METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE DOCUMENT NO.
METHOD STATEMENT
A) Main Power System B) Lighting and Small Power System C) Earthing & lightning Protection system.
METHOD STATEMENT:
1 of 35
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
2 of 35
DOCUMENT NO.
The procedures and methodologies that shall be employed herein shall be done in accordance with the Project's Technical Specification, the Rules and Regulations of the Local Authority, and the latest standards as set forth by the Qatar Construction Specifications. Importantly, all testing and commissioning works shall be done in a safe manner so as to avoid danger to people and to the equipment. Testing and commissioning must be carried out in sequence as set out below: Stage 1:
Tests before connection of Electrical Supply - To carry out all visual inspection and electrical tests to ensure that all electrical equipment like panels , board sand devices, cables and wires, etc., are completed prior to the supply or connection of power.
Stage 2:
Pre-commissioning Test - To carry out all pre-commissioning test to demonstrate that all electrical equipment or devices are properly operating in accordance with its required function.
Stage 3:
Commissioning Test - To carry out the full commissioning test to the following electrical systems: A) Main Power System B) Lighting and Small Power System C) Earthing & lightning Protection system.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE DOCUMENT NO.
STAGE 1 TEST BEFORE CONNECTION OF ELECTRICAL SUPPLY
3 of 35
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
4 of 35
DOCUMENT NO.
1.1 Test/Checks on Main Switch Board MV PANELS LOCATION:- BASEMENT-1 MSB Manufacturer: Ampere/Voltage Rating: Bus bar Rating: Fault Rating: Form/Separation: IP Rating: Earthing: Drawing Ref. No.:
SCHNEIDER Electric- M/s. Bin Galib Engineering 2500 Ampere 2500 Ampere 44 KA for 3 Seconds form-4B Type2 IP -54
Checks
Checked
01 02 03
Check equipment nameplate data with drawings and specification. Inspect physical and mechanical condition. Verify appropriate anchorage, required clearance, and alignment.
04 05 06
Inspect all doors, panels, and sections for corrosion, dents, scratches, etc. Verify that fuse and/or circuit breaker size and types correspond to drawings. Check all outgoing MCCB ratings with drawings and specifications.
07
Test all outgoing feeder circuits to verify insulation resistance and continuity
08 09
10
All cables including gland connections were checked for tightness. Verify that all CTs, fuses, metering and indicating instruments, and selector switches correspond to drawings. Inspect insulators for evidence of physical damage or contaminations.
11 12
Verify if proper labels were provided or mounted on panels. Check if a laminated single line diagram is posted adjacent to the MSB.
13
Verify all the interfaces with BMS demo s per the approved drawings.
14 15
Check all the Battery charged connected & working properly. Insulation Resistance test shall be done twice the system supply voltage.
16
Check cable trench chequered plates are provided properly
17 18
Verify REF relay connection is completed. Check the entire Pipe sleeves/wall Penetration are sealed by fire sealant.
Note: 1) See attached Factory Test and Insulation Test Reports at APPENDIX. 2) MV panel will be energizing in the presence of manufacturer and contractor engineer. 3) REF relay settings will be checked by Kahrama Engineer. CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
5 of 35
DOCUMENT NO.
1.2 Test/Checks on all Sub main Boards (SMBs) LOCATION:- BASEMENT-1 SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:
415 Volt. 25 KA for 3s
IP Rating: Drawing Ref. No.: Checks
Checked
01
Check sub main board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check MCCB ratings with drawings and specifications
06
Test all outgoing sub feeder circuits to verify insulation resistance and continually.
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
All cables including gland connections were checked for tightness.
09
Check main and outgoing MCCB ratings against drawings.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of circuits.
12
Check SMB diagram is posted at inside of door.
13
Ensure the operation at full load and no load properly.
14
Earth continuity shall be checked for while the metal bodies.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.3 Test/Checks on all Sub main Boards (SMBs)
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
6 of 35
DOCUMENT NO.
