HINDUSTAN PETROLEUM CORPORATION LIMITED Visakh Refinery Modernization Project Doc Title: Heat Load Calculation for HVAC System Doc No: AV2K20-085-DOC-A001 OWNER’S CONSULTANT & PMC:
ENGINEERS INDIA LIMITED
EPC CONTRACTOR:
MYTHRI INFRA HVAC CONTRACTOR:
ADVANCE VENTILATION PVT LIMITED
0 Rev
10.10.2019
FOR REVIEW
R.L
J.K
S.N
Date
Purpose of Issue
Prepared By
Checked By
Approved By
08-NOV-2019 SUTHAR KETANBHAI (C360) 1 of 168
Page 2 of 168
HEAT LOAD ESTIMATION FOR VRMP
INDEX FOR HEAT LOAD OF SUBSTATION-86 CT & NHT CCR BUILDING SECTION SECTION 1
DESCRIPTION 1.1 General Project Information 1.2 Applicable Codes &Standards
SECTION 2
SECTION 3
SECTION 4
SECTION 5
SECTION 6
PAGE NOS.
1. General Information
2.DesignParameters 2.1WeatherData 2.2IndoorCriteria 2.3Lighting Load, Equipment Load, Fresh air ACPH, Occupancy 3.U-Factors, corrective ETD value for Wall &Roof, Sensible & latent heat load by human being Overall heat transfer co-efficient-Detail Calculation Overall heat transfer co-efficient – Relevant pages from ASHRAE&ISHRAE Corrective ETD value for wall &roof Sensible & latent heat load by human being Corrective ETD value for wall, roof & glass Reference Documents 4.Heat load 4.1.1 Heat load summary for Substation Building 86-CT 4.1.2 Summer, Monsoon & Winter heat load for Substation Building 86-CT 4.2.1 Heat load summary for NHT CCR Building 4.2.2 Summer, Monsoon & Winter heat load for NHT CCR Building
03-05
06-14
15-34
35-69
5. Equipment selection
70-71
6.Architecture Drawing
72-82
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 2 of 168
Page 2 of 82
Page 3 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-1 GENERAL INFORMATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 3 of 168
Page 3 of 82
Page 4 of 168
HEAT LOAD ESTIMATION FOR VRMP
1.1GENERAL PROJECT INFORMATION PROJECT
HPCL VIZAG REFINERY EXPANSION PROJECT
OWNER
HINDUSTAN PETROLEUM CORPORATION LIMITED
HVAC CONTRACTOR
ADVANCE VENTILATION PVT. LTD.
PLANT LOCATION
VISAKHAPATNAM, INDIA
1. SUBSTATION BUILDING- 86 CT
BUILDING
2. NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 4 of 168
Page 4 of 82
Page 5 of 168
HEAT LOAD ESTIMATION FOR VRMP
1.2APPLICATION CODE AND RELEVENT STANDARD LATEST ISSUE ASHRAE (American society of Heating, Refrigeration & Air-conditioning Engineer’s) fundamentals, Systems, Equipment’s & Application Handbook. ISHRAE(Indian society Of Heating Refrigeration & Air Conditioning Engineer’s) Fundamentals, Systems, Equipment’s &Application Handbook For Outdoor & Indoor Design conditions. Ref. document no- (B015-000-80-43-SP-8203, Rev.0, Pg 9-10 ) for NHT CCR Building Ref. document no- (B015-000-80-43-SP-8204, Rev.0, Pg 10 ) for Substation Building- 86 CT
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 5 of 168
Page 5 of 82
Page 6 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-2 DESIGN PARAMETERS
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 6 of 168
Page 6 of 82
Page 7 of 168
HEAT LOAD ESTIMATION FOR VRMP
2.1 WEATHER DATA Design Parameters Name of city
VISAKHAPATNAM
Location(state)
ANDHRA PRADESH
Design outside atmospheric condition for HVAC calculation Season
DBT(0C)
WBT(0C)
RH%
Summer
33.3
27.8
65.8
Monsoon
30.6
27.8
80.6
Winter
18.3
13.9
61.4
2.2 Indoor design condition Room / Area
Design temp DBT(0C)
RH%
Substation Building- 86 CT
26 +/- 1
50 +/- 5
NHT CCR Building
24 +/-1
50 +/- 5
2.3 Lighting Load, Equipment Load, Fresh air ACPH, Occupancy
Lighting Load= 5W/ sq.m
Equipment Load/ Fresh Air ACPH/ Occupancy=
Ref. document no- (B015-000-80-43-SP-8203, Rev.0, Pg 10-11 ) for NHT CCR Building Ref. document no- (B015-000-80-43-SP-8204, Rev.0, Pg 11 ) for Substation Building- 86 CT
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 7 of 168
Page 7 of 82
Page 8 of 168
HEAT LOAD ESTIMATION FOR VRMP
DESIGN PARAMETERS SUBSTATION-SS 86 CT BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 8 of 168
Page 8 of 82
Page 9 of 168
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR PLANT & NON PLANT BUILDING WORKS
DOCUMENT No. B015-000-80-43-SP-8204 Rev. 0 Page 10 of 18
y) All Instruments, Controls and safety devices (Contractor to attach list of controls and safety devices) including all necessary interlocks, control panel, cabling, wiring etc. as detailed in the Instrumentation Specifications attached elsewhere. z) Electrical work/items as per Electrical specifications attached elsewhere. aa) Self standing/ wall mounted audio-visual annunciation panel. bb) Plant room ventilation system. 3.2.3
The entire work of design, engineering, manufacture, installation, commissioning and performance testing of equipment/systems shall be executed by one of the roved vendor for HVAC work.
3.2.4
Contractor shall develop the complete HVAC system configuration and submit for
3.2.5
Contractor shall be solely responsible to demonstrate the specified inside conditions throughout the year irrespective of any variation in the outside condition.
3.2.6
DESIGN DATA
3.2.6.1 Outside Design Condition SEASON
DBT (ºC)
WBT (ºC)
Summer
33.3
27.8
Monsoon
30.6
Winter
18.3
Air Quantity (As per Class GX (severe) of ANSI/ISAS71.04) H2S
50 ppb
27.8
SO2/SO3
300 ppb
13.9
Cl2
10 ppb
NOX
1250 ppb
Notes: 1. Outdoor design condition mentioned above shall be followed for AC heat load calculation purpose.
3.2.6.2
Inside Design Conditions S. No.
1. 2. 3.
Area
DBT, °C
SRR Building (area to be air-conditioned) Switch Gear Hall & Operator Room of Sub Station building Scale Room Building (For Split ACs)
% RH
23 ± 1
50 ± 5
26 ± 1
50 ± 5
24 ± 1
30 to 70
08-NOV-2019
Air Quality (As Per Class G1(mild) of doc. ISA -571.04) H2S < 3 ppb SO2/SO3 < 10 ppb Cl2 < 1 ppb NOx < 50 ppb Not Applicable
Copyright EIL
Format No. EIL 1641-1924 Rev. 1
SUTHAR KETANBHAI (C360) 9 of 168
Page 9 of 82
All rights reserved
Page 10 of 168
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR PLANT & NON PLANT BUILDING WORKS
3.2.6.3
DOCUMENT No. B015-000-80-43-SP-8204 Rev. 0 Page 11 of 18
Other Design Requirements Description Under Deck Insulation
Requirement Thermal insulation shall be provided for the areas to be air-conditioned, packaged AC Rooms and AHU Rooms. Fouling factor for water cooled 0.0004 hr.m².ºC/kcal Condenser Refrigerant (for VCR based AC R-134a or R-407a or R-407c or R-410a System) Hours of operation 24 hrs / 365 Days Lighting Load 5 Watts/m2 Outdoor Fresh Air 2.0 ACPH for Substation building & 1.5 ACPH for SRR Building Equipment Heat Dissipation As per Below Table Occupancy As per Below Table Table: Elect/Instru. Equipment Heat Dissipation & Occupancy Building Room/Area to Eqpt. Heat Occupancy be Air Load Conditioned (Elec.+Instru.) (Nos.) (kW) 1 Sub Station-96 Switch Gear Hall 97.0* -(Tankages) Operator Room 1.0* 4 2 Sub Station-86 Switch Gear Hall 111.0* -(Cooling Tower) Operator Room 1.0* 4 Rack Room 44.0 3 UPS Room 9.0 -Tech. Room 1.0 4 Engg. Room 1.0 3 Lobby --UPS Room 11.0 -Tech. Room 1.0 4 Engg. Room 1.0 3 Lobby --3 SRR-Tankages Rack Room 44.0 3 UPS Room 9.0 -Tech. Room 1.0 4 Engg. Room 1.0 3 Lobby --4 SRR- New Flare & Rack Room 53.0 3 Blending station Engg. Room 1.0 3 UPS Room 8.6 -Lobby --*: Equipment Heat Load mentioned includes heat load due to lighting also, Hence while calculating heat load for that particular area, lighting load shall not be considered. Sr. No.
3.2.7
Air conditioning system load/ capacities specified in Scope of Work & Supply are minimum to be considered by the contractor for HVAC equipment and same is given for estimation purpose only. Contractor shall submit the detailed heat load calculations as per the approved/ AFC building drawings and equipment
08-NOV-2019
Copyright EIL
Format No. EIL 1641-1924 Rev. 1
SUTHAR KETANBHAI (C360) 10 of 168
Page 10 of 82
All rights reserved
Page 11 of 168
HEAT LOAD ESTIMATION FOR VRMP
DESIGN PARAMETERS NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 11 of 168
Page 11 of 82
Page 12 of 168 Page 1088 of 1419
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR CONSTRUCTION OF FIELD ROOM & MSC. CIVIL WORKS
DOCUMENT No. B015-000-80-43-SP-8203 Rev. 0 Page 9 of 18
viii) Supply and fixing of steel supports for duct/cable/pipe/tubing etc. ix) Breaking and making good of openings in wall. x) Temporary scaffolding related to erection, testing and commissioning.
3.1.4
o)
Structural steel works as required for equipment support and base frame of equipment.
p)
Electrical panels and electrical works as per Electrical Specification attached elsewhere in the tender.
q)
Self standing/ wall mounted audio-visual annunciation panel.
Each air conditioning system with Inverter Controlled Split Air Conditioners for CWTP Field Room building and Auxiliary Fire station Building shall comprise of but not limited to the following: a)
Inverter controlled split air conditioner complete with all accessories, fittings and voltage stabilizer with time delay relay. Split unit shall have wall mounted indoor unit and remotely located air cooled condenser (outdoor unit) with insulated refrigerant piping, Controls and line accessories, Initial charge of refrigerant, Electrical and civil works (e.g. civil work related to concealing of refrigerant piping, condensate piping to the nearest drain, cabling in AC space and outside upto the outdoor unit) as required including the structural steel framework, pedestal to mount the indoor/outdoor units, supports for indoor/outdoor units, supports & clamps for refrigerant piping/cables, stabilizer, hold down nuts & bolts.
b)
Spares for commissioning and start up.
3.1.5
The entire work of design, engineering, manufacture, installation, commissioning and performance testing of equipment/systems shall be executed by one of the owner’s/EIL approved vendor for HVAC work (attached elsewhere in the tender). The list of acceptable sub-vendors for bought out items for HVAC System has also been tabulated in cl. no. 10.0 below for consideration by HVAC Contractor.
3.1.6
Contractor shall develop the complete HVAC system configuration and submit for Owner/EIL’s approval before starting the detail engineering work.
3.1.7
Contractor shall be solely responsible to demonstrate the specified inside conditions throughout the year irrespective of any variation in the outside condition.
3.1.8
DESIGN DATA
3.1.8.1 Outside Design Condition SEASON
DBT (ºC)
WBT (ºC)
Summer
33.3
27.8
Monsoon
30.6
27.8
SO2/SO3 ≤ 300 ppb
Winter
18.3
13.9
Cl2
≤ 10 ppb
NOX
≤ 1250 ppb
08-NOV-2019 Format No. EIL 1641-1924 Rev. 1 SUTHAR KETANBHAI (C360)
Air Quantity (As per Class GX (severe) of ANSI/ISAS71.04) H2S
≤ 50 ppb
Copyright EIL – All rights reserved
12 of 168
Page 12 of 82
Page 13 of 168 Page 1089 of 1419
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR CONSTRUCTION OF FIELD ROOM & MSC. CIVIL WORKS
DOCUMENT No. B015-000-80-43-SP-8203 Rev. 0 Page 10 of 18
Notes: 1. Outdoor design condition mentioned above shall be followed for AC heat load calculation purpose. 2. Design temperature for sizing of air cooled exchanger/condenser shall be 450C (peak ambient temperature).
3.1.8.2
Inside Design Conditions S. No.
1.
2.
3.
3.1.8.3
Sl. Area
DBT, °C
Switch Gear Hall & Operator Room of Sub Station building Shift-in-charge & Dining room of Field Room Buildings CWTP Field Room & Auxiliary Fire Station Building (For Split ACs)
% RH
26 ± 1
50 ± 5
24 ± 1
50 ± 5
Air Quality (As Per Class G1(mild) of doc. ISA -571.04) H 2S < 3 ppb SO2/SO3 < 10 ppb Cl2 < 1 ppb NOx < 50 ppb
24 ± 1
30 to 70
Not Applicable
Other Design Requirements Description Under Deck Insulation
Requirement Thermal insulation shall be provided for the areas to be air-conditioned, packaged AC Rooms and AHU Rooms. Fouling factor for water cooled 0.0004 hr.m².ºC/kcal Condenser Cooling water inlet temperature 33°C Design temperature for sizing Air 45°C cooled exchanger/condenser Refrigerant (for VCR based AC R-134a or R-407a or R-407c or R-410a System) Hours of operation 24 hrs / 365 Days Lighting Load 5 Watts/m2 Outdoor Fresh Air a. 2.0 ACPH or 17 CFM per person whichever is higher for Substation building & b. 1.0 ACPH or 17 CFM per person whichever is higher for Field Room buildings Equipment Heat Dissipation As per Below Table Occupancy As per Below Table
Sr. No.
Table: Elect/Instru. Equipment Heat Dissipation & Occupancy Building Room/Area to Eqpt. Heat Occupancy be Air Load Conditioned (Elec.+Instru.) (Nos.)
08-NOV-2019 Format No. EIL 1641-1924 Rev. 1 SUTHAR KETANBHAI (C360)
Copyright EIL – All rights reserved
13 of 168
Page 13 of 82
Page 14 of 168 Page 1090 of 1419
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR CONSTRUCTION OF FIELD ROOM & MSC. CIVIL WORKS
DOCUMENT No. B015-000-80-43-SP-8203 Rev. 0 Page 11 of 18
(kW) 1
Sub Station-92
2
Sub Station-98
3
Each Field Room (Having Water cooled PAC System)
Switch Gear Hall Operator Room Switch Gear Hall Operator Room Shift-in-charge Room Dining Room
73.0* 0.7* 40.0* 0.7* 1.0
-6 -6 6
--
6
*: Equipment Heat Load mentioned includes heat load due to lighting also. Hence while calculating heat load for that particular area, lighting load need not to be considered. However, for other buildings / areas, lighting load shall be considered as specified in this job specification. 3.1.9
Air conditioning system load/ capacities specified in Scope of Work & Supply are minimum to be considered by the contractor for HVAC equipment and same is given for estimation purpose only. Contractor shall submit the detailed heat load calculations as per the approved/ AFC building drawings and equipment shall be selected for the higher of the two capacities i.e. capacities as per Scope of Work and capacities as per approved heat load calculation. No price or time implication shall be admissible to the contractor due to increase in heat load values provided equipment heat dissipation & air-conditioned area remain the same. Also, no price or time implication shall be admissible to the contractor on account of selection of higher capacity machine due to nonavailability of required/ exact capacity machine in the market. Contractor shall be solely responsible to demonstrate the specified inside conditions throughout the year irrespective of any variation in the outside condition. Accordingly, Contractor shall cross check the estimated plant capacity in his own interest before accepting the same. In case, Contractor desires to increase the plant capacity, he shall furnish adequate technical reasons and necessary technical data including heat load calculations in support of such increased plant capacity during pre-bid meeting. However, minimum capacity of the plant shall be as indicated in the Scope of Work & Supply, which shall be complied by the contractor.
3.1.10 Chemical filtration shall be provided in fresh air circuit of AC system (installed in AHU Room/ Packaged AC room) to maintain air quality (G1 environment) inside satellite rack room/ substation. Chemical filters shall be selected to capture Group-A gases as per ISA-71- 04 standard (from GX environment at outside to G1 environment at inside). 3.1.11 Air Conditioning equipment shall be interlocked with gas/smoke detection and firefighting systems. For Satellite Rack Room, required Hydrocarbon Detection System shall also be provided in AC suction and in ducts as per OISD standard. 3.1.12 Contractor shall consider heat dissipation from electrical/electronic equipment, Lighting Load & Occupancy while estimating the capacity of air-conditioning system. 3.1.13 Safety factor shall be considered as minimum 12.5% in respect of Room Sensible Heat and minimum 10% in respect of Room Latent Heat. 3.1.14 Packaged Units/ AHUs shall provide cooling and dehumidification in summer/monsoon by handling mixture of fresh and return air. Reheating shall be 08-NOV-2019 Format No. EIL 1641-1924 Rev. 1 SUTHAR KETANBHAI (C360)
Copyright EIL – All rights reserved
14 of 168
Page 14 of 82
Page 15 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-3 U-VALUE CALCULATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 15 of 168
Page 15 of 82
Page 16 of 168
HEAT LOAD ESTIMATION FOR VRMP
U-FACTOR SUMMARY ASHRAE Description
U- Value--BTU/(hr)(ft².°F)
External wall - Solid Brick wall - 230mm thick
0.36
External wall - RCC Concrete wall - 230mm thick
0.48
Partition wall - Solid Brick wall - 230mm thick
0.32
Exposed Roof - RCC 150mm thick+50mm Insulation
0.11
Floor - RCC 150mm thick(Without Underdeck Insulation)
0.36
Ceiling - RCC 150mm thick(Without Underdeck Insulation)
0.29
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 16 of 168
Page 16 of 82
Page 17 of 168
HEAT LOAD ESTIMATION FOR MREP
U-Value calculation 1
External wall - Solid Brick wall - 230mm thick Thickness
Density
mm
kg/m3
Layer
Thermal Conductivit y W/m.K
R-Value
R-Value
(m².K)/W
(hr.ft².°F)/BTU
0.12
0.68
Reference
a
Inside vertical surface resistance (Air film)
b
Cement plaster, sand aggregate
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
c
Solid Brick Wall
230
1920
0.81
0.28
1.61
ASHRAE Fundamentals Handbook, Table 1
d
Cement plaster, sand aggregate
18
1860
0.72
0.03
0.14
ASHRAE Fundamentals Handbook, Table 1
0.04
0.25
ASHRAE Fundamentals Handbook, Table 10
0.49
2.78
2.04
0.36
R-Value
R-Value
(m².K)/W
(hr.ft².°F)/BTU
0.12
0.68
e
Outside surface resistance U-VALUE
2
ASHRAE Fundamentals Handbook, Table 10
Partition wall - Solid Brick wall - 230mm thick Thickness
Density
mm
kg/m3
Layer
Thermal Conductivit y W/m.K
Reference
a
Inside vertical surface resistance (Air film)
b
Cement plaster, sand aggregate
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
c
Solid Brick Wall
230
1920
0.81
0.28
1.61
ASHRAE Fundamentals Handbook, Table 1
d
Cement plaster, sand aggregate Inside vertical surface resistance (Air film)
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
0.12
0.68
0.56
3.16
1.79
0.32
e
U-VALUE
MUMBAI REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 17 of 168
Page 17 of 82
ASHRAE Fundamentals Handbook, Table 10
ASHRAE Fundamentals Handbook, Table 10
Page 18 of 168
HEAT LOAD ESTIMATION FOR MREP
3
External wall - RCC Concrete wall - 230mm thick Thickness
Density
Thermal Conductivity
R-Value
R-Value
mm
kg/m3
W/m.K
(m2.K)/W
(hr.ft2.°F)/BTU
0.12
0.68
Layer a b c
Reference
Inside vertical surface resistance (Air film)
ASHRAE Fundamentals Handbook, Table 10
Cement plaster, sand aggregate
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
RCC Concrete Wall
230
2400
1.4
0.16
0.93
ASHRAE Fundamentals Handbook, Table 1
d
Cement plaster, sand aggregate
18
1860
0.72
0.03
0.14
ASHRAE Fundamentals Handbook, Table 1
e
Outside surface resistance
0.04
0.25
ASHRAE Fundamentals Handbook, Table 10
0.37
2.10
2.70
0.48
R-Value
R-Value
(m2.K)/W
(hr.ft2.°F)/BTU
0.16
0.92
U-VALUE 4
Exposed Roof - RCC 150mm thick+50mm Insulation Layer
Thickness
Density
mm
kg/m3
Thermal Conductivity W/m.K
Reference
a
Indoor air film, still air, horizontal surface, downward heat flow
b
Underdeck Insulation(Mineral Wool)
50
16-48
0.04
1.25
7.10
ASHRAE Fundamentals Handbook, Table 1
c
RCC
150
2400
1.4
0.11
0.61
ASHRAE Fundamentals Handbook, Table 1
d
Light Weight Aggregate
20
960
0.3
0.07
0.38
ASHRAE Fundamentals Handbook, Table 1
0.04
0.25
ASHRAE Fundamentals Handbook, Table 10
1.77
10.02
0.57
0.10
e
Outside surface resistance U-VALUE
MUMBAI REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 18 of 168
Page 18 of 82
ASHRAE Fundamentals Handbook, Table 10
Page 19 of 168
HEAT LOAD ESTIMATION FOR MREP
5
Floor - RCC 150mm thick(Without Underdeck Insulation) Layer
a b
Thickness
Density
mm
kg/m3
Thermal Conductivity W/m.K
R-Value
R-Value
(m2.K)/W
(hr.ft2.°F)/BTU
0.11
0.62
Indoor air film, still air, horizontal surface, upward heat flow RCC
150
c
Light Weight Aggregate
50
d
Indoor air film, still air, horizontal surface, upward heat flow
ASHRAE Fundamentals Handbook, Table 10
2400
1.4
0.11
0.61
ASHRAE Fundamentals Handbook, Table 1
960
0.3
0.17
0.95
ASHRAE Fundamentals Handbook, Table 1
0.11
0.62
0.49
2.80
2.03
0.36
R-Value
R-Value
(m2.K)/W
(hr.ft2.°F)/BTU
0.16
0.92
U-VALUE 6
Reference
ASHRAE Fundamentals Handbook, Table 10
Ceiling - RCC 150mm thick(Without Underdeck Insulation) Layer
Thickness
Density
mm
kg/m3
Thermal Conductivity W/m.K
Reference
a
Indoor air film, still air, horizontal surface, downward heat flow
b
RCC
150
2400
1.4
0.11
0.61
ASHRAE Fundamentals Handbook, Table 1
c
Light Weight Aggregate
50
960
0.3
0.17
0.95
ASHRAE Fundamentals Handbook, Table 1
d
Indoor air film, still air, horizontal surface, downward heat flow
0.16
0.92
0.60
3.40
1.67
0.29
U-VALUE
MUMBAI REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 19 of 168
Page 19 of 82
ASHRAE Fundamentals Handbook, Table 10
ASHRAE Fundamentals Handbook, Table 10
Page 20 of 168
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
01234678429 7 381 938 797 796
171 2318728 18371
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
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 W1 m8737 9 op tpuvwx u vwxpt o{puovwx \1z1819m1 j9 2379231'8-672 |}cd~bcdecbb 3%=547"7%##))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)M K %"%&.:BB:0 A)Q#!M): B)BCV#!B)BCM >!"%&5%'#"".:B//0 @)M#!/: B)BCB#!B)BCh >!"%&5%'#"".:B//0 /h#!/C B)BhA#!B)Bh@ >!"%&5%'#"".:B//0 :: B)Bhh >!"%&5%'#"".:B//0 _!'G%&63%;+!!37%##))))))))))))))))))))))))))))))))))))))))))))))))))))) B)M K %"%&./@@V0 h:#!hA B)BhV#!B)BhA J&%&5%'#"".:B//0 CQ B)Bhh#!B)BhQ J&%&5%'#"".:B//0 `4&"%3+!!3-53#6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /V#!CM B)BCB gES<.:BBV0-
E
!"%&5%'#"".:B//0 %;6/MB6%1)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) ::#!QM B)B:@ J&%&5%'#"".:B//0 "!(%&("!6'#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) hB B)BhB J&%&5%'#"".:B//0 %;6Q1%"%#:Cg)))))))))))))))))))))))))))))))))))))))))))))))))))))) h:#!hQ BBhB J&%&5%'#"".:B//0 73!+&+4#$3!+;3!7%3+%" 4&;(!#%3.L0.Q0 73!+4&;%;))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)BhQ#!B)BhV J&%&5%'#"".:B//0 ?(%&66(!31#1"&-!3667%6))))))))))))))))))))))))))))))))) /)Q K %"%&./@@V0 /V#!:C B)BhQ#!B)BhA E&6(&6##"(!"#.:BBM0 :@ B)Bhh E&6(&6##"(!"#.:BBM0 `4&"%3547"7!%"6-+#53#6))))))))))))))))))))))))))))))))))))))))))))) /VB B)BhA B)M K %"%&./@@V0 _!'G+!!37!%"6))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)M K %"%&./@@V0 53!!"%&6+%33))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) VC#!/hB B)Bhh#!B)BhV >4,%&5%'#"".:B//0 "!!54&;)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/VB#!/MB) B)Bh@#!B)BC: B)M >4,%&5%'#"".:B//0 B)V#!B)M O'!#4'%3#43)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) hCB#!hAB B)BQ:#!B)BQh L"34#7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /CB B)BQ: J&%&5%'#"".:B/B0 L!314!'1%&"%#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /)Q K %"%&./@@V0 &5%'6-%;6("g%&Tgabcdecfe
Page 20 of 82
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
°
±iq6[0\6Z029 o²9 21932 u[jx X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 op tpuvwx u vwxpt o{puovwx \1z1819m1 B)B:B#!B)B:h J&%&5%'#"".:B//0 /)C
E!"%&5%'#"".:B//0 /@#!:V B)Bh@#!B)BCB >!"%&5%'#"".:B//0 QV B)Bh@#!B)BCB J&%&5%'#"".:B//0 h:#!VC B)Bh@#!B)BCQ /)/ .`%&5%'#""-(":BB/0 VC#!/:B B)BCQ#!B)BQ: .`%&5%'#""-(":BB/0 / : B # ! / M B B ) B Q : # ! B ) B V / .`%&5%'#""-(":BB/0 3%547"6 %##4'-·/BB#!VBB ))))))))))))))))))))))))))))))))))))))))))))))))) V)C#!M)B B)BQ:#!B)BQQ >!"%&5%'#"".:B//0 %##4'-·VBB#!//BB )))))))))))))))))))))))))))))))))))))))))))))))) M#!@)V B)BC@#!B)BQ: >!"%&5%'#"".:B//0 '3!6%##4'!"+%33'%,4#4)))))))))))))))))))))))))))))))))))))))))))) :@#!hA B)BhQ#!B)BhV >!"%&5%'#"".:B//0 _!'G%&63%;+!!36 %##4'-·@B#!//Q )))))))))))))))))))))))))))))))))))))))))))))))))))) :C#!:V B)BC@ N$"%&5%'#"".:B//0 %##4'-·/:Q#!ChB )))))))))))))))))))))))))))))))))))))))))))))))))) :C#!:@ B)BCV#!B)BCM N$"%&5%'#"".:B//0 '3!6%##4'!"+%33'%,4#4)))))))))))))))))))))))))))))))))))))))))))) VC B)Bh@#!B)BC: N$"%&5%'#"".:B//0 ¸" 4'34#-?5!34%#6))))))))))))))))))))))))))))))))))))))))))))))))))))))))//:#!/h/ B)BVM /)h <%74&#%3)./@AQ0 VC#!@V B)BVh `%&5%'#"".(":BB/0 a¹fcº»c¹¹}µe g333!-("%164!!(&+%33'%,4#4)))))))))))))))))))) :V#!C: B)Bh@#!B)BCB N+!%&5%'#"".:B//0 3%547"-("%164!!(&+%33!"%##4''%,4#4)))))) /V B)Bh@#!B)BC: `%&5%'#""F%!'4%#4!&.:B//0 :@#!hA B)Bhh#!B)BhA >!"%&5%'#"".:B//0 L!31"#$%&5!% )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /)Q K %"%&.:BB:0 3!+6&4#1-!(&'33)))))))))))))))))))))))))))))))))))))))))))))))))))) A):#!/B B)BhA#!B)BC: N$"%&5%'#"".:B//0 64 6&4#1-'3!6'33-%;6/MB6%1)))))))))))))))))) hB#!Q/ B)B:B#!B)B:@ >4,%&5%'#"".:B//0 7 79 28 29 [7 79 |cfe O7#!T' 7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@BB B)QA /)BB
!##%;./@CA0 g 7!%"6))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) //QB B):Q B)MC K %"%&.:BB:0 >47"T' 7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /CBB B):Q B)MC K %"%&.:BB:0 /BBB B)/@ B)MC K %"%&./@@V0 CBB B)BA /)MM K %"%&./@@V0 hBB B)BV /)MM K %"%&./@@V0 1( !"(3%#"7!%"6))))))))))))))))))))))))))))))))))))))))))))))))))))) VCB B)/V /)/Q K %"%&.:BB:0 J"46#"%&67!%"6.J<S0)))))))))))))))))))))))))))))@#!// VQB B)// /)MM K %"%&.:BB:0 )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/:)A VQB B)/: /)MM K %"%&.:BB:0 L31+!!6.6!;3%54"0))))))))))))))))))))))))))))))))))))))))))))/:)A CVB B)/C /)MM K %"%&.:BB:0 )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/Q)@ QCB B)/Q /)MM K %"%&.:BB:0 L31+!!6T+!!6(%&3))))))))))))))))))))))))))))))))))))))))))))/@)B CQB B)/@ /)MM K %"%&.:BB:0 ¸;#%73547"7!%"6 VQB B)// /)MM K %"%&.:BB:0 $%#$4&;-";3%"6&4#1))))))))))))))))))))))))))))))))/:)A :@B B):h /)hB +4./@VA0 4" 64%#6&4#1)))))))))))))))))))))))))))))))))))/:)A hQB B)/@ /)hB +4./@VA0 &%43=7%6$%#$4&;))))))))))))))))))))))))))))))))))))))))/:)A CBB B)/@ /)hB $4&;37%'G"))))))))))))))))))))))))))))))))))))))))))))))))))))@)Q :@B B)/A /)hB !&66%6&4&;7!%"6))))))))))))))))))))))))))))))))))))/:)A :CB B):C /):V #43%&63%1=4&(%&3-(3%4&!"%'!#4' :@B B)BQM B)Q@ 3% 4&%#6(%("7!%"6 CMB B)BA: /)hM +4./@VA0 $! !;&!7!%"65"! "(3(6(%(" CMB B)BA: /)/A *%"67!%"6 64 6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) MBB B)/BQ /)hB +4./@VA0 $4;$6&4#1-",4'=# ("6;"%6%&6",4';"%6 MMB B)/: /)hC +4./@VA0 $4;$6&4#1-#%&6%"6=# ("6;"%6)))))))))))))))))))))))))) /B/B B)/CC /)hC +4./@VA0 L%"#4'37!%"6 3!+6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) Q@B B)/B: /)hB +4./@VA0 64 6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) MBB B)/hQ /)hB +4./@VA0 $4;$6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /BBB /)/M +4./@VA0 &6"3%1 ))))))))))))))))))))))))))))))))))))))))))))))))))/Q)@ VCB /):: /):/ +4./@VA0 %5"7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) ABB B)BA: /)MM K %"%&./@@V0 a¼µd½} O7#!T' )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@BB B)BhA !!6-CBB -/@B ?(!")))))))))))))))))))))))))))))))) B)/Q /)hB !!6-6!73-CBB -hBB ?(!"))))))))))))))))))) B):/ /)/A !!6-(34&)7%'G"7!%"6)))))))))))))))))))))))))))))))M B):Q /)hB aµeµd½ O7#!T' -3%((6))))))))))))))))))))))))))))))))))V)C B)BhA /)B/ O($%3#"!33464&;))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)B:V /)CA O($%3#4&3%#4&;464&;./:)A 760)))))))))))))))))))))) B):V /)CA W1 m8737 9 L$&!34'5!% 7!%"6+4#$5%'"-%;6)))))))))))))))))))))))))))))))) ³´µ}} g333!547"-3!!5433))))))))))))))))))))))))))))))))))))))))))))))))))))) %##4'%((34'%#4!&(#!/BB )))))))))))))))))))))))))))))))))))))) %##4'%((34'%#4!&¶/BB )))))))))))))))))))))))))))))))))))))))))))) +%33%((34'%#4!&-6&(%'G6)))))))))))))))))))))))))))))))))))))) L"34#-?(%&66)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))
Page 21 of 168
08-NOV-2019 SUTHAR KETANBHAI (C360) 21 of 168
Page 21 of 82
Page 22 of 168
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
01234678429 7 381 938 797 796
171 2318728 18371
Æ
X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx W1 m8737 9 *%"67!%"6464&;)))))))))))))))))))))))))))))))))))))))))))))))// !!6-6"!(-:BB ))))))))))))))))))))))))))))))))))))))))):Q !!6-7,3 :BB -3%((6))))))))))))))))))))))))))))))))))))))))))/h :QB -3%((6))))))))))))))))))))))))))))))))))))))))))/@ !!6-(31+!!6-3%((6))))$))-)4)))))))))))))))))))))))))))))@)Q O3 4& -#3-!",4&13- !,"$%#$4&;))))))))))))))))) $!33!+=7%'G6))))))))))))))))))))))))))))))))))))))))))))))))))))))) 4&3%#4&;=7!%"6=7%'G6)))))))))))))))))))))))))))@)Q 5!43=7%'G6))))))))))))))))))))))))))))))))))))))))))))))))@)Q O"'$4#'#"%3.!6%=34 53!%#0;3% 7 7918291 ¸%(!"=(" %7353#)))))))))))))))))))))))))))))))))):))))))))))))))))))))))))) ¸%(!"Ç%3-:3%1"!5!((6B)AhG;T 53#))))))))))))))))) ¸%(!"Ç%3-(3%#4'543 ))))))))))))))))))))))))))))))))))))))))))))))))))))))) ²797 Ȳ 879231872 g%"(#%&6"7!&66"#$%&(%6))))))))))))))))))))))))/@ g%"(#%&6"77"(%6.!&=(4'0))))))))))))))))))))))))@)Q L43'%"(#+4#$"77"(%6)))))))))))))))))))))))))@)Q#!/:)A 4&!3 T'!"G#43))))))))))))))))))))))))))))))))))))))))))))))))))V)C L¸gT"77"53!!"'!,"4&;)))))))))))))))))))))))))))))))))))))))))))))))))) "77"#43)))))))))))))))))))))))))))))))))))))))))))))))))))))))))):Q #""%RR!)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):Q 132 .<g$%(#"hh-N%73h0 \ z79 O7#!T' $4&;3)))))))))))))))))))))))))))))))))))))))))))))))))))) O($%3#.74# &+4#$4&"#54330))))))))))))))))))))))))))))))))))))))))) O($%3#"!33"!!54&;))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) O($%3#$4&;3)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) S43#=("!!54&;)))))))))))))))))))))))))))))))))))))))))))))))))))))))/B `%#4'%($%3#.$%,1-:BD;"4#0)))))))))))))))))))))))))))))))))))))))) _6#$%#'$)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) _!!54&;53#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) <3%#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/h <#"%+#$%#'$))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) !!6$4&;3-(3%4&%&6(3%#4'=543=5%'6))))))))))))))))))))))) 2 31879231872 g (3%#"-%&6%;;";%#))))))))))))))))))))))))))))))))))))))))))) <%&6%;;";%#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))/B ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):B 1( (3%#")))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) 4;$#+4;$#%;;";%#)))))))))))))))))))))))))))))))))))))))))))))/h ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/V !&#%33%#$))))))))))))))))))))))))))))))))))))))))))))))))))))))/@ L"34#%;;";%#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) <%&6%;;";%#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) !&#%33%#$))))))))))))))))))))))))))))))))))))))))))))))))))))))/@ ¸" 4'34#%;;";%#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 op tpuvwx u vwxpt o{puovwx \1z1819m1 B)/: /)/A B)/C /)/A B)/C /)/A B)/M /)/A B)/B /):: B)// /)::4 B)h: /)hC B)Q: :QBB /)B B)MC B)B// B):/
;34;473 //B B)C:
E
L"34#(3%#"))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) L3(7!%"6!"(%("(3%#"))))))))))))))))))))))))))))))))))))))))))))))))))) <%&6T' (3%#"-'!&64#4!&6)))))))))))))))))))))))))))))))))))))))) <%&6T' T34(3%#"-'!&64#4!&6)))))))))))))))))))))))))))))))) <%&6T;1( .hÇ/0(3%#"-'!&64#4!&6)))))))))))))))))))))))))))))) 2 98n231872 ÉcdfºÊdµb S"4'G-54"6'3%1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) :CBB ::CB :BMB /@:B
B)Ch B)QM /)/Q B)/@ B)B@ /):B B)BA B)A: B)hM B)CV A:B A:B B):: B)M/ B)/C B):B B):Q B):V B)hB B)BM B)/@ B)BA B)Vh B)CM B)VQ
B)BhA B)B:A B)BAM B)BQ@ B)BB@ B)/VV B)B/h B)B:V B)BMh B)B:h
/)BB /)Q/ /):V /)CA /):V /)hB B)MC B)MC B)MC B)BQV B)BVV /)hC B)MC
/):/#!/)CA /)BA#!/)hB B)@:#!/)/: B)M/#!B)@M
B)MB
08-NOV-2019 SUTHAR KETANBHAI (C360) 22 of 168
Page 22 of 82
gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
i±
±iq6[0\6Z029 o²9 21932 u[jx X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 op tpuvwx u vwxpt o{puovwx \1z1819m1 /AVB B)A/#!B)MQ ¸%3!"./@MM0 /VBB B)V/#!B)AC ¸%3!"./@MM0 /CCB B)Q:#!B)V: ¸%3!"./@MM0 /:MB B)Ch#!B)Qh ¸%3!"./@MM0 //:B B)hV#!B)CQ ¸%3!"./@MM0 B)/C B)MM _!+31%&6O3;"&./@hA0 B):B _!+31%&6O3;"&./@hA0 B):A _!+31%&6O3;"&./@hA0 B)hh _!+31%&6O3;"&./@hA0 B)h@ _!+31%&6O3;"&./@hA0 B)CC _!+31%&6O3;"&./@hA0 MBB B):B K %"%&./@@V0 AAB B):: K %"%&./@@V0
W1 m8737 9
g3%1#43-$!33!+ /'336())))))))))))))))))))))))))))))))))))))))))))))))))))))))))AQ ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/BB :'336())))))))))))))))))))))))))))))))))))))))))))))))))))))/QB )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):BB )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):QB h'336())))))))))))))))))))))))))))))))))))))))))))))))))))))hBB 4;$#+4;$#7"4'G)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) ËdÌfb}Ì~5-; 4#!&%;;";%# ·:BB -/V)hG;-::BBG;Th'!&'"#-:'!"))))))))) +4#$("34#=54336'!")))h))))))))))))))))))))))))))))))))))))))))) ·hBB -:QG;-::BBG;T '!&'"#-:'!")))))))))))) +4#$("34#=54336'!"))))))))))))))))))))))))))))))))))))))))))))
!" %3=+4;$#%;;";%#.%&6%h&6;"%,30 ·:BB -/VG;-:/BBG;T '!&'"#-:!"h'!"Í +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!"h)))))))))))))))))))))))))))))))))))) ·hBB -::)AG;-:BBBG;T '!&'"#-:'!"))))))) `64 =+4;$#%;;";%#.'! 74&%#4!&h!5&!" %3%&634;$#+4;$#%;;";%#0 ·:BB -/hG;-/QQB#!/MBBG;T '!&'"#-:!"h'!" +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!")))))))))))))))))))))))))))))))))))) +4#$!366=L<=54336.7%60'!"))))))))))))))))))))) +4#$!366L<4&"#4&'!")))))))))))))))))))))))))))) !+= %%;;";%#.?(%&66$%:3-'3%1-3%#!"3%;-( 4'0 ·/QB -A/T:G;-/CBBG;T '!&'"#-:!"h'!" +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!"))))))))))))):))))))))))))))))))))))) :BB -M#!/BG;-//QB#!/hMBG;T '!&'"#))))) +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!")))))))))))))))))))))))))))))))))))) +4#$!366=L<=54336.7%60'!"))))))))))))))))))))) +4#$>5!% =54336'!"))))))))))))))))))))))))))))))))))))))) +4#$!366L<4&"#4&'!")))))))))))))))))))))))))))) hBB -/VG;-/CBBG;Th-'!&'"#-:!"h'!")))) +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!")))))))))))))))))))))))))))))))))))) <#!&-34-!"%&6))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) :MMB /B)C Î%"#R4#4'%&6%&6#!&)))))))))))))))))))))))))))))))))))))))))))))))))))))) :QVB V): ::CB h)CV /@:B /)MM g%3'4#4'-6!3! 4#4'-34#!&-%"73-%&6;"%&4#))))))))))))) :MMB C)hh :QVB h)/A ::CB :)h/ /@:B /)Q@ /VBB /)/Q 1( (%"#4#4!+ AQ71hBB71AVB -!346)))))))))))))))))))))))))))))))))))))))) C'33))))))))))))))))))))))))))))))))))) /BB71hBB71AVB -h'33)))))))))))))))))))))))))))))))))))) 4#!&)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) :CBB B)QA :VBB B)@h ËdÌfb4 <%&6%&6;"%,3!"#!&%;;";%#'!&'"#))))))))))))))))))))) :CBB /)C#!:)@ .'!&'"#+4#$¶QBD2%"#R!"2%"#R4#%&6$%, ::CB /)h#!:)V '!&6'#4,4#44&$4;$"&6!5"%&;0 :BMB /)B#!/)@ !+= %%;;";%#!"34#!&'!&'"#))))))))))))))))))))))) /@:B B)@#!/)h ?(%&66$%3-'3%1-!"3%#9?(%&6h63%;9'4&6"9 /VBB B)VM#!B)M@ ( 4'.+4#$6&4#1(#!/VBBG;T 09'!"4%.%&66 /:MB B)CM#!B)Q@ '!&'"#$%,'!&6'#4,4#44&$4;$"&6!5"%&;0 @VB B)hB#!B)hV VCB B)/M
