Method Statement – Electrical Installation Works: Ref: Ew2/ccpl/msra/002/b

  • Uploaded by: rajap2737
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Method Statement – Electrical Installation Works: Ref: Ew2/ccpl/msra/002/b as PDF for free.

More details

  • Words: 6,638
  • Pages: 26
Loading documents preview...
EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

Method Statement – Electrical Installation Works (HLD, DUN, RGN & MAY)

Ventilation Building Ref: EW2/CCPL/MSRA/002/B

APPROVALS Date: Written by:

Saravanan Project Engineer

5-Feb-16

Reviewed by:

Vimal Raj Asst. Project Manager

5-Feb-16

Approved by:

Ken Lee Project Manager

5-Feb-16

1|Page

Initials:

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

LIST OF ABBREVIATIONS TVECS FPS ES ITPM CS LHS CS CC DB FCU FSB GS HDG HV SKEC SPPA LV OCC PPE SB SWC SSO TS VB TS

Tunnel Ventilation and Environmental Control System Fire Protection System Electrical System Integrated Traffic and Plant Management System Communications System Lifts and Hoists System Cladding System Civil Contractors Distribution Board Fuse Connection Unit Fire Safety Bureau General Specifications Hot Dipped Galvanised High Voltage SK Engineering & Construction Pte Ltd SP power Assests Low Voltage Operation Control Centre Personal Protective Equipment Sub-board System Wide Contractors Switched Socket Outlet Technical Specifications Ventilation Building Technical Specifications

2|Page

Date: 5 Feb 2016

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

Table of Contents NO

DESCRIPTION

PAGE

1

INTRODUCTION

4

2

REFERENCES

4

3

SCOPE OF WORK

5

4

MATERIALS & EQUIPMENT USED

5

INSTALLATION PROCEDURES

6

SAFE WORK PROCEDURE FOR WORKING AT HEIGHT

20-24

7

KEY STAFFS

24-25

8

ITP

Attached

9

RA

Attached

10

EMERGENCY CONTACT NUMBER

3|Page

6-8 8-20

26

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

1 Introduction Concord Corporation Pte Ltd has been awarded the contract for installation of electrical system that includes low voltage electrical distribution system, standby electricity supply system, emergency lightings system, lighting and small power system, lightning protection system, security system and communication system. The electrical system will have the provision of back-up supply in the event of a power failure and incorporates energy saving features. The document describes the Method Statement for the LV Electrical Installation, lighting installation, bracket supporting systems installations, Main switchboard, UPS, DBs, SBs, Isolator, SSO, lighting and the Delivery and Installation of the LV sub-mains and final circuit cables in all the equipment and surface Buildings, as well as the shaft, escape staircase, cable gallery that including the connecting cable gallery constructed by others at Rangoon Cable Entry Shaft. The electrical installation works for the main tunnel, and adits (including adit connecting to Holland Ventilation Shaft) will be covered in another Method Statement for Tunnel electrical installation.

2 REFERENCES REFERENCE DOCUMENTS 

LV Power Distribution System Final Design



Ventilation Building, Shaft & Escape Staircase Installation Drawings (Lighting, Power and Single Line Diagrams)



Contract EW2 Design Criteria and Performance Specification for M&E Works



Contract EW2 Material & Workmanship Specification for M&E Works

 Singapore Code of Practice SS CP5.

4|Page

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

3. Scope of work CCPL details scope of works for this project will be contractually based on the items listed in the contract documents.

In general, CCPL scope of works will be the following: 

Install Cable Tray and Conduit



Equipment Installation



Install Lighting, SSO and Isolator



Cable Laying



Termination



Loop Testing



Install Supporting System



Install Cable Ladder and Conduit



Lighting system



Lightning system

5|Page

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

4. MATERIAL AND EQUIPMENT USED 4.1 

EQUIPMENT DELIVERY

Work areas at site shall be accessible and minimum clearance space is allowed for at least two trucks clearance. Work areas and road surface shall be cleared of all obstructions such as debris, stones & rocks and ready for vehicle movement.

