Loading documents preview...
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
100(1)
Designation
Clearing & Grubbing (with Stripping) ha 0.05 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd) b. Payloader (1.50 cu.m.) c. Bulldozer, D6H SERIES II PSDS/DD
2 1 1
(Hauling Distance - within three (3) km.) Assumed 150mm cut
Sub - Total for B C. Total (A + B) D. Output per hour = 0.05 ha E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
100(3)a
Individual Removal of Trees (small a, 150mm Ø up to ea. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (12 cu. yd) c. Chain Saw Minor Tools (5% of Labor Cost)
1 1 1
* Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Rope, 1" dia. - 5 uses
m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
100(3)b
Individual Removal of Trees (small b, above 300mm Ø ea. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (12 cu. yd) c. Chain Saw Minor Tools (5% of Labor Cost)
1 1 1
* Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Rope, 1" dia. - 5 uses
m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
100(4)a
Individual Removal of Trees (large a, above 500mm Ø ea. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (12 cu. yd) c. Chain Saw Minor Tools (5% of Labor Cost)
1 1 1
* Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 01. ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Rope, 1" dia. - 5 uses
m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
100(4)b
Individual Removal of Trees (large b, above 750 up to ea. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Dump Truck (12 cu. yd) c. Chain Saw Minor Tools (5% of Labor Cost)
1 1 1
* Boom Truck - if necessary for trimming in Urban Areas
Sub - Total for B C. Total (A + B) D. Output per hour = 01. ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Rope, 1" dia. - 5 uses
m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(1)
Removal of Structures and Obstruction ls 1.00
Designation
No. of Person
A. Labor See derivation for Item Nos. 101(1)a to 101(1)d
Sub - Total for A Name and Capacity
No of Units
B. Equipment
See derivation for Item Nos. 101(1)a to 101(1)d
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
See derivation for Item Nos. 101(1)a to 101(1)d
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(1)a
Designation
Removal of Concrete Bridge Structures cu.m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.)
1
b. Jackhammer c. Air Compressor (356 - 450 cfm) d. Dump Truck (12 cu.yd.) e. Payloader (1.50 cu.m.) f. Truck Mounted Crane (31 - 35 mt) g. Cutting Outfit
2 1 1 1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Oxy/Acytelene
set
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(1)b
Removal of Steel Bridge Structures kg. 1,000.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Truck Mounted Crane (31 - 35 mt)
1
b. Service Truck/Cargo Truck (2 - 5 mt)
1
c. Welding Machine (300A), Gas/Diesel Driven d. Cutting Outfit Minor Tools (10% of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1000.0000 kg E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Oxy/Acytelene b. Welding Rod c. Rope 1" dia.
set kg. m.
* Include shoring materials if needed based on actual field condition
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(1)c
Designation
Removal of Stone Masonry Lined Drainage Structures cu.m. 10.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.)
1
b. Backhoe (0.80 cu.m.) - for loading c. Dump Truck (12 cu. yd)
1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 10.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Unit
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(1)d
Designation
Removal of Concrete Drainage Structures cu.m. 2.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.)
1
b. Backhoe (0.80 cu.m.) - for loading
1
c. Dump Truck (12 cu. yd) d. Cutting Outfit
1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Oxy/Acetylene
set
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)a
Designation
Removal of RCPC (24" dia.) - 610mm dia. ea 6.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Boom Truck (2 - 5 mt)
1
Minor Tools (10 % of Labor Cost)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 6.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)b
Designation
Removal of RCPC (30" dia.) - 760mm dia. ea 5.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Boom Truck (2 - 5 mt)
1
Minor Tools (10 % of Labor Cost)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 5.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)c
Designation
Removal of RCPC (36" dia.) - 910mm dia ea 4.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Boom Truck (2 - 5 mt)
1
Minor Tools (10 % of Labor Cost)
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)d
Designation
Removal of RCPC (42" dia.) - 1070mm dia. ea 4.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) Minor Tools (10 % of Labor Cost)
1 1
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)e
Designation
Removal of RCPC (48" dia.) - 1220mm dia ea 3.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) Minor Tools (10 % of Labor Cost)
1 1
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)f
Designation
Removal of RCPC (60" dia.) - 1520mm dia. ea 2.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) Minor Tools (10 % of Labor Cost)
1 1
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(2)g
Designation
Removal of Pipes other than Pipe Culverts (PVC/GI/As ea. 2.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (Wheel Type 0.28 cu.m.) b. Cargo Truck (2 - 5 mt) Minor Tools (10% of Labor Cost)
1 1
Note: Exclude Excavation Works
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(3)a.1
Removal of Existing Concrete Pavement (0.23m thk.) sq.m. 40.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Pavement Breaker (0.80 cu.m.) b. Payloader (1.50 cu.m.), LX80-2C c. Dump Truck (12 cu. yd) Minor Tools (10% of Labor Cost)
1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 40.00 sq.m. E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(3)a.2
Removal of Existing PCC Pavement, 0.23m thk. (for R sq.m. 30.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Pavement Breaker (0.80 cu.m.) b. Payloader (1.50 cu.m.), LX80-2C c. Dump Truck (12 cu. yd) d. Concrete Saw (7.5 Hp), 14" Blade Ø Minor Tools (10% of Labor Cost)
1 1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 30.00000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Concrete Saw (diamond blade 14")
pc.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(3)b
Removal of Existing Asphalt Pavement (100mm thk.) sq.m. 60.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader w/ Scarifier, G710A b. Payloader (1.50 cu.m.), LX80-2C c. Dump Truck (12 cu. yd) Minor Tools (10% of Labor Cost)
1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.00000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(3)c
Designation
Removal of Sidewalk (100mm thk) sq.m. 75.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.) b. Backhoe (0.80 cu.m.) c. Dump Truck (12 cu. yd)
1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 75.00000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(4)a
Designation
Removal of Curb m. 50.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.) b. Backhoe (0.80 cu.m.) c. Dump Truck (12 cu. yd)
1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
101(4)b
Designation
Removal of Curb & Gutter m 30.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Pavement (0.80 cu.m.) b. Backhoe (0.80 cu.m.) c. Dump Truck (12 cu. yd)
1 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 30.00000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(1)
Designation
Roadway Excavation (Unsuitable) cu.m. 20.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd) b. Backhoe (0.80 cu.m.) c. Payloader (1.50 cu.m.) at disposal site Minor Tools (10% of Labor Cost)
2 1 1
* Disposal area (within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(2)a
Designation
Roadway Excavation (Surplus Common) cu.m. 60.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bulldozer, D6H SERIES II PSDS/DD b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (12 cu.yd.)
1 1 1 2
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 60.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
1,420.00 1,733.00 3,379.00
2,840.00 1,733.00 3,379.00
7,952.00 8,099.36 161,987.20 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 161,987.20 14,578.85 12,958.98 9,476.25 199,001.28
ILED UNIT PRICE ANALYSIS (DUPA)
of Trees (small a, 150mm Ø up to 300mm Ø)
No. of Hours
Hourly Rate
Amount
0.33 0.33 0.33
69.42 50.18 38.97
22.91 16.56 25.72
65.19 No. of Hours
Hourly Rate
Amount
0.25 0.17 0.17
1,537.00 1,420.00 75.36
384.25 241.40 12.81 3.26
641.72 706.91 706.91 Quantity
Unit Cost
Amount
20.00
3.50
14.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
14.00 720.91 64.88 57.67 42.17 885.64
ILED UNIT PRICE ANALYSIS (DUPA)
of Trees (small b, above 300mm Ø up to 500mm Ø)
No. of Hours
Hourly Rate
Amount
0.67 0.67 0.67
69.42 50.18 38.97
46.51 33.62 52.22
132.35 No. of Hours
Hourly Rate
Amount
0.50 0.33 0.33
1,537.00 1,420.00 75.36
768.50 468.60 24.87 6.62
1,268.59 1,400.94 1,400.94 Quantity
Unit Cost
Amount
20.00
3.50
14.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
14.00 1,414.94 127.34 113.20 82.77 1,738.25
ILED UNIT PRICE ANALYSIS (DUPA)
of Trees (large a, above 500mm Ø up to 750mm Ø)
No. of Hours
Hourly Rate
Amount
3.33 3.33 3.33
69.42 50.18 38.97
231.17 167.10 259.54
657.81 No. of Hours
Hourly Rate
Amount
2.50 1.67 1.67
1,537.00 1,420.00 75.36
3,842.50 2,371.40 125.85 32.89
6,372.64 7,030.45 7,030.45 Quantity
Unit Cost
Amount
20.00
3.50
14.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
14.00 7,044.45 634.00 563.56 412.10 8,654.11
ILED UNIT PRICE ANALYSIS (DUPA)
of Trees (large b, above 750 up to 900mm Ø)
No. of Hours
Hourly Rate
Amount
6.67 6.67 6.67
69.42 50.18 38.97
463.03 334.70 519.86
1,317.59 No. of Hours
Hourly Rate
Amount
5.00 3.33 3.33
1,537.00 1,420.00 75.36
7,685.00 4,728.60 250.95 65.88
12,730.43 14,048.02 14,048.02 Quantity
Unit Cost
Amount
20.00
3.50
14.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
14.00 14,062.02 1,265.58 1,124.96 822.63 17,275.19
ILED UNIT PRICE ANALYSIS (DUPA)
es and Obstruction
No. of Hours
Hourly Rate
Amount
0 0 0
0.00 No. of Hours
Hourly Rate
Amount
0.00 0.00 0.00
0.00 0.00 0.00 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 0.00 0.00 0.00 0.00 0.00
ILED UNIT PRICE ANALYSIS (DUPA)
e Bridge Structures
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.50
1,998.10
999.05
1.00 1.00 0.125 0.125 0.25 1.00
150.00 965.00 1,420.00 1,733.00 1,861.00 45.45
300.00 965.00 177.50 216.63 465.25 45.45
3,168.88 3,494.54 3,494.54 Quantity
Unit Cost
Amount
0.10
2,500.00
250.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
250.00 3,744.54 337.01 299.56 219.06 4,600.16
ILED UNIT PRICE ANALYSIS (DUPA)
dge Structures
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 1.00
1,861.00 783.00
1,861.00 783.00
1.00 1.00
371.00 45.45
371.00 45.45 32.57
3,093.02 3,418.68 3.42 Quantity
Unit Cost
Amount
0.00025 0.002 0.05
2,500.00 90.00 3.50
0.63 0.18 0.18
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.98 4.40 0.40 0.35 0.26 5.40
ILED UNIT PRICE ANALYSIS (DUPA)
asonry Lined Drainage Structures
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
0.50
1,998.10
999.05
0.50 1.00
1,537.00 1,420.00
768.50 1,420.00
3,187.55 3,334.91 333.49 Quantity
Unit Cost
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
Amount
0.00 333.49 30.01 26.68 19.51 409.69
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
0.50 0.25
1,998.10 1,537.00
999.05 384.25
0.50 1.00
1,420.00 45.45
710.00 45.45
2,138.75 2,336.29 1,168.15 Quantity
Unit Cost
Amount
0.10
2,500.00
250.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
250.00 1,418.15 127.63 113.45 82.96 1,742.19
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00
1,537.00 1,017.90
1,537.00 508.95
0.50
14.74
2,060.69 2,208.05 368.01 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 368.01 33.12 29.44 21.53 452.10
ILED UNIT PRICE ANALYSIS (DUPA)
30" dia.) - 760mm dia.
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1
1,537.00 1,017.90
1,537.00 508.95
0.50
14.74
2,060.69 2,208.05 441.61 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 441.61 39.74 35.33 25.83 542.52
ILED UNIT PRICE ANALYSIS (DUPA)
36" dia.) - 910mm dia
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00
1,537.00 1,017.90
1,537.00 508.95
0.50
14.74
2,060.69 2,208.05 552.01 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 552.01 49.68 44.16 32.29 678.15
ILED UNIT PRICE ANALYSIS (DUPA)
42" dia.) - 1070mm dia.
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 0.50
1,537.00 1,017.90
1,537.00 508.95 14.74
2,060.69 2,208.05 552.01 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 552.01 49.68 44.16 32.29 678.15
ILED UNIT PRICE ANALYSIS (DUPA)
48" dia.) - 1220mm dia
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 0.50
1,537.00 1,017.90
1,537.00 508.95 14.74
2,060.69 2,208.05 736.02 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 736.02 66.24 58.88 43.06 904.19
ILED UNIT PRICE ANALYSIS (DUPA)
60" dia.) - 1520mm dia.
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 0.50
1,537.00 1,017.90
1,537.00 508.95 14.74
2,060.69 2,208.05 1,104.02 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 1,104.02 99.36 88.32 64.59 1,356.29
ILED UNIT PRICE ANALYSIS (DUPA)
her than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L=10 ft.
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 0.50
922.00 783.00
922.00 391.50 14.74
1,328.24 1,475.60 737.80 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 737.80 66.40 59.02 43.16 906.38
ILED UNIT PRICE ANALYSIS (DUPA)
Concrete Pavement (0.23m thk.)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.50
1,998.10 1,733.00 1,420.00
1,998.10 1,733.00 710.00 14.74
4,455.84 4,603.20 115.08 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 115.08 10.36 9.21 6.73 141.38
ILED UNIT PRICE ANALYSIS (DUPA)
PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.50 0.50
1,998.10 1,733.00 1,420.00 32.63
1,998.10 1,733.00 710.00 16.32 14.74
4,472.15 4,619.51 153.98 Quantity
Unit Cost
Amount
0.00015
8,000.00
1.20
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1.20 155.18 13.97 12.41 9.08 190.64
ILED UNIT PRICE ANALYSIS (DUPA)
Asphalt Pavement (100mm thk.)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.50
2,173.00 1,733.00 1,420.00
2,173.00 1,733.00 710.00 14.74
4,630.74 4,778.10 79.63 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 79.63 7.17 6.37 4.66 97.83
ILED UNIT PRICE ANALYSIS (DUPA)
k (100mm thk)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.50
1,998.10 1,537.00 1,420.00
1,998.10 1,537.00 710.00
4,245.10 4,392.46 58.57 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 58.57 5.27 4.69 3.43 71.95
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
1,998.10 1,537.00 1,420.00
999.05 768.50 710.00
2,477.55 2,624.91 52.50 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 52.50 4.72 4.20 3.07 64.49
ILED UNIT PRICE ANALYSIS (DUPA)
Gutter
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
1,998.10 1,537.00 1,420.00
999.05 768.50 710.00
2,477.55 2,624.91 87.50 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 87.50 7.87 7.00 5.12 107.49
ILED UNIT PRICE ANALYSIS (DUPA)
n (Unsuitable)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.10
1,420.00 1,537.00 1,733.00
2,840.00 1,537.00 173.30 18.63
4,568.93 4,755.26 237.76 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 237.76 21.40 19.02 13.91 292.09
ILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Common)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25 1.00
3,379.00 1,733.00 1,733.00 1,420.00
3,379.00 1,733.00 433.25 2,840.00
8,385.25 8,532.61 142.21 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 142.21 12.80 11.38 8.32 174.71
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(2)b
Designation
Roadway Excavation (Surplus Common) cu.m. 80.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bulldozer, D6H SERIES II PSDS/DD b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (12 cu.yd.) e. Backhoe (0.80 cu.m.)
1 1 1 3 1
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 80.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (D Item No./Description Unit of Measurement Output per hour
: : :
102(3)a
Roadway Excavation (Surplus Soft Rock) cu.m. 56.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (12 cu.yd.) e. Backhoe (0.80 cu.m.) w/ attachment
1 1 1 2 1
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 56.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(3)b
Roadway Excavation (Surplus Soft Rock) cu.m. 42.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (12 cu.yd.)
1 1 1 2
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 42.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(3)c
Roadway Excavation (Surplus Hard Rock) - Blasting cu.m. 4.20
Designation A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Construction Foreman b Unskilled Labor Sub - Total for A Name and Capacity
No. of Person (Drilling)
(Blasting)
(Disposal)
1 2 4 1 1 2 1 2 No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (12 cu.yd.) e. Pneumatic Drilling Machine f. Air Compressor (161 - 185 cfm) (Hauling Distance - within three (3) km.)
1 1 1 1 2 1
Sub - Total for B C. Total (A + B) D. Output per hour = 4.2000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Dynamite b. Detonation Cord c. Detonator d. Ammonium Sulfate
kg. m. pc. kg.
e. Blasting Cap f. Safety Fuse
pc. m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(3)d
Roadway Excavation (Surplus Hard Rock) - Blasting (T cu.m. 1.65
Designation A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Construction Foreman b Unskilled Labor Sub - Total for A Name and Capacity
No. of Person (Drilling)
(Blasting)
(Disposal)
1 2 4 1 1 2 1 2 No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Backhoe w/ Chipping Hammer (0.80 cu.m.) c. Dump Truck (12 cu. yd) d. Pneumatic Drilling Machine e. Air Compressor (161 - 185 cfm) f. Payloader (1.50 cu.m.) g. Payloader (1.50 cu.m.) - at disposal area h. Water Truck/Pump (16000L)
1 1 1 2 1 1 1 1
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.65 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Dynamite b. Detonation Cord c. Detonator d. Ammonium Sulfate
kg. m. pc. kg.
e. Blasting Cap f. Safety Fuse
pc. m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
102(4)
Designation
Roadway Excavation (Surplus Unclassified) cu.m. 50.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bulldozer, D6H SERIES II PSDS/DD
1
b. Payloader (1.50 cu.m.) c. Payloader (1.50 cu.m.) - at disposal area d. Dump Truck (12 cu. yd)
1 1 2
(Hauling Distance - within three (3) km.)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(1)a
Designation
Structure Excavation (Common Soil) cu.m. 20.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd)
2
b. Backhoe (0.80 cu.m.) Minor Tools (10% of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 20.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(1)b
Designation
Structure Excavation (Soft Rock) cu.m. 14.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd)
2
b. Backhoe (0.80 cu.m.)
1
c. Backhoe w/ Breaker (0.80 cu.m.) Minor Tools (10% of Labor Cost )
1
Sub - Total for B C. Total (A + B) D. Output per hour = 14.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(1)c
Designation
Structure Excavation (Solid Rock) cu.m. 4.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd)
1
b. Backhoe (0.80 cu.m.) c. Backhoe w/ Breaker (0.80 cu.m.) Minor Tools (10% of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Unit
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(2)a
Designation
Bridge Excavation (Common Soil) cu.m. 20.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Backhoe (0.80 cu.m.)
1
b. Dump Truck (12 cu. yd)
2
Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 20.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(2)b
Designation
Bridge Excavation (Soft Rock) cu.m. 14.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Backhoe w/ Breaker (0.80 cu.m.)
1
c. Dump Truck (12 cu.yd.) Minor Tools (10% of Labor Cost)
2
Sub - Total for B C. Total (A + B) D. Output per hour = 14.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(2)c
Designation
Bridge Excavation (Solid Rock) cu.m. 4.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Backhoe w/ Breaker (0.80 cu.m.)
1
c. Dump Truck (12 cu. yd) Minor Tools (10% of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(2)d
Designation
Bridge Excavation (Solid Rock) cu.m. 1.50 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Jack Hammer
2
b. Air Compressor (356 - 450 cfm)
1
c. Backhoe (0.80 cu.m.) d. Dump Truck (12 cu. yd) Minor Tools (10% of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.500 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(3)
Designation
Foundation Fill cu.m. 1.25 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Plate Compactor (5 Hp) b. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Filling Materials
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(4)
Designation
Excavation ordered below Plan Elevation cu.m. 20.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd) b. Backhoe (0.80 cu.m.) Minor Tools (10% of Labor Cost)
2 1
Sub - Total for B C. Total (A + B) D. Output per hour = 20. cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
103(5)a
Designation
Shoring l.s. 1.00 No. of Person
A. Labor Note:
*) The component quantity of items of work involved such as item 404/405/509 shall be based actual design of the shoring. **) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of ite as processed component pay item.
Sub - Total for A Name and Capacity
No of Units
B. Equipment
Sub - Total for B C. Total (A + B) D. Output = 1.0000 l.s E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials/Processed Component Pay Item a. 404 - Reinforcing Steel Bar b. 405 - Structural Concrete c. 509 - Steel Sheet Pile
kg. cu.m. l.m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
103(5)b
Cribbing/Cofferdamming l.s. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Crawler Crane (36 - 40 mt) b. Vibro Hammer (Hydraulic Operated) c. Welding Machine (300 A, Gas/Diesel Driven d. Cutting Outfit e. Water Pump, 100mm suction diameter
1 1 1 1 1
Sub - Total for B C. Total (A + B) D. Output = 1.0000 l.s E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Steel Sheet Pile b. Walling, Bracing, Diagonal, etc. Miscellaneous (1% of Materials Cost)
kg. kg.
Note: a.) The assume dimesion of area to be provided with cofferdam is 12m x 12m square with Steel Sheet Piles depth of 9m at 48 kg./m. b.) The quantity of component materials requirement may vary depending on the actual design of Cribbing/Cofferdamming.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
103(6)
Designation
Pipe Culvert and Drain Excavation cu.m. 20.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Dump Truck (12 cu. yd) b. Backhoe (0.80 cu.m.) Minor Tools (10% of Labor Cost)
2 1
Sub - Total for B C. Total (A + B) D. Output per hour = 20.00000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
104(1)a
Embankment (from Borrow) cu.m. 50.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Common Borrow (w/ 25% Shrinkage Factor)
cu.m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
104(1)b
Designation A. Labor For Excavation Work: a. Construction Foreman b. Unskilled Labor Spreading and Compaction: a. Construction Foreman b. Unskilled Labor
Embankment from Roadway Excavation cu.m. 50.00 No. of Person
1 2
1 2
Sub - Total for A Name and Capacity B. Equipment For Excavation Work: a. Bulldozer, D6H SERIES II PSDS/DD b. Payloader (1.50 cu.m.) c. Dump Truck (12 cu.yd.) Spreading and Compaction: a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
No of Units
1 1 2
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
104(2)
Selected Borrow for topping , case 1 cu.m. 50.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Selected Borrow (w/ 25% Shrinkage Factor)
cu.m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
104(3)
Selected Borrow for topping , case 2 cu.m. 50.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.00000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Selected Borrow (w/ 25% Shrinkage Factor)
cu.m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
104(4)
Designation
Earth Berm cu.m. 1.25 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Plate Compactor (5 Hp) b.Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Filling Materials
cu.m.
