WAEP MASTER SCHEDULE (Acelerated) Activity ID
Activity Name
Original Remaining Duration Duration
WAEP MASTER SCHEDULE (Acelerated) Milestones Schedule A1030
Safe Wells, RMT & Inspections
A1060
PUT KCDP-B Well on production
A1040 A1070 A1080
Re-development of greater Kalaekule (P1 + P2)
Blockwide Exploration/Appraisal Development Programme
Integrated Schedule (Accelerated Case)
1.0 Safe Wells & Xmas Trees Workscope (including sourcing) 1.1 Haliburton & P & E Contracts A1910 Addendum to Halliburton Contract to include Supply of Certified NNRA Vessel for RA source Power and Energy Contract
A1940
C & P Contact Vendors for Quotes
604d
0d
0d
460d
Life extension survey & Integrity repair/refurbishment
A1920
803d
0d 0d 0d 0d
Evaluate of Quotes and Contract Award
1.3 Source new SEWOP, Security boats, mobilize and Jack-Up A1960 Obtain NAPIMS Approval of Execution Strategy and Source SEWOP, Security Boats, PSV & FSIV A1970
Inspection of SEWOP and Vessels
A1990
Contract Approval/Execution
A1980 A2000 A2010
Commercial Discussions With Selected Contractor (s) Ten working days notice to SEWOP contractor before mobilization
Mobilization of SEWOP from Warri (4 days to transport, position, jack-up, pre-load and secure in position #1) 1.4 Community Engagement A2020 Meet with Community Leaders and WAEP Management A2030
Secure FTO (FTO Agreement Signed)
A2050
Emergency Response workshop
A2070
Vendor Kick-off Meeting in Port Harcourt
Safe Well Pr e-Activities A2040 Joint HAZOP/HAZID with all vendors in Lagos A2060
0d 0d 0d 0d
A3000 A3010
Backload the equipment on the PSV (Equipment to be moved twice because of available deck space on PSV.)
1.6 RMT Log(Including sourcing and permits timelines) A3020 Boat for RA source. (Bids and Recommendation)
A3070 A3080
Split bar
Actual Work
Mobilize HAL crew (10 persons for RMT and Pump) using FSV(3 days to offload WF equipment, load HAL, transit at SEWOP
PSV loads HAL equipment and takes offshore (1 Day off load and transport to Kalaekule site with SEWOP) Remaining Work
Critical Remaining Work
Milestone
Summary
0% 0%
2d
100% 04-Dec-19*
05-Dec-19
0% 01-Nov-19 100% 01-Nov-19*
05-Jan-20 15-Nov-19
7d
0% 03-Dec-19 100% 03-Dec-19* 100% 06-Dec-19*
03-Jan-22, WAEP MASTER SCHEDULE (Acelera
Safe Wells, RMT & Inspections PUT KCDP-B Well on production
Re-development of greater Kalaekule (P1 + P2)
Blockwide Exploration/Appraisal Development Pro
30-May-20
30-May-20, Integrated Schedule (Accelerated Case)
01-Feb-20
01-Feb-20, 1.0 Safe Wells & Xmas Trees Workscope (including sourcing)
31-Dec-19 16-Dec-19*
31-Dec-19, 1.1 Haliburton & P & E Contracts Addendum to Halliburton Contract to include Supply of Certified NNRA Vessel for RA source Power and Energy Contract
12-Dec-19
12-Dec-19, 1.2 Acquire Riggers Crew/Welders (for Dismantling of Wellfluids Equipment) Define Scope of Work for Dismantling of Wellfluids Equipment C & P Contact Vendors for Quotes
12-Dec-19
Evaluate of Quotes and Contract Award
56d 11d
56d 11d
12d
12d
100% 18-Nov-19
03-Dec-19*
Inspection of SEWOP and Vessels
8d
8d
100% 06-Dec-19
13-Dec-19*
Contract Approval/Execution
100% 30-Dec-19*
05-Jan-20
0d
0d
18d
18d
3d 2d
3d 2d
7d
3d
7d
3d
19d 2d
19d 2d
2d
2d
0d 2d
100% 06-Dec-19 100% 13-Dec-19* 0% 06-Jan-20 100% 06-Jan-20* 100% 06-Jan-20*
0% 17-Dec-19 100% 19-Dec-19* 100% 17-Dec-19*
Ten working days notice to SEWOP contractor before mobilization
Mobilization of SEWOP from Warri (4 days to transport, position, jack-up, pre-load and secure in position 08-Jan-20, 1.4 Community Engagement Meet with Community Leaders and WAEP Management
08-Jan-20