LOCATION:- GROUND FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:
415 Volt. 25 KA for 3s
IP Rating: Drawing Ref. No.: Checks
Checked
01
Check sub main board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check MCCB ratings with drawings and specifications
06
Test all outgoing sub feeder circuits to verify insulation resistance and continually.
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
All cables including gland connections were checked for tightness.
09
Check main and outgoing MCCB ratings against drawings.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of circuits.
12
Check SMB diagram is posted at inside of door.
13
Ensure the operation at full load and no load properly.
14
Earth continuity shall be checked for while the metal bodies.
Note: See attached Insulation Test Report at APPENDIX. CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.4 Test/Checks on all Sub main Boards (SMBs) LOCATION:- FIRST FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
7 of 35
DOCUMENT NO.
SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:
415 Volt. 25 KA for 3s
IP Rating: Drawing Ref. No.: Checks
Checked
01
Check sub main board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check MCCB ratings with drawings and specifications
06
Test all outgoing sub feeder circuits to verify insulation resistance and continually.
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
All cables including gland connections were checked for tightness.
09
Check main and outgoing MCCB ratings against drawings.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of circuits.
12
Check SMB diagram is posted at inside of door.
13
Ensure the operation at full load and no load properly.
14
Earth continuity shall be checked for while the metal bodies.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.5 Test/Checks on all Sub main Boards (SMBs) LOCATION:- SECOND FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
8 of 35
DOCUMENT NO.
SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:
415 Volt. 25 KA for 3s
IP Rating: Drawing Ref. No.: Checks
Checked
01
Check sub main board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check MCCB ratings with drawings and specifications
06
Test all outgoing sub feeder circuits to verify insulation resistance and continually.
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
All cables including gland connections were checked for tightness.
09
Check main and outgoing MCCB ratings against drawings.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of circuits.
12
Check SMB diagram is posted at inside of door.
13
Ensure the operation at full load and no load properly.
14
Earth continuity shall be checked for while the metal bodies.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.6 Test/Checks on all Sub main Boards (SMBs) LOCATION:- THIRD FLOOR SMB Manufacturer: SCHNEIDER Electric-Bin Galib Engineering SMB Ref.: Voltage Rating:
415 Volt.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
Bus bar Rating: Fault Rating:
ELECTRICAL TESTING & COMMISSIONING
PAGE
9 of 35
DOCUMENT NO.
25 KA for 3s
IP Rating: Drawing Ref. No.: Checks
Checked
01
Check sub main board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check MCCB ratings with drawings and specifications
06
Test all outgoing sub feeder circuits to verify insulation resistance and continually.
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
All cables including gland connections were checked for tightness.
09
Check main and outgoing MCCB ratings against drawings.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of circuits.
12
Check SMB diagram is posted at inside of door.
13
Ensure the operation at full load and no load properly.
14
Earth continuity shall be checked for while the metal bodies.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.7 Test/Checks on all Sub main Boards (SMBs) LOCATION:- ROOF FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering SMB Ref.: Voltage Rating:
415 Volt.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
Bus bar Rating: Fault Rating:
ELECTRICAL TESTING & COMMISSIONING
PAGE
10 of 35
DOCUMENT NO.
25 KA for 3s
IP Rating: Drawing Ref. No.: Checks
Checked
01
Check sub main board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check MCCB ratings with drawings and specifications
06
Test all outgoing sub feeder circuits to verify insulation resistance and continually.
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
All cables including gland connections were checked for tightness.
09
Check main and outgoing MCCB ratings against drawings.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of circuits.
12
Check SMB diagram is posted at inside of door.
13
Ensure the operation at full load and no load properly.
14
Earth continuity shall be checked for while the metal bodies.
