METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE DOCUMENT NO.

METHOD STATEMENT

A) Main Power System B) Lighting and Small Power System C) Earthing & lightning Protection system.

METHOD STATEMENT:

1 of 35

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

2 of 35

DOCUMENT NO.

The procedures and methodologies that shall be employed herein shall be done in accordance with the Project's Technical Specification, the Rules and Regulations of the Local Authority, and the latest standards as set forth by the Qatar Construction Specifications. Importantly, all testing and commissioning works shall be done in a safe manner so as to avoid danger to people and to the equipment. Testing and commissioning must be carried out in sequence as set out below: Stage 1:

Tests before connection of Electrical Supply - To carry out all visual inspection and electrical tests to ensure that all electrical equipment like panels , board sand devices, cables and wires, etc., are completed prior to the supply or connection of power.

Stage 2:

Pre-commissioning Test - To carry out all pre-commissioning test to demonstrate that all electrical equipment or devices are properly operating in accordance with its required function.

Stage 3:

Commissioning Test - To carry out the full commissioning test to the following electrical systems: A) Main Power System B) Lighting and Small Power System C) Earthing & lightning Protection system.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE DOCUMENT NO.

STAGE 1 TEST BEFORE CONNECTION OF ELECTRICAL SUPPLY

3 of 35

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

4 of 35

DOCUMENT NO.

1.1 Test/Checks on Main Switch Board MV PANELS LOCATION:- BASEMENT-1 MSB Manufacturer: Ampere/Voltage Rating: Bus bar Rating: Fault Rating: Form/Separation: IP Rating: Earthing: Drawing Ref. No.:

SCHNEIDER Electric- M/s. Bin Galib Engineering 2500 Ampere 2500 Ampere 44 KA for 3 Seconds form-4B Type2 IP -54

Checks

Checked

01 02 03

Check equipment nameplate data with drawings and specification. Inspect physical and mechanical condition. Verify appropriate anchorage, required clearance, and alignment.

  

04 05 06

Inspect all doors, panels, and sections for corrosion, dents, scratches, etc. Verify that fuse and/or circuit breaker size and types correspond to drawings. Check all outgoing MCCB ratings with drawings and specifications.

  

07

Test all outgoing feeder circuits to verify insulation resistance and continuity



08 09

 

10

All cables including gland connections were checked for tightness. Verify that all CTs, fuses, metering and indicating instruments, and selector switches correspond to drawings. Inspect insulators for evidence of physical damage or contaminations.

11 12

Verify if proper labels were provided or mounted on panels. Check if a laminated single line diagram is posted adjacent to the MSB.

 

13

Verify all the interfaces with BMS demo s per the approved drawings.



14 15

Check all the Battery charged connected & working properly. Insulation Resistance test shall be done twice the system supply voltage.

 

16

Check cable trench chequered plates are provided properly



17 18

Verify REF relay connection is completed. Check the entire Pipe sleeves/wall Penetration are sealed by fire sealant.

 



Note: 1) See attached Factory Test and Insulation Test Reports at APPENDIX. 2) MV panel will be energizing in the presence of manufacturer and contractor engineer. 3) REF relay settings will be checked by Kahrama Engineer. CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

5 of 35

DOCUMENT NO.

1.2 Test/Checks on all Sub main Boards (SMBs) LOCATION:- BASEMENT-1 SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:

415 Volt. 25 KA for 3s

IP Rating: Drawing Ref. No.: Checks

Checked

01

Check sub main board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check MCCB ratings with drawings and specifications



06

Test all outgoing sub feeder circuits to verify insulation resistance and continually.



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

All cables including gland connections were checked for tightness.



09

Check main and outgoing MCCB ratings against drawings.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of circuits.



12

Check SMB diagram is posted at inside of door.



13

Ensure the operation at full load and no load properly.



14

Earth continuity shall be checked for while the metal bodies.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.3 Test/Checks on all Sub main Boards (SMBs)

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

6 of 35

DOCUMENT NO.

