Loading documents preview...
"MEJORAMIENTO DE LOS SERVICIOS DE CULTURA, DEPORTE y RECREACION EN EL PARQUE ZONAL H
NTT. +0.80
NPT. +1.04 CAMINO PEATO NAL
NPT. +0.78 NPT. +0.75 NPT. + 0.18
PISCINA PATERA NPT. 0.00 NPT. +0.38 NPT. +0.75
NPT. + 0.08
3
PISCINA SEMIOLIMPICA
-0.75
NPT. - 0.20
NPT. +0.40
NPT. 0.00 NPT. 0.00
NPT. +0.45
NPT. 99.22=0.45
NPT. 0.00
-1.05 PISCINA RECREATIVA
-1.20
NPT. 0.00
NPT. 0.00
CAMINO PEATONAL
NPT. -1.22
NPT. 0.00
NTT. + 0.70
NPT. 0.00
MEJORAMIENTO DE LA PISCINA SEMIOLIMPICA, PATERA y CREACION DE LA PISCINA RECREATIVA
RENOVACIÓN Y MEJORAMIENTO DE CERCOS
CALENDARIO VALORIZADO ACELERADO DE OBRA +AMPLIACION DE PLAZO N° 2 L. P. N°
:
OBRA
:
003-2013-INPE-0IP-CE PRIMERA CONVOCATORIA
"MEJORAMIENTO DE LOS SERVICIOS DE CULTURA, DEPORTE y RECREACION EN EL PARQU ZONAL HUASCAR EN EL DISTRITO DE VILLA EL SALVADOR, PROVINCIA DE LIMA - LIMA"
"MEJORAMIENTO DE LOS SERVICIOS DE CULTURA, DEPORTE y RECREACION EN EL PARQU ZONAL HUASCAR EN EL DISTRITO DE VILLA EL SALVADOR, PROVINCIA DE LIMA - LIMA" CONTRATISTA SUPERVISION
: :
CONSORCIO EDIFICADOR LIMA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L.
JEFE DE SUPERVISION DE OBRA
:
ING. JUAN VARGAS VALVERDE
RESIDENTE
:
ING. MIGUEL HUGO CAMPOMANES MORAN
L PARQUE ZONAL HUASCAR "
MEJ
RENO
O DE OBRA
RECREACION EN EL PARQUE INCIA DE LIMA - LIMA"
E-VO-01.2
Err:507
Valorizaciones de Obra
No:
#REF!
#REF!
#REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
Formato
Contenido
1 E-VO-01.2
Err:507
2 E-VO-14
Err:507
3 E-VO-04.2
Err:507
4
Factura
5 Inspector de ObrErr:507 6 E-VO-03.2
Err:507
7 E-VO-05
Err:507
8 E-VO-06
Err:507
9 E-VO-07.2
Err:507
10 E-VO-08
Err:507
11 E-VO-09
Err:507
12 E-VO-10
Err:507
13 E-VO-11
Err:507
14 E-VO-12
Err:507
15 E-VO-13
Err:507
16
Copia del contrato principal, resoluciones y adendas respectivas
VO-01.2
Página 5
17
Copia de los Índices de Reajuste de Precios emitido por el INEI
18
Copia de Cartas Fianzas Vigentes
19
Anexo Fotográfico
Nota:
0
0
El presente constituye un formato de control que una vez llenado debe colocarse en la primera hoja del expediente, el mismo que deberá contener todos los documentos indicados y en el orden establecido
0
VO-01.2
0
Página 6
Fecha:
Pág
#REF!
Presenta
ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ ÿ VO-01.2
Página 7
ÿ ÿ ÿ
que deberá contener todos los documentos
VO-01.2
Página 8
Err:507
E-VO-03.2 Valorizaciones de Obra /
No: #REF! #REF! #REF! #REF!
#REF!
Fecha:
#REF! #REF! #REF! #REF!
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION D
1) Datos del Adicional de Obra Presupuesto
Mto Aprobado (1)
Resumen del Presupuesto y sus modificaciones PASCO
Deductivos (2)
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
#REF!
-
#REF!
-
IGV
Mto Disp Neto (MDN)
#VALUE!
#REF!
#REF!
#REF!
Resolución Aprob Num:
CONSTRUCTORA C
#VALUE!
#REF!
Fecha de Resol Aprob:
ING. OSCAR HE
#VALUE!
#REF!
#VALUE!
Inicio de los trabajos Adic:
#REF!
Notas (1) Monto según Contrato Original
(2) Sumatoria de los montos deducADS N° 013-2013-INPE-OIP-CEP PRIMERA CONVOCATORIA
2) Histórico de Valorizaciones de Adicional de Obra
664414.7
11/30/2012
E-VO-03.2-1
Página 9
Err:507
E-VO-03.2 Valorizaciones de Obra /
No:
#REF!
Fecha:
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION D
563,063.31 Especialidad
ARQUITECTURA ESTRUCTURAS INST. SANITARIAS INST. ELECTRICAS Val Mensual (V)
MDN
#REF! #REF! #REF! #REF!
% Avance Mensual % Avance Mensual Acumulado
Reajustes por Valorización (Reajustes - Deducciones) Especialidad
ARQUITECTURA ESTRUCTURAS INST. SANITARIAS INST. ELECTRICAS TOTAL REAJUSTES
Val 01
040-2013-INPE-OIP 597,973.24 506,756.98 0.90 75.00 75.00 #REF! #REF! #REF! #REF!
#REF!
Jul/2013
040-2013-INPE-OIP
#REF! #REF!
-
VALORIZACION REAJUSTADA (VR) = (V+R)
Adelanto
ADELANTO DIRECTO ADELANTO MATERIALES TOTAL AMORTIZACION (Amo)
94,455.00 #REF! #REF!
#REF!
-
75.00
Amortización de Adelantos
#REF!
10,000.00 20,000.00
#REF! #REF!
30,000.00 #REF! #REF!
Jul/2013
-
(R)
#REF!
44,455.00 50,000.00
-
#REF!
Val 02
#REF!
#REF!
#REF!
444.00 500.00
-
100.00 200.00
944.00 95,399.00
-
300.00 30,300.00
De la Valorización Mensual = (CD+GG+UU)*FR Pagado (s/IGV)
#REF!
-
Jul/2013
-
Jul/2013
7/19/2013 10/1/2013 83,022.00
E-VO-03.2-1
#REF!
-
#REF!
-
#REF!
-
-
Página 10
Err:507
E-VO-03.2 Valorizaciones de Obra /
No: #REF! #REF! #REF! #REF!
#REF!
Fecha:
#REF! #REF! #REF! #REF!
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION D AMORTIZACION ACUMULADA (AmoAcu) VALORIZACION NETA (VN) = (VR-Amo)
-
83,022.00 -82,947.00
83,022.00 -
E-VO-03.2-1
83,022.00 95,399.00
83,022.00 -
83,022.00 30,300.00
Página 11
Err:507
E-VO-03.2 Valorizaciones de Obra /
No: #REF! #REF! #REF! #REF!
#REF!
Fecha:
#REF! #REF! #REF! #REF!
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION D
Avance Financiero
De la Valorización Mensual = (CD+GG+UU)*FR
Avance Financiero del Mes (AFM) = (VN-R) Avance Financiero = (AF) = Acum de AFM Avance Financiero en % = (MEPC/MC)
#REF!
#VALUE! #VALUE!
94,455.00 #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
30,000.00 #VALUE! #VALUE!
Retenciones y Multas Concepto
FONDO DE GARANTIA RETENCION X GAR. FIEL CUMPL. MULTA POR ATRAZO DE OBRA OTRO TOTAL RETENCIONES (TR)
A Retener
#REF!
040-2013-INPE-OIP
Jul/2013
#REF!
1,000.00
#REF!
#REF!
1,000.00
1,000.00
-
-
-
1,000.00
-
-
Monto a Facturar Concepto
(forma de llenar la factura)
#REF!
NETO I.G.V. = (MF*IGV) MF=
Monto a Entregar al Contta. En Efectivo En IGV
#REF! #REF! #REF!
ME= (VN-TR) I.G.V. = (MF*IGV) (ME + IGV) =
040-2013-INPE-OIP
597,973.24 #REF! #REF! 040-2013-INPE-OIP
Jul/2013
#REF!
506,756.98 #REF! #REF! Jul/2013
#REF! #REF!
#REF!
95,399.00 #REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF!
E-VO-03.2-1
#REF!
30,300.00 #REF! #REF! #REF!
30,300.00 #REF! #REF!
Página 12
Err:507
E-VO-03.2 Valorizaciones de Obra /
No: #REF! #REF! #REF! #REF!
#REF!
Fecha:
#REF! #REF! #REF! #REF!
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION D
Monto Desembolsado Desembolsado Acumulado
(MF + IGV) =
#REF! #REF!
#REF! #REF!
E-VO-03.2-1
#REF! #REF!
Página 13
#REF!
E IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
Adicional de Obra No #REF! #REF! 20-May-2009
Nota Debe elaborarse un cuadro por cada adicional aprobado de obra
01
Inicio Contractual:
#REF!
Venc Ctr Vigente:
#REF!
IGV de Obra:
#REF!
E-VO-03.2-1
Página 14
#REF!
E IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
TOTAL
100,000.00 20,000.00 10,000.00 130,000.00 #REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
-
#REF!
0.00
-
#REF!
0.00
-
#REF!
-
-
#REF!
-
-
#REF!
-
SALDO
#REF! #REF! #REF! -75.00 #REF!
TOTAL
#REF!
1,000.00 200.00 100.00 1,300.00 131,300.00
752,428.24 596,756.98 10,000.90 75.00 1,359,261.12
-
E-VO-03.2-1
1,544.00 900.00 100.00 2,544.00 1,361,805.12
TOTAL
SALDO
41,474.00 41,548.00 83,022.00
-41,474.00 -41,548.00 -83,022.00
Página 15
#REF!
E IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
83,022.00 131,300.00 35,021.98
83,022.00 0.00
83,022.00 -
83,022.00 -
83,022.00 -
83,022.00 -
E-VO-03.2-1
166,044.00 1,278,783.12
Página 16
#REF!
E IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
60,788.48 95,810.46 1,995.51 97,805.97
0.00 1,995.51 #REF!
1,995.51 #REF!
1,995.51 #REF!
1,995.51 #REF!
1,276,239.12 1,995.51 #REF!
0.18*F(-1)C 97,805.97 -22,611.20
#REF!
0.00
#REF!
131,300.00 #REF! #REF! #REF!
131,300.00 #REF! #REF!
#REF!
0.00
#REF!
#REF! #REF! #REF!
#REF! #REF!
#REF!
-
#REF!
#REF! #REF! #REF!
#REF! #REF!
#REF!
-
#REF!
#REF! #REF! #REF!
#REF! #REF!
TOTAL
#REF!
-
#REF!
#REF! #REF! #REF!
#REF! #REF!
-
#REF!
1,000.00 1,000.00
SALDO -
TOTAL
1,361,729.22 #REF! #REF! #REF! 299,073.36 #REF!
#REF! #REF!
E-VO-03.2-1
TOTAL 161,600.00 #REF! 299,073.36
Página 17
#REF!
E IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
E-VO-03.2-1
#REF!
Página 18
Err:507
E-VO-04.2 Valorizaciones de Obra / Obra:
“MEJORAMIENTO DEL SERVICIO DE ALCANTARILLADO EN EL ESTABLECIMIENTO PENITENCIARIO DE ICA”
No:
60552
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA
Adicional de Obra No
ICA
#REF! IGV=
#REF!
(Ver Histor
ICA
VALORIZACION Estructura Inspector de Arquitectura
=+REDONDEAR(FC[-2]/(1+F20C13),2) CONSTRUCTORA CANRI E.I.R.L ING. OSCAR HELI VASQUEZ MATTA
SE HA REALIZADO TRABAJOS PRELIMINARES ,
Inst. Eléctricas Inst. Sanitarias TOTAL VALORIZACIADS N° 013-2013-INPE-OIP-CEP PRIMERA CONVOCATORIA
664414.71 CONTROL DE SALD Monto de la Valori 563063.313559322 Monto de la Valori 040-2013-INPE-OIP 597973.24 Saldo por Valorizar
V=
11/30/2012 7/11/2013
b= c = V+b = SPV = MDN - c =
0
VB = V+(R-D) =
506756.983050848
REAJUSTES DEDUCI0.9 Estructura Arquitectura Inst. Eléctricas Inst. Sanitarias Total Reajustes VALORIZACION BR
75 75
0
0 AMORTIZACIONES 0 Amortización De Adelanto Directo Amortización Del Adelanto Para Materiales 0 TOTAL AMORTIZAC0 VALORIZACION NETA
RETENCIONES Por Fondo De Garantía Por Fiel Cumplimie Multa Por Atraso D Otro
7/18/2013 7/19/2013 10/1/2013
Página 19
AM = VN = VB-AM =
Adicional de Obra No
ICA
TOTAL RETENSIONES
Ret =
Monto a Facturar (
NETO = (VN) = IGV = TOTAL = (NETO + IGV) =
Monto a Entregar al Contratista
NETO - Ret = IGV = TOTAL =
Compromiso A Solicitar
NOTAS PARA EL PAGO
Página 20
Fecha:
DO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
#REF!
#REF!
(Ver Historico de Valorizaciones del Adicional ICA)
Monto en NS/.
455,300.00
* *
587.00 1,458.00 * 123.00 *
457,468.00 #REF!
Monto en NS/.
111,100.00 *
568,568.00 #REF! #REF!
Monto en NS/.
36,582.86 525.53 -19.71 222.05
* * * *
37,310.73 494,778.73 Monto en NS/.
100,000.00 * 155,222.00 * 255,222.00 239,556.73
Monto en NS/.
1,000.00 -
* * * *
Página 21
#REF!
#REF!
1,000.00
239,556.73 #REF!
35,021.98 60,788.48
95,810.46 1,995.51 97,805.97 238,556.73 0.18*F(-1)C 97,805.97 #REF! #REF!
#REF!
-22,611.20
#REF!
Página 22
Err:507
E-VO-06 “MEJORAMIENTO DEL SERVICIO DE ALCANTARILLADO
Valorizaciones de Obra /
No:
EN EL ESTABLECIMIENTO PENITENCIARIO DE ICA”
Obra:
Adicional de Obra No
Fecha:
Resolución Aprob Num:
RP 123-2011
Fecha de Resol Aprob:
10-Dec-2011
Inicio de los trabajos Adic:
20-May-2009
60552
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES D
ESTRUCTURAS ICA PRESUPUESTO BASE Area Geografica
May-09 ZONA5
ICA 0.00
K Mo
Inspector de Obra
Simb
=
CONSTRUCTORA CANRI E.I.R.L
ING. OSCAR HELI VASQUEZ MASE HA REALIZADO TRABAJOS PRELIMINARES , EXCAVACION DE ZANJAS PARCIAL, EXCAVACION DE CAMARA SECA Y HUMED Elemento Representativo Cod. Nº Coef. % Incl. Ind. Base Índice Índice Índice Abr-11
1.00
AC
K
May-11
K
May-11
K
0.27
J 47.00
2.00
Abr-11
### 21.00 7/11/2013
100.00%
0.30
E-VO-06
58.00% 42.00%
#VALUE! #VALUE! 586.47 586.47 -
-
0.000
427.68 427.68 578.14 354.74 -
0.000
427.68 427.68 578.14 354.74 -
0.000
Página 23
2.00
3.00
0.30
AC 5.00 43.00
MA
0.167
49.00 4.00
38.92% 61.08%
0.000
#VALUE! #VALUE!
0.000 #VALUE!
0.000
#VALUE! #VALUE!
0.000 #VALUE!
0.000
#VALUE! #VALUE!
0.00 #VALUE!
0.000
#VALUE! #VALUE! -
0.097
-
-
10/1/2013
39.00 FACTOR DE REAJUSTE
0.000
0.000
100.00%
M
GGU
484.31 688.46 420.50 240.64 240.64 -
#VALUE! #VALUE!
-
6.00
#VALUE! #VALUE! -
0.167
0.000
0.000
0.000
0.000
0.000
100.00%
K
0.00
0.000
484.31 688.46 420.50 240.64 240.64 362.29 362.29
0.000
0.000
0.000
0.000
0.000
0.000 0.000 0.000
35,021.98
E-VO-06
Página 24
01 Inicio Contractual:
Sat 14-Feb-09
Venc Ctr Vigente:
Wed 04-Nov-09
IGV de Obra:
18.00%
EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
CA Y HUMEDA ASIMISMO PROVISION DE TUBERIAS DE DESAGUE. Índice Índice Índice May-11
427.68 427.68 578.14 354.74 -
K
0.000
May-11
### ### ### -
K
0.000
May-11
427.68 427.68 578.14 354.74 -
Índice K
0.000
May-11
427.68 427.68 578.14 354.74 -
Índice K
### 0.000 ### ### ###
E-VO-06
Página 25
484.31 688.46 420.50 240.64 240.64 362.29 362.29
0.000 #VALUE! 688.46 0.000 420.50 240.64 0.000 240.64 0.000 0.000 0.000 362.29 0.000 362.29 0.000
0.000
0.000
0.000
0.000
0.000
0.000 0.000 0.000
484.31 688.46 420.50 240.64 240.64 362.29 362.29
0.000
0.000
0.000
0.000
0.000
0.000 0.000 0.000
484.31 688.46 420.50 240.64 240.64 362.29 362.29
0.000 ### ### ### 0.000 ### ### ### 0.000 ### ### ### 0.000 ### ### ### 0.000 ### ### ### 0.000 ### 0.000 0.000
E-VO-06
Página 26
“MEJORA MIENTO DEL SERVICIO DE ALCANTA RILLADO EN EL ESTABLEC IMIENTO PENITEN CIARIO DE ICA”
E-VO-07.2 Valorizaciones de Obra / Obra:
Err:507 No:
Fecha:
60552
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE
25-Nov-2009 180 dc 30 dc 210 dc
Fecha de Inicio Plazo Original Amp Plazo Plazo Ampliado
ICA ICA
Monto Aprobado
ICA
###
Monto a Programar Venc Contr Vigente
827,692.46 c/IGV
Montos Deducidos
3
Calendario No
-
Notas
827,692.46
#VALUE!
###
CONSTRUCTORA CANRI E.I.R.L Inspector de Obra
Item
ING. OSCAR HELI VA SE HA REALIZADO TRABAJOS PRELIMINARES , EXCAVACION DE ZAN
11/25/2009
12/1/2009
1/1/2010
Del
11/30/2009
12/31/2009
1/31/2010
Al
5 dias
30 dias
30 dias
Mes 1
Mes 2
Mes 3
Und.
Descripcion
Metrado
Precio U.
Parcial
001 ESTRUCTURAS 01 OBRAS PRELIMINARES 01.01 Campamento provisional de la obra 36 01.02 Movilizacion de equipo 04.01.01 ……. 04.01.02 ……. 04.10.03 …….
### 11/30/2012 ###
040-2013### ### 0.90 75.00 75.00
7/11/2013
UN
1.00
2,460.18
2,460.18
1,230.09
1,230.09
ES
1.00
12,673.96
12,673.96
6,336.98
6,336.98
KG M3 M2
42,000.00 467.30 1,402.59
5.21 349.18 32.87
218,820.00 163,171.81 46,103.13
E-VO-07.2
65,646.00
153,174.00 163,171.81
Página 27
“MEJORA MIENTO DEL SERVICIO DE ALCANTA RILLADO EN EL ESTABLEC IMIENTO PENITEN CIARIO DE ICA”
E-VO-07.2 Valorizaciones de Obra / Obra:
Err:507 No:
Fecha:
60552
Costo Directo Gastos Generales Utilidad Parcial Parcial x Factor de Relación (FR) Impuesto IGV TOTAL PRESUPUESTO PORCENTAJE DE AVANCE ( % ) PORCENTAJE ACUMULADO DE AVANCE ( Item
-
-
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE 443,229.08 7,567.07 73,213.07 316,345.81 10% 44,544.52 760.49 7,357.91 31,792.75 8% 33,459.36 571.24 5,526.85 23,880.95 0% 521,232.96 8,898.80 86,097.83 372,019.51 96% 500,618.20 8,546.85 82,692.66 357,306.14 0% 500,618.20 8,546.85 82,692.66 357,306.14 2% 17% 71% 2% 18% 90%
Descripcion
Und.
Metrado
Precio U.
Parcial
Mes 1
Mes 2
Mes 3
002 ARQUITECTURA 01 01.01 01.02 19.01 20
OBRAS PRELIMINARES Limpieza de terreno manual Cartel de identificacion de la obra de …. ….
7/18/2013 7/19/2013 10/1/2013
Costo Directo Gastos Generales Utilidad Parcial Parcial x Factor de Relación (FR) Impuesto IGV TOTAL PRESUPUESTO PORCENTAJE DE AVANCE ( % ) PORCENTAJE ACUMULADO DE AVANCE ( % )
M2 UN UN
1,441.00 1.00 1.00
8% 96% 18%
E-VO-07.2
2.48 1,621.55 172,600.00
3,573.68 1,621.55 172,600.00
3,573.68 810.78
810.78
177,795.23 35,021.98 60,788.48 95,810.46 1,995.51 97,805.97 0.18*F(-1)C 97,805.97 -22,611.20
4,384.46 #VALUE! 330.98 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
810.78 #VALUE! 61.21 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Página 28
E-VO-07.2 Valorizaciones de Obra / Obra:
“MEJORA MIENTO DEL SERVICIO DE ALCANTA RILLADO EN EL ESTABLEC IMIENTO PENITEN CIARIO DE ICA”
Err:507 No:
Fecha:
60552
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE
E-VO-07.2
Página 29
E-VO-07.2 Valorizaciones de Obra / Obra:
“MEJORA MIENTO DEL SERVICIO DE ALCANTA RILLADO EN EL ESTABLEC IMIENTO PENITEN CIARIO DE ICA”
Err:507 No:
Fecha:
60552
MEJORAMIENTO DEL SERVICIO DE DESAGUE DE TODO EL E.P DE IVA , QUE CONSISTE EN CONSTRUCCION DE BUZONES, TUBERIAS NUEVAS EXTERIORES DE DESAGUE 40,147.00 12/31/2009 1/31/2010 Parcial Mes 1 Mes 2 Mes 3
RESUMEN DEL PRESUPUEST ESTRUCTURAS ARQUITECTURA INST SANITARIAS INST ELECTRICAS Costo Directo Gastos Generales Utilidad Parcial Parcial x Factor de Relación (FR) Impuesto IGV TOTAL PRESUPUESTO PORCENTAJE DE AVANCE ( % ) PORCENTAJE ACUMULADO DE AVANCE (
### 506,756.98 10% 8% 0.96045
E-VO-07.2
443,229.08 177,795.23
7,567.07 4,384.46
73,213.07 810.78
316,345.81 -
621,024.31 62,412.94 46,881.13 730,318.38 701,434.29 #VALUE! #VALUE!
11,951.53 1,201.13 902.22 14,054.88 13,499.00 #VALUE! #VALUE! #VALUE! #VALUE!
74,023.85 7,439.40 5,588.06 87,051.31 83,608.43 #VALUE! #VALUE! #VALUE! #VALUE!
316,345.81 31,792.75 23,880.95 372,019.51 357,306.14 #VALUE! #VALUE! #VALUE! #VALUE!
Página 30
Resolución Aprob Num: RP 123-2011
Adicional de Obra No
01
Elaborado en función del Diagrama Gantt correspondiente a las partidas del Presupuesto Adicional indicado afectado por los deductivos correspondientes
Fecha de Resol Aprob:
10-Dec-2011
Inicio de los trabajos Adic:
20-May-2009
Incio Contractual:
Sat 14-Feb-09
Venc Ctr Vigente:
Wed 04-Nov-09
IGV de Obra:
18.00%
UEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE.
2/1/2010
3/1/2010
4/1/2010
5/1/2010
6/1/2010
7/1/2010
8/1/2010
9/1/2010
10/1/2010
2/28/2010
3/31/2010
4/30/2010
5/31/2010
6/30/2010
7/31/2010
8/31/2010
9/30/2010
10/31/2010
27 dias
30 dias
29 dias
30 dias
29 dias
30 dias
30 dias
29 dias
30 dias
Mes 4
Mes 5
Mes 6
Mes 7
Mes 8
Mes 9
Mes 10
Mes 11
Total
2,460.18 12,673.96
6,915.47
6,915.47
218,820.00 163,171.81 46,103.13
32,272.19
E-VO-07.2
Página 31
Resolución Aprob Num: RP 123-2011
Adicional de Obra No
01
Elaborado en función del Diagrama Gantt correspondiente a las partidas del Presupuesto Adicional indicado afectado por los deductivos correspondientes
UEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE. 6,915.47 6,915.47 32,272.19 695.00 695.00 3,243.36 522.05 522.05 2,436.23 8,132.52 8,132.52 37,951.78 7,810.88 7,810.88 36,450.79 7,810.88 7,810.88 36,450.79 2% 2% 7% 91% 93% 100% Mes 4
Mes 5
Mes 6
0% 100%
Mes 7
Fecha de Resol Aprob:
10-Dec-2011
Inicio de los trabajos Adic:
20-May-2009
Incio Contractual:
Sat 14-Feb-09
Venc Ctr Vigente:
Wed 04-Nov-09
IGV de Obra:
18.00%
0% 100%
0% 100%
0% 100% Mes 8
0% 100% Mes 9
Mes 10
Mes 11
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
172,600.00 #VALUE! 13,029.57 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
E-VO-07.2
Total 3,573.68 1,621.55 172,600.00 -
172,600.00
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
443,229.08 44,544.52 33,459.36 521,232.96 500,618.20 500,618.20 100%
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
177,795.23 #VALUE! 13,421.76 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Página 32
Resolución Aprob Num: RP 123-2011
Adicional de Obra No
01
Elaborado en función del Diagrama Gantt correspondiente a las partidas del Presupuesto Adicional indicado afectado por los deductivos correspondientes
UEVAS EXTERIORES DE DESAGUE, CAMARA SECA Y HUMEDA DE DESAGUE. 2/28/2010 3/31/2010 4/30/2010 5/31/2010 Mes 4 Mes 5 Mes 6 Mes 7 6,915.47 -
6,915.47 -
32,272.19 -
6,915.47 695.00 522.05 8,132.52 7,810.88 #VALUE! #VALUE! #VALUE! #VALUE!
6,915.47 695.00 522.05 8,132.52 7,810.88 #VALUE! #VALUE! #VALUE! #VALUE!
32,272.19 3,243.36 2,436.23 37,951.78 36,450.79 #VALUE! #VALUE! #VALUE! #VALUE!
-
#VALUE! #VALUE! #VALUE! #VALUE!
6/30/2010 Mes 8 -
#VALUE! #VALUE! #VALUE! #VALUE!
Fecha de Resol Aprob:
10-Dec-2011
Inicio de los trabajos Adic:
20-May-2009
Incio Contractual:
Sat 14-Feb-09
Venc Ctr Vigente:
Wed 04-Nov-09
IGV de Obra:
18.00%
8/31/2010 Mes 10
9/30/2010 Mes 11
7/31/2010 Mes 9 -
#VALUE! #VALUE! #VALUE! #VALUE!
172,600.00
172,600.00 17,346.30 13,029.57 202,975.87 194,948.17 #VALUE! #VALUE! #VALUE! #VALUE!
E-VO-07.2
-
#VALUE! #VALUE! #VALUE! #VALUE!
Total 443,229.08 177,795.23
621,024.31 62,412.94 46,881.13 730,318.38 701,434.29 #VALUE! #VALUE! #VALUE!
Página 33
E-VO-07.1
1.OBRA CONTRATISTA SUPERVISA Fecha de Inicio Plazo Original Ampliaciones Plazo Ampliado
RESUMEN DE CRONOGRAMA VALORIZADO “Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima” CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. 16-Nov-2017 180.00 0.00 180 dc
ITEM
001 002 003 004 005 006
Calendario No Venc Contr Vigente
RESUMEN DEL PRESUPUESTO
UND
CERCO PERIMETRICO ZONA RECREATIVA PISCINAS - ESTRUCTURAS ZONA RECREATIVA PISCINAS - ARQUITECTURA ZONA RECREATIVA PISCINAS - INST. SANITARIAS ZONA RECREATIVA PISCINAS - INST. ELECTRICAS ZONA DE MUNIGRANJA Y ZOO Costo Directo Gastos Generales Utilidad Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
METRADO
P.U.
´01 14-May-2018
Del
11/16/2017
12/1/2017
1/1/2018
2/1/2018
3/1/2018
4/1/2018
5/1/2018
Al Días
11/30/2017 15 dias
12/31/2017 31 dias
1/31/2018 31 dias
2/28/2018 28 dias
3/31/2018 31 dias
4/30/2018 30 dias
5/14/2018 14 dias
Mes 1
Mes 2
Mes 3
Mes 4
Mes 5
Mes 6
Mes 7
PARCIAL
GLB GLB
1.00 1.00
1,435,034.12 2,393,811.38
1,435,034.12 2,393,811.38
GLB
1.00
3,436,119.10
3,436,119.10
-
-
GLB
1.00
884,669.85
884,669.85
-
GLB
1.00
456,102.25
456,102.25
-
GLB
1.00
1,146,495.79
1,146,495.79
8.0000% 7.00% 0.97100 18%
9,752,232.49 780,178.60 682,656.27 11,215,067.36 10,889,829.99 1,960,169.41 12,849,999.40
PORCENTAJE DE AVANCE ( % ) PORCENTAJE ACUMULADO DE AVANCE ( % )
2.OBRA CONTRATISTA SUPERVISA Fecha de Inicio Plazo Original
207,417.97
237,988.12
300,240.65
368,757.72
256,907.15
623,847.73
781,476.32
587,688.08
143,892.10
178,982.48
568,386.05
901,567.86
1,145,724.80
641,457.91
-
70,424.84
119,992.11
241,025.37
291,376.47
161,851.07
-
35,445.33
111,479.32
153,021.14
120,252.54
35,903.91
354,011.68 28,320.93 24,780.82 407,113.43 395,307.13 71,155.28 466,462.41
221,237.10
2,288.02
-
-
90,267.84
157,720.77
153,448.40
244,114.16
334,184.18
166,760.42
921,533.54 73,722.68 64,507.35 1,059,763.58 1,029,030.39 185,225.47 1,214,255.86
1,462,037.87 116,963.03 102,342.65 1,681,343.55 1,632,584.52 293,865.21 1,926,449.73
1,841,234.61 147,298.77 128,886.42 2,117,419.80 2,056,014.55 370,082.62 2,426,097.17
2,052,378.36 164,190.27 143,666.49 2,360,235.11 2,291,788.21 412,521.88 2,704,310.09
2,112,775.09 169,022.01 147,894.26 2,429,691.36 2,359,230.22 424,661.44 2,783,891.66
1,008,261.34 80,660.91 70,578.29 1,159,500.54 1,125,874.98 202,657.50 1,328,532.48
3.6301%
9.4495%
15.0018%
18.8801%
21.0352%
21.6645%
10.3388%
3.63%
13.08%
28.08%
46.96%
68.00%
89.66%
100.00%
RESUMEN DE CRONOGRAMA ACELERADO VALORIZADO DE OBRA + AMP. DE PLA “Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima” CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. 16-Nov-2017 180.00
Ampl. de Plaso N° 2
62.00
Tiempo de Paralizacion
50.00
Plazo Ampliado
97,104.53
292 dc
Calendario No
Venc Contr Vigente
´02
03-Sep-2018
E-VO-07.1
1.OBRA CONTRATISTA SUPERVISA
ITEM
001 002 003 004 005 006
RESUMEN DE CRONOGRAMA VALORIZADO “Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima” CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L.
RESUMEN DEL PRESUPUESTO
UND
CERCO PERIMETRICO ZONA RECREATIVA PISCINAS - ESTRUCTURAS ZONA RECREATIVA PISCINAS - ARQUITECTURA ZONA RECREATIVA PISCINAS - INST. SANITARIAS ZONA RECREATIVA PISCINAS - INST. ELECTRICAS ZONA DE MUNIGRANJA Y ZOO Costo Directo Gastos Generales Utilidad Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
METRADO
P.U.
11/16/2017
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
Al Días
11/30/2017 15 dias
12/31/2017 31 dias
1/31/2018 31 dias
2/28/2018 28 dias
3/19/2018 19 dias
3/31/2018 12 dias
4/30/2018 30 dias
PARCIAL
NOVIEMBRE 131,144.14
DICIEMBRE 134,830.73
ENERO 274,573.59
FEBRERO 75,972.34
405,284.58
301,146.22
703,865.07
101,185.89
18,304.33
51,629.83
114,097.93
70,030.22
44,215.95
-
69,212.72
11,145.11
15,482.50
-
-
4,640.95
-
25,814.35
-
-
5,909.71
-
38,113.79
GLB GLB
1.00 1.00
1,435,034.12 2,393,811.38
1,435,034.12 2,393,811.38
GLB
1.00
3,436,119.10
3,436,119.10
-
GLB
1.00
884,669.85
884,669.85
-
GLB
1.00
456,102.25
456,102.25
GLB
1.00
1,146,495.79
1,146,495.79
8.0000% 7.00% 0.97100 18%
Del
9,752,232.49 780,178.60 682,656.27 11,215,067.36 10,889,829.99 1,960,169.41 12,849,999.40
536,428.73 42,914.30 37,550.01 616,893.04 599,003.12 107,820.56 706,823.68
487,606.78 39,008.54 34,132.47 560,747.80 544,486.10 98,007.50 642,493.60
1,172,299.97 93,784.00 82,061.00 1,348,144.97 1,309,048.71 235,628.77 1,544,677.48
258,333.56 20,666.68 18,083.35 297,083.59 288,468.15 51,924.27 340,392.42
MARZO 45,092.22
ABRIL
INTERRUPCION DE OBRA POR NULID TEMPORAL DE CONTRATO
187,023.14 14,961.85 13,091.62 215,076.61 208,839.38 37,591.09 246,430.47
-
-
PORCENTAJE DE AVANCE ( % )
5.50%
5.00%
12.02%
2.65%
1.92%
0.00%
0.00%
PORCENTAJE ACUMULADO DE AVANCE ( % )
5.50%
10.50%
22.5214%
25.17%
27.09%
0.00%
0.00%
DO
Total
1,435,034.12 2,393,811.38 3,436,119.10 884,669.85 456,102.25 1,146,495.80 9,752,232.49 780,178.60 682,656.27 11,215,067.36 10,889,829.99 1,960,169.41 12,849,999.40 100%
RA + AMP. DE PLAZO N° 2
DO
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
9/1/2018
5/8/2018 8 dias
5/31/2018 23 dias
6/30/2018 30 dias
7/31/2018 31 dias
8/31/2018 31 dias
9/3/2018 3 dias
MAYO
CION DE OBRA POR NULIDAD PORAL DE CONTRATO
-
Total 292 dias
40,363.30
JUNIO 57,543.67
JULIO 358,622.33
AGOSTO 255,786.70
SETIEMBRE 61,105.10
37,370.57
193,498.01
115,434.45
516,146.89
1,575.30
2,393,811.38
80,050.89
293,320.48
1,213,930.68
1,291,703.25
277,139.78
3,436,119.10
47,029.57
47,604.82
592,856.28
101,338.85
53,238.67
60,733.05
175,896.52
135,778.71
61,969.78
229,920.73
513,343.39
290,281.76
6,956.63
1,146,495.79
320,022.78 25,601.82 22,401.59 368,026.19 357,353.42 64,323.62 421,677.04
882,620.75 70,609.66 61,783.45 1,015,013.86 985,578.42 177,404.12 1,162,982.54
2,970,083.66 237,606.69 207,905.86 3,415,596.21 3,316,543.79 596,977.88 3,913,521.67
2,591,036.16 207,282.89 181,372.53 2,979,691.58 2,893,280.41 520,790.47 3,414,070.88
346,776.81 27,742.14 24,274.38 398,793.33 387,228.31 69,701.10 456,929.41
9,752,232.49 780,178.60 682,656.27 11,215,067.36 10,889,830.00 1,960,169.41 12,849,999.40
-
0.00%
3.28%
9.05%
30.46%
26.57%
3.56%
0.00%
30.37%
39.42%
69.88%
96.44%
100.00%
1,435,034.12
884,669.85 456,102.25
100%
CRONOGRAMA VALORIZADO ACELERADO DE AVANCE DE OBRA- CERCO PERIMETRICO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
S/. 87,213.69
DICIEMBRE
ENERO
FEBRERO
JUNIO
JULIO
AGOSTO
SETIEMBRE
11/16/2017
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
9/1/2018
11/30/2017
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
9/3/2018
15 dias
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
3 dias
S/. 525.00
S/. 29,865.00
S/. 20,414.89
S/. 23,925.42
MARZO
01
OBRAS PRELIMINARES
1.01 1.02
TRASLADO DE EQUIPOS Y HERRAMIENTAS CARTEL DE OBRA DE 7.20 x 3.60 M.
glb und
1.03 1.04
CERCO PERIMETRICO PROVISIONAL CASETA PARA ALMACEN, GUARDIANIA Y OFICINA TECNICA
m m2
1.05 1.06
SS.HH. TEMPORAL PARA PERSONAL DE OBRA COMEDOR Y VESTIDORES PARA PERSONAL
mes m2
3.00 S/. 1,400.00 34.00 S/. 80.48
1.07 1.08
INSTALACION PROVISIONAL DE AGUA Y DESAGUE INSTALACION PROVISIONAL DE INSTALACIONE ELECTRICAS
est est
1.09 1.10
CONSUMO DE ENERGIA ELECTRICA Y AGUA POTABLE EQUIPO DE PROTECCION PERSONAL
mes glb
1.11 02
INSUMOS DE PROTECCION GENERAL DE OBRA TRABAJOS PRELIMINARES
glb
2.01 2.02
TRAZO Y NIVELACION INICIO DE OBRA TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA
m m
2372.43 S/. 2.10 2372.43 S/. 2.51
S/. 4,982.10 S/. 5,954.80
S/472.50 S/0.00
S/1,050.00 S/1,757.00
S/2,491.05 S/893.22
S/315.00 S/502.00
S/92.67 S/397.38
2.03 2.04
DEMOLICION DE MURO DE LADRILLO ASENTADO DE SOGA DEMOLICION DE COLUMNAS DE CONCRETO
m2 m3
1854.63 S/. 18.43 49.09 S/. 306.90
S/. 34,180.83 S/. 15,065.72
S/14,784.55 S/6,767.15
S/3,686.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,898.01 S/1,530.80
2.05 2.06
DEMOLICION DE CIMIENTO CORRIDO Y SOBRECIMIENTO LIMPIEZA PERMANENTE DE LA ZONA DE TRABAJO
m3 mes
204.71 S/. 261.14 3.00 S/. 765.00
S/. 53,457.97 S/. 2,295.00
03 3.01 3.02
MOVIMIENTO DE TIERRAS EXCAVACION PARA ZAPATAS DE COLUMNAS EXCAVACION PARA BASE DE MURO DE CONTENCION
m3 m3
52.30 S/. 37.57 83.04 S/. 37.57
S/. 34,495.15 S/. 1,964.91 S/. 3,119.81
3.03
EXCAVACION PARA CIMENTO CORRIDO
m3
24.17 S/. 37.57
3.04
EXCAVACION PARA DADOS DE CONCRETO P/POSTES DE CERCO METALICO
m3
19.96 S/. 37.57
3.05
RELLENO CON MATERIAL PROPIO
m3
3.06 3.07
RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE
04 4.01
1.00 S/. 1,200.00 2.00 S/. 1,274.82
S/. 2,733.59
S/. 2,824.71
S/. 2,824.71
S/. 273.36
S/131.39
S/135.77
S/135.77
S/13.14
S/250.77
S/303.57
S/395.96
S/409.15
S/409.15
S/39.60
S/. 67,585.42 S/. 4,068.45
S/485.40 S/379.49
S/587.59 S/459.38
S/766.42 S/599.19
S/791.97 S/619.17
S/791.97 S/619.17
S/76.64 S/59.92
S/. 4,200.00 S/. 2,736.32
S/0.00 S/0.00
S/65.04 S/125.50
S/78.73 S/151.92
S/102.69 S/198.15
S/106.12 S/204.76
S/106.12 S/204.76
S/10.27 S/19.82
S/. 468.96 S/. 904.90
S/0.00 S/75.00
S/166.42 S/114.42
S/201.46 S/138.50
S/262.77 S/180.66
S/271.53 S/186.68
S/271.53 S/186.68
S/26.28 S/18.07
S/. 1,200.00 S/. 1,500.00
S/73.87 S/. 6,140.64
S/96.35 S/. 8,009.53
S/99.56 S/. 8,276.52
S/99.56 S/. 1,050.55
S/112.18 S/481.04
S/146.32 S/627.44
S/151.19 S/648.36
S/151.19 S/648.36
S/3,508.12 S/1,853.08
S/4,575.81 S/2,417.06
S/4,728.34 S/2,497.63
S/120.00 S/2,549.64
S/120.00
S/. 67,585.42 S/. 4,068.45
S/0.00 S/0.00
S/29,340.00 S/0.00
S/14,670.00 S/2,260.25
S/23,575.42
S/. 4,200.00 S/. 2,736.32
S/0.00 S/0.00
S/0.00 S/0.00
S/700.00 S/0.00
1.00 S/. 468.96 1.00 S/. 904.90
S/. 468.96 S/. 904.90
S/0.00 S/0.00
S/0.00 S/0.00
3.00 S/. 400.00 1.00 S/. 1,500.00
S/. 1,200.00 S/. 1,500.00
S/0.00 S/225.00
S/0.00 S/225.00
1.00 S/. 800.00
S/. 800.00 S/. 115,936.42
S/120.00 S/. 64,123.82
S/41,717.12 S/382.50
S/120.00 S/. 18,998.85
S/11,740.85 S/765.00
S/40.00 S/. 3,422.52
S/0.00 S/38.25
S/150.00 S/80.00 S/. 817.00
S/61.02 S/. 5,072.70
S/0.00 S/0.00
S/153.84
S/. 0.00 S/0.00 S/0.00
S/. 1,482.42 S/33.38 S/0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/186.22
S/242.90
S/. 1,482.42 S/33.38 S/0.00
S/. 1,482.42 S/33.38 S/0.00
S/251.00
S/. 800.00 S/. 115,936.42 S/. 4,982.10 S/. 5,954.80 S/. 34,180.83 S/. 15,065.72
S/251.00
S/0.00
S/0.00
S/0.00
S/0.00
S/90.81
S/90.81
S/90.81
S/635.65
S/. 908.07
S/0.00
S/0.00
S/104.99
S/0.00
S/64.49
S/64.49
S/64.49
S/451.44
S/. 749.90
84.05 S/. 25.04
S/. 2,104.61
S/0.00
S/0.00
S/0.00
S/0.00
S/210.46
S/210.46
S/210.46
S/1,473.23
S/. 2,104.61
m3 m3
0.70 S/. 64.94 864.07 S/. 29.63
S/. 45.46 S/. 25,602.39
S/0.00 S/0.00
S/0.00 S/11,852.00
S/0.00 S/2,963.00
S/0.00 S/0.00
S/4.55 S/1,078.74
S/4.55 S/1,078.74
S/4.55 S/1,078.74
S/31.82 S/7,551.17
S/. 45.46 S/. 25,602.39
OBRAS DE CONCRETO SIMPLE SOLADO PARA ZAPATAS Y BASE DE MURO DE CONTENCION e= 0.05 M.
m2
326.33 S/. 17.15
S/. 86,253.85 S/. 5,596.56
S/. 2,560.89 S/2,560.89
S/. 2,079.27 S/2,079.27
S/. 4,742.89 S/0.00
S/. 2,763.92 S/0.00
4.02
CIMIENTO CORRIDO - CONCRETO CICLOPEO C:H = 1:10 + 30 % P.G (MAX. 6")
m3
167.42 S/. 216.42
S/. 36,233.04
S/0.00
S/0.00
S/0.00
S/0.00
S/3,623.30
S/3,623.30
S/3,623.30
S/25,363.13
S/. 36,233.04
4.03
SOBRECIMIENTO - CONCRETO f´c= 175 KG/CM2
m3
23.50 S/. 358.11
S/. 8,415.59
S/0.00
S/0.00
S/0.00
S/0.00
S/841.56
S/841.56
S/841.56
S/5,890.91
S/. 8,415.59
4.04 4.05
SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO CARAVISTA FALSO PISO - e= 4"
m2 m2
313.32 S/. 63.92 4.62 S/. 37.14
S/. 20,027.41 S/. 171.59
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,002.74 S/17.16
S/2,002.74 S/17.16
S/2,002.74 S/17.16
S/14,019.19 S/120.11
S/. 20,027.41 S/. 171.59
4.06 4.07
BASE PARA POSTES - CONCRETO f´c= 175 KG/CM2 BASE PARA POSTES - ENCOFRADO Y DESENCOFRADO
m3 m2
28.53 S/. 358.11 109.17 S/. 51.23
S/. 10,216.88 S/. 5,592.78
S/0.00 S/0.00
S/0.00 S/0.00
S/3,065.06 S/1,677.83
S/1,790.55 S/973.37
S/536.13 S/294.16
S/536.13 S/294.16
S/536.13 S/294.16
S/3,752.89 S/2,059.11
05 5.01
OBRAS DE CONCRETO ARMADO ZAPATAS - CONCRETO f¨c= 210 KG/CM2
m3
23.25 S/. 375.78
S/. 59,621.70 S/1,704.54
S/. 36,691.95 S/2,025.45
S/. 13,834.96 S/751.56
S/. 4,487.08 S/425.53
S/. 4,487.08 S/425.53
S/. 48,833.17 S/2,978.74
5.02 5.03 5.04
ZAPATAS - ACERO fy= 4200 KG/CM2 BASE DE MUROS - CONCRETO f´c= 210 KG/CM2 BASE DE MUROS - ACERO fy= 4200 KG/CM2
kg m3 kg
487.08 S/. 4.50 23.72 S/. 375.78 476.25 S/. 4.50
S/. 2,191.86 S/. 8,913.50 S/. 2,143.13
S/1,431.36 S/8,913.50 S/2,143.13
S/760.50 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/. 2,191.86 S/. 8,913.50 S/. 2,143.13
5.05 5.06
SARDINEL - CONCRETO f´c= 210 KG/CM2 SARDINEL - CONCRETO f´c= 175 KG/CM2
m3 m3
3.75 S/. 398.87 25.42 S/. 358.11
S/. 1,495.76 S/. 9,103.16
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/149.58 S/910.32
S/149.58 S/910.32
S/149.58 S/910.32
S/1,047.03 S/6,372.21
S/. 1,495.76 S/. 9,103.16
5.07 5.08
SARDINEL - ENCOFRADO Y DESENCOFRADO CARAVISTA SARDINEL - ACERO fy= 4200 KG/CM2
m2 kg
S/. 24,052.46 S/. 5,964.08
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,405.25 S/596.41
S/2,405.25 S/596.41
S/2,405.25 S/596.41
S/16,836.72 S/4,174.86
S/. 24,052.46 S/. 5,964.08
5.09 5.10
COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO
m3 m2
38.06 S/. 405.65 444.53 S/. 56.87
S/. 15,439.04 S/. 25,280.42
S/0.00 S/0.00
S/4,348.57 S/6,238.64
S/4,632.52 S/8,450.88
S/0.00 S/0.00
S/6,457.95 S/10,590.90
S/. 15,439.04 S/. 25,280.42
5.11 5.12
COLUMNAS - ACERO fy= 4200 KG/CM2 MUROS ARMADOS - CONCRETO f¨c= 210 KG/CM2
kg m3
1930.95 S/. 4.50 56.63 S/. 402.41
S/. 8,689.28 S/. 22,788.48
S/3,911.12 S/14,464.63
S/4,405.41 S/8,321.84
S/0.00 S/0.00
S/0.00 S/0.00
S/372.75 S/2.01
S/. 8,689.28 S/. 22,788.48
5.13 5.14
MUROS ARMADOS - ENCOFRADO Y DESENCOFRADO CARVISTA MURO ARMADO - ACERO fy= 4200 KG/CM2
m2 kg
453.26 S/. 63.92 1927.24 S/. 4.50
S/. 28,972.38 S/. 8,672.58
S/18,380.84 S/8,672.58
S/10,591.54 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/. 28,972.38 S/. 8,672.58
5.15 5.16
VIGAS - CONCRETO f´c= 210 KG/CM2 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO
m3 m2
2.83 S/. 402.41 3.53 S/. 56.87
S/. 1,138.82 S/. 200.75
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,138.82 S/200.75
S/. 1,138.82 S/. 200.75
5.17 5.18
VIGAS - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - CONCRETO f´c= 210 KG/CM2
kg m3
67.64 S/. 4.50 0.27 S/. 369.42
S/. 304.38 S/. 99.74
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/304.38 S/99.74
S/. 304.38 S/. 99.74
5.19 5.20
TECHO ALIGERADO - ENCOFRADO Y DESENCOFRADO TECHO ALIGERADO - ACERO fy= 4200 KG/CM2
m2 kg
4.50 S/. 52.84 20.46 S/. 4.50
S/. 237.78 S/. 92.07
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/237.78 S/92.07
S/. 237.78 S/. 92.07
376.29 S/. 63.92 1325.35 S/. 4.50
S/. 174,621.86 S/. 8,736.89
S/. 0.00 S/0.00
S/. 4,487.08 S/425.53
S/. 0.00
S/. 0.00
S/. 0.00
S/. 7,410.69 S/95.64
S/. 51,874.82 S/669.48
S/. 0.00
S/. 0.00
S/. 53,457.97 S/. 2,295.00
S/. 749.90
S/. 7,410.69 S/95.64
S/. 0.00
S/24.29
S/. 908.07
S/. 0.00
S/. 10,376.95 S/233.64 S/0.00
S/. 1,200.00 S/. 2,549.64
S/. 3,067.99 S/0.00 S/0.00
S/. 0.00
S/. 0.00
S/9.64 S/. 24.29
S/. 87,213.69
S/. 12,290.22 S/438.22 S/0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 4,312.73 S/1,192.92 S/3,119.81
S/. 7,410.69 S/95.64
S/. 0.00
S/. 0.00
292 dias
S/100.73
S/180.00 S/0.00
S/. 0.00
MAYO
S/. 2,095.75
S/180.00 S/0.00
S/. 1,731.27
ABRIL
S/83.21
S/. 1,200.00 S/. 2,549.64
921.41 S/. 73.35 45.00 S/. 90.41
TOTAL
AÑO 2018
NOVIEMBRE
S/. 0.00
S/. 34,495.15 S/. 1,964.91 S/. 3,119.81
S/. 86,253.85 S/. 5,596.56
S/. 10,216.88 S/. 5,592.78 S/. 2,178.84
S/. 0.00
S/. 174,621.86 S/. 8,736.89
CRONOGRAMA VALORIZADO ACELERADO DE AVANCE DE OBRA- CERCO PERIMETRICO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
TOTAL
AÑO 2018
NOVIEMBRE
DICIEMBRE
ENERO
FEBRERO
JUNIO
JULIO
AGOSTO
SETIEMBRE
11/16/2017
12/1/2017
1/1/2018
2/1/2018
3/1/2018
MARZO 3/20/2018
4/1/2018
ABRIL 5/1/2018
MAYO 5/9/2018
6/1/2018
7/1/2018
8/1/2018
9/1/2018
11/30/2017
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
9/3/2018
15 dias
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
3 dias
5.21
TECHO ALIGERADO - LADRILLO HUECO DE TECHO DE 12 x 30 x 30 CM.
und
39.00 S/. 2.70
S/. 105.30
S/0.00
S/0.00
S/0.00
S/0.00
06 6.01
MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA
S/. 0.00 S/0.00
S/. 0.00 S/0.00
S/. 0.00 S/0.00
S/. 0.00 S/0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 1,784.95 S/1,784.95
S/. 0.00
29.00 S/. 61.55
S/. 1,784.95 S/. 1,784.95
S/. 0.00
m2
S/. 1,784.95 S/. 1,784.95
07 7.01
REVOQUES, ENLUCIDOS Y MOLDURAS SOLAQUEADO DE MUROS
S/. 6,165.44 S/3,244.50
S/. 3,220.34 S/2,317.50
S/. 0.00 S/0.00
S/. 2,156.41 S/782.73
S/. 0.00
S/. 0.00
725.30 S/. 15.45
S/. 0.00 S/0.00
S/. 0.00
m2
S/. 27,257.77 S/. 11,205.89
S/. 2,610.39 S/947.51
S/. 3,404.86 S/1,235.89
S/. 3,518.35 S/1,277.08
S/. 5,841.50 S/1,277.08
S/. 340.49 S/123.59
S/. 27,257.77 S/. 11,205.89
7.02 7.03
TARRAJEO DE MUROS INTERIORES TARRAJEO DE COLUMNAS
m2 m2
21.00 S/. 24.75 439.46 S/. 31.24
S/. 519.75 S/. 13,728.73
S/0.00 S/0.00
S/0.00 S/2,920.94
S/0.00 S/902.84
S/0.00 S/0.00
S/2,241.27
S/519.75 S/2,241.27
S/216.90
S/. 519.75 S/. 13,728.73
7.04 7.05
TARRAJEO DE MUROS EXTERIORES VESTIDURA DE DERRAMES
m2 m
50.40 S/. 28.68 7.40 S/. 13.08
S/. 1,445.47 S/. 96.79
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,445.47 S/96.79
7.06 08
BRUÑAS CIELORRASOS
m
27.90 S/. 9.36
S/. 261.14 S/. 149.18
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/261.14 S/. 149.18
S/. 0.00
S/. 261.14 S/. 149.18
8.01 09
ENLUCIO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS
m2
4.50 S/. 33.15
S/. 149.18 S/. 160.04
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/149.18 S/. 160.04
S/. 0.00
S/. 149.18 S/. 160.04
9.01 10
PISO DE CEMENTO FROTACHADO Y BRUÑADO CONTRAZOCALOS
m2
4.62 S/. 34.64
S/. 160.04 S/. 480.72
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/160.04 S/. 480.72
S/. 0.00
S/. 160.04 S/. 480.72
10.01 11
CONTRAZOCALO DE CEMENTO PULIDO COBERTURAS
m
27.90 S/. 17.23
S/. 480.72 S/. 774.29
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/480.72 S/. 774.29
S/. 0.00
S/. 480.72 S/. 774.29
11.01 12
COBERTURA CON LADRILLO PASTELERO ASENTADO CON MEZCLA CARPINTERIA DE MADERA
m2
S/. 774.29 S/. 1,518.23
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00
S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/774.29 S/. 1,518.23
S/. 0.00
S/. 774.29 S/. 1,518.23
12.01
PUERTA CONTRAPLACADA EN MDF, MARCO Y ESTRUCTURA INTERIOR DE CEDRO
1.68 S/. 328.71
S/. 552.23
S/0.00
S/0.00
S/0.00
S/0.00
S/552.23
12.02
TABLERO DE MELAMINE DE 18 mm DE O.50 M. DE ANCHO DE COLOR BLANCO m FIJADO CON ÁNGULO DE Fe.
