PROYECTO ENTIDAD FECHA

PRESUPUESTO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE PROVINCIA DE ANGARAES - DEPARTAMENTO DE HUANCAVELICA" : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE : JULIO DEL 2020 GASTOS COSTO DIRECTO

ESPECÍFICA DE GASTOS

DESCRIPCION

UND

CANT

P. UNITARIO PARCIAL

TOTAL

I. CON APORTE DEL PROGRAMA 2 . 6 . 2 3 . 2 4 COSTO DE CONSTRUCCIÓN POR ADMINISTRACIÓN DIRECTA - PERSONAL MANO DE OBRA PARTICIPANTE hh 37,790.9744 2 . 6 . 2 3 . 2 5 COSTO DE CONSTRUCCIÓN POR ADMINISTRACIÓN DIRECTA - BIENES CEMENTO (PUESTO EN OBRA) CEMENTO PORTLAND TIPO I (42.5 kg) BOL IMPLEMENTOS DE SEGURIDAD CASCOS CON TAPASOL, BARBIQUEJO Y CORTAVIENTO GUANTES DE PROTECCIÓN, SEGÚN EL TIPO DE TRABAJO LENTES DE SEGURIDAD MASCARILLAS PONCHOS O CHALECOS POLOS ZAPATOS DE SEGURIDAD Y/O BOTAS DE JEBE FAJAS ERGONÓMICAS BOTIQUIN

184,231.00 4.875

184,231.00 99,201.00 47,719.00

1,800.72

26.50

47,719.00

95.00 245.00 95.00 245.00 95.00 245.00 245.00 95.00 1.00

18.00 8.00 8.00 8.00 20.00 20.00 50.00 30.00 513.00

1,710.00 1,960.00 760.00 1,960.00 1,900.00 4,900.00 12,250.00 2,850.00 513.00

3.00 3.00 4.00 4.00 5.00 5.00 6.00 7.00 8.00 8.00 8.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 12.00 15.00 15.00 15.00 20.00 20.00 20.00 20.00 20.00 20.00 25.00 26.00 35.00 50.00 74.00 74.00 100.00 202.00 500.00

30.00 70.00 70.00 12.00 80.00 16.00 24.00 27.00 16.00 5.00 5.00 6.00 60.00 120.00 12.00 40.00 28.00 15.00 60.00 70.00 12.00 35.00 25.00 145.00 16.00 23.00 16.00 25.00 14.00 1.00 30.00 90.00 8.00 38.00 25.00 2.50 1.50 2.70

90.00 210.00 280.00 48.00 400.00 80.00 144.00 189.00 128.00 40.00 40.00 60.00 600.00 1,200.00 120.00 400.00 280.00 150.00 600.00 840.00 180.00 525.00 375.00 2,900.00 320.00 460.00 320.00 500.00 280.00 25.00 780.00 3,150.00 400.00 2,812.00 1,850.00 250.00 303.00 1,350.00

28,803.00 UND PAR UND UND UND UND PAR UND

HERRAMIENTAS MANUALES INFLADOR DE LLANTAS UND WINCHA METALICA CON MANGO DE 50 M Und. CIZALLA DE ACERO DE 18" UND CORDEL DE NYLON X 100 M UND BARRETA HEXAGONAL 1 1/4" X 1.80 M UND CINCELES PUNTA DE ACERO UND SERRUCHO DOBLE HOJA UND ESCUADRA GRANDE 0.60CM UND ARCO DE SIERRA REFORZADO UND BRUÑA DE ACERO DE MEDIO UND BRUÑA O CANTONERA DE ACERO UND BALDES DE 20L UND COMBA GRANDE DE 12 LIBRAS INC/MANGO UND COMBA GRANDE DE 20 LIBRAS INC/MANGO UND ESCOBA DE NYLON Und. COMBA MEDIANO DE 8 LIBRAS INC/MANGO UND FLEXOMETRO DE 8ml UND PLOMADA UND TOMACORRIENTES CON CABLE N° 12 DE 60M UND CILINDRIO DE PLASTICO DE 50 GAL UND ALICATE UNIVERSAL UND KIT DE LLANTA PARA BOOGUIES UND OREJERA DE PROTECCION UND BUGUI CON NEUMATICO INC/RODAJE REFORZADO CON LOGOTI UND FLEXOMETRO DE 5ml UND MARTILLO CABEZA NEGRA PESADO UND NIVEL DE BURBUJA O MANO ALUMINIO DOBLE 0.60CM UND PLANCHA DE PULIR DE METAL DE ACERO INOXIDABLE UND PALETA DE PVC MEDIANO UND SOLAQUEADOR TIPO ESPONJA MEDIANOS UND RASTRILLOS METALICOS UND REGLA DE ALUMINIO DE 2X4X6 PESADO UND HOJA DE SIERRA No 018 UND PICOS CON MANGO DE PLASTICO UND LAMPAS CON MANGO DE PLASTICO UND SACOS Und. MANGUERA TRANSPARENTE DE 3/8 REFORZADO UND PLASTICO DOBLE ANCHO ML

