QUESTION 1 1.
Consider Column 2 of Div. C, Table 3.5.2.2., the Building Code Act and the Building Code Examination Syllabi 2012. The person referred to in Div. C, Clause 3.4.3.2.(1)(a) would need to successfully complete the: a. General Legal/Process Examination b. Legal/Process
Examination on Powers and Duties of a Registered Code
Agency c. Legal/Process
Examination on Powers and Duties of a Chief Building Official d. Designer Legal/Process Examination 1 points
QUESTION 2 1.
Under the BCA, the initial authority to enter into a conditional permit agreement with the applicant and such other persons as the CBO determines lies with the: a. Principal Authority b. Inspector
who has the same powers and duties as the CBO in relation to plumbing c. Registered Code Agency d. Chief
Building Official 1 points
QUESTION 3 1.
The construction of a self-service storage building, (a special Group F Division 2 occupancy), of one storey in building height with a building area of 300 m² is regulated by: a. Part 9 of Division B b. Section 3.10. of Division B and the applicable requirements of Part 3 c. Part 3 of Division B d. Section 3.10. of Division B and the applicable requirements of Part 9 1 points
QUESTION 4 1.
When Field E of the Application for a Permit to Construct or Demolish indicates that the purpose of the application is for a conditional permit, in deciding whether to issue or refuse to issue the conditional permit, the CBO: a. must comply with the time period set out in Article 1.3.1.3. and Table 1.3.1.3. b. is NOT compelled to comply with the time period set out in Article 1.3.1.3. and Table 1.3.1.3. 1 points
QUESTION 5 1.
The Construction Company Limited was issued another Order to Comply for the same infraction and once again a guilty conviction was determined in court. It may be fined; a. $100,000 max. b. $50,000
max.
c. $200,000
max.
d. $200,000
max. + $10,000 max. / day 1 points
QUESTION 6 1.
A “Restraining Order” made by a Justice of the Ontario Superior Court of Justice is; a. NOT subject to an appeal b. subject
to an appeal to the Minister of Municipal Affairs
c. subject
to an appeal to the Divisional Court
d. subject
to an appeal to the Building Code Commission 1 points
QUESTION 7 1.
Under the BCA, the only issue which is NOT subject to appeal to the Ontario Superior Court of Justice, is the decision of the Chief Building Official to; a. issue a Stop Work Order b. refuse
to issue a Conditional Permit
c. appoint d. refuse
an RCA
to review an order made by an Inspector 1 points
QUESTION 8 1.
Clause 3.6.2.3.(1)(a) of Division C requires a RCA to have liability insurance for claims that are first made and reported to the insurer during the period of insurance or during the extended reporting period after the RCA ceases to be insured. For a RCA the insured amount of indemnity during any one period of insurance must not be less than: a. $250,000 per claim and $500,000 in the aggregate b. $500,000
per claim and $1,000,000 in the aggregate
c. $1,000,000
per claim and $2,000,000 in the aggregate
d. $2,000,000
per claim and $4,000,000 in the aggregate 1 points
QUESTION 9 1.
Condition: A
new mercantile occupancy [Group E] is to be located adjacent to a restaurant [Group A-2]. There is a 45 minute fire separation between the occupancies. [Div. B, Table 3.1.3.1. requires a fire separation with 2 h of fire-resistance rating and C.A. of Table 10.3.2.2.B. would allow 1.5 h or 1 h in sprinklered buildings.] Question: Is there reduction in performance under Part 10 of Div. B? Yes No 1 points
QUESTION 10 1.
The authority to make an Order to Comply under Subsection 12(2) of the BCA is; a. imperative, must be done, to obtain compliance with the Code b. questionable practice for a first time offender of the Code c. permissive, may be done, to obtain compliance with the Code d. the only means available to an inspector, chief building official, registered code agency or person
authorized by a registered code agency, as the case may be, to obtain compliance for a contravention of the Code 1 points
QUESTION 11 1.