  

4.2

The materials delivered and installed shall comply in accordance with the relevant specifications as detailed in the approved material sample submission. All the equipment / materials received on site shall be properly unloaded, mobilised and stored in the designated area/staging area as per the safety requirements. All the materials shall be taken to site only during the time of installation.

MANUAL HANDLING 1. From the unloading area outside each Ventilation Building, all equipment / materials are manually delivered to the respective team of general workers through designated delivery routes agreed with SKE & Construction. The practices for safe lifting are: a. Use mechanical lifting aids. b. Do not attempt to lift load alone if is beyond the ability to lift alone. Take extra care when lifting awkwardly shaped objects. c. Proper personal protective equipment such as gloves and safety boots must always be used to prevent injury such as cuts bruises or crushed toes. d. Clear vision over the load. e. If one does not have a clear vision over the load, don’t proceed. Get help immediately. f. When two or more people do lifting, a leader should be appointed to ensure that the lifting operation is co-coordinated.

g. The workers should follow these lifting procedures:  Keep the back straight. 6|Page

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

 Tuck the chin in.  Position the feet correctly - generally one foot behind and the other alongside the object pointing in the direction of movement after lifting.  Bend the knees.  Get firm grips using the whole hand and not the fingertips.  Now start pushing up with the legs thereby using the strongest set of muscles and using arm muscle to carry the load.  Keep the load close to the body and slowly carry down from the entrance stairs to concourse landing. The materials used for the installation works shall be in compliance to those approved in material schedule. The following are the materials used for the electrical installation:  Cable tray, ladder and accessories.  Conduit and Accessories.  Threaded rod, angle bar, unistrut, bolts, nuts and accessories.  Light Fittings and accessories.  Cables, glands, lugs, cable markers and cable ties.  Warning sign, label plates and other accessories if necessary.  Scaffold components  Scissor Lift  Ladders The following are the equipment’s / tools that will be used for the installation work.  Drilling machine c/w masonry bit (LEW inspected / endorsed).  Scaffolding / staging as per relevant safety gear.  Common hand tools.  Personal Protective Equipment (such as helmets, task light, ventilation fan, vests, goggles, Safety harness)  Portable cutting tool (LEW inspected / endorsed).  Hand drill, Torch light, First aid box, Loudhailer, etc., 7|Page

EW2 Ref: EW2/CCPL/MSRA/002/B

5.

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

INSTALLATION PROCEDURES 5.1

SITE SURVEY AND PREPARATION

Before the actual commencement of installation of the installation works, the following survey and preparation works are carried out:  Proper access road and spaces is required for our installation works.  For the installation works listed below, confirm and approved construction drawings are the prerequisite for our installation works.  For the installation of panels and DBs, certain architecture & structural completion is required. For example, structural inspection clearance, architecture defect clearance, completion of painting works & etc. this is to reduce the possibility of the damage to panels.  For the installation of luminaries at high level, completion of roof is required and the structural inspection clearance is required to ensure the structural is safe to complete with the installation.  For the installation of conduit & trunking works, the requirement is the opening reserved for the penetration. For the concealed items, brick wall is required to be completed and confirm safe to proceed with cutting and hacking the glove line.  Trenches (If have) & area required by cable routing should be clear from any debris, watering, construction waste and any obstruction. For the cable installed underground, others services which will be installed around that particular area need to be completed in order to avoid the damage to the cable. For the cable installed within the cable supporting system, protection on this cable will be required by whoever is working around the corner, for example, protect the cable will plywood or canvas will doing welding or cutting job on top of it.  A requirement for the cable termination is the installation completion of the Main Switchboards, DBs, SBs etc.  Requirements for the installation of MCT will be the completion of cable laying works.  For the sealing up of wall & floor penetration for cable support, complete installation of tray / ladder is required.

8|Page

EW2 Ref: EW2/CCPL/MSRA/002/B

5.2.