4.00 S/. 241.50
S/. 966.00
S/0.00
S/0.00
S/0.00
S/0.00
S/966.00
13
CARPINTERIA METALICA
S/. 0.00
S/. 28,740.00
S/. 225,870.00
S/. 48,466.00
S/. 22,751.65
13.01
CERCO DE MALLA DE ALAMBRE GALVANIZADO, CON PARANTE DE TUBO DE Fe. DE 3"x 3", MARCO DE ANGULO DE 2"x2" Y PLATINA DE 1 1/2", FIJADA A m COLUMNAS Y SARDINEL MEDIANTE TUBO CUADRADO DE 2" x 2"
S/. 140,773.12
S/0.00
S/28,740.00
S/80,472.00
S/0.00
S/1,578.06
13.02
PUERTA DE INGRESO DE MALLA DE ALAMBRE GALVANIZADO, CON PARANTE DE TUBO DE Fe. DE 3" x 3", MARCO DE ANGULO DE 2"x2" Y PLATINA DE 1 1/2", CON PLANCHA METÁLICA Y FIJADA A COLUMNAS DE Fe 6" x 6"
S/. 4,572.65
S/0.00
S/0.00
S/0.00
S/0.00
13.03
CERCO DE MALLA DE ALAMBRE GALVANIZADO, CON PARANTE DE TUBO DE Fe. DE 3"x 3", MARCO DE ANGULO DE 2"x2" Y PLATINA DE 1 1/2", FIJADA A m PARANTES MEDIANTE TUBO CUADRADO DE 2"x 2"
S/. 346,536.75
S/0.00
S/0.00
S/145,398.00
S/48,466.00
13.04
PUERTA DE INGRESO DE MALLA DE ALAMBRE GALVANIZADO, CON PARANTE DE TUBO DE Fe. DE 3" x 3", MARCO DE ANGULO DE 2"x2" Y PLATINA DE 1 1/2", CON PLANCHA METÁLICA Y FIJADA A COLUMNAS DE Fe 4" x 4"
S/0.00
S/0.00
S/0.00
S/0.00
14
CERRAJERIA
14.01 14.02
BISAGRAS CAPUCHINAS ALUMINIZADAS DE 2 1/2 x 2 1/2" BISAGRAS DE Fe. DE 5/8" x 10"
14.03 14.04 14.05
CERRADURA PARA PUERTA INTERIOR DE DOS GOLPES und CERRADURA PARA PORTON - CON ALDABA CORREDIZA Y PORTA CANDADO und GARRUCHA GIRATORIA CON RUEDA DE NYLON PESADA DE 5" Y RODAMIENTO und 400 A 600 KG
15
VIDRIOS CRISTALES Y SIMILARES
15.01
CRISTAL TEMPLADO OSCURECIDO Y PERFORACIONES PARA AUDIO DE 6 MM
16
PINTURA
16.01 16.02
PINTURA EN MUROS INTERIORES CON LATEX LAVABLE PINTURA EN MUROS EXERIORES Y COLUMNAS
m2 m2
22.11 S/. 15.26 457.05 S/. 18.62
16.03 17
PINTURA EN CIELORRASO INSTALACIONES ELECTRICAS
m2
4.50 S/. 14.82
17.01
MOVIMIENTO DE TIERRAS
17.01.01
EXCAVACION DE ZANJAS PARA ALIMENTADORES DE TABLEROS DEDISTRIBUCION
m3
711.26 S/. 37.57
S/. 26,722.04
17.01.02
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO
m3
711.26 S/. 29.91
17.01.03
RETIRO DE CABLEADO DEL TD-A AL TD-BL Y NUEVA INSTALACION DE CABLES
m
40.00 S/. 6.97
17.02 17.02.01
ALIMENTADORES GENERALES ALIMENTADOR ENTRE TABLERO TG-1 Y TD-1
45.00 S/. 69.49
m2
16.52 S/. 46.87
S/. 501,464.57
m2
612.27 S/. 229.92
24.78 S/. 184.53
1430.02 S/. 242.33
S/105.30
292 dias
S/1,373.68
S/. 0.00
S/1,662.87
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/2,168.97
S/. 0.00
S/. 105.30
S/. 1,445.47 S/. 96.79
S/. 552.23 S/. 966.00
S/. 14,727.97
S/. 14,727.97
S/. 99,414.22
S/. 30,460.73
S/. 16,306.03
S/1,578.06
S/1,578.06
S/20,514.73
S/3,156.11
S/3,156.11
S/4,572.65
S/21,173.59
S/13,149.92
S/13,149.92
S/78,899.49
S/13,149.92
S/. 501,464.57 S/. 140,773.12
S/. 4,572.65
S/13,149.92
m2
50.40 S/. 190.12
S/. 9,582.05
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
und und
4.00 S/. 16.53 48.00 S/. 50.11
S/. 66.12 S/. 2,405.28
S/0.00 S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/66.12 S/2,405.28
S/. 66.12 S/. 2,405.28
1.00 S/. 84.58 12.00 S/. 149.15
S/. 84.58 S/. 1,789.80
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/84.58 S/1,789.80
S/. 84.58 S/. 1,789.80
12.00 S/. 127.63
S/. 1,531.56
S/0.00
S/0.00
S/0.00
S/0.00
S/1,531.56
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/. 5,877.34
S/. 112.65 m2
0.27 S/. 417.23
S/. 112.65 S/. 8,914.36
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 5,877.34
S/. 112.65
S/. 9,582.05 S/. 0.00
S/. 1,531.56 S/. 0.00
S/112.65 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 8,914.36
S/. 112.65 S/. 112.65
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/0.00 S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/. 66.69 S/. 388,019.05
S/0.00 S/. 0.00
S/0.00
S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 1,408.36
S/. 15,287.54
S/. 133,503.61
S/66.69 S/. 193,658.61
S/. 44,160.93
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 4,827.46
S/. 28,964.78
S/. 4,827.46
S/. 9,654.93
S/0.00
S/0.00
S/0.00
S/0.00
S/2,672.20
S/16,033.22
S/2,672.20
S/5,344.41
S/. 26,722.04
S/. 21,273.79
S/0.00
S/0.00
S/0.00
S/0.00
S/2,127.38
S/12,764.27
S/2,127.38
S/4,254.76
S/. 21,273.79
S/. 278.80
S/0.00
S/0.00
S/0.00
S/0.00
S/27.88
S/167.28
S/27.88
S/55.76
S/. 278.80
S/. 23,045.74 S/. 3,127.05
S/. 0.00 S/0.00
S/. 0.00 S/0.00
S/. 0.00 S/0.00
S/. 0.00 S/0.00
S/. 2,304.57 S/312.71
S/. 13,827.44 S/1,876.23
S/. 2,304.57 S/312.71
S/. 4,609.15 S/625.41
S/. 23,045.74 S/. 3,127.05
S/0.00
S/. 0.00
S/. 5,877.34
S/. 337.40 S/. 8,510.27
S/. 48,274.63
m
S/0.00
S/9,582.05
S/. 346,536.75
S/. 0.00
S/337.40 S/8,510.27
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 8,914.36 S/. 337.40 S/. 8,510.27 S/. 66.69 S/. 388,019.05 S/. 48,274.63
CRONOGRAMA VALORIZADO ACELERADO DE AVANCE DE OBRA- CERCO PERIMETRICO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
17.02.02 17.02.03 17.02.04 17.02.05 17.02.06 17.03 17.03.01 17.03.02 17.03.03 17.03.04 17.03.05 17.04 17.04.01
ALIMENTADOR ENTRE TABLERO TD-1 Y TD-2 ALIMENTADOR ENTRE TABLERO TD-2 Y TD-3 ALIMENTADOR ENTRE TABLERO TD-3 Y TD-4 ALIMENTADOR ENTRE TABLERO TD-4 Y TD-5 ALIMENTADOR ENTRE TABLERO TG-3 Y TD-6 CABLEADO DE CIRCUITOS DE ILUMINACION DE CERCO CABLE 3x16 mm2 NYY , inc. terminales y mangas CABLE 3-1x10 mm2 NYY,inc terminales y mangas CABLE 3-1x6 mm2 NYY ,inc terminales y mangas CABLE 1x6 mm2 NYY (T), inc. terminales y mangas CABLE 1x4 mm2 NYY (T), inc. terminales y mangas SALIDAS ELECTRICAS SALIDA PARA ARTEFACTO ADOSADO EN EL TECHO
m m m m m
66.00 S/. 69.49 105.00 S/. 50.27 100.00 S/. 50.27 15.00 S/. 50.27 85.00 S/. 50.27
m m m m m
680.00 S/. 33.43 875.00 S/. 17.89 715.00 S/. 14.13 330.00 S/. 6.66 1940.00 S/. 6.66
pto
17.04.02
SALIDA PARA TOMACORRIENTE BIPOLAR CON COMA A TIERRA
pto
17.04.03 17.05
und
17.05.01
SALIDA PARA INTERRUPTORES SIMPLES ALUMBRADO ELECTRICO INSTALACIÓN DE FAROLA LED EQUIPADA CON POTENCIA 43W MITHA LED O SIMILAR
und
17.05.02
INSTALACIÓN DE REFLECTORES LED DE 86 w
und
17.05.03
INSTALACIÓN DE PHILIPS BGP070 FG O SIMILAR EQUIPADA CON LAMPARA LED DE POTENCIA 45W
und
17.05.04
POSTES DE CONCRETO PARA ALUMBRADO DE 9 m DE ALTURA, CON PASTORAL DE 50 W
und
39.00 S/. 2,246.15
und
2.00 S/. 308.62
17.05.05 17.06 17.06.01 17.06.02 17.06.03 17.06.04 17.06.05 17.06.06 17.06.07 17.07 17.07.01 17.08 17.08.01 17.08.02 17.08.03 17.08.04 17.08.05 17.08.06
LUMINARIA INDUSTRIAL HERMÉTICA ADOSADA CON 2 LÁMPARAS FLORESCENTES DE 36W DE ALTA EFICIENCIA, 220V, 60 HZ TABLEROS ELECTRICOS TABLERO GENERAL EMPOTRADO TD-BL (16 polos) TABLERO GENERAL EMPOTRADO TD-1 (12 polos) TABLERO GENERAL EMPOTRADO TD-2 (12 polos) TABLERO GENERAL EMPOTRADO TD-3 (12 polos) TABLERO GENERAL EMPOTRADO TD-4 (12 polos) TABLERO GENERAL EMPOTRADO TD-5 (12 polos) TABLERO GENERAL EMPOTRADO TD-6 (12 polos) SISTEMA DE PUESTA A TIERRA POZO A TIERRA MURETES PARA TABLEROS ELECTRICOS EXCAVACION PARA BASE DE MURETES CIMIENTO DE MURETES - CONCRETO CICLOPEO 1:10 + 30% P.G. SOBRECIMIENTO DE MURETE - CONCRETO 1:8 + 25% P.M. SOBRECIMIENTO DE MURETE - ENCOFRADO Y DESENCOFRADO MURETE CE LADRILLO KK ASENTADO DE CABEZA TARRAJEO DE MURETE Costo Directo Gastos Generales Utilidad Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
pza pza pza pza pza pza pza und m3 m3 m3 m2 m2 m2
TOTAL
AÑO 2018
NOVIEMBRE
DICIEMBRE
ENERO
FEBRERO
JUNIO
JULIO
AGOSTO
SETIEMBRE
11/16/2017
12/1/2017
1/1/2018
2/1/2018
3/1/2018
MARZO 3/20/2018
4/1/2018
ABRIL 5/1/2018
MAYO 5/9/2018
6/1/2018
7/1/2018
8/1/2018
9/1/2018
11/30/2017
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
9/3/2018
15 dias
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
3 dias
S/458.63 S/527.84 S/502.70 S/75.41 S/427.30 S/. 6,360.73 S/2,273.24 S/1,565.38 S/1,010.30 S/219.78 S/1,292.04 S/. 56.88 S/21.75
S/2,751.80 S/3,167.01 S/3,016.20 S/452.43 S/2,563.77 S/. 38,164.38 S/13,639.44 S/9,392.25 S/6,061.77 S/1,318.68 S/7,752.24 S/. 341.27 S/130.50
S/458.63 S/527.84 S/502.70 S/75.41 S/427.30 S/. 6,360.73 S/2,273.24 S/1,565.38 S/1,010.30 S/219.78 S/1,292.04 S/. 56.88 S/21.75
S/917.27 S/1,055.67 S/1,005.40 S/150.81 S/854.59 S/. 12,721.46 S/4,546.48 S/3,130.75 S/2,020.59 S/439.56 S/2,584.08 S/. 113.76 S/43.50
S/. 4,586.34 S/. 5,278.35 S/. 5,027.00 S/. 754.05 S/. 4,272.95 S/. 63,607.30 S/. 22,732.40 S/. 15,653.75 S/. 10,102.95 S/. 2,197.80 S/. 12,920.40 S/. 568.78 S/. 217.50
292 dias
2.00 S/. 108.75
S/. 4,586.34 S/. 5,278.35 S/. 5,027.00 S/. 754.05 S/. 4,272.95 S/. 63,607.30 S/. 22,732.40 S/. 15,653.75 S/. 10,102.95 S/. 2,197.80 S/. 12,920.40 S/. 568.78 S/. 217.50
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
2.00 S/. 137.52
S/. 275.04
S/0.00
S/0.00
S/0.00
S/0.00
S/27.50
S/165.02
S/27.50
S/55.01
S/. 275.04
1.00 S/. 76.24
S/. 76.24 S/. 235,143.69
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/7.62 S/. 0.00
S/45.74 S/. 41,778.39
S/7.62 S/. 176,303.66
S/15.25 S/. 17,061.64
S/. 76.24 S/. 235,143.69
40.00 S/. 756.05
S/. 30,242.00
S/0.00
S/0.00
S/0.00
S/0.00
S/27,573.59
S/2,668.41
S/. 30,242.00
44.00 S/. 691.05
S/. 30,406.20
S/0.00
S/0.00
S/0.00
S/0.00
S/27,723.30
S/2,682.90
S/. 30,406.20
128.00 S/. 674.05
S/. 86,278.40
S/0.00
S/0.00
S/0.00
S/0.00
S/78,665.60
S/7,612.80
S/. 86,278.40
S/. 87,599.85
S/0.00
S/0.00
S/0.00
S/0.00
S/41,778.39
S/4,043.07
S/. 87,599.85
S/. 617.24
S/0.00
S/0.00
S/0.00
S/0.00
S/562.78
S/54.46
S/. 617.24
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/131,144.14 S/10,491.53 S/9,180.09 S/150,815.76 S/146,442.10 S/26,359.58 S/172,801.68
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/134,830.73 S/10,786.46 S/9,438.15 S/155,055.34 S/150,558.73 S/27,100.57 S/177,659.30
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/274,573.59 S/21,965.89 S/19,220.15 S/315,759.63 S/306,602.59 S/55,188.47 S/361,791.06
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/75,972.34 S/6,077.79 S/5,318.06 S/87,368.19 S/84,834.51 S/15,270.21 S/100,104.72
S/. 1,658.46 S/308.19 S/225.47 S/263.37 S/207.03 S/254.15 S/217.83 S/182.41 S/. 1,158.26 S/1,158.26 S/. 988.59 S/40.58 S/186.99 S/80.29 S/143.82 S/290.27 S/246.65 S/255,786.70 S/20,462.94 S/17,905.07 S/294,154.71 S/285,624.21 S/51,412.36 S/337,036.57
S/. 0.00
S/. 8,292.32 1.00 S/. 1,540.96 S/. 1,540.96 1.00 S/. 1,127.36 S/. 1,127.36 1.00 S/. 1,316.86 S/. 1,316.86 1.00 S/. 1,035.16 S/. 1,035.16 1.00 S/. 1,270.76 S/. 1,270.76 1.00 S/. 1,089.16 S/. 1,089.16 1.00 S/. 912.06 S/. 912.06 S/. 5,791.29 3.00 S/. 1,930.43 S/. 5,791.29 S/. 3,295.30 3.60 S/. 37.57 S/. 135.25 2.88 S/. 216.42 S/. 623.29 0.90 S/. 297.38 S/. 267.64 8.40 S/. 57.07 S/. 479.39 8.82 S/. 109.70 S/. 967.55 29.93 S/. 27.47 S/. 822.18 S/1,435,034.12 8.00% S/114,802.73 7.00% S/100,452.39 S/1,650,289.24 0.971 S/1,602,430.79 18.00% S/288,437.54 S/1,890,868.33
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/41,778.39
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/45,092.22 S/3,607.38 S/3,156.46 S/51,856.06 S/50,352.23 S/9,063.40 S/59,415.63
S/. 829.23 S/154.10 S/112.74 S/131.69 S/103.52 S/127.08 S/108.92 S/91.21 S/. 579.13 S/579.13 S/. 0.00
S/40,363.30 S/3,229.06 S/2,825.43 S/46,417.79 S/45,071.67 S/8,112.90 S/53,184.57
S/. 829.23 S/154.10 S/112.74 S/131.69 S/103.52 S/127.08 S/108.92 S/91.21 S/. 579.13 S/579.13 S/. 329.53 S/13.53 S/62.33 S/26.76 S/47.94 S/96.76 S/82.22 S/57,543.67 S/4,603.49 S/4,028.06 S/66,175.22 S/64,256.14 S/11,566.11 S/75,822.25
S/. 4,975.39 S/924.58 S/676.42 S/790.12 S/621.10 S/762.46 S/653.50 S/547.24 S/. 3,474.77 S/3,474.77 S/. 1,977.18 S/81.15 S/373.97 S/160.58 S/287.63 S/580.53 S/493.31 S/358,622.33 S/28,689.79 S/25,103.56 S/412,415.68 S/400,455.61 S/72,082.01 S/472,537.62
S/. 8,292.32 S/. 1,540.96 S/. 1,127.36 S/. 1,316.86 S/. 1,035.16 S/. 1,270.76 S/. 1,089.16 S/. 912.06 S/. 0.00 S/. 5,791.29 S/. 5,791.29 S/. 0.00 S/. 3,295.30 S/. 135.25 S/. 623.29 S/. 267.64 S/. 479.39 S/. 967.55 S/. 822.18 S/61,105.10 S/1,435,034.12 S/4,888.40 S/114,802.73 S/4,277.37 S/100,452.39 S/70,270.87 S/1,650,289.24 S/68,233.01 S/1,602,430.79 S/12,281.93 S/288,437.54 S/80,514.94 S/1,890,868.33
PORCENTAJE DE AVANCE ( % )
9.14%
9.40%
19.13%
5.29%
3.14%
2.81%
4.01%
24.99%
17.82%
4.26%
PORCENTAJE ACUMULADO DE AVANCE ( % )
9.14%
18.53%
37.67%
42.96%
46.10%
48.92%
52.93%
77.92%
95.74%
100.00%
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
1 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.1 1.11 1.12 1.13 1.14 1.15 1.16 2
OBRAS PRELIMINARES MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb CARTEL DE OBRA DE 3.60 x 7.20 M. und CERCO PERIMETRICO PROVISIONAL m OFICINA DE OBRA m2 CASETA DE GUARDIANIA m2 COMEDOR, VESTUARIOS Y SSHH PARA OBREROS m2 INSTALACIONES PROVISIONALES DE AGUA Y DESAGUE glb INSTALACIONES PROVISIONALES DE INSTALACIONES ELECTRICAS glb CONSUMO DE ENERGIA Y AGUA mes ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y glb EQUIPO DE PROTECCION INDIVIDUAL glb EQUIPO DE PROTECCION COLECTIVA glb SEÑALIZACION TEMPORAL DE SEGURIDAD glb CAPACITACION EN SEGURIDAD Y SALUD glb RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD EN EL glb MITIGACION DE IMPACTO AMBIENTAL est SS.HH. Y VESTUARIOS MUJERES
1.00 2.00 545.50 42.00 9.00 45.00 1.00 1.00 6.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
S/. 5,000.00 S/. 1,253.07 S/. 73.35 S/. 90.41 S/. 84.45 S/. 84.45 S/. 776.43 S/. 1,479.56 S/. 400.00 S/. 1,500.00 S/. 1,500.00 S/. 650.00 S/. 150.00 S/. 5,100.00 S/. 6,000.00 S/. 15,000.00
S/90,432.08 S/5,000.00 S/2,506.14 S/40,012.43 S/3,797.22 S/760.05 S/3,800.25 S/776.43 S/1,479.56 S/2,400.00 S/1,500.00 S/1,500.00 S/650.00 S/150.00 S/5,100.00 S/6,000.00 S/15,000.00 S/219,446.56
S/9,832.31 S/850.00 S/2,506.14 S/0.00 S/0.00 S/0.00 S/2,508.17 S/388.22 S/739.78 S/0.00 S/0.00 S/150.00 S/65.00 S/15.00 S/510.00 S/600.00 S/1,500.00 S/29,206.21
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
2.01 02.01.01 02.01.02 2.02 02.02.01 02.02.02 02.02.03 02.02.04 02.02.05 2.03 02.03.01 02.03.02 02.03.03 02.03.04 02.03.05 2.04 02.04.01 02.04.02
TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA ZAPATAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4" CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO ZAPATAS - CONCRETO f´c= 210 KG/CM2 ZAPATAS - ENCOFRADO Y DESENCOFRADO
m2 m2
386.56 386.56
S/. 3.64 S/. 1.91
m3 m3 m3 m3 m3
75.12 56.34 29.30 31.34 132.80
S/. 42.93 S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m2 m3 m3 m2 m2
58.90 57.44 11.16 152.56 313.62
S/. 24.28 S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2
29.46 106.20
S/. 357.87 S/. 57.07
S/2,145.41 S/1,407.08 S/738.33 S/13,381.52 S/3,224.90 S/2,418.68 S/1,477.31 S/2,890.17 S/3,370.46 S/36,470.42 S/1,430.09 S/12,871.16 S/4,486.77 S/8,706.60 S/8,975.80 S/167,449.21 S/10,542.85 S/6,060.83
S/1,164.00 S/763.42 S/400.58 S/4,455.19 S/1,620.61 S/1,208.48 S/0.00 S/0.00 S/1,626.10 S/705.09 S/705.09 S/0.00 S/0.00 S/0.00 S/0.00 S/22,881.93 S/5,196.27 S/3,001.88
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
621.34 19.46 210.76 4174.24 29.52 224.82 6379.74 22.84 263.84 1707.28 2300.00 9.92 142.36 1076.94
S/. 4.50 S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55 S/. 370.72 S/. 56.49 S/. 4.50
11/16/2017 11/30/2017 15 dias
02.04.03 02.04.04 02.04.05 02.04.06 02.04.07 02.04.08 02.04.09 02.04.10 02.04.11 02.04.12 02.04.13 02.04.14 02.04.15 02.04.16 3 3.01 03.01.01 03.01.02
ZAPATAS - ACERO fy= 4200 KG/CM2 COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. TEATINAS - CONCRETO f´c= 210 KG/CM2 TEATINAS - ENCOFRADO Y DESENCOFRADO TEATINAS - ACERO fy= 4200 KG/CM2 SS.HH. Y VESTUARIOS HOMBRES TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO 03.01.01 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA 03.01.02
kg m3 m2 kg m3 m2 kg m2 m2 kg und m3 m2 kg
m2 m2
342.12 342.12
S/. 3.64 S/. 1.91
S/2,796.03 S/8,312.53 S/13,218.87 S/18,784.08 S/13,593.66 S/14,210.87 S/28,708.83 S/9,574.07 S/13,833.13 S/7,682.76 S/3,565.00 S/3,677.54 S/8,041.92 S/4,846.23 S/279,740.67 S/1,898.77 S/1,245.32 S/653.45
S/2,110.55 S/0.00 S/0.00 S/12,573.23 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/11,166.75 S/1,108.11 S/726.76 S/381.35
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
3.02 03.02.01 03.02.02 03.02.03 03.02.04 03.02.05 03.02.06 3.03 03.03.01 03.03.02 03.03.03 03.03.04 03.03.05 3.04 03.04.01 03.04.02 03.04.03 03.04.04
MOVIMIENTO DE TIERRAS EXCAVACION PARA ZAPATAS EXCAVACION PARA CIMIENTOS CORRIDOS EXCAVACION PARA CISTERNA, CUARTO DE MAQUINAS, ESCALERA Y POZO SUMIDE RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4" CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO ZAPATAS - CONCRETO f´c= 210 KG/CM2 ZAPATAS - ENCOFRADO Y DESENCOFRADO ZAPATAS - ACERO fy= 4200 KG/CM2 COLUMNAS - CONCRETO f´c= 210 KG/CM2
m3 m3 m3 m3 m3 m3
49.62 41.24 320.47 26.48 23.52 500.3
S/. 42.93 S/. 42.93 S/. 15.44 S/. 50.42 S/. 92.22 S/. 25.38
m2 m3 m3 m2 m2
123.4 42.81 9.82 66.1 154.55
S/. 24.28 S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2 kg m3
19.46 70.50 408.02 16.80
S/. 357.87 S/. 57.07 S/. 4.50 S/. 427.16
S/25,050.43 S/2,130.19 S/1,770.43 S/4,948.06 S/1,335.12 S/2,169.01 S/12,697.61 S/24,732.60 S/2,996.15 S/9,592.86 S/3,948.03 S/3,772.33 S/4,423.22 S/228,058.88 S/6,964.15 S/4,023.44 S/1,836.09 S/7,176.29
S/4,116.53 S/1,497.40 S/1,037.19 S/0.00 S/0.00 S/0.00 S/1,581.94 S/487.79 S/487.79 S/0.00 S/0.00 S/0.00 S/0.00 S/5,454.32 S/1,084.35 S/627.77 S/1,931.76 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
189.74 3798.22 26.70 213.36 5557.04 20.04 234.74 1424.50 2056.00 9.40 134.28 1018.72 54.16 353.73 5992.66 8.44 55.20 600.25
S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55 S/. 370.72 S/. 56.49 S/. 4.50 S/. 439.07 S/. 63.21 S/. 4.50 S/. 402.04 S/. 56.49 S/. 4.50
11/16/2017 11/30/2017 15 dias
03.04.05 03.04.06 03.04.07 03.04.08 03.04.09 03.04.10 03.04.11 03.04.12 03.04.13 03.04.14 03.04.15 03.04.16 03.04.17 03.04.18 03.04.19 03.04.20 03.04.21 03.04.22
COLUMNAS - ENCOFRADO Y DESENCOFRADO m2 kg COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 m3 m2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 kg m2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO m2 LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 kg TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. und m3 TEATINAS - CONCRETO f´c= 210 KG/CM2 TEATINAS - ENCOFRADO Y DESENCOFRADO m2 TEATINAS - ACERO fy= 4200 KG/CM2 kg CISTERNA, CUARTO DE MAQ. Y POZO SUMIDERO - CONCRETO f´c= 210 KG/CM2 m3 CISTERNA, CUARTO DE MAQ. Y POZO SUMIDERO - ENCOFRADO Y DESENCOFRADO m2 CISTERNA, CUARTO DE MAQ. Y POZO SUMIDERO - ACERO fy= 4200 KG/CM2 kg ESCALERA - CONCRETO f´c= 210 KG/CM2 m3 ESCALERA - ENCOFRADO Y DESENCOFRADO m2 ESCALERA - ACERO fy= 4200 KG/CM2 kg
S/11,900.49 S/17,091.99 S/12,295.08 S/13,486.49 S/25,006.68 S/8,400.37 S/12,307.42 S/6,410.25 S/3,186.80 S/3,484.77 S/7,585.48 S/4,584.24 S/23,780.03 S/22,359.27 S/26,966.97 S/3,393.22 S/3,118.25 S/2,701.13
S/0.00 S/1,810.44 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
4 4.01 04.01.01 04.01.02 4.02 04.02.01 04.02.02 04.02.03 04.02.04 4.03 04.03.01 04.03.02 04.03.03 04.03.04 04.03.05 4.04 04.04.01 04.04.02
SS.HH. DE HOMBRES Y MUJERES TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA ZAPATAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4" CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO ZAPATAS - CONCRETO f´c= 210 KG/CM2 ZAPATAS - ENCOFRADO Y DESENCOFRADO
m2 m2
72.80 72.80
S/. 3.64 S/. 1.91
m3 m3 m3 m3
34.85 30.62 19.25 75.29
S/. 42.93 S/. 42.93 S/. 92.22 S/. 25.38
m2 m3 m3 m2 m2
1.09 16.70 3.62 55.68 62.78
S/. 24.28 S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2
7.62 27.72
S/. 357.87 S/. 57.07
S/92,507.60 S/404.04 S/264.99 S/139.05 S/6,496.72 S/1,496.11 S/1,314.52 S/1,775.24 S/1,910.86 S/10,198.41 S/26.47 S/3,742.14 S/1,455.38 S/3,177.66 S/1,796.76 S/75,408.43 S/2,726.97 S/1,581.98
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
kg m3 m2 kg m3 m2 kg m2 m2 kg und
419.62 16.16 280.80 3641.34 11.16 64.80 1209.00 8.32 95.04 792.00 1032.50
S/. 4.50 S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55
m2 m2
60.74 60.74
S/. 3.64 S/. 1.91
m3 m3
22.37 2.75
S/. 42.93 S/. 92.22
11/16/2017 11/30/2017 15 dias
04.04.03 04.04.04 04.04.05 04.04.06 04.04.07 04.04.08 04.04.09 04.04.10 04.04.11 04.04.12 04.04.13 5 5.01 05.01.01 05.01.02 5.02 05.02.01 05.02.02
ZAPATAS - ACERO fy= 4200 KG/CM2 COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. SS.HH. NIÑOS Y NIÑAS TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL DE PRESTAMO
S/1,888.29 S/6,902.91 S/17,611.78 S/16,386.03 S/5,139.07 S/4,096.01 S/5,440.50 S/3,487.58 S/4,982.95 S/3,564.00 S/1,600.38 S/24,758.25 S/337.11 S/221.09 S/116.01 S/1,866.98 S/960.34 S/253.61
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
05.02.03 5.03 05.03.01 05.03.02 05.03.03 05.03.04 5.04 05.04.01 05.04.02 05.04.03 05.04.04 05.04.05 05.04.06 05.04.07 05.04.08 05.04.09 05.04.10 6
ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. TOPICO
m3
25.73
S/. 25.38
m3 m3 m2 m3
12.20 2.64 40.67 47.88
S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2 kg m3 m2 kg m2 m2 kg und
3.90 33.38 749.35 1.80 8.09 407.92 3.08 35.23 294.00 192.89
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55
S/653.03 S/7,486.52 S/2,733.78 S/1,061.39 S/2,321.04 S/1,370.33 S/15,067.65 S/1,665.92 S/2,093.59 S/3,372.08 S/828.88 S/511.37 S/1,835.64 S/1,291.07 S/1,847.11 S/1,323.00 S/298.98 S/38,918.89
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
6.01 06.01.01 06.01.02 6.02 06.02.01 06.02.02 06.02.03 06.02.04 6.03 06.03.01 06.03.02 6.04 06.04.01 06.04.02 06.04.03 06.04.04 06.04.05 06.04.06
TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION MASIVA EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO SOBRECIMIENTO ARMADO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO ARMADO - ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO ARMADO - ACERO fy= 4200 KG/CM2 COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2
m2 m2
32.07 32.07
S/. 3.64 S/. 1.91
m3 m3 m3 m3
75.06 13.22 3.98 101.52
S/. 10.82 S/. 42.93 S/. 92.22 S/. 25.38
m3 m2
10.76 30.68
S/. 224.08 S/. 28.62
m3 m2 kg m3 m2 kg
3.15 48.44 223.41 2.14 243.20 278.55
S/. 412.65 S/. 62.72 S/. 4.50 S/. 427.16 S/. 62.72 S/. 4.50
S/177.99 S/116.73 S/61.25 S/4,323.30 S/812.15 S/567.53 S/367.04 S/2,576.58 S/3,289.16 S/2,411.10 S/878.06 S/31,128.44 S/1,299.85 S/3,038.16 S/1,005.35 S/914.12 S/15,253.50 S/1,253.48
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
06.04.07 06.04.08 06.04.09 06.04.10 06.04.11 06.04.12 06.04.13 7 07.01. 07.01.01 07.01.02 07.02. 07.02.01 07.02.02 07.02.03 07.02.04 07.02.05 7.03
VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. MIRADOR TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS COMPACTACION DE TERRENO NATURAL CON MAQUINARIA RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXEDENTE OBRAS DE CONCRETO SIMPLE
m3 m2 kg m3 m2 kg und
1.89 37.67 312.65 2.44 27.89 233.00 111.00
S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55
m2 m2
60.82 60.82
S/. 3.64 S/. 1.91
m3 m2 m3 m3 m3
1.23 77.61 42.80 8.36 101.52
S/. 42.93 S/. 5.40 S/. 50.42 S/. 92.22 S/. 25.38
S/870.33 S/2,381.12 S/1,406.93 S/1,022.80 S/1,462.27 S/1,048.50 S/172.05 S/34,317.12 S/337.55 S/221.38 S/116.17 S/5,977.41 S/52.80 S/419.09 S/2,157.98 S/770.96 S/2,576.58 S/20,324.20
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
07.03.01 07.03.02 7.04 07.04.01 07.04.02 07.04.03 07.04.04 07.04.05 07.04.06 07.04.07 07.04.08 07.04.09 8 8.01 08.01.01 08.01.02 8.02 08.02.01
CIMIENTO CORRIDO C:H 1:10 + 30% PG CONCRETO f´c= 140 KG/CM2 OBRAS DE CONCRETO ARMADO LOSA DE PISO - CONCRETO f´c= 210 KG/CM2 LOSA DE PISO - ENCOFRADO Y DESENCOFRADO LOSA DE PISO - ACERO fy= 4200 KG/CM2 ESCALERA - CONCRETO f´c= 210 KG/CM2 ESCALERA - ENCOFRADO Y DESENCOFRADO ESCALERA - ACERO fy= 4200 KG/CM2 JUNTA DE DILATACION e= 1" BANCA DE CONCRETO - CONCRETO f´c= 175 KG/CM2 BANCA DE CONCRETO - LADRILLO HUECO DE TECHO MALOCA TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA ZAPATAS
m3 m3
83.59 5.34
S/. 224.08 S/. 298.38
m3 m2 kg m3 m2 kg m m3 und
9.12 7.87 232.96 1.81 1.81 93.86 2.80 3.53 252.00
S/. 357.87 S/. 56.49 S/. 4.50 S/. 402.04 S/. 56.49 S/. 4.50 S/. 3.94 S/. 371.16 S/. 1.38
m2 m2
190.00 190.00
S/. 3.64 S/. 1.91
m3
18.43
S/. 42.93
S/18,730.85 S/1,593.35 S/7,677.97 S/3,263.77 S/444.58 S/1,048.32 S/727.69 S/102.25 S/422.37 S/11.03 S/1,310.19 S/347.76 S/13,982.44 S/1,054.50 S/691.60 S/362.90 S/1,651.40 S/791.20
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
08.02.02 08.02.03 8.03 08.03.01 8.04 08.04.01 08.04.02 08.04.03 08.04.04 08.04.05 08.04.06 8.05 08.05.01 08.05.02 08.05.03 08.05.04 08.05.05 08.05.06
RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CONCRETO f´c= 140 KG/CM2 OBRAS DE CONCRETO ARMADO ZAPATAS - CONCRETO f´c= 210 KG/CM2 ZAPATAS - ENCOFRADO Y DESENCOFRADO ZAPATAS - ACERO fy= 4200 KG/CM2 PEDESTAL - CONCRETO f´c= 210 KG/CM2 PEDESTAL - ENCOFRADO Y DESENCOFRADO PEDESTAL - ACERO fy= 4200 KG/CM2 ESTRUSTURA METALICA PLANCHA DE ACERO PL 05 e= 1/4" PERNOS DE FIJACION DE 1/2" x 3" PLANCHA DE ACERO PL 02 e= 1/4" PERNOS DE FIJACIÓN DE 3/8" x 2 1/2" PLANCHA DE ACERO PL 04 e= 1/4" PLANCHA DE ACERO PL 03 e= 1/4"
m3 m3
3.24 22.12
S/. 92.22 S/. 25.38
m3
2.07
S/. 298.38
m3 m2 kg m3 m2 kg
2.30 7.68 82.37 0.36 4.80 37.20
S/. 357.87 S/. 57.07 S/. 4.50 S/. 427.16 S/. 62.72 S/. 4.50
kg und kg und kg kg
142.66 112.00 122.43 96.00 24.70 22.22
S/. 10.95 S/. 25.00 S/. 10.95 S/. 5.50 S/. 10.95 S/. 10.95
S/298.79 S/561.41 S/617.65 S/617.65 S/2,254.30 S/823.10 S/438.30 S/370.67 S/153.78 S/301.06 S/167.40 S/8,404.60 S/1,562.13 S/2,800.00 S/1,340.61 S/528.00 S/270.47 S/243.31
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
08.05.07 08.05.08 08.05.09 08.05.10 9 9.01 09.01.01 09.01.02 9.02 09.02.01 09.02.02 09.02.03 09.02.04 09.02.05 9.03 09.03.01 09.03.02 09.03.03
PERNOS DE 3/8" x 2 1/2" PLANCHA DE ACERO PL 01 e= 1/4" TUBO DE FIERRO DE 2" CON PINTURA ANTICORROSIVA PERNOS DE FIJACION DE 1/4" x 2 1/2" BOLETERIA TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS EXCAVACION PARA BASE DE PERGOLA RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO
und kg kg und
104.00 12.35 63.64 64.00
S/. 5.50 S/. 10.95 S/. 10.95 S/. 4.00
m2 m2
112.72 112.72
S/. 3.64 S/. 1.91
m3 m3 m3 m3 m3
10.96 2.16 0.69 1.97 16.16
S/. 42.93 S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m3 m3 m2
8.77 1.72 22.83
S/. 224.08 S/. 402.04 S/. 57.07
S/572.00 S/135.23 S/696.86 S/256.00 S/20,327.03 S/625.60 S/410.30 S/215.30 S/1,189.85 S/470.51 S/92.73 S/34.79 S/181.67 S/410.14 S/4,524.27 S/1,965.18 S/691.51 S/1,302.91
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
09.03.04 9.04 09.04.01 09.04.02 09.04.03 09.04.04 09.04.05 09.04.06 09.04.07 09.04.08 09.04.09 09.04.10 09.04.11 09.04.12 09.04.13 10 10.01 10.01.01
FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. BASE DE PERGOLA - CONCRETO f´c= 210 KG/CM2 BASE DE PERGOLA - ENCOFRADO Y DESENCOFRADO BASE DE PERGOLA - BASE METALICA ANCLAJE DE COLUMNAS DE MADERA DEPOSITO DE INSUMOS QUIMICOS TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO
m2
19.73
S/. 28.62
m3 m2 kg m3 m2 kg m2 m2 kg und m3 m2 kg
1.31 15.69 251.60 2.54 17.17 379.39 1.44 15.69 71.41 147.00 3.60 9.60 175.28
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55 S/. 427.16 S/. 62.72 S/. 18.45
m2
35.92
S/. 3.64
S/564.67 S/13,987.32 S/559.58 S/984.08 S/1,132.20 S/1,169.64 S/1,085.32 S/1,707.26 S/603.62 S/822.63 S/321.35 S/227.85 S/1,537.78 S/602.11 S/3,233.92 S/18,069.59 S/199.36 S/130.75
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
10.01.02 10.02 10.02.01 10.02.02 10.02.03 10.02.04 10.02.05 10.03 10.03.01 10.03.02 10.03.03 10.03.04 10.03.05 10.04 10.04.01 10.04.02 10.04.03 10.04.04
TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA ZAPATAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4" CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO ZAPATAS - CONCRETO f´c= 210 KG/CM2 ZAPATAS - ENCOFRADO Y DESENCOFRADO ZAPATAS - ACERO fy= 4200 KG/CM2 COLUMNAS - CONCRETO f´c= 210 KG/CM2
m2
35.92
S/. 1.91
m3 m3 m3 m3 m3
13.61 7.56 3.56 2.65 22.89
S/. 42.93 S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m2 m3 m3 m2 m2
9.90 6.05 1.30 17.37 26.54
S/. 24.28 S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2 kg m3
4.95 18.90 80.19 1.76
S/. 357.87 S/. 57.07 S/. 4.50 S/. 427.16
S/68.61 S/1,913.65 S/584.28 S/324.55 S/179.50 S/244.38 S/580.95 S/3,869.59 S/240.37 S/1,355.68 S/522.65 S/991.31 S/759.57 S/12,086.99 S/1,771.46 S/1,078.62 S/360.86 S/751.80
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
10.04.05 10.04.06 10.04.07 10.04.08 10.04.09 10.04.10 10.04.11 10.04.12 10.04.13 11 11.01 11.01.01 11.01.02 11.02 11.02.01 11.02.02 11.02.03 11.02.04
COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. PISCINA RECREATIVA TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION MASIVA EXCAVACION PARA CIMIENTOS CORRIDOS EXCAVACION PARA CANALETA RELLENO CON MATERIAL DE PRESTAMO
m2 kg m3 m2 kg m2 m2 kg und
20.67 363.46 1.84 10.87 226.03 1.89 22.32 83.21 196.00
S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18 S/. 52.43 S/. 4.50 S/. 1.55
m2 m2
2712.56 2712.56
S/. 3.64 S/. 1.91
m3 m3 m3 m3
2018.57 154.24 58.41 403.71
S/. 10.82 S/. 42.93 S/. 42.93 S/. 92.22
S/1,296.42 S/1,635.57 S/847.30 S/687.09 S/1,017.14 S/792.25 S/1,170.24 S/374.45 S/303.80 S/648,385.31 S/15,054.71 S/9,873.72 S/5,180.99 S/141,816.85 S/21,840.93 S/6,621.52 S/2,507.54 S/37,230.14
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/59,892.93 S/15,054.71 S/9,873.72 S/5,180.99 S/44,838.22 S/10,922.79 S/1,888.92 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
m3
2900.58
S/. 25.38
m2
2252.59
S/. 24.28
m3 m2 kg m3 m2 kg
444.44 645.25 24982.38 77.23 706.70 3726.51
S/. 427.16 S/. 62.72 S/. 4.50 S/. 427.16 S/. 62.72 S/. 4.50
m2 m2
60.18 60.18
S/. 3.64 S/. 1.91
m3 m3 m3
27.17 2.13 2.13
S/. 42.93 S/. 50.42 S/. 92.22
11/16/2017 11/30/2017 15 dias
11.02.05 11.03 11.03.01 11.04 11.04.01 11.04.02 11.04.03 11.04.04 11.04.05 11.04.06 12 12.01 12.01.01 12.01.02 12.02 12.02.01 12.02.02 12.02.03
ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4" OBRAS DE CONCRETO ARMADO PISCINA - CONCRETO f´c= 210 KG/CM2 PISCINA - ENCOFRADO Y DESENCOFRADO PISCINA - ACERO fy= 4200 KG/CM2 CANALETA - CONCRETO f´c= 210 KG/CM2 CANALETA - ENCOFRADO Y DESENCOFRADO CANALETA - ACERO fy= 4200 KG/CM2 DUCHAS OBLIGATORIAS TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO
S/73,616.72 S/54,692.89 S/54,692.89 S/436,820.87 S/189,846.99 S/40,470.08 S/112,420.71 S/32,989.57 S/44,324.22 S/16,769.30 S/20,708.14 S/334.00 S/219.06 S/114.94 S/2,296.35 S/1,166.41 S/107.39 S/196.43
S/32,026.51 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
12.02.04 12.03 12.03.01 12.03.02 12.03.03 12.03.04 12.04 12.04.01 12.04.02 12.04.03 13 13.01 13.01.01 13.01.02 13.02 13.02.01 13.02.02 13.02.03
ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 175 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 CUARTO DE MAQUINAS II Y CISTERNA DE COMPENSACION TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CISTERNA, CUARTO DE MAQUINAS, ESCALERA Y POZO SUMIDERO RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO
m3
32.55
S/. 25.38
m3 m3 m2 m2
20.38 3.80 50.74 21.23
S/. 224.08 S/. 328.90 S/. 57.07 S/. 28.62
m3 m2 kg
3.85 57.90 773.74
S/. 427.16 S/. 62.72 S/. 4.50
m2 m2
214.76 214.76
S/. 3.64 S/. 1.91
m3 m3 m3
378.35 5.51 42.95
S/. 15.44 S/. 50.42 S/. 92.22
S/826.12 S/9,319.90 S/4,566.75 S/1,249.82 S/2,895.73 S/607.60 S/8,757.88 S/1,644.57 S/3,631.49 S/3,481.83 S/192,087.86 S/1,191.92 S/781.73 S/410.19 S/22,381.82 S/5,841.72 S/277.81 S/3,960.85
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
13.02.04 13.03 13.03.01 13.04 13.04.01
ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4" OBRAS DE CONCRETO ARMADO CISTERNA, CUARTO DE MAQ. Y POZO SUMIDERO - CONCRETO f´c= 210 KG/CM2
m3
484.69
S/. 25.38
m2
214.76
S/. 24.28
m3
144.99
S/. 439.07
S/12,301.43 S/5,214.37 S/5,214.37 S/163,299.75 S/63,660.76
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
13.04.02 13.04.03 13.04.04 13.04.05 13.04.06 14 14.01 14.01.01 14.02 14.02.01 15 15.01 15.01.01 15.01.02 15.01.03 15.02 15.02.01 15.02.02
CISTERNA, CUARTO DE MAQ. Y POZO SUMIDERO - ENCOFRADO Y DESENCOFRADO m2 CISTERNA, CUARTO DE MAQ. Y POZO SUMIDERO - ACERO fy= 4200 KG/CM2 kg ESCALERA - CONCRETO f´c= 210 KG/CM2 m3 ESCALERA - ENCOFRADO Y DESENCOFRADO m2 ESCALERA - ACERO fy= 4200 KG/CM2 kg REMODELACION DE PISCINAS EXISTENTES TRABAJOS PRELIMINARES PICADO DE MUROS Y PISOS PARA RETIRO DE ENCHAPE EXISTENTE m2 MOVIMIENTO DE TIERRAS ELIMINACION DE MATERIAL EXCEDENTE m3 CERCO Y AREA DE CIRCULACION TRABAJOS PRELIMINARES m2 DEMOLICION DE ESTRUCTURAS EXISTENTES LIMPIEZA DE TERRENO m2 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA m2 MOVIMIENTO DE TIERRAS m3 CORTE Y NIVELACIÓN DE AREA DE CIRCULACION EXCAVACION PARA POSTES DE CERCO m3
569.46 13,315.36 3.72 19.79 246.84
S/. 63.21 S/. 4.50 S/. 402.04 S/. 56.49 S/. 4.50
696.45
S/. 50.10
45.27
S/. 25.38
4536.02 4956.15 4956.15
S/. 32.89 S/. 3.64 S/. 1.91
1982.46 13.20
S/. 10.74 S/. 42.93
S/35,995.57 S/59,919.12 S/1,495.59 S/1,117.94 S/1,110.78 S/36,041.10 S/34,892.15 S/34,892.15 S/1,148.95 S/1,148.95 S/578,433.72 S/176,696.33 S/149,189.70 S/18,040.39 S/9,466.25 S/239,056.61 S/21,291.62 S/566.68
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/36,041.10 S/34,892.15 S/34,892.15 S/1,148.95 S/1,148.95 S/259,145.28 S/159,824.00 ### S/16,380.00 S/8,595.00 S/99,321.28 S/10,740.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
m3 m3
991.23 4956.15
S/. 92.22 S/. 25.38
m2
4956.15
S/. 28.62
m3 m2 und
16.97 37.68 165.00
S/. 371.16 S/. 51.69 S/. 76.30
m2 m2
60.71 60.71
S/. 3.64 S/. 1.91
m3 m3 m3
215.53 9.10 280.19
S/. 42.93 S/. 92.22 S/. 25.38
m2
60.71
S/. 24.28
11/16/2017 11/30/2017 15 dias
15.02.03 15.02.04 15.03 15.03.01 15.04 15.04.01 15.04.02 15.04.03 16 16.01 16.01.01 16.01.02 16.02 16.02.01 16.02.02 16.02.03 16.03 16.03.01
RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO BASE DE POSTES CERCOS - CONCRETO f´c= 175 KG/CM2 BASE DE POSTES CERCOS - ENOFRADO Y DESENCOFRADO BASE DE POSTES - PLANCHA DE 8"x8"x 2.50 MM SUBESTACION ELECTRICA TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA SUB ESTACION ELECTRICA RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE SOLADO C:H 1:10 E = 4"
S/91,411.23 S/125,787.09 S/141,845.01 S/141,845.01 S/20,835.76 S/6,298.59 S/1,947.68 S/12,589.50 S/85,654.89 S/336.94 S/220.98 S/115.96 S/17,203.13 S/9,252.70 S/839.20 S/7,111.22 S/1,474.04 S/1,474.04
