Loading documents preview...
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102&106 – PHASE 1
TURN DOWN RATIO STUDY REPORT
Document Number 135355-01-REP-06-012
Project No.: 135355
00
19-05-14
Issued for Review
VHN
NVP
NTS
Rev
Date
Purpose of Issue
Prepared By
Checked By
PVE
PTSC
APPROVED
PVGAS Approval
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
TABLE OF CONTENTS 1.0
INTRODUCTION ............................................................................................................... 3
1.1
PROJECT DISCRIPTION .................................................................................................... 3
1.2
PURPOSE OF DOCUMENT ................................................................................................ 5
2.0
GENERAL INFORMATION AND REQUIREMENT ................................................... 5
2.1
LANGUAGE AND UNITS OF MEASUREMENT ............................................................. 5
2.2
ABBREVIATION AND DEFINITION ................................................................................ 5
2.2.1 Definition............................................................................................................................... 5 2.2.2 Abbreviations ........................................................................................................................ 6 3.0
BASIS AND ASSUMPTION .............................................................................................. 6
3.1
THERMO-DYNAMIC AND SIMULATION PACKAGE .................................................. 7
4.0
TURN DOWN & AVERAGE TEMPERATURE SIMULATION CASE SCHEME ... 8
5.0
TURN DOWN RATIO RESULTS AND CONCLUSION ............................................... 8
6.0
REFERENCE DOCUMENT............................................................................................ 12
7.0
APPENDICES ................................................................................................................... 12
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 2 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
1.0
INTRODUCTION
1.1
PROJECT DISCRIPTION Thai Binh gas field was discovered in 2006 through Thai Binh-1X exploration well which discovered gas accumulation in two separate sand packages of Middle Miocene U220 (4 distinctly separate intervals, interval 1 to 4) and Lower Miocene U250 (2 distinctly separate intervals, interval 5 and 6). Total Thai Binh Gas Initially In Place (TB GIIP) of 139.8 Bscf was approved in Thai Binh - Reserves Assessment Report (RAR) 2010. However, due to the lack of evidence on the fault seal between the main area with the northern portion of interval 5, an upside potential of 30 Bscf remains to be unlocked during development phase. Thai Binh field development will focus mainly on the central area with a proven connected volume of 97Bscf in interval 3 and 5. In the event the northern portion is found to be isolated by a sealing fault, an additional long reach well might be required in the 11th year to sustain the 20 mmscfd required gas sale volume. Thai Binh development plan consists of a Wellhead platform (WHP) with minimum facilities. The gas will be sold ex-platform as full well stream (FWS) to shore via a 25 km pipeline. Thai Binh development is expected to deliver its peak gas production of 20 mmscfd from 2 wells. Individual well capacity can deliver the gas production up to 20 mmscfd. Thai Binh Field Development can be summarized as follows: -
To commit with Gas Sale Agreement (GSA) of 20 mmscfd for a period of 8 + 2 years on a commercially acceptable gas price.
-
To drill 2 wells to develop 74 Bscf of gas recovery from main sand of Miocene reservoirs (interval 3 & 5), and to prove up the northern area connectivity of 30 Bscf in interval 5.
-
Installation of a 3 legged well head platform with 4 slots.
-
Minor reservoirs to be developed later as behind casing opportunities i.e. add perforation or through infill drilling
Petro Vietnam Gas Joint Stock Corporation (PVGas) is responsible for the development of Thai Binh - Ham Rong Gas Distribution and Gathering System Project to transport gas from Ham Rong field (Block 106), Thai Binh field (Block 102) and Other fields (Hong Long, Sapa Nam, Hong Ha- Block 103 & 107) to industrial zones in Thai Binh and neighboring provinces in the North of Vietnam. Phase 1 of the Project includes facilities on Thai Binh Platform, Gas Distribution Center (GDC) and gas transport pipeline connecting Thai Binh field to GDC as followings: -
Platform topside facilities include Pig launcher and Corrosion Inhibitor skid.
-
Spool is installed for connections from Ham Rong field, other fields
-
Tie-in point for LNG exports FPSO in the future.