Note: See attached Insulation Test Report at APPENDIX. WITNESSED / APPROVED BY CONSULTANT
CARRIED OUT BY Name:
Name:
Signature:
Signature:
Date:
Date:
1.8 Test/Checks on all Control Panels; MCC Manufacturer: MCC Ref.:
Bin Galib Engineering AHU’s CONTROL PANELS
Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.:
IP65
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
11 of 35
DOCUMENT NO.
Checks
Checked
01
Check Control panel’s data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check isolator and MCBs ratings with drawings and specifications.
06
Test all outgoing sub feeder circuits to verify insulation resistance and continuity
07
Inspect dead front covers, panel doors for dents, scratches, etc.
08
Circuit homeruns were checked for its designated phase colures.
09
All cables including gland connections were checked for tightness.
10
Inspect terminations/connections to CBs and terminals for tightness.
11
Verify proper labeling and designating of branch circuits.
12
Check if a laminated control panel drawing is posted at inside of door.
13
Verify all the metal parts are connected by Earth continuity conductor.
14
Ensure the polarities and phase rotation of all the rotating machines.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.9 Test/Checks on all Distribution Boards (DBs) LOCATION:- BASEMENT-1 MCC Manufacturer: DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating:
SCHNEIDER. BIN GALIB
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
12 of 35
DOCUMENT NO.
Drawing Ref. No.: Checks
Checked
01
Check distribution board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check main isolator, and all outgoing branch MCBs with drawings and specifications.
06
Inspect terminations/connections to MCBs and terminals for tightness.
07
Test all outgoing branch circuits to verify insulation resistance and continuity.
08
Inspect dead front covers, panel doors for dents, scratches, etc.
09
Check cable gland connection if terminated properly.
10
Verify proper labeling and designating of circuits.
11
Check DB Schedule is posted at inside of door.
12
Verify all the metal parts are connected by Earth continuity conductor.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.10
Test/Checks on all Distribution Boards (DBs)
LOCATION:- GROUND FLOOR MCC Manufacturer: DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.:
SCHNEIDER. BIN GALIB
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
13 of 35
DOCUMENT NO.
Checks
Checked
01
Check distribution board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check main isolator, and all outgoing branch MCBs with drawings and specifications.
06
Inspect terminations/connections to MCBs and terminals for tightness.
07
Test all outgoing branch circuits to verify insulation resistance and continuity.
08
Inspect dead front covers, panel doors for dents, scratches, etc.
09
Check cable gland connection if terminated properly.
10
Verify proper labeling and designating of circuits.
11
Check DB Schedule is posted at inside of door.
12
Verify all the metal parts are connected by Earth continuity conductor.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.11
Test/Checks on all Distribution Boards (DBs)
LOCATION:- FIRST FLOOR MCC Manufacturer:
SCHNEIDER. BIN GALIB
DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks
Checked
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
14 of 35
DOCUMENT NO.
01
Check distribution board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check main isolator, and all outgoing branch MCBs with drawings and specifications.
06
Inspect terminations/connections to MCBs and terminals for tightness.
07
Test all outgoing branch circuits to verify insulation resistance and continuity.
08
Inspect dead front covers, panel doors for dents, scratches, etc.
09
Check cable gland connection if terminated properly.
10
Verify proper labeling and designating of circuits.
11
Check DB Schedule is posted at inside of door.
12
Verify all the metal parts are connected by Earth continuity conductor.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.12
Test/Checks on all Distribution Boards (DBs)
LOCATION:- SECOND FLOOR MCC Manufacturer:
SCHNEIDER. BIN GALIB
DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks
01
Checked
Check distribution board's data with drawings and specification.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
15 of 35
DOCUMENT NO.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check main isolator, and all outgoing branch MCBs with drawings and specifications.
06
Inspect terminations/connections to MCBs and terminals for tightness.
07
Test all outgoing branch circuits to verify insulation resistance and continuity.
08
Inspect dead front covers, panel doors for dents, scratches, etc.
09
Check cable gland connection if terminated properly.
10
Verify proper labeling and designating of circuits.
