Loading documents preview...
WBS Code 1
Task Name Duration Project
1.1
37 days
Analysis
15 days
Bidding
20 days
Approvals Submissions Planning Working Drawings Final Estimates Team Selection Design Architecture
2 days 43 days 43 days
Architectural Layout Plan
14 days
Architectural Design Structure Structure Layout Plan Structure Design
17 days
Construction
336 days
Surveying & Marking
21 days
1.3.1
Diversions
14 days
1.3.2
Removal of Trees Site Mobilization
1.1.1.1 1.1.1.2 1.1.1.3 1.1.2 1.1.3 1.1.3.1 1.1.3.2 1.1.3.3 1.2 1.2.1 1.2.1.1 1.2.1.2 1.2.2 1.2.2.1 1.2.2.2 1.3
1.3.3
22 days 20 days 1 day
-
Thu 1/16/20
Wed 2/12/20
3
Thu 2/13/20 Mon 2/17/20 Thu 4/16/20
Fri 2/14/20 Wed 4/15/20 Mon 6/15/20
4 5 6
Thu 4/16/20
Fri 5/15/20
6
Mon 5/18/20
Fri 6/12/20
8
Mon 6/15/20
Mon 6/15/20
9
Tue 6/16/20 Tue 6/16/20
Wed 9/2/20 Tue 7/28/20
1
Consultant
Tue 6/16/20
Fri 7/3/20
1
Consultant
Mon 7/6/20
Tue 7/28/20
13
Wed 7/29/20
Wed 9/2/20
Contractor,Project Manager Consultant,Project Manager Consultant,Project Manager
14
12 days
Consultant
Tue 8/18/20
Wed 9/2/20
16
Thu 9/3/20
Thu 12/16/21
11
Thu 9/3/20
Thu 10/1/20
11
Fri 10/2/20
Wed 10/21/20
19
Thu 10/22/20
Wed 11/4/20
20
Thu 11/5/20
Mon 11/23/20
21
Tue 11/24/20
Thu 12/10/20
22
Fri 12/11/20
Tue 12/29/20
23
Wed 12/30/20
Tue 1/19/21
24
Wed 1/20/21
Thu 1/28/21
25
Fri 1/29/21
Thu 3/11/21
Fri 1/29/21
Thu 2/11/21
26
Fri 2/12/21
Fri 3/5/21
28
Mon 3/8/21
Thu 3/11/21
29
Fri 3/12/21
Wed 4/21/21
27
Fri 3/12/21
Mon 3/22/21
27
Tue 3/23/21
Mon 4/12/21
32
10 days 13 days
Clearance and Preparation
15 days
1.3.7
Temporary Site Construction
7 days
1.3.8
Earthwork
30 days
Excavation
10 days
1.3.9.1
Foundation
16 days
1.3.9.2
Backfilling
4 days
1.3.10.1
Wed 1/15/20
Mon 8/17/20
1.3.6
Formwork
Fri 2/14/20
Wed 7/29/20
13 days
1.3.10
Mon 6/15/20
Consultant
Site Layout Plans
Retaining Walls
Predecessors
14 days
1.3.5
1.3.9.3
Finish
Thu 12/26/19
26 days
13 days
1.3.9
Consultant,Project Manager Consultant,Project Manager Consultant Contractor
57 days 31 days
Breaking of Existing Pavements
1.3.4
Start Thu 12/26/19 Thu 12/26/19
123 days
Contracts
1.1.1
Resource Names
Labor D,Project Manager,Labor E,Labor F Labor A,Labor B,Labor C,Labor D,Project Manager,Labor E Labor B,Labor D,Surveyor,Labor A Labor B,Labor D,Surveyor,Labor A Labor A,Labor B,Labor C,Labor D,Project Manager,Labor E Project Manager,Planner Labor A,Labor B,Labor C,Labor D,Project Manager,Labor E Labor A,Labor B,Labor C,Labor D,Project Manager,Labor E Labor A,Labor B,Labor C,Labor D,Project Manager,Labor E Labor A,Labor B,Labor C,Labor D,Project Manager,Labor E Labor E,Labor F,Labor G,Labor H,Project Manager