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 3 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
-
The pipeline from Thai Binh Platform to GDC shall be designed with additional capacity to service other platforms 106, 103 & 107. It shall include: ¾ Approximately 13.1 km from TBDP-A to LFP at Con Thu islet. ¾ Approximately 5.28 km from LFP to LFS. ¾ Approximately 5.8 km from LFS to onshore GDC.
In Tien Hai GDC, the 3 phase separator and filter/separator will be expected to install in order to separate water, flit solid object, take condensate and sale gas. Condensates will be stored and send out by truck loading system. Sales gas will be supplied to industrial customers via pipeline or by CNG trailers. According to the approved Field Development Plan (FDP), the First gas schedule is targeted on 15th June 2014. However, the above schedule will be updated according to the First gas schedule of Petronas Overseas SDN. BHD (PCOSB), expected to complete on Q2, 2015
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 4 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
Figure 2 – Onshore facilities 1.2
PURPOSE OF DOCUMENT The objective of this document is to propose turn down ratio about flowrate and duty of Equipments / Level control valves, Pressure control valves based on simulating cases of the Thai Binh - Ham Rong Gas Distribution and Gathering Project to ensure consistency and safety in operating equipment.
2.0
GENERAL INFORMATION AND REQUIREMENT
2.1
LANGUAGE AND UNITS OF MEASUREMENT The content, references, attachments and any supplementary information for all engineering documents shall be in English. Units of measurement for all engineering documents shall be in the System International (SI).
2.2
ABBREVIATION AND DEFINITION
2.2.1 Definition COMPANY
Petro Vietnam Gas Project Management Company (PVGAS-PMC)
CONTRACT
The EPC contract between COMPANY and CONTRACTOR for execution of the EPC works of
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 5 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
PROJECT EPC CONTRACTOR/ CLIENT
PETROVIETNAM TECHNICAL CORPORATION (PTSC)
SERVICES
PROJECT
Thai Binh – Ham Rong Gas Distribution And Gathering System Project, Block 102 & 106 – Phase 1
PURCHASER
As defined in the PO
PVE
PV Engineering J.S.C - An entity subcontracted by PTSC to perform the detailed engineering design.
VENDOR
The supplier of the materials, plant or equipment as determined by this Specification and other associated documents as attached to the Material Requisition
2.2.2 Abbreviations
3.0
GDC
Gas Distribution Center
LFS
Land Fall Station
LFP
Land Fall Point
API
American Petroleum Institute
ASTM
American Society for Testing and Material
BCV
Building Code of Vietnam
ISO
International Organization for Standardization
TCVN
Vietnamese Codes and Standards
TD(R)
Turn down (Ratio)
BASIS AND ASSUMPTION The following data, information and assumption are used to basic on modeling and showing the equipment turn down ratio at turn down condition as well as other condition. The selection and consideration case SS-4D in Flow Assuarance Report as turn down case with following condition:
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 6 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
AMB. Temp.
CASE
TURNDOWN CASE
SS-4D
OTHER CASEs
SS-1C/D/K; SS-2C/C1/G SS-3C/C1/G
Min
Total Flowrate, Mmscfd
10
Inlet Temp. @ TBWHP oC
38.38
Pressure, Barg
Temp, oC
TB
LFS
GDC
LFS
GDC
15.8
14.4
14
14.6
4.07
The detail results showns in Process Simulation Report 135355-01-REP-06-001
The Production specification and requirement to be kept same concept with all simulation cases The following provisions for pressure drop is considered in various equipments (these pressure drops to be updated after have final data from Equipments Vendors) Table 3.1: Pressure Drop in Various Equipments Pressure Drop Equipment
3.1
(kPa)
(psi)
Separator (Vessel)
20
2.900
Filter Separator
30
4.351
Heat exchanger
30
4.351
Heater
50
7.252
Metering
50
7.252
Pump
50
7.252
THERMO-DYNAMIC AND SIMULATION PACKAGE The process simulation models are built using the HYSYS Process Simulation Program, (Version v8.0). The Peng Robinson (PR) equation of state (EOS) has been selected as the fluid property package to generate process simulation. Design Compositions and flow rates to be used for this simulation are provided in the following sections, these dates are taken from document: “135355-01-BOD-04001_Process and Utility Basis of Design”
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 7 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
4.0
TURN DOWN SIMULATION CASE SCHEME
5.0
TURN DOWN RATIO RESULTS AND CONCLUSION The following results based on simulation cases thence taken turndown ratio for each of equipment / valve about flowrare as well as duty at corresponding units. The detailed result is tabulation below:
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 8 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
Table 5.1: The Turndown ratio result of Equipment /Valves in Thai Binh –Ham Rong Project
Unit
1
2
3
4
Desciption
GDC pressure control valve
Tag no.