Secure FTO (FTO Agreement Signed)
04-Jan-20 20-Dec-19
0% 06-Jan-20 100% 06-Jan-20*
15-Jan-20 07-Jan-20
04-Jan-20, Safe Well Pre-Activities Joint HAZOP/HAZID with all vendors in Lagos
Emergency Response workshop Safewell Workshop/HAZID
04-Jan-20
Vendor Kick-off Meeting in Port Harcourt
15-Jan-20, 1.5 Dismantling & Removal of Installed WellFluids(Contractor) Equipment (24 pieces) Mobilize Well Fluid Services: people/Equipment to Onne and equipment to platform/SEWOP
1d
1d
3d
3d
100% 09-Jan-20*
12-Jan-20
Safely remove the Well Fluid Services Equipment (24 pieces). It may require re-positioning of SEWOP
3d
3d
100% 13-Jan-20
15-Jan-20
Backload the equipment on the PSV (Equipment to be moved twice because of available deck space on
101d 0d
101d 0d
0% 07-Oct-19 100% 02-Dec-19
01-Feb-20
21d
21d
100% 07-Oct-19*
04-Nov-19
2d
2d
1d
1d
100% 08-Jan-20*
Commercial Discussions With Selected Contractor (s)
08-Jan-20 07-Jan-20
24-Dec-19
100% 03-Jan-20*
05-Jan-20, 1.3 Source new SEWOP, Security boats, mobilize and Jack-Up Obtain NAPIMS Approval of Execution Strategy and Source SEWOP, Security Boats, PSV & FSIV
30-Dec-19
100% 23-Dec-19*
03-Jan-22, Milestones Schedule
Life extension survey & Integrity repair/refurbishment
03-Jan-22*
2d
0% 07-Oct-19
31-May-20
01-Jan-21*
31-Dec-19*
7d
0% 07-Oct-19
01-Jan-20
05-Feb-20 09:00
2019 2020 2021 2022 N D J F M A M J J A S O N D J F M A M J J A S ON D J F M A M J J A S O N D J F M A M J J A S O N D
13-Mar-20*
100% 02-Dec-19
10d 0d
Reposition SEWOP for W/L and S/L Intervention Work
Mobilize HAL RA tools, WL skid and HT 400 pump--different vessel than crew (PSV returns from field, offloads WF equipmen
0%
30d
A3050 A3060
31-Dec-20*
Split bar start Split bar finish
29-May-20*
30d
NNRA Approvals/Registration and HSE Permit (Pending Approval of MEDIVAC/Hospital 30d 30d Facilities Engagement of RSA (Radiation Safety Advisor)
0%
0%
0% 01-Nov-19 100% 01-Nov-19
101d
A3030 A3040
03-Jan-22
51d 36d
2d
Move personnel by boat to KCDP-A, offload personnel, welding and cutting tools, lifting equipment at Kalaekule (1d) Safely remove the Well Fluid Services Equipment (24 pieces). It may require re-positioning of SEWOP
0% 13-Mar-20
51d 36d
101d
9d 1.5 Dismantling & Removal of Installed WellFluids(Contractor) Equipment9d(24 pieces) A2080 Mobilize Well Fluid Services: people/Equipment to Onne and equipment to platform/SEWOP 2d 2d A2090
3.33% 01-Jan-19 A 03-Jan-22
188d
0d
Safewell Workshop/HAZID
470d
Finish
384d
10d 1.2 Acquire Rigger s Crew/Welder s (for Dismantling of Wellfluids Equipment) A1930 Define Scope of Work for Dismantling of Wellfluids Equipment 0d A1950
Schedule % Start Complete
Classic WBS Layout
08-Jan-20
100% 01-Nov-19*
10-Dec-19
100% 16-Jan-20*
16-Jan-20
100% 16-Jan-20
Move personnel by boat to KCDP-A, offload personnel, welding and cutting tools, lifting equipment at Ka
01-Feb-20, 1.6 RMT Log(Including sourcing and permits timelines) Boat for RA source. (Bids and Recommendation)
NNRA Approvals/Registration and HSE Permit (Pending Approval of MEDIVAC/Hospital Facilities
Engagement of RSA (Radiation Safety Advisor)
Reposition SEWOP for W/L and S/L Intervention Work
17-Jan-20*
Mobilize HAL RA tools, WL skid and HT 400 pump--different vessel than crew (PSV returns from field, o
1d
1d
100% 17-Jan-20
17-Jan-20
Mobilize HAL crew (10 persons for RMT and Pump) using FSV(3 days to offload WF equipment, load H
1d
1d
100% 18-Jan-20
18-Jan-20
PSV loads HAL equipment and takes offshore (1 Day off load and transport to Kalaekule site with SEWO
Page 1 of 4
TASK filter: All Activities © Primavera Systems, Inc.