LOCATION:- GROUND FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:

415 Volt. 25 KA for 3s

IP Rating: Drawing Ref. No.: Checks

Checked

01

Check sub main board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check MCCB ratings with drawings and specifications



06

Test all outgoing sub feeder circuits to verify insulation resistance and continually.



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

All cables including gland connections were checked for tightness.



09

Check main and outgoing MCCB ratings against drawings.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of circuits.



12

Check SMB diagram is posted at inside of door.



13

Ensure the operation at full load and no load properly.



14

Earth continuity shall be checked for while the metal bodies.



Note: See attached Insulation Test Report at APPENDIX. CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.4 Test/Checks on all Sub main Boards (SMBs) LOCATION:- FIRST FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

7 of 35

DOCUMENT NO.

SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:

415 Volt. 25 KA for 3s

IP Rating: Drawing Ref. No.: Checks

Checked

01

Check sub main board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check MCCB ratings with drawings and specifications



06

Test all outgoing sub feeder circuits to verify insulation resistance and continually.



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

All cables including gland connections were checked for tightness.



09

Check main and outgoing MCCB ratings against drawings.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of circuits.



12

Check SMB diagram is posted at inside of door.



13

Ensure the operation at full load and no load properly.



14

Earth continuity shall be checked for while the metal bodies.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.5 Test/Checks on all Sub main Boards (SMBs) LOCATION:- SECOND FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

8 of 35

DOCUMENT NO.

SMB Ref.: Voltage Rating: Bus bar Rating: Fault Rating:

415 Volt. 25 KA for 3s

IP Rating: Drawing Ref. No.: Checks

Checked

01

Check sub main board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check MCCB ratings with drawings and specifications



06

Test all outgoing sub feeder circuits to verify insulation resistance and continually.



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

All cables including gland connections were checked for tightness.



09

Check main and outgoing MCCB ratings against drawings.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of circuits.



12

Check SMB diagram is posted at inside of door.



13

Ensure the operation at full load and no load properly.



14

Earth continuity shall be checked for while the metal bodies.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.6 Test/Checks on all Sub main Boards (SMBs) LOCATION:- THIRD FLOOR SMB Manufacturer: SCHNEIDER Electric-Bin Galib Engineering SMB Ref.: Voltage Rating:

415 Volt.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

Bus bar Rating: Fault Rating:

ELECTRICAL TESTING & COMMISSIONING

PAGE

9 of 35

DOCUMENT NO.

25 KA for 3s

IP Rating: Drawing Ref. No.: Checks

Checked

01

Check sub main board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check MCCB ratings with drawings and specifications



06

Test all outgoing sub feeder circuits to verify insulation resistance and continually.



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

All cables including gland connections were checked for tightness.



09

Check main and outgoing MCCB ratings against drawings.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of circuits.



12

Check SMB diagram is posted at inside of door.



13

Ensure the operation at full load and no load properly.



14

Earth continuity shall be checked for while the metal bodies.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.7 Test/Checks on all Sub main Boards (SMBs) LOCATION:- ROOF FLOOR SMB Manufacturer: SCHNEIDER Electric- Bin Galib Engineering SMB Ref.: Voltage Rating:

415 Volt.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

Bus bar Rating: Fault Rating:

ELECTRICAL TESTING & COMMISSIONING

PAGE

10 of 35

DOCUMENT NO.

25 KA for 3s

IP Rating: Drawing Ref. No.: Checks

Checked

01

Check sub main board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check MCCB ratings with drawings and specifications



06

Test all outgoing sub feeder circuits to verify insulation resistance and continually.



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

All cables including gland connections were checked for tightness.



09

Check main and outgoing MCCB ratings against drawings.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of circuits.



12

Check SMB diagram is posted at inside of door.



13

Ensure the operation at full load and no load properly.



14

Earth continuity shall be checked for while the metal bodies.