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
105(1)
Designation
Subgrade Preparation (Common Material) sq.m. 300.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 300.00000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
105(2)
Designation
Subgrade Preparation (Existing Pavement) sq.m. 300.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 300.00000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
105(3)
Designation
Subgrade Preparation (Unsuitable Material) sq.m. 300.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 300.00000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
G. H. I. J. K.
Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Unit
ILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Common)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.30 1.00 1.00
3,379.00 1,733.00 1,733.00 1,420.00 1,537.00
3,379.00 1,733.00 519.90 4,260.00 1,537.00
11,428.90 11,576.26 144.70 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 144.70 13.02 11.58 8.47 177.77
AILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Soft Rock)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25 1.00 1.00
3,885.85 1,733.00 1,733.00 1,420.00 1,537.00
3,885.85 1,733.00 433.25 2,840.00 1,537.00
10,429.10 10,576.46 188.87 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 188.87 17.00 15.11 11.05 232.02
ILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Soft Rock)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.20 1.00
3,885.85 1,733.00 1,733.00 1,420.00
3,885.85 1,733.00 346.60 2,840.00
8,805.45 8,952.81 213.16 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 213.16 19.18 17.05 12.47 261.87
ILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Hard Rock) - Blasting
No. of Hours
Hourly Rate
Amount
0.40 0.40 0.40 0.20 0.20 0.20 0.40 0.40
69.42 50.18 38.97 69.42 50.18 38.97 69.42 38.97
27.768 40.144 62.352 13.884 10.036 15.588 27.768 31.176 228.72
No. of Hours
Hourly Rate
Amount
0.20 0.15 0.05 0.40 0.40 0.40
1,537.00 1,733.00 1,733.00 1,420.00 170.00 502.00
307.40 259.95 86.65 568.00 136.00 200.80
1,558.80 1,787.52 425.60 Quantity
Unit Cost
Amount
0.40 2.00 0.15 0.20
280.00 80.00 260.00 75.00
112.00 160.00 39.00 15.00
0.40 0.10
45.00 40.00
18.00 4.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
348.00 773.60 69.62 61.89 45.26 950.37
ILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Hard Rock) - Blasting (Tunnel Excavation)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.50
69.42 50.18 38.97 69.42 50.18 38.97 69.42 38.97
69.42 100.36 155.88 69.42 50.18 77.94 34.71 38.97 596.88
No. of Hours
Hourly Rate
Amount
0.50 0.10 0.50 1.00 1.00 0.20 0.03 0.05
1,537.00 1,998.10 1,420.00 170.00 502.00 1,733.00 1,733.00 2,450.00
768.50 199.81 710.00 340.00 502.00 346.60 51.99 122.50
3,041.40 3,638.28 2,205.02 Quantity
Unit Cost
Amount
2.00 1.40 2.00 1.00
280.00 80.00 260.00 75.00
560.00 112.00 520.00 75.00
0.45 0.10
45.00 40.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
20.25 4.00
1,291.25 3,496.27 314.66 279.70 204.53 4,295.17
ILED UNIT PRICE ANALYSIS (DUPA)
n (Surplus Unclassified)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00
3,379.00
3,379.00
1.00 0.20 1.00
1,733.00 1,733.00 1,420.00
1,733.00 346.60 2,840.00
8,298.60 8,445.96 168.92 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 168.92 15.20 13.51 9.88 207.52
ILED UNIT PRICE ANALYSIS (DUPA) (Common Soil)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
Amount
1.00
1,420.00
2,840.00
1.00
1,537.00
1,537.00 18.63
4,395.63 4,581.96 229.10 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 229.10 20.62 18.33 13.40 281.45
ILED UNIT PRICE ANALYSIS (DUPA) (Soft Rock)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
Amount
1.00 0.50
1,420.00 1,537.00
2,840.00 768.50
0.50
1,998.10
999.05 18.63
4,626.18 4,812.51 343.75 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 343.75 30.94 27.50 20.11 422.30
ILED UNIT PRICE ANALYSIS (DUPA) (Solid Rock)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
Amount
1.00
1,420.00
1,420.00
0.25 0.75
1,537.00 1,998.10
384.25 1,498.58 18.63
3,321.46 3,507.79 876.95 Quantity
Unit Cost
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
Amount
0.00 876.95 78.93 70.16 51.30 1,077.33
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
1.00
1,537.00 1,420.00
1,537.00 2,840.00
1.00
19.75
4,396.75 4,594.29 229.71 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 229.71 20.67 18.38 13.44 282.20
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
0.50 0.50
1,537.00 1,998.10
768.50 999.05
1.00
1,420.00
2,840.00 19.75
4,627.30 4,824.84 344.63 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 344.63 31.02 27.57 20.16 423.38
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
0.50 1.00
1,537.00 1,998.10
768.50 1,998.10
0.50
1,420.00
710.00 19.75
3,496.35 3,693.89 923.47 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 923.47 83.11 73.88 54.02 1,134.49
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
1.00 1.00
150.00 965.00
300.00 965.00
0.15 0.15
1,537.00 1,420.00
230.55 213.00 19.75
1,728.30 1,925.84 1,283.90 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 1,283.90 115.55 102.71 75.11 1,577.27
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 155.88
225.30 No. of Hours
Hourly Rate
Amount
1.00 0.01
123.00 2,450.00
123.00 24.50 22.53
170.03 395.33 316.26 Quantity
Unit Cost
Amount
1.15
465.00
534.75
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
534.75 851.01 76.59 68.08 49.78 1,045.47
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
Amount
1.00 1.00
1,420.00 1,537.00
2,840.00 1,537.00 18.63
4,395.63 4,581.96 229.10 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 229.10 20.62 18.33 13.40 281.45
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
No. of Hours
Hourly Rate
Amount
Quantity
Unit Cost
Amount
item 404/405/509 shall be based on the
d Unit Price Analysis (DUPA) of item 404/405/509
* * *
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
160 160 160
69.42 50.18 38.97
11,107.20 16,057.60 24,940.80
52,105.60 No. of Hours
Hourly Rate
Amount
160.00 160.00 40.00 40.00 160.00
1,902.00 2,123.00 371.00 45.45 266.25
304,320.00 339,680.00 14,840.00 1,818.00 42,600.00
703,258.00 755,363.60 755,363.60 Quantity
Unit Cost
Amount
69,120.00 7,323.77
48.00 48.00
3,317,760.00 351,540.96 36,693.01
dam is 12m x 12m square with
ary depending on the actual
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
3,705,993.97 4,461,357.57 401,522.18 356,908.61 260,989.42 5,480,777.77
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
Amount
1.00 1.00
1,420.00 1,537.00
2,840.00 1,537.00 18.63
4,395.63 4,581.96 229.10 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 229.10 20.62 18.33 13.40 281.45
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
Amount
1.25
160.00
200.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
200.00 295.58 26.60 23.65 17.29 363.12
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
0.83 0.83
69.42 38.97
57.62 64.69
1.00 1.00
69.42 38.97
69.42 77.94 269.67
No. of Hours
Hourly Rate
Amount
0.83 0.83 0.83
3,379.00 1,733.00 1,420.00
2,804.57 1,438.39 2,357.20
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
11,231.66 11,501.33 230.03 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 230.03 20.70 18.40 13.46 282.59
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
Amount
1.25
420.00
525.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
525.00 620.58 55.85 49.65 36.30 762.38
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
Amount
1.25
420.00
525.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
525.00 620.58 55.85 49.65 36.30 762.38
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 155.88
225.30 No. of Hours
Hourly Rate
Amount
1.00 0.01
123.00 2,450.00
123.00 24.50 22.53
170.03 395.33 316.26 Quantity
Unit Cost
Amount
1.25
420.00
525.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
525.00 841.26 75.71 67.30 49.21 1,033.49
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 15.93 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 15.93 1.43 1.27 0.93 19.57
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 15.93 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 15.93 1.43 1.27 0.93 19.57
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 15.93 Quantity
Unit Cost
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
Amount
0.00 15.93 1.43 1.27 0.93 19.57
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
200
Designation
Aggregate Subbase Course cu.m 50.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregate Subbase Course (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
200(1)
Designation
Aggregate Subbase Course (for Intermittent Reblockin cu.m 40.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A
1
b. Vibratory Roller (10 m.t.), SD100DC c. Plate Compactor (5 Hp) d. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 40.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregate Subbase Course (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
201
Designation
Aggregate Base Course cu.m 50.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A
1
b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregate Base Course (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
201(1)
Designation
Aggregate Base Course (for Reblocking) cu.m 40.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC a. Plate Compactor (5 Hp) d. Water Truck/Pump (16000L)
1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 40.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregate Base Course (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
202
Designation
Crushed Aggregate Base Course cu.m 50.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Crushed Aggregate Base Course (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)
Course
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
Amount
1.15
350.00
402.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
402.50 498.08 44.83 39.85 29.14 611.89
ILED UNIT PRICE ANALYSIS (DUPA)
Course (for Intermittent Reblocking)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00
2,173.00
2,173.00
1.00 0.25 0.25
1,846.00 123.00 2,450.00
1,846.00 30.75 612.50
4,662.25 4,809.61 120.24 Quantity
Unit Cost
Amount
1.15
580.00
667.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
667.00 787.24 70.85 62.98 46.05 967.12
ILED UNIT PRICE ANALYSIS (DUPA)
urse
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00
2,173.00
2,173.00
1.00 0.25
1,846.00 2,450.00
1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
Amount
1.15
650.00
747.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
747.50 843.08 75.88 67.45 49.32 1,035.72
ILED UNIT PRICE ANALYSIS (DUPA)
urse (for Reblocking)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25 0.25
2,173.00 1,846.00 123.00 2,450.00
2,173.00 1,846.00 30.75 612.50
4,662.25 4,809.61 120.24 Quantity
Unit Cost
Amount
1.15
650.00
747.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
747.50 867.74 78.10 69.42 50.76 1,066.02
ILED UNIT PRICE ANALYSIS (DUPA)
Base Course
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
Amount
1.15
700.00
805.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
805.00 900.58 81.05 72.05 52.68 1,106.36
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
203
Lime Stabilized Road Mix Base Course cu.m. 15.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 10
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 15.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Hydrated Lime, Type N (Normal) b. Aggregate Base Course
bag cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
204
Designation
Portland Cement Stabilized Road Mix Base Course cu.m. 15.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 10
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A
1
b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 15.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Aggregate Base Course
bag cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
205
Designation
Asphalt Stabilized Road Mix Base Course cu.m. 15.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 10
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A
1
b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L) d. Asphalt Distributor, 10 ft. wide (5 ton)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 15.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Emulsified Asphalt SS-1 b. Aggregate Base Course
m.t. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
206
Designation
Portland Cement Treated Plant Mix Base Course cu.m. 15.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Concrete Batching Plant (30 cu.m.) b. Dump Truck (12 cu.yd.) c. Motorized Road Grader (140 hp), G710A d. Vibratory Roller (10 m.t.), SD100DC e. Payloader (1.50 cu.m.), LX80-2C f. Water Truck/Pump (16000L) g. Asphalt Distributor, 10 ft. wide (5 ton)
1 3 1 1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 15.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Aggregate Base Course c. MC 70 Cut-back Asphalt
bag cu.m. m.t.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)
d Mix Base Course
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 389.70
459.12 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25
2,173.00 1,846.00 2,450.00
2,173.00 1,846.00 612.50
4,631.50 5,090.62 339.37 Quantity
Unit Cost
Amount
2.80 1.15
180.00 650.00
504.00 747.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,251.50 1,590.87 143.18 127.27 93.07 1,954.39
ILED UNIT PRICE ANALYSIS (DUPA)
abilized Road Mix Base Course
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 389.70
459.12 No. of Hours
Hourly Rate
Amount
1.00
2,173.00
2,173.00
1.00 0.25
1,846.00 2,450.00
1,846.00 612.50
4,631.50 5,090.62 339.37 Quantity
Unit Cost
Amount
3.00 1.15
220.00 650.00
660.00 747.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,407.50 1,746.87 157.22 139.75 102.19 2,146.04
ILED UNIT PRICE ANALYSIS (DUPA)
oad Mix Base Course
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 389.70
459.12 No. of Hours
Hourly Rate
Amount
1.00
2,173.00
2,173.00
1.00 0.25 1.00
1,846.00 2,450.00 936.00
1,846.00 612.50 936.00
5,567.50 6,026.62 401.77 Quantity
Unit Cost
Amount
0.07 1.15
44,000.00 650.00
3,080.00 747.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
3,827.50 4,229.27 380.63 338.34 247.41 5,195.66
ILED UNIT PRICE ANALYSIS (DUPA)
eated Plant Mix Base Course
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50 0.50 0.50 0.25 0.10
1,759.50 1,352.00 2,173.00 1,846.00 1,733.00 2,450.00 936.00
879.75 2,028.00 1,086.50 923.00 866.50 612.50 93.60
6,489.85 6,815.51 454.37 Quantity
Unit Cost
Amount
3.00 1.15 0.0075
220.00 650.00 40,300.00
660.00 747.50 302.25
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,709.75 2,164.12 194.77 173.13 126.60 2,658.62
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
300(1)
Gravel Surface Course (Uncrushed) cu.m 50.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A
1
b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Uncrushed Aggregate Surface Course (w/ 15% Shrinkage Factor)
241+32
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
300(2)
Crushed Aggregate Surface Course cu.m 50.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader (140 hp), G710A
1
b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Crushed Aggregate Surface Course (w/ 15% Shrinkage Factor)
243+32
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
301(1)
Bituminous Prime Coat (MC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons)
1
b. Power Broom (20 m. wide)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. MC 70 Cut-back Asphalt (w/ 5% wastage)
m.t.
245+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
301(2)
Bituminous Prime Coat (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons)
1
b. Power Broom (20 m. wide)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. RC 70 Cut-back Asphalt (w/ 5% wastage)
m.t.
247+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
302(1)
Bituminous Tack Coat (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons)
1
b. Power Broom (20 m. wide)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. RC 70 Cut-back Asphalt (w/ 5% wastage)
m.t.
249+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
302(2)
Bituminous Tack Coat (Emulsified Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Emulsified Asphalt SS-1 (w/ 5% wastage)
m.t.
251+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
303(1)
Bituminous Seal Coat (Cover Aggregate) m.t. 16.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 20
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Tandem Steel Roller (10.1 m.t.), CC421 b. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 16.0000 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cover Aggregate (w/ 15% Shrinkage Factor)
m.t.
Note: 1.60 m.t./cu.m.
253+32
using unit wt. of 1,600 kg./m³
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
303(2)
Bituminous Seal Coat (MC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. MC Cut-back Asphalt (w/ 5% Wastage)
m.t.
255+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
303(3)
Bituminous Seal Coat (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. RC 70 Cut-back Asphalt (w/ 5% Wastage)
m.t.
257+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
303(4)
Bituminous Seal Coat (Asphalt Cement Penetration Gr m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Asphalt Cement Penetration Grade 120-150 (w/ 5% Wastage)
259+32
m.t.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
304(1)
Bituminous Surface Treatment (Aggregate Grading) m.t. 16.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 20
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 16.0000 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregates (w/ 15% Shrinkage Factor)
m.t.
261+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
304(2)
Bituminous Surface Treatment (Asphalt Cement Penet m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Asphalt Cement Penetration Grade 120-150 (w/ 5% Wastage)
263+32
m.t.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
304(3)
Bituminous Surface Treatment (MC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 tons) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. MC Cut-back Asphalt (w/ 5% Wastage)
m.t.
265+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
304(4)
Bituminous Surface Treatment (RC Cut-back Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 ton) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. RC 70 Cut-back Asphalt (w/ 5% Wastage)
m.t.
267+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
304(5)
Bituminous Surface Treatment (Emulsified Asphalt) m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 ton) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Emulsified Asphalt SS-1 (w/ 5% wastage)
m.t.
269+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
305(1)
Bituminous Penetration Macadam Pavement (Aggrega m.t. 16.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 20
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Vibratory Roller (10 m.t.), SD100DC c. Water Truck/Pump (16000L)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 16.0000 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregates (w/ 15% Shrinkage Factor)
m.t.
271+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
305(2)
Bituminous Penetration Macadam Pavement (Asphalt m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 ton) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Asphalt Cement (w/ 5% Wastage)
m.t.
273+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
305(3)
Bituminous Penetration Macadam Pavement (RC Cutm.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 ton) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. RC 70 Cut-back Asphalt (w/ 5% Wastage)
m.t.
275+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
305(4)
Bituminous Penetration Macadam Pavement (Emulsifi m.t. 0.30
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Asphalt Distributor, 10 ft. wide (5 ton) b. Power Broom (20 m. wide)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.300 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Emulsified Asphalt SS-1 (w/ 5% wastage)
m.t.
277+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
306(a)
Bituminous Road Mix Surface Course m.t. 12.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader w/ Scarifier (140 hp), G710A b. Tandem Steel Roller (10.1 m.t.), CC421 c. Pneumatic Tire Roller (10 m.t.) d. Asphalt Distributor, 10 ft. wide (5 ton) e. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 12.0000 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Crushed Gravel b. MC Cut-back Asphalt (7%) c. Hydrated Lime (0.75%)
m.t. m.t. bag
279+32
0.0575(2.335)(1.05) = 0.141 0.0075(35.29) = 0.26, say 0.30
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
306(b)
Bituminous Road Mix Surface Course m.t. 12.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader w/ Scarifier (140 hp), G710A b. Tandem Steel Roller (10.1 m.t.), CC421 c. Pneumatic Tire Roller (10 m.t.) d. Asphalt Distributor, 10 ft. wide (5 ton) e. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 12.0000 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Crushed Gravel b. Emulsified Asphalt (10%) c. Hydrated Lime (0.75%)
m.t. m.t. bag
281+32
0.08(2.335)(1.05) = 0.196 0.0075(35.29) = 0.26, say 0.30
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
306(1)
Aggregates for Bituminous Road Mix Surface Course m.t. 12.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 3
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Motorized Road Grader w/ Scarifier (140 hp), G710A b. Tandem Steel Roller (10.1 m.t.), CC421 c. Pneumatic Tire Roller (10 m.t.) c. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 12.0000 m.t E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Crushed Gravel
m.t.
283+32
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
RICE ANALYSIS (DUPA)
)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 77.94
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
147.36
S
Amount
Nam B. Equipment
1.00
2,173.00
2,173.00
1.00 0.25
1,846.00 2,450.00
1,846.00 612.50
4,631.50 4,778.86 95.58 Quantity
Unit Cost
a. Asphalt Distributor, 10 f
S C. D. Output per hour = 1.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15
700.00
805.00
285+32
a. MC Cut-back Asphalt
805.00 900.58 81.05 72.05 52.68 1,106.36
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
1.00 1.00
Hourly Rate
Amount
69.42 38.97
69.42 77.94
147.36 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00
2,173.00
2,173.00
a. Asphalt Paver (80 Hp),
1.00 0.25
1,846.00 2,450.00
1,846.00 612.50
b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Dump Truck (12 cu.yd.) e. Asphalt Batch Plant ( 60 f. Water Truck/Pump (160 g. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
4,631.50 4,778.86 95.58 Quantity
Unit Cost
S
C. D. Output per hour = 171.300 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15
750.00
862.50
287+32
a. Bituminous Material (8% b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
862.50 958.08 86.23 76.65 56.05 1,177.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
ck Asphalt)
Item No./Description Unit of Measurement Output per hour No. of Hours
1.00 1.00
Hourly Rate
Amount
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00
936.00
936.00
a. Asphalt Paver (80 Hp),
1.00
130.54
130.54
b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Dump Truck (12 cu.yd.) e. Asphalt Batch Plant ( 60 f. Water Truck/Pump (160 g. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
1,066.54 1,252.87 4,176.23 Quantity
Unit Cost
S
C. D. Output per hour = 171.300 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
40,300.00
42,315.00
289+32
a. Emulsified Asphalt (10% b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
42,315.00 46,491.23 4,184.21 3,719.30 2,719.74 57,114.48
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
ck Asphalt)
Item No./Description Unit of Measurement Output per hour No. of Hours
1.00 1.00
Hourly Rate
Amount
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00
936.00
936.00
a. Asphalt Paver (80 Hp),
1.00
130.54
130.54
b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Dump Truck (12 cu.yd.) e. Asphalt Batch Plant ( 60 f. Water Truck/Pump (160 g. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
1,066.54 1,252.87 4,176.23 Quantity
Unit Cost
S
C. D. Output per hour = 171.300 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
41,575.00
43,653.75
291+32
a. MC - 70 Cut-back Asph b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
43,653.75 47,829.98 4,304.70 3,826.40 2,798.05 58,759.13
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
k Asphalt)
Item No./Description Unit of Measurement Output per hour No. of Hours
1.00 1.00
Hourly Rate
Amount
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00
936.00
936.00
a. Dump Truck (12 cu. yd)
1.00
130.54
130.54
b. Asphalt Batch Plant ( 60 c. Water Truck/Pump (160 d. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
1,066.54 1,252.87 4,176.23 Quantity
Unit Cost
S
C. D. Output per hour = 171.300 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
41,575.00
43,653.75
293+32
a. MC - 70 Cut-back Asph b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
43,653.75 47,829.98 4,304.70 3,826.40 2,798.05 58,759.13
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
sphalt)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Asphalt Paver (80 Hp), b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Water Truck/Pump (160 Minor Tools (10% of Labor
S
4,176.23
C. D. Output per hour = 285.51 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
44,000.00
46,200.00
295+32
a. Bituminous Concrete Su thickness = 30mm (w/ 5%
46,200.00 50,376.23 4,533.86 4,030.10 2,947.01 61,887.20
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
gate)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 779.40
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
848.82
S
Amount
Nam B. Equipment
1.00 0.25
1,652.00 2,450.00
1,652.00 612.50
2,264.50 3,113.32 194.58 Quantity
Unit Cost
a. Asphalt Paver (80 Hp), b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 c. Water Truck/Pump (160 Minor Tools (10% of Labor
S C. D. Output per hour = 214.13 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15
406.25
467.19
297+32
a. Bituminous Concrete Su thickness = 40mm (w/ 5%
467.19 661.77 59.56 52.94 38.71 812.98
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
k Asphalt)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87 4,176.23 Quantity
Unit Cost
a. Asphalt Paver (80 Hp), b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 c. Water Truck/Pump (160 Minor Tools (10% of Labor
S
C. D. Output per hour = 171.300 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
40,300.00
42,315.00
299+32
a. Bituminous Concrete Su thickness = 50mm (w/ 5%
42,315.00 46,491.23 4,184.21 3,719.30 2,719.74 57,114.48
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
k Asphalt)
Item No./Description Unit of Measurement Output per hour No. of Hours
1.00 1.00
Hourly Rate
Amount
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Asphalt Paver (80 Hp), b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Dump Truck (12 cu.yd.) e. Asphalt Batch Plant ( 60 f. Water Truck/Pump (160 g. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
S
4,176.23
C. D. Output per hour = 285.51 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
41,575.00
43,653.75
301+32
a. Asphalt Cement (8%) b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
43,653.75 47,829.98 4,304.70 3,826.40 2,798.05 58,759.13
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
ment Penetration Grade 120-150)
No. of Hours
1.00 1.00
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount
69.42 38.97
69.42 116.91
186.33 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Asphalt Paver (80 Hp), b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Dump Truck (12 cu.yd.) e. Asphalt Batch Plant ( 60 f. Water Truck/Pump (160 g. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
S
4,176.23
C. D. Output per hour = 214.13 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
50,775.00
53,313.75
303+32
a. Asphalt Cement (8%) b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
53,313.75 57,489.98 5,174.10 4,599.20 3,363.16 70,626.44
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
regate Grading)
Item No./Description Unit of Measurement Output per hour
No. of Hours
1.00 1.00
Hourly Rate
Amount
69.42 38.97
69.42 779.40
848.82 No. of Hours
Hourly Rate
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor a. Batching Plant Enginee b. Mechanical Engineer c. Electrical Engineer d. Unskilled Laboratory Te e. Unskilled Labor S
Amount
Nam B. Equipment
1.00 0.25
1,846.00 2,450.00
1,846.00 612.50
2,458.50 3,307.32 206.71 Quantity
Unit Cost
a. Asphalt Paver (80 Hp), b. Pneumatic Tire Roller (1 c. Tandem Steel Roller (10 d. Dump Truck (12 cu.yd.) e. Asphalt Batch Plant ( 60 f. Water Truck/Pump (160 g. Payloader (1.50 cu.m.), Minor Tools (10% of Labor
S
C. D. Output per hour = 171.300 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15
406.25
467.19
305+32
a. Asphalt Cement (8%) b. Aggregates, Sand (79% c. Aggregates, 3/8 (19%) d. Mineral Filler (7%)
e. Diesel
467.19 673.90 60.65 53.91 39.42 827.88
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
halt Cement Penetration Grade 120-150)
No. of Hours
Item No./Description Unit of Measurement Output per hour
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Concrete Batching Plan d. Payloader (1.50 cu.m.), e. Concrete Screeder (5.5 f. Water Truck/Pump (160 g. Concrete Saw (7.5 Hp), h. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
4,176.23
C. D. Output per hour = 107.33 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
50,775.00
53,313.75
307+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond i. Pipe Sleeve, 1" dia. j. Grease/Tar
53,313.75 57,489.98 5,174.10 4,599.20 3,363.16 70,626.44
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Cut-back Asphalt)
Item No./Description Unit of Measurement Output per hour
No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Concrete Vibrator b. Concrete Screeder (5.5 c. Concrete Saw (7.5 Hp), d. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
4,176.23
C. D. Output per hour = 107.33 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
40,300.00
42,315.00
309+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Ready Mix Concrete, 35 f. Concrete Saw (diamond g. Pipe Sleeve, 1" dia. h. Grease/Tar
42,315.00 46,491.23 4,184.21 3,719.30 2,719.74 57,114.48
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
Cut-back Asphalt)
Item No./Description Unit of Measurement Output per hour
No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Concrete Batching Plan d. Payloader (1.50 cu.m.), e. Concrete Screeder (5.5 f. Water Truck/Pump (160 g. Concrete Saw (7.5 Hp), h. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
4,176.23
C. D. Output per hour = 80.500 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
41,575.00
43,653.75
311+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond i. Pipe Sleeve, 1 1/2" dia. j. Grease/Tar
43,653.75 47,829.98 4,304.70 3,826.40 2,798.05 58,759.13
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
ulsified Asphalt)
Item No./Description Unit of Measurement Output per hour
No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Concrete Vibrator b. Concrete Screeder (5.5 c. Concrete Saw (7.5 Hp), d. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
4,176.23
C. D. Output per hour = 80.5 sq E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
44,000.00
46,200.00
313+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Ready Mix Concrete, 35 f. Concrete Saw (diamond g. Pipe Sleeve, 1" dia. h. Grease/Tar
46,200.00 50,376.23 4,533.86 4,030.10 2,947.01 61,887.20
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
Pavement (Aggregates)
No. of Hours
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 779.40
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
848.82
S
Amount
Nam B. Equipment
1.00 0.25
1,846.00 2,450.00
1,846.00 612.50
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Concrete Batching Plan d. Payloader (1.50 cu.m.), e. Concrete Screeder (5.5 f. Water Truck/Pump (160 g. Concrete Saw (7.5 Hp), h. Bar Cutter, Single Phas Minor Tools (5% of Labor
2,458.50 3,307.32
S
206.71 Quantity
Unit Cost
C. D. Output per hour = 70.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15
406.25
467.19
315+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond i. Pipe Sleeve, 2" dia. j. Grease/Tar
467.19 673.90 60.65 53.91 39.42 827.88
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
Pavement (Asphalt Cement)
No. of Hours
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87 4,176.23 Quantity
Unit Cost
a. Concrete Vibrator b. Concrete Screeder (5.5 c. Concrete Saw (7.5 Hp), d. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
C. D. Output per hour = 70. sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
50,775.00
53,313.75
317+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Ready Mix Concrete, 35 f. Concrete Saw (diamond g. Pipe Sleeve, 1" dia. h. Grease/Tar
53,313.75 57,489.98 5,174.10 4,599.20 3,363.16 70,626.44
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
Pavement (RC Cut-back Asphalt)
No. of Hours
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Concrete Batching Plan d. Payloader (1.50 cu.m.), e. Concrete Screeder (5.5 f. Water Truck/Pump (160 g. Concrete Saw (7.5 Hp), h. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
4,176.23
C. D. Output per hour = 64.400 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
41,575.00
43,653.75
319+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond i. Pipe Sleeve, 2" dia. j. Grease/Tar
43,653.75 47,829.98 4,304.70 3,826.40 2,798.05 58,759.13
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
Pavement (Emulsified Asphalt)
No. of Hours
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
69.42 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
186.33
S
Amount
Nam B. Equipment
1.00 1.00
936.00 130.54
936.00 130.54
1,066.54 1,252.87
Quantity
Unit Cost
a. Concrete Vibrator b. Concrete Screeder (5.5 c. Concrete Saw (7.5 Hp), d. Bar Cutter, Single Phas Minor Tools (5% of Labor
S
4,176.23
C. D. Output per hour = 64.4 sq E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.05
44,000.00
46,200.00
321+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Ready Mix Concrete, 35 f. Concrete Saw (diamond g. Pipe Sleeve, 1" dia. h. Grease/Tar
46,200.00 50,376.23 4,533.86 4,030.10 2,947.01 61,887.20
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
se
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
69.42 50.18 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
236.51
S
Amount
Nam B. Equipment
1.00 1.00 1.00 1.00 0.25
2,824.90 1,652.00 561.00 936.00 2,450.00
2,824.90 1,652.00 561.00 936.00 612.50 23.65
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Concrete Batching Plan d. Payloader (1.50 cu.m.), e. Concrete Screeder (5.5 f. Water Truck/Pump (160 g. Concrete Saw (7.5 Hp), h. Bar Cutter, Single Phas Minor Tools (5% of Labor
6,610.05 6,846.56
S
570.55 Quantity
Unit Cost
C. D. Output per hour = 57.500 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15 0.07 0.30
406.25 40,300.00 180.00
467.19 2,821.00 54.00
323+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond i. Pipe Sleeve, 2" dia. j. Grease/Tar
3,342.19 3,912.73 352.15 313.02 228.89 4,806.79
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
se
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
69.42 50.18 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
236.51
S
Amount
Nam B. Equipment
1.00 1.00 1.00 1.00 0.25
2,824.90 1,652.00 561.00 936.00 2,450.00
2,824.90 1,652.00 561.00 936.00 612.50 23.65
a. Concrete Vibrator b. Concrete Screeder (5.5 c. Concrete Saw (7.5 Hp), d. Bar Cutter, Single Phas Minor Tools (5% of Labor
6,610.05 6,846.56
S
570.55 Quantity
Unit Cost
C. D. Output per hour = 57.5 sq E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15 0.10 0.30
406.25 44,000.00 180.00
467.19 4,400.00 54.00
325+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Ready Mix Concrete, 35 f. Concrete Saw (diamond g. Pipe Sleeve, 1" dia. h. Grease/Tar
4,921.19 5,491.73 494.26 439.34 321.27 6,746.60
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
x Surface Course
Item No./Description Unit of Measurement Output per hour
No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
69.42 50.18 116.91
Hourly Rate
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
236.51
S
Amount
Nam B. Equipment
1.00 1.00 1.00 0.25
2,824.90 1,652.00 561.00 2,450.00
2,824.90 1,652.00 561.00 612.50 23.65
a. Transit Mixer (5 cu.m.) b. Concrete Vibrator c. Concrete Batching Plan d. Payloader (1.50 cu.m.), e. Concrete Screeder (5.5 f. Water Truck/Pump (160 g. Concrete Saw (7.5 Hp), h. Bar Cutter, Single Phas Minor Tools (5% of Labor
5,674.05 5,910.56
S
492.55 Quantity
Unit Cost
C. D. Output per hour = 53.67 s E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.15
406.25
467.19
327+32
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond i. Pipe Sleeve, 2" dia. j. Grease/Tar
467.19 959.73 86.38 76.78 56.14 1,179.03
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
306(2)
Designation
r
Bituminous Material for Bituminous Road Mix Surface Course m.t. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 3
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
1.00
936.00
Unit
Quantity
Unit Cost
m.t.
