List Documents Deliverables

  • Uploaded by: Dini Sulastri
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View List Documents Deliverables as PDF for free.

More details

  • Words: 5,112
  • Pages: 7
Loading documents preview...
ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

FC BSD BSD 21 JULY 2010

SIZE

2,1

: : : :

Project Execution Plan Document & Equipment Numbering Procedure Project Control Plan Document Approval Procedure Invoicing Procedure Change Order Procedure Project Correspondence and Coordination Procedure

A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot

1 1 1 1 1 1 1

HSE

Health and Safety Management Plan Environmental Management Plan Emergency Response Plan Job Hazard Analysis HSE Disposal Handling Job Safety Analysis

A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot

1 1 1 1 1 1

QA/QC

Quality Assurance Plan QA/QC Plan General Welding Procedure Welding and Welder Qualification Test Procedure NDT Procedure Handover Procedure Pipe Handling and Transportation Procedure Inspection and Test Plan For Civil Material Inspection and Test Plan For Piping Material Inspection and Test Plan For Instrument Inspection and Test Plan For Electrical Inspection and Test Plan For Offshore Pipeline Inspection and Test Plan For Mechanical Equipment Inspection and Test Plan For Field Joint Coating Inspection and Test Plan For Insulation & Coating Inspection and Test Plan For Pipelaying Barge And Other Offshore Spread Inspection and Test Plan For Onshore and Shore Crossing Equipment WPS & PQR For Pipeline WPS & PQR For Pipeline and Piping WPS & PQR For Steel Structure WPS List And Welding Map

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

ENGINEERING

List of Engineering Data Book Engineering Quality Plan Engineering List Of Relevant Codes and Standards Engineering Procedure

A4 A4 A4 A4

lot lot lot lot

1 1 1 1

PROCUREMENT

Procurement & Subcontracting Plan Procurement & Logistik Monitoring

A4 A4

lot lot

1 1

CONSTRUCTION ENGINEERING PROCEDURE

Construction Execution Plan Pipeline Installation Procedure Riser Lifting and Installation Procedure Contigency Procedure (Dry and Wet Buckle) Anchor Handling and Mooring Procedures Preconstruction Survey Procedure As Laid Survey Procedure ROV Operation Procedure Pilot Drill and Reaming HDD Procedure Pullback Pipeline Procedures Offshore Loading and Unloading Procedure Diving Operation Procedures Pig Launcher Installation Procedure Demolish Procedure Field Joint Coating and Infill Procedure Bolt and Nut Tightening Procedure Survey And Positioning Procedure Personnel Transfer Procedure Concrete Weight Coating Stripping off Procedure Pipeline Flooding Procedure Trenching and backfiling Procedure Towing Procedure Loading Procedure Pressure Test Procedure for Piping on ORF Fabrication Procedure for Piping at ORF Post Trenching Procedure Instrument Calibration, Inspection and test procedure

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Process Flow Diagram Heat and Mass Balance

A3 A4

sheet Sheet

4 1

P&ID Muara Karang ORF Legend and Sysmbols P&ID Muara Karang ORF Pig Receiver P&ID Muara Karang ORF Filter P&ID Muara Karang ORF Pressure Letdown and Metering skid P&ID Muara Karang ORF Indirect and Fire ed Water Bath Heater P&ID Muara Karang ORF Pressure Letdown and Metering skid ( PGN ) P&ID Muara Karang ORF Cold Vent System P&ID Muara Karang ORF Instrument Air Compressor P&ID Muara Karang ORF Instrument Air Dryer P&ID Muara Karang ORF Instrument Air Receiver P&ID Muara Karang ORF Potable Water System P&ID Muara Karang ORF Emergency Diesel Generator P&ID Muara Karang ORF Fire Water Pump and Main Ring P&ID Muara Karang ORF Spray system

A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3

Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet Sheet

3 1 1 1 1 1 1 1 1 1 1 1 2 1

Muara karang ORF Utility Consumption Report Muara karang ORF Line Sizing Muara karang ORF Relief System, Radiation and Dispersion Study Report

A4 A4 A4

lot lot lot

1 1 1

WBS GROUP

PROJECT IMPLEMENTATION MANUAL PROJECT MANAGEMENT

2

By Chkd Appvd Date

UNIT

NO

1

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

DOC. NO.