WAEP MASTER SCHEDULE (Acelerated) Activity ID
Activity Name
A3090 A4000 A4010 A4020 A4030 A4040 A4050 A4060 A4070 A4080 A4090 A5000 A5010
Offload @ KCDP-A, HAL WL skid, RMT tools and Pump at Platform/SEWOP, begin rig up and test of lubricator using HAL pum
Original Remaining Duration Duration 1d
1d
Test Xmas tree above hanger using P&E installed 2 way check and HAL HT 400 pump. Start on 18 L then 18S, then 16L, then
3d
100% 18-Jan-20
20-Jan-20
Test Xmas tree above hanger using P&E installed 2 way check and HAL HT 400 pump. Start on 18 L th
1d
1d
100% 13-Jan-20*
13-Jan-20
1/2 day - Complete Rig up and testing of HAL wireline lubricator on well 18L, RIH and commence logg
Run RMT on 18L, 3 -5 days (during this period large crane is fully utilised, thus no boat offload, no supplies, no pers Rig down lubricator/prepare to move to well 16L
5d
5d
100% 14-Jan-20*
18-Jan-20
Run RMT on 18L, 3 -5 days (during this period large crane is fully utilised, thus no boat offload, no supp
0d
0d
100% 19-Jan-20 100% 19-Jan-20
19-Jan-20*
Run RMT on 16L , 3-5 days ( during thie period large crane is fully utilised, thus no boat offload, no suppies, nor per
5d
5d
100% 20-Jan-20*
24-Jan-20
Run RMT on 16L , 3-5 days ( during thie period large crane is fully utilised, thus no boat offload, no sup
Transport, Mobilize Slickline unit and crew on the FSV (parralel to RMT on 16L) Rig down lubricator and wireline unit. Backoad RA /RMT tools and equipment to PSV vessel , backload WL skid and crew to FSV Offload, HAL Slickline unit with tools for setting WRSCSSSV at Platform/SEWOP, begin rig up and test of SL lubrica
1d
1d
100% 23-Jan-20
23-Jan-20
Transport, Mobilize Slickline unit and crew on the FSV (parralel to RMT on 16L)
2d
2d
100% 24-Jan-20
25-Jan-20*
Rig down lubricator and wireline unit. Backoad RA /RMT tools and equipment to PSV vessel , backload
2d
2d
100% 24-Jan-20*
25-Jan-20
FSV Offload, HAL Slickline unit with tools for setting WRSCSSSV at Platform/SEWOP, begin rig up an
5d
5d
100% 26-Jan-20*
30-Jan-20
Conduct re-installation of OTIS downhole safety valves using HAL SL unit and crew ( 6 days) 10 strings
Rig down Slickline unit, secure wells and demobilize genset, explosion proof lights, all crews and materials all back to Jack down SEWOP, move SEWOP to KCVJ-A, PSV/HAL equip & crew to Onne
3d
3d
100% 30-Jan-20
01-Feb-20*
Rig down Slickline unit, secure wells and demobilize genset, explosion proof lights, all crews and mater
1d
1d
100% 31-Jan-20*
31-Jan-20
Jack down SEWOP, move SEWOP to KCVJ-A, PSV/HAL equip & crew to Onne
4d
4d
0% 28-Feb-20
03-Mar-20
03-Mar-20, 2.0 Platform inspection, minor restoration & manifold fabrication
284d
88d
0% 01-Feb-20
30-May-20
20d
20d
1/2 day - Complete Rig up and testing of HAL wireline lubricator on well 18L, RIH and commence logging. 3 days best ca