The authority of a Principal Authority to terminate the appointment of an RCA that has not performed all of the functions for which it was appointed lies with: a. the authority of the Chief Building Official b. the
terms of the agreement under Subsection 4.1.(1)
c. the
authority of the Director
d. the
terms of the appointment under Subsection 4.1.(2) 1 points
QUESTION 12 1.
Which of the following describes an unfinished Part 9 building of residential occupancy which may be occupied under Article 1.3.3.2.? a. the middle unit of a 2 storey row house building with 5 units b. a
two storey apartment building with six dwelling units per floor sharing a public corridor c. a triplex d. a
one-storey motel 1 points
QUESTION 13 1.
A person is building an addition to his/her house and is issued an Order to Comply. The person fails to comply and is subsequently convicted in court. This is this person’s first offence. This individual may be fined; a. $200,000 max. b. $50,000
max.
c. $100,000 d. $10,000
max.
max. / day the offence continues 1 points
QUESTION 14 1.
The Categories of Qualifications for Chief Building Officials whose duties include plans review or inspection activities, can be found in: a. Div. A, Rows 1 to 12 of Table 3.5.2.2. b. Div.
B, Rows 1 to 12 of Table 3.5.2.1.
c. Div.
C, Rows 1 to 12 of Table 3.5.2.1.
d. Div.
C, Rows 1 to 12 of Table 3.5.2.2. 1 points
QUESTION 15 1.
In deciding whether to issue or to refuse to issue a permit to construct or demolish under Subsection 8(1) of the BCA, the CBO must determine if the proposed building, construction or demolition, will contravene any other applicable law. For purposes of Section 8 of the BCA, the“ applicable law” is listed in: a. Division A, Sentence 1.4.1.3.(1) b. Division
B, Sentence 1.4.1.3.(1)
c. Division
C, Sentence 1.4.1.3.(1)
d. Division
A, Sentence 1.4.1.3.(2) 1 points
QUESTION 16 1.
Condition: Question:
An office occupancy is changed to a low hazard industrial occupancy Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 17 1.
To satisfy Subsection 8.(1.1) of the BCA, the owner or the authorized agent of the owner who makes an application for a permit to construct or demolish must use the form that is: a. prescribed in the BCA b. prescribed
in the Building By-law enacted under Clause 7.(1)(f) of the
BCA c. approved
by the Chief Building Official
d. approved
by the Minister of Municipal Affairs and Housing 1 points
QUESTION 18 1.
According to the BCA, the Principal Authority or the CBO, as the case may be, may appoint a RCA under agreement, to perform specified functions in respect of the construction of a building or class of buildings; a. only after a permit is issued under Section 10 of the BCA b. either c. only
before or after a permit is issued under section 10 of the BCA
after a permit is issued under Section 8 of the BCA
d. either
before or after a permit is issued under Section 8 of the BCA 1 points
QUESTION 19 1.
Condition: construction will result in an additional bathroom in a dwelling unit with an on-site sewage system where the components of the existing sewage system cannot accommodate the new total daily design sanitary sewage flow Question: Will there be a reduction in performance level? Yes No 1 points
QUESTION 20 1.
According to the BCA, a Chief Building Official that receives a written request, from Professional Engineers Ontario or the Ontario Association of Architects, for a copy of drawings, plans or specifications accompanying an application for a permit or for reports arising out of the general review of the building, the CBO: a. must comply with the request b. may
comply with the request if it is deemed reasonable
c. must d. may
comply with the request only if it is deemed reasonable
refer the request to the Minister of Municipal Affairs and Housing for a binding interpretation
1 points
QUESTION 21 1.
A corporation building a high rise office building is guilty of an offence under the Building Code Act if it; a. contravenes the Building Code Act b. has
outstanding fines that remain unpaid for more than six months
c. is
NOT registered as a builder or vendor with the ONWHPA
d. is
issued an Order to Comply 1 points
QUESTION 22 1.