S/0.00 S/88,581.28 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERAD OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTCONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES . SUPERVISA CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 NOVIEMBRE
VALOR REFERENCIAL COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
11/16/2017 11/30/2017 15 dias
16.04 16.04.01 16.04.02 16.04.03
OBRAS DE CONCRETO ARMADO SUBESTACION ELECTRICA - CONCRETO f´c= 210 KG/CM2 SUBESTACION ELECTRICA - ENCOFRADO Y DESENCOFRADO SUBESTACION ELECTRICA - ACERO fy= 4200 KG/CM2 Costo Directo Gastos Generales Utilidad Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
m3 m2 kg
54.15 298.42 5,333.78
S/66,640.78 S/. 439.07 S/23,775.64 S/. 63.21 S/18,863.13 S/. 4.50 S/24,002.01 S/2,393,811.38 8.00% S/191,504.91 7.00% S/167,566.80 S/2,752,883.09 0.971 S/2,673,049.38 18.00% S/481,148.89 S/3,154,198.27
S/0.00 S/0.00 S/0.00 S/0.00 S/405,284.58 S/32,422.77 S/28,369.92 S/466,077.27 S/452,561.01 S/81,460.98 S/534,021.99
PORCENTAJE DE AVANCE ( % )
16.93%
PORCENTAJE ACUMULADO DE AVANCE ( % )
16.93%
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
S/34,309.50 S/750.00 S/0.00 S/33,007.50 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/150.00 S/45.00 S/19.50 S/4.50 S/153.00 S/180.00 S/0.00 S/93,137.59
31 dias
S/10,053.08 S/900.00 S/0.00 S/1,467.00 S/0.00 S/0.00 S/1,292.08 S/194.11 S/369.89 S/0.00 S/150.00 S/300.00 S/130.00 S/30.00 S/1,020.00 S/1,200.00 S/3,000.00 S/76,049.19
28 dias
S/8,672.87 S/500.00 S/0.00 S/0.00 S/3,797.22 S/760.05 S/0.00 S/77.64 S/147.96 S/400.00 S/150.00 S/150.00 S/65.00 S/15.00 S/510.00 S/600.00 S/1,500.00 S/0.00
MARZO
19 dias
S/3,822.79 S/277.37 S/0.00 S/768.03 S/0.00 S/0.00 S/0.00 S/16.15 S/30.78 S/277.37 S/145.62 S/118.58 S/51.38 S/11.86 S/403.16 S/474.31 S/1,248.18 S/0.00
ABRIL
12 dias
30 dias
MAYO
8 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/4,627.59 S/335.77 S/0.00 S/929.72 S/0.00 S/0.00 S/0.00 S/19.55 S/37.26 S/335.77 S/176.28 S/143.54 S/62.20 S/14.35 S/488.04 S/574.16 S/1,510.95 S/0.00
30 dias
S/6,035.98 S/437.96 S/0.00 S/1,212.68 S/0.00 S/0.00 S/0.00 S/25.50 S/48.60 S/437.96 S/229.93 S/187.23 S/81.13 S/18.72 S/636.57 S/748.91 S/1,970.80 S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
S/981.41 S/643.66 S/337.75 S/5,053.20 S/1,604.29 S/1,210.20 S/1,477.31 S/0.00 S/761.40 S/13,691.69 S/725.00 S/6,431.10 S/2,239.36 S/4,296.23 S/0.00 S/73,411.29 S/5,346.58 S/3,058.95
31 dias
S/0.00 S/0.00 S/0.00 S/3,873.13 S/0.00 S/0.00 S/0.00 S/2,890.17 S/982.96 S/17,585.74 S/0.00 S/6,440.06 S/2,247.41 S/4,410.37 S/4,487.90 S/54,590.32 S/0.00 S/0.00
28 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
19 dias
ABRIL
12 dias
30 dias
MAYO
8 dias
JUNIO
23 dias
30 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/685.49 S/4,271.60 S/6,585.60 S/6,210.86 S/13,593.66 S/7,103.54 S/14,354.42 S/0.00 S/6,895.59 S/3,600.00 S/1,705.00 S/0.00 S/0.00 S/0.00 S/63,265.94 S/598.77 S/518.55 S/80.22
S/0.00 S/4,040.93 S/6,633.27 S/0.00 S/0.00 S/7,107.33 S/14,354.42 S/9,574.07 S/6,937.54 S/4,082.76 S/1,860.00 S/0.00 S/0.00 S/0.00 S/116,737.39 S/191.88 S/0.00 S/191.88
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/15,661.17 S/0.00 S/0.00 S/0.00
MARZO
S/2,610.32 S/0.00 S/0.00 S/0.00
ABRIL
S/0.00 S/0.00
S/0.00 S/0.00
MAYO
S/0.00 S/0.00
JUNIO
S/9,873.78 S/0.00 S/0.00 S/0.00
S/60,425.32 S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
S/15,736.30 S/0.00 S/214.65 S/4,948.06 S/0.00 S/0.00 S/10,573.59 S/12,724.22 S/1,553.92 S/6,274.24 S/2,613.26 S/2,282.80 S/0.00 S/34,206.65 S/4,652.31 S/2,568.15 -S/95.67 S/3,699.21
31 dias
S/1,626.76 S/0.00 S/0.00 S/0.00 S/0.00 S/1,626.76 S/0.00 S/2,901.65 S/690.04 S/0.00 S/0.00 S/0.00 S/2,211.61 S/112,017.10 S/0.00 S/0.00 S/0.00 S/854.32
28 dias
S/3,028.58 S/632.79 S/518.59 S/0.00 S/1,335.12 S/0.00 S/542.08 S/3,391.02 S/264.40 S/1,658.19 S/723.67 S/744.76 S/0.00 S/9,241.57 S/1,227.50 S/827.52 S/0.00 S/0.00
MARZO
19 dias
S/245.31 S/0.00 S/0.00 S/0.00 S/0.00 S/245.31 S/0.00 S/2,365.01 S/0.00 S/751.15 S/276.45 S/336.92 S/1,000.49 S/0.00
ABRIL
12 dias
30 dias
MAYO
8 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/296.95 S/0.00 S/0.00 S/0.00 S/0.00 S/296.95 S/0.00 S/2,862.91 S/0.00 S/909.29 S/334.65 S/407.85 S/1,211.12 S/6,713.92 S/0.00 S/0.00 S/0.00 S/262.28
30 dias
S/0.00
S/0.00
S/60,425.32 S/0.00 S/0.00 S/0.00 S/2,360.48
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/3,763.20 S/6,840.00 S/0.00 S/0.00 S/0.00 S/0.00 S/6,029.45 S/2,250.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/4,500.00 S/0.00 S/0.00 S/0.00
S/3,763.20 S/7,200.00 S/7,377.05 S/8,091.89 S/15,004.01 S/4,200.18 S/246.15 S/1,025.64 S/1,593.40 S/0.00 S/0.00 S/0.00 S/17,835.02 S/22,359.27 S/22,466.97 S/0.00 S/0.00 S/0.00
S/0.00 S/1,241.55 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/5,945.01 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/437.41 S/0.00 S/491.80 S/539.46 S/1,000.27 S/420.02 S/603.18 S/313.46 S/159.34 S/348.48 S/758.55 S/458.42 S/0.00 S/0.00 S/0.00 S/339.32 S/311.82 S/270.11
S/3,936.68 S/0.00 S/4,426.23 S/4,855.14 S/9,002.40 S/3,780.17 S/5,428.64 S/2,821.15 S/1,434.06 S/3,136.29 S/6,826.93 S/4,125.82 S/0.00 S/0.00 S/0.00 S/3,053.90 S/2,806.42 S/2,431.01
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
31 dias
S/74,039.04 S/404.04 S/264.99 S/139.05 S/6,496.72 S/1,496.11 S/1,314.52 S/1,775.23 S/1,910.86 S/10,198.41 S/26.47 S/3,742.14 S/1,455.38 S/3,177.66 S/1,796.76 S/56,939.87 S/2,726.97 S/1,581.98
28 dias
S/18,468.56 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/18,468.56 S/0.00 S/0.00
MARZO
19 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
ABRIL
12 dias
30 dias
MAYO
8 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
30 dias
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/1,888.29 S/6,902.91 S/17,611.78 S/16,386.03 S/0.00 S/2,048.00 S/2,720.25 S/0.00 S/2,491.47 S/1,782.00 S/800.19 S/11,438.76 S/337.11 S/221.10 S/116.01 S/1,613.37 S/960.34 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/5,139.07 S/2,048.01 S/2,720.25 S/3,487.58 S/2,491.48 S/1,782.00 S/800.18 S/11,695.56 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/734.64 S/0.00 S/0.00 S/0.00 S/114.73 S/0.00 S/114.73
ABRIL
MAYO
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/889.30 S/0.00 S/0.00 S/0.00 S/138.88 S/0.00 S/138.88
S/0.00 S/0.00
S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/653.03 S/6,116.20 S/2,733.78 S/1,061.39 S/2,321.04 S/0.00 S/3,372.08 S/0.00 S/0.00 S/3,372.08 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/177.98
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/11,695.56 S/1,665.92 S/2,093.59 S/0.00 S/828.88 S/511.37 S/1,835.64 S/1,291.07 S/1,847.11 S/1,323.00 S/298.98 S/7,620.84
MARZO
S/0.00 S/619.91 S/0.00 S/0.00 S/0.00 S/619.91 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
ABRIL
MAYO
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
S/0.00 S/750.41 S/0.00 S/0.00 S/0.00 S/750.42 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/3,112.01
S/0.00
S/0.00
S/28,008.06
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
31 dias
S/177.98 S/116.73 S/61.25 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
28 dias
S/0.00 S/0.00 S/0.00 S/3,956.26 S/812.15 S/567.53 S/0.00 S/2,576.58 S/2,411.10 S/2,411.10 S/0.00 S/1,253.48 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/1,253.48
MARZO
19 dias
ABRIL
12 dias
30 dias
MAYO
8 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/0.00 S/0.00 S/0.00 S/36.70 S/0.00 S/0.00 S/36.70 S/0.00 S/87.81 S/0.00 S/87.81 S/2,987.50 S/129.98 S/303.82 S/100.53 S/91.41 S/1,525.35 S/0.00
30 dias
S/0.01 S/0.00 S/0.00 S/330.33 S/0.00 S/0.00 S/330.33 S/0.00 S/790.26 S/790.26 S/26,887.47 S/1,169.86 S/2,734.34 S/904.81 S/822.71 S/13,728.15 S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/2,157.98 S/0.00 S/0.00 S/0.00 S/2,157.98 S/0.00 S/0.00 S/2,157.98 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/4,156.98 S/337.55 S/221.38 S/116.17 S/3,819.43 S/52.80 S/419.09 S/0.00 S/770.96 S/2,576.58 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/25,503.24 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/20,324.20
MARZO
S/124.95 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
ABRIL
MAYO
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
S/87.03 S/238.11 S/140.69 S/102.28 S/146.23 S/104.85 S/17.21 S/2,373.98 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/783.29 S/2,143.01 S/1,266.23 S/920.52 S/1,316.05 S/943.65 S/154.85 S/0.00 S/0.00
S/0.00
S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/18,730.85 S/1,593.35 S/5,179.04 S/3,263.77 S/444.58 S/1,048.32 S/0.00 S/0.00 S/422.37 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/0.00 S/0.00 S/124.95 S/0.00 S/0.00 S/0.00 S/36.38 S/5.11 S/0.00 S/0.55 S/65.51 S/17.39 S/0.00 S/0.00
S/0.00
ABRIL
MAYO
JUNIO
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00 S/2,373.98 S/0.00 S/0.00 S/0.00 S/691.31 S/97.13 S/0.00 S/10.48 S/1,244.69 S/330.37 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,398.24 S/105.45 S/69.16 S/36.29 S/165.14 S/79.12
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
30 dias
S/29.88 S/56.14 S/61.76 S/61.76 S/225.43 S/82.31 S/43.83 S/37.07 S/15.38 S/30.11 S/16.74 S/840.46 S/156.21 S/280.00 S/134.06 S/52.80 S/27.05 S/24.33
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
30 dias
S/57.20 S/13.52 S/69.69 S/25.60 S/2,032.70 S/62.56 S/41.03 S/21.53 S/118.98 S/47.05 S/9.27 S/3.48 S/18.17 S/41.01 S/452.43 S/196.52 S/69.15 S/130.29
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/8,376.08 S/199.36 S/130.75
MARZO
ABRIL
MAYO
JUNIO
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/4,385.16 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/5,308.35 S/0.00 S/0.00
30 dias
S/56.47 S/1,398.73 S/55.96 S/98.41 S/113.22 S/116.96 S/108.53 S/170.73 S/60.36 S/82.26 S/32.13 S/22.79 S/153.78 S/60.21 S/323.39 S/0.00 S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/68.61 S/1,734.16 S/584.28 S/324.55 S/0.00 S/244.38 S/580.95 S/1,596.05 S/240.37 S/1,355.68 S/0.00 S/0.00 S/0.00 S/4,846.51 S/1,771.46 S/1,078.62 S/360.86 S/0.00
MARZO
S/0.00 S/81.20 S/0.00 S/0.00 S/81.20 S/0.00 S/0.00 S/1,028.51 S/0.00 S/0.00 S/236.44 S/448.45 S/343.62 S/3,275.46 S/0.00 S/0.00 S/0.00 S/340.10
ABRIL
MAYO
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
S/0.00 S/98.29 S/0.00 S/0.00 S/98.29 S/0.00 S/0.00 S/1,245.03 S/0.00 S/0.00 S/286.21 S/542.86 S/415.96 S/3,965.03 S/0.00 S/0.00 S/0.00 S/411.70
S/0.00
S/0.00
S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/47,248.22 S/0.00 S/0.00 S/0.00 S/47,248.22 S/0.00 S/2,404.08 S/0.00 S/37,230.14
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/401,622.99 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/1,635.57 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/586.48 S/0.00 S/383.30 S/310.83 S/460.13 S/358.40 S/529.39 S/169.39 S/137.43 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
ABRIL
MAYO
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
S/709.95 S/0.00 S/464.00 S/376.27 S/557.00 S/433.85 S/640.84 S/205.05 S/166.37 S/9,467.58 S/0.00 S/0.00 S/0.00 S/4,973.04 S/1,091.81 S/232.85 S/250.75 S/0.00
S/49,251.91 S/0.00
S/44,757.37 S/9,826.32 S/2,095.67 S/2,256.79 S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/7,614.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/54,692.89 S/54,692.89 S/346,930.10 ### S/40,470.08 ### S/0.00 S/0.00 S/4,192.32 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/5,187.56 S/167.00 S/109.53 S/57.47 S/996.26 S/583.20 S/0.00 S/0.00
MARZO
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
ABRIL
MAYO
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/3,397.62 S/0.00 S/0.00 S/4,494.54 S/0.00 S/0.00 S/0.00 S/1,649.48 S/2,216.21 S/628.85 S/776.03 S/8.35 S/5.48 S/2.87 S/65.00 S/29.16 S/5.37 S/9.82
30 dias
S/30,578.59 S/0.00 S/4,494.54
S/1,649.48 S/2,216.21 S/628.85 S/776.03 S/8.35 S/5.48 S/2.87 S/65.00 S/29.16 S/5.37 S/9.82
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/50,653.99 S/1,191.92 S/781.73 S/410.19 S/17,247.70 S/4,349.60 S/0.00 S/3,960.85
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/413.06 S/2,283.38 S/2,283.38 S/0.00 S/0.00 S/0.00 S/1,740.92 S/0.00 S/0.00 S/1,740.92 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/20.65 S/351.83 S/114.17 S/62.49 S/144.79 S/30.38 S/350.85 S/82.23 S/181.57 S/87.05 S/256.71 S/0.00 S/0.00 S/0.00 S/256.71 S/74.61 S/13.89 S/0.00
30 dias
S/20.65 S/351.83 S/114.17 S/62.49 S/144.79 S/30.38 S/350.85 S/82.23 S/181.57 S/87.05 S/7,071.69 S/0.00 S/0.00 S/0.00 S/256.71 S/74.61 S/13.89 S/0.00
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/8,937.25 S/5,214.37 S/5,214.37 S/27,000.00 S/0.00
MARZO
S/0.00 S/0.00 S/0.00
ABRIL
MAYO
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
23 dias
S/168.21 S/0.00 S/0.00 S/0.00
30 dias
S/168.21 S/0.00 S/0.00 S/6,814.99 S/3,183.04
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/27,000.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/10,373.00 S/7,688.00 S/6,578.00 S/728.00 S/382.00 S/2,685.00 S/2,685.00 S/0.00
MARZO
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/6,626.48 S/459.22 S/388.13 S/46.62 S/24.46 S/6,167.27 S/354.00 S/25.50
ABRIL
MAYO
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
JUNIO
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/685.25 S/0.00
S/685.25 S/39.33 S/2.83
30 dias
S/1,799.78 S/1,645.96 S/74.78 S/55.90 S/55.54 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/30,891.54 S/918.43 S/776.27 S/93.24 S/48.92 S/13,705.03 S/786.66 S/56.67
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/9,589.64 S/336.94 S/220.98 S/115.96 S/9,252.70 S/9,252.70 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
23 dias
S/4,113.51 S/1,674.26 S/0.00
S/0.00
S/0.00
S/0.00
S/457.06 S/186.03 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
30 dias
S/9,141.12 S/3,720.58 S/14,184.50 S/14,184.50 S/2,083.58 S/629.86 S/194.77 S/1,258.95 S/7,606.52 S/0.00 S/0.00 S/0.00 S/795.04 S/0.00 S/83.92 S/711.12 S/147.40 S/147.40
IZADO ACELERADO DE AVANCE DE OBRA- ZONA RECREATIVA ESTRUCTURAS
AÑO 2017
AÑO 2018 DICIEMBRE
ENERO
FEBRERO
12/1/2017
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
12/31/2017
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/301,146.22 S/24,091.70 S/21,080.24 S/346,318.16 S/336,274.92 S/60,529.49 S/396,804.41
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/703,865.07 S/56,309.21 S/49,270.56 S/809,444.84 S/785,970.91 S/141,474.76 S/927,445.67
28 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/101,185.89 S/8,094.87 S/7,083.01 S/116,363.77 S/112,989.21 S/20,338.06 S/133,327.27
MARZO
19 dias
S/0.00
S/0.00 S/18,304.33 S/1,464.35 S/1,281.30 S/21,049.98 S/20,439.53 S/3,679.12 S/24,118.65
ABRIL
12 dias
S/0.00
30 dias
S/0.00
MAYO
8 dias
S/0.00
JUNIO
23 dias
S/0.00
S/37,370.57 S/2,989.65 S/2,615.94 S/42,976.16 S/41,729.85 S/7,511.37 S/49,241.22
30 dias
S/6,664.08 S/2,377.56 S/1,886.31 S/2,400.20 S/193,498.01 S/15,479.84 S/13,544.86 S/222,522.71 S/216,069.54 S/38,892.52 S/254,962.06
12.58%
29.40%
4.23%
0.76%
1.56%
8.08%
29.51%
58.91%
63.14%
63.91%
65.47%
73.55%
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
S/6,237.18 S/452.55 S/0.00 S/1,253.11 S/0.00 S/0.00 S/0.00 S/26.35 S/50.22 S/452.55 S/237.59 S/193.47 S/83.84 S/19.35 S/657.79 S/773.87 S/2,036.50 S/10,040.94
S/6,237.18 S/452.55 S/0.00 S/1,253.11 S/0.00 S/0.00 S/0.00 S/26.35 S/50.22 S/452.55 S/237.59 S/193.47 S/83.84 S/19.35 S/657.79 S/773.87 S/2,036.50 S/10,040.94
292 dias
3 dias
S/603.60 S/43.80 S/0.00 S/121.27 S/0.00 S/0.00 S/0.00 S/2.55 S/4.86 S/43.80 S/22.99 S/18.72 S/8.11 S/1.87 S/63.66 S/74.89 S/197.08 S/971.70
S/90,432.08 S/5,000.00 S/2,506.14 S/40,012.43 S/3,797.22 S/760.05 S/3,800.25 S/776.43 S/1,479.56 S/2,400.00 S/1,500.00 S/1,500.00 S/650.00 S/150.00 S/5,100.00 S/6,000.00 S/15,000.00 S/219,446.58
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/2,140.39
S/2,140.39
S/207.13
S/2,140.39 S/7,900.56
S/2,140.39 S/7,900.56
S/207.13 S/764.57
S/2,145.41 S/1,407.08 S/738.33 S/13,381.52 S/3,224.90 S/2,418.68 S/1,477.31 S/2,890.17 S/3,370.46 S/36,470.42 S/1,430.09 S/12,871.16 S/4,486.77 S/8,706.60 S/8,975.80 S/167,449.23 S/10,542.85 S/6,060.83
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/1,753.90 S/3,835.38 S/2,311.28 S/0.00 S/0.00
S/1,753.90 S/3,835.38 S/2,311.28 S/0.00 S/0.00
S/169.73 S/371.17 S/223.67 S/0.00 S/0.00
292 dias
S/2,796.04 S/8,312.53 S/13,218.87 S/18,784.09 S/13,593.66 S/14,210.87 S/28,708.84 S/9,574.07 S/13,833.13 S/7,682.76 S/3,565.00 S/3,677.54 S/8,041.92 S/4,846.23 S/279,740.67 S/1,898.77 S/1,245.32 S/653.45
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/25,050.43 S/2,130.19 S/1,770.43 S/4,948.06 S/1,335.12 S/2,169.01 S/12,697.61 S/24,732.60 S/2,996.15 S/9,592.86 S/3,948.03 S/3,772.33 S/4,423.22 S/228,058.88 S/6,964.15 S/4,023.44 S/1,836.09 S/7,176.29
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
292 dias
S/11,900.49 S/17,091.99 S/12,295.08 S/13,486.49 S/25,006.68 S/8,400.37 S/12,307.42 S/6,410.25 S/3,186.80 S/3,484.77 S/7,585.48 S/4,584.24 S/23,780.03 S/22,359.27 S/26,966.97 S/3,393.22 S/3,118.25 S/2,701.13
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
292 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/92,507.60 S/404.04 S/264.99 S/139.05 S/6,496.72 S/1,496.11 S/1,314.52 S/1,775.24 S/1,910.86 S/10,198.41 S/26.47 S/3,742.14 S/1,455.38 S/3,177.66 S/1,796.76 S/75,408.43 S/2,726.97 S/1,581.98
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/1,888.29 S/6,902.91 S/17,611.78 S/16,386.03 S/5,139.07 S/4,096.01 S/5,440.50 S/3,487.58 S/4,982.95 S/3,564.00 S/1,600.38 S/24,758.25 S/337.11 S/221.09 S/116.01 S/1,866.98 S/960.34 S/253.61
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/653.03 S/7,486.52 S/2,733.78 S/1,061.39 S/2,321.04 S/1,370.33 S/15,067.65 S/1,665.92 S/2,093.59 S/3,372.08 S/828.88 S/511.37 S/1,835.64 S/1,291.07 S/1,847.11 S/1,323.00 S/298.98 S/38,918.89
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/177.99 S/116.73 S/61.25 S/4,323.30 S/812.15 S/567.53 S/367.04 S/2,576.58 S/3,289.16 S/2,411.10 S/878.06 S/31,128.44 S/1,299.85 S/3,038.16 S/1,005.35 S/914.12 S/15,253.50 S/1,253.47
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/870.33 S/2,381.12 S/1,406.93 S/1,022.80 S/1,462.27 S/1,048.50 S/172.05 S/34,317.12 S/337.55 S/221.38 S/116.17 S/5,977.41 S/52.80 S/419.09 S/2,157.98 S/770.96 S/2,576.58 S/20,324.20
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/0.00
S/0.00
S/0.00
S/12,584.20 S/949.05 S/622.44 S/326.61 S/1,486.26 S/712.08
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
292 dias
S/18,730.85 S/1,593.35 S/7,677.97 S/3,263.77 S/444.58 S/1,048.32 S/727.69 S/102.25 S/422.37 S/11.03 S/1,310.19 S/347.76 S/13,982.44 S/1,054.50 S/691.60 S/362.90 S/1,651.40 S/791.20
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/268.91 S/505.27 S/555.88 S/555.88 S/2,028.87 S/740.79 S/394.47 S/333.60 S/138.40 S/270.95 S/150.66 S/7,564.14 S/1,405.91 S/2,520.00 S/1,206.55 S/475.20 S/243.42 S/218.98
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/298.79 S/561.41 S/617.65 S/617.65 S/2,254.30 S/823.10 S/438.30 S/370.67 S/153.78 S/301.06 S/167.40 S/8,404.60 S/1,562.13 S/2,800.00 S/1,340.61 S/528.00 S/270.47 S/243.31
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/514.80 S/121.71 S/627.17 S/230.40 S/18,294.33 S/563.04 S/369.27 S/193.77 S/1,070.86 S/423.46 S/83.46 S/31.31 S/163.51 S/369.13 S/4,071.84 S/1,768.66 S/622.36 S/1,172.62
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/572.00 S/135.23 S/696.86 S/256.00 S/20,327.03 S/625.60 S/410.30 S/215.30 S/1,189.85 S/470.51 S/92.73 S/34.79 S/181.67 S/410.14 S/4,524.27 S/1,965.18 S/691.51 S/1,302.91
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/508.21 S/12,588.58 S/503.62 S/885.67 S/1,018.98 S/1,052.68 S/976.78 S/1,536.53 S/543.26 S/740.36 S/289.21 S/205.07 S/1,384.00 S/541.90 S/2,910.52 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
292 dias
S/564.67 S/13,987.32 S/559.58 S/984.08 S/1,132.20 S/1,169.64 S/1,085.32 S/1,707.26 S/603.62 S/822.63 S/321.35 S/227.85 S/1,537.78 S/602.11 S/3,233.92 S/18,069.59 S/199.36 S/130.75
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/68.61 S/1,913.65 S/584.28 S/324.55 S/179.50 S/244.38 S/580.95 S/3,869.59 S/240.37 S/1,355.68 S/522.65 S/991.31 S/759.57 S/12,086.99 S/1,771.46 S/1,078.62 S/360.86 S/751.80
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/8,989.08 S/0.00
S/71,912.61 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
292 dias
S/1,296.42 S/1,635.57 S/847.30 S/687.09 S/1,017.14 S/792.25 S/1,170.24 S/374.45 S/303.80 S/648,385.31 S/15,054.71 S/9,873.72 S/5,180.99 S/141,816.85 S/21,840.93 S/6,621.52 S/2,507.54 S/37,230.14
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/0.00
S/0.00
S/0.00
S/8,989.08
S/71,912.61
S/0.00
S/3,298.96 S/4,432.42 S/1,257.70 S/1,552.06 S/16.70 S/10.95 S/5.75 S/130.01 S/58.32 S/10.74 S/19.64
S/26,391.65 S/35,459.38 S/10,061.58 S/12,416.46 S/133.60 S/87.62 S/45.98 S/1,040.07 S/466.57 S/85.92 S/157.14
S/0.00 S/0.00
S/0.00
292 dias
S/73,616.72 S/54,692.89 S/54,692.89 S/436,820.87 S/189,846.99 S/40,470.08 S/112,420.71 S/32,989.57 S/44,324.22 S/16,769.30 S/20,708.14 S/334.00 S/219.06 S/114.94 S/2,296.35 S/1,166.41 S/107.39 S/196.43
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/41.31 S/703.65 S/228.34 S/124.98 S/289.57 S/60.76 S/701.70 S/164.46 S/363.15 S/174.09 S/14,143.39 S/0.00 S/0.00 S/0.00 S/513.41 S/149.21 S/27.78 S/0.00
S/330.45 S/5,629.22 S/1,826.70 S/999.86 S/2,316.59 S/486.08 S/5,613.57 S/1,315.65 S/2,905.19 S/1,392.73 S/119,962.08 S/0.00 S/0.00 S/0.00 S/4,107.30 S/1,193.70 S/222.25 S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00
292 dias
S/826.12 S/9,319.90 S/4,566.75 S/1,249.82 S/2,895.73 S/607.60 S/8,757.88 S/1,644.57 S/3,631.49 S/3,481.83 S/192,087.86 S/1,191.92 S/781.73 S/410.19 S/22,381.82 S/5,841.72 S/277.81 S/3,960.85
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/336.42 S/0.00 S/0.00 S/13,629.98 S/6,366.08
S/2,691.35 S/0.00 S/0.00 S/115,854.79 S/54,111.65
S/0.00 S/0.00
292 dias
S/12,301.43 S/5,214.37 S/5,214.37 S/163,299.75 S/63,660.76
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/3,599.56 S/3,291.91 S/149.56 S/111.79 S/111.08 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/30,891.54 S/918.43 S/776.27 S/93.24 S/48.92 S/13,705.03 S/786.66 S/56.67
S/30,596.23 S/27,981.25 S/1,271.25 S/950.25 S/944.16 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/239,820.62 S/6,888.25 S/5,822.02 S/699.29 S/366.93 S/102,787.75 S/5,899.97 S/425.01
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
292 dias
S/35,995.57 S/59,919.12 S/1,495.59 S/1,117.94 S/1,110.78 S/36,041.10 S/34,892.15 S/34,892.15 S/1,148.95 S/1,148.95 S/578,433.72 S/176,696.33 S/149,189.70 S/18,040.39 S/9,466.25 S/239,056.61 S/21,291.62 S/566.68
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
31 dias
3 dias
S/9,141.12 S/3,720.58 S/14,184.50 S/14,184.50 S/2,083.58 S/629.86 S/194.77 S/1,258.95 S/12,701.73 S/0.00 S/0.00 S/0.00 S/795.04 S/0.00 S/83.92 S/711.12 S/442.21 S/442.21
S/68,558.42 S/27,904.36 S/113,476.01 S/113,476.01 S/16,668.61 S/5,038.87 S/1,558.14 S/10,071.60 S/55,756.99 S/0.00 S/0.00 S/0.00 S/6,360.34 S/0.00 S/671.36 S/5,688.98 S/884.42 S/884.42
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
292 dias
S/91,411.23 S/125,787.09 S/141,845.01 S/141,845.01 S/20,835.76 S/6,298.59 S/1,947.68 S/12,589.50 S/85,654.89 S/336.94 S/220.98 S/115.96 S/17,203.13 S/9,252.70 S/839.20 S/7,111.22 S/1,474.04 S/1,474.04
TOTAL JULIO
AGOSTO
SETIEMBRE
7/1/2018
8/1/2018
9/1/2018
7/31/2018
8/31/2018
9/3/2018
31 dias
S/11,464.48 S/2,377.56 S/1,886.31 S/7,200.60 S/115,434.45 S/9,234.76 S/8,080.41 S/132,749.62 S/128,899.88 S/23,201.98 S/152,101.86
31 dias
S/48,512.22 S/19,020.51 S/15,090.50 S/14,401.21 S/516,146.89 S/41,291.75 S/36,130.28 S/593,568.92 S/576,355.40 S/103,743.97 S/680,099.37
292 dias
3 dias
S/0.00
S/1,575.30 S/126.02 S/110.27 S/1,811.59 S/1,759.06 S/316.63 S/2,075.69
4.82%
21.56%
0.07%
78.37%
99.93%
100.00%
S/66,640.78 S/23,775.64 S/18,863.13 S/24,002.01 S/2,393,811.38 S/191,504.91 S/167,566.80 S/2,752,883.09 S/2,673,049.38 S/481,148.89 S/3,154,198.27
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
01 1.01 01.01.01 01.01.02 1.02 01.02.01 01.02.02 01.02.03 01.02.04 01.02.05 01.02.06 01.02.07 1.03 01.03.01 1.04 01.04.01 01.04.02
SS.HH. Y VESTUARIOS MUJERES MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA MURO DE LADRILLO KK ASENTADO DE CANTO REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO PRIMARIO RAYADO TARRAJEO DE MUROS INTERIORES TARRAJEO DE COLUMNAS TARRAJEO DE VIGAS TARRAJEO DE MUROS EXTERIORES DERRAMES BRUÑAS CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO CERAMICO 45x45 CM. CEMENTO GRIS PLATA
m2 m2
554.98 139.98
S/. 72.90 S/. 57.08
m2 m2 m2 m2 m2 m m
966.66 395.74 207.48 80.38 164.74 42.40 387.90
S/. 20.63 S/. 21.76 S/. 27.98 S/. 33.82 S/. 27.64 S/. 17.94 S/. 3.26
m2
359.08
S/. 31.47
m2 m2
248.86 209.52
S/. 46.80 S/. 83.21
S/. 394,971.57 S/. 48,448.10 S/. 40,458.04 S/. 7,990.06 S/. 43,655.86 S/. 19,942.20 S/. 8,611.30 S/. 5,805.29 S/. 2,718.45 S/. 4,553.41 S/. 760.66 S/. 1,264.55 S/. 11,300.25 S/. 11,300.25 S/. 37,488.94 S/. 11,646.65 S/. 17,434.16
S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
31 dias
S/. 21,081.95 S/. 21,081.95 S/21,081.95 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01.04.03 01.04.04 1.05 01.05.01 01.05.02 01.05.03 01.05.04 1.06 01.06.01 01.06.02 1.07 01.07.01 1.08 01.08.01 01.08.02 01.08.03 01.08.04
PISO DE TERRAZO LAVADO PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. ZOCALOS ZOCALO CERAMICO DE 45 x 45 CM. CEMENTO BLANCO ZOCALO CERAMICO DE 15 x 45 CM. CEMENTO GRIS PLATA ZOCALO CERAMICO DE 30 x 30 CM. COLOR 1 ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 CONTRAZOCALOS CONTRAZOCALO SANITARIO DE TERRAZO LAVADO CONTRAZOCALOS DE CEMENTO PULIDO COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA CARPINTERIA DE MADERA PUERTA CONTRAPLACADA MDF PUERTA EN AREA DE LOCKER DE DOS HOJAS SEGUN DISEÑO PUERTA DE INGRESO A VESTIDORES DOBLE HOJA, SEGÚN DISEÑO CASILLERO DE MELAMINE SEGÚN DISEÑO PARA GUARDARROPA
METRADO
C. Unit.
m2 m2
39.34 70.10
S/. 129.25 S/. 47.41
m2 m2 m2 m2
535.74 44.84 313.60 20.80
S/. 76.64 S/. 76.64 S/. 76.64 S/. 76.64
m m
221.90 46.40
S/. 30.39 S/. 15.27
m2
386.56
S/. 45.52
m2 m2 m2 m
7.14 5.04 6.30 64.96
S/. 204.18 S/. 362.46 S/. 315.16 S/. 450.00
S/. 5,084.70 S/. 3,323.44 S/. 70,124.07 S/. 41,059.11 S/. 3,436.54 S/. 24,034.30 S/. 1,594.11 S/. 7,452.07 S/. 6,743.54 S/. 708.53 S/. 17,596.21 S/. 17,596.21 S/. 34,502.15 S/. 1,457.85 S/. 1,826.80 S/. 1,985.51 S/. 29,232.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
1.09 01.09.01 01.09.02 01.09.03 01.09.04 1.1 01.10.01 01.10.02 01.10.03 1.11 01.11.01 1.12 01.12.01 01.12.02 01.12.03 1.13 01.13.01
CARPINTERIA METALICA REJA DE SEGURIDAD EN VENTANAS DE TEATINAS m2 TABIQUE SEPARADOR METALICO COLOR GRIS CON PUERTA PARA CUBIL D m BARANDA DE TUBO DE ACERO INOXIDABLE DE 1 1/2", EN SS.HH. MINUS m REJILLA METALICA PARA SUMIDERO DE ANGULO Y PERFILES METALICOS am CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS und PESTILLO PARA CUBILES DE INODOROS und VIDRIOS, CRISTALES Y SIMILARES ESPEJO BISELADO e= 6 mm m2 PINTURA PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 APARATOS Y ACCESORIOS SANITARIOS TASA ELONGADA VITRIFICADA TIPO 1 C/FLUXOMETRO PARA DESCARGA INpza
METRADO
C. Unit.
54.72 22.00 3.80 21.60
S/. 157.50 S/. 367.50 S/. 231.00 S/. 175.95
62.00 10.00 10.00
S/. 18.84 S/. 85.67 S/. 18.19
17.50
S/. 132.00
603.22 164.74 439.46
S/. 14.79 S/. 16.59 S/. 11.01
10.00
S/. 689.60
S/. 21,381.72 S/. 8,618.40 S/. 8,085.00 S/. 877.80 S/. 3,800.52 S/. 2,206.68 S/. 1,168.08 S/. 856.70 S/. 181.90 S/. 2,310.00 S/. 2,310.00 S/. 16,493.12 S/. 8,921.62 S/. 2,733.04 S/. 4,838.45 S/. 23,653.69 S/. 6,896.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01.13.02 01.13.03 01.13.04 01.13.05 01.13.06 01.13.07 01.13.08 01.13.09 01.13.10 01.13.11 1.14 01.14.01 01.14.02 01.14.03 01.14.04 2 2.01
TASA ELONGADA VITRIFICADA TIPO 2 C/FLUXOMETRO PARA DESCARGA INpza LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL pza LAVADERO CORRIDO DE CONCRETO S/DISEÑO, ACABADO EN CEMENTO m PULIDO SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza SUMINISTRO E INSTALACION DE LLAVE TEMPORIZADA CON AIREADOR pza SUMINISTRO E INSTALACION DE LLAVE DE GRIFO PARA LAVADERO PARA Cpza SUMINISTRO E INSTALACION DE GRIFERIA CROMADA PARA DUCHA AGUApza DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO und INSTALACION DE APARATOS SANITARIOS pza INSTALACION DE ACCESORIOS SANITARIOS und VARIOS BANCA DE CONCRETO SEGÚN DISEÑO ACABADO EN CEMENTO PULIDO m TABLERO DE CONCRETO SEGÚN DISEÑO ACABADO EN CEMENTO PULIDO m SUMINISTRO DE PAPELERA METÁLICA und ESTANTES PARA VESTIDORES DE MDF 18 mm CON ACABADO EN POLIUREund SS.HH. Y VESTUARIOS HOMBRES MUROS Y TABIQUES DE ALBAÑILERIA
METRADO
C. Unit.
2.00 S/. 674.60 2.00 S/. 240.00 14.40 196.93 12.00 S/. 175.00 2.00 S/. 195.00 4.00 S/. 35.00 36.00 S/. 185.00 12.00 S/. 75.00 14.00 S/. 108.11 12.00 S/. 32.43 65.50 S/. 110.36 8.10 S/. 87.67 12.00 S/. 35.00 2.00 25,000.00
S/. 1,349.20 S/. 480.00 S/. 2,835.79 S/. 2,100.00 S/. 390.00 S/. 140.00 S/. 6,660.00 S/. 900.00 S/. 1,513.54 S/. 389.16 S/. 58,358.71 S/. 7,228.58 S/. 710.13 S/. 420.00 S/. 50,000.00 S/. 359,930.64 S/. 40,203.77
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 17,174.51 S/. 17,174.51
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.01.01 02.01.02 2.02 02.02.01 02.02.02 02.02.03 02.02.04 02.02.05 02.02.06 02.02.07 02.02.08 02.02.09 2.03 02.03.01 2.04 02.04.01 02.04.02
MURO DE LADRILLO KK ASENTADO DE SOGA m2 MURO DE LADRILLO KK ASENTADO DE CANTO m2 REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO PRIMARIO RAYADO m2 TARRAJEO DE MUROS INTERIORES m2 TARRAJEO DE COLUMNAS m2 TARRAJEO DE VIGAS m2 TARRAJEO DE MUROS EXTERIORES m2 TARRAJEO CON IMPERMEABILIZANTE m2 FORJADO DE GRADAS DE ESCALERAS, ACABADO EN CEMENTO FROTACHAm2 DERRAMES m BRUÑAS m CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA m2 PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm m2 PISO CERAMICO 45x45 CM. CEMENTO GRIS PLATA m2
METRADO
C. Unit.
471.58 102.06
S/. 72.90 S/. 57.08
853.18 370.96 30.90 66.54 173.13 173.66 11.94 7.60 362.84
S/. 20.63 S/. 21.76 S/. 27.98 S/. 33.82 S/. 27.64 S/. 33.00 S/. 40.48 S/. 17.94 S/. 3.26
324.64
S/. 31.47
234.74 195.40
S/. 46.80 S/. 83.21
S/. 34,378.18 S/. 5,825.58 S/. 41,106.78 S/. 17,601.10 S/. 8,072.09 S/. 864.58 S/. 2,250.38 S/. 4,785.31 S/. 5,730.78 S/. 483.33 S/. 136.34 S/. 1,182.86 S/. 10,216.42 S/. 10,216.42 S/. 35,901.63 S/. 10,985.83 S/. 16,259.23
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
S/17,174.51 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.04.03 02.04.04 2.05 02.05.01 02.05.02 02.05.03 02.05.04 2.06 02.06.01 02.06.02 2.07 02.07.01 2.08 02.08.01 02.08.02 02.08.03 02.08.04
PISO DE TERRAZO LAVADO PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. ZOCALOS ZOCALO CERAMICO DE 45 x 45 CM. CEMENTO BLANCO ZOCALO CERAMICO DE 15 x 45 CM. CEMENTO GRIS PLATA ZOCALO CERAMICO DE 30 x 30 CM. COLOR 1 ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 CONTRAZOCALOS CONTRAZOCALO SANITARIO DE TERRAZO LAVADO CONTRAZOCALOS DE CEMENTO PULIDO COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA CARPINTERIA DE MADERA PUERTA EN AREA DE LOCKER DE DOS HOJAS SEGUN DISEÑO PUERTA DE INGRESO A VESTIDORES DOBLE HOJA, SEGÚN DISEÑO CASILLERO DE MELAMINE SEGÚN DISEÑO PARA GUARDARROPA PUERTA CONTRAPLACADA MDF - PLASTIFICADA
METRADO
C. Unit.
m2 m2
39.34 75.34
S/. 129.25 S/. 47.41
m2 m2 m2 m2
485.26 42.52 288.72 19.20
S/. 76.64 S/. 76.64 S/. 76.64 S/. 76.64
m m
193.36 38.80
S/. 30.39 S/. 15.27
m2
347.22
S/. 45.52
m2 m2 m m2
5.04 6.30 50.40 2.10
S/. 362.46 S/. 315.16 S/. 450.00 S/. 215.07
S/. 5,084.70 S/. 3,571.87 S/. 64,048.05 S/. 37,190.33 S/. 3,258.73 S/. 22,127.50 S/. 1,471.49 S/. 6,468.69 S/. 5,876.21 S/. 592.48 S/. 15,805.45 S/. 15,805.45 S/. 26,943.95 S/. 1,826.80 S/. 1,985.51 S/. 22,680.00 S/. 451.65
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
2.09 02.09.01 02.09.02 02.09.03 02.09.04 02.09.05 2.1 02.10.01 02.10.02 02.10.03 2.11 02.11.01 2.12 02.12.01 02.12.02 02.12.03 2.13
CARPINTERIA METALICA REJA DE SEGURIDAD EN VENTANAS DE TEATINAS m2 TABIQUE SEPARADOR METALICO COLOR GRIS CON PUERTA PARA CUBIL D m m TABIQUE SEPARADOR METALICO COLOR GRIS PARA SEPARACION DE URINARIOS H= 0.90 M. REJILLA METALICA PARA SUMIDERO DE ANGULO Y PERFILES METALICOS am REJILLA DE MALLA METALICA ELECTROSOLDADA m2 CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS und PESTILLO PARA CUBILES DE INODOROS und VIDRIOS, CRISTALES Y SIMILARES ESPEJO BISELADO e= 6 mm m2 PINTURA PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 APARATOS Y ACCESORIOS SANITARIOS
METRADO
C. Unit.
51.80 S/. 157.50 22.00 S/. 367.50 3.60 125.00 21.60 S/. 175.95 1.08 S/. 136.50 36.00 5.00 10.00
S/. 18.84 S/. 85.67 S/. 18.19
8.58
S/. 132.00
402.22 173.13 391.18
S/. 14.79 S/. 16.59 S/. 11.01
S/. 20,641.44 S/. 8,158.50 S/. 8,085.00 S/. 450.00 S/. 3,800.52 S/. 147.42 S/. 1,288.49 S/. 678.24 S/. 428.35 S/. 181.90 S/. 1,132.56 S/. 1,132.56 S/. 13,127.95 S/. 5,948.83 S/. 2,872.23 S/. 4,306.89 S/. 25,919.34
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.13.01 02.13.02 02.13.03 02.13.04 02.13.05 02.13.06 02.13.07 02.13.08 2.14 02.14.01 02.14.02 02.14.03 3 3.01 03.01.01 3.02 03.02.01
TASA ELONGADA VITRIFICADA TIPO 1 C/FLUXOMETRO PARA DESCARGA INpza URINARIO CADET BLANCO C/FLUXOMETRO PARA DESCARGA INDIRECTA pza LAVADERO CORRIDO DE CONCRETO S/DISEÑO, ACABADO EN CEMENTO Pm SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza SUMINISTRO E INSTALACION DE GRIFERIA CROMADA PARA DUCHA AGUApza DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO und INSTALACION DE APARATOS SANITARIOS pza INSTALACION DE ACCESORIOS SANITARIOS und VARIOS BANCA DE CONCRETO SEGÚN DISEÑO ACABADO EN CEMENTO PULIDO m SUMINISTRO DE PAPELERA METÁLICA und ESTANTES PARA VESTIDORES DE MDF 18 mm CON ACABADO EN POLIUREund SS.HH. DE HOMBRES Y MUJERES MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA m2 REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO PRIMARIO RAYADO m2