Logistics day**CONTINGENCY (offload boats, move people, backload any missing kit from WF, etc) rig up and test WL lubri
Conduct re-installation of OTIS downhole safety valves using HAL SL unit and crew ( 6 days) 10 strings (+ 1 day continge
3.1 Integration, Hook-up & Commisioning of MOPU/EPF & Manifold A5030 MOPU - HAZID/Seabed Survey A5040
MOPU - Pre-Move, Fit out
A5070
MOPU - Position, Hook-up & Commisioning
MOPU - Mobilization(1 month) assume heavy lift Fabrication Work
Offshore Integration & Well Hook-up)
A6020
FSO Deployment
A6060
Hoses /Pipework Installation
Shuttle Tanker Deployment
Life extension survey,Integrity, Repair/Refurbishment Finalize scope
A1110
Execute works
A1100
Award contracts
PUT KCDP-B Wells on production A1150
Confirm scope of work-safe wells and safe access
A1170
Mobilsed from KCDDP-A to B with contract extension
A1160 A1270 A1280 A1290 Split bar
Actual Work
Confirm 205 class SEWOP is suitable for workscope Installation of well safety valves RMT Logging
Critical Remaining Work
14d 20d 40d
Summary
4d 4d
0% 03-Feb-20 10% 03-Feb-20*
14d
0% 19-Feb-20
20d
1d 2d
60d
60d
60d
5d
60d 10d
5d 1d 3d
239d
239d
10d
10d
7d
7d
224d
224d
10d
10d
31d
5d 5d 5d
0% 28-Feb-20 0% 28-Feb-20
64d 10d
67d 10d
10d Milestone
1d
67d 14d
10d
Inspection-WT mearsurement Remaining Work
282d 10d
20d 20d
Handover
A1090
4d 4d
10d
3.3 First Oil A6070 Pre-Commisioning/Commmisioning A6080
1d
10d
3.2 Deployment of FSO, Shuttle Tanker & Hoses A6010 FSO Mooring Studies (Dependent on EPF Award) A6030
2019 2020 2021 2022 N D J F M A M J J A S O N D J F M A M J J A S ON D J F M A M J J A S O N D J F M A M J J A S O N D
3d
3.0 EPF/FSO/Shuttle Tanker Deployment
A5090
Split bar start Split bar finish
19-Jan-20
2.1 EPF/FSO/Shuttle Tanker Contract Award A5020 Site Visit for Asset Integrity Work (Stage 1)
A5080
Finish
05-Feb-20 09:00
100% 19-Jan-20
2.0 Platform inspection, minor restoration & manifold fabrication
A5060
Schedule % Start Complete
Classic WBS Layout
0% 01-Mar-20 0% 09-Mar-20
0% 13-Apr-20* 0% 16-Apr-20*
0% 01-Feb-20 0% 04-Feb-20* 5% 01-Feb-20 5% 01-Feb-20
0% 17-Apr-20* 0% 25-Apr-20 0% 25-Apr-20* 0% 11-May-20 0% 03-Feb-20
14.29% 03-Feb-20
0% 10-Feb-20* 0% 24-Feb-20*
31d
3.33% 03-Feb-20
5d
20% 03-Feb-20
5d 5d
10d 10d
0% 02-Mar-20*
20% 03-Feb-20
0% 08-Feb-20* 0% 13-Feb-20* 0% 26-Feb-20*
Offload @ KCDP-A, HAL WL skid, RMT tools and Pump at Platform/SEWOP, begin rig up and test of l
Rig down lubricator/prepare to move to well 16L
Logistics day**CONTINGENCY (offload boats, move people, backload any missing kit from WF, etc) rig
03-Mar-20 03-Mar-20
03-Mar-20, 2.1 EPF/FSO/Shuttle Tanker Contract Award Site Visit for Asset Integrity Work (Stage 1)
30-May-20, 3.0 EPF/FSO/Shuttle Tanker Deployment
30-Apr-20 14-Feb-20
30-Apr-20, 3.1 Integration, Hook-up & Commisioning of MOPU/EPF & Manifold MOPU - HAZID/Seabed Survey