DESCRIPTION

QTY

ENGINEERING PROCESS ENGINEERING PFD & MATERIAL BALANCE

PIPING & INSTRUMENTATION DIAGRAM

CALCULATION AND STUDY

ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

WBS GROUP

By Chkd Appvd Date

: : : :

FC BSD BSD 21 JULY 2010

SIZE

NO

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

UNIT

Hydraulic Calculation PSV Load Calculation HAZOP & Report Capacity Limitation Study Corosion Study

A4 A4 A4 A4 A4

lot lot lot lot lot

1 1 1 1 1

Equipment List Line List (Index) Instrument Setting Point List SAFE Chart Process Description & Operating Philosophy

A4 A4 A4 A4 A4

lot lot lot lot lot

1 1 1 1 1

Operation Manual ORF Precommissioning Procedure Pipeline Precommissioning Procedure Commissioning Procedure

A4 A4 A4 A4

lot lot lot lot

1 1 1 1

Process Data Sheet For Pig Receiver Process Data Sheet For Filter Process Data Sheet For Indirect Fired Water Bath Heater Process Data Sheet For Instrument Air Compressor Package Process Data Sheet For Instrument Air Dryer Package Process Data Sheet For Instrument Air Receiver Process Data Sheet For Potable Water Storgae Tank Process Data Sheet For Potable Water Pump Process Data Sheet For Metering Package Process Data Sheet For Vent Package Process Data Sheet ForFire Water Pump Process Data Sheet ForJockey Fire Water Pump

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set Set Set Set Set Set Set

1 2 1 1 1 1 1 2 1 1 2 2

Process Datasheet for PSV Process Datasheet for Control Valve Process Datasheet for PCV Process Datasheet for Pressure Transmitter Process Datasheet for Level Transmitter / Gauge Process Datasheet for RO Process Datasheet for SDV

A4 A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set Set

4 4 4 9 4 3 4

Fire Water Requirement Calculation Layouts of Junction Main Cable and Juntion Box All Area Layouts of Fire and Gas System Field Wiring For Building Area Layouts of Fire and Gas System Field Wiring For Non Building Area Layouts of Fire Water Pump Fire and Gas Detection Wiring Diagram Fire and Gas Detection Loop Diagram Fire and Gas Detection Interlock Diagram Fire and Gas Detection Cable Schedule Fire and Gas Detection Cable Drum Schedule Fire and Gas Detection MTO Fire and Gas Equipment datasheet Fire Fighting Equipment datasheet Safety Equipment List

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set Set Set Set Set Set Set Set Set

1 1 3 3 1 3 3 3 2 2 1 5 5 1

Requisition for Fire Water & Jockey Pump Requisition for Fire Fighting Equipment Requisition for Fire and Gas Detection Equipment TBE for Fire and Gas Detection Equipment TBE for Fire Water Pumps TBE for Fire Fighting Equipment

A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set

1 1 2 1 1 1

ORFLline Flushing / Blowing ORF Compressor Run Testing ORF Pump Run Testing ORF Fire Protection Equipment Functional Testing ORF Fire Fighting Equipment Performance Testing Pipeline Precommissioning

A4 A4 A4 A4 A4 A4

Lot Lot Lot Lot Lot Lot

1 1 6 1 1 1

Electrical Electrical Electrical Electrical Electrical Electrical Electrical Electrical Electrical Electrical

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1

DOC. NO.

DESCRIPTION

QTY

GENERAL

Procedure

PROCESS DATA SHEET FOR EQUIPMENT

PROCESS DATA SHEET FOR INSTRUMENT

PROCESS SAFETY ENGINEERING

REQUISITION , TBE, CLARICATION, VENDOR PRINT CHECK

PRECOMMISSIONING / COMMISSIONING WORKS

2,2

ELECTRICAL ENGINEERING BASIC DESIGN DOCUMENT Specification

Specification 400VAC Switchgear MCC Specification for Power Transformer Distribution Specification for AC UPS System General Specification Specification for Grounding & Lightning Protection Specification for Surge Arrester Construction Specification Specification for Power and Control Cables Specification for Lighting and Receptacle Panel Specification for Lightning Arrester of Insulation Joint

