Work Breakdown Structure (WBS) Top Chart Layer 0

Oil & Gas Project

Layer 1 Basic Engineering

Detail Engineering

Mechanical Equipment

Equipment Design

Piping Material

Piping Material

Subcontracting

Piping & Plant Design

Electrical Equipment & Material

Electrical Equipment & Material

……. Plant

Electrical Design

Control & Instrument Material

Control & Instrument Material

Control & Instrument Design

Structural Material

Structural Material

Structural Design

Architectural Material

Architectural Material

Civil Design

HVAC Equipment & Material

HVAC Equipment & Material

Architectural Design

Fire Fighting Equipment & Material

Fire Fighting Equipment & Material

Process Design

Equipment Design Piping & Plant Design

Instrument and Control Design Civil / Architecture / Structure Design HVAC / Fire Fighthing Design

Commissioning and Startup

Mechanical Equipment

Process Design

Electrical Design Design

Construction, Erection and Precommissioning

Manufacturing and Delivery

Procurement

HVAC and Fire Fighting Design

Site Handover and Mobilization

Layer 2

Work Breakdown Structure (WBS) Equipment Design Layer 2

Equipment Design

Layer 3 Tanks

Vessels

Heat Exchangers

Tanks, Bins and Hoppers

Filters

Hoists

Specifications

3D Modeling *

……. Tank

……... Tank

Layer 4 Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Typical

Work Breakdown Structure (WBS) Piping & Plant Design Layer 2

Piping & Plant Design

Layer 3 General

….. Plant

Area….

Area….

Area….

3D Model Review

Underground Piping

Plot Plan / Key Plan

Block Modeling

Block Modeling

Block Modeling

Block Modeling

Block Model Review

PDMS Administration and Catalogue

Intermediate Modeling

Intermediate Modeling

Intermediate Modeling

Intermediate Modeling

Intermediate Model Review

Lists and Reports

Final Modeling

Final Modeling

Final Modeling

Final Modeling

Final Model Review

Engineering Specs and Data Sheets P&ID Mechanization and Line Lists

Layer 4

Work Breakdown Structure (WBS) Electrical Design Electrical Design

Layer 2 Layer 3

Conceptual and Basic Design

Lighting and Small Power System Study and Calculation

Emergency Power System

MCC and Control Room

Power

Earthing and Lightning

Power System Analysis

Power System

Power

Hazardous Area Classification

Wiring and Termination Diagram

Electrical System

Relay Setting Study

Cathodic Protection

Paging System

3D Modeling Electrical Heat Tracing Layer 4

Work Breakdown Structure (WBS) Control & Instrument Design Control & Instrument Design

Layer 2 Layer 3

Lists and Schedules

Layouts and Wiring

Hookups

3D Modeling

Layer 4 …. Plant

…. System

…. System

…. System

…. System MCC and Control Room Common Area, General and Offsite

Work Breakdown Structure (WBS) Structural Design Structural Design

Layer 2 Layer 3

General Specifications and Drawings

Pipe Racks and Sleepers

Structures and Buildings

Equipment Foundations

Miscellaneous Works *

3D Modeling

Layer 4 Pipe Rack

…..Plant

….. Plant

….. Plant

….. Plant

Sleepers

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

…...System

MCC and Control Room

* Including Local Platforms, Special Pipe Supports, Concrete Pits, etc.

…...System Common Area, General and Offsite

Work Breakdown Structure (WBS) Civil Design Layer 2

Civil Design

Layer 3 General Specifications and Drawings

Landscaping

Underground Layouts

Non-pressurized Sewage Foundations Location Underground System

* Including Local Platforms, Special Pipe Supports, Concrete Pits, etc.

3D Modeling

Layer 4

Work Breakdown Structure (WBS) Architectural Design Layer 2

Architectural Design

Layer 3 General Specifications and Drawings

Building Design

3D Modeling

Layer 4 …. Plant

…...System

…...System

…...System

…...System MCC and Control Room Common Area, General and Offsite

* Including Local Platforms, Special Pipe Supports, Concrete Pits, etc.

Work Breakdown Structure (WBS) HVAC and Fire Fighting Design Layer 2

HVAC and Fire Fighting Design

Layer 3 Safety and Fire Fighting Design

HVAC Design

General Documents

General Documents

Calculations, Data Sheets and Layouts

Data Sheets and Layouts

* Including Local Platforms, Special Pipe Supports, Concrete Pits, etc.