PCV435
HP Separator LCV420A liquid outlet
Level control valve at LCV420B upstream LP Separator LP level control valve
LCV413A
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 9 of 12
Required TDR
Actually TDR
(Min / Max)
(Min / Max)
Cases
Cv’s Opening
Cv’s Opening Flowrate (Am3/h)
Valve’s Cv
Remark
(Calculation)
(from FA)
Valve’s Cv
4D/3C
64.6/3480
10/90
712/4206
222.4/1308
19/55
Selection Requied Cv & Opening Following catalog Fisher’s Valve.
0.08/13.6
10/100
15 (*)
12.12
90
- Min Q (continuous) = 0.107 m3/h
(%)
(%)
- Max Q (surge liquid volume) = 15m3/h
4D 0.08/13.6
10/100
0.11/7.5
0.09/6.2
5/80
4D/3G
0.24/27.2
10/100
1.37/5.63
0.56/1.9
10/30
1C/3G
0.24/27.2
10/100
0.67/5.63
0.5/1.9
10/30
0.02/4.8
10/100
1.44
3.23
82
- Volume (LAH-LAL) = 93.56 m3
Selection Requied Cv & Opening Following catalog Fisher’s Valve Selection Requied Cv & Opening Following catalog Fisher’s Valve
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
Unit
5
Desciption
Tag no.
Cases (in FA)
Required TDR
Actually TDR
(Min / Max)
(Min / Max)
Flowrate (Am3/h)
Duty (kW)
Remark
Duty
Flowrate (Am3/h)
(kW)
0.53/3
7.86/170
- Converted Ratio Q: 17.3/100
Condensate Heater 1C
-
- Converted Ratio Pow: 4.6/100
1/100 H401 (**) 4D
- Converted Ratio Q: 19/100 0.57/3
21.5/170 - Converted Ratio Pow: 12.6/100
6
LP Condensate Pumps
- Converted Ratio Q: 15/100 P402AB
4D
10/100
0.39/3
0.04/0.31
- Converted Ratio Pow: 12.9/100 - Volume working: 0.58 m3
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 10 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
Notes: General recommendation: The minimum flowrate of Pumps & Valves is shown based on the worst simulation cases at continuous condition. The maximum flowrate is calculated in on-specification condition in worst case such that covering system. Selection Requied Valve’s Cv as well as Opening follow catalog Fisher’s Valve. (See detailed in Appendix 2) Selection Requied Electric Heater’s duty follow catalog Vulcanic’s Vendor (Thyristor) and Chromalox. (See detailed in Appendix 3) The controlling concept will base on actual condition to have corrected suitable pump duty as well as opening percent of valve to ensure consistency and stabilization processing operating. These information shown on table as referency and the Selection Requied Cv & Opening percent of Valves will be finally confirmed and advise by Valve Vendor. Recommendation for valves LCV-420A/B (*): LCV-420A: In case of flowrate at 15 m3/h (maximum) and turndown flowrate at 0.11 m3/h required large range of valve opening. Therefor, consider to install a LCV line for normal operation case. LCV-420B: In case of volume flowrate at turndown condition is reducing more than max fowrate. The operator will supervised and considered valve’s opening percent suitable with actual condition to maintain gas / condensated level is consistency at NLL. About the range of valve