Standard Drawing

Electrical Standard Detail Installation Electrical Legend & Symbol

A3 A3

sheet sheet

15 2

Data Sheet

Data Sheet for Power Transformer Data Sheet for 400VAC Switchgear MCC Data Sheet for AC UPS

A4 A4 A4

lot lot lot

1 1 1

Requisition Requisition Requisition Requisition Requisition Requisition

A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot

1 1 1 1 1 1

REQUISITION & MTO AND TBE Requisition Equipment / Material

for for for for for for

Power Transformer 400VAC Switchgear MCC AC UPS Cable & Wire Electrical Cable Tray Lighting & Receptacle Panel

ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

WBS GROUP

Technical Bid Evaluation (TBE)

2,3

By Chkd Appvd Date

: : : :

FC BSD BSD 21 JULY 2010

SIZE

NO

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

UNIT

Requisition for Lighting Fixture and Receptacle Requisition for Electrical Building Material Requisition for Electrical Bulk Material

A4 A4 A4

lot lot lot

1 1 1

TBE TBE TBE TBE TBE TBE TBE TBE TBE

A3 A3 A3 A3 A3 A3 A3 A3 A3

lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1

DOC. NO.

DESCRIPTION

for for for for for for for for for

Power Transformer 400VAC Switchgear MCC AC UPS Cable & Wire Electrical Cable Tray Lighting & Receptacle Panel Lighting Fixture and Receptacle Electrical Building Material Electrical Bulk Material

QTY

ELECTRICAL SYSTEM CALCULATION & ANALISYS

Electrical Load Data Calculation Generator Capacity Calculation Voltage Drop Calculation Short Circuit Calculation Cable Size Calculation Illumination Level Calculation Cable Tray Calculation Relay Coordination Study Transformer sizing calculation Grounding calculation

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1

DETAIL DESIGN

Hazardous Area Classification Drawing - Muara Karang Station Single Line Diagram - Muara Karang Station Power and Control Wiring Layout (General) Equipment and Base Frame Layout Cable Tray Layout for Control Building Power and Control Wiring Layout for Control Building Power and Control Wiring Layout Street Lighting Wiring Layout Lighting, Receptacle and AC Wiring Layout Lighting and Receptacle Wiring Layout (General) Lighting and Receptacle Wiring Layout for Control Building Lighting and Receptacle Wiring Layout for Building-building Cable Schedule for Lighting & Receptacle Grounding & Lightning Protection Wiring Layout (General) Grounding Wiring Layout for Control Building Lightning Protection Wiring Layout for Control Building Panel Schedule for Lighting, Receptacle, Space Heater and AC Panel Connection Diagram - Muara Karang Station Cable Schedule for Power & Control

A1 A1 A1 A1 A1 A1 A1 A1 A1 A1 A1 A1 A3 A1 A1 A1 A3 A3 A3

sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet lot sheet sheet sheet lot lot lot

2 1 1 1 1 1 1 1 4 1 1 1 1 1 1 1 1 1 1

Piping Design Specification Piping Material Specification Piping Standard Drawing Piping Standard Support Basis For Piping Thermal Expansion Stress Analysis Piping 3D Model Preparation Procedure Piping Color Code Identification Procedure Piping Material Identification Specification Data Sheet Insulting Joint Data Sheet Barred Tee Data Sheet Spring Support Data Sheet Valve

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1

EXECUTION PROCEDURE

Piping Engineering Document List Piping Design Control Procedure Design Practice For Piping Information Drawing Design Practice For Drafting Procedure Of Piping Lay-Out Drawing Design Practice For Drafting Procedure Of Isometric Drawing Design Practice Of Pipe Support General Specification For Coating And Wrapping Of U/G Steel Pipe Engineering Procedure For Piping Mto 3D Model Rules For Piping

A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1

CONSTRUCTION SPECIFICATION

Fabrication And Installation Of Piping General Requirement For Pipe Welding In Field Construction Control Manual Of Welder & Welding Material In Field Construction Pressure Test Procedure For Piping Bolting Procedure For High Pressure Flange Joint

A4 A4 A4 A4 A4

lot lot lot lot lot

1 1 1 1 1

REQUISITION DOCUMENT

Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

1 1 1 1 1 1 1 1 1 1

A4

lot lot lot lot lot lot lot lot lot lot lot lot

PIPING ENGINEERING PIPING DESIGN SPECIFICATION

Underground Piping Work Above Ground Piping Work Tie - In Piping Work For Pipe For Valve For Flange For Gasket For Bolt & Nut For Fitting For Pipe Support Material For Spring Support For Inner/Outer Coating For U/G Pipe