Layer 4

Work Breakdown Structure (WBS) Procurement (1/2) Procuremen t

Layer 1 Layer 2

Mechanical Equipment

Electrical Equipment & Material

Piping Material

Tanks *

Vessels

Piping Material

Coat & Wrap

MV/LV Switchgears and Distribution Panels Annunciation Panels

Control & Instrument Material

Layer 3

Power Transformer

Junction Boxes

LV Bus Duct

Gas Detectors

Cathodic Protection System and Material Power, Control and Communication Cables

AC/DC UPS and Batteries

Control Cables

Cable Termination Kit, Joint Material & Cable

Cable Trays and Ladders

Heat Exchangers

Conduits and Accessories

Cable Trays and Ladders

Cable Glands

Hoists

Lighting Poles, Brackets and Towers

Socket Outlets and Lighting Material

Cable Glands

Junction Boxes

Earthing and Lightning Material

Paging System

Rotary

Paint

Filters

Insulation Material

Electrical Heat Tracing Material

Work Breakdown Structure (WBS) Procurement (2/2) Procuremen t

Layer 1 Layer 2

Structural Material

Architectural Material

Steel Structure

Aluminum Corrugated Sheets

Anchor Bolts

Aluminum Sandwich Panels

HVAC Equipment & Material

HVAC System

Fire Fighting Equipment & Material

Fire Fighting Equipment

Layer 3

Work Breakdown Structure (WBS) Manufacturing and Delivery (1/2) Manufacturing and Delivery

Layer 1 Layer 2

Mechanical Equipment

Electrical Equipment & Material

Piping Material

Tanks *

Piping Material (Offshore)

MV/LV Switchgears and Distribution Panels

Vessels

Coat and Wrap

Annunciation Panels

Control & Instrument Material

Layer 3

Power Transformer (6.6/0.4 kv)

Junction Boxes

LV Bus Duct

Gas Detectors

Cathodic Protection System and Material Power, Control and Communication Cables

AC/DC UPS and Batteries

Control Cables

Cable Termination Kit, Joint Material & Cable

Cable Trays and Ladders

Heat Exchangers

Conduits and Accessories

Cable Trays and Ladders

Cable Glands

Hoists

Lighting Poles, Brackets and Towers

Socket Outlets and Lighting Material

Cable Glands

Junction Boxes

Earthing and Lightning Material

Paging System

Rotary

Paint

Filters

Insulation Material

Electrical Heat Tracing Material

Work Breakdown Structure (WBS) Manufacturing and Delivery (2/2) Manufacturing and Delivery

Layer 1 Layer 2

Structural Material

Architectural Material

Steel Structure

Aluminum Corrugated Sheets

Anchor Bolts

Aluminum Sandwich Panels

HVAC Equipment & Material

HVAC System

Fire Fighting Equipment & Material

Fire Fighting Equipment

Layer 3

Work Breakdown Structure (WBS) Construction, Erection and Pre-commissioning (1/2) Construction, Erection and Precommissioning

Layer 1 Layer 2

Site Handover and Mobilization

Subcontracting

….. Plant

….. System

….. System

Layer Mechanical 3

Civil Works Subcontract

Mechanical Equipment Installation

Mechanical Equipment Installation

Equipment Installation

Mechanical Erection Subcontract

Piping Installation

Piping Installation

Piping Installation

Electrical Installation

Electrical Installation

Electrical Installation

Control and Instrument Installation

Control and Instrument Installation

Control and Instrument Installation

Structural Installation

Structural Installation

Structural Installation

Architectural Works

Architectural Works

Architectural Works

Safety and Fire Fighting Installation

Safety and Fire Fighting Installation

Safety and Fire Fighting Installation

Painting, Insulation and Fire Proofing

Painting, Insulation and Fire Proofing

Painting, Insulation and Fire Proofing

Work Breakdown Structure (WBS) Construction, Erection and Pre-commissioning (2/2) Construction, Erection and Precommissioning

Layer 1 Layer 2

….. System

MCC and Control Room

…... System

Common Area, General and Offsite

Demobilization and Plant Handover

Mechanical Equipment Installation

Mechanical Equipment Installation

Electrical Installation

Mechanical Equipment Installation

Piping Installation

Piping Installation

Control and Instrument Installation

Piping Installation

Electrical Installation

Electrical Installation

Structural Installation

Electrical Installation

Control and Instrument Installation

Control and Instrument Installation

Architectural Works

Control and Instrument Installation

Structural Installation

Structural Installation

Safety and Fire Fighting

Structural Installation

Architectural Works

Architectural Works

Painting, Insulation and Fire Proofing

Civil Works

Safety and Fire Fighting Installation

Safety and Fire Fighting Installation

Architectural Works

Painting, Insulation and Fire Proofing

Painting, Insulation and Fire Proofing

Safety and Fire Fighting Installation Painting, Insulation and Fire Proofing