22,679.00

PROYECTO ENTIDAD FECHA

PRESUPUESTO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE PROVINCIA DE ANGARAES - DEPARTAMENTO DE HUANCAVELICA" : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE : JULIO DEL 2020 GASTOS COSTO DIRECTO

ESPECÍFICA DE GASTOS

DESCRIPCION

UND

CANT

P. UNITARIO PARCIAL

SUB TOTAL (1): DOSCIENTOS TREINTA Y DOS MIL NOVECIENTOS NOVENTA CON 00/100 SOLES

TOTAL 283,432.00

II. CON APORTE DE LA MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE 2 . 6 . 2 3 . 2 5 COSTO DE CONSTRUCCIÓN POR ADMINISTRACIÓN DIRECTA - BIENES COMBUSTIBLE (PUESTO EN OBRA) GASOLINA 84 OCTANOS PETROLEO D-2

172,901.00 1,900.80

gal gal

110.00 11.00

15.80 14.80

1,738.00 162.80

ACERO CORRUGADO DE 1/2" (PUESTO EN OBRA) ACERO CORRUGADO DE 1/2"

UND

382.00

3.80

1,451.60

ACERO CORRUGADO DE 3/4" (PUESTO EN OBRA) ACERO CORRUGADO DE 3/4"

UND

218.00

3.80

828.40

ACERO CORRUGADO DE 3/8" (PUESTO EN OBRA) ACERO CORRUGADO DE 3/8"

UND

500.00

3.80

1,900.00

ACEROS (PUESTO EN OBRA) ALAMBRE NEGRO RECOCIDO N° 8 ALAMBRE NEGRO RECOCIDO N° 16 CLAVOS PARA MADERA CON CABEZA DE 2" CLAVOS PARA MADERA CON CABEZA DE 3" ABRAZADERA DE FIERRO FUNDIDO PARA TUBO DE 2" MARCO DE FIERRO FUNDIDO PARA BUZON

kg kg kg kg und pza

346.00 492.00 105.00 120.00 1.00 5.00

5.50 5.50 5.50 5.50 6.50 80.00

1,903.00 2,706.00 577.50 660.00 6.50 400.00

TUBERIAS Y ACCESORIOS (PUESTO EN OBRA) TUBERIA PVC SAP PARA AGUA C-5 EC DE 2" TUBERIA PVC SAP C-5 Ø 3/4" (PARA CONEXION LOSAS) TUBERIA PVC DN 160MM ISO - 4435 - UF S-20 TUBERIA PVC PARA DESAGUE 160 X 6m NTP ISO 4435 S-25 TUBERIA PVC SAP C-10 Ø 1" TUBERIA PVC SAP PRESION C-10 EC Ø 1/2" CODO PVC ISO 4435 160 MM S-25 CODO PVC AGUA DOBLE CAMPANA S/P 1/2"X90° ADAPTADOR PVC SAP DE 1/2" CACHIMBA PVC ISO 4435 S-25 160 mm a 160 mm INC ANILLO NIPLE PVC 7.5 X 3/4"-REEMP MEDIDOR 1/2"

m m m und m m und und und und und

27.00 280.00 141.00 1.00 144.00 7.00 1.00 2.00 3.00 1.00 1.00

5.00 3.50 32.00 140.00 6.20 1.80 38.00 2.50 2.50 35.00 3.50

135.00 980.00 4,512.00 140.00 892.80 12.60 38.00 5.00 7.50 35.00 3.50

CEMENTO (PUESTO EN OBRA) CEMENTO PORTLAND TIPO I (42.5 kg)

