KIKEH SPAR OFFSHORE HOOK-UP & COMMISSIONING PROJECT
PROJECT HSE PLAN
ATTACHMENT 1 HSE OBJECTIVES To manage the KIKEH SPAR projects in the most cost-effective and safe manner with the full co-operation of all teams at the Hook-up and Commissioning works sites to meet Clients' aspiration and business commitments HSE PERFORMANCE GOALS TMM/EJJV Safety target on KIKEH SPAR for offshore HUC Project are tabulated as follows: No.
QUANTITY Sub-Contactors TMM/EJJV & Vendors 0 case
HSE TARGET ITEMS
1
Fatal Accident
2
Lost Time Injury (LTI)
0 case
3
Medical Treatment Case (MTC)
0 case
4
First Aid Injury (FAI)
0 case
5
Fire/Explosion
0 case
6
Near Misses Incident until end of the project
0 case
7
Man-hours LTI free (by the end of the project)
50,000
8
No. of day LTI free
60
9
LTI Frequency rate
0 case
HSE INCENTIVE SCHEME: TMM/EJJV Management proposed the following safety incentive scheme award to employees involved in the KIKEH SPAR HUC upon achieving the following: No. 1.
Safety Achievement LTI Free and completion of Project ahead of schedule
Safety Award Items T-shirts or Wind-breakers with safety slogan
Recipients All Workers
2.
Highest contribution in ACT program (Unsafe Act & Condition) during project execution
Token in the form of bag with safety slogan
Best & Safety conscious Workers by trade discipline