Note: See attached Insulation Test Report at APPENDIX. WITNESSED / APPROVED BY CONSULTANT

CARRIED OUT BY Name:

Name:

Signature:

Signature:

Date:

Date:

1.8 Test/Checks on all Control Panels; MCC Manufacturer: MCC Ref.:

Bin Galib Engineering AHU’s CONTROL PANELS

Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.:

IP65

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

11 of 35

DOCUMENT NO.

Checks

Checked

01

Check Control panel’s data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check isolator and MCBs ratings with drawings and specifications.



06

Test all outgoing sub feeder circuits to verify insulation resistance and continuity



07

Inspect dead front covers, panel doors for dents, scratches, etc.



08

Circuit homeruns were checked for its designated phase colures.



09

All cables including gland connections were checked for tightness.



10

Inspect terminations/connections to CBs and terminals for tightness.



11

Verify proper labeling and designating of branch circuits.



12

Check if a laminated control panel drawing is posted at inside of door.



13

Verify all the metal parts are connected by Earth continuity conductor.



14

Ensure the polarities and phase rotation of all the rotating machines.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.9 Test/Checks on all Distribution Boards (DBs) LOCATION:- BASEMENT-1 MCC Manufacturer: DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating:

SCHNEIDER. BIN GALIB

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

12 of 35

DOCUMENT NO.

Drawing Ref. No.: Checks

Checked

01

Check distribution board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check main isolator, and all outgoing branch MCBs with drawings and specifications.



06

Inspect terminations/connections to MCBs and terminals for tightness.



07

Test all outgoing branch circuits to verify insulation resistance and continuity.



08

Inspect dead front covers, panel doors for dents, scratches, etc.



09

Check cable gland connection if terminated properly.



10

Verify proper labeling and designating of circuits.



11

Check DB Schedule is posted at inside of door.



12

Verify all the metal parts are connected by Earth continuity conductor.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.10

Test/Checks on all Distribution Boards (DBs)

LOCATION:- GROUND FLOOR MCC Manufacturer: DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.:

SCHNEIDER. BIN GALIB

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

13 of 35

DOCUMENT NO.

Checks

Checked

01

Check distribution board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check main isolator, and all outgoing branch MCBs with drawings and specifications.



06

Inspect terminations/connections to MCBs and terminals for tightness.



07

Test all outgoing branch circuits to verify insulation resistance and continuity.



08

Inspect dead front covers, panel doors for dents, scratches, etc.



09

Check cable gland connection if terminated properly.



10

Verify proper labeling and designating of circuits.



11

Check DB Schedule is posted at inside of door.



12

Verify all the metal parts are connected by Earth continuity conductor.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.11

Test/Checks on all Distribution Boards (DBs)

LOCATION:- FIRST FLOOR MCC Manufacturer:

SCHNEIDER. BIN GALIB

DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks

Checked

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

14 of 35

DOCUMENT NO.

01

Check distribution board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check main isolator, and all outgoing branch MCBs with drawings and specifications.



06

Inspect terminations/connections to MCBs and terminals for tightness.



07

Test all outgoing branch circuits to verify insulation resistance and continuity.



08

Inspect dead front covers, panel doors for dents, scratches, etc.



09

Check cable gland connection if terminated properly.



10

Verify proper labeling and designating of circuits.



11

Check DB Schedule is posted at inside of door.



12

Verify all the metal parts are connected by Earth continuity conductor.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.12

Test/Checks on all Distribution Boards (DBs)

LOCATION:- SECOND FLOOR MCC Manufacturer:

SCHNEIDER. BIN GALIB

DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks

01

Checked

Check distribution board's data with drawings and specification.



METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

15 of 35

DOCUMENT NO.

02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check main isolator, and all outgoing branch MCBs with drawings and specifications.



06

Inspect terminations/connections to MCBs and terminals for tightness.



07

Test all outgoing branch circuits to verify insulation resistance and continuity.



08

Inspect dead front covers, panel doors for dents, scratches, etc.



09

Check cable gland connection if terminated properly.