A4

1 1

PLOT PLAN

General Plot Plan

A1

sheet

1

DRAWING AREA INDEX

Drawing Area Index

A1

sheet

1

PIPING ARRANGEMENT DRAWING

Piping Piping Piping Piping Piping Piping Piping

A1 A1 A1 A1 A1 A1 A1

sheet sheet sheet sheet sheet sheet sheet

1 1 1 1 1 1 1

Arrangement Drawing For Pig Receiver Area Arrangement Drawing For Utilities Area Arrangement Drawing For Metring Area Arrangement Drawing For Fire Water Bath Heater Area Section And Detail Drawing For Pig Receiver Area Section And Detail Drawing For Utilities Area Section And Detail Drawing For Metering Area

ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

FC BSD BSD 21 JULY 2010

ISOMETRIC DRAWING

Isometric Drawing For Pig Receiver Area Isometric Drawing For Utilities Area Isometric Drawing For Metering Area

A3 A3 A3

sheet sheet sheet

25 25 20

PIPE SUPPORT DRAWING

Support Style List For Pig Receiver Area Support Style List For Utilities Area Support Style List For Metering Area

A4 A4 A4

sheet sheet sheet

35 20 25

Balance Material Pipe Material Class Report Material Line Report Summary Of Mto

A4 A4 A4 A4

lot lot lot lot

1 1 1 1

Carbon Steel Carbon Steel Carbon Steel Carbon Steel Gasket Bolt & Nut Carbon Steel

A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot

1 1 1 1 1 1 1

A4 A4 A4

lot lot lot

1 1 1

A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot

1 1 1 1 1 1 1

BILL OF QUANTITY

SPECIAL

DOC. NO.

DESCRIPTION

Pipe Gate Valve Ball Valve Flange

Fitting -- 1St Mto

Insulating Joint Barred Tee Spring Support Vendor Vendor Vendor Vendor Vendor Vendor Vendor

TEST BLOCK DIAGRAM

Test Block Diagram

A3

sheet

33

PIPE STANCHION SUPPORT INFORMATION

Information Drawing For Pipe Stanchion Pig Receiving Area Information Drawing For Pipe Stanchion Utilities Area Information Drawing For Pipe Stanchion Metering Area

A3 A3 A3

sheet sheet sheet

1 1 1

LOCAL FOUNDATION INFORMATION

Information Drawing For Local Foundation Of Pig Receiving Area Information Drawing For Local Foundation Of Utilities Area Information Drawing For Local Foundation Of Metering Area

A3 A3 A3

sheet sheet sheet

1 1 1

STRESS ANALISYS CALCULATION

Stress Analisys Calculation Receiving Gas Line Stress Analisys Calculation Kicker Line Stress Analisys Calculation Metering Line

A3 A3 A3

sheet sheet sheet

1 1 1

Pile Lay Out Foundation Lay Out Fenching Lay Out Underground Composite Lay Out Road ,Pavement and Graveling Sewer,Drainage and Trenching

A1 A1 A1 A1 A1 A1

sheet sheet sheet sheet sheet sheet

2 2 3 4 4 6

FACILITY

Control Room Building Fire Water Bath Heater Sales Gas Meter Skid Air Compressor & Dryer Emergency Diesel Generator Filter Cold Vent Portable Water tank Pipe Support & Lokal Foundation Pipe Sleeper

A1 A1 A1 A1 A1 A1 A1 A1 A1 A1

sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet

25 10 4 4 4 4 2 3 4 3

DOCUMENTS

Requisition Civil Design Basis Standard Drawing Specification Shop Drawing As built Dwg

A4 A4 A3 A4 A3 A1

Set Set Set Set Set Set

17 1 42 23 50 84

Pile Calculation Foundation Calculation Fenching Lay Out & Detail Underground Composite Lay Out Road ,Pavement and Graveling Sewer,Drainage and Trenching HVAC Plumbing

A4 A4 A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set Set Set

1 9 4 2 3 3 4 3

Control Room Building Fire Water Bath Heater Sales Gas Meter Skid Air Compressor & Dryer Emergency Diesel Generator Filter Cold Vent Portable Water tank Pipe Support & Lokal Foundation Pipe Sleeper