METRADO
10.00 10.00 10.80 12.00 36.00 10.00 20.00 10.00
C. Unit.
S/. 689.60 S/. 490.00 S/. 196.93 S/. 175.00 S/. 185.00 S/. 75.00 S/. 108.11 S/. 32.43
61.40 S/. 110.36 10.00 S/. 35.00 2.00 25,000.00
202.52
S/. 72.90
463.14
S/. 20.63
S/. 6,896.00 S/. 4,900.00 S/. 2,126.84 S/. 2,100.00 S/. 6,660.00 S/. 750.00 S/. 2,162.20 S/. 324.30 S/. 57,126.10 S/. 6,776.10 S/. 350.00 S/. 50,000.00 S/. 153,528.33 S/. 14,763.71 S/. 14,763.71 S/. 17,340.34 S/. 9,554.58
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
03.02.02 03.02.03 03.02.04 03.02.05 03.02.06 03.02.07 3.03 03.03.01 3.04 03.04.01 03.04.02 3.05 03.05.01 03.05.02 03.05.03 03.05.04 3.06
TARRAJEO DE MUROS INTERIORES TARRAJEO DE COLUMNAS TARRAJEO DE VIGAS TARRAJEO DE MUROS EXTERIORES DERRAMES BRUÑAS CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO CERAMICO 45x45 CM. CEMENTO GRIS PLATA ZOCALOS ZOCALO CERAMICO DE 45 x 45 CM. CEMENTO BLANCO ZOCALO CERAMICO DE 15 x 45 CM. CEMENTO GRIS PLATA ZOCALO CERAMICO DE 30 x 30 CM. COLOR 1 ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 CONTRAZOCALOS
METRADO
C. Unit.
m2 m2 m2 m2 m m
59.40 5.88 71.20 60.18 99.66 144.00
S/. 21.76 S/. 27.98 S/. 33.82 S/. 27.64 S/. 17.94 S/. 3.26
m2
93.34
S/. 31.47
m2 m2
125.60 113.42
S/. 46.80 S/. 83.21
m2 m2 m2 m2
213.96 16.24 163.92 3.40
S/. 76.64 S/. 76.64 S/. 76.64 S/. 76.64
S/. 1,292.54 S/. 164.52 S/. 2,407.98 S/. 1,663.38 S/. 1,787.90 S/. 469.44 S/. 2,937.41 S/. 2,937.41 S/. 15,315.76 S/. 5,878.08 S/. 9,437.68 S/. 30,465.93 S/. 16,397.89 S/. 1,244.63 S/. 12,562.83 S/. 260.58 S/. 3,795.71
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
03.06.01 3.07 03.07.01 3.08 03.08.01 3.09 03.09.01 03.09.02 03.09.03 03.09.04 3.1 03.10.01 03.10.02 03.10.03 3.11 03.11.01 3.12
CONTRAZOCALO SANITARIO DE TERRAZO LAVADO m COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA m2 CARPINTERIA DE MADERA m2 PUERTA CONTRAPLACADA MDF CARPINTERIA METALICA VENTANAS DE SEGURIDAD TIPO REJAS m2 TABIQUE SEPARADOR METALICO COLOR GRIS CON PUERTA PARA CUBIL D m TABIQUE SEPARADOR METALICO COLOR GRIS PARA SEPARACION DE URINA m BARANDA DE TUBO DE ACERO INOXIDABLE DE 1 1/2", EN SS.HH. MINUS m CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS und PESTILLO PARA CUBILES DE INODOROS und VIDRIOS, CRISTALES Y SIMILARES ESPEJO BISELADO e= 6 mm m2 PINTURA
METRADO
C. Unit.
124.90
S/. 30.39
123.94
S/. 45.52
18.28 204.18 8.24 29.80 3.60 7.60
S/. 189.00 S/. 367.50 S/. 125.00 S/. 231.00
38.00 10.00 20.00
S/. 18.84 S/. 85.67 S/. 18.19
19.28
S/. 132.00
S/. 3,795.71 S/. 5,641.75 S/. 5,641.75 S/. 3,732.41 S/. 3,732.41 S/. 14,714.46 S/. 1,557.36 S/. 10,951.50 S/. 450.00 S/. 1,755.60 S/. 1,936.42 S/. 715.92 S/. 856.70 S/. 363.80 S/. 2,544.96 S/. 2,544.96 S/. 3,996.43
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
03.12.01 03.12.02 03.12.03 3.13 03.13.01 03.13.02 03.13.03 03.13.04 03.13.05 03.13.06 03.13.07 03.13.08 03.13.09 03.13.10 03.13.11 3.14 03.14.01
PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 APARATOS Y ACCESORIOS SANITARIOS TASA ELONGADA VITRIFICADA TIPO 1 C/FLUXOMETRO PARA DESCARGA INpza TASA ELONGADA VITRIFICADA TIPO 2 C/FLUXOMETRO PARA DESCARGA INpza LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL pza URINARIO CADET BLANCO C/FLUXOMETRO PARA DESCARGA INDIRECTA pza LAVADERO CORRIDO DE CONCRETO S/DISEÑO, ACABADO EN CEMENTO Pm SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza SUMINISTRO E INSTALACION DE LLAVE TEMPORIZADA CON AIREADOR pza SUMINISTRO E INSTALACION DE LLAVE DE GRIFO PARA LAVADERO PARA Cpza DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO und INSTALACION DE APARATOS SANITARIOS pza INSTALACION DE ACCESORIOS SANITARIOS und VARIOS SUMINISTRO DE PAPELERA METÁLICA und
METRADO
C. Unit.
80.22 60.18 164.54
S/. 14.79 S/. 16.59 S/. 11.01
20.00 4.00 4.00 8.00 16.82 20.00 4.00 2.00 24.00 36.00 24.00
S/. 689.60 S/. 674.60 S/. 240.00 S/. 490.00 S/. 196.93 S/. 175.00 S/. 195.00 S/. 35.00 S/. 75.00 S/. 108.11 S/. 32.43
24.00
S/. 35.00
S/. 1,186.45 S/. 998.39 S/. 1,811.59 S/. 35,503.04 S/. 13,792.00 S/. 2,698.40 S/. 960.00 S/. 3,920.00 S/. 3,312.36 S/. 3,500.00 S/. 780.00 S/. 70.00 S/. 1,800.00 S/. 3,891.96 S/. 778.32 S/. 840.00 S/. 840.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
4 4.01 04.01.01 4.02 04.02.01 04.02.02 04.02.03 04.02.04 04.02.05 04.02.06 4.03 04.03.01 4.04 04.04.01 04.04.02 4.05 04.05.01
SS.HH. NIÑOS Y NIÑAS MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO PRIMARIO RAYADO TARRAJEO DE MUROS INTERIORES TARRAJEO DE COLUMNAS TARRAJEO DE MUROS EXTERIORES DERRAMES BRUÑAS CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO CERAMICO 30x30 CM. COLOR 1 ZOCALOS ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 INTERIOR
METRADO
C. Unit.
m2
100.29
S/. 72.90
m2 m2 m2 m2 m m
161.83 54.16 1.92 34.85 30.10 65.70
S/. 20.63 S/. 21.76 S/. 27.98 S/. 27.64 S/. 17.94 S/. 3.26
m2
31.75
S/. 31.47
m2 m2
46.86 42.92
S/. 46.80 S/. 82.48
m2
77.13
S/. 76.64
S/. 54,428.91 S/. 7,311.14 S/. 7,311.14 S/. 6,288.23 S/. 3,338.55 S/. 1,178.52 S/. 53.72 S/. 963.25 S/. 539.99 S/. 214.18 S/. 999.17 S/. 999.17 S/. 5,733.09 S/. 2,193.05 S/. 3,540.04 S/. 11,864.64 S/. 5,911.24
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.05.02 04.05.03 4.06 04.06.01 4.07 04.07.01 4.08 04.08.01 4.09 04.09.01 04.09.02 04.09.03 04.09.04 4.1 04.10.01 04.10.02 04.10.03
ZOCALO CERAMICO DE 30 x 30 CM. COLOR 1 m2 ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 m2 CONTRAZOCALOS CONTRAZOCALO SANITARIO DE TERRAZO LAVADO m COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA m2 CARPINTERIA DE MADERA PUERTA CONTRAPLACADA MDF m2 CARPINTERIA METALICA REJA DE SEGURIDAD EN VENTANAS DE TEATINAS m2 VENTANAS DE SEGURIDAD TIPO REJAS m2 TABIQUE SEPARADOR METALICO COLOR GRIS CON PUERTA PARA CUBIL D m BARANDA DE TUBO DE ACERO INOXIDABLE DE 1 1/2", EN SS.HH. MINUS m CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS und PESTILLO PARA CUBILES DE INODOROS und
METRADO
C. Unit.
74.26 3.42
S/. 76.64 S/. 76.64
50.20
S/. 30.39
37.38
S/. 45.52
3.36
S/. 204.18
2.34 1.76 14.90 3.80
S/. 157.50 S/. 189.00 S/. 367.50 S/. 231.00
7.00 2.00 8.00
S/. 18.84 S/. 85.67 S/. 18.19
S/. 5,691.29 S/. 262.11 S/. 1,525.58 S/. 1,525.58 S/. 1,701.54 S/. 1,701.54 S/. 686.04 S/. 686.04 S/. 7,054.74 S/. 368.55 S/. 332.64 S/. 5,475.75 S/. 877.80 S/. 448.74 S/. 131.88 S/. 171.34 S/. 145.52
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
4.11 04.11.01 4.12 04.12.01 04.12.02 04.12.03 4.13 04.13.01 04.13.02 04.13.03 04.13.04 04.13.05 04.13.06 04.13.07 04.13.08 04.13.09 04.13.10
VIDRIOS, CRISTALES Y SIMILARES ESPEJO BISELADO e= 6 mm m2 PINTURA PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 APARATOS Y ACCESORIOS SANITARIOS INODORO BLANCO TANQUE BAJO PARA NIÑOS pza TASA ELONGADA VITRIFICADA TIPO 2 C/FLUXOMETRO PARA DESCARGA INpza LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL pza LAVADERO CORRIDO DE CONCRETO SS.HH. NIÑOS Y NIÑAS, ACABADO E m URINARIO CORRIDO DE CONCRETO SS.HH. NIÑOS ACABADO EN CEMENTOm SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza SUMINISTRO E INSTALACION DE LLAVE TEMPORIZADA CON AIREADOR pza SUMINISTRO E INSTALACION DE LLAVE DE GRIFO PARA LAVADERO PARA Cpza DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO und INSTALACION DE APARATOS SANITARIOS pza
METRADO
C. Unit.
0.83
S/. 132.00
60.61 34.85 31.75
S/. 14.79 S/. 16.59 S/. 11.01
8.00 1.00 1.00 5.62 3.65 6.00 1.00 1.00 9.00 10.00
S/. 224.60 S/. 674.60 S/. 240.00 S/. 234.39 S/. 306.90 S/. 175.00 S/. 195.00 S/. 35.00 S/. 75.00 S/. 108.11
S/. 109.56 S/. 109.56 S/. 1,824.15 S/. 896.42 S/. 578.16 S/. 349.57 S/. 8,476.83 S/. 1,796.80 S/. 674.60 S/. 240.00 S/. 1,317.27 S/. 1,120.19 S/. 1,050.00 S/. 195.00 S/. 35.00 S/. 675.00 S/. 1,081.10
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.13.11 4.14 04.14.01 04.14.02 5 5.01 05.01.01 5.02 05.02.01 05.02.02 05.02.03 05.02.04 05.02.05 05.02.06 05.02.07 5.03 05.03.01
INSTALACION DE ACCESORIOS SANITARIOS und VARIOS TABLERO DE CONCRETO EN SS.HH. PARA NIÑOS ACABADO EN CEMENTO Pm SUMINISTRO DE PAPELERA METÁLICA und TOPICO MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA m2 REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO PRIMARIO RAYADO m2 TARRAJEO DE MUROS INTERIORES m2 TARRAJEO DE MUROS EXTERIORES m2 TARRAJEO DE GRADAS m2 TARRAJEO CON IMPERMEABILIZANTE m2 DERRAMES m BRUÑAS m CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA m2
METRADO
C. Unit.
9.00
S/. 32.43
1.20 9.00
S/. 75.39 S/. 35.00
34.00
S/. 72.90
93.46 12.44 10.81 0.52 18.87 30.61 42.98
S/. 20.63 S/. 21.76 S/. 27.64 S/. 27.64 S/. 33.00 S/. 17.94 S/. 3.26
24.79
S/. 31.47
S/. 291.87 S/. 405.47 S/. 90.47 S/. 315.00 S/. 64,311.47 S/. 2,478.60 S/. 2,478.60 S/. 3,823.90 S/. 1,928.08 S/. 270.69 S/. 298.79 S/. 14.37 S/. 622.71 S/. 549.14 S/. 140.11 S/. 780.14 S/. 780.14
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
5.04 05.04.01 05.04.02 05.04.03 5.05 05.05.01 05.05.02 5.06 05.06.01 5.07 05.07.01 5.08 05.08.01 5.09 05.09.01 5.1 05.10.01
PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO CERAMICO 30x30 CM. COLOR 1 PISO DE TERRAZO LAVADO ZOCALOS ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 INTERIOR ZOCALO CERAMICO DE 30 x 30 CM. COLOR 2 CONTRAZOCALOS CONTRAZOCALO SANITARIO DE TERRAZO LAVADO COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA SARDINEL DE CONCRETO SARDINEL PERALTADO DE CONCRETO h= 0.60 M (PROMEDIO) CARPINTERIA DE MADERA PUERTA CONTRAPLACADA MDF CARPINTERIA METALICA VENTANAS DE SEGURIDAD TIPO REJAS
METRADO
C. Unit.
m2 m2 m2
66.82 25.34 42.00
S/. 46.80 S/. 82.48 S/. 129.25
m2 m2
29.77 50.86
S/. 76.64 S/. 76.64
m
22.73
S/. 30.39
m2
37.38
S/. 45.52
m
37.22
S/. 687.87
m2
3.98
S/. 204.18
m2
0.23
S/. 189.00
S/. 10,645.72 S/. 3,127.18 S/. 2,090.04 S/. 5,428.50 S/. 6,179.48 S/. 2,281.57 S/. 3,897.91 S/. 690.76 S/. 690.76 S/. 1,701.54 S/. 1,701.54 S/. 25,602.52 S/. 25,602.52 S/. 812.64 S/. 812.64 S/. 963.57 S/. 43.47
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.10.02 5.11 05.11.01 05.11.02 5.12 05.12.01 5.13 05.13.01 05.13.02 05.13.03 5.14 05.14.01 05.14.02 05.14.03 05.14.04 05.14.05 05.14.06
VENTANAS CON MARCO DE ALUMINIO Y VIDRIO DOBLE m2 CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS und VIDRIOS, CRISTALES Y SIMILARES ESPEJO BISELADO e= 6 mm m2 PINTURA PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 APARATOS Y ACCESORIOS SANITARIOS TASA ELONGADA VITRIFICADA TIPO 2 C/FLUXOMETRO PARA DESCARGA INpza LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL pza LAVADERO DE ACERO INOXIDABLE 1 POSA pza SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza SUMINISTRO E INSTALACION DE GRIFERIA CROMADA PARA DUCHA AGUApza DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO und
METRADO
C. Unit.
3.79
S/. 242.77
7.00 2.00
S/. 18.84 S/. 85.67
0.83
S/. 132.00
60.61 34.85 31.75
S/. 14.79 S/. 16.59 S/. 11.01
1.00 1.00 1.00 1.00 1.00 1.00
S/. 674.60 S/. 240.00 S/. 195.00 S/. 175.00 S/. 185.00 S/. 75.00
S/. 920.10 S/. 303.22 S/. 131.88 S/. 171.34 S/. 109.56 S/. 109.56 S/. 1,824.15 S/. 896.42 S/. 578.16 S/. 349.57 S/. 1,901.36 S/. 674.60 S/. 240.00 S/. 195.00 S/. 175.00 S/. 185.00 S/. 75.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.14.07 05.14.08 5.15 05.15.01 05.15.02 05.15.03 05.15.04 05.15.05 05.15.06 05.15.07 05.15.08 6 6.01 06.01.01 06.01.02 06.01.03 6.02
INSTALACION DE APARATOS SANITARIOS pza INSTALACION DE ACCESORIOS SANITARIOS und VARIOS SUMINISTRO DE PAPELERA METÁLICA und CAMILLA und MESA PARA LAVADERO EMPOTRADO ACABADO EN PORCELANATO m2 BIOMBO DE LONA - SEGÚN MODELO und ESCRITORIO - SEGÚN MODELO und SILLAS - SEGÚN MODELO und MUEBLE DE APOYO - SEGÚN MODELO und TRIPODE DE APOYO - SEGÚN MODELO und MIRADOR REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO DE BANCA Y SARDINEL DE CONCRETO ACABADO EN TERRAZO m2 LAVADO REVESTIMIENTO DE GRADAS Y ESCALERAS CON TERRAZO m2 m BRUÑAS PISOS Y PAVIMENTOS
METRADO
3.00 1.00
C. Unit.
S/. 108.11 S/. 32.43
1.00 S/. 35.00 1.00 1,850.00 0.40 S/. 198.27 1.00 S/. 850.00 1.00 1,250.00 5.00 S/. 54.00 1.00 1,600.00 1.00 S/. 560.00
31.38 S/. 106.75 19.50 S/. 106.75 73.07 S/. 3.26
S/. 324.33 S/. 32.43 S/. 6,494.31 S/. 35.00 S/. 1,850.00 S/. 79.31 S/. 850.00 S/. 1,250.00 S/. 270.00 S/. 1,600.00 S/. 560.00 S/. 18,218.33 S/. 5,669.65 S/. 3,349.82 S/. 2,081.63 S/. 238.21 S/. 9,008.48
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.02.01 06.02.02 6.03 06.03.01 06.03.02 7 7.01 07.01.01 07.01.02 07.01.03 7.02 07.02.01 07.02.02 07.02.03 07.02.04 07.02.05 07.02.06
CONTRAPISO e= 40 mm m2 PISO DE TERRAZO LAVADO m2 CARPINTERIA METALICA BARANDA DE Fe TUBULAR DE 2" ESCALERA h= 0.90 M. m PARANTES DE Fe. TUBULAR 2" ALREDEDOR DE BANCAS DE MIRADOR SEGm MALOCA REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO DE BASE DE BANCAS ACABADO CEMENTO PULIDO m2 TARRAJEO DE BASE DE BANCAS ACABADO TERRAZO LAVADO m2 TARRAJEO DE PEDESTAL DE COLUMNAS ACABADO TERRAZO LAVADO m2 CARPINTERIA DE MADERA COLUMNA DE 8" x8" x 2.40 M p2 VIGUETA DE MADERA RADIAL DE 1 1/2" x 6" p2 VIGA PERIMETRICA DE 4" x 10" p2 ANILLO CENTRAL DE 4" x 10" p2 CORREAS DE MADERA CIRCULAR DE 2" x 1 1/2" p2 SOPORTES DE MADERA PARA CUMBRERA DE 2" x 2" p2
METRADO
C. Unit.
51.17 S/. 46.80 51.17 S/. 129.25 12.40 S/. 115.50 24.80 S/. 85.00
0.64 2.40 2.40
S/. 33.82 S/. 53.49 S/. 53.49
341.33 531.30 382.22 60.44 494.80 8.00
S/. 44.40 S/. 44.40 S/. 44.40 S/. 44.40 S/. 44.40 S/. 44.40
S/. 2,394.76 S/. 6,613.72 S/. 3,540.20 S/. 1,432.20 S/. 2,108.00 S/. 93,552.44 S/. 278.40 S/. 21.64 S/. 128.38 S/. 128.38 S/. 82,991.59 S/. 15,155.05 S/. 23,589.72 S/. 16,970.57 S/. 2,683.54 S/. 21,969.12 S/. 355.20
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
07.02.07 07.02.08 7.03 07.03.01 07.03.02 8 8.01 08.01.01 8.02 08.02.01 08.02.02 08.02.03 08.02.04 08.02.05 08.02.06 8.03 08.03.01
VIGUETAS RADIALES EN CUMBRERA DE 2" x 4" CORRES DE MADERA EN PINACULO DE 2" x 1 1/2" COBERTURAS COBERTURA DE CELOSIA DE MADERA DE 1" x 1 1/2" COBERTURA DE PLANCHA DECORATIVA PLANA COLOR VERDE PIZARRA BOLETERIA MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO PRIMARIO RAYADO TARRAJEO DE MUROS INTERIORES SOLAQUEADO DE BASE PARA COLUMNAS DE PERGOLA TARRAJEO DE MUROS EXTERIORES DERRAMES BRUÑAS CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA
METRADO
C. Unit.
p2 p2
25.42 25.67
S/. 44.40 S/. 44.40
m2 m2
106.03 95.03
S/. 44.51 S/. 58.54
m2
54.85
S/. 72.90
m2 m2 m2 m2 m m
8.63 50.76 11.60 63.09 44.59 27.25
S/. 20.63 S/. 21.76 S/. 13.55 S/. 27.64 S/. 17.94 S/. 3.26
m2
18.90
S/. 31.47
S/. 1,128.65 S/. 1,139.75 S/. 10,282.45 S/. 4,719.40 S/. 5,563.06 S/. 72,135.78 S/. 3,998.57 S/. 3,998.57 S/. 4,072.34 S/. 178.04 S/. 1,104.54 S/. 157.18 S/. 1,743.81 S/. 799.94 S/. 88.84 S/. 594.78 S/. 594.78
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
8.04 08.04.01 08.04.02 08.04.03 8.05 08.05.01 8.06 08.06.01 08.06.02 8.07 08.07.01 8.08 08.08.01 08.08.02 08.08.03 8.09 08.09.01
PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO CERAMICO 30x30 CM. COLOR 1 PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. ZOCALOS ZOCALO CERAMICO DE 30 x 30 CM. COLOR 1 CONTRAZOCALOS CONTRAZOCALO SANITARIO DE TERRAZO LAVADO CONTRAZOCALO DE TERRAZO PULIDO H=0.15 M COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA CARPINTERIA DE MADERA PUERTA CONTRAPLACADA MDF ESTRUCTURA DE MADERA DE PERGOLA NUEVA CASILLERO DE MELAMINE DE 15 MM SEGÚN DISEÑO CARPINTERIA METALICA REJILLAS
METRADO
C. Unit.
m2 m2 m2
2.04 2.04 17.13
S/. 46.80 S/. 82.48 S/. 47.41
m2
8.15
S/. 76.64
m m
4.85 20.65
S/. 30.39 S/. 22.62
m2
24.31
S/. 45.52
m2 m2 m2
3.68 82.86 1.26
S/. 204.18 S/. 473.20 S/. 180.00
m2
1.25
S/. 466.53
S/. 1,075.86 S/. 95.47 S/. 168.26 S/. 812.13 S/. 624.62 S/. 624.62 S/. 614.49 S/. 147.39 S/. 467.10 S/. 1,106.59 S/. 1,106.59 S/. 40,187.53 S/. 751.38 S/. 39,209.35 S/. 226.80 S/. 10,448.71 S/. 583.16
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
08.09.02 08.09.03 08.09.04 8.10. 08.10.01 08.10.02 08.10.03 8.11 08.11.01 08.11.02 8.12 08.12.01 08.12.02 08.12.03 8.13 08.13.01 08.13.02
VENTANAS CON MARCO DE ALUMINIO Y VIDRIO DOBLE m2 BANDEJA MEDIA CAÑA DE ACERO INOXIDABLE EN VENTANILLA, SEGÚN Dund MOLINETES DE INGRESO Y SALIDA SEGÚN DISEÑO pza CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS und und CERRADURA PARA SS.HH. VIDRIOS, CRISTALES Y SIMILARES VIDRIO TEMPLADO DE 8 MM VENTANA ATENCION BOLETERIA m2 ESPEJO BISELADO e= 6 mm m2 PINTURA m2 PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 APARATOS Y ACCESORIOS SANITARIOS TASA ELONGADA VITRIFICADA TIPO 1 C/FLUXOMETRO PARA DESCARGA INpza LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL pza
METRADO
C. Unit.
1.25 8.00 4.00
S/. 242.77 S/. 350.00 S/. 1,690.52
7.00 1.00 1.00
S/. 18.84 S/. 85.67 S/. 45.67
1.17 0.83
S/. 399.84 S/. 132.00
57.45 63.09 18.90
S/. 14.79 S/. 16.59 S/. 11.01
1.00 1.00
S/. 689.60 S/. 240.00
S/. 303.46 S/. 2,800.00 S/. 6,762.08 S/. 263.22 S/. 131.88 S/. 85.67 S/. 45.67 S/. 577.37 S/. 467.81 S/. 109.56 S/. 2,104.44 S/. 849.69 S/. 1,046.66 S/. 208.09 S/. 1,428.25 S/. 689.60 S/. 240.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
08.13.03 08.13.04 08.13.05 08.13.06 8.14 08.14.01 08.14.02 08.14.03 9 9.01 09.01.01 9.02 09.02.01 09.02.02 09.02.03 09.02.04 09.02.05
SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO und INSTALACION DE APARATOS SANITARIOS pza INSTALACION DE ACCESORIOS SANITARIOS und VARIOS SUMINISTRO DE PAPELERA METÁLICA und TABLERO DE ATENCIÓN CON CAJONERAS SEGÚN DISEÑO m2 SILLA PARA PERSONAL DE ATENCIÓN - SEGÚN MODELO und DEPOSITO DE INSUMOS QUIMICOS MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA m2 REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO DE MUROS INTERIORES m2 TARRAJEO DE COLUMNAS m2 TARRAJEO DE VIGAS m2 TARRAJEO DE MUROS EXTERIORES m2 DERRAMES m
METRADO
C. Unit.
1.00 1.00 2.00 1.00
S/. 175.00 S/. 75.00 S/. 108.11 S/. 32.43
1.00 3.28 8.00
S/. 35.00 S/. 550.00 S/. 400.00
45.79
S/. 72.90
51.40 5.76 3.42 51.21 5.90
S/. 21.76 S/. 27.98 S/. 33.82 S/. 27.64 S/. 17.94
S/. 175.00 S/. 75.00 S/. 216.22 S/. 32.43 S/. 5,039.00 S/. 35.00 S/. 1,804.00 S/. 3,200.00 S/. 13,763.27 S/. 3,338.09 S/. 3,338.09 S/. 3,062.96 S/. 1,118.46 S/. 161.16 S/. 115.66 S/. 1,415.44 S/. 105.85
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
09.02.06 9.03 09.03.01 9.04 09.04.01 9.05 09.05.01 9.06 09.06.01 9.07 09.07.01 9.08 09.08.01 9.09 09.09.01 09.09.02 9.1
BRUÑAS CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA CARPINTERIA DE MADERA PUERTA CONTRAPLACADA MDF CARPINTERIA METALICA REJILLA DE MALLA METALICA ELECTROSOLDADA CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS PINTURA
METRADO
C. Unit.
m
44.90
S/. 3.26
m2
25.24
S/. 31.47
m2
26.54
S/. 47.41
m
44.90
S/. 15.27
m2
30.00
S/. 45.52
m2
3.57
S/. 204.18
m2
1.91
S/. 136.50
und und
8.00 1.00
S/. 18.84 S/. 85.67
S/. 146.37 S/. 794.30 S/. 794.30 S/. 1,258.26 S/. 1,258.26 S/. 685.62 S/. 685.62 S/. 1,365.60 S/. 1,365.60 S/. 728.92 S/. 728.92 S/. 260.72 S/. 260.72 S/. 236.39 S/. 150.72 S/. 85.67 S/. 2,032.41
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
09.10.01 09.10.02 09.10.03 10 10.01 10.01.01 10.02 10.02.01 10.02.02 10.02.03 10.03 10.03.01 10.04 10.04.01 10.04.02 10.04.03 10.04.04
PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS m2 PISCINA RECREATIVA REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO CON IMPERMEABILIZANTE m2 PISOS Y PAVIMENTOS PISO DE MAYOLICA PARA PISCINA m2 PISO DE TERRAZO LAVADO EN PISCINA m2 PISO DE TERRAZO LAVADO EN CIRCULACION m2 ZOCALOS ZOCALO DEMAYOLICA PARA PISCINA m2 VARIOS CANALETAS DE PVC m ESCALERA DE SEGURIDAD DE ACERO INOXIDABLE - SEGÚN DISEÑO und SOMBRILLAS HEXAGONALES DE 2.50 M Y BASE DE CONCRETO und GRADERIA DESMONTABLE DE ESTRUCTURA METALICA DE 6.00 LARGO, 4,0und
METRADO
C. Unit.
58.64 51.21 28.66
S/. 14.79 S/. 16.59 S/. 11.01
2,615.14
S/. 33.00
1,260.55 758.03 576.98
S/. 77.28 S/. 129.25 S/. 129.25
198.31
S/. 71.39
468.03 5.00 70.00 4.00
S/. 78.75 S/. 350.00 S/. 200.00 S/. 15,600.00
S/. 867.29 S/. 849.57 S/. 315.55 S/. 485,429.68 S/. 86,299.62 S/. 86,299.62 S/. 269,965.35 S/. 97,415.30 S/. 97,975.38 S/. 74,574.67 S/. 14,157.35 S/. 14,157.35 S/. 115,007.36 S/. 36,857.36 S/. 1,750.00 S/. 14,000.00 S/. 62,400.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
11.00. 11.01 11.02 11.02.01 11.03 11.03.01 11.04 11.04.01 11.04.02 11.05 11.05.01 11.06 11.06.01 11.07 11.07.01 11.08 11.08.01
DUCHAS OBLIGATORIAS TORRES DE SALVATAJE SEGUN DISEÑO MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO KK ASENTADO DE SOGA REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO CON IMPERMEABILIZANTE PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO DE TERRAZO LAVADO ZOCALOS ZOCALO CERAMICO DE 20 x 30 CM. CONTRAZOCALOS CONTRAZOCALO SANITARIO DE TERRAZO LAVADO PINTURA PINTADO CON PINTURA EPOXICA APARATOS Y ACCESORIOS SANITARIOS SUMINISTRO E INSTALACION DE CABEZAL DE DUCHAS LATERALES
METRADO
C. Unit.
und
10.00
S/. 650.00
m2
39.74
S/. 72.90
m2
392.15
S/. 33.00
m2 m2
77.64 77.64
S/. 46.80 S/. 129.25
m2
392.15
S/. 62.99
m
64.40
S/. 30.39
m2
30.40
S/. 25.80
pza
56.00
S/. 75.00
S/. 87,732.44 S/. 6,500.00 S/. 2,897.05 S/. 2,897.05 S/. 12,940.95 S/. 12,940.95 S/. 13,668.52 S/. 3,633.55 S/. 10,034.97 S/. 24,701.53 S/. 24,701.53 S/. 1,957.12 S/. 1,957.12 S/. 784.32 S/. 784.32 S/. 16,860.93 S/. 4,200.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
11.08.02 11.08.03 11.08.04 11.09 11.09.01 12 12.01 12.01.01 12.01.02 12.01.03 12.01.04 12.01.05 12.01.06 12.01.07 12.02 12.02.01 12.03
SUMINSTRO E INSTALACION DE CABEZAL DE DUCHAS ESPAÑOLAS DE 4" pza LAVADERO CORRIDO DE CONCRETO ENCHAPADO EN CERAMICO DE 20x30m2 CM SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA pza VARIOS MURO CORTINA DE TUBO AL 4"x2" PESADO , "U" DE AL DE 1/2" x 1/2" m2 CUARTO DE MAQUINAS II Y CISTERNA DE COMPENSACION REVOQUES, ENLUCIDOS Y MOLDURAS m2 TARRAJEO DE MUROS INTERIORES m2 TARRAJEO DE VIGAS m2 TARRAJEO DE MUROS EXTERIORES m2 TARRAJEO CON IMPERMEABILIZANTE FORJADO DE GRADAS DE ESCALERAS, ACABADO EN CEMENTO FROTACHAm2 m DERRAMES m BRUÑAS CIELORRASOS m2 ENLUCIDO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS
METRADO
C. Unit.
34.00 10.30 10.00
S/. 220.00 S/. 333.10 S/. 175.00
42.84
S/. 173.25
59.53 3.90 70.06 316.80 25.00 9.40 43.30
S/. 21.76 S/. 33.82 S/. 27.64 S/. 33.00 S/. 40.48 S/. 17.94 S/. 3.26
81.75
S/. 31.47
S/. 7,480.00 S/. 3,430.93 S/. 1,750.00 S/. 7,422.03 S/. 7,422.03 S/. 66,619.66 S/. 15,139.92 S/. 1,295.37 S/. 131.90 S/. 1,936.46 S/. 10,454.40 S/. 1,012.00 S/. 168.64 S/. 141.16 S/. 2,572.67 S/. 2,572.67 S/. 32,644.97
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
12.03.01 12.03.02 12.03.03 12.04 12.04.01 12.05 12.05.01 12.06 12.06.01 12.06.02 12.06.03 12.07 12.07.01 12.07.02 12.08 12.08.01 12.08.02
m2 CONTRAPISO e= 40 mm m2 PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. m2 PISO DE GRASS SINTETICO EN TERRAZA CONTRAZOCALOS m CONTRAZOCALOS DE CEMENTO PULIDO CARPINTERIA DE MADERA m2 PUERTA CONTRAPLACADA MDF - PLASTIFICADA CARPINTERIA METALICA m2 REJILLA DE MALLA METALICA ELECTROSOLDADA m2 REJA DE MALLA ELECTRIOSOLDADA PINTA AL ESMALTE, CON CUATRO BARNADA DE Fe DE 2" CON PARANTES DE TUBO DE Fe DE 1 1/2", MASILL m CERRAJERIA und BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" und CERRADURA PARA PUERTAS PINTURA m2 PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS m2 PINTADO DE MUROS EXTERIORES CON LATEX LAVABLE 2 MANOS
METRADO
C. Unit.
197.00 85.60 197.00
S/. 46.80 S/. 47.41 S/. 98.31
43.30
S/. 15.27
6.00
S/. 215.07
0.54 3.00 71.65
S/. 136.50 S/. 273.00 S/. 136.71
8.00 1.00
S/. 18.84 S/. 85.67
86.60 70.06
S/. 14.79 S/. 16.59
S/. 9,219.60 S/. 4,058.30 S/. 19,367.07 S/. 661.19 S/. 661.19 S/. 1,290.42 S/. 1,290.42 S/. 10,687.98 S/. 73.71 S/. 819.00 S/. 9,795.27 S/. 236.39 S/. 150.72 S/. 85.67 S/. 3,386.12 S/. 1,280.81 S/. 1,162.30
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
12.08.03 13 13.01 13.01.01 13.02 13.02.01 13.02.02 13.02.03 13.03 13.03.01 13.03.02 13.03.03 14 14.01 14.01.01 14.02 14.02.01
PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS REMODELACION DE PISCINAS EXISTENTES REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO CON IMPERMEABILIZANTE PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO DE MAYOLICA PARA PISCINA PISO DE TERRAZO LAVADO EN CIRCULACION ZOCALOS ZOCALO DE MAYOLICA PARA PISCINA CANALETAS DE PVC ESCALERA DE SEGURIDAD DE ACERO INOXIDABLE - SEGÚN DISEÑO CERCO Y AREA DE CIRCULACION REVOQUES, ENLUCIDOS Y MOLDURAS SOLAQUEADO DE BASES POSTES DE CERCO PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm
m2
METRADO
C. Unit.
85.65 11.01
m2
609.52
S/. 33.00
m2 m2 m2
86.93 460.93 86.93
S/. 46.80 S/. 77.28 S/. 129.25
m2 m und
148.59 141.90 2.00
S/. 71.39 S/. 78.75 S/. 350.00
m2
56.52
S/. 10.95
m2
4,956.15
S/. 46.80
S/. 943.01 S/93,521.32 S/. 20,114.16 S/. 20,114.16 S/. 50,924.70 S/. 4,068.32 S/. 35,620.67 S/. 11,235.70 S/. 22,482.47 S/. 10,607.84 S/. 11,174.63 S/. 700.00 S/1,316,560.78 S/. 618.89 S/. 618.89 S/. 872,530.21 S/. 231,947.82
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/13,373.40 S/. 0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
14.02.02 14.03 14.03.01 14.03.02 14.03.03 14.03.04 14.04 14.04.01 14.04.02 14.04.03 14.04.04 14.04.05 15 15.01 15.01.01 15.02 15.02.01
PISO DE TERRAZO LAVADO CARPINTERIA METALICA CERCO METALICO DE MALLA TIPO PRODAC h=3.00 M. PUERTA REJA DE UNA HOJA BATIENTE PUERTA DE DOBLE HOJA BATIENTE MOLINETES DE INGRESO Y SALIDA SEGÚN DISEÑO VARIOS TRASLADO DE ARBOLES DIFERENTES ALTURAS POLTRONES TACHOS DE BASURA SEÑALETICA MESA BAJA SUBESTACION ELECTRICA REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO DE MUROS INTERIORES CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA
m2
METRADO
4,956.15
C. Unit.
S/. 129.25
m m2 m2 pza
378.70 S/. 789.84 6.00 S/. 671.63 27.00 S/. 671.63 4.00 1,690.52
und und und und und
5.00 2,674.68 100.00 S/. 350.00 30.00 S/. 900.00 20.00 1,600.00 100.00 S/. 80.00
m2
119.72
S/. 21.76
m2
34.27
S/. 31.47
S/. 640,582.39 S/. 328,038.28 S/. 299,112.41 S/. 4,029.78 S/. 18,134.01 S/. 6,762.08 S/. 115,373.40 S/. 13,373.40 S/. 35,000.00 S/. 27,000.00 S/. 32,000.00 S/. 8,000.00 S/. 12,040.14 S/. 2,605.11 S/. 2,605.11 S/. 1,078.48 S/. 1,078.48
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 13,373.40 S/13,373.40 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
15.03 15.03.01 15.04 15.04.01 15.05 15.05.01 15.05.02 16 16.01 16.01.01 16.02 16.02.01 16.02.02 16.02.03
PISOS Y PAVIMENTOS PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. CARPINTERIA METALICA REJILLA METALICA C/PLATINA DE 1 1/4" x 3/16" PINTURA PINTADO DE MUROS INTERIORES CON LATEX LAVABLE 2 MANOS PINTADO DE CIELORRASO CON PINTURA TEMPLE 2 MANOS AREAS VERDES TRABAJOS PRELIMINARES TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA AREAS VERDES PREPARACION DE TERRENO PARA SEMBRIO DE GRASS SUMINISTRO E INSTALACION DE CHAMPA DE GRASS SUMINISTRO E INSTALACION DE PALMERAS H= 1.5M
