IRAQ GATES CONTRACTING COMPANY Method Statement

Rev: 02

Testing MV Cables at Um-Qasr xxxxxxxxxxxxx

Doc. Cat.

EXT

Method Statement

Testing MV Cables at Um-Qasr

02

13 July 2018

Revised

C.B.

BGC

A

01-May2018

Issued for Review

A.W.

E.B.

B.M.

REV

DATE

DESCRIPTION

PREPARED BY

REVIEWED BY

APPROVED

1 OF 7

IRAG GATES CONTRACTING COMPANY

Method Statement

Testing MV Cables at Um-Qasr XXXXXXXXXXXXX

Rev: 02 Doc. Cat.

EXT

TABLE OF CONTENTS 1.

Introduction

2.

Definitions

3.

Abbreviations

4.

Methodology

5.

MTO

6.

HSE Requirements

7.

Attachments

2 OF 7

IRAG GATES CONTRACTING COMPANY

Method Statement

Testing MV Cables at Um-Qasr XXXXXXXXXXXXX

Rev: 02 Doc. Cat.

EXT

Method Statement

Testing MV Cables at Um-Qasr 1. Introduction As part of BGC development plan, Work Order (WO-026) to perform Refrigerated Export Project (Testing MV Cables at Um-Qasr) at Um-Qasr Storage Terminal has been issued to IGCC. This Method Statement, aims to provide sufficient definition for Refrigerated Export Project (Testing MV Cables at Um-Qasr) Storage Terminal. Its intent is to also facilitate implementation in a safe and efficient manner and for all involved parties to understand the risks, roles and responsibilities associated with the Testing MV Cables at Um-Qasr.

2. Definitions COMPANY

BGC (Basra Gaz Company)

PROJECT

Refrigerated Export Project Testing MV Cables at Um-Qasr

CONTRACTOR

(IGCC) Iraq Gates Contracting Company

WORK

Shall mean all and any of the work andor services andor materials required to be provided by the CONTRACTOR under contract with COMPANY.

SHALL AND MUST

Indicates mandatory requirements.

SHOULD

Indicates that a provision is not mandatory but recommended as good practice.

3. Abbreviations Abbreviation

Definition

SOW

Scope of Work

BGC

Basra Gas Company

3 OF 7

IRAG GATES CONTRACTING COMPANY

Method Statement

Testing MV Cables at Um-Qasr XXXXXXXXXXXXX

Rev: 02 Doc. Cat.

EXT

4. Methodology 4.1 Engineering Phase - Preparation and Submission of Method Statement. - Preparation and Submission of all HSE Deliverables. - Preparation and Submission of all QA/QC Deliverables.

4.2 Procurement Phase - N/A

4.3 Mobilization Phase - Transportation to site all Manpower & Equipment. - Establishment of Site Office for IGCC’s Staff.

4.4 Dismantling Phase 4.4.1 Prior to Start the Works - Having valid PTW with approved method statement. - Having Electrical isolation certificate from client. - Area Barricaded with all HSE signs.

4.4.2 Testing of MV Cables at Storage Terminal 4.4.2.1 Preparation Works - Perform zero voltage verification for all circuit elements - Cable disconnecting from the both sides 4.4.2.2 Continuity Test - By utilizing calibrated multi-meter tester, continuity test will be performed by qualified electrician. - Continuity Test and record on related BGC - ITR form

4 OF 7

IRAG GATES CONTRACTING COMPANY

Method Statement

Testing MV Cables at Um-Qasr XXXXXXXXXXXXX

Rev: 02 Doc. Cat.