1.05
40,300.00
Sub - Total for A Name and Capacity
utor, 10 ft. wide (5 tons)
Sub - Total for B Total (A + B) = 1.0000 m.t Name and Specification
329+32
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
307
Bituminous Plant Mix Surface Course-General (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
(80 Hp), NF220BIIVDM
1
1.00
1,833.00
e Roller (10 m.t.) Roller (10.1 m.t.), CC421 12 cu.yd.) Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
1 1 2 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00
561.00 1,652.00 1,420.00 4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.00981 0.041 0.010 0.130
44,000.00 650.00 650.00 240.56
Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
Sub - Total for A Name and Capacity
Sub - Total for B Total (A + B) = 171.300 sq.m Name and Specification
aterial (8%) and (79%) 8 (19%)
331+32
L
1.165
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
308(a)
Cold Asphalt Plant Mix (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
(80 Hp), NF220BIIVDM
1
1.00
1,833.00
e Roller (10 m.t.) Roller (10.1 m.t.), CC421 12 cu.yd.) Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
1 1 2 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00
561.00 1,652.00 1,420.00 4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.01226 0.041 0.01 0.13
44,000.00 650.00 650.00 240.56
Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
Sub - Total for A Name and Capacity
Sub - Total for B Total (A + B) = 171.300 sq.m Name and Specification
halt (10%) and (79%) 8 (19%)
333+32
L
1.165
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
308(b)
Cold Asphalt Plant Mix (50mm thk.) sq.m. 171.30
Designation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
(80 Hp), NF220BIIVDM
1
1.00
1,833.00
e Roller (10 m.t.) Roller (10.1 m.t.), CC421 12 cu.yd.) Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
1 1 2 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00
561.00 1,652.00 1,420.00 4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.00858 0.0488 0.01 0.13
40,300.00 650.00 650.00 240.56
Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
Sub - Total for A Name and Capacity
Sub - Total for B Total (A + B) = 171.300 sq.m Name and Specification
ack Asphalt (7%) and (79%)
335+32
L
1.165
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
309
Bituminous Plant Mix (Stockpile Maintenance Mixture) sq.m. 171.30
Designation Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
2
1.00
1,420.00
1 1 1
1.00 1.00 1.00
4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.01226 0.041 0.01 0.13
40,300.00 650.00 650.00 240.56
Sub - Total for A Name and Capacity
12 cu. yd)
Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
Sub - Total for B Total (A + B) = 171.300 sq.m Name and Specification
ack Asphalt (10%) and (79%)
337+32
L
1.165
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
310(a.1)
Designation
r
Bituminous Concrete Surface Course (30mm thk.) sq.m. 285.51 No. of Person
No. of Hours
Hourly Rate
1 4 8
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1.00 1.00 1.00 1.00
1,833.00 561.00 1,652.00 2,450.00
Unit
Quantity
Unit Cost
m.t.
0.074
4,500.00
Sub - Total for A Name and Capacity
(80 Hp), NF220BIIVDM e Roller (10 m.t.) Roller (10.1 m.t.), CC421 ump (16000L) % of Labor Cost)
Sub - Total for B Total (A + B) = 285.51 sq.m Name and Specification
ncrete Surface Course m (w/ 5% wastage)
339+32
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
310(a.2)
Designation
r
Bituminous Concrete Surface Course (40mm thk.) sq.m. 214.13 No. of Person
No. of Hours
Hourly Rate
1 4 8
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1.00 1.00 1.00 1.00
1,833.00 561.00 1,652.00 2,450.00
Unit
Quantity
Unit Cost
m.t.
0.098
4,500.00
Sub - Total for A Name and Capacity
(80 Hp), NF220BIIVDM e Roller (10 m.t.) Roller (10.1 m.t.), CC421 ump (16000L) % of Labor Cost )
Sub - Total for B Total (A + B) = 214.13 sq.m Name and Specification
ncrete Surface Course m (w/ 5% wastage)
341+32
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
310(a.3)
Designation
r
Bituminous Concrete Surface Course (50mm thk.) sq.m. 171.30 No. of Person
No. of Hours
Hourly Rate
1 4 8
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1 1
1.00 1.00 1.00 1.00
1,833.00 561.00 1,652.00 2,450.00
Unit
Quantity
Unit Cost
m.t.
0.123
4,500.00
Sub - Total for A Name and Capacity
(80 Hp), NF220BIIVDM e Roller (10 m.t.) Roller (10.1 m.t.), CC421 ump (16000L) % of Labor Cost)
Sub - Total for B Total (A + B) = 171.300 sq.m Name and Specification
ncrete Surface Course m (w/ 5% wastage)
343+32
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
310(b.1)
Bituminous Concrete Surface Course (30mm thk.) sq.m. 285.51
Designation Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1 2 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00
1,833.00 561.00 1,652.00 1,420.00 4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.00588 0.025 0.006 0.078
40,300.00 650.00 650.00 240.56
Sub - Total for A Name and Capacity
(80 Hp), NF220BIIVDM e Roller (10 m.t.) Roller (10.1 m.t.), CC421 12 cu.yd.) Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
Sub - Total for B Total (A + B) = 285.51 sq.m Name and Specification
and (79%)
345+32
L
0.699
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
310(b.2)
Bituminous Concrete Surface Course (40mm thk.) sq.m. 214.13
Designation Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1 2 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00
1,833.00 561.00 1,652.00 1,420.00 4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.00785 0.033 0.008 0.104
40,300.00 650.00 650.00 240.56
Sub - Total for A Name and Capacity
(80 Hp), NF220BIIVDM e Roller (10 m.t.) Roller (10.1 m.t.), CC421 12 cu.yd.) Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
Sub - Total for B Total (A + B) = 214.13 sq.m Name and Specification
and (79%)
347+32
L
0.932
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
310(b.3)
Bituminous Concrete Surface Course (50mm thk.) sq.m. 171.30
Designation Laying & Compaction Engineer
ratory Technician
Batching/ Mixing operation
No. of Person
No. of Hours
Hourly Rate
1 4 8 1 1 1 1 4
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1 2 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00
1,833.00 561.00 1,652.00 1,420.00 4,286.63 2,450.00 1,733.00
Unit
Quantity
Unit Cost
m.t cu.m. cu.m. bag
0.00981 0.041 0.01 0.13
40,300.00 650.00 650.00 240.56
Sub - Total for A Name and Capacity
(80 Hp), NF220BIIVDM e Roller (10 m.t.) Roller (10.1 m.t.), CC421 12 cu.yd.) Plant ( 60-80 TPH) ump (16000L) 0 cu.m.), LX80-2C % of Labor Cost)
Sub - Total for B Total (A + B) = 171.300 sq.m Name and Specification
and (79%)
349+32
L
1.165
240.56
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.1
Designation
r
PCC Pavement (Plain) - Conventional Method, 150mm thk. sq.m. 107.33 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
4 2 1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.10
1,318.00 91.25 1,759.50 1,733.00 545.00 2,450.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.33 0.29 0.12 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
5 cu.m.)
hing Plant (30 cu.m.) 0 cu.m.), LX80-2C eder (5.5 Hp) ump (16000L) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 107.33 sq.m Name and Specification
351+32
(diamond blade 14" dia)
cu.m. cu.m. bag pc. m L
0.0825 0.15 1.43 0.00015 0.0078 0.0015
850.00 650.00 220.00 8,000.00 34.33 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.1.1
Designation
r
PCC Pavement (Plain) - Conventional Method, 150mm thk. sq.m. 107.33 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
2 1 1 1
1.00 1.00 1.00 0.10
91.25 545.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.33 0.29 0.12 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
eder (5.5 Hp) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 107.33 sq.m Name and Specification
353+32
ncrete, 3500 psi (diamond blade 14" dia)
cu.m. pc. m L
0.15 0.00015 0.0078 0.0015
850.00 8,000.00 34.33 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.2
Designation
r
PCC Pavement (Plain) - Conventional Method, 200mm thk. sq.m. 80.50 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
4 2 1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.10
1,318.00 91.25 1,759.50 1,733.00 545.00 2,450.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.39 0.29 0.12 0.46
36.00 75.00 50.00 56.00
Sub - Total for A Name and Capacity
5 cu.m.)
hing Plant (30 cu.m.) 0 cu.m.), LX80-2C eder (5.5 Hp) ump (16000L) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 80.500 sq.m Name and Specification
355+32
(diamond blade 14" dia) 1/2" dia.
cu.m. cu.m. bag pc. m L
0.11 0.20 1.90 0.00015 0.0086 0.0056
500.00 600.00 240.00 8,000.00 97.00 210.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.2.1
Designation
r
PCC Pavement (Plain) - Conventional Method, 200mm thk. sq.m. 80.50 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
2 1 1 1
1.00 1.00 1.00 0.10
91.25 545.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.39 0.29 0.12 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
eder (5.5 Hp) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 80.5 sq.m Name and Specification
357+32
ncrete, 3500 psi (diamond blade 14" dia)
cu.m. pc. m L
0.2 0.00015 0.0086 0.0056
850.00 8,000.00 34.33 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.3
Designation
r
PCC Pavement (Plain) - Conventional Method, 230mm thk. sq.m. 70.00 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
4 2 1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.10
1,318.00 91.25 1,759.50 1,733.00 545.00 2,450.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.43 0.29 0.12 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
5 cu.m.)
hing Plant (30 cu.m.) 0 cu.m.), LX80-2C eder (5.5 Hp) ump (16000L) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 70.0000 sq.m Name and Specification
359+32
(diamond blade 14")
cu.m. cu.m. bag pc. m L
0.1265 0.23 2.19 0.00015 0.0071 0.0087
850.00 650.00 220.00 8,000.00 97.00 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.3.1
Designation
r
PCC Pavement (Plain) - Conventional Method, 230mm thk. sq.m. 70.00 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
2 1 1 1
1.00 1.00 1.00 0.10
91.25 545.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.43 0.29 0.12 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
eder (5.5 Hp) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 70. sq.m Name and Specification
361+32
ncrete, 3500 psi (diamond blade 14" dia)
cu.m. pc. m L
0.23 0.00015 0.0071 0.0087
850.00 8,000.00 34.33 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.4
Designation
r
PCC Pavement (Plain) - Conventional Method, 250mm thk. sq.m. 64.40 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
4 2 1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.10
1,318.00 91.25 1,759.50 1,733.00 545.00 2,450.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.45 0.29 0.15 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
5 cu.m.)
hing Plant (30 cu.m.) 0 cu.m.), LX80-2C eder (5.5 Hp) ump (16000L) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 64.400 sq.m Name and Specification
363+32
(diamond blade 14")
cu.m. cu.m. bag pc. m L
0.1375 0.25 2.38 0.00015 0.0078 0.0095
850.00 650.00 220.00 8,000.00 97.00 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.4.1
Designation
r
PCC Pavement (Plain) - Conventional Method, 250mm thk. sq.m. 64.40 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
2 1 1 1
1.00 1.00 1.00 0.10
91.25 545.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.45 0.29 0.15 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
eder (5.5 Hp) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 64.4 sq.m Name and Specification
365+32
ncrete, 3500 psi (diamond blade 14" dia)
cu.m. pc. m L
0.25 0.00015 0.0078 0.0095
850.00 8,000.00 34.33 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.5
Designation
r
PCC Pavement (Plain) - Conventional Method, 280mm thk. sq.m. 57.50 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
4 2 1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.10
1,318.00 91.25 1,759.50 1,733.00 545.00 2,450.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.50 0.29 0.17 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
5 cu.m.)
hing Plant (30 cu.m.) 0 cu.m.), LX80-2C eder (5.5 Hp) ump (16000L) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 57.500 sq.m Name and Specification
367+32
(diamond blade 14")
cu.m. cu.m. bag pc. m L
0.154 0.28 2.66 0.00015 0.0078 0.0078
850.00 650.00 220.00 8,000.00 97.00 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.5.1
Designation
r
PCC Pavement (Plain) - Conventional Method, 280mm thk. sq.m. 57.50 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
2 1 1 1
1.00 1.00 1.00 0.10
91.25 545.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.50 0.29 0.17 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
eder (5.5 Hp) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 57.5 sq.m Name and Specification
369+32
ncrete, 3500 psi (diamond blade 14" dia)
cu.m. pc. m L
0.28 0.00015 0.0078 0.0078
850.00 8,000.00 34.33 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
311(1)a.6
Designation
r
PCC Pavement (Plain) - Conventional Method, 300mm thk. sq.m. 53.67 No. of Person
No. of Hours
Hourly Rate
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
4 2 1 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.10
1,318.00 91.25 1,759.50 1,733.00 545.00 2,450.00 32.63 219.75
Unit
Quantity
Unit Cost
kg. L L m
0.55 0.29 0.18 0.46
40.00 28.00 44.00 50.00
Sub - Total for A Name and Capacity
5 cu.m.)
hing Plant (30 cu.m.) 0 cu.m.), LX80-2C eder (5.5 Hp) ump (16000L) (7.5 Hp), 14" Blade Ø gle Phase of Labor Cost)
Sub - Total for B Total (A + B) = 53.67 sq.m Name and Specification
371+32
(diamond blade 14")
cu.m. cu.m. bag pc. m L
0.165 0.30 2.85 0.00015 0.0094 0.0094
850.00 650.00 220.00 8,000.00 97.00 300.00
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)a.6.1
Designation A. Labor
69.42 50.18 116.91
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
236.51
Sub - Total for A
Amount
Name and Capacity B. Equipment
936.00
a. Concrete Vibrator b. Concrete Screeder (5.5 Hp) c. Concrete Saw (7.5 Hp), 14" Blade Ø d. Bar Cutter, Single Phase Minor Tools (5% of Labor Cost)
936.00 1,172.51 1,172.51
Sub - Total for B C. Total (A + B) D. Output per hour = 53.67 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
42,315.00
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
373+32
PCC Pavement (Plain) sq.m. 53.67
e. Ready Mix Concrete, 3500 psi f. Concrete Saw (diamond blade 14" dia) g. Pipe Sleeve, 1" dia. h. Grease/Tar
42,315.00 43,487.51 3,913.88 3,479.00 2,544.02 53,424.41
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.1
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 581.90
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00
a. Concrete Batching Plant (30 cu.m.)
561.00 1,652.00 2,840.00 4,286.63 2,450.00 1,733.00 58.19
b. Concrete Paver, COM, III, FOUR-TRACK c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck/Pump (16000L) f. Concrete Saw (7.5 Hp), 14" Blade Ø g. Concrete Vibrator h. Bar Cutter, Single Phase
15,413.82 15,995.72 93.38
Sub - Total for B C. Total (A + B) D. Output per hour = 90.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
431.64 26.65 6.50 31.27
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand
375+32
PCC Pavement (Plain) sq.m. 90.00
280.25
776.32 869.69 78.27 69.58 50.88 1,068.42
e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.1.1
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 581.90
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00
a. Concrete Paver, COM, III, FOUR-TRACK
561.00 1,652.00 2,840.00 4,286.63 2,450.00 1,733.00 58.19
b. Concrete Screeder (5.5 Hp) d. Concrete Vibrator d. Bar Cutter, Single Phase
15,413.82 15,995.72 93.38
Sub - Total for B C. Total (A + B) D. Output per hour = 100.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
539.44 26.65 6.50 31.27
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Ready Mix Concrete, 3500 psi
377+32
PCC Pavement (Plain) sq.m. 100.00
280.25
884.12 977.49 87.97 78.20 57.18 1,200.85
e. Concrete Saw (diamond blade 14" dia) f. Pipe Sleeve, 1" dia. g. Grease/Tar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.2
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 581.90
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00
a. Concrete Batching Plant (30 cu.m.)