METRADO
C. Unit.
m2
41.25
S/. 47.41
m2
6.64
S/. 640.50
m2 m2
119.72 34.27
S/. 14.79 S/. 11.01
m2
5,090.97
S/. 1.91
m2 m2 und
5,090.97 5,090.97 30.00
S/. 15.38 S/. 11.03 S/. 173.27
Costo Directo Gastos Generales Utilidad
8.00% 7.00%
S/. 1,955.66 S/. 1,955.66 S/. 4,252.92 S/. 4,252.92 S/. 2,147.97 S/. 1,770.66 S/. 377.31 S/. 149,374.37 S/. 9,723.75 S/. 9,723.75 S/. 139,650.62 S/. 78,299.12 S/. 56,153.40 S/. 5,198.10 3,436,119.10 274,889.53 240,528.34
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 0.00 0.00 0.00
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 51,629.83 4,130.39 3,614.09
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
0.971 18.00%
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
3,951,536.97 3,836,942.25 690,649.61 4,527,591.86
0.00 0.00 0.00 0.00
59,374.31 57,652.45 10,377.44 68,029.89
PORCENTAJE DE AVANCE ( % )
0.00%
1.50%
PORCENTAJE ACUMULADO DE AVANCE ( % )
0.00%
1.50%
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
19 dias
12 dias
30 dias
8 dias
31 dias
S/. 63,056.97 S/. 22,230.09 S/19,376.09 S/2,854.00 S/. 35,176.76 S/15,953.76 S/6,027.91 S/4,644.23 S/2,174.76 S/4,553.41 S/684.59 S/1,138.10 S/. 5,650.12 S/5,650.12 S/. 0.00 S/0.00 S/0.00
28 dias
S/. 33,215.11 S/. 0.00 S/0.00 S/0.00 S/. 5,935.37 S/2,791.91 S/1,808.37 S/812.74 S/380.58 S/0.00 S/53.25 S/88.52 S/. 3,955.09 S/3,955.09 S/. 3,302.06 S/1,640.34 S/0.00
MARZO
S/. 4,241.00 S/. 2,323.46 S/0.00 S/2,323.45 S/. 1,150.74 S/541.29 S/350.61 S/157.57 S/73.79 S/0.00 S/10.32 S/17.16 S/. 766.80 S/766.80 S/. 0.00
ABRIL
MAYO
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
S/. 13,755.34 S/. 2,812.60 S/0.00 S/2,812.60 S/. 1,393.00 S/655.24 S/424.42 S/190.75 S/89.32 S/0.00 S/12.49 S/20.77 S/. 928.23 S/928.23 S/. 5,288.67 S/4,342.36 S/174.34
30 dias
31 dias
31 dias
S/. 10,890.61 S/. 0.00
S/. 144,456.62 S/. 0.00
S/. 97,738.05 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 6,829.73 S/5,663.95 S/174.34
S/. 22,068.48
S/. 0.00
S/17,085.48
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/1,661.72 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 17,596.21 S/17,596.21 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
31 dias
23 dias
S/50.85 S/721.12 S/. 701.24 S/410.59 S/34.37 S/240.34 S/15.94 S/. 74.52 S/67.44 S/7.09 S/. 0.00 S/0.00 S/. 0.00
30 dias
S/50.85 S/940.60 S/. 701.24 S/410.59 S/34.37 S/240.34 S/15.94 S/. 74.52 S/67.44 S/7.09 S/. 0.00 S/0.00 S/. 0.00
S/4,983.00 S/. 68,721.59 S/40,237.93 S/3,367.81 S/23,553.62 S/1,562.23 S/. 7,303.03 S/6,608.67 S/694.36 S/. 0.00 S/0.00 S/. 17,251.08 S/728.92 S/913.40 S/992.75 S/14,616.00
S/. 0.00
S/. 0.00
S/. 0.00 S/0.00 S/. 17,251.08 S/728.92 S/913.40 S/992.75 S/14,616.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 164.93 S/89.22 S/27.33 S/48.38 S/. 0.00
S/. 164.93 S/89.22 S/27.33 S/48.38 S/. 0.00
31 dias
S/. 10,690.86 S/4,309.20 S/4,042.50 S/438.90 S/1,900.26 S/. 1,103.34 S/584.04 S/428.35 S/90.95 S/. 1,155.00 S/1,155.00 S/. 16,163.25 S/8,743.19 S/2,678.38 S/4,741.69 S/. 0.00
31 dias
S/. 10,690.86 S/4,309.20 S/4,042.50 S/438.90 S/1,900.26 S/. 1,103.34 S/584.04 S/428.35 S/90.95 S/. 1,155.00 S/1,155.00 S/. 0.00
S/. 21,566.60 S/6,287.53
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 32,632.28 S/. 5,072.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 2,426.38 S/2,207.20 S/219.18 S/0.00 S/0.00 S/. 26,903.01 S/. 7,290.00
MARZO
S/. 0.00
S/. 8,800.89 S/. 2,814.97
ABRIL
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
S/. 0.00
S/. 0.00 S/. 0.00
S/. 2,392.14 S/2,179.09 S/213.05
S/. 18,727.88 S/. 3,407.60
S/. 3,120.19 S/2,842.29 S/277.89
S/. 129,416.28 S/. 4,444.69
31 dias
S/. 0.00
S/1,230.15 S/437.65 S/2,585.58 S/1,914.71 S/355.59 S/127.65 S/6,072.35 S/820.59 S/1,379.99 S/354.82 S/. 45,971.18
S/. 0.00 S/. 0.00
S/382.94 S/45,588.24 S/. 115,133.81 S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/3,645.00 S/1,427.00 S/. 21,430.43 S/8,800.55 S/4,843.25 S/518.75 S/1,350.23 S/2,392.66 S/2,865.39 S/0.00 S/68.17 S/591.43 S/. 6,129.85 S/6,129.85 S/. 0.00 S/0.00 S/0.00
S/7,290.00 S/0.00 S/. 2,865.39 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/2,865.39 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 6,637.69 S/4,851.76 S/0.00
MARZO
S/1,654.23 S/1,160.74 S/. 4,436.23 S/2,322.37 S/852.05 S/91.26 S/237.54 S/631.39 S/0.00 S/127.55 S/17.99 S/156.07 S/. 1,078.40 S/1,078.40 S/. 471.29
ABRIL
S/. 0.00
S/. 0.00
MAYO
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
30 dias
31 dias
31 dias
23 dias
S/2,002.49 S/1,405.10 S/. 5,370.17 S/2,811.29 S/1,031.43 S/110.47 S/287.55 S/764.32 S/0.00 S/154.40 S/21.78 S/188.93 S/. 1,305.43 S/1,305.43 S/. 3,232.46 S/2,661.96
S/2,611.95 S/1,832.74 S/. 7,004.57 S/3,666.90 S/1,345.35 S/144.10 S/375.06 S/996.94 S/201.39 S/28.41 S/246.43 S/. 1,702.74 S/1,702.74 S/. 25,560.19 S/3,472.12 S/16,259.23
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/1,785.93 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 7,902.73 S/7,902.73 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/471.29 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/570.51 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 3,429.48 S/3,429.48 S/. 0.00
S/5,084.70 S/744.14 S/. 64,048.05 S/37,190.33 S/3,258.73 S/22,127.50 S/1,471.49 S/. 6,468.69 S/5,876.21 S/592.48 S/. 4,473.24 S/4,473.24 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 24,566.55 S/1,665.61 S/1,810.32 S/20,678.82 S/411.80
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 13,127.95 S/5,948.83 S/2,872.23 S/4,306.89 S/. 0.00
S/. 18,820.14 S/7,438.63 S/7,371.62 S/410.29 S/3,465.18 S/134.41 S/. 1,174.80 S/618.40 S/390.55 S/165.85 S/. 1,032.63 S/1,032.63 S/. 0.00
S/. 0.00
S/. 23,632.34
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 14,763.71 S/. 14,763.71 S/14,763.71 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 2,207.20 S/2,207.20 S/0.00 S/0.00 S/. 6,245.99 S/. 0.00 S/0.00 S/. 4,777.29 S/4,777.29
MARZO
S/. 0.00
S/. 2,825.57 S/. 0.00 S/0.00 S/. 2,161.15 S/2,161.15
ABRIL
S/. 0.00
S/. 0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 1,982.73 S/1,982.73
S/. 3,420.43 S/. 0.00 S/0.00 S/. 2,616.13 S/2,616.13
31 dias
S/. 0.00
S/6,287.53 S/4,467.65 S/1,939.18 S/1,914.71 S/6,072.35 S/683.82 S/1,971.42 S/295.69 S/. 45,907.35
S/. 67,001.34 S/. 0.00
S/. 17,332.84 S/. 0.00
S/319.12 S/45,588.24 S/. 38,238.01 S/. 0.00
S/. 7,785.77
S/. 0.00
S/. 0.00
S/. 2,586.17 S/2,586.17
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 1,468.70 S/1,468.70 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 664.42 S/664.42 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 804.29 S/804.29 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/1,292.54 S/164.52 S/2,407.98 S/1,663.38 S/1,787.90 S/469.44 S/. 0.00 S/. 15,315.76 S/5,878.08 S/9,437.68 S/. 30,465.93 S/16,397.89 S/1,244.63 S/12,562.83 S/260.58 S/. 3,795.71
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/3,795.71 S/. 5,641.75 S/5,641.75 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 3,996.43
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 3,403.08 S/3,403.08 S/. 13,416.13 S/1,419.95 S/9,985.19 S/410.29 S/1,600.69 S/. 1,765.56 S/652.75 S/781.11 S/331.70 S/. 2,320.40 S/2,320.40 S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/1,186.45 S/998.39 S/1,811.59 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 16,932.22 S/6,577.72 S/1,286.93 S/457.85 S/1,869.54 S/1,579.74 S/1,669.23 S/372.00 S/33.38 S/858.46 S/1,856.17 S/371.20 S/. 400.62 S/400.62
S/. 16,932.22 S/6,577.72 S/1,286.93 S/457.85 S/1,869.54 S/1,579.74 S/1,669.23 S/372.00 S/33.38 S/858.46 S/1,856.17 S/371.20 S/. 400.62 S/400.62
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 3,645.00 S/. 3,645.00 S/3,645.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/. 3,666.14 S/. 3,666.14 S/3,666.14 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
8 dias
23 dias
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
30 dias
S/. 28,112.24 S/. 0.00 S/0.00 S/. 6,288.23 S/3,338.55 S/1,178.52 S/53.72 S/963.25 S/539.99 S/214.18 S/. 999.17 S/999.17 S/. 5,733.09 S/2,193.05 S/3,540.04 S/. 11,864.64 S/5,911.24
31 dias
31 dias
S/. 9,064.18 S/. 0.00
S/. 9,064.18 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/5,691.29 S/262.11 S/. 1,525.58 S/1,525.58 S/. 1,701.54 S/1,701.54 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 327.19 S/327.19 S/. 3,364.57 S/175.77 S/158.64 S/2,611.51 S/418.64 S/. 214.01 S/62.90 S/81.72 S/69.40
S/. 327.19 S/327.19 S/. 3,364.57 S/175.77 S/158.64 S/2,611.51 S/418.64 S/. 214.01 S/62.90 S/81.72 S/69.40
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 52.25 S/52.25 S/. 869.98 S/427.52 S/275.74 S/166.72 S/. 4,042.79 S/856.94 S/321.73 S/114.46 S/628.24 S/534.24 S/500.77 S/93.00 S/16.69 S/321.92 S/515.60
S/. 52.25 S/52.25 S/. 869.98 S/427.52 S/275.74 S/166.72 S/. 4,042.79 S/856.94 S/321.73 S/114.46 S/628.24 S/534.24 S/500.77 S/93.00 S/16.69 S/321.92 S/515.60
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 23,821.55 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 2,478.60 S/. 2,478.60 S/2,478.60 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 3,823.90 S/1,928.08 S/270.69 S/298.79 S/14.37 S/622.71 S/549.14 S/140.11 S/. 780.14 S/780.14
31 dias
31 dias
S/139.20 S/. 193.38 S/43.15 S/150.23 S/. 18,128.48 S/. 0.00
S/139.20 S/. 193.38 S/43.15 S/150.23 S/. 18,128.48 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 10,645.72 S/3,127.18 S/2,090.04 S/5,428.50 S/. 6,179.48 S/2,281.57 S/3,897.91 S/. 690.76 S/690.76 S/. 1,701.54 S/1,701.54 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 12,210.43 S/12,210.43 S/. 387.57 S/387.57 S/. 459.55 S/20.73
S/. 12,210.43 S/12,210.43 S/. 387.57 S/387.57 S/. 459.55 S/20.73
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
31 dias
S/438.82 S/. 144.61 S/62.90 S/81.72 S/. 52.25 S/52.25 S/. 869.98 S/427.52 S/275.74 S/166.72 S/. 906.80 S/321.73 S/114.46 S/93.00 S/83.46 S/88.23 S/35.77
31 dias
S/438.82 S/. 144.61 S/62.90 S/81.72 S/. 52.25 S/52.25 S/. 869.98 S/427.52 S/275.74 S/166.72 S/. 906.80 S/321.73 S/114.46 S/93.00 S/83.46 S/88.23 S/35.77
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 1,821.83 S/. 566.96 S/334.98 S/208.16 S/23.82 S/. 900.85
S/. 16,396.49 S/. 5,102.68 S/3,014.83 S/1,873.46 S/214.39 S/. 8,107.63
31 dias
31 dias
S/154.68 S/15.47 S/. 3,097.29 S/16.69 S/882.31 S/37.82 S/405.38 S/596.15 S/128.77 S/763.08 S/267.08 S/. 0.00 S/. 0.00
S/154.68 S/15.47 S/. 3,097.29 S/16.69 S/882.31 S/37.82 S/405.38 S/596.15 S/128.77 S/763.08 S/267.08 S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
30 dias
31 dias
31 dias
23 dias
S/239.48 S/661.37 S/. 354.02 S/143.22 S/210.80 S/. 15.00 S/. 15.00 S/2.16 S/12.84
S/2,155.28 S/5,952.35 S/. 3,186.18 S/1,288.98 S/1,897.20 S/. 135.02 S/. 135.02 S/19.48 S/115.54
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 44,545.77 S/. 61.23
S/. 44,545.77 S/. 61.23
S/61.23 S/. 39,580.61 S/7,227.79 S/11,250.48 S/8,093.66 S/1,279.84 S/10,477.58 S/169.40
S/61.23 S/. 39,580.61 S/7,227.79 S/11,250.48 S/8,093.66 S/1,279.84 S/10,477.58 S/169.40
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 1,208.73 S/. 399.86 S/399.86 S/. 407.23 S/17.80 S/110.45 S/15.72 S/174.38 S/79.99 S/8.88 S/. 59.48 S/59.48
S/. 10,878.53 S/. 3,598.71 S/3,598.71 S/. 3,665.11 S/160.23 S/994.08 S/141.46 S/1,569.43 S/719.95 S/79.95 S/. 535.30 S/535.30
31 dias
31 dias
S/538.28 S/543.57 S/. 4,903.94 S/2,250.79 S/2,653.15 S/. 28,638.52 S/. 0.00
S/538.28 S/543.57 S/. 4,903.94 S/2,250.79 S/2,653.15 S/. 28,638.52 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 107.59 S/9.55 S/16.83 S/81.21 S/. 62.46 S/62.46 S/. 61.45 S/14.74 S/46.71 S/. 110.66 S/110.66 S/. 0.00
S/. 968.28 S/85.92 S/151.43 S/730.92 S/. 562.15 S/562.15 S/. 553.05 S/132.65 S/420.39 S/. 995.93 S/995.93 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 19,166.36 S/358.35 S/18,699.84 S/108.17 S/. 4,983.23 S/278.12
S/. 19,166.36 S/358.35 S/18,699.84 S/108.17 S/. 4,983.23 S/278.12
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
31 dias
S/144.73 S/1,335.38 S/3,224.99 S/. 125.54 S/62.90 S/40.86 S/21.78 S/. 275.36 S/223.11 S/52.25 S/. 1,003.65 S/405.23 S/499.18 S/99.24 S/. 681.17 S/328.89 S/114.46
31 dias
S/144.73 S/1,335.38 S/3,224.99 S/. 125.54 S/62.90 S/40.86 S/21.78 S/. 275.36 S/223.11 S/52.25 S/. 1,003.65 S/405.23 S/499.18 S/99.24 S/. 681.17 S/328.89 S/114.46
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 3,966.08 S/. 1,448.61 S/1,448.61 S/. 1,329.21 S/485.37 S/69.94 S/50.19 S/614.25 S/45.93
S/. 5,173.15 S/. 1,889.49 S/1,889.49 S/. 1,733.75 S/633.09 S/91.23 S/65.47 S/801.19 S/59.91
31 dias
31 dias
S/83.46 S/35.77 S/103.12 S/15.47 S/. 2,403.22 S/16.69 S/860.37 S/1,526.15 S/. 2,658.69 S/. 0.00
S/83.46 S/35.77 S/103.12 S/15.47 S/. 2,403.22 S/16.69 S/860.37 S/1,526.15 S/. 1,642.49 S/. 0.00
S/. 0.00
S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00
S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
30 dias
31 dias
31 dias
23 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/63.52 S/. 344.70 S/344.70 S/. 546.04 S/546.04 S/. 297.53 S/297.53 S/. 0.00
S/82.85 S/. 449.61 S/449.61 S/. 712.22 S/712.22 S/. 388.09 S/388.09 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 651.29 S/651.29 S/. 347.64 S/347.64 S/. 124.34 S/124.34 S/. 112.74 S/71.88 S/40.86 S/. 1,422.68
S/. 651.29 S/651.29 S/. 347.64 S/347.64 S/. 124.34 S/124.34 S/. 112.74 S/71.88 S/40.86 S/. 406.48
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
31 dias
S/607.10 S/594.70 S/220.88 S/. 339,800.78 S/. 60,409.73 S/60,409.73 S/. 188,975.74 S/68,190.71 S/68,582.76 S/52,202.27 S/. 9,910.15 S/9,910.15 S/. 80,505.15 S/25,800.15 S/1,225.00 S/9,800.00 S/43,680.00
31 dias
S/173.46 S/169.91 S/63.11 S/. 97,085.94 S/. 17,259.92 S/17,259.92 S/. 53,993.07 S/19,483.06 S/19,595.08 S/14,914.93 S/. 2,831.47 S/2,831.47 S/. 23,001.47 S/7,371.47 S/350.00 S/2,800.00 S/12,480.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
S/. 28,348.53 S/2,940.48 S/. 1,310.57 S/1,310.57 S/. 5,854.24 S/5,854.24 S/. 6,183.38 S/1,643.75 S/4,539.63 S/. 11,174.50 S/11,174.50 S/. 885.36 S/885.36 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
30 dias
S/. 34,657.00 S/3,559.52 S/. 1,586.48 S/1,586.48 S/. 7,086.71 S/7,086.71 S/. 7,485.14 S/1,989.80 S/5,495.34 S/. 13,527.03 S/13,527.03 S/. 1,071.75 S/1,071.75 S/. 340.37 S/340.37 S/. 0.00
31 dias
31 dias
S/. 443.95
S/. 11,581.10
S/. 11,581.10
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 443.95 S/443.95 S/. 0.00
S/. 0.00
S/. 0.00
S/. 8,041.37 S/2,003.08
S/. 8,041.37 S/2,003.08
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
31 dias
S/3,567.38 S/1,636.29 S/834.62 S/. 3,539.74 S/3,539.74 S/. 31,772.45 S/. 7,220.58 S/617.79 S/62.91 S/923.54 S/4,985.94 S/482.65 S/80.43 S/67.32 S/. 1,226.97 S/1,226.97 S/. 15,569.14
31 dias
S/3,567.38 S/1,636.29 S/834.62 S/. 3,539.74 S/3,539.74 S/. 31,772.45 S/. 7,220.58 S/617.79 S/62.91 S/923.54 S/4,985.94 S/482.65 S/80.43 S/67.32 S/. 1,226.97 S/1,226.97 S/. 15,569.14
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
31 dias
S/4,397.04 S/1,935.50 S/9,236.60 S/. 315.34 S/315.34 S/. 615.43 S/615.43 S/. 5,097.35 S/35.15 S/390.60 S/4,671.59 S/. 112.74 S/71.88 S/40.86 S/. 1,614.92 S/610.85 S/554.33
31 dias
S/4,397.04 S/1,935.50 S/9,236.60 S/. 315.34 S/315.34 S/. 615.43 S/615.43 S/. 5,097.35 S/35.15 S/390.60 S/4,671.59 S/. 112.74 S/71.88 S/40.86 S/. 1,614.92 S/610.85 S/554.33
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/201.81 S/. 201.81 S/201.81 S/. 0.00
31 dias
S/449.74 S/44,602.48 S/. 9,592.91 S/9,592.91 S/. 24,287.16 S/1,940.28 S/16,988.32 S/5,358.57 S/. 10,722.41 S/5,059.12 S/5,329.44 S/333.85 S/511,035.93 S/. 208.54 S/208.54 S/. 349,012.08 S/92,779.13
31 dias
S/449.74 S/44,602.48 S/. 9,592.91 S/9,592.91 S/. 24,287.16 S/1,940.28 S/16,988.32 S/5,358.57 S/. 10,722.41 S/5,059.12 S/5,329.44 S/333.85 S/661,692.78 S/. 208.54 S/208.54 S/. 436,265.10 S/115,973.91
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 849.49 S/. 849.49 S/849.49 S/. 0.00
31 dias
31 dias
S/256,232.96 S/. 131,215.31 S/119,644.96 S/1,611.91 S/7,253.60 S/2,704.83 S/. 30,600.00
S/320,291.19 S/. 164,019.14 S/149,556.20 S/2,014.89 S/9,067.01 S/3,381.04 S/. 61,200.00
S/10,500.00 S/8,100.00 S/9,600.00 S/2,400.00 S/. 10,312.84 S/. 877.81 S/877.81 S/. 1,078.48 S/1,078.48
S/21,000.00 S/16,200.00 S/19,200.00 S/4,800.00 S/. 877.81 S/. 877.81 S/877.81 S/. 0.00
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 114,097.93 9,127.83 7,986.86
S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 S/. 0.00 S/0.00 S/. 0.00 S/0.00 S/0.00 S/. 0.00 70,030.22 5,602.42 4,902.12
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 1,955.66 S/1,955.66 S/. 4,252.92 S/4,252.92 S/. 2,147.97 S/1,770.66 S/377.31 S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
44,215.95 3,537.28 3,095.12
0.00
0.00
0.00
80,050.89 6,404.07 5,603.56
293,320.48 23,465.64 20,532.43
1,213,930.68 97,114.45 84,975.15
S/. 0.00 S/. 0.00 S/. 0.00
S/. 90,961.38 S/. 8,865.77 S/8,865.77 S/. 82,095.61 S/39,149.56 S/39,307.38 S/3,638.67 1,291,703.25 103,336.26 90,419.23
ADO DE AVANCE DE OBRA- ZONA RECREATIVA ARQUITECTURA
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
131,212.62 127,407.45 22,933.34 150,340.79
80,534.76 78,199.25 14,075.87 92,275.12
MARZO
50,848.35 49,373.74 8,887.27 58,261.01
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
92,058.52 89,388.82 16,089.99 105,478.81
337,318.55 327,536.30 58,956.53 386,492.83
31 dias
1,396,020.28 1,355,535.64 243,996.42 1,599,532.06
31 dias
1,485,458.74 1,442,380.38 259,628.47 1,702,008.85
3.32%
2.04%
1.29%
2.33%
8.54%
35.33%
37.59%
4.82%
6.86%
8.15%
10.48%
19.01%
54.34%
91.93%
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 6,535.91 S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 394,971.57 S/. 48,448.10 S/40,458.04 S/7,990.06 S/. 43,655.86 S/19,942.20 S/8,611.30 S/5,805.29 S/2,718.45 S/4,553.41 S/760.66 S/1,264.55 S/. 11,300.25 S/11,300.25 S/. 37,488.94 S/11,646.65 S/17,434.16
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/5,084.70 S/3,323.44 S/. 70,124.07 S/41,059.11 S/3,436.54 S/24,034.30 S/1,594.11 S/. 7,452.07 S/6,743.54 S/708.53 S/. 17,596.21 S/17,596.21 S/. 34,502.15 S/1,457.85 S/1,826.80 S/1,985.51 S/29,232.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00
S/. 2,087.09 S/608.47
S/. 21,381.72 S/8,618.40 S/8,085.00 S/877.80 S/3,800.52 S/. 2,206.68 S/1,168.08 S/856.70 S/181.90 S/. 2,310.00 S/2,310.00 S/. 16,493.12 S/8,921.62 S/2,733.04 S/4,838.45 S/. 23,653.69 S/6,896.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/119.05 S/42.35 S/250.22 S/185.29 S/34.41 S/12.35 S/587.65 S/79.41 S/133.55 S/34.34 S/. 4,448.82
S/37.06 S/4,411.76 S/. 11,141.98 S/. 0.00
S/1,349.20 S/480.00 S/2,835.79 S/2,100.00 S/390.00 S/140.00 S/6,660.00 S/900.00 S/1,513.54 S/389.16 S/. 58,358.71 S/7,228.58 S/710.13 S/420.00 S/50,000.00 S/. 359,930.64 S/. 40,203.77
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 0.00 S/. 0.00
S/34,378.18 S/5,825.58 S/. 41,106.78 S/17,601.10 S/8,072.09 S/864.58 S/2,250.38 S/4,785.31 S/5,730.78 S/483.33 S/136.34 S/1,182.86 S/. 10,216.42 S/10,216.42 S/. 35,901.63 S/10,985.83 S/16,259.23
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 0.00
S/. 0.00 S/. 2,377.41 S/161.19 S/175.19 S/2,001.18 S/39.85
S/5,084.70 S/3,571.87 S/. 64,048.05 S/37,190.33 S/3,258.73 S/22,127.50 S/1,471.49 S/. 6,468.69 S/5,876.21 S/592.48 S/. 15,805.45 S/15,805.45 S/. 26,943.95 S/1,826.80 S/1,985.51 S/22,680.00 S/451.65
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 1,821.30 S/719.87 S/713.38 S/39.71 S/335.34 S/13.01 S/. 113.69 S/59.84 S/37.80 S/16.05 S/. 99.93 S/99.93 S/. 0.00
S/. 2,287.00
S/. 20,641.44 S/8,158.50 S/8,085.00 S/450.00 S/3,800.52 S/147.42 S/. 1,288.49 S/678.24 S/428.35 S/181.90 S/. 1,132.56 S/1,132.56 S/. 13,127.95 S/5,948.83 S/2,872.23 S/4,306.89 S/. 25,919.34
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/608.47 S/432.35 S/187.66 S/185.29 S/587.65 S/66.18 S/190.78 S/28.61 S/. 4,442.65 S/30.88 S/4,411.76 S/. 3,700.45 S/. 0.00 S/. 0.00
S/6,896.00 S/4,900.00 S/2,126.84 S/2,100.00 S/6,660.00 S/750.00 S/2,162.20 S/324.30 S/. 57,126.10 S/6,776.10 S/350.00 S/50,000.00 S/. 153,528.33 S/. 14,763.71 S/14,763.71 S/. 17,340.34 S/9,554.58
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00 S/. 0.00
S/. 0.00
S/. 0.00
S/1,292.54 S/164.52 S/2,407.98 S/1,663.38 S/1,787.90 S/469.44 S/. 2,937.41 S/2,937.41 S/. 15,315.76 S/5,878.08 S/9,437.68 S/. 30,465.93 S/16,397.89 S/1,244.63 S/12,562.83 S/260.58 S/. 3,795.71
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00 S/. 329.33 S/329.33 S/. 1,298.33 S/137.41 S/966.31 S/39.71 S/154.91 S/. 170.86 S/63.17 S/75.59 S/32.10 S/. 224.56 S/224.56 S/. 0.00
S/3,795.71 S/. 5,641.75 S/5,641.75 S/. 3,732.41 S/3,732.41 S/. 14,714.46 S/1,557.36 S/10,951.50 S/450.00 S/1,755.60 S/. 1,936.42 S/715.92 S/856.70 S/363.80 S/. 2,544.96 S/2,544.96 S/. 3,996.43
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 1,638.60 S/636.55 S/124.54 S/44.31 S/180.92 S/152.88 S/161.54 S/36.00 S/3.23 S/83.08 S/179.63 S/35.92 S/. 38.77 S/38.77
S/1,186.45 S/998.39 S/1,811.59 S/. 35,503.04 S/13,792.00 S/2,698.40 S/960.00 S/3,920.00 S/3,312.36 S/3,500.00 S/780.00 S/70.00 S/1,800.00 S/3,891.96 S/778.32 S/. 840.00 S/840.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 877.18 S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00
S/. 54,428.91 S/. 7,311.14 S/7,311.14 S/. 6,288.23 S/3,338.55 S/1,178.52 S/53.72 S/963.25 S/539.99 S/214.18 S/. 999.17 S/999.17 S/. 5,733.09 S/2,193.05 S/3,540.04 S/. 11,864.64 S/5,911.24
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00 S/. 0.00 S/. 31.66 S/31.66 S/. 325.60 S/17.01 S/15.35 S/252.73 S/40.51 S/. 20.71 S/6.09 S/7.91 S/6.72
S/5,691.29 S/262.11 S/. 1,525.58 S/1,525.58 S/. 1,701.54 S/1,701.54 S/. 686.04 S/686.04 S/. 7,054.74 S/368.55 S/332.64 S/5,475.75 S/877.80 S/. 448.74 S/131.88 S/171.34 S/145.52
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 5.06 S/5.06 S/. 84.19 S/41.37 S/26.68 S/16.13 S/. 391.24 S/82.93 S/31.14 S/11.08 S/60.80 S/51.70 S/48.46 S/9.00 S/1.62 S/31.15 S/49.90
S/. 109.56 S/109.56 S/. 1,824.15 S/896.42 S/578.16 S/349.57 S/. 8,476.83 S/1,796.80 S/674.60 S/240.00 S/1,317.27 S/1,120.19 S/1,050.00 S/195.00 S/35.00 S/675.00 S/1,081.10
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/13.47 S/. 18.71 S/4.18 S/14.54 S/. 1,754.37 S/. 0.00 S/. 0.00
S/. 0.00
S/291.87 S/. 405.47 S/90.47 S/315.00 S/. 64,311.47 S/. 2,478.60 S/2,478.60 S/. 3,823.90 S/1,928.08 S/270.69 S/298.79 S/14.37 S/622.71 S/549.14 S/140.11 S/. 780.14 S/780.14
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 0.00
S/. 0.00 S/. 0.00 S/. 1,181.65 S/1,181.65 S/. 37.51 S/37.51 S/. 44.47 S/2.01
S/. 10,645.72 S/3,127.18 S/2,090.04 S/5,428.50 S/. 6,179.48 S/2,281.57 S/3,897.91 S/. 690.76 S/690.76 S/. 1,701.54 S/1,701.54 S/. 25,602.52 S/25,602.52 S/. 812.64 S/812.64 S/. 963.57 S/43.47
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/42.47 S/. 13.99 S/6.09 S/7.91 S/. 5.06 S/5.06 S/. 84.19 S/41.37 S/26.68 S/16.13 S/. 87.76 S/31.14 S/11.08 S/9.00 S/8.08 S/8.54 S/3.46
S/920.10 S/. 303.22 S/131.88 S/171.34 S/. 109.56 S/109.56 S/. 1,824.15 S/896.42 S/578.16 S/349.57 S/. 1,901.36 S/674.60 S/240.00 S/195.00 S/175.00 S/185.00 S/75.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/14.97 S/1.50 S/. 299.74 S/1.62 S/85.38 S/3.66 S/39.23 S/57.69 S/12.46 S/73.85 S/25.85 S/. 0.00 S/. 0.00
S/. 0.00
S/324.33 S/32.43 S/. 6,494.31 S/35.00 S/1,850.00 S/79.31 S/850.00 S/1,250.00 S/270.00 S/1,600.00 S/560.00 S/. 18,218.33 S/. 5,669.65 S/3,349.82 S/2,081.63 S/238.21 S/. 9,008.48
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 4,310.88 S/. 5.93
S/5.93 S/. 3,830.38 S/699.46 S/1,088.76 S/783.26 S/123.86 S/1,013.96 S/16.39
S/2,394.76 S/6,613.72 S/. 3,540.20 S/1,432.20 S/2,108.00 S/. 93,552.44 S/. 278.40 S/21.64 S/128.38 S/128.38 S/. 82,991.59 S/15,155.05 S/23,589.72 S/16,970.57 S/2,683.54 S/21,969.12 S/355.20
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/52.09 S/52.60 S/. 474.57 S/217.82 S/256.76 S/. 2,771.47 S/. 0.00 S/. 0.00
S/. 0.00
S/1,128.65 S/1,139.75 S/. 10,282.45 S/4,719.40 S/5,563.06 S/. 72,135.78 S/. 3,998.57 S/3,998.57 S/. 4,072.34 S/178.04 S/1,104.54 S/157.18 S/1,743.81 S/799.94 S/88.84 S/. 594.78 S/594.78
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00
S/. 0.00 S/. 0.00
S/. 0.00 S/. 1,854.81 S/34.68 S/1,809.66 S/10.47 S/. 482.25 S/26.92
S/. 1,075.86 S/95.47 S/168.26 S/812.13 S/. 624.62 S/624.62 S/. 614.49 S/147.39 S/467.10 S/. 1,106.59 S/1,106.59 S/. 40,187.53 S/751.38 S/39,209.35 S/226.80 S/. 10,448.71 S/583.16
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/14.01 S/129.23 S/312.10 S/. 12.15 S/6.09 S/3.95 S/2.11 S/. 26.65 S/21.59 S/5.06 S/. 97.13 S/39.22 S/48.31 S/9.60 S/. 65.92 S/31.83 S/11.08
S/303.46 S/2,800.00 S/6,762.08 S/. 263.22 S/131.88 S/85.67 S/45.67 S/. 577.37 S/467.81 S/109.56 S/. 2,104.44 S/849.69 S/1,046.66 S/208.09 S/. 1,428.25 S/689.60 S/240.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/8.08 S/3.46 S/9.98 S/1.50 S/. 232.57 S/1.62 S/83.26 S/147.69 S/. 322.85 S/. 0.00 S/. 0.00
S/175.00 S/75.00 S/216.22 S/32.43 S/. 5,039.00 S/35.00 S/1,804.00 S/3,200.00 S/. 13,763.27 S/. 3,338.09 S/3,338.09 S/. 3,062.96 S/1,118.46 S/161.16 S/115.66 S/1,415.44 S/105.85
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00 S/. 0.00 S/. 0.00 S/. 63.03 S/63.03 S/. 33.64 S/33.64 S/. 12.03 S/12.03 S/. 10.91 S/6.96 S/3.95 S/. 203.24
S/146.37 S/. 794.30 S/794.30 S/. 1,258.26 S/1,258.26 S/. 685.62 S/685.62 S/. 1,365.60 S/1,365.60 S/. 728.92 S/728.92 S/. 260.72 S/260.72 S/. 236.39 S/150.72 S/85.67 S/. 2,032.41
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/86.73 S/84.96 S/31.55 S/. 48,542.97 S/. 8,629.96 S/8,629.96 S/. 26,996.53 S/9,741.53 S/9,797.54 S/7,457.47 S/. 1,415.74 S/1,415.74 S/. 11,500.74 S/3,685.74 S/175.00 S/1,400.00 S/6,240.00
S/867.29 S/849.57 S/315.55 S/. 485,429.68 S/. 86,299.62 S/86,299.62 S/. 269,965.35 S/97,415.30 S/97,975.38 S/74,574.67 S/. 14,157.35 S/14,157.35 S/. 115,007.36 S/36,857.36 S/1,750.00 S/14,000.00 S/62,400.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 1,120.75 S/. 0.00 S/. 0.00 S/. 0.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 778.20 S/193.85
S/. 87,732.44 S/6,500.00 S/. 2,897.05 S/2,897.05 S/. 12,940.95 S/12,940.95 S/. 13,668.52 S/3,633.55 S/10,034.97 S/. 24,701.53 S/24,701.53 S/. 1,957.12 S/1,957.12 S/. 784.32 S/784.32 S/. 16,860.93 S/4,200.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/345.23 S/158.35 S/80.77 S/. 342.56 S/342.56 S/. 3,074.75 S/. 698.77 S/59.79 S/6.09 S/89.38 S/482.51 S/46.71 S/7.78 S/6.51 S/. 118.74 S/118.74 S/. 1,506.69
S/7,480.00 S/3,430.93 S/1,750.00 S/. 7,422.03 S/7,422.03 S/. 66,619.66 S/. 15,139.92 S/1,295.37 S/131.90 S/1,936.46 S/10,454.40 S/1,012.00 S/168.64 S/141.16 S/. 2,572.67 S/2,572.67 S/. 32,644.97
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/425.52 S/187.31 S/893.86 S/. 30.52 S/30.52 S/. 59.56 S/59.56 S/. 493.29 S/3.40 S/37.80 S/452.09 S/. 10.91 S/6.96 S/3.95 S/. 156.28 S/59.11 S/53.64
S/9,219.60 S/4,058.30 S/19,367.07 S/. 661.19 S/661.19 S/. 1,290.42 S/1,290.42 S/. 10,687.98 S/73.71 S/819.00 S/9,795.27 S/. 236.39 S/150.72 S/85.67 S/. 3,386.12 S/1,280.81 S/1,162.30
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/43.52 S/4,316.37 S/. 928.35 S/928.35 S/. 2,350.37 S/187.77 S/1,644.03 S/518.57 S/. 1,037.65 S/489.59 S/515.75 S/32.31 S/130,256.85 S/. 0.00 S/. 87,253.02 S/23,194.78
S/943.01 S/93,521.32 S/. 20,114.16 S/20,114.16 S/. 50,924.70 S/4,068.32 S/35,620.67 S/11,235.70 S/. 22,482.47 S/10,607.84 S/11,174.63 S/700.00 S/1,316,560.78 S/. 618.89 S/618.89 S/. 872,530.21 S/231,947.82
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/64,058.24 S/. 32,803.83 S/29,911.24 S/402.98 S/1,813.40 S/676.21 S/. 10,200.00 S/3,500.00 S/2,700.00 S/3,200.00 S/800.00 S/. 0.00 S/. 0.00 S/. 0.00
S/640,582.39 S/. 328,038.28 S/299,112.41 S/4,029.78 S/18,134.01 S/6,762.08 S/. 115,373.40 S/13,373.40 S/35,000.00 S/27,000.00 S/32,000.00 S/8,000.00 S/. 12,040.14 S/. 2,605.11 S/2,605.11 S/. 1,078.48 S/1,078.48
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/. 0.00 S/. 0.00 S/. 0.00
S/. 58,412.99 S/. 857.98 S/857.98 S/. 57,555.01 S/39,149.56 S/16,846.02 S/1,559.43 277,139.78 22,171.18 19,399.78
S/. 1,955.66 S/1,955.66 S/. 4,252.92 S/4,252.92 S/. 2,147.97 S/1,770.66 S/377.31 S/. 149,374.37 S/. 9,723.75 S/9,723.75 S/. 139,650.62 S/78,299.12 S/56,153.40 S/5,198.10 3,436,119.10 274,889.53 240,528.34
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
318,710.74 309,468.11 55,704.26 365,172.37 8.07% 100.00%
3,951,536.97 3,836,942.25 690,649.61 4,527,591.86
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01 1.01 01.01.01 01.01.02 01.01.03 1.02 01.02.01 01.02.02 01.02.03 01.02.04 01.02.05 01.02.06 01.02.07 01.02.08 1.03 01.03.01
SISTEMA DE AGUA FRIA SALIDA DE AGUA FRIA SALIDA DE AGUA FRIA TUB. PVC CLASE 10 C/R 1/2" SALIDA DE AGUA FRIA TUB. PVC CLASE 10 C/R 1" SALIDA DE AGUA FRIA TUB. PVC CLASE 10 C/R 1 1/4" REDES DE DISTRIBUCION DE AGUA FRIA EN TUBERIA DE PVC RED DE DISTRIBUCION 1/2" PVC SAP RED DE DISTRIBUCION 3/4" PVC SAP RED DE DISTRIBUCION 1" PVC SAP RED DE DISTRIBUCION 1 1/4" PVC SAP RED DE DISTRIBUCION 1 1/2" PVC SAP RED DE DISTRIBUCION 2" PVC SAP RED DE DISTRIBUCION 2 1/2" PVC SAP RED DE DISTRIBUCION 4" PVC SAP ACCESORIOS TEE PVC S/ PRESION 4"
METRADO
C. Unit.
pto pto pto
168.00 5.00 59.00
S/161.34 S/171.20 S/202.01
m m m m m m m m
92.66 67.53 77.77 141.37 45.44 62.53 338.52 427.58
S/20.29 S/21.04 S/21.54 S/62.04 S/63.29 S/67.93 S/68.45 S/72.32
3.00
S/28.65
pza
S/133,520.31 S/39,879.71 S/27,105.12 S/856.00 S/11,918.59 S/74,964.50 S/1,880.07 S/1,420.83 S/1,675.17 S/8,770.59 S/2,875.90 S/4,247.66 S/23,171.69 S/30,922.59 S/4,967.72 S/85.95
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01.03.02 01.03.03 01.03.04 01.03.05 01.03.06 01.03.07 01.03.08 01.03.09 01.03.10 01.03.11 01.03.12 01.03.13 01.03.14 01.03.15 01.03.16 01.03.17
TEE PVC S/ PRESION 2 1/2" TEE PVC S/ PRESION 1 1/2" TEE PVC S/ PRESION 1 1/4" TEE PVC S / PRESION 1" TEE PVC S/ PRESION 3/4" TEE PVC S/ PRESION 1/2" CODO PVC S/ PRESION 4" CODO PVC S/ PRESION 2 1/2" x 90º CODO PVC S/ PRESION 1 1/2" x 90º CODO PVC S/ PRESION 1 1/4" x 90º CODO PVC S/ PRESION 1" x 90º CODO PVC S/ PRESION 3/4" CODO DE 45° 4" CODO PVC SAP 2 1/2" X 45° CODO DE 45° 2" CODO PVC SAP 1 1/4" X 45º
pza und pza pza und pza und pza pza pza pza und pza pza pza pza
METRADO
13.00 17.00 57.00 39.00 34.00 8.00 3.00 3.00 9.00 43.00 24.00 4.00 4.00 6.00 2.00 1.00
C. Unit.
S/16.05 S/12.90 S/10.80 S/8.70 S/7.13 S/4.50 S/26.40 S/13.80 S/12.75 S/11.70 S/9.60 S/5.93 S/27.60 S/14.01 S/12.44 S/9.60
S/208.65 S/219.30 S/615.60 S/339.30 S/242.42 S/36.00 S/79.20 S/41.40 S/114.75 S/503.10 S/230.40 S/23.72 S/110.40 S/84.06 S/24.88 S/9.60
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01.03.18 01.03.19 01.03.20 01.03.21 01.03.22 01.03.23 01.03.24 01.03.25 01.03.26 01.03.27 01.03.28 01.03.29 01.03.30 01.03.31 01.03.32 1.04
CODO PVC S/PRESION DE 22.5° 2 1/2" CODO PVC S/PRESION DE 22.5° 2" CODO PVC S/PRESIO DE 22.5° 3/4" REDUCCION PVC S/ PRESION 4" - 2" REDUCCION PVC S/PRESION 2 1/2" A 3/4" REDUCCION PVC S/ PRESION 1 1/2" - 1 1/4" REDUCCION PVC S/ PRESION 1 1/2" - 1" REDUCCION PVC S/PRESION 1 1/2" A 3/4" REDUCCION PVC S/PRESION 1 1/2" A 1/2" REDUCCION PVC S/PRESION 1 1/4" A 1" REDUCCION PVC S/PRESION 1 1/4" A 3/4" REDUCCION PVC S/PRESION 1 1/4" A 1/2" REDUCCION PVC S/ PRESION 1" - 3/4" REDUCCION PVC S/PRESION DE 1" A 1/2" REDUCCION PVC S/PRESION 3/4" A 1/2" LLAVES Y VALVULAS
pza pza pza pza pza pza pza pza pza pza pza pza pza pza pza
METRADO
2.00 1.00 2.00 2.00 1.00 9.00 1.00 38.00 4.00 14.00 1.00 59.00 1.00 37.00 3.00
C. Unit.
S/15.90 S/13.80 S/6.45 S/25.50 S/16.05 S/12.90 S/10.80 S/12.90 S/12.90 S/12.90 S/11.85 S/11.85 S/8.70 S/7.65 S/7.13
S/31.80 S/13.80 S/12.90 S/51.00 S/16.05 S/116.10 S/10.80 S/490.20 S/51.60 S/180.60 S/11.85 S/699.15 S/8.70 S/283.05 S/21.39 S/12,315.30
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01.04.01 01.04.02 01.04.03 01.04.04 01.04.05 1.05 01.05.01 02 2.01 02.01.01 02.01.02 02.01.03 2.02 02.02.01 02.02.02 02.02.03
VALVULA DE COMPUERTA DE BRONCE 1 1/2" VALVULA COMPUERTA DE BRONCE DE 1 1/4" VALVULA DE COMPUERTA DE BRONCE 1" VALVULA COMPUERTA DE BRONCE DE 3/4" CAJAS DE CONCRETO PARA VALVULAS GRIFOS DE RIEGO GRIFO DE RIEGO DE 1/2" DESAGUE Y VENTILACION SALIDAS DE DESAGUE Y VENTILACION SALIDA DE DESAGUE PVC SAL 4" SALIDA DE DESAGUE PVC SAP 2" SALIDA DE VENTILACION PVC SAL 2" REDES DE DERIVACION TUBERIA PVC SAL Ø 8" TUBERIA PVC SAL Ø 6" TUBERIA PVC SAL Ø 4"
METRADO
C. Unit.
pza pza pza pza und
5.00 20.00 2.00 3.00 3.00
S/361.80 S/329.80 S/300.80 S/186.44 S/916.46
und
4.00
S/348.27
pto pto pto
43.00 156.00 37.00
S/154.80 S/130.81 S/105.45
m m m
96.60 148.35 343.70
S/77.99 S/76.89 S/61.36
S/1,809.00 S/6,596.00 S/601.60 S/559.32 S/2,749.38 S/1,393.08 S/1,393.08 S/107,543.57 S/30,964.41 S/6,656.40 S/20,406.36 S/3,901.65 S/55,978.19 S/7,533.83 S/11,406.63 S/21,089.43
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.02.04 2.03 02.03.01 02.03.02 02.03.03 02.03.04 2.04 02.04.01 03 3.01 3.02 04 4.01 04.01.01 04.01.02 04.01.03
TUBERIA PVC SAL Ø 2" ACCESORIOS DE DESAGUE Y VENTILACION REGISTRO DE BRONCE 4" REGISTRO DE BRONCE 2" SUMIDERO DE BRONCE 2" SOMBRERO DE VENTILACION PVC DE 2" CAJA DE REGISTRO DE ALBAÑILERIA CAJA DE REGISTRO 12"x24" PRUEBAS HIDRAULICAS Y DESINFECCION PRUEBA HIDRAULICA DE AGUA FRIA PRUEBA HIDRAULICA DE DESAGUE PISCINAS REDES DE AGUA FRIA RED DE TUBERIA PVC 10" RED DE TUBERIA PVC 8" RED DE TUBERIA PVC SAP 6"
METRADO
C. Unit.
m
276.64
S/57.65
pza und pza pza
19.00 23.00 155.00 43.00
S/103.22 S/89.42 S/88.71 S/27.81
pza
5.00
S/327.45
m m
1,510.18 994.09
m m m
62.20 213.95 323.85
S/5.44 S/3.25
S/85.22 S/82.72 S/80.22
S/15,948.30 S/18,963.72 S/1,961.18 S/2,056.66 S/13,750.05 S/1,195.83 S/1,637.25 S/1,637.25 S/11,446.17 S/8,215.38 S/3,230.79 S/303,322.90 S/154,199.20 S/5,300.68 S/17,697.94 S/25,979.25
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.01.04 04.01.05 04.01.06 04.01.07 4.02 04.02.01 04.02.02 04.02.03 04.02.04 04.02.05 04.02.06 04.02.07 04.02.08 04.02.09 04.02.10 04.02.11
RED DE TUBERIA PVC SAP 4" RED DE TUBERIA PVC SAP 3" RED DE TUBERIA PVC SAP 2" RED DE TUBERIA PVC SAP 1 1/2" ACCESORIOS DE REDES DE AGUA FRIA TEE PVC C-10 S/P 10" c/red. 4" TEE PVC C-10 S/P 10" c/red. 3" TEE PVC C-10 S/P 8" c/red. 3" TEE PVC C-10 S/P 6" TEE PVC C-10 S/P 6" c/red. 4" TEE PVC C-10 S/P 6" c/red. 3" TEE PVC C-10 S/P 4" TEE PVC C-10 S/P 4" c/red. 3" TEEPVC C-10 S/P 4" c/red. 2" TEE PVC C-10S/P 3" TEE PVC C-10 S/P 3" c/red. 2"
METRADO
C. Unit.
m m m m
508.25 496.19 373.36 126.85
S/72.32 S/69.82 S/67.93 S/66.68
pza pza pza pza pza pza pza pza pza pza pza
1.00 10.00 14.00 1.00 10.00 20.00 1.00 30.00 1.00 17.00 2.00
S/65.00 S/65.00 S/55.00 S/51.00 S/48.00 S/48.00 S/27.40 S/25.40 S/25.40 S/20.40 S/18.40
S/36,756.64 S/34,643.99 S/25,362.34 S/8,458.36 S/8,326.80 S/65.00 S/650.00 S/770.00 S/51.00 S/480.00 S/960.00 S/27.40 S/762.00 S/25.40 S/346.80 S/36.80
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.02.12 04.02.13 04.02.14 04.02.15 04.02.16 04.02.17 04.02.18 04.02.19 04.02.20 04.02.21 04.02.22 04.02.23 04.02.24 04.02.25 04.02.26 04.02.27
TEE PVC C-10 S/P 3" c/red. 1 1/2" TEE PVC C-10 S/P 2" TEE PVC C-10 S/P 2" c/red. 1 1/2" TEE PVC C-10 S/P 1 1/2" CODO PVC C-10 S/P 45° x 10" CODO PVC C-10 S/P45° x 10" c/red. 8" CODO PVC C-10 S/P 45° x 8" CODO PVC C-10 S/P 45° x 8" c/red. 6" CODO PVC C-10 S/P 45° x 6" CODO PVC C-10 S/P 45° x 6" c/red. 4" CODO PVC C-10 S/P 90° x 4" CODO PVC C-10 S/P 45° x 4" CODO PVC C-10 S/P 90° x 3" CODO PVC C-10 S/P 45° x 4" c/red. 3" CODO PVC C-10 S/P 45° x 3" CODO PVC C-10 S/P45° x 3" c/red. 2"
pza pza pza pza pza pza pza pza pza pza pza pza pza pza pza pza
METRADO
5.00 21.00 12.00 6.00 3.00 2.00 14.00 2.00 6.00 3.00 4.00 14.00 5.00 5.00 35.00 1.00
C. Unit.
S/18.40 S/14.40 S/14.40 S/14.40 S/64.40 S/64.40 S/54.40 S/54.40 S/47.40 S/47.40 S/25.20 S/25.20 S/19.20 S/19.20 S/17.20 S/17.20
S/92.00 S/302.40 S/172.80 S/86.40 S/193.20 S/128.80 S/761.60 S/108.80 S/284.40 S/142.20 S/100.80 S/352.80 S/96.00 S/96.00 S/602.00 S/17.20
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.02.28 04.02.29 04.02.30 04.02.31 04.02.32 4.03 04.03.01 04.03.02 04.03.03 04.03.04 04.03.05 4.04 04.04.01 04.04.02 04.04.03 04.04.04
CODO PVC C-10 S/P 90° x 2" CODO PVC C-10 S/P 90° x 1 1/2" CODO PVC C-10 S/P 45° x 2" CODO PVC C-10 S/P 45° x 2" c/red. 1 1/2" REDUCCION PVC S/ PRESION 4" - 2" ACCESORIOS DE PISCINAS BOQUILLA DE LLENADO DE AGUA DE LA RED SEGUN DISEÑO SUCCION DE FONDO CON SUMIDERO DE 12" x 12" BOQUILLA DE ASPIRACION DE AGUA BOQULLA DE RETORNO DE AGUA DESNATADOR REDES DE DESAGUE TUBERIA PVC SAL Ø 6" TUBERIA PVC SAL Ø 4" TUBERIA PVC SAL Ø3" TUBERIA PVC SAL Ø 2"
pza pza pza pza pza und und und und und m m m m
METRADO
17.00 2.00 14.00 2.00 6.00
C. Unit.
S/13.20 S/13.20 S/13.20 S/13.20 S/25.50
3.00 19.00 25.00 73.00 4.00
S/204.05 S/474.05 S/414.05 S/414.05 S/614.05
74.65 128.29 197.28 214.28
S/76.89 S/61.36 S/60.45 S/57.65
S/224.40 S/26.40 S/184.80 S/26.40 S/153.00 S/52,652.20 S/612.15 S/9,006.95 S/10,351.25 S/30,225.65 S/2,456.20 S/37,890.53 S/5,739.84 S/7,871.87 S/11,925.58 S/12,353.24
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
4.05 04.05.01 04.05.02 04.05.03 04.05.04 04.05.05 04.05.06 04.05.07 04.05.08 04.05.09 04.05.10 04.05.11 04.05.12 04.05.13 04.05.14 04.05.15
ACCESORIOS DE RED DE DESAGUE YEE PVC SAL 6" YEE PVC SAL 6" c/red. 4" YEE PVC SAL 6" c/red. 3" YEE PVC SAL 6" c/red. 2" YEE PVC SAL 4" c/red. 3" YEE PVC SAL 4" c/red. 2" YEE PVC SAL 3" YEE PVC SAL 3" c/red. 2" YEE PVC SAL 2" CODO PVC SAL 45° x 6" CODO PVC SAL 45° x 6" c/red. 4" CODO PVC SAL 45° x 6" c/red. 3" CODO PVC SAL 45° x 4" CODO PVC SAL 45° x 4" c/red. 3" CODO PVC SAL 45° x 3" c/red. 2"
pza pza pza pza pza pza pza pza pza pza pza pza pza pza pza
METRADO
1.00 1.00 1.00 5.00 1.00 24.00 14.00 45.00 9.00 1.00 1.00 1.00 7.00 3.00 7.00
C. Unit.
S/13.00 S/13.00 S/13.00 S/13.00 S/8.40 S/8.40 S/7.40 S/7.40 S/6.40 S/10.40 S/10.40 S/10.40 S/6.20 S/6.20 S/5.20
S/36,807.80 S/13.00 S/13.00 S/13.00 S/65.00 S/8.40 S/201.60 S/103.60 S/333.00 S/57.60 S/10.40 S/10.40 S/10.40 S/43.40 S/18.60 S/36.40
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.05.16 04.05.17 04.05.18 04.05.19 4.06 04.06.01 04.06.02 05 5.01 05.01.01 05.01.02 05.01.03 05.01.04 05.01.05 05.01.06 05.01.07
CODO PVC SAL 45° x 3" CODO PVC SAL 45° x 2" SUMIDERO DE CANALETA DE PISCINA DE 2" SUMIDERO DE CANALETA DE PISCINA DE 3" PRUEBAS HIDRAULICAS Y DESINFECCION PRUEBA HIDRAULICA DE AGUA FRIA PRUEBA HIDRAULICA DE DESAGUE CISTERNA Y CUARTO DE MAQUINAS 1 - USO DOMESTICO CAMARA HUMEDA TUBERIA SCH-40 2" TUBERIA SCH-40 3" TUBERIA SCH-40 6" CODO SCH 2" x 90° CODO SCH 3" x 90° CODO SCH 6" x 90° BRIDA ROMPE AGUA 2"
pza pza pza pza m m
m m m pza pza pza pza
METRADO
10.00 6.00 94.00 82.00 2,104.64 614.50
1.50 12.00 1.50 1.00 6.00 2.00 1.00
C. Unit.
S/5.20 S/4.20 S/194.05 S/214.05 S/5.44 S/3.25
S/41.26 S/61.43 S/127.57 S/413.02 S/475.02 S/1,499.38 S/77.63
S/52.00 S/25.20 S/18,240.70 S/17,552.10 S/13,446.37 S/11,449.24 S/1,997.13 S/98,963.65 S/9,233.96 S/61.89 S/737.16 S/191.36 S/413.02 S/2,850.12 S/2,998.76 S/77.63
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.01.08 05.01.09 05.01.10 05.01.11 5.02 05.02.01 05.02.02 05.02.03 05.02.04 05.02.05 05.02.06 05.02.07 05.02.08 05.02.09 05.02.10 05.02.11
BRIDA ROMPE AGUA Ø 3" BRIDA ROMPE AGUA 6" VALVULA FLOTADORA CON BOYA DE 2" VALVULA DE PIE CON CANASTILLA DE SUCCION DE BRONCE DE 3" CAMARA SECA TUBERIA SCH-40 6" TUBERIA SCH-40 3" TUBERIA SCH-40 2" Tee SCH-40 ø 2" Tee SCH-40 ø 3" CODO SCH 3" x 90° CODO SCH 2" x 90° Reduccion SCH-40 de 3" a -2" Manifold SCH-40 de 10" Niple SCH-40 ø2" x 4" Niple SCH-40 ø3" x 4"
METRADO
und pza pza pza
3.00 1.00 1.00 3.00
m m m pza pza pza pza pza pza pza pza
10.00 10.00 55.00 5.00 1.00 4.00 10.00 6.00 4.00 2.00 12.00
C. Unit.
S/50.34 S/138.95 S/117.20 S/498.95 S/127.57 S/61.43 S/41.26 S/319.05 S/371.05 S/475.02 S/413.02 S/439.02 S/1,599.07 S/267.63 S/299.01
S/151.02 S/138.95 S/117.20 S/1,496.85 S/89,729.69 S/1,275.70 S/614.30 S/2,269.30 S/1,595.25 S/371.05 S/1,900.08 S/4,130.20 S/2,634.12 S/6,396.28 S/535.26 S/3,588.12
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.02.12 05.02.13 05.02.14 05.02.15 05.02.16 05.02.17 05.02.18 05.02.19 05.02.20 05.02.21 05.02.22 05.02.23 05.02.24 05.02.25 05.02.26 05.02.27
Valvula Esferica BB 2" Valvula Sheck BB 2" Valvula Sheck BB 3" Valvula BB de pie 3" Valvula BB de pie 2" Valvula flotador BB ø2" Valvula compuerta BB 1" Valvula compuerta BB 2" Valvula compuerta BB 3" Valvula multi puertos Medidor de caudal BB 4" Electrobamba de presion constante de 3 HP Electrobamba sumergible para desague de 1 HP Electrobamba de presion constante de 1 HP Tanque hidroneomatico con membrana de 20 gl MANOMETRO DE PRESION 0-100PSI
pza pza pza pza pza pza pza pza pza pza pza pza pza pza pza pza
METRADO
1.00 5.00 3.00 3.00 2.00 1.00 1.00 5.00 6.00 2.00 1.00 3.00 2.00 4.00 1.00 1.00
C. Unit.
S/1,109.54 S/1,084.54 S/1,243.08 S/1,258.08 S/1,134.54 S/858.02 S/993.08 S/1,124.54 S/1,218.08 S/1,250.00 S/1,688.66 S/3,088.77 S/1,868.32 S/1,573.77 S/1,019.39 S/160.69
S/1,109.54 S/5,422.70 S/3,729.24 S/3,774.24 S/2,269.08 S/858.02 S/993.08 S/5,622.70 S/7,308.48 S/2,500.00 S/1,688.66 S/9,266.31 S/3,736.64 S/6,295.08 S/1,019.39 S/160.69
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.02.28 05.02.29 05.02.30 05.02.31 05.02.32 06 6.01 06.01.01 06.01.02 06.01.03 06.01.04 06.01.05 06.01.06 06.01.07 6.02 06.02.01
Filtro vertical con vaso visor 2.46 PIES2 y 49 GPM Dosificador de Cloro tipo clorimax de conexión 1/4" y 20 kg Tuberia PVC SAL 4" Codo PVC SAL ø 4"x 90 Trampa PVC SAL tipo p ø4" CISTERNA DE COMPENSACION Y CUARTO DE MAQUINAS 2 CAMARA HUMEDA TUBERIA SCH - 40 4" TUBERIA SCH-40 6" CODO SCH - 40 6" x 90º - RANURADO CODO SCH - 40 2" x 90º - RANURADO BRIDA ROMPE AGUA 6" BRIDA ROMPE AGUA 4" BRIDA ROMPE AGUA 3" CAMARA SECA TUBERIA SCH-40 6"
METRADO
C. Unit.
pza pza m pza pza
2.00 1.00 10.00 1.00 1.00
S/3,060.06 S/1,910.06 S/61.36 S/6.20 S/16.20
m m pza pza pza pza pza
6.00 1.50 2.00 2.00 1.00 4.00 2.00
S/90.02 S/127.57 S/199.16 S/123.30 S/138.95 S/118.08 S/116.08
m
60.00
S/127.57
S/6,120.12 S/1,910.06 S/613.60 S/6.20 S/16.20 S/229,873.25 S/2,219.83 S/540.12 S/191.36 S/398.32 S/246.60 S/138.95 S/472.32 S/232.16 S/227,653.42 S/7,654.20
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.02.02 06.02.03 06.02.04 06.02.05 06.02.06 06.02.07 06.02.08 06.02.09 06.02.10 06.02.11 06.02.12 06.02.13 06.02.14 06.02.15 06.02.16 06.02.17
TUBERIA SCH - 40 4" TUBERIA SCH - 40 3" Tee SCH-40 BB 6" CODO SCH 2" x 90° CODO SCH 4" x 90° CODO SCH 6" x 90° Manifold SCH-40 de 10" Niple SCH-40 ø2" x 4" Niple SCH-40 ø3" x 4" Valvula Esferica BB 2" Valvula Sheck BB 2" Valvula Sheck BB 3" Valvula Sheck BB 4" Valvula BB de pie 2" Valvula compuerta BB 3" Valvula compuerta BB 4"
m m pza pza pza pza pza pza pza pza pza pza pza pza pza pza
METRADO
35.00 60.00 14.00 6.00 6.00 12.00 4.00 4.00 6.00 5.00 2.00 6.00 2.00 2.00 12.00 6.00
C. Unit.
S/90.02 S/53.63 S/760.05 S/413.02 S/407.02 S/785.54 S/1,599.07 S/267.63 S/299.01 S/1,109.54 S/1,084.54 S/1,243.08 S/1,286.58 S/1,134.54 S/1,218.08 S/1,287.38
S/3,150.70 S/3,217.80 S/10,640.70 S/2,478.12 S/2,442.12 S/9,426.48 S/6,396.28 S/1,070.52 S/1,794.06 S/5,547.70 S/2,169.08 S/7,458.48 S/2,573.16 S/2,269.08 S/14,616.96 S/7,724.28
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.02.18 06.02.19 06.02.20 06.02.21 06.02.22 06.02.23 06.02.24 06.02.25 06.02.26 06.02.27 06.02.28 06.02.29
Valvula compuerta BB 6" Valvula multi puertos Medidor de caudal BB 4" Electrobamba de presión constante de 5 HP ELECTROBOMBA DE PRESION CONSTANTE DE 10 HP Electrobamba sumergible para desague de 1 HP Electrobamba de presion constante de 1 HP MANOMETRO DE PRESION 0-100PSI Filtro vertical con vaso visor 12.57 p2 y 140 GPM Filtro vertical con vaso visor 50.27 p2 y 420 GPM Dosificador de Cloro tipo clorimax de conexión 1/4" y 20 kg TUBERIA PVC SAL Ø 2"