opening level (%) will be clarified after had Vendor’s supply confirmed. Recommendation for valves LCV-413A (*): This valve will be operated at on-off stated corresponding with LAH-NLL (0.36 m3) in 15 minutes. The flowrate is used to size for this valve of 1.44 m3/h and will be confirmed by Valve Vendor when LP Separator’s dimension be available. Recommendation for Heater H-401 (**): The range of electric heater duty (%) will be clarified after had Vendor’s supply confirmed
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 11 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 & 106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
Recommendation for Pumps P-401A/B (***): Pump will operator at continuous condition to always maintain fluid to temperature exchange with condensate fluid. In case of turn down, the flowrate will be reducing appreciable. Considering install a bypass line with a LCV / globe valve to adjust back flow based on liquid arrival during operation modes to Heat exchange equipment to ensure steadily operating process. 6.0
7.0
REFERENCE DOCUMENT 1. 135355-01-REP-06-004
Flow Assurance Study Report
2. 135355-01-REP-06-001
Process Simulation Report
APPENDICES 1. THE SCHEME OF SIMULATION CASE 1C,3C,3G,4D 2. VENDOR CATALOG FOR SELECTING LEVEL CONTROL VALVE 3. VENDOR CATALOG FOR SELECTING ELECTRIC HEATER’s DUTY 4. P&IDs
Document No.: 135355-01-REP-06-012 Rev. 00 Page No.: 12 of 12
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 &106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
APPENDIX 1 – THE SCHEME OF SIMULATION CASE 1C, 3C, 3G, 4D (05 Page including this cover)
Document No. : 135355-01-REP-06-012 APPENDIX 1_Rev. 00 Page No.: 1 of 1
THAI BINH HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT CASE SIMULATION : CASE 1 BASE CASE - MAX GAS (CASE 1C IN FA) Gas Sources: TB 2013 : 20 MMSCFD Min Pressure @ GDC : 14 barg Temperature @ WHP : 38.38 oC Max Ambient Temperature
Fuel Gas Heater DUTY
0.2692
Feed Temperature
kW
36.36
C
Product Temperature 51.49
C
SPRDSHT-1
3-Gas From Filter
A1: HCDew 28.53
Temperature 36.36
C
Pressure
1471
kPa
Molar Flow
19.76
MMSCFD
A Q_FG
op-102
1-To HP Separator Temperature 36.52
C
Pressure
1501
kPa
Molar Flow
20.00
MMSCFD
3-Gas From Filter
TB WHP 2013
To Fuel Gas System
TEE-100
Filter Separator F-401
BAL-3
Temperature 38.38
C
Pressure
1866
kPa
Molar Flow
20.00
MMSCFD
2-Gas To Filter
1-To HP Separator
FG To PCV
Fuel Gas Heater
To TEG
Liquid From Filter
Metering
Water in Oil
Water
A
TEE-102
Duty 3.508
W2
Oil in Water (ppm) 2000
13-Condensate From Heat Exchanger
kW
8-Fluid To Heater MIX-101
Actual Volume Flow
0.5285
m3/h
9-Fluid From Heater Actual Volume Flow
VLV-100
1
To Closed Drain Temperature
37.17
C
Pressure
131.3
kPa
Molar Flow
0.1781
MMSCFD
S SET-1
0.6718
m3/h
C
Pressure
kPa
151.3
8-Fluid To Heater
9-Fluid Heater From Heater
10-Fluid To LP Separator
LP Separator PCV