561.00 1,652.00 2,840.00 4,286.63 2,450.00 1,733.00 58.19
b. Concrete Paver, COM, III, FOUR-TRACK c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck/Pump (16000L) f. Concrete Saw (7.5 Hp), 14" Blade Ø g. Concrete Vibrator h. Bar Cutter, Single Phase
15,413.82 15,995.72 93.38
Sub - Total for B C. Total (A + B) D. Output per hour = 82.800 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
345.77 31.72 6.50 31.27
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand
379+32
PCC Pavement (Plain) sq.m. 82.80
280.25
695.52 788.90 71.00 63.11 46.15 969.16
e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.2.1
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 581.90
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
2,840.00
a. Concrete Paver, COM, III, FOUR-TRACK
4,286.63 2,450.00 1,733.00 58.19
b. Concrete Screeder (5.5 Hp) d. Concrete Vibrator d. Bar Cutter, Single Phase
11,367.82 11,949.72 69.76
Sub - Total for B C. Total (A + B) D. Output per hour = 100.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
494.08 26.65 6.50 31.27
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Ready Mix Concrete, 3500 psi
381+32
PCC Pavement (Plain) sq.m. 100.00
280.25
838.75 908.51 81.77 72.68 53.15 1,116.11
e. Concrete Saw (diamond blade 14" dia) f. Pipe Sleeve, 1" dia. g. Grease/Tar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.3
Designation A. Labor
69.42 200.72 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
581.90
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00 561.00 1,652.00 2,450.00 58.19
6,554.19 7,136.09 24.99
a. Concrete Batching Plant (30 cu.m.) b. Concrete Paver, COM, III, FOUR-TRACK c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck/Pump (16000L) f. Concrete Saw (7.5 Hp), 14" Blade Ø g. Concrete Vibrator h. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 73.93 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
333.00
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand
383+32
PCC Pavement (Plain) sq.m. 73.93
e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
333.00 357.99 32.22 28.64 20.94 439.80
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.3.1
Designation A. Labor
69.42 200.72 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
581.90
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00 561.00 1,652.00 2,450.00 58.19
6,554.19 7,136.09 33.33
a. Concrete Paver, COM, III, FOUR-TRACK b. Concrete Screeder (5.5 Hp) d. Concrete Vibrator d. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 100.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
441.00
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Ready Mix Concrete, 3500 psi
385+32
PCC Pavement (Plain) sq.m. 100.00
e. Concrete Saw (diamond blade 14" dia) f. Pipe Sleeve, 1" dia. g. Grease/Tar
441.00 474.33 42.69 37.95 27.75 582.71
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.4
Designation A. Labor
69.42 200.72 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
581.90
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00 561.00 1,652.00 2,450.00 58.19
6,554.19 7,136.09 41.66
a. Concrete Batching Plant (30 cu.m.) b. Concrete Paver, COM, III, FOUR-TRACK c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck/Pump (16000L) f. Concrete Saw (7.5 Hp), 14" Blade Ø g. Concrete Vibrator h. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 69.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
553.50
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Sand
387+32
PCC Pavement (Plain) sq.m. 69.00
e. Gravel f. Cement g. Concrete Saw (diamond blade 14") h. Pipe Sleeve, 2" dia. i. Grease/Tar
553.50 595.16 53.56 47.61 34.82 731.15
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)b.4.1
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 512.48
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00 561.00 1,652.00 2,840.00 4,286.63 2,450.00 1,733.00 51.25
15,406.88 15,919.36 55.76
a. Concrete Paver, COM, III, FOUR-TRACK b. Concrete Screeder (5.5 Hp) d. Concrete Vibrator d. Bar Cutter, Single Phase
Sub - Total for B C. Total (A + B) D. Output per hour = 100.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
236.96 16.25 3.90 18.76
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Ready Mix Concrete, 3500 psi
389+32
PCC Pavement (Plain) sq.m. 100.00
168.15
e. Concrete Saw (diamond blade 14" dia) f. Pipe Sleeve, 1" dia. g. Grease/Tar
444.03 499.79 44.98 39.98 29.24 613.99
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)c
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 581.90
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00 561.00 1,652.00 2,840.00 4,286.63 2,450.00 1,733.00 58.19
15,413.82 15,995.72 74.70
a. One Bagger Mixer b. Water Truck/Pump (16000L) c. Concrete Vibrator d. Bar Cutter, Single Phase e. Concrete Saw (7.5 Hp), 14" Blade Ø Minor Tools (5% of Labor Cost )
Sub - Total for B C. Total (A + B) D. Output per hour = 12.0000 sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
316.36 21.45 5.20 25.02
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
391+32
PCC Pavement (Plain) sq.m. 12.00
224.20
592.23 666.93 60.02 53.35 39.02 819.32
e. Sand f. Gravel g. Cement h. Concrete Saw (diamond blade 14") i. Pipe Sleeve, 1" dia. j. Grease/Tar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(1)c.1
Designation A. Labor
69.42 200.72 311.76 0.00 0.00 0.00 0.00 0.00 581.90
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
Sub - Total for A
Amount
Name and Capacity B. Equipment
1,833.00 561.00 1,652.00 2,840.00 4,286.63 2,450.00 1,733.00 58.19
15,413.82 15,995.72 93.38
a. Concrete Vibrator b. Concrete Saw (7.5 Hp), 14" Blade Ø c. Bar Cutter, Single Phase Minor Tools (5% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 12. sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
395.34 26.65 6.50 31.27
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
393+32
PCC Pavement (Plain) sq.m. 12.00
280.25
740.02 833.40 75.01 66.67 48.75 1,023.83
e. Ready Mix Concrete, 3500 psi f. Concrete Saw (diamond blade 14" dia) g. Pipe Sleeve, 1" dia. h. Grease/Tar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(2)
Designation A. Labor
69.42 200.72 467.64
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
737.78
Sub - Total for A
Amount
Name and Capacity B. Equipment
5,272.00 182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 21.98 36.89
a. Concrete Batching Plant (30 cu.m.) b. Concrete Screeder (5.5 Hp) c. Transit Mixer (5 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Water Truck/Pump (16000L) f. Concrete Vibrator g. Bar Cutter, Single Phase h. Bar Bender Minor Tools (5% of Labor)
12,033.49 12,771.27
Sub - Total for B C. Total (A + B) D. Output per hour = 6.0000 sq.m E. Direct Unit Cost (C ÷ D)
118.99 Amount
Name and Specification F. Materials
13.20 8.12 5.28 23.00
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
395+32
PCC Pavement (Reinforc sq.m. 6.00
70.13 97.50 314.60 1.20 0.27 0.45
533.74 652.73 58.75 52.22 38.18 801.88
e. Sand f. Gravel g. Cement h. # 16 GI Tie Wire (2% of RSB)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
DETAILE Item No./Description Unit of Measurement Output per hour
: : :
Amount
311(2)1
Designation A. Labor
69.42 200.72 467.64
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
737.78
Sub - Total for A
Amount
Name and Capacity B. Equipment
182.50 545.00 32.63 21.98 36.89
818.99 1,556.77 14.50
a. Concrete Vibrator b. Concrete Saw (7.5 Hp), 14" Blade Ø c. Bar Cutter, Single Phase d. Bar Bender Minor Tools (5% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 6. sq.m E. Direct Unit Cost (C ÷ D)
Amount
Name and Specification F. Materials
13.20 8.12 5.28 23.00
a. Reinforcing Steel Bar b. Curing Compound c. Asphalt Sealant d. Steel Forms (Rental)
397+32
PCC Pavement (Reinforc sq.m. 6.00
127.50 1.20 0.27 0.45
179.02 193.52 17.42 15.48 11.32 237.74
e. Ready Mix Concrete, 3500 psi f. # 16 GI Tie Wire (2% of RSB)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
928-5
Amount
69.42 200.72 467.64
737.78 Amount
5,272.00 182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 21.98 36.89
12,033.49 12,771.27 158.65 Amount
14.04 21.75 6.00 25.76
399+32
55.00 120.00 456.00 1.20 0.83 1.18
701.76 860.41 77.44 68.83 50.33 1,057.01
928-5
Amount
69.42 200.72 467.64
737.78 Amount
182.50 545.00 32.63 21.98 36.89
818.99 1,556.77 19.34 Amount
15.60 8.12 5.28 23.00
401+32
170.00 1.20 0.30 1.68
225.18 244.51 22.01 19.56 14.30 300.39
928-5
Amount
69.42 200.72 467.64
737.78 Amount
5,272.00 182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 21.98 36.89
12,033.49 12,771.27 182.45 Amount
17.20 8.12 5.28 23.00
403+32
107.53 149.50 481.80 1.20 0.69 2.61
796.92 979.37 88.14 78.35 57.29 1,203.16
928-5
Amount
69.42 200.72 467.64
737.78 Amount
182.50 545.00 32.63 21.98 36.89
818.99 1,556.77 22.24 Amount
17.20 8.12 5.28 23.00
405+32
195.50 1.20 0.24 2.61
253.15 275.39 24.79 22.03 16.11 338.32
928-5
Amount
69.42 200.72 467.64
737.78 Amount
5,272.00 182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 21.98 36.89
12,033.49 12,771.27 198.31 Amount
18.00 8.12 6.60 23.00
407+32
116.88 162.50 523.60 1.20 0.76 2.85
863.50 1,061.81 95.56 84.95 62.12 1,304.44
928-5
Amount
69.42 200.72 467.64
737.78 Amount
182.50 545.00 32.63 21.98 36.89
818.99 1,556.77 24.17 Amount
18.00 8.12 6.60 23.00
409+32
212.50 1.20 0.27 2.85
272.54 296.71 26.70 23.74 17.36 364.51
928-5
Amount
69.42 200.72 467.64
737.78 Amount
5,272.00 182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 21.98 36.89
12,033.49 12,771.27 222.11 Amount
20.00 8.12 7.48 23.00
411+32
130.90 182.00 585.20 1.20 0.76 2.34
961.00 1,183.11 106.48 94.65 69.21 1,453.45
928-5
Amount
69.42 200.72 467.64
737.78 Amount
182.50 545.00 32.63 21.98 36.89
818.99 1,556.77 27.07 Amount
20.00 8.12 7.48 23.00
413+32
238.00 1.20 0.27 2.34
300.41 327.48 29.47 26.20 19.16 402.31
928-5
Amount
69.42 200.72 467.64
737.78 Amount
5,272.00 182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 21.98 36.89
12,033.49 12,771.27 237.96 Amount
22.00 8.12 7.92 23.00
415+32
140.25 195.00 627.00 1.20 0.91 2.82
1,028.22 1,266.18 113.96 101.29 74.07 1,555.50
928-5
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Conventional Method, 300mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 467.64
737.78 No of Units
No. of Hours
Hourly Rate
Amount
2
1.00
91.25
182.50
1 1 1
1.00 1.00 0.10
545.00 32.63 219.75
545.00 32.63 21.98 36.89
818.99 1,556.77 29.01 Unit
Quantity
Unit Cost
Amount
kg. L L m
0.55 0.29 0.18 0.46
40.00 28.00 44.00 50.00
22.00 8.12 7.92 23.00
417+32
cu.m. pc. m L
0.3 0.00015 0.0094 0.0094
850.00 8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
255.00 1.20 0.32 2.82
320.38 349.39 31.45 27.95 20.44 429.22
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 230mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1
1.00
1,759.50
1,759.50
1 4 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 0.10 0.10
6,765.00 1,318.00 1,733.00 2,450.00 32.63 91.25 219.75
6,765.00 5,272.00 1,733.00 2,450.00 32.63 9.13 21.98
18,043.23 18,703.07 207.81 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.43 0.29 0.12 0.1265
40.00 28.00 44.00 850.00
17.20 8.12 5.28 107.53
419+32
cu.m. bag pc. m L
0.23 2.19 0.00015 0.0071 0.0087
650.00 220.00 8,000.00 97.00 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
149.50 481.80 1.20 0.69 2.61
773.92 981.74 88.36 78.54 57.43 1,206.06
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 230mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1
1.00
6,765.00
6,765.00
1 1 1
1.00 0.10 0.10
545.00 91.25 219.75
545.00 9.13 21.98
7,341.10 8,000.94 80.01 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.43 0.29 0.12 0.23
40.00 28.00 44.00 850.00
17.20 8.12 5.28 195.50
421+32
pc. m L
0.00015 0.0071 0.0087
8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
1.20 0.24 2.61
230.15 310.16 27.91 24.81 18.14 381.04
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 250mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1
1.00
1,759.50
1,759.50
1 4 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 0.10 0.10
6,765.00 1,318.00 1,733.00 2,450.00 32.63 91.25 219.75
6,765.00 5,272.00 1,733.00 2,450.00 32.63 9.13 21.98
18,043.23 18,703.07 225.88 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.45 0.29 0.15 0.1375
40.00 28.00 44.00 850.00
18.00 8.12 6.60 116.88
423+32
cu.m. bag pc. m L
0.25 2.38 0.00015 0.0078 0.0095
650.00 220.00 8,000.00 97.00 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
162.50 523.60 1.20 0.76 2.85
840.50 1,066.38 95.97 85.31 62.38 1,310.05
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 250mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1
1.00
6,765.00
6,765.00
1 1 1
1.00 0.10 0.10
545.00 91.25 219.75
545.00 9.13 21.98
7,341.10 8,000.94 80.01 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.45 0.29 0.15 0.25
40.00 28.00 44.00 850.00
18.00 8.12 6.60 212.50
425+32
pc. m L
0.00015 0.0078 0.0095
8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
1.20 0.27 2.85
249.54 329.55 29.66 26.36 19.28 404.85
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 280mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1 1 4 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 0.10 0.10
1,759.50 6,765.00 1,318.00 1,733.00 2,450.00 32.63 91.25 219.75
1,759.50 6,765.00 5,272.00 1,733.00 2,450.00 32.63 9.13 21.98
18,043.23 18,703.07 252.98 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.50 0.29 0.17 0.154
40.00 28.00 44.00 850.00
20.00 8.12 7.48 130.90
427+32
cu.m. bag pc. m L
0.28 2.66 0.00015 0.0078 0.0078
650.00 220.00 8,000.00 97.00 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
182.00 585.20 1.20 0.76 2.34
938.00 1,190.98 107.19 95.28 69.67 1,463.12
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 280mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1 1 1 1
1.00 1.00 0.10 0.10
6,765.00 545.00 91.25 219.75
6,765.00 545.00 9.13 21.98
7,341.10 8,000.94 80.01 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.50 0.29 0.17 0.28
40.00 28.00 44.00 850.00
20.00 8.12 7.48 238.00
429+32
pc. m L
0.00015 0.0078 0.0078
8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
1.20 0.27 2.34
277.41 357.42 32.17 28.59 20.91 439.09
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 300mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1 1 4 1 1 1 1 1
1.00 1.00 1.00 1.00 1.00 1.00 0.10 0.10
1,759.50 6,765.00 1,318.00 1,733.00 2,450.00 32.63 91.25 219.75
1,759.50 6,765.00 5,272.00 1,733.00 2,450.00 32.63 9.13 21.98
18,043.23 18,703.07 271.06 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.55 0.29 0.18 0.165
40.00 28.00 44.00 850.00
22.00 8.12 7.92 140.25
431+32
cu.m. bag pc. m L
0.30 2.85 0.00015 0.0094 0.0094
650.00 220.00 8,000.00 97.00 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
195.00 627.00 1.20 0.91 2.82
1,005.22 1,276.28 114.87 102.10 74.66 1,567.91
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Using Concrete Paver, 300mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 10
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 389.70
659.84 No of Units
No. of Hours
Hourly Rate
Amount
1 1 1 1
1.00 1.00 0.10 0.10
6,765.00 545.00 91.25 219.75
6,765.00 545.00 9.13 21.98
7,341.10 8,000.94 80.01 Unit
Quantity
Unit Cost
Amount
kg. L L cu.m.
0.55 0.29 0.18 0.3
40.00 28.00 44.00 850.00
22.00 8.12 7.92 255.00
433+32
pc. m L
0.00015 0.94 0.94
8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
1.20 32.27 282.00
608.51 688.52 61.97 55.08 40.28 845.85
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Conventional Method, 150mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 8 16
1.00 1.00 1.00
69.42 50.18 38.97
69.42 401.44 623.52
1,094.38 No of Units
No. of Hours
Hourly Rate
Amount
1 1 2 1 1
1.00 0.05 1.00 0.05 0.10
172.00 2,450.00 91.25 219.75 32.63
172.00 122.50 182.50 10.99 3.26 54.72
545.97 1,640.35 136.70 Unit
Quantity
Unit Cost
Amount
kg. L L m
0.33 0.29 0.12 0.46
40.00 28.00 44.00 50.00
13.20 8.12 5.28 23.00
435+32
cu.m. cu.m. bag pc. m L
0.0825 0.15 1.43 0.00015 0.0078 0.0015
850.00 650.00 220.00 8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
70.13 97.50 314.60 1.20 0.27 0.45
533.74 670.44 60.34 53.64 39.22 823.63
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Plain) - Conventional Method, 150mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 8 16
1.00 1.00 1.00
69.42 50.18 38.97
69.42 401.44 623.52
1,094.38 No of Units
No. of Hours
Hourly Rate
Amount
2 1 1
1.00 0.05 0.10
91.25 32.63 219.75
182.50 1.63 21.98 54.72
260.83 1,355.21 112.93 Unit
Quantity
Unit Cost
Amount
kg. L L m
0.33 0.29 0.12 0.46
40.00 28.00 44.00 50.00
13.20 8.12 5.28 23.00
437+32
cu.m. pc. m L
0.15 0.00015 0.0078 0.0015
850.00 8,000.00 34.33 300.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
127.50 1.20 0.27 0.45
179.02 291.95 26.28 23.36 17.08 358.66
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Reinforced), 300mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 467.64
737.78 No of Units
No. of Hours
Hourly Rate
Amount
1 1 2 1 1 1 1 1
0.10 0.10 0.10 0.10 0.10 0.10 0.25 0.25
1,759.50 545.00 1,318.00 1,733.00 2,450.00 91.25 219.75 351.50
175.95 54.50 263.60 173.30 245.00 9.13 54.94 87.88 36.89
1,101.18 1,838.96 306.49 Unit
Quantity
Unit Cost
Amount
kg. L L m
54.21 0.29 0.18 0.46
40.00 28.00 44.00 50.00
2,168.40 8.12 7.92 23.00
439+32
cu.m. cu.m. bag kg.
0.1650 0.30 2.85 1.084
850.00 650.00 220.00 47.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
140.25 195.00 627.00 50.95
3,220.64 3,527.13 317.44 282.17 206.34 4,333.08
DETAILED UNIT PRICE ANALYSIS (DUPA)
vement (Reinforced), 300mm thk.
No. of Person
No. of Hours
Hourly Rate
Amount
1 4 12
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 467.64
737.78 No of Units
No. of Hours
Hourly Rate
Amount
1 1 1 1
0.10 0.10 0.25 0.25
91.25 32.63 219.75 351.50
9.13 3.26 54.94 87.88 36.89
192.09 929.87 154.98 Unit
Quantity
Unit Cost
Amount
kg. L L m
54.21 0.29 0.18 0.46
40.00 28.00 44.00 50.00
2,168.40 8.12 7.92 23.00
441+32
cu.m. kg.
0.30 1.084
850.00 47.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
928-5
255.00 50.95
2,513.39 2,668.37 240.15 213.47 156.10 3,278.09
443+32
928-5
445+32
928-5
447+32
928-5
449+32
928-5
451+32
928-5
453+32
928-5
455+32
928-5
457+32
928-5
459+32
928-5
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
404
Designation A.
Reinforcing Steel Bar, Grade 40 (Minor Structures) kg. 180.00 No. of Person
Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity B.
Equipment a. Bar Cutter b. Bar Bender c. Cargo Truck (9 - 10 mt)
C. D. E.
1 1 1
Sub - Total for B Total (A + B) Output per hour = 180.00000 kg Direct Unit Cost (C ÷ D) Name and Specification
F.
No of Units
Unit
Materials a. Tie Wire (2% of RSB) b. Reinforcing Steel Bar, Grade 40 (w/ 5% Wastage)
kg. kg.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
405
Designation A.
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 4 8
Installation/Removal of Formworks b. Skilled Labor c. Unskilled Labor Sub - Total for A
4 8
F.
No of Units
Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck/Pump (16000L) Minor Tools (5% of Labor)
C. D. E.
No. of Person
Labor
Name and Capacity B.
Structural Concrete Class A (Minor Structures) cu.m. 1.40
1 1 1
Sub - Total for B Total (A + B) Output per hour = 1.4000 cu.m Direct Unit Cost (C ÷ D) Name and Specification
Unit
a. Lumber, Good - 4 uses b. Marine Plywood (1/2" x 4' x 8') - 4 uses c. Assorted CWN (1kg./100 bd.ft. of Lumber) d. Cement
bd.ft. pc. kg. bag
Materials
e. Sand f. Gravel
cu.m. cu.m.
Note: *Quantities for lumber, plywood and CWN are dependent on the type of minor structure. The above-computed quantities are based on box culvert.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)
r, Grade 40 (Minor Structures)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
0.50 0.50 0.15
219.75 351.50 1,212.00
109.88 175.75 181.80
467.43 948.97 5.27 Quantity
Unit Cost
Amount
0.021 1.05
47.00 40.00
0.99 42.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
42.99 48.26 4.34 3.86 2.82 59.29
ILED UNIT PRICE ANALYSIS (DUPA)
Class A (Minor Structures)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 311.76
1.00 1.00
50.18 38.97
200.72 311.76 1,094.38
No. of Hours
Hourly Rate
Amount
1.00 1.00 0.10
172.00 91.25 2,450.00
172.00 91.25 245.00 54.72
562.97 1,657.35 1,183.82 Quantity
Unit Cost
Amount
* 70.0000 * 1.600 * 0.700 9.50
40.00 700.00 68.00 220.00
700.00 280.00 47.60 2,090.00
0.50 1.00
850.00 650.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
425.00 650.00
4,192.60 5,376.42 483.88 430.11 314.52 6,604.93
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
500(1)a
Designation
Pipe Culverts, 610mm dia. (24" Ø) m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. R.C. Pipes (610mm dia.) d. Sand Bedding/Selected Sandy Soil
bag cu.m. pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
500(1)b
Designation
Pipe Culverts, 760mm dia. (30" Ø) m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. R.C. Pipes (760mm dia.) d. Sand Bedding/Selected Sandy Soil
bag cu.m. pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
500(1)c
Designation
Pipe Culverts, 910mm dia. (36" Ø) m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. R.C. Pipes (910mm dia.) d. Sand Bedding/Selected Sandy Soil
bag cu.m. pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
500(1)d
Designation
Pipe Culverts, 1070mm dia. (42" Ø) m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. R.C. Pipes (1070mm dia.) d. Sand Bedding/Selected Sandy Soil
bag cu.m. pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
500(1)e
Designation
Pipe Culverts, 1220mm dia. (48" Ø) m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. R.C. Pipes (1220mm dia.) d. Sand Bedding/Selected Sandy Soil
bag cu.m. pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
500(1)f
Designation
Pipe Culverts, 1520mm dia. (60" Ø) m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.)
1
b. Plate Compactor (5 Hp) Minor Tools (10 % of Labor Cost)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. R.C. Pipes (1520mm dia.) d. Sand Bedding/Selected Sandy Soil
bag cu.m. pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
501(1)
Designation
Underdrain m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Plate Compactor (5 Hp)
1
Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Coarse Aggregates b. Fine Aggregates c. Filter Cloth d. 150 mm. dia. Concrete Perforated Pipe
cu.m. cu.m. sq.m. pc.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
501(2)
Designation
Blind Drain m 1.25 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Coarse Aggregates b. Fine Aggregates c. Filter Cloth
cu.m. cu.m. sq.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
501(3)
Granular Backfill filter material for Underdrains cu.m. 1.25
Designation
No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Plate Compactor (5 Hp)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Coarse Aggregates (Granular Backfill Materials) (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (D Item No./Description Unit of Measurement Output
: : :
502
Designation A. Labor
Item No.
Manhole/Catch Basin/Inlet ea. 1.00 No. of Person
Description
502(1)a Manhole (610mm dia RCPC) 502(1)b Manhole (760mm dia RCPC) 502(1)c Manhole (910mm dia RCPC) 502(1)d Manhole (1070mm dia RCPC) 502(1)e Manhole (1220mm dia RCPC) 502(2)a Inlet, Type I 502(2)b Inlet, Type I-A 502(3)a.1 Catch Basin (Single Barrel 610 mm dia RCPC) 502(3)a.2 Catch SubBasin - Total(Single for A Barrel 760 mm dia RCPC) 502(3)a.3 Catch Basin (Single Barrel 910 mm dia RCPC) 502(3)a.4 Catch (Single Barrel 1070mm dia RCPC) NameBasin and Capacity No of Units 502(3)a.5 Catch Basin (Single Barrel 1220mm dia RCPC) B. Equipment 502(3)b.1 Catch Basin (Double Barrel 610 mm dia RCPC) 502(3)b.2 Catch Basin (Double Barrel 910 mm dia RCPC) 502(3)b.3 Catch Basin (DoubleBarrel 1220 mm dia RCPC) 502(7) Adjusting Manhole, Type I-A 502(8) Adjusting Inlet, Type I and Type I-A 502(9)a Adjusting Catch Basin (Single Barrel, 610mm dia.) 502(9)b Adjusting Catch Basin (Double Barrel, 610mm dia.)