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

INSTALLATION OF PANELS, DBS AND SBS  To make sure that the entire installation is in conformance and in accordance with the design intent of the project for the Electrical and Low Voltage System in addition to the specification and as per approved shop drawings and comply.  Before beginning installation in any area, examine all parts of the adjoining works into which applicable work is to be placed. Should any condition be found which will prevent the proper execution of the work, installation shall not proceed in that area until such conditions are corrected by the contractor.  Mount single DB at 1800mm from finish floor level to top of equipment, unless shown otherwise on drawing / schedules.  Ensures that clearance in front of switchgear is not less than 600mm, or as indicated.  Deploy sufficient workers for delivery and installation of the panels / DB / SB.  Ensure the workers must be use proper tools.  Firstly mark up the location of the anchoring points and check the level with water split ruler.  Drill the anchoring location by using electrical hammer drill and install with suitable size of anchor bolts. If the panel installed at area which is selfstanding, custom make supporting frame will be required.  Install the Panels / DB on the anchoring points and fasten with suitable size of bolt & nuts.  After installation of Panels / DB at actual locations and ensure proper alignments.

5.3. INSTALLATION OF TRANSFORMERS 

References are made to the attached manufacturer’s Transport, storage and erection guide.



To install the equipment’s by using the proper tools



To drill the floor according to the mounting position of the panel layout.



The transformers mounting positioned according to the room layout.



Positioned the first transformer to it final position. Move the second transformer and align with the first transformer.



Anchor fasteners & bolt of two panels together using the bolt provided.



Ensure that the bolts do not hit the structural re bars.

9|Page

EW2 Ref: EW2/CCPL/MSRA/002/B



EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

The process will be repeated for all subsequent cubicles. 

Ensure the area is well ventilated and free from explosive or corrosive gas or vapours.



Check the transformer nameplate and verify that it is the correct KVA, frequency, line and load voltage for the application.



Mount the transformer securely.



Connect the transformer primary and secondary according to the wiring diagram on the nameplate.

 5.4.

Request for inspection and get ready for hand over.

INSTALLATION OF SWITCHES, SSO AND ISOLATORS



Check the location of the switches and isolator according to the construction drawing. Ensure on the type of the fittings is suitable to be used at that area.



Mark up the location of switches and isolator to a standard height of 1500mm from finishing floor level to top of switches, SSO & isolator.



Switches at the foyer area, reception area, control room and those ID areas are required to be concealed mount.



Check the ceiling height at that area, mark up the groove line which need to hack to conceal the conduit pipe & Knock Out box.



Wet the brick at the area, cut the wall by using electrical cutting tools. Install the concealed conduits pipe and rough touch up with cement.



Whereas for surface installation method, drill a M6 holes on the wall and fasten the fixtures with wall plug or anchor bolts.



Lastly, Fix the fixture and terminate the cable into it.



Surface mounted fixtures and fittings should be pre-installed and checked for alignment, fixing etc, after primary and secondary wall finishes and prior to final wall finish. Engraved adhesive labels shall be provided for all switch outlets and switch plates. All unused openings shall be closed.

 

5.5. 

INSTALLATION OF EXIT LIGHTS The exit light may be installed as either a ceiling or wall mounted fitting.

10 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



The light’s detachable, mounting bracket makes installation easy.



To install the exit light, please follow the steps below:



Remove mounting bracket from the body of the exit light.



If wall mounting exit light, drill two holes (between 4-6mm in diameter), in the ‘U’ shaped niches in the rear of the mounting Bracket, and cut out the cable access hole also (accessible behind supply cover).



Mark four holes in the ceiling for ceiling mounting, or two holes in the wall for wall mounting, and then install the mounting bracket using the appropriate fasteners (not included).



Install the base of the exit light fixture to the mounting bracket and check its levelness using a level bar.



Strip and connect the mains cable, using a screwdriver.



Secure the mains cable with the tape.



Please note: •

The un-switched Active wire connects to the terminal marked A.



The Neutral wire connects to the terminal marked N.



