Submission of Proposed Breakdown of Lump sum Amount (28 Days) (14.1)
Sign of Contract Agreement (28 Days) (8.1)
First Estimate of Payment Submission (42 Days) (14.4) No Receiving of IPC Reply (42 Days) (16.1)
Commencement of Works (28 Days) (8.1) Submission of Performance Security (28 Days) (8.1)
Agreement on Insurances (8.1)
Issuance of IPC by Engineer (28 Days) (14.6)
IPC Request (14.6) (28 Days) (1.1.3.1) Base Date of Date Submission of Tender
Receiving of Letter of Acceptance (LOA) by Contractor (4.2)
Delay in IPC by Employer (21 Days) (16.1) Request to show Employer Financials (28 Days) (2.4)
Notification to Employer for Claim (28 Days) (20.1)
Submission of Full Detail Claim by Contractor (42 Days) (20.1) Notice of Commencement (7 Days) (8.1)
Termination by the Employer (28 Days) (15.5) After Late Dates: Contractor Receives Notice Employer Return Performance Security
Programme Submission (28 Days) (8.3)
PRE-CONSTRUCTION PHASE
Engineer Replacement (42 Days) (3.4)
Engineer’s Reply (21 Days) (4.2)
Contractor Termination of Contract (21 Days) (16.1) Suspension of Work (21 Days) (16.1) Testing (24 hrs to engr.) (7.4)
Force Majeure Awareness Notification (14 Days) (19.2) Termination Notice (Force Majeure) (84/140 Days) (19.6) Submission of Statement at Completion (84 Days) (11.3) Suspension of Work (84 Days) (8.11)
Taking Over Certificate (10.1)
Decision by DAB after Receiving Reference (84 Days) (20.4)
Floating Deliverables
Contractor request to Proceed…. Engineer’s Reply Termination by (28 Days) Contractor (8.11) (8.11)
Final Statement (56 Days) (14.11)
Issuance of T.O or Rejection (28 Days) (10.1)
Issuance of Final Payment Certificate (28 Days) (14.13)
Defect Remedial (Further Tests) (28 Days) (11.6)
Notice to other Party if Dissatisfied (28 Days) (20.4) Arbitration Initiation (56 Days) (20.5)
EXECUTION PHASE
Decided Deliverables
Payment of Remaining Half of Retention Money (14 Days) Release of (14.9) Performance Certificate (10.1)
Notice by the Contractor (14 Days) (10.1) Claim after notification (28 Days) (17.5)
FIDIC General Conditions Timeline
Payment of First Half of Retention Money (14 Days) (14.9)
Maximum Defect Liability Period (02 Years) (11.3)
OPERATION & MAINTENANCE PHASE