Page 23 of 168
B)hA ¸%3!"./@MM0 B)VQ ¸%3!"./@MM0 B):B#!B)/A B)@: ¸%& ./@MQ0 B)hQ ¸%& ./@MQ0 B)hC#!B):C ¸%3!"./@MM0 B):/A B)@: ¸%3!"./@MM0 B)hB#!B):: ¸%& ./@MQ0 B)VQ#!B)C/ ¸%& ./@MQ0 B)QM ¸%& ./@MQ0 B)QV ¸%& ./@MQ0 B)CA ¸%& ./@MQ0 B)hC#!B):@ ¸%& ./@MQ0 B)AC ¸%& ./@MQ0 B)Qh ¸%& ./@MQ0 B)QV#!B)hh B)MM ¸%& ./@MQ0 /):B#!B)AA ¸%& ./@MQ0 B)@h#!B)V@ <$#%3)./@A@0 B)MQ <$#%3)./@A@0 B)A@ <$#%3)./@A@0 B)V: <$#%3)./@A@0 B)CV#!B)CB ¸%& ./@MQ0 /)V#!/)/ ¸%& ./@MQ0 /)B ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 B)MM ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 B)MM ¸%3!"./@MM0 ¸%3!"./@MM0 B)::: B)A@ _!+31%&6O3;"&./@hA0 B):hM _!+31%&6O3;"&./@hA0 B):@C _!+31%&6O3;"&./@hA0 B)MC K %"%&.:BB:0 B)MC K %"%&.:BB:0 ¸%3!"./@MM0 B)MB#!/)BB¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 B)MC ¸%3!"./@MM0 B)MC ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0
08-NOV-2019 SUTHAR KETANBHAI (C360) 23 of 168
Page 23 of 82
Page 24 of 168
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
01234678429 7 381 938 797 796
171 2318728 18371
ii
X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 W1 m8737 9 op tpuvwx u vwxpt o{puovwx \1z1819m1 1( T547"'!&'"#.MA)QD;1( -/:)QD+!!6'$4(0 MBB B):C B)MC _!+31%&6O3;"&./@hA0 g T34-!"#%"-%&6#''!))))))))))))))))))))))))))))))))))))))))) /@:B /)CB ¸%3!"./@MM0 /VBB B)@A ¸%3!"./@MM0 /:MB B)VQ ¸%3!"./@MM0 L"34#-," 4'34#-%&6(!31#1"&7%6))))))))))))))))))))))))) MBB B):V#!B):A ¸%3!"./@MM0 VCB B):B#!B):: B)Vh#!B)@V¸%3!"./@MM0 CMB B)/V ¸%3!"./@MM0 h:B B)/: ¸%3!"./@MM0 >!% '!&'"#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@:B B)AQ ¸%3!"./@MM0 /VBB B)VB ¸%3!"./@MM0 /:MB B)CC ¸%3!"./@MM0 //:B B)hV ¸%3!"./@MM0 >!% '!&'"#%&6'333%"'!&'"#)))))))))))))))))))))))))))))))) @VB B)hB ¸%3!"./@MM0 VCB B):B ¸%3!"./@MM0 h:B B)/: ¸%3!"./@MM0 O"%#6'!&'"#.!,&=6"460))))))))))))))))))))))))))))))))))))))))))))ChB#!MBB B):B B)MC K %"%&./@@V0 L!31#1"&'!&'"#.!,&=6"460)))))))))))))))))))))))))))))))))))))):QQ#!MBB B)hA B)MC K %"%&./@@V0 L!31 "'!&'"#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@QB /)VC K %"%&./@@V0 ::BB /)Bh K %"%&./@@V0 L!31 "' ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /MAB B)AM K %"%&./@@V0 <3%;'!&'"#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) @VB B):: N!3!G4%&#%3./@AB0 /:MB B)h: N!3!G4%&#%3)./@AB0 /VBB B)Ch N!3!G4%&#%3)./@AB0 :BBB /):h N!3!G4%&#%3)./@AB0 t
./:D!4#"'! Ñ Ñ /)VhG 43G./@A@0 ÏcfeÐe J%G))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))VVB#!AQB B)/V#!B)/M g%"6&%%&6S473./@MA0 S4"'$))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))VMB#!A:Q B)/A#!B)/M g%"6&%%&6S473./@MA0 `%(3)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))VhQ#!ABB B)/V#!B)/A g%"6&%%&6S473./@MA0 O$)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))V/Q#!VAB B)/Q#!B)/V g%"6&%%&6S473./@MA0 a´bÐe Ñ Ñ Ñ /)VhG 43G./@A@0
%¸%3 %"5!"%&# ("%#"!5:Cg)_("%#4,,%35!"6"1%#"4%3%"4&66 4¸4&13('454'$%#Õ/)BGÖT.G;UK0 %64;&.&!#('454'%#4!&0,%35!"%#"4%34&&!" %3)N$" %3,%3!54&3%#4&; 8<O6% ./@A/0-`%'%&./@C/0-%&643G./@A@0)g!&6'#4,4#1,%3
%#"4%3 %16455"5"! 64;&,%36(&64&;!&4&=4#("!("#4.);)-6&4#1%&6 !4#"'!-!"4%#4!&-#')0%&6 %&5%'#"4&;,%"4%7434#1)>!"("!("#4!5('454' ("!6'#-,%3((34671%&5%'#""!"&74%6##) 7<1 7!3 Ó%3!6#!"("#$" %3'!&6'#4,4#1) 'P! &!#4&'36(%("7%'G4&;%&65%'4&;-45%&1)$"4&3%#4!&5!" 7!&6%"1."53'= #4,!"!#$"+40!5%4"(%'-N%73:%&6h5!"4&3%#4&;,%3!5%4"(%'+4#$%(("!= ("4%#55'#4, 4##%&'%&6# ("%#"'!&64#4!&!5(%') 6g!&6'#4,4#1,%"4+4#$547"64% #".g$%(#":Q0)S%##-73%&G#-%&63!!=5433 4&= "%3547"4&3%#4!&%" %&5%'#"6#!%'$4,('4546_=,%3-#$!#'! !&!5 +$4'$%"34#64&#$#%73)S'%!56455"&'4&%&5%'#"4&;("!'%&6%#"4= %3-#$("!6'##$4'G&-6&4#4-%&6#$" %3'!&6'#4,4#4,%"1!,"'!&46"%73 "%&;5!"%('4546_=,%3) E&3%#4&; ,%3!5%'!#4'%3#43,%"1-6(&64&;!&6&4#1!57!%"6%&6!(-4R-%&6 6 ( # $ ! 5 ( "5!"%#4!&) 5¸%35!"5331;"!#673!'G %17%(("!?4 %#64&;,%35!"'!&'"#+4#$4 43%" &4#6&4#1) ;¸%3 5!"'!&'"#73!'G%&6'!&'"#%"%#!4#"'!"("%#4,!5&!" %3) $¸%35!"#%3!",4&13464&;%((346!,"53%#"5%',%"1+4631-6(&64&;!&,= 3%#4!&!5#$%4"(%'7&%#$#$464&;9+$#$"%4"(%'4"53'#4,!"&!&"53'#4,9%&6 !&#$4'G&-#1(-%&6%((34'%#4!&!54&3%#4&;7%'G4&;=7!%"66)¸%3%"%,"%;5!" %64;&;46-%&6+"!7#%4&65"! ,"%3;%"66$!#7!?##.O
Page 24 of 82
34#6%"5!"$%##"%&5"%'"!#$;"%4&)N$" %3'!&6'#4,4#1!5+!!6,%"4 34&%"31+4#$6&4#1-%&66&4#1"%&;34#6%"#$!&!" %3315!&65!"+!!6 ('4;4,&)E56&4#1!5+!!6('44&!#G&!+&- %&'!&6'#4,4#1 ,%3)>!"?#"%(!3%#4!&#!!#$"!4#"'!-#$5!33!+4&; (4"4'%32%= #4!&6,3!(67143G./@A@0%176Ç ß=/=)=M=A==C==Ý===/=B==Ü=:==Þ==Q==)A==Q=h===Ý==/==B=Ü=C==É==à==×= ~Õ B)/A@/Þ= /ÞB)B/É +$"×46&4#1!5!4#+!!64&G;T h-%&6É4!4#"'!4&("') G>"! 43G./@A@0-%& (4"4'%32%#4!&5!"('454'$%#!5 !4#+!!6%# :Cg4%5!33!+Ç Ì¹ Õ =ß=B=ß)=:/=@==Þ@==BÞ==)B=B=/)=B=É/==Éà===àÞØ̹ +$"Ø̹%''!5!"$%#!5!"(#4!&%&646&!#671 Ø̹ á Éß/)@:/Ý/BÜhÜh)/VMÝ/BÜQÉà +$"É4!4#"'!4&("'71%) 3S3%&G(%'4&"5"&''!3 &4&64'%#$4#!"4'%3,%35"! (",4!,!3= !5ÙaÏÚÙÛÏcde~)
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
±
±iq6[0\6Z029 o²9 21932 u[jx
X21° Xn7m2628193XÈ182 9 m37r73nl21 z 8[ 7 4tpuvwx
X21i± [8z2m1²7 1zz7m7193 p\1 7 329m1
[8z2m1Z73329m14ä \1z1m37r1 W781m37 9 Ò ä98å1z±1Æm±37r1 äå±± äå±±æ z 0123² ã ç y ç y ç yÂ
\1m 19 1 l21 z 8W1 792 Ò 82\291 Y ã 07Èm B)V#!:)Q B)AM :):Q B)@#!:)Q /)VC :):Q B)@#!/)V /)/: /)QV B)@#!:)Q B)@Q :):Q
737 9 z [8z2m1 j9 8 *!"4R!%3 (+%"6 @):V B)// Q)/A B)/@ C)h: B):h <3!(4&;%#CQ (+%"6 @)B@ B)// Q)BB B):B C)/Q B):C %_%!&%73 ,%35!"+$&&!4#=!"!43=('454'6%#%%"%,%43%73) *!"4R!%3 M):@ B)/: C):B B):C h)hQ B)hB 7`!6"%#31'!&",%#4 ,,%35!" 4&4 $%#3!#$"!;$!43.);)-4&!43 ¸"#4'%3 $%#?'$%&;"!"%"#$='!%'#'!!34&;'%3'3%#4!&0)¸%3%"5"! <%3! !&%&6 <3!(4&;%#CQ P!+&+%"6 A)QB B)/h h)C/ B):@ :)QV B)h@ `%"3!+./@M@0) *!"4R!%3 P!+&+%"6 V)/h B)/V :)/B B)CM /):Q B)MB '`!6"%#31 '!&",%#4,,%35!"%?4 $%#3!#$"!;$!43.);)-4&(%G ]3 8.%&1(!4#4!&0 ç¿ y¿ +4"$%#3!'%3'3%#4!&0)¸%3%"5"! <%3! !&%&6`%"3!+./@M@0) 4 & 6 . 5 ! " +4 & # " 0 O& 1 h C)B B)BhB X21Æ Xn7m2628193XÈ182 9 m37r73nl21 %#V)AT z 8\ mo 4tpuvwx 4&6.5!" "0 O&1 ::)A B)BCC %#h)CT Ò 82\291 èbÇ L 4'-#55-!7464%& B)Q#!:): /)<":5%''!&6'#%&'¼µ%&6¼%"64&T. :UK09"4#%&'Úµ%&6Ú4& . UK0T) S%%3# B)Q#!:)V :)
!"5%'$%7!#$%&%4"(%'"4#%&',%3%&6%"5%'"4#%&',%3) <$%3 B)@#!C)B h)g!&6'#%&'%"5!""5%'!5#$#%#6 4##%&'5%'4&;,4"#%373%'G7!61"= "!&64&;%#% # ("%#"%% 74%4")¸%37%6!&"5%'T%4"# ("%= "%&4# /)A#!C)h #"6455"&'!5Q)VK%&6"5%'# ("%#"!5:/g) 4#!&-6!3! 4#-%"73 /):#!C)h C)<g$%(#"C5!"!"6#%4364&5!" %#4!&) Î%"#R!%&6#!& /)C#!A)M Q)g!&6&%#'%&$%,4;&454'%55'#!&"5%' 4##%&'.N%73:0)O3!-!?4=
<%&6 <43# g3%1 !%
O$%#53!+#$"!;$!43- !4#"#&6#! !,%+%15"! #$$%#!"')N$4!4#"4;"%#4!&("!,464&4#4%3%#"%&= (!"#!5$%#-7#4#%3!6"4#$!43%68%'#!#$$%#!"'-#$ 3!+"4&;#$%((%"#$" %3'!&6'#4,4#14&#$%#R!&!5!43) N1(4'%331-+$&!#$"5%'#!"%"$36'!&#%-~4&'"%+4#$ !4#"'!%&6+4#$6"16&4#1!5%!43-7#6'"%+4#$ 4&'"%4&;!";%&4''!!5%!43%&65!"&45!" ;"%6%#4!&%&6 "!&66!43;"%4&.7'%;"%4&=#!=;"%4&'!%'#%""6'60) N$~!5%5"!R&!43%17$4;$"!"3!+"#$%&#$%#!5#$% &5"!R&!43.7'%#$'!&6'#4,4#1!54'4$4;$"#$%&#$%#!5 +%#"7#3!+"#$%&#$%#!5#1(4'%3!43;"%4&0)P455"&'4&~ 73!+ !4#"'!!5A#!MD%"24# %33)O#%(("!?4= %#31/QD!4#"'!-~%1,%"1(#!hBD5"! &5"!R& ,%3) $&'%3'3%#4&;%&&%3&";1-'$!!,%3#$%#"("= #1(4'%3%&4#'!&64#4!&)E&'34%#+$";"!&65"R4&; 44;&454'%-%''"%#$%##"%&5"43%#4!&$!364&'36#$ 55'#!5#$3%#$%#!554!&!5+%#")&";1"3%66"4&; #$4($%'$%&;4;&454'%"#%"6#$("!;"!5#$5"!#5"! 4&!4#!43) >!"5"#$"4&5!" %#4!&-g$%(#"/A-+$4'$4&'36% #$!65!"#4%#4&;$%#3!#$"!;$5!&6%#4!&)
[â\²6Z²jY]Z²²jjZÒX[p \Z[j[X6ÒZ[
O?(3%4&64&g$%(#":Q-#$!,"%33#$" %3"4#%&'!5%& % 731'! ("44#"5%'=#!="5%'#$" %3"4#%&'Ú %&6#$"5%'543 "4#%&'7#+&#$% 731F"5%' %&6#$4"4!"%&6?#"4!"&,4"!& .Ú%&6Ú0)N%73/B ;4,#1(4'%3,%35!"#$"5%'543 '!554µ'4¼µ%&6¼%&6 #$4""'4("!'%3-#$"5%'"4#%&'Úµ%&6Ú)O$!+&-#$ 4&6!!",%36(&6!&(!4#4!&!5#$"5%'-64"'#4!&!5$%# #"%&5"-%&6#$"5%'F3!&;=+%, 44,4#1)J#6!!"-#$,%3= 6(&6!&%4"(6%&6#$"5%'F3!&;=+%, 44,4#1) N%73/B"53'##%&6%"64#%#4!&-+4#$%&% 6.%(("!?4= %#04"4!""5%'# ("%#""("%#4,!5+%33!""!!5 % 734)>!"4#%#4!&#$%#6,4%#7#%%3315"! #%&6%"6
Page 25 of 168
6%#4!&-'!""!4!&-%&6%'' 3%#4!&!56#%&664"#'%&6"% %#4'%3314&'"%"= 5%' 4##%&') 4##%&',%3!5B)BQ$!36!&3176+$"$4;$31"53'#4, "5%''%&7%4%4&6!,"#$",4'345!5#$% 731)
X21ii Z8 129[8z2m1²7 1zz7m7193 p\1 7 329m1
737 9 z[8z2m1 j9 8 *!"4R!%3-3!(4&;#!CQ ¸"#4'%3-3!(4&;71!&6CQ ]3 8
W781m37 9 z ç4 y4 0123² ã tpu vwx u vwxpt (+%"6 /B B)/ P!+&+%"6 V B)/A O&164"'#4!& A)A B)/h :Q B)BC
'!&64#4!&-4&'364&;4"4!""5%'# ("%#"5!"5&#"%#4!& 1# -O<*_O./@@M0!",%35"! g$%(#"/Q#!6#"= 4&#$"5%'543 '!554'4T"4#%&')N%73//34##$ #%&6%"6"5%'543 '!554'4,%364&"!(%&#%&= 6%"6)
]WZ[6ÒW[X6ÒW6\W[
O<*_O):B/B)&";1#%&6%"65!"74364&;?'(#3!+="4"46%3 74364&;)O
<ETO<*_OTE<abcdecfe@B)/=:B/B) O<*_O):BB@)g"4#"4%5!" !4#"='!"!364;&4&74364&;)O
<ET O<*_Oabcdecfe/VB=:BB@) O
08-NOV-2019 SUTHAR KETANBHAI (C360) 25 of 168
Page 25 of 82
08-NOV-2019
Page 26 of 82
08-NOV-2019 SUTHAR KETANBHAI (C360)
Page 27 of 82
Page 28 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-3.1 ETD CALCULATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 28 of 168
Page 28 of 82
HEAT LOAD ESTIMATION FOR VRMP Equivalent Temp. Difference Calculations HVAC Contractor- Advance Ventilation Pvt. Ltd. Daily Range in deg.F
Summer (˚F)= 20.52
Monsoon (˚F)= 15.66
Project: Vizag Refinery Modernization Project DBT in deg.F SUMMER
MONSOON
Page 29 of 168
OUTDOOR
91.9
INDOOR
78.8
DIFFERENTIAL
13.1
OUTDOOR
87.1
INDOOR
78.8
DIFFERENTIAL
8.3
OUTDOOR
64.9
INDOOR
78.8
DIFFERENTIAL
-13.9
WALL
Wt. of Wall(lb/sq.ft)
ETD (deg.F)
N
100
4
-2.12
2
NE
100
10
-2.12
8
E
100
18
-2.12
16
SE
100
18
-2.12
16
S
100
16
-2.12
14
SW
100
14
-2.12
12
W
100
12
-2.12
10
NW
100
6
-2.12
4
ROOF
80
32
-2.12
30
WINTER
CORRECTION FACTOR SUMMER
NET ETD(deg.F)
Design Inside Condition: Temp (˚F):
78.8
RH (%):
50
Remarks
ISHRAE Handbook Table1.21/1.22/1.23
MONSOON N
100
4
-4.55
-1
NE
100
10
-4.55
5
SE
100
18
-4.55
13
E
100
18
-4.55
13
S
100
16
-4.55
11
SW
100
14
-4.55
9
W
100
12
-4.55
7
NW
100
6
-4.55
1
ROOF
80
32
-4.55
27
ISHRAE Handbook Table1.21/1.22/1.23
# Taken reference of Visakhapatnam
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 29 of 168
Page 29 of 82
HEAT LOAD ESTIMATION FOR VRMP Equivalent Temp. Difference Calculations HVAC Contractor- Advance Ventilation Pvt. Ltd. Daily Range in deg.F
Summer (˚F)= 20.52
Monsoon (˚F)= 15.66
Project: Vizag Refinery Modernization Project DBT in deg.F SUMMER
91.9
INDOOR
75.2
DIFFERENTIAL
16.7
INDOOR
75.2
Design Inside Condition: Temp (˚F):
DIFFERENTIAL
11.9
RH (%):
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10.3
WALL
Wt. of Wall(lb/sq.ft)
ETD (deg.F)
N
100
4
1.48
5
NE
100
10
1.48
11
E
100
18
1.48
19
SE
100
18
1.48
19
S
100
16
1.48
17
SW
100
14
1.48
15
W
100
12
1.48
13
NW
100
6
1.48
7
ROOF
80
32
1.48
33
MONSOON
Page 30 of 168
OUTDOOR
WINTER
OUTDOOR
87.1
CORRECTION FACTOR SUMMER
NET ETD(deg.F)
75.2 50
Remarks
ISHRAE Handbook Table1.21/1.22/1.23
MONSOON N
100
4
-0.95
3
NE
100
10
-0.95
9
SE
100
18
-0.95
17
E
100
18
-0.95
17
S
100
16
-0.95
15
SW
100
14
-0.95
13
W
100
12
-0.95
11
NW
100
6
-0.95
5
ROOF
80
32
-0.95
31
ISHRAE Handbook Table1.21/1.22/1.23
# Taken reference of Visakhapatnam
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 30 of 168
Page 30 of 82
Page 31 of 168
HEAT LOAD ESTIMATION FOR VRMP
3.2 HEAT GAIN FROM PEOPLE
From ISHRAE HVAC data book Table- 1.24
Degree of activity
Typical application
Office worker
Office, Hotels, Apts., college Dept. Retail or Variety Store
Standing, walking slowly
Room Dry-bulb temperature (75 deg.F)
Metabolic rate(adult male Btu/hr) 475
Btu/hr Sensible
Btu/hr Latent
550
245
205
SOLAR HEAT GAIN FACTOR (Btu/Hr)(Sq.ft ) AT 200 EXPOSURE
SUMMER (MAY21) At 4pm*
MONSOON (AUG 24) At 4pm*
NORTH
23
11
NORTH EAST
12
11
EAST
12
11
SOUTH EAST
12
11
SOUTH
12
11
SOUTH WEST
85
113
WEST
163
165
NORTH WEST
138
118
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 31 of 168
Page 31 of 82
08-NOV-2019
Page 32 of 82
08-NOV-2019
Page 33 of 82
08-NOV-2019
Page 34 of 82
Page 35 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-4 HEAT LOAD CALCULATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 35 of 168
Page 35 of 82
Page 36 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.1.1 SUMMARY SHEET FOR SUBSTATION 86-CT BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 36 of 168
Page 36 of 82
Page 37 of 168
PROJECT : VIZAG REFINERY MODERNIZATION PROJECT OWNER : HINDUSTAN PETROLEUM CORPORATION LIMITED
CONSULTANT: ENGINEERS INDIA LIMITED
SUMMARY SHEET FOR SUBSTATION SS-86 (COOLING TOWER) BUILDING
Date: 03.10.19
J9
B15
B18
I108
I107
I109
Winter Load ( KW)
I110
Monsoon Heating ( KW )
I111
78.8 78.8 78.8 78.8
50.0 50.0 50.0 50.0
2.0 2.0 1.5 0.0
5605 590 120 0
21980 544 288 0
74.39 4.29 1.30 1.37
-11.16 -7.04 -0.68 0.00
11.39 1.18 0.21 0.00
-17.08 -1.80 -0.37 0.00
112000.00
4.00
6316
22812
81.35
-18.87
12.78
-19.25
44000 9000 1000 1000 0 0 0 55000.00
3.0 0.0 4.0 3.0 0.0 0.0 0.0 10.00
1038 346 487 249 326 158 0 2603
9033 2034 918 632 562 348 0 13526
23.73 5.92 4.71 2.70 3.03 1.62 1.55 43.27
6.96 -0.33 -5.97 -2.91 -4.68 -2.35 0.00 -9.29
2.66 0.99 0.70 0.58 0.74 0.35 0.00 6.02
-3.16 -1.05 -1.48 -0.76 -0.99 -0.48 0.00 -7.93
167000.00
14.00
8919
36338
124.62
-28.16
18.80
-27.18
SUBTOTAL(A) SECOND FLOOR RACK ROOM UPS ROOM TECH ROOM ENGINEER ROOM LOBBY 1 LOBBY 2 AHU ROOM SF SUBTOTAL(B)
5 6 7 8 9 10 11
TOTAL(A+B)
14020.92 78.85 39.36 38.69 18.93 99.29 19.84 39.41
55.89 36.87 41.07 55.89 15.81 48.45 41.07
4221.16 1404.61 1542.25 1011.29 1569.72 961.35 1571.88 12282.25 26303.17
9.84 9.84 12.63 9.84 12.46 9.84 19.96
08-NOV-2019 SUTHAR KETANBHAI (C360) 37 of 168
Page 37 of 82
78.8 78.8 78.8 78.8 78.8 78.8 78.8
50.0 50.0 50.0 50.0 50.0 50.0 50.0
1.5 1.5 1.5 1.5 1.0 1.0 0.0
Humidifier ( Kw)
H9
0.0 0.0 4.0 0.0
Unit Ref. Load
B58
Dehumidified Unit CFM
Fresh air ACPH
B59 111000 0 1000 0
fresh air CFM
Room Design RH in %age
D11 14.76 22.25 14.76 18.97
Room Design Temp. in deg. F
B12 11391.97 795.63 326.46 1506.85
Height ( Ft )
C11 50.59 20.57 16.73 38.61
Floor Area(sqft)
B11 218.42 38.69 19.52 39.03
Width(Ft)
Occup. (Persons)
B10 FIRST FLOOR SWITCHGEAR HALL SWITCHGEAR HALL GIS PANELS OPERATOR ROOM AHU ROOM FF
Eqip. Load(W)
1 2 3 4
Length(Ft)
S.no
Area Description
Rev. 00
Page 38 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.1.2 CALCULATION SHEET FOR SUBSTATION 86-CT BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 38 of 168
Page 38 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
SWITCHGEAR HALL
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
218.42
50.59
14.76
MONSOON
DESIGN CONDITIONS
ROOM AREA
11391.97 Sq.ft
INDOOR
ROOM VOLUME
168145.44 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
2.00
17.00
cfm/per
5604.85
Cfm @ AC/Hr
0.00
Cfm @ Occup
FRESH AIR
5604.85 Cfm Selected
GLASS AREA
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
73.7 -17
BF
0.12 Occupant Heat
Sens
245.00
1-BF
0.88
Lat
205.00
N
NE
E
SE
S
SW
W
NW
8.53
0.00
0.00
0.00
8.53
0.00
0.00
0.00
H
1.97
0.00
0.00
0.00
1.97
0.00
0.00
0.00
QTY
Gr/LB 150.0
50.0
L
All Glass 67.13
2.00
0.00
0.00
0.00
2.00
0.00
0.00
0.00
33.57
0.00
0.00
0.00
33.57
0.00
0.00
0.00
Partition
L
156.62
0.00
0.00
0.00
138.74
0.00
0.00
0.00
177.12
H
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
0.00
0.00
0.00
2014.30
0.00
0.00
0.00
2614.29
AREA WALL AREA
WINTER
RH
1
NETT AREA 2278.14
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
34
1.00
23
11
0
772
369
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
34
1.00
12
11
0
403
369
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
N
S
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
2278
0.36
2
-1
-14
1542
-451
-11367
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
2014
0.36
14
11
-14
10065
8303
-10051
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
S
Trans. Gain-Except Wall & Roof All Glass
67
1.13
13
8
-14
997
628
-1051
Partition
2614
0.32
8
3
-9
6810
2744
-7412
Ceiling
2028
0.29
8
3
-9
4788
1929
-5212
11392
0.36
8
3
-9
33383
13452
-36336
Floor
Internal Heat Occupants (Nos.)
0
245
0
0
0
Power (W)
111000
3.40
377400
377400
188700
Lights (W)
5294
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 39 of 168
17998
17998
8999
454158
422742
126270
510928
475585
126270
9545
6014
-10068
520473
481599
116203
12.5%
08-NOV-2019
5604.85
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 39 of 168
Page 39 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
5604.85
0.12
76
85
-17
0.68
0
0
0
34896
38738
-7912
ERLH
34896
38738
-7912
ERTH
555369
520337
108290
Outdoor Air(S)
5604.85
0.88
13
8
-14
1.08
69995
44106
Outdoor Air(Lt)
5604.85
0.88
76
85
-17
0.68
255906
284079
-58023
GTH
881269
848522
-23563
Refrigeration Load
881269
848522
-23563
Monsoon Reheat
-73830
38873
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
9241
5328
890511
892724
74.21
74.39
Winter KW
-14485
-11.16
Monsoon Heaters (KW)
11.39
ESHF =(ERSH/ERTH)
0.94
0.93
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
21980
20433
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-17.08
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-27.84
Final Values: Selected Load (TR)
74.39
Selected Airquantity (CFM)
21980.31
Winter Load (KW)
-11.16
Monsoon Heating (KW)
11.39
Humidifier (KW)
-17.08
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
156.62
0.00
0.00
0.00
138.74
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
1148.15
0.00
0.00
0.00
1017.10
0.00
0.00
0.00
1298.43
NET AREA
Partition 177.12
Solar & Trans. Gain-Wall & Roof N
1148
0.36
2
-1
-14
777
-227
-5729
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
1017
0.36
14
11
-14
5082
4193
-5075
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
1298
0.32
8
3
-9
3382
1363
-3681
S
08-NOV-2019
Return Air Heat Load Gain
Page 40 of 168
9241
SUTHAR KETANBHAI (C360) 40 of 168
Page 40 of 82
5328
-14485
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL GIS PANELS
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
SWITCHGEAR HALL GIS PANELS
DIFFERENTIAL
13.1
OUTDOOR
87.1
INDOOR
78.8
ROOM SIZE
38.69
ROOM AREA
795.63
ROOM VOLUME
20.57
22.25
MONSOON
Sq.ft
17706.67 Cu.ft
OCCUPANCY
0.00
AIR CHANGES
2.00
17.00
DESIGN CONDITIONS
DIFFERENTIAL cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
590.22
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
590.22
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
8.53
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
1.97
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
67.13
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
38.69
0.00
0.00
0.00
20.57
H
22.25
22.25
22.25
22.25
22.25
22.25
22.25
22.25
22.25
NETT AREA
0.00
0.00
0.00
0.00
793.85
0.00
0.00
0.00
457.68
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
67
1.00
12
11
0
806
738
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
S
B.Th.U/Hr/Sq.ft.
67.13
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
794
0.36
14
11
-14
3967
3272
-3961
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
S
Trans. Gain-Except Wall & Roof All Glass
67
1.13
13
8
-14
997
628
-1051
Partition
458
0.32
8
3
-9
1192
480
-1298
0
0.29
8
3
-9
0
0
0
796
0.36
8
3
-9
2332
939
-2538
0
Ceiling Floor
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
370
3.40
1257
1257
629
10550
7316
-8219
11869
8230
-8219
1005
633
-1060
12874
8864
-9279
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 41 of 168
12.5%
08-NOV-2019
590.22
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 41 of 168
Page 41 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL GIS PANELS Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
590.22
0.12
76
85
-17
0.68
0
0
0
3675
4079
-833
ERLH
3675
4079
-833
ERTH
16548
12943
-10113
Outdoor Air(S)
590.22
0.88
13
8
-14
1.08
7371
4645
Outdoor Air(Lt)
590.22
0.88
76
85
-17
0.68
26948
29915
-6110
GTH
50868
47503
-23998
Refrigeration Load
50868
47503
-23998
Monsoon Reheat
-7775
4010
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
50868
51513
4.24
4.29
0
Winter KW
-7.04
Monsoon Heaters (KW)
1.18
ESHF =(ERSH/ERTH)
0.78
0.68
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
544
376
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-1.80
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-2.93
Final Values: Selected Load (TR)
4.29
Selected Airquantity (CFM)
543.67
Winter Load (KW)
-7.04
Monsoon Heating (KW)
1.18
Humidifier (KW)
-1.80
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
38.69
0.00
0.00
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
20.57
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 42 of 168
0
SUTHAR KETANBHAI (C360) 42 of 168
Page 42 of 82
0 0
0
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT OPERATOR ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
OPERATOR ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
19.52
16.73
14.76
MONSOON
DESIGN CONDITIONS
ROOM AREA
326.46
Sq.ft
INDOOR
ROOM VOLUME
4818.60
Cu.ft
DIFFERENTIAL
OCCUPANCY
4.00
AIR CHANGES
1.50
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
120.47
Cfm @ AC/Hr
68.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
120.47
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
NETT AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Partition
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Trans. Gain-Except Wall & Roof All Glass
0
1.13
13
8
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
326
0.36
8
3
-9
957
385
-1041
Floor
Internal Heat Occupants (Nos.)
4
245
980
980
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
152
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 43 of 168
516
516
258
5852
5281
917
6584
5941
917
205
129
-216
6789
6071
700
12.5%
08-NOV-2019
120.47
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 43 of 168
Page 43 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT OPERATOR ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
820
820
0
820
820
0
902
902
0
750
833
-170
ERLH
1652
1735
-170
ERTH
8441
7805
530
Latent Heat Occupants(Nos.)
4.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
120.47
0.12
76
85
-17
0.68
Outdoor Air(S)
120.47
0.88
13
8
-14
1.08
1504
948
Outdoor Air(Lt)
120.47
0.88
76
85
-17
0.68
5500
6106
-1247
GTH
15446
14859
-2304
Refrigeration Load
15446
14859
-2304
Monsoon Reheat
-1587
718
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
15446
15577
1.29
1.30
0
Winter KW
-0.68
Monsoon Heaters (KW)
0.21
ESHF =(ERSH/ERTH)
0.80
0.78
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
288
258
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.37
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.60
Final Values: Selected Load (TR)
1.30
Selected Airquantity (CFM)
288.04
Winter Load (KW)
-0.68
Monsoon Heating (KW)
0.21
Humidifier (KW)
-0.37
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 44 of 168
0
SUTHAR KETANBHAI (C360) 44 of 168
Page 44 of 82
0 0
0
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT AHU ROOM FF
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
AHU ROOM FF
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
39.03
38.61
18.97
MONSOON
DESIGN CONDITIONS
ROOM AREA
1506.85 Sq.ft
INDOOR
ROOM VOLUME
28592.25 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
0.00
FRESH AIR
17.00
cfm/per
WINTER
RH
1 Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
0.00
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
0.00
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
8.53
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
1.97
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
67.13
0.00
0.00
0.00
L
0.00
0.00
0.00
0.00
39.03
0.00
38.61
0.00
0.00
H
18.97
18.97
18.97
18.97
18.97
18.97
18.97
18.97
18.97
NETT AREA
0.00
0.00
0.00
0.00
673.49
0.00
732.53
0.00
0.00
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
67
1.00
12
11
0
806
738
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
S
B.Th.U/Hr/Sq.ft.
67.13
Partition
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
673
0.36
14
11
-14
3365
2776
-3360
S SW
0
0.36
12
9
-14
0
0
0
733
0.36
10
7
-14
2605
1965
-3655
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
W
Trans. Gain-Except Wall & Roof All Glass
67
1.13
13
8
-14
997
628
-1051
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
1507
0.36
8
3
-9
4416
1779
-4806
0
Floor
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
700
3.40
2381
2381
1190
14570
10267
-11683
16391
11551
-11683
0
0
0
16391
11551
-11683
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 45 of 168
12.5%
08-NOV-2019
0.00
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 45 of 168
Page 45 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT AHU ROOM FF Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
0
0
0
0
0
0
ERLH
0
0
0
ERTH
16391
11551
-11683
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
0.00
0.12
76
85
-17
0.68
Outdoor Air(S)
0.00
0.88
13
8
-14
1.08
0
0
Outdoor Air(Lt)
0.00
0.88
76
85
-17
0.68
0
0
0
GTH
16391
11551
-11683
Refrigeration Load
16391
11551
-11683
Monsoon Reheat
0
4840
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
16391
16391
1.37
1.37
0
Winter KW
0.00
Monsoon Heaters (KW)
0.00
ESHF =(ERSH/ERTH)
1.00
1.00
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
0
0
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
0.00
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
0.00
Final Values: Selected Load (TR)
1.37
Selected Airquantity (CFM)
0.00
Winter Load (KW)
0.00
Monsoon Heating (KW)
0.00
Humidifier (KW)
0.00
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
39.03
0.00
38.61
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 46 of 168
0
SUTHAR KETANBHAI (C360) 46 of 168
Page 46 of 82
0 0
0
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT RACK ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
RACK ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
78.85
55.89
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
4221.16 Sq.ft
INDOOR
ROOM VOLUME
41536.17 Cu.ft
DIFFERENTIAL
OCCUPANCY
3.00
AIR CHANGES
1.50
17.00
cfm/per
1038.40
Cfm @ AC/Hr
51.00
Cfm @ Occup
FRESH AIR
1038.40 Cfm Selected
GLASS AREA
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
73.7 -17
BF
0.12 Occupant Heat
Sens
245.00
1-BF
0.88
Lat
205.00
N
NE
E
SE
S
SW
W
NW
3.94
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
5.90
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
Gr/LB 150.0
50.0
L
All Glass 371.81
8.00
0.00
0.00
0.00
8.00
0.00
0.00
0.00
185.91
0.00
0.00
0.00
185.91
0.00
0.00
0.00
Partition
L
78.85
0.00
0.00
0.00
78.85
0.00
0.00
0.00
55.89
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
0.00
0.00
0.00
589.99
0.00
0.00
0.00
549.97
AREA WALL AREA
WINTER
RH
1
NETT AREA 589.99
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
186
1.00
23
11
0
4276
2045
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
186
1.00
12
11
0
2231
2045
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
N
S
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
590
0.36
2
-1
-14
399
-117
-2944
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
590
0.36
14
11
-14
2948
2432
-2944
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
4221
0.11
30
27
-14
13874
12746
-6436
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
372
1.13
13
8
-14
5521
3479
-5823
Partition
550
0.32
8
3
-9
1433
577
-1559
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
3
245
735
735
0
Power (W)
44000
3.40
149600
149600
74800
Lights (W)
1962
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 47 of 168
6669
6669
3335
187686
180211
58429
211146
202737
58429
1768
1114
-1865
212915
203852
56564
12.5%
08-NOV-2019
1038.40
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 47 of 168
Page 47 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT RACK ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
615
615
0
615
615
0
Latent Heat Occupants(Nos.)
3.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
1038.40
0.12
76
85
-17
0.68
677
677
0
6465
7177
-1466
ERLH
7142
7853
-1466
ERTH
220056
211705
55098
Outdoor Air(S)
1038.40
0.88
13
8
-14
1.08
12968
8172
-13678
Outdoor Air(Lt)
1038.40
0.88
76
85
-17
0.68
47411
52631
-10750
GTH
280435
272508
30669
Refrigeration Load
280435
272508
30669
Monsoon Reheat
9063
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
4347
2698
284782
284269
23.73
23.69
-6930
Winter KW
6.96
Monsoon Heaters (KW)
2.66
ESHF =(ERSH/ERTH)
0.97
0.96
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
CFM Dehum ={(ERSH)/(1.08*Deh Rise)}
9033
8649
Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-3.16
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-5.16
Final Values: Selected Load (TR)
23.73
Selected Airquantity (CFM)
9033.32
Winter Load (KW)
6.96
Monsoon Heating (KW)
2.66
Humidifier (KW)
-3.16
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
78.85
0.00
0.00
0.00
78.85
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
578.04
0.00
0.00
0.00
578.04
0.00
0.00
0.00
409.73
NET AREA
Partition 55.89
Solar & Trans. Gain-Wall & Roof N
578
0.36
2
-1
-14
391
-114
-2884
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
578
0.36
14
11
-14
2888
2383
-2884
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
410
0.32
8
3
-9
1067
430
-1162
S
08-NOV-2019
Return Air Heat Load Gain
Page 48 of 168
4347
SUTHAR KETANBHAI (C360) 48 of 168
Page 48 of 82
2698
-6930
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT UPS ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
ROOM NAME
UPS ROOM
DIFFERENTIAL
13.1
ROOM SIZE
39.36
OUTDOOR
87.1 78.8
36.87
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
1404.61 Sq.ft
INDOOR
ROOM VOLUME
13821.36 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
1.50
WALL AREA
cfm/per
WINTER
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
345.53
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
N
NE
E
SE
S
SW
W
NW
L
3.94
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
5.90
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
Gr/LB 150.0
50.0
345.53 FRESH AIR
GLASS AREA
17.00
RH
1
All Glass 92.95
4.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
92.95
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
39.36
0.00
0.00
0.00
0.00
0.00
0.00
0.00
36.87
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
0.00
0.00
0.00
0.00
0.00
0.00
0.00
362.77
NETT AREA 294.35
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
93
1.00
23
11
0
2138
1022
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
N
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
294
0.36
2
-1
-14
199
-58
-1469
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1405
0.11
30
27
-14
4617
4241
-2141
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
363
0.32
8
3
-9
945
381
-1029
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
0
Power (W)
9000
3.40
30600
30600
15300
Lights (W)
653
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 49 of 168
2219
2219
1110
42098
39275
10315
47360
44184
10315
588
371
-621
47949
44555
9694
12.5%
08-NOV-2019
345.53
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 49 of 168
Page 49 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT UPS ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
345.53
0.12
76
85
-17
0.68
0
0
0
2151
2388
-488
ERLH
2151
2388
-488
ERTH
50100
46943
9207
Outdoor Air(S)
345.53
0.88
13
8
-14
1.08
4315
2719
-4552
Outdoor Air(Lt)
345.53
0.88
76
85
-17
0.68
15776
17513
-3577
GTH
70192
67176
1078
Refrigeration Load
70192
67176
1078
Monsoon Reheat
3394
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
899
227
71091
70796
5.92
5.90
-2206
Winter KW
-0.33
Monsoon Heaters (KW)
0.99
ESHF =(ERSH/ERTH)
0.96
0.95
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
CFM Dehum ={(ERSH)/(1.08*Deh Rise)}
2034
1890
Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-1.05
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-1.72
Final Values: Selected Load (TR)
5.92
Selected Airquantity (CFM)
2034.32
Winter Load (KW)
-0.33
Monsoon Heating (KW)
0.99
Humidifier (KW)
-1.05
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
39.36
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
288.54
0.00
0.00
0.00
0.00
0.00
0.00
0.00
270.27
NET AREA
Partition 36.87
Solar & Trans. Gain-Wall & Roof N
289
0.36
2
-1
-14
195
-57
-1440
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
270
0.32
8
3
-9
704
284
-766
08-NOV-2019
Return Air Heat Load Gain
Page 50 of 168
899
SUTHAR KETANBHAI (C360) 50 of 168
Page 50 of 82
227
-2206
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT TECH ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
TECH ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
38.69
41.07
12.63
MONSOON
DESIGN CONDITIONS
ROOM AREA
1542.25 Sq.ft
INDOOR
ROOM VOLUME
19475.49 Cu.ft
DIFFERENTIAL
OCCUPANCY
4.00
AIR CHANGES
1.50
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
486.89
Cfm @ AC/Hr
68.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
486.89
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
92.95
0.00
0.00
0.00
Partition
L
0.00
0.00
24.88
0.00
38.69
0.00
0.00
0.00
10.40
H
12.63
12.63
12.63
12.63
12.63
12.63
12.63
12.63
12.63
NETT AREA
0.00
0.00
314.17
0.00
395.59
0.00
0.00
0.00
131.30
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
93
1.00
12
11
0
1115
1022
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0 0
GLASS AREA
WALL AREA
Solar Gain - Glass
S
B.Th.U/Hr/Sq.ft.
