Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
Page
Serial n°
1 0001
1 / 17
0109
PETRONAS RAPID PROJECT PACKAGE 14- UTILITIES, INTERCONNECTING, OFFSITE UNITS 1 - REJECTED Do not proceed with any work defined by the data submitted. Revise and resubmit per Purchaser comments consistent with the Purchase Order, unless otherwise noted. Authorization to proceed does not relieve Contractor /Supplier of its responsibility or liability under the Contract and/or Purchase Order.
METHOD STATEMENT FOR
WATERPROOFING AND EXPANSION JOINT 3 - PROCEED Authorization to proceed does not relieve Contractor /Supplier of its responsibility or liability under the Contract and/or Purchase Order.
OWNER Approval :
PRPC Utilities and Facilities Sdn. Bhd.
By Lau Lee Yeng on May 26, 2017
Name : Date
(DD-MMM-YY)
:
Signature :
Document Class :
Z
Pages modified under this revision: -
Ervina 2017.05.22 11:48:52 +08'00'
mohd fazil 2017.05.22 11:56:48 +08'00'
Ihsan cn=Ihsan, o, ou, email=ihsan_idris@
wct.my, c=MY 2017.05.22 11:49:18 +08'00'
1
22-May-17
IFC
Issued for Construction
Ervina@Zurinah Mutih
Mohd Fazil Mohd Noh
Ihsan Idris
0
19-Apr-17
IFC
Issued for Construction
Siti Rodhiana
Mohd Fazil Mohd Noh
Ihsan Idris
B
4- Mar-17
IFA-Issued for Approval
Nur Najihah Wahab
Mohd Fazil Mohd Noh
Ihsan Idris
A
2-Feb-17
IFR
Nur Najihah Wahab
Mohd Fazil Mohd Noh
REV.
DATE DD-MMM-YY
Issued for Review
STATUS
REVISION MEMO
WRITTEN BY
(name & signature)
CHECKED BY
(name & signature)
Ihsan Idris APPROVED BY (name & signature)
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_0.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
2 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
CONTENTS
1.
Introduction
..
.3
2. Acronym and Definition
..4
3. Objective and Scope
of Work
4
4. References
.4
5. Resources Planning
.4
5.1 Material Planning
.....5 5.2 Machinery
and Equipment Planning
.5
5.3 Manpower Planning
.5
6. Construction Procedures
...5
6.1 Preliminary
Procedures
...5
6.2 Scaffolding and Work at 6.3 Material
Height
.6
and Proper Storage
.
...6
6.4 Work Procedure
..7
7. QAQC Aspect
.
.14
8. Safety and Health Aspects
.
.15
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Rev.
Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Unit n°
Page
Serial n°
1 0001
3 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
1.
INTRODUCTION
PETRONAS intends to build a grass root integrated Refinery and Petrochemicals
Complex
by
developing
the
RAPID
PROJECT
(Refinery
and
Petrochemical
Integrated Development) to meet both domestic and Asia's energy and chemicals
demand. The RAPID PROJECT consists of a world scale integrated site which
includes Refinery with a deep conversion scheme, 300 000 barrels per stream day
capacity, Naphtha Steam Cracker of 1.28 million tons of ethylene per year capacity; Petrochemical Derivative Units, utilities, off site and jetty installations.
The RAPID PROJECT is a fundamental component of the Pengerang Integrated
Complex (PIC) which also includes the following major projects; Pengerang
Cogeneration Plant (PCP), a new LNG Regasification Terminal (RGT2), Raw
Water Supply Project (PAMER), Pengerang Deep Water Terminal (PDWT) and Air
Separation Unit (ASU) which provides oxygen and nitrogen gases to the Complex
and to the local market. The RAPID PROJECT is located at Pengerang, Mukim of Pengerang, Kota Tinggi District, Johor and is in close proximity to the international
shipping lane connecting the Straits of Malacca, Singapore and the South China
Sea.
WCT has been contracted by PRPC Package 14-1702 of
RAPID complex. The
Package 14-1702 is an EPCC contract providing Engineering, Procurement, Construction & Commissioning (EPCC) of Substations (275kV, 33kV & 11kV), Field Auxiliary Rooms, Operator Shelter Buildings and Local Control Building. This
method statement introduces construction methodology of water proofing, and
expansion joint work.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
Page
Serial n°
1 0001
4 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK 2.
