Loading documents preview...
29th Annual
HANDS-ON RELAY SCHOOL March 12 - 16, 2012
BREAKER FAILURE PROTECTION
Brent Carper, PE P r o te c t i o n & I n te g r a t i o n E n g i n e e r b r e n t . c @ r e l aya p p l i c a t i o n . c o m
OUTLINE
Protection System Failures and Breaker Failures BF Protection versus BF Relaying BF Relay Schemes and Logic Special BF Situations BF Setting Calculation Exercise Impacts from Changing Technology Testing and Maintenance of BF Schemes
P r i m a r y Re f e r e n c e : C 37. 1 1 9 - 2 0 0 5 I E E E G u i d e f o r B r e a ke r Fa i l u r e P r o te c t i o n o f Pow e r C i r c u i t B r e a ke r s
PROTECTION FAILURE Protection System Failures
Relay failure Settings failure Control system failure CT/PT failure Batter y system failure Catastrophic control house failure (fire)
Breaker Failures
Fails to trip Trips too slow Fails to interrupt fault current Fails to interrupt load current Flashover when open Fails to close Auxiliar y contact problems Catastrophic failure
Breaker Failure Protection versus Breaker Failure Relaying
BREAKER FAILURE PROTECTION BY COORDINATION
T
A
B
BREAKER FAILURE PROTECTION BY COORDINATION
T
A
B
BREAKER FAILURE PROTECTION BY COORDINATION
T
A
B
BREAKER FAILURE PROTECTION BY COORDINATION
T
A
B
BREAKER FAILURE PROTECTION BY COORDINATION
T
A
B
Advantages:
Disadvantages:
S i m p l e – N o ex t r a e q u i p m e n t Simple – No risk of misoperation U l t i m a te p r o te c t i o n . C ov e r s A L L f a i l u r e s , n o t j u s t B r e a ke r Fa i l u r e ( f a i l u r e o f b r e a ke r, r e l ay, s e t t i n g s , c o n t r o l s a n d w i r i n g , b a t te r y, e t c . )
S l ow M ay n o t b e p o s s i b l e f o r t h e b a c ku p r e l ay i n g a t [ A ] to s e e a l l f a u l t s
Conclusions:
C o m m o n p r a c t i c e f o r D i s t r i b u t i o n , b u t t y p i c a l l y n o t s u f f i c i e n t f o r Tr a n s m i s s i o n . T h e r e i s “ B r e a ke r Fa i l P r o te c t i o n ” eve n t h o u g h t h e r e i s n o t “ B r e a ke r Fa i l Re l ay i n g ” . B r e a ke r f a i l u r e p r o te c t i o n i s b u i l t - i n to g o o d p r o te c t i o n p r a c t i c e s .
BREAKER FAILURE PROTECTION BY COORDINATION A
T
1 2 T
M
3 4 5
B
BREAKER FAILURE PROTECTION BY COORDINATION A
T
B
1 2 T
M
3 4 5
[ A ] c a n p r o b a b l y b a c k u p [ B ] a n d s e e a m i n i m u m f a u l t a l l t h e way a t t h e e n d o f t h e l i n e . [ M ] m ay n o t b e a b l e to f u l l y b a c k u p t h e f e e d e r b r e a ke r s f o r a n e n d o f l i n e f a u l t . Example:
Assume 200A load per feeder section, and 800A minimum fault current at the end of line. [A] has 400A max load and needs to pickup on an 800A fault. [M] has 1000A max load, so it cannot be set to pickup on an 800A fault.
IEEE EXAMPLE B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE PROPER CLEARING B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE PROPER CLEARING B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE BREAKER FAILURE B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE BREAKER FAILURE B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE REMOTE BACKUP B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE REMOTE BACKUP B
C
A
A
1
2
3
4
5
6
Load
C
Load 7
8 Load
Advantages:
Disadvantages:
C o m p l e te l y i n d e p e n d e n t o f Substation B.