29 days 7 days 15 days
Labor G,Labor H,Labor E,Project Manager,Labor I Labor G,Labor
Reinforcement work
1.3.10.2 1.3.10.3 1.3.11
Concreting and Curing Drainage
7 days 31 days
Excavation
4 days
Dewatering
14 days
1.3.11.2
R.C.C pipes
6 days
1.3.11.3
Backfilling
7 days
1.3.11.1
1.3.11.4 1.3.12
Columns Placement Formwork
1.3.12.1
Reinforcement work
1.3.4.12.2
Concreting and Curing
1.3.12.3
1.3.13
1.3.14
Precast Slab
Slope Levelling
14 days
21 days
14 days
7 days
1.3.14.1
Sub base
11 days
1.3.14.2
Asphalt coating (Pavement)
1.3.14.4 1.3.14.5 1.3.15
Electrical fittings & Finishes Finishes Closure
5 days
14 days
21 days 22 days
Labor C,Labor D,Labor E,Labor F,Labor G[70%],Labor H,Project Manager,Labor I Labor C,Labor D,Labor E,Labor F,Labor G[70%],Labor H,Project Manager Labor A,Labor B,Labor C,Machine Labor,Project Manager Labor D,Labor E,Labor F,Project Manager Labor A,Labor B,Labor C,Project Manager Project Manager,Contractor
53 days
Tue 4/13/21
Wed 4/21/21
33
Thu 4/22/21
Thu 6/3/21
31
Thu 4/22/21
Tue 4/27/21
31
Wed 4/28/21
Mon 5/17/21
36
Tue 5/18/21
Tue 5/25/21
37
Wed 5/26/21
Thu 6/3/21
38
Fri 6/4/21
Wed 8/11/21
35
Fri 6/4/21
Wed 6/23/21
35
Thu 6/24/21
Thu 7/22/21
41
Fri 7/23/21
Wed 8/11/21
42
Thu 8/12/21
Fri 8/20/21
40
Mon 8/23/21
Thu 12/16/21
44
Mon 8/23/21
Mon 9/6/21
44
Tue 9/7/21
Tue 9/21/21
46
Wed 9/22/21
Tue 9/28/21
47
Wed 9/29/21
Mon 10/18/21
48
Tue 10/19/21
Tue 11/16/21
49
Thu 12/16/21
50
Tue 3/1/22
18
Wed 11/17/21 Fri 12/17/21
Contractor,Project Manager
Fri 12/17/21
Wed 1/19/22
18
14 days 7 days 7 days 15 days
Contractor Contractor
Thu 1/20/22 Thu 1/20/22 Mon 1/31/22 Wed 2/9/22
Tue 2/8/22 Fri 1/28/22 Tue 2/8/22 Tue 3/1/22
53 53 55 56
15 days
Contractor
Wed 2/9/22
Tue 3/1/22
56
1.3.16
Inspection
24 days
1.4 1.4.1 1.4.3 1.4.4
Documents Reports Bills Mainenance Solution and Services
1.4.4.1
Labor D,Labor E,Labor F,Project Manager Labor C,Labor D,Labor E,Labor F,Labor G,Labor H,Project Manager Labor D,Labor E,Labor F,Project Manager Labor A,Labor B,Labor C,Labor D,Machine Labor,Project Manager
84 days
11 days
Side walks
Labor E,Labor F,Labor G,Labor H,Project Manager Labor A,Labor B,Labor C,Labor D,Project Manager Labor E,Labor F,Labor G,Labor H,Labor I,Project Manager Labor B,Labor C,Labor D,Labor E,Labor F,Labor G,Labor H,Labor I,Machine Labor,Project Manager,Labor A
49 days
Backfilling
1.3.14.3
H,Labor E,Project Manager,Labor I Labor G,Labor H,Labor E,Project Manager,Labor I