26-Mar-20
MOPU - Pre-Move, Fit out
06-Mar-20*
MOPU - Mobilization(1 month) assume heavy lift
03-Apr-20*
MOPU - Position, Hook-up & Commisioning
16-Apr-20
Fabrication Work
30-Apr-20
Offshore Integration & Well Hook-up)
30-Apr-20 17-Feb-20
30-Apr-20, 3.2 Deployment of FSO, Shuttle Tanker & Hoses FSO Mooring Studies (Dependent on EPF Award)
21-Apr-20*
FSO Deployment
21-Apr-20*
Shuttle Tanker Deployment
30-Apr-20
Hoses /Pipework Installation
30-May-20 01-May-20
30-May-20, 3.3 First Oil Pre-Commisioning/Commmisioning
30-May-20*
Handover
31-Dec-20 11-Feb-20
Finalize scope
21-Feb-20
Award contracts
31-Dec-20
31-Dec-20, Life extension survey,Integrity, Repair/Refurbishment
Execute works
13-Mar-20
13-Mar-20, PUT KCDP-B Wells on production
07-Feb-20
Confirm 205 class SEWOP is suitable for workscope
12-Feb-20
Installation of well safety valves
13-Mar-20
Confirm scope of work-safe wells and safe access
07-Feb-20
Mobilsed from KCDDP-A to B with contract extension
26-Feb-20
RMT Logging
11-Mar-20
Inspection-WT mearsurement
Page 2 of 4
TASK filter: All Activities © Primavera Systems, Inc.
WAEP MASTER SCHEDULE (Acelerated) Activity ID
Activity Name
A1300
Original Remaining Duration Duration
3rd party inspection
10d
Re-devlopment of greater kalaekule (P1+ P2)
Data Loading and QC
0d
100% 01-Jan-19 A 30-Aug-19 A
Petrophysical Evaluation
A1340
Petrophysical Evaluation
174d
A1360 A1370 A1380 A1390 A1400 A1410 A1420 A1430 A1440 A1450 A1460 A1470 A1480 A1490 A1500 A1510 A1520 A1530 A1540
174d 174d
Review PP Evaluations /Core-Log integration
93.75% 01-Jan-19 A 25-Jun-20
175d
131d
89.14% 01-Jul-19 A
218d
0d
Quantitative Interpretation
5d
0d
301d 131d
0d 5d
Quality check Static Models from Stop Gap (4) Reservoir studies
130d
130d
Static Modeling (PAF/UAD Reservoirs )
108d
108d
0d
0d
Static Modeling (for select 4 Reservoirs ) Volumetrics (Map/Model Based)
87d
282d
2nd Peer Review/TCM
87d
282d
04-Aug-20*
0.77% 03-Feb-20*
31-Jul-20
20% 03-Feb-20
1.15% 03-Feb-20* 0.93% 03-Feb-20*
261d
0.38% 03-Feb-20*
01-Feb-21
0d
0d
100%
03-Feb-20
KAUE Infill well planning (Gas /Oil wells )/Pore Pres sure Prediction
88d
88d
66d
66d
100% 02-Sep-19 A 31-Oct-19 A 0% 01-Jul-20* 0% 01-Jul-20*
109d
0% 01-Jul-20*
30-Nov-20
A1570
KAUE, KD, Koronama and Kugbe (Clus ter 1) FFD/FDP Report
132d
132d
0% 01-Jul-20*
31-Dec-20
A1580 A1590 A1600
OML 72 (Deep) Prospectivity Studies Detailed Subsurface Report
Stakeholder's Engagement ( incl. DPR, NAPIMS, FIRST E&P etc)
Blockwide explo./Appraisal Dev. Programme
132d 262d 262d
0d
132d 262d 262d
0d
784d
500d
129d
0d
43d
0d
0% 01-Jul-20* 0.38% 03-Feb-20* 0.38% 03-Feb-20* 100%
Development Concept Re-assessment and Economics
3rd Peer Review/TCM
KAUE Infill well planning (Gas /Oil wells )/Pore Pres sure Prediction KAUE Infill Well Proposals