The Earth wire connects to the terminal marked.



Check that the stripped wire ends are completely inserted into the terminal block and no bare conductors are exposed. With multi-strand conductors, ensure that all of the strands are twisted together before inserting them into the terminal block. You must also protect the mains cable with a grommet, gland or bush where it passes through the cable entry hole.



Install the desired decals onto the diffuser(s) ensuring that the top and bottom of the decal(s) have been inserted into the groove found on the diffuser.



Remove the locking screw and rubber cover (found in the mounting bracket) and slide the body of the exit light onto the rails of the bracket.



Note: Before fitting the body to the mounting bracket, ensure the LED lamp is correctly installed.



Push the body into position until it fits snugly and use the locking screw to ensure the body of the exit light is secured to the mounting bracket.



Use the rubber cover to fill the screw hole.



Connect the exit light to the mains and check the operation of the fitting to ensure that the installation was successful. When powered up, allow a few minutes to give the battery a small charge, then press the manual test button located on the side of the fitting. When the test button is held down for a few seconds, the exit lamp should light up and stay ON until the test button is released.

11 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

5.6.

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

INSTALLATION OF LIGHT FITTINGS



Light fitting will be installed using platform ladders and mobile scaffold.



Ensure that the wall / ceiling are plastered and painted according to the builder’s requirement.



Prior to anchor installation; mark up the anchorage points of the equipment.



With the luminaire in its open state and the lamp and diffuser removed; install the housing of fixture.



After checking the alignment of the fixture, tighten all the nuts to secure the housing, terminate the cable and return the lamp and diffuser.



Continue with the installation for the next fixtures to ensure the distance between the light fittings is in standard distance and level.



After the completed installation of light fittings, terminate the cable to the DB and check the lux density of lighting by using lux meter.

Pole mounted lighting installation procedure:   



Lift the light pole into position over the installed anchors. Ensure that the base plate is resting on all four washers. Install washer, lock washer and hex nut. Plumb and level the pole and tighten all anchors. Install clamp on pole. Remove access panel on luminaire arm, Retain screws and washers. Using a hex key socket with extension, install luminaire to clamp. Connect wiring to connection terminals in the luminaire. Refer to wiring diagrams. Install the top cap on the pole (shipped with the pole). If the unit has a twist lock receptacle, assemble the receptacle and the top cap and connect wiring before installing the top cap. Install provided shorting cap or photo‐electric control. Replace the access panel on the luminaire arm.



Install the nut covers or the cover plate.



Check the lux density of lighting by using lux meter.

    

5.7. 

INSTALLATION OF CONDUITS To carry out installation work in accordance with approved shop drawings, CSD drawings and specifications. 12 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



Drill saddle fixing hole along the reference line and space it according to the approved shop drawings.



Ensure that the cable support is in correct location & elevation.



Secure the conduit on the conduit bender vice clamp to bend or cut to the required length.



Thread the ends of the conduit using threading tools.



Use a file to remove burrs from the cut edges.



Insert the nylon plug into the drill hole and secure the bar saddle.



Place the conduit over the bar saddle and secure it.



Install and tighten all securing screws.



Branch out the conduit from trunking / tray or terminate to the SBs or DBs according to the typical installation drawings. Run the conduit in line with the building structure diagonal runs will not be accepted. Run the conduit up to the wall and terminate at the wall light, isolator, switches or outlets.



Request for authority to inspect installed items.

5.8. INSTALLATION OF CABLE SUPPORTING SYSTEMS, CABLE TRAY & LADDER 

Ensure that the ceiling or soft-fit are plastered and painted according to builder‘s requirement.



To make sure that the entire installation is in conformance and in accordance with the design intent of the project for the Electrical and Low Voltage System in addition to the specification and as per approved shop drawings and comply with Local and International Standards.



Adhere to the drawings as closely as possible.



Before beginning installation in any area, examine all parts of the adjoining work onto which applicable work is to be placed. Should any condition be found which will prevent the proper execution of the work, installation shall not proceed in that area until such conditions are corrected by the contractor.