10

Verify proper labeling and designating of circuits.



11

Check DB Schedule is posted at inside of door.



12

Verify all the metal parts are connected by Earth continuity conductor.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.13

Test/Checks on all Distribution Boards (DBs)

LOCATION:- THIRD FLOOR MCC Manufacturer:

SCHNEIDER. BIN GALIB

DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks

Checked

01

Check distribution board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

16 of 35

DOCUMENT NO.

04

Inspect bus bar, neutral & earth terminals, and internal components.



05

Check main isolator, and all outgoing branch MCBs with drawings and specifications.



06

Inspect terminations/connections to MCBs and terminals for tightness.



07

Test all outgoing branch circuits to verify insulation resistance and continuity.



08

Inspect dead front covers, panel doors for dents, scratches, etc.



09

Check cable gland connection if terminated properly.



10

Verify proper labeling and designating of circuits.



11

Check DB Schedule is posted at inside of door.



12

Verify all the metal parts are connected by Earth continuity conductor.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.14

Test/Checks on all Distribution Boards (DBs)

LOCATION:- ROOF FLOOR MCC Manufacturer:

SCHNEIDER. BIN GALIB

DB Ref.: Voltage Rating: Bus bar Rating: Fault Rating: IP Rating: Drawing Ref. No.: Checks

Checked

01

Check distribution board's data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify mounting at wall, anchorage, clearances, and alignment.



04

Inspect bus bar, neutral & earth terminals, and internal components.



METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

17 of 35

DOCUMENT NO.

05

Check main isolator, and all outgoing branch MCBs with drawings and specifications.



06

Inspect terminations/connections to MCBs and terminals for tightness.



07

Test all outgoing branch circuits to verify insulation resistance and continuity.



08

Inspect dead front covers, panel doors for dents, scratches, etc.



09

Check cable gland connection if terminated properly.



10

Verify proper labeling and designating of circuits.



11

Check DB Schedule is posted at inside of door.



12

Verify all the metal parts are connected by Earth continuity conductor.



Note: See attached Insulation Test Report at APPENDIX.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.15

Tests/Checks on Power Factor Correction Units; PFCUs

Manufactures:

SCHNEIDER. BIN GALIB

Drawing Ref. No.: Checks

Checked

01

Check equipment nameplate data with drawings and specification.



02

Inspect physical and mechanical condition.



03

Verify appropriate anchorage, required clearance, and alignment.



04

Inspect all doors, panels, and sections for corrosion, dents, scratches, etc.



05

Verify that fuse and/or circuit breaker size and types correspond to drawings.



06

Check all outgoing MCCB ratings with drawings and specifications.



07

Test all outgoing feeder circuits to verify insulation resistance and continuity



08

All cables including gland connections were checked for tightness.



09

Verify that all CTs, fuses, metering and indicating instruments, and selector switches



METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

18 of 35

DOCUMENT NO.

correspond to drawings. 10

Inspect insulators for evidence of physical damage or contaminations.



11

Verify if proper labels were provided or mounted on panels.



12

Check if a laminated single line diagram is posted adjacent to the MSB.



13

Check all the metal bodies are connected by ECC.



14

Verify all the interface connections with BMS done by properly



CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

1.16

Tests/Checks on all Electrical & Auxiliary Wiring Devices;

Device Manufacturer: Designations:

Switches, Socket Outlets, Flex Outlets, DP Switches, Switched & Un-switched Spur Units

Drawing Ref. No.: Checks

Checked

01

Compare nameplate with drawings and specification.



02

Inspect for any missing components or loose parts, defects, etc.



03

Inspect for proper terminations, and wire management.



04

Check for plate cover mounting as to alignment and tightness.



05

Inspect plate covers for dirt, scratches, dents, etc.



06

Check all the earth wires are connected properly.



METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

07 08

ELECTRICAL TESTING & COMMISSIONING

PAGE DOCUMENT NO.