Except where otherwise provided by the Act, the responsibility for the enforcement of the BCA lies with the: a. Council of the Municipality b. Chief
Building Official
c. Director d. the
of the Building and Development Branch
Minister of Municipal Affairs 1 points
QUESTION 23 1.
The decision made by the Superior Court of Justice is subject to an appeal to the; a. Building Code Commission b. Chief
Building Official
c. Principal
Authority
d. Divisional
Court 1 points
QUESTION 24 1.
A Chief Building Official is a person who is appointed by the Council of a Municipality or Upper-Tier Municipality under the authority of Subsection; a. 3(2) or 3(6) of the BCA as the case may be b. 3(2),
3(6) and 4(5) of the BCA as the case may be
c. 6.1(4)
and (5) of the BCA in the case of plumbing
d. 6.2(3)
and (4) of the BCA in the case of sewage systems 1 points
QUESTION 25 1.
Ontario’s 2012 Objective-Based Code has: a. four categories of objectives b. five categories of objectives c. six categories of objectives d. seven categories of objectives 1 points
QUESTION 26 1.
Condition: construction will cause a change of major occupancy and the existing structural system is not adequate for the new occupancy Question: Will there be a reduction in performance level? Yes No 1 points
QUESTION 27 1.
Subsection 1(1.3) and Section 6.2 of the BCA inform us that an Inspector who has the same powers and duties as the CBO in relation to sewage systems; a. does not have to authority to issue a conditional permit b. has the authority to issue a conditional permit c. has the authority to issue a conditional permit if the appointment By-law extended that authority to
him or her d. does not have the authority to issue a conditional permit unless the authority is given to him or her by
the Principal Authority 1 points
QUESTION 28 1.
When the CBO decides to refuse to issue a Building or Demolition Permit applied for under Subsection 8.(1) of the BCA, he/she will have to, a. refund the permit application fee to the applicant b. refund
the design activities fee to the applicant
c. inform
in writing the Director of the Building and Development Branch of the Ministry of Municipal Affairs and of the main reasons for the refusal d. inform the applicant in writing of all the reasons for the refusal 1 points
QUESTION 29 1.
According to Section 7.1 of the BCA, the duty of a Principal Authority to establish and enforce a Code of Conduct is; a. imperative, must be done b. imperative, must be done, if the Principal Authority does not have a policy to deal with conflicts of
interest c. permissive, may be done d. permissive, may be done, if the Principal Authority does not have a policy to deal with conflicts of
interests
1 points
QUESTION 30 1.
As a general rule, the requirements of Div. B, Section 9.5. “Design of Areas and Spaces” apply to a Part 9; a. hotel/motel occupancy b. cottage built as a dwelling unit and used at various times throughout the year as a seasonal
recreational building c. all occupancies d. dwelling unit that is intended for use on a continuing or year round basis as a principal residence 1 points
QUESTION 31 1.
By way of Subsection 8.(1.1) of the BCA, Clause 1.3.1.2.(1)(b) of Division C informs us that the application for a permit under Section 8 may be made by the authorized agent of the owner. Consequently, when considering an application submitted by the “authorized agent of the owner”, the CBO: a. may request a written authorization from the owner b. may
not request a written authorization from the owner and must accept the application at face value c. must request a written authorization from the owner d. must
not request a written authorization from the owner and must accept the application at face value 1 points
QUESTION 32 1.
Which of the following describes a Part 9 building of residential occupancy which may be occupied under Article 1.3.3.4.? a. the middle unit of a 2 storey row house building with 5 units b. a
two storey apartment building with six dwelling units per floor sharing a public corridor c. a duplex d. a
one-storey motel
1 points
QUESTION 33 1.