DUTY
7.863
14-Condensate To Tank
Q
LP Separator V-402
Heater
Pressure Drop
kW
B
20-To Oily Water Treatment
Condensate Tank TK-401
TVP @ 38 oC
64.54
kPa
TVP @ 45 oC
73.40
kPa
Water (% Volume) 0.3408
BAL-6
15-Condensate Product
Condensate Specification
TVP at 38_degC
B
P-101
11-Condesate From LP Separator
18-Off Gas to Flare
17-Vent
Closed Drain Vessel Water to Treatment System
1.000
Q_Heater
Gas to Flare
To Closed Drain
MIX-102
2.358
Vapour Fraction @ 250 barg 4oC
Temperature 75.00
BAL-5 6-Water from HP Separator
50.00
Mol composition (CO2+N2)
10-Fluid To LP Separator Q_Pump
Oil in Water
Water in Oil (%vol) 1.000
0.0000
Water content (mg/SCM)
P-100
Cond PreHeater
ADJ-2
Oil and Water Separation
Calorific Value (LHV MMBTU/SCM) 3.537e-002
12-Condensate To Heat Exchanger
Cond PreHeater
ADJ-1 Prod Header
Calorific Value (HHV MMBTU/SCM) 3.914e-002
Sales Gas Properties
7-Liquid From HP MIX-100 Separator
A
Sales Gas Specification
Sulfur Content (ppm)
L1 TEE-101
MMSCFD
GP
Water from TEG
Liquid HP Separator V-401
kPa
3.057e-002
250barg_4oC
ADJ-4
WHP Production
C
801.3
BAL-4
5-Sales Gas
A
TEG
48.53
Pressure Molar Flow
19-Fuel Gas
FG PCV
Temperature
B
4-Gas To Metering Skid
B TB WHP 2013
19-Fuel Gas
GP
ADJ-3
C
TVP at 45_degC
16-Oily Water From LP Separator
BASE CASE-MAX GAS-TEG.HSC
THAI BINH HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT CASE SIMULATION : CASE 7 MAX CASE - MAX GAS (CASE 3C IN FA) Gas Sources: TB 2013+HR+Other Fields : 53.4 MMSCFD Min Pressure @ GDC : 14 barg Temperature @ WHP : 28.6 oC Max Ambient Temperature
SPRDSHT-1 A1: HCDew
20.90
C
A GP
ADJ-3 Temperature
28.60
C
Temperature
29.01
C
Pressure
3525
kPa
Pressure
1501
kPa
Molar Flow
20.00
MMSCFD
Actual Volume Flow
4206
m3/h
3-Gas From Filter
TEE-100
HR from WHP
BAL-3
2-Gas To Filter
1-To HP Separator
28.60
C
Pressure
3525
kPa
Liquid HP Separator V-401
MMSCFD Other from WHP
7-Liquid From HP MIX-100 Separator
A Water in Oil
Water
Temperature
28.60
C
Water in Oil (%vol)
1.000
Pressure
3525
kPa
Oil in Water (ppm)
2000
Molar Flow
28.00
MMSCFD
VLV-100
ADJ-2
S
3.930e-002
Calorific Value (LHV MMBTU/SCM)
3.554e-002
Duty
6.220
kW
Sales Gas Properties
12-Condensate To Heat Exchanger
Q_Pump 13-Condensate From Heat Exchanger
Temperature
75.00
C
Pressure
151.3
kPa
Q_Heater
8-Fluid To Heater
9-Fluid Heater From Heater
Pressure Drop
Heater DUTY
17.10
Q
Condensate Tank TK-401
11-Condesate From LP Separator
18-Off Gas to Flare 10-Fluid To LP Separator
LP Separator PCV
kW
LP Separator V-402
B TVP at 38_degC
15-Condensate Product
Condensate Specification TVP @ 38 oC
59.63
kPa
TVP @ 45 oC
69.27
kPa
Water (% Volume)
BAL-6
14-Condensate To Tank 20-To Oily Water Treatment
0.0000
Vapour Fraction @ 250 barg 4oC
BAL-5
P-101
3.309
Mol composition (CO2+N2)
B
Water to Treatment System
50.00
Water content (mg/SCM)
17-Vent
Closed Drain Vessel
0.0000
Sulfur Content (ppm)
GP
Gas to Flare
To Closed Drain
SET-1