31-Dec-20
PAF and UAD Well selection and Proposals
KAUE, KD, Koronama and Kugbe (Clus ter 1) FFD/FDP Report
02-Feb-21
OML 72 (Deep) Prospectivity Studies
02-Feb-21
Detailed Subsurface Report
03-Feb-20
0% 01-Jan-19 A 31-Dec-21
01-Jan-20
31-May-20
100% 01-Jan-19 A 28-Jun-19 A
01-Jan-20
29-Feb-20
KI/KI-South Subsurface Activities- FFD (Green Field) (Cluster 2 FFD784d Studies 500d Time Lime) 0% 01-Jan-19 A 31-Dec-21 A1670
Seismic Interpretation
A1750
Review of static model (inhouse)
A1700 A1760 A1770 A1610 A1620 A1630 A1640 A1660 A1680 A1690 A1720 A1740 A1780 Split bar
Actual Work
TWT/Depth Map and Sensititivity
218d
Volumetrics (Map/Model Based)
282d
Data Loading
174d
Petrophysical Evaluation
174d
Dynamic Modeling and Forecast (D8000 and E4100) Geological Correlation
174d
Core-Log Integration
174d
Synthetic Seismogram
174d
Velocity Sensitive Analysis
301d
Trend Analysis
175d
Quantitative Interpretation
5d
Static Modeling (D4000, D8000 & E4100)
197d
Shallow Gas/Geo Hazard studies Remaining Work
Critical Remaining Work
66d
23d
Milestone
Summary
01-Jan-20
0d
91.28% 01-May-19 A 31-Aug-19 A
0d
62.41% 01-May-19 A 31-Dec-19 A
0d
100% 01-Jan-19 A 28-Feb-19 A
0d 0d 0d 0d 0d 0d 0d 5d
197d 23d
100% 01-Nov-19 A 31-Dec-19 A 100% 01-Oct-19 A 31-Dec-19 A
01-Feb-20
01-Mar-20 01-Apr-20 01-Apr-20
100% 01-Jan-19 A 31-Mar-19 A 100% 01-Jan-19 A 31-Mar-19 A 100% 01-Jan-19 A 28-Feb-19 A 100% 01-Jan-19 A 28-Feb-19 A
94.68% 01-Mar-19 A 28-Jun-19 A
Stakeholder's Engagement ( incl. DPR, NAPIMS, FIRST E&P etc)
31-Dec-21, Blockwide explo./Appraisal Dev. Progr
31-May-20
Seismic Interpretation
29-Feb-20
Review of static model (inhouse)
30-Apr-20
31-May-20
07-Feb-20
4.35% 03-Feb-20*
04-Mar-20
0.51% 03-Feb-20*
31-Dec-21, KI/KI-South Subsurface Activities- FFD
TWT/Depth Map and Sensititivity
31-Mar-20
Volumetrics (Map/Model Based)
Dynamic Modeling and Forecast (D8000 and E4100)
Data Loading
Geological Correlation
Petrophysical Evaluation
Core-Log Integration
Synthetic Seismogram
Velocity Sensitive Analysis
89.14% 01-Apr-19 A 30-Jun-19 A 20% 03-Feb-20
Classical Reservoir Engineering analysis Dynamic Modeling and Forecast for KAUE, KD, koronama, Kugbe,
30-Sep-20
109d
Volumetrics (Map/Model Based)
Quality check Dynamic Modeling and Forecas t from stop gap studies
30-Oct-20
KAUE Infill Well Proposals
PAF and UAD Well selection and Proposals
2nd Peer Review/TCM
01-Jan-21
A1550 A1560
Static Modeling (PAF/UAD Reservoirs )
03-Feb-20
261d
3rd Peer Review/TCM
Quality check Static Models from Stop Gap (4) Reservoir studies
Static Modeling (for select 4 Reservoirs )
01-Jul-20
Dynamic Modeling and Forecast for KAUE, KD, koronama, Kugbe, Development Concept Re-assessment and Economics
Quantitative Interpretation
02-Jun-20
0.42% 03-Feb-20*
0d
TWT/Depth Map and Sensititivity
07-Feb-20
240d