ACRONYMS AND DEFINITIONS OWNER
PRPC Utilities and Facilities Sdn. Bhd.
EPCM CONTRACTOR
OUI JV: Joint venture appointed by OWNER
with specified authority to perform the EPCM
Services of UIO Project.
PROJECT or UIO PROJECT
EPCM of utilities, interconnecting and offsite
facilities (UIO) Package 14 for RAPID
PROJECT at Pengerang, Johor.
EPCM
Engineering, Procurement and Construction
PACKAGE
means each package of works or supplies
Management forming part or parts of the PROJECT.
PACKAGE CONTRACTOR
means any Contractor engaged by OWNER to
undertake the PACKAGE WORKS for a
PACKAGE
SUBCONTRACTOR
means any company which EPCM
CONTRACTOR has engaged or proposes to
engage (s the context may require) to undertake
any part of the EPCM CONTRACTOR Services
3. OBJECTIVE & SCOPE OF WORK
x
To outline the sequence of work for Water Proofing and Expansion Joint Work.
The extent of work shall be in accordance with the contract documents inclusive
the established specification and drawing.
x
To outline details step by step construction methodology until completion of the
work.
x x x
To outline preparation or coordination required before start work To outline quality plan or inspection test required during project implementation To perform safe working environment and compliance to the safety requirements.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
Page
Serial n°
1 0001
5 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK 4. REFERENCE Reference
1.
5.
Description
RAPID-P0014-OUI-ARC-DES-0001-
Project
Specification:
0001_0
Architectural Specification
Building
and
RESOURCES PLANNING
5.1
Material Planning Item
5.2
Material Descriptions
1.
Polyurethane Waterproofing Membrane - XYLASTIC-500
2.
Cementitious Waterproofing Coating - XYLASTIC-FLEXCEM
3.
Extruded Polystyrene Thermal Insulation Board - SEALFLEX XPS
4.
Liquid Rubber Membrane - TRITOFLEX
5.
Heavy Duty Fiber Mesh
Machinery & Equipment Planning Item
Machinery & Equipment Descriptions
1.
Light Steel Trowel
2.
Electric Stirrer
3.
Squeegee
4.
Roller
5.
Brush/Broom
6.
Airless Spray Equipment
7.
Glove
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
6 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK 5.3
Manpower Planning
Item
6.
Manpower Descriptions
1
Project Manager
2
Site Quality Manager
3
QAQC Engineer
4
QC Inspector
5
Site Supervisor / Coordinator
6
Safety Supervisor
7
Skill Workers-Water Proofing Application
8
General Workers
CONSTRUCTION PROCEDURE
6.1.
PRELIMINARY PREPARATION
6.1.1 Submit for approval and ensure shop drawings have been approved.
6.1.2 Submit for approval and ensure materials have been approved. 6.1.3 Submit and ensure Method Statement, Inspection and Test Plan to the Engineer have been approved.
6.1.4 Arrange all necessary personnel, equipment and services are required for the works and ensure adequate water, lighting, power and
access arrangement are in place.
6.2.
SCAFFOLDING AND WORK AT HEIGHT
Please refer to PERI Scaffolding Installation
6.3.
MATERIALS AND PROPER STORAGE
System and procedure of preservation, delivery and storage of materials shall be in accordance to established Procedure & Inspection Test Plan
(ITP).
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
7 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK 6.4.
WORK PROCEDURE
6.4.1 RC FLAT ROOF WATERPROOFING APPLICATION
6.4.1.1 SURFACE PREPARATION
x
Ensure the structure in such condition that apart from final cleaning, it
will be ready to receive the waterproofing system.
x
All the timber formwork, steel bar, construction debris, concrete
dropping, paints, solvents, oils, grease or like materials and loose
debris, including mud etc to be removed from the structure.
x
All cracks honeycomb or defective structure shall be repaired prior application of waterproofing system.
x
All
penetrations
including
piping
systems
and
through-concrete
structures, etc are to be properly and permanently positioned.
x
The concrete surface shall be smooth and clean. Any sharp projections
shall be removed.