These pay items are variable in dimensions based on the actual consdition which standard estimate should be based on the standard Detailed unit Analysis (DUPA
Further, these items with unit of measure as "each" in the Blue Book is recomme component items such as Items 103(3) - Foundation Fill, 404 - Reinforcing Steel B (Minor Structures) in the Summarry of quantities in the preparation of design plan
These pay items are variable in dimensions based on the actual consdition which standard estimate should be based on the standard Detailed unit Analysis (DUPA
Further, these items with unit of measure as "each" in the Blue Book is recomme component items such as Items 103(3) - Foundation Fill, 404 - Reinforcing Steel B (Minor Structures) in the Summarry of quantities in the preparation of design plan
C. D. Output = 1.0000 ea E. Direct Unit Cost (C ÷ D)
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials/Processed Component Pay Item a. 103(3) - Foundation Fill b. 404 - Reinforcing Steel Bar c. 405 - Structural Concrete
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
cu.m. kg. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
502(4)
Concrete Covers ea. 5.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Bar Cutter c. Concrete Vibrator c. Welding Machine (300 A, Gas/Diesel Driven c. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
C. D. Output = 5.0000 ea E. Direct Unit Cost (C ÷ D)
1 1 1 1 1
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials Dimension: 1.29m x 0.57m x 0.20m w/ Flat Bar Frame a. Portland Cement b. Sand c. Gravel
bag cu.m. cu.m.
d. Reinforcing Steel Bar e. #16 GI Tie Wire (2% of RSB) f. 6mm thk. Steel Plate g. 16mm thk. Steel Plate h. 1/2" Ordinary Plywood - 2 uses i. 16mm dia. U-bolt & Knot j. Welding Rod (1 kg./2000 kg. of Steel)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
kg. kg. kg. kg. pc. set kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
502(5)
Metal Frames and Gratings pair 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment Minor Tools (10% of Labor Cost)
C. D. Output = 1.0000 pair E. Direct Unit Cost (C ÷ D)
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials a. 410mmx660mmx60mm, C.I. Cover with Frame
set
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
502(6)
Metal Frames and Covers (Circular) pair 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment Minor Tools (10% of Labor Cost)
C. D. Output = 1.0000 pair E. Direct Unit Cost (C ÷ D)
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials a. 580mm dia. C.I. Manhole Cover with Frame
set
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
503(a)
Drainage Steel Grating with Frame (675mm x 975mm set 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bar Cutter b. Welding Machine (300 A, Gas/Diesel Driven
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 set E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. 65mm x 5mm Flat Bar b. 6mm dia. x 975mm Twisted Cross Rod c. 75mm x 75mm x 9mm Angle Bar d. Welding Rod (1 kg./2000 kg. of Steel)
kg. kg. kg. kg.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
503(b)
Drainage Steel Grating with Frame (715mm x 2000mm set 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Bar Cutter b. Welding Machine (300 A, Gas/Diesel Driven
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 set E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. 65mm x 5mm Flat Bar b. 6mm dia. x 975mm Twisted Cross Rod c. 75mm x 75mm x 9mm Angle Bar d. Welding Rod (1 kg./2000 kg. of Steel)
kg. kg. kg. kg.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(1)a
Designation
Removing, Cleaning, Stockpiling Salvaged Culvert Pip m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) c. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(1)b
Designation
Removing, Cleaning, Stockpiling Salvaged Culvert Pip m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) c. Water Truck/Pump (16000L) Minor Tools (10% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(1)c
Designation
Removing, Cleaning, Stockpiling Salvaged Culvert Pip m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) c. Water Truck/Pump (16000L) Minor Tools (10% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(1)d
Designation
Removing, Cleaning, Stockpiling Salvaged Culvert Pip m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) c. Water Truck/Pump (16000L) Minor Tools (10% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(1)e
Designation
Removing, Cleaning, Stockpiling Salvaged Culvert Pip m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Boom Truck (2 - 5 mt) c. Water Truck/Pump (16000L) Minor Tools (10% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(2)a
Designation
Removing, Cleaning and Re-laying Salvaged Culvert P m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck/Pump (16000L) Minor Tools (10 % of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials
a. Portland Cement b. Sand c. Sand Bedding
bag cu.m. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(2)b
Designation
Removing, Cleaning and Re-laying Salvaged Culvert P m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck/Pump (16000L) Minor Tools (10 % of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials
a. Portland Cement b. Sand c. Sand Bedding
bag cu.m. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(2)c
Designation
Removing, Cleaning and Re-laying Salvaged Culvert P m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck/Pump (16000L) Minor Tools (10 % of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials
a. Portland Cement b. Sand c. Sand Bedding
bag cu.m. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(2)d
Designation
Removing, Cleaning and Re-laying Salvaged Culvert P m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck/Pump (16000L) Minor Tools (10 % of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials
a. Portland Cement b. Sand c. Sand Bedding
bag cu.m. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(2)e
Designation
Removing, Cleaning and Re-laying Salvaged Culvert P m 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (0.80 cu.m.) b. Plate Compactor (5 Hp) c. Water Truck/Pump (16000L) Minor Tools (10 % of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials
a. Portland Cement b. Sand c. Sand Bedding
bag cu.m. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(3)a
Designation
Cleaning Culvert Pipe in place (610mm dia.) - Half Silt m 8.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (2 - 5 mt) b. Steel Wheel w/ Nylon Rope c. Improvised Bamboo with Bucket Minor Tools (10% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 8.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(3)b
Designation
Cleaning Culvert Pipe in place (760mm dia.) - Half Silt m 5.25 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment c. Cargo Truck (9 - 10 mt) b. Steel Wheel w/ Nylon Rope c. Improvised Bamboo with Bucket Minor Tools (10% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 5.2500 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)
m dia. (24" Ø)
No. of Hours
Hourly Rate
Amount
0.44 0.44 0.44
69.42 50.18 38.97
30.54 44.16 68.59
143.29 No. of Hours
Hourly Rate
Amount
0.22 0.22
1,537.00 123.00
338.14 27.06 14.33
379.53 522.82 522.82 Quantity
Unit Cost
Amount
0.774 0.044 1.00 0.088
240.00 500.00 1,000.00 500.00
185.76 22.00 1,000.00 44.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,251.76 1,774.58 159.71 141.97 103.81 2,180.07
ILED UNIT PRICE ANALYSIS (DUPA)
m dia. (30" Ø)
No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
69.42 50.18 38.97
34.71 50.18 77.94
162.83 No. of Hours
Hourly Rate
Amount
0.25
1,537.00
384.25
0.25
123.00
30.75 16.28
431.28 594.11 594.11 Quantity
Unit Cost
Amount
0.918 0.052 1.00 0.108
220.00 850.00 1,750.00 850.00
201.96 44.20 1,750.00 91.80
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,087.96 2,682.07 241.39 214.57 156.90 3,294.93
ILED UNIT PRICE ANALYSIS (DUPA)
m dia. (36" Ø)
No. of Hours
Hourly Rate
Amount
0.57 0.57 0.57
69.42 50.18 38.97
39.57 57.21 88.85
185.63 No. of Hours
Hourly Rate
Amount
0.29
1,537.00
445.73
0.29
123.00
35.67 18.56
499.96 685.59 685.59 Quantity
Unit Cost
Amount
1.080 0.061 1.00 0.128
220.00 850.00 2,170.00 850.00
237.60 51.85 2,170.00 108.80
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,568.25 3,253.84 292.85 260.31 190.35 3,997.34
ILED UNIT PRICE ANALYSIS (DUPA)
mm dia. (42" Ø)
No. of Hours
Hourly Rate
Amount
0.67 0.67 0.67
69.42 50.18 38.97
46.51 67.24 104.44
218.19 No. of Hours
Hourly Rate
Amount
0.33
1,537.00
507.21
0.33
123.00
40.59 21.82
569.62 787.81 787.81 Quantity
Unit Cost
Amount
1.242 0.070 1.00 0.149
220.00 850.00 2,900.00 850.00
273.24 59.50 2,900.00 126.65
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
3,359.39 4,147.20 373.25 331.78 242.61 5,094.84
ILED UNIT PRICE ANALYSIS (DUPA)
mm dia. (48" Ø)
No. of Hours
Hourly Rate
Amount
0.80 0.80 0.80
69.42 50.18 38.97
55.54 80.29 124.70
260.53 No. of Hours
Hourly Rate
Amount
0.40
1,537.00
614.80
0.40
123.00
49.20 26.05
690.05 950.58 950.58 Quantity
Unit Cost
Amount
1.404 0.080 1.00 0.170
220.00 850.00 3,800.00 850.00
308.88 68.00 3,800.00 144.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4,321.38 5,271.96 474.48 421.76 308.41 6,476.60
ILED UNIT PRICE ANALYSIS (DUPA)
mm dia. (60" Ø)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.50
1,537.00
768.50
0.50
123.00
61.50 32.57
862.57 1,188.23 1,188.23 Quantity
Unit Cost
Amount
1.710 0.097 1.00 0.210
220.00 850.00 6,175.00 850.00
376.20 82.45 6,175.00 178.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
6,812.15 8,000.38 720.03 640.03 468.02 9,828.46
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
0.80 0.80
69.42 38.97
55.54 124.70
180.24 No. of Hours
Hourly Rate
Amount
0.40
123.00
49.20 18.02
67.22 247.46 247.46 Quantity
Unit Cost
Amount
0.20 0.39 2.00 1.05
900.00 850.00 275.00 230.00
180.00 331.50 550.00 241.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,303.00 1,550.46 139.54 124.04 90.70 1,904.75
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 155.88
225.30 No. of Hours
Hourly Rate
Amount
22.53
22.53 247.83 198.26 Quantity
Unit Cost
Amount
0.22 0.39 2.00
900.00 850.00 275.00
198.00 331.50 550.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,079.50 1,277.76 115.00 102.22 74.75 1,569.73
ILED UNIT PRICE ANALYSIS (DUPA)
r material for Underdrains
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 155.88
225.30 No. of Hours
Hourly Rate
Amount
1.00
123.00
123.00 22.53
145.53 370.83 296.66 Quantity
Unit Cost
Amount
1.15
900.00
1,035.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,035.00 1,331.66 119.85 106.53 77.90 1,635.95
AILED UNIT PRICE ANALYSIS (DUPA)
RCPC) RCPC) RCPC) RCPC) RCPC) RCPC) RCPC) RCPC)
No. of Hours
Hourly Rate
Amount
No. of Hours
Hourly Rate
Amount
0mm dia.) 10mm dia.)
on the actual consdition which combines component items , hence d Detailed unit Analysis (DUPA).
in the Blue Book is recommended to be broken down seperately by n Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete Class A the preparation of design plans
on the actual consdition which combines component items , hence d Detailed unit Analysis (DUPA).
in the Blue Book is recommended to be broken down seperately by n Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete Class A the preparation of design plans
Quantity
Direct
Unit Cost
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
Direct Cost
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50 0.25 0.05
172.00 219.75 148.88 371.00 2,450.00
86.00 109.88 74.44 92.75 122.50 32.57
518.13 843.79 168.76 Quantity
Unit Cost
Amount
1.43 0.075 0.15
220.00 850.00 650.00
314.60 63.75 97.50
46.46 0.93 73.58 2.97 0.33 2.00 0.04
40.00 47.00 48.00 48.00 620.00 250.00 90.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,858.40 43.71 3,531.84 71.28 102.30 250.00 1.80
6,335.18 6,503.94 585.35 520.32 380.48 7,990.09
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
69.42 50.18 38.97
34.71 25.09 19.49
79.29 No. of Hours
Hourly Rate
Amount
7.93
7.93 87.21 87.21 Quantity
Unit Cost
Amount
1.00
4,700.00
4,700.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4,700.00 4,787.21 430.85 382.98 280.05 5,881.09
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
69.42 50.18 38.97
34.71 25.09 19.49
79.29 No. of Hours
Hourly Rate
Amount
7.93
7.93 87.21 87.21 Quantity
Unit Cost
Amount
1.00
5,700.00
5,700.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
5,700.00 5,787.21 520.85 462.98 338.55 7,109.59
ILED UNIT PRICE ANALYSIS (DUPA)
ng with Frame (675mm x 975mm Sump Grating)
No. of Hours
Hourly Rate
Amount
4.00 4.00 4.00
69.42 50.18 38.97
277.68 200.72 155.88
634.28 No. of Hours
Hourly Rate
Amount
2.00 4.00
219.75 371.00
439.50 1,484.00
1,923.50 2,557.78 2,557.78 Quantity
Unit Cost
Amount
62.557 1.244 38.36 0.051
48.00 48.00 48.00 90.00
3,002.74 59.71 1,841.28 4.59
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4,908.32 7,466.10 671.95 597.29 436.77 9,172.10
ILED UNIT PRICE ANALYSIS (DUPA)
ng with Frame (715mm x 2000mm Trench Grating)
No. of Hours
Hourly Rate
Amount
8.00 8.00 8.00
69.42 50.18 38.97
555.36 401.44 311.76
1,268.56 No. of Hours
Hourly Rate
Amount
4.00 8.00
219.75 371.00
879.00 2,968.00
3,847.00 5,115.56 5,115.56 Quantity
Unit Cost
Amount
127.066 3.174 41.64 0.086
48.00 48.00 48.00 90.00
6,099.17 152.35 1,998.72 7.74
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
8,257.98 13,373.54 1,203.62 1,069.88 782.35 16,429.39
ILED UNIT PRICE ANALYSIS (DUPA)
, Stockpiling Salvaged Culvert Pipe (24" dia) - 610mm
No. of Hours
Hourly Rate
Amount
0.33 0.33 0.33
69.42 50.18 38.97
22.91 33.12 51.44
107.47 No. of Hours
Hourly Rate
Amount
0.17 0.17 0.08
1,537.00 1,017.90 2,450.00
261.29 173.04 196.00 10.75
641.08 748.55 748.55 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 748.55 67.37 59.88 43.79 919.59
ILED UNIT PRICE ANALYSIS (DUPA)
, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
No. of Hours
Hourly Rate
Amount
0.40 0.40 0.40
69.42 50.18 38.97
27.77 40.14 62.35
130.26 No. of Hours
Hourly Rate
Amount
0.20 0.20 0.10
1,537.00 1,017.90 2,450.00
307.40 203.58 245.00 13.03
769.01 899.27 899.27 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 899.27 80.93 71.94 52.61 1,104.75
ILED UNIT PRICE ANALYSIS (DUPA)
, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
69.42 50.18 38.97
34.71 50.18 77.94
162.83 No. of Hours
Hourly Rate
Amount
0.25 0.25 0.13
1,537.00 1,017.90 2,450.00
384.25 254.48 318.50 16.28
973.51 1,136.34 1,136.34 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 1,136.34 102.27 90.91 66.48 1,395.99
ILED UNIT PRICE ANALYSIS (DUPA)
, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
69.42 50.18 38.97
34.71 50.18 77.94
162.83 No. of Hours
Hourly Rate
Amount
0.25 0.25 0.13
1,537.00 1,017.90 2,450.00
384.25 254.48 318.50 16.28
973.51 1,136.34 1,136.34 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 1,136.34 102.27 90.91 66.48 1,395.99
ILED UNIT PRICE ANALYSIS (DUPA)
, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
No. of Hours
Hourly Rate
Amount
0.67 0.67 0.67
69.42 50.18 38.97
46.51 67.24 104.44
218.19 No. of Hours
Hourly Rate
Amount
0.33 0.33 0.17
1,537.00 1,017.90 2,450.00
507.21 335.91 416.50 21.82
1,281.44 1,499.63 1,499.63 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 1,499.63 134.97 119.97 87.73 1,842.29
ILED UNIT PRICE ANALYSIS (DUPA) and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
No. of Hours
Hourly Rate
Amount
0.67 0.67 0.67
69.42 50.18 38.97
46.51 67.24 104.44
218.19 No. of Hours
Hourly Rate
Amount
0.40 0.33 0.10
1,537.00 123.00 2,450.00
614.80 40.59 245.00 21.82
922.21 1,140.40 1,140.40 Quantity
Unit Cost
Amount
0.774 0.044 0.088
220.00 850.00 850.00
170.28 37.40 74.80
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
282.48 1,422.88 128.06 113.83 83.24 1,748.01
ILED UNIT PRICE ANALYSIS (DUPA) and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
No. of Hours
Hourly Rate
Amount
0.80 0.80 0.80
69.42 50.18 38.97
55.54 80.29 124.70
260.53 No. of Hours
Hourly Rate
Amount
0.48 0.40 0.12
1,537.00 123.00 2,450.00
737.76 49.20 294.00 26.05
1,107.01 1,367.54 1,367.54 Quantity
Unit Cost
Amount
0.918 0.052 0.108
220.00 850.00 850.00
201.96 44.20 91.80
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
337.96 1,705.50 153.50 136.44 99.77 2,095.21
ILED UNIT PRICE ANALYSIS (DUPA) and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.60 0.50 0.15
1,537.00 123.00 2,450.00
922.20 61.50 367.50 32.57
1,383.77 1,709.43 1,709.43 Quantity
Unit Cost
Amount
1.080 0.061 0.128
220.00 850.00 850.00
237.60 51.85 108.80
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
398.25 2,107.68 189.69 168.61 123.30 2,589.28
ILED UNIT PRICE ANALYSIS (DUPA) and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.60 0.50 0.15
1,537.00 123.00 2,450.00
922.20 61.50 367.50 32.57
1,383.77 1,709.43 1,709.43 Quantity
Unit Cost
Amount
1.242 0.070 0.149
220.00 850.00 850.00
273.24 59.50 126.65
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
459.39 2,168.82 195.19 173.51 126.88 2,664.39
ILED UNIT PRICE ANALYSIS (DUPA) and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
No. of Hours
Hourly Rate
Amount
1.33 1.33 1.33
69.42 50.18 38.97
92.33 133.48 207.32
433.13 No. of Hours
Hourly Rate
Amount
0.80 0.67 0.20
1,537.00 123.00 2,450.00
1,229.60 82.41 490.00 43.31
1,845.32 2,278.45 2,278.45 Quantity
Unit Cost
Amount
1.404 0.080 0.170
220.00 850.00 850.00
308.88 68.00 144.50
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
521.38 2,799.83 251.98 223.99 163.79 3,439.59
ILED UNIT PRICE ANALYSIS (DUPA)
e in place (610mm dia.) - Half Silted
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
783.00 300.00 200.00
783.00 300.00 200.00 32.57
1,315.57 1,641.23 205.15 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 205.15 18.46 16.41 12.00 252.03
ILED UNIT PRICE ANALYSIS (DUPA)
e in place (760mm dia.) - Half Silted
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
1,212.00 300.00 200.00
1,212.00 300.00 200.00 32.57
1,744.57 2,070.23 394.33 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 394.33 35.49 31.55 23.07 484.43
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(3)c
Designation
Cleaning Culvert Pipe in place (910mm dia.) - Half Silt m 3.75 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment c. Cargo Truck (9 - 10 mt) Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 3.7500 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(3)d
Designation
Cleaning Culvert Pipe in place (1070mm dia.) - Half Si m 2.75 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment c. Cargo Truck (9 - 10 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.75 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(3)e
Designation
Cleaning Culvert Pipe in place (1220mm dia.) - Half Si m 2.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment c. Cargo Truck (9 - 10 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 2.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
504(3)f
Designation
Cleaning Culvert Pipe in place (1520mm dia.) - Half Si m 1.50 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment c. Cargo Truck (9 - 10 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.5000 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
504(4)
Reconditioning Drainage Structures ea. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment c. Cargo Truck (9 - 10 mt)
1
b. Bamboo with Bucket - 4 uses Minor Tools (10% of Labor)
1
C. D. Output = 1.000 ea E. Direct Unit Cost (C ÷ D)
Sub - Total for B Total (A + B)
Name and Specification F. Materials
* If some repair is needed, component materials required and corresponding man-hour will be added to DUPA
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(1)
Designation
Riprap (Class A) cu.m. 1.50 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment Minor Tools (5% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.50 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Boulders (15 - 25 kg.) Miscellaneous (1% of Materials Cost)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(2)
Designation
Riprap (Class B) cu.m. 1.25 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (Wheel Type 0.28 cu.m.)
1
Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Boulders (30 - 70 kg.) Miscellaneous (1% of Materials Cost)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(3)
Designation
Riprap (Class C) cu.m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (Wheel Type 0.28 cu.m.)
1
Minor Tools (5% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Boulders (50 - 100 kg.) Miscellaneous (1% of Materials Cost)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(4)
Designation
Riprap (Class D) cu.m. 0.75 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe (Wheel Type 0.28 cu.m.)
1
Minor Tools (5% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 0.75 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Boulders (100 - 200 kg.) Miscellaneous (1% of Materials Cost)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(5)
Designation
Grouted Riprap (Class A) cu.m. 1.25 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer c. Water Truck/Pump (16000L) Minor Tools (5% of Labor)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.25 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC) e. Filter Cloth f. Boulders (15 - 25 kg.) Miscellaneous (1% of Materials Cost)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
bag cu.m. cu.m. m sq.m. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(6)
Designation
Grouted Riprap (Class B) cu.m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Water Truck/Pump (16000L) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC)
bag cu.m. cu.m. m
e. Filter Cloth f. Boulders (30 - 70 kg.) Miscellaneous (1% of Materials Cost)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
sq.m. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(7)
Designation
Grouted Riprap (Class C) cu.m. 0.75 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Water Truck/Pump (16000L) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.75 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC)
bag cu.m. cu.m. m
e. Filter Cloth f. Boulders (60 - 100 kg.) Miscellaneous (1% of Materials)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
sq.m. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(8)
Designation
Grouted Riprap (Class D) cu.m. 0.50 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Water Truck/Pump (16000L) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 0.50 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC)
bag cu.m. cu.m. m
e. Filter Cloth f. Boulders (100 - 200 kg.) Miscellaneous (1% of Materials)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
sq.m. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
505(9)
Designation
Filter Layer of Granular Material cu.m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Granular Materials
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
506
Designation
Stone Masonry cu.m. 1.60 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Water Truck/Pump (16000L) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (10% Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour =1.6000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC)
bag cu.m. cu.m. m
e. Filter Cloth f. Boulders Miscellaneous (1% of Materials Cost)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
sq.m. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
507
Designation
Rubble Concrete cu.m. 1.40 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Water Truck/Pump (16000L) c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (10% Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.400 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel Fill d. Weep Holes (PVC)
bag cu.m. cu.m. m
e. Filter Cloth f. Boulders g. Gravel Miscellaneous (2% of Materials) Note: 60% Boulder 50% Class "B" Concrete (w/ side forms only)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
sq.m. cu.m. cu.m.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
508
Designation
Hand Laid Rock Embankment cu.m. 3.125 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment
Minor Tools (10% of Labor Cost)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.125 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Boulders
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
509(a)
Designation
Timber Sheet Pile m. 4.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Drop Hammer (15 T) Minor Tools (10% of Labor Cost)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Timber Sheet Piles, ave. dia. 395mm b. Coco Log - 2 uses c. Lumber (Falsework) - 4 uses d. Nail/Spike (1 kg./100 bd.ft. of Lumber)
bd.ft. m. bd.ft. kg.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
509(b)
Steel Sheet Pile (Slope Protection) m 10.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Crawler Crane (36 - 40 T) b. Vibro Hammer (Hydraulic Operated) c. Welding Machine (300 A, Gas/Diesel Driven d. Cutting Outfit
1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 10.0000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Steel Sheet Piles (48 kg./m.) Miscellaneous (3% of Materials Cost)
kg.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
509(c)
Designation
Concrete Sheet Pile, furnished and driven - 0.50 m x 0 m 1.38 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 6 6
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Truck Mounted Crane (41 - 45 mt) b. Diesel Hammer (K25 or equivalent) c. One Bagger Mixer d. Concrete Vibrator e. Water Truck/Pump (16000L) f. Bar Cutter, Single Phase f. Bar Bender g. Drop Hammer h. Jack Hammer i. Air Compressor (356 - 450 cfm) j. Plate Compactor (5 Hp) Minor Tools (5% of Labor)
1 1 1 1 1 1 1 1 2 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.3800 m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials a. Coco Log b. Reinforcing Steel Bar c. Cement d. Sand e. Gravel
Unit kg. bag cu.m. cu.m. pc.
G. H. I. J. K.
f. Marine Plywood, 1/2" x 4' x 8' - 4 uses g. Lumber, 2' x 2' - 4 uses h. # 16 GI Tie Wire (2% of RSB) i. Spike (1 kg/100 bd.ft of Lumber h. Assorted CWN (1 kg./100 bd.ft. of Lumber) Casting Bed a. Ready Mix Concrete b. Coco Lumber - 4 uses c. Base Course Sub - Total for F Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
pc. bd.ft. kg. kg. kg. cu.m bd.ft. cu.m
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
510(1)
Designation
Bed Course Granular Material cu.m. 1.25 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Plate Compactor Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.2500 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Aggregate Subbase Course (w/ 15% Shrinkage Factor)
cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
510(2)
Designation
Concrete Slope Protection cu.m. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor Installation of Formworks & Rebars b. Skilled Labor c. Unskilled Labor
1 4 8 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer c. Water Truck/Pump (16000L) a. Backhoe (Wheel Type 0.28 cu.m.) b. Concrete Vibrator h. Bar Cutter, Single Phase b. Bar Bender Minor Tools (10% Labor)
1 1 1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.0000 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Weep Holes (PVC) d. Filter Cloth e. Gravel
bag cu.m. m sq.m. cu.m.
f. Granular Filter f. Reinforcing Steel Bar g. Marine Plywood 1/2" x 4' x 8' - 4 uses h. Lumber - 4 uses i. #16 GI Tie Wire (2% of RSB) j. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K. *
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost Note: RSB quantity is variable based on approved plan.
cu.m. kg. pc. bd.ft. kg. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
511(1)
Gabions cu.m. 2.50
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment Note: Exclude Excavation Works Backhoe excluded, excavation should be separate as the quantity is variable.