S l ow – s y s te m i n s t a b i l i t y S l ow – vo l t a g e d i p s Wide area outage M ay n o t b e p o s s i b l e f o r t h e b a c ku p r e l ay to s e e a l l f a u l t s
IEEE EXAMPLE B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE BREAKER FAILURE RELAYING B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE BREAKER FAILURE RELAYING B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
C
IEEE EXAMPLE BREAKER FAILURE RELAYING B A
A
1
2
C 3
4
5
6
Load
Load 7
8 Load
BFR on breaker [3] detects breaker failure condition B F R t r i p s a L o c ko u t r e l ay L o c ko u t r e l ay ( 8 6 ) t r i p s b r e a ke r s [ 2 ] , [ 5 ] , a n d [ 7 ] L o c ko u t r e l ay b l o c k s c l o s e o f [ 2 ] , [ 5 ] , a n d [ 7 ] What else? Tr a n s f e r Tr i p to b r e a ke r [ 4 ] Cancel reclose of [4]
C
BREAKER FAILURE RELAYING
01 21 Z1
87B 21 Z2
21 Z2 67 G
86B
67 G 50 62
BFI
86BF
trip all adjacent bkrs
trip all bkrs on bus
DTT/RC to remote bkrs
BREAKER FAILURE RELAYING
21 B
87B
BFI
21 P
BFI
50 62
86BF
BFI
86B
BREAKER FAILURE RELAYING
1
3
2
87B
87B
BF 1
BF 2 21 B
21 P BF 3 21 B
21 P
BREAKER FAILURE LOGIC 1. 2. 3. 4. 5. 6. 7. 8. 9.
Basic Breaker Failure Scheme 50BF Torque Control Breaker Re-Trip Logic BFI Control Timer BFI Seal-In Minimal Current Scheme Timer Bypass Scheme Dual Timer Scheme Special Schemes
BASIC BREAKER FAILURE SCHEME
Four Par ts to a Breaker Failure Scheme:
Fault Detector (50) or other Failure Detectors Initiator Circuit (BFI) Logic and Timers (62) Output Circuit (BFT)
50BF TORQUE CONTROL
BREAKER RE-TRIP LOGIC
BFI CONTROL TIMER
BFI SEAL-IN
MINIMAL CURRENT SCHEME
TIMER BYPASS SCHEME
Note: This logic is for illustrative purposes only. Not intended as a complete scheme. The timer bypass scheme should be supervised by a fault detector, which may not be compatible with torque controlled 50BF.
EXAMPLE BE1-50BF LOGIC
DUAL TIMER SCHEMES Use fast BF timer for multi-phase faults (L-L, L-L-G, 3P) Use slower BF timer for single-phase faults (SLG) Multi-phase faults have larger impact on system stability, and may require fast breaker failure times. Single-phase faults are more common. Dual timer allows fast BFT for the multi-phase fault, but keeps the security of a slower BFT for the most common fault scenario.
SPECIAL SCHEMES
Voltage dif ferential Frame leakage detection Breaker dif ferential IPO breakers Redundant breakers
BF SETTINGS
Logic Fault or Load Current Detector Pickup Other Breaker Failure Detectors Set Timers
NORMAL CLEARING TIME PROTECTIVE RELAY OPERATE TIME
BREAKER OPERATE TIME
BFI INPUT P/U
50FD RESET
MARGIN
BF TIMER SETTING
50FD P/U
CONTROL TIMER SETTING
86BF BFR OUTPUT OPERATE TIME RELAY TIME
LOCAL BACKUP BREAKER OPERATE TIME TT CHANNEL TIME
REMOTE END BACKUP BREAKER OPERATE TIME
MAX CRITICAL CLEARING TIME BY COMPANY POLICY
FAULT
PROPER OPERATION FAULT CLEARED
CRITICAL CLEARING TIME CALCULATED BY STUDY
CALCULATING BF SCHEME TIMERS
NORMAL CLEARING TIME PROTECTIVE RELAY OPERATE TIME
BREAKER OPERATE TIME
BFI INPUT P/U
50FD RESET
MARGIN
BF TIMER SETTING
50FD P/U
CONTROL TIMER SETTING
86BF BFR OUTPUT OPERATE TIME RELAY TIME
LOCAL BACKUP BREAKER OPERATE TIME TT CHANNEL TIME
REMOTE END BACKUP BREAKER OPERATE TIME
MAX CRITICAL CLEARING TIME BY COMPANY POLICY
FAULT
PROPER OPERATION FAULT CLEARED
CRITICAL CLEARING TIME CALCULATED BY STUDY
CALCULATING BF SCHEME TIMERS
EXERCISE
