Process and Production Introduction and key activities
© 2015 LafargeHolcim
Key topics of PRODUCTION & PROCESS group Synergies & Cost Leadership • Clinker and cement volume increase • Mining sustainability • Improve eqpt. availability • Energy cost management • Optimize cost • Organizational efficiency
• Improve product quality (via clinker reactivity)
Regional Project / Initiatives
• • • • • •
• Application-Based Cement Testing Proj.
SATF Support
• • • • • •
Support MTP Target
HEALTH & SAFETY
Commercial Excellence & Innovation
Area Ownership Talent Dev’t.
Petcoke Proj. Slag-Addition Proj. Clinker movement Vertical Mill Optmization Cooler Optimization World-Class Maint. Proj.
COi bmi MANi FANi IFC Others
15.7 mCHF 7.6 mCHF 7.3 mCHF 2.1 mCHF 6.9 mCHF 14.3 mCHF
Lean Capital Spending • Maximize asset utilization • Key CAPEX to Develop Projects (e.g. Kanthan debottlenecking)
871.7 mio CHF
regional CIP reduces risk of not achieving
• Product portfolio management (technical)
• CAPEX Management • Leverage on Best Cost Countries
TARGETED BENEFITS
• DSCQP
32 – 39 mCHF
• Establish business case for actions that require CAPEX
TARGETED BENEFITS
Architecture, Assessment & Development and Certification 2015-08-04
2016 CLC EBITDA 1
Training and Development, Succession Planning and Communities of Best Practice © 2015 LafargeHolcim
53.9 mCHF
1
excl. Myanmar, Australia and New Zealand 2
PRODUCTION AND PROCESS Vertical Mill Optimization Vertical Mill Optimization • Recurring savings of 5 mCHF per year (Philippines, Malaysia and Indonesia) • Increasing mill throughput to increase clinker volume • Reduction of electrical energy consumption by 0.5-0.8 kWh/t clinker • Regional CIP activities: • Conduct B level on-site together with the plant • Support designing the modification (without CAPEX) • On-site support on the modification and commissioning © 2015 LafargeHolcim
PRODUCTION AND PROCESS Sample Case: Hon Chong VRM Optimization • Root cause:
Existing raw mill BDP 334 tpd will be unsufficient to scope with kiln 5,000 tpd project when the raw mill capacity required 359 tph (dry) at least
• Objectives:
To debottleneck the raw mill to increase the capacity at least 359 tph (dry)
To address all the bottleneck on auxiliary equipment to maintain the raw mill capacity at highest level • Scope:
Modify the blind plates of nozzles ring Optimize gas flow control to keep raw mill fan sufficient at new capacity
• Total budget:
30,000 USD
• Achievement:
Raw mill production increase achieved – 367 tph
Power reduction in Raw mill – 0.8 Kwh/ton
© 2015 LafargeHolcim
4
PRODUCTION AND PROCESS Clinker Cooler Optimization Clinker Cooler Initiative • Recurring savings of 3 mCHF per year (Philippines, Malaysia and Indonesia) • Reducing the specific heat consumption by 15 kcal/kg clinker • Improvement in clinker quality • Regional CIP activities: • Conduct B level on-site together with the plant
• Support designing the modification (without CAPEX)
• On-site support on the modification and commissioning © 2015 LafargeHolcim
PRODUCTION AND PROCESS False Air Reduction Initiative False Air Reduction • Tracking, best practices sharing and pilot plant implementation • Focus areas: VRM, main dedusting and pre-heater
• Benefits: Reduction in electrical and thermal energy including volume increase through process efficiency. • Regional CIP activities: • On-site assessment and coaching together with the plant • Support designing the modification (without CAPEX) © 2015 LafargeHolcim
Key topics of PROCESS & PRODUCTION group Key project
Description
Potential savings MCHF
Plant covered
Cross Transversal regional CIP initiative
- To optimize energy VRM consumption Optimization - To increase throughput
Davao, Lugait, La Union, Surma, Kanthan, Cilacap
Materials, Maintenance, Training
- To optimize cooler efficiency Cooler - To optimize thermal energy Optimization consumption (via heat recuperation)
Surma, Hon Chong, langkawi
Materials, Maintenance, Training
False Air Reduction
- To reduce false air in the key areas: VRM, main dedusting and pre-heater
All plants
Slow Down Tracking
- To meet the target Production Rate Index
Bulacan, Lugait, Davao, La Union
Maintenance
TOTAL mio CHF
2015-08-04
© 2015 LafargeHolcim
7
© 2015 LafargeHolcim