Cable Tray / Trunking shall be stored on site under cover in dry, well ventilated storage facilities.



Where sizes of Cable Trays / Trunking are not detailed on drawing then tray shall be adequately sized to support the cables without bunching and some reserve margin shall be allowed in size and weight be loaded.



All routes are chosen to allow ease of access to all cables when installed. All horizontal cables are to be set around all vertical rising services as necessary. Ensure sufficient clearance from soffit for every installation.



Earth continuity conductors shall be provided across gaps in all Cable Tray / Trunking runs and bolted connections. 13 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



Support shall be by means of steel brackets installed at intervals necessary to provide a rigid fixing and to ensure that deflection does not exceed 5mm mid span of support when fully loaded. Treatment of cut edges as per cut edges to be included. Supports for Tray / Trunking (spacing) shall be as per standard practice and manufacturer's recommendations.



Additional support shall be provided where the Cable Tray / Trunking changes direction or cables drop out of the cable tray. Dome headed bolts, nuts and washers of finish suitable to the tray shall be used between trays.



Suspension sets comprise threaded hanger rods together with nuts and locking washers, supports channel hold down clips all of which shall have a galvanized finish. Any cut ends supports, rods, etc, must be corrosion protected by use of galvanized or equal. No extended rods to be left.



The cable tray shall be installed with a 40mm minimum space between the structure and the tray.



Ensure that the copper links are used at all joints.



All cable shall be securely fixed to the tray, work and the complete installation must be carried out in a neat and workmanlike manner without crossovers.



Cables on face-up horizontally fixed tray must be secured by use of the tie wraps where not in view. If cables are bunched or single cables greater than 25sq mm are installed, cleats or metal straps shall be used.



Request authority to inspect the installation of cable support.

5.9.

INSTALLATION / LAYING OF CABLES



Carry out installation work in accordance with relevant approved shop drawings and specifications. Attention shall be paid to Technical specifications and site safety requirements at all times.



Ensure that area is free to any obstruction prior to execution of works



Set up pre – fabricated steel cable stand on a solid and level ground



Lift the cable drum by using hydraulic jack fitted below the cable drum stand



Provide suitable distance between ground level and cable drum, to enable cable drum rolled without obstruction



Check cable direction & pull cable from directions that required the least tension



Proceed cable pulling manually and with care until it reached the final destination/termination points.



Ensure adequate length is provided at the both ends of termination points before cutting the cable.



Ensure that cable tray / trunking / conduits are correct for installation of electrical cables. 14 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



Ensure that the cable rollers were in place and fixed properly.



Cable pulling persons shall not stand on cable trays/trunking during cable pulling



Cables shall be aligned, arranged and dressed properly and fixed with suitable approved cable ties. If cable cannot be terminate immediately after installation, ensure cable kept and secure properly and must inform OCC the new cable will not affect the vehicle services.



Until permanent cable tag is fixed, temporary marking of cable number shall be provided at both ends with permanent marker/pen similarly.



Repeat the same procedures as mention until all cable pulling/installation are completed.



Request for inspection and get ready for hand over

5.10. CABLE GLANDING AND TERMINATION 

Cables shall be terminated in accordance with industry standards.



Training of cable end as straight as possible and fix cable to holding fittings.



Cut cable leaving its part slightly extending from fitting terminal for being used as cable core to be straightened.



Stripping off the cable armouring and serving.



Strip off cable sheath, cotton tape and filler.



After straightening each core at a fixed distance and deciding the position of terminal, cut off extra core, strip off insulation slightly longer than the length of hole of terminal lugs with wire stripper.



Insert terminal lug into conductive core and contact bond it with proper crimping.



Tape treating of the part cut off in sheath and armouring wit self-bonding tape and stretching the tape around 1-2 times as long as the original one.



When all treating have been finished, fit up the wire identification marker in accordance to the label system as agreed with the main engineering-incharge.