11
Check DB Schedule is posted at inside of door.
12
Verify all the metal parts are connected by Earth continuity conductor.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.13
Test/Checks on all Distribution Boards (DBs)
LOCATION:- THIRD FLOOR MCC Manufacturer:
SCHNEIDER. BIN GALIB
DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks
Checked
01
Check distribution board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
16 of 35
DOCUMENT NO.
04
Inspect bus bar, neutral & earth terminals, and internal components.
05
Check main isolator, and all outgoing branch MCBs with drawings and specifications.
06
Inspect terminations/connections to MCBs and terminals for tightness.
07
Test all outgoing branch circuits to verify insulation resistance and continuity.
08
Inspect dead front covers, panel doors for dents, scratches, etc.
09
Check cable gland connection if terminated properly.
10
Verify proper labeling and designating of circuits.
11
Check DB Schedule is posted at inside of door.
12
Verify all the metal parts are connected by Earth continuity conductor.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.14
Test/Checks on all Distribution Boards (DBs)
LOCATION:- ROOF FLOOR MCC Manufacturer:
SCHNEIDER. BIN GALIB
DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks
Checked
01
Check distribution board's data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify mounting at wall, anchorage, clearances, and alignment.
04
Inspect bus bar, neutral & earth terminals, and internal components.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
17 of 35
DOCUMENT NO.
05
Check main isolator, and all outgoing branch MCBs with drawings and specifications.
06
Inspect terminations/connections to MCBs and terminals for tightness.
07
Test all outgoing branch circuits to verify insulation resistance and continuity.
08
Inspect dead front covers, panel doors for dents, scratches, etc.
09
Check cable gland connection if terminated properly.
10
Verify proper labeling and designating of circuits.
11
Check DB Schedule is posted at inside of door.
12
Verify all the metal parts are connected by Earth continuity conductor.
Note: See attached Insulation Test Report at APPENDIX.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.15
Tests/Checks on Power Factor Correction Units; PFCUs
Manufactures:
SCHNEIDER. BIN GALIB
Drawing Ref. No.: Checks
Checked
01
Check equipment nameplate data with drawings and specification.
02
Inspect physical and mechanical condition.
03
Verify appropriate anchorage, required clearance, and alignment.
04
Inspect all doors, panels, and sections for corrosion, dents, scratches, etc.
05
Verify that fuse and/or circuit breaker size and types correspond to drawings.
06
Check all outgoing MCCB ratings with drawings and specifications.
07
Test all outgoing feeder circuits to verify insulation resistance and continuity
08
All cables including gland connections were checked for tightness.
09
Verify that all CTs, fuses, metering and indicating instruments, and selector switches
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
18 of 35
DOCUMENT NO.
correspond to drawings. 10
Inspect insulators for evidence of physical damage or contaminations.
11
Verify if proper labels were provided or mounted on panels.
12
Check if a laminated single line diagram is posted adjacent to the MSB.
13
Check all the metal bodies are connected by ECC.
14
Verify all the interface connections with BMS done by properly
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
1.16
Tests/Checks on all Electrical & Auxiliary Wiring Devices;
Device Manufacturer: Designations:
Switches, Socket Outlets, Flex Outlets, DP Switches, Switched & Un-switched Spur Units
Drawing Ref. No.: Checks
Checked
01
Compare nameplate with drawings and specification.
02
Inspect for any missing components or loose parts, defects, etc.
03
Inspect for proper terminations, and wire management.
04
Check for plate cover mounting as to alignment and tightness.
05
Inspect plate covers for dirt, scratches, dents, etc.
06
Check all the earth wires are connected properly.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
07 08
ELECTRICAL TESTING & COMMISSIONING
PAGE DOCUMENT NO.
Check the effectiveness of completed earthing installation earth fault loop impedance test Test continuity of ring main circuits of all final power.
19 of 35
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
STAGE 2
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
20 of 35
DOCUMENT NO.