Check the effectiveness of completed earthing installation earth fault loop impedance test Test continuity of ring main circuits of all final power.

19 of 35

 

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

STAGE 2

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

20 of 35

DOCUMENT NO.

PRE-COMMISSIONING TEST

Operational/Functional Test of the following:

Checks

Checked

01

Test on Main Switch Board

02

Test on SMDB's

03

Test on all Control Panels

04

Test on Earthing and lightning protection system.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

21 of 35

DOCUMENT NO.

Notes/Comments:

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

2.1 Tests on Main Switch Board; Ensure all incoming / outgoing Breaker ACBs will be kept off before.

Checks

01

Checked



02

Check the power supply is available on the incomer ACB and indication lights are working normal. Check the system voltage on each phases & neutral.

03

Ensure all the incoming breakers of all SMDB's are kept open position.



04

Kept off all O/G Breakers while Charge the power supply of MV panel incomer ACB



05

Check the voltages and phases on the front panel.



06

Close the MCCB's of outgoing feeders step by step and check the voltages & phase indication are properly working on the SMDB's. RFE relay functions to be checked by Kahramaa Engineer while energizing the MV panel



07





METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

08

ELECTRICAL TESTING & COMMISSIONING

PAGE

22 of 35

DOCUMENT NO.

Check the battery Charger voltage showing properly.



Note: MV panel supply will be energized with the presence of manufacturer,Kahramaa and contractor.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

2.2 Test on SMDB's;

Checks

01

Checked



02

Check the system voltage and phase indication are showing properly on the SMDB's front panel. Ensure all the outgoing breakers are kept off before switch on the main incomer.

03

Switch on the main incomer.



04

Switch on the outgoing breakers one by one after switch the main breaker.



05

Ensure the DB incomer isolators will be kept off while switch on the outgoing breakers.



06

Ensure all the outgoing Feeders are found normal.



07

Check the panels connected with full load.





METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

23 of 35

DOCUMENT NO.

Note:

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

2.3 Test on all Control Panels;

Checks

Checked

01

Check the system voltage and phase indication are working normal.



02

Kept off all the outgoing breakers before switch on the main isolator.



03

Check the power supply available at isolator end after switch on the sub feeders.



04

Then switch on the isolator and check the rotation is working normal.



05

Check all the BMS & fire alarm interface controls are working properly.



06

Verify all the metal bodies are connected by ECC.



07

Verify the polarity and phase rotation of all rotating equipments.



Note:

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

24 of 35

DOCUMENT NO.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

2.4 Test on Earthing and lightning protection system

Checks

Checked

01

Check the Earth resistance is showing according to the Kahramaa regulations.



02

Ensure the electrical Earth resistance reading found normal.



03

Check the Qtel Earth resistance not grated than 1 Ohm.



04

Check the cut ape/installations are done properly.



05

Verify all the mechanical equipments are connected through network.



06

Check earth fault loop impedance test of all the effectiveness earthing system installation



Note:

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

25 of 35

DOCUMENT NO.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

STAGE 3

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

26 of 35

DOCUMENT NO.

COMMISSIONING TEST

Commissioning Test of the following:

Checks

Checked

Test on Main Switch Board Test on all Sub main Boards (SMBs) Test on all Control Panels. Test on all Distribution Boards (DBs) Tests on Power Factor Correction Units Tests on all Electrical & Auxiliary Wiring Devices

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

27 of 35

DOCUMENT NO.

Notes: 1) Found the MV panels, PFCU, SMDB's, DB's & control panels working in normal conditions. 2) Ensure all the electrical wiring devices are working properly.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

APPENDIX

In APPENDIX, attach all Test Results as required, Calibration Certificate of the Test Instrument used, and all other attachments as necessary to complete this Document.

1- MV panel factory test reports. Sub main board factory test reports.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

28 of 35

DOCUMENT NO.