IMPACT OF CHANGING TECHNOLOGY Digital Relay BF Protection: Faster, Better, Cheaper, More
Solved transient stability problems previously unsolvable Better protection against wide-area and cascading outages Protect against all breaker failure modes, not just one or two Can be more secure if designed well
Most utilities moving away from Stand- Alone BF Relays Some utilities (not many) are reversing the trend and going back to stand alone Breaker Failure Relays Reduce misoperations “unscheduled maintenance tests” Use longer maintenance cycles for BF protection systems
IMPACT OF CHANGING TECHNOLOGY
21 B
87B
BFI
21 P
BFI
50 62
86BF
BFI
86B
IMPACT OF CHANGING TECHNOLOGY
21 B
87B
BFI
21 P
BFI
BF
86BF
BFI
86B
IMPACT OF CHANGING TECHNOLOGY
BF
21 B
87B
BFI
BFI
21 P
BF
86BF
BFI
86B
IMPACT OF CHANGING TECHNOLOGY
21 B
87B
BF
I
21 P
BF
BF
86BF
BFI
86B
IMPACT OF CHANGING TECHNOLOGY
BF
21 B
BF
BFI
87B
BFI
BFI
21 P
BF
86BF
86B
IMPACT OF CHANGING TECHNOLOGY
1
3
2
87B
87B
BF 1
BF 2 21 B
21 P BF 3 21 B
21 P
IMPACT OF CHANGING TECHNOLOGY
1
BF 1
3
2
87B
87B
BF 1
21 B
BF 2
BF 1
21 P
BF 2
BF 2
21 B
BF 3
BF 2
21 P
BF 3
BF 3
IMPACT OF CHANGING TECHNOLOGY Digital Relay Timing and Logic Precise timing eliminates relay misoperations due to calibration drift Precise timing and logic allows reducing “design margins”
Digital Relay I/O Sensitive BFI inputs (transients, DC grounds) Solid state relay outputs (sneak circuits)
Digital Relay Protective Elements Used to be limited to a 50FD Now we can use 50L and other sensitive detectors that may pick up a lot Solution: Consider using other elements to help add Security, not just Sensitivity (negative sequence, voltage elements, synch check and frequency elements, etc.)
IMPACT OF CHANGING TECHNOLOGY Challenges from Complexity
Elaborate/exotic BF logic Wide variety of BF schemes, even in the same model of relay at the same utility May have more than one BF scheme in a single relay May have more than one BF scheme for single breaker Solution: Engineering Standardization Solution: Documentation (written setting descriptions, logic diagrams, and test plans)
Challenges with Integrated BF
May not be able to disable all BFI’s May not be able to disable all BFT’s Trend is to completely eliminate all hardwired BFT and lockout relays (IEC 61850) Solution: Design with test switch to relay input that disables the BFI and/or BFT. Especially important for BFTT or 61850.
TESTING AND MAINTENANCE OF BREAKER FAILURE PROTECTION Challenges with BF Protection D i f f i c u l t to te s t i n te n t i o n a l l y E a s y to te s t u n i n te n t i o n a l l y
TESTING AND MAINTENANCE OF BREAKER FAILURE PROTECTION There is a dif ference between testing the BF Relay and testing the BF Relaying System M a ny u t i l i t i e s p e r f o r m m a i n te n a n c e te s t i n g o f t h e B F Re l ay, b u t a r e n o t te s t i n g t h e e n t i r e B r e a ke r Fa i l u r e P r o te c t i o n S y s te m . G o o d m a i n te n a n c e p r a c t i c e s ( a n d N E R C c o m p l i a n c e r e q u i r e m e n t s ) a r e to te s t t h e P r o te c t i o n S y s te m : Maintenance program for the BF Relay Maintenance program for CT’s/PT’s Maintenance program for the Battery and DC system Maintenance of the BFR Protection System must include: Rolling lockout relays and tripping breakers Best practice: simultaneous functional test (clear the bus)