92.95
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
NE
0
0.36
8
5
-14
0
0
0
314
0.36
16
13
-14
1796
1521
-1568
E SE
0
0.36
16
13
-14
0
0
0
396
0.36
14
11
-14
1977
1631
-1974
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1542
0.11
30
27
-14
5069
4657
-2351
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
131
0.32
8
3
-9
342
138
-372
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
4
245
980
980
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
717
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 51 of 168
2437
2437
1218
18496
16655
-4802
20808
18737
-4802
829
522
-875
21637
19260
-5677
12.5%
08-NOV-2019
486.89
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 51 of 168
Page 51 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT TECH ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
820
820
0
820
820
0
Latent Heat Occupants(Nos.)
4.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
486.89
0.12
76
85
-17
0.68
902
902
0
3031
3365
-687
ERLH
3933
4267
-687
ERTH
25571
23527
-6364
Outdoor Air(S)
486.89
0.88
13
8
-14
1.08
6080
3831
Outdoor Air(Lt)
486.89
0.88
76
85
-17
0.68
22230
24678
-5040
GTH
53881
52036
-17818
Refrigeration Load
53881
52036
-17818
Monsoon Reheat
-6414
2378
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
2658
2132
56540
56546
4.71
4.71
-2541
Winter KW
-5.97
Monsoon Heaters (KW)
0.70
ESHF =(ERSH/ERTH)
0.85
0.82
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
918
817
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-1.48
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-2.42
Final Values: Selected Load (TR)
4.71
Selected Airquantity (CFM)
918.00
Winter Load (KW)
-5.97
Monsoon Heating (KW)
0.70
Humidifier (KW)
-1.48
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
24.88
0.00
38.69
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
182.38
0.00
283.61
0.00
0.00
0.00
76.22
10.40
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
NE
0
0.36
8
5
-14
0
0
0
182
0.36
16
13
-14
1043
883
-910
E SE
0
0
0.36
16
13
-14
0
0
0
284
0.36
14
11
-14
1417
1169
-1415
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
76
0.32
8
3
-9
199
80
-216
S
08-NOV-2019
Return Air Heat Load Gain
Page 52 of 168
2658
SUTHAR KETANBHAI (C360) 52 of 168
Page 52 of 82
2132
-2541
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT ENGINEER ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
ENGINEER ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
18.93
55.89
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
1011.29 Sq.ft
INDOOR
ROOM VOLUME
9951.11
DIFFERENTIAL
OCCUPANCY
3.00
AIR CHANGES
1.50
WALL AREA
17.00
cfm/per
WINTER
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
Cfm @ AC/Hr
51.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
248.78
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
N
NE
E
SE
S
SW
W
NW
L
3.94
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
5.90
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
Gr/LB 150.0
50.0
248.78 FRESH AIR
GLASS AREA
Cu.ft
RH
1
All Glass 92.95
2.00
0.00
0.00
0.00
2.00
0.00
0.00
0.00
AREA
46.48
0.00
0.00
0.00
46.48
0.00
0.00
0.00
Partition
L
18.93
0.00
0.00
0.00
18.93
0.00
0.00
0.00
0.00
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
0.00
0.00
0.00
139.75
0.00
0.00
0.00
0.00
NETT AREA 139.75
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
46
1.00
23
11
0
1069
511
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
46
1.00
12
11
0
558
511
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
N
S
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
140
0.36
2
-1
-14
95
-28
-697
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
140
0.36
14
11
-14
698
576
-697
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1011
0.11
30
27
-14
3324
3054
-1542
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
3
245
735
735
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
470
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 53 of 168
1598
1598
799
12856
11227
-1893
14463
12630
-1893
424
267
-447
14887
12897
-2340
12.5%
08-NOV-2019
248.78
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 53 of 168
Page 53 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT ENGINEER ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
615
615
0
615
615
0
Latent Heat Occupants(Nos.)
3.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
248.78
0.12
76
85
-17
0.68
677
677
0
1549
1719
-351
ERLH
2225
2396
-351
ERTH
17113
15293
-2691
Outdoor Air(S)
248.78
0.88
13
8
-14
1.08
3107
1958
Outdoor Air(Lt)
248.78
0.88
76
85
-17
0.68
11359
12609
-2575
GTH
31578
29860
-8544
Refrigeration Load
31578
29860
-8544
Monsoon Reheat
-3277
1990
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
787
544
32365
32394
2.70
2.70
-1385
Winter KW
-2.91
Monsoon Heaters (KW)
0.58
ESHF =(ERSH/ERTH)
0.87
0.84
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
632
547
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.76
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-1.24
Final Values: Selected Load (TR)
2.70
Selected Airquantity (CFM)
631.62
Winter Load (KW)
-2.91
Monsoon Heating (KW)
0.58
Humidifier (KW)
-0.76
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
18.93
0.00
0.00
0.00
18.93
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
138.74
0.00
0.00
0.00
138.74
0.00
0.00
0.00
0.00
NET AREA
Partition 0.00
Solar & Trans. Gain-Wall & Roof N
139
0.36
2
-1
-14
94
-27
-692
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
139
0.36
14
11
-14
693
572
-692
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
S
08-NOV-2019
Return Air Heat Load Gain
Page 54 of 168
787
SUTHAR KETANBHAI (C360) 54 of 168
Page 54 of 82
0 544
-1385
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT LOBBY 1
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
LOBBY 1
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
99.29
15.81
12.46
MONSOON
DESIGN CONDITIONS
ROOM AREA
1569.72 Sq.ft
INDOOR
ROOM VOLUME
19564.96 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
1.00
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
326.08
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
326.08
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
19.68
0.00
0.00
0.00
74.10
H
12.46
12.46
12.46
12.46
12.46
12.46
12.46
12.46
12.46
NETT AREA
0.00
0.00
0.00
0.00
245.29
0.00
0.00
0.00
923.52
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
245
0.36
14
11
-14
1226
1011
-1224
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1570
0.11
30
27
-14
5159
4740
-2393
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
0
1.13
13
8
-14
0
0
0
Partition
924
0.32
8
3
-9
2406
969
-2618
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
729
3.40
2480
2480
1240
11271
9200
-4995
12679
10350
-4995
555
350
-586
13235
10700
-5581
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 55 of 168
12.5%
08-NOV-2019
326.08
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 55 of 168
Page 55 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT LOBBY 1 Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
326.08
0.12
76
85
-17
0.68
0
0
0
2030
2254
-460
ERLH
2030
2254
-460
ERTH
15265
12954
-6042
Outdoor Air(S)
326.08
0.88
13
8
-14
1.08
4072
2566
Outdoor Air(Lt)
326.08
0.88
76
85
-17
0.68
14888
16527
-3376
GTH
34225
32047
-13713
Refrigeration Load
34225
32047
-13713
Monsoon Reheat
-4295
2535
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
2136
1165
36361
35747
3.03
2.98
-2260
Winter KW
-4.68
Monsoon Heaters (KW)
0.74
ESHF =(ERSH/ERTH)
0.87
0.83
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
562
454
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.99
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-1.62
Final Values: Selected Load (TR)
3.03
Selected Airquantity (CFM)
561.51
Winter Load (KW)
-4.68
Monsoon Heating (KW)
0.74
Humidifier (KW)
-0.99
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
19.68
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
0.00
0.00
144.27
0.00
0.00
0.00
543.18
74.10
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
144
0.36
14
11
-14
721
595
-720
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
543
0.32
8
3
-9
1415
570
-1540
S
08-NOV-2019
Return Air Heat Load Gain
Page 56 of 168
2136
SUTHAR KETANBHAI (C360) 56 of 168
Page 56 of 82
1165
-2260
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT LOBBY 2
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
LOBBY 2
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
19.84
48.45
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
961.35
Sq.ft
INDOOR
ROOM VOLUME
9459.73
Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
1.00
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
157.66
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
157.66
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
4.92
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
8.20
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
1.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
40.34
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
19.84
0.00
0.00
0.00
19.84
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
NETT AREA
0.00
0.00
0.00
0.00
154.92
0.00
0.00
0.00
195.26
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
40
1.00
12
11
0
484
444
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
S
B.Th.U/Hr/Sq.ft.
40.34
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
155
0.36
14
11
-14
774
639
-773
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
961
0.11
30
27
-14
3160
2903
-1466
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
40
1.13
13
8
-14
599
377
-632
Partition
195
0.32
8
3
-9
509
205
-554
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
447
3.40
1519
1519
759
7045
6086
-2665
7925
6847
-2665
268
169
-283
8194
7016
-2948
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 57 of 168
12.5%
08-NOV-2019
157.66
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 57 of 168
Page 57 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT LOBBY 2 Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH
0
0
0
982
1090
-223
ERLH
982
1090
-223
ERTH
9175
8106
-3170
Outdoor Air
157.66
0.12
76
85
-17
0.68
Outdoor Air(S)
157.66
0.88
13
8
-14
1.08
1969
1241
Outdoor Air(Lt)
157.66
0.88
76
85
-17
0.68
7199
7991
-1632
GTH
18343
17338
-6879
Refrigeration Load
18343
17338
-6879
Monsoon Reheat
-2077
1177
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
1106
752
19448
19267
1.62
1.61
-1138
Winter KW
-2.35
Monsoon Heaters (KW)
0.35
ESHF =(ERSH/ERTH)
0.89
0.87
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
348
298
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.48
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.78
Final Values: Selected Load (TR)
1.62
Selected Airquantity (CFM)
347.63
Winter Load (KW)
-2.35
Monsoon Heating (KW)
0.35
Humidifier (KW)
-0.48
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
19.84
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
0.00
0.00
145.47
0.00
0.00
0.00
145.47
19.84
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
145
0.36
14
11
-14
727
600
-726
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
145
0.32
8
3
-9
379
153
-412
S
08-NOV-2019
Return Air Heat Load Gain
Page 58 of 168
1106
SUTHAR KETANBHAI (C360) 58 of 168
Page 58 of 82
752
-1138
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT AHU ROOM SF
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
AHU ROOM SF
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
39.41
41.07
19.96
MONSOON
DESIGN CONDITIONS
ROOM AREA
1571.88 Sq.ft
INDOOR
ROOM VOLUME
31372.82 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
0.00
FRESH AIR
17.00
cfm/per
WINTER
RH
1 Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
0.00
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
0.00
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
92.95
0.00
0.00
0.00
L
0.00
0.00
0.00
0.00
39.41
0.00
41.07
0.00
0.00
H
19.96
19.96
19.96
19.96
19.96
19.96
19.96
19.96
19.96
NETT AREA
0.00
0.00
0.00
0.00
693.61
0.00
819.62
0.00
0.00
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
93
1.00
12
11
0
1115
1022
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
S
B.Th.U/Hr/Sq.ft.
92.95
Partition
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
694
0.36
14
11
-14
3466
2859
-3461
S SW W NW Roof Sun
0
0.36
12
9
-14
0
0
0
820
0.36
10
7
-14
2915
2198
-4090
0
0.36
4
1
-14
0
0
0
1572
0.11
30
27
-14
5166
4746
-2396
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
730
3.40
2483
2483
1242
16527
14179
-10161
18592
15952
-10161
0
0
0
18592
15952
-10161
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 59 of 168
12.5%
08-NOV-2019
0.00
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 59 of 168
Page 59 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT AHU ROOM SF Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
0
0
0
0
0
0
ERLH
0
0
0
ERTH
18592
15952
-10161
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
0.00
0.12
76
85
-17
0.68
Outdoor Air(S)
0.00
0.88
13
8
-14
1.08
0
0
Outdoor Air(Lt)
0.00
0.88
76
85
-17
0.68
0
0
0
GTH
18592
15952
-10161
Refrigeration Load
18592
15952
-10161
Monsoon Reheat
0
2641
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
18592
18592
1.55
1.55
0
Winter KW
0.00
Monsoon Heaters (KW)
0.00
ESHF =(ERSH/ERTH)
1.00
1.00
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
0
0
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
0.00
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
0.00
Final Values: Selected Load (TR)
1.55
Selected Airquantity (CFM)
0.00
Winter Load (KW)
0.00
Monsoon Heating (KW)
0.00
Humidifier (KW)
0.00
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
39.41
0.00
41.07
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 60 of 168
0
SUTHAR KETANBHAI (C360) 60 of 168
Page 60 of 82
0 0
0
Page 61 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.2.1 SUMMARY SHEET FOR NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 61 of 168
Page 61 of 82
Page 62 of 168
PROJECT : VIZAG REFINERY MODERNIZATION PROJECT OWNER : HINDUSTAN PETROLEUM CORPORATION LIMITED
CONSULTANT: ENGINEERS INDIA LIMITED
SUMMARY SHEET FOR NHT CCR FIELD ROOM BUILDING
Date: 03.10.2019
B18
1.0 1.0 0.0
102.00 102.00 0.00 204.00
08-NOV-2019 SUTHAR KETANBHAI (C360) 62 of 168
Page 62 of 82
I110
I111
-1.34 -1.06 -0.74 -3.15
0.43 0.27 0.35 1.05
-0.16 -0.16 0.00 -0.32
I108
I107
I109
826 326 302 1454.30
2.22 1.32 0.48 4.03
Humidifier ( Kw)
B15
50.0 50.0 50.0
Monsoon Heating ( KW )
J9
75.2 75.2 75.2
Winter Load ( KW)
H9
6.0 6.0 0.0 12.00
Unit Ref. Load
B58
Dehumidified Unit CFM
Fresh air ACPH
B59 1000 0 0 1000.00
fresh air CFM
Room Design RH in %age
D11 9.84 9.84 14.60
Room Design Temp. in deg. F
B12 621.83 264.15 164.60 1050.58
Height ( Ft )
C11 27.80 18.86 11.81
Floor Area(sqft)
B11 22.37 14.01 13.94
Width(Ft)
Occup. (Persons)
1 2 3
Length(Ft)
B10 SHIFT INCHARGE ROOM DINING ROOM PACKAGE AC ROOM TOTAL
S.no
Eqip. Load(W)
Area Description
Rev. 00
Page 63 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.2.2 CALCULATION SHEET FOR NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 63 of 168
Page 63 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM SHIFT INCHARGE ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
NHT CCR FIELD ROOM
INDOOR
75.2
SHIFT INCHARGE ROOM
DIFFERENTIAL
16.7
OUTDOOR
87.1
ROOM SIZE
22.37
27.80
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
621.83
Sq.ft
INDOOR
75.2
ROOM VOLUME
6118.81
Cu.ft
DIFFERENTIAL
11.9
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10
OCCUPANCY
6.00
AIR CHANGES
1.00
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
65.3 84.7
82.0
158.4 50.0
65.3 93.1
57.0
56.4 50.0
101.98
Cfm @ AC/Hr
102.00
Cfm @ Occup
BF
0.17 Occupant Heat
Sens
245.00
102.00
Cfm Selected
1-BF
0.83
Lat
205.00
FRESH AIR
1
65.3 -9
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
27.80
0.00
22.37
0.00
0.00
0.00
30.57
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
NETT AREA
0.00
0.00
273.53
0.00
220.12
0.00
0.00
0.00
300.80
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0 0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
NE
0
0.48
11
9
-10
0
0
0
274
0.48
19
17
-10
2558
2239
-1347
E SE
0
0.48
19
17
-10
0
0
0
220
0.48
17
15
-10
1847
1590
-1084
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
622
0.11
33
31
-10
2290
2124
-702
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
0
1.13
17
12
-10
0
0
0
Partition
301
0.32
12
7
-5
1130
662
-506
Ceiling
0
0.29
12
7
-5
0
0
0
Floor
0
0.36
12
7
-5
0
0
0
Internal Heat Occupants (Nos.)
6
245
1470
1470
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
289
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 64 of 168
982
982
491
13677
12467
-1448
15387
14026
-1448
313
222
-192
15700
14248
-1640
12.5%
08-NOV-2019
102.00
0.17
17
12
-10
1.08
SUTHAR KETANBHAI (C360) 64 of 168
Page 64 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM SHIFT INCHARGE ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
1230
1230
0
1230
1230
0
1353
1353
0
999
1098
-105
Latent Heat Occupants(Nos.)
6.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
102.00
0.17
85
93
-9
0.68
ERLH
2352
2451
-105
ERTH
18052
16699
-1745
Outdoor Air(S)
102.00
0.83
17
12
-10
1.08
1531
1086
Outdoor Air(Lt)
102.00
0.83
85
93
-9
0.68
4876
5360
-512
GTH
24459
23145
-3196
Refrigeration Load
24459
23145
-3196
Monsoon Reheat
-938
1452
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
1983
2096
26441
26693
2.20
2.22
-1371
Winter KW
-1.34
Monsoon Heaters (KW)
0.43
ESHF =(ERSH/ERTH)
0.87
0.85
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
17.60
17.60
826
750
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.16
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.26
Final Values: Selected Load (TR)
2.22
Selected Airquantity (CFM)
826.17
Winter Load (KW)
-1.34
Monsoon Heating (KW)
0.43
Humidifier (KW)
-0.16
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
27.80
0.00
22.37
0.00
0.00
0.00
Partition
H
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
NET AREA
0.00
0.00
127.65
0.00
102.72
0.00
0.00
0.00
140.38
30.57
Solar & Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
NE
0
0.48
11
9
-10
0
0
0
128
0.48
19
17
-10
1194
1045
-629
E SE
0
0
0.48
19
17
-10
0
0
0
103
0.48
17
15
-10
862
742
-506
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
Roof Sun
0
0.11
33
31
-10
0
0
0
Partition
140
0.32
12
7
-5
527
309
-236
S
08-NOV-2019
Return Air Heat Load Gain
Page 65 of 168
2583
SUTHAR KETANBHAI (C360) 65 of 168
Page 65 of 82
2096
-1371
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM DINING ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
NHT CCR FIELD ROOM
INDOOR
75.2
DINING ROOM
DIFFERENTIAL
16.7
OUTDOOR
87.1
ROOM SIZE
14.01
18.86
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
264.15
Sq.ft
INDOOR
75.2
ROOM VOLUME
2599.19
Cu.ft
DIFFERENTIAL
11.9
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10
OCCUPANCY
6.00
AIR CHANGES
1.00
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
65.3 84.7
82.0
158.4 50.0
65.3 93.1
57.0
56.4 50.0
43.32
Cfm @ AC/Hr
102.00
Cfm @ Occup
BF
0.17 Occupant Heat
Sens
245.00
102.00
Cfm Selected
1-BF
0.83
Lat
205.00
FRESH AIR
1
65.3 -9
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
14.01
0.00
0.00
0.00
32.87
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
NETT AREA
0.00
0.00
0.00
0.00
137.82
0.00
0.00
0.00
323.40
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
138
0.48
17
15
-10
1156
996
-679
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
264
0.11
33
31
-10
973
902
-298
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
0
1.13
17
12
-10
0
0
0
Partition
323
0.32
12
7
-5
1215
712
-544
Ceiling
0
0.29
12
7
-5
0
0
0
Floor
0
0.36
12
7
-5
0
0
0
0
Internal Heat Occupants (Nos.)
6
245
1470
1470
Power (W)
0
3.40
0
0
0
Lights (W)
123
3.40
417
417
209
5231
4497
-1313
5885
5059
-1313
313
222
-192
6199
5282
-1505
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 66 of 168
12.5%
08-NOV-2019
102.00
0.17
17
12
-10
1.08
SUTHAR KETANBHAI (C360) 66 of 168
Page 66 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM DINING ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
1230
1230
0
1230
1230
0
1353
1353
0
999
1098
-105
ERLH
2352
2451
-105
ERTH
8551
7732
-1610
Latent Heat Occupants(Nos.)
6.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
102.00
0.17
85
93
-9
0.68
Outdoor Air(S)
102.00
0.83
17
12
-10
1.08
1531
1086
Outdoor Air(Lt)
102.00
0.83
85
93
-9
0.68
4876
5360
-512
GTH
14957
14178
-3060
Refrigeration Load
14957
14178
-3060
Monsoon Reheat
-938
917
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
707
797
15664
15892
1.31
1.32
-571
Winter KW
-1.06
Monsoon Heaters (KW)
0.27
ESHF =(ERSH/ERTH)
0.72
0.68
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
17.60
17.60
326
278
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.16
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.26
Final Values: Selected Load (TR)
1.32
Selected Airquantity (CFM)
326.19
Winter Load (KW)
-1.06
Monsoon Heating (KW)
0.27
Humidifier (KW)
-0.16
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
14.01
0.00
0.00
0.00
Partition
H
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
NET AREA
0.00
0.00
0.00
0.00
64.31
0.00
0.00
0.00
150.92
32.87
Solar & Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
64
0.48
17
15
-10
540
465
-317
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
Roof Sun
0
0.11
33
31
-10
0
0
0
Partition
151
0.32
12
7
-5
567
332
-254
S
08-NOV-2019
Return Air Heat Load Gain
Page 67 of 168
1107
SUTHAR KETANBHAI (C360) 67 of 168
Page 67 of 82
797
-571
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM PACKAGE AC ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
NHT CCR FIELD ROOM
INDOOR
75.2
PACKAGE AC ROOM
DIFFERENTIAL
16.7
OUTDOOR
87.1
ROOM SIZE
13.94
11.81
14.60
MONSOON
DESIGN CONDITIONS
ROOM AREA
164.60
Sq.ft
INDOOR
75.2
ROOM VOLUME
2402.55
Cu.ft
DIFFERENTIAL
11.9
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10
OCCUPANCY
0.00
AIR CHANGES
0.00
FRESH AIR
17.00
cfm/per
WINTER
RH
1 Gr/LB 150.0
50.0
65.3 84.7
82.0
158.4 50.0
65.3 93.1
57.0
56.4 50.0
0.00
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.17 Occupant Heat
Sens
245.00
0.00
Cfm Selected
1-BF
0.83
Lat
205.00
65.3 -9
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
13.94
0.00
11.81
0.00
25.75
H
14.60
14.60
14.60
14.60
14.60
14.60
14.60
14.60
14.60
NETT AREA
0.00
0.00
0.00
0.00
203.47
0.00
172.35
0.00
375.82
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
203
0.48
17
15
-10
1707
1470
-1002
S SW W NW Roof Sun
0
0.48
15
13
-10
0
0
0
172
0.48
13
11
-10
1115
914
-849
0
0.48
7
5
-10
0
0
0
165
0.11
33
31
-10
606
562
-186
Trans. Gain-Except Wall & Roof All Glass
0
1.13
17
12
-10
0
0
0
Partition
376
0.32
12
7
-5
1412
827
-633
Ceiling
0
0.29
12
7
-5
0
0
0
Floor
0
0.36
12
7
-5
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
76
3.40
260
260
130
5100
4034
-2539
5738
4538
-2539
0
0
0
5738
4538
-2539
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 68 of 168
12.5%
08-NOV-2019
0.00
0.17
17
12
-10
1.08
SUTHAR KETANBHAI (C360) 68 of 168
Page 68 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM PACKAGE AC ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
0
0
0
0
0
0
ERLH
0
0
0
ERTH
5738
4538
-2539
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
0.00
0.17
85
93
-9
0.68
Outdoor Air(S)
0.00
0.83
17
12
-10
1.08
0
0
Outdoor Air(Lt)
0.00
0.83
85
93
-9
0.68
0
0
0
GTH
5738
4538
-2539
Refrigeration Load
5738
4538
-2539
Monsoon Reheat
0
1200
Return Air Heat Load
-400
0
Grand Total Refrigeration Load
BTU/HR
5338
5738
Grand Total Refrigeration Load
TR
0.44
0.48
0
Winter KW
-0.74
Monsoon Heaters (KW)
0.35
ESHF =(ERSH/ERTH)
1.00
1.00
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
17.60
17.60
302
239
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
0.00
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
0.00
Final Values: Selected Load (TR)
0.48
Selected Airquantity (CFM)
301.94
Winter Load (KW)
-0.74
Monsoon Heating (KW)
0.35
Humidifier (KW)
0.00
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
13.94
0.00
11.81
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
25.75
Solar & Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
S
0
0.48
17
15
-10
0
0
0
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
Roof Sun
0
0.11
33
31
-10
0
0
0
Partition
0
0.32
12
7
-5
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 69 of 168
0
SUTHAR KETANBHAI (C360) 69 of 168
Page 69 of 82
0 0
0
Page 70 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-5 EQUIPMENT SELECTION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 70 of 168
Page 70 of 82
Page 71 of 168
HEAT LOAD ESTIMATION FOR VRMP
5.1. SELECTION
BUILDING/ FLOOR
AIR CONDITIONING SYSTEM TYPE
VAM
SYSTEM QUANTITY/ CAPACITY Total Load = 124.62 TR x 65 % each i.e. 81 TR each 2 Nos. of 83 TR VAM (Actual Capacity) 1 No. x 22850 CFM for First Floor
AIR HANDLING UNIT 1 No. x 13550 CFM for Second Floor 1 No. x 21 KW for First Floor
SUBSTATION BUILDING- 86 CT
HEATER 1 No. x 10.5 KW for Second Floor 1 No. x 21 KW for First Floor HUMIDIFIER 1 No. x 9 KW for Second Floor 2 Nos. x 3160 CFM for First Floor CHEMICAL FILTER UNIT 1 No. x 2650 CFM for Second Floor
NHT CCR BUILDING
Water Cooled Package AC
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 71 of 168
Page 71 of 82
2 Nos.(1W+1S) x 5.5 TR Water Cooled PAC Dehumidified CFM- 2200 CFM each
Page 72 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-6 ARCHITECTURE DRAWINGS
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 72 of 168
Page 72 of 82
Page 73 of 168
HEAT LOAD ESTIMATION FOR VRMP
6.1 LIST OF DRAWINGS: Sl No.
Drawing Title
Drawing Number
A.
Substation- 86 (CT)
1
Ground & First Floor Plan
B015-000-8141-02421, Rev.3
2
Second Floor Plan, Elevations & Sections
B015-000-8141-02422, Rev.2
3
Terrace Plan & Elevations
B015-000-8141-02423, Rev.1
4
Elevations & Sections
B015-000-8141-02424, Rev.2
5
Profile of Doors/Windows
B015-000-8141-02425, Rev.2
B.
Field Room-NHT CCR Plans, Elevations & Sections Terrace Plan, Elevations, Sections & Profile of Doors
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 73 of 168
Page 73 of 82
B015-000-8141-12821, Rev.0 B015-000-8141-12822, Rev.0
Page 74 of 168
HEAT LOAD ESTIMATION FOR VRMP
SUBSTATION BUILDING- 86 CT
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 74 of 168
Page 74 of 82
3
4
5
6
7
8
9
10
11
12
N
14
15
B015-000-81-41-02422 B015-000-81-41-02423 B015-000-81-41-02424 B015-000-81-41-02425
16
REFERENCE DRAWING TITLE SECOND FLOOR PLAN & SECTION TERRACE PLAN, ELEVATION & SECTION ELEVATIONS & SECTIONS DOORS & WINDOWS PROFILE
A
1 NOTES :-
FLOOR TRAP
V1A
V1A
V1A
V1A
REFER NOTE 16 & 17 900 900
RS1
B
AHU ROOM
POWER TRANSFORMER BELOW
HEAVY DUTY FLOORING
GYPSUM BOARD PARTITION UPTO FALSE CEILING
OPERATOR ROOM
1050
AC FC
LOADING/ UNLOADING PLATFORM
MONORAIL 1500
7500
33000
UP SD1A AL1
W2
V1
WALL TO BE CONSTRUCTED AFTER INSTALLATION OF EQUIPMENT
V1
RS1
AIR LOCK LOBBY
FC
AL2
1200
FC AC
1200
VITRIFIED TILE FLOORING
E
UP
UP STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
V1 5500mm HIGH WALL (TYP)
50 DIA G.I. SPOUT (TYP.)
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
DN
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
UP
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
SD1
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
DISTRIBUTION TRANSFORMER BELOW
SINK
W1
W1
W1
3500
6000
6000
1
6000
-
3300
STD. STEEL ROLLING SHUTTER, ELECTRICALLY OPERATED
RS2
3000x3000
-
3000
STD. STEEL ROLLING SHUTTER, PARTLY GRILL TYPE, ELECTRICALLY OPERATED
3
D1
1100x2100
0880x2090
2100
35 THK FULLY PANELLED DOOR SOMGLE SHUTTER AS PER EIL STD. 7-75-0066
3
D2
0900x2100
0880x2090
2100 PVC DOOR AS PER SPECIFICATIONS
04
AL1
1500x2500
1480x2490
POWDER COATED ALMN. GLAZED DOOR WITH 2500 6mm THK TOUGHENED GLASS, DOUBLE LEAF AS/EIL STD NO. 7-75-0014.
06
AL2
1000x2100
0980x2090
2100 SAME AS AL1A BUT SINGLE SHUTTER
06
W1
6000
550
6000 66550
6000
50 DIA G.I. SPOUT (TYP.)
2 EXHAUST FANS OF 450MM DIA
6000
6000
6000
6000
3500
F
3000x3300
W1
3
6000
W1
NOS.
RS1
EPOXY PAINT ON FLOOR WITH 2500 MM HIGH EPOXY PAINT ON DADO/WALL
DISTRIBUTION TRANSFORMER BELOW
G
160 Ø R.W.P. (TYP)
LINTEL TYPE OPENING SIZE FRAME SIZE LEVEL
1000 HIGH S.S. RAILING
BATTERY ROOM
1500
6000
DISTRIBUTION TRANSFORMER BELOW
5500mm HIGH WALL (TYP)
SCHEDULE OF DOORS & WINDOWS
1500
V1 1000 HIGH S.S. RAILING
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, SD1 1000 HIGH
1500
7500
FIRE HYDRANT
750
DN
DN
E
D
AIR LOCK LOBBY
AL2
HEAVY DUTY FLOORING
AL2
F
HEAVY DUTY FLOORING
2
SWITCHGEAR HALL
2500
15000
FC
MONORAIL 1500
AL2
AL2
VITRIFIED TILE FLOORING
REMOVEABLE TYPE 1000 HIGH S.S. RAILING
LOADING/ UNLOADING PLATFORM
PROTECTIVE STEEL PLATE COVER OVER EXP JOINT (TYP)
AL2
750
C
LIF T
2
FIRE HYDRANT
7500mm HIGH WALL (TYP)
RS1
HEAVY DUTY FLOORING
D
7500mm HIGH WALL (TYP)
R-150 T-300 W-1500 STEPS
VITRIFIED TILE FLOORING
2300
6000
HEAVY DUTY FLOORING
REMOVEABLE TYPE 1000 HIGH S.S. RAILING
1050
LOADING/ UNLOADING PLATFORM
POWER TRANSFORMER BELOW
CAPACITOR BANK BELOW
CAPACITOR BANK BELOW
2500
2 NOS. MONORAILS TO BE PROVIDED
6000
V1
GIS PANELS
3350
1500
V1
V1
V1
C
03 01
02
ELBUOD , ROOD DEZALG , DETAR ER I F RH - 2 1500x2500 1480x2490 2500 . NO I TAC I F FD1 I CEPS S ' RERUTCAFUNAM REP SA RETTUHS
G
05
73550
FD2
RETTUHS ELGN I S , 1DF SA EMAS 1000x2100 0980x2090 2100
SD1
1500x2500
1480x2490
2500
SD1A
1500x2500
1480x2490
2500 SAME AS SD1 BUT AIR-TIGHT
SD2
1000x2100
980x2090
2100
W1
1200x1800
1180x1790
ALMN. GLAZED WINDOW POWDER COATED WITH 3500 6 mm THKTOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
W2
3500x1800
3480x1790
V1
2600x 600
BEAM ALMN. GLAZED VENTILATOR POWDER COATED 2580x 590 BOTTOM WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
V1A
2600x 600
3
V2
1500x 600
3
V3
4000x 600
BEAM ALMN. GLAZED VENTILATOR POWDER COATED 3980x 590 BOTTOM WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
03
V4
2600x 600
2580x 590
ALMN. GLAZED VENTILATOR POWDER COATED 3500 WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
04
FIRST FLOOR PLAN
SLOPE 1:6 RAMP UP
1000 WIDE PLINTH PROTECTION ALL AROUND THE BUILDING
I
1485
EQ. 115 D2
EQ. D2
O
1340
TOILET
D/W
V1
V1
V1
V1
SLOPE 1:6 RAMP UP
RS2
PE
A C PLANT ROOM
D1
HEAVY DUTY FLOORING (CLEAR HEIGHT 3500mm - BEAM BOTTOM)
100.300
3
POWER TRANSFORMER
12000
F.F.L
LOADING/ UNLOADING PLATFORM
6000
TRANSFORMER GATE AS/ EIL STANDARD NO. 7-75-0052 (TYPICAL)
3 V1
V1 J
SLOPE 1:6 RAMP UP
FC
900
6000
600 WIDE R.C.C. SUNSHADE ABOVE
FLOOR TRAP
SL
SLOPE 1:6 RAMP UP
WALL TO BE CONSTRUCTED AFTER INSTALLATION OF EQUIPMENT
V1
V2
1
3
HEAVY DUTY FLOORING
100.150
100.150
EXHAUST FANS OF 450MM DIA (TYP)
100.150
TOP OF GRAVEL
TOP OF GRAVEL
02
PRESSED STEEL DOOR WITH PRESSED STEEL 08 FRAME, DOUBLE SHUTTER AS/EIL.STD. 7-75-0071 02
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, SINGLE SHUTTER AS/EIL.STD. 7-75-0070
46
ALMN. GLAZED WINDOW POWDER COATED WITH 2500 6 mm THK TOUGHENED GLASS, FIXED TYPE.
BEAM ALMN. GLAZED VENTILATOR POWDER COATED 2580x 590 BOTTOM WITH 6 mm THK TOUGHENED GLASS, FIXED TYPE. ALMN. GLAZED VENTILATOR POWDER COATED 1480x 590 3000 WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
H
05
01
24
I
04
02
J
LEGEND:
100.150
TOP OF GRAVEL
7500mm HIGH WALL (TYP)
V3
POWER TRANSFORMER
CAPACITOR BANK
CAPACITOR BANK
F.R.L. F.F.L.
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL AC = AIR CONDITIONED FC = FALSE CEILING AC UD UD = UNDERDECK INSULATION
TOP OF GRAVEL
7500mm HIGH WALL (TYP)
FC
V1
LIF T
V1
2300
H
K
K
KEY PLAN (Not To Scale) T-300 R-150
T-300 R-150
V1
PE
PE
FLOOR TRAP
345 THK BRICK WALL (TYP)
5500mm HIGH WALL (TYP)
6000
DISTRIBUTION TRANSFORMER 100.150 TOP OF GRAVEL
O SL
345 THK BRICK WALL (TYP) FLOOR TRAP
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER 100.150 TOP OF GRAVEL
345 THK BRICK WALL (TYP)
345 THK BRICK WALL (TYP)
5500mm HIGH WALL (TYP)
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
SD1
TOP OF GRAVEL
TOP OF GRAVEL
TOP OF GRAVEL
1500
6000
FLOOR TRAP
DISTRIBUTION TRANSFORMER 100.150
106.88
1200
100.300
F.F.L
F.F.L SD2
R-150 T-300
550
6000
3 2 1 0 D C B A
RAIN WATER PIPE UNDER FLOOR FOR WATER DISPOSAL (TYPICAL)
100.300
TOP OF GRAVEL
1000 HIGH S.S. RAILING
CEMENT CONCRETE FLOORING
CEMENT CONCRETE FLOORING
V1
3
PE
STORE ROOM
MAINTENANCE ROOM
V1
RAMP UP SLOPE 1:6
6000
M
O
1500
600 6000
DISTRIBUTION TRANSFORMER 100.150
RESIDUE UPGRADATION FACILITY (RUF)
V1
SD2
900
6000
SL
FLOOR TRAP
AL1
RAMP UP SLOPE 1:6
TRANSFORMER GATE AS/ EIL STANDARD NO. 7-75-0051 (TYPICAL)
6000
345 THK BRICK WALL (TYP)
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER 100.150
TOP OF GRAVEL
160 Ø R.W.P. (TYP)
3500
5500mm HIGH WALL (TYP)
100.300 F.F.L
2 1
O
UP
VITRIFIED TILE FLOORING
DISTRIBUTION TRANSFORMER 100.150
RAIN WATER PIPE UNDER FLOOR FOR WATER DISPOSAL (TYPICAL)
345 THK BRICK WALL (TYP)
FLOOR TRAP
LOBBY
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER 100.150
PE
345 THK BRICK WALL (TYP)
FIRE HYDRANT
750
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
SL O
PE O
SL
125 (TYP) 1500 (TYP)
07.05.18 13.03.18 08.11.17 02.11.17 11.08.17 21.06.17 16.06.17 08.06.17
REVISED AS MARKED 3 & REISSUED FOR CONSTRUCTION REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION REVISED AS MARKED & RE-ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG. REISSUED FOR TENDER ISSUED FOR TENDER ISSUED FOR COMMENTS
REV. DATE T-300 R-150 STEP UP
RAMP UP SLOPE 1:6
1
6000
L
REVISIONS
SM SM SM SM SM SG SG SG
GJK GJK GJK GJK GJK GJK GJK GJK
BY
JS JS JS JS JS JS JS JS
N
V1
O SL
S/S 86 & SRR (FOR CT)
CWTP
RAMP UP
1500
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
1000 HIGH S.S. RAILING
N
1500
1500 (TYP) UP
SUMP BCW PH
SLOPE 1:6
SD1
125 (TYP) 1500 1500 (TYP) (TYP) UP
M
BCT(6+1)
1800
SD1
7500
750
2
HEAVY DUTY FLOORING
PROTECTIVE STEEL PLATE COVER OVER EXP JOINT (TYP)
OWS/CRWS SUMP-3 & PUMP HOUSE
STEP
CEMENT CONCRETE FLOORING 1500
SLOPE 1:6
1200
15000
FIRE HYDRANT
V3 LOADING/ UNLOADING PLATFORM
CHKD APPD PEM/PC
600 WIDE R.C.C. SUNSHADE ABOVE
O
CABLE CELLAR
1800
RAMP UP
1500
7500
2
L
N
2 1
EXHAUST FANS OF 450MM DIA (TYP)
V3
400.98
1 2
STEP
33000
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
13
EXPANSION JOINT WITH POLYSULPHIDE SEALANT COVERED WITH PROTECTIVE STEEL PLATE
3
12000
A B
2
REF. DWG. NO.
B015-000-81-41-02421
Page 75 of 168
1
(A Govt. of India Undertaking) 6000
6000
6000
6000
3500
66550 73550
100.00
GROUND FLOOR PLAN
P
SUB STATION - 86 (CT) GROUND & FIRST FLOOR PLAN
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 75 of 168
Page 75 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 1 3 A0-1189 x 841
P
F.R.L
A B
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REF. DWG. NO.
B015-000-81-41-02422
Page 76 of 168
1
REFERENCE DRAWING TITLE
B015-000-81-41-02421 GROUND & FIRST FLOOR PLAN B015-000-81-41-02423 TERRACE PLAN & ELEVATION B015-000-81-41-02424 ELEVATIONS & SECTIONS B015-000-81-41-02425 DOORS & WINDOWS PROFILE
A
N NOTES :-
B
2
2 1000 HIGH R.C.C. PARAPET WALL WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL. 750 WIDE R.C.C. GUTTER
C
C
900
TERRACE
WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL. 750 WIDE R.C.C. GUTTER
900
RACK ROOM
900
D
900
1250
800
D
1800
3000
1800
FALSE CEILING
FALSE CEILING AT 4500 HEIGHT 4500
SWITCHGEAR HALL CUT-OUTS IN SWITCHGEAR HALL FLOOR SLAB SHALL BE AS PER RELEVANT STRUCTURE DRAWING
6500
7500
DISTRIBUTION TRANSFORMER
E
CAPACITOR BANK
5500
6500
CABLE CELLAR
100.150
100.300
100.150
F.F.L
TOP OF GRAVEL
100.300
100.00
TOP OF GRAVEL
100.00
F.F.L
F.R.L
F.R.L
F
F
SECTION 1-1
WEST ELEVATION
G
G
EXPANSION JOINT WITH POLYSULPHIDE SEALANT COVERED WITH PROTECTIVE STEEL PLATE
H
3
H
1 750 WIDE RCC GUTTER (TYP)
160 Ø R.W.P. (TYP)
V2 1485
W1
EQ.
W1
W1
W1
FLOOR TRAP
W1
W1
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
W1
AHU ROOM
TECH ROOM
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
900
D1
SLOPE 1:80
D2 FC
SUNK SLAB
I
HEAVY DUTY FLOORING
12000
VITRIFIED TILES FLOORING
LOADING/ UNLOADING PLATFORM
1000 HIGH S.S. RAILING
AC FC UD
TERRACE
UD
TERRACE
HEAVY DUTY FLOORING
TREAD-300 RISER-150 (max.)