6.4.1.2 APPLICATION METHOD
Waterproofing Coating
x
All surface to be swept clean.
x
Prior to application, stir well XYLASTIC-500 in order to achieve a
homogeneous mixture. Let is settle in order to let entrapped air escape.
x
XYLASTIC-500 may be applied by broom, roller, trowel, and squeegee
or by airless spray equipment.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
8 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
x
Dilute one part XYLASTIC-500 to one part water and apply first or
2
0.30kg/m .
x
When the first coat still wet or tacky, lay one layer of heavy duty fiber
mesh reinforcement onto the first coat. 2
x
Apply second coat XYLASTIC-500 or 0.50kg/m and allow curing.
x
Apply third coat XYLASTIC-500 or 0.50kg/m and allow curing.
x
For flood testing, the newly applied XYLASTIC-500 coating must be
2
cured for at least 24 hours beforehand. Plug off all outlets, down pipes
and etc. Then flood with min 25mm of water and leave for 24 hours prior
inspection. Where it is impracticable, because or slab screed to falls or
otherwise to contain the 25mm depth of water, the slab shall be induced
with water by continuously sprinkle with water for 4 hours.
Laying Topping Concrete with Panel Joints
x
Lay one layer of 50mm thick extruded thermal insulation board in
interlocking system which interlocks with the key provided on the
material.
x
Lay one layer 0.25mm thick polythene sheet on top of insulation board.
x
Form level peg and position on R.C flat roof surface.
x
Place one layer of steel reinforcement mesh BRC A5.
x
Place average 65mm thick concrete topping to fall and steel trowel to
require finish level.
x
Place average 65mm thick concrete topping to fall and steel trowel to
require finish level.
x
Upon concrete fully cured, mark in line to demarcate 3 meter x 3 meter panel and diamond cut 12mm wide x 8mm deep groove line.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
9 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
x
Clean groove line and sealed joint by using UV resistant polyurethane
sealant.
WATERPROOFING DETAIL RC FLAT ROOF
6.4.2 TOILET WATERPROOFING APPLICATION
6.4.2.1 SURFACE PREPARATION
x
Ensure the structure in such condition that apart from final cleaning, it
will be ready to receive the waterproofing system.
x
All the timber formwork, steel bar, construction debris, concrete
dropping, paints, solvents, oils, grease or like materials and loose
debris, including mud etc to be removed from the structure.
x
All cracks honeycomb or defective structure shall be repaired prior application of waterproofing system.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
10 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
x
All
penetrations
including
piping
systems
and
through-concrete
structures, etc are to be properly and permanently positioned.
x
The concrete surface shall be smooth and clean. Any sharp projections
shall be removed.
6.4.2.2 APPLICATION METHOD
x
All surface to be swept clean.
x
Prior to application, stir well XYLASTIC-FLEXCEM in order to achieve a
homogeneous mixture. Let is settle in order to let entrapped air escape.
x
XYLASTIC-FLEXCEM may be applied by broom, roller, trowel, and
squeegee or by airless spray equipment.
x
Supply and apply two coats of XYLASTIC-FLEXCEM cementitious 2
Flexible waterproofing membrane or 1.0kg/m per coat onto proper
prepared concrete surface, all in accordance with manufacturers instruction.
x
Supply and apply two coats of XYLASTIC-500 liquid applied seamless
modified polyurethane waterproofing membrane at the rate of 0.5kg/m
2
Per coat onto proper prepared concrete surface, all in accordance with
manufacturers instruction.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
11 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
WATERPROOFING DETAIL FOR TOILET
6.4.3
EXPANSION JOINT
The expansion joint will be 2 options as below:Option 1
Expansion joint with gap 25~50mm
Option 2
Expansion joint with gap >50mm
6.4.3.1 SURFACE PREPARATION
Surface preparations for both options are same. All surface must be
pressure washed clean, free of loose materials, grease, oils, release
agents, and other contaminants. Any damaged areas and existing
substrate should be properly patched or sealed with appropriate repair materials that will bond to the existing substrates and will allow TRITOflex
to bond well to it. TRITOprime is used for asphaltic based substrates as
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
12 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK well as for concrete and metal to create a superior bond with the
TRITOflex membrane.
6.4.3.2 APPLICATION METHOD
Option 1
Application methods for external, internal and external wall in option 1 are same. Supply and spray apply one layer of 1.5mm thick TRITOflex instant setting liquid rubber membrane with 1914% elongation onto proper
prepared surface. All in accordance to manufacturers instruction.
