Project Risk Log Template Wilmont's Pharmacy Drone Project Revision: 0; Date: 02-July-2020
Risk ID Priority
1
2
2
2
3
2
WBS
1.1.3
1.2.1
1.3.1
Dates
2
10
Katie O'Ryan
02-Jul-20
4
3
12
Eileen Seymour
Design is not completed in a timely manner
Delay in DroneTech system interface to Wilmont's system
1.4.1, 1.4.2, 1.4.3 Eileen Seymour
5
3
1.4.2
Eileen Seymour
Customer data is not protected during regsitration process
6
1
1.2.2
Sandeep Vasu
Cost estimate is incorrect. Fund issues
Gerald Hasper
Drones fail to operate during testing
8
1
9
2
10
3
5 4 3 2 1
1.6.1
1.6.4
1.3.2, 1.6.4
1.7.1, 1.7.2
02-Jul-20
4
02-Jul-20
5
3
3
Prior to After Mitigation Mitigation Mitigation Strategy
12
15
> 4 Weeks delay
<1 week delay
Add schedule contingency in plan for design to be complete. Add additional staff
$4,000
Add schedule contingency in plan for construction to be complete. Add additional staff
$4,000
Add schedule contingency in plan for system interface to be complete. Add additional staff
$8,000
2
2
4
02-Jul-20
5
3
15
02-Jul-20
5
1
5
02-Jul-20
4
4
16
Gerald Hasper
Harsh weather affecting Drone Operations
02-Jul-20
4
2
8
William Holt
Products delivery problem due to improper packing system
Double check packing system. Trial runs at DroneTech facility before handover
Wilmont's not accepting change orders/variations Description
02-Jul-20
2
3
6
All change orders to be documented and approved prior to implementation
Sandeep Vasu
Cost
Schedule
Very High High Moderate Low Very Low
> $ 100,000 < $ 75,000 < $ 50,000 < $ 25,000 < $ 10,000
> 4 Weeks delay > 2 Weeks delay > 1 Week delay < 1 Week delay 1-2 days delay
Likelihood Rating Scale
Description
5 4 3 2 1
> 80% probability of occuring 50-80% chance of occuring 21-49% chance of occuring 1-20% chance of occuring < 1% chance of occuring
Scope
Quality Drone not operating Product damage Drone performance affected Compensation Required Corrections required
Health, Safety and Environment
Contingency
Add schedule contingency in plan for contract negotiations to be complete.
02-Jul-20
Impact Rating Scale
Nearly Certain Likely Possible Unlikely Rare
Severity
5
1
2
Likelihood Rating
Contract with Wilmont's cannot be finalized in time for scheduled start 02-Jul-20 of Project
4
7
Impact Rating
Risk Description
Construction of Drones is not completed in a timely manner
Closed
Impact
Responsible Person
William Holt
Open
Analysis
Double check system integrity during customer registration > 4 Weeks delay
<1 week delay
Consider a cost contingency of 10% over budget
$25,000
Double check design. Flight Operations team to be involved in design > 2 Weeks delay
<1 week delay
Alternate delivery methods to be developed and standby in case of adverse weather
$10,000
Status