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set Set Set Set Set

4 3 2 1 3 1 1 1 1 1

CIVIL ENGINEERING DETAIL DRAWING GENERAL

FACILITY

INSTRUMENTATION ENGINEERING SPECIFICATION

Print Print Print Print Print Print Print

Check Check Check Check Check Check Check

For For For For For For For

Valve Flange Gasket Fitting Pipe Support Material Spring Hanger Special Items

QTY

VENDOR PRINT CHECK

CALCULATION GENERAL

2,5

: : : :

UNIT

WBS GROUP

MATERIAL TAKE OFF & BILL OF QUANTITY MTO REPORT

2,4

By Chkd Appvd Date

SIZE

NO

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

WBS GROUP

By Chkd Appvd Date

DOC. NO.

DESCRIPTION

QTY

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1

STANDARD DRAWING

Typical Drawing for Instrument Installation Work Instrument Boundary Work With Mechanical Instrument Boundary Work With Civil Instrument Boundary Work With Electrical Instrument Boundary Work With Piping Symbol and Index for Instrument Installation Drawing Standard Drawing for Orifice Plate and Flange Overall System Architecture

A3 A3 A3 A3 A3 A1 A3 A3

lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1

INDIVIDUAL SPECIFICATION

Ind. Ind. Ind. Ind. Ind. Ind. Ind. Ind. Ind. Ind. Ind.

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

Set Set Set Set Set Set Set Set Set Set Set

2 2 2 2 2 6 7 6 10 3 2

Control Valves RestrictionPlate PSV Shut Down Valve

A4 A4 A4 A4

Set Set Set Set

6 2 6 7

Instrument Loop Diagram Instrument Index Instrument I/O List Instrument Connection List Interlock Logic Diagram Instrument Nozzle Arrangement/ Vessel Sketch

A3 A3 A4 A4 A3 A3

Set Set Set Set Set Set

15 2 2 20 5 5

LAY OUT

Lay Lay Lay Lay Lay

A1 A1 A1 A1 A1

Set Set Set Set Set

4 3 3 3 1

INSTRUMENT HOOK-UP

Instrument Hook-Up Pressure Lead Piping Instrument Hook-Up Air Piping & Tubing

A3 A3

Set Set

20 15

CABLE SCHEDULE

Instrument Cable Schedule for Process Unit & Control Room

A3

Set

3

MATERIAL TAKE OFF

MTO MTO MTO MTO

A4 A4 A4 A4

lot lot lot lot

1 1 1 1

REQUISITION

Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition Requisition

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

TBE

TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE TBE

A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

DETAIL ENGINEERING DETAIL DRAWING

for for for for for for for for for for for

Calculation Calculation Calculation Calculation

Out Out Out Out Out

of of of of of

for for for for

for for for for for for for for for for for for for for for for

Instrument Calibration, Inspection dan Test Procedure Cable Ladder, Tray, Fabrication Material & Accessories Instrument Signal, Power, Control Cable & Grounding Cable ICSS Instrument Design Junction Box CCTV System Metering System Pressure Let Down Skid Fiber Optic & Accessories

UNIT

General General General General General General General General General General

Spec. Spec. Spec. Spec. Spec. Spec. Spec. Spec. Spec. Spec. Spec.

for for for for for for for for for for

FC BSD BSD 21 JULY 2010

GENERAL SPECIFICATION

CALCULATION

Specification Specification Specification Specification Specification Specification Specification Specification Specification Specification

: : : :

SIZE

NO

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

Magnetic Level Gauge c/w Transmitter Top Mounted Level Transmitter Ultrasonic Flowmeter Restriction Orifice Plate Temperature Transmitters c/w Thermo Element &Thermowell Control Valve c/w Accessories Shut Down Valve PSV MOV Pressure & Pressure Differential Transmitter Pressure & Pressure Differential Indicator

for for for for

Field Instrument Location Plan Instrument Main Cable Way & JB Field Wiring & Grounding Instrument A/S Piping & Tubing Control Room