DETAIL FOR EXPANSION JOINT AT EXPOSED WALL
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
13 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
DETAIL FOR EXPANSION JOINT AT EXPOSED ROOF
DETAIL FOR EXPANSION JOINT (INTERNAL)
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
14 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK Option 2
Application methods for external, internal and external wall in option 2 are same. Supply and spray apply one layer of 2.0mm thick TRITOflex instant
setting liquid rubber membrane with 1914% elongation onto proper
prepared surface. All in accordance to manufacturers instruction. 6mm thick removable MS plate installed on top, bolted with 12mm countersunk
bolt.
DETAIL FOR EXPANSION JOINT AT EXPOSED WALL
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
15 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
DETAIL FOR EXPANSION JOINT AT EXPOSED ROOF
DETAIL FOR EXPANSION JOINT (INTERNAL) "In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
Page
Serial n°
1 0001
16 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK 7.
QAQC ASPECT
7.1
The purpose of the quality control is to provide a guideline for a proper
operation framework such that the following targets will be attained: -
o
To achieve consistently high quality standards of workmanship in all
aspects of the work.
o
All quality matters shall follows as per MS ISO 9001 : 2000 and Project
Quality Plan to ensure the quality in construction.
7.2
Issuance of Request for Inspection
Any work in which to be carried out at site shall be requested by formal
requisition as stated in established procedure by using RFIN format form
and
implemented
according
to
Request
for
Inspection
Procedure
referenced RAPID-P0014-OUI-CON-PRC-0001-2006_0
8.
SAFETY, HEALTH AND ENVIRONMENTAL ASPECTS
x
Safety and health aspects at site shall adhere strictly to the requirements
set by DOSH/ NIOSH and DOE.
x
All machinery and equipment are to be checked at the site to ensure that it
is well functioning and be handled by only trained personnel with relevant experience.
x
Material Safety Data Sheet (MSDS) shall be prepared and always be
available at site.
x
Sufficient care shall be exercise in handling and slinging of materials.
x
Material is to be fastened in such way to prevent slipping (multiple loop grip tie) with the following controls :-
o
No dragging along ground.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
17 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
o x
Lifting rate at slower pace.
All supervisor and workers are to use PPE safety requirements at site area
at all time. Where site condition is damp and wet the use of rubber boots in which has been reinforced by steel not only in the toes but also in the soles
is essential.
x
All soft spots or holes shall be identified and barricaded if necessary.
x
The site shall be kept clean and clear of unnecessary obstruction. First aid
boxes in the charge of a responsible person have to be kept on all working
areas.
x
Appropriate and sufficient safety signboards, barriers and lighting shall be
provided as necessary by the nature of and location of the works. Safety
and health plan for the project site shall be conducted to achieve a secure
working environment.
x
While working at height:
o
100% tie off while working at roof by using proper anchor point
(lifeline)
o
Make sure workers properly hydrated by drinking water frequently.
o
Always carry only needed tools while performing work on top of roof.
o
To ensure workers to attend Working at Height Training under OUI
JV.
o
PTW should be applied and approved complete with working at
height and working on roof permit.
o
STA must be conducted prior starting work
o
All workers must attend
OUI JVs working at height training
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc
Document Number Project
Package
Originator
Discipline
Doc. Type
RAPID
P0014
0008
CON
MST
Rev. Unit n°
1 0001
Page
Serial n°
18 /18
0109
METHOD STATEMENT FOR WATER PROOFING AND EXPANSION JOINT WORK
x
While working on scaffolding:
o
Scaffolding must be erected and dismantled by Qualified Scaffolder.
o
Scaffold fittings and other connections should be securely tightened.
o
All bracings, ties, guys and buttresses should be installed as the
scaffold is erected.
o
Adequate anchor points with life lines shall be provided for workers
to hook when performing roof work.
o
Do not climb on guardrails to gain extra height
o
Edge protection and any means of access can be removed as the
scaffolding is dismantled provided it is removed at the last possible
stage.
o
To prevent injury, do not drop scaffolding components from height
during dismantling.
o
Wear full body harness and hook up to suitable anchor point.
o
Barricade and display warning signage at scaffolding work area while
erection and dismantling
o
No other activity below while work being perform
o
Scaffolding Tag must be installed (Red / Green)
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER. CONFIDENTIAL Not to disclose without authorization Electronic Filename: RAPID-P0014-0008-CON-MST-0001-0109_1.doc