All necessary internal and external fittings and insulating materials shall be Included in the termination process, which is designed such that the erection and dismantling of glands can be achieved without the use of special tools. 15 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



Earthing and labelling of cables shall be to the required standards as specified.



All joints used shall be appropriate to the size and type of cables with which they are used for.



All necessary measures to ensure safety in termination shall be deployed



Use correct size and type of cable glands for individual cables.



Enforce care on cable during peeling of insulation.



Use correct size and type of lug when terminating into terminal block / MCB.



Tidy cable inside the panel / equipment.

5.11. LABELLING 

Ensure use approved materials for label all the cables going in and out of SBs, EDBs and isolators by attaching cable markers with the designated abbreviation indicated in the drawings near to the termination point at both ends.



After completion of installation the cables follow drawing and ensure cable labelling of end is similar.



Internal QA/QC to ensure proper labelling for the cables.

5.12. LIGHTNING PROTECTION SYSTEM 

Carry out installation work in accordance with approved shop drawings and specifications.



Ensure that area is free to any obstruction prior to execution of works.



Ensure that the lightning protection system materials are correct approved materials.



Ensure that the lightning support is in correct location & elevation.



Saddle fixing hole along the reference line and space it according to the approved shop drawings.



Place the copper conductor over the saddle and secure it.



Install and tighten all securing screws.



All roof conductors shall be secured with saddles at intervals not exceeding 900mm.



Conductor crossing point shall be secured by using square clamp. 16 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



Ensure that the support assembly is securely fixed in place.



Insert the tapping screw into the drill hole and secure the saddle into the wall by using wall plug.



Place the copper conductor over the saddle and secure into the wall (vertical saddle interval 500mm for each saddle).

Conductor tape saddles shall be fixed to the walls by Round-head 37.5mm x No. 8 brass wood screws and raw plugs, the saddles being spaced at not less than 1.00m intervals. As an alternative the Contractor may cast pockets into the structural wall and secure studs via vast resin adhesive once the form-work is removed. Bi-metal connections shall be provided between aluminium and copper interfaces and elsewhere as necessary to avoid electrolytic action. Air terminations shall be formed and be of the type shown on the drawings. Provide a network of conductor tape around the roof area of the building. This shall be used to connect all down conductors, window cleaning track, cladding, spire, structural reinforcing and all other exposed conductive metal parts to a common potential.

17 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

Lightning Protection down Conductors

1. Provide down conductor tapes in locations as indicated on the approved shop drawings. 2. Down conductors shall be either: Installed surface on the structure concealed behind the cladding OR Reinforcing bars within the concrete structure. 3. Down conductor tapes shall terminate on to dedicated reinforcing bars which shall be utilized as the final connection to earth via the pile foundations. The Contractor shall include for supervising and testing the installation of the reinforcing bars including all joints prior to the concrete being poured. 4. Down conductors to be connected at roof level to a common loop tape. 5. Provide horizontally mounted conductor tapes at levels indicated on the drawings. These shall provide a common connection for all down conductors, structure, cladding, steelwork and exposed metalwork.

18 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

 

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

The system shall be tested for resistance to earth and electrical continuity of earthing system. Request for inspection and get ready for hand over.

5.13. WALL OPENING 

Ensure PTW has been approved and obtained prior to commencement of works inside the essential rooms



Conduct a Site Survey to determine the existing condition. Where feasible, the opening point will be made based on the existing services routing (i.e. the reference point).



Set out the location, size and quantity of the opening required accordingly.



Before commencement of work, use canvas to cover the work area and equipment nearby the proposed wall opening in order to prevent dust and debris from entering during execution of work.



Power tool such as hammer drill / chisel will be used to hack the wall opening. Before hacking or drilling, use a concealed services detector to confirm that there is no trunking/conduit obstruction and blockage within the walls/concrete. 19 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



While the wall opening has been created, the respective services or cables will be installed through the new opening.



Upon completion of all installation works, seal all affected openings with approved fire-stop compound.



Clean-up the work area and clear of all debris upon completion of working order to satisfy the handing over to the authorized person.