According to the BCA, it is the role of manufacturers, suppliers and retailers of products that are intended for use in Ontario in the construction of a building for a purpose that is regulated by the BCA and the provisions of the Code to ensure that; a. construction does not proceed unless any permit required under the BCA has been issued by the CBO b. the designer has the necessary qualifications under the BCA and the Code c. the CBO or the Inspector, as the case may be has the necessary qualifications under the BCA and the Code d. the products comply with the standards established under the BCA and the Code 1 points
QUESTION 34 1.
An Inspector is a person who is appointed by a Principal Authority under the authority of Subsection; a. 3(2) of the BCA b. 3(2)
or 3.1(2) of the BCA as the case may be
c. 3(2),
3.1(2) or 6.1(4) of the BCA as the case may be
d. 3(2),
3.1(2), 6.1(4) or 6.2(3) of the BCA as the case may be 1 points
QUESTION 35 1.
When Principal Authority-A is responsible for the enforcement of the BCA and the provisions of the Code except the provisions of Part 8 Sewage Systems which are enforced by Principal Authority-B under Section 3.1 or 6.2 of the BCA, as the case may be, the time period prescribed by Sentence 1.3.1.3.(1) for the purposes of considering an application for a permit under Subsection 8(1) of the BCA by Principal Authority-A, begins on the day following the later of: a. the day on which an application meeting the requirements of Sentence 1.3.1.3.(5) is made b. the day on which an application meeting the requirements of Sentence 1.3.1.3.(5) is made and on which the payment of fees required to be paid on application is made c. the day on which an application meeting the requirements of Sentence 1.3.1.3.(5) is made and the day on which the permit for the sewage system is issued
d. the
day on which an application meeting the requirements of Sentence 1.3.1.3.(5) is made or the day on which the permit for the proposed sewage system is issued 1 points
QUESTION 36 1.
As an exception to the general rule the time period, prescribed by Sentence 1.3.1.3.(1) for the purposes of considering an application for a permit under Subsection 8(1) of the BCA, does not include: a. Sundays b. Saturdays
and Sundays
c. Saturdays
and holidays
d. Saturdays,
holidays and all other days when the offices of the Principal Authority are not open for the transaction of business with the public 1 points
QUESTION 37 1.
Where there is more than one inspector in the area of jurisdiction, the responsibility to designate the Inspector with the powers and duties of a CBO in relation to sewage systems when an agreement under Subsection 6.2.(2) exists, lies with the: a. council of the municipality, b. the
council of the upper-tier municipality
c. the
council of the upper-tier municipality, the board of health or the conservation authority as the case may be d. the board of health or the conservation authority as the case may be 1 points
QUESTION 38 1.
According to the Building Code Act which of the following persons does NOT enjoy immunity from action for any act done in good faith in the execution or intended execution of any power or duty under the Act? a. Chief Building Official b. Inspector c. Director
of the Building and Development Branch
d. Designer,
Owner or Contractor 1 points
QUESTION 39 1.
A medium hazard industrial occupancy is changed to a low hazard industrial occupancy Condition:
Question:
Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 40 1.
Under the BCA, who may apply to the Superior Court of Justice for a “Restraining Order” directing a person to comply with the BCA, the building code or an order? a. the Chief Building Official b. the
Inspector
c. the
Director of the Building and Development Branch
d. the
Registered Code Agency 1 points
QUESTION 41 1.
When the provisions of on-site sewage systems are enforced by a Conservation Authority under agreement with a municipality as authorized in Subsection 6.2(2) of the BCA, the Chief Building Official and the Inspectors appointed by the municipality to enforce the other provisions of the building code have; a. less authority to enforce the other provisions of the Code b. more
authority to enforce the other provisions of the Code
c. joint
authority with the Sewage System Inspectors of the Conservation Authority to enforce plumbing d. no authority to deal with the provisions for on-site sewage systems 1 points
QUESTION 42 1.
Condition: Question:
A mercantile occupancy is changed to an office occupancy Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 43 1.