J
2 2300
STEP UP
6000
J
SLOPE
1000 HIGH RCC PARAPET WALL (TYP)
TOILET
D/W
6000
1340
D2
I
SLOPE
W1
EQ. 115
LIF T SD1A SD1
4800
VITRIFIED TILE FLOORING
FD1
SD1
W1
W1
DN
2
FALSE FLOORING
RACK ROOM
AC FC FF UD
FIRE HYDRANT
L
DN
STEP DOWN TREAD-300
FALSE FLOORING
EPOXY PAINT ON FLOOR WITH 2500 MM HIGH EPOXY PAINT ON DADO/WALL
VITRIFIED TILES FLOORING
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
FF = FALSE FLOORING
FD2
750
UPS ROOM
BATTERY ROOM
V4
FC
FALSE FLOORING AC FC FF UD
ELECTRICAL ROOM
FF UD
VITRIFIED TILE FLOORING
K
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
AC FC
STEP UP
UP
RISER-150 (max.)
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
AC FC FF UD
SINK
1800
7500
UP
TREAD-300 RISER-150 (max.)
AIR LOCK LOBBY
1200 750
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
V4
FD2
FIRE HYDRANT
F.R.L. F.F.L. FD1
FALSE FLOORING
AC FC FF UD
LEGEND:
W1
W1
ENGINEERING ROOM
LOBBY 2 AL1
L
W1
W1
PROTECTIVE STEEL PLATE COVER OVER EXP JOINT (TYP)
SD1
FC
V4
W1
W1
FD1
1200
7500
33000
VITRIFIED TILE FLOORING
2
W1
W1 FD1
RAMP UP SLOPE 1:7
AC FC UD
AIR LOCK LOBBY
K
WALL TO BE CONSTRUCTED AFTER INSTALLATION OF EQUIPMENT
LOBBY 1
1000
AL1
FD1
V4
15000
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
E
FD1
W1
W1
W1 DN
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
6000
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
W1
W1
W1
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL,1000 HIGH
1500 SLOPE
W1
W1
W1
W1
W1
W1
M
1000 HIGH S.S. RAILING
2
TERRACE
W1
UP
SLOPE
W1
TERRACE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
2 1 0 C B A
N
160 Ø R.W.P. (TYP)
3500
3
6000
6000
6000
1
6000
6000
6000 66550
550
6000
6000
6000
6000
6000
3500
13.03.18 08.11.17 02.11.17 11.08.17 16.06.17 08.06.17
REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION REVISED AS MARKED & RE-ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG. ISSUED FOR TENDER ISSUED FOR COMMENTS
REV. DATE
73550
REVISIONS
O
SM SM SM SM SG SG
GJK GJK GJK GJK GJK GJK
BY
JS JS JS JS JS JS
N
W1
CHKD APPD PEM/PC
O
W1
SLOPE 1:80
W1
1000 HIGH S.S. RAILING
SLOPE 1:80
W1
SLOPE 1:80
W1
SLOPE 1:80
W1
SLOPE 1:80
M
W1
1500
W1
(A Govt. of India Undertaking)
P
SUB STATION - 86 (CT) द्वितीय
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
दृश्य और काट
JOB NO.
SECOND FLOOR PLAN, ELEVATION & SECTION
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 76 of 168
Page 76 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 2 2 A0-1189 x 841
P
SECOND FLOOR PLAN
A B
2
3
4
5
6
7
8
9
10
11
12
13
15
16
REFERENCE DRAWING TITLE
B015-000-81-41-02421 GROUND & FIRST FLOOR PLAN B015-000-81-41-02422 SECOND FLOOR PLAN, ELEVATION & SECTION B015-000-81-41-02424 ELEVATIONS & SECTIONS B015-000-81-41-02425 DOORS & WINDOWS PROFILE
A
N NOTES :-
B
C
C
D
D
E
E
2300
600 HIGH RCC PARAPET WALL (TYP)
F 7500
F
15000
1
G
G
1
SLO
PE
SLO
PE
SLO
PE
7500
NORTH ELEVATION
H 160 Ø PVC RAIN WATER PIPE (TYP.) 3500
160 Ø PVC RAIN WATER PIPE (TYP.)
SLOPE
SLOPE
750 WIDE RAIN WATER GUTTER (TYP)
SLOPE
SLOPE
SLOPE
SLOPE
3
1000 HIGH RCC PARAPET WALL (TYP) SLOPE
SLOPE
1
SLOPE
I
I
MUMTY PLAN SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
6000
TERRACE BELOW
12000
600 HIGH RCC PARAPET WALL (TYP)
J
A MONORAIL BEAM TO BE PROVIDED INSIDE THE MACHINE ROOM (BOTTOM OF BEAM = 2500mm FROM FFL) FOR INSTALLATION OF CHAIN PULLEY IN THE MACHINE ROOM.
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
F.R.L. F.F.L.
SLOPE
7500
7500
LI FT
160 Ø PVC RAIN WATER PIPE (TYP.)
PE
K
2
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
7500
33000
AC UD
E
EXPANSION JOINT WITH POLYSULPHIDE SEALANT COVERED WITH PROTECTIVE STEEL PLATE
K
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
FC
OP
SL
LIFT MACHINE ROOM
2
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
PE SLO
RIDGE LINE
LEGEND:
2300
6000
J
SLO 3500
L
SD2
L 15000
RIDGE LINE
SD2
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
DN
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
MUMTY PLAN
M
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
600 HIGH RCC PARAPET WALL (TYP)
1
SLOPE 1000 HIGH S.S. RAILING
6000
6000
PE
SLO
1000 HIGH S.S. RAILING
SLOPE 1:80
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH 1500
M
1
FIRE HYDRANT
750
DN
SLO PE
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
DN
SLOPE 1:80
750
7500
SLOPE 1:80
SD2
SLOPE 1:80
SLO
V1
N
160 Ø PVC RAIN WATER PIPE (TYP.)
TERRACE BELOW
N
1 0 B A
SLO
PE
PE
V1 6000
3500
6000
6000
6000
6000
REVISED AS MARKED 1 & REISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG. ISSUED FOR TENDER
REV. DATE
160 Ø R.W.P. (TYP)
3
13.03.18 08.11.17 11.08.17 16.06.17
REVISIONS
SM SM SM SG
GJK GJK GJK GJK
BY
JS JS JS JS
CHKD APPD PEM/PC
1 6000
6000
550
6000
6000
6000
6000
6000
3500
(A Govt. of India Undertaking)
66550
0
O
FIRE HYDRANT
1200
SD2
1200
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
14
REF. DWG. NO.
B015-000-81-41-02423
Page 77 of 168
1
MUMTY PLAN
73550
SUB STATION - 86 (CT) छत
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
दृश्य
JOB NO.
TERRACE PLAN & ELEVATION
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 77 of 168
Page 77 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 3 1 A0-1189 x 841
P
TERRACE PLAN P
A B
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REF. DWG. NO.
B015-000-81-41-02424
Page 78 of 168
1
REFERENCE DRAWING TITLE
B015-000-81-41-02421 GROUND & FIRST FLOOR PLAN B015-000-81-41-02422 SECOND FLOOR PLAN & SECTION B015-000-81-41-02423 TERRACE PLAN & ELEVATION B015-000-81-41-02425 DOORS & WINDOWS PROFILE
A
N NOTES :-
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL.
B
LOBBY
3800
2500
AIR LOCK LOBBY
RACK ROOM
ENGINEERING ROOM
800
AIR LOCK LOBBY
FALSE CEILING 3000
FALSE CEILING
C
C MONORAIL
MONORAIL 1500 1500
FALSE CEILING AT 4500 HEIGHT
SWITCHGEAR HALL
D
600
3300 600
D
LOADING/ UNLOADING PLATFORM
4500
ROLLING SHUTTER
3300
LOADING/ UNLOADING PLATFORM
LOADING/ UNLOADING PLATFORM
LOADING/ UNLOADING PLATFORM
CABLE CELLAR 100.300
100.00
F.F.L
F.R.L
E
2
SECTION 2-2
F
F 1000 HIGH R.C.C. PARAPET WALL WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL. 750 WIDE R.C.C. GUTTER
TERRACE
G
G
2700
LOBBY
2500
BATTERY ROOM
3800
2500
FALSE CEILING
AHU ROOM
CINDER FILLING
H 900
1250
H
FALSE CEILING AT 4500 HEIGHT
SWITCHGEAR HALL 4500
AHU ROOM
DISTRIBUTION TRANSFORMER
I 5500
I
2500
CUT-OUTS IN SWITCHGEAR HALL FLOOR SLAB SHALL BE AS PER RELEVANT STRUCTURE DRAWING 6500
AC PLANT ROOM
3000
CABLE CELLAR 100.300
100.150
100.300
100.00
F.F.L
TOP OF GRAVEL
F.F.L
F.R.L
2 J
J
SECTION 3-3
EAST ELEVATION
LEGEND: F.R.L. F.F.L.
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
K
K
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
FC AC UD
L
L
M
M
N
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
E
N
07.05.18 13.03.18 08.11.17 11.08.17
REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION REVISED AS MARKED 1 & REISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG.
REV. DATE
O
REVISIONS
SM SM SM SM
GJK GJK GJK GJK
BY
JS JS JS JS
CHKD APPD PEM/PC
O
2 1 0 A
(A Govt. of India Undertaking)
2
SUB STATION - 86 (CT) दृश्य और
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
काट
JOB NO.
ELEVATIONS & SECTIONS
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 78 of 168
Page 78 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 4 2 A0-1189 x 841
P
SOUTH ELEVATION P
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REF. DWG. NO.
1480 1480
EQ.
N 880
500
2490
2090
VISION PANEL AS PER SPECIFICATION
VISION PANEL AS PER SPECIFICATION
NOTES :-
900
1350
LATCH AND LOCKING SYSTEM
900
900
GLASS
B
1350
2490
2090
PRESSED STEEL FRAME
LATCH AND LOCKING SYSTEM
900
GLASS
OVER HEAD HYDRAULIC DOOR CLOSER (HEAVY DUTY)
PRESSED STEEL FRAME
DOOR STOPPER
TEAK WOOD BOTTOM RAIL 200x35
A
AL. FRAME GLASS
GLASS
GLASS
OVER HEAD HYDRAULIC DOOR CLOSER (HEAVY DUTY)
500
AL. FRAME GLASS
75 LONG ALUMINIUM TOILET DOOR LATCH
300x25x6 THK. M.S. HOLD FAST @ MAX. 600 C/C. 11.10 DIA. 150 LONG ALUMINIUM BUTT HINGES @ MAX. 600 C/C.
1335 C
TOWER BOLT
CHROMIUM PLATE BRASS COAT AND HAT HOOK FIXED WITH BRASS SCREWS. (INTERNAL SIDE OF THE DOOR)
TEAK WOOD LOCK RAIL 150x35
EQ.
REFERENCE DRAWING TITLE GROUND & FIRST FLOOR PLAN SECOND FLOOR PLAN, ELEVATION & SECTION TERRACE PLAN & ELEVATION ELEVATIONS & SECTIONS
980
12 THK. PARTICLE BOARD
75 LONG ALUMINIUM TOILET DOOR LATCH
EQ.
ALUMINIUM TOWER BOLT 150X10 mm.
TEAK WOOD TOP RAIL 100x35 TEAK WOOD FRAME OUT OF 125x65 TEAK WOOD STYLE 100x35
CHROMIUM PLATE BRASS COAT AND HAT HOOK FIXED WITH BRASS SCREWS. (INTERNAL SIDE OF THE DOOR)
B015-000-81-41-02421 B015-000-81-41-02422 B015-000-81-41-02423 B015-000-81-41-02424
1480 EQ.
2490
1180 ALUMINIUM TOWER BOLT 150X10 mm.
2090
A B
B015-000-81-41-02425
Page 79 of 168
1
DOOR STOPPER
C
ACRYLIC KICK PLATE 200X3 THICK. RUBBER BEADING
ELEVATION : D1
ELEVATION : D2
35 THK FULLY PANELLED DOOR SINGLE SHUTTER AS/EIL STD NO. 7-75-0066 D
OPENING SIZE REQUIRED NOS.
: :
OPENING SIZE REQUIRED NOS.
2
: :
DOOR HANDLE
DOOR HANDLE
POWDER COATED ALMN. GLAZED DOOR WITH 6mm THK TOUGHENED GLASS, DOUBLE LEAF AS/EIL STD NO. 7-75-0014.
0900x2100 04
OPENING SIZE REQUIRED NOS.
: :
RUBBER BEADING
ELEVATION :SD1
ELEVATION :SD1A
SAME AS AL1A, BUT SINGLE SHUTTER
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, DOUBLE SHUTTER AS/EIL.STD. 7-75-0071
SAME AS SD1, BUT AIRTIGHT
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
ELEVATION : AL2
ELEVATION : AL1
PVC DOOR SINGLE SHUTTER
1100x2100 02
LEGEND-
RUBBER BEADING
F. - FIXED GLASS. SH. - SIDE HUNG SHUTTER. TH. - TOP HUNG SHUTTER.
D
1500x2500 06
: :
1000x2100 06
: :
1500x2500 08
: :
1500x2500 02
2 1180
(6 EQ.PARTS)
E
600
F
600
980
ARCHITECTURAL FINISHES SCHEDULE OVER HEAD HYDRAULIC DOOR CLOSER (HEAVY DUTY)
F
F
F
F
F
F
LOADING/ UNLOADING PLATFORM
HEAVY DUTY FLOORING
TRANSFORMER/ CAPACITOR BANK/ POWER TRANSFORMER
GRAVEL
910
910
1350
LATCH AND LOCKING SYSTEM
900
CEMENT CONCRETE FLOORING
CABLE CELLAR
SKIRTING/ WALL BASE 125mm HIGH CEMENT PLASTER SKIRTING 125mm HIGH CEMENT PLASTER SKIRTING
G
DOOR STOPPER
ELEVATION : W1
ELEVATION : W2
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, SINGLE SHUTTER AS/EIL.STD. 7-75-0070
ALMN. GLAZED WINDOW POWDER COATED WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
ALMN. GLAZED WINDOW POWDER COATED WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
: :
1000x2100 05
: :
1200x1800 46
: :
BOTTOM OF ROOF BEAM
F
580
ROOF BEAM
I
T.H.
SWITCHGEAR HALL
(5 EQ.PARTS) BOTTOM OF
T.H.
F
F
F
F
T.H.
AIR HANDLING UNIT
F
2990
ELEVATION : V1
ELEVATION : V1A
ELEVATION : V2
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE. OPENING SIZE : 2600x0600 REQUIRED NOS. : 24
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, FIXED TYPE.
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, OPENABLE TYPE.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
2580
580
F
T.H.
F
125mm HIGH CEMENT CEMENT PLASTER + POP PUNNING + PLASTIC PLASTER SKIRTING EMULSION PAINT 125mm HIGH CEMENT CEMENT PLASTER + OIL PLASTER SKIRTING BOUND DISTEMPER
HEAVY DUTY FLOORING
: :
1500x0600 02
BATTERY ROOM
EPOXY PAINT
OPERATOR ROOM
VITRIFIED TILE FLOORING
2
(5 EQ.PARTS)
T.H.
125mm HIGH VITRIFIED TILES SKIRTING -
125mm HIGH GRANITE SKIRTING -
125mm HIGH VITRIFIED TILES SKIRTING
BOTTOM OF
F
T.H.
F
P
2
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
2500 MM HIGH EPOXY PAINT ON WALL OVER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT ABOVE 2500MM HEIGHT
CEMENT PLASTER + OIL BOUND DISTEMPER
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
GYPSUM BOARD PANEL FALSE CEILING
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
UPS ROOM
FALSE FLOORING
-----
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
VITRIFIED TILE FLOORING
LOBBY
ELEVATION : V4
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
-----
125mm HIGH VITRIFIED TILES SKIRTING
K
L
M
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
2 07.05.18 REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION 1 13.03.18 REVISED AS MARKED 1 & REISSUED FOR CONSTRUCTION 0 08.11.17 ISSUED FOR CONSTRUCTION REV. DATE
VITRIFIED TILE FLOORING
125mm HIGH VITRIFIED TILES SKIRTING
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
VITRIFIED TILE FLOORING
125mm HIGH VITRIFIED TILES SKIRTING
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
O
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE. OPENING SIZE : 2600x0600 REQUIRED NOS. : 04
CEMENT PLASTER + OIL BOUND DISTEMPER
FALSE FLOORING
ELECTRICAL ROOM
ELEVATION : V3
CERAMIC TILES DADO UP TO CEILING
ENGG. ROOM
TECH. ROOM
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE. OPENING SIZE : 4000x0600 REQUIRED NOS. : 03
GYPSUM BOARD PANEL FALSE CEILING
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
T.H.
N
I
CEMENT PLASTER + OIL BOUND DISTEMPER
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
3500
580
T.H.
H
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
-----
ROOF BEAM F
CEMENT PLASTER + OIL BOUND DISTEMPER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
FALSE FLOORING
3980
T.H.
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
G
RACK ROOM T.H.
(7 EQ.PARTS)
M
CEMENT PLASTER + OIL BOUND DISTEMPER
HEAVY DUTY FLOORING
GRANITE STONE FLOORING WITH ATI SLIP GROOVES
STAIRCASE
2
CEMENT PLASTER + OIL BOUND DISTEMPER
F
J
K
2600x0600 04
CEMENT PLASTER + OIL BOUND DISTEMPER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
125mm HIGH CEMENT CEMENT PLASTER + OIL PLASTER SKIRTING BOUND DISTEMPER
NON-SLIP VITRIFIED TILE FLOORING
TOILET
: :
CEMENT PLASTER + OIL BOUND DISTEMPER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
125mm HIGH CEMENT CEMENT PLASTER + POP PLASTER SKIRTING PUNNING + PLASTIC EMULSION PAINT
VITRIFIED TILE FLOORING
2410
J
CEILING FINISH
CEMENT CONCRETE FLOORING
F
AIR LOCK LOBBY
L
HEAVY DUTY FLOORING
1500
2580
(5 EQ.PARTS)
F
STORE & MAINTENANCE ROOM
3500x1800 01
(3 EQ.PARTS)
2580
T.H.
A C PLANT ROOM
580
H
ELEVATION : SD2
-----
WALL FINISH
N
S.H.
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
2
3
4
5
SM SM SM
GJK GJK GJK
BY
JS JS JS
CHKD APPD PEM/PC
(A Govt. of India Undertaking)
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
SUB STATION - 86 (CT) PROFILE OF DOORS/WINDOWS
SCALE
001:1 1
REVISIONS
O
2690 1180
S.H.
6
7
8
9
10
11
12
13
14
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 79 of 168
Page 79 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 5 2 A0-1189 x 841
P
2090
500
PRESSED STEEL FRAME VISION PANEL AS PER SPECIFICATION
FLOOR FINISH
ROOM 2690 1180
F
580
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
3480
(2 EQ.PARTS)
E
Page 80 of 168
HEAT LOAD ESTIMATION FOR VRMP
NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 80 of 168
Page 80 of 82
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING (AS/SPECS.) R.C.C. SLAB AS/ STRL. DETAIL
N
REFERENCE DRAWING TITLE
NOTES:
750 WIDE R.C.C. GUTTER
1000
1. ALL DIMENSIONS ARE IN MILLIMETRES & LEVELS IN METRES. 2. EL100.000 INDICATES FINISHED APPROACH ROAD LEVEL NEAR THE BUILDING. 3. UNDERDECK INSULATION SHALL BE PROVIDED UNDER THE ROOF OF AC PACKAGE ROOM AND OTHER AC AREAS. 4. ALL OUTSIDE SURFACES SHALL BE FINISHED WITH 18MM. THK PLAIN CEMENT PLASTER ON BRICK SURFACES & 6MM THK PLAIN CEMENT PLASTER ON R.C.C. SURFACES, EXCEPT SAND FACE PLASTER WHEREVER MENTIONED. 5. ALL INTERNAL PERIPHERIAL WALLS SHALL BE FINISHED WITH 12MM THK PLAIN CEMENT PLASTER & 12MM/15MM THK PLAIN CEMENT PLASTER ON EITHER SIDE OF INTERNAL WALLS. 6MM THK PLAIN CEMENT PLASTER SHALL BE PROVIDED ON BOTTOM / UNDERSIDE OF ROOF. 6. 1000 WIDE PLINTH PROTECTION WITH BUILDING DRAIN SHALL BE PROVIDED ALL AROUND THE BUILDING. 7. ALL DOORS IN AC AREAS SHALL BE AIR TIGHT. 8. FOR INTERNAL AND EXTERNAL FINISHES, ENGINEERING DESIGN BASIS SHALL BE REFERRED. 9. FOR EXACT COORDINATES, LOCATION RESPECTIVE AREA DRAWING SHALL BE REFERRED. 10. LAN, TELEPHONE, SEATING POSITION IN SHIFT INCHARGE SHALL BE FINALISED INITIALLY TO AVOID REWORK ON PLASTERED SURFACES. 11. PROVISION OF STANDBY CEILING FANS ON WALL TO BE MADE IN ALL THE AREAS.
SHIFT INCHARGE ROOM
FALSE CEILING
PASSAGE
3000
B015-000-81-41-12821
100.450 100.00
100.00
F.R.L
F.R.L
F.F.L
19500
12. OTHER FACILITIES TO BE PROVIDED ARE AS FOLLOWS:
SECTION X-X
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
NORTH ELEVATION
A. A SMALL CHAIR/ SOFA TO BE PROVIDED IN WASH ROOMS/ CHANGE ROOMS. B. INDIVIDUAL LOCKERS WITH PROPER KEY AND LOCK SYSTEM TO BE PROVIDED. C. PROPER SIGNBOARD (HE/SHE, LADIES/GENTS WASHROOM) TO BE DISPLAYED IN ALL WASHROOMS. D. FOR ALL WESTERN/ INDIAN FACILITIES, WATER GUNS/ JET SPRAY TO BE PROVIDED. E. HAND DRIER IN ALL THE WASHROOMS TO BE PROVIDED. F. FOLLOWING FACILITIES IN ALL THE WASHROOMS TO BE PROVIDED. · FULL SIZE MIRROR · LIQUID HAND WASH · BATHROOM FRESHENERS · TOWELS · PROPER LIGHTING FACILITIES · TISSUE ROLLS · VENDING MACHINE FOR SANITARY NAPKINS, SANITARY DISPOSAL DUSTBIN & PAPER WRAPS FOR DISPOSAL IN LADIES WASHROOM
SCHEDULE OF DOORS & WINDOWS TYPE OPENING SIZE FRAME SIZE
100.00 F.R.L
19500
SOUTH ELEVATION
LINTEL DESCRIPTION LEVEL
NOS.
m m6 HT IW ROOD DEZALG . NMLA DETAOC REDWOP AL1 1100x2100 1080x2090 2100 RETTUHS E LGN I S , S SALG DENEHGUOT . KHT
01
m m6 HT IW ROOD DEZALG . NMLA DETAOC REDWOP AL2 1200x2100 1180x2090 2100 RETTUHS E LGN I S , S SALG DENEHGUOT . KHT
01
RETTUHS E LBUOFD1 D , ROO D DEZALG , 1480x2090 DETAR ER I F 2100 RH - 2 1500x2100 . NO I TAC I F I CEP S S ' RERUTCAFUNAM REP SA
01
D1
1100x2100
1080x2090
2100
35mm THK. PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
02
D2
900x2100
880x2090
2100
35mm THK. PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
02
SD1
1200x2100
1180x2090
2100
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, 01 AIR-TIGHT,SINGLE SHUTTER AS/EIL.STD. 7-75-0070
EAST ELEVATION X
E-752.37 N-875.72
D2
HEAVY DUTY FLOORING
2500
1600
F.R.L
FC UD
NHT/CCR UNIT
Y
VITRIFIED TILE FLOORING
BATH
F.R.L. F.F.L.
100.00
DOCMETN/ STORE ROOM
SHIFT INCHARGE ROOM VITRIFIED TILE FLOORING AC FC UD
NON SLIP VITRIFIED TILE FLOORING
2
CAT LADDER
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
= 230 THK BRICK WALL = RCC BLAST RESISTANT WALL
N FC AC UD
AL1
G.LOCKER ROOM
UD
F.F.L
LEGEND:
STEP UP R = 150 T = 300
2
1400
BATH
EQ
NON SLIP VITRIFIED TILE FLOORING
FD1
1600
EQ
G. TOILET
AC PACKAGE ROOM
8500
BATH
100.450
115 900
11500
EQ
WC
EQ
1600
GRANITE FLOORING
FC UD
11.50 3
EQ EQ
3000
Y
FC UD
PASSAGE
D1
NON SLIP VITRIFIED TILE FLOORING
NON SLIP VITRIFIED TILE FLOORING
WC WC
L.LOCKER ROOM
D2
L. TOILET FC UD
45°
WC
1600
1000 WIDE PLINTH PROTECTION (TYP.)
300 DIA EXHAUST FAN AT 3000 HEIGHT WITH RCC HOOD (TYP.)
FIELD ROOM (BLAST RESISTANT) NHT/CCR 19.5X11.5
AC = AIR CONDITIONED (SPLIT TYPE AC) FC = FALSE CEILING UD = UNDERDECK INSULATION
BLAST RESISTANT STRUCTURE
3 19.50
D1
SD1
F.F.L
PASSAGE
VITRIFIED TILE FLOORING
AL2
GRANITE FLOORING
AC FC UD
1000
100.450
1900
DINING ROOM
RAMP UP 1:12
45°
Page 81 of 168
REF. DWG. NO.
B015-000-81-41-12822 TERRACE PLAN, ELEVATION, SECTION & PROFILES OF DOORS
D/W
0 G F E D C B A
100.00 F.R.L 160 dia PVC RWP EMBEDDED IN PCC (TYP.)
4500
3500
4500
750 WIDE RCC GUTTER ABOVE (TYP.) 7000
22.07.19 02.04.19 11.01.19 30.11.18 01.11.18 27.07.18 28.06.18 14.06.18
ISSUED FOR CONSTRUCTION REVISED AND REISSUED FOR ENGG. ISSUED FOR DET. ENGG. REVISED & REISSUED FOR COMMENTS/TENDER ISSUED FOR TENDER REVISED AND REISSUED FOR CLIENTS APPROVAL REISSUED FOR COMMENTS ISSUED FOR COMMENTS
REV. DATE
REVISIONS
SM SM SM SM SM SM SM SM BY
GJK GJK GJK GJK GJK GJK GJK GJK
JS JS JS JS JS JS JS JS
CHKD APPD PEM/PC
19500
KEY PLAN
X
GROUND FLOOR PLAN FIELD ROOM - NHT CCR SCALE
001:1
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
3-1641-0501 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 81 of 168
Page 81 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 1 2 8 2 1 0 A1-841 x 594
REFERENCE DRAWING TITLE
N 1080
1080
1480
1180
1180
880
NOTES:
DEZALG .M NLADETA O CRW O ED P .K H Tm m 6H TW IR O D ELG NIS ,SSALGDENEH G U O T RETT U HS
DEZALG .M NLADETA O CRW O ED P .K H Tm m 6H TW IR O D ELG NIS ,SSALGDENEH G U O T RETT U HS
OPENING SIZE = 1100X2100
,R O DDEZALG ,DETARERIFR H -2 REP SARETT U HS ELB U O D .N OITACIFICEPS S 'RER U TCAFU N M A OPENING SIZE = 1500X2100
2090
2090
2090
2090
2090
1. ALL DIMENSIONS ARE IN MILLIMETRES & LEVELS IN METRES. 2. FOR ALL OTHER NOTES, REFER DWG. NO. B015-000-81-41-12821.
2090
B015-000-81-41-12822
35mm THK. WOODEN PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
35mm THK. WOODEN PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, AIR-TIGHT,SINGLE SHUTTER AS/EIL.STD. 7-75-0070
OPENING SIZE = 1100X2100
OPENING SIZE = 900X2100
OPENING SIZE = 1200X2100
OPENING SIZE = 1200X2100
PROFILES OF DOORS
300
1000
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING (AS/SPECS.) R.C.C. SLAB AS/ STRL. DETAIL
FALSE CEILING
230 300 230
GENTS TOILET 3000
1000
100.00
DOCMETN/ STORE ROOM
100.450
SHIFT INCHARGE RM. 3000
1000
F.F.L
F.R.L
SECTION Y-Y
WEST ELEVATION
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
8500
SLOPE 1:80
3000
1000 HIGH RCC PARAPET WALL (TYP)
11500
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
(SCALE - 1:50)
0 30
Page 82 of 168
REF. DWG. NO.
B015-000-81-41-12821 PLANS, ELEVATIONS & SECTION
1000
CAT LADDER
SLOPE 160 Ø PVC RAIN WATER PIPE (TYP.)
SLOPE
SLOPE
SLOPE
SLOPE
750 WIDE RCC GUTTER (TYP.)
4500
3500
4500 19500
7000
0 22.07.19 ISSUED FOR CONSTRUCTION B 02.04.19 REVISED AND REISSUED FOR ENGG. A 11.01.19 ISSUED FOR DET. ENGG. REV. DATE
REVISIONS
SM SM SM BY
GJK GJK GJK
JS JS JS
CHKD APPD PEM/PC
TERRACE PLAN FIELD ROOM - NHT CCR SCALE
001:1
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
3-1641-0501 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 82 of 168
Page 82 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 1 2 8 2 2 0 A1-841 x 594
Page 83 of 168
Refer attached document for comments marked in. Revised document incorporating comments shall be submitted for approavl.
08-NOV-2019 SUTHAR KETANBHAI (C360) 83 of 168
Page 84 of 168
HINDUSTAN PETROLEUM CORPORATION LIMITED Visakh Refinery Modernization Project Doc Title: Heat Load Calculation for HVAC System Doc No: AV2K20-085-DOC-A001 OWNER’S CONSULTANT & PMC:
ENGINEERS INDIA LIMITED
EPC CONTRACTOR:
MYTHRI INFRA HVAC CONTRACTOR:
ADVANCE VENTILATION PVT LIMITED
0 Rev
10.10.2019
FOR REVIEW
R.L
J.K
S.N
Date
Purpose of Issue
Prepared By
Checked By
Approved By
08-NOV-2019 SUTHAR KETANBHAI (C360) 84 of 168
Page 85 of 168
HEAT LOAD ESTIMATION FOR VRMP
INDEX FOR HEAT LOAD OF SUBSTATION-86 CT & NHT CCR BUILDING SECTION SECTION 1
DESCRIPTION 1.1 General Project Information 1.2 Applicable Codes &Standards
SECTION 2
SECTION 3
SECTION 4
SECTION 5
SECTION 6
PAGE NOS.
1. General Information
2.DesignParameters 2.1WeatherData 2.2IndoorCriteria 2.3Lighting Load, Equipment Load, Fresh air ACPH, Occupancy 3.U-Factors, corrective ETD value for Wall &Roof, Sensible & latent heat load by human being Overall heat transfer co-efficient-Detail Calculation Overall heat transfer co-efficient – Relevant pages from ASHRAE&ISHRAE Corrective ETD value for wall &roof Sensible & latent heat load by human being Corrective ETD value for wall, roof & glass Reference Documents 4.Heat load 4.1.1 Heat load summary for Substation Building 86-CT 4.1.2 Summer, Monsoon & Winter heat load for Substation Building 86-CT 4.2.1 Heat load summary for NHT CCR Building 4.2.2 Summer, Monsoon & Winter heat load for NHT CCR Building
03-05
06-14
15-34
35-69
5. Equipment selection
70-71
6.Architecture Drawing
72-82
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 85 of 168
Page 2 of 82
Page 86 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-1 GENERAL INFORMATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 86 of 168
Page 3 of 82
Page 87 of 168
HEAT LOAD ESTIMATION FOR VRMP
1.1GENERAL PROJECT INFORMATION PROJECT
HPCL VIZAG REFINERY EXPANSION PROJECT
OWNER
HINDUSTAN PETROLEUM CORPORATION LIMITED
HVAC CONTRACTOR
ADVANCE VENTILATION PVT. LTD.
PLANT LOCATION
VISAKHAPATNAM, INDIA
1. SUBSTATION BUILDING- 86 CT
BUILDING
2. NHT CCR BUILDING
building scope for SS-86 is covered under different tender (i.e. 8204). HVAC documents pertaining to that tender need to be submitted separately under respective DCI.
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 87 of 168
Page 4 of 82
Page 88 of 168
HEAT LOAD ESTIMATION FOR VRMP
1.2APPLICATION CODE AND RELEVENT STANDARD LATEST ISSUE ASHRAE (American society of Heating, Refrigeration & Air-conditioning Engineer’s) fundamentals, Systems, Equipment’s & Application Handbook. ISHRAE(Indian society Of Heating Refrigeration & Air Conditioning Engineer’s) Fundamentals, Systems, Equipment’s &Application Handbook For Outdoor & Indoor Design conditions. Ref. document no- (B015-000-80-43-SP-8203, Rev.0, Pg 9-10 ) for NHT CCR Building Ref. document no- (B015-000-80-43-SP-8204, Rev.0, Pg 10 ) for Substation Building- 86 CT
Both above buildings are covered under separate tenders . Hence all documents pertaining to HVAC shall be generated separately for respective tender.
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 88 of 168
Page 5 of 82
Page 89 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-2 DESIGN PARAMETERS
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 89 of 168
Page 6 of 82
Page 90 of 168
HEAT LOAD ESTIMATION FOR VRMP
2.1 WEATHER DATA Design Parameters Name of city
VISAKHAPATNAM
Location(state)
ANDHRA PRADESH
Design outside atmospheric condition for HVAC calculation Season
DBT(0C)
WBT(0C)
RH%
Summer
33.3
27.8
65.8
Monsoon
30.6
27.8
80.6
Winter
18.3
13.9
61.4
for second floor of SS-86 building , insider room temp shall be considered as indicated for SRR as SF of SS-86 houses SRR
2.2 Indoor design condition Room / Area
Design temp DBT(0C)
RH%
Substation Building- 86 CT
26 +/- 1
50 +/- 5
NHT CCR Building
24 +/-1
50 +/- 5
2.3 Lighting Load, Equipment Load, Fresh air ACPH, Occupancy
Lighting Load= 5W/ sq.m
Equipment Load/ Fresh Air ACPH/ Occupancy=
Ref. document no- (B015-000-80-43-SP-8203, Rev.0, Pg 10-11 ) for NHT CCR Building Ref. document no- (B015-000-80-43-SP-8204, Rev.0, Pg 11 ) for Substation Building- 86 CT
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 90 of 168
Page 7 of 82
Page 91 of 168
HEAT LOAD ESTIMATION FOR VRMP
DESIGN PARAMETERS SUBSTATION-SS 86 CT BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 91 of 168
Page 8 of 82
Page 92 of 168
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR PLANT & NON PLANT BUILDING WORKS
DOCUMENT No. B015-000-80-43-SP-8204 Rev. 0 Page 10 of 18
y) All Instruments, Controls and safety devices (Contractor to attach list of controls and safety devices) including all necessary interlocks, control panel, cabling, wiring etc. as detailed in the Instrumentation Specifications attached elsewhere. z) Electrical work/items as per Electrical specifications attached elsewhere. aa) Self standing/ wall mounted audio-visual annunciation panel. bb) Plant room ventilation system. 3.2.3
The entire work of design, engineering, manufacture, installation, commissioning and performance testing of equipment/systems shall be executed by one of the roved vendor for HVAC work.
3.2.4
Contractor shall develop the complete HVAC system configuration and submit for
3.2.5
Contractor shall be solely responsible to demonstrate the specified inside conditions throughout the year irrespective of any variation in the outside condition.
3.2.6
DESIGN DATA
3.2.6.1 Outside Design Condition SEASON
DBT (ºC)
WBT (ºC)
Summer
33.3
27.8
Monsoon
30.6
Winter
18.3
Air Quantity (As per Class GX (severe) of ANSI/ISAS71.04) H2S
50 ppb
27.8
SO2/SO3
300 ppb
13.9
Cl2
10 ppb
NOX
1250 ppb
Notes: 1. Outdoor design condition mentioned above shall be followed for AC heat load calculation purpose.
3.2.6.2
Inside Design Conditions S. No.
1. 2. 3.
Area
DBT, °C
SRR Building (area to be air-conditioned) Switch Gear Hall & Operator Room of Sub Station building Scale Room Building (For Split ACs)
% RH
23 ± 1
50 ± 5
26 ± 1
50 ± 5
24 ± 1
30 to 70
08-NOV-2019
Air Quality (As Per Class G1(mild) of doc. ISA -571.04) H2S < 3 ppb SO2/SO3 < 10 ppb Cl2 < 1 ppb NOx < 50 ppb Not Applicable
Copyright EIL
Format No. EIL 1641-1924 Rev. 1
SUTHAR KETANBHAI (C360) 92 of 168
Page 9 of 82
All rights reserved
Page 93 of 168
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR PLANT & NON PLANT BUILDING WORKS
3.2.6.3
DOCUMENT No. B015-000-80-43-SP-8204 Rev. 0 Page 11 of 18
Other Design Requirements Description Under Deck Insulation
Requirement Thermal insulation shall be provided for the areas to be air-conditioned, packaged AC Rooms and AHU Rooms. Fouling factor for water cooled 0.0004 hr.m².ºC/kcal Condenser Refrigerant (for VCR based AC R-134a or R-407a or R-407c or R-410a System) Hours of operation 24 hrs / 365 Days Lighting Load 5 Watts/m2 Outdoor Fresh Air 2.0 ACPH for Substation building & 1.5 ACPH for SRR Building Equipment Heat Dissipation As per Below Table Occupancy As per Below Table Table: Elect/Instru. Equipment Heat Dissipation & Occupancy Building Room/Area to Eqpt. Heat Occupancy be Air Load Conditioned (Elec.+Instru.) (Nos.) (kW) 1 Sub Station-96 Switch Gear Hall 97.0* -(Tankages) Operator Room 1.0* 4 2 Sub Station-86 Switch Gear Hall 111.0* -(Cooling Tower) Operator Room 1.0* 4 Rack Room 44.0 3 UPS Room 9.0 -Tech. Room 1.0 4 Engg. Room 1.0 3 Lobby --UPS Room 11.0 -Tech. Room 1.0 4 Engg. Room 1.0 3 Lobby --3 SRR-Tankages Rack Room 44.0 3 UPS Room 9.0 -Tech. Room 1.0 4 Engg. Room 1.0 3 Lobby --4 SRR- New Flare & Rack Room 53.0 3 Blending station Engg. Room 1.0 3 UPS Room 8.6 -Lobby --*: Equipment Heat Load mentioned includes heat load due to lighting also, Hence while calculating heat load for that particular area, lighting load shall not be considered. Sr. No.
3.2.7
Air conditioning system load/ capacities specified in Scope of Work & Supply are minimum to be considered by the contractor for HVAC equipment and same is given for estimation purpose only. Contractor shall submit the detailed heat load calculations as per the approved/ AFC building drawings and equipment
08-NOV-2019
Copyright EIL
Format No. EIL 1641-1924 Rev. 1
SUTHAR KETANBHAI (C360) 93 of 168
Page 10 of 82
All rights reserved
Page 94 of 168
HEAT LOAD ESTIMATION FOR VRMP
DESIGN PARAMETERS NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 94 of 168
Page 11 of 82
Page 95 of 168 Page 1088 of 1419
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR CONSTRUCTION OF FIELD ROOM & MSC. CIVIL WORKS
DOCUMENT No. B015-000-80-43-SP-8203 Rev. 0 Page 9 of 18
viii) Supply and fixing of steel supports for duct/cable/pipe/tubing etc. ix) Breaking and making good of openings in wall. x) Temporary scaffolding related to erection, testing and commissioning.
3.1.4
o)
Structural steel works as required for equipment support and base frame of equipment.
p)
Electrical panels and electrical works as per Electrical Specification attached elsewhere in the tender.
q)
Self standing/ wall mounted audio-visual annunciation panel.
Each air conditioning system with Inverter Controlled Split Air Conditioners for CWTP Field Room building and Auxiliary Fire station Building shall comprise of but not limited to the following: a)
Inverter controlled split air conditioner complete with all accessories, fittings and voltage stabilizer with time delay relay. Split unit shall have wall mounted indoor unit and remotely located air cooled condenser (outdoor unit) with insulated refrigerant piping, Controls and line accessories, Initial charge of refrigerant, Electrical and civil works (e.g. civil work related to concealing of refrigerant piping, condensate piping to the nearest drain, cabling in AC space and outside upto the outdoor unit) as required including the structural steel framework, pedestal to mount the indoor/outdoor units, supports for indoor/outdoor units, supports & clamps for refrigerant piping/cables, stabilizer, hold down nuts & bolts.
b)
Spares for commissioning and start up.
3.1.5
The entire work of design, engineering, manufacture, installation, commissioning and performance testing of equipment/systems shall be executed by one of the owner’s/EIL approved vendor for HVAC work (attached elsewhere in the tender). The list of acceptable sub-vendors for bought out items for HVAC System has also been tabulated in cl. no. 10.0 below for consideration by HVAC Contractor.
3.1.6
Contractor shall develop the complete HVAC system configuration and submit for Owner/EIL’s approval before starting the detail engineering work.
3.1.7
Contractor shall be solely responsible to demonstrate the specified inside conditions throughout the year irrespective of any variation in the outside condition.
3.1.8
DESIGN DATA
3.1.8.1 Outside Design Condition SEASON
DBT (ºC)
WBT (ºC)
Summer
33.3
27.8
Monsoon
30.6
27.8
SO2/SO3 ≤ 300 ppb
Winter
18.3
13.9
Cl2
≤ 10 ppb
NOX
≤ 1250 ppb
08-NOV-2019 Format No. EIL 1641-1924 Rev. 1 SUTHAR KETANBHAI (C360)
Air Quantity (As per Class GX (severe) of ANSI/ISAS71.04) H2S
≤ 50 ppb
Copyright EIL – All rights reserved
95 of 168
Page 12 of 82
Page 96 of 168 Page 1089 of 1419
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR CONSTRUCTION OF FIELD ROOM & MSC. CIVIL WORKS
DOCUMENT No. B015-000-80-43-SP-8203 Rev. 0 Page 10 of 18
Notes: 1. Outdoor design condition mentioned above shall be followed for AC heat load calculation purpose. 2. Design temperature for sizing of air cooled exchanger/condenser shall be 450C (peak ambient temperature).