6.

SAFE WORK PROCEDURE FOR WORKING AT HEIGHT General 1. Work involves 2 meters or more shall have a valid PTW. A risk assessment is required for work activity involves working at height. Work Involves Using Ladder 

All platform ladders and A Frame ladders when in use especially near platform edges must be held by other person or properly secured.



When working with ‘live’ electrical installation, use good condition nonconductive ladder.



Ladder mounted against the wall shall have an inclination of 1 to 4 and land at least 1 meter above the highest level of the structure.



When working at height of 2 meters or more safety harness shall be used and hook with safe secured point.



Person shall face the ladder when ascending up or descending down.



Both of the hands must have proper grip to the ladder vertical poles when ascending and descending.



Do not step on the top three rungs of the ladder.



Person must have three point contacts when accessing and descending the ladder.



Defective ladder such as missing or damaged rungs, no rubber padding at its footing, cracked, etc shall NOT be used.



Self-made ladder shall not be allowed to be used at site. 1. Ladder shall be placed on flat and solid ground and NOT on slope terrain.

20 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

2. Ladder shall not be placed on boxes, scaffold, etc meant for extension of height. 3. Portable aluminium ladders are advised to be used for low level work with short duration. 4. Platform ladder with buddy system are allow to perform the installation works. 5. Step ladders shall not be used when leaned up against vertical walls. 6. Ensure that a “buddy” system is in place when using the platform ladder or A Frame ladder. Work Involves Using Scaffolds 

No person shall access any scaffold without valid scaffold tag certified by Scaffold Supervisor or scaffold tag which stated the scaffold is “Not safe for use”, displayed at entrance of scaffold access.



No one shall access or work on any damaged scaffold



Anyone who found any sub-standards conditions on the scaffold, the person shall immediately inform site supervisor or WHS officer / Supervisor and DO NOT use the scaffold.



No one is allowed to access or use the scaffold with tag “Not safe for use” display at the entrance.



All personnel shall use the proper access provided for ascending and descending the scaffold.



All person who work on scaffold comply with the following rules:

o

Must wear safety harness

o

Shall secure their safety feasible

o

Shall abide strictly with ‘Safe Working Load’ sign displayed on the scaffold

o

Shall NOT leave any loose materials that are subject to fall, e.g. bolts and nuts, tools, etc on the scaffold working platform

o

Shall place loose materials e.g. bolts and nuts, working tools, etc in proper container or tool box

o

Shall NOT throw material from scaffold to below

o

Shall NOT dismantle or modify any part of the scaffold

21 | P a g e

harness on rigid anchorage point whenever

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

o

Shall NOT remove any signs from the scaffold



All personals must stand and work within the scaffold platform at all times. Do not stretch out of the scaffold platform.



All scaffolds must have equal levelled.



All scaffolds should be used on the firm and level ground only.



When the mobile scaffold is used, the caster wheels must be locked and with outrigger extended.



When shifting of scaffold is required, the following rules shall comply

o

No person, material or equipment shall be left on the working platform or elsewhere in the structure when motion.

o

Ensure no overhead or ground obstruction when shifting

o

Ensure adequate manpower involves in shifting



Upon completion of using the mobile scaffold, the aforesaid scaffold shall be kept in the location which

o

Will not cause obstruction to the emergency escape routes or passenger movement.

o

Is positioned on firm and level ground with wheels of the scaffold always locked



When the scaffold is not going to be used further, dismantle the scaffold and remove from site.