Power factor correction unit’s factory test reports. 2- Calibration certificates of insulation Tester and multi meter. And earth resistance tester. 3- Insulation and continuity report of MV panels, SMDB's out going Feeder cables. 4- Insulation and continuity test report of distribution board final circuits for lighting and power system. 5- Chick lists.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE DOCUMENT NO.

PROCEDURES

1- ELECTRICAL LIGHTING AND POWER SYSTEM 2- EARTHING AND LIGHTNING PROTECTION SYSTEM 3- TOOLS & SAFETY PROCEDURES

29 of 35

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

30 of 35

DOCUMENT NO.

PROCEDURES 1.0 ELECTRICAL LIGHTING AND POWER SYSTEM

Procedures:

1) All electrical Installations to be completed and approved by the consultant prior to start the Testing and commissioning. 2)

MV panels, SMDB's& PFCU's are tested at factory witnessed by the Consultant.

3)

Insulation and Continuity test sheets provided along with inspection of each SMDB's and DB's incoming and outgoing cables and final circuits.

4) Continuity/ insulation test will be take each phase to phase, phase to neutral and neutral to earth conductors. 5) Test will be conducted within all the breakers in open position to confirm no short circuits in the feeders. 6) Earth Leakage circuits will be tested for tripping the breakers properly.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

31 of 35

DOCUMENT NO.

7) Ensure main isolator of MVP, SMDB's& DB's will be kept off while energizing the power supply. 8)

Check the system Voltage reading by the selector switch on the front panel. (Phase to phase and phase to neutral) and 3 phase supply available indication are showing properly.

9) Outgoing feeders of MVP, SMDB's& final circuits of DB's close one by one. 10) Ensure all the feeders, sub feeders and final circuits are working in normal condition. 11) Verify the Polarity and phase rotation of all Fuses, control switches Isolators and Motor/Pumps etc…. 12) A test shall be made to verify the Continuity of all conductors (including ECC) of every ring circuits and all reading shall be tabulated Notes: 1- Earth continuity shall be checked for all the metal connecting points. 2- Checked all the wiring devices are connected and working properly. 3- Insulation resistance test shall be conducted twice the system supply voltage.

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

32 of 35

DOCUMENT NO.

PROCEDURES 2.0 EARTHING AND LIGHTING PROTECTION SYSTEM

Procedures:

1) ALL Earthing and lighting protection system installation to be completed and approved prior to start Testing and Commissioning. 2) All Earth Pits shall be tested individually by the earth resistance tester and record the values on the attached table while installation. 3) Check the electrical earth resistance up to the MVP, Generator and reading to be record. 4) QTEL and low current earth pit shall be tested separately. 5)

Earthing for lightning protection system shall be tested from the down conductors to earth pit.

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

33 of 35

DOCUMENT NO.

6) Over all earth resistance readings to be taken for the lightning protection system earthing and shall not be greater than 10 Ohms. 7)

Verify all mechanical equipments are connected to the network.

8) Earth fault loop impedance test conducted for the complete earthing system installation. Notes:

CARRIED OUT BY

WITNESSED / APPROVED BY CONSULTANT

Name:

Name:

Signature:

Signature:

Date:

Date:

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

34 of 35

DOCUMENT NO.

3.0 TOOLS & SAFETY PROCEDURES

3.1 Testing and commissioning tools:

1) Multi meter for continuity testing and voltage check. 2) Clamp meter 3) Electrical tool kit 4) Insulation resistance tester (Megger) 5) Earth Resistance Tester 3.2 SAFTY PROCEDURES

Project safety plan shall be adhered during the complete Testing &Commissioning of Room Management System. Necessary safety precautions shall be taken care of:

METHOD STATEMENT Issue Date

14/10/2013

Rev # 00

00

ELECTRICAL TESTING & COMMISSIONING

PAGE

35 of 35

DOCUMENT NO.



All employees shall wear PPE which shall be fit for purpose.



Safe access to the place of work shall be provided for all employees.



Only qualified and competent technicians shall perform the work in accordance with relevant codes and practice.



Good House Keeping shall be performed prior to leaving the work area.