Sub - Total for B C. Total (A + B) D. Output per hour = 2.500 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Gabion Wire Mesh (1 x 1 x 2) (w/ complete accessories) b. Boulders
pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
511(2)
Mattresses cu.m. 3.125
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment Note: Exclude Excavation Works Backhoe excluded, excavation should be separate as the quantity is variable.
Sub - Total for B C. Total (A + B) D. Output per hour = 3.125 cu.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Mattresses (6 x 2 x 0.3 ) (w/ complete accessories) b. Boulders
pc. cu.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
511(3)
Designation
Filter Cloth sq.m. 100.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (9 - 10 mt)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 100.0000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Filter Cloth Miscellaneous (5% of Materials Cost)
sq.m.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
ILED UNIT PRICE ANALYSIS (DUPA)
e in place (910mm dia.) - Half Silted
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00
1,212.00
1,212.00 32.57
1,244.57 1,570.23 418.73 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 418.73 37.69 33.50 24.50 514.41
ILED UNIT PRICE ANALYSIS (DUPA)
e in place (1070mm dia.) - Half Silted
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00
1,212.00
1,212.00 32.57
1,244.57 1,570.23 570.99 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 570.99 51.39 45.68 33.40 701.46
ILED UNIT PRICE ANALYSIS (DUPA)
e in place (1220mm dia.) - Half Silted
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00
1,212.00
1,212.00 32.57
1,244.57 1,570.23 785.11 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 785.11 70.66 62.81 45.93 964.51
ILED UNIT PRICE ANALYSIS (DUPA)
e in place (1520mm dia.) - Half Silted
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00
1,212.00
1,212.00 32.57
1,244.57 1,570.23 1,046.82 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 1,046.82 94.21 83.75 61.24 1,286.02
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
0.50 0.50 0.50
69.42 50.18 38.97
34.71 25.09 38.97
98.77 No. of Hours
Hourly Rate
Amount
0.25
1,212.00
303.00
0.50
200.00
25.00 9.88
337.88 436.65 436.65 Quantity
Unit Cost
Amount
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
0.00 436.65 39.30 34.93 25.54 536.42
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
24.08
24.08 505.62 337.08 Quantity
Unit Cost
Amount
1.05
920.00
966.00 9.66
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
975.66 1,312.74 118.15 105.02 76.80 1,612.70
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.50
922.00
461.00 16.28
477.28 802.94 642.35 Quantity
Unit Cost
Amount
1.05
810.00
850.50 8.51
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
859.01 1,501.36 135.12 120.11 87.83 1,844.42
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
0.75
922.00
691.50 16.28
707.78 1,033.44 1,033.44 Quantity
Unit Cost
Amount
1.05
740.00
777.00 7.77
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
784.77 1,818.21 163.64 145.46 106.37 2,233.67
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00
922.00
922.00 16.28
938.28 1,263.94 1,685.26 Quantity
Unit Cost
Amount
1.05
650.00
682.50 6.83
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
689.33 2,374.58 213.71 189.97 138.91 2,917.17
ILED UNIT PRICE ANALYSIS (DUPA)
ss A)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
1.00 0.05
172.00 2,450.00
172.00 122.50 24.08
318.58 800.12 640.09 Quantity
Unit Cost
Amount
3.00 0.25 0.015 0.30 0.015 1.05
220.00 850.00 650.00 144.67 275.00 920.00
660.00 212.50 9.75 43.40 4.13 966.00 18.96
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,914.73 2,554.83 229.93 204.39 149.46 3,138.61
ILED UNIT PRICE ANALYSIS (DUPA)
ss B)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 0.05 0.50
172.00 2,450.00 922.00
172.00 122.50 461.00 16.28
771.78 1,097.44 1,097.44 Quantity
Unit Cost
Amount
2.50 0.21 0.015 0.30
220.00 850.00 650.00 144.67
550.00 178.50 9.75 43.40
0.015 1.05
275.00 810.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4.13 850.50 16.36
1,652.64 2,750.08 247.51 220.01 160.88 3,378.48
ILED UNIT PRICE ANALYSIS (DUPA)
ss C)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 0.05 0.75
172.00 2,450.00 922.00
172.00 122.50 691.50 16.28
1,002.28 1,327.94 1,770.59 Quantity
Unit Cost
Amount
2.20 0.18 0.015 0.30
220.00 850.00 650.00 144.67
484.00 153.00 9.75 43.40
0.015 1.05
275.00 730.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4.13 766.50 14.61
1,475.38 3,245.97 292.14 259.68 189.89 3,987.68
ILED UNIT PRICE ANALYSIS (DUPA)
ss D)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 0.05 1.00
172.00 2,450.00 922.00
172.00 122.50 922.00 16.28
1,232.78 1,558.44 3,116.89 Quantity
Unit Cost
Amount
1.80 0.15 0.015 0.30
220.00 850.00 650.00 144.67
396.00 127.50 9.75 43.40
0.015 1.05
275.00 650.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4.13 682.50 12.63
1,275.91 4,392.79 395.35 351.42 256.98 5,396.55
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
19.75
19.75 217.29 217.29 Quantity
Unit Cost
Amount
1.05
900.00
945.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
945.00 1,162.29 104.61 92.98 67.99 1,427.88
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
1.00 0.05 0.10
172.00 2,450.00 922.00
172.00 122.50 92.20 48.15
434.85 916.39 572.75 Quantity
Unit Cost
Amount
5.50 0.30 0.02 0.30
240.00 500.00 600.00 195.00
1,320.00 150.00 12.00 58.50
0.015 1.05
160.00 560.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2.40 588.00 21.31
2,152.21 2,724.96 245.25 218.00 159.41 3,347.61
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
1.00 0.05 0.10
172.00 2,450.00 922.00
172.00 122.50 92.20 48.15
434.85 916.39 654.57 Quantity
Unit Cost
Amount
4.20 0.2625 0.02 0.30
220.00 850.00 650.00 144.67
924.00 223.13 13.00 43.40
0.015 0.63 0.525
275.00 810.00 650.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4.13 510.30 341.25 36.72
2,095.92 2,750.49 247.54 220.04 160.90 3,378.98
ILED UNIT PRICE ANALYSIS (DUPA)
bankment
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
48.15
48.15 529.69 169.50 Quantity
Unit Cost
Amount
1.05
920.00
966.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
966.00 1,135.50 102.20 90.84 66.43 1,394.96
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 50.18 77.94
197.54 No. of Hours
Hourly Rate
Amount
1.00 1.00
2,606.00 200.00
2,606.00 200.00 19.75
2,825.75 3,023.29 755.82 Quantity
Unit Cost
Amount
52.25 1.00 16.00 0.16
40.00 350.00 40.00 68.00
2,090.00 175.00 160.00 10.88
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,435.88 3,191.70 287.25 255.34 186.71 3,921.01
ILED UNIT PRICE ANALYSIS (DUPA)
pe Protection)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 155.88
325.66 No. of Hours
Hourly Rate
Amount
1.00 1.00 0.25 0.25
1,902.00 2,123.00 371.00 45.45
1,902.00 2,123.00 92.75 11.36
4,129.11 4,454.77 445.48 Quantity
Unit Cost
Amount
48.00
48.00
2,304.00 69.12
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,373.12 2,818.60 253.67 225.49 164.89 3,462.65
ILED UNIT PRICE ANALYSIS (DUPA) furnished and driven - 0.50 m x 0.35 m
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 301.08 233.82
604.32 No. of Hours
Hourly Rate
Amount
0.23 0.13 0.15 0.15 0.01 0.20 0.20 0.13 0.01 0.01 0.01
2,606.00 150.00 172.00 91.25 2,450.00 219.75 351.50 200.00 150.00 965.00 123.00
599.38 19.50 25.80 13.69 24.50 43.95 70.30 26.00 3.00 9.65 1.23 30.22 867.21 1,471.53 1,066.33
Quantity
Unit Cost
Amount
0.71 41.64 1.66 0.09 0.18
40.00 220.00 850.00 650.00 700.00
28.40 9,160.80 1,411.00 58.50 126.00
0.24 18.59 0.83 0.06 0.19
700.00 40.00 47.00 68.00 68.00
42.00 185.90 39.01 4.08 12.92
0.03 1.50 0.03
2,840.00 20.00 530.00
85.20 7.50 15.90 11,161.31 12,227.64 1,100.49 978.21 715.32 15,021.65
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ILED UNIT PRICE ANALYSIS (DUPA)
r Material
No. of Hours
Hourly Rate
Amount
1.00 1.00
69.42 38.97
69.42 155.88
225.30 No. of Hours
Hourly Rate
Amount
1.00
123.00
123.00 22.53
145.53 370.83 296.66 Quantity
Unit Cost
Amount
1.15
580.00
667.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
667.00 963.66 86.73 77.09 56.37 1,183.86
ILED UNIT PRICE ANALYSIS (DUPA)
ection
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 200.72 311.76
1.00 1.00
50.18 38.97
100.36 155.88 838.14
No. of Hours
Hourly Rate
Amount
1.00 0.05 0.10 0.50 0.05 0.05
172.00 2,450.00 922.00 91.25 219.75 351.50
172.00 122.50 92.20 45.63 10.99 17.58 83.81
544.70 1,382.84 1,382.84 Quantity
Unit Cost
Amount
8.40 0.50 0.21 0.015 1.00
220.00 850.00 144.67 275.00 650.00
1,848.00 425.00 30.38 4.13 650.00
0.016 * 26.03 0.48 18.76 0.521 0.188
650.00 40.00 700.00 40.00 47.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
10.40 1,041.20 84.00 187.60 24.49 12.78
4,317.98 5,700.82 513.07 456.07 333.50 7,003.46
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
0.00 481.54 192.62 Quantity
Unit Cost
Amount
0.50
2,900.00
1,450.00
1.05
920.00
966.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,416.00 2,608.62 234.78 208.69 152.60 3,204.68
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
0.00 481.54 154.09 Quantity
Unit Cost
Amount
0.28
5,000.00
1,400.00
1.05
920.00
966.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,366.00 2,520.09 226.81 201.61 147.43 3,095.93
ILED UNIT PRICE ANALYSIS (DUPA)
No. of Hours
Hourly Rate
Amount
1.00 1.00 1.00
69.42 50.18 38.97
69.42 100.36 311.76
481.54 No. of Hours
Hourly Rate
Amount
0.25
1,212.00
303.00
303.00 784.54 7.85 Quantity
Unit Cost
Amount
1.05
275.00
288.75 14.44
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
303.19 311.03 27.99 24.88 18.20 382.10
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
600(1)
Designation
Concrete Curb (Cast in place) - 0.45m x 0.15/0.20m m. 17.50 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 4 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Concrete Vibrator b. One Bagger Mixer c. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 17.500 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses
bag cu.m. cu.m. pc.
e. Form Lumber - 4 uses f. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
bd.ft. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
600(2)
Designation
Concrete Gutter (Cast in place) - 0.50m x 0.15m m. 17.50 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 4 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Concrete Vibrator b. One Bagger Mixer c. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 17.500 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel d. Good Lumber - 4 uses
bag cu.m. cu.m. bd.ft.
e. Assorted CWN (1 kg./100 bd.ft. of Lumber) f. Reinforcing Steel Bar
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
kg. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
600(3)
Designation
Concrete Curb and Gutter, Type A (Cast in place) - Na m 10.30 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 4 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Concrete Vibrator b. One Bagger Mixer c. Water Truck/Pump (16000L) Minor Tools (10% of Labor Cost)
1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 10.300 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses
bag cu.m. cu.m. pc.
e. Form Lumber - 4 uses f. Assorted CWN (1 kg./100 bd.ft. of Lumber) Miscellaneous (2% of Materials)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
bd.ft. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
600(4)
Designation
Concrete Curb (Precast) pc. 4.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Boom Truck (2 - 5 mt) Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 pc E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Fabricated Concrete Curb Miscellaneous (5% of materials)
m
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
600(5)
Designation
Concrete Gutter (Precast) pc. 4.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Boom Truck (2 - 5 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 pc E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Fabricated Concrete Gutter Miscellaneous (5% of materials)
m
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
600(6)
Designation
Concrete Curb and Gutter (Precast) pc. 3.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 1
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Boom Truck (2 - 5 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 3.0000 pc E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Fabricated Concrete Curb and Gutter Miscellaneous (5% of materials)
m
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
601(a)
Designation
Sidewalk (100mm thk.) sq.m. 161.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 4 12
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Transit Mixer (5 cu.m.)
4
b. Concrete Vibrator c. Concrete Batching Plant (30 cu.m.) d. Payloader (1.50 cu.m.), LX80-2C e. Concrete Screeder (5.5 Hp) f. Water Truck/Pump (16000L) g. Concrete Saw (7.5 Hp), 14" Blade Ø Minor Tools (5% of Labor)
2 1 1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 161.0000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Curing Compound b. Asphalt Sealant c. Forms d. Sand
L L m cu.m.
e. Gravel f. Cement
cu.m. bag
Note : Bed Course excluded
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
601(b)
Designation
Sidewalk (100mm thk.) sq.m. 20.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 4 12
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer
1
b. Water Truck/Pump (16000L) c. Concrete Vibrator d. Concrete Saw (7.5 Hp), 14" Blade Ø Minor Tools (5% of Labor Cost)
2 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 20.0000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Curing Compound b. Asphalt Sealant c. Forms d. Sand
L L m cu.m.
e. Gravel f. Cement
cu.m. bag
Note : Bed Course excluded
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
602(1)a
Designation
Right-of-Way Monument ea. 2.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Concrete Vibrator
1
b. Cargo Truck (9 - 10 mt) Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 2.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Concrete Class "A" b. Reinforcing Steel Bar, Grade 40 c. Plywood, 1/2" x 4' x 8' - 4 uses d. Form Lumber, Good - 4 uses
cu.m. kg. pc. bd.ft.
e. Reflectorized Paint, Marker f. # 16 Tie Wire (2% of RSB) g. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
L kg. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
602(1)b
Designation
Right-of-Way Monument (Precast) ea. 4.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Cargo Truck (9 - 10 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Fabricated Right-of-Way Monument (delivered at site)
ea.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
602(2)a
Designation
Maintenance Marker Post ea. 2.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Concrete Vibrator
1
b. Cargo Truck (9 - 10 mt) Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 2.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Concrete Class "A" b. Reinforcing Steel Bar, Grade 40 c. Plywood, 1/2" x 4' x 8' - 4 uses d. Form Lumber, Good - 4 uses
cu.m. kg. pc. bd.ft.
e. Reflectorized Paint, Marker f. # 16 Tie Wire (2% of RSB) g. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
L kg. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
602(2)b
Designation
Maintenance Marker Post (Precast) ea. 4.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment b. Cargo Truck (9 - 10 mt)
1
Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 4.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Fabricated Maintenance Marker Post (delivered at site)
ea.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
602(3)a
Designation
Kilometer Post ea. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (9 - 10 mt)
1
b. Concrete Vibrator Minor Tools (10% of Labor)
1
C. D. Output = 1.0000 ea E. Direct Unit Cost (C ÷ D)
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials a. Concrete Class "A" b. Reinforcing Steel Bar c. Plywood 1/2" x 4' x 8' - 2 uses d. Lumber - 2 uses
cu.m. kg. pc. bd.ft.
e. Portland Cement f. Pebble g. Reflectorized Paint, Marker h. # 16 Tie Wire (2% of RSB) i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
bag cu.m. L kg. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
602(3)b
Designation
Kilometer Post (Precast) ea. 2.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (9 - 10 mt) b. Concrete Vibrator Minor Tools (10% of Labor)
C. D. Output = 2.0000 ea E. Direct Unit Cost (C ÷ D)
1 1
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials a. Fabricated Kilometer Post b. Concrete Class "A" c. Reflectorized Paint, Marker
ea. cu.m. lit.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
602(4)
Designation
Guide Post ea. 50.00 No. of Person
A. Labor a. Construction Foreman b. Unskilled Labor
1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment Minor Tools (10% of Labor)
Sub - Total for B C. Total (A + B) D. Output per hour = 50.0000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Guide Post (Portable) b. Post Reflector Miscellaneous (5% of Materials)
ea. ea.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
603(1)
Designation
Cable Wire Guardrail m 1.15 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 8
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck/Pump (16000L) d. Cargo Truck (2 - 5 mt) Minor Tools (10% of Labor)
1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.15 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel d. Guardrail Post
bag cu.m. cu.m. set
e. Galvanized Wire Rope (1.21 kg./m) f. Check Rope g. Hook Bolt h. Anchor Bracket i. Wire Mesh j. Tension Fittings Miscellaneous (5% of Materials) Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost * Tentative Canvass Price
kg. set ea. unit sq.m. set
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
603(3)a
Designation
Metal Guardrails (Metal Beam) including Concrete Pos m 4.20 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Concrete Vibrator c. Water Truck/Pump (16000L) d. Cargo Truck (9 - 10 mt) Minor Tools (5 % of Labor Cost)
1 1 1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 4.2000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel d. Metal Beam Guardrail
bag cu.m. cu.m. m
e. Plywood Marine, 1/2" thk. x 4' x 8' - 4 uses f. Lumber - 4 uses g. Reinforcing Steel Bars, Grade 40 h. Tie Wire (2% of RSB) i. Assorted CWN (1 kg./100 bd.ft. of Lumber) j. Bolt, Nut & Washer 5/8" dia. x 9" k. Bolt, Nut & Washer 5/8" dia. x 1"
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
pc. bd.ft. kg. kg. kg. pc. pc.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
603(3)b
Designation
Metal Beam End Piece ea. 6.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (9 - 10 mt) Minor Tools (5% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 6.00000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Metal Guardrail End Piece
ea.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
603(4)
Guardrail (Timber) m 5.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 4
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (9 - 10 mt) Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 5.00000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) b. Lumber, 3" x 8" Plank (Tanguile) - Untreated c. Carriage Bolt, 1/2"Ø x 12" Miscellaneous (5% of Materials)
bd.ft. bd.ft. pc.
Note: Exclude Excavation Works
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
604(1)
Fencing (Barbed Wire) m 18.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Welding Machine (300 A, Gas/Diesel Driven Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 18.00000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. 3-Strand Galvanized Barbed Wire, Ga 12.5 b. 50mmx50mmx6m Angle Bar c. Ga. 9 Twisted Wire Fastener Miscellaneous (2% of Materials, Welding Rod & etc.)
m kg. pc.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
604(2)
Fencing (Chain Link Fence Fabric) - Type I m 6.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Welding Machine (300 A, Gas/Diesel Driven Minor Tools (10% of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 6.00000 m E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Cyclone Wire 8' Ga 10 b. 38mm x 38mm x 4mm Angle Bar c. Welding Rod (1 kg/2000 kf of Steel
m kg kg
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
604(3)
Designation
Fencing (Post) - Type I ea. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 2 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. One Bagger Mixer b. Bar Cutter, Single Phase c. Bar Bender d. Water Truck/Pump (16000L) Minor Tools (10% of Labor)
C. D. Output = 1.00000 ea E. Direct Unit Cost (C ÷ D)
1 1 1 1
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials a. Cement b. Sand c. Gravel d. Reinforcing Steel Bar
bag cu.m. cu.m. kg.
e. # 16 Tie Wire (2% of RSB) f. Plywood 1/4' x 4' x 8' - 2 uses g. Lumber - 2 uses h. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
kg. pc. bd.ft. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output
: : :
604(4)
Fencing (Gates) - (Height 3m. & Length 4.24m.) ea. 1.00
Designation
No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Welding Machine (300 A, Gas/Diesel Driven Minor Tools (10% of Labor)
C. D. Output = 1.00000 ea E. Direct Unit Cost (C ÷ D)
1
Sub - Total for B Total (A + B)
Name and Specification
Unit
F. Materials a. 50 mm. Ø G.I. Pipe, Schedule 40 b. Cyclone Wire Galvanized 10' Gauge 10 c. 6mm dia. Plain Bar Miscellaneous (3% of Material Cost, Gate Lock, Hinge & etc.)
pc. m kg.
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
605(1)a
Designation
Danger/Warning Signs (60cm Triangle) ea. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses
bag cu.m. cu.m. bd.ft.
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
m. kg. pc. pc. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
605(1)b
Designation
Danger/Warning Signs (90cm Triangle) ea. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses
bag cu.m. cu.m. bd.ft.
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
m. kg. pc. pc. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
605(2)a
Designation
Regulatory Signs (60cm Triangle) ea. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses
bag cu.m. cu.m. bd.ft.
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
m. kg. pc. pc. kg.
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
605(2)b
Designation
Regulatory Signs (90cm Triangle) ea. 1.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Labor c. Unskilled Labor
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labor)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 1.00000 ea E. Direct Unit Cost (C ÷ D) Name and Specification
Unit
F. Materials a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4 uses
bag cu.m. cu.m. bd.ft.
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Aluminum Sheet i. Assorted CWN (1 kg./100 bd.ft. of Lumber)
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
m. kg. pc. pc. kg.