bol

1,538.68

26.50

40,774.94

PIEDRA CHANCADA Y OTROS(PUESTO EN OBRA) PIEDRA CHANCADA DE 1/2"-3/4" GRAVILLA PIEDRA LAJA e=5 CM

m3 m3 m2

197.00 3.00 218.00

120.00 100.00 35.00

23,640.00 300.00 7,630.00

AGREGADOS Y SIMILARES (PUESTO EN OBRA) ARENA FINA ARENA GRUESA HORMIGON

m3 m3 m3

13.00 183.00 24.00

120.00 85.00 75.00

1,560.00 15,555.00 1,800.00 -

MATERIAL DE CANTERA AFIRMADO Y SIMILARES (PUESTO EN OBRA) MATERIAL GRANULAR S.A1A-A1B AASHTO

48

159.00

25.00

3,975.00

1,451.60

828.40

1,900.00

6,253.00

6,761.40

40,774.94

31,570.00

18,915.00

5,620.00

PROYECTO ENTIDAD FECHA

PRESUPUESTO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE PROVINCIA DE ANGARAES - DEPARTAMENTO DE HUANCAVELICA" : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE : JULIO DEL 2020 GASTOS COSTO DIRECTO

ESPECÍFICA DE GASTOS

DESCRIPCION

UND

AFIRMADO

m3

MURO DE ADOBE ADOBE 0.40 X 0.30 X0.12 M BARRO PREPARADO PAJA DE FIBRA FINA

und m3 kg

MADERAS (PUESTO EN OBRA) REGLA DE MADERA MADERA EUCALIPTO ROLLIZO 3" X 3 m. MADERA TORNILLO 1"X8"X10' TRIPLAY DE 4 X 8 X 19 MM

P. UNITARIO PARCIAL 47.00 35.00 1,645.00

CANT

TOTAL

4,550.50 2,647.00 14.00 6.00

1.50 20.00 50.00

3,970.50 280.00 300.00

25.00 18.00 6,378.00 33.00

5.00 5.00 5.50 120.00

125.00 90.00 35,079.00 3,960.00

39,254.00 p2 p2 p2 pln

MATERIALES DE FERRETERIA (PUESTO EN OBRA) GRASA AMARILLA ASFALTO RC-250 MARCO Y TAPA DE CONCRETO REFORZADO PARA MEDIDOR DE TECNOPOR DE 1"X4X8' CAL BOLSA 25 kg YESO BOLSA 28 kg OCRE TAPA DE CONCRETO ARMADO C/PERFIL F°G° 0.60 TAPA CONCRETO ARMADO DESAG 0.3X0.6 M CAJA DE CONCRETO PARA CONEXIONES DOMICILIARIAS CAJA DE CONCRETO P/MEDIDOR AGUA PEGAMENTO PLASTICO PVC LUBRICANTE PARA TUBERIA PVC UF SELLADOR ELASTICO POLIURETANO ADITIVO IMPERMEABILIZANTE LIJA PARA MADERA LETRINA DOMICILIARIA PREFABRICADA DE 1.20 X 1.20 CINTA TEFLON CINTA SEÑALADORA AMARILLA ANILLO DE JEBE PARA TUBERIA PVC ISO 4435 DN 160 MM LLAVE DE PASO PVC 1/2" (INC.TUER-NIPLE) GUANTES DE JEBE ESCOBA MOLDE METALICO PARA BUZON PERNO DE 5/8" CON TUERCA Y HUACHA 5" WINCHA HIPOCLORITO DE CALCIO 70% ZARANDA ESPUMA DE POLYOLEFINA D=1 1/4" CORDEL CORPORATION RT-NIPLE-TUERCA-EMPAQ. 1/2"

kg gal und m2 bol bol kg und und und und gal gal gal kg pln und rll m und und par und und und und kg und m m und

2.00 33.00 1.00 58.00 3.00 2.00 25.00 5.00 1.00 1.00 1.00 0.25 7.00 7.00 33.00 2.00 2.00 1.00 280.00 27.00 2.00 2.00 2.00 2.00 6.00 1.00 0.25 30.00 74.00 25.00 1.00

12.00 25.00 45.00 14.00 10.00 12.50 12.30 50.00 80.00 65.00 45.00 95.00 18.00 102.00 10.00 2.50 814.81 1.50 0.50 8.00 12.00 12.00 12.00 180.00 6.00 120.00 20.00 35.00 30.00 0.50 8.50