Cond PreHeater
MIX-101
1 MIX-102
A
Calorific Value (HHV MMBTU/SCM)
P-100
Oil in Water W2
250barg_4oC
Cond PreHeater
A
TEE-102 Oil and Water Separation
BAL-4
10-Fluid To LP Separator
ADJ-1 Prod Header
Other from WHP
6-Water from HP Separator
TEE-101
Metering
5-Sales Gas
ADJ-4 Water from TEG L1
Temperature
Sales Gas Specification
B
TEG
Liquid From Filter
19-Fuel Gas
FG PCV
4-Gas To Metering Skid
WHP Production
HR from WHP
op-102
FG To PCV
Fuel Gas Heater
To TEG
B
5.400
To Fuel Gas System
Filter Separator F-401
TB WHP 2013
Molar Flow
Q_FG
1-To HP Separator
TB WHP 2013
0.3344
TVP at 45_degC
16-Oily Water From LP Separator
MAX CASE-MAX GAS-TEG.HSC
THAI BINH HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT CASE SIMULATION : CASE 9 MAX CASE - MAX WATER (CASE 3G IN FA) Gas Sources: TB 2019+HR+Other Fields : 53.4 MMSCFD Max Pressure @ WHP : 35 barg Temperature @ WHP : 28.6 oC Min Ambient Temperature
SPRDSHT-1 A1: HCDew
-3.482
A
19-Fuel Gas
ADJ-3
Q_FG
TB WHP 2019 Temperature
28.60
C
Pressure
3601
kPa
Molar Flow
20.00
MMSCFD
3-Gas From Filter
TEE-100
Filter Separator F-401
TB WHP 2019
HR from WHP
BAL-3
2-Gas To Filter
1-To HP Separator
Temperature
16.52
C
op-102
Pressure
801.3
kPa
L1 Liquid
Temperature 28.60
C
Pressure
3601
kPa
Molar Flow
28.00
MMSCFD
HP Separator V-401
TEE-101
Other from WHP
Water in Oil
Water TEE-102
Water in Oil (%vol)
1.000
Oil in Water (ppm)
2000
ADJ-4
A
Sales Gas Properties
Q_Pump 13-Condensate From Heat Exchanger
Cond PreHeater Duty
15.93
MIX-101
kW
8-Fluid To Heater
9-Fluid From Heater Temperature
114.8
C
Pressure
1801
kPa
A VLV-100
m3/h
5.540
C
Pressure
1881
kPa
Molar Flow
1.900
MMSCFD
Actual Liquid Flow
1.671
m3/h
1.000
11-Condesate From LP Separator
C
Pressure
kPa
151.3
Q_Heater
9-Fluid Heater From Heater
DUTY
88.64
kW
To Closed Drain
18-Off Gas to Flare
10-Fluid To LP Separator
LP Separator PCV
LP Separator V-402
B
17-Vent
Condensate Specification
TVP at 38_degC
B
TVP @ 38 oC
63.65
kPa
TVP @ 45 oC
74.99
kPa
Water (% Volume)
6-Water from HP Separator Temperature
3.603
Vapour Fraction @ 250 barg 4oC
Heater Pressure Drop
Gas to Flare
1 MIX-102
50.00
Mol composition (CO2+N2)
Temperature 75.00
BAL-5
ADJ-5
0.0000
Water content (mg/SCM)
P-100
Actual Volume Flow 5.626
6-Water from HP Separator
3.442e-002
12-Condensate To Heat Exchanger
Oil in Water W2
3.810e-002
Calorific Value (LHV MMBTU/SCM) Sulfur Content (ppm)
GP
Cond PreHeater
ADJ-2
Oil and Water Separation
250barg_4oC
Calorific Value (HHV MMBTU/SCM)
10-Fluid To LP Separator
ADJ-1 Prod Header
BAL-4
5-Sales Gas
Metering
Copy 4 at 20mmscfd
7-Liquid From HP MIX-100 Separator
A
Sales Gas Specification
A
Water from TEG
MMSCFD
B
TEG
Liquid From Filter
3.057e-002
19-Fuel Gas
FG PCV
4-Gas To Metering Skid
WHP Production
Other from WHP
FG To PCV
Fuel Gas Heater
To TEG
B
2
GP
Molar Flow To Fuel Gas System
C
S SET-1
14-Condensate To Tank
Closed Drain Vessel P-101
