Box Culverts-method Statement

  • Uploaded by: memekenya
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Box Culverts-method Statement as PDF for free.

More details

  • Words: 552
  • Pages: 2
Loading documents preview...
METHOD STATEMENT FOR CONSTRUCTION OF BOX CULVERTS    SCOPE OF WORK  As cross‐main drainage structures, box culverts will be constructed at instructed locations by the  Supervisor’s Representative to replace hydraulically inadequate pipe culverts.  METHOD  A site store has been set‐up to stock materials including cement and reinforcing steel. Mobilization of  plant and equipment will commence upon receipt of a go ahead/ site instruction to commence work on  the culverts.   The main works will include activities such as setting out, excavations, blinding, reinforcement and  formwork, batching, mixing and casting, curing and backfilling.  All works will only commence upon acceptance and/or approval of previously completed work at every  stage of the construction.  Safety precautions are to be adhered by ensuring that, all plants are operated by authorized operators.  Besides, all workers in the concrete section will be provided with safety gears including dust masks,  hand gloves, gumboots, helmets, goggles and others as applicable.    DESCRIPTION OF OPERATIONS  Activity  Setting out             Excavations 

Details/ Description  A survey team consisting of one surveyor,  two assistances and four chainmen will  take levels and set out the excavation  area by use of pegs to mark points on the  ground.     Upon acceptance of the setting out by  the S.R, excavations will be done by use  of a back hoe loader to the satisfaction of  the S.R.    Excavated levels will be taken after  acceptance of excavations. 

Plant  2 No. Pick up    1 No. back hoe  loader     

labor  1 No. surveyor    2 No. assistance    4 No. chainmen    2 N o. driver    1 No. operator    1 No. foreman     

Blinding,              Reinforcement          Formwork           Batching          Mixing and  casting          Quality control         

Curing and  Backfilling. 

 

Teams headed by a concrete foreman will  start with blinding the base to the  specified thickness using materials  complying with specifications and of  approved mix design to the acceptance of  the S.R.    Reinforcement will be laid and fixed by  adhering to the bar bending schedule and  any other site instruction issued by the  S.R regarding bending of steel bars.    Upon approval of the reinforcement,  formwork using wrought and unwrought  timber will be firmly fixed to the  satisfaction of the S.R.     Batching to the instructed mix design will  be done for concrete materials that  comply with relevant  Specifications.    Upon acceptance of batching, concrete  mixing will be done by means of a  concrete mixer and concrete casted and  compacted using a poker vibrator to the  satisfaction of the S.R.     Concrete cubes at acceptable batch  intervals will be cast to monitor quality of  concrete laid.      Similar procedures will be applied to  construct the walls, end structures and  finally the deck all to the satisfaction and  approval  of the S.R.  A team led by the concrete foreman will  ensure proper curing of the structures  with adequate portable water.    After curing, a team headed by the  earthworks foreman will ensure that  backfilling with specifications compliant   materials is adequately compacted and  accepted by the S.R.  

1 No. 300 ltr.  Concrete mixer  Or  1 No. self  propelled mixing  plant    3 No. pick‐up    1 No. water  tanker    1 No. tipper truck    1No. poker  vibrator 

1 No. foreman    2 No. operator    3 No. assistance  foremen.    5 No. drivers    5‐8 No. artisans    10‐20 unskilled     

1 No. water  tanker    1 No. roller    1 No. tipper truck    2 No. pick up    1 No. back hoe  loader 

2 No. foremen    2 No. operator    4 No.  drivers    4‐6 unskilled 

Related Documents

Mirror Box
January 2021 0
Pandoras Box
February 2021 9
Box Culvert
January 2021 1
Mystery Box
January 2021 0

More Documents from "Gono Genie"