PRE-COMMISSIONING TEST
Operational/Functional Test of the following:
Checks
Checked
01
Test on Main Switch Board
02
Test on SMDB's
03
Test on all Control Panels
04
Test on Earthing and lightning protection system.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
21 of 35
DOCUMENT NO.
Notes/Comments:
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
2.1 Tests on Main Switch Board; Ensure all incoming / outgoing Breaker ACBs will be kept off before.
Checks
01
Checked
02
Check the power supply is available on the incomer ACB and indication lights are working normal. Check the system voltage on each phases & neutral.
03
Ensure all the incoming breakers of all SMDB's are kept open position.
04
Kept off all O/G Breakers while Charge the power supply of MV panel incomer ACB
05
Check the voltages and phases on the front panel.
06
Close the MCCB's of outgoing feeders step by step and check the voltages & phase indication are properly working on the SMDB's. RFE relay functions to be checked by Kahramaa Engineer while energizing the MV panel
07
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
08
ELECTRICAL TESTING & COMMISSIONING
PAGE
22 of 35
DOCUMENT NO.
Check the battery Charger voltage showing properly.
Note: MV panel supply will be energized with the presence of manufacturer,Kahramaa and contractor.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
2.2 Test on SMDB's;
Checks
01
Checked
02
Check the system voltage and phase indication are showing properly on the SMDB's front panel. Ensure all the outgoing breakers are kept off before switch on the main incomer.
03
Switch on the main incomer.
04
Switch on the outgoing breakers one by one after switch the main breaker.
05
Ensure the DB incomer isolators will be kept off while switch on the outgoing breakers.
06
Ensure all the outgoing Feeders are found normal.
07
Check the panels connected with full load.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
23 of 35
DOCUMENT NO.
Note:
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
2.3 Test on all Control Panels;
Checks
Checked
01
Check the system voltage and phase indication are working normal.
02
Kept off all the outgoing breakers before switch on the main isolator.
03
Check the power supply available at isolator end after switch on the sub feeders.
04
Then switch on the isolator and check the rotation is working normal.
05
Check all the BMS & fire alarm interface controls are working properly.
06
Verify all the metal bodies are connected by ECC.
07
Verify the polarity and phase rotation of all rotating equipments.
Note:
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
24 of 35
DOCUMENT NO.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
2.4 Test on Earthing and lightning protection system
Checks
Checked
01
Check the Earth resistance is showing according to the Kahramaa regulations.
02
Ensure the electrical Earth resistance reading found normal.
03
Check the Qtel Earth resistance not grated than 1 Ohm.
04
Check the cut ape/installations are done properly.
05
Verify all the mechanical equipments are connected through network.
06
Check earth fault loop impedance test of all the effectiveness earthing system installation
Note:
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
25 of 35
DOCUMENT NO.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
STAGE 3
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
26 of 35
DOCUMENT NO.
COMMISSIONING TEST
Commissioning Test of the following:
Checks
Checked
Test on Main Switch Board Test on all Sub main Boards (SMBs) Test on all Control Panels. Test on all Distribution Boards (DBs) Tests on Power Factor Correction Units Tests on all Electrical & Auxiliary Wiring Devices
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
27 of 35
DOCUMENT NO.
Notes: 1) Found the MV panels, PFCU, SMDB's, DB's & control panels working in normal conditions. 2) Ensure all the electrical wiring devices are working properly.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
APPENDIX
In APPENDIX, attach all Test Results as required, Calibration Certificate of the Test Instrument used, and all other attachments as necessary to complete this Document.
1- MV panel factory test reports. Sub main board factory test reports.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
28 of 35
DOCUMENT NO.
Power factor correction unit’s factory test reports. 2- Calibration certificates of insulation Tester and multi meter. And earth resistance tester. 3- Insulation and continuity report of MV panels, SMDB's out going Feeder cables. 4- Insulation and continuity test report of distribution board final circuits for lighting and power system. 5- Chick lists.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE DOCUMENT NO.