pza pza pza pza und pza pza pza pza pza pza m
METRADO
8.00 4.00 2.00 6.00 3.00 3.00 1.00 2.00 2.00 2.00 2.00 14.00
C. Unit.
S/1,788.11 S/1,250.00 S/1,688.66 S/7,618.77 S/13,153.77 S/1,868.32 S/1,573.77 S/160.69 S/3,760.06 S/4,760.06 S/1,910.06 S/57.65
Costo Directo Gastos Generales Utilidad Parcial
8.00% 7.00%
S/14,304.88 S/5,000.00 S/3,377.32 S/45,712.62 S/39,461.31 S/5,604.96 S/1,573.77 S/321.38 S/7,520.12 S/9,520.12 S/3,820.12 S/807.10 S/884,669.85 S/70,773.59 S/61,926.89 S/1,017,370.33
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO DE AVA Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
METRADO
C. Unit.
0.971 18.00%
S/987,866.55 S/177,815.98 S/1,165,682.53
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
PORCENTAJE DE AVANCE ( % )
0.00%
0.00%
PORCENTAJE ACUMULADO DE AVANCE ( % )
0.00%
0.00%
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/7,480.14 S/0.00 S/0.00 S/0.00 S/0.00 S/7,480.14 S/846.03 S/639.37 S/753.82 S/3,946.77 S/1,294.15 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/11,145.11 S/11,145.11 S/8,067.00 S/856.00 S/2,222.11 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/12,998.99 S/12,998.99 S/8,612.48 S/0.00 S/4,386.50 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/16,460.14 S/15,735.61 S/10,425.64 S/0.00 S/5,309.98 S/674.84 S/10.34 S/7.81 S/9.21 S/48.24 S/15.82 S/42.48 S/231.72 S/309.23 S/49.68 S/0.86
S/3,622.60 S/0.00
S/74,959.15 S/0.00
S/6,854.19 S/0.00
S/0.00
S/0.00
S/0.00
S/3,374.22 S/51.70 S/39.07 S/46.07 S/241.19 S/79.09 S/212.38 S/1,158.58 S/1,546.13 S/248.39 S/4.30
S/63,435.30 S/972.00 S/734.57 S/866.07 S/4,534.40 S/1,486.84 S/3,992.80 S/21,781.39 S/29,067.23 S/4,669.66 S/80.79
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/2.09 S/2.19 S/6.16 S/3.39 S/2.42 S/0.36 S/0.79 S/0.41 S/1.15 S/5.03 S/2.30 S/0.24 S/1.10 S/0.84 S/0.25 S/0.10
S/10.43 S/10.97 S/30.78 S/16.97 S/12.12 S/1.80 S/3.96 S/2.07 S/5.74 S/25.16 S/11.52 S/1.19 S/5.52 S/4.20 S/1.24 S/0.48
S/196.13 S/206.14 S/578.66 S/318.94 S/227.87 S/33.84 S/74.45 S/38.92 S/107.87 S/472.91 S/216.58 S/22.30 S/103.78 S/79.02 S/23.39 S/9.02
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/0.00
ABRIL
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/29.89 S/12.97 S/12.13 S/47.94 S/15.09 S/109.13 S/10.15 S/460.79 S/48.50 S/169.76 S/11.14 S/657.20 S/8.18 S/266.07 S/20.11 S/6,157.65
S/6,157.65
S/0.00
S/0.32 S/0.14 S/0.13 S/0.51 S/0.16 S/1.16 S/0.11 S/4.90 S/0.52 S/1.81 S/0.12 S/6.99 S/0.09 S/2.83 S/0.21 S/0.00
S/1.59 S/0.69 S/0.65 S/2.55 S/0.80 S/5.81 S/0.54 S/24.51 S/2.58 S/9.03 S/0.59 S/34.96 S/0.44 S/14.15 S/1.07 S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/12,090.90 S/11,436.00 S/2,322.00 S/7,848.60 S/1,265.40 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/904.50 S/3,298.00 S/300.80 S/279.66 S/1,374.69 S/696.54 S/696.54 S/79,860.15 S/18,356.71 S/4,074.34 S/11,804.29 S/2,478.08 S/52,619.50 S/7,081.80 S/10,722.23 S/19,824.07
S/904.50 S/3,298.00 S/300.80 S/279.66 S/1,374.69 S/696.54 S/696.54 S/8,883.95 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,083.01 S/97.64 S/21.67 S/62.79 S/13.18 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/1,850.24 S/97.64 S/21.67 S/62.79 S/13.18 S/559.78 S/75.34 S/114.07 S/210.89
S/3,775.33 S/976.42 S/216.72 S/627.89 S/131.81 S/2,798.91 S/376.69 S/570.33 S/1,054.47
S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/654.90 S/654.90 S/0.00 S/0.00 S/0.00 S/49,351.71 S/42,080.21 S/0.00 S/0.00 S/8,788.90
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/540.97
S/540.97 S/444.40 S/444.40 S/0.00
S/359.65 S/359.65
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/159.48 S/654.86
S/797.41 S/0.00
S/14,991.40 S/8,883.95 S/980.59 S/1,028.33 S/6,875.03
S/8,883.95 S/980.59 S/1,028.33 S/6,875.03
S/0.00
S/0.00
S/0.00
S/0.00
S/5,723.09 S/4,107.69 S/1,615.40 S/214,316.56 S/88,038.12 S/2,693.79 S/8,994.04 S/8,736.08
S/5,723.09 S/4,107.69 S/1,615.40 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/654.86 S/537.95 S/537.95 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/8,145.73 S/359.65
S/31,149.25 S/23,361.57 S/2,606.89 S/8,703.91 S/8,454.27
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/9,849.98 S/19,976.90 S/3,464.43 S/0.00 S/3,060.80 S/0.00 S/0.00 S/0.00 S/51.00 S/240.00 S/480.00 S/27.40 S/381.00 S/25.40 S/163.20 S/18.40
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/134.53 S/73.34 S/109.49 S/42.29 S/0.00
ABRIL
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/1,345.33 S/733.35 S/1,094.90 S/422.92 S/958.37 S/13.00 S/130.00 S/154.00 S/0.00 S/48.00 S/96.00 S/0.00 S/76.20 S/0.00 S/36.72 S/3.68
S/25,292.26 S/13,787.06 S/20,584.04 S/7,950.86 S/3,812.64 S/45.50 S/455.00 S/539.00 S/0.00 S/168.00 S/336.00 S/0.00 S/266.70 S/0.00 S/128.52 S/12.88
S/0.00
S/134.53 S/73.34 S/109.49 S/42.29 S/494.99 S/6.50 S/65.00 S/77.00 S/0.00 S/24.00 S/48.00 S/0.00 S/38.10 S/0.00 S/18.36 S/1.84
S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/36.80 S/158.40 S/86.40 S/43.20 S/64.40 S/64.40 S/380.80 S/54.40 S/142.20 S/47.40 S/50.40 S/176.40 S/38.40 S/38.40 S/292.40 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/5.52 S/14.40 S/8.64 S/4.32 S/12.88 S/6.44 S/38.08 S/5.44 S/14.22 S/9.48 S/5.04 S/17.64 S/5.76 S/5.76 S/30.96 S/0.86
S/11.04 S/28.80 S/17.28 S/8.64 S/25.76 S/12.88 S/76.16 S/10.88 S/28.44 S/18.96 S/10.08 S/35.28 S/11.52 S/11.52 S/61.92 S/0.86
S/38.64 S/100.80 S/60.48 S/30.24 S/90.16 S/45.08 S/266.56 S/38.08 S/99.54 S/66.36 S/35.28 S/123.48 S/40.32 S/40.32 S/216.72 S/15.48
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/11.22 S/1.32 S/9.24 S/1.32 S/7.65 S/2,632.61 S/30.61 S/450.35 S/517.56 S/1,511.28 S/122.81 S/1,894.53 S/286.99 S/393.59 S/596.28 S/617.66
S/11.22 S/1.32 S/9.24 S/1.32 S/7.65 S/2,632.61 S/30.61 S/450.35 S/517.56 S/1,511.28 S/122.81 S/1,894.53 S/286.99 S/393.59 S/596.28 S/617.66
S/201.96 S/23.76 S/166.32 S/23.76 S/137.70 S/47,386.98 S/550.94 S/8,106.26 S/9,316.13 S/27,203.09 S/2,210.58 S/34,101.48 S/5,165.85 S/7,084.69 S/10,733.02 S/11,117.92
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/0.00
ABRIL
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/1,840.39 S/0.65 S/0.65 S/0.65 S/3.25 S/0.42 S/10.08 S/5.18 S/16.65 S/2.88 S/0.52 S/0.52 S/0.52 S/2.17 S/0.93 S/1.82
S/1,840.39 S/0.65 S/0.65 S/0.65 S/3.25 S/0.42 S/10.08 S/5.18 S/16.65 S/2.88 S/0.52 S/0.52 S/0.52 S/2.17 S/0.93 S/1.82
S/33,127.02 S/11.70 S/11.70 S/11.70 S/58.50 S/7.56 S/181.44 S/93.24 S/299.70 S/51.84 S/9.36 S/9.36 S/9.36 S/39.06 S/16.74 S/32.76
S/0.00
S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/4,210.70 S/4,210.70 S/0.00 S/289.97 S/289.97 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/2.60 S/1.26 S/912.04 S/877.61 S/923.57 S/723.85 S/199.71 S/3,062.19 S/117.35 S/0.31 S/3.69 S/0.96 S/2.07 S/14.25 S/14.99 S/0.39
S/2.60 S/1.26 S/912.04 S/877.61 S/461.78 S/361.93 S/99.86 S/3,392.04 S/447.20 S/3.09 S/36.86 S/9.57 S/20.65 S/142.51 S/149.94 S/3.88
S/46.80 S/22.68 S/16,416.63 S/15,796.89 S/7,850.32 S/6,152.76 S/1,697.56 S/92,182.80 S/8,342.78 S/58.18 S/692.93 S/179.87 S/388.24 S/2,679.11 S/2,818.83 S/72.97
S/0.00
S/0.00
S/0.00
S/0.00
S/36.65 S/36.65 S/0.31 S/3.69 S/0.96 S/2.07 S/14.25 S/14.99 S/0.39
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00 S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/151.02 S/138.95 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00 S/5.86 S/74.84 S/2,944.84 S/63.79 S/30.72 S/113.47 S/79.76 S/18.55 S/95.00 S/206.51 S/131.71 S/319.81 S/26.76 S/179.41
S/0.00 S/0.00 S/5.86 S/74.84 S/2,944.84 S/63.79 S/30.72 S/113.47 S/79.76 S/18.55 S/95.00 S/206.51 S/131.71 S/319.81 S/26.76 S/179.41
S/0.00 S/0.00 S/105.48 S/1,347.17 S/83,840.02 S/1,148.13 S/552.87 S/2,042.37 S/1,435.73 S/333.95 S/1,710.07 S/3,717.18 S/2,370.71 S/5,756.65 S/481.73 S/3,229.31
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/55.48 S/271.14 S/186.46 S/188.71 S/113.45 S/42.90 S/49.65 S/281.14 S/365.42 S/125.00
S/55.48 S/271.14 S/186.46 S/188.71 S/113.45 S/42.90 S/49.65 S/281.14 S/365.42 S/125.00
S/998.59 S/4,880.43 S/3,356.32 S/3,396.82 S/2,042.17 S/772.22 S/893.77 S/5,060.43 S/6,577.63 S/2,250.00 S/1,688.66 S/9,266.31 S/3,736.64 S/6,295.08 S/1,019.39 S/160.69
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/1,004.21 S/1,004.21 S/244.34 S/86.57 S/180.19 S/111.56 S/62.86 S/213.67 S/105.02 S/0.00
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/17,511.27 S/1,215.62 S/295.78 S/104.79 S/218.13 S/135.04 S/76.09 S/258.65 S/127.14 S/16,295.65 S/765.42
S/5,665.60 S/0.00
S/6,120.12 S/1,910.06 S/613.60 S/6.20 S/16.20 S/125,814.54 S/0.00
S/5,665.60 S/382.71
S/125,814.54 S/6,506.07
S/79,877.63 S/0.00
S/79,877.63
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/315.07 S/321.78 S/1,596.11 S/371.72 S/366.32 S/1,413.97 S/959.44 S/160.58 S/269.11 S/832.16 S/325.36 S/1,118.77 S/385.97 S/340.36 S/2,192.54 S/1,158.64
S/157.54 S/160.89 S/532.04 S/123.91 S/122.11 S/471.32 S/319.81 S/53.53 S/89.70 S/277.39 S/108.45 S/372.92 S/128.66 S/113.45 S/730.85 S/386.21
S/2,678.10 S/2,735.13 S/8,512.56 S/1,982.50 S/1,953.70 S/7,541.18 S/5,117.02 S/856.42 S/1,435.25 S/4,438.16 S/1,735.26 S/5,966.78 S/2,058.53 S/1,815.26 S/11,693.57 S/6,179.42
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/69,212.72 S/5,537.02 S/4,844.89 S/79,594.63
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/11,145.11 S/891.61 S/780.16 S/12,816.88
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/2,145.73 S/750.00 S/506.60
S/15,482.50 S/1,238.60 S/1,083.78 S/17,804.88
S/47,029.57 S/3,762.37 S/3,292.07 S/54,084.01
S/715.24 S/250.00 S/168.87
S/47,604.82 S/3,808.39 S/3,332.34 S/54,745.55
S/11,443.90 S/4,000.00 S/2,701.86 S/13,713.79 S/11,838.39 S/1,681.49 S/472.13 S/96.41 S/2,256.04 S/2,856.04 S/1,146.04 S/403.55 S/592,856.28 S/47,428.50 S/41,499.94 S/681,784.72
S/31,998.83 S/27,622.92 S/3,923.47 S/1,101.64 S/224.97 S/5,264.08 S/6,664.08 S/2,674.08 S/403.55 S/101,338.85 S/8,107.11 S/7,093.72 S/116,539.68
LERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. SANITARIAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/77,286.38 S/13,911.55
S/12,445.19 S/2,240.13
S/17,288.54 S/3,111.94
S/52,515.57 S/9,452.80
S/53,157.92 S/9,568.43
S/662,012.94 S/119,162.33
S/113,160.03 S/20,368.81
S/91,197.93
S/14,685.32
S/20,400.48
S/61,968.37
S/62,726.35
S/781,175.27
S/133,528.84
7.82%
1.26%
1.75%
5.32%
5.38%
67.01%
11.45%
7.82%
9.08%
10.83%
16.15%
21.53%
88.55%
100.00%
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00
S/0.00
S/133,520.31 S/39,879.71 S/27,105.12 S/856.00 S/11,918.59 S/74,964.50 S/1,880.07 S/1,420.83 S/1,675.17 S/8,770.59 S/2,875.90 S/4,247.66 S/23,171.69 S/30,922.59 S/4,967.72 S/85.95
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/208.65 S/219.30 S/615.60 S/339.30 S/242.42 S/36.00 S/79.20 S/41.40 S/114.75 S/503.10 S/230.40 S/23.72 S/110.40 S/84.06 S/24.88 S/9.60
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/31.80 S/13.80 S/12.90 S/51.00 S/16.05 S/116.10 S/10.80 S/490.20 S/51.60 S/180.60 S/11.85 S/699.15 S/8.70 S/283.05 S/21.39 S/12,315.30
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00
S/0.00
S/1,809.00 S/6,596.00 S/601.60 S/559.32 S/2,749.38 S/1,393.08 S/1,393.08 S/107,543.57 S/30,964.41 S/6,656.40 S/20,406.36 S/3,901.65 S/55,978.19 S/7,533.83 S/11,406.63 S/21,089.43
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/15,948.30 S/18,963.72 S/1,961.18 S/2,056.66 S/13,750.05 S/1,195.83 S/1,637.25 S/1,637.25 S/11,446.17 S/8,215.38 S/3,230.79 S/303,322.90 S/154,199.20 S/5,300.68 S/17,697.94 S/25,979.25
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/36,756.64 S/34,643.99 S/25,362.34 S/8,458.36 S/8,326.80 S/65.00 S/650.00 S/770.00 S/51.00 S/480.00 S/960.00 S/27.40 S/762.00 S/25.40 S/346.80 S/36.80
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/92.00 S/302.40 S/172.80 S/86.40 S/193.20 S/128.80 S/761.60 S/108.80 S/284.40 S/142.20 S/100.80 S/352.80 S/96.00 S/96.00 S/602.00 S/17.20
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/224.40 S/26.40 S/184.80 S/26.40 S/153.00 S/52,652.20 S/612.15 S/9,006.95 S/10,351.25 S/30,225.65 S/2,456.20 S/37,890.53 S/5,739.84 S/7,871.87 S/11,925.58 S/12,353.24
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/36,807.80 S/13.00 S/13.00 S/13.00 S/65.00 S/8.40 S/201.60 S/103.60 S/333.00 S/57.60 S/10.40 S/10.40 S/10.40 S/43.40 S/18.60 S/36.40
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/52.00 S/25.20 S/18,240.70 S/17,552.10 S/13,446.37 S/11,449.24 S/1,997.13 S/98,963.65 S/9,233.96 S/61.89 S/737.16 S/191.36 S/413.02 S/2,850.12 S/2,998.76 S/77.63
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/151.02 S/138.95 S/117.20 S/1,496.85 S/89,729.69 S/1,275.70 S/614.30 S/2,269.30 S/1,595.25 S/371.05 S/1,900.08 S/4,130.20 S/2,634.12 S/6,396.28 S/535.26 S/3,588.12
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/1,109.54 S/5,422.70 S/3,729.24 S/3,774.24 S/2,269.08 S/858.02 S/993.08 S/5,622.70 S/7,308.48 S/2,500.00 S/1,688.66 S/9,266.31 S/3,736.64 S/6,295.08 S/1,019.39 S/160.69
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00
S/6,120.12 S/1,910.06 S/613.60 S/6.20 S/16.20 S/229,873.25 S/2,219.83 S/540.12 S/191.36 S/398.32 S/246.60 S/138.95 S/472.32 S/232.16 S/227,653.42 S/7,654.20
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/3,150.70 S/3,217.80 S/10,640.70 S/2,478.12 S/2,442.12 S/9,426.48 S/6,396.28 S/1,070.52 S/1,794.06 S/5,547.70 S/2,169.08 S/7,458.48 S/2,573.16 S/2,269.08 S/14,616.96 S/7,724.28
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00 S/0.00
S/14,304.88 S/5,000.00 S/3,377.32 S/45,712.62 S/39,461.31 S/5,604.96 S/1,573.77 S/321.38 S/7,520.12 S/9,520.12 S/3,820.12 S/807.10 S/884,669.85 S/70,773.59 S/61,926.89 S/1,017,370.33
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/987,866.55 S/177,815.98
S/0.00
S/1,165,682.53
0.00% 100.00%
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01 1.01 01.01.01 1.02 01.02.01 01.02.01.01 01.02.01.02 01.02.01.03 01.02.01.04 01.02.01.05 01.02.01.06 01.02.02 01.02.02.01 01.02.02.02 01.02.02.03
SS.HH. Y VESTUARIOS MUJERES INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra Salida para interruptores simples Salida para interruptores triples Salida para interruptores dobles Salida para secadora de manos Tablero De Distribución TABLERO DE DISTRIBUCION DE 18 POLOS INTERRUPTOR TERMOMAGNETICO 3x100A INTERRUPTOR TERMOMAGNETICO 2x20A
glb
METRADO
2.00
C. Unit.
1,600.00
und und und und und und
48.00 14.00 6.00 2.00 4.00 2.00
108.75 137.52 76.24 93.24 84.24 116.85
pza pza pza
2.00 2.00 6.00
219.34 201.26 69.95
S/24,441.94 S/3,200.00 S/3,200.00 S/21,241.94 S/8,359.86 S/5,220.00 S/1,925.28 S/457.44 S/186.48 S/336.96 S/233.70 S/2,769.12 S/438.68 S/402.52 S/419.70
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
01.02.02.04 01.02.02.05 01.02.03
INTERRUPTOR TERMOMAGNETICO 2x25 A Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
pza und
01.02.03.01
Luminaria adosada a techo con rejilla de aluminio y 2 lámparas fluorescente compactas de 18w josfel o similar
und
28.00
209.02
01.02.03.02
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar Josfel modelo le-at.
und
20.00
213.02
02 2.01 02.01.01
SS.HH. Y VESTUARIOS HOMBRES INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores
2.02
Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles
02.02.01 02.02.01.01 02.02.01.02
Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra
glb
und und
6.00 12.00
2.00
44.00 14.00
80.95 85.21
S/485.70 S/1,022.52 S/10,112.96 S/5,852.56
31 dias
S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
1,600.00
S/4,260.40 S/23,623.90 S/3,200.00 S/3,200.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
108.75 137.52
S/20,423.90 S/7,619.90 S/4,785.00 S/1,925.28
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
02.02.01.03 02.02.01.04 02.02.01.05 02.02.01.06 02.02.02 02.02.02.01 02.02.02.02 02.02.02.03 02.02.02.04 02.02.02.05 02.02.03
Salida para interruptores simples Salida para interruptores triples Salida para interruptores dobles Salida para secadora de manos Tablero De Distribución Tablero de 24 polos Interuptores termomagnèticos trifàsicos de 3x32Amp INTERRUPTOR TERMOMAGNETICO 2x20A INTERRUPTOR TERMOMAGNETICO 2x25 A Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
und und und und
2.00 2.00 4.00 2.00
76.24 93.24 84.24 116.85
und und pza pza und
2.00 2.00 6.00 6.00 12.00
493.34 306.26 69.95 80.95 85.21
02.02.03.01
Luminaria adosada a techo con rejilla de aluminio y 2 lámparas fluorescente compactas de 18w josfel o similar
und
24.00
209.02
S/152.48 S/186.48 S/336.96 S/233.70 S/3,527.12 S/986.68 S/612.52 S/419.70 S/485.70 S/1,022.52 S/9,276.88 S/5,016.48
31 dias
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.02.03.02 03 3.01 03.01.01 3.02 03.02.01 03.02.01.01 03.02.01.02 03.02.01.03 03.02.02 03.02.02.01 03.02.02.02 03.02.02.03
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar Josfel modelo le-at. SS.HH. DE HOMBRES Y MUJERES INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles Salidas Salida para artefacto. Adosado en techo Salida para secadora de manos Salida para interruptores simples Tablero De Distribución TABLERO DE DISTRIBUCION DE 12 POLOS INTERRUPTOR TERMOMAGNETICO 3x40A INTERRUPTOR TERMOMAGNETICO 2x20A
und
glb
und und und pza pza pza
METRADO
20.00
2.00
16.00 4.00 8.00 2.00 2.00 4.00
C. Unit.
213.02
1,600.00
108.75 116.85 76.24 193.34 119.76 69.95
S/4,260.40 S/11,021.75 S/3,200.00 S/3,200.00 S/7,821.75 S/2,817.32 S/1,740.00 S/467.40 S/609.92 S/1,660.11 S/386.68 S/239.52 S/279.80
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
03.02.02.04 03.02.02.05 03.02.03
INTERRUPTOR TERMOMAGNETICO 2x25 A Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
pza und
3.00 6.00
80.95 85.21
03.02.03.01
Luminaria adosada a techo con rejilla de aluminio y 2 lámparas fluorescente compactas de 18w josfel o similar
und
16.00
209.02
04 4.01 04.01.01 4.02 04.02.01 04.02.01.01 04.02.01.02 04.02.01.03 04.02.02 04.02.02.01
SS.HH. NIÑOS Y NIÑAS INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra Salida para interruptores simples Tablero De Distribución Tablero de 12 polos
glb
1.00
1,600.00
und und und
6.00 3.00 4.00
108.75 137.52 76.24
und
1.00
193.34
31 dias
S/242.85 S/511.26 S/3,344.32
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/3,344.32 S/4,827.06 S/1,600.00 S/1,600.00 S/3,227.06 S/1,370.02 S/652.50 S/412.56 S/304.96 S/602.92 S/193.34
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
04.02.02.02 04.02.02.03 04.02.02.04 04.02.03
INTERRUPTOR TERMOMAGNETICO 3x30A Interuptores termomagnèticos monofàsicos de 2x20Amp Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
pza und und
1.00 2.00 2.00
99.26 69.95 85.21
04.02.03.01
Luminaria adosada a techo con rejilla de aluminio y 2 lámparas fluorescente compactas de 18w josfel o similar
und
6.00
209.02
05 5.01 05.01.01 5.02 05.02.01 05.02.01.01 05.02.01.02 05.02.01.03 05.02.01.04
TOPICO INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra Salida para interruptores simples Salida para interruptores triples
glb
1.00
1,600.00
und und und und
5.00 5.00 1.00 1.00
108.75 137.52 76.24 93.24
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/99.26 S/139.90 S/170.42 S/1,254.12
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/1,254.12 S/4,652.85 S/1,600.00 S/1,600.00 S/3,052.85 S/1,400.83 S/543.75 S/687.60 S/76.24 S/93.24
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
05.02.02 05.02.02.01 05.02.02.02 05.02.02.03 05.02.02.04 05.02.03
Tablero De Distribución Tablero de 12 polos INTERRUPTOR TERMOMAGNETICO 3x30A Interuptores termomagnèticos monofàsicos de 2x20Amp Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
und pza und und
1.00 1.00 2.00 2.00
193.34 99.26 69.95 85.21
05.02.03.01
Luminaria adosada a techo con rejilla de aluminio y 2 lámparas fluorescente compactas de 18w josfel o similar
und
4.00
209.02
05.02.03.02
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar Josfel modelo le-at.
und
1.00
213.02
06 6.01 06.01.01
BOLETERIA INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores
6.02
Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles
glb
1.00
1,600.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/602.92 S/193.34 S/99.26 S/139.90 S/170.42 S/1,049.10
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/836.08
S/0.00
S/0.00
S/213.02 S/4,828.10 S/1,600.00 S/1,600.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/3,228.10
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.02.01 06.02.01.01 06.02.01.02 06.02.01.03 06.02.01.04 06.02.02 06.02.02.01 06.02.02.02 06.02.02.03 06.02.02.04 06.02.03
Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra Salida para interruptores simples Salida para interruptores dobles Tablero De Distribución Tablero de 12 polos INTERRUPTOR TERMOMAGNETICO 3x30A Interuptores termomagnèticos monofàsicos de 2x20Amp Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
06.02.03.01
Luminaria adosada a techo con rejilla de aluminio y 2 lámparas fluorescente compactas de 18w josfel o similar
METRADO
C. Unit.
und und und und
6.00 4.00 1.00 1.00
108.75 137.52 76.24 84.24
und pza und und
1.00 1.00 2.00 2.00
193.34 99.26 69.95 85.21
und
4.00
209.02
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/1,363.06 S/652.50 S/550.08 S/76.24 S/84.24 S/602.92 S/193.34 S/99.26 S/139.90 S/170.42 S/1,262.12
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/836.08
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.02.03.02
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar josfel modelo le-at.
07
CUARTO DE MAQ. USO DOMESTICO Y CTO. DE INSUMOS QUIMICOS
7.01 07.01.01
INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores
7.02
Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles
07.02.01 07.02.01.01 07.02.01.02 07.02.01.03 07.02.01.04 07.02.01.05
Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra p/agua Salida para interruptores simples Salida de fuerza para electrobombas 3HP Salida de fuerza para electrobombas 1HP
und
glb
und und und und und
METRADO
2.00
1.00
4.00 2.00 2.00 3.00 6.00
C. Unit.
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
213.02 S/426.04
S/0.00
S/0.00
1,600.00
S/15,570.22 S/1,600.00 S/1,600.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
108.75 137.52 76.24 152.88 147.38
S/13,970.22 S/2,205.44 S/435.00 S/275.04 S/152.48 S/458.64 S/884.28
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
07.02.02 07.02.02.01 07.02.02.02 07.02.02.03 07.02.02.04 07.02.02.05 07.02.03 07.02.03.01 07.02.03.02 07.02.03.03 07.02.04 07.02.04.01 07.02.04.02 07.02.04.03 07.02.05
Tablero De Distribución TD-11 TABLERO DE DISTRIBUCION 16 POLOS INTERRUPTOR TERMOMAGNETICO 3x50A Interuptores termomagnèticos trifàsicos de 3x40Amp Interuptores termomagnèticos monofàsicos de 2x20Amp Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial Tablero De Fuerza TF-3 Tablero de 18 polos INTERRUPTOR TERMOMAGNETICO 3x40A Interuptores termomagnèticos trifàsicos de 3x25Amp Tablero De Cotrol y Protección Tablero de Cotrol y Protección TB-1 (Electrobomba 1HP) Tablero de Cotrol y Protección TB-2 (Electrobomba 3HP) Tablero de Cotrol y Protección TB-3 (Electrobomba 3HP) Tablero De Fuerza TF-4
METRADO
C. Unit.
pza pza und und und
1.00 1.00 2.00 2.00 2.00
213.34 136.86 119.76 69.95 85.21
und pza und
1.00 1.00 1.00
219.34 119.76 91.51
und und und
1.00 1.00 1.00
1,080.03 1,990.03 1,990.03
S/900.04 S/213.34 S/136.86 S/239.52 S/139.90 S/170.42 S/430.61 S/219.34 S/119.76 S/91.51 S/5,060.09 S/1,080.03 S/1,990.03 S/1,990.03 S/542.95
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
07.02.05.01 07.02.05.02 07.02.05.03 07.02.06 07.02.06.01 07.02.06.02 07.02.06.03 07.02.07 07.02.07.01 07.02.07.02 07.02.07.03 07.02.07.04 07.02.08
TABLERO DE DISTRIBUCION 16 POLOS INTERRUPTOR TERMOMAGNETICO 3x40A Interuptores termomagnèticos monofàsicos de 2x20Amp Tablero De Cotrol y Protección Tablero de Cotrol y Protección TB-4 (Electrobombas 1 HP) Tablero de Cotrol y Protección TB-5 (Electrobombas 1 HP) Tablero de Cotrol y Protección TB-6 (Electrobomba 1 HP) Tablero De Distribución TD-12 Tablero de 18 polos INTERRUPTOR TERMOMAGNETICO 3x30A Interuptores termomagnèticos monofàsicos de 2x20Amp Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial ILUMINACION
METRADO
C. Unit.
pza pza und
1.00 1.00 3.00
213.34 119.76 69.95
und und und
1.00 1.00 1.00
1,080.03 1,080.03 1,080.03
und pza und und
1.00 1.00 2.00 2.00
219.34 99.26 69.95 85.21
S/213.34 S/119.76 S/209.85 S/3,240.09 S/1,080.03 S/1,080.03 S/1,080.03 S/628.92 S/219.34 S/99.26 S/139.90 S/170.42 S/962.08
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
Luminaria industrial hermética con 2 lámparas fluorescentes de 36w de alta eficiencia, 220vca, 60 hz, adosado a pared, alto factor de potencia, similar a josfel und modelo AHR-Z.
2.00
07.02.08.02
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar josfel modelo le-at.
2.00
08 8.01 08.01.01 8.02 08.02.01 08.02.01.01 08.02.01.02 08.02.01.03 08.02.01.04
CUARTO DE MAQUINAS II Y CISTERNA DE COMPENSACION INSTALACIONES ELECTRICAS Y MECANICAS Conexión A La Red Externa De Medidores Salidas Para Alumbrado, Tomacorrientes, Fuerza y Señales Debiles Salidas Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra p/agua Salida para interruptores simples Salida para interruptores dobles
07.02.08.01
und
C. Unit.
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
268.02 S/536.04
S/0.00
S/0.00
S/426.04 S/19,638.37 S/1,600.00 S/1,600.00 S/18,038.37 S/3,360.89 S/1,522.50 S/275.04 S/76.24 S/168.48
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
213.02
glb
1.00
1,600.00
und und und und
14.00 2.00 1.00 2.00
108.75 137.52 76.24 84.24
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
08.02.01.05 08.02.01.06 08.02.01.07 08.02.02 08.02.02.01 08.02.02.02 08.02.02.03 08.02.02.04 08.02.02.05 08.02.02.06 08.02.03 08.02.03.01 08.02.03.02 08.02.03.03 08.02.03.04
Salida de fuerza para electrobombas 10HP Salida de fuerza para electrobombas 5HP Salida de fuerza para electrobombas 1HP Tablero De Distribución Tablero de 18 polos INTERRUPTOR TERMOMAGNETICO 3x100A INTERRUPTOR TERMOMAGNETICO 3x60A INTERRUPTOR TERMOMAGNETICO 3x50A Interuptores termomagnèticos monofàsicos de 2x20Amp Interuptores termomagnèticos monofàsicos de 2x25Amp - Diferencial Tablero De Fuerza TF-1 Tablero de 12 polos INTERRUPTOR TERMOMAGNETICO 3x60A INTERRUPTOR TERMOMAGNETICO 3x50A Interuptores termomagnèticos monofàsicos de 2x20Amp
METRADO
C. Unit.
und und und
3.00 3.00 2.00
179.41 161.88 147.38
und pza pza pza und und
1.00 1.00 1.00 1.00 2.00 2.00
219.34 201.26 181.26 136.86 69.95 85.21
und pza pza und
1.00 1.00 3.00 1.00
193.34 181.26 136.86 69.95
S/538.23 S/485.64 S/294.76 S/1,049.04 S/219.34 S/201.26 S/181.26 S/136.86 S/139.90 S/170.42 S/855.13 S/193.34 S/181.26 S/410.58 S/69.95
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
08.02.04 08.02.04.01 08.02.04.02 08.02.04.03 08.02.04.04 08.02.05 08.02.05.01 08.02.05.02 08.02.05.03 08.02.06
Tablero De Fuerza TF-2 Tablero de 12 polos INTERRUPTOR TERMOMAGNETICO 3x50A Interuptores termomagnèticos trifàsicos de 3x40Amp INTERRUPTOR TERMOMAGNETICO 2x25 A Tablero De Cotrol y Protección Tablero de Control y Protección TB-1 y TB-4 (Electrobomba 1HP) Tablero de Control y Protección TB-2 (Electrobomba 10HP) Tablero de Control y Protección TB-3 (Electrobomba 5HP) ILUMINACION
08.02.06.01
08.02.06.02
METRADO
C. Unit.
und pza und pza
1.00 1.00 1.00 1.00
193.34 136.86 119.76 80.95
und und und
2.00 1.00 1.00
1,080.03 4,380.03 2,280.03
Luminaria industrial hermética con 2 lámparas fluorescentes de 36w de alta eficiencia, 220vca, 60 hz, adosado a pared, alto factor de potencia, similar a josfel und modelo AHR-Z.
8.00
268.02
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar josfel modelo le-at.
6.00
und
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/530.91 S/193.34 S/136.86 S/119.76 S/80.95 S/8,820.12 S/2,160.06 S/4,380.03 S/2,280.03 S/3,422.28
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/2,144.16
S/0.00
S/0.00
S/1,278.12
S/0.00
S/0.00
213.02
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
09 9.01 09.01.01
ALIMENTADORES REDES GENERALES Alimentadores
09.01.01.01
TG-1 A ST-1 3x70mm2(N2XOH)+1x70mm2(N2XOH)(N)+1x16mm2(NH-80)(T)65mm PVC-P
m
70.00
101.77
09.01.01.02
TG-1 A TD-11 3x35mm2(NH-80)+1x35mm2(NH-80)(N)+1x16mm2(NH-80)(T)40mm PVC-P
m
155.00
79.31
09.01.01.03
TG-1 A TD-3 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x6mm2(NH-80)(T)-25mm PVC-P
m
50.00
36.48
09.01.01.04
TG-1 A TD-5 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x4mm2(NH-80)(T)-25mm PVC-P
m
55.00
59.92
09.01.01.05
TG-1 A TD-6 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x4mm2(NH-80)(T)-25mm PVC-P
m
35.00
59.92
09.01.01.06
TG-1 A TD-8 3-1x10mm2(NHX)+1x6mm2(NHX)(N)+1x6mm2(NHX) (T)-25mm? PVC-P
m
80.00
63.08
09.01.01.07
TG-1 A TD-11 3-1x10mm2(NHX)+1x6mm2(NHX)(N)+1x6mm2(NHX) (T)-25mm? PVC-P
m
60.00
63.08
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/176,527.04 S/81,372.27 S/70,527.42
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/7,123.90
S/0.00
S/0.00
S/12,293.05
S/0.00
S/0.00
S/1,824.00
S/0.00
S/0.00
S/3,295.60
S/0.00
S/0.00
S/2,097.20
S/0.00
S/0.00
S/5,046.40
S/0.00
S/0.00
S/3,784.80
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
09.01.01.08
ST-1 A ST-2 3x70mm2(N2XOH)+1x70mm2(N2XOH)(N)+1x16mm2(NH-80)(T)65mm PVC-P
m
75.00
101.77
09.01.01.09
ST-1 A ST-4 3x16mm2(NH-80)+1x16mm2(NH-80)(N)+1x6mm2(NH-80)(T)-35mm PVC-P
m
50.00
68.52
09.01.01.10
ST-2 A ST-3 3x50mm2(N2XOH)+1x50mm2(N2XOH)(N)+1x16mm2(NH-80)(T)50mm PVC-P
m
70.00
68.16
09.01.01.11
ST-2 A TD-7 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x6mm2(NH-80)(T)-25mm PVC-P
m
65.00
60.44
09.01.01.12
ST-3 A TD-9 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x6mm2(NH-80)(T)-25mm PVC-P
m
30.00
60.44
09.01.01.13
ST-3 A TD-10 3x50mm2(NH-80)+1x50mm2(NH-80)(N)+1x10mm2(NH-80)(T)65mm PVC-P
m
75.00
70.59
09.01.01.14
ST-3 A TD-12 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x6mm2(NH-80)(T)-25mm PVC-P
m
83.00
60.44
09.01.01.15
TD-1 A TD-2 3x10mm2(NH-80)+1x10mm2(NH-80)(N)+1x6mm2(NH-80)(T)-25mm m PVC-P
25.00
54.67
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/7,632.75
S/0.00
S/0.00
S/3,426.00
S/0.00
S/0.00
S/4,771.20
S/0.00
S/0.00
S/3,928.60
S/0.00
S/0.00
S/1,813.20
S/0.00
S/0.00
S/5,294.25
S/0.00
S/0.00
S/5,016.52
S/0.00
S/0.00
S/1,366.75
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
09.01.01.16
TD-1 A TD-4 3x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x6mm2(NH-80)(T)-25mm PVC-P
09.01.02 09.01.02.01 09.01.02.02 09.01.02.03 09.01.02.04 09.01.02.05 09.01.02.06 09.01.02.07 09.01.02.08 09.01.03 09.01.03.01 09.01.03.02 09.01.03.03
Tablero General TG-1 Tablero Autosoporttado de 36 polos 380/220V 3?- 4 Hilos Interuptores termomagnèticos trifàsicos de 3x450Amp INTERRUPTOR TERMOMAGNETICO 3x250A INTERRUPTOR TERMOMAGNETICO 3x100A INTERRUPTOR TERMOMAGNETICO 3x30A INTERRUPTOR TERMOMAGNETICO 3x40A INTERRUPTOR TERMOMAGNETICO 2x30A INTERRUPTOR TERMOMAGNETICO 3x50A Tablero De Distribución ST-1 Tablero de 14 polos 380/220V 3?- 4 Hilos INTERRUPTOR TERMOMAGNETICO 3x250A INTERRUPTOR TERMOMAGNETICO 3x200A
m
METRADO
C. Unit.
30.00
60.44
pza und pza pza pza pza pza pza
1.00 1.00 1.00 1.00 3.00 1.00 1.00 1.00
4,367.34 486.26 251.26 201.26 99.26 119.76 100.95 136.86
pza pza pza
1.00 1.00 1.00
200.84 251.26 233.76
S/1,813.20 S/5,961.47 S/4,367.34 S/486.26 S/251.26 S/201.26 S/297.78 S/119.76 S/100.95 S/136.86 S/1,318.27 S/200.84 S/251.26 S/233.76
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
09.01.03.04 09.01.03.05 09.01.03.06 09.01.04 09.01.04.01 09.01.04.02 09.01.04.03 09.01.04.04 09.01.04.05 09.01.04.06 09.01.05 09.01.05.01 09.01.05.02 09.01.05.03 09.01.05.04
INTERRUPTOR TERMOMAGNETICO 3x60A INTERRUPTOR TERMOMAGNETICO 3x30A INTERRUPTOR HORARIO DIGITAL Tablero De Distribución ST-2 Tablero de 14 polos 380/220V 3?- 4 Hilos INTERRUPTOR TERMOMAGNETICO 3x200A INTERRUPTOR TERMOMAGNETICO 3x150A INTERRUPTOR TERMOMAGNETICO 2x30A INTERRUPTOR TERMOMAGNETICO 3x30A INTERRUPTOR HORARIO DIGITAL Tablero De Distribución ST-3 TABLERO DE DISTRIBUCION 16 POLOS INTERRUPTOR TERMOMAGNETICO 3x150A Interuptor termomagnètico trifàsico de 3x100Amp INTERRUPTOR TERMOMAGNETICO 2x30A
METRADO
C. Unit.
pza pza pza
1.00 1.00 1.00
181.26 99.26 351.89
pza pza pza pza pza pza
1.00 1.00 2.00 1.00 1.00 1.00
200.84 233.76 226.26 100.95 99.26 351.89
pza pza und pza
1.00 1.00 2.00 1.00
213.34 226.26 201.26 100.95
S/181.26 S/99.26 S/351.89 S/1,439.22 S/200.84 S/233.76 S/452.52 S/100.95 S/99.26 S/351.89 S/1,493.48 S/213.34 S/226.26 S/402.52 S/100.95
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
09.01.05.05 09.01.05.06 09.01.06 09.01.06.01 09.01.06.02 09.01.06.03 9.02
INTERRUPTOR TERMOMAGNETICO 3x30A INTERRUPTOR HORARIO DIGITAL Tablero De Distribución ST-4 Interuptor termomagnètico trifàsico de 3x60Amp INTERRUPTOR TERMOMAGNETICO 3x30A INTERRUPTOR HORARIO DIGITAL ALUMBRADO EXTERIOR PISCINA
METRADO
C. Unit.
pza pza
2.00 1.00
99.26 351.89
und pza pza
1.00 1.00 1.00
181.26 99.26 351.89
S/198.52 S/351.89 S/632.41 S/181.26 S/99.26 S/351.89 S/61,664.86
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
09.02.01 09.02.01.01 09.02.01.02 9.03 09.03.01 09.03.01.01 9.04 09.04.01 09.04.01.01 9.05 09.05.01 09.05.01.01 10 10.01
Alumbrado Luminarias tipo LED de 139 W, similar a TECEO de Schreder, en postes de CAC de 9m. Cable de 2x6mm2(NH-80)+1x6mm2(NH-80)(N)+1x4mm2(NH-80)(T)-20mm PVCP POZOS A TIERRA PAT Pozos a Tierra BUZONES BUZON DE BT Buzones de concreto CAJAS DE PASE Caja de pase alimentadores Caja de Pase 150 mm x 150 mm x 2,0 mm (espesor) SUB ESTACION MEDIA TENSION SUBESTACION DE USO EXCLUSIVO
und
METRADO
C. Unit.
13.00
4,149.22
150.00
51.50
und
5.00
2,196.65
und
12.00
1,806.71
und
7.00
118.02
m
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/61,664.86
S/0.00
S/0.00
S/53,939.86
S/0.00
S/0.00
S/7,725.00 S/10,983.25 S/10,983.25 S/10,983.25 S/21,680.52 S/21,680.52 S/21,680.52 S/826.14 S/826.14 S/826.14 S/170,971.02 S/105,374.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
10.01.01
(PMI) POSTE DE MEDICION EN LA INTEMPERIE (CONCESIONARIA)
C. Unit.
1.00
25,000.00
10.01.02
TRANSFORMADOR DE DISTRIBUCION, TRIFASICO DE 150 KVA, 22.9-10/0.38-0,22 und KV, 60HZ, 0-1000 m.s.n.m., CON RUEDAS Y RIELES.
1.00
24,000.00
10.01.03 10.01.04
und und
1.00 1.00
und und
10.02
CELDA DE LLEGADA CON PUERTA CHAPA Y ACCESORIOS CELDA DE TRANSFORMACION CON PUERTA CHAPA Y ACCESORIOS SECCIONADOR DE POTENCIA TRIPOLAR DE APERTURA CON CARGA TRIFASICO, 24KV, 175KV BIL, 400A SECCIONADOR UNIPOLAR APERTURA SIN CARGA, 400A, 24KV, ACCES. FIJACIÓN, USO INTERIOR ACOMETIDA DE ALIMENTACION EN M.T.
10.02.01
CONDUCTOR TIPO 3 - 1x 35 mm2 (N2XSY) 30KV CON TERMINAL DE MEDIA TENSIÓN
m
10.03 10.03.01 10.04
SISTEMA DE PUESTA A TIERRA S.E. POZO DE PUESTA ATIERRA PARA SUB ESTACION PRUEBAS DE CIRCUITOS Y PUESTA EN SERVICIO
10.04.01
PRUEBA Y PUESTA EN SERVICIO (AISLAMIENTO, CONTINUIDAD, RESISTENCIA DE POZO A TIERRA, CON TENSION)
10.01.05 10.01.06
glb
METRADO
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/25,000.00
S/0.00
S/0.00
12,520.00 20,352.00
S/24,000.00 S/12,520.00 S/20,352.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
1.00
12,850.00
S/12,850.00
S/0.00
S/0.00
1.00
10,652.00
S/10,652.00 S/31,500.00
S/0.00 S/0.00
S/0.00 S/0.00
360.00
87.50
und
2.00
3,734.65
S/31,500.00 S/7,469.30 S/7,469.30 S/2,500.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
glb
1.00
2,500.00
S/2,500.00
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
METRADO
C. Unit.
10.05
OTROS
10.05.01
ELABORACION Y APROBACION POR ELECTROCENTRO S.A. DE EXPEDIENTE TECNICO DEL SUBESTACION DE USO EXCLUSIVO
glb
1.00
15,000.00
10.05.02
PAGO POR DERECHO DE CORTE DE ENERGIA
glb
1.00
3,500.00
10.06
SALIDAS PARA ALUMBRADO, TOMACORRIENTES, FUERZA Y SEÑALES DEBILES
10.06.01 10.06.02 10.06.03 10.06.04 10.06.05 10.12
Salida para artefacto. Adosado en techo Salida para tomacorriente bipolar con toma a tierra p/agua Salida para interruptores simples Salida de fuerza para electrobombas 3HP Salida de fuerza para electrobombas 1HP ILUMINACION
und und und und und
4.00 2.00 2.00 3.00 6.00
108.75 137.52 76.24 152.88 147.38
10.12.01
Luminaria industrial hermética con 2 lámparas fluorescentes de 36w de alta eficiencia,220vca, 60 hz, adosado a pared, alto factor de potencia, similar a josfel und modelo AHR-Z.