RICE ANALYSIS (DUPA)
5m x 0.15/0.20m
Item No./Description Unit of Measurement Output per hour
No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 200.72 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
581.90
S
Amount
Nam B. Equipment
1.00 1.00 0.05
91.25 172.00 2,450.00
91.25 172.00 122.50 58.19
443.94 1,025.84 58.62 Quantity
Unit Cost
a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labo
S
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.72 0.04 0.08 0.28
220.00 850.00 650.00 700.00
158.40 34.00 52.00 49.00
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
12.16 0.12
40.00 68.00
121.60 8.16
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
423.16 481.78 43.36 38.54 28.18 591.87
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Al i. Assorted CWN (1 kg./10
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
50m x 0.15m
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 200.72 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
581.90
S
Amount
Nam B. Equipment
1.00 1.00 0.05
91.25 172.00 2,450.00
91.25 172.00 122.50 58.19
443.94 1,025.84 58.62 Quantity
Unit Cost
a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labo
S
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.72 0.04 0.08 3.28
220.00 850.00 650.00 40.00
158.40 34.00 52.00 32.80
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
0.03 0.84
68.00 37.00
2.04 31.08
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
310.32 368.94 33.20 29.52 21.58 453.24
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Al i. Assorted CWN (1 kg./10
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
Cast in place) - National Road
No. of Hours
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 200.72 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
581.90
S
Amount
Nam B. Equipment
1.00 1.00 0.05
91.25 172.00 2,450.00
91.25 172.00 122.50 58.19
443.94 1,025.84 99.60 Quantity
Unit Cost
a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labo
S
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.29 0.07 0.14 0.24
220.00 850.00 650.00 700.00
283.80 59.50 91.00 42.00
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
11.47 0.11
40.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Al i. Assorted CWN (1 kg./10
114.70 7.48 11.97
610.45 710.05 63.90 56.80 41.54 872.29
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 38.97
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
158.57
S
Amount
Nam B. Equipment
0.50
1,017.90
508.95 15.86
a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labo
524.81 683.38
S
170.84 Quantity
Unit Cost
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00
690.00
690.00 34.50
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Al i. Assorted CWN (1 kg./10
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
724.50 895.34 80.58 71.63 52.38 1,099.93
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 38.97
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
158.57
S
Amount
Nam B. Equipment
0.50
1,017.90
508.95
a. Cargo Truck (2 - 5 mt)
15.86
Minor Tools (10 % of Labo
524.81 683.38
S
170.84 Quantity
Unit Cost
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00
680.00
680.00 34.00
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Al i. Assorted CWN (1 kg./10
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
714.00 884.84 79.64 70.79 51.76 1,087.03
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 38.97
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
158.57
S
Amount
Nam B. Equipment
0.50
1,017.90
508.95
a. Cargo Truck (2 - 5 mt)
15.86
Minor Tools (10 % of Labo
524.81 683.38
S
227.79 Quantity
Unit Cost
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00
1,750.00
1,750.00 87.50
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
e. 3"Ø G.I. Pipe f. Plate g. Bolts, 5mm Ø h. Sign Face, 3mm thk. Al i. Assorted CWN (1 kg./10
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,837.50 2,065.29 185.88 165.22 120.82 2,537.21
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 200.72 467.64
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
737.78
S
Amount
Nam B. Equipment
1.00
1,318.00
5,272.00
a. Cargo Truck (2 - 5 mt)
1.00 1.00 1.00 1.00 1.00 1.00
91.25 1,759.50 1,733.00 545.00 2,450.00 32.63
182.50 1,759.50 1,733.00 545.00 2,450.00 32.63 36.89
Minor Tools (5% of Labor)
12,011.52 12,749.30
S
79.19 Quantity
Unit Cost
C. D. Output per hour = 10.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.29 0.12 0.46 0.055
28.00 44.00 250.00 850.00
8.12 5.28 115.00 46.75
a. Pavement Markings (W Miscellaneous (5% of abo
0.10 0.95
650.00 220.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
65.00 209.00
449.15 528.34 47.55 42.27 30.91 649.06
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 200.72 467.64
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
737.78
S
Amount
Nam B. Equipment
1.00
172.00
172.00
1.00 0.125 1.00
2,450.00 91.25 32.63
4,900.00 11.41 32.63 36.89
5,152.93 5,890.71 294.54 Quantity
Unit Cost
a. Cargo Truck (2 - 5 mt)
Minor Tools (10% of Lab
S
C. D. Output per hour = 10.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.29 0.12 0.46 0.055
28.00 44.00 250.00 850.00
8.12 5.28 115.00 46.75
a. Reflectorized Traffic Pa Miscellaneous (5% of abo
0.10 0.95
650.00 220.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
65.00 209.00
449.15 743.69 66.93 59.49 43.51 913.62
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.20
91.25
18.25
0.05
1,212.00
60.60 19.75
98.60 296.14 148.07 Quantity
Unit Cost
a. Cargo Truck (2 - 5 mt)
Minor Tools (10% of Lab
S
C. D. Output per hour = 10.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.03 7.15 0.22 13.53
3,538.78 40.00 700.00 40.00
106.16 286.00 38.50 135.30
a. Reflectorized Traffic Pa Miscellaneous (5% of abo
0.10 0.14 0.14
475.00 47.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
47.50 6.58 9.52
629.56 777.64 69.99 62.21 45.49 955.33
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.05
1,212.00
60.60
a. Diamond Drill, CP-8 wit
19.75
b. Cargo Truck (2 - 5 mt) c. Air Compressor (15 - 35 Minor Tools (5% of Labor)
80.35 277.89
S
69.47 Quantity
Unit Cost
C. D. Output per hour = 10.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00
3,320.00
3,320.00
a. Reflective Stud Catchey 180mm x 140mm (type b. Concrete Epoxy A & B
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
3,320.00 3,389.47 305.05 271.16 198.28 4,163.97
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.20
91.25
18.25
a. Diamond Drill, CP-8 wit
0.05
1,212.00
60.60 19.75
b. Cargo Truck (2 - 5 mt) c. Air Compressor (15 - 35 Minor Tools (5% of Labor)
98.60 296.14
S
148.07 Quantity
Unit Cost
C. D. Output per hour = 10.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.03 7.15 0.22 13.53
3,400.00 40.00 700.00 40.00
102.00 286.00 38.50 135.30
a. Reflective Stud Catchey 100mm x 100mm (type b. Concrete Epoxy A & B
0.10 0.14 0.14
475.00 47.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
47.50 6.58 9.52
625.40 773.47 69.61 61.88 45.25 950.21
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.05
1,212.00
60.60
a. Plate Compactor (5 hp)
19.75
Minor Tools (10% of Labor
80.35 277.89
S
69.47 Quantity
Unit Cost
C. D. Output per hour = 1.25 cu E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00
1,650.00
1,650.00
a. Topsoil
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,650.00 1,719.47 154.75 137.56 100.59 2,112.37
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.50 1.50 1.50
No. of Hours
69.42 50.18 38.97
Hourly Rate
104.13 75.27 116.91
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
296.31
S
Amount
Nam B. Equipment
0.50
1,212.00
606.00
a. Plate Compactor (5 hp)
0.10
91.25
9.13 29.63
Minor Tools (10% of Labor
644.76 941.07
S
941.07 Quantity
Unit Cost
C. D. Output per hour = 1.25 cu E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.184 7.59 0.604 7.15
3,400.00 40.00 700.00 20.00
625.60 303.60 211.40 71.50
0.775 0.044 0.20 0.14 0.07
220.00 900.00 475.00 47.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
170.50 39.60 95.00 6.58 4.76
1,528.54 2,469.61 222.26 197.57 144.47 3,033.91
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.50 1.50 1.50
No. of Hours
69.42 50.18 38.97
Hourly Rate
104.13 75.27 116.91
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
296.31
S
Amount
Nam B. Equipment
0.50 0.05
1,212.00 91.25
606.00 4.56 29.63
a. Water Truck/Pump (160 Minor Tools (10% of Labor
640.19 936.50
S
468.25 Quantity
Unit Cost
C. D. Output per hour = 35.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00 0.095 0.20
4,150.00 3,400.00 475.00
4,150.00 323.00 95.00
a. Sprigs b. Fertilizer
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
4,568.00 5,036.25 453.26 402.90 294.62 6,187.04
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00
No. of Hours
69.42 38.97
Hourly Rate
69.42 77.94
a. Construction Foreman b. Unskilled Labor
147.36
S
Amount
Nam B. Equipment
14.74
a. Water Truck/Pump (160 Minor Tools (10% of Labor
14.74 162.10
S
3.24 Quantity
Unit Cost
C. D. Output per hour = 25.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00 1.00
1,240.00 85.00
1,240.00 85.00 66.25
a. Sods
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,391.25 1,394.49 125.50 111.56 81.58 1,713.13
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 100.36 311.76
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
481.54
S
Amount
Nam B. Equipment
1.00 0.25 0.10 0.25
172.00 91.25 2,450.00 783.00
172.00 22.81 245.00 195.75 48.15
a. Cargo Truck (9 - 10 mt) b. Backhoe (0.80 cu.m.) c. Water Truck/Pump (160 Minor Tools (10% of Labor
Note: Includes watering fo
683.72 1,165.26 1,013.27 Quantity
Unit Cost
S
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
4.18 0.22 0.43 0.27
220.00 850.00 650.00 *1,800.00
919.60 187.00 279.50 486.00
a. Trees (Delivered at Site b. Fertilizers c. Bamboo Pole d. Polyethylene Sheets
4.92 0.22 0.33 0.11 0.11 0.65
186.44 *750.00 *350.00 *1,200.00 *295.00 *1,000.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
917.28 165.00 115.50 132.00 32.45 650.00 194.22 4,078.55 5,091.82 458.26 407.35 297.87 6,255.30
e. Tie Wire
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
uding Concrete Post
No. of Hours
Item No./Description Unit of Measurement Output per hour Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 100.36 155.88
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
325.66
S
Amount
Nam B. Equipment
0.50 0.50 0.05 0.25
172.00 91.25 2,450.00 1,212.00
86.00 45.63 122.50 303.00 16.28
a. Cargo Truck (9 - 10 mt) b. Backhoe (0.80 cu.m.) c. Water Truck/Pump (160 Minor Tools (10% of Labor
573.41 899.07
S
214.06 Quantity
Unit Cost
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.33 0.018 0.036 1.00
220.00 850.00 650.00 1,950.00
72.60 15.30 23.40 1,950.00
a. Fertilizers b. Bamboo Pole c. Polyethylene Sheets d. Tie Wire
0.25 8.00 4.00 0.08 0.08 0.50 2.00
700.00 40.00 40.00 47.00 68.00 28.00 21.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
43.75 80.00 160.00 3.76 5.44 14.00 42.00
2,410.25 2,624.31 236.19 209.95 153.52 3,223.97
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
1.00
1,212.00
1,212.00 9.88
b. Cargo Truck/Delivery Tr b. Applicator Machine c. Kneading Machine Minor Tools (10 % of Labo
1,221.88 1,419.42
S
236.57 Quantity
Unit Cost
C. D. Output per hour = 25.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00
1,350.00
1,350.00
a. Thermoplastic Paint (W b. Glass Beads c. Primer d. LPG (50 kg.)
e. LPG (12 kg.) f. Calsumine Miscellaneous (5% of Mat
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,350.00 1,586.57 142.79 126.93 92.81 1,949.10
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 100.36 155.88
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
325.66
S
Amount
Nam B. Equipment
0.50
1,212.00
606.00 32.57
b. Cargo Truck/Delivery Tr b. Applicator Machine c. Kneading Machine Minor Tools (10 % of Labo
638.57 964.23
S
192.85 Quantity
Unit Cost
C. D. Output per hour = 25.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
14.67 6.67 1.60
90.00 55.00 350.00
1,320.30 366.85 560.00 112.36
a. Thermoplastic Paint (Ye b. Glass Beads c. Primer d. LPG (50 kg.)
e. LPG (12 kg.) f. Calsumine Miscellaneous (5% of Mat
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
2,359.51 2,552.35 229.71 204.19 149.31 3,135.57
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.10
371.00
37.10 19.75
a. Asphalt Kettle/Drum Minor Tools (5% of Labor)
56.85 254.39
S
14.13 Quantity
Unit Cost
C. D. Output per hour = 20.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00 0.58 0.39
15.00 48.00 81.15
15.00 27.84 31.65 1.49
a. Blown Asphalt Miscellaneous (5% of Mat
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
75.98 90.11 8.11 7.21 5.27 110.70
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.50
371.00
185.50 19.75
a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labo
205.25 402.79
S
67.13 Quantity
Unit Cost
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
1.00 9.25 0.005
220.00 850.00 650.00
220.00 7,862.50 3.01
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
e. 75mm Ø G.I. Pipe f. G.I. Flat Bar, 1 1/2"x1/8 g. G.I. Bolts w/ Nuts & Wa h. G.I. Bolts w/ Nuts & Wa i. Sign Face, 3mm thk. Alu j. Assorted CWN (1 kg./10 Miscellaneous (0.3% of M
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
8,085.51 8,152.64 733.74 652.21 476.93 10,015.52
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.50 1.50 1.50
No. of Hours
69.42 50.18 38.97
Hourly Rate
104.13 150.54 116.91
a. Construction Foreman b. Skilled Labor c. Unskilled Labor
371.58
S
Amount
Nam B. Equipment
0.75 0.50 0.50 0.05
172.00 219.75 351.50 2,450.00
129.00 109.88 175.75 122.50 37.16
a. Cargo Truck (2 - 5 mt) Minor Tools (10 % of Labo
574.28 945.86
S
945.86 Quantity
Unit Cost
C. D. Output per hour = 1.00000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
5.68 0.30 0.60 22.07
220.00 850.00 650.00 40.00
1,249.60 255.00 390.00 882.80
a. Portland Cement b. Sand c. Gravel d. Form Lumber, Good - 4
0.441 1.94 28.67 0.29
47.00 350.00 20.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
e. 75mm Ø G.I. Pipe f. G.I. Flat Bar, 1 1/2"x1/8 g. G.I. Bolts w/ Nuts & Wa h. G.I. Bolts w/ Nuts & Wa i. Sign Face, 3mm thk. Alu j. Assorted CWN (1 kg./10 Miscellaneous (0.2% of M
20.73 339.50 286.70 19.72
3,444.05 4,389.91 395.09 351.19 256.81 5,393.00
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
ngth 4.24m.)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
2.00
371.00
742.00 19.75
c. Water Truck/Pump (160 Minor Tools (10% of Labor
761.75 959.29
S
959.29 Quantity
Unit Cost
C. D. Output per hour = 50.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
5.00 4.24 3.37
1,550.00 3,300.00 40.00
7,750.00 13,992.00 134.80 656.30
a. Erosion Control Net CG (Price includes bamboo pe
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
22,533.10 23,492.40 2,114.32 1,879.39 1,374.31 28,860.41
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
gle)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.25
783.00
195.75 19.75
c. Water Truck/Pump (160 Minor Tools (10% of Labor
215.50 413.04
S
413.04 Quantity
Unit Cost
C. D. Output per hour = 50.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
105.60 21.25 32.50 80.00
a. Erosion Control Net CG (Price includes bamboo pe
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 2,800.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,643.00 96.00 120.00 2,800.00 5.44
4,903.79 5,316.83 478.52 425.35 311.03 6,531.73
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA)
gle)
Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.25
783.00
195.75 19.75
Minor Tools (10% of Labor
215.50 413.04
S
413.04 Quantity
Unit Cost
C. D. Output per hour = 15.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
105.60 21.25 32.50 80.00
a. Coco Fiber Roll (CGR 2 (Price includes nylon rope
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 4,200.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,643.00 96.00 120.00 4,200.00 5.44
6,303.79 6,716.83 604.52 537.35 392.93 8,251.63
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.25
783.00
195.75 19.75
Minor Tools (10% of Labor
215.50 413.04
S
413.04 Quantity
Unit Cost
C. D. Output per hour = 15.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
105.60 21.25 32.50 80.00
a. Coco Fiber Roll (CGR 3 (Price includes nylon rope
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 2,800.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,643.00 96.00 120.00 2,800.00 5.44
4,903.79 5,316.83 478.52 425.35 311.03 6,531.73
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1.00 1.00 1.00
No. of Hours
69.42 50.18 38.97
Hourly Rate
69.42 50.18 77.94
a. Construction Foreman b. Unskilled Labor
197.54
S
Amount
Nam B. Equipment
0.25
783.00
195.75 19.75
215.50 413.04 413.04 Quantity
Unit Cost
a. Hydroseeding Machine b. Water Truck/Pump (160 (including maintenance tim
S C. D. Output per hour = 62.500 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
105.60 21.25 32.50 80.00
a. Grass Cover (Price includes grass seed & binding agent for hydros
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 4,200.00 68.00
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
1,643.00 96.00 120.00 4,200.00 5.44
6,303.79 6,716.83 604.52 537.35 392.93 8,251.63
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Item No./Description Unit of Measurement Output per hour
A. Labor a. Construction Foreman b. Unskilled Labor
S
Nam B. Equipment
a. Water Truck/Pump (160 Minor Tools (10% of Labor
S C. D. Output per hour = 35.0000 E. Direct Unit Cost (C ÷ D)
Name F. Materials
a. Vetiver Grass System (Price includes cocopeat f
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
605(2)c
Designation
r
Regulatory Signs (60cm Octagon) ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber)
m. kg. pc. pc. kg.
3.10 2.00 12.00 1.00 0.08
530.00 70.78 10.00 4,500.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
605(2)d
Designation
r
Regulatory Signs (90cm Octagon) ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber)
m. kg. pc. pc. kg.
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 7,500.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
605(3)a
Designation
r
Informative Signs (12"x24") ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
1.320 0.073 0.145 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber)
m. kg. pc. pc. kg.
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 2,750.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
605(3)b
Designation
r
Informative Signs (12"x48") ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
1.320 0.073 0.145 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber)
m. kg. pc. pc. kg.
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 5,450.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
605(3)c
Designation
r
Informative Signs (18"x24") ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
1.320 0.073 0.145 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber)
m. kg. pc. pc. kg.
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 3,750.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
605(3)d
Designation
r
Informative Signs (18"x48") ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
1.320 0.073 0.145 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber)
m. kg. pc. pc. kg.
3.10 2.00 12.00 1.00 0.08
530.00 48.00 10.00 8,200.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
606(1)
Designation
r
Pavement Marking (Premix Reflectorized) sq.m. 10.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.05
783.00
Unit
Quantity
Unit Cost
L
1.00
450.00
Sub - Total for A Name and Capacity
of Labor)
Sub - Total for B Total (A + B) = 10.00000 sq.m Name and Specification
kings (White) % of above)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
606(2)a
Designation
r
Pavement Markings (Reflectorized Traffic Paint - White) sq.m. 10.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.05
783.00
Unit
Quantity
Unit Cost
L
1.00
450.00
Sub - Total for A Name and Capacity
0% of Labor)
Sub - Total for B Total (A + B) = 10.00000 sq.m Name and Specification
Traffic Paint (White) % of above)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
606(2)b
Designation
r
Pavement Markings (Reflectorized Traffic Paint - Yellow) sq.m. 10.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.05
783.00
Unit
Quantity
Unit Cost
L
1.00
475.00
Sub - Total for A Name and Capacity
0% of Labor)
Sub - Total for B Total (A + B) = 10.00000 sq.m Name and Specification
Traffic Paint (Yellow) % of above)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
607(1)
Reflective Pavement Studs ea. 10.00
Designation
r
No. of Person
No. of Hours
Hourly Rate
1 3
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
1.00
201.25
1 1
0.25 1.00
783.00 205.00
Unit
Quantity
Unit Cost
pc.
1.00
3,465.00
L
0.012
1,200.00
Sub - Total for A Name and Capacity
CP-8 with attachment
r (15 - 35 cfm) of Labor)
Sub - Total for B Total (A + B) = 10.00000 ea Name and Specification
d Catcheye Flush Surface mm (type depends on the req.)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
607(2)
Reflective Pavement Studs (4" RPM) ea. 10.00
Designation
r
No. of Person
No. of Hours
Hourly Rate
1 3
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
1.00
201.25
1 1
0.25 1.00
783.00 205.00
Unit
Quantity
Unit Cost
pc.
1.00
3,465.00
L
0.012
1,200.00
Sub - Total for A Name and Capacity
CP-8 with attachment
r (15 - 35 cfm) of Labor)
Sub - Total for B Total (A + B) = 10.00000 ea Name and Specification
d Catcheye Raised Surface mm (type depends on the req.)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
608(1)
Designation
r
Furnishing and Placing Topsoil cu.m. 1.25 No. of Person
No. of Hours
Hourly Rate
1 2 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
1.00
123.00
Unit
Quantity
Unit Cost
cu.m.
1.05
490.00
Sub - Total for A Name and Capacity
or (5 hp)
% of Labor)
Sub - Total for B Total (A + B) = 1.25 cu.m Name and Specification
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
608(2)
Designation
r
Placing Topsoil cu.m. 1.25 No. of Person
No. of Hours
Hourly Rate
1 2 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
1.00
123.00
Unit
Quantity
Unit Cost
Sub - Total for A Name and Capacity
or (5 hp)
% of Labor)
Sub - Total for B Total (A + B) = 1.25 cu.m Name and Specification
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
609
Designation
r
Sprigging sq.m. 35.00 No. of Person
No. of Hours
Hourly Rate
1 2 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
2,450.00
Unit
Quantity
Unit Cost
sq.m. kg.
1.05 0.10
89.00 26.00
Sub - Total for A Name and Capacity
ump (16000L) % of Labor)
Sub - Total for B Total (A + B) = 35.00000 sq.m Name and Specification
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
610
Designation
r
Sodding sq.m. 25.00 No. of Person
No. of Hours
Hourly Rate
1 8
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
0.50
2,450.00
Unit
Quantity
Unit Cost
sq.m.
1.05
89.00
Sub - Total for A Name and Capacity
ump (16000L) % of Labor)
Sub - Total for B Total (A + B) = 25.00000 sq.m Name and Specification
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
611(1)
Designation
r
Trees (Furnishing and Transplanting), 150mm dia. or less ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1
1.00 1.00 0.50
1,212.00 1,537.00 2,450.00
Unit
Quantity
Unit Cost
pc. kg. pc. sq.m.
1.00 3.00 3.00 3.00
400.00 26.00 50.00 10.00
Sub - Total for A Name and Capacity
9 - 10 mt)
ump (16000L) % of Labor)
atering for three (3) months
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
ed at Site)
kg.
0.25
46.67
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
611(2)
Designation
r
Trees (Transplanting), 150mm dia. or less ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1
1.00 1.00 0.50
1,212.00 1,537.00 2,450.00
Unit
Quantity
Unit Cost
kg. pc. sq.m. kg.
3.00 3.00 3.00 0.25
26.00 50.00 10.00 46.67
Sub - Total for A Name and Capacity
9 - 10 mt)
ump (16000L) % of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
612(1)
Designation
r
Reflectorized Thermoplastic Pavement Markings (White) sq.m. 25.00 No. of Person
No. of Hours
Hourly Rate
1 2 6
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1
1.00 1.00 1.00
783.00 93.75 187.50
Unit
Quantity
Unit Cost
bag bag L cyl.
0.325 0.033 0.120 0.004
1,565.00 650.00 160.00 3,800.00
Sub - Total for A Name and Capacity
elivery Truck(2 - 5 mt)
% of Labor Cost)
Sub - Total for B Total (A + B) = 25.00000 sq.m Name and Specification
Paint (White)
cyl. kg.
0.002 0.125
735.00 3.00
% of Materials)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
612(2)
Designation
r
Reflectorized Thermoplastic Pavement Markings (Yellow) sq.m. 25.00 No. of Person
No. of Hours
Hourly Rate
1 2 6
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1 1 1
1.00 1.00 1.00
783.00 93.75 187.50
Unit
Quantity
Unit Cost
bag bag L cyl.
0.325 0.033 0.120 0.004
1,780.00 650.00 175.00 3,800.00
Sub - Total for A Name and Capacity
elivery Truck(2 - 5 mt)
% of Labor Cost)
Sub - Total for B Total (A + B) = 25.00000 sq.m Name and Specification
Paint (Yellow))
cyl. kg.
0.002 0.125
735.00 3.00
% of Materials)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
613
Designation
r
Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types) kg. 20.00 . No. of Person
No. of Hours
Hourly Rate
1 6
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
1.00
10.00
Unit
Quantity
Unit Cost
kg.
1.05
250.00
Sub - Total for A Name and Capacity
of Labor)
Sub - Total for B Total (A + B) = 20.0000 kg Name and Specification
% of Materials)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
620(a)
Designation
r
Chevron Signs (450mmx600mm) ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
1/2"x1/8" uts & Washer, 5mm Ø uts & Washer, 2mm Ø m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber) .3% of Materials)
m. kg. pc. pc. pc. kg.
3.25 5.00 3.00 12.00 2.00 0.08
530.00 48.00 10.00 10.00 3,750.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
620(b)
Designation
r
Chevron Signs (600mmx800mm) ea. 1.00 No. of Person
No. of Hours
Hourly Rate
1 1 2
1.00 1.00 1.00
69.42 50.18 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
783.00
Unit
Quantity
Unit Cost
bag cu.m. cu.m. bd.ft.
0.48 0.025 0.050 8.00
220.00 850.00 650.00 40.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 1.00000 ea Name and Specification
Good - 4 uses
1/2"x1/8" uts & Washer, 5mm Ø uts & Washer, 2mm Ø m thk. Aluminum Sheet (1 kg./100 bd.ft. of Lumber) .2% of Materials)
m. kg. pc. pc. pc. kg.
3.45 5.00 3.00 12.00 2.00 0.08
530.00 48.00 10.00 10.00 7,500.00 68.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
622(1)a
Bio-Engineering Solutions (Coco-net) sq.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 8
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
2,450.00
Name and Specification
Unit
Quantity
Unit Cost
ol Net CGN 400 w/ 5 % wastage amboo pegs)
sq.m.
1.05
110.00
r
Sub - Total for A Name and Capacity
ump (16000L) % of Labor)
Sub - Total for B Total (A + B) = 50.0000 sq.m
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
622(1)b
Bio-Engineering Solutions (Coco-net) sq.m. 50.00
Designation
No. of Person
No. of Hours
Hourly Rate
1 8
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
0.25
2,450.00
Name and Specification
Unit
Quantity
Unit Cost
ol Net CGN 700 w/ 5 % wastage amboo pegs)
sq.m.
