Loading documents preview...
Productivity Rates No. of working days : 6 days/ week (Saturday to Thursday, Friday is day off) Working shifts : one shift / day Working hours : 8 hours / day Over time and Fridays shall be used if necessary to keep on schedule or to compensate for any unexpected events.
No
Division
Productivity Rate per day
Item Describtion
Crew (Manpower/Equipment)
1
Div 02
Excavation Works
350 m³
1nos Loader
2
Div 02
Shoring
50 m²
4 shoring labours
3
Div 02
Backfilling
80 m³
2 Roller + 2 compactor + 4 labors
4
Div 02
Preparation of blinding
200 m²
3 Labours + 1 Compactor
5
Div 02
Anti Termite Control
600 m²
1 labour
6
Div 02
Kerbstones
75m
3 Masons
7
Div 02
Inerlock Tiles
30m²
8
Div 02
Asphalt
9
Div 03
Concrete Slab
30m²
4 Masons 1 Asphalt paver + Roller + Pnuematic wheel + compacter & compressor 4 carpenters + 2 labour + 4 Steel Fixers
10
Div 03
Concrete Columns
5 nos
2 carpenters + 2 steel Fixers + 2 Labours
11
Div 03
Precast Concrete Cladding
60m²
6 mason + 1 crane
12
Div 03
Concrete Topping / Screed
40m³
5 concreter + 1 finisher
13
Div 03
Leight weight concrete
60m³
6 concreter + 1 finisher
14
Div 04
Block Works
15m²
1 Block work mason + 1 Labour
15
Div 04
Glass Block Works
5m²
1 Mason + 1 Helper
16
Div 05
Handrails
10m
1 Handrail mason + 1 helper
17
Div 07
Waterproofing membrane
60m²
1 WP mason
18
Div 07
Protection Board
60m²
1 WP mason
19
Div 07
Building Insulation
100m²
1 Mason + 1 Helper
20
Div 07
Concrete Pavers for Roof
30m²
1 Tile Layer + 1 Helper
21
Div 07
Metal panels cladding
30m²
1 Cladding Mason + 1 Helper
22
Div 07
Aluminium Flashing
60m²
1 Mason + 1 Helper
23
Div 07
Fire Stop
40mr
1 Mason + 1 Helper
24
Div 08
Door Frames
5 Nos
1 Doors carpenters + 1 helper
25
Div 08
Door Leaves
5 Nos
1 Doors carpenters + 1 helper
26
Div 08
Door Hardware
5 Nos
1 Doors carpenters + 1 helper
27
Div 08
Frameless Glass panels
30m²
2 Metal Masons + 1 helper
28
Div 09
Cement plaster 1st stage
60m²
1 Plaster mason + 1 Helper
29
Div 09
Cement plaster 2nd stage
30m²
1 Plaster mason + 1 Helper
30
Div 09
Ceramic walls for wet areas
12m²
1 ceramic mason + 1 helper
31
Div 09
Ceramic Skirting
30mr
1 ceramic mason + 1 helper
32
Div 09
G.B partition Studs+1st Layer +Insulation
20m²
2 mason + 1 Helper
33
Div 09
G.B parititions Closing
50m²
2 mason + 1 Helper
34
Div 09
Gypsum false ceiling
20m²
1 Mason + 1 Helper
35
Div 09
Metal false ceiling
30m²
1 Mason + 1 Helper
36
Div 09
Paint preparation
40m²
1 Painter
37
Div 09
Painting Coats
40m²
1 Painter
38
Div 09
Vinyl Tiles
25m²
1 Tile Layer + 1 Helper
2000m²
111
Productivity Rate per day
No
Division
Item Describtion
39
Div 09
Rubber Tiles
25m²
1 Tile Layer + 1 Helper
40
Div 09
Marble Tiles
12m²
1 Tile Layer + 1 Helper
41
Div 09
Marble Skirting
30mr
1 Tile Layer + 1 Helper
42
Div 09
Marble Threshold
20mr
1 Tile Layer + 1 Helper
43
Div 09
Marble Counter
15mr
1 Tile Layer + 1 Helper
44
Div 09
Granite Flooring
12m²
1 Tile Layer + 1 Helper
45
Div 09
Terrazzo Tiles
15m²
1 Tile Layer + 1 Helper
46
Div 09
Insitu Terrazo tiles
5m²
1 Tile Layer + 1 Helper
47
Div 09
Carpet Tiles
40m²
1 Tile Layer + 1 Helper
48
Div 09
Wood Flooring
10m²
1 Mason + 1 Helper
49
Div 10
Wall & Corner guards
7 nos
1 Mason + 1 Helper
50
Div 10
Toilet Accessories
5 nos
1 Mason + 1 Helper
51
Div 10
Access Flooring
20m²
1 Mason + 1 Helper
52
Div 10
Internal Signage
12 Nos
1 Signage Mason
53
Div 12
Lab Furnitures
10 seats
1 Finishing Carp. + 1 helper
54
Div 13
Shelter Doors
1 nos
55
Div 15
Laying Water supply pipes
30m
1 plumber + 1 helper
56
Div 15
Laying Drainage pipes
24m
1 plumber + 1 helper
57
Div 15
Laying Fire Fighting Pipes
24m
1 FF Pipe Fitter + helper
58
Div 15
Laying HVAC Ducts
70 kg
1 Duct Fitter + 1 helper
59
Div 15
Duct Insulation
20 m
1 Duct Fitter + 1 helper
60
Div 15
HVAC Piping
20m
1 Pipe Fitter + 1 helper
61
Div 16
Installing Cable Trays
15m
1 Electrician + Helper
62
Div 16
Electrian Conduiting
24m
1 Electrician + Helper
63
Div 16
Wiring Works
400m
3 Electricians + 3 helpers
64
Div 16
Laying Cables
20m
3 Electricians + 3 helpers
112
Crew (Manpower/Equipment)
3 Mason + 1 Helper