Condition: construction will cause an occupant load increase less than 15% but the new occupant load will be more than 15% greater than the occupant load requiring a fire alarm system Question: Will there be a reduction in performance level? Yes No
1 points
QUESTION 44 1.
Where there is more than one inspector in the area of jurisdiction, the responsibility to designate the Inspector with the powers and duties of a CBO in relation to sewage systems when an agreement under Subsection 6.2(2) exists, lies with the: a. council of the municipality, b. the
council of the upper-tier municipality
c. the
council of the upper-tier municipality, the board of health or the conservation authority as the case may be d. the board of health or the conservation authority as the case may be 1 points
QUESTION 45 1.
An accessory building was converted to a dwelling without a permit. The situation is also contrary to zoning as only one dwelling per lot is permitted. The owner was charged for building without a permit, under Part I of the Provincial Offences Act. The owner paid the fine. The CBO wants the illegal use of land terminated and the building restored for its original use or removed. His/her best option is to: a. make an Order to Demolish the illegal building b. apply
to the Ontario Court of Justice for a Restraining Order
c. apply
to the Superior Court of Justice for a Restraining Order
d. commence
a proceeding under Part III of the Provincial Offences Act for the zoning infraction and on conviction ask the court for a Restraining Order prohibiting the continuation of the offence against the Zoning Bylaw 1 points
QUESTION 46 1.
When a RCA has been duly appointed, compliance of the proposed construction or building with the requirements of the Code, to satisfy part of Clause 8.(2)(a) of the BCA is substantiated by the; a. Plans Review Certificate as defined in Subsection 1(1) of the BCA and prescribed in Div. C, Sentence 3.7.4.3.(7) b. completed Plans Review Certificate that contains the information prescribed in Div. C, Article 3.7.4.3. c. Final Certificate as defined in Subsection 1(1) of the BCA and prescribed in Div. C, Sentence 3.7.4.3.(7) d. completed Final Certificate that contains the information prescribed in Div. C, Article 3.7.4.3. 1 points
QUESTION 47 1.
According to the Code, a Plans Review Certificate must be signed, on behalf of the appointed RCA, by a person who has the qualifications set out in; a. Div. A, Clause 3.4.3.2.(1)(a) b. Div.
B, Clause 3.4.3.2.(1)(a)
c. Div.
C, Clause 3.4.3.2.(1)(a)
d. Div.
C, Clause 3.1.2.1.(1)(a) 1 points
QUESTION 48 1.
When an amendment to the Code comes into force, the rules for transition, revocation and commencement are found in: a. Section 4.1 of the BCA b. Div.
A, Section 4.1. of the Code
c. Div.
B, Section 4.1 of the BCA
d. Div.
C, Section 4.1. of the Code 1 points
QUESTION 49 1.
The notices of readiness for inspection referenced in Subsection 10.2(1) of the BCA, to request a prescribed inspection for each stage of construction, are included in Article: a. 1.3.5.1. of Division A b. 1.3.5.1.
of Division B
c. 1.3.5.1.
of Division C
d. 1.3.5.2.
of Division C 1 points
QUESTION 50 1.
Condition: Question:
A residential occupancy is changed to a mercantile occupancy Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 51 1.
Considering Div. C, Table 3.5.2.1. and for purposes of exceptions to Designer qualifications under Clause 3.2.4.1.(4)(c), Subclause 3.2.5.1.(2)(b)(ii) and Clause 3.2.5.1.(2)(j), an ancillary building is only associated with the following Type of Building: a. House
b. Small
Building
c. Large
Building
d. Complex
Building 1 points
QUESTION 52 1.
The area of windows (a health requirement) for dwelling units in a 10 storey Group C residential building is calculated from the values found in Division B, a. Sentence 3.7.2.1.(1) b. Part 9 by way of Sentence 3.7.2.1.(1) c. Table 9.7.2.3. by way of Sentence 3.7.2.1.(1) d. Table 9.7.1.2. by way of Article A-3.7.2.1. 1 points
QUESTION 53 1.