Simplified Velocity Analys
1s t Peer Review/TCM
62.41% 03-Jun-19 A 02-Mar-21* 100%
Seismic Interpretation Trend Analysis
91.28% 01-May-19 A 03-Aug-20*
240d 44d
Synthetic Seismogram
94.68% 01-Jan-19 A 29-Mar-21
Classical Reservoir Engineering analysis
Quality check Dynamic Modeling and Forecas t from stop gap studies
Review PP Evaluations /Core-Log integration
100% 01-Jan-19 A 24-Aug-19 A
03-Feb-20
29-Mar-21, Kalaekule/KD/Koronama/Kugbe/KCN Fields (Cluster 1 FD
Core-Log Integration
77.91% 01-Nov-19 A 04-May-20*
100%
29-Mar-21, Re-devlopment of greater kalaekule (P1+ P2)
Geological Correlation and QC
100% 01-Jan-19 A 30-Aug-19 A
103d
301d
1s t Peer Review/TCM
0d
100% 01-Jan-19 A 30-Aug-19 A
304d
Simplified Velocity Analys TWT/Depth Map and Sensititivity
0d
0% 01-Jan-19 A 29-Mar-21
66d
174d
Trend Analysis
301d
0% 01-Jan-19 A 29-Mar-21
86d
Synthetic Seismogram Seismic Interpretation
3rd party inspection
100% 01-Jan-19 A 30-Aug-19 A
174d
Core-Log Integration
14-Feb-20
2019 2020 2021 2022 N D J F M A M J J A S O N D J F M A M J J A S ON D J F M A M J J A S O N D J F M A M J J A S O N D
0d
Data Loading and QC
A1350
Split bar start Split bar finish
301d
A1190
Geological Correlation and QC
10% 03-Feb-20
Finish
05-Feb-20 09:00
546d
546d Kalaekule/KD/Koronama/Kugbe/KCN Fields (Cluster 1 FDD Time Line) A1200
10d
Schedule % Start Complete
Classic WBS Layout
Trend Analysis
03-Nov-20
Quantitative Interpretation
Static Modeling (D4000, D8000 & E4100)
Page 3 of 4
TASK filter: All Activities
Shallow Gas/Geo Hazard studies
© Primavera Systems, Inc.
WAEP MASTER SCHEDULE (Acelerated) Activity ID
Activity Name
A1790
Development Concept Selection (GMP)/Economics
A1810
Pore Pressure Prediction (PPP)
A1800 A1820 A1830 A1840 A1850
Split bar
Actual Work
Original Remaining Duration Duration 87d
87d
Development well planning (Gas wells)
130d
130d
Development Well Design and Proposal
219d
219d
Field Development Report (FDP)
218d
218d
87d
OML 71 (Deep) Prospectivity Studies
218d
Detailed Subsurface Study Report
Remaining Work
Critical Remaining Work
393d
Milestone
Summary
87d
218d 393d
Schedule % Start Complete
Classic WBS Layout Finish
1.15% 03-Feb-20*
02-Jun-20
0% 02-Mar-20*
30-Jun-20
0.77% 03-Feb-20*
0% 02-Mar-20* 0% 02-Mar-20* 0% 02-Mar-20* 0% 01-Jul-20*
Split bar start Split bar finish
05-Feb-20 09:00
2019 2020 2021 2022 N D J F M A M J J A S O N D J F M A M J J A S ON D J F M A M J J A S O N D J F M A M J J A S O N D Development Concept Selection (GMP)/Economics
31-Jul-20
Development well planning (Gas wells)
Pore Pressure Prediction (PPP)
31-Dec-20
Development Well Design and Proposal
30-Dec-20
OML 71 (Deep) Prospectivity Studies
30-Dec-20
Field Development Report (FDP)
31-Dec-21
Detailed Subsurface Study Report
Page 4 of 4
TASK filter: All Activities © Primavera Systems, Inc.