24.00 825.00 45.00 811.97 30.00 25.00 307.50 250.00 80.00 65.00 45.00 23.75 126.00 714.00 330.00 5.00 1,629.62 1.50 140.00 216.00 24.00 24.00 24.00 360.00 36.00 120.00 5.00 1,050.00 2,220.00 12.50 8.50

9,578.34

CARPINTERIA METALICA SEÑAL INFORMATIVA 2 SENTIDOS INC. POSTE Y COLOCACION

und

1.00

235.00

235.00 -

PINTURAS Y SIMILARES (PUESTO EN OBRA) PINTURA ESMALTE BLANCO TRAFICO PINTURA ESMALTE PARA TRAFICO PINTURA NEGRO TRAFICO PINTURA ESMALTE SINTETICO 1/8 gl PINTURA ANTICORROSIVA THINNER IMPRIMANTE PARA ELASTOMERICO DE POLIURETANO XILOL

gal gal gal und gal gal gal gal

0.50 7.00 0.50 0.50 0.50 6.50 1.00 3.50

45.00 45.00 45.00 45.00 45.00 18.00 20.00 15.00

22.50 315.00 22.50 22.50 22.50 117.00 20.00 52.50

235.00

594.50

PROYECTO ENTIDAD FECHA

PRESUPUESTO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE PROVINCIA DE ANGARAES - DEPARTAMENTO DE HUANCAVELICA" : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE : JULIO DEL 2020 GASTOS COSTO DIRECTO

ESPECÍFICA DE GASTOS

DESCRIPCION

IMPLEMENTOS DE SEGURIDAD CASCOS CON TAPASOL, BARBIQUEJO Y CORTAVIENTO GUANTES DE PROTECCIÓN, SEGÚN EL TIPO DE TRABAJO (3) LENTES DE SEGURIDAD MASCARILLAS (3) ZAPATOS DE SEGURIDAD Y/O BOTAS DE JEBE (3) FAJAS ERGONÓMICAS

UND

CANT

P. UNITARIO PARCIAL

1,220.00 UND PAR UND UND PAR UND

10.00 10.00 10.00 10.00 10.00 10.00

18.00 8.00 8.00 8.00 50.00 30.00

180.00 80.00 80.00 80.00 500.00 300.00

KIT DE MATERIAL DE CAPACITACION KIT DE MATERIAL DE CAPACITACION

glb

1.00

450.00

450.00

KIT DE MATERIAL PARA MITIGACION KIT DE MATERIAL PARA MITIGACION

glb

2.00

450.00

900.00

kg und gal und

4.00 1.00 1.50 2.00

14.00 9.52 32.00 15.00

56.00 9.52 48.00 30.00

KIT DE LIMPIEZA DETERGENTE BOLSA LEJIA PAPELERA DE PLASTICO

450.00

900.00

143.52

2 . 6 . 2 3 . 2 6 COSTOS DE CONSTRUCCIÓN POR ADMINISTRACIÓN DIRECTA - SERVICIOS MANO DE OBRA CAPACITADOR TECNICO DE OBRA glb 1.00 TOPOGRAFO Mes 1.00 OPERARIO Mes 20.00 OFICIAL Mes 10.00

128,895.00 68,779.00 1,500.00 1,279.00 2,300.00 2,000.00

1,500.00 1,279.00 46,000.00 20,000.00

IDENTIFICACIÓN DE OBRA (PUESTO EN OBRA) SUMINISTRO E INSTALACION DE IMPRESION DE BANNERS DE CARTEL DE OBRA SEGÚN DISEÑO

346.00 m2

8.65

40.00

346.00

PLACA RECORDATORIA

550.00

PLACA RECORDATORIA S/DISEÑO Y CALIDAD (70 CM Y 42 CM) INCLUIDO MURETE S/DISEÑO

und

ALQUILER DE EQUIPOS TOPOGRÁFICOS ESTACION TOTAL INC. ACCESORIOS NIVEL TOPOGRAFICO INC. ACCESORIOS

DIA MES

MAQUINARIA LIVIANA PLANCHA COMPACTADORA COMPACTADOR VIB. TIPO PLANCHA 4.0 HP COMPACTADOR VIB. TIPO PLANCHA 5.8 HP VIBRADOR DE CONCRETO 4 HP 1.25" MEZCLADORA DE CONCRETO DE 9 -11P3 PISON MANUAL EQUIPO DE PRUEBA HIDRAULICA