According to the BCA, it is the role of manufacturers, suppliers and retailers of products that are intended for use in Ontario in the construction of a building for a purpose that is regulated by the BCA and the provisions of the Code to ensure that; a. construction does not proceed unless any permit required under the BCA has been issued by the CBO b. the designer has the necessary qualifications under the BCA and the Code c. the CBO or the Inspector, as the case may be has the necessary qualifications under the BCA and the Code d. the products comply with the standards established under the BCA and the Code 1 points
QUESTION 54 1.
Where a dwelling unit has been occupied at its substantial completion under the provisions of Article 1.3.3.4., forthwith upon the completion of construction, the person who has permitted the building to be occupied must notify the: a. mortgagor b. there c. CBO d. Fire
is no requirement to notify anyone
or RCA having jurisdiction Department building code Inspector under Subsection 1.3.4. 1 points
QUESTION 55 1.
For purposes of Subsection 8.(2.2) of the BCA, the prescribed time period within which the CBO must determine whether to issue or refuse an application for a permit under Subsection 8.(1) of the BCA, is found in: a. Div. A, Article 1.3.1.3. and Table 1.3.1.3. b. Div.
B, Article 1.3.1.3. and Table 1.3.1.3.
c. Div.
C, Article 1.3.1.3. and Table 1.3.1.3.
d. Div.
A, Article 3.2.1.1. and Table 3.2.1.1. 1 points
QUESTION 56 1.
The authority to issue a Conditional Building Permit lies with the: a. Principal Authority b. Inspector
who has the same powers and duties as the CBO in relation to plumbing c. Registered Code Agency d. Chief
Building Official and the Inspector or Designated Inspector who has the same powers and duties as the CBO in relation to Sewage Systems 1 points
QUESTION 57 1.
A residential suite is converted into two suites of residential occupancy Condition:
Question:
Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 58 1.
Notwithstanding Subsection 31(1) of the Building Code Act,where a Chief Building Official or an Inspector acted in goodfaith in the execution of a power or duty but someone sufferedan injury, in a law-suit the following could be held liable. a. municipality b. Chief
Building Official
c. Inspector d. Registered
Code Agency 1 points
QUESTION 59 1.
According to the Code, the responsibility to maintain on the site of the construction one copy of any applicable BMEC authorization or facsimile thereof lies with the: a. applicant for the permit to construct the building b. holder
of the permit to construct the building
c. designer who reviewed and took responsibility for the design for the construction of
the building d. person
in charge of the construction of the building 1 points
QUESTION 60 1.
Subject to confirmation by the plans review activity, the method of calculating the building area of a selfservice storage building, for purposes of Article 3.10.4.2. is to be decided by; a. the qualified designer who will review and take responsibility for design activities b. the Chief Building Official or the Inspector who has the same powers and duties as the CBO, as the
case may be c. the Chief Building Official because the Inspectors who have the same powers and duties as the CBO in
relation to plumbing or on-site sewage systems do not need to deal with building area d. council who is given the responsibility for enforcement under Subsection 3.(2) of the BCA 1 points
QUESTION 61 1.
To comply with the provisions of the Code as directed by Subsection 8(11) of the BCA, a Designer: a. may use the alternative solutions in Division B b. must use the alternative c. may use the acceptable d. must
solutions in Division B solutions in Division B
use the acceptable solutions in Division B 1 points
QUESTION 62 1.
When the CBO decides not to issue a Conditional Building Permit, he/she is: a. required to provide the applicant with all of the reasons for the refusal of the Conditional Building Permit b. not required to provide the applicant with all of the reasons for the refusal of the Conditional Building Permit because there is no appeal process, under the BCA, from this decision and an application for a Conditional Permit under Subsection 8.(3) of the BCA is NOT an application for a permit under Subsection 8.(1) of the BCA 1 points
QUESTION 63 1.