Water to Treatment System
20-To Oily Water Treatment
0.1762
BAL-6
Condensate Tank TK-401
15-Condensate Product
TVP at 45_degC
Q 16-Oily Water From LP Separator
9 MAX CASE-MAX WATER-TE
s
THAI BINH HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT CASE SIMULATION : CASE 10 TURNDOWN CASE - MIN GAS (CASE 4D IN FA) Gas Sources: TB 2013 : 10 MMSCFD Min Pressure @ GDC : 14 barg Temperature @ WHP : 4.07 oC Max Ambient Temperature
Fuel Gas Heater 0.2940
DUTY
kW
3.879
C
Product Temperature 21.01
C
Feed Temperature
SPRDSHT-1
3-Gas From Filter
A1: HCDew -2.574
C
Temperature 3.879
A
Pressure
1471
kPa
Molar Flow
9.801
MMSCFD
Q_FG
op-102
1-To HP Separator Temperature
4.070
Pressure
1501
Actual Volume Flow 711.5
C kPa
3-Gas From Filter
m3/h
TB WHP 2013
To Fuel Gas System
TEE-100
Filter Separator F-401
BAL-3
Temperature 38.38 Pressure Molar Flow
1681 10.00
2-Gas To Filter
1-To HP Separator
To TEG
4-Gas To Metering Skid
Metering
MMSCFD
TEE-101
TEE-102 Oil and Water Separation
3.011
W2
2000
kW
m3/h
8-Fluid To Heater
m3/h
Pressure Drop
8-Fluid To Heater MIX-101
Actual Volume Flow 0.5709 9-Fluid From Heater
GTF used in PRV datasheet 6-Water from HP Separator
VLV-100
1
Gas to Flare
To Closed Drain
MIX-102
To Closed Drain 4.372
C
Pressure
131.3
kPa
Actual Volume Flow 0.1115
Actual Volume Flow 1.365
S
Temperature
4.372
C
Pressure
131.3
kPa
SET-1
P-101 Q
0.3936
Temperature 75.00
C
Pressure
kPa
21.50
2.366
kW
Vapour Fraction @ 250 barg 4oC
1.000
m3/h
LP Separator V-402
kW
B TVP at 38_degC
B
15-Condensate Product
Condensate Specification TVP @ 38 oC
61.81
kPa
TVP @ 45 oC
72.68
kPa
Water (% Volume) 0.2217
BAL-6
Condensate Tank TK-401
Mol composition (CO2+N2)
18-Off Gas to Flare
10-Fluid To LP Separator
LP Separator PCV
m3/h
20-To Oily Water Treatment
151.3
Heater DUTY
50.00
rpm
11-Condesate From LP Separator
Q_Heater
9-Fluid Heater From Heater
Water content (mg/SCM)
10-Fluid To LP Separator
14-Condensate To Tank Water to Treatment System
2.187e-002
BAL-5
Closed Drain Vessel
m3/h
Power
17-Vent
Water to Treatment System
Actual Volume Flow 0.1071
Temperature
Speed Capacity(Actual Vol. Flow)
13-Condensate From Heat Exchanger
Oil in Water
Water in Oil (%vol) 1.000 Oil in Water (ppm)
Duty
0.0000
Sulfur Content (ppm) P-100
Q_Pump
Cond PreHeater
ADJ-2
Calorific Value (LHV MMBTU/SCM) 3.488e-002
P-100
Cond PreHeater
A
Calorific Value (HHV MMBTU/SCM) 3.861e-002 250barg_4oC
BAL-4
12-Condensate To Heat Exchanger
7-Liquid From HP MIX-100 Separator
A Water in Oil
Water
MMSCFD Sales Gas Specification
Sales Gas Properties
Water from TEG
ADJ-1 Prod Header
5-Sales Gas
ADJ-4
Liquid HP Separator V-401
kPa
3.057e-002
GP
L1
kPa
C
801.3
Molar Flow
19-Fuel Gas
FG PCV
17.43
Pressure
A
TEG
Liquid From Filter
WHP Production
C
Fuel Gas Heater
416AB in
Temperature
B
B TB WHP 2013
19-Fuel Gas
GP
ADJ-3
C
TVP at 45_degC P-102150
1515 16-Oily Water From LP Separator 413A
CASE 10 TURNDOWN CASE-TEG.