1.05
156.00
r
Sub - Total for A Name and Capacity
ump (16000L) % of Labor)
Sub - Total for B Total (A + B) = 50.0000 sq.m
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
622(2)a
Designation
r
Bio-Engineering Solutions (Coco-logs/Fascine) m 15.00 No. of Person
No. of Hours
Hourly Rate
1 2
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
m
1.05
388.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 15.0000 m Name and Specification
ll (CGR 200) ylon ropes and live stakes)
`
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
622(2)b
Designation
r
Bio-Engineering Solutions (Coco-logs/Fascine) m 15.00 No. of Person
No. of Hours
Hourly Rate
1 8
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
Unit
Quantity
Unit Cost
m
1.05
509.00
Sub - Total for A Name and Capacity
% of Labor)
Sub - Total for B Total (A + B) = 15.0000 m Name and Specification
ll (CGR 300) ylon ropes and live stakes)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
622(3)a
Designation
r
Bio-Engineering Solutions (Vegetation) sq.m. 62.50 No. of Person
No. of Hours
Hourly Rate
1 2
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1 1
1.00 1.00
952.00 2,450.00
Unit
Quantity
Unit Cost
sq.m.
1.05
45.00
Sub - Total for A Name and Capacity
Machine ump (16000L) nance time)
Sub - Total for B Total (A + B) = 62.500 sq.m Name and Specification
rass seeds, mulch, cocopeat or hydroseeding)
Sub - Total for F 9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
622(3)b
Designation
r
Bio-Engineering Solutions (Vegetation) sq.m. 35.00 No. of Person
No. of Hours
Hourly Rate
1 8
1.00 1.00
69.42 38.97
No of Units
No. of Hours
Hourly Rate
1
0.50
2,450.00
Sub - Total for A Name and Capacity
ump (16000L) % of Labor)
Sub - Total for B Total (A + B) = 35.0000 sq.m Name and Specification
Unit
Quantity
Unit Cost
sq.m.
1.05
70.00
ocopeat fertilizer)
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 5% of (G + H + I) (G + H + I + J)
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
105.60 21.25 32.50 80.00
1,643.00 141.56 120.00 4,500.00 5.44
6,649.35 7,062.39 635.62 564.99 413.15 8,676.15
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
105.60 21.25 32.50 80.00
1,643.00 96.00 120.00 7,500.00 5.44
9,603.79 10,016.83 901.52 801.35 585.98 12,305.68
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
290.40 62.05 94.25 80.00
1,643.00 96.00 120.00 2,750.00 5.44
5,141.14 5,554.18 499.88 444.33 324.92 6,823.32
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
290.40 62.05 94.25 80.00
1,643.00 96.00 120.00 5,450.00 5.44
7,841.14 8,254.18 742.88 660.33 482.87 10,140.27
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
290.40 62.05 94.25 80.00
1,643.00 96.00 120.00 3,750.00 5.44
6,141.14 6,554.18 589.88 524.33 383.42 8,051.82
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
290.40 62.05 94.25 80.00
1,643.00 96.00 120.00 8,200.00 5.44
10,591.14 11,004.18 990.38 880.33 643.74 13,518.64
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
39.15 9.88
49.03 246.57 24.66 Amount
450.00 22.50
472.50 497.16 44.74 39.77 29.08 610.76
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
39.15 19.75
58.90 256.44 25.64 Amount
450.00 22.50
472.50 498.14 44.83 39.85 29.14 611.97
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
39.15 19.75
58.90 256.44 25.64 Amount
475.00 23.75
498.75 524.39 47.20 41.95 30.68 644.22
ALYSIS (DUPA)
Amount
69.42 116.91
186.33 Amount
201.25 195.75 205.00 9.32
611.32 797.65 79.76 Amount
3,465.00 14.40
3,479.40 3,559.16 320.32 284.73 208.21 4,372.43
ALYSIS (DUPA)
Amount
69.42 116.91
186.33 Amount
201.25 195.75 205.00 9.32
611.32 797.65 79.76 Amount
3,465.00 14.40
3,479.40 3,559.16 320.32 284.73 208.21 4,372.43
ALYSIS (DUPA)
Amount
69.42 100.36 77.94
247.72 Amount
123.00 24.77
147.77 395.49 316.39 Amount
514.50
514.50 830.89 74.78 66.47 48.61 1,020.75
ALYSIS (DUPA)
Amount
69.42 100.36 77.94
247.72 Amount
123.00 24.77
147.77 395.49 316.39 Amount
0.00 316.39 28.48 25.31 18.51 388.69
ALYSIS (DUPA)
Amount
69.42 100.36 77.94
247.72 Amount
612.50 24.77
637.27 884.99 25.29 Amount
93.45 2.60
96.05 121.34 10.92 9.71 7.10 149.06
ALYSIS (DUPA)
Amount
69.42 311.76
381.18 Amount
1,225.00 38.12
1,263.12 1,644.30 65.77 Amount
93.45
93.45 159.22 14.33 12.74 9.31 195.60
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
1,212.00 1,537.00 1,225.00 19.75
3,993.75 4,191.29 4,191.29 Amount
400.00 78.00 150.00 30.00
11.67
669.67 4,860.96 437.49 388.88 284.37 5,971.69
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
1,212.00 1,537.00 1,225.00 19.75
3,993.75 4,191.29 4,191.29 Amount
78.00 150.00 30.00 11.67
269.67 4,460.96 401.49 356.88 260.97 5,480.29
ALYSIS (DUPA)
Amount
69.42 100.36 233.82
403.60 Amount
783.00 93.75 187.50 40.36
1,104.61 1,508.21 60.33 Amount
508.63 21.45 19.20 15.20
1.47 0.38 28.32
594.64 654.96 58.95 52.40 38.32 804.62
ALYSIS (DUPA)
Amount
69.42 100.36 233.82
403.60 Amount
783.00 93.75 187.50 40.36
1,104.61 1,508.21 60.33 Amount
578.50 21.45 21.00 15.20
1.47 0.38 31.90
669.89 730.22 65.72 58.42 42.72 897.08
ALYSIS (DUPA)
Amount
69.42 233.82
303.24 Amount
10.00 15.16
25.16 328.40 16.42 Amount
262.50 13.13
275.63 292.05 26.28 23.36 17.08 358.78
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
105.60 21.25 32.50 80.00
1,722.50 240.00 30.00 120.00 7,500.00 5.44 29.57
9,886.86 10,299.91 926.99 823.99 602.54 12,653.43
ALYSIS (DUPA)
Amount
69.42 50.18 77.94
197.54 Amount
195.75 19.75
215.50 413.04 413.04 Amount
105.60 21.25 32.50 80.00
1,828.50 240.00 30.00 120.00 15,000.00 5.44 34.93
17,498.22 17,911.26 1,612.01 1,432.90 1,047.81 22,003.98
ALYSIS (DUPA)
Amount
69.42 311.76
381.18 Amount
612.50 38.12
650.62 1,031.80 20.64 Amount
115.50
115.50 136.14 12.25 10.89 7.96 167.24
ALYSIS (DUPA)
Amount
69.42 311.76
381.18 Amount
612.50 38.12
650.62 1,031.80 20.64 Amount
163.80
163.80 184.44 16.60 14.75 10.79 226.58
ALYSIS (DUPA)
Amount
69.42 77.94
147.36 Amount
14.74
14.74 162.10 10.81 Amount
407.40
407.40 418.21 37.64 33.46 24.47 513.77
ALYSIS (DUPA)
Amount
69.42 311.76
381.18 Amount
38.12
38.12 419.30 27.95 Amount
534.45
534.45 562.40 50.62 44.99 32.90 690.91
ALYSIS (DUPA)
Amount
69.42 77.94
147.36 Amount
952.00 2,450.00
3,402.00 3,549.36 56.79 Amount
47.25
47.25 104.04 9.36 8.32 6.09 127.81
ALYSIS (DUPA)
Amount
69.42 311.76
381.18 Amount
1,225.00 38.12
1,263.12 1,644.30 46.98 Amount
73.50
73.50 120.48 10.84 9.64 7.05 148.01
ITEM NO. PART C 100(1) 100(2)a 100(2)b 100(3)a 100(3)b 101(1) 101(2) 101(2) 101(2) 101(2) 101(2)a 101(2)b 101(2)c 101(2)d 101(2)e 101(2)f 101(2)g 101(3)a.1 101(3)a.2 101(3)b 101(3)c 101(4)a 101(4)b 102(1) 102(2)a 102(2)b 102(3)a 102(3)b 102(3)c 102(3)d 102(4) 103(1)a 103(1)b 103(1)c 103(2)a 103(2)b 103(2)c 103(3) 103(4) 103(5)a
ITEM NO. 103(5)b 103(6) 104(1)a 104(1)b
ITEM NO. 104(2) 104(3) 104(4) 105(1) 105(2) 105(3) PART D
200 200(1) 201 201(1) 202 203 204 205 206 PART E 300(1) 300(2) 301(1) 301(2) 302(1) 302(2) 303(1) 303(2) 303(3) 303(4) 304(1) 304(2) 304(3) 304(4) 304(5) 305(1) 305(2) 305(3) 305(4) 306(a) 306(b) 306(1) 306(2) 307 308(a)
ITEM NO. 308(b) 309 310(a.1)
ITEM NO. 310(a.2) 310(a.3) 310(b.1) 310(b.2) 310(b.3) 311(1)a.1 311(1)a.2 311(1)a.3 311(1)a.4 311(1)a.5 311(1)a.6 311(1)b.1 311(1)b.2 311(1)b.3 311(1)b.4 311(1)c 311(2) PART G 404 405
500(1)a 500(1)b
500(1)c 500(1)d 500(1)e 500(1)f 501(1) 501(2)
501(3) 502 502(4) 502(5) 502(6) 503(a) 503(b) 504(1)a 504(1)b 504(1)c 504(1)d 504(1)e 504(2)a 504(2)b
ITEM NO. 504(2)c 504(2)d 504(2)e 504(3)a 504(3)b 504(3)c 504(3)d 504(3)e 504(3)f 504(4) 505(1) 505(2) 505(3) 505(4) 505(5) 505(6) 505(7) 505(8) 505(9) 506 507 508 509(a) 509(b.1) 509(b.2) 509(c) 510(1) 510(2) 511(1) 511(2) 511(3) PART H 600(1) 600(2) 600(3) 600(4) 600(5) 600(6) 601(a) 601(b) 602(1)a
ITEM NO. 602(1)b 602(2)a 602(2)b 602(3)a 602(3)b 602(4) 603(1) 603(3)a 603(3)b 603(4) 604(1) 604(2) 604(3) 604(4) 605(1)a 605(1)b 605(2)a 605(2)b 605(2)c 605(2)d 605(3)a 605(3)b 605(3)c 605(3)d 606(1) 606(2)a 606(2)b 607(1) 607(2) 608(1) 608(2) 609 610 611(1) 611(2) 612(1) 612(2) 613 620(a) 620(b) 622(1)a
ITEM NO. 622(1)b 622(2)a 622(2)b 622(3)a 622(3)b PART J SPL 2(a) SPL 2(b) SPL 3(a) SPL 3(b)
DESCRIPTION EARTHWORKS Clearing and Grubbing (with Stripping) Individual Removal of Trees (small a,150-300mm Ø) Individual Removal of Trees (small b, 301-500mm Ø) Individual Removal of Trees (large a, 501-750mm Ø) Individual Removal of Trees (large b, 751-900mm Ø) Removal of Structures and Obstruction (other than concrete) Removal of Concrete Bridge Structures Removal of Steel Bridge Structures Removal of Stone Masonry Lined Drainage Structures Removal of Concrete Drainage Structures Removal of RCPC (24" dia.) - 610mm Removal of RCPC (30" dia.) - 760mm Removal of RCPC (36" dia.) - 910mm Removal of RCPC (42" dia.) - 1070mm Removal of RCPC (48" dia.) - 1220mm Removal of RCPC (60" dia.) - 1520mm Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L = 10 ft. Removal of Existing Concrete Pavement (0.23m thk.) Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)) Removal of Existing Asphalt Pavement (100mm thk.) Removal of Sidewalk Removal of Curb Removal of Existing Curbs & Gutter Roadway Excavation (Unsuitable) Roadway Excavation (Surplus Common) Roadway Excavation (Surplus Common) - w/ Backhoe Roadway Excavation (Surplus Soft Rock) - w/ Backhoe Roadway Excavation (Surplus Soft Rock) Roadway Excavation (Surplus Hard Rock) - Blasting Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation) Roadway Excavation (Unclassified) Structure Excavation (Common Soil) Structure Excavation (Soft Rock) Structure Excavation (Solid Rock) Bridge Excavation (Common Soil) Bridge Excavation (Soft Rock) Bridge Excavation (Solid Rock) Foundation Fill Excavation ordered below Plan Elevation Shoring
DESCRIPTION Cribbing/Cofferdamming Pipe Culvert and Drain Excavation Embankment from Borrow Embankment from Roadway Excavation
DESCRIPTION Selected Borrow for topping, case 1 Selected Borrow for topping, case 2 Earth Berm Subgrade Preparation (Common Material) Subgrade Preparation (Existing Pavement) Subgrade Preparation (Unsuitable Material) SUBBASE AND BASE COURSE Aggregate Subbase Course Aggregate Subbase Course (for intermittent Reblocking) Aggregate Base Course Aggregate Base Course (for Reblocking) Crushed Aggregate Base Course Lime Stabilized Road Mix Base Course Portland Cement Stabilized Road Mix Base Course Asphalt Stabilized Road Mix Base Course Portland Cement Treated Plant Mix Base Course SURFACE COURSE Gravel Surface Course (Uncrushed) Crushed Aggregate Surface Course Bituminous Prime Coat (MC Cut-back Asphalt) Bituminous Prime Coat (RC Cut-back Asphalt) Bituminous Tack Coat (RC Cut-back Asphalt) Bituminous Tack Coat (Emulsified Asphalt) Bituminous Seal Coat (Cover Aggregate) Bituminous Seal Coat (MC Cut-back Asphalt) Bituminous Seal Coat (RC Cut-back Asphalt) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150) Bituminous Surface Treatment (Aggregate Grading) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150) Bituminous Surface Treatment (MC Cut-back Asphalt) Bituminous Surface Treatment (RC Cut-back Asphalt) Bituminous Surface Treatment (Emulsified Asphalt) Bituminous Penetration Macadam Pavement (Aggregates) Bituminous Penetration Macadam Pavement (Asphalt Cement) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt) Bituminous Penetration Macadam Pavement (Emulsified Asphalt) Bituminous Road Mix Surface Course (MC Cut-back Asphalt) Bituminous Road Mix Surface Course (Emulsified Asphalt) Aggregate for Bituminous Road Mix Surface Course Bituminous Material for Bituminous Road Mix Surface Course Bituminous Plant Mix Surface Course-General - 50mm thk. Cold Asphalt Plant Mix (Emulsified Asphalt) - 50mm thk.
DESCRIPTION Cold Asphalt Plant Mix (Cut-back Asphalt) - 50mm thk. Bituminous Plant Mix (Stockpile Maintenance Mixture) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Delivered)
DESCRIPTION Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Delivered) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Delivered) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Batching Plant) Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Batching Plant) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Batching Plant) PCC Pavement (Plain) - Conventional Method, 150mm thk. PCC Pavement (Plain) - Conventional Method, 200mm thk. PCC Pavement (Plain) - Conventional Method, 230mm thk. PCC Pavement (Plain) - Conventional Method, 250mm thk. PCC Pavement (Plain) - Conventional Method, 280mm thk. PCC Pavement (Plain) - Conventional Method, 300mm thk. PCC Pavement (Plain) - Using Concrete Paver, 230mm thk. PCC Pavement (Plain) - Using Concrete Paver, 250mm thk. PCC Pavement (Plain) - Using Concrete Paver, 280mm thk. PCC Pavement (Plain) - Using Concrete Paver, 300mm thk. PCC Pavement (Plain) - Conventional Method, 150mm thk. (Using One Bagger Mixer) PCC Pavement (Reinforced), 230mm thk. DRAINAGE AND SLOPE PROTECTION STRUCTURES Reinforcing Steel Bar, Grade 40 (Minor Structures) Structural Concrete Class A (Minor Structures) Pipe Culverts, 610mm dia. (24" Ø) Pipe Culverts, 760mm dia. (30" Ø) Pipe Culverts, 910mm dia. (36" Ø) Pipe Culverts, 1070mm dia. (42" Ø) Pipe Culverts, 1220mm dia. (48" Ø) Pipe Culverts, 1520mm dia. (60" Ø) Underdrain Blind drain Granular Backfill filter material for Underdrains Manhole/Catch Basin/Inlet Concrete Covers Metal Frames and Gratings Metal Frames and Covers (Circular) Drainage Steel Grating w/ Frame (675mm x 975mm Sump Grating) Drainage Steel Grating w/ Frame (715mm x 2000mm Trench Grating) Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia.) - 610mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
DESCRIPTION Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm Cleaning Culvert Pipe in place (610mm dia.) - Half Silted Cleaning Culvert Pipe in place (760mm dia.) - Half Silted Cleaning Culvert Pipe in place (910mm dia.) - Half Silted Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted Reconditioning Drainage Structures Riprap, Class A Riprap, Class B Riprap, Class C Riprap, Class D Grouted Riprap, Class A Grouted Riprap, Class B Grouted Riprap, Class C Grouted Riprap, Class D Filter Layer of Granular Material Stone Masonry Rubble Concrete Hand-Laid Rock Embankment Sheet Piles (Timber) Sheet Piles (Steel) - Slope Protection Sheet Piles (Steel) - Cofferdamming Sheet Piles (Concrete), furnished and driven Bed Course Granular Material Concrete Slope Protection Gabions Mattresses Filter Cloth MISCELLANEOUS STRUCTURES Concrete Curb (Cast in place) Concrete Gutter (Cast in place) Concrete Curb and Gutter, Type A (Cast in place) - National Road Concrete Curb (Precast) Concrete Gutter (Precast) Concrete Curb & Gutter (Precast) Sidewalk (100mm thk.) Sidewalk - Using One Bagger Mixer, (100mm thk.) Right-of-Way Monuments (Cast in place)
DESCRIPTION Right-of-Way Monuments (Precast) Maintenance Marker Posts (Cast in place) Maintenance Marker Posts (Precast) Kilometer Post (Cast in Place) Kilometer Post (Precast) Guide Post Cable Wire Guardrail Metal Guardrail (Metal Beam) including Concrete Post Metal Beam End Piece Guardrail (Timber) Fencing (Barbed Wire) Fencing (Chain Link Fence Fabric) Fencing (Posts) Fencing (Gates) - (Height = 3m & length = 4.24m) Danger/Warning Signs (60cm Triangle) Danger/Warning Signs (90cm Triangle) Regulatory Signs (60cm Triangle) Regulatory Signs (90cm Triangle) Regulatory Signs (60cm Octagon) Regulatory Signs (90cm Octagon) Informative Signs (12" x 24") Informative Signs (12" x 48") Informative Signs (18" x 24") Informative Signs (18" x 48") Pavement Markings (Premix Reflectorized) Pavement Markings (Reflectorized Thermoplastic), White Pavement Markings (Reflectorized Thermoplastic), Yellow Reflectorized Pavement Studs (Flush Type) Reflectorized Pavement Studs (Raised Profile Type) Furnishing and Placing Topsoil Placing Topsoil Sprigging Sodding Trees (Furnishing and Transplanting), 150mm dia. or less Trees (Transplanting), 150mm dia. or less Reflectorized Thermoplastic Pavement Markings (White) Reflectorized Thermoplastic Pavement Markings (Yellow) Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types) Chevron Signs (450mmx600mm) Chevron Signs (600mmx800mm) Bio-Engineering Solutions (Coco-net), CGN 400
DESCRIPTION Bio-Engineering Solutions (Coco-net), CGN 700 Bio-Engineering Solutions (Coco-logs/Fascine), CGR 200 Bio-Engineering Solutions (Coco-logs/Fascine), CGR 300 Bio-Engineering Solutions (Vegetation), Hydroseeding Bio-Engineering Solutions (Vegetation), Vetiver Grass System SPECIAL ITEMS Crack and Seat - Using Backhoe Crack and Seat - Using Arrow Master Tree Planting - With Tree Guard Tree Planting
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
SPL 2(a)
Designation
Crack and Seat sq.m. 35.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Backhoe w/ Breaker (0.80 cu.m.)
1
b. Vibratory Roller (10 m.t.), SP56
1
c. Water Truck (1000 gal.)
1
Sub - Total for B C. Total (A + B) D. Output per hour = 35.0000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Unit
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS Item No./Description Unit of Measurement Output per hour
: : :
SPL 2(b)
Designation
Crack and Seat sq.m. 30.00 No. of Person
A. Labor a. Construction Foreman b. Skilled Laborer c. Laborer
1 1 2
Sub - Total for A Name and Capacity
No of Units
B. Equipment a. Arrow Master D 500
1
(Additional 35% for Oil and Lubricants) b. Vibratory Roller (10 m.t.), SP56 c. Water Truck (1000 gal.)
1 1
Sub - Total for B C. Total (A + B) D. Output per hour = 30.0000 sq.m E. Direct Unit Cost (C ÷ D) Name and Specification F. Materials
Sub - Total for F G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies & Miscellaneous (OCM) Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
Unit
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1 1 1
No. of Hours
109.19 79.70 61.44
Rental Rate
109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
S
Amount
Nam B. Equipment
0.75
2,074.95 1,507.00
2,074.95 1,130.25
0.10
1,065.00
106.50
1.00
3,311.70 3,623.47 103.53 Quantity
Unit Cost
a. Cargo Truck (5 T)
b. Water Truck (1000 gal.)
Minor Tools (10% of Labor
S
C. D. Output per hour = 60.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials
a. Saplings b. Coco Lumber c. Assorted CWN (1 kg./10 d. Fertilizers
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
0.00 103.53 9.32 8.28 14.54 135.66
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
RICE ANALYSIS (DUPA) Item No./Description Unit of Measurement Output per hour No. of Hours
Hourly Rate
Amount A. Labor
1 1 1
No. of Hours
109.19 79.70 61.44
Rental Rate
109.19 79.70 122.88
a. Construction Foreman b. Laborer
311.77
S
Amount
Nam B. Equipment
1.00
1,485.84
1,485.84
a. Cargo Truck (5 T)
b. Water Truck (1000 gal.) 0.75 0.10
1,507.00 1,065.00
1,130.25 106.50
Minor Tools (10% of Labor
2,722.59 3,034.36 101.15 Quantity
Unit Cost
S C. D. Output per hour = 60.0000 E. Direct Unit Cost (C ÷ D)
Amount
Name F. Materials a. Saplings b. Fertilizers
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
0.00 101.15 9.10 8.09 14.20 132.54
S G. H. I. J. K.
Direct Unit Cost (E + F) Overhead, Contingencies Contractor's Profit (CP) Value Added Tax (VAT) Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
SPL 3(a)
Designation
Tree Planting pc. 60.00 No. of Person
No. of Hours
Hourly Rate
1 10
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
1
0.25
712.00 1,065.00
Unit
Quantity
Unit Cost
pc. bd.ft. kg. kg.
1 8 0.08 0.10
50.00 20.00 68.00 50.00
Sub - Total for A Name and Capacity
1000 gal.)
% of Labor)
Sub - Total for B Total (A + B) = 60.0000 pc Name and Specification
(1 kg./100 bd.ft.)
Sub - Total for F 9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
ngencies & Miscellaneous (OCM)
DETAILED UNIT PRICE ANALYSIS (DUPA) : : :
SPL 3(b)
Designation
Tree Planting pc. 60.00 No. of Person
No. of Hours
Hourly Rate
1 10
1 1
109.19 61.44
No of Units
No. of Hours
Hourly Rate
1
0.25
1
0.25
712.00 1,065.00
Sub - Total for A Name and Capacity
1000 gal.)
% of Labor)
Sub - Total for B Total (A + B) = 60.0000 pc Name and Specification
Unit
Quantity
Unit Cost
pc. kg.
1 0.10
50.00 26.00
Sub - Total for F
ngencies & Miscellaneous (OCM)
9% of G 8% of G 12% of (G + H + I) (G + H + I + J)
ALYSIS (DUPA)
Amount
109.19 614.40
723.59 Amount
178.00 266.25 72.36
516.61 1,240.20 20.67 Amount
50.00 160.00 5.44 5.00
220.44 241.11 21.70 19.29 33.85 315.95
ALYSIS (DUPA)
Amount
109.19 614.40
723.59 Amount
178.00 266.25 72.36
516.61 1,240.20 20.67 Amount
50.00 2.60
52.60 73.27 6.59 5.86 10.29 96.01