Work Involves Using Aerial Work Platforms 1. All aerial work platforms must be in good working conditions and have a valid examination certification issued by Authorised Examiner prior to using on site. 2. Only operators who completed training course on safe operation are allowed to operate the aerial work platform. 3. Operators shall always operate the aerial work platform safety without risks themselves and others. 4. Operator shall not abuse, ignore or override any safety devices of the aerial work platform. 5. When operating the aerial work platform, persons who are standing on the work platform must wear safety harness and secure to an anchorage point

22 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

within the platform and in additional with safety helmet and chin strap at all times. 6. Ladders, hop ups or boxes must never be used on the platform to gain extra height or reach. 7. Operator must stand firmly on the floor of the basket, and must not sit or climb on the edge of the basket, or stand on mid-rails or top-rails or use other devices for a work position. 8. Care must be taken not to exceed the Safe Working Load (SWL) when working with tools and equipment from the aerial work platforms. 9. All hand tools must be secured used lanyard to prevent dropping while working from the platform. 10. Working area of the aerial work platform must be barricaded. 11. When travelling the aerial work platform, the following measures must be observed. a. No ramps, trenches, holes or other ground obstructions lie in the path of travel b. The equipment is clear of overhead electrical cables, building projections or other overhead hazards c. When necessary deploy a banksman assist movement of the aerial work platform 12. Prior to and during operation, the brakes must be set. 13. Ensure that the equipment is set on level and stable surface. 14. Aerial work platform must not be moved when the boom is in a working position with personnel in the basket. 15. Avoid working near or passing by the live / energised lines. 16. Upon completion of using the aerial working platform, the aforesaid aerial working platform shall be parked at the location which: a. Will not cause obstruction to the emergency escape routes or movement of the vehicles or human b. Is on firm and level ground

23 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

c. Must be inoperative to prevent from unauthorised person to operate Fall Protection 1. On all cases, all open edges of the platform shall be effectively barricaded. 2. Openings on the floor shall be effectively covered with firm flooring, otherwise with effective barricade to prevent from failing into it. 3. Where it is impractical to erect effective barricading to prevent person falling from height, person working at the area must be issued with suitable Personal Protective Equipment (PPE) to prevent them from failing from height. 4. The following are the appropriate PPE and safe work practices recommended for all persons working at height in the prevention of falling. a. Provision of proper foothold and handhold b. Use of safety harness to restrict from reaching the opening edges or out of the enclosure of the aerial working platform c. When working at height above 2 metres, safety harness must be anchored to secured points Toe-board of at least 90mm in height shall be provided along the opening edges or working platform of the scaffolds to prevent loose material from falling below.

7.

KEY STAFFS

The following are key staffs for the installation works:-



SK Engineering Site Engineers and Supervisors



Site Manager



Manage day-to-day running of the project.



Establish site work procedures & system.



Attend site/co-ordination meeting with others.



Submit reports.



Ensure project is running on schedule.



Ensure QC is carried out



Ensure safety is observed on site.

24 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016



Site Supervisors



Supervise & organise workers for the installation work on site.



Identify non-conformity on site.



Ensure installation work carried out in a proper manner.



Ensure safety is observed by the workers on site.



Safety Officer and Coordinator



Responsible for all site safety issue.



Conduct daily safety tool-box meeting.



Enforcement of the all safety rules and regulations at site.



Attend all site safety meetings and prepare safety reports.



Signaller and Rigger and Lifting Supervisors



Confined space safety assessor and rescuer.



General Workers.

25 | P a g e

EW2 Ref: EW2/CCPL/MSRA/002/B

EW2 ELECTRICAL SYSTEM MSRA - Electrical Installation Works (Buildings)

Date: 5 Feb 2016

10 . EMERGENCY CONTACT NUMBERS EMERGENCY SERVICES: Ambulance

995

Non Emergency Services 777 0000 Police

999

Police Hotline 1800 2250000 Fire Bridge

995

SK E& C Contacts Numbers: Designation

Name

Mobile Number

Project manager

Mr Yun sang Pil

91345452

M&E Engineer

Mr Choi

98258709

M&E Coordinator

Mr Rowel

91275445

M&E Coordinator

Mr Winson

90462799

Concord Contact Numbers Designation

Name

Mobile Number

Project manager

Mr Ken Lee

97267888

Assistant PM

Mr Vimal

98278650

Safety officer

Mr Homayun

91079483

26 | P a g e

Related Documents


More Documents from "Shamih Sikthy"