3.1.8.2
Inside Design Conditions S. No.
1.
2.
3.
3.1.8.3
Sl. Area
DBT, °C
Switch Gear Hall & Operator Room of Sub Station building Shift-in-charge & Dining room of Field Room Buildings CWTP Field Room & Auxiliary Fire Station Building (For Split ACs)
% RH
26 ± 1
50 ± 5
24 ± 1
50 ± 5
Air Quality (As Per Class G1(mild) of doc. ISA -571.04) H 2S < 3 ppb SO2/SO3 < 10 ppb Cl2 < 1 ppb NOx < 50 ppb
24 ± 1
30 to 70
Not Applicable
Other Design Requirements Description Under Deck Insulation
Requirement Thermal insulation shall be provided for the areas to be air-conditioned, packaged AC Rooms and AHU Rooms. Fouling factor for water cooled 0.0004 hr.m².ºC/kcal Condenser Cooling water inlet temperature 33°C Design temperature for sizing Air 45°C cooled exchanger/condenser Refrigerant (for VCR based AC R-134a or R-407a or R-407c or R-410a System) Hours of operation 24 hrs / 365 Days Lighting Load 5 Watts/m2 Outdoor Fresh Air a. 2.0 ACPH or 17 CFM per person whichever is higher for Substation building & b. 1.0 ACPH or 17 CFM per person whichever is higher for Field Room buildings Equipment Heat Dissipation As per Below Table Occupancy As per Below Table
Sr. No.
Table: Elect/Instru. Equipment Heat Dissipation & Occupancy Building Room/Area to Eqpt. Heat Occupancy be Air Load Conditioned (Elec.+Instru.) (Nos.)
08-NOV-2019 Format No. EIL 1641-1924 Rev. 1 SUTHAR KETANBHAI (C360)
Copyright EIL – All rights reserved
96 of 168
Page 13 of 82
Page 97 of 168 Page 1090 of 1419
JOB SPECIFICATION (EQUIPMENT DIVISION) FOR CONSTRUCTION OF FIELD ROOM & MSC. CIVIL WORKS
DOCUMENT No. B015-000-80-43-SP-8203 Rev. 0 Page 11 of 18
(kW) 1
Sub Station-92
2
Sub Station-98
3
Each Field Room (Having Water cooled PAC System)
Switch Gear Hall Operator Room Switch Gear Hall Operator Room Shift-in-charge Room Dining Room
73.0* 0.7* 40.0* 0.7* 1.0
-6 -6 6
--
6
*: Equipment Heat Load mentioned includes heat load due to lighting also. Hence while calculating heat load for that particular area, lighting load need not to be considered. However, for other buildings / areas, lighting load shall be considered as specified in this job specification. 3.1.9
Air conditioning system load/ capacities specified in Scope of Work & Supply are minimum to be considered by the contractor for HVAC equipment and same is given for estimation purpose only. Contractor shall submit the detailed heat load calculations as per the approved/ AFC building drawings and equipment shall be selected for the higher of the two capacities i.e. capacities as per Scope of Work and capacities as per approved heat load calculation. No price or time implication shall be admissible to the contractor due to increase in heat load values provided equipment heat dissipation & air-conditioned area remain the same. Also, no price or time implication shall be admissible to the contractor on account of selection of higher capacity machine due to nonavailability of required/ exact capacity machine in the market. Contractor shall be solely responsible to demonstrate the specified inside conditions throughout the year irrespective of any variation in the outside condition. Accordingly, Contractor shall cross check the estimated plant capacity in his own interest before accepting the same. In case, Contractor desires to increase the plant capacity, he shall furnish adequate technical reasons and necessary technical data including heat load calculations in support of such increased plant capacity during pre-bid meeting. However, minimum capacity of the plant shall be as indicated in the Scope of Work & Supply, which shall be complied by the contractor.
3.1.10 Chemical filtration shall be provided in fresh air circuit of AC system (installed in AHU Room/ Packaged AC room) to maintain air quality (G1 environment) inside satellite rack room/ substation. Chemical filters shall be selected to capture Group-A gases as per ISA-71- 04 standard (from GX environment at outside to G1 environment at inside). 3.1.11 Air Conditioning equipment shall be interlocked with gas/smoke detection and firefighting systems. For Satellite Rack Room, required Hydrocarbon Detection System shall also be provided in AC suction and in ducts as per OISD standard. 3.1.12 Contractor shall consider heat dissipation from electrical/electronic equipment, Lighting Load & Occupancy while estimating the capacity of air-conditioning system. 3.1.13 Safety factor shall be considered as minimum 12.5% in respect of Room Sensible Heat and minimum 10% in respect of Room Latent Heat. 3.1.14 Packaged Units/ AHUs shall provide cooling and dehumidification in summer/monsoon by handling mixture of fresh and return air. Reheating shall be 08-NOV-2019 Format No. EIL 1641-1924 Rev. 1 SUTHAR KETANBHAI (C360)
Copyright EIL – All rights reserved
97 of 168
Page 14 of 82
Page 98 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-3 U-VALUE CALCULATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 98 of 168
Page 15 of 82
Page 99 of 168
HEAT LOAD ESTIMATION FOR VRMP
U-FACTOR SUMMARY ASHRAE Description
U- Value--BTU/(hr)(ft².°F)
External wall - Solid Brick wall - 230mm thick
0.36
External wall - RCC Concrete wall - 230mm thick
0.48
Partition wall - Solid Brick wall - 230mm thick
0.32
Exposed Roof - RCC 150mm thick+50mm Insulation
0.11
Floor - RCC 150mm thick(Without Underdeck Insulation)
0.36
Ceiling - RCC 150mm thick(Without Underdeck Insulation)
0.29
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 99 of 168
Page 16 of 82
Page 100 of 168
HEAT LOAD ESTIMATION FOR MREP
U-Value calculation 1
External wall - Solid Brick wall - 230mm thick Thickness
Density
mm
kg/m3
Layer
Thermal Conductivit y W/m.K
R-Value
R-Value
(m².K)/W
(hr.ft².°F)/BTU
0.12
0.68
Reference
a
Inside vertical surface resistance (Air film)
b
Cement plaster, sand aggregate
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
c
Solid Brick Wall
230
1920
0.81
0.28
1.61
ASHRAE Fundamentals Handbook, Table 1
d
Cement plaster, sand aggregate
18
1860
0.72
0.03
0.14
ASHRAE Fundamentals Handbook, Table 1
0.04
0.25
ASHRAE Fundamentals Handbook, Table 10
0.49
2.78
2.04
0.36
R-Value
R-Value
(m².K)/W
(hr.ft².°F)/BTU
0.12
0.68
e
Outside surface resistance U-VALUE
2
ASHRAE Fundamentals Handbook, Table 10
Partition wall - Solid Brick wall - 230mm thick Thickness
Density
mm
kg/m3
Layer
Thermal Conductivit y W/m.K
Reference
a
Inside vertical surface resistance (Air film)
b
Cement plaster, sand aggregate
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
c
Solid Brick Wall
230
1920
0.81
0.28
1.61
ASHRAE Fundamentals Handbook, Table 1
d
Cement plaster, sand aggregate Inside vertical surface resistance (Air film)
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
0.12
0.68
0.56
3.16
1.79
0.32
e
U-VALUE
MUMBAI REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 100 of 168
Page 17 of 82
ASHRAE Fundamentals Handbook, Table 10
ASHRAE Fundamentals Handbook, Table 10
Page 101 of 168
HEAT LOAD ESTIMATION FOR MREP
3
External wall - RCC Concrete wall - 230mm thick Thickness
Density
Thermal Conductivity
R-Value
R-Value
mm
kg/m3
W/m.K
(m2.K)/W
(hr.ft2.°F)/BTU
0.12
0.68
Layer a b c
Reference
Inside vertical surface resistance (Air film)
ASHRAE Fundamentals Handbook, Table 10
Cement plaster, sand aggregate
12
1860
0.72
0.02
0.09
ASHRAE Fundamentals Handbook, Table 1
RCC Concrete Wall
230
2400
1.4
0.16
0.93
ASHRAE Fundamentals Handbook, Table 1
d
Cement plaster, sand aggregate
18
1860
0.72
0.03
0.14
ASHRAE Fundamentals Handbook, Table 1
e
Outside surface resistance
0.04
0.25
ASHRAE Fundamentals Handbook, Table 10
0.37
2.10
2.70
0.48
R-Value
R-Value
(m2.K)/W
(hr.ft2.°F)/BTU
0.16
0.92
U-VALUE 4
Exposed Roof - RCC 150mm thick+50mm Insulation Layer
Thickness
Density
mm
kg/m3
Thermal Conductivity W/m.K
Reference
a
Indoor air film, still air, horizontal surface, downward heat flow
b
Underdeck Insulation(Mineral Wool)
50
16-48
0.04
1.25
7.10
ASHRAE Fundamentals Handbook, Table 1
c
RCC
150
2400
1.4
0.11
0.61
ASHRAE Fundamentals Handbook, Table 1
d
Light Weight Aggregate
20
960
0.3
0.07
0.38
ASHRAE Fundamentals Handbook, Table 1
0.04
0.25
ASHRAE Fundamentals Handbook, Table 10
1.77
10.02
0.57
0.10
e
Outside surface resistance U-VALUE
MUMBAI REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 101 of 168
Page 18 of 82
ASHRAE Fundamentals Handbook, Table 10
Page 102 of 168
HEAT LOAD ESTIMATION FOR MREP
5
Floor - RCC 150mm thick(Without Underdeck Insulation) Layer
a b
Thickness
Density
mm
kg/m3
Thermal Conductivity W/m.K
R-Value
R-Value
(m2.K)/W
(hr.ft2.°F)/BTU
0.11
0.62
Indoor air film, still air, horizontal surface, upward heat flow RCC
150
c
Light Weight Aggregate
50
d
Indoor air film, still air, horizontal surface, upward heat flow
ASHRAE Fundamentals Handbook, Table 10
2400
1.4
0.11
0.61
ASHRAE Fundamentals Handbook, Table 1
960
0.3
0.17
0.95
ASHRAE Fundamentals Handbook, Table 1
0.11
0.62
0.49
2.80
2.03
0.36
R-Value
R-Value
(m2.K)/W
(hr.ft2.°F)/BTU
0.16
0.92
U-VALUE 6
Reference
ASHRAE Fundamentals Handbook, Table 10
Ceiling - RCC 150mm thick(Without Underdeck Insulation) Layer
Thickness
Density
mm
kg/m3
Thermal Conductivity W/m.K
Reference
a
Indoor air film, still air, horizontal surface, downward heat flow
b
RCC
150
2400
1.4
0.11
0.61
ASHRAE Fundamentals Handbook, Table 1
c
Light Weight Aggregate
50
960
0.3
0.17
0.95
ASHRAE Fundamentals Handbook, Table 1
d
Indoor air film, still air, horizontal surface, downward heat flow
0.16
0.92
0.60
3.40
1.67
0.29
U-VALUE
MUMBAI REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 102 of 168
Page 19 of 82
ASHRAE Fundamentals Handbook, Table 10
ASHRAE Fundamentals Handbook, Table 10
Page 103 of 168
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
01234678429 7 381 938 797 796
171 2318728 18371
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
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 W1 m8737 9 op tpuvwx u vwxpt o{puovwx \1z1819m1 j9 2379231'8-672 |}cd~bcdecbb 3%=547"7%##))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)M K %"%&.:BB:0 A)Q#!M): B)BCV#!B)BCM >!"%&5%'#"".:B//0 @)M#!/: B)BCB#!B)BCh >!"%&5%'#"".:B//0 /h#!/C B)BhA#!B)Bh@ >!"%&5%'#"".:B//0 :: B)Bhh >!"%&5%'#"".:B//0 _!'G%&63%;+!!37%##))))))))))))))))))))))))))))))))))))))))))))))))))))) B)M K %"%&./@@V0 h:#!hA B)BhV#!B)BhA J&%&5%'#"".:B//0 CQ B)Bhh#!B)BhQ J&%&5%'#"".:B//0 `4&"%3+!!3-53#6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /V#!CM B)BCB gES<.:BBV0-
E!"%&5%'#"".:B//0 %;6/MB6%1)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) ::#!QM B)B:@ J&%&5%'#"".:B//0 "!(%&("!6'#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) hB B)BhB J&%&5%'#"".:B//0 %;6Q1%"%#:Cg)))))))))))))))))))))))))))))))))))))))))))))))))))))) h:#!hQ BBhB J&%&5%'#"".:B//0 73!+&+4#$3!+;3!7%3+%" 4&;(!#%3.L0.Q0 73!+4&;%;))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)BhQ#!B)BhV J&%&5%'#"".:B//0 ?(%&66(!31#1"&-!3667%6))))))))))))))))))))))))))))))))) /)Q K %"%&./@@V0 /V#!:C B)BhQ#!B)BhA E&6(&6##"(!"#.:BBM0 :@ B)Bhh E&6(&6##"(!"#.:BBM0 `4&"%3547"7!%"6-+#53#6))))))))))))))))))))))))))))))))))))))))))))) /VB B)BhA B)M K %"%&./@@V0 _!'G+!!37!%"6))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)M K %"%&./@@V0 53!!"%&6+%33))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) VC#!/hB B)Bhh#!B)BhV >4,%&5%'#"".:B//0 "!!54&;)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/VB#!/MB) B)Bh@#!B)BC: B)M >4,%&5%'#"".:B//0 B)V#!B)M O'!#4'%3#43)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) hCB#!hAB B)BQ:#!B)BQh L"34#7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /CB B)BQ: J&%&5%'#"".:B/B0 L!314!'1%&"%#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /)Q K %"%&./@@V0 &5%'6-%;6("g%&Tgabcdecfe
Page 20 of 82
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
°
±iq6[0\6Z029 o²9 21932 u[jx X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 op tpuvwx u vwxpt o{puovwx \1z1819m1 B)B:B#!B)B:h J&%&5%'#"".:B//0 /)C
E!"%&5%'#"".:B//0 /@#!:V B)Bh@#!B)BCB >!"%&5%'#"".:B//0 QV B)Bh@#!B)BCB J&%&5%'#"".:B//0 h:#!VC B)Bh@#!B)BCQ /)/ .`%&5%'#""-(":BB/0 VC#!/:B B)BCQ#!B)BQ: .`%&5%'#""-(":BB/0 / : B # ! / M B B ) B Q : # ! B ) B V / .`%&5%'#""-(":BB/0 3%547"6 %##4'-·/BB#!VBB ))))))))))))))))))))))))))))))))))))))))))))))))) V)C#!M)B B)BQ:#!B)BQQ >!"%&5%'#"".:B//0 %##4'-·VBB#!//BB )))))))))))))))))))))))))))))))))))))))))))))))) M#!@)V B)BC@#!B)BQ: >!"%&5%'#"".:B//0 '3!6%##4'!"+%33'%,4#4)))))))))))))))))))))))))))))))))))))))))))) :@#!hA B)BhQ#!B)BhV >!"%&5%'#"".:B//0 _!'G%&63%;+!!36 %##4'-·@B#!//Q )))))))))))))))))))))))))))))))))))))))))))))))))))) :C#!:V B)BC@ N$"%&5%'#"".:B//0 %##4'-·/:Q#!ChB )))))))))))))))))))))))))))))))))))))))))))))))))) :C#!:@ B)BCV#!B)BCM N$"%&5%'#"".:B//0 '3!6%##4'!"+%33'%,4#4)))))))))))))))))))))))))))))))))))))))))))) VC B)Bh@#!B)BC: N$"%&5%'#"".:B//0 ¸" 4'34#-?5!34%#6))))))))))))))))))))))))))))))))))))))))))))))))))))))))//:#!/h/ B)BVM /)h <%74&#%3)./@AQ0 VC#!@V B)BVh `%&5%'#"".(":BB/0 a¹fcº»c¹¹}µe g333!-("%164!!(&+%33'%,4#4)))))))))))))))))))) :V#!C: B)Bh@#!B)BCB N+!%&5%'#"".:B//0 3%547"-("%164!!(&+%33!"%##4''%,4#4)))))) /V B)Bh@#!B)BC: `%&5%'#""F%!'4%#4!&.:B//0 :@#!hA B)Bhh#!B)BhA >!"%&5%'#"".:B//0 L!31"#$%&5!% )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /)Q K %"%&.:BB:0 3!+6&4#1-!(&'33)))))))))))))))))))))))))))))))))))))))))))))))))))) A):#!/B B)BhA#!B)BC: N$"%&5%'#"".:B//0 64 6&4#1-'3!6'33-%;6/MB6%1)))))))))))))))))) hB#!Q/ B)B:B#!B)B:@ >4,%&5%'#"".:B//0 7 79 28 29 [7 79 |cfe O7#!T' 7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@BB B)QA /)BB
!##%;./@CA0 g 7!%"6))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) //QB B):Q B)MC K %"%&.:BB:0 >47"T' 7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /CBB B):Q B)MC K %"%&.:BB:0 /BBB B)/@ B)MC K %"%&./@@V0 CBB B)BA /)MM K %"%&./@@V0 hBB B)BV /)MM K %"%&./@@V0 1( !"(3%#"7!%"6))))))))))))))))))))))))))))))))))))))))))))))))))))) VCB B)/V /)/Q K %"%&.:BB:0 J"46#"%&67!%"6.J<S0)))))))))))))))))))))))))))))@#!// VQB B)// /)MM K %"%&.:BB:0 )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/:)A VQB B)/: /)MM K %"%&.:BB:0 L31+!!6.6!;3%54"0))))))))))))))))))))))))))))))))))))))))))))/:)A CVB B)/C /)MM K %"%&.:BB:0 )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/Q)@ QCB B)/Q /)MM K %"%&.:BB:0 L31+!!6T+!!6(%&3))))))))))))))))))))))))))))))))))))))))))))/@)B CQB B)/@ /)MM K %"%&.:BB:0 ¸;#%73547"7!%"6 VQB B)// /)MM K %"%&.:BB:0 $%#$4&;-";3%"6&4#1))))))))))))))))))))))))))))))))/:)A :@B B):h /)hB +4./@VA0 4" 64%#6&4#1)))))))))))))))))))))))))))))))))))/:)A hQB B)/@ /)hB +4./@VA0 &%43=7%6$%#$4&;))))))))))))))))))))))))))))))))))))))))/:)A CBB B)/@ /)hB $4&;37%'G"))))))))))))))))))))))))))))))))))))))))))))))))))))@)Q :@B B)/A /)hB !&66%6&4&;7!%"6))))))))))))))))))))))))))))))))))))/:)A :CB B):C /):V #43%&63%1=4&(%&3-(3%4&!"%'!#4' :@B B)BQM B)Q@ 3% 4&%#6(%("7!%"6 CMB B)BA: /)hM +4./@VA0 $! !;&!7!%"65"! "(3(6(%(" CMB B)BA: /)/A *%"67!%"6 64 6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) MBB B)/BQ /)hB +4./@VA0 $4;$6&4#1-",4'=# ("6;"%6%&6",4';"%6 MMB B)/: /)hC +4./@VA0 $4;$6&4#1-#%&6%"6=# ("6;"%6)))))))))))))))))))))))))) /B/B B)/CC /)hC +4./@VA0 L%"#4'37!%"6 3!+6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) Q@B B)/B: /)hB +4./@VA0 64 6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) MBB B)/hQ /)hB +4./@VA0 $4;$6&4#1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /BBB /)/M +4./@VA0 &6"3%1 ))))))))))))))))))))))))))))))))))))))))))))))))))/Q)@ VCB /):: /):/ +4./@VA0 %5"7!%"6)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) ABB B)BA: /)MM K %"%&./@@V0 a¼µd½} O7#!T' )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@BB B)BhA !!6-CBB -/@B ?(!")))))))))))))))))))))))))))))))) B)/Q /)hB !!6-6!73-CBB -hBB ?(!"))))))))))))))))))) B):/ /)/A !!6-(34&)7%'G"7!%"6)))))))))))))))))))))))))))))))M B):Q /)hB aµeµd½ O7#!T' -3%((6))))))))))))))))))))))))))))))))))V)C B)BhA /)B/ O($%3#"!33464&;))))))))))))))))))))))))))))))))))))))))))))))))))))))))) B)B:V /)CA O($%3#4&3%#4&;464&;./:)A 760)))))))))))))))))))))) B):V /)CA W1 m8737 9 L$&!34'5!% 7!%"6+4#$5%'"-%;6)))))))))))))))))))))))))))))))) ³´µ}} g333!547"-3!!5433))))))))))))))))))))))))))))))))))))))))))))))))))))) %##4'%((34'%#4!&(#!/BB )))))))))))))))))))))))))))))))))))))) %##4'%((34'%#4!&¶/BB )))))))))))))))))))))))))))))))))))))))))))) +%33%((34'%#4!&-6&(%'G6)))))))))))))))))))))))))))))))))))))) L"34#-?(%&66)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))
Page 104 of 168
08-NOV-2019 SUTHAR KETANBHAI (C360) 104 of 168
Page 21 of 82
Page 105 of 168
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
01234678429 7 381 938 797 796
171 2318728 18371
Æ
X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx W1 m8737 9 *%"67!%"6464&;)))))))))))))))))))))))))))))))))))))))))))))))// !!6-6"!(-:BB ))))))))))))))))))))))))))))))))))))))))):Q !!6-7,3 :BB -3%((6))))))))))))))))))))))))))))))))))))))))))/h :QB -3%((6))))))))))))))))))))))))))))))))))))))))))/@ !!6-(31+!!6-3%((6))))$))-)4)))))))))))))))))))))))))))))@)Q O3 4& -#3-!",4&13- !,"$%#$4&;))))))))))))))))) $!33!+=7%'G6))))))))))))))))))))))))))))))))))))))))))))))))))))))) 4&3%#4&;=7!%"6=7%'G6)))))))))))))))))))))))))))@)Q 5!43=7%'G6))))))))))))))))))))))))))))))))))))))))))))))))@)Q O"'$4#'#"%3.!6%=34 53!%#0;3% 7 7918291 ¸%(!"=(" %7353#)))))))))))))))))))))))))))))))))):))))))))))))))))))))))))) ¸%(!"Ç%3-:3%1"!5!((6B)AhG;T 53#))))))))))))))))) ¸%(!"Ç%3-(3%#4'543 ))))))))))))))))))))))))))))))))))))))))))))))))))))))) ²797 Ȳ 879231872 g%"(#%&6"7!&66"#$%&(%6))))))))))))))))))))))))/@ g%"(#%&6"77"(%6.!&=(4'0))))))))))))))))))))))))@)Q L43'%"(#+4#$"77"(%6)))))))))))))))))))))))))@)Q#!/:)A 4&!3 T'!"G#43))))))))))))))))))))))))))))))))))))))))))))))))))V)C L¸gT"77"53!!"'!,"4&;)))))))))))))))))))))))))))))))))))))))))))))))))) "77"#43)))))))))))))))))))))))))))))))))))))))))))))))))))))))))):Q #""%RR!)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):Q 132 .<g$%(#"hh-N%73h0 \ z79 O7#!T' $4&;3)))))))))))))))))))))))))))))))))))))))))))))))))))) O($%3#.74# &+4#$4&"#54330))))))))))))))))))))))))))))))))))))))))) O($%3#"!33"!!54&;))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) O($%3#$4&;3)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) S43#=("!!54&;)))))))))))))))))))))))))))))))))))))))))))))))))))))))/B `%#4'%($%3#.$%,1-:BD;"4#0)))))))))))))))))))))))))))))))))))))))) _6#$%#'$)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) _!!54&;53#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) <3%#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/h <#"%+#$%#'$))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) !!6$4&;3-(3%4&%&6(3%#4'=543=5%'6))))))))))))))))))))))) 2 31879231872 g (3%#"-%&6%;;";%#))))))))))))))))))))))))))))))))))))))))))) <%&6%;;";%#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))/B ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):B 1( (3%#")))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) 4;$#+4;$#%;;";%#)))))))))))))))))))))))))))))))))))))))))))))/h ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/V !&#%33%#$))))))))))))))))))))))))))))))))))))))))))))))))))))))/@ L"34#%;;";%#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) <%&6%;;";%#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) !&#%33%#$))))))))))))))))))))))))))))))))))))))))))))))))))))))/@ ¸" 4'34#%;;";%#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 op tpuvwx u vwxpt o{puovwx \1z1819m1 B)/: /)/A B)/C /)/A B)/C /)/A B)/M /)/A B)/B /):: B)// /)::4 B)h: /)hC B)Q: :QBB /)B B)MC B)B// B):/
;34;473 //B B)C:
E
L"34#(3%#"))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) L3(7!%"6!"(%("(3%#"))))))))))))))))))))))))))))))))))))))))))))))))))) <%&6T' (3%#"-'!&64#4!&6)))))))))))))))))))))))))))))))))))))))) <%&6T' T34(3%#"-'!&64#4!&6)))))))))))))))))))))))))))))))) <%&6T;1( .hÇ/0(3%#"-'!&64#4!&6)))))))))))))))))))))))))))))) 2 98n231872 ÉcdfºÊdµb S"4'G-54"6'3%1))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) :CBB ::CB :BMB /@:B
B)Ch B)QM /)/Q B)/@ B)B@ /):B B)BA B)A: B)hM B)CV A:B A:B B):: B)M/ B)/C B):B B):Q B):V B)hB B)BM B)/@ B)BA B)Vh B)CM B)VQ
B)BhA B)B:A B)BAM B)BQ@ B)BB@ B)/VV B)B/h B)B:V B)BMh B)B:h
/)BB /)Q/ /):V /)CA /):V /)hB B)MC B)MC B)MC B)BQV B)BVV /)hC B)MC
/):/#!/)CA /)BA#!/)hB B)@:#!/)/: B)M/#!B)@M
B)MB
08-NOV-2019 SUTHAR KETANBHAI (C360) 105 of 168
Page 22 of 82
gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 gES<.:BBV0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
i±
±iq6[0\6Z029 o²9 21932 u[jx X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 op tpuvwx u vwxpt o{puovwx \1z1819m1 /AVB B)A/#!B)MQ ¸%3!"./@MM0 /VBB B)V/#!B)AC ¸%3!"./@MM0 /CCB B)Q:#!B)V: ¸%3!"./@MM0 /:MB B)Ch#!B)Qh ¸%3!"./@MM0 //:B B)hV#!B)CQ ¸%3!"./@MM0 B)/C B)MM _!+31%&6O3;"&./@hA0 B):B _!+31%&6O3;"&./@hA0 B):A _!+31%&6O3;"&./@hA0 B)hh _!+31%&6O3;"&./@hA0 B)h@ _!+31%&6O3;"&./@hA0 B)CC _!+31%&6O3;"&./@hA0 MBB B):B K %"%&./@@V0 AAB B):: K %"%&./@@V0
W1 m8737 9
g3%1#43-$!33!+ /'336())))))))))))))))))))))))))))))))))))))))))))))))))))))))))AQ ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))/BB :'336())))))))))))))))))))))))))))))))))))))))))))))))))))))/QB )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):BB )))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))):QB h'336())))))))))))))))))))))))))))))))))))))))))))))))))))))hBB 4;$#+4;$#7"4'G)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) ËdÌfb}Ì~5-; 4#!&%;;";%# ·:BB -/V)hG;-::BBG;Th'!&'"#-:'!"))))))))) +4#$("34#=54336'!")))h))))))))))))))))))))))))))))))))))))))))) ·hBB -:QG;-::BBG;T '!&'"#-:'!")))))))))))) +4#$("34#=54336'!"))))))))))))))))))))))))))))))))))))))))))))
!" %3=+4;$#%;;";%#.%&6%h&6;"%,30 ·:BB -/VG;-:/BBG;T '!&'"#-:!"h'!"Í +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!"h)))))))))))))))))))))))))))))))))))) ·hBB -::)AG;-:BBBG;T '!&'"#-:'!"))))))) `64 =+4;$#%;;";%#.'! 74&%#4!&h!5&!" %3%&634;$#+4;$#%;;";%#0 ·:BB -/hG;-/QQB#!/MBBG;T '!&'"#-:!"h'!" +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!")))))))))))))))))))))))))))))))))))) +4#$!366=L<=54336.7%60'!"))))))))))))))))))))) +4#$!366L<4&"#4&'!")))))))))))))))))))))))))))) !+= %%;;";%#.?(%&66$%:3-'3%1-3%#!"3%;-( 4'0 ·/QB -A/T:G;-/CBBG;T '!&'"#-:!"h'!" +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!"))))))))))))):))))))))))))))))))))))) :BB -M#!/BG;-//QB#!/hMBG;T '!&'"#))))) +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!")))))))))))))))))))))))))))))))))))) +4#$!366=L<=54336.7%60'!"))))))))))))))))))))) +4#$>5!% =54336'!"))))))))))))))))))))))))))))))))))))))) +4#$!366L<4&"#4&'!")))))))))))))))))))))))))))) hBB -/VG;-/CBBG;Th-'!&'"#-:!"h'!")))) +4#$("34#=54336'!")))))))))))))))))))))))))))))))))))))))))))) +4#$," 4'34#=54336'!")))))))))))))))))))))))))))))))))))) <#!&-34-!"%&6))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) :MMB /B)C Î%"#R4#4'%&6%&6#!&)))))))))))))))))))))))))))))))))))))))))))))))))))))) :QVB V): ::CB h)CV /@:B /)MM g%3'4#4'-6!3! 4#4'-34#!&-%"73-%&6;"%&4#))))))))))))) :MMB C)hh :QVB h)/A ::CB :)h/ /@:B /)Q@ /VBB /)/Q 1( (%"#4#4!+ AQ71hBB71AVB -!346)))))))))))))))))))))))))))))))))))))))) C'33))))))))))))))))))))))))))))))))))) /BB71hBB71AVB -h'33)))))))))))))))))))))))))))))))))))) 4#!&)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) :CBB B)QA :VBB B)@h ËdÌfb4 <%&6%&6;"%,3!"#!&%;;";%#'!&'"#))))))))))))))))))))) :CBB /)C#!:)@ .'!&'"#+4#$¶QBD2%"#R!"2%"#R4#%&6$%, ::CB /)h#!:)V '!&6'#4,4#44&$4;$"&6!5"%&;0 :BMB /)B#!/)@ !+= %%;;";%#!"34#!&'!&'"#))))))))))))))))))))))) /@:B B)@#!/)h ?(%&66$%3-'3%1-!"3%#9?(%&6h63%;9'4&6"9 /VBB B)VM#!B)M@ ( 4'.+4#$6&4#1(#!/VBBG;T 09'!"4%.%&66 /:MB B)CM#!B)Q@ '!&'"#$%,'!&6'#4,4#44&$4;$"&6!5"%&;0 @VB B)hB#!B)hV VCB B)/M
Page 106 of 168
B)hA ¸%3!"./@MM0 B)VQ ¸%3!"./@MM0 B):B#!B)/A B)@: ¸%& ./@MQ0 B)hQ ¸%& ./@MQ0 B)hC#!B):C ¸%3!"./@MM0 B):/A B)@: ¸%3!"./@MM0 B)hB#!B):: ¸%& ./@MQ0 B)VQ#!B)C/ ¸%& ./@MQ0 B)QM ¸%& ./@MQ0 B)QV ¸%& ./@MQ0 B)CA ¸%& ./@MQ0 B)hC#!B):@ ¸%& ./@MQ0 B)AC ¸%& ./@MQ0 B)Qh ¸%& ./@MQ0 B)QV#!B)hh B)MM ¸%& ./@MQ0 /):B#!B)AA ¸%& ./@MQ0 B)@h#!B)V@ <$#%3)./@A@0 B)MQ <$#%3)./@A@0 B)A@ <$#%3)./@A@0 B)V: <$#%3)./@A@0 B)CV#!B)CB ¸%& ./@MQ0 /)V#!/)/ ¸%& ./@MQ0 /)B ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 B)MM ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 B)MM ¸%3!"./@MM0 ¸%3!"./@MM0 B)::: B)A@ _!+31%&6O3;"&./@hA0 B):hM _!+31%&6O3;"&./@hA0 B):@C _!+31%&6O3;"&./@hA0 B)MC K %"%&.:BB:0 B)MC K %"%&.:BB:0 ¸%3!"./@MM0 B)MB#!/)BB¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0 B)MC ¸%3!"./@MM0 B)MC ¸%3!"./@MM0 ¸%3!"./@MM0 ¸%3!"./@MM0
08-NOV-2019 SUTHAR KETANBHAI (C360) 106 of 168
Page 23 of 82
Page 107 of 168
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
01234678429 7 381 938 797 796
171 2318728 18371
ii
X21i 7 7929 j9 2379231872 kW1 79l21 2u¾¿ÀÁÂÀÃÄÅx
W19 73qn4 9 m37r73ns4\1 7 329m1y4[1m7z7m01234 W1 m8737 9 op tpuvwx u vwxpt o{puovwx \1z1819m1 1( T547"'!&'"#.MA)QD;1( -/:)QD+!!6'$4(0 MBB B):C B)MC _!+31%&6O3;"&./@hA0 g T34-!"#%"-%&6#''!))))))))))))))))))))))))))))))))))))))))) /@:B /)CB ¸%3!"./@MM0 /VBB B)@A ¸%3!"./@MM0 /:MB B)VQ ¸%3!"./@MM0 L"34#-," 4'34#-%&6(!31#1"&7%6))))))))))))))))))))))))) MBB B):V#!B):A ¸%3!"./@MM0 VCB B):B#!B):: B)Vh#!B)@V¸%3!"./@MM0 CMB B)/V ¸%3!"./@MM0 h:B B)/: ¸%3!"./@MM0 >!% '!&'"#)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@:B B)AQ ¸%3!"./@MM0 /VBB B)VB ¸%3!"./@MM0 /:MB B)CC ¸%3!"./@MM0 //:B B)hV ¸%3!"./@MM0 >!% '!&'"#%&6'333%"'!&'"#)))))))))))))))))))))))))))))))) @VB B)hB ¸%3!"./@MM0 VCB B):B ¸%3!"./@MM0 h:B B)/: ¸%3!"./@MM0 O"%#6'!&'"#.!,&=6"460))))))))))))))))))))))))))))))))))))))))))))ChB#!MBB B):B B)MC K %"%&./@@V0 L!31#1"&'!&'"#.!,&=6"460)))))))))))))))))))))))))))))))))))))):QQ#!MBB B)hA B)MC K %"%&./@@V0 L!31 "'!&'"#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /@QB /)VC K %"%&./@@V0 ::BB /)Bh K %"%&./@@V0 L!31 "' ))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) /MAB B)AM K %"%&./@@V0 <3%;'!&'"#))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))) @VB B):: N!3!G4%&#%3./@AB0 /:MB B)h: N!3!G4%&#%3)./@AB0 /VBB B)Ch N!3!G4%&#%3)./@AB0 :BBB /):h N!3!G4%&#%3)./@AB0 t
./:D!4#"'! Ñ Ñ /)VhG 43G./@A@0 ÏcfeÐe J%G))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))VVB#!AQB B)/V#!B)/M g%"6&%%&6S473./@MA0 S4"'$))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))VMB#!A:Q B)/A#!B)/M g%"6&%%&6S473./@MA0 `%(3)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))VhQ#!ABB B)/V#!B)/A g%"6&%%&6S473./@MA0 O$)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))V/Q#!VAB B)/Q#!B)/V g%"6&%%&6S473./@MA0 a´bÐe Ñ Ñ Ñ /)VhG 43G./@A@0
%¸%3 %"5!"%&# ("%#"!5:Cg)_("%#4,,%35!"6"1%#"4%3%"4&66 4¸4&13('454'$%#Õ/)BGÖT.G;UK0 %64;&.&!#('454'%#4!&0,%35!"%#"4%34&&!" %3)N$" %3,%3!54&3%#4&; 8<O6% ./@A/0-`%'%&./@C/0-%&643G./@A@0)g!&6'#4,4#1,%3
%#"4%3 %16455"5"! 64;&,%36(&64&;!&4&=4#("!("#4.);)-6&4#1%&6 !4#"'!-!"4%#4!&-#')0%&6 %&5%'#"4&;,%"4%7434#1)>!"("!("#4!5('454' ("!6'#-,%3((34671%&5%'#""!"&74%6##) 7<1 7!3 Ó%3!6#!"("#$" %3'!&6'#4,4#1) 'P! &!#4&'36(%("7%'G4&;%&65%'4&;-45%&1)$"4&3%#4!&5!" 7!&6%"1."53'= #4,!"!#$"+40!5%4"(%'-N%73:%&6h5!"4&3%#4&;,%3!5%4"(%'+4#$%(("!= ("4%#55'#4, 4##%&'%&6# ("%#"'!&64#4!&!5(%') 6g!&6'#4,4#1,%"4+4#$547"64% #".g$%(#":Q0)S%##-73%&G#-%&63!!=5433 4&= "%3547"4&3%#4!&%" %&5%'#"6#!%'$4,('4546_=,%3-#$!#'! !&!5 +$4'$%"34#64&#$#%73)S'%!56455"&'4&%&5%'#"4&;("!'%&6%#"4= %3-#$("!6'##$4'G&-6&4#4-%&6#$" %3'!&6'#4,4#4,%"1!,"'!&46"%73 "%&;5!"%('4546_=,%3) E&3%#4&; ,%3!5%'!#4'%3#43,%"1-6(&64&;!&6&4#1!57!%"6%&6!(-4R-%&6 6 ( # $ ! 5 ( "5!"%#4!&) 5¸%35!"5331;"!#673!'G %17%(("!?4 %#64&;,%35!"'!&'"#+4#$4 43%" &4#6&4#1) ;¸%3 5!"'!&'"#73!'G%&6'!&'"#%"%#!4#"'!"("%#4,!5&!" %3) $¸%35!"#%3!",4&13464&;%((346!,"53%#"5%',%"1+4631-6(&64&;!&,= 3%#4!&!5#$%4"(%'7&%#$#$464&;9+$#$"%4"(%'4"53'#4,!"&!&"53'#4,9%&6 !&#$4'G&-#1(-%&6%((34'%#4!&!54&3%#4&;7%'G4&;=7!%"66)¸%3%"%,"%;5!" %64;&;46-%&6+"!7#%4&65"! ,"%3;%"66$!#7!?##.O
Page 24 of 82
34#6%"5!"$%##"%&5"%'"!#$;"%4&)N$" %3'!&6'#4,4#1!5+!!6,%"4 34&%"31+4#$6&4#1-%&66&4#1"%&;34#6%"#$!&!" %3315!&65!"+!!6 ('4;4,&)E56&4#1!5+!!6('44&!#G&!+&- %&'!&6'#4,4#1 ,%3)>!"?#"%(!3%#4!&#!!#$"!4#"'!-#$5!33!+4&; (4"4'%32%= #4!&6,3!(67143G./@A@0%176Ç ß=/=)=M=A==C==Ý===/=B==Ü=:==Þ==Q==)A==Q=h===Ý==/==B=Ü=C==É==à==×= ~Õ B)/A@/Þ= /ÞB)B/É +$"×46&4#1!5!4#+!!64&G;T h-%&6É4!4#"'!4&("') G>"! 43G./@A@0-%& (4"4'%32%#4!&5!"('454'$%#!5 !4#+!!6%# :Cg4%5!33!+Ç Ì¹ Õ =ß=B=ß)=:/=@==Þ@==BÞ==)B=B=/)=B=É/==Éà===àÞØ̹ +$"Ø̹%''!5!"$%#!5!"(#4!&%&646&!#671 Ø̹ á Éß/)@:/Ý/BÜhÜh)/VMÝ/BÜQÉà +$"É4!4#"'!4&("'71%) 3S3%&G(%'4&"5"&''!3 &4&64'%#$4#!"4'%3,%35"! (",4!,!3= !5ÙaÏÚÙÛÏcde~)
¡ ¢£¤¥¤¦§¨©ª«¬«®¬¯
±
±iq6[0\6Z029 o²9 21932 u[jx
X21° Xn7m2628193XÈ182 9 m37r73nl21 z 8[ 7 4tpuvwx
X21i± [8z2m1²7 1zz7m7193 p\1 7 329m1
[8z2m1Z73329m14ä \1z1m37r1 W781m37 9 Ò ä98å1z±1Æm±37r1 äå±± äå±±æ z 0123² ã ç y ç y ç yÂ
\1m 19 1 l21 z 8W1 792 Ò 82\291 Y ã 07Èm B)V#!:)Q B)AM :):Q B)@#!:)Q /)VC :):Q B)@#!/)V /)/: /)QV B)@#!:)Q B)@Q :):Q
737 9 z [8z2m1 j9 8 *!"4R!%3 (+%"6 @):V B)// Q)/A B)/@ C)h: B):h <3!(4&;%#CQ (+%"6 @)B@ B)// Q)BB B):B C)/Q B):C %_%!&%73 ,%35!"+$&&!4#=!"!43=('454'6%#%%"%,%43%73) *!"4R!%3 M):@ B)/: C):B B):C h)hQ B)hB 7`!6"%#31'!&",%#4 ,,%35!" 4&4 $%#3!#$"!;$!43.);)-4&!43 ¸"#4'%3 $%#?'$%&;"!"%"#$='!%'#'!!34&;'%3'3%#4!&0)¸%3%"5"! <%3! !&%&6 <3!(4&;%#CQ P!+&+%"6 A)QB B)/h h)C/ B):@ :)QV B)h@ `%"3!+./@M@0) *!"4R!%3 P!+&+%"6 V)/h B)/V :)/B B)CM /):Q B)MB '`!6"%#31 '!&",%#4,,%35!"%?4 $%#3!#$"!;$!43.);)-4&(%G ]3 8.%&1(!4#4!&0 ç¿ y¿ +4"$%#3!'%3'3%#4!&0)¸%3%"5"! <%3! !&%&6`%"3!+./@M@0) 4 & 6 . 5 ! " +4 & # " 0 O& 1 h C)B B)BhB X21Æ Xn7m2628193XÈ182 9 m37r73nl21 %#V)AT z 8\ mo 4tpuvwx 4&6.5!" "0 O&1 ::)A B)BCC %#h)CT Ò 82\291 èbÇ L 4'-#55-!7464%& B)Q#!:): /)<":5%''!&6'#%&'¼µ%&6¼%"64&T. :UK09"4#%&'Úµ%&6Ú4& . UK0T) S%%3# B)Q#!:)V :)
!"5%'$%7!#$%&%4"(%'"4#%&',%3%&6%"5%'"4#%&',%3) <$%3 B)@#!C)B h)g!&6'#%&'%"5!""5%'!5#$#%#6 4##%&'5%'4&;,4"#%373%'G7!61"= "!&64&;%#% # ("%#"%% 74%4")¸%37%6!&"5%'T%4"# ("%= "%&4# /)A#!C)h #"6455"&'!5Q)VK%&6"5%'# ("%#"!5:/g) 4#!&-6!3! 4#-%"73 /):#!C)h C)<g$%(#"C5!"!"6#%4364&5!" %#4!&) Î%"#R!%&6#!& /)C#!A)M Q)g!&6&%#'%&$%,4;&454'%55'#!&"5%' 4##%&'.N%73:0)O3!-!?4=
<%&6 <43# g3%1 !%
O$%#53!+#$"!;$!43- !4#"#&6#! !,%+%15"! #$$%#!"')N$4!4#"4;"%#4!&("!,464&4#4%3%#"%&= (!"#!5$%#-7#4#%3!6"4#$!43%68%'#!#$$%#!"'-#$ 3!+"4&;#$%((%"#$" %3'!&6'#4,4#14&#$%#R!&!5!43) N1(4'%331-+$&!#$"5%'#!"%"$36'!&#%-~4&'"%+4#$ !4#"'!%&6+4#$6"16&4#1!5%!43-7#6'"%+4#$ 4&'"%4&;!";%&4''!!5%!43%&65!"&45!" ;"%6%#4!&%&6 "!&66!43;"%4&.7'%;"%4&=#!=;"%4&'!%'#%""6'60) N$~!5%5"!R&!43%17$4;$"!"3!+"#$%&#$%#!5#$% &5"!R&!43.7'%#$'!&6'#4,4#1!54'4$4;$"#$%&#$%#!5 +%#"7#3!+"#$%&#$%#!5#1(4'%3!43;"%4&0)P455"&'4&~ 73!+ !4#"'!!5A#!MD%"24# %33)O#%(("!?4= %#31/QD!4#"'!-~%1,%"1(#!hBD5"! &5"!R& ,%3) $&'%3'3%#4&;%&&%3&";1-'$!!,%3#$%#"("= #1(4'%3%&4#'!&64#4!&)E&'34%#+$";"!&65"R4&; 44;&454'%-%''"%#$%##"%&5"43%#4!&$!364&'36#$ 55'#!5#$3%#$%#!554!&!5+%#")&";1"3%66"4&; #$4($%'$%&;4;&454'%"#%"6#$("!;"!5#$5"!#5"! 4&!4#!43) >!"5"#$"4&5!" %#4!&-g$%(#"/A-+$4'$4&'36% #$!65!"#4%#4&;$%#3!#$"!;$5!&6%#4!&)
[â\²6Z²jY]Z²²jjZÒX[p \Z[j[X6ÒZ[
O?(3%4&64&g$%(#":Q-#$!,"%33#$" %3"4#%&'!5%& % 731'! ("44#"5%'=#!="5%'#$" %3"4#%&'Ú %&6#$"5%'543 "4#%&'7#+&#$% 731F"5%' %&6#$4"4!"%&6?#"4!"&,4"!& .Ú%&6Ú0)N%73/B ;4,#1(4'%3,%35!"#$"5%'543 '!554µ'4¼µ%&6¼%&6 #$4""'4("!'%3-#$"5%'"4#%&'Úµ%&6Ú)O$!+&-#$ 4&6!!",%36(&6!&(!4#4!&!5#$"5%'-64"'#4!&!5$%# #"%&5"-%&6#$"5%'F3!&;=+%, 44,4#1)J#6!!"-#$,%3= 6(&6!&%4"(6%&6#$"5%'F3!&;=+%, 44,4#1) N%73/B"53'##%&6%"64#%#4!&-+4#$%&% 6.%(("!?4= %#04"4!""5%'# ("%#""("%#4,!5+%33!""!!5 % 734)>!"4#%#4!&#$%#6,4%#7#%%3315"! #%&6%"6
Page 108 of 168
6%#4!&-'!""!4!&-%&6%'' 3%#4!&!56#%&664"#'%&6"% %#4'%3314&'"%"= 5%' 4##%&') 4##%&',%3!5B)BQ$!36!&3176+$"$4;$31"53'#4, "5%''%&7%4%4&6!,"#$",4'345!5#$% 731)
X21ii Z8 129[8z2m1²7 1zz7m7193 p\1 7 329m1
737 9 z[8z2m1 j9 8 *!"4R!%3-3!(4&;#!CQ ¸"#4'%3-3!(4&;71!&6CQ ]3 8
W781m37 9 z ç4 y4 0123² ã tpu vwx u vwxpt (+%"6 /B B)/ P!+&+%"6 V B)/A O&164"'#4!& A)A B)/h :Q B)BC
'!&64#4!&-4&'364&;4"4!""5%'# ("%#"5!"5&#"%#4!& 1# -O<*_O./@@M0!",%35"! g$%(#"/Q#!6#"= 4&#$"5%'543 '!554'4T"4#%&')N%73//34##$ #%&6%"6"5%'543 '!554'4,%364&"!(%&#%&= 6%"6)
]WZ[6ÒW[X6ÒW6\W[
O<*_O):B/B)&";1#%&6%"65!"74364&;?'(#3!+="4"46%3 74364&;)O
<ETO<*_OTE<abcdecfe@B)/=:B/B) O<*_O):BB@)g"4#"4%5!" !4#"='!"!364;&4&74364&;)O
<ET O<*_Oabcdecfe/VB=:BB@) O
08-NOV-2019 SUTHAR KETANBHAI (C360) 108 of 168
Page 25 of 82
08-NOV-2019
Page 26 of 82
08-NOV-2019 SUTHAR KETANBHAI (C360)
Page 27 of 82
Page 111 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-3.1 ETD CALCULATION
1.ETD caln for blast proof building construction shall be included and same shall be considered for NHT-CRR building. 2.ETD caln for inside temp of 23 Deg C and 24 Deg C shall be included. (for Rack room and UPS room of SF for SS-86) 3. consider daily range of 11 deg F for all seasons as per ISHRAE 2014 4. Indicate building type suitably (i.e. blast proof/ Non blast proof )
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 111 of 168
Page 28 of 82
HEAT LOAD ESTIMATION FOR VRMP Equivalent Temp. Difference Calculations for "Indicate inside temp" HVAC Contractor- Advance Ventilation Pvt. Ltd.