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 &106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
APPENDIX 2 – VENDOR CATALOG FOR SELECTING LEVEL CONTROL VALVE (03 Page including this cover)
Document No.: 135355-01-REP-06-012 -APPENDIX 2 _Rev. 00 Page No.: 1 of 1
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 &106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
APPENDIX 3 – VENDOR CATALOG FOR SELECTING ELECTRIC HEATER’s DUTY (05 Page including this cover)
Document No.: 135355-01-REP-06-012 -APPENDIX 3 _Rev. 00 Page No.: 1 of 1
DATA SHEET FOR POWER CONTROL PANEL • •
500KW/400V/50Hz/Single Stage Main Incoming Rated @ 900 Amps
The power control panel is installed in safe area, indoor condition. FEATURES :
•
Type of electrical panel o o o o o o o
•
Material o o o
• •
Floor Mounted Fitted with mounting plinth 100mm Approximate overall dimensions: High = 2000 mm, Width = 1800 mm, Depth = 500 mm Weight : 650 kG Approximate Single tier enclosure. Lifting rings for handling and transportation. Protection class: min. IP 42.
Mild steel Colour manufacturers standard RAL 7035 Thickness of the panel:1.5 mm
Min/Max ambient temperature: 5°C/35°C. Cooling: o Fan with filter (+5°C/+35°C)
ELECTRICAL CONNECTIONS :
The panel is provided with a removable, undrilled and non-magnetic gland plate for the contractor cables. • • • •
Electrical supply: Bottom entry directly onto copper bars. Power outlets: Bottom entry directly onto copper bars. Auxiliaries and Sensors: Bottom entry onto terminals. Cable glands: Excluded.
CONTROL PANEL FUNCTION:
•
Rev 1
To control the power and monitor the temperature of one number 500 kW heater Tag No. TBC.
MODIFICATIONS
DATE
Made
Initial Enquiry
23/12/2013
BH
Made by : BH Date : 23/12/2013 Checked by: VE Date :
Chkd
Rev
MODIFICATIONS
DATA SHEET FOR POWER CONTROL PANEL 500kW Control Panel
DATE
Made
N° 202643-CPDS
Page
Chkd
Rev 1 1
/5
DATA SHEET FOR POWER CONTROL PANEL
TEMPERATURE REGULATION DEVICE CARRIED OUT BY :
• • •
Heater power will be controlled to achieve a preset outlet temperature. In Remote - Electrical power controlled by hardwired, proportional 4-20mA control signal with remote set point from DCS. In Local – Power to the heater would be controlled from panel mounted potentiometer with manual set point adjustment.
POWER CONTROL DESCRIPTION :
•
Power control: Power fed to the heater would be modulated from 1% to 100% as controlled by the 4-20mA control signal. Power regulation would achieved by thyristor ..
•
Power control device : The heater will be fully Thyristor controlled as follows:o
•
o o o o
1
Thyristor
The thyristor will be provided with high-speed fuse protection, and will have the following specification:o o
Rev
1% - 100%
Rated at 849 Amps Control technique: Burst or Single cycle zero crossover firing. The thyristors are cycled on for a period, and then off. By varying the length of the on period relative to the off period the power to the load may be controlled. Thyristor to modulate power in two of the three phases. Total Harmonic Distortion < 5%. Single Harmonic < 3%. Thyristor failure to include. • Fuse failure. • Over temperature detection on thyristors
MODIFICATIONS
DATE
Made
Initial Enquiry
23/12/2013
BH
Made by : BH Date : 23/12/2013 Checked by: VE Date :
Chkd
Rev
MODIFICATIONS
DATA SHEET FOR POWER CONTROL PANEL 500kW Control Panel
DATE
Made
N° 202643-CPDS
Page
Chkd
Rev 1 2
/5
THAI BINH – HAM RONG GAS DISTRIBUTION AND GATHERING SYSTEM PROJECT, BLOCK 102 &106 – PHASE 1 TURN DOWN RATIO STUDY REPORT
APPENDIX 4 – P&IDs (03 Page including this cover)
Document No.: 135355-01-REP-06-012 -APPENDIX 4 _Rev. 00 Page No.: 1 of 1