8.00
268.02
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/18,500.00
S/0.00
S/0.00
S/15,000.00 S/3,500.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,205.44 S/435.00 S/275.04 S/152.48 S/458.64 S/884.28 S/3,422.28
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/2,144.16
S/0.00
S/0.00
E-VO-09.02
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
10.12.02
Luminaria de emergencia adosada a techo con dos lámparas fluoresc. comp. de 18w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida. Similar josfel modelo le-at.
und
METRADO
6.00
C. Unit.
Utilidad
8.00% 7.00%
Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
213.02
Costo Directo Gastos Generales
NOVIEMBRE
0.971 18.00%
S/1,278.12 456,102.25 36,488.18 31,927.16 524,517.59 509,306.56 91,675.18
S/0.00
S/0.00 0.00 0.00 0.00 0.00 0.00 0.00
600,981.74
0.00 0.00 0.00 0.00 0.00 0.00
0.00
0.00
PORCENTAJE DE AVANCE ( % )
0.00%
0.00%
PORCENTAJE ACUMULADO DE AVANCE ( % )
0.00%
0.00%
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/3,217.29 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/5,026.72 S/1,447.62 S/1,447.62
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/6,084.97 S/1,752.38 S/1,752.38
S/3,297.70 S/0.00
S/3,407.63 S/0.00
S/3,407.63 S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
S/3,217.29 S/3,217.29 S/2,610.00 S/0.00 S/228.72 S/93.24 S/168.48 S/116.85
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/3,579.10 S/2,326.40 S/1,180.71 S/870.96 S/103.47 S/42.18 S/76.22 S/52.86
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/4,332.59 S/2,816.17 S/1,429.29 S/1,054.32 S/125.25 S/51.06 S/92.26 S/63.99
S/3,297.70 S/0.00
S/3,407.63 S/0.00
S/3,407.63 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/1,252.70 S/198.45 S/182.09 S/189.86
S/0.00
S/0.00
S/0.00
S/1,516.42 S/240.23 S/220.43 S/229.84
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
S/0.00 S/0.00
MARZO
S/0.00
S/219.72 S/462.57
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
30 dias
31 dias
31 dias
S/265.98 S/559.95 S/3,297.70
S/3,407.63
S/3,407.63
S/0.00
S/1,908.44
S/1,972.06
S/1,972.06
S/0.00
S/0.00
S/1,389.26
S/1,435.57
S/1,435.57
S/1,423.66 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/5,846.28 S/1,447.62 S/1,447.62
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/7,077.08 S/1,752.38 S/1,752.38
S/3,025.07 S/0.00
S/3,125.91 S/0.00
S/3,125.91 S/0.00
S/1,423.66 S/1,423.66
S/0.00 S/0.00 S/0.00 S/0.00
S/4,398.66 S/2,803.06 S/1,623.48 S/870.96
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/5,324.70 S/3,393.18 S/1,965.27 S/1,054.32
S/3,025.07 S/0.00
S/3,125.91 S/0.00
S/3,125.91 S/0.00
S/1,196.25
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
19 dias
12 dias
30 dias
8 dias
31 dias
28 dias
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
30 dias
31 dias
31 dias
S/38.12 S/46.62 S/84.24 S/58.43
S/0.00 S/0.00 S/0.00 S/0.00
S/51.73 S/63.27 S/114.33 S/79.29
S/62.63 S/76.59 S/138.39 S/95.98
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/1,595.60 S/446.36 S/277.09 S/189.86 S/219.72 S/462.57
S/0.00
S/0.00
S/0.00
S/1,931.52 S/540.32 S/335.43 S/229.84 S/265.98 S/559.95
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/3,025.07
S/3,125.91
S/3,125.91
S/0.00
S/0.00
S/1,635.81
S/1,690.34
S/1,690.34
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/1,389.26
S/1,435.57
S/1,435.57
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/3,473.12 S/1,447.62 S/1,447.62
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/4,204.31 S/1,752.38 S/1,752.38
S/1,090.54 S/0.00
S/1,126.89 S/0.00
S/1,126.89 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/2,025.50 S/1,274.50 S/787.14 S/211.44 S/275.92
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,451.93 S/1,542.82 S/952.86 S/255.96 S/334.00
S/1,090.54 S/0.00
S/1,126.89 S/0.00
S/1,126.89 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/751.00 S/174.93 S/108.35 S/126.58
S/0.00
S/0.00
S/0.00
S/909.11 S/211.75 S/131.17 S/153.22
S/0.00
S/0.00
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
19 dias
12 dias
30 dias
8 dias
31 dias
28 dias
MARZO
ABRIL
MAYO
S/0.00 S/0.00
S/0.00 S/0.00
S/109.86 S/231.28
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/1,616.33 S/723.81 S/723.81
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/892.52 S/619.77 S/295.18 S/186.63 S/137.96
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/272.75 S/87.46
S/0.00
S/0.00
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
30 dias
31 dias
31 dias
S/132.99 S/279.98 S/0.00
S/0.00
S/0.00
S/0.00
S/1,090.54
S/1,126.89
S/1,126.89
S/1,090.54
S/1,126.89
S/1,126.89
S/1,956.61 S/876.19 S/876.19
S/408.95 S/0.00
S/422.58 S/0.00
S/422.58 S/0.00
S/0.00 S/0.00
S/1,080.42 S/750.25 S/357.32 S/225.93 S/167.00
S/408.95 S/0.00
S/422.58 S/0.00
S/422.58 S/0.00
S/0.00
S/330.17 S/105.88
S/0.00
S/0.00
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
19 dias
12 dias
30 dias
8 dias
31 dias
28 dias
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
30 dias
31 dias
31 dias
S/408.95
S/422.58
S/422.58
S/408.95
S/422.58
S/422.58
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/44.90 S/63.29 S/77.09
S/54.36 S/76.61 S/93.33
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/1,630.27 S/723.81 S/723.81
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,973.48 S/876.19 S/876.19
S/342.10 S/0.00
S/353.50 S/0.00
S/353.50 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/906.46 S/633.71 S/245.98 S/311.06 S/34.49 S/42.18
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,097.29 S/767.12 S/297.77 S/376.54 S/41.75 S/51.06
S/342.10 S/0.00
S/353.50 S/0.00
S/353.50 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/272.75 S/87.46 S/44.90 S/63.29 S/77.09
S/0.00
S/0.00
S/0.00
S/330.17 S/105.88 S/54.36 S/76.61 S/93.33
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/342.10
S/353.50
S/353.50
S/0.00
S/0.00
S/272.63
S/281.72
S/281.72
S/0.00
S/0.00
S/69.46
S/71.78
S/71.78
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/1,613.18 S/723.81 S/723.81
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,952.80 S/876.19 S/876.19
S/411.56 S/0.00
S/425.28 S/0.00
S/425.28 S/0.00
S/0.00
S/0.00
S/889.37
S/0.00
S/0.00
S/0.00
S/1,076.61
S/411.56
S/425.28
S/425.28
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/616.62 S/295.18 S/248.85 S/34.49 S/38.11
S/0.00
S/0.00
S/0.00
S/746.44 S/357.32 S/301.23 S/41.75 S/46.13
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/272.75 S/87.46 S/44.90 S/63.29 S/77.09
S/0.00
S/0.00
S/0.00
S/330.17 S/105.88 S/54.36 S/76.61 S/93.33
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/411.56
S/425.28
S/425.28
S/0.00
S/0.00
S/272.63
S/281.72
S/281.72
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/138.93
S/143.56
S/143.56
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/6,608.44 S/723.81 S/723.81
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/7,999.70 S/876.19 S/876.19
S/313.72 S/0.00
S/324.18 S/0.00
S/324.18 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/5,884.63 S/997.70 S/196.79 S/124.42 S/68.98 S/207.48 S/400.03
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/7,123.51 S/1,207.74 S/238.21 S/150.62 S/83.50 S/251.16 S/484.25
S/313.72 S/0.00
S/324.18 S/0.00
S/324.18 S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/407.16 S/96.51 S/61.91 S/108.35 S/63.29 S/77.09
S/0.00
S/0.00
S/0.00
S/492.88 S/116.83 S/74.95 S/131.17 S/76.61 S/93.33
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/194.80 S/99.23 S/54.18 S/41.40
S/0.00
S/0.00
S/0.00
S/235.81 S/120.11 S/65.58 S/50.11
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/2,289.09 S/488.59 S/900.25 S/900.25
S/0.00
S/0.00
S/0.00
S/2,771.00 S/591.45 S/1,089.78 S/1,089.78
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/245.62
S/0.00
S/0.00
S/0.00
S/297.33
S/0.00
S/0.00
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
19 dias
12 dias
30 dias
8 dias
31 dias
28 dias
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/96.51 S/54.18 S/94.93
S/116.83 S/65.58 S/114.92
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/1,465.76 S/488.59 S/488.59 S/488.59
S/0.00
S/0.00
S/0.00
S/1,774.34 S/591.45 S/591.45 S/591.45
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/284.51 S/99.23 S/44.90 S/63.29 S/77.09
S/0.00
S/0.00
S/0.00
S/344.41 S/120.11 S/54.36 S/76.61 S/93.33
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/313.72
S/324.18
S/324.18
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/174.80
S/180.62
S/180.62
S/0.00
S/0.00
S/138.93
S/143.56
S/143.56
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,899.70 S/438.10 S/438.10
S/4,610.61 S/571.43 S/571.43
S/11,974.90 S/590.48 S/590.48
S/1,153.16 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,461.61 S/336.09 S/152.25 S/27.50 S/7.62 S/16.85
S/4,039.18 S/672.18 S/304.50 S/55.01 S/15.25 S/33.70
S/11,384.42 S/2,352.62 S/1,065.75 S/192.53 S/53.37 S/117.94
S/1,153.16 S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
28 dias
19 dias
12 dias
30 dias
8 dias
31 dias
MARZO
ABRIL
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018 31 dias
30 dias
31 dias
S/53.82 S/48.56 S/29.48
23 dias
S/107.65 S/97.13 S/58.95
S/376.76 S/339.95 S/206.33
S/0.00
S/104.90 S/21.93 S/20.13 S/18.13 S/13.69 S/13.99 S/17.04
S/209.81 S/43.87 S/40.25 S/36.25 S/27.37 S/27.98 S/34.08
S/734.33 S/153.54 S/140.88 S/126.88 S/95.80 S/97.93 S/119.29
S/0.00
S/0.00
S/85.51 S/19.33 S/18.13 S/41.06 S/7.00
S/171.03 S/38.67 S/36.25 S/82.12 S/13.99
S/598.59 S/135.34 S/126.88 S/287.41 S/48.97
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/53.09 S/19.33 S/13.69 S/11.98 S/8.10
S/106.18 S/38.67 S/27.37 S/23.95 S/16.19
S/371.64 S/135.34 S/95.80 S/83.83 S/56.67
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/882.01 S/216.01 S/438.00 S/228.00
S/1,764.02 S/432.01 S/876.01 S/456.01
S/6,174.08 S/1,512.04 S/3,066.02 S/1,596.02
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,115.96
S/1,153.16
S/1,153.16
S/0.00
S/0.00
S/699.18
S/722.49
S/722.49
S/0.00
S/0.00
S/416.78
S/430.67
S/430.67
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00
ABRIL
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/13,723.04 S/9,221.71 S/7,052.74
S/37,451.54 S/21,696.88 S/14,105.48
S/122,017.30 S/49,369.19 S/49,369.19
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/3,335.15 S/1,084.49 S/0.00
S/0.00
S/0.00
S/712.39
S/1,424.78
S/4,986.73
S/0.00
S/0.00
S/1,229.31
S/2,458.61
S/8,605.14
S/0.00
S/0.00
S/182.40
S/364.80
S/1,276.80
S/0.00
S/0.00
S/329.56
S/659.12
S/2,306.92
S/0.00
S/0.00
S/209.72
S/419.44
S/1,468.04
S/0.00
S/0.00
S/504.64
S/1,009.28
S/3,532.48
S/0.00
S/0.00
S/378.48
S/756.96
S/2,649.36
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/763.28
S/1,526.55
S/5,342.93
S/0.00
S/0.00
S/342.60
S/685.20
S/2,398.20
S/0.00
S/0.00
S/477.12
S/954.24
S/3,339.84
S/0.00
S/0.00
S/392.86
S/785.72
S/2,750.02
S/0.00
S/0.00
S/181.32
S/362.64
S/1,269.24
S/0.00
S/0.00
S/529.43
S/1,058.85
S/3,705.98
S/0.00
S/0.00
S/501.65
S/1,003.30
S/3,511.56
S/0.00
S/0.00
S/136.68
S/273.35
S/956.73
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
5/9/2018
6/1/2018
7/1/2018
8/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
28 dias
19 dias
12 dias
30 dias
8 dias
23 dias
30 dias
31 dias
31 dias
S/181.32
S/362.64
S/1,269.24
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/596.15 S/436.73 S/48.63 S/25.13 S/20.13 S/29.78 S/11.98 S/10.10 S/13.69
S/1,192.29 S/873.47 S/97.25 S/50.25 S/40.25 S/59.56 S/23.95 S/20.19 S/27.37
S/4,173.03 S/3,057.14 S/340.38 S/175.88 S/140.88 S/208.45 S/83.83 S/70.67 S/95.80
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/131.83 S/20.08 S/25.13 S/23.38
S/263.65 S/40.17 S/50.25 S/46.75
S/922.79 S/140.59 S/175.88 S/163.63
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
28 dias
19 dias
12 dias
30 dias
8 dias
31 dias
MARZO
ABRIL
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
31 dias
23 dias
30 dias
S/18.13 S/9.93 S/35.19
S/36.25 S/19.85 S/70.38
S/126.88 S/69.48 S/246.32
S/0.00
S/143.92 S/20.08 S/23.38 S/45.25 S/10.10 S/9.93 S/35.19
S/287.84 S/40.17 S/46.75 S/90.50 S/20.19 S/19.85 S/70.38
S/1,007.45 S/140.59 S/163.63 S/316.76 S/70.67 S/69.48 S/246.32
S/0.00
S/0.00
S/149.35 S/21.33 S/22.63 S/40.25 S/10.10
S/298.70 S/42.67 S/45.25 S/80.50 S/20.19
S/1,045.44 S/149.34 S/158.38 S/281.76 S/70.67
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
28 dias
19 dias
12 dias
30 dias
8 dias
31 dias
MARZO
ABRIL
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
31 dias
23 dias
30 dias
S/19.85 S/35.19
S/39.70 S/70.38
S/138.96 S/246.32
S/0.00
S/63.24 S/18.13 S/9.93 S/35.19
S/126.48 S/36.25 S/19.85 S/70.38
S/442.69 S/126.88 S/69.48 S/246.32
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/61,664.86
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
MARZO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00
ABRIL
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/61,664.86
S/0.00
S/0.00
S/53,939.86
S/0.00
S/0.00
S/7,725.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/10,983.25 S/10,983.25 S/10,983.25
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,168.05 S/2,168.05 S/2,168.05
S/4,336.10 S/4,336.10 S/4,336.10
S/15,176.36 S/15,176.36 S/15,176.36
S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/82.61 S/82.61 S/82.61
S/165.23 S/165.23 S/165.23
S/578.30 S/578.30 S/578.30
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/16,754.87 S/10,537.40
S/33,509.75 S/21,074.80
S/117,284.12 S/73,761.80
S/3,422.28 S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
5/8/2018
28 dias
19 dias
12 dias
30 dias
8 dias
31 dias
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
31 dias
31 dias
23 dias
30 dias
S/0.00
S/0.00
S/2,500.00
S/5,000.00
S/17,500.00
S/0.00
S/0.00
S/2,400.00
S/4,800.00
S/16,800.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,252.00 S/2,035.20
S/2,504.00 S/4,070.40
S/8,764.00 S/14,246.40
S/0.00
S/0.00
S/1,285.00
S/2,570.00
S/8,995.00
S/0.00
S/0.00
S/1,065.20
S/2,130.40
S/7,456.40
S/0.00
S/0.00
S/3,150.00
S/6,300.00
S/22,050.00
S/0.00
S/0.00
S/3,150.00
S/6,300.00
S/22,050.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/746.93 S/746.93
S/1,493.86 S/1,493.86
S/5,228.51 S/5,228.51
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/250.00
S/500.00
S/1,750.00
S/0.00
S/0.00
S/0.00
S/250.00
S/500.00
S/1,750.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00
S/0.00
S/0.00
MARZO
S/0.00
ABRIL
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/1,850.00
S/3,700.00
S/12,950.00
S/0.00
S/0.00
S/1,500.00
S/3,000.00
S/10,500.00
S/0.00
S/0.00
S/350.00
S/700.00
S/2,450.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/220.54 S/43.50 S/27.50 S/15.25 S/45.86 S/88.43
S/441.09 S/87.00 S/55.01 S/30.50 S/91.73 S/176.86
S/1,543.81 S/304.50 S/192.53 S/106.74 S/321.05 S/619.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/3,422.28
S/0.00
S/0.00
S/2,144.16
ERADO DE AVANCE DE OBRA- ZONA RECREATIVA INST. ELECTRICAS
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00 4,640.95 371.28 324.87 5,337.10 5,182.32 932.82
S/1,278.12 0.00 0.00 0.00 0.00 0.00 0.00
6,115.14
0.00
25,814.35 2,065.15 1,807.00 29,686.50 28,825.59 5,188.61 34,014.20
53,238.67 4,259.09 3,726.71 61,224.47 59,448.96 10,700.81 70,149.77
60,733.05 4,858.64 4,251.31 69,843.00 67,817.55 12,207.16 80,024.71
175,896.52 14,071.72 12,312.76 202,281.00 196,414.85 35,354.67 231,769.52
135,778.71 10,862.30 9,504.51 156,145.52 151,617.29 27,291.11 178,908.40
1.02%
0.00%
5.66%
11.67%
13.32%
38.57%
29.77%
1.02%
1.02%
6.68%
18.35%
31.67%
70.23%
100.00%
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/24,441.94 S/3,200.00 S/3,200.00 S/21,241.94 S/8,359.86 S/5,220.00 S/1,925.28 S/457.44 S/186.48 S/336.96 S/233.70 S/2,769.12 S/438.68 S/402.52 S/419.70
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/485.70 S/1,022.52 S/10,112.96 S/5,852.56
S/0.00 S/0.00
S/0.00 S/0.00
S/4,260.40 S/23,623.90 S/3,200.00 S/3,200.00 S/20,423.90 S/7,619.90 S/4,785.00 S/1,925.28
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/152.48 S/186.48 S/336.96 S/233.70 S/3,527.12 S/986.68 S/612.52 S/419.70 S/485.70 S/1,022.52 S/9,276.88 S/5,016.48
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/4,260.40 S/11,021.75 S/3,200.00 S/3,200.00 S/7,821.75 S/2,817.32 S/1,740.00 S/467.40 S/609.92 S/1,660.11 S/386.68 S/239.52 S/279.80
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/242.85 S/511.26 S/3,344.32 S/3,344.32 S/4,827.06 S/1,600.00 S/1,600.00 S/3,227.06 S/1,370.02 S/652.50 S/412.56 S/304.96 S/602.92 S/193.34
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/99.26 S/139.90 S/170.42 S/1,254.12 S/1,254.12 S/4,652.85 S/1,600.00 S/1,600.00 S/3,052.85 S/1,400.83 S/543.75 S/687.60 S/76.24 S/93.24
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/602.92 S/193.34 S/99.26 S/139.90 S/170.42 S/1,049.10 S/836.08
S/0.00 S/0.00
S/213.02 S/4,828.10 S/1,600.00 S/1,600.00
S/0.00
S/3,228.10
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/1,363.06 S/652.50 S/550.08 S/76.24 S/84.24 S/602.92 S/193.34 S/99.26 S/139.90 S/170.42 S/1,262.12 S/836.08
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/426.04 S/0.00 S/0.00
S/15,570.22 S/1,600.00 S/1,600.00
S/0.00 S/0.00
S/13,970.22 S/2,205.44 S/435.00 S/275.04 S/152.48 S/458.64 S/884.28
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/900.04 S/213.34 S/136.86 S/239.52 S/139.90 S/170.42 S/430.61 S/219.34 S/119.76 S/91.51 S/5,060.09 S/1,080.03 S/1,990.03 S/1,990.03 S/542.95
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/213.34 S/119.76 S/209.85 S/3,240.09 S/1,080.03 S/1,080.03 S/1,080.03 S/628.92 S/219.34 S/99.26 S/139.90 S/170.42 S/962.08
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/536.04
S/0.00 S/0.00 S/0.00 S/0.00
S/426.04 S/19,638.37 S/1,600.00 S/1,600.00 S/18,038.37 S/3,360.89 S/1,522.50 S/275.04 S/76.24 S/168.48
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/538.23 S/485.64 S/294.76 S/1,049.04 S/219.34 S/201.26 S/181.26 S/136.86 S/139.90 S/170.42 S/855.13 S/193.34 S/181.26 S/410.58 S/69.95
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/530.91 S/193.34 S/136.86 S/119.76 S/80.95 S/8,820.12 S/2,160.06 S/4,380.03 S/2,280.03 S/3,422.28
S/2,144.16
S/1,278.12
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00
S/176,527.04 S/81,372.27 S/70,527.42 S/7,123.90 S/12,293.05 S/1,824.00 S/3,295.60 S/2,097.20 S/5,046.40 S/3,784.80
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/7,632.75 S/3,426.00 S/4,771.20 S/3,928.60 S/1,813.20 S/5,294.25 S/5,016.52 S/1,366.75
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/1,813.20 S/5,961.47 S/4,367.34 S/486.26 S/251.26 S/201.26 S/297.78 S/119.76 S/100.95 S/136.86 S/1,318.27 S/200.84 S/251.26 S/233.76
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/181.26 S/99.26 S/351.89 S/1,439.22 S/200.84 S/233.76 S/452.52 S/100.95 S/99.26 S/351.89 S/1,493.48 S/213.34 S/226.26 S/402.52 S/100.95
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/198.52 S/351.89 S/632.41 S/181.26 S/99.26 S/351.89 S/61,664.86
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/61,664.86 S/53,939.86
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/7,725.00 S/10,983.25 S/10,983.25 S/10,983.25 S/21,680.52 S/21,680.52 S/21,680.52 S/826.14 S/826.14 S/826.14 S/170,971.02 S/105,374.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/25,000.00 S/24,000.00 S/12,520.00 S/20,352.00 S/12,850.00
S/0.00
S/0.00 S/0.00
S/10,652.00 S/31,500.00 S/31,500.00 S/7,469.30 S/7,469.30 S/2,500.00 S/2,500.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/18,500.00 S/15,000.00 S/3,500.00
S/0.00
S/0.00
S/2,205.44 S/435.00 S/275.04 S/152.48 S/458.64 S/884.28 S/3,422.28
S/2,144.16
TOTAL SETIEMBRE 9/1/2018 292 dias
9/3/2018 3 dias
0.00% 100.00%
0.00 0.00 0.00 0.00 0.00 0.00
S/1,278.12 456,102.25 36,488.18 31,927.16 524,517.59 509,306.56 91,675.18
0.00
600,981.74
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
01 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 02 2.01 02.01.01 02.01.02 2.02
OBRAS PRELIMINARES TRASLADO DE EQUIPOS Y HERRAMIENTAS CARTEL DE OBRA DE 7.20 x 3.60 M. CERCO PERIMETRICO PROVISIONAL CASETA PARA ALMACEN, GUARDIANIA Y OFICINA TECNICA SS.HH. TEMPORAL PARA PERSONAL DE OBRA COMEDOR Y VESTIDORES PARA PERSONAL INSTALACION PROVISIONAL DE AGUA Y DESAGUE INSTALACION PROVISIONAL DE INSTALACIONE ELECTRICAS CONSUMO DE ENERGIA ELECTRICA Y AGUA POTABLE EQUIPO DE PROTECCION PERSONAL INSUMOS DE PROTECCION GENERAL DE OBRA BOLETERIA TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS
glb und m m2 mes m2 est est mes glb glb
m2 m2
METRADO
1.00 2.00 270.60 42.00 4.00 34.00 1.00 1.00 4.00 1.00 1.00
6.61 6.61
C. Unit.
S/. 1,200.00 S/. 1,274.82 S/. 73.35 S/. 90.41 S/. 1,400.00 S/. 80.48 S/. 468.96 S/. 904.90 S/. 400.00 S/. 1,500.00 S/. 800.00
S/. 3.64 S/. 1.91
S/41,005.55 S/1,200.00 S/2,549.64 S/19,848.51 S/3,797.22 S/5,600.00 S/2,736.32 S/468.96 S/904.90 S/1,600.00 S/1,500.00 S/800.00 S/9,536.78 S/36.69 S/24.06 S/12.63 S/297.63
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.02.01 02.02.02 02.02.03 02.02.04 2.03 02.03.01 02.03.02 02.03.03 02.03.04 2.04 02.04.01 02.04.02 02.04.03 02.04.04 02.04.05 02.04.06 02.04.07
EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 LOSA ALIGERADA - CONCRETO f´c= 210 KG/CM2
METRADO
C. Unit.
m3 m3 m3 m3
3.20 0.39 0.52 3.65
S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m3 m3 m2 m2
2.40 0.49 1.09 5.22
S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2 kg m3 m2 kg m2
0.66 9.14 183.70 0.63 6.66 137.61 0.44
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50 S/. 419.18
S/137.38 S/19.66 S/47.95 S/92.64 S/946.40 S/537.79 S/197.00 S/62.21 S/149.40 S/4,127.85 S/281.93 S/573.26 S/826.65 S/290.11 S/420.98 S/619.25 S/184.44
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
02.04.08 02.04.09 02.04.10 2.05 02.05.01 2.06 02.06.01 02.06.02 02.06.03 2.07 02.07.01 2.08 02.08.01 2.09 02.09.01 2.10 02.10.01
LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO LOSA ALIGERADA - ACERO fy= 4200 KG/CM2 TECHO ALIGERADO - LADRILLO HUECO DE TECHO 15x30x30 CM. MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES DERRAMES CIELORRASOS ENLUCIDO DE CIELORRASO CON MEZCLA PISOS Y PAVIMENTOS PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURAS COBERTURA C/L. PASTELERO ASENTADO CON MEZCLA
METRADO
C. Unit.
m2 kg und
5.10 132.02 45.00
S/. 52.43 S/. 4.50 S/. 1.55
m2
11.62
S/. 90.86
m2 m2 m
5.51 10.39 10.40
S/. 13.77 S/. 13.77 S/. 17.94
m2
5.10
S/. 31.47
m2
5.22
S/. 47.41
m
8.60
S/. 15.27
m2
6.60
S/. 45.52
S/267.39 S/594.09 S/69.75 S/1,055.79 S/1,055.79 S/405.52 S/75.87 S/143.07 S/186.58 S/160.50 S/160.50 S/247.48 S/247.48 S/131.32 S/131.32 S/300.43 S/300.43
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
2.11 02.11.01 02.11.02 02.11.03 02.11.04 2.12 02.12.01 02.12.02 03 3.01 03.01.01 03.01.02 3.02 03.02.01 03.02.02 03.02.03 03.02.04
CARPINTERIA DE MADERA PUERTA CONTRAPLACADA MDF VENTA DE MADERA TIPO GUILLOTINA CELOSIA DE MADERA ROLLIZA TABLERO DE MDF 18 mm COLOR BLANCO FIJADO C/PERFIL DE FIERRO a= 0.30M. CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS SERVICIOS HIGIENICOS TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE
METRADO
C. Unit.
m2 m2 m2 m
1.68 1.80 2.34 3.00
S/. 204.18 S/. 256.20 S/. 120.00 S/. 200.00
und und
3.00 1.00
S/. 18.84 S/. 85.67
m2 m2
23.94 23.94
S/. 3.64 S/. 1.91
m3 m3 m3 m3
8.98 1.94 0.72 9.15
S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
S/1,684.98 S/343.02 S/461.16 S/280.80 S/600.00 S/142.19 S/56.52 S/85.67 S/54,327.02 S/132.87 S/87.14 S/45.73 S/781.95 S/385.51 S/97.81 S/66.40 S/232.23
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
3.03 03.03.01 03.03.02 03.03.03 03.03.04 3.04 03.04.01 03.04.02 03.04.03 03.04.04 03.04.05 03.04.06 3.05 03.05.01 3.06 03.06.01 03.06.02
OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA REVOQUES Y ENLUCIDOS TARRAJEO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES
METRADO
C. Unit.
m3 m3 m2 m2
5.39 1.35 3.02 18.43
S/. 224.08 S/. 402.04 S/. 57.07 S/. 28.62
m3 m2 kg m3 m2 kg
1.71 22.08 525.05 0.95 12.37 181.18
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50
m2
34.04
S/. 90.86
m2 m2
65.52 13.15
S/. 21.76 S/. 13.77
S/2,450.36 S/1,207.79 S/542.75 S/172.35 S/527.47 S/6,512.72 S/730.44 S/1,384.86 S/2,362.73 S/437.47 S/781.91 S/815.31 S/3,092.87 S/3,092.87 S/2,010.23 S/1,425.72 S/181.08
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
03.06.03 03.06.04 3.07 03.07.01 03.07.02 3.08 03.08.01 3.09 03.09.01 3.10 03.10.01 03.10.02 3.11 03.11.01 03.11.02 03.11.03 3.12
DERRAMES BRUÑAS PISOS Y PAVIMENTOS CONTRAPISO e= 40 mm PISO DE CERAMICO 0.40x0.40 ZOCALOS ZOCALO DE CERAMICO 0.40x0.40 CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURA CUBIERTA DE FIBRO CEMENTO TIPO TEJA ANDINA CUMBRERA DE FIBRO CEMENTO PARA TEJA ANDINA CARPINTERIA DE MADERA ESTRUCTURA DE MADERA SOPORTE DE COBERTURA EN SS.HH. PUERTA CONTRAPLACADA MDF CUBICULOS DE OSB DE 11 mm, SEGUN DISEÑO LAQUEADO DOS MANOS CARPINTERIA METALICA
METRADO
C. Unit.
m m
16.80 31.30
S/. 17.94 S/. 3.26
m2 m2
18.43 18.43
S/. 46.80 S/. 76.05
m2
57.73
S/. 76.73
m
8.60
S/. 15.27
m2 m
35.95 8.40
S/. 62.99 S/. 43.66
m2 m2 m
33.18 5.73 7.50
S/. 558.33 S/. 204.18 S/. 265.00
S/301.39 S/102.04 S/2,264.12 S/862.52 S/1,401.60 S/4,429.62 S/4,429.62 S/131.32 S/131.32 S/2,631.23 S/2,264.49 S/366.74 S/21,682.84 S/18,525.39 S/1,169.95 S/1,987.50 S/312.48
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
03.12.01 3.13 03.13.01 03.13.02 03.13.03 03.13.04 3.14 03.14.01 3.15 03.15.01 03.15.02 03.15.03 03.15.04 03.15.05 03.15.06 03.15.07 03.15.08
BARRA DE ACERO INOXIDABLE PARA DISCAPACITADOS CERRAJERIA BISAGRAS PARA PUERTAS DOBLE HOJA DE 3 1/2" BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS PESTILLO PARA CUBILES DE INODOROS VIDRIOS, CRISTALES Y SIMILARES ESPEJO BISELADO e= 6 mm APARATOS Y ACCESORIOS SANITARIOS TASA ELONGADA VITRIFICADA TIPO 1 C/FLUXOMETRO PARA DESCARGA INDIRECTA DE 1.6VITRIFICADA GAL. O 6 LTS.TIPO ACABADO CROMADO PARA DESCARGA TASA ELONGADA 2 C/FLUXOMETRO INDIRECTA DE 1.6 GAL. O 6 LTS. ACABADO CROMADO LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL LAVADERO CORRIDO DE CONCRETO S/DISEÑO, ACABADO EN CEMENTO PULIDO URINARIO CORRIDO DE CONCRETO ACABADO EN CEMENTO PULIDO SUMINISTRO E INSTALACION DE LLAVE GRIFO CROMADO CON VALVULA AHORRADORA LAVADERO SUMINISTRO E PARA INSTALACION DE LLAVE TEMPORIZADA CON AIREADOR ANTIVANDÁLICO ACABADO CROMADO SUMINISTRO E INSTALACION DE LLAVE DE GRIFO PARA LAVADERO PARA CTO. DE LIMPIEZA
m
METRADO
C. Unit.
2.00
S/. 156.24
und und und und
12.00 6.00 2.00 4.00
S/. 22.80 S/. 18.84 S/. 85.67 S/. 18.19
m2
0.48
S/. 132.00
pza pza pza m m pza pza pza
4.00 1.00 1.00 4.40 1.45 4.00 1.00 1.00
S/. 689.60 S/. 674.60 S/. 240.00 S/. 196.93 S/. 306.90 S/. 175.00 S/. 195.00 S/. 35.00
S/312.48 S/630.74 S/273.60 S/113.04 S/171.34 S/72.76 S/63.36 S/63.36 S/7,025.31 S/2,758.40 S/674.60 S/240.00 S/866.49 S/445.01 S/700.00 S/195.00 S/35.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
03.15.09 03.15.10 03.15.11 3.16 03.16.01 04 4.01 04.01.01 04.01.02 4.02 04.02.01 04.02.02 04.02.03 04.02.04 4.03 04.03.01 04.03.02
DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO INSTALACION DE APARATOS SANITARIOS INSTALACION DE ACCESORIOS SANITARIOS VARIOS SUMINISTRO DE PAPELERA METÁLICA VETERINARIA Y ALMACEN TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2
METRADO
C. Unit.
und pza und
4.00 6.00 5.00
S/. 75.00 S/. 108.11 S/. 32.43
und
5.00
S/. 35.00
m2 m2
50.00 50.00
S/. 3.64 S/. 1.91
m3 m3 m3 m3
11.51 3.88 18.00 9.92
S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m3 m3
8.64 1.81
S/. 224.08 S/. 402.04
S/300.00 S/648.66 S/162.15 S/175.00 S/175.00 S/84,618.47 S/277.50 S/182.00 S/95.50 S/2,601.48 S/494.12 S/195.63 S/1,659.96 S/251.77 S/9,198.72 S/1,936.05 S/727.69
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.03.03 04.03.04 4.04 04.04.01 04.04.02 04.04.03 04.04.04 04.04.05 04.04.06 4.05 04.05.01 4.06 04.06.01 04.06.02 04.06.03 04.06.04 4.07
SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES DERRAMES BRUÑAS PISOS Y PAVIMENTOS
METRADO
C. Unit.
m2 m2
24.26 179.96
S/. 57.07 S/. 28.62
m3 m2 kg m3 m2 kg
1.11 20.30 239.40 0.99 13.20 134.06
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50
m2
21.54
S/. 90.86
m2 m2 m m
38.33 27.72 4.80 98.90
S/. 13.77 S/. 13.77 S/. 17.94 S/. 3.26
S/1,384.52 S/5,150.46 S/4,718.20 S/474.15 S/1,273.22 S/1,077.30 S/455.89 S/834.37 S/603.27 S/1,957.12 S/1,957.12 S/1,318.02 S/527.80 S/381.70 S/86.11 S/322.41 S/8,531.90
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.07.01 4.08 04.08.01 4.09 04.09.01 04.09.02 4.10 04.10.01 04.10.02 04.10.03 04.10.04 4.11 04.11.01 04.11.02 4.12 04.12.01 04.12.02
PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURA CUBIERTA DE FIBRO CEMENTO TIPO TEJA ANDINA CUMBRERA DE FIBRO CEMENTO PARA TEJA ANDINA CARPINTERIA DE MADERA ESTRUCTURA DE MADERA SOPORTE DE COBERTURA EN VETERINARIO Y ALMACÉN PUERTA CONTRAPLACADA MDF CERRAMIENTO DE POLICARBONATO CON MRCO DE MADERA DE 2"x2" MALLA MOSQUITERO FIJADO CON JUNQUILLOS DE MADERA CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS APARATOS Y ACCESORIOS SANITARIOS TASA ELONGADA VITRIFICADA TIPO 2 C/FLUXOMETRO PARA DESCARGA INDIRECTA DE 1.6 GAL. LAVATORIO DE LOSA VITRIFICADA CON SEMI PEDESTAL
METRADO
C. Unit.
m2
179.96
S/. 47.41
m
98.90
S/. 15.27
m2 m
63.60 10.60
S/. 62.99 S/. 43.66
m2 m2 m2 m2
59.36 8.40 30.39 8.59
S/. 609.32 S/. 204.18 S/. 265.64 S/. 110.61
und und
15.00 3.00
S/. 18.84 S/. 85.67
pza pza
1.00 3.00
S/. 674.60 S/. 240.00
S/8,531.90 S/1,510.20 S/1,510.20 S/4,468.96 S/4,006.16 S/462.80 S/46,907.29 S/36,169.24 S/1,715.11 S/8,072.80 S/950.14 S/539.61 S/282.60 S/257.01 S/2,519.47 S/674.60 S/720.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
04.12.03 04.12.04 04.12.05 04.12.06 4.13 04.13.01 05 5.01 05.01.01 05.01.02 5.02 05.02.01 05.02.02 05.02.03 05.02.04 5.03 05.03.01
SUMINISTRO E INSTALACION DE LLAVE TEMPORIZADA CON AIREADOR ANTIVANDÁLICO ACABADO CROMADO DISPENSADOR DE PAPEL HIGIENICO DE POLIESTIRENO DE ALTO IMPACTO INSTALACION DE APARATOS SANITARIOS INSTALACION DE ACCESORIOS SANITARIOS VARIOS SUMINISTRO DE PAPELERA METÁLICA CONEJOS Y CUYES TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG
METRADO
C. Unit.
pza und pza und
3.00 1.00 4.00 1.00
S/. 195.00 S/. 75.00 S/. 108.11 S/. 32.43
und
2.00
S/. 35.00
m2 m2
54.75 54.75
S/. 3.64 S/. 1.91
m3 m3 m3 m3
11.53 2.12 16.50 10.82
S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m3
8.14
S/. 224.08
S/585.00 S/75.00 S/432.44 S/32.43 S/70.00 S/70.00 S/92,102.86 S/303.86 S/199.29 S/104.57 S/2,398.11 S/494.98 S/106.89 S/1,521.63 S/274.61 S/10,192.15 S/1,824.01
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.03.02 05.03.03 05.03.04 5.04 05.04.01 05.04.02 05.04.03 05.04.04 05.04.05 05.04.06 5.05 05.05.01 5.06 05.06.01 05.06.02 05.06.03 05.06.04
SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO FALSO PISO e= 4" OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES DERRAMES BRUÑAS
METRADO
C. Unit.
m3 m2 m2
2.29 30.51 199.38
S/. 402.04 S/. 57.07 S/. 28.62
m3 m2 kg m3 m2 kg
1.03 24.22 165.82 0.71 9.42 125.89
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50
m2
27.12
S/. 90.86
m2 m2 m m
48.26 34.74 6.05 124.52
S/. 13.77 S/. 13.77 S/. 17.94 S/. 3.26
S/920.67 S/1,741.21 S/5,706.26 S/4,194.14 S/439.97 S/1,519.08 S/746.19 S/326.95 S/595.44 S/566.51 S/2,464.12 S/2,464.12 S/1,657.39 S/664.54 S/478.37 S/108.54 S/405.94
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
5.07 05.07.01 5.08 05.08.01 5.09 05.09.01 05.09.02 5.10 05.10.01 05.10.02 05.10.03 05.10.04 05.10.05 5.11 05.11.01 05.11.02 5.12
PISOS Y PAVIMENTOS PISO DE CEMENTO PULIDO Y BRUÑADO 1.00 x 1.00 M. CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURA CUBIERTA DE FIBRO CEMENTO TIPO TEJA ANDINA CUMBRERA DE FIBRO CEMENTO PARA TEJA ANDINA CARPINTERIA DE MADERA ESTRUCTURA DE MADERA SOPORTE DE COBERTURA DE CONEJOS Y CUYES BARANDA C/PARANTES DE MADERA ROLLIZA Y CERRAMIENTO DE LISTONES DE MADERA h= 1.00 M PUERTA CONTRAPLACADA MDF CERRAMIENTO DE POLICARBONATO CON MRCO DE MADERA DE 2"x2" MALLA MOSQUITERO FIJADO CON JUNQUILLOS DE MADERA CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS VARIOS
METRADO
C. Unit.
m2
199.38
S/. 47.41
m
109.50
S/. 15.27
m2 m
69.53 11.55
S/. 62.99 S/. 43.66
m2 m m2 m2 m2
64.68 12.00 8.40 34.88 9.86
S/. 621.60 S/. 150.14 S/. 204.18 S/. 265.64 S/. 110.61
und und
15.00 2.00
S/. 18.84 S/. 85.67
S/9,452.61 S/9,452.61 S/1,672.07 S/1,672.07 S/4,883.96 S/4,379.69 S/504.27 S/54,078.01 S/40,205.09 S/1,801.68 S/1,715.11 S/9,265.52 S/1,090.61 S/453.94 S/282.60 S/171.34 S/352.50
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
05.12.01 06 6.01 06.01.01 06.01.02 6.02 06.02.01 06.02.02 06.02.03 06.02.04 6.03 06.03.01 06.03.02 06.03.03 6.04 06.04.01 06.04.02
CANALETA DE PVC DE O.20 M GALLINERO TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO
METRADO
C. Unit.
m
4.70
S/. 75.00
m2 m2
19.68 19.68
S/. 3.64 S/. 1.91
m3 m3 m3 m3
4.61 0.85 6.60 4.33
S/. 42.93 S/. 50.42 S/. 92.22 S/. 25.38
m3 m3 m2
3.26 0.88 12.20
S/. 224.08 S/. 402.04 S/. 57.07
m3 m2
0.41 9.69
S/. 427.16 S/. 62.72
S/352.50 S/28,749.40 S/109.23 S/71.64 S/37.59 S/959.32 S/197.91 S/42.86 S/608.65 S/109.90 S/1,780.55 S/730.50 S/353.80 S/696.25 S/1,675.25 S/175.14 S/607.76
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.04.03 06.04.04 06.04.05 06.04.06 6.05 06.05.01 6.06 06.06.01 06.06.02 06.06.03 06.06.04 6.07 06.07.01 6.08 06.08.01 06.08.02 6.09
COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES DERRAMES BRUÑAS CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURA CUBIERTA DE FIBRO CEMENTO TIPO TEJA ANDINA CUMBRERA DE FIBRO CEMENTO PARA TEJA ANDINA CARPINTERIA DE MADERA
METRADO
C. Unit.
kg m3 m2 kg
66.33 0.28 3.77 50.36
S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50
m2
10.85
S/. 90.86
m2 m2 m m
19.30 13.90 2.42 49.81
S/. 13.77 S/. 13.77 S/. 17.94 S/. 3.26
m
43.80
S/. 15.27
m2 m
27.67 6.75
S/. 62.99 S/. 43.66
S/298.49 S/128.94 S/238.30 S/226.62 S/985.83 S/985.83 S/662.95 S/265.76 S/191.40 S/43.41 S/162.38 S/668.83 S/668.83 S/2,037.64 S/1,742.93 S/294.71 S/13,739.66
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
06.09.01 06.09.02 06.09.03 6.10 06.10.01 6.11 06.11.01 06.11.02 07 7.01 07.01.01 07.01.02 7.02 07.02.01 07.02.02 07.02.03 7.03
ESTRUCTURA DE MADERA SOPORTE DE COBERTURA DE GALLINERO CERRAMIENTO DE POLICARBONATO CON MRCO DE MADERA DE 2"x2" MALLA MOSQUITERO FIJADO CON JUNQUILLOS DE MADERA CARPINTERIA METALICA CERRAMIENTO DE MALLAGALVANIZADA DE 2"x2" CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS PUESTO DE VENTAS TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA LOSA DE PISO RELLENO CON MATERIAL DE PRESTAMO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE
METRADO
C. Unit.
m2 m2 m2
25.65 7.86 5.92
S/. 428.73 S/. 265.64 S/. 110.61
m2
22.67
S/. 259.98
und und
8.00 1.00
S/. 18.84 S/. 85.67
m2 m2
4.00 4.00
S/. 3.64 S/. 1.91
m3 m3 m3
1.20 0.40 1.56
S/. 42.93 S/. 92.22 S/. 25.38
S/10,996.92 S/2,087.93 S/654.81 S/5,893.75 S/5,893.75 S/236.39 S/150.72 S/85.67 S/2,312.78 S/22.20 S/14.56 S/7.64 S/128.00 S/51.52 S/36.89 S/39.59 S/1,054.23
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
07.03.01 07.03.02 07.03.03 7.04 07.04.01 07.04.02 7.05 07.05.01 7.06 07.06.01 08 8.01 08.01.01 08.01.02 8.02 08.02.01 08.02.02
CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES COBERTURA CUBIERTA DE FIBRO CEMENTO TIPO TEJA ANDINA CARPINTERIA DE MADERA ESTRUCTURA DE MADERA CON TABLERO MDF COLOR BEIGE SUM TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO
METRADO
C. Unit.
m3 m3 m2
3.26 0.28 3.70
S/. 224.08 S/. 402.04 S/. 57.07
m2 m2
1.70 2.00
S/. 13.77 S/. 13.77
m2
4.00
S/. 62.99
m2
4.00
S/. 201.36
m2 m2
234.00 234.00
S/. 3.64 S/. 1.91
m3 m3
56.63 19.09
S/. 42.93 S/. 50.42
S/730.50 S/112.57 S/211.16 S/50.95 S/23.41 S/27.54 S/251.96 S/251.96 S/805.44 S/805.44 S/270,259.75 S/1,298.70 S/851.76 S/446.94 S/4,632.45 S/2,431.13 S/962.52
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
08.02.03 8.03 08.03.01 08.03.02 08.03.03 8.04 08.04.01 08.04.02 08.04.03 08.04.04 08.04.05 08.04.06 8.05 08.05.01 8.06 08.06.01 08.06.02
ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS INTERIORES SOLAQUEADO DE MUROS EXTERIORES
METRADO
C. Unit.
m3
48.81
S/. 25.38
m3 m3 m2
42.51 8.91 119.36
S/. 224.08 S/. 402.04 S/. 57.07
m3 m2 kg m3 m2 kg
5.45 99.85 1,177.85 4.87 64.94 659.59
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50
m2
105.98
S/. 90.86
m2 m2
188.58 136.38
S/. 13.77 S/. 13.77
S/1,238.80 S/19,919.70 S/9,525.64 S/3,582.18 S/6,811.88 S/23,206.55 S/2,328.02 S/6,262.59 S/5,300.33 S/2,242.59 S/4,104.86 S/2,968.16 S/9,629.34 S/9,629.34 S/6,484.72 S/2,596.75 S/1,877.95
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
08.06.03 08.06.04 8.07 08.07.01 8.08 08.08.01 08.08.02 8.09 08.09.01 08.09.02 8.10 08.10.01 08.10.02 09 9.01 09.01.01 09.01.02
DERRAMES BRUÑAS CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO COBERTURA CUBIERTA DE FIBRO CEMENTO TIPO TEJA ANDINA CUMBRERA DE FIBRO CEMENTO PARA TEJA ANDINA CARPINTERIA DE MADERA ESTRUCTURA DE MADERA SOPORTE DE COBERTURA EN SUM PUERTA CONTRAPLACADA MDF CERRAJERIA BISAGRAS CAPUCHINAS ALUMINIZADAS DE 3 1/2" x 3 1/2" CERRADURA PARA PUERTAS CERCO PERIMETRAL TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA
METRADO
C. Unit.
m m
23.62 486.59
S/. 17.94 S/. 3.26
m
486.59
S/. 15.27
m2 m
293.11 41.40
S/. 62.99 S/. 43.66
m2 m2
273.24 6.72
S/. 641.27 S/. 204.18
und und
24.00 4.00
S/. 18.84 S/. 85.67
m2 m2
103.80 103.80
S/. 3.64 S/. 1.91
S/423.74 S/1,586.28 S/7,430.23 S/7,430.23 S/20,270.52 S/18,463.00 S/1,807.52 S/176,592.70 S/175,220.61 S/1,372.09 S/794.84 S/452.16 S/342.68 S/173,328.22 S/576.09 S/377.83 S/198.26
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
9.02 09.02.01 09.02.02 09.02.03 9.03 09.03.01 09.03.02 09.03.03 9.04 09.04.01 09.04.02 09.04.03 09.04.04 09.04.05 09.04.06 9.05 09.05.01
MOVIMIENTO DE TIERRAS EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO OBRAS DE CONCRETO ARMADO COLUMNAS - CONCRETO f´c= 210 KG/CM2 COLUMNAS - ENCOFRADO Y DESENCOFRADO COLUMNAS - ACERO fy= 4200 KG/CM2 VIGAS - CONCRETO f´c= 210 KG/CM2 VIGAS - ENCOFRADO Y DESENCOFRADO VIGAS - ACERO fy= 4200 KG/CM2 MUROS Y TABIQUES DE ALBAÑILERIA MURO DE LADRILLO ASENTADO DE SOGA Y SOLAQUEADO AMBAS CARAS TIPO CARAVISTA
METRADO
C. Unit.
m3 m3 m3
83.04 13.11 90.91
S/. 42.93 S/. 50.42 S/. 25.38
m3 m3 m2
62.28 16.31 217.44
S/. 224.08 S/. 402.04 S/. 57.07
m3 m2 kg m3 m2 kg
2.43 32.40 954.72 7.65 102.04 954.64
S/. 427.16 S/. 62.72 S/. 4.50 S/. 460.49 S/. 63.21 S/. 4.50
m2
181.20
S/. 90.86
S/6,533.22 S/3,564.91 S/661.01 S/2,307.30 S/32,922.27 S/13,955.70 S/6,557.27 S/12,409.30 S/21,634.95 S/1,038.00 S/2,032.13 S/4,296.24 S/3,522.75 S/6,449.95 S/4,295.88 S/16,463.83 S/16,463.83
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
9.06 09.06.01 09.06.02 9.07 09.07.01 9.08 09.08.01 09.08.02 9.09 09.09.01 09.09.02 09.09.03 10 10.01 10.01.01 10.01.02 10.02
REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS EXTERIORES BRUÑAS CONTRAZOCALOS CONTRAZOCALOS DE CEMENTO PULIDO CARPINTERIA METALICA PUERTA DE INGRESO DE MALLA DE ALAMBRE GALVANIZADO, CON CERRAMIENTO DE MALLAGALVANIZADA DE 2"x2" PARANTE DE TUBO DE Fe. DE 3"x3" MARCO DE ANGULO DE 2"x2" Y PLATINA DE 1 1/2", CON PLANCHA METÁLICA Y FIJADA A COLUMNAS DE CERRAJERIA Fe 6" x 6" BISAGRAS DE Fe. DE 5/8" x 10" CERRADURA PARA PORTON - CON ALDABA CORREDIZA Y PORTA CANDADO GARRUCHA GIRATORIA CON RUEDA DE NYLON PESADA DE 5" Y RODAMIENTO 400 A 600 KG CERCOS INTERIORES TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA MOVIMIENTO DE TIERRAS
METRADO
C. Unit.
m2 m
227.57 510.20
S/. 13.77 S/. 3.26
m
483.20
S/. 15.27
m2 m2
306.12 9.90
S/. 259.98 S/. 184.53
und und und
16.00 2.00 4.00
S/. 50.11 S/. 149.15 S/. 127.63
m2 m2
145.91 145.91
S/. 3.64 S/. 1.91
S/4,796.89 S/3,133.64 S/1,663.25 S/7,378.46 S/7,378.46 S/81,411.93 S/79,585.08 S/1,826.85 S/1,610.58 S/801.76 S/298.30 S/510.52 S/97,468.61 S/809.80 S/531.11 S/278.69 S/4,432.47
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
10.02.01 10.02.02 10.02.03 10.03 10.03.01 10.03.02 10.03.03 10.04 10.04.01 10.05 10.05.01 10.05.02 10.05.03 11 11.01 11.01.01 11.01.02
EXCAVACION PARA CIMIENTOS CORRIDOS RELLENO CON MATERIAL PROPIO ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE CIMIENTO CORRIDO C:H 1:10 + 30% PG SOBRECIMIENTO - CONCRETO f´c= 210 KG/CM2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS EXTERIORES CARPINTERIA DE MADERA BARANDA CON PARANTE DE MADERA ROLLIZA Y CERRAMIENTO DE LISTONES MADERA h=1.20 BARANDADE CON PARANTE DE MADERA ROLLIZA Y CERRAMIENTO DE LISTONES DE MADERA h=0.90 BARANDA CON PARANTE DE MADERA ROLLIZA Y CERAMIENTO CON MALLA GALVANIZDA DE 2"x2" COBERTURAS TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA
METRADO
C. Unit.
m3 m3 m3
58.36 0.09 75.75
S/. 42.93 S/. 50.42 S/. 25.38
m3 m3 m2
43.77 19.15 255.34
S/. 224.08 S/. 402.04 S/. 57.07
m2
237.10
S/. 13.77
m m m
92.49 238.35 33.93
S/. 165.31 S/. 150.14 S/. 171.14
m2 m2
187.25 187.25
S/. 3.64 S/. 1.91
S/2,505.39 S/4.54 S/1,922.54 S/32,079.30 S/9,807.98 S/7,699.07 S/14,572.25 S/3,264.87 S/3,264.87 S/56,882.17 S/15,289.52 S/35,785.87 S/5,806.78 S/38,460.75 S/1,039.24 S/681.59 S/357.65
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
11.02 11.02.01 11.02.02 11.03 11.03.01 11.03.02 11.04 11.04.01 11.05 11.05.01 11.05.02 11.05.03 12 12.01 12.01.01 12.01.02 12.01.03
MOVIMIENTO DE TIERRAS EXCAVACION PARA BASE DE COLUMAS DE MADERA ELIMINACION DE MATERIAL EXCEDENTE OBRAS DE CONCRETO SIMPLE BASE Y PEDESTAL DE COLUMNAS - CONCRETO f´c= 210 KG/CM2 BASE Y PEDESTAL DE COLUMNAS - ENCOFRADO Y DESENCOFRADO REVOQUES Y ENLUCIDOS SOLAQUEADO DE MUROS EXTERIORES CARPINTERIA DE MADERA MODULO DE SOMBRA A (5.00x 1.25 M.) MODULO DE SOMBRA B (3.35 x 2.50 M.) MODULO DE SOMBRA B´ (6.00x2.50 M.) OBRAS EXTERIORES ZONA DE CIRCULACION CAMINOS AFIRMADO CUBRESUELOS DE CONFITILLO PATIO CON PISO DE CEMENTO FROTACHADO Y BRUÑADO SARDINELES h= 0.15 M
METRADO
C. Unit.
m3 m3
4.48 5.82
S/. 42.93 S/. 25.38
m3 m2
4.75 7.20
S/. 402.04 S/. 57.07
m2
7.20
S/. 13.77
und und und
8.00 2.00 8.00
S/. 1,364.26 S/. 1,853.99 S/. 2,504.96
m2 m2 m
663.85 163.23 316.92
S/. 51.05 S/. 86.58 S/. 31.93
S/340.04 S/192.33 S/147.71 S/2,320.59 S/1,909.69 S/410.90 S/99.14 S/99.14 S/34,661.74 S/10,914.08 S/3,707.98 S/20,039.68 S/134,075.72 S/58,141.25 S/33,889.54 S/14,132.45 S/10,119.26
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
12.02 12.02.01 12.02.02 12.02.03 12.03 12.03.01 12.04 12.04.01 13 13.01 13.01.01 13.01.02 13.01.03 13.02 13.02.01 13.02.02 13.02.03
AREAS VERDES TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA PREPARACION DE TERRENO PARA SEMBRIO DE GRASS SUMINISTRO E INSTALACION DE CHAMPA DE GRASS POZAS PARA GANSOS POZAS PARA GANSOS DE CONCRETO BEBEDEROS PARA ANIMALES BEBEDEROS PARA ANIMALES SEGUN DISEÑO INSTALACIONES ELECTRICAS MOVIMIENTO DE TIERRAS EXCAVACION DE ZANJAS PARA ALIMENTADORES DE TABLEROS DE DISTRIBUCIÓN EXCAVACION DE ZANJAS PARA CIRCUITOD DE ALUMBRADO Y DERIVACIONES RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO ALIMENTADORES GENERALES ALIMENTADOR ENTRE TABLERO TD-1 Y ST-1 ALIMENTADOR ENTRE TABLERO ST-1 Y ST-2 ALIMENTADOR ENTRE TABLERO ST-2 Y ST-3
METRADO
C. Unit.
m2 m2 m2
1,720.85 1,720.85 1,720.85
S/. 1.91 S/. 15.38 S/. 11.03
und
2.00
S/. 5,600.00
und
10.00
S/. 1,600.00
m3 m3 m3
30.72 45.12 75.84
S/. 37.57 S/. 37.57 S/. 29.91
m m m
70.00 35.00 40.00
S/. 28.48 S/. 21.43 S/. 22.48
S/48,734.47 S/3,286.82 S/26,466.67 S/18,980.98 S/11,200.00 S/11,200.00 S/16,000.00 S/16,000.00 S/68,054.34 S/5,117.68 S/1,154.15 S/1,695.16 S/2,268.37 S/4,241.11 S/1,993.60 S/750.05 S/899.20
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
13.02.04 13.02.05 13.03 13.03.01 13.03.02 13.03.03 13.04 13.04.01 13.04.02 13.04.03 13.04.04 13.04.05 13.04.06 13.05 13.05.01 13.05.02 13.05.03
ALIMENTADOR ENTRE TABLERO ST-3 Y TD-1 ALIMENTADOR ENTRE TABLERO ST-3 Y TD-2 CABLEADO DE CIRCUITOS DE ILUMINACION EXTERIOR CIRCUITO C-3 del ST-1 CIRCUITO C-3 del ST-2 CIRCUITO C-7 del ST-3 CABLEADO DE CIRCUITOS DE ILUMINACION DE SUM (TRAMO DE ST-3 A CAJAS DE PASE) CIRCUITO C-1 del ST-3 CIRCUITO C-2 del ST-3 CIRCUITO C-3 del ST-3 CIRCUITO C-4 del ST-3 CIRCUITO C-5 del ST-3 CIRCUITO C-6 del ST-3 CABLEADO DE CIRCUITOS DE ILUMINACION DE SUM (TRAMO DE ST-2 A CAJAS DE PASE) CIRCUITO C-1 del ST-2 CIRCUITO C-2 del ST-2 CIRCUITO C-3 del ST-2
METRADO
C. Unit.
m m
15.00 12.00
S/. 20.38 S/. 24.38
m m m
35.00 30.00 32.00
S/. 20.38 S/. 20.38 S/. 20.38
m m m m m m
10.00 20.00 32.00 25.00 13.00 10.00
S/. 17.00 S/. 17.00 S/. 17.00 S/. 17.00 S/. 20.38 S/. 20.38
m m m
15.00 10.00 11.00
S/. 17.00 S/. 20.38 S/. 17.00
S/305.70 S/292.56 S/1,976.86 S/713.30 S/611.40 S/652.16 S/1,947.74 S/170.00 S/340.00 S/544.00 S/425.00 S/264.94 S/203.80 S/645.80 S/255.00 S/203.80 S/187.00
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
13.06 13.06.01 13.06.02 13.07 13.07.01 13.07.02 13.07.03 13.07.04 13.07.05 13.08 13.08.01 13.08.02 13.08.03 13.08.04 13.09 13.09.01 13.09.02
CABLEADO DE CIRCUITOS DE ILUMINACION DE SUM (TRAMO DE ST-1 A CAJA1 DE PASE) CIRCUITO C-1 del ST-1 CIRCUITO C-2 del ST-1 ILUMINACION DE VETERIANARIA Y ALMACEN SALIDA PARA ARTEFACTO ADOSADO EN EL TECHO SALIDA PARA TOMACORRIENTE BIPOLAR CON COMA A TIERRA Salida para interruptores dobles Salida para adosada interruptores triples Luminaria a techo con dos lámparas fluoresc. comp. de 36w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida.DE Similar josfelCONEJOS modelo AHR-Z ILUMINACION BLOQUE Y CUYES SALIDA PARA ARTEFACTO ADOSADO EN EL TECHO SALIDA PARA TOMACORRIENTE BIPOLAR CON COMA A TIERRA Salida para adosada interruptores dobles Luminaria a techo con dos lámparas fluoresc. comp. de 36w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida.DE Similar josfel modelo AHR-Z ILUMINACION BOLETERIA SALIDA PARA ARTEFACTO ADOSADO EN EL TECHO SALIDA PARA TOMACORRIENTE BIPOLAR CON COMA A TIERRA
METRADO
C. Unit.
m m
10.00 10.00
S/. 17.00 S/. 20.38
pto pto und und und
10.00 7.00 1.00 1.00 10.00
S/. 108.75 S/. 137.52 S/. 84.24 S/. 93.24 S/. 283.62
pto pto und und
10.00 3.00 2.00 10.00
S/. 108.75 S/. 137.52 S/. 84.24 S/. 283.62
pto pto
10.00 3.00
S/. 108.75 S/. 137.52
S/373.80 S/170.00 S/203.80 S/5,063.82 S/1,087.50 S/962.64 S/84.24 S/93.24 S/2,836.20 S/4,504.74 S/1,087.50 S/412.56 S/168.48 S/2,836.20 S/1,661.07 S/1,087.50 S/412.56
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
13.09.03 13.09.04 13.10 13.10.01 13.10.02 13.10.03 13.10.04 13.11 13.11.01 13.11.02 13.11.03 13.12 13.12.01 13.13 13.13.01 13.13.02 13.13.03
SALIDA PARA INTERRUPTORES SIMPLES Foco ahorrador de 32 w de potencia ILUMINACION DE SS.HH SALIDA PARA ARTEFACTO ADOSADO EN EL TECHO SALIDA PARA INTERRUPTORES SIMPLES Foco ahorrador de 32 w de potencia Luminaria adosada a techo con dos lámparas fluoresc. comp. de 36w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida.DESimilar ILUMINACION LOS 4 josfel SUM modelo AHR-Z SALIDA PARA ARTEFACTO ADOSADO EN EL TECHO SALIDA PARA INTERRUPTORES Luminaria adosada a techo conSIMPLES dos lámparas fluoresc. comp. de 36w. Con batería de cadmio-niquel y equipo electrónico de transferencia con flecha de salida.DESimilar modelo AHR-Z ILUMINACION CERCOjosfel TRANSPARENTE CON PASTORAL POSTES DE CONCRETO PARA ALUMBRADO DE 9 m DE ALTURA, CON PASTORAL DE 50 W TABLEROS ELECTRICOS SUBTABLERO EMPOTRADO ST-1 (16 polos) SUBTABLERO EMPOTRADO ST-2 (16 polos) SUBTABLERO EMPOTRADO ST-3 (16 polos)
METRADO
C. Unit.
und und
1.00 1.00
S/. 76.24 S/. 84.77
pto und und und
4.00 4.00 1.00 3.00
S/. 108.75 S/. 76.24 S/. 84.77 S/. 283.62
pto und und
32.00 4.00 32.00
S/. 108.75 S/. 76.24 S/. 283.62
und
8.00
S/. 2,246.15
pza pza pza
1.00 1.00 1.00
S/. 1,187.76 S/. 1,197.26 S/. 1,178.46
S/76.24 S/84.77 S/1,675.59 S/435.00 S/304.96 S/84.77 S/850.86 S/12,860.80 S/3,480.00 S/304.96 S/9,075.84 S/17,969.20 S/17,969.20 S/4,790.40 S/1,187.76 S/1,197.26 S/1,178.46
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
13.13.04 13.13.05 13.14 13.14.01 13.15 13.15.01 13.15.02 13.15.03 13.15.04 13.15.05 13.15.06 14 14.01 14.01.01 14.01.02 14.02 14.02.01
SUBTABLERO EMPOTRADO TD-1 (8 polos) SUBTABLERO EMPOTRADO TD-2 (8 polos) SISTEMA DE PUESTA A TIERRA POZO A TIERRA MURETES PARA TABLEROS ELECTRICOS EXCAVACION PARA BASE DE MURETES CIMIENTO DE MURETES - CONCRETO CICLOPEO 1:10 + 30% P.G. SOBRECIMIENTO DE MURETE - CONCRETO 1:8 + 25% P.M. SOBRECIMIENTO DE MURETE - ENCOFRADO Y DESENCOFRADO MURETE CE LADRILLO KK ASENTADO DE CABEZA TARRAJEO DE MURETE INSTALACIONES SANITARIAS SALIDA DE AGUA FRIA SALIDA DE AGUA FRIA TUB. PVC CLASE 10 C/R 1/2" SALIDA DE AGUA FRIA TUB. PVC CLASE 10 C/R 1 1/4" REDES DE DISTRIBUCION DE AGUA FRIA EN TUBERIA DE PVC RED DE DISTRIBUCION 1/2" PVC SAP
METRADO
C. Unit.
pza pza
1.00 1.00
S/. 613.46 S/. 613.46
und
1.00
S/. 1,930.43
m3 m3 m3 m2 m2 m2
3.60 2.88 0.90 8.40 8.82 29.93
S/. 37.57 S/. 216.42 S/. 297.38 S/. 57.07 S/. 109.70 S/. 27.47
pto pto
23.00 5.00
S/. 161.34 S/. 202.01
m
94.15
S/. 20.29
S/613.46 S/613.46 S/1,930.43 S/1,930.43 S/3,295.30 S/135.25 S/623.29 S/267.64 S/479.39 S/967.55 S/822.18 S/52,195.54 S/4,720.87 S/3,710.82 S/1,010.05 S/12,476.19 S/1,910.30
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
14.02.02 14.02.03 14.02.04 14.03 14.03.01 14.03.02 14.03.03 14.03.04 14.03.05 14.03.06 14.03.07 14.03.08 14.03.09 14.04 14.04.01 14.04.02 14.05
RED DE DISTRIBUCION 1 1/4" PVC SAP RED DE DISTRIBUCION 1 1/2" PVC SAP RED DE DISTRIBUCION 2" PVC SAP ACCESORIOS CODO PVC S/ PRESION 1 1/2" x 90º CODO PVC S/ PRESION 1 1/4" x 90º CODO PVC C-10 S/P 45° x 2" CODO 45° 1 1/2" CODO PVC C-10 S/P 90° x 1/2" CODO PVC C-10 S/P 22,5° x 1 1/2" CODO PVC S/PRESION DE 22.5° 2" REDUCCION PVC S/PRESION 2 1/2" A 3/4" REDUCCION PVC S/PRESION 1 1/2" A 1/2" LLAVES Y VALVULAS VALVULA COMPUERTA DE BRONCE DE 1 1/4" CAJAS DE CONCRETO PARA VALVULAS GRIFOS DE RIEGO
METRADO
C. Unit.
m m m
10.97 51.21 97.81
S/. 62.04 S/. 63.29 S/. 67.93
pza pza pza pza pza pza pza pza pza
4.00 7.00 1.00 2.00 12.00 1.00 1.00 2.00 10.00
S/. 12.75 S/. 11.70 S/. 13.20 S/. 13.80 S/. 3.30 S/. 13.80 S/. 13.80 S/. 16.05 S/. 12.90
pza und
4.00 4.00
S/. 329.80 S/. 916.46
S/680.58 S/3,241.08 S/6,644.23 S/402.00 S/51.00 S/81.90 S/13.20 S/27.60 S/39.60 S/13.80 S/13.80 S/32.10 S/129.00 S/4,985.04 S/1,319.20 S/3,665.84 S/696.54
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
14.05.01 14.06 14.07 14.07.01 14.07.02 14.07.03 14.08 14.08.01 14.08.02 14.09 14.09.01 14.09.02 14.09.03 14.10 14.10.01 14.11 14.12
GRIFO DE RIEGO DE 1/2" DESAGUE Y VENTILACION SALIDAS DE DESAGUE Y VENTILACION SALIDA DE DESAGUE PVC SAL 4" SALIDA DE DESAGUE PVC SAP 2" SALIDA DE VENTILACION PVC SAL 2" REDES DE DERIVACION TUBERIA PVC SAL Ø 4" TUBERIA PVC SAL Ø 2" ACCESORIOS DE DESAGUE Y VENTILACION REGISTRO DE BRONCE 4" SUMIDERO DE BRONCE 2" SOMBRERO DE VENTILACION PVC DE 2" CAJA DE REGISTRO DE ALBAÑILERIA CAJA DE REGISTRO 12"x24" PRUEBAS HIDRAULICAS Y DESINFECCION PRUEBA HIDRAULICA DE AGUA FRIA
METRADO
C. Unit.
und
2.00
S/. 348.27
pto pto pto
6.00 25.00 11.00
S/. 154.80 S/. 130.81 S/. 105.45
m m
153.92 121.56
S/. 61.36 S/. 57.65
pza pza pza
4.00 2.00 11.00
S/. 103.22 S/. 88.71 S/. 27.81
pza
12.00
S/. 327.45
m
254.14
S/. 5.44
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/696.54
S/0.00
S/0.00
S/5,359.00 S/928.80 S/3,270.25 S/1,159.95 S/16,452.46 S/9,444.53 S/7,007.93 S/896.21 S/412.88 S/177.42 S/305.91 S/3,929.40 S/3,929.40 S/2,277.83 S/1,382.52
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
CRONOGRAMA VALORIZADO ACELERADO Valorizaciones de Obra OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
CONTRATISTA
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERALES .
SUPERVISA
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L. AÑO 2017 VALOR REFERENCIAL
COD.
DESCRIPCION
SUB TOTAL UND
14.13
PRUEBA HIDRAULICA DE DESAGUE
m
METRADO
275.48
C. Unit.
S/. 3.25
Costo Directo Gastos Generales Utilidad
8.00% 7.00%
Parcial Parcial * (F.R.) Impuesto IGV TOTAL PRESUPUESTO
0.971 18.00%
S/895.31
NOVIEMBRE
DICIEMBRE
11/16/2017
12/1/2017
11/30/2017
12/31/2017
15 dias
31 dias
S/0.00
1,146,495.79 91,719.66 80,254.71 1,318,470.16 1,280,234.48 230,442.21 1,510,676.69
S/0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
PORCENTAJE DE AVANCE ( % )
0.00%
0.00%
PORCENTAJE ACUMULADO DE AVANCE ( % )
0.00%
0.00%
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/5,909.71 S/0.00 S/2,549.64 S/0.00 S/1,139.17 S/1,400.00 S/820.90 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/4,867.31 S/166.42 S/0.00 S/2,752.71 S/368.63 S/582.48 S/265.64 S/65.04 S/125.50 S/221.90 S/208.03 S/110.95 S/1,280.72 S/36.69 S/24.06 S/12.63 S/297.63
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/7,685.22 S/262.77 S/0.00 S/4,346.39 S/582.05 S/919.71 S/419.44 S/102.69 S/198.15 S/350.36 S/328.47 S/175.18 S/3,501.80 S/0.00
S/7,941.39 S/271.53 S/0.00 S/4,491.27 S/601.46 S/950.36 S/433.42 S/106.12 S/204.76 S/362.04 S/339.42 S/181.02 S/1,245.25 S/0.00
S/7,941.39 S/271.53 S/0.00 S/4,491.27 S/601.46 S/950.36 S/433.42 S/106.12 S/204.76 S/362.04 S/339.42 S/181.02 S/1,827.17 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/5,892.00 S/201.46 S/0.00 S/3,332.23 S/446.24 S/705.11 S/321.57 S/78.73 S/151.92 S/268.61 S/251.82 S/134.31 S/1,681.84 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/137.38 S/19.66 S/47.95 S/92.64 S/946.40 S/537.79 S/197.00 S/62.21 S/149.40 S/0.00
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,681.84 S/281.93 S/573.26 S/826.65
S/2,446.01
S/0.00
S/0.00
S/290.11 S/420.98 S/619.25 S/184.44
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/267.39 S/594.09 S/69.75 S/1,055.79 S/1,055.79 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/405.52 S/75.87 S/143.07 S/186.58 S/160.50 S/160.50 S/247.48 S/247.48 S/131.32 S/131.32 S/300.43 S/300.43
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/2,837.71 S/132.87 S/87.14 S/45.73 S/781.95 S/385.51 S/97.81 S/66.40 S/232.23
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/10,133.06 S/0.00
S/8,835.29 S/0.00
S/25,320.65 S/0.00
S/1,684.98 S/343.02 S/461.16 S/280.80 S/600.00 S/142.19 S/56.52 S/85.67 S/7,200.31 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/1,922.89 S/1,207.79 S/542.75 S/172.35
ABRIL
S/0.00
S/0.00
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/527.47
S/527.47 S/6,512.72 S/730.44 S/1,384.86 S/2,362.73 S/437.47 S/781.91 S/815.31 S/3,092.87 S/3,092.87 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/2,010.23 S/1,425.72 S/181.08
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/301.39 S/102.04 S/2,264.12 S/862.52 S/1,401.60 S/4,429.62 S/4,429.62 S/131.32 S/131.32 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/2,631.23 S/2,264.49 S/366.74 S/21,682.84 S/18,525.39 S/1,169.95 S/1,987.50 S/312.48
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/312.48 S/630.74 S/273.60 S/113.04 S/171.34 S/72.76 S/63.36 S/63.36 S/0.00
S/0.00
S/0.00 S/7,025.31 S/2,758.40 S/674.60 S/240.00 S/866.49 S/445.01 S/700.00 S/195.00 S/35.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/12,077.70 S/277.50 S/182.00 S/95.50 S/2,601.48 S/494.12 S/195.63 S/1,659.96 S/251.77 S/9,198.72 S/1,936.05 S/727.69
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/6,675.32 S/0.00
S/11,360.12 S/0.00
S/51,915.86 S/0.00
S/300.00 S/648.66 S/162.15 S/175.00 S/175.00 S/2,589.47 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/1,384.52 S/5,150.46 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/4,718.20 S/474.15 S/1,273.22 S/1,077.30 S/455.89 S/834.37 S/603.27 S/1,957.12 S/1,957.12 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,318.02 S/527.80 S/381.70 S/86.11 S/322.41 S/8,531.90
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/8,531.90 S/1,510.20 S/1,510.20 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/4,468.96 S/4,006.16 S/462.80 S/46,907.29 S/36,169.24 S/1,715.11 S/8,072.80 S/950.14 S/539.61 S/282.60 S/257.01 S/0.00
S/0.00
S/0.00
S/0.00
S/2,519.47 S/674.60 S/720.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/8,315.65 S/0.00
S/16,008.64 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/12,894.12 S/303.86 S/199.29 S/104.57 S/2,398.11 S/494.98 S/106.89 S/1,521.63 S/274.61 S/10,192.15 S/1,824.01
S/585.00 S/75.00 S/432.44 S/32.43 S/70.00 S/70.00 S/54,884.45 S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/920.67 S/1,741.21 S/5,706.26 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/4,194.14 S/439.97 S/1,519.08 S/746.19 S/326.95 S/595.44 S/566.51 S/2,464.12 S/2,464.12 S/1,657.39 S/664.54 S/478.37 S/108.54 S/405.94
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/9,452.61 S/9,452.61 S/1,672.07 S/1,672.07 S/4,883.96 S/4,379.69 S/504.27 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00 S/0.00
S/54,078.01 S/40,205.09 S/1,801.68 S/1,715.11 S/9,265.52 S/1,090.61 S/453.94 S/282.60 S/171.34 S/352.50
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/2,849.10 S/109.23 S/71.64 S/37.59 S/959.32 S/197.91 S/42.86 S/608.65 S/109.90 S/1,780.55 S/730.50 S/353.80 S/696.25 S/0.00
S/2,661.08 S/0.00
S/3,369.42 S/0.00
S/352.50 S/19,869.80 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,675.25 S/175.14 S/607.76
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/298.49 S/128.94 S/238.30 S/226.62 S/985.83 S/985.83 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/662.95 S/265.76 S/191.40 S/43.41 S/162.38 S/668.83 S/668.83 S/2,037.64 S/1,742.93 S/294.71 S/0.00
S/0.00
S/0.00 S/0.00
S/13,739.66
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/1,108.35 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,204.43 S/22.20 S/14.56 S/7.64 S/128.00 S/51.52 S/36.89 S/39.59 S/1,054.23
S/10,996.92 S/2,087.93 S/654.81 S/5,893.75 S/5,893.75 S/236.39 S/150.72 S/85.67 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/730.50 S/112.57 S/211.16 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/50.95 S/23.41 S/27.54 S/251.96 S/251.96 S/805.44 S/805.44 S/58,686.74 S/1,298.70 S/851.76 S/446.94 S/4,632.45 S/2,431.13 S/962.52
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/211,573.01 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,238.80 S/19,919.70 S/9,525.64 S/3,582.18 S/6,811.88 S/23,206.55 S/2,328.02 S/6,262.59 S/5,300.33 S/2,242.59 S/4,104.86 S/2,968.16 S/9,629.34 S/9,629.34 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/6,484.72 S/2,596.75 S/1,877.95
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/56,520.07 S/187.86 S/123.21 S/64.65
S/423.74 S/1,586.28 S/7,430.23 S/7,430.23 S/20,270.52 S/18,463.00 S/1,807.52 S/176,592.70 S/175,220.61 S/1,372.09 S/794.84 S/452.16 S/342.68 S/58,404.07 S/194.12 S/127.31 S/66.81
S/0.00 S/0.00
S/0.00
S/0.00
S/58,404.07 S/194.12 S/127.31 S/66.81
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/2,130.40 S/1,162.47 S/215.55 S/752.38 S/10,735.52 S/4,550.77 S/2,138.24 S/4,046.51 S/7,054.88 S/338.48 S/662.65 S/1,400.95 S/1,148.72 S/2,103.24 S/1,400.83 S/5,368.64 S/5,368.64
S/2,201.41 S/1,201.22 S/222.73 S/777.46 S/11,093.37 S/4,702.46 S/2,209.51 S/4,181.39 S/7,290.04 S/349.76 S/684.74 S/1,447.65 S/1,187.01 S/2,173.35 S/1,447.52 S/5,547.59 S/5,547.59
S/2,201.41 S/1,201.22 S/222.73 S/777.46 S/11,093.37 S/4,702.46 S/2,209.51 S/4,181.39 S/7,290.04 S/349.76 S/684.74 S/1,447.65 S/1,187.01 S/2,173.35 S/1,447.52 S/5,547.59 S/5,547.59
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/1,564.20 S/1,021.84 S/542.36 S/2,406.02 S/2,406.02 S/26,547.37 S/25,951.66 S/595.71 S/525.19 S/261.44 S/97.27 S/166.47 S/31,783.24 S/264.07 S/173.19 S/90.88 S/1,445.37
S/1,616.34 S/1,055.90 S/560.44 S/2,486.22 S/2,486.22 S/27,432.28 S/26,816.71 S/615.57 S/542.70 S/270.16 S/100.51 S/172.02 S/32,842.68 S/272.87 S/178.96 S/93.91 S/1,493.55
S/1,616.34 S/1,055.90 S/560.44 S/2,486.22 S/2,486.22 S/27,432.28 S/26,816.71 S/615.57 S/542.70 S/270.16 S/100.51 S/172.02 S/32,842.68 S/272.87 S/178.96 S/93.91 S/1,493.55
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/816.98 S/1.48 S/626.92 S/10,460.64 S/3,198.25 S/2,510.57 S/4,751.82 S/1,064.63 S/1,064.63 S/18,548.53 S/4,985.71 S/11,669.31 S/1,893.52 S/12,541.55 S/338.88 S/222.26 S/116.63
S/844.21 S/1.53 S/647.81 S/10,809.33 S/3,304.86 S/2,594.25 S/4,910.21 S/1,100.12 S/1,100.12 S/19,166.82 S/5,151.90 S/12,058.28 S/1,956.63 S/12,959.60 S/350.18 S/229.67 S/120.51
S/844.21 S/1.53 S/647.81 S/10,809.33 S/3,304.86 S/2,594.25 S/4,910.21 S/1,100.12 S/1,100.12 S/19,166.82 S/5,151.90 S/12,058.28 S/1,956.63 S/12,959.60 S/350.18 S/229.67 S/120.51
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/110.88 S/62.72 S/48.17 S/756.71 S/622.73 S/133.99 S/32.33 S/32.33 S/11,302.74 S/3,558.94 S/1,209.12 S/6,534.68 S/0.00 S/0.00
S/114.58 S/64.81 S/49.77 S/781.94 S/643.48 S/138.46 S/33.41 S/33.41 S/11,679.50 S/3,677.57 S/1,249.43 S/6,752.50 S/63,943.80 S/27,728.90 S/16,162.70 S/6,740.09 S/4,826.11
S/114.58 S/64.81 S/49.77 S/781.94 S/643.48 S/138.46 S/33.41 S/33.41 S/11,679.50 S/3,677.57 S/1,249.43 S/6,752.50 S/63,943.80 S/27,728.90 S/16,162.70 S/6,740.09 S/4,826.11
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/9,649.50 S/725.64 S/163.65 S/240.36 S/321.63 S/601.35 S/282.67 S/106.35 S/127.50
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/11,680.97 S/878.41 S/198.10 S/290.96 S/389.35 S/727.95 S/342.19 S/128.74 S/154.34
S/15,236.05 S/1,145.75 S/258.39 S/379.51 S/507.84 S/949.50 S/446.33 S/167.92 S/201.31
S/23,242.59 S/1,567.56 S/12,622.57 S/9,052.47 S/5,341.54 S/5,341.54 S/7,630.77 S/7,630.77 S/15,743.91 S/1,183.94 S/267.00 S/392.16 S/524.77 S/981.15 S/461.21 S/173.52 S/208.02
S/23,242.59 S/1,567.56 S/12,622.57 S/9,052.47 S/5,341.54 S/5,341.54 S/7,630.77 S/7,630.77 S/15,743.91 S/1,183.94 S/267.00 S/392.16 S/524.77 S/981.15 S/461.21 S/173.52 S/208.02
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/43.35 S/41.48 S/280.30 S/101.14 S/86.69 S/92.47 S/276.17 S/24.10 S/48.21 S/77.13 S/60.26 S/37.57 S/28.90 S/91.57 S/36.16 S/28.90 S/26.51
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/52.47 S/50.22 S/339.31 S/122.43 S/104.94 S/111.94 S/334.31 S/29.18 S/58.36 S/93.37 S/72.95 S/45.47 S/34.98 S/110.85 S/43.77 S/34.98 S/32.10
S/68.44 S/65.50 S/442.58 S/159.69 S/136.88 S/146.01 S/436.06 S/38.06 S/76.12 S/121.79 S/95.15 S/59.31 S/45.63 S/144.58 S/57.09 S/45.63 S/41.87
S/70.72 S/67.68 S/457.33 S/165.02 S/141.44 S/150.87 S/450.60 S/39.33 S/78.66 S/125.85 S/98.32 S/61.29 S/47.15 S/149.40 S/58.99 S/47.15 S/43.26
S/70.72 S/67.68 S/457.33 S/165.02 S/141.44 S/150.87 S/450.60 S/39.33 S/78.66 S/125.85 S/98.32 S/61.29 S/47.15 S/149.40 S/58.99 S/47.15 S/43.26
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/53.00 S/24.10 S/28.90 S/718.00 S/154.20 S/136.49 S/11.94 S/13.22 S/402.15 S/638.73 S/154.20 S/58.50 S/23.89 S/402.15 S/235.52 S/154.20 S/58.50
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/83.69 S/38.06 S/45.63 S/1,133.69 S/243.47 S/215.52 S/18.86 S/20.87 S/634.97 S/1,008.52 S/243.47 S/92.36 S/37.72 S/634.97 S/371.88 S/243.47 S/92.36
S/86.48 S/39.33 S/47.15 S/1,171.48 S/251.59 S/222.70 S/19.49 S/21.57 S/656.14 S/1,042.14 S/251.59 S/95.44 S/38.98 S/656.14 S/384.28 S/251.59 S/95.44
S/86.48 S/39.33 S/47.15 S/1,171.48 S/251.59 S/222.70 S/19.49 S/21.57 S/656.14 S/1,042.14 S/251.59 S/95.44 S/38.98 S/656.14 S/384.28 S/251.59 S/95.44
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/64.16 S/29.18 S/34.98 S/869.16 S/186.66 S/165.23 S/14.46 S/16.00 S/486.81 S/773.20 S/186.66 S/70.81 S/28.92 S/486.81 S/285.11 S/186.66 S/70.81
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/10.81 S/12.02 S/237.58 S/61.68 S/43.24 S/12.02 S/120.64 S/1,823.55 S/493.43 S/43.24 S/1,286.87 S/2,547.87 S/2,547.87 S/679.24 S/168.41 S/169.76 S/167.10
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/13.09 S/14.55 S/287.60 S/74.66 S/52.34 S/14.55 S/146.04 S/2,207.45 S/597.31 S/52.34 S/1,557.79 S/3,084.27 S/3,084.27 S/822.23 S/203.87 S/205.50 S/202.27
S/17.07 S/18.98 S/375.13 S/97.39 S/68.27 S/18.98 S/190.49 S/2,879.28 S/779.10 S/68.27 S/2,031.90 S/4,022.96 S/4,022.96 S/1,072.48 S/265.92 S/268.04 S/263.83
S/17.64 S/19.61 S/387.64 S/100.63 S/70.55 S/19.61 S/196.84 S/2,975.26 S/805.07 S/70.55 S/2,099.63 S/4,157.05 S/4,157.05 S/1,108.23 S/274.78 S/276.98 S/272.63
S/17.64 S/19.61 S/387.64 S/100.63 S/70.55 S/19.61 S/196.84 S/2,975.26 S/805.07 S/70.55 S/2,099.63 S/4,157.05 S/4,157.05 S/1,108.23 S/274.78 S/276.98 S/272.63
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/86.98 S/86.98 S/273.72 S/273.72 S/467.24 S/19.18 S/88.38 S/37.95 S/67.97 S/137.19 S/116.58 S/7,400.86 S/669.38 S/526.16 S/143.22 S/1,769.01 S/270.86
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/105.30 S/105.30 S/331.34 S/331.34 S/565.61 S/23.21 S/106.98 S/45.94 S/82.28 S/166.07 S/141.12 S/8,958.94 S/810.30 S/636.93 S/173.37 S/2,141.44 S/327.89
S/137.34 S/137.34 S/432.19 S/432.19 S/737.75 S/30.28 S/139.54 S/59.92 S/107.33 S/216.62 S/184.07 S/11,685.57 S/1,056.91 S/830.78 S/226.13 S/2,793.18 S/427.68
S/141.92 S/141.92 S/446.59 S/446.59 S/762.35 S/31.29 S/144.19 S/61.92 S/110.90 S/223.84 S/190.21 S/12,075.09 S/1,092.14 S/858.47 S/233.67 S/2,886.28 S/441.94
S/141.92 S/141.92 S/446.59 S/446.59 S/762.35 S/31.29 S/144.19 S/61.92 S/110.90 S/223.84 S/190.21 S/12,075.09 S/1,092.14 S/858.47 S/233.67 S/2,886.28 S/441.94
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
MARZO
S/96.50 S/459.56 S/942.09 S/57.00 S/7.23 S/11.61 S/1.87 S/3.91 S/5.61 S/1.96 S/1.96 S/4.55 S/18.29 S/706.83 S/187.05 S/519.78 S/98.76
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/116.82 S/556.30 S/1,140.43 S/69.00 S/8.75 S/14.06 S/2.27 S/4.74 S/6.80 S/2.37 S/2.37 S/5.51 S/22.14 S/855.64 S/226.43 S/629.21 S/119.56
S/152.37 S/725.61 S/1,487.51 S/90.00 S/11.42 S/18.34 S/2.96 S/6.18 S/8.87 S/3.09 S/3.09 S/7.19 S/28.88 S/1,116.05 S/295.34 S/820.71 S/155.94
S/157.45 S/749.80 S/1,537.10 S/93.00 S/11.80 S/18.95 S/3.05 S/6.39 S/9.16 S/3.19 S/3.19 S/7.43 S/29.84 S/1,153.26 S/305.19 S/848.07 S/161.14
S/157.45 S/749.80 S/1,537.10 S/93.00 S/11.80 S/18.95 S/3.05 S/6.39 S/9.16 S/3.19 S/3.19 S/7.43 S/29.84 S/1,153.26 S/305.19 S/848.07 S/161.14
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
MARZO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00
S/0.00
S/98.76
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00 S/0.00
S/759.86 S/131.70 S/463.69 S/164.47 S/2,332.81 S/1,339.15 S/993.66 S/127.07 S/58.54 S/25.16 S/43.38 S/557.15 S/557.15 S/322.98 S/196.03
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/119.56
S/155.94
S/161.14
S/161.14
S/919.83 S/159.42 S/561.31 S/199.10 S/2,823.93 S/1,621.08 S/1,202.85 S/153.83 S/70.87 S/30.45 S/52.51 S/674.45 S/674.45 S/390.97 S/237.30
S/1,199.78 S/207.94 S/732.15 S/259.69 S/3,683.39 S/2,114.45 S/1,568.94 S/200.64 S/92.44 S/39.72 S/68.49 S/879.72 S/879.72 S/509.96 S/309.52
S/1,239.77 S/214.87 S/756.55 S/268.35 S/3,806.17 S/2,184.93 S/1,621.24 S/207.33 S/95.52 S/41.04 S/70.77 S/909.04 S/909.04 S/526.96 S/319.84
S/1,239.77 S/214.87 S/756.55 S/268.35 S/3,806.17 S/2,184.93 S/1,621.24 S/207.33 S/95.52 S/41.04 S/70.77 S/909.04 S/909.04 S/526.96 S/319.84
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
S/0.00
O ACELERADO DE AVANCE DE OBRA- MUNIGRANJA Y ZOO
AÑO 2018 ENERO
FEBRERO
1/1/2018
2/1/2018
3/1/2018
3/20/2018
4/1/2018
5/1/2018
1/31/2018
2/28/2018
3/19/2018
3/31/2018
4/30/2018
31 dias
28 dias
19 dias
12 dias
30 dias
S/0.00
S/0.00
5,909.71 472.78 413.68 6,796.17 6,599.08 1,187.83 7,786.91
MARZO
S/126.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00
38,113.79 3,049.10 2,667.97 43,830.86 42,559.77 7,660.76 50,220.53
ABRIL
MAYO
JUNIO
JULIO
AGOSTO
5/9/2018
6/1/2018
7/1/2018
8/1/2018
5/8/2018
5/31/2018
6/30/2018
7/31/2018
8/31/2018
8 dias
23 dias
30 dias
31 dias
31 dias
S/153.67
S/200.44
S/207.12
S/207.12
61,969.78 4,957.58 4,337.88 71,265.24 69,198.54 12,455.74 81,654.28
229,920.73 18,393.66 16,094.45 264,408.84 256,740.97 46,213.37 302,954.34
513,343.39 41,067.47 35,934.04 590,344.90 573,224.88 103,180.48 676,405.36
290,281.76 23,222.54 20,319.72 333,824.02 324,143.11 58,345.76 382,488.87
0.52%
0.00%
3.32%
5.41%
20.05%
44.77%
25.32%
0.52%
0.52%
3.84%
9.24%
29.30%
74.07%
99.39%
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/768.52 S/26.28 S/0.00 S/434.64 S/58.21 S/91.97 S/41.94 S/10.27 S/19.82 S/35.04 S/32.85 S/17.52 S/0.00 S/0.00
S/0.00
S/41,005.55 S/1,200.00 S/2,549.64 S/19,848.51 S/3,797.22 S/5,600.00 S/2,736.32 S/468.96 S/904.90 S/1,600.00 S/1,500.00 S/800.00 S/9,536.78 S/36.69 S/24.06 S/12.63 S/297.63
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/137.38 S/19.66 S/47.95 S/92.64 S/946.40 S/537.79 S/197.00 S/62.21 S/149.40 S/4,127.85 S/281.93 S/573.26 S/826.65 S/290.11 S/420.98 S/619.25 S/184.44
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/267.39 S/594.09 S/69.75 S/1,055.79 S/1,055.79 S/405.52 S/75.87 S/143.07 S/186.58 S/160.50 S/160.50 S/247.48 S/247.48 S/131.32 S/131.32 S/300.43 S/300.43
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00 S/0.00
S/0.00
S/1,684.98 S/343.02 S/461.16 S/280.80 S/600.00 S/142.19 S/56.52 S/85.67 S/54,327.02 S/132.87 S/87.14 S/45.73 S/781.95 S/385.51 S/97.81 S/66.40 S/232.23
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00 S/0.00
S/2,450.36 S/1,207.79 S/542.75 S/172.35 S/527.47 S/6,512.72 S/730.44 S/1,384.86 S/2,362.73 S/437.47 S/781.91 S/815.31 S/3,092.87 S/3,092.87 S/2,010.23 S/1,425.72 S/181.08
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/301.39 S/102.04 S/2,264.12 S/862.52 S/1,401.60 S/4,429.62 S/4,429.62 S/131.32 S/131.32 S/2,631.23 S/2,264.49 S/366.74 S/21,682.84 S/18,525.39 S/1,169.95 S/1,987.50 S/312.48
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/312.48 S/630.74 S/273.60 S/113.04 S/171.34 S/72.76 S/63.36 S/63.36 S/7,025.31 S/2,758.40 S/674.60 S/240.00 S/866.49 S/445.01 S/700.00 S/195.00 S/35.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/300.00 S/648.66 S/162.15 S/175.00 S/175.00 S/84,618.47 S/277.50 S/182.00 S/95.50 S/2,601.48 S/494.12 S/195.63 S/1,659.96 S/251.77 S/9,198.72 S/1,936.05 S/727.69
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/0.00
S/1,384.52 S/5,150.46 S/4,718.20 S/474.15 S/1,273.22 S/1,077.30 S/455.89 S/834.37 S/603.27 S/1,957.12 S/1,957.12 S/1,318.02 S/527.80 S/381.70 S/86.11 S/322.41 S/8,531.90
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/8,531.90 S/1,510.20 S/1,510.20 S/4,468.96 S/4,006.16 S/462.80 S/46,907.29 S/36,169.24 S/1,715.11 S/8,072.80 S/950.14 S/539.61 S/282.60 S/257.01 S/2,519.47 S/674.60 S/720.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/585.00 S/75.00 S/432.44 S/32.43 S/70.00 S/70.00 S/92,102.86 S/303.86 S/199.29 S/104.57 S/2,398.11 S/494.98 S/106.89 S/1,521.63 S/274.61 S/10,192.15 S/1,824.01
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/920.67 S/1,741.21 S/5,706.26 S/4,194.14 S/439.97 S/1,519.08 S/746.19 S/326.95 S/595.44 S/566.51 S/2,464.12 S/2,464.12 S/1,657.39 S/664.54 S/478.37 S/108.54 S/405.94
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/9,452.61 S/9,452.61 S/1,672.07 S/1,672.07 S/4,883.96 S/4,379.69 S/504.27 S/54,078.01 S/40,205.09 S/1,801.68 S/1,715.11 S/9,265.52 S/1,090.61 S/453.94 S/282.60 S/171.34 S/352.50
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00
S/352.50 S/28,749.40 S/109.23 S/71.64 S/37.59 S/959.32 S/197.91 S/42.86 S/608.65 S/109.90 S/1,780.55 S/730.50 S/353.80 S/696.25 S/1,675.25 S/175.14 S/607.76
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/298.49 S/128.94 S/238.30 S/226.62 S/985.83 S/985.83 S/662.95 S/265.76 S/191.40 S/43.41 S/162.38 S/668.83 S/668.83 S/2,037.64 S/1,742.93 S/294.71 S/13,739.66
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/0.00
S/10,996.92 S/2,087.93 S/654.81 S/5,893.75 S/5,893.75 S/236.39 S/150.72 S/85.67 S/2,312.78 S/22.20 S/14.56 S/7.64 S/128.00 S/51.52 S/36.89 S/39.59 S/1,054.23
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00 S/0.00 S/0.00
S/0.00
S/730.50 S/112.57 S/211.16 S/50.95 S/23.41 S/27.54 S/251.96 S/251.96 S/805.44 S/805.44 S/270,259.75 S/1,298.70 S/851.76 S/446.94 S/4,632.45 S/2,431.13 S/962.52
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00 S/0.00
S/1,238.80 S/19,919.70 S/9,525.64 S/3,582.18 S/6,811.88 S/23,206.55 S/2,328.02 S/6,262.59 S/5,300.33 S/2,242.59 S/4,104.86 S/2,968.16 S/9,629.34 S/9,629.34 S/6,484.72 S/2,596.75 S/1,877.95
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/423.74 S/1,586.28 S/7,430.23 S/7,430.23 S/20,270.52 S/18,463.00 S/1,807.52 S/176,592.70 S/175,220.61 S/1,372.09 S/794.84 S/452.16 S/342.68 S/173,328.22 S/576.09 S/377.83 S/198.26
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/6,533.22 S/3,564.91 S/661.01 S/2,307.30 S/32,922.27 S/13,955.70 S/6,557.27 S/12,409.30 S/21,634.95 S/1,038.00 S/2,032.13 S/4,296.24 S/3,522.75 S/6,449.95 S/4,295.88 S/16,463.83 S/16,463.83
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/0.00
S/0.00 S/0.00
S/0.00
S/4,796.89 S/3,133.64 S/1,663.25 S/7,378.46 S/7,378.46 S/81,411.93 S/79,585.08 S/1,826.85 S/1,610.58 S/801.76 S/298.30 S/510.52 S/97,468.61 S/809.80 S/531.11 S/278.69 S/4,432.47
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00 S/0.00
S/0.00 S/0.00
S/2,505.39 S/4.54 S/1,922.54 S/32,079.30 S/9,807.98 S/7,699.07 S/14,572.25 S/3,264.87 S/3,264.87 S/56,882.17 S/15,289.52 S/35,785.87 S/5,806.78 S/38,460.75 S/1,039.24 S/681.59 S/357.65
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00 S/0.00
S/6,188.11 S/2,683.44 S/1,564.13 S/652.27 S/467.04
S/340.04 S/192.33 S/147.71 S/2,320.59 S/1,909.69 S/410.90 S/99.14 S/99.14 S/34,661.74 S/10,914.08 S/3,707.98 S/20,039.68 S/134,075.72 S/58,141.25 S/33,889.54 S/14,132.45 S/10,119.26
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/2,249.28 S/151.70 S/1,221.54 S/876.05 S/516.92 S/516.92 S/738.46 S/738.46 S/0.00 S/0.00
S/0.00
S/48,734.47 S/3,286.82 S/26,466.67 S/18,980.98 S/11,200.00 S/11,200.00 S/16,000.00 S/16,000.00 S/68,054.34 S/5,117.68 S/1,154.15 S/1,695.16 S/2,268.37 S/4,241.11 S/1,993.60 S/750.05 S/899.20
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/305.70 S/292.56 S/1,976.86 S/713.30 S/611.40 S/652.16 S/1,947.74 S/170.00 S/340.00 S/544.00 S/425.00 S/264.94 S/203.80 S/645.80 S/255.00 S/203.80 S/187.00
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00
S/373.80 S/170.00 S/203.80 S/5,063.82 S/1,087.50 S/962.64 S/84.24 S/93.24 S/2,836.20 S/4,504.74 S/1,087.50 S/412.56 S/168.48 S/2,836.20 S/1,661.07 S/1,087.50 S/412.56
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00 S/0.00
S/76.24 S/84.77 S/1,675.59 S/435.00 S/304.96 S/84.77 S/850.86 S/12,860.80 S/3,480.00 S/304.96 S/9,075.84 S/17,969.20 S/17,969.20 S/4,790.40 S/1,187.76 S/1,197.26 S/1,178.46
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00 S/0.00
S/0.00 S/0.00
S/0.00
S/613.46 S/613.46 S/1,930.43 S/1,930.43 S/3,295.30 S/135.25 S/623.29 S/267.64 S/479.39 S/967.55 S/822.18 S/52,195.54 S/4,720.87 S/3,710.82 S/1,010.05 S/12,476.19 S/1,910.30
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/680.58 S/3,241.08 S/6,644.23 S/402.00 S/51.00 S/81.90 S/13.20 S/27.60 S/39.60 S/13.80 S/13.80 S/32.10 S/129.00 S/4,985.04 S/1,319.20 S/3,665.84 S/696.54
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
S/0.00
S/0.00
S/0.00
S/0.00 S/0.00
S/696.54 S/0.00 S/5,359.00 S/928.80 S/3,270.25 S/1,159.95 S/16,452.46 S/9,444.53 S/7,007.93 S/896.21 S/412.88 S/177.42 S/305.91 S/3,929.40 S/3,929.40 S/2,277.83 S/1,382.52
TOTAL SETIEMBRE 9/1/2018 9/3/2018
292 dias
3 dias
6,956.63 556.53 486.96 8,000.12 7,768.12 1,398.26 9,166.38 0.61% 100.00%
S/895.31 S/0.00 1,146,495.79 91,719.66 80,254.71 1,318,470.16 1,280,234.48 230,442.21 1,510,676.69
GRAFICO DEL PORCEN OBRA
“Mejoramiento de los Servicios de Cultura, Deporte y Recreación en el Parque Zonal Huáscar en el Distrito de Villa
Contratista
CONSOCIO EDIFICADOR LIMA CONFORMADO POR EMPRESAS: BLUE HORIZON S.A.C. M&C CONTRATISTAS GENERA
Superv.de Obra
CONSTRUCTORA MEGA INVERSIONES TIMBA S.C.R.L.
120.00%
PORCENTAJE DE AVANCE MENSUAL ACUMULADO ( %)
100.00%
80.00%
60.00%
40.00%
27.0 22.52%
20.00%
25.17%
27.09%
10.50% 5.50% 0.00% 0.00% I NICI O
NOVI EMBRE
DI CI EMBRE
ENERO
FEBRERO
MARZO
MARZO Pa
MONTOS P
MES
MES INICIO NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO MARZO Paralizado ABRIL Paralizado MAYO Paralizado MAYO JUNIO JULIO AGOSTO SETIEMBRE TOTAL
GRAFICO DEL PORCENTAJE DE AVANCE REPROGRAMADO
ue Zonal Huáscar en el Distrito de Villa el Salvador, Provincia de Lima – Lima”
ON S.A.C. M&C CONTRATISTAS GENERALES .
69.88%
39.42% 27.09%
.17%
RERO
27.09%
27.09%
30.37%
27.09%
MARZO
MARZO Pa ra l i za do ABRI L Pa ra l i za do MAYO Pa ra l i za do
MAYO
MONTOS PROGRAMADOS ACTUALIZADOS MONTOS TOTAL (Sin/ IGV) PARCIAL
ACUMUL.
PORCENTAJES PARCIAL
ACUMUL.
JUNI O
JULI O
A
S/. S/0.00 S/599,003.12 S/544,486.10 S/1,309,048.71 S/288,468.15 S/208,839.38 Paralizacion S/357,353.42 S/985,578.42 S/3,316,543.79 S/2,893,280.41 S/387,228.31 S/10,889,829.83
S/. S/0.00 S/599,003.12 S/1,143,489.22 S/2,452,537.93 S/2,741,006.09 S/2,949,845.46 S/2,949,845.46 S/2,949,845.46 S/2,949,845.46 S/3,307,198.89 S/4,292,777.31 S/7,609,321.10 S/10,502,601.52 S/10,889,829.83
%
%
0.00% 5.50% 5.00% 12.02% 2.65% 1.92% 0.00% 0.00% 0.00% 3.28% 9.05% 30.46% 26.57% 3.56%
0.00% 5.50% 10.50% 22.52% 25.17% 27.09% 27.09% 27.09% 27.09% 30.37% 39.42% 69.88% 96.44% 100.00%
100.00%
100.00% 96.44%
69.88%
39.42%
JUNI O
JULI O
AGOSTO
SETI EMBRE