Building type?
Daily Range in deg.F
Summer (˚F)= 20.52
Monsoon (˚F)= 15.66
Project: Vizag Refinery Modernization Project DBT in deg.F SUMMER
MONSOON
91.9
INDOOR
78.8
DIFFERENTIAL
13.1
OUTDOOR
87.1
INDOOR
78.8
DIFFERENTIAL
8.3
OUTDOOR
64.9
INDOOR
78.8
DIFFERENTIAL
-13.9
WALL
Wt. of Wall(lb/sq.ft)
ETD (deg.F)
N
100
4
-2.12
2
NE
100
10
-2.12
8
E
100
18
-2.12
16
SE
100
18
-2.12
16
S
100
16
-2.12
14
SW
100
14
-2.12
12
W
100
12
-2.12
10
NW
100
6
-2.12
4
ROOF
80
32
-2.12
30
WINTER
Page 112 of 168
OUTDOOR
CORRECTION FACTOR SUMMER
NET ETD(deg.F)
Design Inside Condition: Temp (˚F):
78.8
RH (%):
50
Remarks
ISHRAE Handbook Table1.21/1.22/1.23
MONSOON N
100
4
-4.55
-1
NE
100
10
-4.55
5
SE
100
18
-4.55
13
E
100
18
-4.55
13
S
100
16
-4.55
11
SW
100
14
-4.55
9
W
100
12
-4.55
7
NW
100
6
-4.55
1
ROOF
80
32
-4.55
27
ISHRAE Handbook Table1.21/1.22/1.23
# Taken reference of Visakhapatnam
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 112 of 168
Page 29 of 82
HEAT LOAD ESTIMATION FOR VRMP Equivalent Temp. Difference Calculations for "Indicate inside temp" HVAC Contractor- Advance Ventilation Pvt. Ltd.
Building type?
Daily Range in deg.F
Summer (˚F)= 20.52
Monsoon (˚F)= 15.66
Project: Vizag Refinery Modernization Project DBT in deg.F SUMMER
91.9
INDOOR
75.2
DIFFERENTIAL
16.7
INDOOR
75.2
Design Inside Condition: Temp (˚F):
DIFFERENTIAL
11.9
RH (%):
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10.3
WALL
Wt. of Wall(lb/sq.ft)
ETD (deg.F)
N
100
4
1.48
5
NE
100
10
1.48
11
E
100
18
1.48
19
SE
100
18
1.48
19
S
100
16
1.48
17
SW
100
14
1.48
15
W
100
12
1.48
13
NW
100
6
1.48
7
ROOF
80
32
1.48
33
MONSOON
OUTDOOR
WINTER
Page 113 of 168
OUTDOOR
87.1
CORRECTION FACTOR SUMMER
NET ETD(deg.F)
75.2 50
Remarks
ISHRAE Handbook Table1.21/1.22/1.23
MONSOON N
100
4
-0.95
3
NE
100
10
-0.95
9
SE
100
18
-0.95
17
E
100
18
-0.95
17
S
100
16
-0.95
15
SW
100
14
-0.95
13
W
100
12
-0.95
11
NW
100
6
-0.95
5
ROOF
80
32
-0.95
31
ISHRAE Handbook Table1.21/1.22/1.23
# Taken reference of Visakhapatnam
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 113 of 168
Page 30 of 82
HEAT LOAD ESTIMATION FOR VRMP
3.2 HEAT GAIN FROM PEOPLE
From ISHRAE HVAC data book Table- 1.24
Degree of activity
Typical application
Office worker
Office, Hotels, Apts., college Dept. Retail or Variety Store
Standing, walking slowly
Page 114 of 168
Room Dry-bulb temperature (75 deg.F)
Metabolic rate(adult male Btu/hr) 475
Btu/hr Sensible
Btu/hr Latent
550
245
205
SOLAR HEAT GAIN FACTOR (Btu/Hr)(Sq.ft ) AT 200 EXPOSURE
SUMMER (MAY21) At 4pm*
MONSOON (AUG 24) At 4pm*
NORTH
23
11
NORTH EAST
12
11
EAST
12
11
SOUTH EAST
12
11
SOUTH
12
11
SOUTH WEST
85
113
WEST
163
165
NORTH WEST
138
118
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 114 of 168
Page 31 of 82
08-NOV-2019
Page 32 of 82
08-NOV-2019
Page 33 of 82
08-NOV-2019
Page 34 of 82
Page 118 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-4 HEAT LOAD CALCULATION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 118 of 168
Page 35 of 82
Page 119 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.1.1 SUMMARY SHEET FOR SUBSTATION 86-CT BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 119 of 168
Page 36 of 82
Page 120 of 168
PROJECT : VIZAG REFINERY MODERNIZATION PROJECT OWNER : HINDUSTAN PETROLEUM CORPORATION LIMITED
CONSULTANT: ENGINEERS INDIA LIMITED
SUMMARY SHEET FOR SUBSTATION SS-86 (COOLING TOWER) BUILDING
Date: 03.10.19
J9
B15
B18
I108
I107
I109
Winter Load ( KW)
I110
Monsoon Heating ( KW )
I111
78.8 78.8 78.8 78.8
50.0 50.0 50.0 50.0
2.0 2.0 1.5 0.0
5605 590 120 0
21980 544 288 0
74.39 4.29 1.30 1.37
-11.16 -7.04 -0.68 0.00
11.39 1.18 0.21 0.00
-17.08 -1.80 -0.37 0.00
112000.00
4.00
6316
22812
81.35
-18.87
12.78
-19.25
44000 9000 1000 1000 0 0 0 55000.00
11000
3.0 0.0 4.0 3.0 0.0 0.0 0.0 10.00
1038 346 487 249 326 158 0 2603
9033 2034 918 632 562 348 0 13526
23.73 5.92 4.71 2.70 3.03 1.62 1.55 43.27
6.96 -0.33 -5.97 -2.91 -4.68 -2.35 0.00 -9.29
2.66 0.99 0.70 0.58 0.74 0.35 0.00 6.02
-3.16 -1.05 -1.48 -0.76 -0.99 -0.48 0.00 -7.93
167000.00
14.00
8919
36338
124.62
-28.16
18.80
-27.18
SUBTOTAL(A) SECOND FLOOR 5 6 7 8 9 10 11
RACK ROOM UPS ROOM TECH ROOM ENGINEER ROOM LOBBY 1 LOBBY 2 AHU ROOM SF SUBTOTAL(B) TOTAL(A+B)
14020.92 78.85 39.36 38.69 18.93 99.29 19.84 39.41
55.89 36.87 41.07 55.89 15.81 48.45 41.07
4221.16 1404.61 1542.25 1011.29 1569.72 961.35 1571.88 12282.25 26303.17
9.84 9.84 12.63 9.84 12.46 9.84 19.96
78.8 78.8 78.8 78.8 78.8 78.8 78.8
50.0 50.0 50.0 50.0 50.0 50.0 50.0
1.5 1.5 1.5 1.5 1.0 1.0 0.0
Second floor of building is Control room which is SRR for which Inside room temp of 23 deg C shall be considered.
08-NOV-2019 SUTHAR KETANBHAI (C360) 120 of 168
Page 37 of 82
Humidifier ( Kw)
H9
0.0 0.0 4.0 0.0
Unit Ref. Load
B58
Dehumidified Unit CFM
Fresh air ACPH
B59 111000 0 1000 0
fresh air CFM
Room Design RH in %age
D11 14.76 22.25 14.76 18.97
Room Design Temp. in deg. F
B12 11391.97 795.63 326.46 1506.85
Height ( Ft )
C11 50.59 20.57 16.73 38.61
Floor Area(sqft)
B11 218.42 38.69 19.52 39.03
Width(Ft)
Occup. (Persons)
B10 FIRST FLOOR SWITCHGEAR HALL SWITCHGEAR HALL GIS PANELS OPERATOR ROOM AHU ROOM FF
Eqip. Load(W)
1 2 3 4
Length(Ft)
S.no
Area Description
Rev. 00
Page 121 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.1.2 CALCULATION SHEET FOR SUBSTATION 86-CT BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 121 of 168
Page 38 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
SWITCHGEAR HALL
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
218.42
50.59
14.76
MONSOON
DESIGN CONDITIONS
ROOM AREA
11391.97 Sq.ft
INDOOR
ROOM VOLUME
168145.44 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
2.00
17.00
cfm/per
5604.85
Cfm @ AC/Hr
0.00
Cfm @ Occup
FRESH AIR
5604.85 Cfm Selected
GLASS AREA
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
73.7 -17
BF
0.12 Occupant Heat
Sens
245.00
1-BF
0.88
Lat
205.00
N
NE
E
SE
S
SW
W
NW
8.53
0.00
0.00
0.00
8.53
0.00
0.00
0.00
H
1.97
0.00
0.00
0.00
1.97
0.00
0.00
0.00
QTY
Gr/LB 150.0
50.0
L
All Glass 67.13
2.00
0.00
0.00
0.00
2.00
0.00
0.00
0.00
33.57
0.00
0.00
0.00
33.57
0.00
0.00
0.00
Partition
L
156.62
0.00
0.00
0.00
138.74
0.00
0.00
0.00
177.12
H
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
0.00
0.00
0.00
2014.30
0.00
0.00
0.00
2614.29
AREA WALL AREA
WINTER
RH
1
NETT AREA 2278.14
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
34
1.00
23
11
0
772
369
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
34
1.00
12
11
0
403
369
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
1542
-451
-11367
0
0
0
0
0
0
0
0
0
N
S
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
ETD values as per daily range of 11 shall be revised
2278
0.36
2
-1
-14
NE
0
0.36
8
5
-14
E
0
0.36
16
13
-14
SE
0
0.36
16
13
-14
2014
0.36
14
11
-14
10065
8303
-10051
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
S
Trans. Gain-Except Wall & Roof All Glass
67
1.13
13
8
-14
997
628
-1051
Partition
2614
0.32
8
3
-9
6810
2744
-7412
Ceiling
2028
0.29
8
3
-9
4788
1929
-5212
11392
0.36
8
3
-9
33383
13452
-36336
Floor
Internal Heat Occupants (Nos.)
0
245
0
0
0
Power (W)
111000
3.40
377400
377400
188700
Lights (W)
5294
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 122 of 168
17998
17998
8999
454158
422742
126270
510928
475585
126270
9545
6014
-10068
520473
481599
116203
12.5%
08-NOV-2019
5604.85
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 122 of 168
Page 39 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
5604.85
0.12
76
85
-17
0.68
0
0
0
34896
38738
-7912
ERLH
34896
38738
-7912
ERTH
555369
520337
108290
Outdoor Air(S)
5604.85
0.88
13
8
-14
1.08
69995
44106
Outdoor Air(Lt)
5604.85
0.88
76
85
-17
0.68
255906
284079
-58023
GTH
881269
848522
-23563
Refrigeration Load
881269
848522
-23563
Monsoon Reheat
-73830
38873
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
9241
5328
890511
892724
74.21
74.39
Winter KW
-14485
-11.16
Monsoon Heaters (KW)
11.39
ESHF =(ERSH/ERTH)
0.94
0.93
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
21980
20433
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-17.08
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-27.84
Final Values: Selected Load (TR)
74.39
Selected Airquantity (CFM)
21980.31
Winter Load (KW)
-11.16
Monsoon Heating (KW)
11.39
Humidifier (KW)
-17.08
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
156.62
0.00
0.00
0.00
138.74
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
1148.15
0.00
0.00
0.00
1017.10
0.00
0.00
0.00
1298.43
NET AREA
Partition 177.12
Solar & Trans. Gain-Wall & Roof N
1148
0.36
2
-1
-14
777
-227
-5729
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
1017
0.36
14
11
-14
5082
4193
-5075
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
1298
0.32
8
3
-9
3382
1363
-3681
S
08-NOV-2019
Return Air Heat Load Gain
Page 123 of 168
SUTHAR KETANBHAI (C360)
U factor for Roof sun to be checked and corrected.
123 of 168
Page 40 of 82
9241
5328
-14485
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
OWNER
HPCL
PROJECT
VRMP
LOCATION ROOM NAME
comments provided on switch gear hall is also applicable for this DESIGN CONDITIONS area.SEASON
SUBSTATION 86 CT SWITCHGEAR HALL GIS PANELS
Sheet No. DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
SWITCHGEAR HALL GIS PANELS
DIFFERENTIAL
13.1
OUTDOOR
87.1
INDOOR
78.8
ROOM SIZE
SUMMER
38.69
ROOM AREA
795.63
ROOM VOLUME
20.57
22.25
MONSOON
Sq.ft
17706.67 Cu.ft
OCCUPANCY
0.00
AIR CHANGES
2.00
17.00
DIFFERENTIAL cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
590.22
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
590.22
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
8.53
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
1.97
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
67.13
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
38.69
0.00
0.00
0.00
20.57
H
22.25
22.25
22.25
22.25
22.25
22.25
22.25
22.25
22.25
NETT AREA
0.00
0.00
0.00
0.00
793.85
0.00
0.00
0.00
457.68
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
67
1.00
12
11
0
806
738
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
S
67.13
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
794
0.36
14
11
-14
3967
3272
-3961
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
S
Trans. Gain-Except Wall & Roof All Glass
67
1.13
13
8
-14
997
628
-1051
Partition
458
0.32
8
3
-9
1192
480
-1298
0
0.29
8
3
-9
0
0
0
796
0.36
8
3
-9
2332
939
-2538
0
Ceiling Floor
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
370
3.40
1257
1257
629
10550
7316
-8219
11869
8230
-8219
1005
633
-1060
12874
8864
-9279
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 124 of 168
12.5%
08-NOV-2019
590.22
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 124 of 168
Page 41 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT SWITCHGEAR HALL GIS PANELS Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
590.22
0.12
76
85
-17
0.68
0
0
0
3675
4079
-833
ERLH
3675
4079
-833
ERTH
16548
12943
-10113
Outdoor Air(S)
590.22
0.88
13
8
-14
1.08
7371
4645
Outdoor Air(Lt)
590.22
0.88
76
85
-17
0.68
26948
29915
-6110
GTH
50868
47503
-23998
Refrigeration Load
50868
47503
-23998
Monsoon Reheat
-7775
4010
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
50868
51513
4.24
4.29
0
Winter KW
-7.04
Monsoon Heaters (KW)
1.18
ESHF =(ERSH/ERTH)
0.78
0.68
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
544
376
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-1.80
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-2.93
Final Values: Selected Load (TR)
4.29
Selected Airquantity (CFM)
543.67
Winter Load (KW)
-7.04
Monsoon Heating (KW)
1.18
Humidifier (KW)
-1.80
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
38.69
0.00
0.00
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
20.57
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 125 of 168
0
SUTHAR KETANBHAI (C360) 125 of 168
Page 42 of 82
0 0
0
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise)
OWNER
HPCL
comments provided on switch gear hall is also SEASON DESIGN applicable for thisCONDITIONS area.
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
Appl. Room
SUBSTATION 86 CT OPERATOR ROOM
Sheet No. DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
OPERATOR ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
19.52
16.73
14.76
MONSOON
ROOM AREA
326.46
Sq.ft
INDOOR
ROOM VOLUME
4818.60
Cu.ft
DIFFERENTIAL
OCCUPANCY
4.00
AIR CHANGES
1.50
FRESH AIR
17.00
cfm/per
WINTER
RH
1 Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
120.47
Cfm @ AC/Hr
68.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
120.47
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
14.76
NETT AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Partition
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Trans. Gain-Except Wall & Roof All Glass
0
1.13
13
8
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
326
0.36
8
3
-9
957
385
-1041
Floor
Internal Heat Occupants (Nos.)
4
245
980
980
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
152
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 126 of 168
516
516
258
5852
5281
917
6584
5941
917
205
129
-216
6789
6071
700
12.5%
08-NOV-2019
120.47
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 126 of 168
Page 43 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT OPERATOR ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
820
820
0
820
820
0
902
902
0
750
833
-170
ERLH
1652
1735
-170
ERTH
8441
7805
530
Latent Heat Occupants(Nos.)
4.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
120.47
0.12
76
85
-17
0.68
Outdoor Air(S)
120.47
0.88
13
8
-14
1.08
1504
948
Outdoor Air(Lt)
120.47
0.88
76
85
-17
0.68
5500
6106
-1247
GTH
15446
14859
-2304
Refrigeration Load
15446
14859
-2304
Monsoon Reheat
-1587
718
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
15446
15577
1.29
1.30
0
Winter KW
-0.68
Monsoon Heaters (KW)
0.21
ESHF =(ERSH/ERTH)
0.80
0.78
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
288
258
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.37
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.60
Final Values: Selected Load (TR)
1.30
Selected Airquantity (CFM)
288.04
Winter Load (KW)
-0.68
Monsoon Heating (KW)
0.21
Humidifier (KW)
-0.37
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 127 of 168
0
SUTHAR KETANBHAI (C360) 127 of 168
Page 44 of 82
0 0
0
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise)
OWNER
HPCL
PROJECT
VRMP
LOCATION ROOM NAME
comments provided on switch gear hall is also applicable for this area. SEASON DESIGN CONDITIONS
Appl. Room
SUBSTATION 86 CT AHU ROOM FF
Sheet No. DB
WB
OUTDOOR
91.9
82.0
SUBSTATION 86 CT
INDOOR
78.8
AHU ROOM FF
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
SUMMER
39.03
38.61
18.97
MONSOON
ROOM AREA
1506.85 Sq.ft
INDOOR
ROOM VOLUME
28592.25 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
0.00
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
0.00
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
0.00
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
8.53
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
1.97
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
67.13
0.00
0.00
0.00
L
0.00
0.00
0.00
0.00
39.03
0.00
38.61
0.00
0.00
H
18.97
18.97
18.97
18.97
18.97
18.97
18.97
18.97
18.97
NETT AREA
0.00
0.00
0.00
0.00
673.49
0.00
732.53
0.00
0.00
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
67
1.00
12
11
0
806
738
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
S
67.13
Partition
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
673
0.36
14
11
-14
3365
2776
-3360
S SW
0
0.36
12
9
-14
0
0
0
733
0.36
10
7
-14
2605
1965
-3655
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
W
Trans. Gain-Except Wall & Roof All Glass
67
1.13
13
8
-14
997
628
-1051
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
1507
0.36
8
3
-9
4416
1779
-4806
0
Floor
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
700
3.40
2381
2381
1190
14570
10267
-11683
16391
11551
-11683
0
0
0
16391
11551
-11683
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 128 of 168
12.5%
08-NOV-2019
0.00
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 128 of 168
Page 45 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT AHU ROOM FF Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
0
0
0
0
0
0
ERLH
0
0
0
ERTH
16391
11551
-11683
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
0.00
0.12
76
85
-17
0.68
Outdoor Air(S)
0.00
0.88
13
8
-14
1.08
0
0
Outdoor Air(Lt)
0.00
0.88
76
85
-17
0.68
0
0
0
GTH
16391
11551
-11683
Refrigeration Load
16391
11551
-11683
Monsoon Reheat
0
4840
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
16391
16391
1.37
1.37
0
Winter KW
0.00
Monsoon Heaters (KW)
0.00
ESHF =(ERSH/ERTH)
1.00
1.00
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
0
0
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
0.00
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
0.00
Final Values: Selected Load (TR)
1.37
Selected Airquantity (CFM)
0.00
Winter Load (KW)
0.00
Monsoon Heating (KW)
0.00
Humidifier (KW)
0.00
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
39.03
0.00
38.61
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 129 of 168
0
SUTHAR KETANBHAI (C360) 129 of 168
Page 46 of 82
0 0
0
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
inside temp. for rack room of 23deg C to be SEASON DESIGN CONDITIONS considered SUMMER OUTDOOR
HPCL
PROJECT
VRMP
LOCATION
SUBSTATION 86 CT
INDOOR
78.8
ROOM NAME
RACK ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
78.85
55.89
9.84
MONSOON
ROOM AREA
4221.16 Sq.ft
INDOOR
ROOM VOLUME
41536.17 Cu.ft
DIFFERENTIAL
OCCUPANCY
3.00
AIR CHANGES
1.50
FRESH AIR
17.00
cfm/per
1038.40
Cfm @ AC/Hr
51.00
Cfm @ Occup
1038.40 Cfm Selected
GLASS AREA
DB
WB
91.9
82.0
RH
Gr/LB 73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
73.7 -17
BF
0.12 Occupant Heat
Sens
245.00
1-BF
0.88
Lat
205.00
N
NE
E
SE
S
SW
W
NW
3.94
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
5.90
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
1
150.0 50.0
L
All Glass 371.81
8.00
0.00
0.00
0.00
8.00
0.00
0.00
0.00
185.91
0.00
0.00
0.00
185.91
0.00
0.00
0.00
Partition
L
78.85
0.00
0.00
0.00
78.85
0.00
0.00
0.00
55.89
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
0.00
0.00
0.00
589.99
0.00
0.00
0.00
549.97
AREA WALL AREA
WINTER
RACK ROOM
Sheet No.
OWNER
ROOM SIZE
SUBSTATION 86 CT
NETT AREA 589.99
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
186
1.00
23
11
0
4276
2045
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
186
1.00
12
11
0
2231
2045
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
-117
-2944
0
0
0
0
N
S
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
590
0.36
2
-1
-14
NE
0
0.36
8
5
-14
E
0
0.36
16
13
-14
SE
0
0.36
16
13
-14
590
0.36
14
11
-14
SW
0
0.36
12
9
W
0
0.36
10
7
NW
0
0.36
4
4221
0.11
S
Roof Sun
ETD values shall be corrected for daily 399 range of 11 Deg F 0 and inside room temp 0 0 of 23 deg C
0
0
2948
2432
-2944
-14
0
0
0
-14
0
0
0
1
-14
0
0
0
30
27
-14
13874
12746
-6436
Trans. Gain-Except Wall & Roof All Glass
372
1.13
13
8
-14
5521
3479
-5823
Partition
550
0.32
8
3
-9
1433
577
-1559
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
3
245
735
735
0
Power (W)
44000
3.40
149600
149600
74800
Lights (W)
1962
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 130 of 168
6669
6669
3335
187686
180211
58429
211146
202737
58429
1768
1114
-1865
212915
203852
56564
12.5%
08-NOV-2019
1038.40
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 130 of 168
Page 47 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT RACK ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
615
615
0
615
615
0
Latent Heat Occupants(Nos.)
3.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
1038.40
0.12
76
85
-17
0.68
677
677
0
6465
7177
-1466
ERLH
7142
7853
-1466
ERTH
220056
211705
55098
Outdoor Air(S)
1038.40
0.88
13
8
-14
1.08
12968
8172
-13678
Outdoor Air(Lt)
1038.40
0.88
76
85
-17
0.68
47411
52631
-10750
GTH
280435
272508
30669
Refrigeration Load
280435
272508
30669
Monsoon Reheat
9063
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
4347
2698
284782
284269
23.73
23.69
-6930
Winter KW
6.96
Monsoon Heaters (KW)
2.66
ESHF =(ERSH/ERTH)
0.97
0.96
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
CFM Dehum ={(ERSH)/(1.08*Deh Rise)}
9033
8649
Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-3.16
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-5.16
Final Values: Selected Load (TR)
23.73
Selected Airquantity (CFM)
9033.32
Winter Load (KW)
6.96
Monsoon Heating (KW)
2.66
Humidifier (KW)
-3.16
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
78.85
0.00
0.00
0.00
78.85
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
578.04
0.00
0.00
0.00
578.04
0.00
0.00
0.00
409.73
NET AREA
Partition 55.89
Solar & Trans. Gain-Wall & Roof N
578
0.36
2
-1
-14
391
-114
-2884
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
578
0.36
14
11
-14
2888
2383
-2884
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
410
0.32
8
3
-9
1067
430
-1162
S
08-NOV-2019
Return Air Heat Load Gain
Page 131 of 168
SUTHAR KETANBHAI (C360) 131 of 168
-Heat gain from roof sun to be considered. -ETD values shall be checked and corrected
Page 48 of 82
4347
2698
-6930
OWNER
HPCL
PROJECT
VRMP
LOCATION
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Comments provided on Rack room also Heat Load Calculations for Airconditioning system Location (Areawise) applicable for this area. Appl. Room - inside temp of 24 Deg C shall be considered. accordingly ETD values shall SEASON DESIGN CONDITIONS DB be corretced. SUMMER
OUTDOOR
91.9
SUBSTATION 86 CT
INDOOR
78.8
ROOM NAME
UPS ROOM
DIFFERENTIAL
13.1
ROOM SIZE
39.36
OUTDOOR
87.1 78.8
36.87
9.84
MONSOON
ROOM AREA
1404.61 Sq.ft
INDOOR
ROOM VOLUME
13821.36 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
1.50
WALL AREA
cfm/per
WINTER
UPS ROOM
Sheet No. WB
RH
82.0
Gr/LB 73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
345.53
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
N
NE
E
SE
S
SW
W
NW
L
3.94
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
5.90
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
1
150.0 50.0
345.53 FRESH AIR
GLASS AREA
17.00
SUBSTATION 86 CT
All Glass 92.95
4.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
92.95
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
39.36
0.00
0.00
0.00
0.00
0.00
0.00
0.00
36.87
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
0.00
0.00
0.00
0.00
0.00
0.00
0.00
362.77
NETT AREA 294.35
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
93
1.00
23
11
0
2138
1022
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
N
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
294
0.36
2
-1
-14
199
-58
-1469
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1405
0.11
30
27
-14
4617
4241
-2141
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
363
0.32
8
3
-9
945
381
-1029
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
0
Power (W)
9000
3.40
30600
30600
15300
Lights (W)
653
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 132 of 168
2219
2219
1110
42098
39275
10315
47360
44184
10315
588
371
-621
47949
44555
9694
12.5%
08-NOV-2019
345.53
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 132 of 168
Page 49 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT UPS ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
345.53
0.12
76
85
-17
0.68
0
0
0
2151
2388
-488
ERLH
2151
2388
-488
ERTH
50100
46943
9207
Outdoor Air(S)
345.53
0.88
13
8
-14
1.08
4315
2719
-4552
Outdoor Air(Lt)
345.53
0.88
76
85
-17
0.68
15776
17513
-3577
GTH
70192
67176
1078
Refrigeration Load
70192
67176
1078
Monsoon Reheat
3394
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
899
227
71091
70796
5.92
5.90
-2206
Winter KW
-0.33
Monsoon Heaters (KW)
0.99
ESHF =(ERSH/ERTH)
0.96
0.95
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
CFM Dehum ={(ERSH)/(1.08*Deh Rise)}
2034
1890
Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-1.05
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-1.72
Final Values: Selected Load (TR)
5.92
Selected Airquantity (CFM)
2034.32
Winter Load (KW)
-0.33
Monsoon Heating (KW)
0.99
Humidifier (KW)
-1.05
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
39.36
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
288.54
0.00
0.00
0.00
0.00
0.00
0.00
0.00
270.27
NET AREA
Partition 36.87
Solar & Trans. Gain-Wall & Roof N
289
0.36
2
-1
-14
195
-57
-1440
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
270
0.32
8
3
-9
704
284
-766
08-NOV-2019
Return Air Heat Load Gain
Page 133 of 168
899
SUTHAR KETANBHAI (C360) 133 of 168
Page 50 of 82
227
-2206
-Comments provided on Rack room also applicable for this area. -- inside temp of 24 Deg C DESIGN CONDITIONS shall SEASON be considered. SUMMER OUTDOOR accordingly ETD values INDOOR shall be corretced. DIFFERENTIAL
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise)
OWNER
HPCL
PROJECT
VRMP
LOCATION
SUBSTATION 86 CT
ROOM NAME
TECH ROOM
ROOM SIZE
38.69
41.07
12.63
MONSOON
INDOOR DIFFERENTIAL
4.00
AIR CHANGES
1.50
FRESH AIR
17.00
cfm/per
WINTER
DB
WB 82.0
78.8
RH
1 Gr/LB 150.0
50.0
13.1 78.8
1542.25 Sq.ft 19475.49 Cu.ft
TECH ROOM
91.9
87.1
ROOM VOLUME
SUBSTATION 86 CT
Sheet No.
OUTDOOR
ROOM AREA OCCUPANCY
Appl. Room
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
486.89
Cfm @ AC/Hr
68.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
486.89
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
92.95
0.00
0.00
0.00
Partition
L
0.00
0.00
24.88
0.00
38.69
0.00
0.00
0.00
10.40
H
12.63
12.63
12.63
12.63
12.63
12.63
12.63
12.63
12.63
NETT AREA
0.00
0.00
314.17
0.00
395.59
0.00
0.00
0.00
131.30
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
93
1.00
12
11
0
1115
1022
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0 0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
S
92.95
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
NE
0
0.36
8
5
-14
0
0
0
314
0.36
16
13
-14
1796
1521
-1568
E SE
0
0.36
16
13
-14
0
0
0
396
0.36
14
11
-14
1977
1631
-1974
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1542
0.11
30
27
-14
5069
4657
-2351
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
131
0.32
8
3
-9
342
138
-372
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
4
245
980
980
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
717
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 134 of 168
2437
2437
1218
18496
16655
-4802
20808
18737
-4802
829
522
-875
21637
19260
-5677
12.5%
08-NOV-2019
486.89
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 134 of 168
Page 51 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT TECH ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
820
820
0
820
820
0
Latent Heat Occupants(Nos.)
4.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
486.89
0.12
76
85
-17
0.68
902
902
0
3031
3365
-687
ERLH
3933
4267
-687
ERTH
25571
23527
-6364
Outdoor Air(S)
486.89
0.88
13
8
-14
1.08
6080
3831
Outdoor Air(Lt)
486.89
0.88
76
85
-17
0.68
22230
24678
-5040
GTH
53881
52036
-17818
Refrigeration Load
53881
52036
-17818
Monsoon Reheat
-6414
2378
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
2658
2132
56540
56546
4.71
4.71
-2541
Winter KW
-5.97
Monsoon Heaters (KW)
0.70
ESHF =(ERSH/ERTH)
0.85
0.82
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
918
817
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-1.48
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-2.42
Final Values: Selected Load (TR)
4.71
Selected Airquantity (CFM)
918.00
Winter Load (KW)
-5.97
Monsoon Heating (KW)
0.70
Humidifier (KW)
-1.48
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
24.88
0.00
38.69
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
182.38
0.00
283.61
0.00
0.00
0.00
76.22
10.40
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
NE
0
0.36
8
5
-14
0
0
0
182
0.36
16
13
-14
1043
883
-910
E SE
0
0
0.36
16
13
-14
0
0
0
284
0.36
14
11
-14
1417
1169
-1415
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
76
0.32
8
3
-9
199
80
-216
S
08-NOV-2019
Return Air Heat Load Gain
Page 135 of 168
2658
SUTHAR KETANBHAI (C360) 135 of 168
Page 52 of 82
2132
-2541
-Comments provided on Rack room also applicable for this area. - inside temp of 24 Deg C shall be considered. accordingly ETD SEASON DESIGN CONDITIONS values shall be corretced. SUMMER OUTDOOR
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
HPCL
PROJECT
VRMP
LOCATION
SUBSTATION 86 CT
INDOOR
78.8
ROOM NAME
ENGINEER ROOM
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
18.93
55.89
9.84
MONSOON
ROOM AREA
1011.29 Sq.ft
INDOOR
ROOM VOLUME
9951.11
DIFFERENTIAL
OCCUPANCY
3.00
AIR CHANGES
1.50
FRESH AIR
GLASS AREA
WALL AREA
Cu.ft 17.00
cfm/per
WINTER
ENGINEER ROOM
Sheet No.
OWNER
ROOM SIZE
SUBSTATION 86 CT
DB
WB
91.9
82.0
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
248.78
Cfm @ AC/Hr
51.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
248.78
Cfm Selected
1-BF
0.88
Lat
205.00
73.7 -17
N
NE
E
SE
S
SW
W
NW
L
3.94
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
5.90
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
1
All Glass 92.95
2.00
0.00
0.00
0.00
2.00
0.00
0.00
0.00
AREA
46.48
0.00
0.00
0.00
46.48
0.00
0.00
0.00
Partition
L
18.93
0.00
0.00
0.00
18.93
0.00
0.00
0.00
0.00
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
0.00
0.00
0.00
139.75
0.00
0.00
0.00
0.00
NETT AREA 139.75
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Area
U
Sum
Mon
Win
Sum
Mon
Win
46
1.00
23
11
0
1069
511
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
46
1.00
12
11
0
558
511
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
N
S
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
140
0.36
2
-1
-14
95
-28
-697
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
140
0.36
14
11
-14
698
576
-697
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1011
0.11
30
27
-14
3324
3054
-1542
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
Internal Heat Occupants (Nos.)
3
245
735
735
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
470
3.40
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 136 of 168
1598
1598
799
12856
11227
-1893
14463
12630
-1893
424
267
-447
14887
12897
-2340
12.5%
08-NOV-2019
248.78
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 136 of 168
Page 53 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT ENGINEER ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
615
615
0
615
615
0
Latent Heat Occupants(Nos.)
3.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
248.78
0.12
76
85
-17
0.68
677
677
0
1549
1719
-351
ERLH
2225
2396
-351
ERTH
17113
15293
-2691
Outdoor Air(S)
248.78
0.88
13
8
-14
1.08
3107
1958
Outdoor Air(Lt)
248.78
0.88
76
85
-17
0.68
11359
12609
-2575
GTH
31578
29860
-8544
Refrigeration Load
31578
29860
-8544
Monsoon Reheat
-3277
1990
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
787
544
32365
32394
2.70
2.70
-1385
Winter KW
-2.91
Monsoon Heaters (KW)
0.58
ESHF =(ERSH/ERTH)
0.87
0.84
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
632
547
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.76
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-1.24
Final Values: Selected Load (TR)
2.70
Selected Airquantity (CFM)
631.62
Winter Load (KW)
-2.91
Monsoon Heating (KW)
0.58
Humidifier (KW)
-0.76
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
18.93
0.00
0.00
0.00
18.93
0.00
0.00
0.00
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
138.74
0.00
0.00
0.00
138.74
0.00
0.00
0.00
0.00
NET AREA
Partition 0.00
Solar & Trans. Gain-Wall & Roof N
139
0.36
2
-1
-14
94
-27
-692
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
139
0.36
14
11
-14
693
572
-692
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
S
08-NOV-2019
Return Air Heat Load Gain
Page 137 of 168
787
SUTHAR KETANBHAI (C360) 137 of 168
Page 54 of 82
0 544
-1385
Proj Engg.