MAQUINARIA PESADA RETROEXCAVADOR DE 1/2 A 1/4 yd3 MOTONIVELADORA DE 125 HP CAMION VOLQUETE DE 15 m2 RODILLO LISO VIBR AUTOP 101-135HP 10-12T PRUEBAS DE LABORATORIO

TOTAL

1.00

550.00

550.00

3.00 2.00

70.00 250.00

210.00 500.00

hm hm hm hm hm hm hm

44.00 50.00 7.50 217.00 265.00 20.00 2.00

25.00 15.00

1,100.00 750.00 120.00 3,255.00 7,950.00 40.00 10.00 -

hm hm hm hm

40.00 4.00 185.00 3.00

180.00 235.00 180.00 250.00

710.00

13,225.00

16.00 15.00 30.00 2.00 5.00

42,190.00 7,200.00 940.00 33,300.00 750.00 1,595.00

PROYECTO ENTIDAD FECHA

PRESUPUESTO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE PROVINCIA DE ANGARAES - DEPARTAMENTO DE HUANCAVELICA" : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE : JULIO DEL 2020 GASTOS COSTO DIRECTO

ESPECÍFICA DE GASTOS

DESCRIPCION

UND

CANT

PRUEBA : ROTURA DE PROBETA DISEÑO DE MEZCLA DE CONCRETO PRUEBA PROCTOR MODIFICADO Y DENS. CAMPO PRUEBA DENSIDAD DE CAMPO

und und und und

15.00 2.00 2.00 4.00

ALQUILER DE LOCAL PARA OBRA ALQUILER DE LOCAL

mes

3.00

P. UNITARIO PARCIAL 25.00 375.00 300.00 600.00 150.00 300.00 80.00 320.00

TOTAL

1,500.00 500.00

1,500.00

SUB TOTAL (2): CIENTO TRECE MIL OCHO CON 00/100 SOLES

301,796.00

TOTAL PRESUPUESTO COSTO DIRECTO

585,228.00

PRESUPUESTO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA PROYECTO CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE - PROVINCIA DE ANGARAES - DEPARTAMENTO DE HUANCAVELICA" ENTIDAD : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE FECHA : JULIO DEL 2020 COSTO INDIRECTO ESPECÍFICA DE GASTOS

DESCRIPCIÓN

UND

CANT

P.UNITARI O

PARCIAL

TOTAL

I. CON APORTE DE LA MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE GASTOS DE OPERACIÓN 2 . 6 . 2 3 . 2 5 COSTO DE CONSTRUCCIÓN POR ADMINISTRACIÓN - BIENES UTILES DE ESCRITORIO CUADERNO DE OBRA (100 Folios) UND HOJAS BOND DE 75 GR MILLAR FOLDER MANILA A4 CON FASTHENER DOC LAPICERO 031 FINE DOC LAPIZ TIPO PORTAMINAS UND PERFORADORES MEDIANOS M-81 UND EMGRAPADOR TIPO TIJERA Y PLEGABLE MEDIANOS UND LIBRETA DE NOTAS UND ARCHIVADORES T/OFICIO UND CUADERNO ESPIRAL DE PASTA GRUESA DE 200 HOJAS UND PAPEL LUSTRE DOC COLA SITETICO UND BORRADOR UND RESLTADOR UND CORRECTOR UND

900.00 900.00 4.00 15.00 6.00 3.00 2.00 3.00 2.00 4.00 10.00 2.00 2.00 2.00 4.00 3.00 4.00

50.00 25.00 7.00 12.00 10.00 15.00 15.00 8.00 6.00 10.00 3.50 3.00 1.00 3.00 3.50

200.00 375.00 42.00 36.00 20.00 45.00 30.00 32.00 60.00 20.00 7.00 6.00 4.00 9.00 14.00

2 . 6 . 2 3 . 2 6 COSTOS DE CONSTRUCCIÓN POR ADMINISTRACIÓN DIRECTA - SERVICIOS SERVICIOS PERSONALES RESIDENTE DE OBRA ASISTENTE TÉCNICO DE OBRA ASISTENTE ADMINISTRATIVO MAESTRO DE OBRA ALMACENERO GUARDIANIA PLAN DE MONITOREO ARQUEOLOGICO ARQUEOLOGO OTROS SERVICIOS DE TERCEROS SEGURO DE PARTICIPANTES

