PT. PLN ( PERSERO ) DISTRIBUSI BANTEN

1.

2.

LAPORAN PEKERJAAN.

Kode Unit :

Pemeliharaan Sistem Pembumian (Arde)

DIS.HAR.010(2).A

DATA 1.1. Nomer Gardu Portal 1.2. Lokasi 1.3. Tanggal Pemeliharaan

: Gardu Portal DTA : Kawasan Pendidikan Tangerang : 15 November 2017

URAIAN PEKERJAAN : Pengukuran Tahanan Pembumian : a. Pada Saat Posisi Kabel Sejajar : Nilai Tahanan Pembumian = 0.9 ohm. b. Pada Saat Posisi Kabel Silang : Nilai Tahanan Pembumian = 0.67 ohm.

Kesimpulan Hasil Pembumian : Dari dua hasil yang didapatkan nilai tahanan pembumian di lokasi gardu portal sangat bagus, dikarenakan hasilnya dibawah standar maksimal nilai tahanan pembumian yaitu 0.9 dan 0.67 ohm . Sedangkan Nilai maksimal tahanan pembumian 5 ohm. Tangerang,16 November 2017 Petugas Pemiliharaan

Wirangga Septiano Putra

Dokumentasi

Mengetahui

(

)

S

Safety Briefing

Gelar Kabel

Penancapan Ground Rod

Pengukuran Nilai Tahanan Pembumian

Nilai Tahanan Pembumian yang didapatkan dari alat ukur Kyoritsu