-Comments provided on Rack room also applicable for this area. Appl. Room - inside temp of 24 Deg C shall be considered. accordingly ETD values DB shall be SEASON corretced. DESIGN CONDITIONS Job no
Heat Load Calculations for Airconditioning system Location (Areawise)
OWNER
HPCL
PROJECT
VRMP
LOCATION ROOM NAME
SUMMER
OUTDOOR
91.9
SUBSTATION 86 CT
INDOOR
78.8
LOBBY 1
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
ROOM SIZE
99.29
15.81
12.46
MONSOON
ROOM AREA
1569.72 Sq.ft
INDOOR
ROOM VOLUME
19564.96 Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
1.00
17.00
cfm/per
WINTER
Rahul Lal M20/DEL-085.MI SUBSTATION 86 CT LOBBY 1
Sheet No. WB
RH
82.0
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
326.08
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
326.08
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
19.68
0.00
0.00
0.00
74.10
H
12.46
12.46
12.46
12.46
12.46
12.46
12.46
12.46
12.46
NETT AREA
0.00
0.00
0.00
0.00
245.29
0.00
0.00
0.00
923.52
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
245
0.36
14
11
-14
1226
1011
-1224
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
1570
0.11
30
27
-14
5159
4740
-2393
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
0
1.13
13
8
-14
0
0
0
Partition
924
0.32
8
3
-9
2406
969
-2618
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
729
3.40
2480
2480
1240
11271
9200
-4995
12679
10350
-4995
555
350
-586
13235
10700
-5581
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 138 of 168
12.5%
08-NOV-2019
326.08
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 138 of 168
Page 55 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT LOBBY 1 Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
326.08
0.12
76
85
-17
0.68
0
0
0
2030
2254
-460
ERLH
2030
2254
-460
ERTH
15265
12954
-6042
Outdoor Air(S)
326.08
0.88
13
8
-14
1.08
4072
2566
Outdoor Air(Lt)
326.08
0.88
76
85
-17
0.68
14888
16527
-3376
GTH
34225
32047
-13713
Refrigeration Load
34225
32047
-13713
Monsoon Reheat
-4295
2535
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
2136
1165
36361
35747
3.03
2.98
-2260
Winter KW
-4.68
Monsoon Heaters (KW)
0.74
ESHF =(ERSH/ERTH)
0.87
0.83
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
562
454
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.99
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-1.62
Final Values: Selected Load (TR)
3.03
Selected Airquantity (CFM)
561.51
Winter Load (KW)
-4.68
Monsoon Heating (KW)
0.74
Humidifier (KW)
-0.99
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
19.68
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
0.00
0.00
144.27
0.00
0.00
0.00
543.18
74.10
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
144
0.36
14
11
-14
721
595
-720
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
543
0.32
8
3
-9
1415
570
-1540
S
08-NOV-2019
Return Air Heat Load Gain
Page 139 of 168
2136
SUTHAR KETANBHAI (C360) 139 of 168
Page 56 of 82
1165
-2260
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise)
-Comments provided on Rack room also applicable for this area. - inside temp of 24 Deg C shall be considered.SEASON accordingly ETD DESIGN CONDITIONS OUTDOOR values shallSUMMER be corretced.
Appl. Room
HPCL
PROJECT
VRMP
LOCATION
SUBSTATION 86 CT
INDOOR
78.8
ROOM NAME
LOBBY 2
DIFFERENTIAL
13.1
OUTDOOR
87.1 78.8
19.84
48.45
9.84
MONSOON
ROOM AREA
961.35
Sq.ft
INDOOR
ROOM VOLUME
9459.73
Cu.ft
DIFFERENTIAL
OCCUPANCY
0.00
AIR CHANGES
1.00
17.00
cfm/per
WINTER
LOBBY 2
Sheet No.
OWNER
ROOM SIZE
SUBSTATION 86 CT
DB
WB
91.9
82.0
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
157.66
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
157.66
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
4.92
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
8.20
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
1.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
40.34
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
19.84
0.00
0.00
0.00
19.84
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
NETT AREA
0.00
0.00
0.00
0.00
154.92
0.00
0.00
0.00
195.26
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
40
1.00
12
11
0
484
444
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
S
40.34
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
155
0.36
14
11
-14
774
639
-773
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
961
0.11
30
27
-14
3160
2903
-1466
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
40
1.13
13
8
-14
599
377
-632
Partition
195
0.32
8
3
-9
509
205
-554
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
447
3.40
1519
1519
759
7045
6086
-2665
7925
6847
-2665
268
169
-283
8194
7016
-2948
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 140 of 168
12.5%
08-NOV-2019
157.66
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 140 of 168
Page 57 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT LOBBY 2 Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH
0
0
0
982
1090
-223
ERLH
982
1090
-223
ERTH
9175
8106
-3170
Outdoor Air
157.66
0.12
76
85
-17
0.68
Outdoor Air(S)
157.66
0.88
13
8
-14
1.08
1969
1241
Outdoor Air(Lt)
157.66
0.88
76
85
-17
0.68
7199
7991
-1632
GTH
18343
17338
-6879
Refrigeration Load
18343
17338
-6879
Monsoon Reheat
-2077
1177
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
1106
752
19448
19267
1.62
1.61
-1138
Winter KW
-2.35
Monsoon Heaters (KW)
0.35
ESHF =(ERSH/ERTH)
0.89
0.87
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
348
298
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.48
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.78
Final Values: Selected Load (TR)
1.62
Selected Airquantity (CFM)
347.63
Winter Load (KW)
-2.35
Monsoon Heating (KW)
0.35
Humidifier (KW)
-0.48
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
19.84
0.00
0.00
0.00
Partition
H
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
7.33
NET AREA
0.00
0.00
0.00
0.00
145.47
0.00
0.00
0.00
145.47
19.84
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
145
0.36
14
11
-14
727
600
-726
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
145
0.32
8
3
-9
379
153
-412
S
08-NOV-2019
Return Air Heat Load Gain
Page 141 of 168
1106
SUTHAR KETANBHAI (C360) 141 of 168
Page 58 of 82
752
-1138
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
OWNER
HPCL
PROJECT
VRMP
LOCATION
SUBSTATION 86 CT
ROOM NAME
AHU ROOM SF
ROOM SIZE
39.41
-Comments provided on Rack room also applicable for this area. - inside temp of 24 Deg C shall be SEASON DESIGN CONDITIONS SUMMER accordingly OUTDOOR considered. ETD INDOOR values shall be corretced.
41.07
19.96
MONSOON
78.8
INDOOR DIFFERENTIAL
AIR CHANGES
0.00
17.00
cfm/per
WINTER
78.8 87.1
1571.88 Sq.ft 0.00
WB 82.0
OUTDOOR
31372.82 Cu.ft
OCCUPANCY
DB 91.9 13.1
ROOM VOLUME
AHU ROOM SF
Sheet No.
DIFFERENTIAL
ROOM AREA
SUBSTATION 86 CT
RH
Gr/LB 150.0
50.0
73.7 76.3
82.0
8.3
0.0
OUTDOOR
64.9
57.0
INDOOR
78.8
DIFFERENTIAL
-14
158.4 50.0
73.7
0.0
84.7 56.4
50.0
0.00
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.12 Occupant Heat
Sens
245.00
0.00
Cfm Selected
1-BF
0.88
Lat
205.00
FRESH AIR
1
73.7 -17
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
3.94
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
5.90
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
4.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
92.95
0.00
0.00
0.00
L
0.00
0.00
0.00
0.00
39.41
0.00
41.07
0.00
0.00
H
19.96
19.96
19.96
19.96
19.96
19.96
19.96
19.96
19.96
NETT AREA
0.00
0.00
0.00
0.00
693.61
0.00
819.62
0.00
0.00
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
93
1.00
12
11
0
1115
1022
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
S
92.95
Partition
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
694
0.36
14
11
-14
3466
2859
-3461
S SW
0
0.36
12
9
-14
0
0
0
820
0.36
10
7
-14
2915
2198
-4090
0
0.36
4
1
-14
0
0
0
1572
0.11
30
27
-14
5166
4746
-2396
W NW Roof Sun
Trans. Gain-Except Wall & Roof All Glass
93
1.13
13
8
-14
1380
870
-1456
Partition
0
0.32
8
3
-9
0
0
0
Ceiling
0
0.29
8
3
-9
0
0
0
Floor
0
0.36
8
3
-9
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
730
3.40
2483
2483
1242
16527
14179
-10161
18592
15952
-10161
0
0
0
18592
15952
-10161
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 142 of 168
12.5%
08-NOV-2019
0.00
0.12
13
8
-14
1.08
SUTHAR KETANBHAI (C360) 142 of 168
Page 59 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
SUBSTATION 86 CT AHU ROOM SF Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
0
0
0
0
0
0
ERLH
0
0
0
ERTH
18592
15952
-10161
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
0.00
0.12
76
85
-17
0.68
Outdoor Air(S)
0.00
0.88
13
8
-14
1.08
0
0
Outdoor Air(Lt)
0.00
0.88
76
85
-17
0.68
0
0
0
GTH
18592
15952
-10161
Refrigeration Load
18592
15952
-10161
Monsoon Reheat
0
2641
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
0
0
18592
18592
1.55
1.55
0
Winter KW
0.00
Monsoon Heaters (KW)
0.00
ESHF =(ERSH/ERTH)
1.00
1.00
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
21.82
21.82
0
0
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
0.00
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
0.00
Final Values: Selected Load (TR)
1.55
Selected Airquantity (CFM)
0.00
Winter Load (KW)
0.00
Monsoon Heating (KW)
0.00
Humidifier (KW)
0.00
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
39.41
0.00
41.07
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Solar & Trans. Gain-Wall & Roof N
0
0.36
2
-1
-14
0
0
0
NE
0
0.36
8
5
-14
0
0
0
E
0
0.36
16
13
-14
0
0
0
SE
0
0.36
16
13
-14
0
0
0
S
0
0.36
14
11
-14
0
0
0
SW
0
0.36
12
9
-14
0
0
0
W
0
0.36
10
7
-14
0
0
0
NW
0
0.36
4
1
-14
0
0
0
Roof Sun
0
0.11
30
27
-14
0
0
0
Partition
0
0.32
8
3
-9
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 143 of 168
0
SUTHAR KETANBHAI (C360) 143 of 168
Page 60 of 82
0 0
0
Page 144 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.2.1 SUMMARY SHEET FOR NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 144 of 168
Page 61 of 82
Page 145 of 168
PROJECT : VIZAG REFINERY MODERNIZATION PROJECT OWNER : HINDUSTAN PETROLEUM CORPORATION LIMITED
CONSULTANT: ENGINEERS INDIA LIMITED
SUMMARY SHEET FOR NHT CCR FIELD ROOM BUILDING
Date: 03.10.2019
B18
1.0 1.0 0.0
102.00 102.00 0.00 204.00
08-NOV-2019 SUTHAR KETANBHAI (C360) 145 of 168
Page 62 of 82
I110
I111
-1.34 -1.06 -0.74 -3.15
0.43 0.27 0.35 1.05
-0.16 -0.16 0.00 -0.32
I108
I107
I109
826 326 302 1454.30
2.22 1.32 0.48 4.03
Humidifier ( Kw)
B15
50.0 50.0 50.0
Monsoon Heating ( KW )
J9
75.2 75.2 75.2
Winter Load ( KW)
H9
6.0 6.0 0.0 12.00
Unit Ref. Load
B58
Dehumidified Unit CFM
Fresh air ACPH
B59 1000 0 0 1000.00
fresh air CFM
Room Design RH in %age
D11 9.84 9.84 14.60
Room Design Temp. in deg. F
B12 621.83 264.15 164.60 1050.58
Height ( Ft )
C11 27.80 18.86 11.81
Floor Area(sqft)
B11 22.37 14.01 13.94
Width(Ft)
Occup. (Persons)
1 2 3
Length(Ft)
B10 SHIFT INCHARGE ROOM DINING ROOM PACKAGE AC ROOM TOTAL
S.no
Eqip. Load(W)
Area Description
Rev. 00
Page 146 of 168
HEAT LOAD ESTIMATION FOR VRMP
4.2.2 CALCULATION SHEET FOR NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 146 of 168
Page 63 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM SHIFT INCHARGE ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
NHT CCR FIELD ROOM
INDOOR
75.2
SHIFT INCHARGE ROOM
DIFFERENTIAL
16.7
OUTDOOR
87.1
ROOM SIZE
22.37
27.80
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
621.83
Sq.ft
INDOOR
75.2
ROOM VOLUME
6118.81
Cu.ft
DIFFERENTIAL
11.9
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10
OCCUPANCY
6.00
AIR CHANGES
1.00
FRESH AIR
17.00
cfm/per
WINTER
RH
1 Gr/LB 150.0
50.0
65.3 84.7
82.0
158.4 50.0
65.3 93.1
57.0
56.4 50.0
101.98
Cfm @ AC/Hr
102.00
Cfm @ Occup
BF
0.17 Occupant Heat
Sens
245.00
102.00
Cfm Selected
1-BF
0.83
Lat
205.00
65.3 -9
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
27.80
0.00
22.37
0.00
0.00
0.00
30.57
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
NETT AREA
0.00
0.00
273.53
0.00
220.12
0.00
0.00
0.00
300.80
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
0
0
0
0
0
0
2558
2239
-1347
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
NE
0
0.48
11
9
-10
274
0.48
19
17
-10
E SE
0
0.48
19
17
-10
220
0.48
17
15
-10
SW
0
0.48
15
13
-10
W
0
0.48
13
11
-10
NW
0
0.48
7
5
-10
622
0.11
33
31
-10
S
Roof Sun
0.00
ETD values shall be considered for Blast proof construction. Pl check and correct.
0
0
0
1847
1590
-1084
0
0
0
0
0
0
0
0
0
2290
2124
-702
Trans. Gain-Except Wall & Roof All Glass
0
1.13
17
12
-10
0
0
0
Partition
301
0.32
12
7
-5
1130
662
-506
Ceiling
0
0.29
12
7
-5
0
0
0
Floor
0
0.36
12
7
-5
0
0
0
6
245
1470
1470
0
Power (W)
1000
3.40
3400
3400
1700
Lights (W)
289
3.40
Internal Heat Occupants (Nos.)
ETD for heat gain from ceiling/ roof to be considered. heat gain from roof sun to be considered,
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 147 of 168
982
982
491
13677
12467
-1448
15387
14026
-1448
313
222
-192
15700
14248
-1640
12.5%
08-NOV-2019
102.00
0.17
17
12
-10
1.08
SUTHAR KETANBHAI (C360) 147 of 168
Page 64 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM SHIFT INCHARGE ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
1230
1230
0
1230
1230
0
1353
1353
0
999
1098
-105
Latent Heat Occupants(Nos.)
6.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
102.00
0.17
85
93
-9
0.68
ERLH
2352
2451
-105
ERTH
18052
16699
-1745
Outdoor Air(S)
102.00
0.83
17
12
-10
1.08
1531
1086
Outdoor Air(Lt)
102.00
0.83
85
93
-9
0.68
4876
5360
-512
GTH
24459
23145
-3196
Refrigeration Load
24459
23145
-3196
Monsoon Reheat
-938
1452
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
1983
2096
26441
26693
2.20
2.22
-1371
Winter KW
-1.34
Monsoon Heaters (KW)
0.43
ESHF =(ERSH/ERTH)
0.87
0.85
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
17.60
17.60
826
750
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.16
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.26
Final Values: Selected Load (TR)
2.22
Selected Airquantity (CFM)
826.17
Winter Load (KW)
-1.34
Monsoon Heating (KW)
0.43
Humidifier (KW)
-0.16
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
27.80
0.00
22.37
0.00
0.00
0.00
Partition
H
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
NET AREA
0.00
0.00
127.65
0.00
102.72
0.00
0.00
0.00
140.38
30.57
Solar & Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
NE
0
0.48
11
9
-10
0
0
0
128
0.48
19
17
-10
1194
1045
-629
E SE
0
0
0.48
19
17
-10
0
0
0
103
0.48
17
15
-10
862
742
-506
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
Roof Sun
0
0.11
33
31
-10
0
0
0
Partition
140
0.32
12
7
-5
527
309
-236
S
08-NOV-2019
heat gain from roof sun not considerd. pl check and correct.
Return Air Heat Load Gain
Page 148 of 168
2583
SUTHAR KETANBHAI (C360) 148 of 168
Page 65 of 82
2096
-1371
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
OWNER
HPCL
PROJECT
VRMP
LOCATION ROOM NAME
comments given on shift in charge room applicable to dining room too.
DINING ROOM
Sheet No. DB
WB
OUTDOOR
91.9
82.0
NHT CCR FIELD ROOM
INDOOR
75.2
DINING ROOM
DIFFERENTIAL
16.7
OUTDOOR
87.1
ROOM SIZE
SEASON
NHT CCR FIELD ROOM
SUMMER
14.01
18.86
9.84
MONSOON
DESIGN CONDITIONS
ROOM AREA
264.15
Sq.ft
INDOOR
75.2
ROOM VOLUME
2599.19
Cu.ft
DIFFERENTIAL
11.9
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10
OCCUPANCY
6.00
AIR CHANGES
1.00
FRESH AIR
17.00
cfm/per
WINTER
RH
1 Gr/LB 150.0
50.0
65.3 84.7
82.0
158.4 50.0
65.3 93.1
57.0
56.4 50.0
43.32
Cfm @ AC/Hr
102.00
Cfm @ Occup
BF
0.17 Occupant Heat
Sens
245.00
102.00
Cfm Selected
1-BF
0.83
Lat
205.00
65.3 -9
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
14.01
0.00
0.00
0.00
32.87
H
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
9.84
NETT AREA
0.00
0.00
0.00
0.00
137.82
0.00
0.00
0.00
323.40
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
138
0.48
17
15
-10
1156
996
-679
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
264
0.11
33
31
-10
973
902
-298
S
Roof Sun
Trans. Gain-Except Wall & Roof All Glass
0
1.13
17
12
-10
0
0
0
Partition
323
0.32
12
7
-5
1215
712
-544
Ceiling
0
0.29
12
7
-5
0
0
0
Floor
0
0.36
12
7
-5
0
0
0
0
Internal Heat Occupants (Nos.)
6
245
1470
1470
Power (W)
0
3.40
0
0
0
Lights (W)
123
3.40
417
417
209
5231
4497
-1313
5885
5059
-1313
313
222
-192
6199
5282
-1505
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 149 of 168
12.5%
08-NOV-2019
102.00
0.17
17
12
-10
1.08
SUTHAR KETANBHAI (C360) 149 of 168
Page 66 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM DINING ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
1230
1230
0
1230
1230
0
1353
1353
0
999
1098
-105
ERLH
2352
2451
-105
ERTH
8551
7732
-1610
Latent Heat Occupants(Nos.)
6.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
102.00
0.17
85
93
-9
0.68
Outdoor Air(S)
102.00
0.83
17
12
-10
1.08
1531
1086
Outdoor Air(Lt)
102.00
0.83
85
93
-9
0.68
4876
5360
-512
GTH
14957
14178
-3060
Refrigeration Load
14957
14178
-3060
Monsoon Reheat
-938
917
Return Air Heat Load Grand Total Refrigeration Load
BTU/HR
Grand Total Refrigeration Load
TR
707
797
15664
15892
1.31
1.32
-571
Winter KW
-1.06
Monsoon Heaters (KW)
0.27
ESHF =(ERSH/ERTH)
0.72
0.68
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
17.60
17.60
326
278
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
-0.16
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
-0.26
Final Values: Selected Load (TR)
1.32
Selected Airquantity (CFM)
326.19
Winter Load (KW)
-1.06
Monsoon Heating (KW)
0.27
Humidifier (KW)
-0.16
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
14.01
0.00
0.00
0.00
Partition
H
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
4.59
NET AREA
0.00
0.00
0.00
0.00
64.31
0.00
0.00
0.00
150.92
32.87
Solar & Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
64
0.48
17
15
-10
540
465
-317
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
Roof Sun
0
0.11
33
31
-10
0
0
0
Partition
151
0.32
12
7
-5
567
332
-254
S
08-NOV-2019
Return Air Heat Load Gain
Page 150 of 168
1107
SUTHAR KETANBHAI (C360) 150 of 168
Page 67 of 82
797
-571
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM PACKAGE AC ROOM
Sheet No. OWNER
HPCL
SEASON
PROJECT
VRMP
SUMMER
LOCATION ROOM NAME
DB
WB
OUTDOOR
91.9
82.0
NHT CCR FIELD ROOM
INDOOR
75.2
PACKAGE AC ROOM
DIFFERENTIAL
16.7
OUTDOOR
87.1
ROOM SIZE
13.94
11.81
14.60
MONSOON
DESIGN CONDITIONS
ROOM AREA
164.60
Sq.ft
INDOOR
75.2
ROOM VOLUME
2402.55
Cu.ft
DIFFERENTIAL
11.9
OUTDOOR
64.9
INDOOR
75.2
DIFFERENTIAL
-10
OCCUPANCY
0.00
AIR CHANGES
0.00
17.00
cfm/per
WINTER
RH
Gr/LB 150.0
50.0
65.3 84.7
82.0
158.4 50.0
65.3 93.1
57.0
56.4 50.0
0.00
Cfm @ AC/Hr
0.00
Cfm @ Occup
BF
0.17 Occupant Heat
Sens
245.00
0.00
Cfm Selected
1-BF
0.83
Lat
205.00
FRESH AIR
1
65.3 -9
All Glass
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
QTY
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Partition
L
0.00
0.00
0.00
0.00
13.94
0.00
11.81
0.00
25.75
H
14.60
14.60
14.60
14.60
14.60
14.60
14.60
14.60
14.60
NETT AREA
0.00
0.00
0.00
0.00
203.47
0.00
172.35
0.00
375.82
Area
U
Sum
Mon
Win
Sum
Mon
Win
N
0
1.00
23
11
0
0
0
0
NE
0
1.00
12
11
0
0
0
0
E
0
1.00
12
11
0
0
0
0
SE
0
1.00
12
11
0
0
0
0
S
0
1.00
12
11
0
0
0
0
SW
0
1.00
85
113
0
0
0
0
W
0
1.00
163
165
0
0
0
0
NW
0
1.00
138
118
0
0
0
0
GLASS AREA
WALL AREA
Solar Gain - Glass
B.Th.U/Hr/Sq.ft.
0.00
Btu/Hr
Temperature Difference
Solar&Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
203
0.48
17
15
-10
1707
1470
-1002
S SW W NW Roof Sun
0
0.48
15
13
-10
0
0
0
172
0.48
13
11
-10
1115
914
-849
0
0.48
7
5
-10
0
0
0
165
0.11
33
31
-10
606
562
-186
Trans. Gain-Except Wall & Roof All Glass
0
1.13
17
12
-10
0
0
0
Partition
376
0.32
12
7
-5
1412
827
-633
Ceiling
0
0.29
12
7
-5
0
0
0
Floor
0
0.36
12
7
-5
0
0
0
0
Internal Heat Occupants (Nos.)
0
245
0
0
Power (W)
0
3.40
0
0
0
Lights (W)
76
3.40
260
260
130
5100
4034
-2539
5738
4538
-2539
0
0
0
5738
4538
-2539
1.00
Sub Total Safety Factor RSH Outdoor Air ERSH
Page 151 of 168
12.5%
08-NOV-2019
0.00
0.17
17
12
-10
1.08
SUTHAR KETANBHAI (C360) 151 of 168
Page 68 of 82
Proj Engg.
Rahul Lal
Job no
M20/DEL-085.MI
Heat Load Calculations for Airconditioning system Location (Areawise) Appl. Room
NHT CCR FIELD ROOM PACKAGE AC ROOM Sheet No.
Temperature Difference Summer
Monsoon
2
Btu/Hr
Winter
Sum
Mon
Win
0
0
0
0
0
0
0
0
0
0
0
0
ERLH
0
0
0
ERTH
5738
4538
-2539
Latent Heat Occupants(Nos.)
0.00
205.00
0.00 Winter
Sub Total Safety factor
10.0%
RLH Outdoor Air
0.00
0.17
85
93
-9
0.68
Outdoor Air(S)
0.00
0.83
17
12
-10
1.08
0
0
Outdoor Air(Lt)
0.00
0.83
85
93
-9
0.68
0
0
0
GTH
5738
4538
-2539
Refrigeration Load
5738
4538
-2539
Monsoon Reheat
0
1200
Return Air Heat Load
-400
0
Grand Total Refrigeration Load
BTU/HR
5338
5738
Grand Total Refrigeration Load
TR
0.44
0.48
0
Winter KW
-0.74
Monsoon Heaters (KW)
0.35
ESHF =(ERSH/ERTH)
1.00
1.00
ADP (Calculated)
55.00
54.90
ADP (Selected)
54.00
54.00
Deh Rise={(Tr-Tadp)*(1-BF)}
17.60
17.60
302
239
CFM Dehum ={(ERSH)/(1.08*Deh Rise)} Humidifier KW
= {(Moisture addition to FA in Kg/Hr* Latent heat of steam(540))/880}
0.00
Moisture addition (Kg/Hr) =[(FA* Gr Diff(Out-Wint))/(1580*2.2046)]
0.00
Final Values: Selected Load (TR)
0.48
Selected Airquantity (CFM)
301.94
Winter Load (KW)
-0.74
Monsoon Heating (KW)
0.35
Humidifier (KW)
0.00
RETURN AIR HEAT LOAD
WALL AREA
N
NE
E
SE
S
SW
W
NW
L
0.00
0.00
0.00
0.00
13.94
0.00
11.81
0.00
Partition
H
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
NET AREA
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
25.75
Solar & Trans. Gain-Wall & Roof N
0
0.48
5
3
-10
0
0
0
NE
0
0.48
11
9
-10
0
0
0
E
0
0.48
19
17
-10
0
0
0
SE
0
0.48
19
17
-10
0
0
0
S
0
0.48
17
15
-10
0
0
0
SW
0
0.48
15
13
-10
0
0
0
W
0
0.48
13
11
-10
0
0
0
NW
0
0.48
7
5
-10
0
0
0
Roof Sun
0
0.11
33
31
-10
0
0
0
Partition
0
0.32
12
7
-5
0
0
08-NOV-2019
Return Air Heat Load Gain
Page 152 of 168
0
SUTHAR KETANBHAI (C360) 152 of 168
Page 69 of 82
0 0
0
Page 153 of 168
HEAT LOAD ESTIMATION FOR VRMP
SECTION-5 EQUIPMENT SELECTION
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 153 of 168
Page 70 of 82
HEAT LOAD ESTIMATION FOR VRMP
5.1. SELECTION
BUILDING/ FLOOR
AIR CONDITIONING SYSTEM TYPE
Minimum capacity indicated as per tender shall be ensured.
VAM
SYSTEM QUANTITY/ CAPACITY Total Load = 124.62 TR x 65 % each i.e. 81 TR each 2 Nos. of 83 TR VAM (Actual Capacity) 1 No. x 22850 CFM for First Floor
AIR HANDLING UNIT 1 No. x 13550 CFM for Second Floor 1 No. x 21 KW for First Floor
SUBSTATION BUILDING- 86 CT
Page 154 of 168
HEATER 1 No. x 10.5 KW for Second Floor 1 No. x 21 KW for First Floor HUMIDIFIER 1 No. x 9 KW for Second Floor 2 Nos. x 3160 CFM for First Floor CHEMICAL FILTER UNIT 1 No. x 2650 CFM for Second Floor
NHT CCR BUILDING
Water Cooled Package AC
2 Nos.(1W+1S) x 5.5 TR Water Cooled PAC Nominal capacity Dehumidified CFM- 2200 CFM each
-Also indicate Actual capacity of machine. -Capacity of Chemical filter, Heater and humidifier shall be indicated . -Ensure to include 10% margin over calculated capacity for heater and humidifier.
1.Add following note Suitably:(equipment sizing): Air conditioning machine capacity indicated is Actual capacity based on heat load calculation. Equivalent nominal capacity, capacity deration chart (duly furnished by OEM), catalogues etc shall be included in respective equipment datasheet. 2. Capacity margin for Heater and humidifier shall be ensured as per EIL std spec 6-61-0017. VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 154 of 168
Page 71 of 82
HEAT LOAD ESTIMATION FOR VRMP
SECTION-6 ARCHITECTURE DRAWINGS The Arch dwg of substation (CT ) is as per current revision. However, the current revision of Field Room for NHT CCR is attached. Although there is no change in the area under Air conditioning wrt Rev 0, it is advisable that contractor shall use the latest arch drawing for further engineering.
Page 155 of 168
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 155 of 168
Page 72 of 82
Page 156 of 168
HEAT LOAD ESTIMATION FOR VRMP
6.1 LIST OF DRAWINGS: Sl No.
Drawing Title
Drawing Number
A.
Substation- 86 (CT)
1
Ground & First Floor Plan
B015-000-8141-02421, Rev.3
2
Second Floor Plan, Elevations & Sections
B015-000-8141-02422, Rev.2
3
Terrace Plan & Elevations
B015-000-8141-02423, Rev.1
4
Elevations & Sections
B015-000-8141-02424, Rev.2
5
Profile of Doors/Windows
B015-000-8141-02425, Rev.2
B.
Field Room-NHT CCR Plans, Elevations & Sections Terrace Plan, Elevations, Sections & Profile of Doors
B015-000-8141-12821, Rev.0 B015-000-8141-12822, Rev.0
latest revision of drgs for NHT CCR attached. Pl check caln accordingly and use latest revision.
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 156 of 168
Page 73 of 82
Page 157 of 168
HEAT LOAD ESTIMATION FOR VRMP
SUBSTATION BUILDING- 86 CT
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 157 of 168
Page 74 of 82
3
4
5
6
7
8
9
10
11
12
N
14
15
B015-000-81-41-02422 B015-000-81-41-02423 B015-000-81-41-02424 B015-000-81-41-02425
16
REFERENCE DRAWING TITLE SECOND FLOOR PLAN & SECTION TERRACE PLAN, ELEVATION & SECTION ELEVATIONS & SECTIONS DOORS & WINDOWS PROFILE
A
1 NOTES :-
FLOOR TRAP
V1A
V1A
V1A
V1A
REFER NOTE 16 & 17 900 900
RS1
B
AHU ROOM
POWER TRANSFORMER BELOW
HEAVY DUTY FLOORING
GYPSUM BOARD PARTITION UPTO FALSE CEILING
OPERATOR ROOM
1050
AC FC
LOADING/ UNLOADING PLATFORM
MONORAIL 1500
7500
33000
UP SD1A AL1
W2
V1
WALL TO BE CONSTRUCTED AFTER INSTALLATION OF EQUIPMENT
V1
RS1
AIR LOCK LOBBY
FC
AL2
1200
FC AC
1200
VITRIFIED TILE FLOORING
E
UP
UP STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
V1 5500mm HIGH WALL (TYP)
50 DIA G.I. SPOUT (TYP.)
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
DN
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
UP
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
SD1
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER BELOW
DISTRIBUTION TRANSFORMER BELOW
SINK
W1
W1
W1
3500
6000
6000
1
6000
-
3300
STD. STEEL ROLLING SHUTTER, ELECTRICALLY OPERATED
RS2
3000x3000
-
3000
STD. STEEL ROLLING SHUTTER, PARTLY GRILL TYPE, ELECTRICALLY OPERATED
3
D1
1100x2100
0880x2090
2100
35 THK FULLY PANELLED DOOR SOMGLE SHUTTER AS PER EIL STD. 7-75-0066
3
D2
0900x2100
0880x2090
2100 PVC DOOR AS PER SPECIFICATIONS
04
AL1
1500x2500
1480x2490
POWDER COATED ALMN. GLAZED DOOR WITH 2500 6mm THK TOUGHENED GLASS, DOUBLE LEAF AS/EIL STD NO. 7-75-0014.
06
AL2
1000x2100
0980x2090
2100 SAME AS AL1A BUT SINGLE SHUTTER
06
W1
6000
550
6000 66550
6000
50 DIA G.I. SPOUT (TYP.)
2 EXHAUST FANS OF 450MM DIA
6000
6000
6000
6000
3500
F
3000x3300
W1
3
6000
W1
NOS.
RS1
EPOXY PAINT ON FLOOR WITH 2500 MM HIGH EPOXY PAINT ON DADO/WALL
DISTRIBUTION TRANSFORMER BELOW
G
160 Ø R.W.P. (TYP)
LINTEL TYPE OPENING SIZE FRAME SIZE LEVEL
1000 HIGH S.S. RAILING
BATTERY ROOM
1500
6000
DISTRIBUTION TRANSFORMER BELOW
5500mm HIGH WALL (TYP)
SCHEDULE OF DOORS & WINDOWS
1500
V1 1000 HIGH S.S. RAILING
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, SD1 1000 HIGH
1500
7500
FIRE HYDRANT
750
DN
DN
E
D
AIR LOCK LOBBY
AL2
HEAVY DUTY FLOORING
AL2
F
HEAVY DUTY FLOORING
2
SWITCHGEAR HALL
2500
15000
FC
MONORAIL 1500
AL2
AL2
VITRIFIED TILE FLOORING
REMOVEABLE TYPE 1000 HIGH S.S. RAILING
LOADING/ UNLOADING PLATFORM
PROTECTIVE STEEL PLATE COVER OVER EXP JOINT (TYP)
AL2
750
C
LIF T
2
FIRE HYDRANT
7500mm HIGH WALL (TYP)
RS1
HEAVY DUTY FLOORING
D
7500mm HIGH WALL (TYP)
R-150 T-300 W-1500 STEPS
VITRIFIED TILE FLOORING
2300
6000
HEAVY DUTY FLOORING
REMOVEABLE TYPE 1000 HIGH S.S. RAILING
1050
LOADING/ UNLOADING PLATFORM
POWER TRANSFORMER BELOW
CAPACITOR BANK BELOW
CAPACITOR BANK BELOW
2500
2 NOS. MONORAILS TO BE PROVIDED
6000
V1
GIS PANELS
3350
1500
V1
V1
V1
C
03 01
02
ELBUOD , ROOD DEZALG , DETAR ER I F RH - 2 1500x2500 1480x2490 2500 . NO I TAC I F FD1 I CEPS S ' RERUTCAFUNAM REP SA RETTUHS
G
05
73550
FD2
RETTUHS ELGN I S , 1DF SA EMAS 1000x2100 0980x2090 2100
SD1
1500x2500
1480x2490
2500
SD1A
1500x2500
1480x2490
2500 SAME AS SD1 BUT AIR-TIGHT
SD2
1000x2100
980x2090
2100
W1
1200x1800
1180x1790
ALMN. GLAZED WINDOW POWDER COATED WITH 3500 6 mm THKTOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
W2
3500x1800
3480x1790
V1
2600x 600
BEAM ALMN. GLAZED VENTILATOR POWDER COATED 2580x 590 BOTTOM WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
V1A
2600x 600
3
V2
1500x 600
3
V3
4000x 600
BEAM ALMN. GLAZED VENTILATOR POWDER COATED 3980x 590 BOTTOM WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
03
V4
2600x 600
2580x 590
ALMN. GLAZED VENTILATOR POWDER COATED 3500 WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
04
FIRST FLOOR PLAN
SLOPE 1:6 RAMP UP
1000 WIDE PLINTH PROTECTION ALL AROUND THE BUILDING
I
1485
EQ. 115 D2
EQ. D2
O
1340
TOILET
D/W
V1
V1
V1
V1
SLOPE 1:6 RAMP UP
RS2
PE
A C PLANT ROOM
D1
HEAVY DUTY FLOORING (CLEAR HEIGHT 3500mm - BEAM BOTTOM)
100.300
3
POWER TRANSFORMER
12000
F.F.L
LOADING/ UNLOADING PLATFORM
6000
TRANSFORMER GATE AS/ EIL STANDARD NO. 7-75-0052 (TYPICAL)
3 V1
V1 J
SLOPE 1:6 RAMP UP
FC
900
6000
600 WIDE R.C.C. SUNSHADE ABOVE
FLOOR TRAP
SL
SLOPE 1:6 RAMP UP
WALL TO BE CONSTRUCTED AFTER INSTALLATION OF EQUIPMENT
V1
V2
1
3
HEAVY DUTY FLOORING
100.150
100.150
EXHAUST FANS OF 450MM DIA (TYP)
100.150
TOP OF GRAVEL
TOP OF GRAVEL
02
PRESSED STEEL DOOR WITH PRESSED STEEL 08 FRAME, DOUBLE SHUTTER AS/EIL.STD. 7-75-0071 02
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, SINGLE SHUTTER AS/EIL.STD. 7-75-0070
46
ALMN. GLAZED WINDOW POWDER COATED WITH 2500 6 mm THK TOUGHENED GLASS, FIXED TYPE.
BEAM ALMN. GLAZED VENTILATOR POWDER COATED 2580x 590 BOTTOM WITH 6 mm THK TOUGHENED GLASS, FIXED TYPE. ALMN. GLAZED VENTILATOR POWDER COATED 1480x 590 3000 WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
H
05
01
24
I
04
02
J
LEGEND:
100.150
TOP OF GRAVEL
7500mm HIGH WALL (TYP)
V3
POWER TRANSFORMER
CAPACITOR BANK
CAPACITOR BANK
F.R.L. F.F.L.
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL AC = AIR CONDITIONED FC = FALSE CEILING AC UD UD = UNDERDECK INSULATION
TOP OF GRAVEL
7500mm HIGH WALL (TYP)
FC
V1
LIF T
V1
2300
H
K
K
KEY PLAN (Not To Scale) T-300 R-150
T-300 R-150
V1
PE
PE
FLOOR TRAP
345 THK BRICK WALL (TYP)
5500mm HIGH WALL (TYP)
6000
DISTRIBUTION TRANSFORMER 100.150 TOP OF GRAVEL
O SL
345 THK BRICK WALL (TYP) FLOOR TRAP
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER 100.150 TOP OF GRAVEL
345 THK BRICK WALL (TYP)
345 THK BRICK WALL (TYP)
5500mm HIGH WALL (TYP)
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
SD1
TOP OF GRAVEL
TOP OF GRAVEL
TOP OF GRAVEL
1500
6000
FLOOR TRAP
DISTRIBUTION TRANSFORMER 100.150
106.88
1200
100.300
F.F.L
F.F.L SD2
R-150 T-300
550
6000
3 2 1 0 D C B A
RAIN WATER PIPE UNDER FLOOR FOR WATER DISPOSAL (TYPICAL)
100.300
TOP OF GRAVEL
1000 HIGH S.S. RAILING
CEMENT CONCRETE FLOORING
CEMENT CONCRETE FLOORING
V1
3
PE
STORE ROOM
MAINTENANCE ROOM
V1
RAMP UP SLOPE 1:6
6000
M
O
1500
600 6000
DISTRIBUTION TRANSFORMER 100.150
RESIDUE UPGRADATION FACILITY (RUF)
V1
SD2
900
6000
SL
FLOOR TRAP
AL1
RAMP UP SLOPE 1:6
TRANSFORMER GATE AS/ EIL STANDARD NO. 7-75-0051 (TYPICAL)
6000
345 THK BRICK WALL (TYP)
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER 100.150
TOP OF GRAVEL
160 Ø R.W.P. (TYP)
3500
5500mm HIGH WALL (TYP)
100.300 F.F.L
2 1
O
UP
VITRIFIED TILE FLOORING
DISTRIBUTION TRANSFORMER 100.150
RAIN WATER PIPE UNDER FLOOR FOR WATER DISPOSAL (TYPICAL)
345 THK BRICK WALL (TYP)
FLOOR TRAP
LOBBY
5500mm HIGH WALL (TYP)
DISTRIBUTION TRANSFORMER 100.150
PE
345 THK BRICK WALL (TYP)
FIRE HYDRANT
750
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
SL O
PE O
SL
125 (TYP) 1500 (TYP)
07.05.18 13.03.18 08.11.17 02.11.17 11.08.17 21.06.17 16.06.17 08.06.17
REVISED AS MARKED 3 & REISSUED FOR CONSTRUCTION REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION REVISED AS MARKED & RE-ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG. REISSUED FOR TENDER ISSUED FOR TENDER ISSUED FOR COMMENTS
REV. DATE T-300 R-150 STEP UP
RAMP UP SLOPE 1:6
1
6000
L
REVISIONS
SM SM SM SM SM SG SG SG
GJK GJK GJK GJK GJK GJK GJK GJK
BY
JS JS JS JS JS JS JS JS
N
V1
O SL
S/S 86 & SRR (FOR CT)
CWTP
RAMP UP
1500
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
1000 HIGH S.S. RAILING
N
1500
1500 (TYP) UP
SUMP BCW PH
SLOPE 1:6
SD1
125 (TYP) 1500 1500 (TYP) (TYP) UP
M
BCT(6+1)
1800
SD1
7500
750
2
HEAVY DUTY FLOORING
PROTECTIVE STEEL PLATE COVER OVER EXP JOINT (TYP)
OWS/CRWS SUMP-3 & PUMP HOUSE
STEP
CEMENT CONCRETE FLOORING 1500
SLOPE 1:6
1200
15000
FIRE HYDRANT
V3 LOADING/ UNLOADING PLATFORM
CHKD APPD PEM/PC
600 WIDE R.C.C. SUNSHADE ABOVE
O
CABLE CELLAR
1800
RAMP UP
1500
7500
2
L
N
2 1
EXHAUST FANS OF 450MM DIA (TYP)
V3
400.98
1 2
STEP
33000
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
13
EXPANSION JOINT WITH POLYSULPHIDE SEALANT COVERED WITH PROTECTIVE STEEL PLATE
3
12000
A B
2
REF. DWG. NO.
B015-000-81-41-02421
Page 158 of 168
1
(A Govt. of India Undertaking) 6000
6000
6000
6000
3500
66550 73550
100.00
GROUND FLOOR PLAN
P
SUB STATION - 86 (CT) GROUND & FIRST FLOOR PLAN
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 158 of 168
Page 75 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 1 3 A0-1189 x 841
P
F.R.L
A B
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REF. DWG. NO.
B015-000-81-41-02422
Page 159 of 168
1
REFERENCE DRAWING TITLE
B015-000-81-41-02421 GROUND & FIRST FLOOR PLAN B015-000-81-41-02423 TERRACE PLAN & ELEVATION B015-000-81-41-02424 ELEVATIONS & SECTIONS B015-000-81-41-02425 DOORS & WINDOWS PROFILE
A
N NOTES :-
B
2
2 1000 HIGH R.C.C. PARAPET WALL WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL. 750 WIDE R.C.C. GUTTER
C
C
900
TERRACE
WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL. 750 WIDE R.C.C. GUTTER
900
RACK ROOM
900
D
900
1250
800
D
1800
3000
1800
FALSE CEILING
FALSE CEILING AT 4500 HEIGHT 4500
SWITCHGEAR HALL CUT-OUTS IN SWITCHGEAR HALL FLOOR SLAB SHALL BE AS PER RELEVANT STRUCTURE DRAWING
6500
7500
DISTRIBUTION TRANSFORMER
E
CAPACITOR BANK
5500
6500
CABLE CELLAR
100.150
100.300
100.150
F.F.L
TOP OF GRAVEL
100.300
100.00
TOP OF GRAVEL
100.00
F.F.L
F.R.L
F.R.L
F
F
SECTION 1-1
WEST ELEVATION
G
G
EXPANSION JOINT WITH POLYSULPHIDE SEALANT COVERED WITH PROTECTIVE STEEL PLATE
H
3
H
1 750 WIDE RCC GUTTER (TYP)
160 Ø R.W.P. (TYP)
V2 1485
W1
EQ.
