperature switches

B

A

9

50110

Requisition for pressure relief valves

B

M

1

62059

General plot plan

B

M

2

62020

Piping details standard

C

M

2

62070

Piping general arrangement Area 1

D

M

4

60100

Special items list

D

HERVE BARON

Engineering Quality Assurance: Document checking and distribution

HERVE BARON

Engineering Quality Assurance: Document revision

HERVE BARON

Engineering Integrity: Site Query from Construction

HERVE BARON

Interface Agreement

Section/Step 1

Section/Step 2

HERVE BARON

Interface definition

HERVE BARON

The Oil & Gas Engineering Guide 2nd edition

Do you want to know more... Much more?

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition Table of Contents

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition Table of Contents

Discipline presentation: activities and deliverables

© 2015 – Hervé Baron

HERVE BARON

The work of each Engineering discipline is described

© 2015 – Hervé Baron

HERVE BARON

Design activities are explained, e.g., Plant Equipment layout

© 2015 – Hervé Baron

HERVE BARON

Complex activities, such as QRA, are explained through a practical example.

© 2015 – Hervé Baron

HERVE BARON

A sample of all common Engineering documents is included

© 2015 – Hervé Baron

HERVE BARON

Difference between Engineering and Shop drawings

© 2015 – Hervé Baron

HERVE BARON

Understand the main technical aspects, e.g., DCS vs ESD

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition Table of Contents

The overall process © 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition Table of Contents

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition Table of Contents

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition Table of Contents

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide 2nd edition Order direct from the publisher: http://www.editionstechnip.com/en/catal ogue-detail/1111/oil-gas-engineeringguide-the.html

© 2015 – Hervé Baron