Instr.Hook Up Pressure Lead & Air Supply Instr.Signal, Control, Power, Grounding Cable Instr. for Cable Ladder, Tray, Fabrication Material & Accessories Instrument Junction Box, Grounding, & Wiring Accessories for for for for for for for for for for for for for for for for for for for for for

Magnetic Level Gauge c/w Transmitter Top Mounted Level Transmitter Ultrasonic Flowmeter Restriction Orifice Plate Temperature Transmitters c/w Thermo Element &Thermowell Control Valve c/w Accessories Shut Down Valve PSV MOV Pressure & Pressure Differential Transmitter Pressure & Pressure Differential Indicator ICSS CCTV System Metering System Pressure Let Down Skid Instrument Signal, Power, Control Cable & Grounding Cable Bulk Materials Instrument Wiring, Grounding & Accessories Fiber Optic and Accessories Junction Box Subcontractor

Magnetic Level Gauge c/w Transmitter Top Mounted Level Transmitter Ultrasonic Flowmeter Restriction Orifice Plate Temperature Transmitters c/w Thermo Element &Thermowell Control Valve c/w Accessories Shut Down Valve PSV MOV Pressure & Pressure Differential Transmitter Pressure & Pressure Differential Indicator ICSS CCTV System Metering System Pressure Let Down Skid Instrument Signal, Power, Control Cable & Grounding Cable

ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

WBS GROUP

By Chkd Appvd Date

DOC. NO.

DESCRIPTION

TBE TBE TBE TBE TBE

2,6

for for for for for

Bulk Materials Instrument Wiring, Grounding & Accessories Fiber Optic and Accessories Junction Box Subcontractor

: : : :

FC BSD BSD 21 JULY 2010

SIZE

NO

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

UNIT

QTY

A3 A3 A3 A3 A3

lot lot lot lot lot

1 1 1 1 1

INTERFACE WITH OTHER DICIPLINE

Instrument Engineering Document List Instrument Construction Work Volume Interfacing w/ Compressor Package Interfacing w/ DEG Package Interfacing w/ UPS Package Interfacing w/ HVAC Package Interfacing w/Indirect Fired Water Bath Heater Package Interfacing w/ MCC Package

A4 A4 A4 A4 A4 A4 A4 A4

sheet sheet lot lot lot lot lot lot

2 8 1 1 1 1 1 1

AS BUILT DRAWING

As Built Drawing

A3

sheet

252

Pig receiver Filters Indirect fired Water Bath Heaters Cold vent tower CO2 snuffing package Air compressor & dryer package Air compressor Instrument air pre-filter Instrument air post-filter Instrument water separator Instrument air dryers Air cooler Instrument air receiver Portable water storage tank Portable water Pump Emergency Diesel Generator

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

GENERAL SPECIFICATION

Pressure Vessel Instrument air compressor and dryer package Fired water bath heater Emergency Diesel Generator Pump (non API)

A4 A4 A4 A4 A5

lot lot lot lot lot

1 1 1 1 2

CONSTRUCTION SPECIFICATION

Static Equipment Rotating Equipment Package Equipment

A4 A4 A4

lot lot lot

1 1 1

Pig receiver Filters Indirect fired Water Bath Heaters Cold vent tower CO2 snuffing package Air compressor & dryer package Air compressor Instrument air pre-filter Instrument air post-filter Instrument water separator Instrument air dryers Air cooler Instrument air receiver Portable water storage tank Portable water Pump Emergency Diesel Generator

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

TBE

Pig receiver Filters Indirect fired Water Bath Heaters Cold vent tower CO2 snuffing package Air compressor & dryer package Air compressor Instrument air pre-filter Instrument air post-filter Instrument water separator Instrument air dryers Air cooler Instrument air receiver Portable water storage tank Portable water Pump Emergency Diesel Generator

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

LOADING DATA

Pig receiver Filters Indirect fired Water Bath Heaters Cold vent tower CO2 snuffing package Air compressor & dryer package Air compressor Instrument air pre-filter Instrument air post-filter Instrument water separator Instrument air dryers Air cooler Instrument air receiver Portable water storage tank Portable water Pump Emergency Diesel Generator

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

CALCULATION

Calculation of Tank

A4

lot

1

MECHANICAL ENGINEERING BASIC ENGINEERING MECHANICAL DATA SHEET

DETAIL ENGINEERING REQUISITION

ENGINEERING & PROJECT IMPLEMENTATION MANUAL DELIVERABLES LIST JOB NAME CLIENT LOCATION SUBJECT

By Chkd Appvd Date

: : : :