W1
W1
W1
FLOOR TRAP
W1
W1
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
W1
AHU ROOM
TECH ROOM
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
900
D1
SLOPE 1:80
D2 FC
SUNK SLAB
I
HEAVY DUTY FLOORING
12000
VITRIFIED TILES FLOORING
LOADING/ UNLOADING PLATFORM
1000 HIGH S.S. RAILING
AC FC UD
TERRACE
UD
TERRACE
HEAVY DUTY FLOORING
TREAD-300 RISER-150 (max.)
J
2 2300
STEP UP
6000
J
SLOPE
1000 HIGH RCC PARAPET WALL (TYP)
TOILET
D/W
6000
1340
D2
I
SLOPE
W1
EQ. 115
LIF T SD1A SD1
4800
VITRIFIED TILE FLOORING
FD1
SD1
W1
W1
DN
2
FALSE FLOORING
RACK ROOM
AC FC FF UD
FIRE HYDRANT
L
DN
STEP DOWN TREAD-300
FALSE FLOORING
EPOXY PAINT ON FLOOR WITH 2500 MM HIGH EPOXY PAINT ON DADO/WALL
VITRIFIED TILES FLOORING
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
FF = FALSE FLOORING
FD2
750
UPS ROOM
BATTERY ROOM
V4
FC
FALSE FLOORING AC FC FF UD
ELECTRICAL ROOM
FF UD
VITRIFIED TILE FLOORING
K
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
AC FC
STEP UP
UP
RISER-150 (max.)
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
AC FC FF UD
SINK
1800
7500
UP
TREAD-300 RISER-150 (max.)
AIR LOCK LOBBY
1200 750
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
V4
FD2
FIRE HYDRANT
F.R.L. F.F.L. FD1
FALSE FLOORING
AC FC FF UD
LEGEND:
W1
W1
ENGINEERING ROOM
LOBBY 2 AL1
L
W1
W1
PROTECTIVE STEEL PLATE COVER OVER EXP JOINT (TYP)
SD1
FC
V4
W1
W1
FD1
1200
7500
33000
VITRIFIED TILE FLOORING
2
W1
W1 FD1
RAMP UP SLOPE 1:7
AC FC UD
AIR LOCK LOBBY
K
WALL TO BE CONSTRUCTED AFTER INSTALLATION OF EQUIPMENT
LOBBY 1
1000
AL1
FD1
V4
15000
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
E
FD1
W1
W1
W1 DN
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
6000
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
W1
W1
W1
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL,1000 HIGH
1500 SLOPE
W1
W1
W1
W1
W1
W1
M
1000 HIGH S.S. RAILING
2
TERRACE
W1
UP
SLOPE
W1
TERRACE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
2 1 0 C B A
N
160 Ø R.W.P. (TYP)
3500
3
6000
6000
6000
1
6000
6000
6000 66550
550
6000
6000
6000
6000
6000
3500
13.03.18 08.11.17 02.11.17 11.08.17 16.06.17 08.06.17
REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION REVISED AS MARKED & RE-ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG. ISSUED FOR TENDER ISSUED FOR COMMENTS
REV. DATE
73550
REVISIONS
O
SM SM SM SM SG SG
GJK GJK GJK GJK GJK GJK
BY
JS JS JS JS JS JS
N
W1
CHKD APPD PEM/PC
O
W1
SLOPE 1:80
W1
1000 HIGH S.S. RAILING
SLOPE 1:80
W1
SLOPE 1:80
W1
SLOPE 1:80
W1
SLOPE 1:80
M
W1
1500
W1
(A Govt. of India Undertaking)
P
SUB STATION - 86 (CT) द्वितीय
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
दृश्य और काट
JOB NO.
SECOND FLOOR PLAN, ELEVATION & SECTION
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 159 of 168
Page 76 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 2 2 A0-1189 x 841
P
SECOND FLOOR PLAN
A B
2
3
4
5
6
7
8
9
10
11
12
13
15
16
REFERENCE DRAWING TITLE
B015-000-81-41-02421 GROUND & FIRST FLOOR PLAN B015-000-81-41-02422 SECOND FLOOR PLAN, ELEVATION & SECTION B015-000-81-41-02424 ELEVATIONS & SECTIONS B015-000-81-41-02425 DOORS & WINDOWS PROFILE
A
N NOTES :-
B
C
C
D
D
E
E
2300
600 HIGH RCC PARAPET WALL (TYP)
F 7500
F
15000
1
G
G
1
SLO
PE
SLO
PE
SLO
PE
7500
NORTH ELEVATION
H 160 Ø PVC RAIN WATER PIPE (TYP.) 3500
160 Ø PVC RAIN WATER PIPE (TYP.)
SLOPE
SLOPE
750 WIDE RAIN WATER GUTTER (TYP)
SLOPE
SLOPE
SLOPE
SLOPE
3
1000 HIGH RCC PARAPET WALL (TYP) SLOPE
SLOPE
1
SLOPE
I
I
MUMTY PLAN SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
6000
TERRACE BELOW
12000
600 HIGH RCC PARAPET WALL (TYP)
J
A MONORAIL BEAM TO BE PROVIDED INSIDE THE MACHINE ROOM (BOTTOM OF BEAM = 2500mm FROM FFL) FOR INSTALLATION OF CHAIN PULLEY IN THE MACHINE ROOM.
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
F.R.L. F.F.L.
SLOPE
7500
7500
LI FT
160 Ø PVC RAIN WATER PIPE (TYP.)
PE
K
2
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
7500
33000
AC UD
E
EXPANSION JOINT WITH POLYSULPHIDE SEALANT COVERED WITH PROTECTIVE STEEL PLATE
K
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
FC
OP
SL
LIFT MACHINE ROOM
2
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
PE SLO
RIDGE LINE
LEGEND:
2300
6000
J
SLO 3500
L
SD2
L 15000
RIDGE LINE
SD2
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
DN
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
MUMTY PLAN
M
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
SLOPE
600 HIGH RCC PARAPET WALL (TYP)
1
SLOPE 1000 HIGH S.S. RAILING
6000
6000
PE
SLO
1000 HIGH S.S. RAILING
SLOPE 1:80
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH 1500
M
1
FIRE HYDRANT
750
DN
SLO PE
STAIRS AS/STRL.DESIGN WD. OF STAIRS-1500 TREAD-300 RISER-150 (max.) RAILING-STAINLESS STEEL, 1000 HIGH
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
DN
SLOPE 1:80
750
7500
SLOPE 1:80
SD2
SLOPE 1:80
SLO
V1
N
160 Ø PVC RAIN WATER PIPE (TYP.)
TERRACE BELOW
N
1 0 B A
SLO
PE
PE
V1 6000
3500
6000
6000
6000
6000
REVISED AS MARKED 1 & REISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG. ISSUED FOR TENDER
REV. DATE
160 Ø R.W.P. (TYP)
3
13.03.18 08.11.17 11.08.17 16.06.17
REVISIONS
SM SM SM SG
GJK GJK GJK GJK
BY
JS JS JS JS
CHKD APPD PEM/PC
1 6000
6000
550
6000
6000
6000
6000
6000
3500
(A Govt. of India Undertaking)
66550
0
O
FIRE HYDRANT
1200
SD2
1200
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
14
REF. DWG. NO.
B015-000-81-41-02423
Page 160 of 168
1
MUMTY PLAN
73550
SUB STATION - 86 (CT) छत
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
दृश्य
JOB NO.
TERRACE PLAN & ELEVATION
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 160 of 168
Page 77 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 3 1 A0-1189 x 841
P
TERRACE PLAN P
A B
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REF. DWG. NO.
B015-000-81-41-02424
Page 161 of 168
1
REFERENCE DRAWING TITLE
B015-000-81-41-02421 GROUND & FIRST FLOOR PLAN B015-000-81-41-02422 SECOND FLOOR PLAN & SECTION B015-000-81-41-02423 TERRACE PLAN & ELEVATION B015-000-81-41-02425 DOORS & WINDOWS PROFILE
A
N NOTES :-
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL.
B
LOBBY
3800
2500
AIR LOCK LOBBY
RACK ROOM
ENGINEERING ROOM
800
AIR LOCK LOBBY
FALSE CEILING 3000
FALSE CEILING
C
C MONORAIL
MONORAIL 1500 1500
FALSE CEILING AT 4500 HEIGHT
SWITCHGEAR HALL
D
600
3300 600
D
LOADING/ UNLOADING PLATFORM
4500
ROLLING SHUTTER
3300
LOADING/ UNLOADING PLATFORM
LOADING/ UNLOADING PLATFORM
LOADING/ UNLOADING PLATFORM
CABLE CELLAR 100.300
100.00
F.F.L
F.R.L
E
2
SECTION 2-2
F
F 1000 HIGH R.C.C. PARAPET WALL WATER PROOFING AS/TENDER SPECS. R.C.C. SLAB AS/STRL. 750 WIDE R.C.C. GUTTER
TERRACE
G
G
2700
LOBBY
2500
BATTERY ROOM
3800
2500
FALSE CEILING
AHU ROOM
CINDER FILLING
H 900
1250
H
FALSE CEILING AT 4500 HEIGHT
SWITCHGEAR HALL 4500
AHU ROOM
DISTRIBUTION TRANSFORMER
I 5500
I
2500
CUT-OUTS IN SWITCHGEAR HALL FLOOR SLAB SHALL BE AS PER RELEVANT STRUCTURE DRAWING 6500
AC PLANT ROOM
3000
CABLE CELLAR 100.300
100.150
100.300
100.00
F.F.L
TOP OF GRAVEL
F.F.L
F.R.L
2 J
J
SECTION 3-3
EAST ELEVATION
LEGEND: F.R.L. F.F.L.
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
K
K
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
FC AC UD
L
L
M
M
N
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
E
N
07.05.18 13.03.18 08.11.17 11.08.17
REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION REVISED AS MARKED 1 & REISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION ISSUED FOR DET. ENGG.
REV. DATE
O
REVISIONS
SM SM SM SM
GJK GJK GJK GJK
BY
JS JS JS JS
CHKD APPD PEM/PC
O
2 1 0 A
(A Govt. of India Undertaking)
2
SUB STATION - 86 (CT) दृश्य और
SCALE
001:1 1
2
3
4
5
6
7
8
9
10
11
12
13
14
काट
JOB NO.
ELEVATIONS & SECTIONS
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 161 of 168
Page 78 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 4 2 A0-1189 x 841
P
SOUTH ELEVATION P
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
REF. DWG. NO.
1480 1480
EQ.
N 880
500
2490
2090
VISION PANEL AS PER SPECIFICATION
VISION PANEL AS PER SPECIFICATION
NOTES :-
900
1350
LATCH AND LOCKING SYSTEM
900
900
GLASS
B
1350
2490
2090
PRESSED STEEL FRAME
LATCH AND LOCKING SYSTEM
900
GLASS
OVER HEAD HYDRAULIC DOOR CLOSER (HEAVY DUTY)
PRESSED STEEL FRAME
DOOR STOPPER
TEAK WOOD BOTTOM RAIL 200x35
A
AL. FRAME GLASS
GLASS
GLASS
OVER HEAD HYDRAULIC DOOR CLOSER (HEAVY DUTY)
500
AL. FRAME GLASS
75 LONG ALUMINIUM TOILET DOOR LATCH
300x25x6 THK. M.S. HOLD FAST @ MAX. 600 C/C. 11.10 DIA. 150 LONG ALUMINIUM BUTT HINGES @ MAX. 600 C/C.
1335 C
TOWER BOLT
CHROMIUM PLATE BRASS COAT AND HAT HOOK FIXED WITH BRASS SCREWS. (INTERNAL SIDE OF THE DOOR)
TEAK WOOD LOCK RAIL 150x35
EQ.
REFERENCE DRAWING TITLE GROUND & FIRST FLOOR PLAN SECOND FLOOR PLAN, ELEVATION & SECTION TERRACE PLAN & ELEVATION ELEVATIONS & SECTIONS
980
12 THK. PARTICLE BOARD
75 LONG ALUMINIUM TOILET DOOR LATCH
EQ.
ALUMINIUM TOWER BOLT 150X10 mm.
TEAK WOOD TOP RAIL 100x35 TEAK WOOD FRAME OUT OF 125x65 TEAK WOOD STYLE 100x35
CHROMIUM PLATE BRASS COAT AND HAT HOOK FIXED WITH BRASS SCREWS. (INTERNAL SIDE OF THE DOOR)
B015-000-81-41-02421 B015-000-81-41-02422 B015-000-81-41-02423 B015-000-81-41-02424
1480 EQ.
2490
1180 ALUMINIUM TOWER BOLT 150X10 mm.
2090
A B
B015-000-81-41-02425
Page 162 of 168
1
DOOR STOPPER
C
ACRYLIC KICK PLATE 200X3 THICK. RUBBER BEADING
ELEVATION : D1
ELEVATION : D2
35 THK FULLY PANELLED DOOR SINGLE SHUTTER AS/EIL STD NO. 7-75-0066 D
OPENING SIZE REQUIRED NOS.
: :
OPENING SIZE REQUIRED NOS.
2
: :
DOOR HANDLE
DOOR HANDLE
POWDER COATED ALMN. GLAZED DOOR WITH 6mm THK TOUGHENED GLASS, DOUBLE LEAF AS/EIL STD NO. 7-75-0014.
0900x2100 04
OPENING SIZE REQUIRED NOS.
: :
RUBBER BEADING
ELEVATION :SD1
ELEVATION :SD1A
SAME AS AL1A, BUT SINGLE SHUTTER
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, DOUBLE SHUTTER AS/EIL.STD. 7-75-0071
SAME AS SD1, BUT AIRTIGHT
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
ELEVATION : AL2
ELEVATION : AL1
PVC DOOR SINGLE SHUTTER
1100x2100 02
LEGEND-
RUBBER BEADING
F. - FIXED GLASS. SH. - SIDE HUNG SHUTTER. TH. - TOP HUNG SHUTTER.
D
1500x2500 06
: :
1000x2100 06
: :
1500x2500 08
: :
1500x2500 02
2 1180
(6 EQ.PARTS)
E
600
F
600
980
ARCHITECTURAL FINISHES SCHEDULE OVER HEAD HYDRAULIC DOOR CLOSER (HEAVY DUTY)
F
F
F
F
F
F
LOADING/ UNLOADING PLATFORM
HEAVY DUTY FLOORING
TRANSFORMER/ CAPACITOR BANK/ POWER TRANSFORMER
GRAVEL
910
910
1350
LATCH AND LOCKING SYSTEM
900
CEMENT CONCRETE FLOORING
CABLE CELLAR
SKIRTING/ WALL BASE 125mm HIGH CEMENT PLASTER SKIRTING 125mm HIGH CEMENT PLASTER SKIRTING
G
DOOR STOPPER
ELEVATION : W1
ELEVATION : W2
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, SINGLE SHUTTER AS/EIL.STD. 7-75-0070
ALMN. GLAZED WINDOW POWDER COATED WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
ALMN. GLAZED WINDOW POWDER COATED WITH 6 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
: :
1000x2100 05
: :
1200x1800 46
: :
BOTTOM OF ROOF BEAM
F
580
ROOF BEAM
I
T.H.
SWITCHGEAR HALL
(5 EQ.PARTS) BOTTOM OF
T.H.
F
F
F
F
T.H.
AIR HANDLING UNIT
F
2990
ELEVATION : V1
ELEVATION : V1A
ELEVATION : V2
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE. OPENING SIZE : 2600x0600 REQUIRED NOS. : 24
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, FIXED TYPE.
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, OPENABLE TYPE.
OPENING SIZE REQUIRED NOS.
OPENING SIZE REQUIRED NOS.
2580
580
F
T.H.
F
125mm HIGH CEMENT CEMENT PLASTER + POP PUNNING + PLASTIC PLASTER SKIRTING EMULSION PAINT 125mm HIGH CEMENT CEMENT PLASTER + OIL PLASTER SKIRTING BOUND DISTEMPER
HEAVY DUTY FLOORING
: :
1500x0600 02
BATTERY ROOM
EPOXY PAINT
OPERATOR ROOM
VITRIFIED TILE FLOORING
2
(5 EQ.PARTS)
T.H.
125mm HIGH VITRIFIED TILES SKIRTING -
125mm HIGH GRANITE SKIRTING -
125mm HIGH VITRIFIED TILES SKIRTING
BOTTOM OF
F
T.H.
F
P
2
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
2500 MM HIGH EPOXY PAINT ON WALL OVER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT ABOVE 2500MM HEIGHT
CEMENT PLASTER + OIL BOUND DISTEMPER
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
GYPSUM BOARD PANEL FALSE CEILING
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
UPS ROOM
FALSE FLOORING
-----
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
VITRIFIED TILE FLOORING
LOBBY
ELEVATION : V4
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
-----
125mm HIGH VITRIFIED TILES SKIRTING
K
L
M
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
2 07.05.18 REVISED AS MARKED 2 & REISSUED FOR CONSTRUCTION 1 13.03.18 REVISED AS MARKED 1 & REISSUED FOR CONSTRUCTION 0 08.11.17 ISSUED FOR CONSTRUCTION REV. DATE
VITRIFIED TILE FLOORING
125mm HIGH VITRIFIED TILES SKIRTING
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
VITRIFIED TILE FLOORING
125mm HIGH VITRIFIED TILES SKIRTING
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
O
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE. OPENING SIZE : 2600x0600 REQUIRED NOS. : 04
CEMENT PLASTER + OIL BOUND DISTEMPER
FALSE FLOORING
ELECTRICAL ROOM
ELEVATION : V3
CERAMIC TILES DADO UP TO CEILING
ENGG. ROOM
TECH. ROOM
ALMN. GLAZED VENTILATOR POWDER COATED WITH 5 mm THK TOUGHENED GLASS, PARTLY FIXED PARTLY OPENABLE TYPE. OPENING SIZE : 4000x0600 REQUIRED NOS. : 03
GYPSUM BOARD PANEL FALSE CEILING
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
T.H.
N
I
CEMENT PLASTER + OIL BOUND DISTEMPER
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
3500
580
T.H.
H
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
-----
ROOF BEAM F
CEMENT PLASTER + OIL BOUND DISTEMPER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
FALSE FLOORING
3980
T.H.
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
G
RACK ROOM T.H.
(7 EQ.PARTS)
M
CEMENT PLASTER + OIL BOUND DISTEMPER
HEAVY DUTY FLOORING
GRANITE STONE FLOORING WITH ATI SLIP GROOVES
STAIRCASE
2
CEMENT PLASTER + OIL BOUND DISTEMPER
F
J
K
2600x0600 04
CEMENT PLASTER + OIL BOUND DISTEMPER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
125mm HIGH CEMENT CEMENT PLASTER + OIL PLASTER SKIRTING BOUND DISTEMPER
NON-SLIP VITRIFIED TILE FLOORING
TOILET
: :
CEMENT PLASTER + OIL BOUND DISTEMPER CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
125mm HIGH CEMENT CEMENT PLASTER + POP PLASTER SKIRTING PUNNING + PLASTIC EMULSION PAINT
VITRIFIED TILE FLOORING
2410
J
CEILING FINISH
CEMENT CONCRETE FLOORING
F
AIR LOCK LOBBY
L
HEAVY DUTY FLOORING
1500
2580
(5 EQ.PARTS)
F
STORE & MAINTENANCE ROOM
3500x1800 01
(3 EQ.PARTS)
2580
T.H.
A C PLANT ROOM
580
H
ELEVATION : SD2
-----
WALL FINISH
N
S.H.
CEMENT PLASTER + POP PUNNING + PLASTIC EMULSION PAINT
2
3
4
5
SM SM SM
GJK GJK GJK
BY
JS JS JS
CHKD APPD PEM/PC
(A Govt. of India Undertaking)
COMBINATION OF MINERAL FIBRE TILES & GYPSUM BOARD PANEL FALSE CEILING
SUB STATION - 86 (CT) PROFILE OF DOORS/WINDOWS
SCALE
001:1 1
REVISIONS
O
2690 1180
S.H.
6
7
8
9
10
11
12
13
14
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
15
16
3-1641-0500 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 162 of 168
Page 79 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 0 2 4 2 5 2 A0-1189 x 841
P
2090
500
PRESSED STEEL FRAME VISION PANEL AS PER SPECIFICATION
FLOOR FINISH
ROOM 2690 1180
F
580
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
3480
(2 EQ.PARTS)
E
Page 163 of 168
HEAT LOAD ESTIMATION FOR VRMP
NHT CCR BUILDING
VIZAG REFINERY EXPANSION PROJECT 08-NOV-2019 SUTHAR KETANBHAI (C360) 163 of 168
Page 80 of 82
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING (AS/SPECS.) R.C.C. SLAB AS/ STRL. DETAIL
N
REFERENCE DRAWING TITLE
NOTES:
750 WIDE R.C.C. GUTTER
1000
1. ALL DIMENSIONS ARE IN MILLIMETRES & LEVELS IN METRES. 2. EL100.000 INDICATES FINISHED APPROACH ROAD LEVEL NEAR THE BUILDING. 3. UNDERDECK INSULATION SHALL BE PROVIDED UNDER THE ROOF OF AC PACKAGE ROOM AND OTHER AC AREAS. 4. ALL OUTSIDE SURFACES SHALL BE FINISHED WITH 18MM. THK PLAIN CEMENT PLASTER ON BRICK SURFACES & 6MM THK PLAIN CEMENT PLASTER ON R.C.C. SURFACES, EXCEPT SAND FACE PLASTER WHEREVER MENTIONED. 5. ALL INTERNAL PERIPHERIAL WALLS SHALL BE FINISHED WITH 12MM THK PLAIN CEMENT PLASTER & 12MM/15MM THK PLAIN CEMENT PLASTER ON EITHER SIDE OF INTERNAL WALLS. 6MM THK PLAIN CEMENT PLASTER SHALL BE PROVIDED ON BOTTOM / UNDERSIDE OF ROOF. 6. 1000 WIDE PLINTH PROTECTION WITH BUILDING DRAIN SHALL BE PROVIDED ALL AROUND THE BUILDING. 7. ALL DOORS IN AC AREAS SHALL BE AIR TIGHT. 8. FOR INTERNAL AND EXTERNAL FINISHES, ENGINEERING DESIGN BASIS SHALL BE REFERRED. 9. FOR EXACT COORDINATES, LOCATION RESPECTIVE AREA DRAWING SHALL BE REFERRED. 10. LAN, TELEPHONE, SEATING POSITION IN SHIFT INCHARGE SHALL BE FINALISED INITIALLY TO AVOID REWORK ON PLASTERED SURFACES. 11. PROVISION OF STANDBY CEILING FANS ON WALL TO BE MADE IN ALL THE AREAS.
SHIFT INCHARGE ROOM
FALSE CEILING
PASSAGE
3000
B015-000-81-41-12821
100.450 100.00
100.00
F.R.L
F.R.L
F.F.L
19500
12. OTHER FACILITIES TO BE PROVIDED ARE AS FOLLOWS:
SECTION X-X
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
NORTH ELEVATION
A. A SMALL CHAIR/ SOFA TO BE PROVIDED IN WASH ROOMS/ CHANGE ROOMS. B. INDIVIDUAL LOCKERS WITH PROPER KEY AND LOCK SYSTEM TO BE PROVIDED. C. PROPER SIGNBOARD (HE/SHE, LADIES/GENTS WASHROOM) TO BE DISPLAYED IN ALL WASHROOMS. D. FOR ALL WESTERN/ INDIAN FACILITIES, WATER GUNS/ JET SPRAY TO BE PROVIDED. E. HAND DRIER IN ALL THE WASHROOMS TO BE PROVIDED. F. FOLLOWING FACILITIES IN ALL THE WASHROOMS TO BE PROVIDED. · FULL SIZE MIRROR · LIQUID HAND WASH · BATHROOM FRESHENERS · TOWELS · PROPER LIGHTING FACILITIES · TISSUE ROLLS · VENDING MACHINE FOR SANITARY NAPKINS, SANITARY DISPOSAL DUSTBIN & PAPER WRAPS FOR DISPOSAL IN LADIES WASHROOM
SCHEDULE OF DOORS & WINDOWS TYPE OPENING SIZE FRAME SIZE
100.00 F.R.L
19500
SOUTH ELEVATION
LINTEL DESCRIPTION LEVEL
NOS.
m m6 HT IW ROOD DEZALG . NMLA DETAOC REDWOP AL1 1100x2100 1080x2090 2100 RETTUHS E LGN I S , S SALG DENEHGUOT . KHT
01
m m6 HT IW ROOD DEZALG . NMLA DETAOC REDWOP AL2 1200x2100 1180x2090 2100 RETTUHS E LGN I S , S SALG DENEHGUOT . KHT
01
RETTUHS E LBUOFD1 D , ROO D DEZALG , 1480x2090 DETAR ER I F 2100 RH - 2 1500x2100 . NO I TAC I F I CEP S S ' RERUTCAFUNAM REP SA
01
D1
1100x2100
1080x2090
2100
35mm THK. PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
02
D2
900x2100
880x2090
2100
35mm THK. PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
02
SD1
1200x2100
1180x2090
2100
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, 01 AIR-TIGHT,SINGLE SHUTTER AS/EIL.STD. 7-75-0070
EAST ELEVATION X
E-752.37 N-875.72
D2
HEAVY DUTY FLOORING
2500
1600
F.R.L
FC UD
NHT/CCR UNIT
Y
VITRIFIED TILE FLOORING
BATH
F.R.L. F.F.L.
100.00
DOCMETN/ STORE ROOM
SHIFT INCHARGE ROOM VITRIFIED TILE FLOORING AC FC UD
NON SLIP VITRIFIED TILE FLOORING
2
CAT LADDER
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
= 230 THK BRICK WALL = RCC BLAST RESISTANT WALL
N FC AC UD
AL1
G.LOCKER ROOM
UD
F.F.L
LEGEND:
STEP UP R = 150 T = 300
2
1400
BATH
EQ
NON SLIP VITRIFIED TILE FLOORING
FD1
1600
EQ
G. TOILET
AC PACKAGE ROOM
8500
BATH
100.450
115 900
11500
EQ
WC
EQ
1600
GRANITE FLOORING
FC UD
11.50 3
EQ EQ
3000
Y
FC UD
PASSAGE
D1
NON SLIP VITRIFIED TILE FLOORING
NON SLIP VITRIFIED TILE FLOORING
WC WC
L.LOCKER ROOM
D2
L. TOILET FC UD
45°
WC
1600
1000 WIDE PLINTH PROTECTION (TYP.)
300 DIA EXHAUST FAN AT 3000 HEIGHT WITH RCC HOOD (TYP.)
FIELD ROOM (BLAST RESISTANT) NHT/CCR 19.5X11.5
AC = AIR CONDITIONED (SPLIT TYPE AC) FC = FALSE CEILING UD = UNDERDECK INSULATION
BLAST RESISTANT STRUCTURE
3 19.50
D1
SD1
F.F.L
PASSAGE
VITRIFIED TILE FLOORING
AL2
GRANITE FLOORING
AC FC UD
1000
100.450
1900
DINING ROOM
RAMP UP 1:12
45°
Page 164 of 168
REF. DWG. NO.
B015-000-81-41-12822 TERRACE PLAN, ELEVATION, SECTION & PROFILES OF DOORS
D/W
0 G F E D C B A
100.00 F.R.L 160 dia PVC RWP EMBEDDED IN PCC (TYP.)
4500
3500
4500
750 WIDE RCC GUTTER ABOVE (TYP.) 7000
22.07.19 02.04.19 11.01.19 30.11.18 01.11.18 27.07.18 28.06.18 14.06.18
ISSUED FOR CONSTRUCTION REVISED AND REISSUED FOR ENGG. ISSUED FOR DET. ENGG. REVISED & REISSUED FOR COMMENTS/TENDER ISSUED FOR TENDER REVISED AND REISSUED FOR CLIENTS APPROVAL REISSUED FOR COMMENTS ISSUED FOR COMMENTS
REV. DATE
REVISIONS
SM SM SM SM SM SM SM SM BY
GJK GJK GJK GJK GJK GJK GJK GJK
JS JS JS JS JS JS JS JS
CHKD APPD PEM/PC
19500
KEY PLAN
X
GROUND FLOOR PLAN FIELD ROOM - NHT CCR SCALE
001:1
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
3-1641-0501 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 164 of 168
Page 81 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 1 2 8 2 1 0 A1-841 x 594
REFERENCE DRAWING TITLE
N 1080
1080
1480
1180
1180
880
NOTES:
DEZALG .M NLADETA O CRW O ED P .K H Tm m 6H TW IR O D ELG NIS ,SSALGDENEH G U O T RETT U HS
DEZALG .M NLADETA O CRW O ED P .K H Tm m 6H TW IR O D ELG NIS ,SSALGDENEH G U O T RETT U HS
OPENING SIZE = 1100X2100
,R O DDEZALG ,DETARERIFR H -2 REP SARETT U HS ELB U O D .N OITACIFICEPS S 'RER U TCAFU N M A OPENING SIZE = 1500X2100
2090
2090
2090
2090
2090
1. ALL DIMENSIONS ARE IN MILLIMETRES & LEVELS IN METRES. 2. FOR ALL OTHER NOTES, REFER DWG. NO. B015-000-81-41-12821.
2090
B015-000-81-41-12822
35mm THK. WOODEN PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
35mm THK. WOODEN PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, AIR-TIGHT,SINGLE SHUTTER AS/EIL.STD. 7-75-0070
OPENING SIZE = 1100X2100
OPENING SIZE = 900X2100
OPENING SIZE = 1200X2100
OPENING SIZE = 1200X2100
PROFILES OF DOORS
300
1000
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING (AS/SPECS.) R.C.C. SLAB AS/ STRL. DETAIL
FALSE CEILING
230 300 230
GENTS TOILET 3000
1000
100.00
DOCMETN/ STORE ROOM
100.450
SHIFT INCHARGE RM. 3000
1000
F.F.L
F.R.L
SECTION Y-Y
WEST ELEVATION
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
8500
SLOPE 1:80
3000
1000 HIGH RCC PARAPET WALL (TYP)
11500
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
(SCALE - 1:50)
0 30
Page 165 of 168
REF. DWG. NO.
B015-000-81-41-12821 PLANS, ELEVATIONS & SECTION
1000
CAT LADDER
SLOPE 160 Ø PVC RAIN WATER PIPE (TYP.)
SLOPE
SLOPE
SLOPE
SLOPE
750 WIDE RCC GUTTER (TYP.)
4500
3500
4500 19500
7000
0 22.07.19 ISSUED FOR CONSTRUCTION B 02.04.19 REVISED AND REISSUED FOR ENGG. A 11.01.19 ISSUED FOR DET. ENGG. REV. DATE
REVISIONS
SM SM SM BY
GJK GJK GJK
JS JS JS
CHKD APPD PEM/PC
TERRACE PLAN FIELD ROOM - NHT CCR SCALE
001:1
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
3-1641-0501 REV.2
08-NOV-2019 SUTHAR KETANBHAI (C360) 165 of 168
Page 82 of 82
REV.
B 0 1 5 0 0 0 8 1 4 1 1 2 8 2 2 0 A1-841 x 594
Page 166 of 168
The Arch dwg of substation (CT ) is as per current revision. However, the current revision of Field Room for NHT CCR is attached. Although there is no change is the area under Air conditioning wrt Rev 0, it is advisable that contractor shall use the latest arch drawing.
08-NOV-2019 SUTHAR KETANBHAI (C360) 166 of 168
REF. DWG. NO.
REFERENCE DRAWING TITLE TERRACE PLAN, ELEVATION, SECTION & PROFILES OF DOORS
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING (AS/SPECS.) R.C.C. SLAB AS/ STRL. DETAIL
N
NOTES:
750 WIDE R.C.C. GUTTER
1000
1. ALL DIMENSIONS ARE IN MILLIMETRES & LEVELS IN METRES. 2. EL100.000 INDICATES FINISHED APPROACH ROAD LEVEL NEAR THE BUILDING. 3. UNDERDECK INSULATION SHALL BE PROVIDED UNDER THE ROOF OF AC PACKAGE ROOM, OTHER AC AREAS AND AS MARKED IN THE DRAWING. 4. ALL OUTSIDE SURFACES SHALL BE FINISHED WITH 18MM. THK PLAIN CEMENT PLASTER ON BRICK SURFACES & 6MM THK PLAIN CEMENT PLASTER ON R.C.C. SURFACES, EXCEPT SAND FACE PLASTER WHEREVER MENTIONED. 5. ALL INTERNAL PERIPHERIAL WALLS SHALL BE FINISHED WITH 12MM THK PLAIN CEMENT PLASTER & 12MM/15MM THK PLAIN CEMENT PLASTER ON EITHER SIDE OF INTERNAL WALLS. 6MM THK PLAIN CEMENT PLASTER SHALL BE PROVIDED ON BOTTOM / UNDERSIDE OF ROOF. 6. 1000 WIDE PLINTH PROTECTION WITH BUILDING DRAIN SHALL BE PROVIDED ALL AROUND THE BUILDING. 7. ALL DOORS IN AC AREAS SHALL BE AIR TIGHT. 8. FOR INTERNAL AND EXTERNAL FINISHES, ENGINEERING DESIGN BASIS SHALL BE REFERRED. 9. FOR EXACT COORDINATES, LOCATION RESPECTIVE AREA DRAWING SHALL BE REFERRED. 10. LAN, TELEPHONE, SEATING POSITION IN SHIFT INCHARGE SHALL BE FINALISED INITIALLY TO AVOID REWORK ON PLASTERED SURFACES. 11. PROVISION OF STANDBY CEILING FANS ON WALL TO BE MADE IN ALL THE AREAS.
PASSAGE
3000
3000
3000
FALSE CEILING
100.450 100.00
100.00
F.R.L
F.F.L
F.R.L
19500
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
A. A SMALL CHAIR/ SOFA TO BE PROVIDED IN WASH ROOMS/ CHANGE ROOMS. B. INDIVIDUAL LOCKERS WITH PROPER KEY AND LOCK SYSTEM TO BE PROVIDED. C. PROPER SIGNBOARD (HE/SHE, LADIES/GENTS WASHROOM) TO BE DISPLAYED IN ALL WASHROOMS. D. FOR ALL WESTERN/ INDIAN FACILITIES, WATER GUNS/ JET SPRAY TO BE PROVIDED. E. HAND DRIER IN ALL THE WASHROOMS TO BE PROVIDED. F. FOLLOWING FACILITIES IN ALL THE WASHROOMS TO BE PROVIDED. FULL SIZE MIRROR LIQUID HAND WASH BATHROOM FRESHENERS TOWELS PROPER LIGHTING FACILITIES TISSUE ROLLS VENDING MACHINE FOR SANITARY NAPKINS, SANITARY DISPOSAL DUSTBIN & PAPER WRAPS FOR DISPOSAL IN LADIES WASHROOM
SCHEDULE OF DOORS & WINDOWS TYPE OPENING SIZE FRAME SIZE
100.00
LINTEL DESCRIPTION LEVEL
NOS.
AL1
1100x2100
1080x2090
2100
02
AL2
1200x2100
1180x2090
2100
01
FD1
1500x2100
1480x2090
2100
D1
1100x2100
1080x2090
2100
35mm THK. PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
02
D2
900x2100
880x2090
2100
35mm THK. PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
03
SD1
1200x2100
1180x2090
2100
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, 01 AIR-TIGHT,SINGLE SHUTTER AS/EIL.STD. 7-75-0070
F.R.L
19500
SOUTH ELEVATION
01
EAST ELEVATION X
E-752.37 N-875.72
1000 WIDE PLINTH PROTECTION (TYP.)
300 DIA EXHAUST FAN AT 3000 HEIGHT WITH RCC HOOD (TYP.)
EQ
NON SLIP VITRIFIED TILE FLOORING
L. TOILET NON SLIP VITRIFIED TILE FLOORING
1400
FC UD
WC
LEGEND: F.R.L. F.F.L.
= FINISHED ROAD LEVEL = FINISHED FLOOR LEVEL
F.F.L
FD1
G. TOILET
1600
NON SLIP VITRIFIED TILE FLOORING
PE
D2
AC PACKAGE ROOM
2500
FC UD
FC UD
D2
N FC AC UD
AL1
AC = AIR CONDITIONED FC = FALSE CEILING UD = UNDERDECK INSULATION
AL1
SHIFT INCHARGE ROOM
FC UD
VITRIFIED TILE FLOORING AC FC UD
NON SLIP VITRIFIED TILE FLOORING
UD
Y
VITRIFIED TILE FLOORING
BATH
G.LOCKER ROOM
HEAVY DUTY FLOORING
= RCC BLAST RESISTANT WALL
DOCMETN/ STORE ROOM
2
EQ
BATH
11.50 3
SLO
PASSAGE GRANITE FLOORING
100.450
1600
EQ
EQ
WC
BATH
115 900
1600
D1
FC UD
= 230 THK BRICK WALL
EQ
WC
L.LOCKER ROOM
D2
EQ
3000
1600
11500
F.R.L
2000
WC
Y
100.00
STEP UP
R = 150 T = 300
8500
BLAST RESISTANT STRUCTURE
2
CAT LADDER
3 19.50
D1
SD1
DINING ROOM
100.450 F.F.L
PASSAGE
VITRIFIED TILE FLOORING
AL2
GRANITE FLOORING
AC FC UD
1000
RAMP UP 1:12
1900
izLrqr vkjs[k ,oa blesa fufgr fMt+kbu bathfu;LkZ bafM;k fyfeVsM dh LkaifRr gSA ;s ek= m/kkj fn, x, gSa vkSj m/kkjdrkZ us ;g Li"V Lke>kSrk fd;k gS fd u rks mUgsa iqu% eqfnzr fd;kk tk,xk] u udy dh tk,xh] u m/kkj fn, tk,axs] u iznf'kZr fd, tk,axs vkSj u gh Lkhfer vkSj futh iz;ksx ds vykok budk dksbZ vU; iz;ksx gksxk vkSj ;g iz;ksx m/kkj nsus okys }kjk m/kkjdrkZ dks fyf[kr :i esa nh xbZ Lkgefr Lks gksxk A
Page 167 of 168
12. OTHER FACILITIES TO BE PROVIDED ARE AS FOLLOWS:
SECTION X-X
NORTH ELEVATION
100.00 F.R.L 160 dia PVC RWP EMBEDDED IN PCC (TYP.)
4500
3500
4500
750 WIDE RCC GUTTER ABOVE (TYP.) 7000 DATE
REVISIONS
BY
CHKD APPD
19500
X
GROUND FLOOR PLAN 08-NOV-2019 SUTHAR KETANBHAI (C360) 167 of 168
KEY PLAN okbtSx fjQkbujh uohuhdj.k izkstSDV QhyM :e&,u,pVh lhlhvkj SCALE
JOB NO.
UNIT
DIVN. DEPT.
DWG. NO.
3-1641-0501 REV.2
REV.
A1-841 x 594
REF. DWG. NO.
REFERENCE DRAWING TITLE PLANS, ELEVATIONS & SECTION
N 1480
1080
1180
880
NOTES:
EQ.
2090
2090
2090
1. ALL DIMENSIONS ARE IN MILLIMETRES & LEVELS IN METRES. 2. FOR ALL OTHER NOTES, REFER DWG. NO. B015-000-81-41-12821.
1100
2090
EQ.
2090
1180
2090
1080
CONTRACTOR TO CHECK SIZE OF OPENING OF DOORS/WINDOWS/VENTILATORS AT SITE BEFORE FABRICATION OF THE SAME.
OPENING SIZE = 1500X2100 OPENING SIZE = 1100X2100
35mm THK. WOODEN PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
35mm THK. WOODEN PANEL DOOR SHUTTER, SINGLE LEAF AS/EIL STD.
PRESSED STEEL DOOR WITH PRESSED STEEL FRAME, AIR-TIGHT,SINGLE SHUTTER AS/EIL.STD. 7-75-0070
OPENING SIZE = 1100X2100
OPENING SIZE = 900X2100
OPENING SIZE = 1200X2100
OPENING SIZE = 1200X2100
PROFILES OF DOORS
300
FALSE CEILING
GENTS TOILET 3000
1000
100.00
DOCMETN/ STORE ROOM
100.450
SHIFT INCHARGE RM.
3000
230 300 230
3000
1000
0
Page 168 of 168
1000
The drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use.
1000 HIGH R.C.C. PARAPET WALL WATER PROOFING (AS/SPECS.) R.C.C. SLAB AS/ STRL. DETAIL
30
F.F.L
F.R.L
SECTION Y-Y
WEST ELEVATION
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
SLOPE 1:80
11500
3000
1000 HIGH RCC PARAPET WALL (TYP)
8500
CAT LADDER
1000
izLrqr vkjs[k ,oa blesa fufgr fMt+kbu bathfu;LkZ bafM;k fyfeVsM dh LkaifRr gSA ;s ek= m/kkj fn, x, gSa vkSj m/kkjdrkZ us ;g Li"V Lke>kSrk fd;k gS fd u rks mUgsa iqu% eqfnzr fd;kk tk,xk] u udy dh tk,xh] u m/kkj fn, tk,axs] u iznf'kZr fd, tk,axs vkSj u gh Lkhfer vkSj futh iz;ksx ds vykok budk dksbZ vU; iz;ksx gksxk vkSj ;g iz;ksx m/kkj nsus okys }kjk m/kkjdrkZ dks fyf[kr :i esa nh xbZ Lkgefr Lks gksxk A
(SCALE - 1:50)
SLOPE
WATER PIPE (TYP.)
SLOPE
SLOPE
SLOPE
SLOPE
750 WIDE RCC GUTTER (TYP.)
4500
3500
4500
7000
19500 DATE
TERRACE PLAN 08-NOV-2019 SUTHAR KETANBHAI (C360) 168 of 168