Loading documents preview...
Chilled Ammonia Process for Post-Combustion CO2 Capture
4 January, 2008, Nina Kr. Solie
POWER
The Alstom group: Two main activities, three sectors Equipment & services
Equipment & services
for power generation
for rail transport
• Alstom Power Systems
• Alstom Transport
• Alstom Power Service
CAP for Post Combustion CO2 Capture –07 January 2008 - P 2
Our History SvenskaFläktfabrikken Fläktfabrikken Svenska 1920 1920
NEBB1873 1873 NEBB
ASEA1883 1883 ASEA
NorskViftefabrikk Viftefabrikk1932 1932 Norsk
NationalIndustri Industri1917 1917 National ABBMiljø Miljø1988 1988 ABB ABBKraft Kraft1988 1988 ABB ABBALSTOM ALSTOMPower Power1999 1999 ABB
ALSTOM Norway AS in 2000 CAP for Post Combustion CO2 Capture –07 January 2008 - P 3
CO2 Capture Solutions
Zero emission technology pathways Power Power Plant Plant with with CO CO22 Capture Capture
Pre-combustion Pre-combustion
Oxy-combustion Oxy-combustion
Post-combustion Post-combustion
(New (New plants plants only) only)
(New (New ++ retrofit) retrofit)
(New (New ++ retrofit) retrofit)
Source: Vattenfall
CAP for Post Combustion CO2 Capture –07 January 2008 - P 4
Source: Vattenfall
Process Schematic of the Chilled Ammonia Process Gas Water Rich Solution Lean Solution CO2
Steam REF
From FGD
Stripper
G6
Clean Combustion Gas
Pressurized CO2
G7 Water Wash
G5 Cooling Cooling
DCC2
REF REF
G2
G3
G4 Steam
Booster Fan
G1
CO2 Absorber
CO2 Regenerator
DCC1 REF Bleed
Refrigeration System
Cooling and Cleaning CAP for Post Combustion CO2 Capture –07 January 2008 - P 5
CO2 Absorption
CO2 Regeneration
Advantages of Ammonia
• Energy efficient capture of CO2 − Low heat of reaction − High pressure regeneration
• High capacity for CO2 per unit of solution • No degradation during absorption-regeneration • Tolerance to oxygen in flue gas • Low cost and harmless reagent
CAP for Post Combustion CO2 Capture –07 January 2008 - P 6
Chilled Ammonia Process Summary Development Plan 2006
2007
2008
2009
2010
2011
1 SMALL BENCH SCALE (Completed) •
First technical hypotheses
2 LARGE BENCH SCALE (SRI)
Major steps
•
Optimize absorber design for pilot
•
Establish absorber removal rate
To be performed on coal, gas and refinery g
•
Demonstrate limited ammonia emissions
Pilots/Demos in Norway, Sweden and USA
3
FIELD PILOTS (15,000 tons per year) •
Validate key performance parameters
4
COMMERCIAL DEMONSTRATIONS (80-100,000 tons per year)
Commercialization
System reliability
Basic concept feasibility to be validated as quickly as possible CAP for Post Combustion CO2 Capture –07 January 2008 - P 7
Phase 1 – Small Bench Scale Testing Key Objectives • Establish process potential − Testing of absorber and regenerator
• Generate data to support initial techno-economic analysis • Identify key issues to be addressed in later development stages • Develop process simulation models to be used to begin process optimization
CAP for Post Combustion CO2 Capture –07 January 2008 - P 8
Phase 2 - Large Bench Scale Testing Key Objectives
• Demonstrate potential to achieve acceptable CO2 capture efficiency for a range of CO2 concentrations in flue gas • Demonstrate low ammonia emission • Measure mass transfer • Optimization of absorber design and operating conditions • Provide data to support the design of the 5 MW pilots
CAP for Post Combustion CO2 Capture –07 January 2008 - P 9
Phase 2 - Large Bench Scale Testing Photo of Absorbers & Water Wash
CAP for Post Combustion CO2 Capture –07 January 2008 - P 10
Phase 3 - Field Pilot Projects at We Energies and E.ON Key Objectives
• Validate operation of the entire system on actual flue gas • Measure heat of reaction to compare against theoretical values • Develop and evaluate the process control logic and operating system • Operate the system in long-term tests to identify O&M issues and establish system reliability • At We Energies, EPRI will develop a techno-economic analysis to scale up the system for commercial applications CAP for Post Combustion CO2 Capture –07 January 2008 - P 11
Phase 3 - Field Pilot at We Energies Project Summary
• Commenced field erection July, 2007 • Project participation through EPRI by over 20 US and international utilities • Pilot commissioning commenced end of 2007 • Testing to continue through 2008 • Designed to capture up around 15,000 tons/year of CO2 at full capacity • Will provide data necessary to establish ‘proof of concept’ CAP for Post Combustion CO2 Capture –07 January 2008 - P 12
We Energies Pleasant Prairie Power Plant (P4)
Phase 3 - Field Pilot at We Energies 3-D View of Pilot
CAP for Post Combustion CO2 Capture –07 January 2008 - P 13
Phase 3 - Field Pilot at We Energies View from the Pilot construction
CAP for Post Combustion CO2 Capture –07 January 2008 - P 14
Phase 3 - Field Pilot at E.ON Karlshamn Project Summary
• Designed to capture up around 15,000 tons/year of CO2 at full capacity • Pilot commissioning and testing to commence in August 2008 • Testing to continue into 2009 CAP for Post Combustion CO2 Capture –07 January 2008 - P 15
E.ON Thermal Karlshamn Power Plant, Karlshamn, Sweden
Phase 4 – AEP Mountaineer Commercial Demonstration Project Status
• Executed MOU in March 2007 • Established project budget • Commenced project engineering • RWE partner • Demonstration unit scheduled for commissioning in 2009 • Designed to capture 100,000 tons/yr of CO2 for sequestration in a well located on the plant property • ALSTOM’s scope includes design, supply, erection, commissioning, operation and maintenance CAP for Post Combustion CO2 Capture –07 January 2008 - P 16
AEP Mountaineer Plant, New Haven, W.Va.
Phase 4 – StatoilHydro Commercial Demonstration Project Status • Executed joint development contract with Statoil (now StatoilHydro) for the CAP technology in August 2007 • European Test Center Mongstad (TCM) will demonstrate CO2 capture for flue gases from a natural gas combined heat and power plant (CHP) and a catalytic cracker (FCCU) • Designed to capture 80,000 tons/yr • Demonstrating CAP and Amine technologies in parallel • Equal share partners in TCM include Shell, Dong, Vattenfall & Gassnova CAP for Post Combustion CO2 Capture –07 January 2008 - P 17
www.alstom.com
POWER