73,852.00 59,600.00

MES MES MES MES MES MES INFORME MES

3.00 3.00 3.00 3.00 3.00 3.00 1.00 1.50

5,000.00 2,500.00 2,000.00 3,000.00 1,100.00 1,100.00 9,500.00 4,000.00

15,000.00 7,500.00 6,000.00 9,000.00 3,300.00 3,300.00 9,500.00 6,000.00

GLB

1.00

8,658.00

8,658.00

14,252.00

AGUA PARA CONSUMO HUMANO GLB 1 5594 5,594.00 SON: SESENTA Y CUATRO MIL DOSCIENTOS SESENTA Y CUATRO CON 00/100 SOLES

74,752.00

GASTOS DE SUPERVISIÓN DE OBRA 2 . 6 . 2 3 . 2 6 COSTOS DE CONSTRUCCIÓN POR ADMINISTRACIÓN DIRECTA - SERVICIOS SERVICIOS NO PERSONALES INGENIERO SUPERVISOR LIQUIDACIÓN DE OBRA

MES MES

3.00 1.00

21,000.00

6,000.00 3,000.00

18,000.00 3,000.00

20,000.00 0.00

20,000.00 0.00

2. 6 . 8 1 . 3 1 ELABORACIÓN Y EVALUACION DE EXPEDIENTE TÉCNICO ELABORACIÓN DE EXPEDIENTE TÉCNICO GLB 1.00 EVALUACION DE EXPEDIENTE TECNICO GLB 1.00 SON: CUARENTA Y DOS MIL CON 00/100 SOLES

20,000.00

41,000.00

SUB TOTAL: CIENTO SEIS MIL DOSCIENTOS SESENTA Y CUATRO CON 00/100 SOLES

115,752.00

TOTAL PRESUPUESTO COSTO INDIRECTO

115,752.00

PROYECTO ENTIDAD FECHA ESPECÍFICA DE GASTOS

RESUMEN CUADRO ANALÍTICO DE GASTOS : "MEJORAMIENTO DE SERVICIO DE TRANSITABILIDAD VEHICULAR Y PEATONAL DEL JIRÓN LIMA CUADRA N°08 DE LA LOCALIDAD DE HUAYLLAY GRANDE DEL DISTRITO DE HUAYLLAY GRANDE - PROVINCIA DE ANGARAES DEPARTAMENTO DE HUANCAVELICA" : MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE : JULIO DEL 2020 TIPO DE GASTO

I. CON APORTE DEL PROGRAMA 2.6.23.24 COSTO DE CONSTRUCCIÓN POR ADMINISTRACION DIRECTA-PERSONAL 2.6.23.25 COSTO DE CONSTRUCCIÓN POR ADMINISTRACION - BIENES SUB TOTAL (1): PRESUPUESTO DEL PROYECTO

MONTO (S/)

184,231.00 99,201.00 283,432.00

II. CON APORTE DE LA MUNICIPALIDAD DISTRITAL DE HUAYLLAY GRANDE 2.6.23.25 2.6.23.26 2.6.81 .31

COSTO DE CONSTRUCCIÓN POR ADMINISTRACION - BIENES COSTOS DE CONSTRUCCIÓN POR ADMINISTRACION DIRECTA - SERVICIOS ELABORACIÓN DE EXPEDIENTE TÉCNICO SUB TOTAL (2): PRESUPUESTO DEL PROYECTO

173,801.00 223,747.00 20,000.00 417,548.00

RESUMEN TOTAL DE CUADRO ANALÍTICO DE GASTOS ESPECÍFICA DE GASTOS 2.6.23.24 2.6.23.25 2.6.23.26 2.6.81 .31

TIPO DE GASTO COSTO DE CONSTRUCCIÓN POR ADMINISTRACION DIRECTA-PERSONAL COSTO DE CONSTRUCCIÓN POR ADMINISTRACION - BIENES COSTOS DE CONSTRUCCIÓN POR ADMINISTRACION DIRECTA - SERVICIOS ELABORACIÓN Y EVALUACION DE EXPEDIENTE TÉCNICO TOTAL PRESUPUESTO DEL PROYECTO

MONTO (S/) 184,231.00 273,002.00 223,747.00 20,000.00 700,980.00