PROCEDURES
1- ELECTRICAL LIGHTING AND POWER SYSTEM 2- EARTHING AND LIGHTNING PROTECTION SYSTEM 3- TOOLS & SAFETY PROCEDURES
29 of 35
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
30 of 35
DOCUMENT NO.
PROCEDURES 1.0 ELECTRICAL LIGHTING AND POWER SYSTEM
Procedures:
1) All electrical Installations to be completed and approved by the consultant prior to start the Testing and commissioning. 2)
MV panels, SMDB's& PFCU's are tested at factory witnessed by the Consultant.
3)
Insulation and Continuity test sheets provided along with inspection of each SMDB's and DB's incoming and outgoing cables and final circuits.
4) Continuity/ insulation test will be take each phase to phase, phase to neutral and neutral to earth conductors. 5) Test will be conducted within all the breakers in open position to confirm no short circuits in the feeders. 6) Earth Leakage circuits will be tested for tripping the breakers properly.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
31 of 35
DOCUMENT NO.
7) Ensure main isolator of MVP, SMDB's& DB's will be kept off while energizing the power supply. 8)
Check the system Voltage reading by the selector switch on the front panel. (Phase to phase and phase to neutral) and 3 phase supply available indication are showing properly.
9) Outgoing feeders of MVP, SMDB's& final circuits of DB's close one by one. 10) Ensure all the feeders, sub feeders and final circuits are working in normal condition. 11) Verify the Polarity and phase rotation of all Fuses, control switches Isolators and Motor/Pumps etc…. 12) A test shall be made to verify the Continuity of all conductors (including ECC) of every ring circuits and all reading shall be tabulated Notes: 1- Earth continuity shall be checked for all the metal connecting points. 2- Checked all the wiring devices are connected and working properly. 3- Insulation resistance test shall be conducted twice the system supply voltage.
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
32 of 35
DOCUMENT NO.
PROCEDURES 2.0 EARTHING AND LIGHTING PROTECTION SYSTEM
Procedures:
1) ALL Earthing and lighting protection system installation to be completed and approved prior to start Testing and Commissioning. 2) All Earth Pits shall be tested individually by the earth resistance tester and record the values on the attached table while installation. 3) Check the electrical earth resistance up to the MVP, Generator and reading to be record. 4) QTEL and low current earth pit shall be tested separately. 5)
Earthing for lightning protection system shall be tested from the down conductors to earth pit.
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
33 of 35
DOCUMENT NO.
6) Over all earth resistance readings to be taken for the lightning protection system earthing and shall not be greater than 10 Ohms. 7)
Verify all mechanical equipments are connected to the network.
8) Earth fault loop impedance test conducted for the complete earthing system installation. Notes:
CARRIED OUT BY
WITNESSED / APPROVED BY CONSULTANT
Name:
Name:
Signature:
Signature:
Date:
Date:
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
34 of 35
DOCUMENT NO.
3.0 TOOLS & SAFETY PROCEDURES
3.1 Testing and commissioning tools:
1) Multi meter for continuity testing and voltage check. 2) Clamp meter 3) Electrical tool kit 4) Insulation resistance tester (Megger) 5) Earth Resistance Tester 3.2 SAFTY PROCEDURES
Project safety plan shall be adhered during the complete Testing &Commissioning of Room Management System. Necessary safety precautions shall be taken care of:
METHOD STATEMENT Issue Date
14/10/2013
Rev # 00
00
ELECTRICAL TESTING & COMMISSIONING
PAGE
35 of 35
DOCUMENT NO.
•
All employees shall wear PPE which shall be fit for purpose.
•
Safe access to the place of work shall be provided for all employees.
•
Only qualified and competent technicians shall perform the work in accordance with relevant codes and practice.
•
Good House Keeping shall be performed prior to leaving the work area.