Condition: A mercantile occupancy is being converted to an office but construction is proposed. Question:
Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 64 1.
True or false? A Sewage Systems Maintenance Program Inspector may be appointed even if the person does not satisfy the requirements in Article 3.1.4.1. of Division C and Clause 15.11(3) of the Act, provided that such unqualified Sewage Systems Maintenance Program Inspector does not issue orders under the Building Code Act, and is supervised by an Inspector or CBO who is qualified under the On-site Sewage Systems Category of Qualification of Table 3.5.2.1. a. True b. False 1 points
QUESTION 65 1.
After the holder of the Building Permit has notified the CBO or the RCA, having jurisdiction, of the substantial completion of structural framing, the inspection must be undertaken not later than: a. two days after the receipt of the notice b. three
days after the receipt of the notice
c. four
days after the receipt of the notice
d. five
days after the receipt of the notice 1 points
QUESTION 66 1.
The agreement between the RCA and the Principal Authority to perform specified functions in respect of the construction of a building or class of buildings; a. must be in writing b. may
be in writing
c. may
be delegated to the Chief Building Official
d. must
be delegated to the Chief Building Official 1 points
QUESTION 67 1.
A restaurant major occupancy changes to a residential occupancy
Condition: Question:
Is change of use permit required under S. 10 of the BCA?
Yes No 1 points
QUESTION 68 1.
According to the BCA, the authority to make an Emergency Order lies with; a. the Building Inspector who discovered the immediate danger b. the
RCA Person who has the qualifications set out in Div. C, Clause 3.4.3.2.(1)(a) and to whom the immediate danger was reported c. the Person authorized by the RCA who discovered the immediate danger d. the CBO who discovered or to whom the immediate danger was reported 1 points
QUESTION 69 1.
Which of the following describes a Part 9 residential building which may NOT be occupied under Article 1.3.3.4.? a. a detached dwelling with an in-law suite in the basement that shares
part of the means of egress detached dwelling that serves as a bed and breakfast
b. a c. a
duplex where each dwelling unit has a separate exit
d. all
of the above 1 points
QUESTION 70 1.
Who may permit the occupancy of an unfinished building after an “Occupancy Permit” has been issued by the CBO or his/her designate? a. the owner b. the
contractor
c. the
designer
d. a
person 1 points
QUESTION 71 1.
Where a building has been occupied prior to its completion, under the provisions of Article 1.3.3.1. or 1.3.3.2., forthwith upon the completion of the building, the person who has permitted the building to be occupied must notify the:
a. mortgagor b. CBO c. CBO d. Fire
or RCA having jurisdiction Department building code Inspector under Subsection 1.3.4. 1 points
QUESTION 72 1.
Condition: A building of combustible construction will be converted to a residential occupancy [Group C] and if this was new construction it would be required to be of noncombustible construction. Question: Is there reduction in performance under Part 10 of Div. B? Yes No 1 points
QUESTION 73 1.
An Inspector is a person who is appointed by a Principal Authority under the authority of Subsection; a. 3.(2) of the BCA b. 3.(2)
or 3.1.(2) of the BCA as the case may be
c. 3.(2),
3.1.(2) or 6.1.(4) of the BCA as the case may be
d. 3.(2),
3.1.(2), 6.1.(4) or 6.2.(3) of the BCA as the case may be 1 points
QUESTION 74 1.
According to the BCA, when an Order to Comply is served by registered mail, it must be sent to the last known address of the; a. applicant for the Permit or that person’s agent b. Permit
holder or that person’s agent
c. contravener d. owner
or that person’s agent
or that person’s agent 1 points
QUESTION 75 1.
Condition: construction will result in an occupancy which will produce a type or quantity of sanitary sewage which is not permitted under Article 8.1.3.1. of Division B Question: Will there be a reduction in performance level? Yes No