EXT

4.4.2.3 IR Test - By utilizing calibrated Megger tester, IR test will be performed by qualified electrician - IR Testing voltage shall not exceed the cable operating voltage; for 3.3KV cables the test will be done at 2.5KV and the 11KV cables will be tested at 5KV - Record the measured value on related ITR form 4.4.2.4 Hi-Pot Test - By utilizing calibrated Hi-Pot Very Low Frequency (VLF) tester, Hi-Pot test will be performed by qualified electrician - Hi-Pot DC voltage is not to be used, under any circumstances - VLF voltage must not exceed the nominal / operating voltage - As an alternative of VLF Hi-Pot testing, may be applicable the “soak test” at nominal voltage and frequency - Record the Hi-Pot measured value on related ITR form 4.4.2.5 List of Cables FROM 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 11kV Switchboard MMS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1

TO Refrigeration Compressor Refrigeration Compressor Refrigeration Compressor Refrigeration Compressor Refrigeration Compressor Propane Shipping Pump Propane Shipping Pump Propane Shipping Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Propane Booster Pump Butane Booster Pump

TAG 6100MK-1A 6100MK-1B 6100MK-1C 6100MK-1D 6100MK-1E 6100MP-10A 6100MP-10B 6100MP-10C 6100MP-3A 6100MP-3B 6100MP-3C 6100MP-3D 6100MP-4A 6100MP-4B 6100MP-4C 6100MP-4D 6100MP-5A 6100MP-5B 6100MP-5C 6100MP-5D 6100MP-6A

Cable Sizes 2 x 3 core 150mm2 2 x 3 core 150mm2 2 x 3 core 150mm2 2 x 3 core 150mm2 2 x 3 core 150mm2 1 x 3 core 70mm2 1 x 3 core 70mm2 1 x 3 core 70mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 5 OF 7

IRAG GATES CONTRACTING COMPANY

Method Statement

Testing MV Cables at Um-Qasr XXXXXXXXXXXXX

FROM 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1 3.3kV Switchboard MS1

TO Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Butane Booster Pump Gasoline Booster Pump Gasoline Booster Pump Gasoline Booster Pump Gasoline Booster Pump Butane Shipping Pump Butane Shipping Pump Butane Shipping Pump Gasoline Shipping Pump Gasoline Shipping Pump Gasoline Shipping Pump

Rev: 02 Doc. Cat.

TAG 6100MP-6B 6100MP-6C 6100MP-6D 6100MP-7A 6100MP-7B 6100MP-7C 6100MP-7D 6100MP-8A 6100MP-8B 6100MP-8C 6100MP-8D 6100MP-11A 6100MP-11B 6100MP-11C 6100MP-9A 6100MP-9B 6100MP-9C

EXT

Cable Sizes 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 35mm2 1 x 3 core 95mm2 1 x 3 core 95mm2 1 x 3 core 95mm2 1 x 3 core 95mm2 1 x 3 core 120mm2 1 x 3 core 95mm2

4.5 Final Documentation - Preparation and Submission of all Final Documentation.

5. MTO N/A

6. HSE Requirements 

Site Induction.



HITRA, JHA & PTW, including approved Method of Statements.



Energy Isolation to be confirmed as per PTW procedure



Where it is not possible to isolate the cable from other equipment, ensure that Surge Arresters and VT’s are disconnected from the cable

 The ‘Cable Tester’ must be the authorized tester who has been appropriately trained and authorized to conduct Testing of HV Cables in accordance with accepted standards. It is the responsibility of the ‘Cable Tester’ to have a clear understanding and comply with the requirements of this ‘Voltage Testing of HV Cables’ technique

6 OF 7

IRAG GATES CONTRACTING COMPANY

Method Statement

Testing MV Cables at Um-Qasr XXXXXXXXXXXXX

Rev: 02 Doc. Cat.

EXT



Job Risk Analysis must be done by the work team before commencing any switching and tests near the underground cables and all parties concerned are in agreement upon that assessment



The tester in charge shall ensure that drawings are made available to familiarize himself with the work area and equipment locations prior to commencing work



Ensure to connect a local earth on the test equipment, if practicable. The case earth must remain connected to the system earth in order to maintain an acceptable single earth potential



After the cable is tested (SI, IR and VLF) cable cores must be then discharged. If applicable, close the Earth switch and then the test set leads may be removed



PPE Requirement:



Use suitable barriers, barricades and warning signs on both sides of the cable to prevent access to the cable by persons not involved with the testing. If there is any danger of exposing the public or staff to energized conductors or equipment a safety observer must be used.



Housekeeping.