FC BSD BSD 21 JULY 2010

SIZE

UNIT

STANDARD DRAWING

Standard Drawing of Static Equipment

A4

lot

1

VENDOR PRINT CHECK

Pig receiver Filters Indirect fired Water Bath Heaters Cold vent tower CO2 snuffing package Air compressor & dryer package Air compressor Instrument air pre-filter Instrument air post-filter Instrument water separator Instrument air dryers Air cooler Instrument air receiver Portable water storage tank Portable water Pump Emergency Diesel Generator

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

2 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1

Basis of Design

A4

lot

1

SPECIFICATION

Line Pipe Hot Induction Bend Field Joint Coating, Infill Foam Insulation Joint Insulation Flange Gasket

A4 A4 A4 A4 A4

lot lot lot lot lot

1 1 1 1 1

ANALYSIS AND CALCULATION

Line Sizing Calculation On Bottom Stability Analysis Pipeline Expansion Analysis Calculation For Shore Crossing / HDD Design Pipeline Span Analysis Pipeline Wall Thickness Verification Line Pipe Transportation Analysis Pipelaying Analysis Pipeline Abandonment And Recovery Analysis Pipeline Dry/Wet Davit Lift Analysis Pipelay Barge Mooring Analysis Working Barge Mooring Analysis Trenching Barge Mooring Analysis Analysis Of Concrete Crushing During Pipeline Laying Lifting Analysis (Riser And Pipe Spool)

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

DETAIL DRAWING

Pipeline Drawing Index Pipeline Schematic Diagram Pipeline Overall Route 24" Import Pl & Seabed Profile 24 Inch Import Pipeline Approach At Mooring Tower Line Pipe End Detail Induction Pipe Bend Detail Typical Free Span Correction - Offshore Pipeline Riser Installation Schematic 24 Inch Riser Plan, View And Detail 24 Inch Import Pipeline Shore Approach / HDD Work Barge Anchor Pattern - Riser, Subsea Spool Installation Lay Barge Anchor Pattern Pull Back Activity Lay Barge Anchor Pattern During Initiation Approach To Mooring Tower Lay Barge Anchor Pattern During Pipeline Abandonment Lay Barge Anchor Pattern During Normal Laying Anchor Pattern Post Trenching Activity General Arrangement Plan Barge (Lay Barge) General Arrangement Plan Barge (Work Barge) General Arrangement Plan Barge (Post Trench) Stowage Plan And Loading Arrangement Pipe 24" On Material Barge Pigging And Hydrotest Equipment Layout Dewatering, Vaccum Drying And N2 Packing Equipment Layout

A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3 A3

sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet sheet

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5 1 1

ALLIGNMENT SHEET

Allignment Sheet Drawing Index Bathymetry Map And Alignment Sheet 24" Import Gas Pipeline

A3 A3

sheet sheet

1 24

DATA SHEET

Line Pipe Hot Induction Bend Field Joint Coating, Infill Foam Insulation Joint Insulation Flange Gasket

A4 A4 A4 A4 A4

lot lot lot lot lot

1 1 1 1 1

RFQ

Line Pipe Coating Line Pipe Field Joint Coating Hot Induction Bend HDPU/Infill Joint Pre-Construction survey Diving Service Insulation Gasket Swivel Flange As Built Survey

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1

TBE

Line Pipe Coating Line Pipe Field Joint Coating Hot Induction Bend HDPU/Infill Joint Pre-Construction survey Diving Service Insulation Gasket Swivel Flange As Built Survey

A4 A4 A4 A4 A4 A4 A4 A4 A4 A4

lot lot lot lot lot lot lot lot lot lot

1 1 1 1 1 1 1 1 1 1

NO

2,7

: LNG TERMINAL FLOATING : PT. NUSANTARA REGAS : MUARA KARANG : DELIVERABLE LIST

WBS GROUP

PIPELINE CONSTRUCTION ENGINEERING: BASIS OF DESIGN

DOC. NO.

DESCRIPTION

QTY

Related Documents


More Documents from "flightstudent"

Kak Kip-k
March 2021 0
Soal Pasien Safety
January 2021 1
Bpjs
January 2021 4